Petition for Writ of Certiorari — United States v. Peotzer
Supreme Court brief1948
Ask Donna
What actually matters in this document.
Text
INDEX
Page
ee nn Tenet eer reer 1
IE, oi, ass GA sop WAS waco abuacawky Oecd Jus Vpenhee hn 1
NE oo skh Cine Shea ste akideaantens eave e 2
Contract provisions involved .......... 2.2... 66. eee eee ees 3
NES El SEES Ne By UP BEM Se enn pane weg ee O 3
1. Claim for $3,217.80 for formed concrete beams....... 5
2. Claim for $2,018 for excavation and concrete floor slabs
IE 0 i a bis nda s SAK GOS Cay CLE RS 7
Specification of errors to be urged .......... 2.0... 0.0005. 10
Reasons for granting the writ........... 2.2.6.0... cece ll
hs oon ia Vu cd Oy AD 5A KEEN ah AMINO AR Kee 27
RA ree merce rerreee rag ae Crea ey are 28
a CITATIONS
. Cases :
3 American Smelting ¢ Refining Co. v. United States, 259
DN tact ak hunt ankles Bickas Guan Rik eek enh 15
: B-W Construction Co. v. United States, 97 C. Cls. 92..... 19
3 B-W Construction Co. v. United States, 101 C. Cls. 748,
F reversed sub nom. United States v. Beuttas, 324 U. S.
: RTGS Coe oie tn arco tee tea oe kes 16, 19
3 Callahan Construction Co. v. United States, 91 C. Cls.
: ERS SS IRE eR. aaa ea 18
; Davis v. United States, 82 C. Cis. 334.................. 18
3 English Const. Co., Inc. v. United States, 43 F. Supp.
3 ag BEER SSR Seep ee tA ale re ine 16,19
: Fleisher Eng. & Constr. Co. v. United States, 98 C.
: ES Wad int ten apn tad SEEKER oes Sea RAR TELA bas 19
Fred R. Comb Co. v. United States, 100 C. Cls. 259... ... 19
Langevin v. United States, 100 C. Cls.15...... .... 16, 19, 22, 25
E McCloskey & Co. v. United States, 103 C. Cis. 254. .16, 19, 22, 25
ES John McShain, Inc. v. United States, 88 C. Cls. 284,
: woveneed, 308 U. B. GIR GED... o.oo. ce cw canes 19
: King v. United States, 100 C. Cls. 475....... 2... ...... 19
. Merrill-Ruckgaber Co. v. United States, 241 U. S. 387,
16, 19, 25
‘ , ,
: Gerhardt F. Meyne v. United States, C. Cls. No. 45926,
EE UIE A EID 05 5 oad Sictn kau i Radha PRA be ees 19
; Norwegian Nitrogen Products Co. v. United States, 288
PR noha Rasa ckpi sin kk bila se Skis ee ee cae
4 Orino v. United States, C. Cls. No. 46063, decided June 1,
4 PA aes cathe Ghik tdin ik wad ag nia pana vik ak Paka 19
Perkins v. Lukens Steel Co.,310U.8.113........... 13, 14, 15
; Priebe & Sons, Inc. v. United States, 332 U. 8.407....... 13
(1)
Il
Schmoll v. United States, 91 C. Cls.1..................
Tobin Quarries, Inc. v. Central Nebraska Public Power
& Irr. Dist., 64 F. Supp. 200, affirmed, 157 F. 2d 482... 16,
25
Union Paving Co. v. United States, 107 C. Cls. 405 16, 19, 22, 25
United States v. Beuttas, 324 U.S. 768....... ....... 12, 16, 17
United States v. Blair, 321 U.S. 730......... ....... 12, 17, 26
United States v. Callahan-Walker Constr. Co., 317 U. S.
UP wera ck Wi eas as ick ls Ws ae I 12, 17,18
United States v. John McShain, Inc., 308 U. S. 512, 520,
11, 16, 17, 19, 22, 25
United States v. Joseph A. Holpuch Co., 328 U. 8S.
EE UG Rak Cc deel ais Sm ahaa s BaKS . 12, 17, 19, 22, 25
United States v. Madsen Const. Co., 139 F. 2d 613........ 16, 19
United States v. New York and Porto Rico Steamship
Sis Es WN Ae ee Lohan inn) eh Wenie ave cancun chs 15
United States v. Standard Rice Co., 323 U.S. 106........ 13
Statutes:
Act of June 17, 1910, 36 Stat. 531, 41 U.S.C. 7......... 23
Act of February 27, 1929, 45 Stat. 1341, 41 U. S. C.
Wie cc 20s Fev dk AeA ci ek nea chewed 23
First War Powers Act, Title II (Act of December 18,
1941, e. 593, 55 Stat. 838, 839, 50 U. S. C. App. 611).. 23
Legislative Appropriation Act, Title IV (Act of June 30,
1932, ec. 314, 47 Stat. 382, 413-415), as amended by
Sec. 16 of the Treasury and Post Office Department
Appropriation Act of March 3, 1933 (c. 212, 47 Stat.
1489, 1517-1519), and Title III of the Act of March
es Fey 5 8S goer oper sree we 15
Pee TUE SUES Sa; cas 8b oSee ba cadens ba dnc on ews 15
Miscellaneous:
Anderson, The Disputes Article in Government Contracts
(1945) 44 Mich. L. Rev. 211, 215, 238-239............ 19
BCA No. 122, July 20, 1943, 1 Contract Cases Federal
(Commerce Clearing House) 230.................... 8,13
BCA No. 292, December 15, 1943, 1 Contract Cases Fed-
eral (Commerce Clearing House) 931................ 7
Bureau of the Budget Circular No. 47 (November 22,
1921), reprinted in Harwood-Nebel Construction Co. v.
United States, 105 C. Cls.116....................... 15
SS 2 RES Ae amep es ERR a Fee 14
PIE eo a rBa oS iG aks ewes a den oad lew oh hen 14
ME eG SUE GS Saks oaks [SoA OK Wed Kok ie ntet 4, 14, 17, 21
Executive Order No. 6166, June 10, 1933............... 14, 20
Executive Order No. 9001 (3 C. F. R. 1941 Supp., pp.
