DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EC00-1-000, et al.]

Energy East Corporation and CMP Group, Inc., et al.; Electric

Rate and Corporate Regulation Filings

December 29, 1999.

Take notice that the following filings have been made with the

Commission:

1. Energy East Corporation and CMP Group, Inc.

[Docket No. EC00-1-000]

Take notice that on December 10, 1999, Energy East Corporation

(Energy East) and CMP Group, Inc. (CMP Group), tendered for filing a

letter with the Commission to update the Commission on matters that had

occurred since their joint application of authorization and approval of

their proposed merger was filed on October 1, 1999.

Comment date: January 20, 2000, in accordance with Standard

Paragraph E at the end of this notice.

2. Commonwealth Chesapeake Company, L.L.C.

[Docket Nos. EG99-15-001 and EG00-59-000]

Take notice that on December 21, 1999, Commonwealth Chesapeake

Company, L.L.C. (Commonwealth Chesapeake), tendered for filing an

application for determination of exempt wholesale generator status,

pursuant to Section 32(a)(1) of the Public Utility Holding Company Act

of 1935 as amended (PUHCA), 15 U.S.C. 79z-5a(a)(1) (1994) and Section

365.8 of the Commission's Regulations, 18 CFR 365.8.

Commonwealth Chesapeake is a Virginia limited liability company

that is constructing and will own and operate a 312 megawatt, oil-fired

electric generating peaking facility to be located in Accomack County,

Virginia. Commonwealth Chesapeake states that it will be engaged

directly, or indirectly through one or more affiliates, as defined in

Section 2(a)(11)(B) of PUHCA, and exclusively in the business of owning

and/or operating an eligible facility and selling electric energy at

wholesale.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

3. Commonwealth Edison Company; Commonwealth Edison Company of

Indiana

[Docket No. ER99-3886-001]

Take notice that on December 21, 1999, Commonwealth Edison Company

and Commonwealth Edison Company of Indiana tendered for filing in

compliance with the Commission's September 29, 1999 Order Accepting for

Filing, as Modified, Revisions to Open Access Tariff, 88 FERC para.

61,296.

Comment date: January 10, 2000, in accordance with Standard

Paragraph E at the end of this notice.

4. ISO New England Inc.

[Docket No. ER00-749-000]

Take notice that on December 22, 1999, ISO New England Inc. (the

ISO), tendered for filing a correction to its filing of December 8,

1999 in the referenced docket.

Copies of said filing have been served upon all Participants in the

New England Power Pool (NEPOOL) and all non-Participant entities that

are customers under the NEPOOL Open Access Transmission Tariff, as well

as, on the governors and utility regulatory agencies of the six New

England States.

Comment date: January 11, 2000, in accordance with Standard

Paragraph E at the end of this notice.

5. PJM Interconnection, L.L.C.

[Docket No. ER00-889-000]

Take notice that on December 23, 1999, PJM Interconnection, L.L.C.

(PJM), tendered for filing a Network Integration Transmission Service

Agreement with Old Dominion Electric Cooperative (ODEC) and a Notice of

Cancellation of a predecessor Network Integration Transmission Service

Agreement with ODEC.

PJM requests a waiver of the 60-day notice requirement and an

effective date of December 1, 1999 for the new Network Integration

Service Agreement and the cancellation of the prior agreement.

Copies of this filing were served upon ODEC and the state

commissions within the PJM control area.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

6. PJM Interconnection, L.L.C.

[Docket No. ER00-890-000]

Take notice that on December 23, 1999, PJM Interconnection, L.L.C.

(PJM), tendered for filing 18 signature pages of parties to the

Reliability Assurance Agreement among Load Serving Entities in the PJM

Control Area (RAA), four of which are replacement pages for entities

[[Page 767]]

which have changed their corporate name, and an amended Schedule 17

listing the parties to the RAA.

