Everglades Restoration: Federal Funding and Implementation Progress

Congressional research reportOct 6, 2017

Ask Donna

What actually matters in this document.

Text

Everglades Restoration: Federal Funding and

Implementation Progress

,name redacted,

Specialist in Natural Resources Policy

October 6, 2017

Congressional Research Service

7-....

www.crs.gov

R42007

Everglades Restoration: Federal Funding and Implementation Progress

Summary

The Everglades is a unique network of subtropical wetlands in South Florida that is

approximately half of its historical size, due in part to degradation from federal water projects

built by the U.S. Army Corps of Engineers (the Corps). In 2000, Congress authorized a plan,

termed the Comprehensive Everglades Restoration Plan (CERP), as a comprehensive framework

for the restoration of the Everglades ecosystem in southern Florida. When originally authorized, it

was estimated that CERP would cost a total of $8.2 billion and take approximately 30 years to

complete. More recent estimates indicate that the plan will cost $16.4 billion and will take

approximately 50 years to implement. At issue for Congress is oversight and implementation of

this commitment.

Under CERP, the federal government (through the Corps and various bureaus within the

Department of the Interior) is required to fund half of the costs for restoration, with an array of

state, tribal, and local agencies paying the other half. In addition to activities under CERP, a

number of ongoing federal and state efforts that predate CERP (known collectively as “nonCERP” or “Foundation” activities) also factor into Everglades restoration. Although non-CERP

efforts technically are not part of CERP, the two sets of activities are widely viewed as

complementary.

Since passage of CERP in 2000, the federal investment in Everglades restoration has increased.

As of the end of FY2016, the federal government had provided in excess of $1.2 billion in

funding for CERP, with the state providing matching funds for CERP projects, as well as

advanced funding for land acquisition and construction for expected future CERP projects.

Federal funding for non-CERP activities has also continued over this period. Together with

CERP, all federal Everglades restoration efforts are estimated to have totaled in excess of $5

billion from FY1993 to FY2016. While estimates of nonfederal funding contributions to CERP

vary depending on what methodology and assumptions are used, observers agree that to date, the

state of Florida has spent more on Everglades restoration than has the federal government.

Although overall progress has fallen short of initial timelines, progress has been made on a

number of Everglades restoration projects. The majority of the land necessary for restoration

projects under CERP has been acquired, and significant progress has been made on non-CERP

activities (including improved water deliveries to Everglades National Park). Of the nine CERP

projects that had been authorized by the end of 2016 (not including pilot projects), construction

was ongoing or complete at eight projects and studies were completed or under way for a number

of other projects. Despite this progress, some projects have seen setbacks in the form of schedule

delays and cost escalations. Assuming that the plan does not change significantly and most of the

50 projects included in the original CERP plan are eventually required to complete the effort,

many new authorizations and significant additional funding would be necessary. Reviewers of the

restoration program have pointed out that at current rates of project authorization and funding,

additional delays would be likely.

Reductions to state funding and the enactment of new CERP project authorizations in 2014 and

2016 legislation have brought renewed attention to Everglades restoration. Restoration of the

Everglades is one of the largest and most mature efforts of its kind; thus, debate and resolution of

Everglades restoration issues has implications not only for South Florida but also for large-scale

restoration initiatives elsewhere. This report provides an overview of the federal role in

Everglades restoration. It discusses background, funding history, and major accomplishments and

challenges to date in federal efforts to restore the Everglades.

Congressional Research Service

Everglades Restoration: Federal Funding and Implementation Progress

Contents

Introduction ..................................................................................................................................... 1

Everglades Restoration Background: CERP and Non-CERP Projects ............................................ 2

Funding for Everglades Restoration ................................................................................................ 3

DOI Funding ............................................................................................................................. 4

U.S. Army Corps of Engineers Funding ................................................................................... 5

Funding Trends.......................................................................................................................... 5

Comparing Federal and State CERP Funding ........................................................................... 6

Implementation Progress and Challenges ....................................................................................... 8

Reporting ................................................................................................................................... 8

Status and Accomplishments..................................................................................................... 8

Land Acquisition, Pilot Efforts, Non-CERP Projects ......................................................... 9

Generation 1 CERP Projects ............................................................................................. 10

Generation 2 CERP Projects ............................................................................................. 10

Generation 3 CERP Projects ............................................................................................. 10

Ongoing Planning .............................................................................................................. 11

Challenges ................................................................................................................................ 11

Figures

Figure 1. Corps/DOI Appropriations for Everglades Restoration ................................................... 6

Tables

Table 1. Comparison of Estimated Comprehensive Everglades Restoration Plan (CERP)

Completion Costs, 1999-2014 ...................................................................................................... 2

Table 2. Corps and DOI Funding for Everglades Restoration, FY2010-FY2018 ........................... 4

Table 3. Status of Major CERP Projects .......................................................................................... 8

Contacts

Author Contact Information .......................................................................................................... 13

Congressional Research Service

Everglades Restoration: Federal Funding and Implementation Progress

Introduction

The Florida Everglades is a unique network of subtropical wetlands that is currently half its

historical size. The federal government has a long history of involvement in the Everglades,

beginning in the 1940s with the U.S. Army Corps of Engineers (the Corps) constructing flood

control projects that shunted water flowing south into the Everglades to make way for agricultural

and urban development. Other factors, including major nonfederal development efforts, also have

contributed to shrinking and altering the Everglades ecosystem.

