DEPARTMENT OF ENERGY

[Docket No. EF95-5171-000, et al.]

Western Area Power Administration, et al.; Electric Rate and

Corporate Regulation Filings

November 1, 1994.

Take notice that the following filings have been made with the

Commission:

1. Western Area Power Administration

[Docket No. EF95-5171-000]

Take notice that on October 25, 1994, the Deputy Secretary of the

Department of Energy, by Rate Order No. WAPA-63, did confirm and

approve on an interim basis, to be effective on December 1, 1994, the

Western Area Power Administration's (Western) Rate Schedule SLIP-F5 for

firm power service from the Salt Lake City Area Integrated Projects.

The rate in Rate Schedule SLIP-F5 will be in effect pending the

Federal Energy Regulatory Commission's (FERC) approval of these or of

substitute rates on a final basis, ending November 3, 1999.

The fiscal year (FY) power repayment study indicated that the

existing rate does not yield sufficient revenue to satisfy the cost-

recovery criteria through the study period. The revised rate schedules

will yield adequate revenue to satisfy these criteria.

The Administrator of Western certifies that the rates are

consistent with applicable law and that they are the lowest possible

rates consistent with sound business principles. The Deputy Secretary

of the Department of Energy states that the rate schedule is submitted

for confirmation and approval on a final basis for a 5-year period

beginning December 1, 1994, and ending November 30, 1999, pursuant to

authority vested in FERC by Delegation Order No. 0204-108, as amended.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

2. SEI Holdings IX, Inc.

[Docket No. EG95-5-000]

On October 28, 1994, SEI Holdings IX, Inc., 900 Ashwood Parkway,

Suite 500, Atlanta, Georgia 30338 (the ``Applicant''), filed with the

Federal Energy Regulatory Commission an application for determination

of exempt wholesale generator (``EWG'') status pursuant to Part 365 of

the Commission's regulations.

The Applicant will be engaged indirectly, through an affiliate as

defined in section 2(a)(11)(B) of the Public Utility Holding Company

Act of 1935 (``PUHCA''), in owning and operating eligible facilities

located in Trinidad and Tobago: the 236 MW Penal Plant, located at

Penal, in the ward of Siparia, County of St. Patrick, consisting of two

simple cycle gas turbines and a combined cycle generating unit

comprised of two gas turbines, one heat recovery steam generator, and

one steam turbine; the 634 MW Point Lisas Plant, located at Point Lisas

Industrial Estate in the ward of Couva, County of Caroni, consisting of

ten simple cycle turbines; and the 308 MW Port of Spain Plant, located

in the city of Port of Spain, consisting of four steam turbine and two

simple cycle gas turbine generator units. The facilities are all in

commercial operation. The facilities are gas fired; the Port of Spain

Plant also has the capability to use fuel oil as a back-up.

Comment date: November 14, 1994, in accordance with Standard

Paragraph E at the end of this notice.

3. Western Resources, Inc.

[Docket No. EL94-34-001]

Take notice that on October 24, 1994, Western Resources, Inc.

tendered for filing its compliance report in the above-referenced

docket.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

4. Midwest Power Systems, Inc.

[Docket No. EL95-3-000]

Take notice that on October 14, 1994, Midwest Power Systems, Inc.

(Midwest Power) tendered for filing a Petition for Declaratory Order

permitting Midwest Power to reduce its annual composite rate of

depreciation from 3.54 percent to 3.49 percent.

5. Equitable Resources Marketing Co., Equitable Power Services Co.

[Docket Nos. ER94-1029-001, ER94-1539-001]

Take notice that on October 17, 1994, Equitable Power Services

Company (EPSC) filed certain information, on behalf of Equitable

Resources Marketing Company (ERMC) and itself, as required by the

Commission's June 7, 1994 letter order in Docket No. ER94-1029-001 and

the Commission's September 8, 1994, letter order in Docket No. ER94-

1539-000. Copies of ERMC and EPSC's informational filing are on file

with the Commission and are available for public inspection.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

6. Rainbow Energy Marketing Corporation

[Docket No. ER94-1061-002]

Take notice that on October 19, 1994, Rainbow Energy Marketing

Corporation (REMC) filed certain information as required by the

Commission's June 10, 1994, letter order in Docket No. ER94-1061-000.

