Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Congressional research reportJun 10, 2014
Ask Donna
What actually matters in this document.
Text
Analysis of Senate-Passed S. 2198:
Emergency Drought Relief Act of 2014
(name redacted)
Specialist in Natural Resources Policy
(name redacted)
Specialist in Natural Resources Policy
June 10, 2014
Congressional Research Service
7-....
www.crs.gov
R43594
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Summary
Over the past five years, portions of the country have been gripped with extensive drought,
including the state of California. Drought conditions in California are “exceptional” and
“extreme” in much of the state, including in prime agricultural areas of the Central Valley,
according to the U.S. Drought Monitor. Such conditions pose significant challenges to water
managers who before this dry winter were already grappling with below-normal surface water
storage in the state’s largest reservoirs. Groundwater levels in many areas of the state also have
declined due to increased pumping over the last three dry years. While March rain had improved
the water year outlook somewhat—moving the year from the driest on record in terms of
precipitation to date to the third-driest—water managers are fearful of the long-term impacts of a
relatively dry winter and little existing snowpack to refresh supplies later in the year.
Because of the extent of the drought in California, drought impacts are varied and widespread.
Most of the San Joaquin Valley is in exceptional drought, and federal and state water supply
allotments are at historic lows. The state has also had to restrict diversions from some rivers and
streams, including the Sacramento and San Joaquin Rivers, two of the state’s largest rivers. Many
farmers are fallowing lands and some are removing permanent tree crops. Cities and towns have
also been affected, and the governor has requested voluntary water use cutbacks of 20%. The
effects of the drought are also likely to be felt on fish and wildlife species and the recreational and
commercial activities they support, potentially including North Coast salmon fisheries.
Congress is considering several bills that would address drought conditions in California. This
report discusses S. 2198, as passed by the Senate on May 22, 2014. S. 2198 would address
drought impacts in California and assist with drought response. The Senate-passed version of S.
2198 contains eight sections, whose provisions range from mandating maximization of California
water supplies, through specific emergency project development, management, and operations
directives and addressing project environmental reviews (as long as actions are consistent with
applicable law and regulations and not highly inefficient), to prioritizing funding for certain
emergency drought activities under existing water laws. In maximizing water supplies, the bill
would address project operations that relate to long-standing and controversial issues associated
with management of the federal Bureau of Reclamation’s Central Valley Project (CVP) and the
California Department of Water Resources’ State Water Project (SWP), which are operated in
coordination under a coordinated operations agreement (COA). Title II of S. 2198 as introduced,
which would have expanded the assistance potentially available under an emergency declaration
for drought (or other emergencies), was not included in the Senate-passed version of S. 2198.
Congressional Research Service
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Contents
Introduction...................................................................................................................................... 1
Emergency Drought Relief .............................................................................................................. 2
Section 4. Emergency Projects .................................................................................................. 3
Section 4(a), Water Supplies, and Section 4(b), Limitation ................................................ 3
Section 4(c). Administration ............................................................................................... 5
Section 4(c)(1) and (2) .................................................................................................. 6
Section 4(c)(3) .............................................................................................................. 8
Section 4(c)(4) .............................................................................................................. 9
Section 4(c)(5) ............................................................................................................ 10
Section 4(c)(6)(A) ....................................................................................................... 11
Section 4(c)(6)(B) ....................................................................................................... 13
Section 4(c)(7) ............................................................................................................ 13
Section 4(c)(8) ............................................................................................................ 13
Section 4(c)(9)(A) ....................................................................................................... 14
Section 4(c)(10) .......................................................................................................... 15
Section 4(c)(11)........................................................................................................... 15
Section 4(c)(12) .......................................................................................................... 16
Section 4(c)(13) .......................................................................................................... 16
Section 4(d). Other Agencies ............................................................................................ 16
Section 4(e). Accelerated Project Decision and Elevation ................................................ 17
Section 5. Emergency Environmental Reviews....................................................................... 18
Section 6. State Revolving Funds ............................................................................................ 19
Section 7. Effect on State Laws ............................................................................................... 20
Section 8. Termination of Authorities. ..................................................................................... 20
Contacts
Author Contact Information........................................................................................................... 20
Acknowledgments ......................................................................................................................... 20
Congressional Research Service
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Introduction
Several western states are experiencing varying degrees of drought, with much of the West
experiencing severe to exceptional drought conditions. Drought conditions persist in all counties
in California, with a majority classified as in either extreme or exceptional drought.1
Notwithstanding March rains,2 California is experiencing its third consecutive dry year, which has
resulted in abnormally low reservoir levels, as well as low surface and groundwater levels.
Current drought conditions in California and much of the West have fueled congressional interest
in drought and its effects on water supplies, agriculture, and fish and wildlife.3
Water deliveries to the federal Central Valley Project (CVP) and the California State Water
Project (SWP), among others, have received significant attention during the drought. Deliveries
to the CVP and SWP are sometimes limited due to federal and state endangered species
regulations, as well as state water quality regulations. Such regulations often limit how much and
when water is released from reservoirs and pumped from the San Francisco Bay and San Joaquin
and Sacramento Rivers Delta (Bay-Delta), and thus result in reduced water deliveries to project
water users. Additionally, the amount of available water that is allocated to water contractors
during drought is based on state water rights allocations, with “senior” water rights holders—
those who were first in line to receive water historically—receiving first priority for available
water. In drought years such as 2014, water contractors with rights “junior” to senior water rights
might see their CVP water deliveries reduced to zero supply. Reductions to water deliveries from
all of the above factors are controversial and are at the crux of management disputes among water
contractors, environmental groups, fisheries interests, and others. Additional water delivery
curtailments resulting from the drought have resulted in some calling for increased operational
flexibility and limits on these environmental restrictions.
Several bills have been introduced in the 113th Congress to address different aspects of drought in
California and other regions.4 This report focuses on Sections 4 through 8 of the Senate-passed
version of S. 2198, the “Emergency Drought Relief Act.” The original version of the bill was
introduced April 2, 2014, and went to the Senate floor, bypassing committee consideration, under
an expedited rule, Senate Rule XIV.5 S. 2198 as introduced was largely a revision of a previous
emergency drought bill, S. 2016, the “California Emergency Drought Relief Act.”6 Some
provisions in S. 2198 as introduced were broadened to apply to states outside of California;
however, the Senate-passed version of S. 2198 dropped many of these provisions. Additionally, S.
2016 contained numerous direct spending provisions that are not included in S. 2198 as
introduced or as passed by the Senate.
1
See http://droughtmonitor.unl.edu/Home/StateDroughtMonitor.aspx?CA.
Although on February 1, 2014, it looked as though 2014 would be the driest year on record for California, recent
precipitation has improved conditions slightly, and as of April 1, the year registers as the third-driest on record.
3
For information on drought in general, see CRS Report R43407, Drought in the United States: Causes and Current
Understanding, by (name redacted) and (name redacted).
4
Other selected bills that address drought or water management in California include H.R. 3964, which passed the
House on February 5, 2014; H.R. 1927; H.R. 4039; H.R. 4239; H.R. 4300; and some bills that address water storage
specifically (e.g., H.R. 4126 and H.R. 4127).
5
For information on Senate Rule XVI, see CRS Report RS22309, Senate Rule XIV Procedure for Placing Measures
Directly on the Senate Calendar, by (name redacted) and Christina Wu.
6
For analysis of S. 2198 as introduced, see CRS Report R43469, Analysis of S. 2198: Emergency Drought Relief Act of
2014, by (name redacted) and (name redacted).
2
Congressional Research Service
1
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
S. 2198 as passed by the Senate would direct the Secretary of Agriculture (added since
introduction), the Secretary of Commerce, the Secretary of the Interior, and the Administrator of
the Environmental Protection Agency (EPA) to undertake numerous actions that would address
emergency drought impacts in California and other states, by aiming to increase water supplies
for California water users, prioritizing and expediting program funding for certain drought
mitigation activities (e.g., projects providing drinking water and avoiding loss of permanent
crops, and including grants for pilot projects increasing reservoir supplies in the Colorado River
Basin), providing for emergency environmental reviews, and addressing Klamath River Basin
water issues.