In recognition of the unique nature of the Everglades, federal and state agencies began ecosystem

restoration activities in the Everglades in the early 1990s, and many of these activities are

ongoing. However, it was not until 2000 that federal and state restoration activities were

coordinated under an integrated plan. In the Water Resources Development Act of 2000 (WRDA

2000; P.L. 106-541), Congress approved the Comprehensive Everglades Restoration Plan (CERP)

as a framework for Everglades restoration. In addition to the CERP framework and related

processes, the WRDA 2000 authorized an initial round of projects with federal participation by

the Corps and the Department of the Interior (DOI). The plan envisioned 50 major projects to

restore the quantity, quality, and timing of water deliveries in south Florida to historical

conditions. According to the process established under CERP, Everglades restoration projects are

to be studied and presented to Congress for authorization as their planning is completed

(presumably in water resources development acts, typically referred to as WRDAs). Since

passage of CERP, nine non-pilot CERP projects have been authorized. Other projects are ongoing

in the study phase (including projects that have completed the study phase and are awaiting

congressional authorization).

Most observers agree that, although progress has been made on Everglades restoration, much

more time and funding would be required to achieve restoration as currently contemplated.

Previously, some have highlighted what they consider to be the “slow” pace of restoration as an

argument for increased and expedited financial support. Conversely, others have argued that

restoration activities in the Everglades receive too much funding relative to other priorities, and

that the level of support provided for these activities is not appropriate given larger fiscal

concerns and the uncertainty of results.

At issue for Congress is oversight and implementation of efforts to restore the Everglades,

including the ongoing federal funding commitment and the priority of Everglades restoration

relative to other federal commitments. Stakeholders involved with planning other large-scale

restoration initiatives (e.g., Great Lakes, Chesapeake Bay) look to the Everglades as a model and

a test case. The achievements realized and challenges faced in Everglades restoration efforts may

provide additional information on the possibilities and limitations inherent to all large-scale

ecosystem restoration efforts.

This report provides information on Everglades restoration, with a focus on the federal role in

funding this restoration and related issues for Congress. The report discusses background, trends,

and major accomplishments and challenges to date in federal efforts to restore the Everglades.

Congressional Research Service

1

Everglades Restoration: Federal Funding and Implementation Progress

Everglades Restoration Background:

CERP and Non-CERP Projects

Federal efforts to restore the Everglades are often divided into two broad categories: CERP and

non-CERP (or “Foundation” projects). CERP efforts refer to projects and programs authorized in

the Comprehensive Everglades Restoration Plan, enacted in WRDA 2000. Non-CERP refers to

the subset of federal Everglades restoration activities that were not enacted in CERP (many of

these efforts predate CERP). CERP considered and assumed implementation of a number of nonCERP projects; thus, both efforts are considered to be complementary.

Federal CERP funding was first authorized in WRDA 2000, with a focus on increasing storage

and treatment of excess water in the rainy season to provide more water during the dry season for

the Everglades ecosystem and for urban and agricultural users. In the original documents

presented to Congress in 1999, CERP was expected to consist of 50 projects and was estimated to

cost $8.2 billion (in 1999 dollars) to complete. Over time, the reported funding requirement to

complete the projects has increased, although some of this increase has been due to inflation (see

Table 1, below). As of 2014 (when the total cost estimate was last updated), the Corps estimated

that completing construction of CERP projects would take more than 50 years and would cost

$16.4 billion.1 Approximately 60% of $8.2 billion (rounded) in cost increases from 1999 to 2014

were attributed to inflationary increases, and the remainder has been attributed to other factors.

Table 1. Comparison of Estimated Comprehensive Everglades Restoration Plan

(CERP) Completion Costs, 1999-2014

(in billions of dollars)

Total Reported Cost

(Estimate)

Increase over

Previous Estimate

Attributed to

Inflation

Increase over

Previous Estimate

Attributed to

Noninflationary

Changes

Original (1999) Estimate

$8.2

—

—

2004 Update

10.9

1.6

1.1

2009 Update

13.5

2.0

0.6

2014 Update

16.4

1.0

2.2

Source: CRS estimates based on 2005, 2010, and 2015 CERP Reports to Congress.

Notes: CERP reports to Congress typically update the estimated total costs for Everglades restoration in

current-year dollars based on information available at the time of the report. This table shows how much of the

cost increase over time has been due to inflationary factors compared to other factors (project scope, etc).

Pursuant to CERP, project construction costs are shared 50/50: the federal government is required

to pay half of project costs, and an array of state, tribal, and local agencies (i.e., nonfederal

1

This figure represents the estimated cost to the federal government in October 2014 dollars according to the Corps.

See U.S. Army Corps of Engineers, Comprehensive Everglades Restoration Plan, 2015 Report to Congress, at

http://evergladesrestoration.gov/content/cerpreports/cerp_2015_rpt_to_congress.pdf. Hereinafter 2015 CERP Report to

Congress.

Congressional Research Service

2

Everglades Restoration: Federal Funding and Implementation Progress

sponsors) must pay the other half.2 The same cost share applies to all project operation and

maintenance costs.

