Proposed Consent Order with Murphy Oil Corporation, Murphy Oil USA, Inc. and Murphy Exploration & Production Company
Federal RegisterJul 27, 1994
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Economic Regulatory Administration
Proposed Consent Order with Murphy Oil Corporation, Murphy Oil
USA, Inc. and Murphy Exploration & Production Company
AGENCY: Economic Regulatory Administration, DOE.
ACTION: Notice of proposed consent order and opportunity for public
comment.
-----------------------------------------------------------------------
SUMMARY: The Economic Regulatory Administration (ERA) announces a
proposed Consent Order between the Department of Energy (DOE) and
Murphy Oil Corporation, Murphy Oil USA, Inc. and Murphy Exploration &
Production Company (Murphy). The agreement proposes to resolve matters
relating to Murphy's compliance with the federal petroleum price and
allocation regulations for the period January 1, 1973 through January
28, 1981. If this Consent Order is approved, Murphy will pay
$10,700,000.00 to DOE. To distribute these monies, DOE's Office of
Hearings and Appeals will be petitioned to implement Special Refund
Procedures pursuant to 10 CFR Part 205, Subpart V, in which proceedings
any persons who claim to have suffered injury from the alleged
overcharges would have the opportunity to submit claims for payment.
Pursuant to 10 CFR Sec. 205.199J, ERA will receive written comments
on the proposed Consent Order and will consider all comments received
from the public in determining whether to accept the settlement and
issue a final Order, renegotiate the agreement and issue a modified
agreement as a final Order, or reject the settlement. DOE's final
decision will be published in the Federal Register, along with an
analysis of significant written comments in response to this notice, as
well as any other considerations that were relevant to the final
decision.
DATES: Comments must be received by August 26, 1994.
ADDRESSES: Interested parties are invited to submit written comments
concerning this proposed Consent Order to: Murphy Consent Order
Comments, U.S. Department of Energy, Economic Regulatory
Administration, GC-44, 820 First Street, N.E., Suite 810, Washington,
D.C. 20585. Any information or data considered confidential by the
person submitting it must be identified as such in accordance with the
provisions of 10 CFR Sec. 205.9(f).
FOR FURTHER INFORMATION CONTACT: Dorothy Hamid, Economic Regulatory
Administration, Department of Energy, 820 First Street, N.E., Suite
810, Washington, D.C. 20585, (202) 523-3045.
SUPPLEMENTARY INFORMATION: Murphy is a petroleum refiner and a producer
subject to the audit jurisdiction of ERA to determine compliance with
the federal petroleum price and allocation regulations. During the
period covered by the proposed Consent Order, January 1, 1973 through
January 28, 1981, Murphy engaged in, among other things, the
production, sale and refining of crude oil. On February 9, 1987, Murphy
and DOE entered into a Consent Order (hereinafter the 1987 Consent
Order) that settled, with certain specific exceptions, all claims and
disputes against Murphy by DOE for the period January 1, 1973 through
January 28, 1981. The 1987 Consent Order specifically excepted, among
other things, issues or claims then pending or arising out of first
sales of crude oil produced and sold from properties operated by
Murphy.
As a result of DOE's investigation of Murphy's compliance with the
federal petroleum price and allocation regulations during the period
covered by the proposed Consent Order, ERA issued a Proposed Remedial
Order (PRO) to Murphy on December 15, 1986. On June 17, 1992, DOE's
Office of Hearings and Appeals (OHA) modified the PRO and issued it as
a Remedial Order (RO) to Murphy. Murphy Oil Corp., 22 DOE 83,005
(1992). The RO finds Murphy liable to make restitution of
$13,366,664.60, plus interest to the date of restitution, for
violations of the regulations applicable to first sales of domestic
crude oil (10 CFR Secs. 212.72-212.74), the regulations exempting from
the price rules the sale of crude oil produced from ``stripper well''
properties (10 CFR Secs. 210.32 and 212.54), and the normal business
practices rule (10 CFR Sec. 210.62(c)) in connection with Murphy's
first sales of crude oil during the period September 1973 through
December 1979. With interest, Murphy's current liability under the RO
would total $67.6 million through June 1994. Murphy appealed that RO to
the Federal Energy Regulatory Commission (FERC).
