Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Congressional research reportDec 11, 2006
Ask Donna
What actually matters in this document.
Text
Navy Ship Acquisition: Options for LowerCost Ship Designs—Issues for Congress
Ronald O’Rourke
Specialist in Naval Affairs
December 11, 2006
Congressional Research Service
7-....
www.crs.gov
RL32914
CRS Report for Congress
Prepared for Members and Committees of Congress
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Summary
Rising procurement costs for Navy ships are a matter of concern for both Navy officials and
Members of Congress who track Navy-related issues. The Congressional Budget Office (CBO)
estimates that executing the 30-year shipbuilding plan that the Navy submitted to Congress in
early 2006 may require annual funding levels about 33% higher than the Navy plans, and about
76% more than the Navy has received on average in recent years. The issue for Congress is how
to respond to rising Navy ship procurement costs.
Aside from reducing planned ship procurement rates, one option would be to reduce Navy ship
procurement costs by shifting from currently planned designs to designs with lower unit
procurement costs. Lower-cost ship designs have been proposed in recent reports by the CBO,
Department of Defense’s Office of Force Transformation (OFT), and the Center for Strategic and
Budgetary Assessments (CSBA).
Options for lower-cost submarines include a non-nuclear-powered submarine and a reduced-cost
SSN design using new technologies now being developed. Options for lower-cost aircraft carriers
include a medium-sized, conventionally powered carrier and a small, high-speed carrier. Options
for lower-cost major surface combatants include a new-design 11,000-ton cruiser-destroyer, a
6,000-ton frigate (FFG(X)), or a lower-cost gunfire support ship. Options for a lower-cost smaller
surface combatant include a 1,000- or 100-ton surface ship.
FY2007 Defense Authorization Act (H.R. 5122/P.L. 109-364). Section 121 of P.L. 109-364
(conference report H.Rept. 109-702 of September 29, 2006) authorizes 4-year incremental
funding for the CVN-21 class aircraft carriers CVN-78, CVN-79, and CVN-80. Section 122
establishes unit procurement cost caps for CVN-21 class aircraft carriers. Section 123 increases a
previously legislated procurement cost cap for the CVN-77 aircraft carrier. Section 125
establishes a unit procurement cost cap for LHA(R) amphibious assault ships. Section 126
establishes unit procurement cost caps for four LPD-17 class amphibious ships. Section 215
authorizes $4 million for implementing or evaluating Navy shipbuilding technology proposals
under the Defense Acquisition Challenge Program. Section 1016 directs the Navy to conduct an
assessment of naval vessel construction efficiencies and of the effectiveness of special contractor
incentives. The sections establishing new procurement cost caps allow the caps to be adjusted
upward for inflation and other factors.
This CRS report will be updated when events warrant.
Congressional Research Service
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Contents
Introduction and Issue For Congress............................................................................................1
Background ................................................................................................................................2
Recent Reports Proposing Lower-Cost Designs .....................................................................2
Basic Approaches For Arriving At Lower-Cost Designs.........................................................2
Options for Lower-Cost Ships ...............................................................................................3
Attack Submarines ..........................................................................................................3
Aircraft Carriers..............................................................................................................6
Larger Surface Combatants ........................................................................................... 10
Smaller Surface Combatants ......................................................................................... 12
Issues For Congress .................................................................................................................. 13
Cost .................................................................................................................................... 14
Development And Design Cost ..................................................................................... 14
Procurement Cost.......................................................................................................... 14
Life-Cycle Operation and Support (O&S) Cost.............................................................. 15
End-Of-Life Disposal Cost............................................................................................ 16
Capability ........................................................................................................................... 16
Payload......................................................................................................................... 16
Detectability and Survivability ...................................................................................... 18
Mobility........................................................................................................................ 18
Ship Numbers In Naval Operations ............................................................................... 20
Technical Risk .................................................................................................................... 21
Homeporting Arrangements ................................................................................................ 21
Impact On Shipbuilding Industrial Base .............................................................................. 21
Total Volume Of Work .................................................................................................. 21
Distribution Of Work Among Shipyards ........................................................................ 22
Legislative Activity For FY2007 ............................................................................................... 23
FY2007 Defense Authorization Act (H.R. 5122/P.L. 109-364) ............................................. 23
House ........................................................................................................................... 23
Senate........................................................................................................................... 26
Conference Report ........................................................................................................ 28
FY2007 Defense Appropriations Act (H.R. 5631/P.L. 109-289) ........................................... 30
House ........................................................................................................................... 30
Tables
Table 1. Matrix of Notional Options For Aircraft Carriers.......................................................... 10
Appendixes
Appendix. Other Options for Responding to Rising Ship Costs.................................................. 32
Congressional Research Service
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Contacts
Author Contact Information ...................................................................................................... 34
Congressional Research Service
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Introduction and Issue For Congress
Rising procurement costs for Navy ships are a matter of concern for both Navy officials and
Members of Congress who track Navy-related issues. The Congressional Budget Office (CBO)
estimates that executing a 30-year Navy shipbuilding plan submitted to Congress in early 2006
may require annual funding levels about 33% higher than the Navy plans, and about 76% more
than the Navy has received on average in recent years.1 Combined with constraints on shipprocurement funding, rising ship procurement costs have caused the Navy in recent years to
reduce planned ship procurement rates. Some Members of Congress have expressed concern
about the effects these reduced rates would have on the future size of the Navy and on the
shipyards that build the Navy’s ships.
The issue for Congress is how to respond to rising Navy ship procurement costs. Congress’s
decisions on this issue could affect future Navy capabilities, Navy funding requirements, and the
shipbuilding industrial base.
Aside from reducing planned ship procurement rates, options for responding to rising Navy ship
procurement costs include the following:
•
increasing annual Navy ship-procurement funding;
•
changing the way Navy ships are funded in the budget;
•
making greater use of multiyear procurement (MYP) in Navy ship-procurement;
•
changing the acquisition strategy for building certain Navy ships;
•
taking steps to reduce the amount of shipyard fixed overhead costs that are
incorporated into the procurement costs of Navy ships;
•
improving the operating efficiency of yards building Navy ships;
•
building ships without some of their planned equipment (or with less expensive
substitute equipment); and
•
building ships in foreign shipyards where construction costs may be lower to due
lower wages and material prices or other factors.
For additional comments relating to these options, see Appendix.
An additional option, particularly if the above options are not implemented or prove insufficient,
would be to reduce Navy ship procurement costs by shifting from currently planned designs to
designs with lower unit procurement costs. This report focuses on this option.
1
For details on the CBO estimate, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans:
Background and Issues for Congress, by Ronald O’Rourke.
Congressional Research Service
1
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
The following section of the report provides background information on notional options for
lower-cost attack submarines, aircraft carriers, larger surface combatants, and smaller
surface combatants. The section that follows discusses issues that Congress may consider in
assessing the merits—the potential advantages and disadvantages—of shifting to lower-cost
designs. The final section of the report reviews recent legislative activity relating to rising Navy
ship procurement costs.
Background
Recent Reports Proposing Lower-Cost Designs
Lower-cost designs for attack submarines, aircraft carriers, larger surface combatants, and smaller
surface combatants have been proposed in recent reports on the future of the Navy by the CBO,2
DOD’s Office of Force Transformation (OFT),3 and an independent policy-research organization
called the Center for Strategic and Budgetary Assessments (CSBA). 4 Several of the lower-cost
ship designs discussed below are taken from these reports.
Basic Approaches For Arriving At Lower-Cost Designs
Options for lower-cost Navy ship designs can be generated by starting with currently planned
Navy ship designs and making one or more of the following changes:
•
Reducing ship size. For a given type of ship, procurement cost tends to be
broadly proportional to ship size. Reducing ship size can thus reduce
procurement cost. The Navy can be viewed as using this strategy for the Littoral
Combat Ship (LCS), which is to be considerably smaller than existing major
Navy surface combatants, but the strategy can be applied more widely.
•
Shifting from nuclear to conventional propulsion. This is a strategy that can be
considered for the Navy’s submarines and aircraft carriers, whose current designs
are nuclear-powered. Equipping a Navy ship with a conventional (i.e., fossil-fuel)
propulsion plant rather than a nuclear propulsion plant can reduce the ship’s
procurement cost by several hundred million dollars.
2
Congressional Budget Office, Options for the Navy’s Future Fleet, May 2006, pp. 56 and 57 (Box 3-1); and
Congressional Budget Office, Budget Options, Feb. 2005, pp. 18-19; and Congressional Budget Office, Transforming
the Navy’s Surface Combatant Force, Mar. 2003, pp. 27-28, 63. (Hereafter cited as CBO 2005 report, and CBO 2003
report, respectively.)
3
Department of Defense, Office of the Secretary of Defense, Alternative Fleet Architecture Design, 2005. (Hereafter
cited as OFT report.)
4
Robert O. Work, Winning the Race: A Naval Fleet Platform Architecture for Enduring Maritime Supremacy, Center
for Strategic and Budgetary Assessments, Washington, 2005. (Hereafter cited as CSBA report.)
Congressional Research Service
2
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
•
Shifting from a hull built to military survivability standards to a hull built to
commercial-ship survivability standards. A hull built to military survivability
standards has more armoring and internal compartmentalization than a hull built
to commercial-ship standards, making it more expensive to build than a
commercial-like hull. The Navy is considering building ships for its planned
Maritime Prepositioning Force (Future), or MPF(F), squadron, with commerciallike hulls, but the strategy can be applied more widely.
•
Using a common hull design for multiple ship classes. Using a common hull
design for multiple ship classes avoids the cost of designing a new hull for each
new class of ship, and permits ship classes sharing a common hull to benefit
from improved production economies of scale regarding their hulls. The Navy
plans to use the hull design for its planned DDG-1000 (formerly DD(X))
destroyer as the hull for its planned CG(X) cruiser, but the strategy can be
applied more widely. The OFT report proposes building four large surface
ships—an aircraft carrier, a missile-and-rocket ship, an amphibious assault ship,
and a small-craft “mother” ship—using a common merchant-like hull. The CSBA
report proposes using hull design for the Navy’s LPD-17 class amphibious ship
for building other kinds of ships.
Most of the lower-cost ship options presented below use one or more of these four approaches.
Information on the estimated procurement costs of the lower-cost designs is presented when
available. Lower-cost ship designs using these approaches will in most cases be individually less
capable than the currently planned ship designs from which they are derived, and this is one of
the assessment factors that is discussed in the final section of the report.
Options for Lower-Cost Ships
For each category of ship below, the discussion describes the current design and then outlines
potential lower-cost options. The discussions are descriptive only; the potential advantages and
disadvantages of shifting to the lower-cost designs are discussed in the final section of the report.
Attack Submarines
Current design:
•
Virginia (SSN-774) class nuclear-powered submarine
Potential lower-cost options:
•
AIP-equipped non-nuclear-powered submarine
•
Reduced-cost “Tango Bravo” nuclear-powered submarine
Congressional Research Service
3
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Virginia-Class (SSN-774) Nuclear-Powered Submarine5
The Navy is currently procuring one Virginia (SSN-774) class nuclear-powered attack submarine
(SSN) per year. Each submarine currently costs about $2.6 billion to procure. The FY2007FY2011 Future Years Defense Plan (FYDP) maintains Virginia-class procurement at one per year
through FY2011.
The Navy is proposing to maintain in coming years a fleet of 313 ships, including 48 SSNs.6
Fully supporting the Navy’s reportedly planned force of 48 boats could involve procuring a total
of 35 boats during the 16-year period FY2007-FY2022, or an average of about 2.2 boats per
year.7 A continuation beyond FY2011 of the current one-per-year rate, in contrast, could reduce
the SSN force to fewer than 30 boats by about 2030, before recovering to a steady-state level of
33 boats.8
One option for a lower-cost attack submarine would be a non-nuclear-powered submarine
equipped with an air-independent propulsion (AIP) system that could be procured in tandem with
Virginia-class SSNs. Another option would be a reduced-cost SSN using new “Tango Bravo”
technologies being developed by the Navy and the Defense Advanced Research Projects Agency
(DARPA) that would be procured as a successor to the Virginia-class design.