WRDA 2000 included initial projects (including pilots), established the aforementioned costsharing ratios and created a process for additional projects to be authorized as part of the CERP

framework. Subsequent legislation has built on this: WRDA 2007 authorized three additional

CERP projects; four other projects completed the study phase between 2007 and 2014 and were

thus authorized for construction in the Water Resources Reform and Development Act of 2014

(WRRDA 2014; P.L. 113-121); and two other CERP projects were authorized in the Water

Infrastructure Improvements for the Nation Act (WIIN Act; P.L. 114-322), enacted on December

16, 2016. The status of these projects is discussed later in this report.

Federal Everglades restoration activities not authorized under CERP are often referred to as “nonCERP” or “Foundation” activities. Most (but not all) of the authorities for this funding predate the

enactment of CERP in 2000. For example, this category includes funding for the Modified Water

Deliveries Project that originally was authorized under the Everglades National Park Protection

and Expansion Act of 1989 (P.L. 101-229).3 Depending on how broadly the non-CERP category

is defined, it can encompass a wide variety of Everglades restoration activities undertaken by

multiple agencies. Similar to CERP funding, non-CERP activities of the Department of the

Interior and the Corps typically receive much attention and are often the focal point of

congressional consideration. Unlike for CERP, there is no statutorily required cost-share split for

non-CERP projects.

Funding for Everglades Restoration

Federal funding for Everglades restoration is largely provided through DOI and the Corps and is

concentrated in two annual appropriations bills—the Interior and Environment appropriations bill

(which provides funds for much of DOI) and the Energy and Water Development appropriations

bill (which funds the Corps). Additional funding in other appropriations bills is sometimes noted

as contributing to Everglades restoration, but is not formally tracked under the Administration’s

non-CERP totals.4

Although the Administration’s budget request typically identifies restoration funding totals for

CERP and non-CERP for both DOI and the Corps, appropriations laws and conference reports

typically do not tabulate and specify their recommended appropriations levels for Everglades

restoration activities (for either CERP or non-CERP totals). Rather, these totals are embedded

within project and account-level totals of the Corps and DOI. A summary of funding for DOI and

Corps CERP and non-CERP activities in recent years is shown in Table 2.

2

Section 101 of WRDA 1986 (P.L. 99-662) requires that local sponsors pay the costs for land, easements, relocation,

and rights-of-way for its projects. After a project cost-share agreement is certified by the Corps, these costs may be

credited toward the overall nonfederal share of project costs.

3

This project is expected to augment flows to Everglades National Park. For more information, see National Park

Service, “Modified Water Deliveries (MWD),” at http://www.nps.gov/ever/learn/nature/modwater.htm.

4

In addition to the Corps and DOI, the South Florida Ecosystem Restoration Task Force also tracks funding provided

to other federal agencies, including the National Oceanic and Atmospheric Administration, the U.S. Environmental

Protection Agency, and the U.S. Department of Agriculture, among others. However, in its annual budget request, the

Administration typically only cites funding for the Corps and DOI under the designation of “non-CERP” Everglades

restoration funding. For additional information, see Everglades crosscut budget documents available at

http://www.sfrestore.org/documents/index.html.

Congressional Research Service

3

Everglades Restoration: Federal Funding and Implementation Progress

Table 2. Corps and DOI Funding for Everglades Restoration, FY2010-FY2018

(in thousands of dollars)

FY2011

FY2012

FY2013

FY2014

FY2015

FY2016

FY2017

Proposeda

FY2018

Proposed

DOI

70,600

99,884

66,355

70,452

62,272

64,429

63,000

54,000

CERP

8,401

8,347

7,883

8,376

8,408

7,934

8,000

8,000

NonCERP

62,199

91,537

58,472

62,076

53,864

56,495

55,000

46,000

Corps

131,066

142,486

96,008

47,616

68,551

94,045

106,000

76,000

CERP

79,860

57,886

76,212

38,499

61,001

69,970

75,000

75,000

NonCERP

41,108

84,600

19,796

9,117

7,550

24,075

31,000

1,000

Total

201,666

242,370

158,683

118,068

130,823

188,000

169,000

130,000

Source: Congressional Budget Justifications for the U.S. Department of the Interior and the U.S. Army Corps of

Engineers, South Florida Ecosystem Restoration Crosscut Budget Report for FY2017.

Note: Unless otherwise indicated, funding levels are actual amounts.

a. FY2017 enacted levels were not available as of the FY2018 budget release.

DOI Funding

Everglades restoration funding within the Department of the Interior, Environment, and Related

Agencies Appropriations bill is generally allotted to four agencies within DOI:

the National Park Service (NPS),

the Fish and Wildlife Service (FWS),

the U.S. Geological Survey (USGS), and

the Bureau of Indian Affairs (BIA).

Within these agencies, two types of Everglades funding are often highlighted in appropriations

debates: funding for CERP and funding for the Modified Water Deliveries Project for Everglades

National Park (also known as the Mod Waters project). Mod Waters is a non-CERP project that

has received significant attention from Congress. It aims to improve water deliveries to

Everglades National Park by removing barriers in and around the Tamiami Trail.5 Although Mod

Waters is technically a non-CERP project, it is widely considered to be a keystone project for

Everglades restoration, with an important nexus to CERP.