330-332, December 27, 1941)
il
Fain and Watt, War Procurement—A New Pattern for
Contracts, (1944) 44 Col. L. Rev. 127
11 Fed. Reg. 13638
Hearings, Senate Committee on Expenditures in the Exec-
utive Departments, 80th Cong. 2d sess., on proposed
Federal Property Act of 1948, p. 129
40 Op. Atty. Gen. No. 53, August 29, 1942, pp. 4,6. .....
Reorganization Plan No. 1, effective July 1, 1939, 53
War Department Procureme Regulations, pars. 304,
1301-1325, 10 C. F. R. Cum. Supp. 81.304, 81.1301—
Bute Supreme Court of the Wnited States
OcToBER TERM, 1948
No. 332
THE UNITED STATES, PETITIONER
v.
EDMOND PFOoTZER AND E. JOHN PFOTZER,
CO-PARTNERS
PETITION FOR A WRIT OF CERTIORARI TO THE
COURT OF CLAIMS
The Solicitor General, on behalf of the United
States, prays that a writ of certiorari issue to re-
view the judgment of the Court of Claims, entered
in the above-entitled case on May 3, 1948.
OPINION BELOW
The opinion of the Court of Claims (R. 46-62)
has not yet been reported.
JURISDICTION
The judgment of the Court of Claims was
entered on May 3, 1948 (R. 62). A motion for a
new trial, seasonably filed, was denied on July 6,
(1)
2
1948 (R. 63). The jurisdiction of this Court is
invoked under 28 U.S.C. 1255.
QUESTIONS PRESENTED
In May 1942, the War Department and a con-
tractor entered into a standard-form construction
contract, Article 15 of which required recourse to
established administrative procedure for the final
determination of disputes concerning questions of
fact, and Article 1 of which incorporated a provi-
sion of the specifications requiring recourse to the
same procedure for final determination of the
‘“‘intent and meaning”’ of the ‘‘drawings and speci-
fications.’”’ Disputes arose concerning the inter-
pretation of the plans and specifications, which
were adjudicated adversely to the contractor by
the designated administrative officials, and the
contractor brought suit in the Court of Claims.
The questions presented are:
1. Whether the contractor has standing to chal-
lenge the validity of the specifications-interpreta-
tion provision or the authority of the contracting
officer to include it in the contract.
2. Whether the specifications - interpretation
provision is valid and authorized.
3. Whether the specifications - interpretation
provision covers issues of interpretation involved
in the determination of amounts due by the Gov-
ernment under the contract. .
3
CONTRACT PROVISIONS INVOLVED
The pertinent portions of the contract and speci-
fications are set forth in the Appendix, infra, pp.
28-29.
STATEMENT
In May, 1942, the United States (through the
War Department’s Corps of Engineers) entered
into a contract with the respondents for the con-
struction of housing and other facilities at Brook-
ley Field, Mobile, Alabama. In this action,
respondents asserted seven claims for additional
compensation, under the contract, which had been
rejected by the War Department. The Court of
Claims denied recovery on four of these items and
entered judgment against the United States on the
remaining three claims. This petition raises the
correctness of the lower court’s rulings on two of
the three claims decided against the Government.
The pertinent facts, as found by the lower court,
are as follows:
The bid submitted by respondents, after they had
consulted the plans and specifications of the project
(R. 24) in response to the War Department’s
invitation for bids, was accepted (R. 25, 26), and
on May 14, 1942, the parties entered into a ‘‘ Letter
Contract’? by which the United States placed an
order for the work which ‘“‘shall include all items
incidental to the proper execution and completion
of the work, ready for use, in strict accordance with
specifications, schedules and drawings, all of
which are made a part hereof * * *’ (R. 25).
4
The letter stated that ‘‘It is understood that this
contract will be supplemented by the execution of
a formal contract between you and the United
States of America, following, in General, U. 8.
Standard Form No. 23 ,Revised * * *’’ (R. 25).
The formal contract, which both parties later exe-
cuted, followed Standard Form No. 23 with cer-
tain additions and eliminations (R. 29-32). It con-
tained the normal form of ‘‘Disputes’’ clause,
Article 15, which entrusted to the contracting officer
the settlement of ‘‘all disputes concerning ques-
tions of fact’’ and with a right of appeal from the
contracting officer’s decision to the head of the
department (R. 14, 59-60, 63). Article 1 of the con-
tract also incorporated by reference the ‘‘specifica-
tions, schedules, and drawings,’’ which were desig-
" nated by title* (R. 10-11, 29-30). Paragraph 1-07
of the incorporated specifications (‘‘ Interpretation
of Contract’’) made the contracting officer the ‘‘in-
terpreter”’ of ‘‘the true intent and meaning of the
drawings and specifications’’ (R. 18, 60, 63-64) ; and
Paragraph 1-08 of the specifications (‘‘Claims,
Protests and Appeals’’) gave the contractor an
appeal to the Secretary of War, or his representa-
tive, from any action or ruling of the contracting
officer which was deemed un* ir, and made the
Secretary’s decision ‘‘final and binding upon the
parties to the contract’’ (R. 18-19, 64). The two
claims for additional compensation involved in this
1 The incorporation of “specifications, schedules, and draw-
ings” is an integral part of U.S. Standard Form No. 23. See
41 C.F.R. 12.23, p. 1326.
5
petition were submitted to the contracting officer,
who ruled against respondents (R. 24, 33, 35, 59),
and his rulings were affirmed by the War Depart-
ment Board of Contract Appeals, the Secretary’s
duly authorized representative, which held that
respondents were not entitled to any further pay-
ments (R. 24, 33, 35, 59).