The Senate-passed version of S. 2198 includes eight sections, whose provisions range from
mandating maximization of California water supplies—consistent with laws and regulations—
through specific project development, management, and operations directives and addressing
project environmental reviews, to prioritizing funding for certain emergency drought activities
under existing water laws and directing development of a comprehensive National Academy of
Sciences study on increasing water supplies through control of an invasive plant species known as
saltcedar (Tamarix ramosissima).
Senate-passed S. 2198 is narrower in scope than the bill as first introduced. Much of the bill
focuses on specific issues related to water infrastructure and conveyance in California. For
example, the bill would direct federal agencies to maximize water supplies and streamline
environmental reviews while remaining “consistent” with laws and regulations. This policy
approach is aimed at addressing drought, and in doing so, touches upon many long-standing and
controversial issues associated with operations of the federal Central Valley Project (CVP),
managed by the U.S. Bureau of Reclamation (hereinafter referred to as Reclamation), and the
State Water Project (SWP), managed by the California Department of Water Resources.
Key issues for Congress include whether the activities mandated and authorized under the bill
would provide adequate supplies of water for irrigation of permanent and other crops and public
health and safety needs, and whether such activities would hasten the decline of certain fish
species protected under state and federal endangered species laws. While the bill would direct
federal agencies to operate within existing laws and regulations, it mandates certain CVP and
SWP operational activities for which long-term consequences on listed species habitat and water
supply are unknown. The proposed provisions related to these projects and operations raise
several additional questions that are noted throughout the analysis of S. 2198 below. The
remainder of this report discusses key provisions of the Senate-passed S. 2198. The discussion
focuses on selected provisions (including subsections) that have received the most attention in
congressional debates and in media and stakeholder accounts.
Emergency Drought Relief
The Senate-passed version of S. 2198 includes numerous sections related to emergency drought
relief. As noted above, these sections range widely. The first three sections of the bill cover the
table of contents, findings, and definitions. The final five sections of S. 2198 are the focus of this
report. Some parts of Section 4 of the bill have received significant attention and are thus
discussed in detail, including specific emergency actions related to California water supply
management, such as in Sections 4(a) and 4(c)(4) through 4(c)(6). Other sections apply to other
activities, such as studying the water supply effects of saltcedar and directing participation in and
funding for pilot water projects in the Colorado River Basin (Section 4(b)(7)). Many of the bill’s
Congressional Research Service
2
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
provisions would expire upon suspension of the state emergency drought declaration. The Senatepassed version of S. 2198 would also modify implementation of financial assistance for some
water resource and water quality programs. These include the WaterSMART program under
Secure Water Act of 2009 (42 U.S.C. 10361 et seq.) and State Revolving Funds (SRFs)
administered by the Environmental Protection Agency (EPA) under the federal Clean Water Act
(33 U.S.C. 1231 et seq.) and the Safe Drinking Water Act (42 U.S.C. 300j-12). One such
provision (Section 7) would direct the Secretary of the Interior to fund or participate in pilot
projects to increase water supplies in the Colorado River Basin.
Those provisions related to California water flow, infrastructure development and operations, and
environmental permitting have one overarching theme: maximization of water supplies available
for general agricultural and municipal and industrial demand while an emergency drought
declaration is in effect—consistent with existing law and regulations. Other provisions under
Title I would largely modify, expand, or reauthorize existing program authorizations.
Section 4. Emergency Projects7
Section 4(a), Water Supplies, and Section 4(b), Limitation
Section 4(a) would direct the Secretary of Agriculture, the Secretary of Commerce, the Secretary
of the Interior, and the Administrator of the Environmental Protection Agency (together defined
as “the Secretaries” under Section 3(4) of the act) to provide the “maximum quantity of water
supplies possible” to CVP agricultural, municipal and industrial (M&I), and refuge service and
repayment contractors; SWP contractors; the Klamath project or operations; and “any other
locality or municipality in the State” of California, by approving, consistent with applicable laws
and regulations, the following types of projects and operations:8
•
any project or operations “as quickly as possible based on available
information” to address emergency conditions;
•
projects that do not need congressional authorization; and
•
projects that have followed procedures required by applicable law.
This provision provides broad authority to the Secretaries to approve “any” project or operational
change to address emergency provisions; however, limitations on this authority, provided in
Section 4(b), prevent undertaking projects (operations are not addressed) that would otherwise
require congressional authorization, or without following procedures required by applicable law.
7
Section 2 of S. 2198 as passed the Senate includes findings related to drought conditions in California, some of which
have changed since S. 2016, a predecessor bill to S. 2198, was introduced and upon which findings in S. 2198 appear to
be based. See CRS Report IF00008, California Drought: Water Supply and Conveyance Issues (In Focus), by (name red
acted), for an update of California precipitation and snowpack conditions. Section 3 of the Senate-passed S. 2198
includes definitions.
8
Sections 4(a) and 4(c) of Senate-passed S. 2198 direct the Secretaries of the Interior, Agriculture, and Commerce, and
the Administrator of the Environmental Protection Agency (EPA), together defined as the “Secretaries” under Section 3
of S. 2198, to maximize water supplies for users within the scope of state and federal laws and regulations. Section 7
states that no state laws in effect on the date of this bill being enacted will be preempted, including area-of-origin and
other water rights protections. Further, in carrying out emergency projects authorized under Section 4(c), the bill
specifically states that projects carried out are to be “consistent with applicable laws (including regulations).”
Congressional Research Service
3
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Projects that could be approved could include, for example, relatively small conservation or
efficiency projects, or large projects not needing congressional approval that would expand
storage or conveyance facilities to provide additional water to users throughout different seasons,
or projects that adjust operations at reservoirs or in the Delta to increase water supplies.9
Additionally, this section would create the authority necessary for federal participation in statedriven projects intended to address the drought. California recently passed a law providing $687.4
million to address the drought. The intent of this section, which is similar to the bill as introduced,
according to some sponsors of the bill, is to provide flexibility to increase water supplies and
allow federal agencies to use water supplies during periods of increased precipitation.10 There are
several questions or issues that might arise from this section. A brief summary of each is listed
below.
•
Section 4(a) raises the question of how agencies would provide the “maximum
quantity of water supplies possible” to CVP and other contractors and, relatedly,
how they would make such a determination consistent with laws and regulations.
Implementation of the provision could be difficult and possibly contentious. For
example, while “take” limits under the federal or state Endangered Species Acts11
may be possible to monitor, the effects of providing maximum water supplies on
species survival and viability and water quality may not be apparent,
quantifiable, or known for several years into the future. Conversely, agencies and
water users may not agree that particular actions are providing maximum water
quantities. Some observers already believe the agencies are maximizing water
supplies to the detriment of species, while others believe the agencies are not
doing enough and are advocating relaxation of some laws and regulations.
•
Some may respond that if the bill is enacted, agency actions specified under this
section would be directed to maximize water supplies for contractors as a priority
over other considerations (e.g., water quality or habitat conservation). In response
to this concern, others might contend that other factors such as water quality and
species needs are addressed in laws and regulations that would prevent harm.
Essentially, agencies would have to balance the new directives with parameters
prescribed in existing law and regulations, thus making it difficult to estimate
what effect the provision would have on projects, project operations, and the
multiple interests that rely upon water supplies through project operations.
