Wave, Tidal, and In-Stream Energy Projects: Which Federal Agency Has the Lead?

Congressional research reportNov 26, 2008

Ask Donna

What actually matters in this document.

Text

Order Code RS22721

Updated November 26, 2008

Wave, Tidal, and In-Stream Energy Projects:

Which Federal Agency Has the Lead?

Nic Lane

Analyst in Natural Resources Policy

Resources, Science, and Industry Division

Summary

Developments in wave, tidal, and in-stream energy generation technologies — also

referred to as hydrokinetic or marine energy — are beginning to gain momentum. At

the same time, their regulatory status is still evolving, as shown by recent changes in law

aimed at clarifying the federal role in ocean wave and renewable energy. Two federal

agencies currently appear to have a lead role in offshore renewable energy projects.

The Department of the Interior’s Minerals Management Service (MMS) indicates

that the Energy Policy Act of 2005, § 388, gave it authority as the lead agency for

projects proposed on the Outer Continental Shelf (OCS). MMS is developing a

regulatory framework and is not accepting applications for hydrokinetic (and other

alternative energy) projects until its rulemaking process is complete.

The Federal Energy Regulatory Commission (FERC) has issued preliminary

permits and accepted license applications for hydrokinetic projects on the OCS and in

the near-shore ocean environment. Also, FERC is developing a licensing process

specific to hydrokinetic projects. The issue of which agency has final regulatory

authority over hydrokinetic projects that are partially or completely on the OCS is

unresolved and may affect project development in this burgeoning industry.

Background

Electric generation projects that are designed to harness the power of waves, tides,

or river currents — without a dam or impoundment — are known as hydrokinetic or

marine energy projects. While the technology to harness this energy is still in the

developmental stage, interest has increased in exploring this potential source of electric

power. For example, projects are being considered in a number of states, including

Alaska, California, Hawaii, Louisiana, Maine, New York, New Jersey, Oregon, Rhode

Island, and Washington. A special temporary license exemption was issued for a

prototype tidal energy project in New York’s East River, and a Federal Energy Regulatory

Commission (FERC) hydropower license, the first for this type of project, is pending for

a wave energy project in Washington. As project developers have begun to explore

CRS-2

opportunities in this sector, Congress has introduced legislation to support and regulate

this nascent industry.

EPACT

The 109th Congress considered legislation related to hydrokinetic power. In

particular, the Energy Policy Act of 2005 (EPACT)1 addresses wave, tidal, and in-stream

energy directly or indirectly in a number of ways. EPACT addresses federal jurisdiction

over, and development of, alternative energy sources. Title II contains provisions for

assessing and reporting on renewable energy resources by the Department of Energy. It

also establishes incentives for renewable energy production, specifies benchmarks for

renewable energy purchases by federal facilities, and authorizes grants supporting rural

electrification, with preference given to renewable energy facilities. Section 931 directs

the Secretary of Energy to establish R&D programs for ocean energy, including wave

energy, and kinetic hydro projects. Section 388 amends § 8 of the Outer Continental

Shelf Lands Act2 to grant authority to the Secretary of the Interior, through the Minerals

Management Service (MMS), to grant leases on the Outer Continental Shelf (OCS) for

producing energy from sources other than oil and gas.

Legislation

P.L. 110-140 authorized $50 million annually from FY2008 through FY2012 for the

creation of at least one national ocean energy research center. The 110th Congress also

approved funding for hydrokinetic energy development in FY2008 appropriations

legislation. Under P.L. 110-161, approximately $10 million was provided for water

power R&D, which includes hydrokinetic generation. The Emergency Economic

Stabilization Act of 2008 (P.L. 110-343) authorized a production tax credit applicable to

hydrokinetic projects having a nameplate capacity of 150 kilowatts or greater and

producing power by January 1, 2012.

Who Has Primary Authority over Hydrokinetic Energy Projects?

In addition to technological and resource uncertainties, one of the principal

uncertainties facing hydrokinetic energy developers is that of the primary regulatory

agency for their industry. Presently, two federal agencies have asserted a lead role in the

oversight of wave, tidal, and in-stream energy projects: FERC and MMS.3

Minerals Management Service (MMS). The Department of the Interior’s MMS

manages the nation’s Outer Continental Shelf (OCS)4 oil, natural gas, and other mineral

resources. The agency is responsible for more than $8 billion in annual revenues from

1

P.L. 109-58.

2

43 U.S.C. § 1337.

3

For more information on broader issues related to hydrokinetic project development, see CRS

Report RL33883, Issues Affecting Tidal, Wave, and In-Stream Generation Projects, by Nic Lane.

4

The OCS is composed of the submerged lands, subsoil, and sea bed lying between the seaward

extent of the states’ jurisdiction and the seaward extent of federal jurisdiction. Typically, this

is the area between 3 and 200 nautical miles.