DOI’s CERP funding largely goes to NPS and FWS to carry out CERP project activities related to

NPS and FWS units (e.g., national parks, wildlife refuges) and authorities that fall under CERP.

Non-CERP DOI Everglades restoration funding provides for a number of different activities in

addition to the Mod Waters project. These activities include management of national parks and

national wildlife refuges in the Everglades, research and monitoring, implementation of relevant

laws in the Everglades such as the Endangered Species Act (16 U.S.C. §§1531-1544) and the

Migratory Bird Treaty Act (16 U.S.C. §§703-712), and BIA funding for the Seminole and

5

Water deliveries refer to flows into Everglades National Park. Efforts to raise portions of the Tamiami Trail (a

highway running east to west across the Everglades that blocks the southward flow of water) are considered a linchpin

in efforts to increase the water flowing from north to south (i.e., into Everglades National Park).

Congressional Research Service

4

Everglades Restoration: Federal Funding and Implementation Progress

Miccosukee to carry out water- and ecosystem-related planning and studies. Non-CERP DOI

funding also includes operations of the South Florida Ecosystem Restoration Task Force, which

supports DOI, the Corps, and the state of Florida in carrying out Everglades restoration. The

FY2018 Trump Administration request for DOI bureaus receiving Everglades restoration funds

was $54 million. That included $8 million for CERP projects and $46 million for non-CERP

projects.

U.S. Army Corps of Engineers Funding

Corps funding is directed toward planning and construction of projects authorized under CERP

and other authorities. Within Corps totals, the amount allocated to CERP projects (i.e., CERP

projects that have been authorized for construction) is widely considered a key benchmark for

Everglades restoration commitment and progress. Corps non-CERP restoration projects include

those projects for which authorization predates CERP. The most prominent recent example is the

ongoing construction of the Kissimmee River Restoration Project,6 as well as operations and

maintenance of other non-CERP projects.

Funding for Corps Everglades restoration projects in the Energy and Water Development

appropriations bill is listed under South Florida Ecosystem Restoration within the Corps

Construction and Operations and Maintenance accounts. The FY2018 requested level for Corps

Everglades restoration funds was $76 million, including $75 million for CERP activities and $1

million for non-CERP activities.7 Previous drops in funding have been attributed to a number of

factors, including the availability of unobligated funds from prior years and the drawdown of

funding for authorized, ongoing construction projects.

Funding Trends

The federal government has provided funding for restoration of the Everglades since the early

1990s. Overall, from FY1993 to FY2016, the total federal investment in Everglades restoration

(including agencies other than the Corps and DOI) is estimated to have exceeded $5 billion. From

FY1993 through FY2000 (i.e., prior to the enactment of CERP), federal appropriations for

Everglades restoration activities totaled more than $1.2 billion. More recently, since the

enactment of CERP in WRDA 2000 through FY2015, total federal funding from all agencies has

exceeded $4 billion, with Corps and DOI accounting for approximately 75% of that total, or

approximately $3 billion.8 CERP projects accounted for approximately $1.1 billion of this

funding.

As previously noted, Everglades funding for the Corps and DOI typically receives much attention

from Congress. Table 2, above, shows the split of CERP and non-CERP totals between the two

agencies since 2010. Although overall funding for Everglades restoration by the Corps and DOI

has ranged between roughly $125 million and $250 million in most years since the enactment of

CERP, the distribution between CERP and non-CERP funding has changed over time (Figure 1).

CERP projects gradually increased from FY2001 to FY2010, including significant increases

6

In the past, the Corps has also received funding to implement the Mod Waters project, although in recent years this

money has been provided to DOI.

7

The FY2018 request for the Corps included funding to continue construction on two ongoing CERP projects

(Picayune Strand and Indian River Lagoon-South) authorized in WRDA 2007, as well as funding for pre-construction

work on the four CERP projects authorized in WRRDA 2014.

8

CRS analysis of departmental data for FY1993-FY2014.

Congressional Research Service

5

Everglades Restoration: Federal Funding and Implementation Progress

under P.L. 111-5 (the American Recovery and Reinvestment Act). Over the same period, funding

for non-CERP projects (such as Mod Waters) decreased from earlier levels. In recent years,

overall appropriations in both categories have decreased.

In most enacted appropriations bills since passage of CERP, Congress has agreed to the

Administration’s funding request for the Everglades. The fluctuations in funding levels over time

can be attributed to a number of factors. For instance, after authorization in FY2007, federal

funding for “Generation 1” CERP projects (i.e., projects authorized in WRDA 2007) increased as

project construction commenced after years of study and pilot projects; these funding levels

began to decline in FY2012 as Generation 1 project construction activities wound down and

“Generation 2” projects (i.e., projects with completed project-implementation reports that were

proposed and eventually authorized in WRRDA 2014) were awaiting construction authorization.

For non-CERP funding trends, more recent decreases in funding can be attributed in part to the

completion of the initial phases of construction on the Mod Waters project.

Figure 1. Corps/DOI Appropriations for Everglades Restoration

(CERP and non-CERP funding split)

Source: CRS estimates based on Corps and Department of the Interior (DOI) budget data.