9
Some might contend that this provision could pave the way for activities under the proposed Bay-Delta Conservation
Plan (BDCP) that do not need congressional approval; however, to date, BDCP documents indicate that the plan is not
intended to provide new, additional water supplies beyond what is authorized. Seasonal increases in the amount of
water supplies provided could result from the BDCP. (See Bay-Delta Conservation Plan: Your Questions Answered,
Surface Water and Storage at http://baydeltaconservationplan.com/AboutBDCP/YourQuestionsAnswered.aspx.) At
least one group has raised this issue. An earlier version of S. 2198 did not include the limitation section provided in
Section 4(b) of the Senate-passed version, which some viewed as a possible authorization for the BDCP. See Friends of
the River, “Senate Drought Bill Has Some Real Solutions, but does it prioritize agribusiness over urban communities
running out of water?,” press release, February 11, 2014. http://www.friendsoftheriver.org/site/DocServer/
FOR_Media_Release—Senate_Drought_Bill.pdf?docID=7481.
10
Senator Diane Feinstein, “California, Oregon Senators Introduce Drought Relief Legislation,” press release, February
11, 2014, http://www.feinstein.senate.gov/public/index.cfm/press-releases?ID=e7668832-d0be-4329-a30fd1e5e47863aa.
11
Under the federal Endangered Species Act, agencies may receive permission to “take” (harm or kill) a specified
number of species within certain limits. For operation of the CVP, take limits are identified for fish killed at the CVP
pumps in the Delta.
Congressional Research Service
4
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
•
Projects or operations that would be authorized under this section are to provide
maximum quantities of water by approving projects and operations to provide
“additional water supplies as quickly as possible”; however, there is no definition
for additional water supplies in S. 2198. The lack of specificity raises the
question of whether the language is meant to apply to water supplies during parts
of the year, the entire year, or several years.
•
The broad variety of potential projects that could be authorized under this section
is tempered by language stating that projects and actions must be consistent with
applicable law. It appears that projects could be conducted throughout the state
and not just limited to the CVP or SWP service areas.
•
Projects and operational changes would have to be consistent with state and
federal endangered species laws and regulations, as well as with the National
Environmental Policy Act (NEPA; 42 U.S.C. §4321, et seq.), California
Environmental Quality Act (CEQA), and water quality laws and regulations,
among other laws and regulations. This provision by itself raises the question of
how the term “consistent with the law” might be interpreted as opposed to
“pursuant to” or “in compliance with” applicable laws. Some might question if
the phrase “consistent with law” would allow for more agency discretion or
flexibility than other phrases. However, the new limitation in Section 4(b) that
would require that projects follow procedures required by applicable law may
mitigate this issue. Regardless, ultimately, it may be left to the courts to
determine what is or is not consistent with laws and regulations and whether all
applicable legal procedures were followed.
•
The authority in this section would also be limited by the duration of the drought
emergency declaration. Specifically, Section 8 states that the authority for this
section of the bill would expire when the governor suspends the state drought
emergency declaration. It is unclear, however, if a project started under this
authority would enjoy permanent authorization or how it would be funded after
the drought emergency declaration is lifted.
•
The provision also would mandate that projects or operations be implemented as
quickly as possible. It appears that this provision could provide additional
authority for agencies to streamline permit processes or feasibility studies for
implementing projects, as long as such actions were consistent with existing laws
and regulations. Although streamlining or shortening these processes would
arguably lower the time it takes for operations and projects to become
operational, and would therefore have a more immediate effect on reducing
drought impacts, it is not clear whether such action would be helpful in the long
run, for example, if full effects on species were not accounted for and species
declined at a rapid pace.
Section 4(c). Administration
Section 4(c) of S. 2198 contains 13 subsections that would direct the Secretaries to implement
several specific project-related and operational actions largely in California for carrying out
Section 4(a). As with Section 4(a), Section 4(c) states that all actions are to be accomplished
Congressional Research Service
5
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
consistent with applicable laws and regulations. The intent of this section, according to some
sponsors of the bill, is to provide flexibility to increase water supplies and allow federal agencies
to use water supplies during periods of increased precipitation.12
Several provisions in Section 4(c) of S. 2198 as passed touch upon long-standing operational
issues associated with managing the CVP and SWP. For example, project water deliveries from
the CVP and SWP are sometimes limited due to federal and state endangered species regulations,
as well as state water quality regulations. Such regulations often limit how much and when water
is released from reservoirs and pumped from the San Francisco Bay and San Joaquin and
Sacramento Rivers Delta (Bay-Delta), and thus result in reduced water deliveries to project water
users. These reductions are controversial and are at the crux of management disputes among
water contractors, environmental groups, fisheries interests, and others.
Several subsections of Section 4(c) address specific projects and project operations that may have
an effect on project water deliveries, as well as species viability and water quality. Following is a
summary and analysis of the 13 subsections under Section 4(c).13
Section 4(c)(1) and (2)
Section 4(c)(1) would direct the Secretaries to ensure that the Delta Cross Channel Gates (Delta
Gates) will remain open to the greatest possible extent timed to maximize peak tide flood periods
and to provide water supply and water quality benefits. This would be for the duration of the
emergency drought declaration by the state. According to the section, this operation is to be
consistent with the State Water Resources Control Board (SWRCB) order for a temporary
urgency change (TUC) in terms of response to the drought, effective January 31, 2014, as
modified by subsequent orders.14
There are some questions and potential issues that could arise from changes in the operations of
the Delta Gates.
•
The provision raises the question as to how it would change existing operations
and ultimately, whether the provision would result in additional water being
provided to CVP and SWP water contractors.15 Some might contend that existing
operations are already implemented to maximize water supplies and that this
provision does not add to existing authorities to operate the gates if such action
12
Senator Diane Feinstein, “California, Oregon Senators Introduce Drought Relief Legislation,” press release, February
11, 2014, http://www.feinstein.senate.gov/public/index.cfm/press-releases?ID=e7668832-d0be-4329-a30fd1e5e47863aa.
13
Several of these specified actions are focused on increasing water supplies (or minimizing reductions to water
supplies); however, their effectiveness in achieving their objectives will be tempered by the condition that they are to
be implemented consistent with applicable laws and regulations. Further, many of the actions specified in this section
are only in effect until the governor of the state suspends the state of drought emergency declaration.
14
For information on the TUCs, see Thomas Howard, Order Approving a Temporary Urgency Change in License and
Permit Terms and Conditions Requiring Compliance with Delta Water Quality Objectives in Response to Drought
Conditions (With Modifications Dated February 7, 2014, February 28, 2014), State Water Resources Control Board,
Order, February 28, 2014. Available at http://www.waterboards.ca.gov/waterrights/water_issues/programs/drought/
docs/022814_revised_tucp_order.pdf. The order has been modified several times since that time. For a listing of related
actions, see http://www.waterboards.ca.gov/waterrights/water_issues/programs/drought/tucp.shtml.
15
This is based on the premise that the gates are opened to maximize flows within environmental regulations.
Congressional Research Service
6
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
would harm listed species or violate state water quality standards. Others might
counter this sentiment by noting that the direction provided in Section 4(c)(1)
would ensure that maximum flows are being sent through the Delta during peak
flood tide, and that the provision would provide definitive authority for the
Secretary of the Interior to maximize flows—as long as such activities are
consistent with laws and regulations. The practical effect of the provision would
depend on how the state and federal agencies or courts determine what and when
such actions are consistent with laws and regulations.