AIP-Equipped Non-Nuclear-Powered Submarine
Non-nuclear-powered submarines are less expensive than nuclear-powered submarines not only
because of the difference in propulsion systems, but also because non-nuclear-powered
submarines tend to be smaller than nuclear-powered submarines.
The OFT report proposed a future Navy consisting of several new kinds of ships, including airindependent propulsion (AIP)-equipped non-nuclear-powered submarines. 9 An AIP system such
as a fuel-cell or closed-cycle diesel engine extends the stationary or low-speed submerged
endurance of a non-nuclear-powered submarine. AIP-equipped submarines are currently being
acquired by certain foreign navies.
AIP submarines could be procured in tandem with Virginia-class boats. One possibility, for
example, would be to procure one Virginia-class boat plus one or more AIP submarines each year.
The OFT report recommended substituting four AIP submarines for one Virginia-class submarine
in each carrier strike group, suggesting that four AIP submarines might be procured for the same
cost ($2.4 billion to $3.0 billion in the FY2006-FY2011 FYDP) as one Virginia-class submarine.
This suggests an average unit procurement cost for an AIP submarine of roughly $600 million to
$750 million each. Although AIP submarines being built by other countries might cost this much
5
For more on the Virginia-class program, see CRS Report RL32418, Navy Attack Submarine Procurement:
Background and Issues for Congress, by Ronald O’Rourke. (Hereafter cited as CRS Report RL32418.)
6
For additional discussion, see CRS Report RL32665, op cit.
7
See CRS Report RL32418.
8
Ibid.
9
See also Christopher J. Castelli, “Defense Department Nudges Navy Toward Developing Diesel Subs,” Inside
the Navy, Mar. 7, 2005; Dave Ahearn, “Lawmakers Assail Navy Budget, But Eye Non-Nuke Subs,” Defense Today,
Mar. 3, 2005.
Congressional Research Service
4
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
to procure, a U.S. Navy AIP submarine might be built to higher capability standards and
consequently cost more to procure, possibly reducing the equal-cost ratio of substitution to three
to one or possibly something closer two to one. If so, then the annual cost of procuring one
Virginia-class SSN plus one, two, or perhaps three AIP submarines could be equal to or less than
that of procuring two Virginia-class boats per year.
Reduced-Cost “Tango Bravo” SSN
The Virginia class was designed in the early to mid-1990s, using technologies that were available
at the time. New technologies that have emerged since that time may now permit the design of a
new SSN that is equivalent in capability to the Virginia class design, but substantially less
expensive to procure. The Navy and DARPA are now pursuing the development of these
technologies under a program called Tango Bravo, a name derived from the initial letters of the
term “technology barriers.” As described by the Navy,
TANGO BRAVO will execute a technology demonstration program to enable design options
for a reduced-size submarine with equivalent capability as the VIRGINIA Class design.
Implicit in this focus is the goal to reduce platform infrastructure and, ultimately, the cost of
future design and production. Additionally, reduced platform infrastructure provides the
opportunity for greater payload volume.
The intent of this collaborative effort is to overcome selected technology barriers that
are judged to have a significant impact on submarine platform infrastructure cost.
Specifically, DARPA and the Navy will jointly formulate technical objectives for critical
technology demonstrations in (a) shaftless propulsion, (b) external weapons, (c) conformal
alternatives to the existing spherical array, (d) technologies that eliminate or substantially
simplify existing submarine systems, and (e) automation to reduce crew workload for
standard tasks.10
Some Navy and industry officials believed in 2004 that if these technologies are developed, it
might be possible to design a new submarine equivalent in capability to the Virginia class, but
with a procurement cost of perhaps 75% of the Virginia class. Such a submarine could more
easily be procured within available resources at a rate of two per year.
Consequently, as an alternative to the option of procuring AIP submarines, another option would
be to start design work now on a new “Tango Bravo” SSN. The idea of designing a submarine
with capability equivalent to that of Virginia-class and a procurement cost that is less than that of
the Virginia class has been discussed by Navy and industry officials. Under this option, Virginiaclass procurement could continue at one per year until the Tango Bravo submarine was ready for
procurement, at which point Virginia-class procurement would end, and procurement of the
Tango Bravo submarine would begin.
If design work on a Tango Bravo submarine is begun now and pursued in a concerted manner, the
first Tango Bravo submarine might be ready for procurement a few years from now.
10
Navy information paper on advanced submarine system development provided to CRS by Navy Office of Legislative
Affairs, Jan. 21, 2005. For additional discussion of the Tango Bravo program, see Aarti Shah, “Tango Bravo
Technology Contract Awards Expected This Spring,” Inside the Navy, Mar. 14, 2005; Andrew Koch, “US Navy In Bid
To Overhaul Undersea Combat,” Jane’s Defence Weekly, Mar. 9, 2005, p. 11; Lolita C. Baldor, “Smaller Subs Could
Ride Waves Of The Future,” NavyTimes.com, Feb. 4, 2005; Robert A. Hamilton, “Navy, DARPA Seek Smaller
Submarines,” Seapower, Feb. 2005, pp. 22, 24-25.
Congressional Research Service
5
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Aircraft Carriers
Current design:
•
Large nuclear-powered carrier, as exemplified by the George H.W. Bush (CVN77) and CVN-78
Potential lower-cost options:
•
Medium-sized, conventionally powered carrier based on LHA(R) amphibious
assault ship design
•
Medium-sized, conventionally powered carrier based on a commercial-like
hull design
•
Small carrier based on high-speed surface effect ship (SES)/ catamaran
hull design
CVN-77 and CVN-7811
The Navy is currently building large nuclear-powered aircraft carriers (CVNs). These ships
have a full load displacement of about 100,000 tons and can embark an air wing of about 75
conventional takeoff and landing (CTOL) airplanes and helicopters.
The George H. W. Bush (CVN-77), the last Nimitz (CVN-68) class carrier, was procured in
FY2001 at a total cost of $4.975 billion, but the ship’s estimated construction cost has since risen
to about $6.1 billion. The ship is scheduled to enter service in 2008.
The FY2007-FY2011 FYDP proposes to procure the next aircraft carrier, called CVN-78, in
FY2008. CVN-78 is the lead ship of a planned new carrier class called the CVN-21 class. (CVN21 simply means aircraft carrier for the 21st Century.) The Navy estimates CVN-78’s procurement
cost at $10.5 billion, including $2.4 billion in detailed design and nonrecurring engineering
(DD/NRE) costs and $8.1 billion in hands-on construction costs.12 Advance procurement funding
for CVN-78 has been provided since FY2001. If the ship is procured in FY2008, it would enter
service in 2015.
The next carrier, called CVN-79, is currently planned for procurement in FY2012. If the ship is
procured in FY2012, it would enter service around 2019. The next carrier after that, CVN-80, is
planned for procurement in FY2016.
One option for a lower-cost aircraft carrier involves designing a medium-sized, conventionally
powered aircraft carrier based on the design for a new amphibious assault ship called LHA-6 or
the LHA Replacement ship (LHA(R)), that is currently being developed by the Navy. 13 A
11
For more on CVN-77 and CVN-78, see CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier
Program: Background and Issues for Congress, by Ronald O’Rourke.
12
The total estimated acquisition cost of CVN-78, which also includes $3.2 billion in research and development
funding for the ship, is $13.7 billion.
13
Navy amphibious ships are given designations beginning with the letter L, which stands for landing, as in
amphibious landing. LHA can be translated as amphibious ship (L), helicopter platform (H), assault (A). Navy
LHAs and closely related ships designated LHDs (the D standing for well deck, an opening in the stern of the ship for
landing craft that the LHAs also have) have flight decks that run the length of the ship, giving these ships an aircraft(continued...)
Congressional Research Service
6
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
second option involves designing a medium-sized, conventionally powered aircraft carrier based
on a commercial-like hull design. A third option involves designing a small, high-speed,
conventionally powered aircraft carrier built on a surface effect ship (SES)/catamaran
hull design. 14
Medium-Sized Carrier Based on LHA(R) Design
The CSBA report recommended procuring CVN-21-class aircraft carriers as needed to maintain a
force of 10 large carriers (two ships less than the current 12-ship force). It also recommended
procuring an additional four medium-sized, conventionally powered aircraft carriers based on the
LHA(R) design. This ship might displace about 40,000 tons and embark an air wing of perhaps
about two dozen vertical/short takeoff or landing (VSTOL) versions of the F-35 Joint Strike
Fighter (JSF). Its unit procurement cost might be roughly $3 billion. 15
Medium-Sized Carrier Based on Commercial-Like Hull
The OFT report recommended procuring a medium-sized carrier based on a relatively
inexpensive, commercial-like hull design developed in 2004 for the Navy’s Maritime
Prepositioning Force (Future), or MPF(F), analysis of alternatives.16 This carrier, which would
have a full load displacement of about 57,000 tons, would embark a notional air wing of
36 manned aircraft—30 Joint Strike Fighters (JSFs) and 6 MV-22 Osprey tilt-rotor aircraft—
and 15 unmanned air vehicles (UAVs).
This ship would be somewhat larger than the LHA(R)-based carrier recommended in the CSBA
report, and roughly the same size as the United Kingdom’s new aircraft carrier design. (The
LHA(R)-based ship and the UK carrier, however, would use military hulls.) The OFT report
recommended substituting two of these 57,000-ton carriers for each of the Navy’s current large
carriers, so that the number of manned aircraft based at sea would remain about the same.
Small Carrier Using High-Speed SES/Catamaran Hull Design
As an alternative to the 57,000-ton medium-sized carrier, the OFT report recommended procuring
a small, high-speed carrier displacing 13,500 tons that would use a surface effect ship
(SES)/catamaran hull. The ship was based on a design for an unmanned aerial vehicle/unmanned
combat aerial vehicle (UAV/UCAV) carrier that was developed in 2000-2002 by a team at the
Naval Postgraduate School. 17 The OFT report recommended using the ship to embark a notional
air wing of 10 manned aircraft—8 JSFs and 2 MV-22s—and 8 UAVs, and have a maximum speed
of 50 to 60 knots.
(...continued)
carrier-like appearance.
14
A surface effect ship is supported above the water by a cushion of air that is trapped beneath the ship.
15
For more on the LHA(R), see CRS Report RL32513, Navy-Marine Corps Amphibious and Maritime Prepositioning
Ship Programs: Background and Oversight Issues for Congress, by Ronald O’Rourke. (Hereafter cited as CRS Report
RL32513.)
16
For more on the MPF(F) program, see CRS Report RL32513. The OFT report also recommended using this same
57,000-ton hull as the basis for a missile-and-rocket ship, an amphibious ship, and a small-combatant mother ship.
17
The design was developed by the Total Ship Systems Engineering group at the Naval Postgraduate School under an
(continued...)
Congressional Research Service
7
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
This ship would be slightly larger than Thailand’s 11,500-ton aircraft carrier, which was
commissioned in 1997. It would be smaller than Spain’s 17,000 aircraft carrier, which was based
on a U.S. design18 and was commissioned in 1988, or the UK’s three existing 20,600-ton carriers,
which were commissioned between 1980 and 1985. The OFT-recommended ship would be much
faster than the Thai, Spanish, or existing UK carriers, or any other aircraft carrier now in
operation. The OFT report recommended substituting eight of these 13,500-ton carriers for each
of the Navy’s current large carriers, so that the number of manned aircraft based at sea would
remain about the same.