Copies of REMC's informational filing are on file with the Commission

and are available for public inspection.

7. Northeast Utilities Service Company

[Docket No. ER94-1125-000]

Take notice that on October 27, 1994, Northeast Utilities Service

Company (NUSCO), submitted for filing, on behalf of the Northeast

Utilities (NU) System Companies, a revised FERC Electric Tariff No. 6--

System Power Sales and Exchanges in response to concerns raised by FERC

staff on the initial filing. NUSCO requests that the proposed tariff be

made effective on the day following the date of receipt of this

amendment by the Commission, or, in the alternative, the earlier of (i)

sixty days following the filing of this amendment or (ii) the earliest

requested effective date for a subsequently filed Service Agreement

under Tariff No. 6.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

8. MidCon Power Services Corporation

[Docket No. ER94-1329-001]

Take notice that on October 26, 1994, MidCon Power Services

Corporation (MPS) filed certain information as required by the

Commission's August 11, 1994, letter order in Docket No. ER94-1329-000.

Copies of MPS's informational filing are on file with the Commission

and are available for public inspection.

9. R. J. Dahnke & Associates

[Docket No. ER94-1352-001]

Take notice that on October 17, 1994, R. J. Dahnke & Associates

(RJD&A) filed certain information as required by the Commission's

August 13, 1994, letter order in Docket No. ER94-1352-000. Copies of

RJD&A's informational filing are on file with the Commission and are

available for public inspection.

10. Valero Power Services Company

[Docket No. ER94-1394-001]

Take notice that on October 26, 1994, Valero Power Services Company

(VPS) filed certain information as required by the Commission's August

24, 1994, letter order in Docket No. ER94-1394-000. Copies of VPS's

informational filing are on file with the Commission and are available

for public inspection.

11. TexPar Energy, Inc.

[Docket No. ER95-62-000]

Take notice that on October 24, 1994, TexPar Energy, Inc. (TexPar),

tendered for filing pursuant to Rule 205, 18 CFR 385.205, a petition

for waiver and blanket approvals under various regulation of the

Commission and for an order accepting its FERC Electric Rate Schedule

No.1.

TexPar intends to engage in electric power and energy transactions

as a marketer and a broker. In transactions where TexPar sells electric

energy it proposes to make such sales on rates, terms, and conditions

to be mutually agreed to with the purchasing party. TexPar is not in

the business of generating, transmitting, or distributing electric

power.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

12. Indiana Michigan Power Company

[Docket No. ER94-1495-000]

Take notice that on October 26, 1994, American Electric Power

Service Corporation, on behalf of Indiana Michigan Power Company,

tendered for filing an amendment to its original filing in the above

referenced docket.

A copy of the filing was served upon the Indiana Utility Regulatory

Commission, the Michigan Power Service Commission, and all parties of

record.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

13. Illinois Power Company

[Docket No. ER94-1505-000]

Take notice that on October 1, 1994, Illinois Power Company

(Illinois) tendered for filing an amendment in the above-referenced

docket.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

14. New England Power Company

[Docket No. ER95-46-000]

Take notice that on October 19, 1994, New England Power Company

(NEP) tendered for filing a Notice of Termination for a Supplement to

the Service Agreement between NEP and Fitchburg Gas and Electric under

NEP's FERC Electric Tariff, Original Volume No. 3.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

15. The Montana Power Company

[Docket No. ER95-57-000]

Take notice that on October 21, 1994, The Montana Power Company

(Montana), tendered for filing with the Federal Energy Regulatory

Commission pursuant to 18 CFR 35.13, Supplements to Montana Rate

Schedule FERC No. 45, the Pacific Northwest Coordination Agreement:

Energy Storage Agreements between Montana and each of Chelan County PUD

No. 1, Colockum Transmission Co., Inc., Cowlitz County PUD No. 1, PUD

No. 1 of Douglas County, PUD No. 1 of Grant County, PUD No. 1 of Pend

Oreille County, PUD No. 1 of Snohomish County, and Tacoma City Light.