1. Claim for $3,217.80 for formed concrete beams
(R. 33-34, 51-53): The Bid Form (which was in-
corporated into the specifications, as the court be-
low expressly held (R. 30-32, 34)) provided for
lump sum payments for each of several types
of buildings (‘e. g. administration, barracks, mess,
warehouse) to be erected by respondents (R. 28),?
and also contained a general unit price ($30.00
per cubic yard) for pouring ‘‘Formed Con-
crete Foundations * * * Concrete includ-
ing reinforcement for all piers, foundation walls,
bases under all piers and foundation walls and
for floor slabs’? (R. 27). In connection with
the construction of the mess buildings, respond-
ents poured a number of formed concrete beams,
reinforced with steel rods, extending around
Ba Head in the Bid Form provided, in this connection
. 27):
“Unit price for each of the buildings listed hereinafter
shall include all work, materials, labor and inciden :
construct them complete with utilities to a point five (5)
feet outside the building except for clearing and grubbing,
excavation, gravel fill under the floor concrete and
reinforcing steel in the piers, footings, f tion walls or
floor slabs on earth or gravel. Concrete floor slabs includ-
ing reinforcement not on earth or gravel shall be included
in the lump sum price bid for each building.”
the perimeter of the kitchen section of each of the
buildings (R. 33). These beams rested on the
concrete foundation piers, and were a minimum of
18 inches above the finished grade of the ground,
and were formed and poured as a monolith with
the floor slabs, which partly rested on the beams
and were poured on wood sub-floors; the beams
could as well, at the contractor’s election, have
been poured as a monolith with the concrete foun-
dation piers (R. 33).
The beams were shown and called for on the
foundation drawings but were apparently specifi-
cally referred to in the written specifications only
in an irrelevant connection (R. 33-34).° Respond-
ents interpreted the Bid Form and the drawings
as intending the beams to be paid for at the gen-
eral unit price for ‘‘Formed Concrete Founda-
tions,’’ and therefore did not include any amount
for their cost in the lump sum price bid for the
mess building (R. 33-34).
On presentation of respondents’ claim for pay-
ment for this concrete work at the unit price of $30
a cubic yard, the contracting officer held that the
beams were part of the superstructure, and not the
foundations, of the buildings, and that compensa-
* Article 2 of the contract (“Specifications and drawings”)
provided, in part: “Anything mentioned in the specifications
and not shown on the drawings, or shown on the drawings and
not mentioned in the specifications, shall be of like effect as if
shown or mentioned in both. In case of difference between
ne and specifications, the specifications shall govern”
7
tion therefor was included in the lump sunt paid for
each building. On appeal, the Board of Contract
Appeals affirmed this ruling (R. 33).* Interpret-
ing the Bid Form (which constituted a part of the
specifications) and the drawings for itself, the
Court of Claims held, with respondents, that the
‘‘contract intended that these formed reinforced
concrete beams should be paid for at the unit price
bid * * * for‘Formed Concrete Foundations’ ”’
(R. 34, 51-53), awarded judgment on this item for
$3,217.80.
2. Claim for $2,018 for excavation and concrete
floor slabs for wash racks (R. 34-35, 53-54): The
contract, through the Bid Form, called for two
‘“Wash Rack, Mod. (25’ x 60’) (5-Car) (Excluding
Booster Pump and connections)’’ at a total lump
sum price of $2,400 (R. 28). In performing this
portion of the contract, respondents did a con-
siderable amount of excavation and laid down a
reinforced concrete floor slab for each wash rack
(R. 3435). Payment for this work, in addi-
tion to the designated lump sum price, was de-
manded under the general item for ‘‘ Formed Con-
crete Foundations’? (R. 27, 35) (quoted supra,
p. 5) (for the floor slabs), and under the similar
general unit price item for ‘‘ Excavation for build-
ing foundations, footings and floor slabs (other
than space grading indicated above)’’ (R. 27, 34)
(for the excavation).
The Board of Contract Appeals’ decision on this claim
(BCA No. 292, December 15, 1943) is reported at 1 Contract
Cases Federal (Commerce Clearing House) 931, at 933.
8
In addition to the excavation and floor slabs, the
wash racks required, among other things, plumb-
ing, water pipes and connections, fixtures and
drains (R. 35). In making their bid, respondents
did not include the cost of excavation in calculating
their price of $1,200 for each of the racks (R. 35).
The above quoted provision in the Bid Form (which
was incorporated in the specifications) was the only —
reference in the written contract or specifications
specifically relating to the wash racks, but the
racks were shown on one of the drawings * (R. 53).
Respondents rested their claim for additional com-
pensation on the wording of the various items, as
quoted above; on the ‘‘Note’’ quoted in foot-
note 2, p. 5; and on ‘‘General Note’ 1 in the
Bid Form.* The claim was, however, denied by
the contracting officer, and, on appeal, by the Board
of Contract Appeals’ (R. 35). The court below
interpreted the specifications for itself, apparently
without considering the pertinent drawing (which
5 See fn. 3, supra, p. 6.
*“Whenever units of measure, i.e. linear foot, cubic yard,
square yards, and similar units of measure are mentioned in
the unit price bids, it shall be interpreted to mean the unit of
material installed in accordance with the plans and specifica-
pers and ready for use. Where items are paid for complete,
omplete in place, ready for use, or furnishe and installed, all
inci entals necessary to the proper operation or use of the item,
such as excavation, backfill, equipment, assemblies, piping and
connection to adjacent work shall be included in the unit
price bid” (R. 28-29).
™The Board of Contract Appeals’ decision (BCA No. 122,
July 20, 1943) is reported at 1 Contract Cases Federal (Com
merce Clearing House) 230, at 238-239 (“Claim for Payment
for Wash Racks and Booster Pumps”).
9
was not in evidence below, but which the Board of
Contract Appeals had considered of prime signifi-
cance), and held that the respondents were entitled
to recover on this claim (R. 34-35, 53-54).
In the general portion of its opinion dealing with
all of respondents’ claims (R. 59-62), the Court of
Claims held that Article 15 (‘‘Disputes’’) did not
apply to any of the contested items, including the
two involved in this petition, because the issues
were not of fact but of law (R. 59-60). It refused to
apply, or be bound by, Paragraphs 1-07 and 1-08 of
the specifications, regarding interpretation of the
intent and meaning of the drawings and specifica-
tions (infra, pp. 28-29), because, in its view (a) the
contracting agency had no authority to vary or add
to Standard Form No. 23 by inserting these pro-
visions in the specifications; (b) Standard Form
No. 23 required all changes or alterations to be noted
in a certain formal manner, and no such notation
was made here; and (c) in any case, Paragraphs
1-07 and 1-08 do not mean that the administrative
interpretation of the plans and specifications is to
be final with respect to questions of “‘amounts
due’’ under the contract (R. 60-62). Accordingly,
the court interpreted the plans, drawings, and
specifications for itself in adjudging that re-
spondents’ claims were valid.
Judgment was entered against the United States
for $6,085.80 on the three claims on which respond-
ents were successful (R. 62, 63). Of that sum, $5,-
10
235.80 represents the recovery on the two claims
involved here (R. 53, 54).
