Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress

Congressional research reportDec 4, 2025

Ask Donna

What actually matters in this document.

Text

Multiyear Procurement (MYP) and Block Buy

Contracting in Defense Acquisition:

Background and Issues for Congress

Updated December 4, 2025

Congressional Research Service

https://crsreports.congress.gov

R41909

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Summary

Multiyear procurement (MYP) and block buy contracting (BBC) are special contracting

mechanisms that Congress permits the Department of Defense (DOD) to use for a limited number

of defense acquisition programs. Compared to the standard or default approach of annual

contracting, MYP and BBC have the potential for reducing weapon procurement costs by a few

or several percent, and for providing a more stable or reliable business planning environment for

the firms producing the weapons.

Under annual contracting, DOD uses one or more contracts for each year’s worth of procurement

of a given kind of item. Under MYP, DOD instead uses a single contract for two to five years’

worth of procurement of a given kind of item without having to exercise a contract option for

each year after the first year. DOD needs congressional approval (in both a DOD appropriations

act and an act other than a DOD appropriations act) for each use of MYP. There is a permanent

statute governing MYP contracting—10 U.S.C. 3501. Under this statute, a program must meet

several criteria to qualify for MYP.

Compared with estimated costs under annual contracting, estimated savings for programs being

proposed for MYP have ranged from less than 5% to more than 15%, depending on the

particulars of the program in question, with many estimates falling in the range of 5% to 10%. In

practice, actual savings from using MYP rather than annual contracting can be difficult to observe

or verify because of cost growth during the execution of the contract due to changes in the

program that are independent of the use of MYP rather than annual contracting.

BBC is similar to MYP in that it permits DOD to use a single contract for more than one year’s

worth of procurement of a given kind of item without having to exercise a contract option for

each year after the first year. BBC is also similar to MYP in that DOD needs congressional

approval for each use of BBC. BBC differs from MYP in the following ways:

•

•

•

•

•

•

There is no permanent statute governing the use of BBC.

There is no requirement that BBC be approved in both a DOD appropriations act

and an act other than a DOD appropriations act.

Programs being considered for BBC do not need to meet any legal criteria to

qualify for BBC, because there is no permanent statute governing the use of BBC

that establishes such criteria.

A BBC contract can cover more than five years of planned procurements.

Economic order quantity (EOQ) authority—the authority to bring forward

selected key components of the items to be procured under the contract and

purchase the components in batch form during the first year or two of the

contract—does not come automatically as part of BBC authority (as it does with

MYP authority), because there is no permanent statute governing the use of BBC

that includes EOQ authority as an automatic feature. For EOQ to be part of a

block buy contract, the legislative provision authorizing the block contract must

explicitly include authority for using EOQ.

BBC contracts are less likely to include cancellation penalties.

Congressional Research Service

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Contents

Introduction ..................................................................................................................................... 1

Issues for Congress ................................................................................................................... 1

Terminology and Scope of Report ............................................................................................ 1

Contracting Mechanisms and Funding Approaches ............................................................ 1

Background ..................................................................................................................................... 3

Multiyear Procurement (MYP) ................................................................................................. 3

MYP in Brief....................................................................................................................... 3

Potential Savings Under MYP ............................................................................................ 3

Permanent Statute Governing MYP.................................................................................... 5

Potential Consequences of Not Fully Funding an MYP Contract ...................................... 8

Effect on Flexibility for Making Procurement Changes ..................................................... 8

Congressional Approval ...................................................................................................... 8

Frequency of Use of MYP .................................................................................................. 8

Block Buy Contracting (BBC) .................................................................................................. 9

BBC in Brief ....................................................................................................................... 9

Terminology Alert: Block Buy Contracting vs. Block Buys............................................. 10

Potential Savings Under BBC ........................................................................................... 10

Frequency of Use of BBC ..................................................................................................11

Using BBC Rather than MYP ............................................................................................11

MYP and BBC vs. Contracts with Options ..............................................................................11

Issues for Congress ........................................................................................................................ 12

Frequency of Using MYP and BBC ........................................................................................ 12

Overview ........................................................................................................................... 12

Interest in Using Multiyear Contracting for Procuring Munitions .................................... 13

Adequacy of Information Submitted for MYP Contracts ....................................................... 14

Permanent Statute for BBC ..................................................................................................... 15

Coast Guard Use of MYP and BBC ........................................................................................ 15

Legislative Activity for FY2026 .................................................................................................... 16

Proposals for MYP and Block Buy Contracts in DOD’s FY2026 Budget Submission .......... 16

FY2026 National Defense Authorization Act (H.R. 3838/S. 2296) ........................................ 16

House ................................................................................................................................ 16

Senate ................................................................................................................................ 18

FY2026 DOD Appropriations Act (H.R. 4016/S. 2572) ......................................................... 20

House ................................................................................................................................ 20

Senate ................................................................................................................................ 20

Streamlining Procurement for Effective Execution and Delivery Act of 2025 (SPEED

Act) (H.R. 3838) .................................................................................................................. 22

House ................................................................................................................................ 22

Tables

Table 1. Contracting Mechanisms and Funding Approaches .......................................................... 2

Table B-1. Programs Approved for MYP in Annual Appropriations Acts Since FY2022............. 28

Congressional Research Service

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Table B-2. Programs Approved for MYP in Annual DOD Appropriations Acts

From FY2011 Through FY2021................................................................................................. 28

Table B-3. Programs Approved for MYP in Annual DOD Appropriations Acts from

FY1990 Through FY2010 .......................................................................................................... 30

Appendixes

Appendix A. Text of 10 U.S.C. 3501 ............................................................................................. 23

Appendix B. Programs Approved for MYP in Annual DOD Appropriations Acts Since

FY1990 ....................................................................................................................................... 28

Contacts

Author Information........................................................................................................................ 32

Congressional Research Service

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Introduction

Issues for Congress

This report provides background information and issues for Congress on multiyear procurement

(MYP) and block buy contracting (BBC),1 which are special contracting mechanisms that

Congress permits the Department of Defense (DOD) to use for a limited number of defense

acquisition programs. Compared to the standard or default approach of annual contracting, MYP

and BBC have the potential for reducing weapon procurement costs by a few or several percent,

and for providing a more stable or reliable business planning environment for the firms producing

the weapons.

Potential issues for Congress concerning MYP and BBC include whether to use MYP and BBC in

the future more frequently, less frequently, or about as frequently as they are currently used;

whether to create a permanent statute to govern the use of BBC, analogous to the permanent

statute that governs the use of MYP; and whether the Coast Guard should begin making use of

MYP and BBC. Congress’s decisions on these issues could affect defense acquisition practices,

defense funding requirements, and the defense industrial base.

Terminology and Scope of Report

Contracting Mechanisms and Funding Approaches

In discussing MYP, BBC, and incremental funding, it can be helpful to distinguish contracting

mechanisms from funding approaches. The two are often mixed together in discussions of DOD

acquisition, sometimes leading to confusion. Stated briefly

•

•

Funding approaches are ways that Congress can appropriate funding for

weapon procurement programs, so that DOD can then put them under contract.

Examples of funding approaches include traditional full funding (the standard or

default approach), incremental funding, and advance appropriations.2 Any of

these funding approaches might make use of advance procurement (AP)

funding.3

Contracting mechanisms are ways for DOD to contract for the procurement of

weapons systems, once funding for those systems has been appropriated by

Congress. Examples of contracting mechanisms include annual contracting (the

1 MYP is an established acronym for multiyear procurement. BBC is not an established acronym for block buy

contracting, but is used in this CRS report for purposes of convenience.

2 For more on these three funding approaches, see CRS Report RL31404, Defense Procurement: Full Funding Policy—

Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776,

Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by Ronald

O'Rourke. Advance appropriations, which are not to be confused with advance procurement (AP) funding (see footnote

3), are essentially a legislatively locked-in form of incremental funding. Unlike incremental funding, advance

appropriations qualify under budgeting regulations as a form of full funding.

3 AP funding is provided in one or more years prior to the year of procurement of a weapon system for the procurement

of long-leadtime components—components with long construction times. Such components must be funded prior to the

procurement of the remainder of the weapon system if they are to be ready for installation in the weapon system at the

appropriate point in the construction process. AP funding is a permitted exception to the full funding provision. AP

funding is not to be confused with advance appropriations (see footnote 2).

Congressional Research Service

1

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

standard or default DOD approach), MYP, and BBC. Contracting mechanisms

can materially change the total procurement cost of a ship.

The use of a particular funding approach in a defense acquisition program does not dictate the use

of a particular contracting mechanism. Defense acquisition programs consequently can be

implemented using various combinations of funding approaches and contracting mechanisms.

Most DOD weapon acquisition programs use a combination of traditional full funding and annual

contracting. A few programs, particularly certain Navy shipbuilding programs, use incremental

funding as their funding approach. A limited number of DOD programs use MYP and block buy

contracting as their contracting approaches. The situation is summarized in Table 1.

Table 1. Contracting Mechanisms and Funding Approaches

Funding Approaches

Contracting

mechanisms

Full funding

Incremental funding

Annual

contracting

Most programs

A few programs

(e.g., CVNs, LHAs,

DDG-1000s, and SSBN826s)

MYP

Selected programs

Block buy

contracting

A few programs (e.g.,

Virginia class submarines

[boats 1-4], Littoral

Combat Ships [ships 526], and John Lewis

(TAO-205) class oilers

[ships 1-6]).

Advance

appropriations

Gerald R. Ford (CVN78) class aircraft

carriers (CVNs 80 and

81).

Source: Table prepared by CRS.

Notes: Advance procurement (AP) can be used with any of the funding approaches. CVNs are nuclear-powered

aircraft carriers; LHAs are large-deck amphibious assault ships; DDG-1000s are destroyers; SSBN-826s are

Columbia-class ballistic missile submarines (where incremental funding is to be used for the first two ships).

This report focuses on the contracting approaches of MYP and BBC and how they compare to

annual contracting. Other CRS reports discuss the funding approaches of traditional full funding,

incremental funding, and advance appropriations.4

4 See footnote 2 for citations to these reports. Appropriating funding for a program and placing a program under

contract are steps in a larger sequence of budget-related events that includes authorization, appropriation, obligation,

and outlays. For a general discussion of this sequence, see CRS Report 98-721, Introduction to the Federal Budget

Process, coordinated by James V. Saturno.

Congressional Research Service

2

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Background

Multiyear Procurement (MYP)

MYP in Brief5

What is MYP, and how does it differ from annual contracting? MYP, also known as multiyear

contracting, is an alternative to the standard or default DOD approach of annual contracting.

Under annual contracting, DOD uses one or more contracts for each year’s worth of procurement

of a given kind of item. Under MYP, DOD instead uses a single contract for two to five years’

worth of procurement of a given kind of item, without having to exercise a contract option for

each year after the first year. DOD needs congressional approval for each use of MYP.

To illustrate the basic difference between MYP and annual contracting, consider a hypothetical

DOD program to procure 20 single-engine aircraft of a certain kind over the five-year period

FY2025-FY2029, at a rate of 4 aircraft per year:

•

•

Under annual contracting, DOD would issue one or more contracts for each

year’s procurement of four aircraft. After Congress funds the procurement of the

first four aircraft in FY2025, DOD would issue one or more contracts (or

exercise a contract option) for those four aircraft. The next year, after Congress

funds the procurement of the next four aircraft in FY2026, DOD would issue one

or more contracts (or exercise a contract option) for those four aircraft, and so on.