PJM states that it served a copy of its filing on all parties to

the RAA, including each of the parties for which a signature page is

being tendered with this filing, and each of the state electric

regulatory commissions within the PJM Control Area.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

7. Delano Energy Company, Inc.

[Docket No. ER00-891-000]

Take notice that on December 23, 1999, Delano Energy Company, Inc.

(Delano), tendered for filing a petition for waiver and blanket

approvals under various regulations of the Commission and for an order

accepting its proposed tariff governing negotiated market-based

capacity and energy sales, including sales of ancillary services. If

accepted for filing, Delano will use the market rate tariff to sell

power from its generation facility.

Delano has requested an effective date for the market rate tariff

as of January 1, 2000.

A copy of this filing was served on the California Public Utilities

Commission.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

8. Delano Energy Company, Inc.

[Docket No. ER00-892-000]

Take notice that on December 23, 1999, Delano Energy Company, Inc.

(Delano), tendered for filing a notice to cancel FERC Electric Rate

Schedule No. 1.

Delano has requested an effective date for notice of cancellation

as of January 1, 2000.

A copy of this filing was served on the California Public Utilities

Commission and Southern California Edison Company.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

9. PacifiCorp

[Docket No. ER00-893-000]

Take notice that on December 23, 1999, PacifiCorp, tendered for

filing in accordance with 18 CFR 35 of the Commission's Rules and

Regulations, a Mutual Netting/Closeout Agreement (Netting Agreement)

between PacifiCorp and Basin Electric Power Cooperative (Basin), City

of Riverside, California (Riverside), San Diego Gas & Electric Company

(San Diego), and The Energy Authority, Inc. (TEA).

Copies of this filing were supplied to the Washington Utilities and

Transportation Commission and the Public Utility Commission of Oregon.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

10. Onondaga Cogeneration Limited Partnership

[Docket No. ER00-895-000]

Take notice that on December 23, 1999, Onondaga Cogeneration

Limited Partnership (Onondaga), tendered for filing pursuant to Rule

204 and Rule 205 (18 CFR 385.204, and 18 CFR 385.205) an application

for waivers and blanket approvals under certain Commission Regulations

and for an order accepting its FERC Electric Rate Schedule No. 2 to be

effective at the earliest possible time, but no later than 60 days from

the date of its filing.

Onondaga intends to engage in marketing and sales of electric

energy and capacity at market-based rates. As described in the

application, Onondaga is an affiliate of GPU, Inc., a public utility

holding company and the parent company of Jersey Central Power & Light

Company, Metropolitan Edison Company and Pennsylvania Electric Company.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

11. Pacific Gas and Electric Company

[Docket No. ER00-900-000]

Take notice that on December 27, 1999, Pacific Gas and Electric

Company (PG&E), tendered for filing a request to change its California

Independent System Operator (ISO) Grid Management Charge (GMC) Pass

Through rate from $.7831 per MWh to $.8300 per MWh. This filing is part

of the comprehensive restructuring proposal for the California electric

power industry that is before the Federal Energy Regulatory Commission.

PG&E requests that its filing be made effective January 1, 2000.

Copies of this filing have been served upon the California Public

Utilities Commission and all other parties on the Service List to this

proceeding.

Comment date: January 16, 2000, in accordance with Standard

Paragraph E at the end of this notice.

12. Public Service Company of New Mexico

[Docket No. ER00-896-000]

Take notice that on December 23, 1999, Public Service Company of

New Mexico (PNM), tendered for filing a proposed unbundled generation

sales agreement (Generation Agreement) between PNM and the United

States Department of Energy on behalf of the United States Government

(the Government) for wholesale power sales under PNM's Electric

Coordination Tariff No. 1, providing for wholesale electric generation

sales to the Government for the Government's wholesale loads, if any,

at the United States Department of Energy's Sandia National

Laboratories and the United States Department of Defense's Kirtland Air

Force Base, collectively.