SPECIFICATION OF ERRORS TO BE URGED
The Court of Claims erred:
1. In rejecting, in connection with Item 2
(‘Claim for $3,217.80 for formed concrete beams’’)
and Item 3 (‘‘Claim for $2,018 for excavation and
concrete floor slabs for wash racks’’), the adminis-
trative interpretations by the contracting officer
and the Board of Contract Appeals of the draw-
ings, plans, and specifications pertinent to those
claims, and in independently interpreting those
drawings, plans, and specifications without regard
to those administrative interpretations.
2. In failing to give finality to the administra-
tive interpretations of the pertinent drawings,
plans, and specifications, as required by Para-
graphs 1-07 and 1-08 of the specifications.
3. In holding that it could properly review the
administrative interpretations and could substitute
its own interpretations of the pertinent plans,
drawings and specifications for those of the con-
tracting officer and the Board of Contract Ap-
peals.
4. In holding that Paragraphs 1-07 and 1-08
of the specifications were not intended to make the
‘decision of the contracting officer and the Secretary
of War (or his representative) final and conclusive
on all issues of the interpretation of the drawings,
ll
plans and specifications, including issues of inter-
pretations involved in questions of amounts due
by the Government under the contract.
5. In holding that a contrary construction of
Paragraphs 1-07 and 1-08 would make those pro-
visions illegal or unauthorized, and subject to be
disregarded by the Court of Claims.
6. In holding that it was beyond the competence
of the parties to confer authority upon the con-
tracting officer and the Secretary of War (or his
representative) to make final and conclusive
rulings on questions of interpretation of the speci-
fications, plans, and drawings.
7. In entering judgment for respondents on
“Claim 2”’ for ‘‘Formed Concrete Beams, $3,-
217.80”’ and on ‘‘Claim 3”’ for ‘‘Excavation Per-
formed and Concrete Floor Slabs Placed for Wash
Racks, $2,018.”’
REASONS FOR GRANTING THE WRIT
The Court of Claims has once again refused to
apply the established provisions of government
construction contracts, long accepted by contrac-
tors, which designate certain contractual disputes
for administrative settlement.’ In this latest of a
8 In less than a decade, the Government has felt it n
to bring to this Court five other decisions of the Court of Claims
inadequately ae the right of the United States to pro-
vide by contract for the administrative settlement of disputes
arising under its construction contracts. See petitions for
writs of certiorari in United States v. John McShain, Inc., No.
43, Oct. T., 1939, pp. 6, 8-9 (reversed per curiam, 308 U. 8.
12
series of restrictive holdings in this field, each
contrary to the principles announced in this Court’s
controlling decisions, the court below has ignored
the traditional clause providing for administra-
tive interpretation of the plans, drawings, and
specifications—used for years in thousands of con-
tracts and often applied by the courts—on the
novel ground that the contracting officer was not
authorized to insert such a provision in the contract.
As in the case of its predecessors in the series, this
palpably erroneous decision requires correction by
this Court.
1. In the first place, even if the contracting
officer were without authority under the regula-
tions to include the disputed provision in the
specifications, the contractor would have no stand-
ing to challenge that clause. Before bidding upon
the project, respondents were furnished with
copies of the specifications containing paragraphs
1-07 (‘‘Interpretation of Contract’’) and 1-08
(‘‘Claims, Protests and Appeals’’) (R. 24). The
‘Letter Contract’’ accepted by them on May 15,
1942 expressly incorporated the specifications (R.
25). The formal contract, later executed by both
512, 520; United States v. Callahan-Walker Constr. Co., No. 65,
Oct. T., 1942, pp. 8-12 (reversed 317 U.S. 56) ; United States v.
Blair, No. 75, Oct. T., 1943, pp. 18-19 (reversed 321 U.S. 730) ;
United States v. Beuttas, No. 431, Oct. T., 1944, pp. 7-8 (re-
versed 324 U. 8. 768) ; United States v. Joseph A. Holpuch Co.,
ae 696 and 697, Oct. T., 1945, pp. 17-18 (reversed 328
. 8. 234).
—
13
parties, likewise made the pertinent specifications
‘fa part’’ of the contract (R. 30). The very pro-
visions now attacked as invalid were thus made
known to respondents at the earliest possible time,
and were voluntarily accepted and agreed to by
them, without any protest so far as we are aware.
In addition, after the dispute arose, respondents
made full use of the review mechanism of para-
graph 1-08 (supra, pp. 7, 8) to procure appellate
decisions by the War Department’s Board of Con-
tract Appeals.® Basic contract law teaches that a
contractor freely agreeing to, and making use of,
a contract term cannot later repudiate it when it
works to his disadvantage; and there is nothing
in the nature of Government contracts which grants
such a special privilege to contractors who would
clearly have no similar right in their private deal-
ings. Cf. Perkins v. Lukens Steel Co., 310 U. S.
113, 127, 129-130; United States v. Standard Rice
Co., 323 U. 8. 106, 111; Priebe & Sons, Inc. v.
United States, 332 U.S. 407, 411.
The Court of Claims has, however, erroneously
found a reason for granting respondents a unique
status, in the asserted absence of authority to
‘“‘deviate’’ from the terms of the standard form
construction contract issued by the Treasury’s
* On some issues (not involved here) involving interpretation
of the plans and specifications, the Board of Contract Ap
upheld ndents rather than the contracting officer. 1
Contract Cases Federal (Commerce Clearing House) 230, at
235-7, 239, 241-2 (supra, fn. 7, p. 8).
14
Procurement Division (R. 60-62).° But established
doctrine flatly denies that a contractor receives any
private right from such a failure of the contracting
officer to stay within the bounds of his contractual
power. ‘‘Like private individuals and businesses,
the Government enjoys the unrestricted power
* * * to fix the terms and conditions upon which it
will make needed purchases’’; and ‘‘the Govern-
ment may for the purpose of keeping its own house
in order lay down guide posts by which its agents
are to proceed in the procurement of supplies, and
which create duties to the Government alone.”