Notes: Does not include agency funding for activities outside of the Corps and DOI. Appropriated funding may

differ from actual spending (due to transfers, etc.). FY2010 includes additional funding under P.L. 111-5 (the

American Recovery and Reinvestment Act).

Comparing Federal and State CERP Funding

Many Everglades restoration supporters view the status and amount of federal CERP funding

relative to nonfederal funding for restoration activities under CERP as an important indicator of

the federal government’s commitment to Everglades restoration. While there is widespread

Congressional Research Service

6

Everglades Restoration: Federal Funding and Implementation Progress

agreement that the state has invested more funding in CERP than has the federal government,

comparisons between federal and state funding levels for Everglades restoration are complicated

for a number of reasons.

CERP project costs must be shared equally between the federal government and project sponsors.

Further, pursuant to general Corps policies under Section 101 of WRDA 1986 (P.L. 99-662), all

local project sponsors must fund the costs for project lands, easements, relocations, right-of-way,

and disposal sites. As a result, a considerable amount of nonfederal funding for Everglades

restoration has been expended by the state of Florida for land acquisition related to the expected

“footprint” of future CERP projects. Although nonfederal CERP funding is widely acknowledged

to be considerable (and by most accounts exceeds federal funding), it has in some cases

anticipated details of future projects that have yet to be federally approved and designed in detail

by the Corps.9

Although some estimates reference large nonfederal contributions toward CERP, estimates of

expenditures that have been formally credited toward CERP’s nonfederal share are typically

smaller. For instance, in 2015 the state of Florida estimated that it had spent $2 billion toward

implementing CERP.10 At the same time, actual credited nonfederal expenditures through 2014

were reported to be $1.05 billion in the 2015 CERP Report to Congress.11 Although some amount

of nonfederal expenditures that have yet to be credited to CERP are expected to be counted

eventually, it is possible that not all of these funds may be credited toward CERP cost shares.

In recent years, the state of Florida’s funding of CERP has decreased due to a number of factors,

including a decline in state tax revenues and a focus on other aspects of Everglades restoration.

For instance, the state has increased its funding for projects under its Restoration Strategies

Regional Water Quality Plan, which is intended to address EPA narrative and numeric nutrient

criteria in the Everglades imposed under the Clean Water Act (33 U.S.C. §§1251 et seq.).12 It is

unclear whether state funding for CERP will return to previous levels at some point in the future.

Previous estimates indicated that approximately $584 million in previous state expenditures

would become “available” for crediting when “Generation 2” projects were authorized by

Congress (as occurred in June 2014). Assuming no major influx of new funding by the state of

Florida in the near future, the status of federal authorizing legislation for subsequent Everglades

restoration projects (in particular those subject to prior spending by the state) may receive added

attention.

9

Funding is not formally “credited” by the Corps toward CERP project cost shares until a number of requirements have

been met. These requirements include completion of a project implementation report (PIR) and authorization for

construction of the project by Congress, as well as signing of a project partnership agreement.

10

South Florida Water Management District, “Quick Facts on Everglades Restoration Progress,” January 2016, at

https://www.sfwmd.gov/sites/default/files/documents/spl_everglades_progress.pdf. Hereinafter, “SFWMD Everglades

Restoration Fact Sheet.” Over this time period, the federal government estimates that it spent $1.2 billion on CERP.

11

2015 CERP Report to Congress, p. 38.

12

These efforts, which began in 2012, are being undertaken in response to a court-ordered Amended Determination by

the EPA. For more information on the Clean Water Act, see CRS Report R42752, Clean Water Act and Pollutant Total

Maximum Daily Loads (TMDLs), by (name redacted) .

Congressional Research Service

7

Everglades Restoration: Federal Funding and Implementation Progress

Implementation Progress and Challenges

Reporting

Congress has mandated multiple reports to regularly evaluate Everglades restoration. Independent

review of Everglades restoration was required in WRDA 2000. As a result, the National

Academies of Sciences, Engineering, and Medicine’s Committee on Independent Scientific

Review of Everglades Restoration Progress (CISRERP) was formed in 2004. Since this time, the

committee has published biennial reviews of Everglades restoration (including both CERP and

non-CERP projects). The most recent report was released in 2016.13 Separately, WRDA 2000 also

required a report, authored jointly by the Corps and DOI, which focuses specifically on CERP

implementation and is published every five years. The most recent of these reports was completed

in 2015.14 Both reports outline accomplishments and challenges related to CERP and non-CERP

projects. Finally, a report by the South Florida Ecosystem Restoration Task Force (a joint

state/federal/tribal governance entity established in WRDA 1996) publishes a biennial strategy

and report on restoration accomplishments.15

Status and Accomplishments

Progress has been made on Everglades restoration for both CERP and non-CERP projects. For

CERP activities, significant accomplishments have included the construction of a number of pilot

projects, the completion of studies, and the initiation of multiple construction projects. Table 3,

below, shows the status of recent major CERP projects. Additionally, some non-CERP projects

are complete or nearing completion, whereas others are ongoing. In addition to progress on the

construction of projects, baseline information and processes also have been established and the

scientific understanding of many of the issues associated with Everglades restoration has

improved significantly since initial enactment of CERP.16

Table 3. Status of Major CERP Projects

Project Name

Construction

Authorization (Public Law)

Project Status

Melaleuca Eradication

WRDA 2000 (P.L. 106-541)

Complete

Site 1 Impoundment

WRDA 2007 (P.L. 110-114)

Under Construction

Picayune Strand

WRDA 2007 (P.L. 110-114)

Under Construction

Indian River Lagoon-South

WRDA 2007 (P.L. 110-114)

Under Construction

C-43 West Storage Basin

WRRDA 2014 (P.L. 113-121)

Under Construction

C-111 Spreader Canal

WRRDA 2014 (P.L. 113-121)

Under Construction

13

Committee on Independent Scientific Review of Everglades Restoration Progress, National Research Council,

Progress Toward Restoring the Everglades: The Sixth Biennial Review, Washington, DC, 2016. Hereinafter referred to

as the Sixth Biennial Review.