CRS-3

federal offshore mineral leases (as well as onshore mineral leases on federal and Indian

lands). EPACT 2005 granted MMS additional authority to act as the lead federal agency

for offshore renewable energy projects. MMS views its primary authorities under EPACT

§ 388 to be (1) granting leases, easements, and rights-of-way for renewable energy-related

uses on federal OCS lands; (2) acting as the lead agency for coordinating the permitting

process with other federal agencies; and (3) monitoring and regulating facilities used for

renewable energy production and energy support services.5

MMS has issued a final programmatic environmental impact statement (PEIS)

analyzing the environmental impact of a program to develop hydrokinetic energy projects

on the OCS. It anticipates issuing a final rule on the process of lease application and

energy project development in the fall of 2008.6 MMS will not issue decisions on

hydrokinetic energy projects until a final rule is established,7 but indicates that in advance

of a final rule it has established an interim process that includes limited-term leases to

allow data collection and technology testing — but no commercial-scale project

development.8 MMS has received over 40 nominations for these limited use leases.9

Additionally, MMS has released proposed rules for alternative energy projects on the

OCS with a 60-day comment period.10 The proposed rules indicate that two types of

leases may be available for project sponsors: commercial and limited. Commercial leases

would have a term up to 25 years and allow full commercial energy production. Limited

leases would have a shorter five-year term and are intended for site assessment,

technology testing, and other pre-commercial activities.11

EPACT § 388 stipulates that MMS authority does not supercede the existing

authority of any other agency for hydrokinetic project permitting, so it is possible that a

wave or tidal energy project on the OCS may also require a FERC license to operate,

although leasing and environmental review would be conducted by MMS.12 MMS

indicates that it intends to finalize its rulemaking process by December 2008.13

Federal Energy Regulatory Commission (FERC). The Federal Power Act

(FPA)14 authorized FERC to be the agency responsible for licensing almost all nonfederal

5

See [http://www.mms.gov/offshore/RenewableEnergy/RenewableEnergyAndAlternateUses.

pdf].

6

See [http://www.mms.gov/offshore/CIAP/PDFs/Visio-3timelines040207A.pdf].

7

See [http://www.mms.gov/offshore/RenewableEnergy/OCSPolicyCmteMtg022107.pdf].

8

72 Fed. Reg. 214, November 6, 2007.

9

73 Fed. Reg. 76, April 18, 2008.

10

73 72 Fed. Reg. 132, July 9, 2008.

11

Ibid.

12

Personal communication with Ms. Julie Fleming, Legislative Specialist, Minerals Management

Service, Washington, DC, January 22, 2007.

13

See [http://www.mms.gov/ooc/press/2008/press0708.htm].

14

16 U.S.C. § 817(1).

CRS-4

hydropower projects.15 There has been no debate about FERC’s jurisdiction over

hydrokinetic projects in rivers and inland waters, but there may be some question about

its authority over these projects in the ocean.

FERC has asserted that its authority includes hydrokinetic projects in the ocean up

to 12 miles from shore.16 FERC supports this statement with citations to the FPA17 and

Presidential Proclamation 5928,18 which extended the territorial sea,19 and thus, FERC

asserts, its jurisdiction, to 12 nautical miles.

Further, FERC has indicated that project features such as undersea anchors or

transmission lines leading to a grid connection on the shore would occupy land under

federal jurisdiction, thereby requiring the project to have a FERC license. In addition,

FERC has stated that it considers hydrokinetic energy facilities to be “powerhouses” as

defined by the FPA licensing provision,20 and has indicated that it considers wave and

tidal projects that connect to the electric grid to be affecting interstate commerce, thus

requiring a FERC license.21

FERC had issued over 100 preliminary permits for developers to study hydrokinetic

project sites, and dozens more preliminary permit applications are pending approval.22

A preliminary permit is not a license to construct and operate a project, but rather grants

the applicant the right to study an area for suitability of project development prior to a

formal license application. Additionally, FERC has finalized the first license for a

hydrokinetic project under a new “conditional” license program (see “MMS-FERC

Conflict,” below).23

MMS-FERC Conflict. In response to FERC’s acceptance of several preliminary

permit applications for hydrokinetic energy projects on the OCS off the coasts of

California and Oregon, MMS filed formal protests with FERC citing specific points of

contention. MMS indicated that it believes FERC jurisdiction does not extend to the OCS

for three reasons and requested that the agency reject the application in question and stop

15

There are limited circumstances when a FERC license, or FERC-granted license exemption,

is not required for a hydropower project. For instance, projects operating under a valid

congressional permit issued before 1920 would not be subject to FERC jurisdiction.

16

102 FERC ¶61,242.

17

16 U.S.C. § 796 (8).

18

54 Federal Register 777, December 27, 1988.

19

Under international law, every coastal nation has sovereign rights over the air space, water

column, sea bed, and anything beneath it, within its territorial sea. In 1988, President Reagan

proclaimed that the United States’ territorial sea extended 12 nautical miles seaward from the

coast.

20

16 U.S.C. § 817 (1).

21

102 FERC ¶61,242.

22

See [http://www.ferc.gov/industries/hydropower/indus-act/hydrokinetics/permits-issued.asp].

