DEPARTMENT OF ENERGY

FEDERAL ENERGY REGULATORY COMMISSION

[Docket No. ER93-540-002, et al.]

American Electric Power Corporation, et al.; Electric Rate and

Corporate Regulation Filings

August 10, 1994.

Take notice that the following filings have been made with the

Commission:

1. American Electric Power Corporation

[Docket No. ER93-540-002]

Take notice that on July 25, 1994, American Electric Power Service

Corporation, on behalf of Appalachian Power Company, Columbus Southern

Power Company, Indiana Michigan Power Company, Kentucky Power Company,

Kingsport Power Company, Ohio Power Company and Wheeling Power Company,

operating companies of the American Electric Power (AEP) System

(collectively ``the AEP Companies'') tendered for filing a Second

Revised Transmission Service and Ancillary Control Area Services

Tariff. The Second Revised Tariff is proposed as a substitute for the

Revised Transmission Service and Ancillary Control Area Services Tariff

accepted for filing by the Commission by order of September 3, 1993, in

this docket. The Second Revised Tariff reflects, among other things,

the Commission's summary disposition of certain issues in its September

3, 1993, order, as affirmed on rehearing. The AEP Companies request an

effective date of August 1, 1994.

Copies have been served upon all participants in this docket and

upon the state regulatory commissions in Indiana, Kentucky, Michigan,

Ohio, Tennessee, Virginia and West Virginia.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

2. JEB Corporation

[Docket No. ER94-1432-000]

Take notice that on July 25, 1994, JEB Corporation (JEB) tendered

for filing pursuant to Rule 205, 18 CFR 385.205, a petition for waivers

and blanket approvals under various regulations of the Commission and

for an order accepting its FERC Electric Rate Schedule No. 1.

JEB intends to engage in electric power and energy transactions as

a marketer and a broker. In transactions where JEB sells electric

energy it proposes to make such sales on rates, terms, and conditions

to be mutually agreed to with the purchasing party. JEB is not in the

business of generating, transmitting, or distributing electric power.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

3. Illinois Power Company

[Docket No. ER94-2505-000]

Take notice that on July 29, 1994, Illinois Power Company

(Illinois) tendered for filing a Services Agreement between Illinois

and Louis Dreyfus Electric Power, Inc. (LDEP). Illinois states that the

purpose of this agreement is to provide for the buying and selling of

capacity and energy between Illinois and LDEP.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

4. AES Power Inc.

[Docket No. ER94-1519-000]

Take notice that on August 1, 1994, AES Power Inc. (AESPI)

submitted for filing with the Commission two Service Agreements under

Rate Schedule FERC No. 1. One is for service to East Kentucky Power

Corporation, Inc. and the second is for service to American Municipal

Power-Ohio, Inc. The Service Agreements are to be effective July 1,

1994.

Comment date: August 24, 1994, in accordance with Standard

Paragraph E at the end of this notice.

5. Pennsylvania Power Company

[Docket No. ER94-1520-000]

Take notice that on August 1, 1994, Pennsylvania Power Company

tendered for filing a document entitled ``Petition of Pennsylvania

Power Company For Permission To Charge A Decrease In Rates Under

Settlement Agreements Pending Commission Action''.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

6. PacifiCorp

[Docket No. ER94-1521-000]

Take notice that on August 2, 1994, PacifiCorp, tendered for filing

in accordance with 18 CFR 35 of the Commission's Rules and Regulations,

Amendment No. 2 (Amendment) dated July 21, 1994, to the Long-Term Power

Sales Agreement (Agreement) between PacifiCorp and The Arizona Power

Pooling Association (APPA) dated March 4, 1991, designated PacifiCorp

Rate Schedule, FERC No. 310.

The Amendment revises the minimum load factor that APPA must

purchase firm energy associated with firm capacity under the Agreement

commencing with the 1994 Summer Season.

PacifiCorp requests, pursuant to 18 CFR 35.11 of the Commission's

Rules and Regulations, that a waiver of prior notice be granted and

that an effective date of May 1, 1994, be assigned to the Amendment,

this date corresponding to date the 1994 Summer Season commenced.

Copies of this filing were supplied to APPA, the Public Utility

Commission of Oregon, the Utah Public Service Commission and the

Washington Utilities and Transportation Commission.

Comment date: August 24, 1994, in accordance with Standard

Paragraph E at the end of this notice.