14

2015 CERP Report to Congress.

15

These reports are available at http://www.evergladesrestoration.gov/content/Strategic_Plan_Biennial_Report.html.

16

For example, since enactment of CERP, research on aquifer storage projects has revealed that the potential for these

projects to provide storage is less than was initially assumed. For more information, see “Challenges” section below.

Congressional Research Service

8

Everglades Restoration: Federal Funding and Implementation Progress

Project Name

Construction

Authorization (Public Law)

Project Status

Broward County Water Preserve

Areas

WRRDA 2014 (P.L. 113-121)

Under Construction

Biscayne Bay Coastal Wetlands

WRRDA 2014 (P.L. 113-121)

Under Construction

Central Everglades Planning Project

WIIN Act (P.L. 114-322)

Awaiting Construction Funding

Big Cypress/L-28 Interceptor

NA

Study in Progress

Loxahatchee River Watershed

Project

NA

Study in Progress

Lake Okeechobee Watershed Project

NA

Study in Progress

Source: CRS based on U.S. Army Corps of Engineers data.

Notes: Does not reflect pilot projects. WRDA 2007 = Water Resources Development Act of 2007; WRRDA

2014 = Water Resources Reform and Development Act of 2014; WIIN Act = Water Infrastructure

Improvements for the Nation Act; NA = not applicable.

For the most part, significant ecosystem benefits as a result of Everglades restoration construction

projects have yet to be achieved. However, some preliminary effects have been noted. According

to recent reporting, documented ecosystem benefits of projects have included increased water

levels and vegetation response, a reduction in seepage loss (i.e., increased water remaining in the

natural system), and improved water quality in some areas.17 Observers expect that most benefits

will lag several years behind project construction and restoration of hydrologic conditions.

Maximizing these benefits is expected to require extensive monitoring and adaptive management,

which would further confirm and refine approaches to restoration.

Selected CERP and non-CERP accomplishments as of June 2017 are discussed below.

Land Acquisition, Pilot Efforts, Non-CERP Projects

As noted above, Everglades restoration has achieved several milestones. Major achievements

included accomplishment of several of the early steps that will be critical to the eventual

completion of larger restoration projects. This includes the purchase by nonfederal project

sponsors of most of the land expected to be required for CERP projects (a necessary first step in

project construction).18 As discussed previously, many of these projects are expected to be

credited toward the nonfederal cost share for individual projects.

Early pilot projects that will influence the eventual prioritization and construction of larger CERP

projects also have been completed. Specifically, design and installation of six pilot projects

authorized in the Water Resources Development Act of 1999 (P.L. 106-53) as well as under CERP

in WRDA 2000 have taken place in recent years. For example, a pilot groundwater seepage

barrier to the southeast of the Mod Waters project was completed and has been found to be

successful in blocking subsurface migration of groundwater.

Many non-CERP projects predate CERP and are therefore more established and in some cases

closer to completion than CERP projects. Some non-CERP accomplishments include the

completion of the Florida Keys Water Quality Improvement Project, as well as the NPS17

Sixth Biennial Review.

The state estimated that as of 2015, it had acquired nearly 64% of lands needed for CERP. See SFWMD Everglades

Restoration Fact Sheet.

18

Congressional Research Service

9

Everglades Restoration: Federal Funding and Implementation Progress

constructed 1-mile bridge component of the Modified Water Deliveries project, which may be

expanded in the future.19 Another major restoration project that predated CERP, the Kissimmee

River Project (authorized in 1992 and initiated in 1999), is nearing completion. Some outside

observers have noted that this project has already resulted in significant ecosystem benefits that

demonstrate the potential for planned CERP projects.20

Generation 1 CERP Projects

Among the Generation 1 CERP projects authorized in WRDA 2000 and WRDA 2007 (Picayune

Strand Restoration, Site 1 Impoundment, Indian River Lagoon-South or IRL-South, and the

programmatic authority for Melaleuca Eradication that was authorized by Congress in WRDA

2000), one project, Melaleuca Eradication, is considered complete.21 As of early 2017, the three

remaining projects were all under construction, with some phases completed and others yet to

begin. The 2016 NRC Biennial Review has noted preliminary ecosystem benefits associated with

several of these projects.22

Generation 2 CERP Projects

As previously noted, WRRDA 2014 (P.L. 113-121) authorized four Generation 2 CERP projects,

with total estimated costs of $1.9 billion: the C-111 Spreader Canal, Biscayne Bay Coastal

Wetlands, C-43 West Basin Storage Reservoir, and Broward County Water Preserve Areas

(WPAs). Two of these (C-43 Reservoir and Broward County WPAs) were new projects, whereas

the two others (the C-111 Spreader Canal and Biscayne Bay Coastal Wetlands) were previously

initiated by the state but required congressional authorization for federal participation. As of early

FY2017, construction had been initiated or planned for initiation for all four projects.