Background on Delta Cross Channel Gates
The Delta Gates control water in the Delta Cross Channel, which diverts fresh water from the Sacramento River
into a branch of the Mokelumne River and through the Delta. The water eventually makes its way across the Delta to
the pumping stations in the South Delta for export with other tributary water via state and federal pumps. The water
is then distributed via aqueduct to contractors within the SWP and CVP service areas south of the Delta. The Delta
Gates are operated according to SWRCB Decision 1641 and federal biological opinions (BiOps)16 under the federal
Endangered Species Act (ESA). The Delta Gates are required to be closed during “selected periods” when the
Sacramento River is experiencing high-level flows to protect fish migration.17 The current operation of the Delta
Gates includes being closed for up to 45 days during the period of October 1 to January 31 for fisheries protection;
closed from February 1 to May 20; closed for a total of 14 days during the period of May 21 to June 15; and generally
open from June 16 to September 30, pending water quality and fisheries conditions which might necessitate a
closure.18
Opening the Delta Gates allows more freshwater to move from the Sacramento River through the interior Delta to
the Southern Delta where pumps are located, instead of following the river’s natural flow south and westward toward
San Francisco Bay. The influx of freshwater reduces the salinity in the interior Delta and increases freshwater supplies
for pumping from the Delta. However, depending on the conditions and timing of opening the Delta gates, there
could be negative effects on migrating salmon. When the Delta gates are closed there is better connectivity of
migratory routes for fish species and improved protection against flooding in the San Joaquin River section of the
Delta. When Delta gates are open, migratory patterns for juvenile salmon can be altered, causing salmon to enter the
Delta and lower their survival rates. Further, closing the Delta Gates increases salinity in the western Delta, affecting
water quality in areas such as the Contra Costa Water District.
Operation of the Delta Gates is addressed in federal BiOps under the federal ESA and SWRCB Decision 1641.
•
Section 4(c)(1) also specifically states that Delta Gates are to be operated
consistent with SWRCB orders approving temporary urgency changes (TUCs) to
D-1641.19 TUCs would allow the Delta Gates to be opened during the period that
they were normally closed unless species are affected.20 If changes to the
16
Federal biological opinions contain “reasonable and prudent alternatives” (RPAs) to an agency’s planned operations
as required by the ESA when a jeopardy decision is reached. Because NMFS and FWS (the Services) found in their
respective BiOps that the planned Reclamation operations were likely to lead to the extinction of the Delta smelt and
salmon species, the ESA required the Services to issue alternative operations that would not imperil those species.
Those measures are called RPAs and are considered part of the BiOp.
17
Craig M. Wilson, Delta Watermaster, Gates and Barriers in the Delta, California Water Boards, State Water
Resources Control Board, A report to the State Water Resources Control Board and Delta Stewardship Council,
Sacramento, CA, April 2013, p. 5.
18
For more information, see https://www.usbr.gov/mp/PA/docs/fact_sheets/Delta_Cross_Channel_Canal.pdf.
19
Decision 1641 is a decision of the California State Water Resources Control Board, which implements the state’s
Water Quality Control Plan. D-1641 includes specific water quality and flow criteria, which affect how much water can
be pumped at specific times and released from reservoirs to manage fish and water quality objectives in the Delta.
20
There are several other requirements in the TUCs that would require compliance by the California DWR and
Reclamation, including modeling and monitoring of changes in water supplies and flows, and setting up the operations
(continued...)
Congressional Research Service
7
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
operations of the gates are outside the parameters of existing ESA permits for
coordinated operations of the CVP and SWP, California Department of Water
Resources (DWR) and the Bureau of Reclamation (Reclamation) would
presumably be responsible for obtaining applicable new permits under the ESA.
Section 4(c)(2)(A) would direct the Secretaries to collect data associated with the operations of
the Delta Gates and the effect of operations on threatened and endangered species listed under the
Endangered Species Act (ESA), water quality, and water supply. Section 4(c)(2)(B) would direct
an assessment of the data collected, and require the Director of the National Marine Fisheries
Service (NMFS) to make recommendations for changing the operations of the CVP and SWP,
including, if appropriate, changes to reasonable and prudent alternatives in the BiOps issued by
NMFS on June 4, 2009. The provision states that the changes should be likely to produce fishery,
water quality, and water supply benefits.
•
This provision would require NMFS to develop recommendations to change
BiOps under ESA that regulate operations of the Delta Gates to address salmon
populations in the Delta. It is uncertain if or how the recommendations would
result in changes to the BiOps. For example, NMFS might reject
recommendations for changes and implement a modified version of the
recommendations, which might have unintended consequences for some
stakeholders. Some might question if this provision would result in changes to
NMFS’s implementation of its 2009 BiOp. The 2009 NMFS BiOp has never
been fully implemented due to court order.21
Section 4(c)(3)
Section 4(c)(3)(A) would direct the Secretaries to implement turbidity control strategies that
would allow for increased water deliveries while avoiding jeopardy to adult delta smelt at the
SWP and CVP pumps.22 Section 4(c)(3)(B) would direct the Secretaries to manage reverse flow
in the Old and Middle Rivers (OMR) according to the FWS Delta smelt biological opinion
(BiOp) dated December 15, 2008,23 and the NMFS BiOp for salmonids, dated June 4, 2009, to
minimize water supply reductions for the CVP and SWP.
•
It is uncertain if existing strategies to address turbidity have been vetted and
could be implemented rapidly to maximize their benefit in addressing drought
conditions and still be consistent with laws and regulations.
•
It appears that Section 4(c)(3) would provide direct authority to manage flows
with the objective of minimizing water supply reductions to SWP and CVP users,
as opposed to relying solely on discretionary actions allowed, or ranges specified,
(...continued)
management process noted above.
21
Consolidated Salmonid Cases, 791 F. Supp. 2d 802 (E.D. Cal. 2011).
22
Delta smelt use turbid waters to consume nutrients and provide cover to hide from predators. Pumps create turbid
waters because of the nutrients and matter being drawn to them from the pumping. Minimizing turbidity at the pumps is
a conservation strategy for smelt because with less turbidity, fewer smelt would arguably be attracted to the pumps and
get entrained.
23
The 2008 FWS BiOp also has not been fully implemented; however, a March 13 Ninth Circuit Court decision upheld
the 2008 BiOp, so measures covered by the BiOp would go into effect even without S. 2198, but are not currently in
place. Delta Smelt Consolidated Cases, 747 F.3d 581 (9th Cir. 2014).
Congressional Research Service
8
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
within reasonable and prudent alternatives (RPAs) under the BiOps. As such, it
raises the question of how the agencies might balance the directive to minimize
water supply reductions with the other legal requirements related to OMR flows,
in particular with water quality and ESA requirements that at times result in
water supply reductions. The outcome of this language would depend on how
Reclamation and DWR implement this provision, as some discretion already
exists, and whether the direction provided in S. 2198 would result in different
management than under temporary operations or under the newly upheld 2008
FWS BiOp, and under the NMFS BiOp.
•
As with Section 4(c)(1) above, at issue for implementing agencies would be how
to balance the directives to maximize water supplies in the short term with
obligations to protect species and habitat over the short and long terms. For
example, the effects of the changed OMR flows may not be immediately visible
or detectible for several years.
Section 4(c)(4)
Section 4(c)(4) would direct the Secretaries to adopt a 1:1 inflow-to-export ratio (I:E ratio) for
increased San Joaquin River flows resulting from water transfers and exchanges, among other
purposes. The flow would be measured on a three-day rolling average from April 1 through May
31 at Vernalis, as long as the governor’s drought emergency declaration is in effect.24
The 1:1 I:E ratio for the increased San Joaquin River flows is currently allowed in “critically dry”
years and is expected to be in effect from February through May of 2014.25 However, the I:E ratio
under the 2009 NMFS BiOp changes based on water year type, and is 2:1 in “dry” years; 3:1 in
“below normal” years; and 4:1 in “above normal” and “wet” years.26 The bill’s original sponsor
noted that the goal of an identical provision found in S. 2016 is to allow 100% of transferred or
exchanged water to be moved through the Delta, instead of a fraction.27
24
The projected hydrologic year-type, upon which the current 1:1 I:E ratio is based, and the duration of a drought
declaration may not go hand-in-hand. For example, California governor Arnold Schwarzenegger declared a drought
emergency in 2009 (a “dry” year for the Sacramento River and “below normal” for the San Joaquin), but the drought
declaration was not rescinded until 2011 by the next governor, Governor Brown. The water year-type in 2010 was
“below normal” under the Sacramento River index and “above normal” under the San Joaquin River index. The water
year-type for 2011 was “wet” under both indices. Thus, under S. 2198, the I:E ratio for water resulting from water
transfers and exchanges may last longer than under current operations for the overall I:E ratio. It is not clear what effect
such a change might have on fish and wildlife or how much more water might be exported under the language. (For
historical data on water year types, see California Dept. of Water Resources, California Data Exchange Center,
Chronological Reconstructed Sacramento and San Joaquin Valley Water Year Hydrologic Classification Indices:
http://cdec.water.ca.gov/cgi-progs/iodir/WSIHIST. Note: these year types do not necessarily reflect the projected year
type at the time when initial CVP and SWP water allocations were made for each year.)
