DOD Cost Overruns and The Nunn-McCurdy Act
Since the U.S. Department of Defense’s (DOD)
establishment, Congress has expressed interest in ensuring
that DOD procures major weapons systems efficiently,
including that a program maintain the same projected costs
throughout its lifecycle. DOD requested a total of $168
billion for defense-wide procurement for fiscal year (FY)
2025. Controlling DOD procurement costs has typically
challenged DOD, which periodically has “cost overruns,”
or instances when a program surpasses its initial cost
estimate.
certifying and approving a program’s procession through
the different formal stages of acquisition.
Congressional efforts to maintain DOD program costs have
included defining programs in statute and creating reporting
requirements, including Selected Acquisition Reports
(SARs), in statute. SARs require DOD to notify Congress
about changes to baseline cost estimates of major defense
acquisition programs (MDAPs) and potential risk factors
and requirements originally outlined in the 1982 NunnMcCurdy Act. The Nunn-McCurdy Act (10 U.S.C. §§43714377) requires DOD to report to Congress if an MDAP
experiences a cost overrun that exceeds certain thresholds.
Depending on the size of the program and extent of the cost
overrun, DOD is legally required to take certain actions and
report its findings to Congress.
Selected Acquisition Reports (SARs)
DOD Acquisition Categories
The level of management and congressional oversight of an
acquisition program generally corresponds with the cost
and technical complexity of the program. All DOD
acquisition programs are designated by an acquisition
category (ACAT). The category is primarily based on the
program’s total cost.
ACAT I refers to the largest acquisition programs in terms
of dollar amounts, and are also known as MDAPs. An
MDAP is defined in statute as any program that is (1) not “a
highly sensitive classified program”, and (2) so designated
by the Secretary of Defense, or (3) has an “eventual total
expenditure” for procurement of more than $1.8 billion or,
for research and development (R&D), of more than $300
million (both in FY1990 constant dollars). According to
DOD estimates, these dollar amounts are adjusted to $3.065
billion for procurement and $525 million for R&D in
FY2020 constant dollars. ACAT I programs are also further
divided into sub-categories depending on their level of
decision authority, or which DOD office is designated to
determine whether or not the program should advance
throughout DOD’s acquisition process “milestones.”
ACAT I programs have three major milestones,
(Milestones, A, B, and C) requiring milestone decision
authority (MDA) approval. For the highest cost or most
technically complex ACAT I programs, the Undersecretary
of Defense for Acquisition and Sustainment (USD(A&S))
is typically the MDA, the DOD entity responsible for
Although there are three other acquisition program
categories, only ACAT I/MDAP programs are subject to
the statutory reporting and oversight requirements of NunnMcCurdy, including reporting requirements concerning the
program’s cost, and procedures DOD must follow should
an MDAP’s eventual cost exceed by a certain percentage its
original estimated cost.
Selected Acquisition Reports (SARs) consist of information
detailing an MDAP’s cost, schedule, and performance. Per
Title 10, SARS must be provided to Congress either
annually (within 30 days after the President’s budget is
transmitted to Congress) or quarterly (within 45 days after
the end of the fiscal year quarter). Quarterly SARs are
required if DOD finds that the program had a 15% or more
cost increase and/or a six-month or more delay of one of the
major program milestones in the last quarter.
Title 10 also requires that DOD establish a program’s
“baseline description,” including a program’s “baseline
estimate,” or a description of the program that must be
prepared early in the program’s acquisition lifecycle.
Should the program experience a cost overrun, the baseline
description is to be used as a point of reference concerning
DOD’s original intentions for the program. Baseline
descriptions may be revised or adjusted, including in the
event of a cost breach, but DOD is to report such an update
in the program’s next SAR.
The Nunn-McCurdy Act
The Nunn-McCurdy Act requires that DOD report to
Congress if an MDAP experiences a cost overrun that
exceeds certain tiers of percentages. Depending on the
threshold, DOD must take certain actions and report its
findings to Congress.
Two major types of cost growth threshold breaches (also
called a “Nunn-McCurdy breach” or a “Nunn-McCurdy,”
after the sponsors of the original legislation, in the DOD
acquisition community) exist:
1) Significant breach. A significant breach occurs
when a program’s cost increases either 15% from
its current baseline estimate, or 30% from its
original baseline estimate; and
2) Critical breach. A critical breach occurs when a
program’s cost increases either 25% from its
current baseline estimate or 50% from its original
baseline estimate.
https://crsreports.congress.gov
DOD Cost Overruns and The Nunn-McCurdy Act
DOD is statutorily required to report a cost growth breach
to Congress in two potential scenarios:
1. End-of-Quarter Notification. Every
quarter, each military branch’s Service
Acquisition Executive (SAE) is to submit
a unit cost report for its MDAPs. If the
Service Acquisition Executive (SAE)
determines a program cost breach, DOD
must notify Congress within 45 days after
the end of the quarter.