Under MYP, DOD would issue one contract covering all 20 aircraft to be

procured during the five-year period FY2025-FY2029. DOD would award this

contract in FY2025, at the beginning of the five-year period, following

congressional approval to use MYP for the program, and congressional

appropriation of the FY2025 funding for the program. To continue the

implementation of the contract over the next four years, DOD would request the

FY2026 funding for the program as part of DOD’s proposed FY2026 budget, the

FY2027 funding as part of DOD’s proposed FY2027 budget, and so on.

Potential Savings Under MYP

How much can MYP save? Compared with estimated costs under annual contracting, estimated

savings for programs being proposed for MYP have ranged from less than 5% to more than 15%,

depending on the particulars of the program in question, with many estimates falling in the range

of 5% to 10%. In practice, actual savings from using MYP rather than annual contracting can be

difficult to observe or verify because of cost growth during the execution of the contract that was

caused by developments independent of the use of MYP rather than annual contracting.

A February 2012 briefing by the Cost Assessment and Program Evaluation (CAPE) office within

the Office of the Secretary of Defense (OSD) states that “MYP savings analysis is difficult due to

the lack of actual costs on the alternative acquisition path, i.e., the path not taken.”6 The briefing

states that CAPE up to that point had assessed MYP savings for four aircraft procurement

5 For an additional brief overview of MYP, see Department of Defense, “Multiyear (MY) Procurement,” undated, 11

pp., accessed October 15, 2020, at https://www.acq.osd.mil/dpap/paic/Docs/multiyear.pdf.

6 Slide 10 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis

symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required), May 14, 2012.

Congressional Research Service

3

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

programs—F/A-18E/F strike fighters, H-60 helicopters, V-22 tilt-rotor aircraft, and CH-47F

helicopters—and that CAPE’s assessed savings ranged from 2% to 8%.7

A 2008 Government Accountability Office (GAO) report stated that

DOD does not have a formal mechanism for tracking multiyear results against original

expectations and makes few efforts to validate whether actual savings were achieved by

multiyear procurement. It does not maintain comprehensive central records and historical

information that could be used to enhance oversight and knowledge about multiyear

performance to inform and improve future multiyear procurement (MYP) candidates. DOD

and defense research centers officials said it is difficult to assess results because of the lack

of historical information on multiyear contracts, comparable annual costs, and the dynamic

acquisition environment.8

How does MYP potentially save money? Compared to annual contracting, using MYP can in

principle reduce the cost of the weapons being procured in two primary ways:

•

•

Contractor optimization of workforce and production facilities. An MYP

contract gives the contractor (e.g., an airplane manufacturer or shipbuilder)

confidence that a multiyear stream of business of a known volume will very

likely materialize. This confidence can permit the contractor to make investments

in the firm’s workforce and production facilities that are intended to optimize the

facility for the production of the items being procured under the contract. Such

investments can include payments for retaining or training workers, or for

building, expanding, or modernizing production facilities. Under annual

contracting, the manufacturer might not have enough confidence about its future

stream of business to make these kinds of investments, or might be unable to

convince its parent firm to finance them.

Economic order quantity (EOQ) purchases of selected long-leadtime

components. Under an MYP contract, DOD is permitted to bring forward

selected key components of the items to be procured under the contract and to

purchase the components in batch form during the first year or two of the

contract. In the hypothetical example introduced earlier, using MYP could permit

DOD to purchase, say, the 20 engines for the 20 aircraft in the first year or two of

the five-year contract. Procuring selected components in this manner under an

MYP contract is called an economic order quantity (EOQ) purchase.9 EOQ

purchases can reduce the procurement cost of the weapons being procured under

the MYP contract by allowing the manufacturers of components to take

7 Slide 12 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis

symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required), May 14, 2012. Slide 12 also

stated that these assessed savings were based on comparing CAPE’s estimate of what the programs would cost under

annual contracting (which the briefing refers to as single-year procurement or SYP) to the contractor’s MYP proposal.

8 Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear

Procurement Should Be Improved, GAO-08-298, February 2008, p. 3. For additional discussion of the potential costs

and benefits of MYP, see Scot A. Arnold and Bruce R. Hamon, The Relative Cost and Benefits of Multi-year

Procurement Strategies, Institute for Defense Analyses, June 2013, IDA Document NS D-4893, 37 pp., accessed

October 15, 2020, at https://www.ida.org/-/media/feature/publications/i/id/ida-nsd-4893-the-relative-costs-and-benefitsof-multi-year-procurement-strategies/ida-document-ns-d-4893.ashx. See also Department of the Navy, DASN(AIR)

Multiyear Procurement (MYP) Guidebook, v. 2.0, November 10, 2010, accessed October 15, 2020, at

https://www.secnav.navy.mil/rda/Policy-OLD/dasnairmypguidebookv20november102010.pdf.

9 The term EOQ is occasionally used in discussions of defense acquisition, somewhat loosely, to refer to any highquantity or batch order of items, even those that do not take place under MYP or BBC. As a general matter, however,

EOQs as described here occur only within MYP and block buy contracts.

Congressional Research Service

4

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

maximum advantage of production economies of scale that are possible with

batch orders.10

What gives the contractor confidence that the multiyear stream of business will materialize? At

least two things give the contractor confidence that DOD will not terminate an MYP contract and

that the multiyear stream of business consequently will materialize:

•

•

For a program to qualify for MYP, DOD must certify, among other things, that

the minimum need for the items to be purchased is expected to remain

substantially unchanged during the contract in terms of production rate,

procurement rate, and total quantities.

Perhaps more important to the contractor, MYP contracts include a cancellation

penalty intended to reimburse a contractor for costs that the contractor has

incurred (i.e., investments the contractor has made) in anticipation of the work

covered under the MYP contract. The undesirability of paying a cancellation

penalty acts as a disincentive for the government against canceling the contract.

(And if the contract is canceled, the cancellation penalty helps to make the

contractor whole.11)

Permanent Statute Governing MYP

Is there a permanent statute governing MYP contracting? There is a permanent statute

governing MYP contracting—10 U.S.C. 3501 (the text of which was previously codified at 10

U.S.C. 2306b).12 The statute was created by Section 909 of the FY1982 Department of Defense

10 A 2008 Government Accountability Office (GAO) report on multiyear contracting lists five areas of savings, most of

which are covered in the two general areas of savings outlined above. One of GAO’s five areas of savings—limited

engineering changes due to design stability—can also occur in programs that use annual contracting. The GAO report

states the following:

Multiyear procurement can potentially save money and improve the defense industrial base by

permitting the more efficient use of a contractor’s resources. Multiyear contracts are expected to

achieve lower unit costs compared to annual contracts through one or more of the following

sources: (1) purchase of parts and materials in economic order quantities (EOQ), (2) improved

production processes and efficiencies, (3) better utilized industrial facilities, (4) limited engineering

changes due to design stability during the multiyear period, and (5) cost avoidance by reducing the

burden of placing and administering annual contracts. Multiyear procurement also offers

opportunities to enhance the industrial base by providing defense contractors a longer and more

stable time horizon for planning and investing in production and by attracting subcontractors,

vendors, and suppliers. However, multiyear procurement also entails certain risks that must be

balanced against potential benefits, such as the increased costs to the government should the

multiyear contract be changed or canceled and decreased annual budget flexibility for the program

and across DOD’s portfolio of weapon systems. Additionally, multiyear contracts often require

greater budgetary authority in the earlier years of the procurement to economically buy parts and

materials for multiple years of production than under a series of annual buys.

Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear

Procurement Should Be Improved, GAO-08-298, February 2008, pp. 4-5.

11 Annual contracts can also include cancellation penalties.

12 A codification note for 10 U.S.C. 3501 states

Pub. L. 116–283, §1822(b)–(l), which had initially directed the transfers of various subsections of

section 2306b of this title [i.e., Title 10] to sections 3501 to 3511, was amended by Pub. L. 117–81,

§1701(k)(2), by striking out subsecs. (b) to (l) and adding a new subsec. (b). After that amendment,

such transfers were no longer directed. Instead, Pub. L. 116–283, §1822(b), as added by Pub. L.

117–81, directed the transfer of section 2306b of this title in its entirety to this section, thereby

omitting what would have been sections 3502 to 3511 of this title. The transfer of section 2306b to

(continued...)

Congressional Research Service

5

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Authorization Act (S. 815/P.L. 97-86 of December 1, 1981), revised and reorganized by Section

1022 of the Federal Acquisition Streamlining Act of 1994 (S. 1587/P.L. 103-355 of October 13,

1994), and further amended on several occasions since.13 For the text of 10 U.S.C. 3501, see

Appendix A.

Under this statute, what criteria must a program meet to qualify for MYP? 10 U.S.C. 3501

states that to qualify for MYP, a program must meet several criteria, including the following:

•

•

•

•

Significant savings or necessary industrial base stability. DOD must estimate

that using an MYP contract would result in either “significant savings” compared

with using annual contracting or “necessary defense industrial base stability not

otherwise achievable” through annual contracting.

Realistic cost estimates. DOD’s estimates of the cost of the MYP contract and

the anticipated savings must be realistic.

Stable need for the items. DOD must expect that its minimum need for the

items will remain substantially unchanged during the contract in terms of

production rate, procurement rate, and total quantities.

Stable design for the items. The design for the items to be acquired must be

stable, and the technical risks associated with the items must not be excessive.

10 U.S.C. 3501 includes provisions requiring the Secretary of Defense or certain other DOD

officials to find, determine, or certify that these and other statutory requirements for using MYP

contracts have been met, and provisions requiring the heads of DOD agencies to provide written

notifications of certain things to the congressional defense committees 30 days before awarding

or initiating an MYP contract, or 10 days before terminating one. 10 U.S.C. 3501 also requires

DOD MYP contracts to be fixed-price type contracts.

Criterion of “necessary industrial base stability.” The criterion of “necessary defense industrial

base stability not otherwise achievable” through annual contracting was added by Section 820 of

the FY2024 National Defense Authorization Act (NDAA) (H.R. 2670/P.L. 118-31 of December

22, 2023). The provision originated as Section 801 of the Senate-passed version of the FY2024

NDAA (S. 2226). The Senate Armed Services Committee’s report on S. 2226 (S.Rept. 118-58 of

July 12, 2023) stated

In section 1244 of the James M. Inhofe National Defense Authorization Act for Fiscal Year

2023 (Public Law 117–263), the committee authorized the use of multiyear procurements

for a number of munitions related to refilling stocks used in the Ukraine conflict and to

strengthen the readiness of U.S. forces. The committee notes with concern that this

authority has not been fully utilized for a number of munitions on the list due to limited

projected cost savings achieved through a multiyear contract versus single year contracts.

The committee believes the use of multiyear contracts offer more advantages than only

cost savings. These contracts can also provide a clear demand signal to industry, which

helps industry plan labor and material needs more effectively, and can better position it to

meet the demands of U.S. requirements. Therefore, the committee believes the Department

this section was executed by transferring the text only of section 2306b, as the section designation

and catchline had already been enacted by Pub. L. 116–283, §1822(a), as amended by Pub. L. 117–

81, §1701(k)(1)(B).