The RO also remands for further proceedings claims against Murphy
pertaining to Murphy's operation of properties for which the PRO found
violations during the year 1979, as well as certain crude oil
properties not included within ERA's investigation of Murphy or within
the PRO.
On January 24, 1994, a FERC Administrative Law Judge issued a
decision and proposed order (D&PO) that modified the RO and directed
recalculation of the amount of restitution. Ocean Drilling &
Exploration Co., et al., 66 FERC 63,002 (1994). The D&PO is now
pending before the Commission in Docket No. RO92-5-000. With interest,
Murphy's current liability under the D&PO (including ERA's estimate of
Murphy's liability for previously unaudited properties and unaudited
time periods (yet to be adjudicated by OHA or FERC)) totals
approximately $5.2 million.
ERA has preliminarily agreed to the proposed $10,700,000 settlement
as resolution of Murphy's liability for DOE regulatory violations for
the period covered by the proposed Consent Order. ERA has made this
tentative determination after an assessment of the risks of the current
matters in litigation. Among other things, ERA has considered the risk
pertaining to the following issues that Murphy has raised in its
defense: whether Murphy properly applied the definition of ``property''
to certain of its offshore and onshore producing premises in the period
September 1973 through August 1976; whether the largest of Murphy's
offshore producing premises qualified as multiple DOE ``properties''
under DOE Rulings 1977-1 and 1977-2; whether Murphy charged prices in
excess of the appropriate ceiling prices for crude oil produced from
offshore and onshore properties that it operated; whether Murphy should
be liable for 100% of the overcharges associated with sales of crude
oil that had been taken ``in kind'' from Murphy-operated properties and
sold by working interest owners; and whether Murphy should be liable
for 100% of the overcharges associated with certain sales of crude oil
from Murphy-operated properties as to which the federal government
received a royalty interest. ERA has also considered the time and
expense that would be required for the government to litigate every
issue fully. Based on these factors, ERA has tentatively concluded that
the resolution of its claims against Murphy for $10,700,000 is an
appropriate settlement and in the public interest. Except as
specifically excluded, all pending and potential civil and
administrative disputes, claims and causes of action, whether or not
heretofore asserted, between the DOE and Murphy relating to Murphy's
compliance with the federal petroleum price and allocation regulations
are resolved and extinguished by this Consent Order. Murphy and DOE
mutually release each other from the claims arising under the subject
matter covered by the proposed Consent Order.
Under the terms of the proposed Consent Order, Murphy is required
to pay the sum of $10,700,000 within thirty (30) days of the effective
date of the Consent Order and shall maintain records as are necessary
to demonstrate compliance with the terms of this Consent Order.
If the settlement is not made final by the one hundred fiftieth
(150th) day following execution, Murphy may withdraw from the proposed
agreement.
Submission of Written Comments:
The proposed Consent Order cannot be made effective until the
conclusion of the public review process, of which this Notice is a
part.
All comments received by the thirtieth (30th) day following
publication of this Notice in the Federal Register will be considered
before determining whether to adopt the proposed Consent Order as a
final Order. Any modifications of the proposed Consent Order which
significantly alter its terms or impact will be published for
additional comments. If, after considering the comments it has
received, ERA determines to issue the proposed Consent Order as a final
Order, the proposed Order will be made final and effective by
publication of a Notice in the Federal Register.
Issued in Washington, D.C., on July 21, 1994.
Robert R. Nordhaus,
Acting Administrator, Economic Regulatory Administration, General
Counsel.
[FR Doc. 94-18291 Filed 7-26-94; 8:45 am]
BILLING CODE 6450-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.