Perkins v. Lukens Steel Co., 310 U.S. at 127 [italics
supplied]. The standardization of government
contract forms, and the centralization of federal
procurement policy in the Treasury Department
in 1933, was not undertaken to confer private rights
on government contractors, but to promote the uni-
formity and efficiency of government contracting,
as the terms of the authorizing Reorganization Act
make clear.” Ifthe Procurement Division’s direc-
tion of uniformity was violated in this instance,
1° By Section 1 of Executive Order No. 6166, June 10, 1933
(note following 5 U.S.C. 132), the Procurement Division of the
Treasury Department (now called the Bureau of Federal
Supply, 11 Fed. Reg. 13638) was authorized to supervise pro-
curement throughout the Federal Government and to require
use of approved contract forms. 41 C.F.R. 1.1—1.2, 11.1—11.3.
U. 8. Standard Form No. 23 (“Construction”) was promul-
gated under this authority, and was to be used “for every
formal contract for the construction or repair of public build-
ings or works.” 41 C.F.R. 12.23, p. 1332.
11 Executive Order No. 6166 was issued under Title IV (‘‘Re-
organization of Executive Departments”) of the Legislative
Appropriation Act for the fiscal year 1933 (Act of June 30,
1932, c. 314, 47 Stat. 382, 413-415), as amended by Section 16
15
the matter is one of internal housekeeping, appro-
priate for correction by superior executive or ad-
ministrative authorities. The provisions of the
contract, freely entered into by respondent, are not
thereby rendered unenforceable against the private
contractor.” In this respect, the Procurement Di-
vision’s requirements are in precisely the same
class of Government-oriented internal regulations
as the Public Contracts Act (Perkins v. Lukens
Steel Co., 310 U.S. at 127-9), the statute directing
Government contracts to be in writing (United
States v. New York and Porto Rico Steamship Co.,
239 U. 8. 88, 92), and the advertising-and-low-
bidder legislation (American Smelting & Refining
Co. v. United States, 259 U. 8. 75, 78; Perkins v.
Lukens Steel Co., 310 U. 8. at 126)—all of which
have been held by this Court not to confer any
of the Treasury and Post-Office Department Appropriation
Act of March 3, 1933 (c. 212, 47 Stat. 1489, 1517-1519), and
Title III of the Act of March 20, 1933, c. 3, 48 Stat. 8, 16.
These statutes empowered the President to reorganize executive
agencies and functions in order “to reduce expenditures * * *,”
“to increase the efficiency of the operations of the Govern-
ment * * *,” “to reduce the number of [executive] agencies,”
“to eliminate overlapping and duplication of effort,” and to
“group, coordinate, and consolidate executive and administra-
tive agencies of the Government * * * according to major pur-
poses.” 47 Stat. 1517. See also Bureau of the Budget Cir-
cular No. 47 (November 22, 1921), reprinted in Harwood-
Nebel Construction Co., Inc., v. United States, 105 C. Cls. 116,
129-130.
12 The question at issue concerns only the alleged deviation
by the contracting officer in inserting paragraph 1-07 of the
specifications into the contract, contrary, it is said, to the
applicable regulations. There is no doubt that the inclusion of
such @ provision could lawfully be authorized by the proper
agency of the Government, and it in nowise infringes on the
judicial power. This Court and the Court of Claims have fre-
quently upheld such clauses. See infra, p. 16.
16
justiciable rights on contractors or would-be con-
tractors.
2. The court below erred even more seriously in
holding that the contracting officer had no authority
to incorporate the disputed ciauses (paragraphs
1-07 and 1-08 of the specifications) in the contract.
Neither general law, nor the Procurement Divi-
sion’s regulations, nor the terms of Standard Form
No. 23, barred the use of these provisions, during
either time of peace or war.
a. Courts throughout the country—this Court,
the Court of Claims, and other tribunals—have long
upheld, as properly includible in construction con-
tracts, clauses giving the power of final interpreta-
tion of plans and specifications to designated of-
ficials.* As the multitude of cases shows, such
provisions have had wide usage for many years,
both in Government and in private agreements.”
The lower court neither suggests any change in the
18 B.g., Merrill-Ruckgaber Co. v. United States, 241 U. S.
387, 388, 393; United States v. John McShain, Inc., 308 U. S§.
512, 520; B-W Construction Co. v. United States, 101 C. Cls.
748, 768 (reversed on other points sub nom. United States v.
Beuttas, 324 U. S. 768) ; Langevin v. United States, 100 C. Cls.
15, 40-41; McCloskey & Co. v. United States, 103 C. Cls. 254;
Union Paving Co. v. United States, 107 C. Cls. 405, 417; United
States v. Madsen Const. Co., 139 F. 2d 613, 614, 616 (C.C.A. 6);
English Const. Co., Inc. v. United States, 43 F. Supp. 313
(D. Del.) ; Tobin rries, Inc. v. Central Nebraska Public
Power & Irr. Dist., 64 F. Supp. 200, 208-210 (D. Neb.), af-
firmed, 157 F. 2d 482 (C.C.A. 8), and state and federal de-
cisions there cited.
14 See cases cited and referred to in fn. 13, supra, and also
infra, p. 19.
17
settled judicial law on the point of ultimate power
to contract for this type of clause, nor that any
statute now requires a different decision, but it does
hold that, at least since the establishment of cen-
tralized procurement in 1933, authority has been
withdrawn by the Treasury’s Procurement Divi-
sion from government contracting agents to insert
these provisions in government construction con-
tracts. The court points to the ‘‘Disputes’’ clause
of the standard form (Article 15) (R. 60,63), which
deals with ‘‘questions of fact,’’** and founds its
invalidation of paragraph 1-07 upon the ‘‘Direc-
tions for Preparation of Contract,’’ attached to
Form No. 23 (R. 61, 64-65; 41 C.F.R. 12.23, p.
1332-2), which state: ‘‘There shall be no deviation
from this standard contract form, except as pro-
vided for in these directions, and except as author-
ized by the Director of Procurement”’ and ‘‘ Addi-
tional contract provisions and instructions, deemed
necessary for the particular work, not inconsistent
with the standard form nor involving questions of
policy, may be incorporated in the specifications or
15 Article 15 (“Disputes”) of U. 8S. Standard Form No. 23
which is limited to questions of fact, was involved in United
States v. Callahan-Walker Constr. Co., 317 U. 8. 56, 58. Article
15 (“Disputes”) of U. 8. Government Form P.W.A. 51, which
form was extensively utilized on government construction con-
tracts between 1933 and 1940, is not so limited and provides
for administrative settlement of “all” disputes concerning ques-
tions arising under the contract. This was the form considered
by this Court in United States v. John McShain, Inc., 308 U. 8.