13 For additional discussion of the legislative origin of MYP, see Congressional Budget Office, Alternative Strategies

for Increasing Multiyear Procurement, Staff Working Paper, pp. 10-12, accessed October 15, 2020, at

https://www.cbo.gov/sites/default/files/99th-congress-1985-1986/reports/doc16a_2.pdf, and David R. Sutton, Miltiyear

Procurement: A Desktop Guide, Naval Postgraduate School thesis, June 1997, pp. 7-10, accessed October 15, 2020, at

https://calhoun.nps.edu/bitstream/handle/10945/8709/multiyearprocure00sutt.pdf.

Congressional Research Service

6

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

of Defense should factor in industrial base concerns as well as projected cost savings when

considering the use of multiyear contracts. (Page 181)

What is meant by “significant savings”? The amount of savings required under 10 U.S.C. 3501

to qualify for using an MYP contract has changed over time; the requirement was changed from

“substantial savings” to “significant savings” by Section 811 of the FY2016 NDAA (S. 1356/P.L.

114-92 of November 25, 2015).14 The joint explanatory statement for the FY2016 NDAA states

the following regarding Section 811 (emphasis added):

Amendment relating to multiyear contract authority for acquisition of property (sec. 811)

The House bill contained a provision (sec. 806) that would strike the existing requirement

that the head of an agency must determine that substantial savings would be achieved

before entering into a multiyear contract.

The Senate amendment contained no similar provision.

The Senate recedes with an amendment that would require that significant savings would

be achieved before entering into a multiyear contract.

The conferees agree that the government should seek to maximize savings whenever it

pursues multiyear procurement. However, the conferees also agree that significant

savings (estimated to be greater than $250.0 million), and other benefits, may be

achieved even if it does not equate to a minimum of 10 percent savings over the cost of an

annual contract. The conferees expect a request for authority to enter into a multiyear

contract will include (1) the estimated cost savings, (2) the minimum quantity needed, (3)

confirmation that the design is stable and the technical risks are not excessive, and (4) any

other rationale for entering into such a contract.15

In addition, 10 U.S.C. 3501 states the following:

If for any fiscal year a multiyear contract to be entered into under this section is authorized

by law for a particular procurement program and that authorization is subject to certain

conditions established by law (including a condition as to cost savings to be achieved under

the multiyear contract in comparison to specified other contracts) and if it appears (after

negotiations with contractors) that such savings cannot be achieved, but that significant

savings could nevertheless be achieved through the use of a multiyear contract rather than

specified other contracts, the President may submit to Congress a request for relief from

the specified cost savings that must be achieved through multiyear contracting for that

program. Any such request by the President shall include details about the request for a

multiyear contract, including details about the negotiated contract terms and conditions.16

What is meant by “stable design”? The term “stable design” is generally understood to mean that

the design for the items to be procured is not expected to change substantially during the period

of the contract. Having a stable design is generally demonstrated by having already built at least a

few items to that design (or in the case of a shipbuilding program, at least one ship to that design)

and concluding, through testing and operation of those items, that the design does not require any

substantial changes during the period of the contract.

14 For a discussion of the earlier evolution of the savings requirement under 10 U.S.C. 3501, including a figure

graphically summarizing the legislative history of the requirement, see Government Accountability Office, Defense

Acquisitions[:] DOD’s Practices and Processes for Multiyear Procurement Should Be Improved, GAO-08-298,

February 2008, pp. 21-22, including Figure 3 on p. 22.

15 Joint explanatory statement for H.R. 1735, the FY2016 NDAA, page 126 (PDF page 127 of 542). H.R. 1735 was

vetoed by the President. A revised FY2016 NDAA, S. 1356, was then passed and enacted into law. There was no new

joint explanatory statement for S. 1356. For the parts of S. 1356 that were unchanged from H.R. 1735, the joint

explanatory statement for H.R. 1735 in effect serves as the joint explanatory statement for S. 1356.

16 10 U.S.C. 3501, subsection (i)(4).

Congressional Research Service

7

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Potential Consequences of Not Fully Funding an MYP Contract

What happens if Congress does not provide the annual funding requested by DOD to continue

the implementation of the contract? If Congress does not provide the funding requested by DOD

to continue the implementation of an MYP contract, DOD would be required to renegotiate,

suspend, or terminate the contract. Terminating the contract could require the government to pay

a cancellation penalty to the contractor. Renegotiating or suspending the contract could also have

a financial impact.

Effect on Flexibility for Making Procurement Changes

What effect does using MYP have on flexibility for making procurement changes? A principal

potential disadvantage of using MYP is that it can reduce Congress’s and DOD’s flexibility for

making changes (especially reductions) in procurement programs in future years in response to

changing strategic or budgetary circumstances, at least without incurring cancellation penalties.

In general, the greater the portion of DOD’s procurement account that is executed under MYP

contracts, the greater the potential loss of flexibility. The use of MYP for executing some portion

of the DOD procurement account means that if policymakers in future years decide to reduce

procurement spending below previously planned levels, the spending reduction might fall more

heavily on procurement programs that do not use MYP, which in turn might result in a less-thanoptimally balanced DOD procurement effort.

Congressional Approval

How does Congress approve the use of MYP? Congress approves the use of MYP on a case-bycase basis, typically in response to requests by DOD.17 Congressional approval for DOD MYP

contracts with a value of more than $500 million must occur in two places: an annual DOD

appropriations act18 and an act other than the annual DOD appropriations act.19

In annual DOD appropriations acts, the provision permitting the use of MYP for one or more

defense acquisition programs is typically included in the title containing general provisions,

which typically is Title VIII. As shown in the tables in Appendix B, since FY2011, it has been

Section 8010.

An NDAA is usually the act other than an appropriations act in which provisions granting

authority for using MYP contracting on individual defense acquisition programs are included.

Such provisions typically occur in Title I of the NDAA, the title covering procurement programs.

Provisions in which Congress approves the use of MYP for a particular defense acquisition

program may include specific conditions for that program in addition to the requirements and

conditions of 10 U.S.C. 3501.

Frequency of Use of MYP

How often is MYP used? MYP is used for a limited number of DOD acquisition programs. As

shown in the Appendix B, annual DOD appropriations acts since FY1990 typically have

17 The Anti-Deficiency Act (31 U.S.C. 1341) prohibits the making of contracts in advance of appropriations. A

multiple-year commitment may be made when authorized by Congress by entering into a firm commitment for one

year and making the government’s liability for future years contingent on funds becoming available.

18 10 U.S.C. 3501, subsection (l)(3).

19 10 U.S.C. 3501, subsection (i)(1).

Congressional Research Service

8

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

approved the use of MYP for zero to a few DOD programs each year. A 2008 Government

Accountability Office (GAO) report stated the following:

Although DOD had been entering into multiyear contracts on a limited basis prior to the

1980s, the Department of Defense Authorization Act, [for fiscal year] 1982,20 codified the

authority for DOD to procure on a multiyear basis major weapon systems that meet certain

criteria. Since that time, DOD has annually submitted various weapon systems as multiyear

procurement candidates for congressional authorization. Over the past 25 years, Congress

has authorized the use of multiyear procurement for approximately 140 acquisition

programs, including some systems approved more than once.21

Block Buy Contracting (BBC)

BBC in Brief

What is BBC, and how does it compare to MYP? BBC is similar to MYP in that it permits DOD

to use a single contract for more than one year’s worth of procurement of a given kind of item

without having to exercise a contract option for each year after the first year.22 BBC is also

similar to MYP in that DOD needs congressional approval for each use of BBC.

BBC differs from MYP in the following ways:

•

•

•

•

•

•

There is no permanent statute governing the use of BBC.

There is no requirement that BBC be approved in both a DOD appropriations act

and an act other than a DOD appropriations act.

Programs being considered for BBC do not need to meet any legal criteria to

qualify for BBC, because there is no permanent statute governing the use of BBC

that establishes such criteria.

A BBC contract can cover more than five years of planned procurements.

Economic order quantity (EOQ) authority—the authority to bring forward

selected key components of the items to be procured under the contract and

purchase the components in batch form during the first year or two of the

contract—does not come automatically as part of BBC authority (as it does with

MYP authority), because there is no permanent statute governing the use of BBC

that includes EOQ authority as an automatic feature. For EOQ to be part of a

block buy contract, the legislative provision authorizing the block contract must

explicitly include authority for using EOQ.

BBC contracts are less likely to include cancellation penalties.

20 S. 815/P.L. 97-86 of December 1, 1981, §909.

21 Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear

Procurement Should Be Improved, GAO-08-298, February 2008, p. 5.

22 Using the hypothetical example introduced earlier involving the procurement of 20 aircraft over the five-year period

FY2024-FY2028, DOD would follow the same general path as it would under MYP: DOD would issue one contract

covering all 20 aircraft in FY2024, at the beginning of the five-year period, following congressional approval to use

BBC for the program, and congressional appropriation of the FY2024 funding for the program. To continue the

implementation of the contract over the next four years, DOD would request the FY2025 funding for the program as

part of DOD’s proposed FY2025 budget, the FY2026 funding as part of DOD’s proposed FY2026 budget, and so on.

Congressional Research Service

9

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Given the one key similarity between BBC and MYP (the use of a single contract for more than

one year’s worth of procurement), and the various differences between BBC and MYP, BBC

might be thought of as a less formal stepchild of MYP.

When and why was BBC invented? BBC was invented by Section 121(b) of the FY1998 NDAA

(H.R. 1119/P.L. 105-85 of November 18, 1997), which granted the Navy the authority to use a

single contract for the procurement of the first four Virginia (SSN-774) class attack submarines.

The 4 boats were scheduled to be procured during the five-year period FY1998-FY2002 in annual

quantities of 1-1-0-1-1. Congress provided the authority granted in Section 121(b) at least in part

to reduce the combined procurement cost of the four submarines. Using MYP was not an option

for the Virginia-class program at that time because the Navy had not even begun, let alone

finished, construction of the first Virginia-class submarine, and consequently could not

demonstrate that it had a stable design for the program.

When Section 121(b) was enacted, there was no name for the contracting authority it provided.

The term block buy contracting came into use later, when observers needed a term to refer to the

kind of contracting authority that Congress authorized in Section 121(b). As discussed in the next

section, this can cause confusion, because the term block buy was already being used in

discussions of DOD acquisition to refer to something else.

Terminology Alert: Block Buy Contracting vs. Block Buys

What’s the difference between block buy contracting and block buys? In discussions of defense

procurement, the term “block buy” by itself (without “contracting” at the end) has sometimes

been used to refer to something quite different from block buy contracting—namely, the simple

act of funding the procurement of more than one copy of an item in a single year, particularly

when no more than one item of that kind might normally be funded in a single year. For example,

when Congress funded the procurement of two aircraft carriers in FY1983, and another two in

FY1988, these acts were each referred to as block buys, because aircraft carriers are normally

procured one at a time, several years apart from one another. This alternate meaning of the term

block buy predates by many years the emergence of the term block buy contracting.

The term block buy is still used in this alternate manner, which can lead to confusion in

discussions of defense procurement. For example, for FY2017, the Air Force requested funding

for procuring five Evolved Expendable Launch Vehicles (EELVs) for its EELV Launch Services

(ELS) program, and sometimes referred to this as a block buy.

At the same time, Navy officials sometimes refer to the use of block buy contracts for the first

four Virginia-class submarines, and in the LCS program, as block buys, when they might be more

specifically referred to as instances of block buy contracting.