Additional Potential Options
Studies of aircraft carrier acquisition options over the years have discussed many other potential
designs, including the following:
•
A large, conventionally powered carrier. Such a ship, which might use the
same hull design as CVN-78, might displace about 100,000 tons. It would be
broadly similar to the Kitty Hawk (CV-63) and John F. Kennedy (CV-67), the
Navy’s two remaining conventionally powered carriers, which displace roughly
82,000 tons and embark air wings similar to those embarked by the Navy’s large
nuclear-powered carriers. The ship might have a procurement cost several
hundred million dollars less than that of CVN-78.
•
A medium-sized nuclear-powered carrier. Such a ship might be based on the
LHA(R) hull and use a half-sized version of the CVN-78 nuclear propulsion
plant.19 Like the CSBA-recommended conventionally powered carrier based on
the LHA(R) design, this ship might displace about 40,000 tons and embark about
two dozen VSTOL JSFs. If the CSBA-recommended conventionally powered
carrier would cost roughly $3 billion, a nuclear-powered version would cost more
than $3 billion. The ship might be considered broadly similar to the France’s
nuclear-powered carrier, the Charles de Gaulle, which was commissioned in
2001, displaces 42,000 tons, and embarks an air wing of about 34 conventional
takeoff and landing (CTOL) airplanes and two helicopters.
(...continued)
effort called the Crossbow project. Within that project, the carrier was referred to as Sea Archer. For more on the Sea
Archer, see http://web.nps.navy.mil/~me/tsse/files/2001.htm. See also Jason Ma, “Naval Postgraduate School Issues
Report on Crossbow Project,” Inside the Navy, Oct. 28, 2002; Randy Woods, “Students Design Small, Fast Carrier At
Projected Cost Of $1.5 Billion,” Inside the Navy, Jan. 7, 2002. The latter article quoted the leader of the project as
saying that if the ship’s speed were reduced from 60 knots to 40 knots, the ship’s estimated procurement cost of $1.5
billion could be reduced substantially.
18
The U.S. design, which was called the Sea Control Ship, was never built for the U.S. Navy.
19
The nuclear propulsion plant planned for CVN-78, like those on almost all the Navy’s nuclear-powered aircraft
carriers, includes two nuclear reactors and two sets of associated propulsion equipment. (The sole Navy carrier with a
different propulsion plant arrangement is the Enterprise [CVN-65], the Navy’s first nuclear-powered carrier, whose
plant includes eight smaller nuclear reactors.) A half-sized version of the CVN-78 plant would use one reactor and one
set of associated equipment.
Congressional Research Service
8
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
•
A very small, high-speed VSTOL carrier. The Naval War College in 2000
developed a conceptual design for a very small, high-speed VSTOL carrier with a
displacement of about 4,000 tons, a maximum speed of 60 knots, and an
embarked air wing of about seven VSTOL JSFs and two helicopters.20
Matrix of Possible Designs
Table 1 below shows how ship size, propulsion type, and hull type create a matrix of notional
aircraft carrier options, including the large nuclear-powered carriers currently being procured and
the potential alternatives described above.
Medium-sized carriers of 40,000 to 70,000 tons might operate either VSTOL or CTOL aircraft,
though ships at the higher end of this size range might be able to operate CTOL aircraft more
easily or efficiently. Small carriers, because of their shorter length, would likely be limited to
VSTOL aircraft.
Although the table does not provide any examples of large or small conventionally powered
carriers using a commercial-like hulls, or any examples of a small nuclear-powered carrier, such
ships are possible. Regarding the possibility of a small nuclear-powered carrier, the Navy
between FY1957 and FY1975 procured a total of nine nuclear-powered cruisers with
displacements ranging from about 9,000 tons to about 17,500 tons.21
The table also does not provide examples of ships combining a nuclear propulsion plant with a
commercial-like hull. Although a small number of nuclear-powered commercial cargo ships were
built years ago, a combat ship such as an aircraft carrier that combined a relatively expensive
nuclear propulsion plant with a commercial-like hull having relatively limited survivability
features might be viewed as a contradictory design.
20
Christian Bohmfalk, “War College Explores Notion of Small, Fast Aircraft Carrier Fleets,” Inside the Navy,
October 9, 2000.
21
The nine cruisers—three one-of-a-kind ships, a class of two ships, and a class of four ships—entered service between
1961 and 1980 and were decommissioned between 1993 and 1999. Procurement of nuclear-powered cruisers was
halted after FY1975 due largely to a desire to constrain the procurement costs of future cruisers. In deciding in the late
1970s on the design for the new cruiser that would carry the Aegis defense system, two nuclear-powered design options
were rejected in favor of the option of placing the Aegis system onto the smaller, conventionally powered hull
developed for the Spruance (DD-963) class destroyer. The resulting design became the Ticonderoga (CG-47) class
Aegis cruiser. The first Aegis cruiser was procured in FY1978. Although nuclear power was abandoned for Navy
cruisers, it was retained for the Navy’s large aircraft carriers because adding nuclear power increases total ship
procurement cost in percentage terms less for a large carrier than for a cruiser, and because the mobility advantages of
nuclear power for a surface ship (see the discussion on mobility in the next section of the report) were viewed as
important for carriers in light of their combat capabilities and limited numbers. Some observers believe that if oil prices
are deemed likely to remain high, the option of nuclear-powered surface combatants might bear revisiting.
Congressional Research Service
9
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Table 1. Matrix of Notional Options For Aircraft Carriers
Military hull
Ship size (full load
displacement)
Nuclearpowered
Conventionally
powered
Large CTOL carrier
(~80,000 to
~100,000tons)
CVN-77 or
CVN-78
Ship broadly similar to
CV-63 and CV-67
Medium CTOL or
VSTOL carrier
(~40,000 to
~70,000 tons)
Carrier based on
LHA(R) design
(CSBA) or ship
similar to new
French carrier
Carrier based on
LHA(R) design (CSBA)
or ship similar to new
UK carrier design
Small VSTOL
carrier (~4,000 to
~30,000 tons)
Commercial-like hull
Nuclearpowered
Conventionally
powered
57,000-ton
carrier (OFT)
13,500-ton high-speed
carrier (OFT) or ship
similar to Spanish,
Thai, or existing UK
carriers
Source: Table prepared by CRS based on Navy data, OFT and CSBA reports, and Jane’s Fighting Ships
2004-2005.
Notes: CTOL = conventional takeoff land landing aircraft. VSTOL = vertical/short takeoff and landing aircraft.
Larger Surface Combatants
Current design:
•
14,500-ton DDG-1000 (formerly DD(X)) destroyer/CG(X) cruiser
Potential lower-cost options:
•
Roughly 11,000-ton cruiser-destroyer (SCD)
•
Roughly 6,000-ton frigate (FFG(X))
•
Low-cost gunfire support ship
14,500-Ton DDG-1000 Destroyer/CG(X) Cruiser22
The Navy currently plans to procure DDG-1000 destroyers and, starting in FY2011, CG(X)
cruisers. The CG(X) would be based on the DDG-1000 design and could be somewhat larger and
more expensive than the DDG-1000. The Navy’s FY2007 budget requests procurement funding
for the first two DDG-1000s, both of which are to be procured in FY2007 using split funding
(i.e., incremental funding) across FY2007 and FY2008.
22
For more on the DDG-1000 and CG(X) programs, see CRS Report RL32109, Navy DDG-1000 and DDG-51
Destroyer Programs: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. (Hereafter cited
as CRS Report RL32109.)
Congressional Research Service
10
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
The DDG-1000 would have a full-load displacement of about 14,500 tons, which would make it
roughly 50% larger than the Navy’s current 9,000-ton Aegis cruisers and destroyers, and larger
than any U.S. Navy destroyer or cruiser since the nuclear-powered cruiser Long Beach (CGN-9),
which was procured in FY1957.
The Navy estimates that the first two DDG-1000s would cost about $3.3 billion each, and that the
third, fourth, and fifth ships would cost an average of about $2.5 billion each.
The Congressional Budget Office believes and the Cost Analysis Improvement Group (CAIG)
within the Office of the Secretary of Defense (OSD) reportedly believes, that DDG-1000
procurement costs may be considerably higher than the Navy estimates. 23
The Navy originally envisaged procuring a total of 16 to 24 DDG-1000s, but now plans, as part
of its proposed 313-ship fleet, to procure a total of 7. The proposed 313-ship fleet also includes
19 CG(X)s. The FY2006-FY2011 FYDP submitted to Congress in February 2005 reduced
planned DDG-1000 procurement to one per year for FY2007-FY2011, for a total of five ships
through FY2009. The FY2007-FY2011 FYDP maintains an average procurement rate of one
DDG-1000 per year for the period FY2007-FY2011.
Options for a reduced-cost surface combatant include a roughly 11,000-ton cruiser-destroyer, a
roughly 6,000-ton frigate, and a lower-cost gunfire support ship based on the basic LPD-17
amphibious ship hull design.
Roughly 11,000-Ton Cruiser-Destroyer Combatant (SCD)
One option for a lower-cost surface combatant would be a new-design ship of about 11,000 tons.
Such a ship would be roughly 25% smaller than the current DDG-1000 design, roughly equal in
size to two classes of nuclear-powered cruisers that the Navy procured in the 1970s,24 and about
1,800 tons larger than today’s Arleigh Burke (DDG-51) class Aegis destroyers. Such a ship,
which might be called the smaller cruiser-destroyer (SCD) could:
23
24
•
be intended as a replacement for either the CG(X) program or both the DDG1000 and CG(X) programs;
•
incorporate many of the same technologies now being developed for the DDG1000 and CG(X);
•
cost substantially less to procure than a DDG-1000 or CG(X);
•
be similar to the DDG-1000 and CG(X) in terms of using a reduced-size crew to
achieve annual operation and support costs that are considerably less than those
of the current DDG-51 design;
•
carry a payload—a combination of sensors, weapon launchers, weapons, related
computers and displays, aircraft, and fuel—that is smaller than that of the DDG1000 or CG(X), but greater than of current Ticonderoga (CG-47) Aegis cruisers
or DDG-51 class Aegis destroyers..
See CRS Report RL32109.
These are the two California (CGN-36) and four Virginia (CGN-38) class cruisers.
Congressional Research Service
11
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
A land-attack oriented version of the SCD could carry two Advanced Gun Systems, or AGSs
(a new-design 155mm gun), like the DDG-1000, while reducing other payload elements. An airand missile-defense version of the SCD would preserve CG(X) radar capabilities while reducing
other payload elements.
Roughly 6,000-Ton Frigate (FFG(X))
A second option for a smaller, less expensive, new-design ship that has been suggested by CBO
would be a frigate intended as a replacement for both the DDG-1000/CG(X) effort and the
Littoral Combat Ship (LCS) program that is discussed later in this report. CBO estimated that
such a ship, which it calls the FFG(X), might displace about 6,000 tons. CBO estimates that a
6,000-ton FFG(X) might have a unit procurement cost of about $800 million.
A 6,000-ton FFG(X) might be too small to be equipped with the AGS, in which case it could not
provide the additional naval gunfire capability that would be provided by the DDG-1000. A
6,000-ton FFG(X) might, however, be capable of performing the non-gunfire missions that would
be performed by both the DDG-1000 and the LCS. A 6,000-ton FFG(X) would could be viewed
as a replacement in the surface combatant force structure for the Navy’s Oliver Hazard Perry
(FFG-7) class frigates and Spruance (DD-963) class destroyers. Since a 6,000-ton FFG(X) would
be roughly midway in size between the 4,000-ton FFG-7 design and the 9,000-ton DD-963
design, it might be suitable for carrying more modern versions of the mission equipment currently
carried by the FFG-7s and DD-963s.
