MQ-25 Stingray: Background and Issues for Congress
Congressional research reportAug 12, 2026
Ask Donna
What actually matters in this document.
Text
Updated August 12, 2026
MQ-25 Stingray: Background and Issues for Congress
Introduction
The U.S. Navy is developing a carrier-based uncrewed
aircraft system (UAS) to perform aerial refueling and
intelligence, surveillance, and reconnaissance (ISR)
missions. The MQ-25 Stingray, if the system is fielded as
planned, would be the U.S. Department of Defense’s
(DOD’s) first uncrewed tanker and the Navy’s first carrierbased uncrewed aerial vehicle (UAV, or drone). (DOD is
“using a secondary Department of War designation,”
under Executive Order 14347 dated September 5, 2025.)
Congress has expressed an interest in the Navy’s efforts to
develop a carrier-based drone and in the future structure of
the carrier air wing.
According to the Navy’s FY2027 budget submission to
Congress, by providing the carrier air wing with a dedicated
aerial tanker, the MQ-25 would extend the effective
operating range of crewed fighter aircraft and reduce the
strain on fighter aircraft modified to provide mid-air
refueling capabilities. In congressional testimony, Navy
officials have further described the Stingray as a
“pathfinder” to what they describe as the “air wing of the
future”—one in which UAVs could potentially conduct
various missions.
For FY2027, the Navy requested $1.75 billion in
discretionary procurement and research, development, test,
and evaluation (RDT&E) funding for the MQ-25. If
approved by Congress, the Navy’s FY2027 request would
fund the procurement of three MQ-25 aircraft and represent
the second year of low-rate initial production (LRIP) of the
aircraft. The MQ-25 program of record currently estimates
a total of 76 aircraft, including 67 operational aircraft and
nine test and developmental aircraft.
Background
In 1999, the Navy and the U.S. Defense Advanced
Research Projects Agency (DARPA) began to develop a
multi-mission, carrier-based uncrewed combat aerial
vehicle (UCAV), a goal Congress supported in the Floyd D.
Spence National Defense Authorization Act for Fiscal Year
2001 (P.L. 106-398, §220). Over the following decade, the
Navy, DOD, and Congress considered various possible
configurations of a carrier-based combat UAV. These
initiatives resulted in the Unmanned Carrier Launched
Surveillance and Strike (UCLASS) program, the
requirements for which DOD initially approved in 2011.
In 2016, the Navy shifted the focus of the development of a
carrier-based UAV from combat missions to refueling
missions. According to the Navy, the new aircraft would
relieve the Navy F/A-18E/F Super Hornet fighters of
having to conduct air-to-air refueling missions, allowing the
Super Hornet fighters to focus on combat missions.
The Navy selected Boeing to produce the Stingray aircraft
in 2018 and awarded the company a fixed-price contract for
the engineering and manufacturing development phase of
the program. A Boeing-owned Stingray demonstrator, the
“T1,” conducted its first flight in 2019 and its first mid-air
refueling of another aircraft in 2021, though it lacked
features of the developmental and production aircraft.
Boeing finished assembling the first developmental MQ-25
aircraft in mid-2025. The Navy conducted the first flight of
a developmental MQ-25 in April 2026 (see Figure 1).
Following the flight, in May 2026, the Navy approved the
start of LRIP. The Navy has estimated that it will continue
flight tests of the MQ-25 until the end of FY2029, later than
initially planned (for more information, see “Schedule”).
Figure 1. MQ-25A Stingray
Source: Jamie Cosgrove, Naval Air Warfare Center.
MQ-25 Stingray
Design
The primary elements of the MQ-25 Stingray program are
the air vehicle and the mission control system and software,
the prime contractors for which are Boeing and Lockheed
Martin, respectively. The Navy is responsible for
integrating these components together and with the ship.
The Navy’s objective for the MQ-25 air vehicle is for the
drone to deliver at least 14,000 pounds of fuel at a distance
of 500 nautical miles (575 miles)—approximately the
capacity of the F/A-18E/F fighters, though less than that of
previous Navy tankers.
Boeing said in 2021 that it would build the MQ-25 at
MidAmerica St. Louis Airport in Mascoutah, IL, and in
2024 the company opened a $200-million production
factory there. Boeing selected the Rolls-Royce AE 3007N
turbofan engine, produced in Indianapolis, IN, to power the
MQ-25. The Stingray will reportedly use the Cobham
https://crsreports.congress.gov
MQ-25 Stingray: Background and Issues for Congress
Aerial Refueling Store, the same equipment used by tankerconfigured F/A-18E/F fighters, for mid-air refueling.
The Unmanned Carrier Aviation Mission Control System
(UMCS, or MD-5) is the planned ground control station for
the MQ-25 Stingray, as well as potentially for future UAVs
that the Navy could integrate into the carrier air wing.