Potential Savings Under BBC

How much can BBC save, compared with MYP? BBC can reduce the unit procurement costs of

ships by amounts less than or perhaps comparable to those of MYP, if the authority granted for

using BBC explicitly includes authority for making economic order quantity (EOQ) purchases of

components. If the authority granted for using BBC does not explicitly include authority for

making EOQ purchases, then the savings from BBC will be less. Potential savings under BBC

might also be less than those under MYP if the BBC contract does not include a cancellation

penalty, or includes one that is more limited than typically found in an MYP contract, because

this might give the contractor less confidence than would be the case under an MYP contract that

the future stream of business will materialize as planned, which in turn might reduce the amount

Congressional Research Service

10

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

of money the contractor invests to optimize its workforce and production facilities for producing

the items to be procured under the contract.

Frequency of Use of BBC

How frequently has BBC been used? Since its use at the start of the Virginia-class program,

BBC has been used very rarely. The Navy did not use it again in a shipbuilding program until

December 2010, when it awarded two block buy contracts, each covering 10 LCSs to be procured

over the six-year period FY2010-FY2015, to the two LCS builders.23 (Each contract was later

amended to include an 11th ship in FY2016, making for a total of 22 ships under the two

contracts.) A third example is the John Lewis (TAO-205) class oiler program, in which the Navy

used a block buy contract to procure the first six ships in the program.24 A fourth example are the

two Gerald R. Ford (CVN-78) class aircraft carriers CVN-80 and CVN-81, which were procured

as a two-ship block buy (although the Navy generally refers to it simply as a two-ship buy, rather

than as a two-ship block buy).25

An additional example, arguably, is the Air Force’s KC-46 aerial refueling tanker program, which

employed a fixed price incentive fee (FPIF) development contract that included a “back end”

commitment to procure certain minimum numbers of KC-46s in certain fiscal years.26

Using BBC Rather than MYP

When might BBC be suitable as an alternative to MYP? BBC might be particularly suitable as

an alternative to MYP in cases where using a multiyear contract can reduce costs, but the program

in question cannot meet all the statutory criteria needed to qualify for MYP. As shown in the case

of the first four Virginia-class boats, this can occur at or near the start of a procurement program,

when design stability has not been demonstrated through the production of at least a few of the

items to be procured (or, for a shipbuilding program, at least one ship).

MYP and BBC vs. Contracts with Options

What is the difference between an MYP or block buy contract and a contract with options? The

military services sometimes use contracts with options to procure multiple copies of an item that

are procured over a period of several years. The Navy, for example, used a contract with options

to procure Lewis and Clark (TAKE-1) class dry cargo ships that were procured over a period of

several years. A contract with options can be viewed as somewhat similar to an MYP or block

buy contract in that a single contract is used to procure several years’ worth of procurement of a

given kind of item.

There is, however, a key difference between an MYP or block buy contract and a contract with

options: In a contract with options, the service is under no obligation to exercise any of the

options, and a service can choose to not exercise an option without having to make a penalty

payment to the contractor. In contrast, in an MYP or block buy contract, the service is under an

23 For further discussion, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and

Issues for Congress, by Ronald O'Rourke.

24 For further discussion, see CRS Report R43546, Navy John Lewis (TAO-205) Class Oiler Shipbuilding Program:

Background and Issues for Congress, by Ronald O'Rourke.

25 For more on the CVN-78 class program, see CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier

Program: Background and Issues for Congress, by Ronald O'Rourke.

26 For more on the KC-46 program, see CRS Report RL34398, Air Force KC-46A Pegasus Tanker Aircraft Program,

coordinated by John R. Hoehn.

Congressional Research Service

11

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

obligation to continue implementing the contract beyond the first year, provided that Congress

appropriates the necessary funds. If the service chooses to terminate an MYP or block buy

contract, and does so as a termination for government convenience rather than as a termination

for contractor default, then the contractor can, under the contract’s termination for convenience

clause, seek a payment from the government for cost incurred for work that is complete or in

process at the time of termination, and may include the cost of some of the investments made in

anticipation of the MYP or block buy contract being fully implemented. The contractor can do

this even if the MYP or block buy contract does not elsewhere include a provision for a

cancellation penalty.27

As a result of this key difference, although a contract with options looks like a multiyear contract,

it operates more like a series of annual contracts, and it cannot achieve the kinds of savings that

are possible under MYP and BBC.

Issues for Congress

Potential issues for Congress concerning MYP and BBC include whether to use MYP and BBC in

the future more frequently, less frequently, or about as frequently as they are currently used; and

whether to create a permanent statute to govern the use of BBC, analogous to the permanent

statute that governs the use of MYP.

Frequency of Using MYP and BBC

Overview

Should MYP and BBC in the future be used more frequently, less frequently, or about as

frequently as they are currently used? Supporters of using MYP and BBC more frequently in the

future might argue the following:

•

•

Since MYP and BBC can reduce procurement costs, making greater use of MYP

and BBC can help DOD get more value out of its available procurement funding.

This can be particularly important if DOD’s budget in real (i.e., inflationadjusted) terms remains flat or declines in coming years.

The risks of using MYP have been reduced by Section 811 of the FY2008 NDAA

(H.R. 4986/P.L. 110-181 of January 28, 2008), which amended what is now 10

U.S.C. 3501 to strengthen the process for ensuring that programs proposed for

MYP meet certain criteria (see “Permanent Statute Governing MYP”).

Supporters of using MYP and BBC less frequently in the future, or at least no more frequently

than now, might argue the following:

•

•

Using MYP and BBC more frequently would further reduce Congress’s and

DOD’s flexibility for making changes in DOD procurement programs in future

years in response to changing strategic or budgetary circumstances.

Since actual savings from using MYP and BBC rather than annual contracting

can be difficult to observe or verify, it is not clear that the financial benefits of

27 Source: Telephone discussion with Elliott Branch, Deputy Assistant Secretary of the Navy for Acquisition &

Procurement, October 3, 2011, and email from Navy Office of legislative Affairs, October 11, 2011. Under the

termination for convenience clause, the contractor can submit a settlement proposal to the service, which would

become the basis for a negotiation between the contractor and the service on the amount of the payment.

Congressional Research Service

12

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

using MYP or BBC more frequently in the future would be worth the resulting

further reduction in Congress’s and DOD’s flexibility for making changes in

procurement programs in future years in response to changing strategic or

budgetary circumstances.

Interest in Using Multiyear Contracting for Procuring Munitions

The war in Ukraine heightened interest among Members of Congress, DOD officials, industry

officials, and other observers in making increased use of multiyear contracting for procuring

munitions, particularly so as to encourage munitions makers to make investments for expanding

their production facilities for supporting increased annual procurement rates.28 Section 1244(c) of

the FY2023 NDAA (H.R. 7776/P.L. 117-263 of December 23, 2022) provided authority for using

multiyear contracting for the following munitions:

•

•

•

•

•

•

•

•

•

•

•

•

•

•

864,000 XM1128, XM1113, M107, and M795 155mm artillery shells;

12,000 AGM-179 Joint Air-to-Ground Missiles (JAGMs);

700 M142 High Mobility Artillery Rocket Systems (HIMARS);

1,700 MGM-140 Army Tactical Missile Systems (ATACMS);

2,600 Harpoon anti-ship cruise missiles;

1,250 Naval Strike Missiles (NSMs) (anti-ship missiles);

106,000 Guided Multiple Launch Rocket Systems (GMLRS);

3,850 PATRIOT Advanced Capability-3 (PAC-3) Missile Segment Enhancement

(MSE);

5,600 FIM-92 Stinger air defense missiles;

28,300 FGM-148 Javelin anti-tank missiles;

5,100 AIM-120 Advanced Medium-Range Air-to-Air Missiles (AMRAAMs);

2,250,000 Modular Artillery Charge System (MACS);

12,050 155m Excalibur M982A1 artillery shells;

950 Long Range Anti-Ship Missiles (LRASMs);

28 See Stephen Losey, “Gen. CQ Brown: Multiyear Missile Buys Would Stabilize Industry,” Defense News, June 7,

2023; Joe Gould, “Army to Seek Multiyear Munitions Buys in Next Budget,” Defense News, March 3, 2023;

Mackenzie Eaglen and Bill Greenwalt, “The Army’s Multiyear Contracts Are a Model for Other Services,” Defense

News, February 3, 2023; Rich Abott, “Navy Looks To Expand Naval Strike Missile Production For Multiyear

Procurement,” Defense Daily, December 13, 2022; Nick Wilson, “Navy Signals Interest in Multiyear Procurement for

Naval Strike Missiles,” Inside Defense, December 12, 2022; Jen Judson, “US Army Weighs Multiyear Contracts for

Munitions to Aid Ukraine,” Defense News, November 21, 2022; Matthew Beinart, “Army Acquisition Chief Cites

Munitions That Could ‘Potentially’ Benefit From Multi-Year Buy Authorities,” Defense Daily, November 22, 2022;

Lee Hudson, “Raytheon Backs Multiyear Buy for Munitions, CFO says,” Politico Pro, November 8, 2022; Joe Gould,

“Congress Poised to Back Multiyear Weapons Purchases, LaPlante Says,” Defense News, November 7, 2022; Matthew

Beinart, “Congress Will Support Authority For Multi-Year Munitions Procurements, LaPlante Says,” Defense Daily,

November 7, 2022; Brian Everstine, “Top U.S. Navy Officer Calls For Multiyear Weapons Procurement,” Aviation

Week, October 19, 2022; John Ferrari, “Four Steps the Pentagon Can Take to Fix the Munitions Industrial Base,” The

Hill, October 17, 2022; Andrew Eversden, “Army Acquisition Chief ‘Not Uncomfortable’ with US Stockpiles,

Considers Multi-Year Deals,” Breaking Defense, September 14, 2022; Mackenzie Eaglen and Bill Greenwalt,

“Multiyear Contracts Could Solve Plenty of Pentagon Problems,” Defense News, September 28, 2022; Marcus

Weisgerber, “US Should Place Multiyear Munitions Orders to Protect Supply, Pentagon Arms Chief Says,” Defense

One, September 7, 2022; Lee Hudson, “LaPlante Wants Multiyear Contracts for Missiles,” Politico Pro, September 7,

2022.

Congressional Research Service

13

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

•

•

•

3,100 Joint Air-to-Surface Standoff Missiles (JASSMs);

1,500 Standard Missle-6 (SM-6) surface-to-air missiles; and

5,100 Sidewinder Missiles (AIM-9X) air-to-air missiles.

Regarding Section 1244(c), the joint explanatory statement for H.R. 7776/P.L. 117-263 states

(emphasis added)

We recognize that the Department of Defense (DOD) would benefit from temporary

acquisition flexibilities to increase the Department’s stocks of critical munitions, provide

material and related services to allies and partners that have supported Ukraine, and provide

material and services to Ukraine. We also support enabling the Secretary of Defense to

enter into cooperative acquisition agreements through the North Atlantic Treaty

Organization (NATO) Support and Procurement Organization. Finally, we believe

providing multi-year procurement authority for certain munitions programs is

essential to increase the Department’s stocks of such munitions, improve warfighting

readiness, provide the defense industrial base with predictable production

opportunities and firm contractual commitments, ensure consistent funding across

the Department’s Future Years Defense Program, increase and expand defense

industrial capacity, and coordinate the timing and funding for capital expenditures

with defense contractors. (PDF page 295 of 748)

Adequacy of Information Submitted for MYP Contracts

Do the military services submit to Congress adequate information regarding MYP contracts?