Low-Cost Gunfire Support Ship
CBO and CSBA have suggested a third option for a smaller, less expensive, new-design ship—a
lower-cost gunfire support ship based on the San Antonio (LPD-17) amphibious ship. This option
would involve placing one or two AGSs on the basic LPD-17 hull design. LPD-17s currently
under construction for supporting Marine operations are to displace about 25,000 tons, but a basic
version of the LPD-17 hull equipped with one or two AGSs might have a different
displacement.25 CBO estimates that an initial AGS-armed LPD-17 might cost about $1.9 billion,
including detailed design and nonrecurring engineering costs, and that subsequent ships might
cost about $1.5 billion each. 26
Smaller Surface Combatants
Current design:
•
2,500- to 3,000-ton Littoral Combat Ship (LCS)
25
The Navy currently plans to procure a total of nine LPD-17 class ships, with the ninth ships to be procured in
FY2008. An additional surface combatant option recommended in the OFT report is a large missile-and-rocket ship
based on the same 57,000-ton commercial-like hull design that the report recommended using as the basis for a
medium-sized aircraft carrier. Although this ship would be based on a commercial-like hull, the unit procurement cost
of this ship would be higher than, not lower than, that of the DDG-1000.
26
Congressional Budget Office, Options for the Navy’s Future Fleet, op cit, p. 57 (Box 3-1).
Congressional Research Service
12
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Potential Lower-Cost Options:
•
Roughly 1,000-ton surface combatant
•
Roughly 100-ton surface combatant
2,500- to 3,000-Ton Littoral Combat Ship (LCS)27
In addition to DDG-1000 destroyers and CG(X) cruisers, the Navy currently plans to procure, as
part of its proposed 313-ship fleet, a total of 55 Littoral Combat Ships (LCSs), which would be
small (2,500- to 3,000-ton), fast surface combatants that would use modular “plug-and-fight”
weapon systems. One LCS was procured in FY2005 and another three were procured in FY2006.
The proposed FY2007 budget requests funding for another two. The Navy wants the procurement
cost of each LCS sea frame (i.e., the basic version of the ship, without any modular weapons
systems) to be no more than $220 million. Figures from the FY2006-FY2011 FYDP suggest that
when the cost of the mission modules is added in, the LCS program might have an average ship
procurement cost of about $387 million, and that a program of 55 might therefore have a total
acquisition (i.e., research and development plus procurement) cost of about $22.1 billion. 28
1,000-Ton Surface Combatant
Rather than procuring the LCS, the OFT report recommended procuring a 1,000-ton surface
combatant. Like the LCS, this ship would have a maximum speed of 40 to 50 knots and standard
interfaces for accepting various modular mission packages, and would self-deploy to the theater
of operations. The ship would be supported in theater by one or more larger types of ships that
were also recommended by OFT.
100-ton Surface Combatant
As an alternative to the 1,000-ton surface combatant, the OFT report recommended procuring a
100-ton surface combatant with a maximum speed of 60 knots and standard interfaces for
accepting various modular mission packages. These ships would be transported to the theater by a
“mother ship” based on the same 57,000-ton commercial-like hull used for OFT’s proposed
medium-sized aircraft carrier. The 100-ton surface combatants would be supported in theater by
the mother ship and possibly another larger ship that was recommended by OFT.
Issues For Congress
The potential lower-cost ship designs outlined above can be assessed in terms of cost,
capability, technical risk, homeporting arrangements, and potential impact on the shipbuilding
industrial base.
27
For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background,
Oversight Issues, and Options for Congress, by Ronald O’Rourke.
28
For a discussion, see CRS Report RL32109.
Congressional Research Service
13
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Cost
Although the potential ship designs outlined in the previous section would have lower unit
procurement costs than currently planned designs, a complete assessment of the cost implications
of these options would take into account development and design cost, procurement cost, lifecycle operation and support cost (O&S), and end-of-life disposal costs. Each of these are
discussed below.
Development And Design Cost
Developing and designing a large, complex Navy ship can cost billions of dollars. Consequently,
if a currently planned ship has already been developed and designed, stopping that program in
favor of a new, lower-cost design could incur substantial additional development and design
costs, and consequently might save money over the long run (i.e., reach the financial break-even
point compared to continuing with the current design) only if the lower-cost design is procured in
large enough total numbers so that the cumulative procurement savings were greater than the
additional up-front development and design costs. The earlier in the development and design
process that an existing ship acquisition program is stopped, the earlier in the future it might be
that a lower-cost alternative design might reach the break-even point. In addition, if a lower-cost
ship could use many of the same technologies intended for the more-expensive ship, or
technologies already developed for other ships, then the cost to develop the new design could be
reduced, perhaps substantially.
Procurement Cost
Through a process common to many manufacturing activities called moving down the learning
curve, the number of shipyard labor hours required to build a ship design decreases as a shipyard
builds more ships to that design and shipyard workers become increasingly familiar with the
design.29 Consequently, if some number of ships have already been built to a currently planned
design, the difference in cost between that design and the first units of a lower-cost alternative
design might be less than if the currently planned design had not yet entered production, and the
break-even point for the lower-cost design will be further into the production run than if the
currently planned design had not yet entered production. On the other hand, if the lower-cost
design can be procured at a greater annual rate than the currently planned design (e.g., two ships
per year for the lower-cost design vs. one ship per year for the currently planned design), then the
lower-cost design could benefit from greater spreading of the shipyard’s annual fixed overhead
costs and also move down the learning curve more quickly and achieve the cost-reducing benefits
of the learning curve more fully than the currently planned design.
29
For more on learning-curve effects in Navy shipbuilding, see CRS Report 96-785, Navy Major Shipbuilding
Programs and Shipbuilders: Issues and Options for Congress, by Ronald O’Rourke, pp. 59, 95-110. (Out of print;
available from the author.)
Congressional Research Service
14
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Life-Cycle Operation and Support (O&S) Cost
Navy ships are expensive to operate and support, and can remain in service for many years—
20 or more years for a small combatant, 30 or more years for an attack submarine or larger
surface combatant, and up to 50 years for an aircraft carrier. Consequently, although ship
procurement costs are often more visible in the budget than ship O&S costs, a ship’s life-cycle
O&S cost can contribute as much as, or even more than, its procurement cost to total long-term
Navy expenditures.
Personnel and Maintenance Costs
Reducing a ship’s life-cycle O&S cost can sometimes involve including design features that
increase its procurement cost. Personnel costs are a major component of ship O&S costs, and
reducing crew size can involve fitting the ship with technology for automating functions that were
previously performed by people, including damage control, which is a function that traditionally
has contributed to a need for larger crews. If the cost of added technology is greater than the
avoided expense of building extra crew-related spaces into the ship, then adding the technology
will increase the ship’s procurement cost. Maintenance costs are another major component of ship
O&S costs, and reducing maintenance costs might require building certain parts of the ship with
more-durable but more-expensive materials, or increasing the size (and thus construction cost) of
certain spaces on the ship, so as to provide room for easier access during maintenance.
In light of these considerations, it is possible for an alternative ship design to have a lower
procurement cost in part because it incorporates features that give it a higher life-cycle O&S cost.
If so, then procuring this ship rather than the currently planned design might not reduce total
Navy expenditures over the long run as much as might be expected by looking only at ship
procurement costs.
Fuel Costs
The life-cycle O&S cost of a conventionally powered ship includes the cost of all the fuel the ship
uses over its life. That is not the case for nuclear-powered ships, because the procurement cost of
a nuclear-powered ship includes the cost of the nuclear fuel core that is loaded into the ship’s
reactor at the time the ship is built. In the case of a nuclear-powered attack submarine, that fuel
core in 2004 cost about $158 million and is designed to power the ship for its entire 33-year
expected life, while in the case of a nuclear-powered carrier, the core in 2004 cost about $300
million and is designed to power the ship for one-half of its 50-year expected life. 30
Consequently, although a nuclear-powered submarine or carrier is more expensive to procure than
an otherwise-equal conventionally powered submarine or carrier, the nuclear-powered submarine
will incur no fuel-related O&S costs over its lifetime, while the conventionally powered carrier
will incur no fuel-related O&S costs during the first half of its lifetime.
30
Source for cost figures: Telephone discussion with Naval Nuclear Propulsion Office, May 21, 2004. The $158million figure is for a 33-year core for a Virginia-class submarine, while the $300 million figure is for a 25-year core
for the aircraft carrier CVN-78. Both figures are in constant FY2005 dollars.
Congressional Research Service
15
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
This difference in accounting for fuel costs means that when procurement and life-cycle O&S
costs are added together, the difference in cost between a nuclear-powered submarine and a
conventionally submarine will be smaller than the difference in procurement cost alone. The same
can true in comparing a nuclear-powered carrier to a conventionally-powered carrier, if the cost
of the nuclear-powered carrier’s second core is less than the cost of the conventionally powered
carrier’s fuel over its entire life. The higher the price of oil during conventionally powered
carrier’s life, the more likely this is to be the case.
A more general consideration arising out of this discussion is that other things held equal, the
higher that oil costs are expected to be in coming decades, the more cost-effective nuclear power
might be compared to conventional power for powering a given type of ship. In theory, if the cost
of oil is high enough, the total ownership cost (i.e., the sum of procurement cost, life-cycle O&S
cost, and end-of-life disposal cost discussed below) of a nuclear powered ship could be less than
that of an otherwise-equal conventionally powered ship.
End-Of-Life Disposal Cost
Other things held equal, nuclear-powered ships have higher end-of-life disposal costs than
conventionally powered ships because of the need to defuel, cut out, and seal up the reactor
compartment and transport it to the permanent Navy reactor-plant storage area at the Hanford
nuclear reservation in Washington state. For a nuclear-powered submarine, this work might cost
about $30 million to $35 million, while for a nuclear-powered carrier, which has a much larger
nuclear propulsion plant, it might cost roughly $570 million.31
Capability
As mentioned earlier, lower-cost ship designs in most cases will be individually less capable than
their higher-cost counterparts. One exception to this might be the reduced-cost Tango Bravo SSN,
which might be equal in capability to the Virginia-class design due to its use of the more
advanced technologies being pursued under the Navy-DARPA Tango Bravo program.
Aspects of capability that may be considered include ship payload, ship detectability and
survivability, ship mobility, and the value of ship numbers in naval operations.
Payload
As the size of a Navy combat ship decreases, its total payload—the weight and volume of the
ship’s sensors, weapon launchers, weapons, related computers and displays, aircraft, and fuel—
tends to decrease. Indeed, due to certain factors relating to ship design, as ship size decreases,
payload can often decrease more quickly, making the smaller ship not just less capable than the
larger ship, but proportionately less capable. One factor contributing to this effect relates to
31
Telephone consultation with the office of the Navy Nuclear Propulsion Program, Apr. 28, 2005. The office stated
that the total cost to inactivate, dismantle, and dispose of a retired nuclear-powered submarine is currently about $64
million, and that work related to the reactor compartment accounts for roughly half of this total. The office stated that
the currently estimated cost to inactivate the nuclear-powered carrier Enterprise (CVN-65) in 2013 is about $1.1 billion
in then-year dollars, which equates to about $830 million in FY2005 dollars, and that work related to the reactor
compartment accounts for about $570 million of this $830-million figure.
Congressional Research Service
16
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
propulsion: As ship size increases, the amount of horsepower needed to move a ton of the ship’s
weight through the water at a certain speed tends to decrease. As a result, as ship size increases,
the size of the propulsion plant increases less than proportionately, leaving proportionately more
room for payload. 32
Consequently, for example, as the size of an aircraft carrier is reduced, the total weight of the
aircraft that can be embarked on the carrier can decline even more quickly. A 40,000-ton
LHA(R)-based medium-sized carrier, for example, is about 40% as large as a 100,000 ton carrier,
but its potential air wing of about two dozen aircraft might have a total weight equivalent to less
than 40% of the 75 aircraft on the 100,000-ton carrier.