25
U.S. Dept. of the Interior, Central Valley Project Water Plan 2014, Bureau of Reclamation, Mid-Pacific Region,
Sacramento, CA, February 3, 2014, p. 8. Hereinafter referred to as “2014 CVP Water Plan,” http://www.usbr.gov/mp/
PA/water/docs/2014_water_plan_v10.pdf.
26
2011 Amendments to the 2009 NMFS BiOp: http://www.westcoast.fisheries.noaa.gov/publications/Central_Valley/
Water%20Operations/Operations,%20Criteria%20and%20Plan/040711_ocap_opinion_2011_amendments.pdf, p. 70.
27
Senator Feinstein, “California Emergency Drought Relief Act of 2014, Bill Summary,” bill summary for S. 2016,
February, 2014: http://www.feinstein.senate.gov/public/index.cfm/files/serve/?File_id=fbdeb35c-1863-47e3-89aa39e7a97b95cd.
Congressional Research Service
9
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
•
According to Reclamation, the agency normally assumes a 10% conveyance or
transport loss associated with transfers and exchanges “from the point of release
and point of Delta diversion.” Thus, typically, 90% would be available for export,
not 100% as called for in S. 2198.
•
Reclamation is planning for a 1:1 ratio in 2014, and because other factors that
might affect the ratio are not anticipated at this time, Section 4(c)(4) would not be
expected to affect operations, assuming the critically dry hydrologic situation
continues.28 However, according to Reclamation, the language could hamper
operations if the hydrologic situation improves or if other opportunities arise
where Reclamation could change operations to improve water supply.29
•
Determining the net effect this provision would have on water supply available
for export and on fish and wildlife habitat is beyond the scope of this report.
However, according to the Westlands Water District, the provision, combined
with direction to manage reverse flow in the “Old and Middle Rivers (OMR) as
prescribed” in the 2008 FWS Delta Smelt BiOp “to minimize water supply
reductions” for the CVP and SWP (Section 103(b)(3)(B)), could generate more
than 500,000 acre-feet of water for CVP and SWP exports from the Delta.30 On
the other hand, some environmental groups state that this provision could be
harmful to salmon species because hydrologic conditions may improve before a
drought declaration is lifted.31 In either case, it is important to note that the 1:1
ratio in S. 2198 would be limited to water made available from transfers and
exchanges, not the total San Joaquin River run-off.
Section 4(c)(5)
Section 4(c)(5) would direct the Secretaries to issue “all necessary permit decisions” under their
authority for temporary barriers or operable gates in Delta channels to improve water quantity and
quality for SWP and CVP south-of-Delta water contractors and other water users within 30 days
of receiving a permit application from the state. According to this section, barriers or gates
“should” provide species benefits and protection and in-Delta water quality and “shall” be
designed so that formal Section 7 consultation under ESA would not be necessary.
•
The directive in this provision could be controversial if such studies noted above
are not completed and considered in the decision. For example, some boaters
have already objected to proposed barriers.32 Further, a 30-day time limit might
not be enough time to render a decision. On the other hand, temporary barriers
and gates have been studied for several years (see box below).
28
E-mail communication with Reclamation, March 14, 2016.
Ibid.
30
Westlands Water District, “Statement of Westlands Water District on the Introduction of the California Emergency
Drought Relief Act of 2014,” press release, February 11, 2014, http://www.westlandswater.org/wwd/pr/
statement20140211.pdf.
31
Letter from conservation groups (Audubon, Audubon California, Defenders of Wildlife, Earthjustice, Endangered
Species Coalition, Environmental Defense Fund, League of Conservation Voters, Natural Resources Defense Council,
Pacific Coast Federation of Fishermen’s Associations, Sierra Club California, The Nature Conservancy California
Chapter) to Senators Feinstein, Boxer, Wyden, and Merkley, March 3, 2014, p. 2.
32
See http://www.tradeonlytoday.com/2014/04/california-group-fears-drought-barriers-harm-boating/.
29
Congressional Research Service
10
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
•
It appears the language could alter or obscure the priority of purposes for which
the temporary and operable gates might be employed, particularly for the South
Delta. According to the Delta Watermaster report, the objectives of the South
Delta Temporary Barriers Project are “1) to reduce fisheries impacts by
improving fishery conditions and 2) to increase water levels and improve
circulation patterns in the Southern Delta area for local agricultural diversions.”33
The priority in Section 4(c)(5) would appear to be first “to improve water
quantity and quality for SWP and CVP South-of-Delta water contractors and
other water users,” as such is directed by the section, while species benefits and
in-Delta water quality “should”—but would not have to be—provided (as long as
such is consistent with existing laws and regulations, per Section 4(a)).
Overview of Temporary Barriers
Temporary barriers and operable gates have been considered and used in the Delta for many years. Examples include
Suisun Marsh Salinity Control Gates in the Northern Delta, Delta Cross Channel (DCC) Gates in the Central Delta,
and South Delta Temporary Barriers Project in the Southern Delta. Non-physical barriers have also been employed as
part of pilot projects in the South Delta and North Delta, and operation and modification of existing gates and
barriers have also been under study. Proposals have included widening the DCC gates, dredging near the DCC gates,
automating the DCC gates (i.e., making them operable), and making the South Delta temporary barriers permanent
with operable gates. According to a 2013 report of the Delta Watermaster, the latter proposal was “on hold
indefinitely” pending fisheries studies and agency approvals.
•
Additionally, it is not clear how the barriers and gates could be designed such
that formal Section 7 consultation is not necessary. Temporary gates and operable
barriers could affect listed fish species and potentially affect their habitat, which
presumably could trigger Section 7 consultation (if not covered elsewhere under
CVP operations to which existing BiOps apply). The bill summary
accompanying S. 2016 (which S. 2198 is based upon) states that such barriers
and gates would “help protect the fish in order to allow additional flexibility for
pumping of Delta channels and to improve water quantity and quality for water
users.”34
Section 4(c)(6)(A)
Section 4(c)(6)(A) would direct the head of the FWS and the Commissioner of Reclamation to
complete all necessary NEPA and ESA requirements, within 30 days of receiving a request for a
permit, for final permit decisions on water transfers associated with voluntary fallowing of
nonpermanent crops in the state of California. Reclamation currently has programmatic NEPA
documentation in place for certain CVP transfers, including within-basin transfers and a 25-year
33
Craig M. Wilson, Delta Watermaster, Gates and Barriers in the Delta, California Water Boards, State Water
Resources Control Board, A report to the State Water Resources Control Board and Delta Stewardship Council,
Sacramento, CA, April 2013, p. 6.
34
Senator Feinstein, “California Emergency Drought Relief Act of 2014, Bill Summary,” bill summary for S. 2016,
February, 2014, p. 2: http://www.feinstein.senate.gov/public/index.cfm/files/serve/?File_id=fbdeb35c-1863-47e3-89aa39e7a97b95cd.