An August 2022 GAO report addressing this question in relation to Navy MYP contracts stated

The Navy used multiyear procurement—a special method to contract for multiple years of

requirements in a single contract—for seven critical weapon system programs in fiscal

years 2021 and 2022. This contracting method can save the government money through

procurement efficiencies but can include future financial commitments. GAO reviewed the

seven programs and found that the budget requests for three programs included quantity

reductions when compared to their multiyear contracts or previous Navy plans. This

hampered their efforts to meet warfighting needs:

• DDG 51 destroyers. The budget request for fiscal year 2022 included funds to procure

one of the two ships in the program’s multiyear contracts. Instead of requesting funding

for the second ship, the Navy requested $33 million to cover the government’s cancellation

liability for reducing its procurement to one ship in fiscal year 2022.

• V-22 aircraft. The budget request for fiscal year 2022 included funds to procure eight of

the 11 aircraft in the program’s multiyear contract for the budget year. The Navy used

additional aircraft funded but not procured in fiscal year 2021 to offset the reduced request

and meet the stated contract quantity for fiscal year 2022.

• Virginia class submarines. The budget request in fiscal year 2021 included funding for

one submarine. This met the multiyear contract quantity but departed from previous

multiyear procurement plans, the steady practice of procuring two of the submarines each

year, and congressional direction.

Navy officials told GAO that affordability was the primary driver leading to the reduction

in quantities requested for DDG 51 and V-22 in the fiscal year 2022 budget. However,

GAO found that Department of Defense financial management regulation does not require

the Navy to notify the congressional defense committees of its rationale for budget

decisions that do not support the procurement quantities stated in multiyear contracts. The

lack of such notification can hamper the ability of the committees to oversee programs and

make decisions without having to request supplemental information and explanations from

the Navy.

Congressional Research Service

14

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

The Navy included additional quantities for the DDG 51, V-22, and Virginia class

programs in unfunded priorities lists provided to the defense committees. Congress

ultimately decided to fund the procurement of additional quantities.29

Permanent Statute for BBC

Should Congress create a permanent statute to govern the use of BBC, analogous to the

permanent statute (10 U.S.C. 3501) that governs the use of MYP? Supporters of creating a

permanent statute to govern the use of BBC might argue the following:

•

•

Such a statute could encourage greater use of BBC, and thereby increase savings

in DOD procurement programs by giving BBC contracting a formal legal

standing and by establishing a clear process for DOD program managers to use in

assessing whether their programs might be considered suitable for BBC.

Such a statute could make BBC more advantageous by including a provision that

automatically grants EOQ authority to programs using BBC, as well as

provisions establishing qualifying criteria and other conditions intended to reduce

the risks of using BBC.

Opponents of creating a permanent statute to govern the use of BBC might argue the following:

•

•

A key advantage of BBC is that it is not governed by a permanent statute. The

lack of such a statute gives DOD and Congress full flexibility in determining

when and how to use BBC for programs that may not qualify for MYP, but for

which a multiyear contract of some kind might produce significant savings.

Such a statute could encourage DOD program managers to pursue their programs

using BBC rather than MYP. This could reduce discipline in DOD multiyear

contracting if the qualifying criteria in the BBC statute are less demanding than

the qualifying criteria in 10 U.S.C. 3501.

Coast Guard Use of MYP and BBC

Should the Coast Guard should begin making use of MYP and BBC? Although the Coast Guard

is part of the Department of Homeland Security (DHS), the Coast Guard is a military service and

a branch of the U.S. Armed Forces at all times (14 U.S.C. 101), and 10 U.S.C. 3501 provides

authority for using MYP not only to DOD, but also to the Coast Guard (and the National

Aeronautics and Space Administration as well). In addition, Section 311 of the Frank LoBiondo

Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of December 4, 2018) provides

permanent authority for the Coast Guard to use block buy contracting with EOQ purchases of

components in major acquisition programs. The authority is now codified at 14 U.S.C. 1137.

The Navy in recent years has made extensive use of MYP and BBC in its ship and aircraft

acquisition programs. The Coast Guard, like the Navy, procures ships and aircraft. In contrast to

the Navy, however, the Coast Guard has never used MYP or BBC in its ship or aircraft

acquisition programs. Instead, the Coast has tended to use contracts with options. As discussed

earlier, although a contract with options looks like a multiyear contract, it operates more like a

series of annual contracts, and it cannot achieve the kinds of savings that are possible under MYP

and BBC. CRS in recent years has testified and reported on the possibility of using BBC or MYP

29 Government Accountability Office, Multiyear Procurement[:] Navy Should Provide Congress More Complete

Information on Budget Request Decisions, GAO-22-105966, August 2022, Highlights page.

Congressional Research Service

15

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

in Coast Guard ship acquisition programs, particularly the Coast Guard’s 25-ship Offshore Patrol

Cutter (OPC) program and the Coast Guard’s three-ship polar icebreaker program.30

Legislative Activity for FY2026

Proposals for MYP and Block Buy Contracts in DOD’s FY2026

Budget Submission

DOD’s FY2026 budget submission requests continued funding for implementing MYP contracts

initiated in fiscal years prior to FY2026. DOD for FY2026 is also requesting authorization for a

block buy contract beginning in FY2026 for procuring up to five Columbia-class ballistic missile

submarines (SSBNs). Columbia-class submarines are programmed to be procured in FY2026 and

subsequent years at a rate of one ship per year. A block buy contract for procuring five Columbiaclass submarines beginning in FY2026 would thus include boats to be procured in FY2026FY2030.31

FY2026 National Defense Authorization Act (H.R. 3838/S. 2296)

House

In H.R. 3838 as reported by the House Armed Services Committee (H.Rept. 119-231 of August

19, 2025),

•

•

•

•

•

•

Section 111 would provide authority for an MYP contract beginning in FY2027

for UH–60 Blackhawk helicopters;

Section 121 would provide authority for a block buy contract for not more than

two Gerald R. Ford (CVN-78) class aircraft carriers;

Section 122 would provide authority for a block buy contract beginning in

FY2026 for up to five Columbia (SSBN-826) class ballistic missile submarines;

Section 123 would provide authority for a contract for the advance procurement

of components for Virginia (SSN-774) class attack submarines;

Section 125 would provide authority for an MYP contract beginning in FY2026

for yard, repair, berthing, and messing barges and associated material;

Section 801 would require DOD to enter into an MYP contact for a major

weapon system (as defined in 10 U.S.C. 3455) if a decision has been made to

move the system to full-rate production; the system is projected to maintain fullrate production for a period of five or more consecutive years after entering into

such a contract; the planned procurement schedule, conducted at the most

effective production rate, will require 36 months or more to obtain the total

quantity of units to be procured until procurement is complete; and the system is

30 For additional discussion, see CRS Testimony TE10004, The Status of Coast Guard Cutter Acquisition Programs, by

Ronald O'Rourke; CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by

Ronald O'Rourke; and CRS Report RL34391, Coast Guard Polar Security Cutter (Polar Icebreaker) Program:

Background and Issues for Congress, by Ronald O'Rourke.

31 For more on the Columbia-class program, see CRS Report R41129, Navy Columbia (SSBN-826) Class Ballistic

Missile Submarine Program: Background and Issues for Congress, by Ronald O'Rourke.

Congressional Research Service

16

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

•

estimated by DOD to have a total procurement cost of more than $1 billion in

constant FY2025 dollars; and

Section 2807 would provide authority for MYP contracts during FY2026 for any

purchase relating certain military construction projects for unaccompanied

housing or military child development centers.

H.Rept. 119-231 states:

Feasibility and Advisability of Combining CH–47F and MH–47G Contracts

The committee is aware that the Army and United States Special Operations Command

(USSOCOM) currently procure the CH–47F and MH–47G Chinook on two separate

contract vehicles with different funding lines, acquisition and contracting authorities, and

aircraft configurations. The committee believes there could be cost savings for the Army

and USSOCOM if these contracts were combined.

Therefore, the committee directs the Under Secretary of Defense for Acquisition and

Sustainment to provide a report to the House Committee on Armed Services not later than

December 1, 2025, on the feasibility and advisability of combining the CH–47F and MH–

47G contracts. The report shall also include, but not be limited to:

(1) any potential cost savings or program efficiencies that could be found as a result of

combining procurement contracts; and

(2) any potential cost savings as a result of using multi-year procurement contracting,

including through the use of Advance Procurement funding. (Page 6)

H.Rept. 119-231 also states:

Report on Multi-Year Procurement Contract for C–130J Recapitalization

The committee notes that Multi-Year Procurement (MYP–III) for the C–130J program

provided cost savings greater than 10 percent per aircraft over more than 50 C–130J

aircraft. As the C–130J program remains the only active U.S. airlifter production line and

given growing threats across the globe, continued reliance on C–130H and C–130T

inventory remains an important factor in near-peer conflict scenarios. The committee

understands that the validated requirements and increasing demand for C–130 inventory

recapitalization within the department could provide the need for a follow-on Multi-Year

Procurement (MYP–IV) program. Therefore, the committee directs the Secretary of the

Air Force, in coordination with the Secretary of the Navy, to submit a report to the

congressional defense committees by March 1, 2026, on the benefits of a multi-year

procurement contract for the C–130J recapitalization program for the whole of the United

States Government. The report shall include the following:

(1) potential cost savings associated with a multi-year procurement contract, including any

reductions in procurement costs, operational costs, and maintenance costs;

(2) impacts of a multi-year procurement contract on the defense industrial base, including

any effects on production rates, workforce stability, and supplier relationships;

(3) ability of a multi-year procurement contract to provide stability and predictability for

the C–130J program, including any benefits for planning, budgeting, and resource

allocation;

(4) potential risks and challenges associated with a multi-year procurement contract,

including any risks related to program requirements, funding, or contractor performance;

and

(5) lessons learned or best practices from other multi-year procurement contracts, including

any relevant experiences from other military services or government agencies. (Page 42)

Congressional Research Service

17

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

H.Rept. 119-231 also states:

Report on Block Buys

The committee is concerned that the Department of Defense is not fully utilizing block

buys to address skilled workforce and supply chain challenges. The committee recognizes

that block buys provide the Defense Industrial Base (DIB) a consistent demand signal,

allowing cost and amortization of investments to be managed more efficiently by allocation

over longer periods of time and in larger quantities. This approach can optimize resources,

enhance competitiveness and innovation, increase supply chain stability, and reduce costs

of products and services for the Department.

Therefore, the committee directs the Secretary of Defense, in coordination with the Service

Secretaries, to provide a report to the House Committee on Armed Services not later than

March 1, 2026, describing how the Department intends to enhance its use of block buys to

more effectively promote a skilled workforce and reliable supply chain to meet Department

requirements by:

(1) optimizing efficiency and supporting competition and innovation in the acquisition of

commercial products and services;

(2) maximizing benefits to the DIB and the taxpayer through stability in demand;

(3) streamlining procurements and minimizing unnecessary contracting actions;

(4) reducing risk of foreign-connected business and investment in the DIB by securing

supply chains through stable, dependable cashflow through longer-term contracts; and

(5) including recommendations to improve the use of block buys consistent with the other

enumerated requirements of the report. (Page 236)

H.Rept. 119-231 also states:

Lower Tier Air and Missile Defense Sensor

The committee understand the Army plans to fully modernize Patriot battalions through

the annual procurement of Low Tier Air and Missile Defense Sensor (LTAMDS) radars.