Moreover, if a medium-sized carrier’s air wing is transferred to a larger carrier, the larger carrier
may be able to use that air wing to generate more sorties (i.e., flights) per day because of its larger
flight deck and greater fuel and ordnance capacities. According to one study, for example, a
carrier capable of embarking 75 aircraft, can, with a 55-aircraft air wing, generate 40% more
strike sorties per day than a medium-sized carrier that is sized for that same 55-aircraft air wing.33
Reducing ship size can, in addition to reducing total payload, make it difficult or impossible for
a ship to be equipped with certain desired systems. A carrier smaller than a certain size, for
example, would not be able to operate CTOL aircraft, while a surface combatant smaller than
a certain size could not be equipped with certain large radars, sonars, missile-launching tubes,
or guns.
A principal implication of payload decreasing more rapidly than ship size is that the total cost to
put a certain collection of combat-related equipment to sea can go up as the size of the ships used
to put the equipment to sea goes down. If total fleet payload is held constant, in other words, then
reducing unit procurement costs by shifting to smaller ships can lead to a fleet design with a
higher total procurement cost. In addition, if crew size and fuel consumption does not go down
proportionately with ship size, then a similar effect could occur with regard to total fleet operation
and support (O&S) costs.
The OFT report counters some of these points by arguing that using new technologies would
permit the payload fraction of its recommended 1,000- and 100-ton surface combatants to be
greater than what would have been possible in the past. Another counter-argument is that
improvements in precision-guidance technology for weapons is permitting weapon size to be
reduced because a smaller warhead that lands precisely on a target can do the same amount of
damage to the target as a larger warhead that lands less precisely. As a result, it could be argued,
payload related to weapons and weapon launchers can be reduced without reducing the ship’s
capability. Any improvements in technology that would permit a reduction in the weight and
volume of sensors (e.g., radars or sonars) could lead to a similar argument relating to the sensor
portion of a ship’s payload.
32
The Navy’s 100,000-ton carriers, for example, are about 11 times as large as the Navy’s 9,000-ton DDG-51 class
destroyers, and both types of ships have a maximum sustained speed of more than 30 knots. In terms of shaft
horsepower, however, the carriers’ propulsion plant is less than three times as powerful as the DDG-51-class
propulsion plant (about 280,000 shaft horsepower vs. about 100,000 shaft horsepower, respectively).
33
David A. Perin, “Are Big Decks Still the Answer?,” U.S. Naval Institute Proceedings, June 2001, pp. 30-33.
Congressional Research Service
17
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Detectability and Survivability
Supporters of larger ships could argue that with careful design and construction, a large ship can
be made no more susceptible to detection by enemy sensors (e.g., radars, sonars, or infrared
sensors) than a much smaller ship. They could also argue that other things held equal, larger ships
and ships built to military survivability standards are better able to withstand a hit from a weapon
of a given size than a smaller ship or a ship built with an equal-sized commercial-like hull. A
larger ship or a ship built to military survivability standards, they could argue, might be able to
continue operations to some degree after being hit, or would at least would not be sunk, whereas a
smaller ship or a ship built with a commercial-like hull is more likely to be sunk or rendered
completely operable.
Supporters of smaller ships or ships built with commercial-like hulls could argue that making
larger ships less detectable adds to their cost, and that a fleet composed of a large number of small
ships could, by presenting the enemy with a large number of targets, overwhelm the enemy’s
target-tracking capabilities.34 They could also argue that even large ships built to military
survivability standards can be sunk or put out of operation, and that a fleet consisting of a
relatively small number of such ships concentrates too large a fraction of the fleet’s total
capability and replacement value in each individual platform. They could argue that the most
important measure of survivability is not individual-ship survivability but overall fleet
survivability, and that a fleet consisting of a larger number of smaller ships can have superior
overall fleet survivability. They could also argue that U.S. leaders might be averse to using
expensive, highly capable Navy ships in certain high-threat situations because they would not
want to risk one or more of them being heavily damaged or sunk, in which case the effective
utility of these ships would be reduced.
Mobility
Nuclear Power
Since nuclear propulsion plants do not require access to the atmosphere to generate power,
equipping a submarine with a nuclear propulsion plant produces a fundamental change in
ship mobility and consequently in the kinds of operations for which the submarine may be
suitable. Some observers, particularly supporters of nuclear-powered submarines, have stated that
without nuclear power, ships referred to as submarines are simply submersibles—ships that
occasionally and for limited periods of time operate below the surface—and that it is the addition
of nuclear power that creates a true submarine—a ship whose primary operating environment is
below the surface.
As mentioned earlier, an AIP system such as a fuel-cell or closed-cycle diesel engine extends the
stationary or low-speed submerged endurance of a non-nuclear-powered submarine. A
conventional diesel-electric submarine has a stationary or low-speed submerged endurance of a
few days, while an AIP-equipped submarine may have a stationary or low-speed submerged
endurance of up to two or three weeks.
34
The OFT report makes the second argument.
Congressional Research Service
18
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
An AIP system does not, however, significantly increase the high-speed submerged endurance of
a non-nuclear-powered submarine. A non-nuclear-powered submarine, whether equipped with a
conventional diesel-electric propulsion system or an AIP system, has a high-speed submerged
endurance of perhaps 1 to 3 hours, a performance limited by the electrical storage capacity of the
submarine’s batteries, which are exhausted quickly at high speed.
In contrast, a nuclear-powered submarine’s submerged endurance, at any speed, tends to be
limited by the amount of food that it can carry. In practice, this means that a nuclear-powered
submarine can remain submerged for weeks or months at a time, operating at high speeds
whenever needed.
As a consequence of their very limited high-speed submerged endurance, non-nuclear-powered
submarines, even those equipped with AIP systems, are not well suited for submarine missions
that require:
•
long, completely stealthy transits from home port to the theater of operation,
•
submerged periods in the theater of operation lasting more than two or three
weeks, or
•
submerged periods in the theater of operation lasting more than a few hours or
days that involve moving the submarine at something more than low speed.
With regard to the first of the three points above, the OFT report proposes transporting the AIP
submarines into the overseas theater of operations aboard a transport ship.35 In doing so, the OFT
report accepts that the presence of a certain number of U.S. AIP submarines in the theater of
operations will become known to others. A potential force-multiplying attribute of having an SSN
in a carrier strike group, in contrast, is that the SSN can be detached from the strike group, and
redirected to a different theater to perform some other mission, without alerting others to this fact.
Opposing forces in the strike group’s theater of operations could not be sure that the SSN was not
in their own area, and could therefore continue to devote resources to detecting and countering it.
This would permit the SSN to achieve military effects in two theaters of operation at the same
time—the strike group’s theater of operations, and the other theater to which it is sent.
With regard to the second and third points above, the effectiveness of an AIP submarine would
depend on what kinds of operations the submarine might need to perform on a day-to-day basis or
in conflict situations while operating as part of a forward-deployed carrier strike group.
For aircraft carriers, the effects of adding nuclear power are less dramatic than they are for
submarines, but still significant. Nuclear-powered carriers can make high-speed transits over long
distances to respond to urgent crises without need for stopping or slowing down to refuel along
the way. They do not need to be refueled upon arriving at the area of operations, permitting them
to commence combat operations immediately upon arrival. And since they do not need large fuel
tanks to store fossil fuel for their own propulsion plant, they can devote more of their internal
volume to the storage of aircraft fuel and ammunition, which permits them to sustain combat
operations for longer periods of time before they need to be resupplied.
35
The strategy of transporting the AIP submarines to the theater using transport ships is not mentioned in the report but
was explained at a Feb. 18, 2005 meeting between CRS and analysts who contributed to the OFT report.
Congressional Research Service
19
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Maximum Speed
Proponents of higher-speed ships like the LCS, the 13,500-ton carrier recommended in the OFT
report, or the 1,000- or 100-ton surface combatants recommended in the OFT report, argue that
the higher maximum speeds of these ships increases their capability by enabling them to shift
locations more rapidly and making them more difficult for the enemy to track and target.
Skeptics could argue that the advantages of ship speeds much higher than about 30 knots are
unproven or overrated.
Ship Numbers In Naval Operations
Advocates of a fleet with a larger number of ships, which is something that might be facilitated
by shifting to lower-cost ship designs, argue that a ship cannot be in two places at the same time,
and consequently that a fleet with a larger number of ships would be better able to maintain a
day-to-day presence in multiple locations around the world or be better able to respond to
simultaneous crises or conflicts in multiple locations. A fleet consisting of a larger number of
less-capable ships, they could argue, might offer more flexibility for responding to situations with
an appropriate amount of naval capability, as opposed to being forced to deploy a naval force
with more capability than needed at a high daily O&S cost.36 Advocates of a fleet with a larger
number of ships could also argue that under the theory of network-centric warfare, the capability
of the force grows as a function of the number of nodes (e.g., ships, aircraft, unmanned vehicles,
and distributed sensors) that make up the network, and that increasing the number of ship
nodes will consequently increase the total capability of the force.37 Advocates who make this
last argument in some cases might argue that in light of networking and other advanced
technologies, U.S. military forces in general should shift to less concentrated and more highly
distributed force designs.
Defenders of a fleet consisting of a smaller number of more-expensive ships could argue that
being able to deploy ships to a greater number of locations around the world might be of limited
value if those ships are less-capable designs that are not capable of performing required missions.
They could also argue that the Navy has taken steps in recent years to increase the fraction of the
fleet that is deployed, or ready to be deployed, at any given time, mitigating the effects of having
a relatively limited total number of ships in the fleet.38 They could argue that current ship designs
already provide adequate flexibility for creating naval formations with appropriate amounts of
capability for responding to various situations. They could also argue that when numbers of
aircraft, unmanned vehicles, and distributed sensors are taken into account, a fleet consisting of a
smaller number of more-expensive ships would still have an adequate number of nodes for
engaging in network-centric warfare.
36
The OFT report makes this point from a budgetary perspective as well, arguing that a fleet consisting of lower-cost
ships can be adjusted in size more smoothly to adapt to changes in available funding levels.
37
For more on network-centric warfare, see CRS Report RL32411, Network Centric Operations: Background and
Oversight Issues for Congress, by (name redacted); and CRS Report RS20557,
Navy Network-Centric Warfare Concept:
Key Programs and Issues for Congress, by Ronald O’Rourke.
38
For additional discussion of this point, see CRS Report RS21338, Navy Ship Deployments: New Approaches—
Background and Issues for Congress, by Ronald O’Rourke.
Congressional Research Service
20
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Technical Risk
Of the lower-cost options outlined earlier, those that might pose some technical risk for the Navy
include the AIP-equipped non-nuclear-powered submarine (because a non-nuclear-powered
submarine has not been designed and built for the U.S. Navy since the 1950s), the Tango Bravo
nuclear-powered submarine (because of the need to mature the Tango Bravo technologies), the
13,500-ton high-speed carrier (because of its fairly large SES/catamaran hull design), and perhaps
the 1,000- and 100-ton surface combatants (because of the new technologies that are intended to
increase their payload fractions).
Homeporting Arrangements
Smaller ships might offer a wider range of homeporting possibilities because some ports might
not have large enough berthing spaces or deep enough waters to accommodate ships of more than
a certain size.
Homeporting a nuclear-powered carrier or submarine can be a more complex undertaking than
homeporting a conventionally powered ship due to requirements that are unique to nuclearpowered ships, such as having access in the home port to a nuclear-certified maintenance shop. In
addition, gaining permission to forward-homeport a Navy ship in a foreign country can be
politically more difficult if the ship in question is nuclear-powered and there are substantial antinuclear sentiments in the intended host country.
Impact On Shipbuilding Industrial Base
Lower-cost ship designs could affect the shipbuilding industrial base by changing the total
volume of Navy shipbuilding work or the distribution of that work among various shipyards.