7. Portland General Electric Company

[Docket No. ER94-1522-000]

Take notice that on August 2, 1994, Portland General Electric

Company (PGE) tendered for filing a service agreement under FERC

Electric Tariff, Original Volume No. 1 (PGE-1) with West Kootenay

Power. PGE has requested that the Service Agreement with West Kootenay

Power be accepted by the Commission, effective July 29, 1994. Copies of

the filing have been served on the parties included in the distribution

list defined in the filing letter.

Comment date: August 24, 1994, in accordance with Standard

Paragraph E at the end of this notice.

8. Maine Public Service Company

[Docket No. ER94-1523-000]

Take notice that on August 2, 1994, Maine Public Service Company

(Maine Public) filed an executed Service Agreement with Enron Power

Marketing, Inc. Maine Public states that the service agreement is being

submitted pursuant to its tariff provision pertaining to the short-term

non-firm sale of capacity and energy which establishes a ceiling rate

at Maine Public's cost of service for the units available for sale.

Maine Public requests that the service agreement become effective

on August 1, 1994, and requests waiver of the Commission's regulations

regarding filing.

Comment date: August 24, 1994, in accordance with Standard

Paragraph E at the end of this notice.

9. Tucson Electric Power Company

[Docket No. ER94-1524-000]

Take notice that on August 2, 1994, Tucson Electric Power Company

(Tucson) tendered for filing a 1994-95 Block Energy Sale Agreement

between Tucson and Texas-New Mexico Power Company (TNP). The Agreement

provides for the sale by Tucson to TNP of 50 MW of block energy for a

period of one-year.

The parties request an effective date of August 3, 1994, and

therefore request waiver of the Commission's regulations with respect

to notice of filing.

Copies of this filing have been served upon all parties affected by

this proceeding.

Comment date: August 24, 1994, in accordance with Standard

Paragraph E at the end of this notice.

10. West Texas Utilities Company

[Docket No. ER94-1526-000]

Take notice that on August 2, 1994, West Texas Utilities Company

(WTU) tendered for filing a corrected form of Supplement to Exhibit A

for the TR-1 Service Specification Sheet under WTU's TR-1 Tariff. The

filing corrects an inadvertent typographical error in the Supplement as

originally filed in Docket No. ER94-11154-000, accepted by letter order

of June 2, 1994.

WTU states that a copy of the filing has been served on each of

WTU's TR-1 customers and the Public Utility Commission of Texas.

WTU requests waiver of the notice requirements to permit an

effective date of June 15, 1994, the date the Supplement, as originally

filed, was accepted for filing.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

11. Carolina Power & Light Company

[Docket No. ER94-1527-000]

Take notice that on August 2, 1994, Carolina Power & Light Company

(CP&L) filed, pursuant to Section 205 of the Federal Power Act and Part

35 of the Commission's Regulations, a Power Supply Agreement Between

Carolina Power & Light Company and the Town of Waynesville, North

Carolina, (PSA) applicable to wholesale electric service provided by

CP&L to the Town of Waynesville (Waynesville). CP&L states that the PSA

revises the rates, terms and conditions under which CP&L will provide

service to Waynesville. Upon the effective date, CP&L states that

Waynesville no longer will take service under Resale Service Schedule

RS88-2B.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

12. Consolidated Edison Company of New York, Inc.

[Docket No. ER94-1528-000]

Take notice that on August 2, 1994, Consolidated Edison Company of

New York, Inc. (Con Edison) tendered for filing a Supplement to its

Rate Schedule FERC 117 an agreement to provide transmission and

interconnection service to Long Island Lighting Company (LILCO). The

Supplement provides for an increase in the annual fixed rate carrying

charges of $187.08. Con Edison has requested that this increase take

effect as of September 1, 1994.

Con Edison states that a copy of this filing has been served by

mail upon LILCO.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

13. Mid-Continent Area Power Pool

[Docket No. ER94-1529-000]

Take notice that Mid-Continent Area Power Pool, on August 2, 1994,

tendered for filing amendments to the Mid-Continent Area Power Pool

Agreement, to implement a megawatt mile-based Transmission Service

Charge for specified transmission services provided by MAPP

Participants. Copies of the filing were served on the Illinois Commerce

Commission, Iowa State Utilities Board, Michigan Public Service

Commission, Minnesota Public Utilities Commission, Montana Public

Service Commission, Nebraska Power Review Board, North Dakota Public

Service Commission, South Dakota Public Utilities Commission, and

Public Service Commission of Wisconsin.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

14. Acme Power Marketing, Inc.

[Docket No. ER94-1530-000]

Take notice that on August 2, 1994, Acme Power Marketing, Inc.