According to the Navy’s FY2027 budget submission, the
UMCS is to consist of the hardware, software, and
networks that allow pilots to plan and conduct flight
missions, including the consoles, beyond line-of-sight
communications, and the Lockheed Martin-developed Multi
Domain Control Capability (MDCX) software. The Navy is
procuring both ship-installed (MD-5C) and shore-based
(MD-5D) versions of the UMCS, as well as a mobile
version (MD-5E) for carriers that do not have the full
control station installed. In 2024, the Navy installed its first
UMCS on the USS George H.W. Bush (CVN 77); in 2026,
the USS Theodore Rosevelt (CVN 71) became the first fully
operational aircraft carrier compatible with the MQ-25.
Schedule
The DOD Office of Inspector General (DODIG), in a 2023
audit of the MQ-25 program, highlighted the potential risks
associated with the Navy’s development and production
schedule. One risk the DODIG identified was the Navy’s
plan to begin LRIP before the service had completed its
developmental and operational tests of the productionrepresentative MQ-25 aircraft. The DODIG recommended
that the Navy either delay its decision to start LRIP “until
the Program Office conducts sufficient tests and
evaluations,” or update its risk management documentation
for the program. In response, Navy officials said that the
program office had updated its risk assessment and delayed
program milestone decisions.
In 2024, the Navy adopted a new schedule and program
baseline for the MQ-25 that extended the development
phase of the program and postponed key milestones. For
example, under the revised schedule, the Navy postponed
the first flight of the developmental aircraft from 2021 to
2025. (The first flight occurred in April 2026.) According
to DOD’s April 2026 Modernized Selected Acquisition
Report (MSAR) for the MQ-25, the program may face
additional delays; DOD estimated that the MQ-25 could
reach an initial operational capability (IOC) in 2029, four
years after the date initially planned and two years after that
in the revised baseline. The MSAR attributed the delays to
multiple factors, including “production challenges due to
technical risk,” changes to the production schedule, and a
labor strike.
Cost
In the 2026 MSAR for the MQ-25, DOD estimated the total
acquisition cost of the program—including procurement,
RDT&E, and military construction—at $19.4 billion and
the acquisition unit cost at $255.8 million per aircraft. In the
2026 SAR, DOD estimated that life-cycle operations and
sustainment costs would be greater than previously
reported, due in part to revised manpower and fuel cost
calculations, higher maintenance and sustainment costs, and
future RDT&E costs.
The Government Accountability Office (GAO), in its 2026
Weapon Systems Annual Assessment, estimated the total
program cost—excluding military construction—at $16.6
billion and the acquisition unit cost at $218 million, a 4%
increase from GAO’s 2025 estimate. GAO attributed cost
increases in part to Navy efforts to mitigate and replace
obsolete components. The 2026 GAO report identified the
Navy’s plan to begin LRIP before it completed testing the
production-representative aircraft as a potential risk for
future “cost increases and further delays.” GAO also
reported that the Navy had lacked “data showing the actual
costs of building the aircraft” due to the nature of the fixedprice contract for development of the aircraft and that the
program office was “working to obtain better cost data.”
FY2026-Enacted Budget
The Department of Defense Appropriations Act, 2026
(Division A of P.L. 119-75), provided a total of $1.03
billion in procurement and RDT&E funding for the MQ-25
program, $10 million less than requested. Additionally, in
the FY2025 reconciliation law, sometimes known as the
One Big Beautiful Bill Act (P.L. 119-21), Congress
provided $100 million in FY2025 mandatory funding to
“accelerate production of MQ-25 aircraft.”
FY2027 Budget Request
The Navy requested $1.75 billion in discretionary FY2027
procurement and RDT&E funding for the MQ-25 program.
DOD did not request that Congress use the reconciliation
process in 2026 to provide mandatory funding for the MQ25. To date, proposed defense authorization and
appropriations legislation in the House and Senate (H.R.
8800, S. 4784; H.R. 9495) would, if enacted, authorize and
provide the amount of funding requested for the program.
Issues for Congress
Congress may, as part of its oversight of Navy programs,
consider the following issues:
• Whether the Navy has provided Congress with sufficient
information regarding the costs of the MQ-25 program,
as well as unit costs relative to lower-cost alternatives.
• The Navy’s plan for conducting cybersecurity tests of
the software for the air vehicle and for the ground
control station.
• Whether the Navy’s plan to begin LRIP before it
completes the test and evaluation period might result in
additional delays and, if so, the Navy’s plan for
managing the risk of schedule delays.
• The Navy’s plan for managing the impact of potential
technical issues identified during its testing of the test
and developmental aircraft on its production schedule.
• What lessons, if any, the Navy plans to apply from the
MQ-25 program to the development of other, carrierbased UAVs, and whether recent armed conflicts have
affected Navy plans for carrier-based UAV missions.
Daniel M. Gettinger, Analyst in U.S. Defense Policy
IF12972
https://crsreports.congress.gov
MQ-25 Stingray: Background and Issues for Congress
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress.
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you
wish to copy or otherwise use copyrighted material.
https://crsreports.congress.gov | IF12972 · VERSION 4 · UPDATED
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.