Total Volume Of Work
The total volume of Navy shipbuilding work is to a large degree a function of the total amount of
funding available for Navy ship procurement. Consequently, the effect that shifting to lower-cost
designs might have on the total volume of shipbuilding work would depend to a large degree on
whether the shift somehow affects the total amount of funding available for Navy ship
procurement. At least three scenarios are possible:
•
One possibility is that shifting to lower-cost designs does not substantially affect
the total amount of funding available for Navy ship procurement, in which case
the total volume of Navy shipbuilding work might not change substantially.
•
A second possibility is that the shift to lower-cost designs is used to reduce the
total cost of building the same total number of ships as previously planned, in
which case the total volume of Navy shipbuilding work would be reduced.
•
A third possibility is that the shift to lower-cost designs makes Navy ships appear
more cost-effective compared to competing Navy or DOD programs, in which
case the total amount of funding available for Navy ship procurement might be
increased, enabling an increase in the total volume of Navy shipbuilding work.
Congressional Research Service
21
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Distribution Of Work Among Shipyards
The lower-cost ship designs in this report could affect the distribution of shipbuilding work
among various shipyards in one or more of the following ways:
•
Attack submarines. A Tango Bravo nuclear-powered submarine would be
designed and built by one or both of the country’s two current nuclear-submarine
construction shipyards—General Dynamics’ Electric Boat (GD/EB) of Groton,
CT, and Quonset Point, RI, and Northrop Grumman Newport News (NGNN) of
Newport News, VA. If both GD/EB and NGNN are involved in the program, the
division of work between the two yards could be different than the current,
roughly even, division of work the two yards have for building Virginia-class
submarines. An AIP-equipped non-nuclear powered submarine could be designed
and built by GD/EB or NGNN, or by a non-nuclear shipyard, such as the Ingalls
shipyard at Pascagoula, MS, that forms part of Northrop Grumman Ship Systems
(NGSS). Ingalls has been associated with past proposals for building nonnuclear-powered submarines for export to foreign countries. If AIP submarines
were procured in lieu of nuclear-powered submarines, that could reduce the total
amount of work available to U.S. naval nuclear propulsion component
manufacturers, many of whom are sustained by the work provided by the Navy’s
nuclear submarine and aircraft carrier programs.
•
Aircraft carriers. NGNN is the only U.S. yard that can build large nuclearpowered carriers (and the only yard that could readily build large conventionally
powered carriers). A medium-sized, conventionally powered carrier based on the
LHA(R) design could be built by NGNN or by another yard, such as Ingalls, the
builder of previous ships similar to the LHA(R). A medium-sized, conventionally
powered carrier based on a merchant-like hull could be built by NGNN, Ingalls,
or other shipyards, particularly those with experience building merchant-like
hulls, such as the Avondale shipyard near New Orleans that also forms part of
NGSS or General Dynamics’ National Steel and Shipbuilding Company
(GD/NASSCO) of San Diego, CA. A small, high-speed carrier using an
SES/catamaran hull design might be built at a number of yards, particularly any
that might have experience building SES/catamaran hulls. If conventionally
powered carriers were procured in lieu of nuclear-powered carriers, that could
reduce the total amount of work available to U.S. naval nuclear propulsion
component manufacturers, many of whom are sustained by the work provided by
the Navy’s nuclear submarine and aircraft carrier programs. In terms of the
amount of work provided to these manufacturers, a carrier nuclear propulsion
plant is considered roughly equivalent to five submarine nuclear propulsion
plants.
•
Larger surface combatants. DDG-1000 destroyers are to be built at NGSS
(particularly Ingalls) and General Dynamics’ Bath Iron Works (GD/BIW) of
Bath, ME. A 11,000-ton SCD, a 6,000-ton FFG(X), or a low-cost gunfire support
ship would likely be built at one or both of the same yards, but could also be built
at other yards, such as Avondale or NGNN. If built at both NGSS and GD/BIW,
the division of work between the two yards might not be the same as would occur
under the DDG-1000 program.
Congressional Research Service
22
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
•
Smaller surface combatants. One version of the LCS is to be built at Marinette
Marine of Marinette, WI, and Bollinger Shipyards of Louisiana and Texas. The
other version is to be built at the Austal USA shipyard at Mobile, AL. A 1,000- or
100-ton surface combatant could be built at either of these yards or at other
yards, particularly yards that focus on building smaller ships.
Legislative Activity For FY2007
FY2007 Defense Authorization Act (H.R. 5122/P.L. 109-364)
House
Sections 122, 123, and 124 of H.R. 5122 would limit the procurement costs of CVN-21 class
aircraft carriers, LHA(R) class ships, and LPD-17 class ships, respectively, to current Navy cost
estimates, with adjustments permitted for inflation and other factors. Section 1014 would
establish a shipbuilding industrial base improvement program.
The House Armed Services Committee, in its report (H.Rept. 109-452 of May 5, 2006) on H.R.
5122, stated:
The rising cost and lengthening production schedules of major defense acquisition
programs has led to more expensive platforms fielded in fewer numbers. The committee
believes that internal DOD pressure to develop follow-on weapons systems that include all
necessary and anticipated military capabilities may create an over-reliance on individual
‘‘mega’’ systems that are potentially more expensive and time-consuming to develop than
less sophisticated but capable systems. These increases in cost and development time
generally result in smaller numbers of platforms purchased, creating a ‘‘high demand, low
density’’ situation in which the needed platforms have higher operational tempos, wear out
faster, increase stress on military personnel, undermine the ability to conduct traditional
presence missions intended to shape the strategic choices of potential adversaries and limit
the strategic depth of United States forces responding to multiple contingencies. (Pages
14-15; see also pages 350-351)
Regarding the affordability of the Navy’s shipbuilding plan, the report stated:
The committee applauds the Chief of Naval Operations for developing the Navy’s future
force structure and the accompanying long-term shipbuilding plan to build it. This long-term
plan provides the shipbuilding industry a view into the future that has been lacking.
However, the committee is concerned that the plan was developed using unrealistic
assumptions that will not make the plan executable. Of greatest concern to the committee is
the affordability of the ship construction plan. According to the Navy’s estimates, execution
of this plan requires a significant increase in shipbuilding funds from $8.7 billion in fiscal
year 2006 to $17.2 billion in fiscal year 2011. Obtaining these additional funds in a period of
anticipated federal spending reductions will be difficult. The plan also assumes that
individual ship acquisition programs can avoid the cost growth that has plagued most Navy
ship acquisition programs.
Congressional Research Service
23
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
The committee is concerned about the affordability of the Navy’s long-term shipbuilding
plan, recreating much of the uncertainty about the future of naval shipbuilding that the plan
was designed to eliminate. (Page 67)
The report also stated:
The committee is concerned that the U.S. shipbuilding/ship repair industrial base has
significant capacity beyond what is necessary for all anticipated DOD new construction and
maintenance work, and believes that Navy ship acquisition programs are paying the price....
The committee directs the Secretary of the Navy to report to the congressional defense
committees on measures that can be taken to manage the capacity of the shipbuilding/ship
repair industrial base in a manner that would make Navy shipbuilding more affordable. Such
report shall be submitted by the submission of the President’s request for fiscal year 2008, as
required by section 1105 of title 31, United States Code. (Pages 70-71)
Regarding the Navy’s cost estimates for ships, the report stated:
The committee is deeply concerned about the process used for establishing the Navy’s ship
cost estimates. The committee notes that the original cost estimates on numerous existing
ship classes have regularly been described by the Navy as inaccurate and unrealistic when
those ships near completion of construction. The committee notes that in several cases it has
been informed that ship cost estimates delivered to the committee in prior years either
intentionally or unintentionally excluded certain known shipbuilding costs such as
escalation, and that these cost estimates were known to be inaccurate on the day they were
first delivered to the committee. The committee recommends that the process for deriving
ship cost estimates be revised to ensure that all major known elements of ship cost are
routinely included in all ship cost estimates.
The committee notes that Sections 122, 123, and 124 of the bill would impose cost
limitations on three current ship classes based on the Navy’s latest costs estimates. The
committee further notes that the imposition of these statutory cost limitations makes the need
for a high level of confidence in the cost estimates for these ship classes unusually important.
Accordingly, the committee directs that the Secretary of the Navy revalidate the cost
estimates for CVN-21, for the ships currently programmed in the LHA Replacement
program, and for the eight ships of the San Antonio class amphibious ship that follow the
lead ship. The committee further directs that the revalidated costs estimates be submitted for
review and approval by the Under Secretary of Defense for Acquisition, Technology, and
Logistics. Finally, the committee directs that no later than July 1, 2006, the Secretary of the
Navy submit a report in writing to the congressional defense committees containing the
revalidated cost estimates for these ship classes including a certification by the Secretary
that all known and anticipated major elements of cost have been included in the estimate.
(Page 71)
Regarding the DDG-1000 program, the report also stated:
The committee does not believe the DD(X) is affordable.... the committee understands
there is no prospect of being able to design and build the two lead ships for the $6.6
billion budgeted....
Originally, the Navy proposed building 32 next generation destroyers, reduced that to 24,
then finally to 7 in order to make the program affordable. In such small numbers, the
committee struggles to see how the original requirements for the next generation destroyer,
for example providing naval surface fire support, can be met.... By reducing the requirements
Congressional Research Service
24
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
for the DD(X), a smaller, less expensive destroyer could be procured in greater numbers.
Because of its expense, the committee does not believe that DD(X) will be procured in
sufficient numbers to meet the operational need.... The committee supports the construction
of up to two DD(X)s to demonstrate technologies that could be incorporated into future,
more affordable, major surface combatants. (Pages 69-70)
Regarding Section 1014 and other measures intended to improve the efficiency of Navy
shipbuilding, the report states:
Maritime technology
The budget request contained no funds in PE 78730N for the maritime technology program.
The committee understands that the purpose of the maritime technology (MARITECH)
program is to reduce the cost of naval ship construction, modification, and repair by
enhancing the efficiency and competitiveness of the U.S. shipbuilding and ship repair
industries. The committee understands that since the late 1970s the Navy has considered
capital for facility investments to be an allowable cost on contracts that are not firm fixed
price. The committee is also aware that in the past three years, the Navy and industry have
agreed to specific recapitalization contract incentives in the Virginia class submarine and the
CVN-21 programs. These incentive clauses have allowed the Navy and the contractors to
identify improvements in sequencing and build processes to lower construction costs. The
committee encourages the expansion of these efforts to all ship procurements, including the
Lewis and Clark (T-AKE) class program.
The committee includes a provision (section 1014) that creates a shipbuilding industrial base
improvement program through which the Secretary of the Navy shall award grants and loan
guarantees to qualified shipyards to improve their productivity and cost effectiveness. These
authorities will allow the Navy to work to an even greater extent with shipbuilders to identify
and finance process changes, equipment investments, and facilities improvements to lower
the cost of Navy ship procurement. The committee expects that these authorities will allow
the Navy to achieve savings in the construction of the T-AKE class ships, in addition to other
ship classes, and improve the competitiveness of U.S. shipyards. Consequently, the
committee recommends providing funds for the shipbuilding industrial base improvement
program and for the enhancement of the U.S. shipbuilding and ship repair industrial base.
The committee recommends $120.0 million in PE 78730N for the maritime technology
program.
National shipbuilding research program
The budget request contained no funds in PE 78730N for the national shipbuilding
research program.
The committee understands that the national shipbuilding research program (NSRP) provides
a unique collaborative environment where shipbuilders and government agencies examine
processes, tooling and management techniques to improve the efficiency of the United States
shipbuilding industry. The committee understands that NSRP operates on a 50-50 cost share
between government and industry, all results are shared with all members, and a conservative
estimate for NSRP’s return on investment is five to one.
The committee recommends $20.0 million in PE 78730N for the national shipbuilding
research program.