PNM requests an effective date as may be determined by the

Commission, but no earlier than December 14, 1999, for the Generation

Agreement, and further requests waiver of the requirements of 18 CFR

35.3(a) to allow the Agreement to become effective less than 60 days or

more than 120 days after filing.

Comment date: January 12, 2000, in accordance with Standard

Paragraph E at the end of this notice.

13. Arizona Public Service Company

[Docket No. ER00-901-000]

Take notice that on December 27, 1999, Arizona Public Service

Company (APS), tendered for filing a Service Agreement to provide

Retail Network Integration Transmission Service under APS' Open Access

Transmission Tariff to the Arizona Public Service Company Merchant

Group (Merchant Group).

A copy of this filing has been served on Merchant Group and the

Arizona Corporation Commission.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

14. Pacific Gas and Electric Company

[Docket No. ER00-902-000]

Take notice that on December 27, 1999, Pacific Gas and Electric

Company (PG&E), tendered for filing an agreement between PG&E and

Dynegy Power Services, Inc. (DPS) (collectively, Parties), entitled

Settlement Agreement between Dynegy Power Services, Inc., and Pacific

Gas and Electric Company. The Settlement Agreement is intended to,

among other things, settle issues and disputes under PG&E Rate Schedule

FERC No. 185.

Copies of this filing have been served upon DPS, CAISO and the

California Public Utilities Commission.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

15. Duke Energy Corporation

[Docket No. ER00-903-000]

Take notice that on December 27, 1999, Duke Energy Corporation

(Duke),

[[Page 768]]

tendered for filing a Service Agreement with Conectiv Energy Supply,

Inc., for Non-Firm Transmission Service under Duke's Open Access

Transmission Tariff.

Duke requests that the proposed Service Agreement be permitted to

become effective on November 2, 1999 or upon acceptance by the

Commission.

Duke states that this filing is in accordance with Part 35 of the

Commission's Regulations and a copy has been served on the North

Carolina Utilities Commission.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

16. Duke Energy Corporation

[Docket No. ER00-904-000]

Take notice that on December 27, 1999, Duke Energy Corporation

(Duke), tendered for filing a Service Agreement with Tampa Electric

Company for Non-Firm Transmission Service under Duke's Open Access

Transmission Tariff.

Duke requests that the proposed Service Agreement be permitted to

become effective on April 22, 1999 or upon acceptance by the

Commission.

Duke states that this filing is in accordance with Part 35 of the

Commission's Regulations and a copy has been served on the North

Carolina Utilities Commission.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

17. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-905-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(Allegheny Energy Supply), tendered for filing Supplement No. 15 to add

one (1) new Customer to the Market Rate Tariff under which Allegheny

Energy Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of December 23, 1999 to Rainbow Energy

Marketing Corporation.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

18. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-906-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(Allegheny Energy Supply), tendered for filing Supplement No. 13 to add

one (1) new Customer to the Market Rate Tariff under which Allegheny

Energy Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of December 5, 1999 to Commonwealth Edison

Company.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

19. PacifiCorp

[Docket No. ER00-908-000]

Take notice that on December 27, 1999, PacifiCorp, tendered for

filing in accordance with 18 CFR 35 of the Commission's Rules and

Regulations, the Power Sales Agreement with Hinson Power Company under

PacifiCorp's FERC Electric Tariff, First Revised Volume No. 12.