Given the long-term nature of this plan, the committee directs the Secretary of the Army

to provide a briefing to the House Committee on Armed Services not later than April 1,

2026, on the feasibility of entering into a multiyear contract for procurement of the

LTADMS. The briefing should include the following:

(1) an estimated timeline for equipping all Patriot battalions with LTAMDS under the

current program of record;

(2) an analysis of at least two different multi-year contract options that vary in either

duration or quantity, at least one of which assumes an average procurement of three

battalions of radars per year;

(3) an assessment of potential cost and schedule savings that could be achieved through a

multiyear procurement approach;

(4) an assessment of potential impacts to the industrial base that could be achieved through

a multiyear procurement approach; and

(5) any other matters the Secretary of the Army considers appropriate. (Pages 364-365)

Senate

In S. 2296 as reported by the Senate Armed Services Committee (S.Rept. 119-39 of July 15,

2025)

Congressional Research Service

18

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

•

•

Section 121 would provide authority for a block buy contract beginning in

FY2026 for procuring not more than five Columbia-class submarines, and

Section 122 would provide authority for a block buy contract beginning in

FY2026 or FY2027 for procuring not more than 15 Medium Landing Ships

(LSMs).

Regarding Section 122, S.Rept. 119-39 states

Sec. 122—Procurement authorities for Medium Landing Ships

The committee recommends a provision that would provide authorities for a block buy of

up to 15 Medium Landing Ships to support testing and experimentation of the Marine

Littoral Regiment formation. The committee notes that this authority may include the lead

ship and follow on commercial or non-developmental ships as authorized under section

128(b) of the Servicemember Quality of Life Improvement and National Defense

Authorization Act for Fiscal Year 2025 (118–159). (Page 5)

S.Rept. 119-39 also states

UH–60M Black Hawk modernization

The committee notes that in February 2024, the Army announced its Aviation Rebalance

Initiative to reallocate its aviation modernization investments across new and enduring

platforms to meet emerging capability requirements in a resource constrained environment.

As part of that announcement, the Army committed to pursuing a new Multi-Year

Procurement (MYP) contract starting in fiscal year 2027 for new UH–60M Black Hawk

aircraft when the current MYP is completed at the end of fiscal year 2026. This new MYP

is needed to ensure adequate inventories of UH–60M helicopters for the active Army and

the Army National Guard (ARNG), given the Army’s decision to cancel the UH–60V

modification program. Even as the Army develops the Future Long Range Assault Aircraft,

the Army has stated that the UH–60M will remain a large part of the Army’s active and

ARNG aviation fleet for decades to come.

The committee endorses the Army’s efforts to continue to procure and modernize the UH–

60M Black Hawk as part of the future aviation force. The committee supports Army efforts

to prepare for a fiscal year 2027 MYP, including any long lead or advance procurement

actions that can be taken to streamline schedules, maintain the supplier base, and secure

key components to ensure timely deliveries.

Therefore, the committee directs the Secretary of the Army to provide a briefing, not later

than September 30, 2026, to the Committees on Armed Services of the Senate and the

House of Representatives, on measures the Army is taking to support a new MYP for the

UH–60M Black Hawk, including the number of aircraft to be included in the new MYP,

delivery schedules, and contracting in advance for key components and subsystems. The

briefing should also include an assessment of the total UH–60M requirement for the active

and ARNG aviation fleet in light of the cancellation of the UH–60V modification program.

(Pages 38-39)

S.Rept. 119-39 also states

Lower Tier Air and Missile Defense Sensor acquisition

The committee strongly supports accelerated integrated air and missile defense (IAMD)

modernization but understands that the Army has not committed to supporting any partner

procurement of the Lower Tier Air and Missile Defense Sensor (LTAMDS) system unless

there is parallel procurement of the Integrated Battle Command System.

Accordingly, the committee directs the Secretary of the Army to provide a one-time

briefing to the congressional defense committees, not later than March 31, 2026, on the

following subjects: (1) Potential adjustments to the LTAMDS acquisition strategy,

Congressional Research Service

19

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

including advance procurement of up to three battalions of radars per year and the use of

multi-year procurement to achieve a higher annual production rate; (2) Possible annual

savings associated with bundling partner procurement of LTAMDS over the period of the

multi-year; and (3) An operational summary of how procurement of LTAMDS at full rate

to meet global demand would enhance IAMD in the U.S. European, Central, and IndoPacific Commands’ areas of responsibility. (Page 274)

FY2026 DOD Appropriations Act (H.R. 4016/S. 2572)

House

In H.R. 4016 as reported by the House Appropriations Committee (H.Rept. 119-162 of June 16,

2025), Section 8010 states

Sec. 8010. None of the funds provided by this Act shall be available to initiate: (1) a

multiyear contract that employs economic order quantity procurement in excess of

$20,000,000 in any one year of the contract or that includes an unfunded contingent

liability in excess of $20,000,000; or (2) a contract for advance procurement leading to a

multiyear contract that employs economic order quantity procurement in excess of

$20,000,000 in any one year, unless the congressional defense committees have been

notified at least 30 days in advance of the proposed contract award: Provided, That no part

of any appropriation contained in this Act shall be available to initiate a multiyear contract

for which the economic order quantity advance procurement is not funded at least to the

limits of the Government's liability: Provided further, That no part of any appropriation

contained in this Act shall be available to initiate multiyear procurement contracts for any

systems or component thereof if the value of the multiyear contract would exceed

$500,000,000 unless specifically provided in this Act: Provided further, That no multiyear

procurement contract can be terminated without 30-day prior notification to the

congressional defense committees: Provided further, That the execution of multiyear

authority shall require the use of a present value analysis to determine lowest cost

compared to an annual procurement: Provided further, That none of the funds provided by

this Act may be used for a multiyear contract executed after the date of the enactment of

this Act unless in the case of any such contract—

(1) the Secretary of Defense has submitted to Congress a budget request for full funding of

units to be procured through the contract and, in the case of a contract for procurement of

aircraft, that includes, for any aircraft unit to be procured through the contract for which

procurement funds are requested in that budget request for production beyond advance

procurement activities in the fiscal year covered by the budget, full funding of procurement

of such unit in that fiscal year;

(2) cancellation provisions in the contract do not include consideration of recurring

manufacturing costs of the contractor associated with the production of unfunded units to

be delivered under the contract;

(3) the contract provides that payments to the contractor under the contract may not be

made in advance of incurred costs on funded units; and

(4) the contract does not provide for a price adjustment based on a failure to award a followon contract.

Senate

In S. 2572 as reported by the Senate Appropriations Committee (S.Rept. 119-52 of July 31,

2025), Section 8010 states

Congressional Research Service

20

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

SEC. 8010. None of the funds provided in this Act shall be available to initiate: (1) a

multiyear contract that employs economic order quantity procurement in excess of

$20,000,000 in any one year of the contract or that includes an unfunded contingent

liability in excess of $20,000,000; or (2) a contract for advance procurement leading to a

multiyear contract that employs economic order quantity procurement in excess of

$20,000,000 in any one year, unless the congressional defense committees have been

notified at least 30 days in advance of the proposed contract award: Provided, That no part

of any appropriation contained in this Act shall be available to initiate a multiyear contract

for which the economic order quantity advance procurement is not funded at least to the

limits of the Government’s liability: Provided further, That no part of any appropriation

contained in this Act shall be available to initiate multiyear procurement contracts for any

systems or component thereof if the value of the multiyear contract would exceed

$500,000,000 unless specifically provided in this Act: Provided further, That no multiyear

procurement contract can be terminated without 30-day prior notification to the

congressional defense committees: Provided further, That the execution of multiyear

authority shall require the use of a present value analysis to determine lowest cost

compared to an annual procurement: Provided further, That none of the funds provided in

this Act may be used for a multiyear contract executed after the date of the enactment of

this Act unless in the case of any such contract—

(1) the Secretary of Defense has submitted to Congress a budget request for full funding of

units to be procured through the contract and, in the case of a contract for procurement of

aircraft, that includes, for any aircraft unit to be procured through the contract for which

procurement funds are requested in that budget request for production be yond advance

procurement activities in the fiscal year covered by the budget, full funding of procurement

of such unit in that fiscal year;

(2) cancellation provisions in the contract do not include consideration of recurring

manufacturing costs of the contractor associated with the production of unfunded units to

be delivered under the contract;

(3) the contract provides that payments to the contractor under the contract shall not be

made in advance of incurred costs on funded units; and

(4) the contract does not provide for a price adjustment based on a failure to award a followon contract.

S.Rept. 119-52 states

MUNITIONS

For several fiscal years, the Committee has emphasized targeted investments in critical

munitions production lines, the use of multiyear procurement contracts, and analysis of

defense industrial supply chains in order to improve warfighter readiness and provide more

predictable funding to the military services and the munitions industrial base. These

investments must be paired with substantive defense industry steps to provide transparent,

sustainable, and cost-effective pricing, rapid development, and modern manufacturing

processes to ensure the best value for the taxpayer. The Committee recognizes the lessons

that current conflicts provide with regard to the need for increased magazine depth, larger

manufacturing capacity, and lower unit costs for high-end interceptors and sophisticated

long-range fires relied upon by U.S. and allied forces. To this end, the Committee

appreciates that the Department of Defense has re-invigorated these shared goals, and

considers the fiscal year 2026 President’s budget request an opportunity to deepen shared

commitment to sustained investment in, and expanded production capacity of, critical

munitions.

In reviewing the fiscal year 2026 budget request, however, the Committee found the

Department did not plan to fully maximize the capacity of a number of critical munitions

production lines and did not request sufficient resources to increase production capacity of

Congressional Research Service

21

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

other lines. Within the limited resources available, the Committee’s recommendations

make significant down payments on efforts to deepen America’s magazine of critical

munitions. The Committee expresses concern that only with adequate prioritization of

munitions programs by the services in their annual budgets and acquisition processes, as

well as greater investment in the organic industrial base, will sufficient progress be made

on this urgent issue.

The Committee recommends $5,171,896,000 above the fiscal year 2026 President’s budget

request for additional all-up rounds and $2,094,375,000 above the fiscal year 2026

President’s budget request for facilitization in the industrial base. (Pages 7-8)

S.Rept. 119-52 also states

Multi-Year Procurement Contracts for Critical Munitions.—In the Department of Defense

Appropriations Act, 2024 (Public Law 118–47), Congress supported the Department’s

requests for multi-year procurement [MYP] authority for six critical munitions programs.