Congressional Research Service
25
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Shipbuilding industrial base improvement grants
The budget request contained no funds in PE 78730N for shipbuilding industrial base
improvement grants.
The committee understands the national security importance of sustaining viable and
efficient shipbuilding and ship repair industries in the United States. Accordingly, the
committee recommends providing grants to U.S. shipyards to facilitate the development of
innovative design and production technologies and processes for naval vessel construction,
and the development of modernized shipbuilding infrastructure.
The committee recommends $50.0 million in PE 78730N for shipbuilding industrial base
improvement grants.
Shipbuilding industrial base improvement loan guarantees
The budget request contained no funds in PE 78730N for shipbuilding industrial base
improvement loan guarantees.
The committee understands the national security importance of sustaining viable and
efficient shipbuilding and ship repair industries in the United States. Accordingly, the
committee recommends providing loan guarantees to U.S. shipyards to facilitate the
acquisition of technologies, processes and infrastructure to enhance the efficiency and
competitiveness of the U.S. shipbuilding and ship repair industries.
The committee recommends $50.0 million in PE 78730N for shipbuilding industrial base
improvement loan guarantees. (Pages 192-193)
Senate
Section 121 of S. 2766 would authorize 4-year incremental funding and economic order quantity
(EOQ) purchases of long-lead components for CVN-21 class aircraft carriers. Section 123 would
increase a previously legislated cost limit on CVN-77 to $6,057 million.
Regarding Section 121 on procurement of aircraft carriers, the Senate Armed Services
Committee, in its report (S.Rept. 109-254 of May 9, 2006) on S. 2766, stated:
In reviewing the budget request for fiscal year 2006, the committee received testimony
from the Navy and industry that the low rate of shipbuilding was driving higher costs, which
in turn further reduced shipbuilding rates, creating a downward spiral. The committee
believes that stable ship requirements, increased funding in the shipbuilding budget, and
increased flexibility for funding large capital ships are critical elements of any strategy to
reverse this trend....
Elsewhere in this report, the committee has expressed concern with cost growth on the
CVN-77 program, and has urged the Navy and the shipbuilder to identify opportunities to
improve affordability of future aircraft carriers. Procurement delays, excess inflation, and
material escalation have been reported as significant contributors to CVN-77 cost growth.
The shipbuilder has proposed to achieve significant CVN-21 class program savings through
a stable procurement plan, and through procurement of economic order quantity material for
CVN-79 and CVN-80 in conjunction with CVN-78 procurement.
Congressional Research Service
26
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
In view of the potential for significant program savings, the committee recommends an
increase of $50.0 million in SCN for CVN-21 class advance procurement, and directs the
Secretary of the Navy to review economic order quantity and long lead time material
procurement for the CVN-21 class. The Secretary is to submit a report to the congressional
defense committees with the fiscal year 2008 budget request, outlining the advance
procurement requirements to potentially optimize economic order quantity savings and
escalation avoidance (to include offsetting factors) for the first three vessels of the CVN-21
class. Of the amount authorized to be appropriated for advance procurement for CVN-79 and
CVN-80, none of the funds are available for obligation prior to 30 days following receipt of
the Secretary’s report. (Page 67)
Regarding Section 123 on the cost limit for CVN-77, the report states:
The procurement cost increase to $6.057 billion, which equals the government’s maximum
contractual liability, is attributed to extraordinary escalation impacts, increased labor hours
and overhead rates, and costs related to schedule delays. The fiscal year 2007 budget request
included $348.4 million for CVN-77 cost growth, with the balance of additional funding to
be included in future budget requests. The committee is aware that the Navy has taken a
series of management actions to contain cost on CVN-77, including deferral of upgrades that
are not required for safe system operation or certification; minimization of contract change
orders; implementation of a joint Navy-shipbuilder Lean Six-Sigma program; and a schedule
revision to enable a more efficient completion of CVN-77. The committee is concerned,
however, that despite these management actions, the Navy is projecting CVN-77 cost to
grow to the contract ceiling, in excess of 30 percent above the baseline cost cap.
The committee notes that the Secretary’s report to Congress on the long-range plan for
construction of naval vessels establishes cost estimates for future ship construction, which
target improved performance based on a series of management actions similar to ongoing
efforts to control CVN-77 cost. Visibility into cost performance while completing CVN-77 is
necessary in order to assess the effectiveness of these management actions, and will assist in
determining further actions necessary to improve affordability of the future force. Improved
visibility into completion cost performance will also afford greater opportunity to deliver
CVN-77 below the contract ceiling. Accordingly, the Secretary of the Navy is directed to
submit a quarterly report to the congressional defense committees, beginning December 1,
2006, providing the following information regarding the CVN-77 ship construction contract:
(1) contract target cost;
(2) Program Manager’s Estimate at Completion;
(3) contractor’s Estimate at Completion;
(4) contract ceiling price;
(5) end of period actual costs; and
(6) percent progress. (Page 69)
Regarding the Littoral Combat Ship (LCS) program, the report states:
The construction of lead LCS vessels at two shipyards inherently adds cost risk, which will
persist until these ships near completion in 2007 and 2008. The emphasis on cost control
would dictate that the Navy pursue competition, commonality, and the results of learning
curves to the extent practical in the procurement of this 55 ship class.
Congressional Research Service
27
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
The committee views LCS as an important component of the Navy’s strategy for conducting
the global war on terror, and has supported the Navy’s approach to rapidly field this
capability. The design and construction of LCS in parallel with development of the mission
modules requires heightened management of program risk to ensure affordable, full mission
capability of the LCS program. However, the committee is concerned that the affordability
appeal of the LCS program is being overtaken by apparent cost growth, and that the
rapid ramp up in LCS procurement will compound the issue. The stated emphasis on
affordability is obscured by the absence of a clear acquisition strategy to guide strategic
program decisions.
Additionally, it is unclear that the Navy has assessed the added cost for training,
maintenance, configuration management, planning and engineering, and supply support for
the two flight 0 ship classes. Further, by virtue of budgeting the costs for procuring the flight
0 LCS vessels in three different appropriations, total costs for the program’s start are difficult
to discern. In view of these concerns, the committee directs the Secretary of the Navy to
submit a report on the LCS program, no later than December 1, 2006 to the congressional
defense committees. The report shall outline the Navy’s acquisition strategy for the program,
including the competition plan, the flight strategy, and the cost containment strategy for the
program; contain a clear representation of all R&D and procurement costs for the total
program; and assess the added life cycle costs associated with operation and support for two
dissimilar flight 0 LCS designs. (Page 113)
Regarding shipyard costs and efficiency, the report states:
The budget request included no funding in PE 78730N for maritime technology. The
National Shipbuilding Research Program-Advanced Shipbuilding Enterprise (NSRP-ASE) is
a collaborative effort between the Navy and industry, which has yielded new processes and
techniques that reduce the cost of building and repairing ships. Annual Navy funding, which
is matched and exceeded by industry investment, has achieved savings and cost avoidance
for the Navy, a positive return on investment, and a high research-to-implementation
transition rate. The committee believes that continuation of the NSRP-ASE provides a vital
contribution towards achieving the overarching objective of improving the affordability of
naval warship construction and maintaining a healthy, innovative shipbuilding industrial
base. The committee recommends an increase of $10.0 million in PE 78730N to support
NSRP-ASE efforts, including:
(1) establishing a comprehensive national program for development and training of a
skilled shipbuilding production and engineering workforce;
(2) establishing a concept for a national supply chain that will enable leveraging
buying power across product lines in an effort to reduce the high cost of material in
ship construction;
(3) exploring secondary and commercial markets for private shipbuilders to broaden the
business base and share the overhead applied to naval shipbuilding; and
(4) developing and deploying an industry-wide architecture for computer
interoperability. (Pages 181-182)
Conference Report
Section 121 of H.R. 5122 (conference report H.Rept. 109-702 of September 29, 2006) authorizes
4-year incremental funding for the CVN-21 class aircraft carriers CVN-78, CVN-79, and CVN80. Section 122 establishes unit procurement cost caps for CVN-21 class aircraft carriers. Section
Congressional Research Service
28
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
123 increases a previously legislated procurement cost cap for the CVN-77 aircraft carrier.
Section 125 establishes a unit procurement cost cap for LHA(R) amphibious assault ships.
Section 126 establishes unit procurement cost caps for four LPD-17 class amphibious ships.
Section 215 authorizes $4 million for implementing or evaluating Navy shipbuilding technology
proposals under the Defense Acquisition Challenge Program. Section 1016 directs the Navy to
conduct an assessment of naval vessel construction efficiencies and of the effectiveness of special
contractor incentives. The sections establishing new procurement cost caps allow the caps to be
adjusted upward for inflation and other factors.
Regarding Section 122, the report states:
The amendment would not provide the Secretary authority to adjust the limitation amounts
for cost increases attributable to congressional actions that impact on the shipbuilding
program of record. However, the conferees understand that such action could have
significant impact on program cost, and therefore direct that the Secretary include, within the
annual written notice to the congressional defense committees regarding changes to the cost
limitations, an assessment of any negative impact of congressional action on program costs.
The conferees understand that the CVN–21 class budget represents the Navy’s risk-balanced
assessment of the cost for completing design and construction of the future class of nuclear
powered aircraft carriers. The conferees recognize that many uncertainties remain with
regard to completion of CVN–21 design and construction, including innumerable,
inestimable events which will impact cost during the next 15 years of performance on the
program. Accordingly, the amendment would allow adjustment to the cost limitation for nonrecurring design and engineering in order to enable the Navy to reduce this risk in the
execution of the design effort.
The conferees expect that the Navy will ultimately manage program execution within the
bounds of the budget estimate. Accordingly, the conferees understand that compliance with
this provision will require procurement cost trade-offs to be accomplished, which could
reduce the capabilities, system performance, safety, crew quality of life, future growth
margin, or other important factors in the design and construction of the CVN–21 class. The
conferees believe that most of these trade-offs will be within the purview of the program
office and requirements office. However, the Secretary shall notify the Committees on
Armed Services of the Senate and the House of Representatives not less than 30 days prior to
implementing any cost-driven reduction which would unacceptably impact safety, crew
quality of life, or otherwise preclude the program from meeting the requirements of the
CVN–21 Operational Requirements Document. The Secretary’s notification shall identify
the specific characteristic proposed to be reduced and the cost avoidance provided by such
reduction. (Page 552)
Regarding Section 125, the report states:
The amendment would not provide the Secretary authority to adjust the limitation amounts
for cost increases attributable to congressional actions that impact on the shipbuilding
program of record. However, the conferees understand that such action could have
significant impact on program cost, and therefore direct that the Secretary include, within the
annual written notice to the congressional defense committees regarding changes to the cost
limitations, an assessment of any negative impact of congressional action on program costs.
The conferees understand that the LHA-6 budget represents the Navy’s risk-balanced
assessment of the cost for completing design and construction of the future LHA
Replacement ship. The conferees recognize that many uncertainties remain with regard to
completion of LHA-6 design and construction, including innumerable, inestimable events
Congressional Research Service
29
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
which will impact cost during the next 6 years of performance on the program. Accordingly,
the amendment would allow adjustment to the cost limitation for non-recurring design
and engineering in order to enable the Navy to reduce this risk in the execution of the
design effort.
The conferees expect that the Navy will ultimately manage program execution within the
bounds of the budget estimate. The conferees understand that compliance with this provision
will require procurement cost trade-offs to be accomplished, which could reduce the
capabilities, system performance, safety, crew quality of life, future growth margin, or other
important factors in the design and construction of the LHA Replacement ship. The
conferees believe that most of these trade-offs will be within the purview of the program
office and requirements office. However, the Secretary shall notify the Committees on
Armed Services of the Senate and the House of Representatives not less than 30 days prior to
implementing any cost-driven reduction which would unacceptably impact safety, crew
quality of life, or otherwise preclude the program from meeting the requirements of the LHA
Replacement program Capability Development Document. The Secretary’s notification shall
identify the specific characteristic proposed to be reduced and the cost avoidance provided
by such reduction. (Pages 553-554)
FY2007 Defense Appropriations Act (H.R. 5631/P.L. 109-289)
House
The House Appropriations Committee, in its report (H.Rept. 109-504 of June 16, 2006) on H.R.