A copy of the filing was served upon each of the utilities listed

above.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

16. Central Power and Light Company West Texas Utilities Company

[Docket No. ER95-58-000]

Take notice that on October 21, 1994, Central Power and Light

Company (CPL) and West Texas Utilities Company (WTU) tendered for

filing a CPL/WTU Electric Reliability Council of Texas (ERCOT)

Coordination Transmission Service Tariff (CST); a revised index of

customers taking service under the CST; unexecuted service agreements

under which CPL and WTU will provide service under the CST; a revised

version of WTU's ERCOT Transmission Service Tariff; a revised version

of CPL's ERCOT Transmission Service Tariff; a revised Attachment A to

WTU's Master ERCOT Transmission Facility Charge Rate Schedule and a

revised Attachment A to CPL's Master ERCOT Transmission Facility Charge

Rate Schedule. The filing would allow CPL and WTU to begin to collect

facility charges in connection with the transmission of Economy ``A''

Energy and Emergency Power for other ERCOT utilities. CPL and WTU

explain that such changes are necessary to being their tariffs into

conformance with recent changes in ERCOT operating practices.

CPL and WTU have requested a waiver of the Commission's regulations

to allow the changed rate schedules to become effective as of October

22, 1994.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

17. Pennsylvania Electric Company

[Docket No. ER95-60-000]

Take notice that on October 24, 1994, Pennsylvania Electric Company

(Penelec) tendered for filing pursuant to Rule 205 of the Commission's

Rules of Practice and Procedure (18 CFR 385.205) an amendment to its

existing rate schedule for transmission and supplemental power services

to Allegheny Electric Cooperative, Inc. (Allegheny Cooperative). Under

such existing rate schedule, Penelec has been providing such services

to Allegheny Cooperative through 173 delivery points in Pennsylvania

and one delivery point in New Jersey.

Allegheny Cooperative has requested, and Penelec has agreed, that

the Penelec demand rates for service supplied by Penelec to Allegheny

Cooperative be revised, on a revenues neutral basis, to provide for

billing by Penelec to Allegheny Cooperative on a coincident peak basis.

Allegheny Cooperative would like to make that change effective as of

November 1, 1994, the start of Allegheny Cooperative's next fiscal

year, and Penelec has requested that effective date for the subject

amendment.

The proposed amendment will also increase, by approximately 5%, the

billing credit that Allegheny Cooperative receives for its 10%

undivided joint ownership interest in the Susquehanna Steam Electric

Station and will resolve two disputes between Penelec and Allegheny

cooperative relating to the scope of Penelec's supply to Allegheny

Cooperative. Penelec has requested a waiver of Section 35.3(a) of the

Commission's Regulations (18 CFR 35.3(a) to the extent required to

permit the proposed amendment to go into effect not later than November

1, 1994.

Copies of the filing have been served on the Pennsylvania Public

Utility Commission and Allegheny Cooperative.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

18. Public Service Company of New Mexico

[Docket No. ER95-61-000]

Take notice that on October 24, 1994, Public Service Company of New

Mexico (PNM), tendered for filing a Notice of Termination of two letter

agreements providing for the banking of energy under Service Schedule C

to the Interconnection Agreement between PNM and the City of Anaheim,

California (Anaheim), Supplements 1 and 2 to Supplement 1 to PNM Rate

Schedule FERC No. 96. Termination of the letter agreements is to be

effective as of October 18, 1994. PNM requests waiver of the applicable

notice requirements.

Copies of this filing have been served upon Anaheim and New Mexico

Public Utility Commission.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

19. Maine Public Service Company

[Docket No. ER95-63-000]

Take notice that on October 24, 1994, Maine Public Service Company

(Maine Public), filed an executed Service Agreement with Louis Dreyfus

Electric Power Inc. Maine Public states that the service agreement is

being submitted pursuant to its tariff provision pertaining to the

short-term non-firm sale of capacity and energy which establishes a

ceiling rate at Maine Public's cost of service for the units available

for sale.

Maine Public requests that the service agreement become effective

on October 17, 1994 and requests waiver of the Commission's regulations

regarding filing.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

20. South Carolina Electric & Gas Company

[Docket No. ER95-64-000]

Take notice that on October 24, 1994, South Carolina Electric & Gas

Company (SCE&G), tendered for filing proposed changes in its FERC

Electric Service Tariff (Volume Nos. 1-1V).

The proposed changes would increase revenues from jurisdictional

sales and service by $1,928,000 based on the 12 month period ending

December 31, 1995. The Company also proposes a revised wholesale

electric tariff designated as Third Revised Volume No. 1, to supersede

Second Revised Volume No. 1.