2. Mid-Quarter Notification. If a cost
growth threshold breach is determined or
anticipated out of the unit cost report
cycle, the respective program office must
immediately report this finding to the
SAE, who must then determine if there is
such a breach and notify Congress within
45 days of that first report.
If Congress is notified of a critical breach, DOD is to
submit a new SAR to Congress. For a critical breach, DOD
is also required to: (1) submit either a written certification
that the program’s continuation is essential to national
security and a root cause analysis of the program’s cost
growth, or (2) submit a notification of the program’s
termination within 60 days. Should the program continue,
DOD is to submit a new SAR in the calendar year
following the year during which the program was
restructured.
DOD Cost Overrun History
The core acquisition framework for major capabilities
includes many MDAPs, which DOD calls the Major
Capability Acquisition pathway. This pathway represents a
milestone-based acquisition approach, which includes three
major phases:
1. Technology Maturation & Risk
Reduction (Milestone A to Milestone B),
2. Engineering & Manufacturing
Development (EMD) (Milestone B to
Milestone C), and
3. Production & Deployment (PostMilestone C).
According to some analysts, historically, most DOD
program cost growth occurred during the EMD phase.
According to SARs from programs that experienced NunnMcCurdy breaches from the 2012-2021 timeframe, more
than half of identified DOD Nunn-McCurdy breaches
occurred in the production phase (post-Milestone C). An
identifiable, direct cause of some of these breaches was
DOD’s decision to decrease the total number of units
procured, driving up the per-unit cost.
The FY2009 Weapon Systems Acquisition Reform Act
(WSARA) (P.L. 111-23) included updates to portions of
Title 10 associated with the Nunn-McCurdy Act. WSARA
included a requirement, in the event of a critical breach, that
DOD submit to Congress a written certification that the
program’s continuation is essential to national security and
a root cause analysis of the program’s cost growth.
DOD Cost Overruns: 2014-2024
According to DOD, it experienced 24 total Nunn-McCurdy
breaches over ten years beginning in 2012: 12 significant
breaches and 12 critical breaches, or an average of 2.4
breaches per year. This number represents an average peryear decrease in Nunn-McCurdy breaches, compared to a
13-year period beginning in 1997, during which DOD
incurred an annual average of about 5.7 breaches, according
to GAO reporting.
Issues for Congress
Determining the Root Cause of Cost Overruns
Over the last ten years, analysts have posited different
potential causes of DOD program cost growth. A 2017
RAND study on Air Force MDAPs with “extreme cost
growth” and programs “that experienced the lowest cost
growth” found that programs that experienced “extreme
cost growth” typically had “premature approval of
Milestone B” and “suboptimal acquisition strategies and
program structure.” A 2022 study in DOD’s Acquisition
Research Journal (ARJ) proposes further research into “the
degree of unrealism in elements of the MS B baseline” and
“the interaction of two or more elements of the MS B
baseline,” while acknowledging that data availability makes
it difficult to study in full.
SARs of different programs from 2012 to 2022 indicate that
explanations for Nunn-McCurdy breaches lack uniformity
and appear to be program-dependent. Some program SARs
provide more technical details as an explanation, while
other SARs simply state that the program experienced a
breach due to cost growth. Congress may consider whether
or not to include additional reporting requirements for cost
overrun explanations to allow for identification of the root
causes of cost overruns.
Oversight of Next-Generation MDAPs
Although the frequency of Nunn-McCurdy breaches has
decreased post-WSARA, DOD is set to procure several new
MDAPs over the next ten years, including the nextgeneration bomber aircraft, the LGM-35A Sentinel
intercontinental ballistic missile (ICBM), and the Ohio‐
class nuclear powered submarine replacement program.
Congress may consider how it exercises oversight for these
programs, particularly if they experience cost overruns.
Oversight of Non-MDAP Programs
Although there are three other acquisition program
categories, ACAT I/MDAP programs are the only category
subject to statutory Nunn-McCurdy reporting requirements,
potentially due to their high cost. Any program that is not
designated as an MDAP may not be subject to the same
statutory reporting requirements, including the NunnMcCurdy process. Congress may consider whether or not to
include some kind of cost overrun reporting requirement for
smaller programs, such as middle tier of acquisition (MTA)
programs.
Alexandra G. Neenan, Analyst in U.S. Defense
Infrastructure Policy
https://crsreports.congress.gov
IF13027
DOD Cost Overruns and The Nunn-McCurdy Act
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress.
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you
wish to copy or otherwise use copyrighted material.