The Committee continues to closely monitor the progress of these programs and is

concerned by the continuing delays in definitizing and executing these contracts. The

Committee is particularly concerned by the inability of the Department of the Air Force

and certain defense contractors to proceed with a MYP contract for the Advanced MediumRange Air-to-Air Missile, as approved by Congress in fiscal year 2024. The Committee

notes that this avoidable failure has resulted in lost opportunities to stabilize the supply

chain and further delays production. The Committee reiterates its expectation that these

procurements should result in unit cost savings, stability in the supplier base, industry

investment in expanding and upgrading their facilities, and weapons being delivered at cost

and on or ahead of schedule. Accordingly, the Committee directs the Secretary of Defense

to provide a semi-annual report to the congressional defense committees on the status of

each such munition MYP award until all munitions covered under such award have been

delivered, to include projected and realized cost savings, the amount and impact of

government and industry investment on capacity and associated supply chains, and an

assessment of the extent to which such award has generated greater stability in the

associated supply chain. (Page 80)

Streamlining Procurement for Effective Execution and Delivery Act

of 2025 (SPEED Act) (H.R. 3838)

House

H.R. 3838 was introduced in the House on June 9, 2025. In H.R. 3838 as introduced, Section 303

would make adjustments to certain acquisition thresholds. Subsection 303(d) states

(d) Multiyear contracts.—Section 3501 of title 10, United States Code, is amended—

(1) by striking “$500,000,000” each place it appears and inserting “$1,000,000,000”;

(2) by striking “$100,000,000” each place it appears and inserting “$150,000,000”; and

(3) by striking “$20,000,000” each place it appears and inserting “$50,000,000”.

Congressional Research Service

22

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Appendix A. Text of 10 U.S.C. 3501

The text of 10 U.S.C. 3501 as of July 9, 2025, is as follows:

§3501. Multiyear contracts: acquisition of property

(a) In General.-To the extent that funds are otherwise available for obligation, the head of

an agency may enter into multiyear contracts for the purchase of property whenever the

head of that agency finds each of the following:

(1) That the use of such a contract will result in(A) significant savings of the total anticipated costs of carrying out the program through

annual contracts; or

(B) necessary defense industrial base stability not otherwise achievable through annual

contracts.

(2) That the minimum need for the property to be purchased is expected to remain

substantially unchanged during the contemplated contract period in terms of production

rate, procurement rate, and total quantities.

(3) That there is a reasonable expectation that throughout the contemplated contract period

the head of the agency will request funding for the contract at the level required to avoid

contract cancellation.

(4) That there is a stable design for the property to be acquired and that the technical risks

associated with such property are not excessive.

(5) That the estimates of both the cost of the contract and the anticipated cost avoidance

through the use of a multiyear contract are realistic.

(6) In the case of a purchase by the Department of Defense, that the use of such a contract

will promote the national security of the United States.

(7) In the case of a contract in an amount equal to or greater than $500,000,000, that the

conditions required by subparagraphs (C) through (F) of subsection (i)(3) will be met, in

accordance with the Secretary’s certification and determination under such subsection, by

such contract.

(b) Regulations.-(1) Each official named in paragraph (2) shall prescribe acquisition

regulations for the agency or agencies under the jurisdiction of such official to promote the

use of multiyear contracting as authorized by subsection (a) in a manner that will allow the

most efficient use of multiyear contracting.

(2)(A) The Secretary of Defense shall prescribe the regulations applicable to the

Department of Defense.

(B) The Secretary of Homeland Security shall prescribe the regulations applicable to the

Coast Guard, except that the regulations prescribed by the Secretary of Defense shall apply

to the Coast Guard when it is operating as a service in the Navy.

(C) The Administrator of the National Aeronautics and Space Administration shall

prescribe the regulations applicable to the National Aeronautics and Space Administration.

(c) Contract Cancellations.-The regulations may provide for cancellation provisions in

multiyear contracts to the extent that such provisions are necessary and in the best interests

of the United States. The cancellation provisions may include consideration of both

recurring and nonrecurring costs of the contractor associated with the production of the

items to be delivered under the contract.

Congressional Research Service

23

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

(d) Participation by Subcontractors, Vendors, and Suppliers.-In order to broaden the

defense industrial base, the regulations shall provide that, to the extent practicable(1) multiyear contracting under subsection (a) shall be used in such a manner as to seek,

retain, and promote the use under such contracts of companies that are subcontractors,

vendors, or suppliers; and

(2) upon accrual of any payment or other benefit under such a multiyear contract to any

subcontractor, vendor, or supplier company participating in such contract, such payment

or benefit shall be delivered to such company in the most expeditious manner practicable.

(e) Protection of Existing Authority.-The regulations shall provide that, to the extent

practicable, the administration of this section, and of the regulations prescribed under this

section, shall not be carried out in a manner to preclude or curtail the existing ability of an

agency(1) to provide for competition in the production of items to be delivered under such a

contract; or

(2) to provide for termination of a prime contract the performance of which is deficient

with respect to cost, quality, or schedule.

(f) Cancellation or Termination for Insufficient Funding.-In the event funds are not made

available for the continuation of a contract made under this section into a subsequent fiscal

year, the contract shall be canceled or terminated. The costs of cancellation or termination

may be paid from(1) appropriations originally available for the performance of the contract concerned;

(2) appropriations currently available for procurement of the type of property concerned,

and not otherwise obligated; or

(3) funds appropriated for those payments.

(g) Contract Cancellation Ceilings Exceeding $100,000,000.-(1) Before any contract

described in subsection (a) that contains a clause setting forth a cancellation ceiling in

excess of $100,000,000 may be awarded, the head of the agency concerned shall give

written notification of the proposed contract and of the proposed cancellation ceiling for

that contract to the congressional defense committees, and such contract may not then be

awarded until the end of a period of 30 days beginning on the date of such notification.

(2) In the case of a contract described in subsection (a) with a cancellation ceiling described

in paragraph (1), if the budget for the contract does not include proposed funding for the

costs of contract cancellation up to the cancellation ceiling established in the contract, the

head of the agency concerned shall, as part of the certification required by subsection

(i)(1)(A),1 give written notification to the congressional defense committees of(A) the cancellation ceiling amounts planned for each program year in the proposed

multiyear procurement contract, together with the reasons for the amounts planned;

(B) the extent to which costs of contract cancellation are not included in the budget for the

contract; and

(C) a financial risk assessment of not including budgeting for costs of contract cancellation.

(h) Defense Acquisitions of Weapon Systems.-In the case of the Department of Defense,

the authority under subsection (a) includes authority to enter into the following multiyear

contracts in accordance with this section:

(1) A multiyear contract for the purchase of a weapon system, items and services associated

with a weapon system, and logistics support for a weapon system.

Congressional Research Service

24

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

(2) A multiyear contract for advance procurement of components, parts, and materials

necessary to the manufacture of a weapon system, including a multiyear contract for such

advance procurement that is entered into in order to achieve economic-lot purchases and

more efficient production rates.

(i) Defense Acquisitions Specifically Authorized by Law.-(1) In the case of the Department

of Defense, a multiyear contract in an amount equal to or greater than $500,000,000 may

not be entered into under this section unless the contract is specifically authorized by law

in an Act other than an appropriations Act.

(2) In submitting a request for a specific authorization by law to carry out a defense

acquisition program using multiyear contract authority under this section, the Secretary of

Defense shall include in the request a report containing preliminary findings of the agency

head required in paragraphs (1) through (6) of subsection (a), together with the basis for

such findings.

(3) A multiyear contract may not be entered into under this section for a defense acquisition

program that has been specifically authorized by law to be carried out using multiyear

contract authority unless the Secretary of Defense certifies in writing, not later than 30 days

before entry into the contract, that each of the following conditions is satisfied:

(A) The Secretary has determined that each of the requirements in paragraphs (1) through

(6) of subsection (a) will be met by such contract and has provided the basis for such

determination to the congressional defense committees.

(B) The Secretary’s determination under subparagraph (A) was made after completion of

a cost analysis conducted on the basis of section 3226(b) of this title, and the analysis

supports the determination.

(C) The system being acquired pursuant to such contract has not been determined to have

experienced cost growth in excess of the critical cost growth threshold pursuant to section

4374 of this title within 5 years prior to the date the Secretary anticipates such contract (or

a contract for advance procurement entered into consistent with the authorization for such

contract) will be awarded.

(D) A sufficient number of end items of the system being acquired under such contract

have been delivered at or within the most current estimates of the program acquisition unit

cost or procurement unit cost for such system to determine that current estimates of such

unit costs are realistic.

(E) During the fiscal year in which such contract is to be awarded, sufficient funds will be

available to perform the contract in such fiscal year, and the future-years defense program

for such fiscal year will include the funding required to execute the program without

cancellation.

(F) The contract is a fixed price type contract.

(G) The proposed multiyear contract provides for production at not less than minimum

economic rates given the existing tooling and facilities.

(4) If for any fiscal year a multiyear contract to be entered into under this section is

authorized by law for a particular procurement program and that authorization is subject to

certain conditions established by law (including a condition as to cost savings to be

achieved under the multiyear contract in comparison to specified other contracts) and if it

appears (after negotiations with contractors) that such savings cannot be achieved, but that

significant savings could nevertheless be achieved through the use of a multiyear contract

rather than specified other contracts, the President may submit to Congress a request for

relief from the specified cost savings that must be achieved through multiyear contracting

for that program. Any such request by the President shall include details about the request

Congressional Research Service

25

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

for a multiyear contract, including details about the negotiated contract terms and

conditions.

(5)(A) The Secretary may obligate funds for procurement of an end item under a multiyear

contract for the purchase of property only for procurement of a complete and usable end

item.

(B) The Secretary may obligate funds appropriated for any fiscal year for advance

procurement under a contract for the purchase of property only for the procurement of those

long-lead items necessary in order to meet a planned delivery schedule for complete major

end items that are programmed under the contract to be acquired with funds appropriated

for a subsequent fiscal year (including an economic order quantity of such long-lead items

when authorized by law).

(6) The Secretary may make the certification under paragraph (3) notwithstanding the fact

that one or more of the conditions of such certification are not met, if the Secretary

determines that, due to exceptional circumstances, proceeding with a multiyear contract

under this section is in the best interest of the Department of Defense and the Secretary

provides the basis for such determination with the certification.

(7) The Secretary may not delegate the authority to make the certification under paragraph

(3) or the determination under paragraph (6) to an official below the level of Under

Secretary of Defense for Acquisition and Sustainment.

(j) Defense Contract Options for Varying Quantities.-The Secretary of Defense may

instruct the Secretary of the military department concerned to incorporate into a proposed

multiyear contract negotiated priced options for varying the quantities of end items to be

procured over the period of the contract.

(k) Multiyear Contract Defined.-For the purposes of this section, a multiyear contract is a

contract for the purchase of property for more than one, but not more than five, program

years. Such a contract may provide that performance under the contract during the second

and subsequent years of the contract is contingent upon the appropriation of funds and (if

it does so provide) may provide for a cancellation payment to be made to the contractor if

such appropriations are not made.

(l) Various Additional Requirements With Respect to Multiyear Defense Contracts.-(1)(A)

The head of an agency may not initiate a contract described in subparagraph (B) unless the

congressional defense committees are notified of the proposed contract at least 30 days in

advance of the award of the proposed contract.

(B) Subparagraph (A) applies to the following contracts:

(i) A multiyear contract(I) that employs economic order quantity procurement in excess of $20,000,000 in any one

year of the contract; or

(II) that includes an unfunded contingent liability in excess of $20,000,000.

(ii) Any contract for advance procurement leading to a multiyear contract that employs

economic order quantity procurement in excess of $20,000,000 in any one year.

(2) The head of an agency may not initiate a multiyear contract for which the economic

order quantity advance procurement is not funded at least to the limits of the Government’s

liability.

(3) The head of an agency may not initiate a multiyear procurement contract for any system

(or component thereof) if the value of the multiyear contract would exceed $500,000,000

unless authority for the contract is specifically provided in an appropriations Act.