Generation 3 CERP Projects

One Generation 3 CERP project, the Central Everglades Planning Project (CEPP), was authorized

for federal construction in the WIIN Act. CEPP, which is made up of a suite of individual projects

from the original CERP, is widely considered to be a high-priority project for Everglades

restoration, and its status has received considerable attention. CEPP was initiated due to a

perceived need to prioritize restoration projects in the central portion of the Everglades ecosystem

and to enhance the prospects for Everglades restoration overall. Before CEPP, most restoration

projects in the Everglades had focused on the periphery of the Everglades, rather than flows to

Lake Okeechobee and the Central Everglades, as CEPP does. The preliminary estimated cost of

CEPP is $1.9 billion. CEPP has yet to be requested by the Corps as a new construction start, and

was not included in the President’s FY2018 budget request.

19

Another planning project, known as the Next Steps project, is being directed by NPS and may eventually lead to the

bridging of up to an additional 5.5 miles of the roadway.

20

Committee on Independent Scientific Review of Everglades Restoration, National Research Council, Progress

Toward Restoring the Everglades, the Fifth Biennial Review, Washington, DC, 2014, p. 102. Hereinafter referred to as

the Fifth Biennial Review.

21

The project consists of a facility that enables the use of biological controls to aid existing efforts to control invasive

exotic plants in south Florida.

22

Sixth Biennial Review, pp. 36-37.

Congressional Research Service

10

Everglades Restoration: Federal Funding and Implementation Progress

Ongoing Planning

Three CERP projects (Loxahatchee River Watershed, Lake Okeechobee Watershed, and Western

Everglades) were beginning or entering the planning phase as of publication of the NRC review

in late 2016. Numerous other original CERP projects had yet to initiate planning. An internal

Corps effort to reduce the time and cost of Corps studies was enacted on a permanent basis in

WRRDA 2014. This program aims to limit the time and review of future Corps studies, including

those for Everglades restoration projects.23

Challenges

Despite the achievement of some milestones, outside reviewers have noted some challenges

associated with Everglades restoration. These observers have pointed out that while there has

been some progress toward restoring the Everglades, project implementation has been slower

than expected due to a number of factors, such as appropriations levels and delayed project

authorizations.24 As previously noted, increasing project costs are another challenge, as the total

estimated cost of restoring the Everglades has gone up significantly over time. Finally, as the

understanding of the ecosystem and local geology and hydrology has improved, other challenges

have become apparent (for example, see box below, “Harmful Algal Blooms in Florida”). If the

full benefits of restoration are to be realized, these challenges will need to be addressed.

One widely noted challenge is the overall slow pace of Everglades restoration to date. Taken both

individually and as a group, CERP projects have been implemented more slowly than initially

anticipated. Although some projects are nearing completion, the project schedules envisioned in

earlier program documents have for the most part not been maintained; a fraction of the project

implementation reports originally envisioned under CERP have been finalized. 25

Funding for projects is a related challenge for Everglades restoration, and one that could continue

or even grow in coming years. Recently authorized Generation 2 and Generation 3 CERP projects

may in some cases compete with ongoing Generation 1 and non-CERP projects for funding, and

all of these projects must compete with other water resource projects and appropriations

priorities. Even if funding were to be maintained at current levels, project implementation could

slow if funding were spread out among multiple projects as they are authorized. In light of

decreased funding by the state of Florida and its shift toward other restoration priorities in recent

years, attaining new state funding where required for project cost shares also may be challenging.

Changing information also poses issues for Everglades restoration. Recent studies have shown

that the Everglades ecosystem was historically wetter than previously assumed; thus, more water

than initially thought may be required to restore the system. At the same time, more than

1 million acre-feet in planned CERP water storage (much of this in the form of aquifer storage

projects) has been shown to be infeasible by additional study. Finally, increasing potential for

saltwater encroachment under various scenarios of sea-level rise adds further uncertainty to

23

The aim of this effort is to complete feasibility studies in less time than is traditional for Corps investigations.

Among other goals, studies initiated under these requirements are expected to adhere to a “3x3x3” rule, which means

that they will be completed with no more than $3 million in federal costs, in three years or less, and with the

involvement of the three levels of Corps review (districts, divisions, and headquarters).

24

The lack of project authorizations in a WRDA appears to have occurred mostly during the 2012-2014 time period,

since PIRs for three projects were completed and awaiting congressional authorization beginning in 2012.

25

As of the end of 2016, none of the original estimated completion dates for projects in the CERP conceptual plan (also

referred to as the “yellow book”) have been met.

Congressional Research Service

11

Everglades Restoration: Federal Funding and Implementation Progress

previous plans. The significance of potential new water needs for ecosystem health and for South

Florida’s people and industry, the effects of lost storage, and the resulting need (and feasibility)

for revisions to old projects and/or construction of new projects has yet to be fully explored.