Congressional Research Service
11
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
transfer program involving San Joaquin Exchange Contractors south of the Delta, and it is
working on streamlined NEPA documentation for others.35
The transfer process involves both NEPA and the ESA in distinct steps, and where listed species
are involved, appears to take much longer than 30 days. For uncomplicated transfers,
Reclamation completes environmental analysis of water generated by a transfer proposal—taking
into account how much water would have been used by the proposed fallowed crop and whether
such water would have been available to the grower during the current water year. That analysis
generally takes between 30 and 60 days. Upon completion, Reclamation issues a biological
assessment (BA) of the proposed action if it finds its action may affect a listed species, pursuant
to the ESA, thus initiating the consultation process with FWS. FWS then reviews whether the
transfer may jeopardize the continued existence of species protected under the ESA. Reclamation
issues an environmental assessment or environmental impact statement under NEPA.36 Transfer
proposals involving fallowing of crops north of the Delta often require ESA consultation with
FWS due to potential harm to threatened or endangered species, in particular, the giant garter
snake (Thamnophis gigas), whose habitat includes watery areas such as irrigation canals and
ditches and surrounding areas, including rice fields and marshy or wetland areas.37 The
consultation process may take up to 135 days to complete once FWS receives the BA from
Reclamation. According to Reclamation, the agency has been working closely with FWS “to
shorten this process considerably.”38 The result of the 30-day deadline in S. 2198 may be that
FWS might deny permits where a listed species is involved in order to meet the statutory
deadline.
Reclamation issues environmental assessments or environmental impact statements for transfers
under NEPA.39 Under NEPA, Reclamation had expected to issue a finding of no significant
impact (FONSI) for the 2014 water transfer program by the end of April 2014;40 however, it is not
clear from Reclamation’s website if it has done so.41 Reclamation also notes that although water
made available through fallowing is difficult to estimate, some contractors have indicated that
perhaps up to 80,000 acre-feet might be made available from fallowing in 2014.42 Even so,
Reclamation also notes that the current CVP BiOps allow for transfers of water through the Delta
(north to south transfers) only from July through September, but the most demand for such water
south of the Delta is during May and June.
•
It appears that the proposed legislation would shorten the current time period for
completing NEPA and ESA requirements, especially when a listed species is
involved, but it is not clear how much water ultimately might be made available
35
2014 CVP Water Plan, p. 9.
E-mail communication from Reclamation, March 14, 2014.
37
Ibid.
38
Ibid., see also FWS, Sacramento Fish and Wildlife Office, “Species Account, Giant Garter Snake, Thamnophis gigas,
last updated Feb. 27, 2014. The giant garter snake was listed as threatened under the federal ESA on October 20, 1993.
Although the snake’s presence is noted in many counties throughout the CVP service area, including several counties
south of the Delta, “[t]here have been only a few recent sightings of giant garter snakes in the San Joaquin Valley,”
according to the above referenced FWS species account.
39
E-mail communication from Reclamation, March 14, 2014.
40
Ibid. A draft EA was released on March 13, 2014, and is available for public comment for 20 days. (See
https://www.usbr.gov/newsroom/newsrelease/detail.cfm?RecordID=46245.)
41
See http://www.usbr.gov/mp/nepa/nepa_base.cfm?location=ncao.
42
Ibid.
36
Congressional Research Service
12
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
for export from the Delta under the expedited review process. Nor is it clear what
effect the process could have on species habitat and survival.
Section 4(c)(6)(B)
Section 4(c)(6)(B) would direct the head of FWS to allow “any water transfer request associated
with fallowing” to maximize water supplies for non-habitat use, as long as the action would
comply with federal law and regulations.
Section 4(c)(6)(A) directs the head of FWS to allow “any water transfer request associated with
fallowing” to maximize water supplies for non-habitat use, as long as the action would comply
with federal law and regulations.
•
This subsection again appears to be aimed at the garter snake issue in California
related to fallowing; however, it is not explicitly stated, nor is the subsection
identified as only applying to California. There may be other species listings for
which the FWS might need to consult on fallowing of lands. By maximizing (as
long as consistent with laws and regulations) allowance of water transfers for
“non-habitat use,” the provision raises the question of whether it would suggest
prioritization of agricultural, municipal and industrial (M&I), power, or other
uses over water supplies for wildlife refuges, or for rice fields that may support
fish and wildlife while not in production. In other words, does such maximization
result in water reductions for habitat uses?
Section 4(c)(7)
Section 4(c)(7) would direct the Secretaries, as soon as practicable, to participate in, provide
grants to, or provide funding for, under existing authority available to the Secretary of the
Interior, pilot projects to increase water in reservoirs in regional river basins that are experiencing
“extreme, exceptional, or sustained drought.” These basins would have to directly affect the water
supply of California (including the Colorado River basin). Further, the Secretary (it is not
explicitly stated whether this refers to the Secretary of the Interior), with respect to the Upper
Division of the Colorado River, would be participating with or providing funding to the
“respective State” in regards to grants, participation, or funding. (It appears that “State” in this
instance refers to the state with which the Secretary is participating or providing funding.)
•
Section 4(c)(7) appears to be aimed at addressing water supply concerns in the
Colorado River Basin. The basin has experienced decreasing water supplies over
the last 14 years, and many fear it is in danger of reaching levels in Lake Mead
that would trigger implementation of water shortage allocations for Colorado
River water users. Existing authority available to the Secretary of the Interior
might include grants made under the Department’s WaterSMART or other
programs.
Section 4(c)(8)
Section 4(c)(8) would direct the Secretaries to maintain all rescheduled water supplies in San Luis
Reservoir and Millerton Reservoir for the following year, unless unable to do so due to storage
Congressional Research Service
13
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
capacity limitations.43 Rescheduling is currently done under agency guidelines, not as a matter of
law. Under agency guidelines, rescheduled water is released when San Luis Reservoir and
Millerton Lake refill. According to Reclamation, the spill priority is included in agency
guidelines. Such practices can cause operational problems when there are extreme low water
supplies such that Reclamation cannot fill all following-year obligations, including senior water
rights.
•
This provision would address a situation that occurred earlier in the 2014 water
year, whereby Reclamation suggested that 2013 rescheduled water supplies
might not be able to be met because water supplies were not available from San
Luis and Millerton Reservoirs. The uncertainty with such a policy given that it is
in guidelines and not a matter of law is of concern to many water users who forgo
water in one season or part of a season as an investment in the next water year.
The issue relates not just to the opportunity costs of not using that water, but also
to other costs that water contractors incur when they reschedule water. On the
other hand, if rescheduled water is taking up storage space that otherwise might
have been able to hold water for another year, balancing such demands becomes
very difficult.
Section 4(c)(9)(A)
Section 4(c)(9) would direct the Secretaries to “the maximum extent possible ... without causing
land subsidence44 or violating water quality standards” to meet contract water supply needs of
CVP refuges through the use of water conservation measures, water conveyance facilities, and
wells for groundwater resources. To accomplish these activities, the Secretaries would use
funding available under the Water Assistance Program or WaterSMART Program of DOI. Further,
Section 4(c)(9)(B) would redirect a quantity of water obtained from measures in subparagraph
(A) from refuges to CVP contractors.
Currently, multiple state and federally owned wildlife refuges in the Central Valley are served by
surface water contract deliveries and other means (including wells and water purchases) required
under CVPIA. These water supplies are generally divided into two “levels”: Level 2 and Level
4.45 Although Level 4 refuge supplies were directed for certain refuges in 2002 under the CVPIA,
Reclamation has only recently delivered full Level 4 refuge water supplies to refuges.46 Instead,
supplies have been largely limited to Level 2 supplies—422,000 acre-feet.47 Sections 3406(b)(3)
and 3406(d) of CVPIA identify and authorize the use of many options for increasing water supply
for fish and wildlife, including purchases, land fallowing, and project operations modifications.
43
Rescheduling is currently done under agency guidelines, not as a matter of law. Under agency guidelines,
rescheduled water is spilled when San Luis Reservoir and Millerton Lake refill.