SCE&G states that the proposed increased rates are necessitated by

the fact that it is realizing an unreasonable low rate of return on

sales to its jurisdictional customers.

Copies of this filing were served upon the public utility's

jurisdictional customers and the South Carolina Public Service

Commission.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

21. Portland General Electric Company

[Docket No. ER95-71-000]

Take notice that on October 25, 1994, Portland General Electric

Company (PGE) tendered for filing service agreements under FERC

Electric Tariff, Original Volume No. 1 (PGE-1), with Rainbow Energy

Marketing Corporation (Rainbow), and British Columbia Power Exchange

Corporation (POWEREX). PGE has requested that the Service Agreements be

accepted by the Commission, effective October 24, 1994. Copies of the

filing have been served on the parties included in the Certificate of

Service attached to the filing letter.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

22. Consumers Power Company

[Docket No. ER95-76-000]

Take notice that on October 26, 1994, Consumers Power Company,

tendered for filing a new wholesale service agreement providing for the

sale of firm and non-firm power to Alpena Power Company.

Copies of the filing were served upon Alpena Power Company and the

Michigan Public Service Commission.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

23. The Washington Water Power Company

[Docket No. ER95-77-000]

Take notice that on October 26, 1994, The Washington Water Power

Company (WWP), tendered for filing with the Federal Energy Regulatory

Commission pursuant to 18 CFR 35.13, a rate revision for the

Transmission Agreement between The Washington Water Power Company, City

of Spokane, and Puget Sound Power & Light Company. WWP states that this

rate schedule is related to transmission wheeling service for the City

of Spokane to Puget Sound Power and Light Company. WWP requests that

the Commission accept the rate revision to be effective at 2400 hours

December 31, 1994.

A copy of this filing was served upon the City of Spokane and Puget

Sound Power and Light Company.

Comment date: November 15, 1994, in accordance with Standard

Paragraph E at the end of this notice.

24. The Dayton Power and Light Company

[Docket No. ER95-83-000]

Take notice that The Dayton Power and Light Company (Dayton)

tendered for filing on October 27, 1994, executed Power Services

Agreements (PSA) between Dayton and The Village of Arcanum, The Village

of Jackson Center, The Village of Lakeview, The Village of Mendon, The

Village of New Bremen, and The Village of Waynesfield, Ohio

(Municipals).

Pursuant to Rate Schedules A through E attached to the PSA, DP&L

will provide to Municipals, on an unbundled basis, long-term firm and

short-interruptible transmission services and a variety of power supply

services, all subject to flexible notice and scheduling provisions and

fixed long-term prices. Dayton and Municipals are currently parties to

a Service Agreement for partial requirements service pursuant to

Dayton's FERC Electric Tariff, Original Volume No. 2, filed pursuant to

and governed by the Settlement Agreement accepted for filing in Docket

No. ER83-333-000. The Agreements will replace the existing Partial

Requirements Service Agreements in place for these municipals. Dayton

and Municipals request an effective date of January 1, 1995.

A copy of the filing was served upon The Village of Arcanum, The

Village of Lakeview, The Village of Mendon, The Village of New Bremen,

and The Village of Waynesfield, Ohio and The Public Utilities

Commission of Ohio.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

25. Green Mountain Power Corporation

[Docket No. ER95-84-000]

Take notice that on October 27, 1994, Green Mountain Power

Corporation (GMP) tendered for filing revisions to the definition of

``Public Utility'' eligible to purchase power under its FERC Electric

Tariff, Original Volume No. 2 (the ``Tariff''). GMP states that these

revisions were intended to permit power marketers regulated by the

Federal Energy Regulatory Commission under Part II of the Federal Power

Act to purchase power under the Tariff, and to clarify that the New

York Power Authority is a municipal corporation eligible to purchase

power from GMP under the Tariff. GMP also tendered for filing service

agreements with two power marketers desiring to purchase power under

the Tariff: Louis Dreyfus Electric Power Inc. and ENRON Power

Marketing. GMP has requested that these filings be made effective as of

January 1, 1995.

Comment date: November 16, 1994, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C.

20426, in accordance with Rules 211 and 214 of the Commission's Rules

of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Lois D. Cashell,

Secretary.

[FR Doc. 94-27535; Filed 11-4-94; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.