Other challenges to Everglades restoration that may be of interest to Congress have been widely

noted. These challenges include ongoing issues associated with water quality in central and

southern Florida and the adequacy (and feasibility) of some restoration efforts in recreating

historical hydrologic conditions; and ongoing degradation of species and ecosystems in south

Florida due to invasive species and other factors (which in some cases appears to have

accelerated in recent years). The interaction of these factors has the potential to impact the status

and effectiveness of other Everglades restoration projects.

Harmful Algal Blooms in Florida: The Connection to Everglades Restoration

In 2015 and 2016, high precipitation events in the Central Everglades (the area around Lake Okeechobee), combined

with decreased water storage available at Lake Okeechobee, led to significant releases of nutrient-laden water from

the lake into the Caloosahatchee and St. Lucie Rivers (the rivers on the lake’s western and eastern sides,

respectively). These releases were made by the U.S. Army Corps of Engineers (Corps), in coordination with the

South Florida Water Management District and pursuant to the lake’s operational rules to avoid flooding. However,

they resulted in harmful algal blooms (sometimes referred to as HABs) in the Caloosahatchee and St. Lucie Rivers and

estuaries. These HABs were detrimental to fish and plant species and were widely covered by the media and

conservation advocates.

A number of solutions have been suggested to combat future occurrence of similar HABs. Major repairs by the Corps

to Herbert Hoover Dike (a federal flood-control project that is not typically counted in Everglades funding totals)

have been ongoing since the 1990s. These repairs (and concerns related to the dike’s structural integrity) are one of

the primary reason that Lake Okeechobee cannot currently hold as much water as it was designed to store and why

high volume water releases into the lake’s two primary outlets (the rivers) are sometimes necessary. Many have

noted the need for expedited completion of the Corps’ dike repair project (which has estimated costs in the

hundreds of millions of dollars) to allow for additional lake storage and revised operational schedules, which would

reduce the potential for future HABs resulting from lake releases.

Some also point to the role of potential Everglades restoration projects (in particular water storage projects) near

Lake Okeechobee in addressing the HAB issue. They note that new water storage projects have the potential to both

hold and treat high-nutrient water that might otherwise be released into the rivers and could add to the storage in

Lake Okeechobee that is expected to be available once dike repair is complete. On May 9, 2017, Florida Governor

Rick Scott signed Senate Bill 10 into state law. The bill, championed by Florida Senate President Joe Negron, directs

contributions to the design and construction by the Corps of a water storage reservoir in the Everglades Agricultural

Area (EAA) to increase water storage south of Lake Okeechobee. The reservoir would be designed to hold at least

240,000 acre-feet of water. The bill appropriates $33 million for the 2017-2018 fiscal years to the South Florida

Water Management District (SFWMD) to implement the EAA reservoir project.26 For each subsequent year, state

funding will be capped at $64 million, with a total of no more than $800 million (i.e., half of the $1.5 billion cost of the

project).

The EAA reservoir project was conditionally authorized in WRDA 2000 as a project component of CERP, but has in

the past not been scheduled for near-term study. Before federal construction can commence, it must be studied and

recommended for construction authorization by the Corps and OMB, and authorized by Congress. If reservoir

construction were authorized, the federal government would be required to fund half of the costs of the project.

Part of the land area envisioned for the EAA project was included in the study area for CEPP. Thus, the state

legislation authorizing the EAA reservoir project directed the South Florida Water Management District to work with

the Corps to develop a Post Authorization Change Report that would revise that portion of CEPP to incorporate the

240,000-acre EAA Reservoir. While the enacted state legislation stipulated that this re-study would not affect the

remainder of CEPP implementation, it is unclear how such a change might actually affect CEPP implementation under

Corps policies.

26

For more information, see http://www.flsenate.gov/Committees/billsummaries/2017/html/1583.

Congressional Research Service

12

Everglades Restoration: Federal Funding and Implementation Progress

Completion of project construction represents only one hurdle for Everglades restoration, with

operations and monitoring of performance representing challenges in their own right. While

preliminary benefits in the early stages of project operations are possible, many observers note

that it will take time for projects to individually and collectively refine their operations and

demonstrate significant long-term positive effects on Everglades-dependent species and the

environment.

Author Contact Information

(name redacted)

Specialist in Natural Resources Policy

[redacted]@crs.loc.gov

, 7-....

Congressional Research Service

13

EveryCRSReport.com

The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the

Library of Congress, charged with providing the United States Congress non-partisan advice on

issues that may come before Congress.

EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The

reports are not classified, and Members of Congress routinely make individual reports available to

the public.

Prior to our republication, we redacted names, phone numbers and email addresses of analysts

who produced the reports. We also added this page to the report. We have not intentionally made

any other changes to any report published on EveryCRSReport.com.

CRS reports, as a work of the United States government, are not subject to copyright protection in

the United States. Any CRS report may be reproduced and distributed in its entirety without

permission from CRS. However, as a CRS report may include copyrighted images or material from a

third party, you may need to obtain permission of the copyright holder if you wish to copy or

otherwise use copyrighted material.

Information in a CRS report should not be relied upon for purposes other than public

understanding of information that has been provided by CRS to members of Congress in

connection with CRS' institutional role.

EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim

copyright on any CRS report we have republished.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.