5631, stated that
the Committee believes that the viability of the Navy’s long range [shipbuilding] plan will
remain tied to the service’s ability to control costs in ship design and construction. Navy
leadership agrees that cost control is essential, but the Navy has produced no plan or
initiatives to meet the cost targets assumed in the long range shipbuilding plan. Furthermore,
the recent history of ongoing shipbuilding programs indicates the trend in cost growth may
be getting worse, and not better. The Committee encourages the Navy to set firm cost targets
in its future shipbuilding programs, to develop specific initiatives addressing cost control,
and to sign contracts that reduce the likelihood of cost growth. (Page 139)
The report recommended reducing by $141.4 million the Navy’s request for FY2007 procurement
funding to cover cost growth on ships procured in prior years. The report stated:
The Committee remains concerned over the lack of cost control in Navy shipbuilding
programs. In last year’s report, the Committee noted the rising cost growth in ongoing ship
construction contracts, and required the Navy to submit a plan on resolving these issues. That
report was submitted two months late, and was little more than a summary of cost overruns
in shipbuilding over the past two decades. The Committee is concerned about the gap
between the Navy’s public statements about the need for firm cost controls, and the
programmatic and contractual actions needed to accomplish that objective. Navy briefings
this year document a litany of programs, including the CVN-77 aircraft carrier and certain
attack submarines of the Virginia class, that continue to defy attempts to control costs. The
Navy estimates an overrun of $867,900,000 over the next 3 years alone in the CVN-77
production effort. These funds cannot be obligated without Congressional legislation to raise
the current cost cap on the program—a cap that was put in place several years ago to control
costs. The fiscal year 2007 budget requests $136,000,000 for further cost growth in the
U.S.S. Texas (SSN-775), and cost performance on the U.S.S. North Carolina (SSN-777) is
seriously below Navy expectations. In fact, current cost performance on the Virginia class
Congressional Research Service
30
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
jeopardizes the ability of the Navy to meet the performance goals of the multiyear contract
signed in 2004 as well as cost targets needed to increase the submarine production rate in
future years. The Committee is unwilling to provide increased appropriations for cost
overruns in the absence of compelling justification or a realistic and detailed plan for cost
control. The Committee recommendation provides $436,449,000 for Completion of Prior
Year Shipbuilding Programs, a reduction of $141,400,000 from the request. The reduction
should be allocated against the following programs: CVN-77 (-$30,000,000); SSN-777
(-$48,000,000); SSN-776 (-$10,000,000); SSN-775 (-$10,000,000); and the LPD-17 class
(-$43,400,000). (Page 140)
Congressional Research Service
31
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Appendix. Other Options for Responding to Rising
Ship Costs
Aside from reducing planned ship procurement rates or shifting or shifting to lower-cost ship designs,
one option for responding to rising Navy ship procurement costs would be to increase annual shipprocurement funding. The Navy’s proposed FY2007 budget and the FY2007-FY2011 shipbuilding
plan propose increasing annual funding for ship construction to an average of roughly $14.4 billion
per year in constant FY2007 dollars. Increasing annual ship-procurement funding substantially from
current levels, however, may not be easy. In a situation of finite defense funding, increasing funding
for Navy ship procurement could require reducing funding for other Navy or DOD priorities. The
Navy has worked in recent years to operate more efficiently on a day-to-day basis so that the resulting
savings could be applied to Navy procurement programs. In practice, however, savings from these
efficiencies have been offset by rising Navy costs in other areas, such as personnel-related costs.
A second option would be to modify the way in which new Navy ships are funded in the budget.
Possible changes that have been suggested include making greater use of incremental funding or
starting to use advance appropriations. This option, which is examined in CRS Report
RL32776,39 might marginally increase the number of ships that could be procured for a given
total amount of money. As discussed in that report, however, it could also pose potentially
significant issues relating to Congress’s power of the purse and Congress’s responsibility for
conducting effective oversight of DOD activities.
A third option would be to make greater use in Navy ship-procurement programs of a contracting
method known as multiyear procurement (MYP). This option, like the previous one, might
marginally increase the number of ships that could be procured for a given total amount of money.
Not all Navy ship-procurement programs, however, would meet the legal requirements for MYP,40
and making greater use of MYP could reduce DOD’s and Congress’s flexibility to adjust shipprocurement plans in future years to respond to changing strategic and budgetary circumstances.41
A fourth option would be to change the acquisition strategy for building certain Navy ships. For
example, the Navy estimated in 2005 that changing from a strategy of dividing DDG-1000
destroyers evenly between two yards to a strategy of having all DDG-1000s built by a single yard
could reduce the cost for building 10 DDG-1000s by a total of $3 billion, or an average of $300
million per ship. 42 Shifting to a single-yard acquisition strategy, however, could cause the second
yard to permanently exit the business of building that kind of ship. That could leave the Navy
with a single source for building that kind of ship, which could prevent the Navy in the future
from using competition or benchmarking43 to spur design innovation, constrain costs, maintain
production quality, and ensure adherence to scheduled delivery dates.
39
CRS Report RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for
Congress, by Ronald O’Rourke. (Hereafter cited as CRS Report RL32776.)
40
These requirements are set forth in 10 U.S.C. § 2306b, the statute governing MYP arrangements.
41
For further discussion, see CRS Report RL32776.
42
See CRS Report RL32109.
43
Benchmarking, which can take place in the absence of active competition, is the process of using one yard’s
performance in building a certain kind of ship to help measure or judge the performance of another yard in building that
kind of ship.
Congressional Research Service
32
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
Another potential change in acquisition strategy would be to make greater use of competition in
Navy ship acquisition. Competition is used today in Navy ship acquisition primarily in the early
stages of ship-acquisition programs, to determine who will design and build the lead ship in each
new class. Making greater use of competition in Navy ship acquisition could involve using
competition between shipyards in awarding contracts for building follow-on ships in each class.
This step, if taken, would represent a return to Navy practices in the 1980s. Employing
competition in the awarding of contracts for building follow-on ships, however, requires either an
annual procurement rate for the class of ship in question that is high enough so that the
government can contemplate giving ships to one yard or another without endangering the
financial health of either yard, or a willingness on the part of the government to have contract
award lead to a decision by the losing yard to permanently withdraw from the business of
building that kind of ship, or Navy ships generally. In the latter case, the Navy’s contract-award
decision could leave the Navy with a single source for that kind of ship in the future.44
A fifth option would be to take steps to reduce the amount of shipyard fixed overhead costs that
are incorporated into the procurement costs of Navy ships. This could be accomplished by
eliminating any excess capacity among the yards building Navy ships, which would eliminate the
fixed overhead costs associated with maintaining that capacity, or by increasing other kinds of
work done by those yards, so that this other work could absorb a greater portion of the yards’
fixed overhead costs. Potential other forms of work include construction of ships for other U.S.
government agencies, such as the Coast Guard or the National Oceanic and Atmospheric
Administration (NOAA), construction of commercial ships, overhaul and repair of Navy or other
U.S. government ships, and overhaul and repair of commercial ships.
A sixth option would be to improve the operating efficiency of yards building Navy ships by
incorporating more advanced design and production processes and equipment. The National
Shipbuilding Research Program (NSRP) Advanced Shipbuilding Enterprise (ASE) is one effort
aimed at this goal.45 A May 2005 DOD report compares the operating efficiency of the yards that
build the Navy’s major ships relative to that of foreign shipyards that are considered to be among
the world’s most efficient, and makes recommendations for how to improve the operating
efficiency of the U.S. yards.46
A seventh option would be to build Navy ships without some of their planned equipment (or with
less expensive substitute equipment). Building a ship without some of its planned equipment (or
with less expensive substitute equipment) would likely reduce its capabilities. Equipment not
installed during the original construction process could be added back later, after the ship had
entered service. This would restore the ship’s lost capability but add back the cost of this
equipment, in which case the ship’s procurement cost, instead of being reduced, would have been
partially deferred into the future. Installing this equipment on an in-service ship, moreover, may
be more expensive than building it into the ship during its original construction process. As a
consequence, this strategy over the long run could increase the procurement total cost of the
ship above what it would have been if the ship had been built from the beginning with all its
planned equipment.
44
For further discussion of competition in Navy ship acquisition, see David H. Lewis, “No Bucks, No Buck Rogers,”
U.S. Naval Institute Proceedings, May 2005, pp. 54-58.
45
For more on this program, see the NSRP ASE website at http://www.nsrp.org/.
46
U.S. Department of Defense, Global Shipbuilding Industrial Base Benchmarking Study, Part I: Major Shipyards,
Washington, 2005, 184 pp. (May 2005, Office of the Deputy Under Secretary of Defense [Industrial Policy].)
Congressional Research Service
33
Navy Ship Acquisition: Options for Lower-Cost Ship Designs—Issues for Congress
An eighth option would be to build Navy ships in foreign shipyards where construction costs may
be lower to due lower wages and material prices or other factors. Regarding this option, 10
U.S.C. § 7309 states that “no vessel to be constructed for any of the armed forces, and no major
component of the hull or superstructure of any such vessel, may be constructed in a foreign
shipyard.” The provision permits the President to authorize exceptions when the President
determines that it is in the national security interest. In such cases, the President is to notify
Congress of the determination, and no contract may be made until the end of the 30-day period
beginning on the date on which the notice is received. The provision also exempts inflatable boats
and rigid inflatable boats. In addition to 10 U.S.C. § 7309, the annual DOD appropriations act
contains a provision in the section entitled “Shipbuilding and Conversion, Navy,” stating that
funds for Navy shipbuilding are made available for the fiscal year in question provided, among
other things, “That none of the funds provided under this heading for the construction or
conversion of any naval vessel to be constructed in shipyards in the United States shall be
expended in foreign facilities for the construction of major components of such vessel: Provided
further, that none of the funds provided under this heading shall be used for the construction of
any naval vessel in foreign shipyards.”
A recent report from the RAND Corporation provides additional discussion of why Navy
ships cost much more today than they did decades ago, and of options for reducing the cost of
Navy ships.47
Author Contact Information
Ronald O’Rourke
Specialist in Naval Affairs
[redacted]@crs.loc.gov, 7-....
47
Mark V. Arena, Irv Blickstein, et al., Why Has the Cost of Navy Ships Risen? A Macroscopic Examination of the
Trends in U.S. Naval Ship Costs Over the Past Several Decades, RAND Corporation, Santa Monica (CA), 2006.
(National Defense Research Institute, MG-484-Navy) 98 pp.
Congressional Research Service
34
EveryCRSReport.com
The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the
Library of Congress, charged with providing the United States Congress non-partisan advice on
issues that may come before Congress.
EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The
reports are not classified, and Members of Congress routinely make individual reports available to
the public.
Prior to our republication, we redacted names, phone numbers and email addresses of analysts
who produced the reports. We also added this page to the report. We have not intentionally made
any other changes to any report published on EveryCRSReport.com.
CRS reports, as a work of the United States government, are not subject to copyright protection in
the United States. Any CRS report may be reproduced and distributed in its entirety without
permission from CRS. However, as a CRS report may include copyrighted images or material from a
third party, you may need to obtain permission of the copyright holder if you wish to copy or
otherwise use copyrighted material.
Information in a CRS report should not be relied upon for purposes other than public
understanding of information that has been provided by CRS to members of Congress in
connection with CRS' institutional role.
EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim
copyright on any CRS report we have republished.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.