44
“Subsidence” refers to the gradual settling or sinking of surface due to subsurface movement of materials, such as
movement of water from underground aquifers resulting from groundwater pumping.
45
CVPIA called for providing water supply to refuges through two sources: Level 2 supplies, which were provided
directly from CVP yield (422,000 acre-feet); and incremental Level 4 supplies, which were to be acquired in addition to
Level 2 and equal the amount of water supplies needed to achieve optimal waterfowl habitat management.
46
While some refuges began receiving full Level 4 water supplies in recent years, 4 of 19 refuges still were unable to
receive Level 4 supplies, according to a 2013 Reclamation Refuge Water Supply Program work plan. Additionally, the
plan notes that 32 of 46 construction projects for refuge water supply had been completed at that time. (See
http://www.usbr.gov/mp/cvpia/docs_reports/meetings/2013/RWSP_AWP_Presentation_Jan172012_DALEfinal.pdf).
47
Ibid.
Congressional Research Service
14
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Further, the Secretary is directed under CVPIA to “endeavor to diversify sources of supply in
order to minimize possible adverse effects upon Central Valley Project contractors.”48
•
This language raises the question of whether it effectively could change
temporarily the priority of CVP water delivery for wildlife refuges under CVPIA,
in that Reclamation would be finding new sources of water for refuges and then
transferring a like-kind of water to CVP contractors. The amount of water for
refuges would still appear to be guaranteed; however, it is not clear that the
quality of water would be the same, even though such activities are not to violate
water quality standards.
•
The provisions would authorize the Secretary to use existing programs to fund
new conservation projects, conveyance facilities, and wells; however, there is no
mention of whether CVP water users would have to pay an additional cost for
water obtained by Reclamation through these new activities. It is possible that
such contractor deliveries would be presumed to be supplementing contract water
supply, for which the cost would be known, but this is not clear. That said, it is
not clear if Reclamation would have the authority to provide the water under
existing contracts from this new source. If Reclamation did not charge to offset
the costs of the new activities, it appears that the provision would essentially be
transferring a new cost for refuge water to the general public. Such an
arrangement does not appear to be any more efficient than Reclamation providing
grants to CVP contractors for conservation measures, water conveyance facilities,
and wells for groundwater resources, all of which are allowed under existing
authorities; however, there could be a conveyance or distributional aspect of such
an arrangement that is not apparent.
Section 4(c)(10)
Section 4(c)(10) would authorize the Secretaries to coordinate with the Secretary of Agriculture
to create an agreement with the National Academy of Sciences to conduct a study on the
effectiveness and environmental impacts of saltcedar tree49 biological control activities and their
effect on increasing water supplies and improving habitat on the Colorado River in California and
elsewhere.
Section 4(c)(11)
Section 4(c)(11) would direct that any WaterSMART grant funding allocated to California be
made available on a “priority and expedited basis”: (1) for emergency drinking and municipal
supplies to meet minimum public health and safety needs; (2) to prevent loss of permanent crops;
(3) to minimize economic losses from drought; and (4) to provide conservation tools and
technology with immediate water supply benefits.50 WaterSMART grants currently are made
available for a host of conservation and efficiency projects with long-term benefits; Reclamation
48
Section 3406(d)(1), 3406(d)(2), and 3406(d)(5) of CVPIA (P.L. 102-575).
Salt Cedar (also known as Tamarix) is an invasive shrub that has been implicated as causing additional stress on
water supplies.
50
Typically, WaterSMART grants are used for a host of conservation and efficiency projects with long-term benefits; it
was not designed as an emergency drought program.
49
Congressional Research Service
15
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
has a separate emergency drought assistance authorization for largely temporary projects, except
in the case of wells.51
•
This provision would apply only to WaterSMART funding allocated to
California. An earlier version of the bill, S. 2016, would prioritize California
projects within all limited funds available through this Reclamation-wide
program.52
Section 4(c)(12)
Section 4(c)(12) would direct the Secretaries to implement “offsite upstream projects” in the
Delta and upstream Sacramento River and San Joaquin River basins in coordination with
California Department of Water Resources and Department of Fish and Wildlife. Projects are to
offset the effects of actions taken under this act on ESA listed species.
•
It appears that this language could apply to a broad range of projects, including
habitat restoration projects. Projects might include habitat restoration, water
quality improvements, storage, or potentially flow adjustments as long as they
offset the effects of other projects that might be implemented under this bill.
Further, it is unclear what “offsite” refers to, both in terms of location and type
and location of projects.53
Section 4(c)(13)
Section 4(c)(13) would direct the Secretaries to use “all available scientific tools” to identify and
implement any changes to the real-time operations of any Reclamation, state, and local water
projects that could result in additional water supplies.
•
This provision raises the question of what scientific tools might be available that
Reclamation is not using or would not have the authority to use under current
law. Note, however, that those changes would have to be consistent with law and
regulations per Sections 4(a) and 4(c). Thus, it is uncertain how this provision
adds to existing authorities or practices. Also, although most of the subsections in
4(c) clearly apply to California, this subsection does not explicitly indicate such.
Section 4(d). Other Agencies
Section 4(d) states that the provisions of Section 4 shall apply to all federal agencies that have a
role in approving projects in Sections 4(a) and 4(c) of this bill. Thus, although not specifically
mentioned, if the Corps of Engineers or another agency has a permitting or approval role in one
of the projects that could be implemented under Section 4, the provisions of Sections 4(a) and
4(c) would also apply to that agency.
51
The Reclamation States Emergency Drought Relief Act.
The enacted WaterSMART program appropriation for FY2014 is $48.9 million. The President’s request for FY2015
is $52.0 million. See http://www.usbr.gov/budget/2015/FY%202015%20Reclamation%20Budget%20Justifications.pdf,
p. Water and Related Resources – 3.
53
For example, it is not clear if “offsite” implies outside the Delta or would include projects such as the “offstream”
project under study by Reclamation for Sites Reservoir, a new storage reservoir north of the Delta.
52
Congressional Research Service
16
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Section 4(e). Accelerated Project Decision and Elevation54
Section 4(e) would direct federal agencies, upon request of the state of California, to use
“expedited procedures under this subsection” to make final decisions related to federal projects or
operations that would provide additional water or address emergency drought conditions under
Sections 4(a) and 4(c). Pursuant to Section 4(e)(2), after receiving a request from the state, the
head of an agency referred to in Section 4(a), or the head of another federal agency responsible
for reviewing a project, the Secretary of the Interior would be required to convene a “final project
decision meeting” with the heads of all relevant federal agencies “to decide whether to approve a
project to provide emergency water supplies.” After receiving a request for resolution, the
Secretary would be required to notify the heads of all relevant agencies of the request for
resolution, the project to be reviewed, and the date of the meeting. The meeting would need to be
convened within seven days of the request for resolution. Not later than 10 days after that meeting
is requested, Section 4(e)(4) would require the head of the relevant federal agency to issue a final
decision on the project. Under Section 4(e)(5), the Secretary of the Interior would be authorized
to convene a final project decision meeting at any time, regardless of whether a request for
resolution is requested under 4(e)(2).
The accelerated project decision and elevation provisions would not mandate federal agency
approval of a project. Instead, they would establish procedures to expedite the federal agency
process for deciding whether to approve a project. As a result, it would appear that agencies could
decide not to approve a project. Unlike several other provisions in Section 4, this provision would
not expire at the time when the drought emergency declaration is withdrawn.
•
This subsection would appear to apply to a broad set of projects and operations,
as long as such are requested by the state or agency heads for final approval.
Specifically, it appears that this subsection could supersede regular processes for
final project decisions under various laws, including but not limited to NEPA and
ESA. However, Section 4(a) notes that actions are to be consistent with current
laws and regulations, and Section 4(b) would provide other limitations. Thus, it is
not clear how this provision would be implemented.55
•
Given the short timeframe for deciding whether to approve the project—10 days
from the request of the state or agency heads—it is difficult to determine whether
a state or agency head may make a request for resolution for a project unless or
until that project complies with applicable law.