23

122 FERC ¶61,248.

CRS-5

processing preliminary permits for similar projects on the OCS.24 The three reasons MMS

cites are as follows:

!

FPA-granted jurisdiction for FERC does not explicitly extend on to the

OCS. Further, MMS refutes FERC’s claim that Presidential Proclamation

5928 also extends FERC authority to 12 nautical miles. In support of this

point, MMS refers to Proclamation language indicating that “Nothing in

this Proclamation: (a) extends or otherwise alters existing Federal or

State law or any jurisdiction, rights, legal interests, or obligations derived

therefrom....”25

!

MMS stresses that § 388 of EPACT specifically grants it authority for

renewable energy projects on the OCS.

!

MMS says that FERC’s existing hydropower permitting and licensing

process is inappropriate for hydrokinetic energy projects on the OCS

because preliminary permits may reserve large areas of potential

development to the first applicant rather than to the best applicant. Also,

MMS says that a 30- to 50-year license is too long for prototype projects.

At least one preliminary permit applicant in the instance cited above subsequently

submitted additional information for its permit application, reconfiguring to a project area

located in state waters within three nautical miles of shore, thus avoiding the OCS and any

issue of MMS jurisdiction.26 FERC issued a preliminary permit for the project reflecting

the modified footprint of the site provided by the applicant.27

FERC has since posted a Notice of Inquiry soliciting comments on its preliminary

permitting procedure and outlining its interim policy on the issue. The agency has

received numerous comments from project proponents, state agencies, and tribal entities.

Pending final resolution, it will continue to issue preliminary permits for hydrokinetic

projects under a “stricter scrutiny” policy. FERC states that preliminary permits will be

issued with more limited project boundaries and that required project progress reports will

be given closer review.28 Although CRS has found no public FERC response to the MMS

protests, it appears that for a period of approximately one year following the protests,

none of the preliminary permits issued were for projects that reach onto the OCS.

However, in March 2008, FERC issued preliminary permits for projects that include

24

MMS, Protest of the United States Minerals Management Service, FERC Docket P-12752-000

(January 30, 2007); MMS, Protest of the United States Minerals Management Service, FERC

Docket P-12750-000 (February 20, 2007); and MMS, Protest of the United States Minerals

Management Service, FERC Docket P-12753-000 (March 2, 2007).

25

54 Federal Register 777, December 27, 1988.

26

FERC, AquaEnergy Group, Ltd submits additional information that reduces the project

boundary & more accurately represents the footprint of the proposed project under P-12752,

Docket Number P-12752-000 (February 6, 2007).

27

FERC, Order issuing preliminary permit re AquaEnergy Group Ltd under P-12752, Docket

Number P-12752-000 (April 26, 2007).

28

FERC, Notice of Inquiry, Docket Number RM07-08-000 (February 15, 2007).

CRS-6

portions of the OCS off of California. The Department of the Interior has filed a request

for rehearing of the FERC order issuing those permits.29 FERC has since reasserted its

authority over projects on the OCS and denied the Department of the Interior’s request

for rehearing.30

FERC has developed a modified license for hydrokinetic pilot projects. This process

is available immediately for interested parties, though the agency is accepting comments

on the process in order to refine it. FERC held a technical conference on October 2, 2007,

to seek feedback from stakeholders on the new license. The goal of the hydrokinetic

license is to eliminate barriers to development by reducing processing time to as little as

six months, allowing installation of test equipment, and allowing power generation to the

grid. The license requires that projects have a size of five megawatts or less, be easily

removed or deactivated, and be installed for no longer than a five-year term. There are

additional provisions for site decommissioning and project changes or equipment removal

if unexpected environmental impacts arise.31

Further, FERC has also developed a conditional license. Unlike the pilot license

program, this is a full project operating license that allows applicants to begin nonconstruction activities while some permitting processes — such as water quality

certification — are still pending.

FERC and MMS are on separate tracks to develop regulatory processes for energy

projects in the ocean. However, the issue of ultimate regulatory authority for projects

entirely or partially on the OCS remains. The uncertainty over lead regulatory status on

the OCS is an important issue that may discourage investors in this developing industry.

Under the current regulatory framework, project owners may be reluctant to develop

sites beyond three nautical miles to avoid the possibility of regulatory duplication. The

final configuration of each agency’s regulatory framework could have a major impact on

project-siting decisions. Developers may decide to site projects completely on one side

of the three-mile OCS boundary, depending on which regulatory process they deem to be

more favorable. This type of approach could distort the industry’s development or leave

otherwise promising sites undeveloped.

29

FERC, Request for Rehearing of U.S. Department of the Interior under P-12779-000 and

P-12781.Docket Numbers P-12779-000 and P-12781-000 (April 14, 2008).

30

125 FERC ¶61,045.

31

See [http://www.ferc.gov/industries/hydropower/indus-act/hydrokinetics/energy-pilot.asp].