512, 520; United States v. Blair, 321 U. 8. 730; United States v.
Beuttas, 324 U. 8. 768, and United States v. Joseph A. Holpuch
Co., 328 U. S. 234.
18
other accompanying papers.’’ The short answer to
this surprise charge of improper deviation is that
none exists, and that neither courts, Government
agencies, nor contractors have hitherto surmised
any inconsistency. Article 15 is limited to disputes
concerning issues of ‘“‘fact,’’ and does not imply
that other disputes cannot be handled similarly, if
the parties so agree; the opening phrase (‘‘ Except
as otherwise specifically provided in this con-
tract’’) itself indicates room for additional pro-
visions regarding contractual disputes to be in-
corporated in the agreement. The inclusion of a
provision extending administrative settlement to
issues of interpretation of the drawings and speci-
fications cannot, therefore, be a deviation from, or
inconsistent with, Article 15, which stands un-
changed and fully effective. To the contrary, the
close affinity, in construction matters, between the
expertise and judgment required to determine
strictly ‘‘factual’’ issues and that needed to solve
problems of the interpretation of plans and specifi-
cations has led some Government contracting agen-
cies to insist, perhaps correctly, that Article 15
itself covers the latter, without need for a supple-
mentary clause like paragraph 1-07. Cf. United
States v. Callahan-W alker Constr. Co., 317 U. 8S.
56 (‘‘equitable adjustment”’ required by change or-
der a ‘‘question of fact’’).**
%® The Court — Claims has, aeuees. mgd pow reed in
recent years, interpretation of plans specifications
feen teh enue water nude th of eh ee ee
Davis v. United States, 82 C. Cls. 334, 346-7; Callahan Con-
19
Nor, at the time this contract was made, did the
challenged clauses of the specifications involve
a new ‘‘question of policy,’’ upon which the specific
ruling of the Procurement Division was necessary.
By 1942, the policy had long been established.
Provisions substantially identical with paragraph
1-07 have been used in numerous government con-
struction contracts for at least thirty-five years, and
are now regarded as ‘‘common.’’** The widespread
use of the clause is proved most simply by a survey
of the Government contract cases in this Court
and the lower courts."* This conclusion is con-
struction Co. v. United States, 91 C. Cls. 538, 616-7; Schmoll
v. United States, 91 C. Cls. 1, 33; John McShain, Inc. v. United
States, 88 C. Cls. 284, 296-7 (reversed, 308 U.S. 512, 520) ; B-W
Construction Co. v. United States, 97 C. Cls. 92, 118; Ger-
hardt F. Meyne v. United States, C. Cls. No. 45926, decided
April 5, 1948; Orino v. United States, C. Cls. No. 46063, de-
cided June 1, 1948; instant opinion, R. 62.
17 Anderson, The Disputes Article in Government Contracts
(1945) 44 Mich. L. Rev. 211, 215, 238-239; B-W Constr. Co. v.
United States, 101 C. Cis. 748, 768 (“It is true that it is not un-
common in construction contracts for the parties to agree that
the decision of the architect or engineer shall be final on such
uestions as the proper interpretation of the plans and speci-
cations * ").
18 The cases in this Court in which it cl Sr svpates at Se
contract contained such a provision are:Merril-
Co. v. United States, 241 U. S. 387, 388, 393 (1916) ; United
in, Inc., 308 U. 8. 512, 520 (1939) ; United
States v. Joseph A. H. Co., 328 U. S. 234, 237 (1946).
Recent cases in the lower federal courts are: Fred R. C Co.
v. United States, 100 C. Cls. 259, 260; King v. United States,
’ . v
100 C. Cls. 475, 482; Fleisher Eng. & Constr. Co. v. United
States, 98 C. Cls. 139, 141; Langevin v. United States, 100 C.
Cls. 15, 26; McC & Co. v. United States, 103 C. Cls. 254;
Union rece ws nited States, 107 C. Cis. 405, 413, 41
422; United v. Madsen Constr. Co., 139 F. 2d
(C.C.A. 6); English Constr. Co. v. United States, 43
313 (D. Del.).
so:
20
firmed by a hasty search through the Government’s
construction-contract records back to 1920, which
reveal that the clause has been used by various gov-
ernment bureaus doing construction work, and con-
sistently by the main such agency, Public Buildings
Administration and its predecessors.” Specifically,
similar provisions were widely used in general
construction specifications, both before the adop-
tion of Standard Form No. 23 in 1926 and there-
after, including the fifteen-year period since the
Procurement Division was granted authority to
require the use of standard forms (see fn. 10, supra,
p. 14). The Procurement Division has been cog-
nizant of, and has always regarded, the inclusion of
such a clause together with Standard Form No.
1° The old Office of the Supervising Architect included in its
“General Conditions” a provision that “The decision of the
Supervising Architect as to the proper interpretation of the
drawings and specifications shall be final,” or, later (e.g. 1932),
that “The decision of the Contracting Officer or his duly author-
ized representative as to the proper interpretation of the draw-
ings and specifications shall be final.” By Executive Order
No. 6166, June 10, 1933 (supra, p. 14, fn. 10), the Office of
the Supervising Architect was transferred to the ‘newly-created
Procurement Division of the Treasury Department. The same
clause was used by the Public Buildin Branch of the Pro-
curement Division (successor to the Office of the Supervising
Architect). By Reorganization Plan No. 1, effective July 1,
1939, 53 Stat. 1423 (note following 5 U.S.C. 133t), the Public
Buildings Branch was transferred to the Federal Works Agency,
and became known as Public Buildings Administration. That
Administration has at all times retained the clause in the
“General Conditions” to its construction contracts, and em-
ploys it a:
In addition, eases cited above (fn. 18), indicate Set 0
similar clause has been used by many other sam caeeaggee
cies, including the War Department, ureau of ian
Affairs, the t of the Interior, Public Works Admin-
istration, oo e Civil Aeronautics Administration.