•
Also, a final decision related to a project pursuant to Sections 4(a) and 4(c)
would be subject to the meetings convened by the Secretary instead of the
traditional processes established by the federal agencies. The specific process for
approving or not approving a project is not provided in the bill and therefore
raises the question of how final project decisions would be made (e.g., by
consensus, majority vote, etc.).
•
Presuming that a meeting could be requested as soon as a project is submitted, it
is uncertain how much analysis of a project could be done within the 10-day time
54
The summary of this subsection was prepared by (name redacted), CRS Analyst in Environmental Policy. (name red
acted), CRS Legislative Attorney, also contributed to this section.
55
For legal questions related to how this process might differ from current practice, please contact (name redacted),
CRS Legislative Attorney, at 7-.....
Congressional Research Service
17
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
frame to approve a project. A question to consider is, if not enough time is
provided to make a decision, could the meeting result in a default rejection of the
project?
Section 5. Emergency Environmental Reviews56
Section 5 would direct the “head of each applicable Federal agency” to consult with the Council
on Environmental Quality (CEQ)57 to develop “alternative arrangements” to comply with NEPA
in accordance with existing regulations “during the emergency.”
Emergency environmental review provisions in Section 5 could affect how certain emergency
federal and federally funded drought projects in California would be required to demonstrate
compliance with NEPA. Broadly speaking, NEPA requires federal agencies to identify and
consider the environmental impacts of a proposed federal action before a final agency decision is
made on that action. In doing so, NEPA intends to inform the federal decision-making process
with regard to agency actions that would affect the environment.
Emergency compliance arrangements are currently allowed in existing CEQ regulations
implementing NEPA.58 These regulations provide that an agency may seek such alternative
arrangements when an emergency makes it necessary to take “an action with significant
environmental impact.”59 Section 5 would apply in California only while the governor’s drought
emergency declaration is in effect. It is difficult to identify whether and/or to which projects such
alternative arrangements would apply. For example, there is some question as to whether the
projects and operations mandated in Section 4(c) would require review under NEPA. Although
the statute is not explicitly repealed, and courts disfavor repeals by implication, courts have found
that where a law gives no discretion to an agency, NEPA does not apply. The theory is that if the
NEPA review would not inform agency decision making—because the actions are strictly
mandated by Congress—NEPA does not apply. In making such a determination, a court would
consider whether a federal agency had control over the action. Some of the Section 4(b) mandates
are very specific (e.g., the mandated 1:1 inflow-to-export ratio for the increased flow of the San
Joaquin River in Section 4(c)(4)). It is possible that the specificity of this action could lead a court
to decide that the agency lacked discretion and that a NEPA review was not required. Other
federal and state environmental laws may still apply, however.
•
Regardless of whether NEPA applies or how NEPA compliance must be
demonstrated, an agency would still be required to determine whether the
project’s impacts would require compliance with state or federal environmental
requirements established under other laws, regulations, or executive orders. That
is, even if compliance with NEPA were not required, the actions required or
funded under S. 2198 would need to be consistent with applicable requirements
such as those established under the ESA or state and federal water quality laws,
56
Summary of Section 105 was prepared by (name redacted), Analyst in Environmental Policy, CRS Resources, Science,
and Industry Division. (name redacted), Legislative Attorney in the CRS American Law Division, also contributed
to this section.
57
This is to be done in accordance with 40 CFR §1506.11, including successor regulations.
58
40 C.F.R 1506.11.
59
Ibid.
Congressional Research Service
18
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
among others. The language raises the question as to how such consistency could
be demonstrated, and at what point that burden of demonstration would cease.
Section 6. State Revolving Funds60
Section 6 addresses California’s use of monies in its State Revolving Fund programs that assist
wastewater and drinking water infrastructure projects, pursuant to the federal Clean Water Act
(CWA) and the federal Safe Drinking Water Act (SDWA), respectively. The SRFs provide loans
and other types of financing assistance under specific terms set by California and other states. S.
2198 adds no new or supplemental funding for California’s SRF programs. Rather, S. 2198 would
direct the Environmental Protection Agency (EPA) Administrator, when allocating SRF funds, to
require that the state of California review and give priority to projects that will “provide
additional water supplies most expeditiously to areas that are at risk of having inadequate supply
of water for public health and safety purposes or to improve resiliency to drought.”
For projects in California that are awarded assistance pursuant to Section 6, the bill would direct
the EPA Administrator to expedite review of Buy American waiver requests, if such requests are
submitted, and it authorizes 40-year loan repayments to the SRFs. Under both of the SRF
programs, loans are normally to be repaid to a state within 20 years, but terms may be extended to
30 years in cases such as economically disadvantaged communities.
Finally, the bill provides that nothing in Section 6 authorizes EPA to modify existing state-bystate funding allocations, funding criteria, or other requirements related to the CWA and SDWA
SRF programs for the state of California.
•
The bill does not appear to add new types of project eligibility under the SRF
programs. Instead, it appears intended to direct the state’s priorities when
awarding assistance among projects that already are SRF-eligible. These could
include water recycling projects (e.g., recycled water treatment works and
recycled water distribution systems) and water conservation measures, which
currently are eligible under the state’s clean water SRF program. It also could
include source water and water storage projects that address the state’s public
health priorities, which are eligible under California’s drinking water SRF
program.
•
The California agencies that administer the SRF programs have well-established
procedures for identifying and prioritizing projects eligible for assistance.
Intended Use Plans are prepared annually and are open to public participation.
While the apparent intention of this section of S. 2198 is to provide funds
expeditiously, it is unclear how quickly this could occur, in light of the state’s
existing priorities.
Under Section 8 of the bill, the authority under Section 6 would expire when a state-declared
drought declaration is suspended by the governor.
60
The summary of Section 106 was prepared by (name redacted), Specialist in Resources and Environmental Policy,
CRS Resources, Science, and Industry Division.
Congressional Research Service
19
Analysis of Senate-Passed S. 2198: Emergency Drought Relief Act of 2014
Section 7. Effect on State Laws
Section 7 of S. 2198 states that nothing in the act would preempt any California state law in effect
on the date of such enactment, including area-of-origin and other water rights protections.
Section 8. Termination of Authorities.
Section 8 states that authorities under Section 4(a); Section 4(c), subsections (1) through (6), (8)
and (9), and (11) through (13); Section 5; and Section 6 would permanently expire when the
governor of the state suspends the drought emergency declaration.
Author Contact Information
(name redacted)
Specialist in Natural Resources Policy
[redacted]@crs.loc.gov, 7-....
(name redacted)
Specialist in Natural Resources Policy
[redacted]@crs.loc.gov, 7-....
Acknowledgments
The authors would like to acknowledge and thank (name redacted), (name redacted), (name redacted), (name
redacted), and Charles Stern for their assistance in producing this report.
Congressional Research Service
20
EveryCRSReport.com
The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the
Library of Congress, charged with providing the United States Congress non-partisan advice on
issues that may come before Congress.
EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The
reports are not classified, and Members of Congress routinely make individual reports available to
the public.
Prior to our republication, we redacted names, phone numbers and email addresses of analysts
who produced the reports. We also added this page to the report. We have not intentionally made
any other changes to any report published on EveryCRSReport.com.
CRS reports, as a work of the United States government, are not subject to copyright protection in
the United States. Any CRS report may be reproduced and distributed in its entirety without
permission from CRS. However, as a CRS report may include copyrighted images or material from a
third party, you may need to obtain permission of the copyright holder if you wish to copy or
otherwise use copyrighted material.
Information in a CRS report should not be relied upon for purposes other than public
understanding of information that has been provided by CRS to members of Congress in
connection with CRS' institutional role.
EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim
copyright on any CRS report we have republished.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.