Moretown Hydroelectric, LLC; Notice of Waiver Period for Water Quality Certification Application

Federal RegisterJan 19, 2023

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 5944-024]

Moretown Hydroelectric, LLC; Notice of Waiver Period for Water Quality Certification Application

On December 20, 2022, Moretown Hydroelectric, LLC submitted to the Federal Energy Regulatory Commission (Commission) evidence of the date on which the certifying agency received the certification request for a Clean Water Act section 401(a)(1) water quality certification filed with the Vermont Department of Environmental Conservation, in conjunction with the above captioned project. Pursuant to 40 CFR 121.6 and section [4.34(b)(5), 5.23(b), 153.4, or 157.22] of the Commission's regulations,

1

we hereby notify the Vermont Department of Environmental Conservation of the following:

1

18 CFR [4.34(b)(5)/5.23(b)/153.4/157.22].

Date of Receipt of the Certification Request:

December 16, 2022.

Reasonable Period of Time to Act on the Certification Request:

One year (December 16, 2023).

If the Vermont Department of Environmental Conservation fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

Dated: January 11, 2023.

Kimberly D. Bose,

Secretary.

[FR Doc. 2023-00892 Filed 1-18-23; 8:45 am]

BILLING CODE 6717-01-P