21
23 as wholly unexceptionable. This is shown most
vividly by the fact that the Procurement Division’s
own Public Buildings Branch made use of the com-
bination from 1933 to 1939, and that since its trans-
fer in that year, the Public Buildings Administra-
tion, the chief government construction agency, has
uniformly employed a ‘‘proper interpretation’’
clause in the General Conditions of its specifica-
tions. Long-established administrative practice of
this strength compels the conclusion that the dis-
puted paragraph cannot be viewed as a deviation
from, or inconsistent with, the standard form, or
as involving an unsettled matter of policy. Cf.
Norwegian Nitrogen Products Co. v. United States,
288 U.S. 294, 315.”
Not only is the instant decision in conflict with
the settled practice, and unsupported by the terms
of Standard Form No. 23, but it constitutes a com-
20 Even if paragraph 1-07 be regarded as a deviation from, or
inconsistent with, Article 15, the established practice of fifteen
years indicates tacit authorisation by the Director of Procure-
ment (as he then was).
The lower court's observation that no notation was made
under the “Alterations” article of the standard form (R. 60-61)
is obviously far wide of the mark. The “Alterations” article
refers only to “changes * * * made in this contract before
it was signed by the parties hereto” (R. 65), and no relevant
changes “in this contract” were made. Article 15 was not al-
tered in any way, and no reference had to be made to the addi-
tion of paragraphs 1-07 and 1-08 of the specifications since
Article 1 of the standard form specifically made the specifica-
tions “a part” of the contract (R. 30; 41 C.F.R. 12.23, p.
1326). It is clear from the Article 22 (“Alterations”) con-
tained in respondent's contract that that provision was used
only to note actual deletions from, or changes in, the standard
my and the specifications submitted with the invitation
22
plete volte face from recent decisions of the Court
of Claims on all fours with this one.” In Langevin
v. United States, 100 C. Cls. 15, 25-26, 40-41 (1943),
the standard form was used, with the normal
Article 15, and the specifications contained a clause
akin to paragraph 1-07; the court below did not
hesitate to recognize and apply the latter provision.
McCloskey & Co. v. United States, 103 C. Cls.
254, 255-256, 264-265 (1945), involving a similar
coupling of disputes provisions, expressly rested
on the ‘‘proper interpretation’’ clause in holding
that the plaintiff could not recover for certain back
counters in a government cafeteria which it claimed
were not called for by the plans and specifications,
but which the contracting officer required to be
built. And in Union Paving Co. v. United States,
107 C. Cls. 405, 408-409, 417 (1946); with similar
contract and specifications, the court relied on the
interpretation provision in the specifications in
holding that the contractor could not recover for
having to use more concrete than it believed was
called for by the specifications. Not only the
novelty but the error of the instant opinion are
underscored by these prior decisions of the Court of
Claims itself.
21 We do not stress a conflict with United States v. John
McShain, Inc., 308 U. S. 512, 520, and United States v. Joseph
A. Holpuch Co., 328 U. S. 234, because Standard Form No. 23
was not used in those cases, and Article 15 (“Disputes”) was
not limited to questions of fact. See fn. 15, supra, p. 17. The
present significance of those cases rests on the fact that they
demonstrate that there is no overall executive, legislative or
judicial policy opposed to provisions according finality to ad-
ministrative decisions of the character here involved.
23
b. In any event, during World War II, the War
Department (the contracting agency here) was
freed by Title II of the First War Powers Act (Act
of December 18, 1941, c. 593, 55 Stat. 838, 839, 50
U.S.C. App. 611) and by Executive Order No. 9001
(3 C.F.R., 1941 Supp., pp. 330-332, December 27,
1941) from the requirement of using the Procure-
ment Division’s standard forms. The statute
authorized the President to permit the war agencies
‘‘to enter into contracts and into amendments or
modifications of contracts * * * without regard to
the provisions of law relating to the making, per-
formance, amendment, or modification of contracts
* * *? and the Executive Order delegated this
power to the War Department, expressly authoriz-
ing ‘‘agreements of all kinds’. As the Attorney
General said in a classic opinion on the Act and
Order (40 Op. Atty. Gen. No. 53, August 29, 1942,
pp. 4, 6), ‘‘the grant is without any limitation what-
ever’’ (save certain specific exceptions not now
relevant), and surely permitted the disregard of
legislation and executive directions concerning the
distribution of procurement functions within the
Government.” During the active life of Title IT
of the First War Powers Act, the War Department
22 The Attorney General’s opinion specifically mentioned (pp.
4, 6), as among the statutes which could be superseded, the
Act of February 27, 1929, 45 Stat. 1341, 41 U.S.C. 7a-7d, cen-
tralizing government purchasing in the Treasury Department.
This is one of the two main acts under which the Procurement
Division (now the Bureau of Federal Supply) has operated.
See Note following 41 U.S.C. 7. The other statute is the Act
of June 17, 1910, 36 Stat. 531, 41 U.S.C. 7.
24
did not consider itself bound to use the peacetime
standard forms, and as a matter of practice fre-
quently departed from the terms of the Procure-
ment Division’s contracts, or instituted new forms,
without seeking or securing any authorization from
the peacetime promulgating agency.” Thousands
upon thousands of war contracts were made which
did not comply with the Treasury’s regulations.
The Procurement Division accepted the Attorney
General’s and the war agencies’ views as to the
scope of the First War Powers Act, and the Comp-
troller General did not object to the use of non-
standard forms.” It follows that the lower court’s
views as to the limits of a contracting officer’s au-
thority to use the Procurement Division’s standard
forms are wholly irrelevant and incorrect as to all
wartime agreements entered into by the many
agencies endowed with power under Title IT of the
First War Powers Act.
3. The Court of Claims’ secondary reason for
ignoring paragraph 1-07 is, apparently, that the
23 The War Department issued an entire series of its own
standard form contracts. See e.g., War Department Procure-
ment Regulations, pars. 304, 1301-1325, 10 C.F.R. Cum. Supp.
81.304, 81.1301-81.1325. Cf. Fain and Watt, War Procure-
ment—A New Pattern for Contracts (1944) 44 Col. L. Rev. 127.
*4A memorandum recently submitted by the Bureau of
Federal Supply to a Senate Committee states that after enact-
ment of the First War Powers Act “the Military Establish-
ment enjoyed for war purposes a complete exemption from all
authority of the Bureau of Federal Supply with respect to
procurement.” Hearings before the Senate Committee on
Expenditures in the Executive Departments, 80th Cong., 2d
sess. on the proposed Federal Property Act of 1948, p. 129.