Congressional Research Service

26

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

(4) Each report required by paragraph (5) with respect to a contract (or contract extension)

shall contain the following:

(A) The amount of total obligational authority under the contract (or contract extension)

and the percentage that such amount represents of(i) the applicable procurement account; and

(ii) the agency procurement total.

(B) The amount of total obligational authority under all multiyear procurements of the

agency concerned (determined without regard to the amount of the multiyear contract (or

contract extension)) under multiyear contracts in effect at the time the report is submitted

and the percentage that such amount represents of(i) the applicable procurement account; and

(ii) the agency procurement total.

(C) The amount equal to the sum of the amounts under subparagraphs (A) and (B), and the

percentage that such amount represents of(i) the applicable procurement account; and

(ii) the agency procurement total.

(D) The amount of total obligational authority under all Department of Defense multiyear

procurements (determined without regard to the amount of the multiyear contract (or

contract extension)), including any multiyear contract (or contract extension) that has been

authorized by the Congress but not yet entered into, and the percentage that such amount

represents of the procurement accounts of the Department of Defense treated in the

aggregate.

(5) The head of an agency may not enter into a multiyear contract (or extend an existing

multiyear contract), the value of which would exceed $500,000,000 (when entered into or

when extended, as the case may be), until the Secretary of Defense submits to the

congressional defense committees a report containing the information described in

paragraph (4) with respect to the contract (or contract extension).

(6) The head of an agency may not terminate a multiyear procurement contract until 10

days after the date on which notice of the proposed termination is provided to the

congressional defense committees.

(7) The execution of multiyear contracting authority shall require the use of a present value

analysis to determine lowest cost compared to an annual procurement.

(8) This subsection does not apply to the National Aeronautics and Space Administration

or to the Coast Guard.

(9) In this subsection:

(A) The term “applicable procurement account” means, with respect to a multiyear

procurement contract (or contract extension), the appropriation account from which

payments to execute the contract will be made.

(B) The term “agency procurement total” means the procurement accounts of the agency

entering into a multiyear procurement contract (or contract extension) treated in the

aggregate.

(m) Increased Funding and Reprogramming Requests.-Any request for increased funding

for the procurement of a major system under a multiyear contract authorized under this

section shall be accompanied by an explanation of how the request for increased funding

affects the determinations made by the Secretary under subsection (i).

Congressional Research Service

27

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Appendix B. Programs Approved for MYP in

Annual DOD Appropriations Acts Since FY1990

This appendix presents, in three tables, programs approved for MYP in annual DOD

Appropriations Acts since FY1990. Table B-1 covers fiscal years since FY2022. Table B-2

covers FY2011 through FY2021, and Table B-3 covers FY1990 through FY2010.

Table B-1. Programs Approved for MYP in Annual Appropriations Acts Since FY2022

Fiscal

Year

Bill/Law

Section on MYP

2025

H.R. 1968/P.L. 119-4

Section 1418 of Division A

CH–53K heavy lift helicopters, T408 engines, and

Virginia-class submarines

2024

H.R. 2882/P.L. 118-47

Section 8010 of Division A

Naval Strike Missile

Guided Multiple Launch Rocket System

PATRIOT Advanced Capability-3 Missile Segment

Enhancement

Long Range Anti-Ship Missile

Joint Air-to-Surface Standoff Missile

Advanced Medium-Range Air-to-Air Missile

USS Virginia Class (SSN–774)

2023

H.R. 2617/P.L. 117-328

Section 8010 of Division C

Up to 15 DDG–51 Arleigh Burke Class Guided Missile

Destroyers

2022

H.R. 2471/P.L. 117-103

Section 8010 of Division C

UH/HH-60M Black Hawk helicopter

AH–64E Apache helicopter

Program(s) Approved for MYP

Source: Table prepared by CRS based on text of bills.

Table B-2. Programs Approved for MYP in Annual DOD Appropriations Acts

From FY2011 Through FY2021

Fiscal

Year

Bill/Law

Section on MYP

2021

H.R. 133/P.L. 116-260

Section 8010 of Division C

[none]

2020

H.R. 1158/P.L. 116-93

Section 8010 of Division A

[none]

2019

H.R. 6157/P.L. 115-245

Section 8010 of Division A

Standard Missile–3 IB

Standard Missile–6

F/A–18E/F Super Hornet and EA–18G Aircraft variants

E–2D Advanced Hawkeye (AHE) Aircraft

C–130J, KC–130J, HC–130J, MC–130J, AC–130J

Aircraft

SSN Virginia Class Submarines and Governmentfurnished equipment

Congressional Research Service

Programs(s) Approved for MYP

28

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Fiscal

Year

Bill/Law

Section on MYP

Programs(s) Approved for MYP

2018

H.R. 1625/P.L. 115-141

Section 8010 of Division C

V–22 Osprey aircraft variants (may not exceed five

years)

up to 13 SSN Virginia Class Submarines and

Government-furnished equipment

DDG–51 Arleigh Burke class Flight III guided missile

destroyers, the MK41 Vertical Launching Systems, and

associated Government-furnished systems and

subsystems

2017

H.R. 244/P.L. 115-31

Section 8010 of Division C

AH–64E Apache Helicopter and UH–60M Blackhawk

Helicopter

2016

H.R. 2029/P.L. 114-113

Section 8010 of Division C

[none]

2015

H.R. 83/P.L. 113-235

Section 8010 of Division C

[none]

2014

H.R. 3547/P.L. 113-76

Section 8010 of Division C

E-2D Advanced Hawkeye

SSN 774 Virginia class submarine

KC-130J, C-130J, HC-130J, MC-130J, AC-130J aircraft,

and government-furnished equipment

2013

H.R. 933/P.L. 113-6

Section 8010 of Division C

F/A-18E, F/A-18F, and EA-18G aircraft

Up to 10 DDG-51 destroyers, as well as the AEGIS

Weapon Systems, MK 41 Vertical Launching Systems,

and Commercial Broadband Satellite Systems

associated with those ships

Virginia class submarines and government-furnished

equipment

CH-47 Chinook helicopters

V-22 Osprey aircraft variants

2012

H.R. 2055/P.L. 112-74

Section 8010 of Division A

UH–60M/HH–60M and MH–60R/MH–60S Helicopter

Airframes

MH–60R/S Mission Avionics and Common Cockpits

2011

H.R. 1473/P.L. 112-10

Section 8010 of Division A

Navy MH-60R/S helicopter systems

Source: Table prepared by CRS based on text of bills.

Congressional Research Service

29

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Table B-3. Programs Approved for MYP in Annual DOD Appropriations Acts

from FY1990 Through FY2010

Fiscal

Year

Bill/Law

Section on MYP

2010

H.R. 3326/P.L. 111-118

Section 8011 of Division A

F-18 aircraft variants

2009

H.R. 2638/P.L. 110-329

Section 8011 of Division C

SSN Virginia class submarine

2008

H.R. 3222/P.L. 110-116

Section 8010 of Division A

Army CH-47 Chinook helicopter

M1A2 Abrams System Enhancement Package

upgrades

M2A3/M3A3 Bradley upgrades

SSN Virginia Class submarine

2007

H.R. 5631/P.L. 109-289

Section 8008 of Division A

C-17 Globemaster

F-22A

MH-60R Helicopters

MH-60R Helicopter mission equipment

V-22 Osprey

2006

H.R. 2863/P.L. 109-148

Section 8008 of Division A

UH-60/MH-60 helicopters

C-17 Globemaster

Apache Block II Conversion

Modernized Target Acquisition Designation

Sight/Pilot Night Vision Sensor (MTADS/PNVS)

2005

H.R. 4613/P.L. 108-287

Section 8008

Lightweight 155mm Howitzer

2004

H.R. 2658/P.L. 108-87

Section 8008

F/A-18 aircraft

E-2C aircraft

Tactical Tomahawk missile

Virginia Class submarine

2003

H.R. 5010/P.L. 107-248

Section 8008

C-130 aircraft

FMTV

F/A-18E and F engine

2002

H.R. 3338/P.L. 107-117

Section 8008 of Division A

UH-60/CH-60 aircraft

C-17

F/A-18E and F engine

2001

H.R. 4576/P.L. 106-259

Section 8008

Javelin missile

M2A3 Bradley fighting vehicle

DDG-51 destroyer

UH-60/CH-60 aircraft

2000

H.R. 2561/P.L. 106-79

Section 8008

Longbow Apache helicopter

Javelin missile

Abrams M1A2 Upgrade

F/A-18E/F aircraft

C-17 aircraft

F-16 aircraft

1999

H.R. 4103/P.L. 105-262

Section 8008

E-2C aircraft

Longbow Hellfire missile

Medium Tactical Vehicle Replacement (MTVR)

Congressional Research Service

Program(s) Approved for MYP

30

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Fiscal

Year

Bill/Law

Section on MYP

Program(s) Approved for MYP

1998

H.R. 2266/P.L. 105-56

Section 8008

Apache Longbow radar

AV-8B aircraft

Family of Medium Tactical Vehicles

1997

H.R. 3610/P.L. 104-208

Section 8009 of Section

101(b) of Title I of Division

A

Javelin missiles

Army Tactical Missile System (ATACMS)

Mk19-3 grenade machine guns

M16A2 rifles

M249 Squad Automatic Weapons

M4 carbine rifles

M240B machine guns

Arleigh Burke (DDG-15 [sic:51] class destroyers

1996

H.R. 2126/P.L. 104-61

Section 8010

UH-60 Blackhawk helicopter

Apache Longbow helicopter

M1A2 tank upgrade

1995

H.R. 4650/P.L. 103-335

Section 8010

MK19-3 grenade machine guns

M16A2 rifles

M249 Squad Automatic Weapons

M4 carbine rifles

1994

H.R. 3116/P.L. 103-139

Section 8011

[none]

1993

H.R. 5504/P.L. 102-396

Section 9013a

Defense Support Satellites 23, 24 and 25

Enhanced Modular Signal Processor

1992

H.R. 2521/P.L. 102-172

Section 8013

MK-48 ADCAP Torpedo

UH-60 Black Hawk helicopter

Army Tactical missile

1991

H.R. 5803/P.L. 101-511

Section 8014

Line of Sight-Rear (Avenger)—Pedestal Mounted

Stinger

Family of Medium Tactical Vehicles (FMTV)

LCAC Landing Craft

LHD Amphibious Ship

MK-45 Gun Mount/MK-6 Ammo Hoist

NAVSTAR Global Positioning Satellite (GPS)

Defense Support Program Satellites 22 and 23

1990

H.R. 3072/P.L. 101-165

Section 9021a

M-1 tank engines

M-1 tank fire control

Bradley Fighting Vehicle

Family of Heavy Tactical Vehicles

Maverick Missile (AGM-65D)

SH-60B/F helicopter

DDG-51 destroyer (two years)

Source: Table prepared by CRS based on text of bills.

a. In H.R. 5504/P.L. 102-396 and H.R. 3072/P.L. 101-165, the general provisions title was Title IX.

Congressional Research Service

31

Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition

Author Information

Ronald O'Rourke

Specialist in Naval Affairs

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan

shared staff to congressional committees and Members of Congress. It operates solely at the behest of and

under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other

than public understanding of information that has been provided by CRS to Members of Congress in

connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not

subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in

its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or

material from a third party, you may need to obtain the permission of the copyright holder if you wish to

copy or otherwise use copyrighted material.

Congressional Research Service

R41909 · VERSION 145 · UPDATED

32