(ACME) tendered for filing with the Federal Energy Regulatory

Commission pursuant to Rule 205, 18 CFR 385.205, an Application for

Order Accepting Blanket Market-Based Rate Schedule and Granting

Waivers, Blanket Approvals and Disclaimer of Jurisdiction.

ACME intends to engage in electric power transactions as a marketer

and/or broker. In transactions where ACME sells electric energy it

proposes to make such sales on rates, terms and conditions to be

mutually agreed upon with the purchasing party. ACME is not in the

business of generating, transmitting, or distributing electric power.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

15. Puget Sound Power & Light Company

[Docket No. ER94-1531-000]

Take notice that on August 3, 1994, Puget Sound Power & Light

Company (Puget) tendered for filing a letter agreement for Temporary

Transmission Service between the Bonneville Power Administration

(Bonneville) and Puget dated as of July 29, 1994. Under the Agreement,

Puget is to temporarily provide transmission service for a Bonneville

load so that Bonneville can perform critical maintenance and

replacement work on facilities in its Ellensburg substation which

normally would carry that load.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

16. PECO Energy Company

[Docket No. ER94-1533-000]

Take notice that on August 4, 1994, PECO Energy Company (PECO)

tendered for filing an Agreement between PECO and General Public

Utilities Corporation (GPU) dated July 29, 1994.

PECO states that the Agreement sets forth the terms and conditions

for the sale of system energy which it expects to have available for

sale from time to time and the purchase of which will be economically

advantageous to GPU. In order to optimize the economic advantage to

both PECO and GPU, PECO requests that the Commission waive its

customary notice period and permit the agreement to become effective on

August 5, 1994.

PECO states that a copy of this filing has been sent to GPU and

will be furnished to the Pennsylvania Public Utility Commission.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

17. Maine Public Service Company

[Docket No. ER94-1534-000]

Take notice that on August 4, 1994, Maine Service Company (Maine

Public) filed an executed Service Agreement with New England Power

Company. Maine Public states that the service agreement is being

submitted pursuant to its tariff provisions pertaining to the short-

term non-firm sale of capacity and energy which establishes a ceiling

rate at Maine Public's cost of service for the units available for the

sale.

Maine Public requests that the service agreement become effective

on August 1, 1994, and requests waiver of the Commission's regulations

regarding the filing.

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

18. John L. Goolsby

[Docket No. ID-2848-000]

Take notice that on August 1, 1994, John L. Goolsby (Applicant)

tendered for filing an application under section 305(b) of the Federal

Power Act to hold the following positions:

Director--Nevada Power Company

Director--Bank of America Nevada

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

19. Jerry Herbst

[Docket No. ID-2849-000]

Take notice that on August 1, 1994, Jerry Herbst (Applicant)

tendered for filing an application under section 305(b) of the Federal

Power Act to hold the following positions:

Director--Nevada Power Company

Director-- Bank of America Nevada

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

20. Charles A. Lenzie

Docket No. ID-2850-000

Take notice that on August 1, 1994, Charles A. Lenzie (Applicant)

tendered for filing an application under section 305(b) of the Federal

Power Act to hold the following positions:

Director--Nevada Power Company

Director--Bank of America Nevada

Comment date: August 25, 1994, in accordance with Standard

Paragraph E at the end of this notice.

21. Newark Bay Cogeneration Partnership, L.P.

[Docket Nos. QF86-1014-006 and EL94-27-000]

On August 2, 1994, Newark Bay Cogeneration Partnership, L.P.

(Newark Bay) tendered for filing an amendment to its filing in these

dockets.

The amendment pertains to information relating to Newark Bay's

Petition For Temporary Waiver of the Commission's Regulations under the

Public Utility Regulatory Policies Act of 1978 (PURPA).

Comment date: August 23, 1994, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C.

20426, in accordance with Rules 211 and 214 of the Commission's Rules

of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Lois D. Cashell

Secretary

[FR Doc. 94-20241 Filed 8-17-94; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.