Disaster Recovery Funding for Military

Facilities on Guam

October 1, 2024

Overview

In May 2023, a category-four typhoon struck the U.S. territory of Guam, causing damage to U.S. Navy

and U.S. Air Force facilities, cutting power lines, and disrupting water supplies for some of the 6,500 U.S.

military servicemembers permanently stationed on the island. Cost estimates for this damage vary, with

some estimates placing the total as high as $50 billion.

Because of the territory’s geographic position—Guam is closer to the Asian mainland than to Hawaii—

DOD officials consider it to be vital to national defense strategy in the Indo-Pacific region. Congress is

debating whether to provide the Department of Defense (DOD) billions of dollars in disaster recovery

funding for military facilities on Guam.

DOD has been investing in infrastructure on Guam for several years (for additional information, see CRS

Report R47643, Guam: Defense Infrastructure and Readiness, by Andrew Tilghman.).

Legislative and Executive Branch Responses

In October 2023, the Biden Administration submitted a supplemental funding request that included $3.16

billion in items related to Guam typhoon recovery. The supplemental request included $1.32 billion for

military construction (MILCON) projects and an additional $1.58 billion for Operation and Maintenance

(O&M) funding to repair various military structures and facilities in Guam damaged by the typhoon. The

Administration reiterated the $3.16 billion request in June 2024.

The Biden Administration did not include disaster recovery for Guam in the President’s budget request for

FY2025, which was submitted to Congress in March 2024.

During consideration of a National Defense Authorization Act (NDAA) for Fiscal Year 2025 (FY2025),

the Senate Armed Services Committee (SASC) reported a draft NDAA (S. 4638) that included $12.50

billion for disaster recovery funding for Guam. The SASC-reported bill includes a list of 51 military

construction projects to support disaster recovery for Guam—8 for the Navy and 43 for the Air Force.

Congressional Research Service

https://crsreports.congress.gov

IN12434

CRS INSIGHT

Prepared for Members and

Committees of Congress

Congressional Research Service

2

A House-passed bill for an FY2025 NDAA (H.R. 8070) did not include disaster relief funding for Guam

in military construction accounts.

On Sept. 5, 2024, one Delegate and three Representatives (Delegate James Moylan and Representatives

Ed Case, Jennifer Kiggans, and Donald Davis) sent a letter to House Speaker Mike Johnson urging

support for funding for Guam’s disaster recovery. The letter said the SASC’s $12.50 billion proposal

understates the long-term needs for Guam, citing higher estimates produced by the Air Force ($9.6

billion) and Navy ($42.97 billion) for their damage sustained to their respective facilities and capabilities.

“These needs span across various accounts including military construction; operations and

maintenance; and facilities sustainment, restoration and modernization accounts,” the letter said.

Proposed recovery efforts include repair of some facilities, new construction to replace some facilities,

and enhancing some structures to be more resilient to natural disasters. Some disaster recovery plans

reportedly call for new construction to replace damaged facilities because repairing older facilities may

not be cost effective. According to documents that the Air Force provided to congressional staffers, some

of the military construction projects for which the Air Force seeks funding include projects that are in

direct response to the storm damage. Other projects are intended to provide “enhanced recovery” and

“preventive/improved resilience” for facilities on Guam.

Current Construction Plans for Guam

For FY2024, Congress provided $1.03 billion for military construction for Guam and the Northern

Marianas Islands. For FY2025, DOD requested $781.5 million for military construction on Guam and the

Northern Mariana Islands.

DOD’s plans for the five-year period covered by the Future Years Defense Plan (FYDP) call for a total of

$4.716 billion on military construction for Guam and the Northern Marianas from FY2025 through

FY2029, according to a DOD official in August 2024. That includes $1.975 billion for the relocation of

U.S. Marines from Okinawa to Guam; it also includes a total of $1.836 billion for a Guam missile defense

program.

Other Legislative Provisions Impacting Guam

Reconstruction

Even before the May 2023 typhoon, DOD officials said that Guam’s local workforce was unable to meet

DOD’s demand for “historic levels of military construction” on the island, resulting in projects taking

longer and costing more. To address concerns about cost and capacity, the FY2024 NDAA included a

provision (Section 1807) that provides DOD construction contractors with additional capacity for an H2B visa workforce through FY2029. In a March 2024 INDOPACOM posture statement submitted to the

HASC, Navy Adm. John Aquilino, the then-commander of INDOPACOM, acknowledged the extension

of the H-2B visa provision for Guam, further stating that:

Additional relief is necessary to enable prolonged extensions of H-2B visas and direct relief for

typhoon recovery and resilience projects in Guam and the CNMI. Absent additional relief before

FY27, the loss of an assured workforce will result in cost and schedule impacts to both military

relocation and typhoon resilience projects; impacts will increase until the workforce collapses in

FY30.

DOD has proposed a provision for inclusion in FY2025 legislation to modify existing prohibitions on

cost-plus contracting to allow such contracts in the INDOPACOM AOR under certain circumstances.

Under cost-plus contracts, the government pays contractors for costs incurred to construct a facility plus

Congressional Research Service

3

an agreed profit. (Typically, DOD uses fixed-price contracts for military construction, in which the

government and the contractor agree to a price upfront.)

Certain DOD officials have said authorizing cost-plus contracts would make it easier to carry out military

construction plans for Guam. Some contractors have indicated their reluctance to engage in fixed-price

contracts on Guam because its remote location makes it difficult to accurately predict material and labor

costs or potential supply-chain problems. Cost-plus contracts in theory could help some contractors

mitigate the risk of unexpected cost increases. These types of contracts also in some circumstances may

provide less incentive for the contractor to control costs. Under current law, the only exception to DOD’s

prohibition on cost-plus contracts for military construction is for projects in Alaska.

Neither the House nor Senate bills for an FY2025 NDAA includes this provision.

Author Information

Andrew Tilghman

Analyst in U.S. Defense Infrastructure Policy

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff

to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of

Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of

information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role.

CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United

States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However,

as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the

permission of the copyright holder if you wish to copy or otherwise use copyrighted material.

IN12434 · VERSION 1 · NEW

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.