Copies of this filing were supplied to the Washington Utilities and

Transportation Commission and the Public Utility Commission of Oregon.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

20. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-909-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(Allegheny Energy Supply), tendered for filing Supplement No. 14 to add

two (2) new Customers to the Market Rate Tariff under which Allegheny

Energy Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of December 6, 1999 to Sempra Energy Trading

Corp., and Wabash Valley Power Association, Inc.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

21. Wisconsin Public Service Corporation

[Docket No. ER00-910-000]

Take notice that on December 27, 1999, Wisconsin Public Service

Corporation (WPSC), tendered for filing an executed Service Agreement

with POWEREX providing for transmission service under FERC Electric

Tariff, Volume No. 1.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

22. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-907-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(``Allegheny Energy Supply'') filed Supplement No. 10 to add three (3)

new Customers to the Market Rate Tariff under which Allegheny Energy

Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of November 29, 1999 to DTE Energy Trading,

Inc., Northern Indiana Public Service Company and PP&L, Inc.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

23. Wisconsin Public Service Corporation

[Docket No. ER00-911-000]

Take notice that on December 27, 1999, Wisconsin Public Service

Corporation (WPSC), tendered for filing an executed Service Agreement

with

[[Page 769]]

POWEREX providing for transmission service under FERC Electric Tariff,

Volume No. 1.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

24. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-912-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(Allegheny Energy Supply), tendered for filing Supplement No. 12 to add

four (4) new Customers to the Market Rate Tariff under which Allegheny

Energy Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of December 2, 1999 to Citizens Power Sales,

Horizon Energy Company d/b/a Exelon Energy, Merchant Energy Group of

the Americas and TXU Energy Trading Company.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

25. Allegheny Energy Service Corporation on behalf of Allegheny

Energy Supply Company, LLC

[Docket No. ER00-913-000]

Take notice that on December 27, 1999, Allegheny Energy Service

Corporation on behalf of Allegheny Energy Supply Company, LLC

(Allegheny Energy Supply), tendered for filing Supplement No. 11 to add

one (1) new Customer to the Market Rate Tariff under which Allegheny

Energy Supply offers generation services.

Allegheny Energy Supply requests a waiver of notice requirements to

make service available as of December 1, 1999 to PG&E Energy Trading-

Power, L.P.

Copies of the filing have been provided to the Public Utilities

Commission of Ohio, the Pennsylvania Public Utility Commission, the

Maryland Public Service Commission, the Virginia State Corporation

Commission, the West Virginia Public Service Commission, and all

parties of record.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

26. PacifiCorp

[Docket No. ER00-914-000]

Take notice that PacifiCorp on December 27, 1999, tendered for

filing in accordance with 18 CFR 35 of the Commission's Rules and

Regulations, Short-term Firm and Non-firm Point-To-Point Transmission

Service Agreements with Deseret Generation and Transmission Cooperative

(Deseret), Morgan Stanley Capital Group Inc. (Morgan Stanley) and PP&L

Montana under PacifiCorp's FERC Electric Tariff, First Revised Volume

No. 11.

Copies of this filing were supplied to the Washington Utilities and

Transportation Commission and the Public Utility Commission of Oregon.

Comment date: January 14, 2000, in accordance with Standard

Paragraph E at the end of this notice.

27. Chugach Electric Association, Inc.

[Docket No. NJ00-1-000]

Take notice that on December 27, 1999, Chugach Electric

Association, Inc. (Chugach), tendered for filing a petition for a

declaratory order determining that its open access transmission tariff

satisfies the Commission comparability standards and is an acceptable

reciprocity tariff. Chugach also seeks a waiver of the requirements of

Order No. 889, on the ground that it is a small electric utility, and

waiver of the filing fee otherwise applicable to a petition for

declaratory order.

Comment date: January 26, 2000, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest such filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,

in accordance with Rules 211 and 214 of the Commission's Rules of

Practice and Procedure (18 CFR 385.211 and 385.214). All such motions

or protests should be filed on or before the comment date. Protests

will be considered by the Commission in determining the appropriate

action to be taken, but will not serve to make protestants parties to

the proceeding. Any person wishing to become a party must file a motion

to intervene. Copies of these filings are on file with the Commission

and are available for public inspection. This filing may also be viewed

on the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-

208-2222 for assistance).

David P. Boergers,

Secretary.

[FR Doc. 00-229 Filed 1-5-00; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.