25
clause was not designed to apply to matters of
‘‘amounts due,’’ but was an interim device requir-
ing the contractor to accept the administrative in-
terpretation during performance but leaving him
entirely free to contest it after completion (R.
61-62). Paragraph 1-07 (‘‘Interpretation of Con-
tract’’), however, flatly makes the contracting offi-
cer the ‘‘interpreter’’ of the ‘‘intent and meaning”’
of the ‘‘drawings and specifications’’, without
qualification as to time or purpose, and paragraph
1-08 provides for an appeal from an adverse inter-
pretation to a tribunal whose decision ‘‘shall be final
and binding upon the parties to the contract.’’ The
lower court’s peculiarly strained construction is
also denied by the long practice under clauses such
as these, both in government and in private con-
tracts, which appears never to have doubted that
the arbiter’s interpretation is final for all pur-
poses.” In addition, this Court and the Court of
Claims in its prior decisions have always accepted
clauses of this type as meaning precisely what they
say, in cases directly involving questions of contract
price or ‘amounts due.’’ Merrill-Ruckgaber Co. v.
United States, 241 U. S. 387, 392-393 ; United States
v. John McShain, Inc., 308 U.S. 512, 520; United
States v. Joseph A. Holpuch Co., 328 U. S. 234;
Langevin v. United States, 100 C. Cls. 15, 39-41;
McCloskey & Co. v. United States, 103 C. Cls. 254:
25 See supra, p. 16, especially the collection of cases in
Tobin Quarries, Inc. v. Central Nebraska Public Power &
Irr. Dist., 64 F. Supp. 200, 208-210 (D. Nebr.).
26
Union Paving Co. v. United States, 107 C. Cls. 405,
417.
4. This decision of the Court of Claims, substan-
tially destroying the effectiveness of the commonly-
used ‘‘proper interpretation’’ clause, will operate,
in a very large and significant class of cases, to
deprive the Government ‘‘of the benefits of the ad-
ministrative machinery it has created to adjudicate
disputes and to avoid large damage claims.”’
United States v. Blair, 321 U.S. 730, 735. As
we have indicated (supra, pp. 19-21), provisions
similar to paragraph 1-07 have for years been used
in government construction contracts by many agen-
cies, and are currently being included in numbers
of agreements. Unless the instant decision is re-
viewed and corrected, all vitality will be drawn
from hundreds of such clauses contained in con-
tracts still outstanding or subject to litigation. The
proper functioning of government procurement
will also be seriously impeded by two other impor-
tant aspects of the decision: (a) by permitting con-
tractors who consent to certain contractual provi-
sions later to attack the contracting officer’s author-
26 The Court of Claims implicitly admits that its decisions on
Claims 2 and 3 necessarily involved interpretations of the
drawings and specifications (R. 59-62). The court’s findings
and opinion make this indisputable (R. 33-35, 51-54). See
supra, pp. 5-9. There is some slight suggestion that the ad-
ministrative interpretations were arbitrary (R. 34), but the
court does not actually go on that ground (R. 33-35, 51-54,
59-62) ; and, in any case, a reading of the pertinent decisions
of the Board of Contract Appeals (supra, pp. 7, 8, fn. 4, 7),
together with the opinion below, demonstrates that the ad-
ministrative determinations were entirely reasonable.
ity, the lower court opens the door for contractors
to escape from distasteful clauses by first accepting
and then disavowing them, and (b) by making it
hazardous to forecast whether a particular added
clause, no matter how ancient or useful, will be
enforced in the Court of Claims, the decision be-
low severely limits the freedom of government
agencies to supplement the terms of standard form
contracts. We do not hesitate, therefore, once
again to petition this Court for relief from a deci-
sion by the Court of Claims nullifying an important
and established clause in government contracts on
the thinnest of grounds.
CONCLUSION
For the reasons stated, it is respectfully sub-
mitted that this petition should be granted.
Purr B. PERLMAN,
' Solicitor General.
OcTOBER 1948.
28
APPENDIX
Article 15 of the Contract provides:
Disputes.—Except as otherwise specifically
provided in this contract, all disputes concern-
ing questions of fact arising under this con-
tract shall be decided by the contracting officer
subject to written appeal by the contractor
within 30 days to the head of the department
concerned or his duly authorized representa-
tive, whose decision shall be final and conclu-
sive upon the parties thereto. In the mean-
time the contractor shall diligently proceed
with the work as directed.
Paragraphs 1-07 and 1-08 of the specifications
provide:
1-07. Interpretation of Contract—Unless
otherwise specifically set forth, the Contractor
shall furnish all materials, plant, supplies,
equipment, labor, etc., necessary to complete
the work according to the true intent and mean-
ing of the drawings and specifications, of which
intent and meaning the Contracting Officer
shall be the interpreter. Except when other-
wise indicated, no local terms or classifications
will be considered in the interpretation of the
contract or the specifications forming a part
thereof.
1-08. Claims, Protests and Appeals.—If the
Contractor considers any work demanded of
him to be outside the requirements of the con-
tract or if he considers any action or ruling
of the Contracting Officer or of the inspectors
29
to be unfair, the Contractor shall without un-
due delay, upon such demand, action, or ruling,
submit his protest thereto in writing to the
Contracting Officer, stating clearly and in de-
tail the basis of his objections. The Contract-
ing Officer shall thereupon promptly investi-
gate the complaint and furnish the Contractor
his decision, in writing, thereon. If the Con-
tractor is not satisfied with the decision of the
Contracting Officer, he may, within thirty days,
appeal in writing to the Secretary of War,
whose decision or that of his duly authorized
representative shall be final and binding upon
the parties to the contract. Except for such
protests or objections as are made of record
in the manner herein specified and within the
time limit stated, the records, rulings instruc-
tions or decisions of the Contracting Officer
shall be final and conclusive. All appeals from
decisions of the Contracting Officer authorized
under the contract shall be addressed to the
Secretary of War, Washington, D. C. The
appeal shall contain all the facts or cireum-
stances upon which the Contractor bases his
claim for relief and should be presented to the
Contracting Officer for transmittal within the
time provided therefor in the contract.
wu. s. GOVERNMENT PRINTING OFFICE: 1948 8073989 148