Transcript of Record — United States v. Binghamton Construction Co.

Supreme Court brief1954

Ask Donna

What actually matters in this document.

Text

IN THE SUPREME COURT OF THE UNITED

STATES

OcToBER TERM, 1953

No. 65

THE UNITED STATES, PETITIONER

vs.

BINGHAMTON CONSTRUCTION CO., INC.

No. 78

BINGHAMTON CONSTRUCTION CO., INC., PETITIONER

vs.

THE UNITED STATES

ON PETITIONS FOR WRITS OF CERTIORARI TO THE UNITED

STATES COURT OF CLAIMS

INDEX

Original Print

Record from the United States Court of Claims__-____-_-___- 1 1

EG navies Sane eStethverebensseerséecetenes ane 1 1

Exhibit—Contract dated May 14, 1941, bet ween

United States and Binghamton Construction Com-

atc acivwbtec ese Keeeum pene censoserneesseec 10 5

Exhibit—Specifications re above contract___.-_----- 14 8

General traverse__._...----.------------------------- 19 12

Report of Comimissioner___-_------------------------- 21 12

Proceedings following filing of Commissioner’ s report____- 49 36

First amended petition_-_-__-_---_-_-_-----_-----_--- 51 36

Contract and Specifications copies) (omitted in

DR cect we poenid un bese secrete sucnes Oneewus 60 41

Argument and submission of case___._________ .________- 71 41

Special findings of fact..___...._._________________--- 73 41

Conciusion of law__._-_----------_-----------_-.----- 100 65

Opinion, Whitaker, J.-...__._____-________-_-_-_-_-_- 100 65

Judgment. __..-.-.--------------- eee 109 72

Protedings after entry of judgment__________________- 111 73

Clerk’s certificate (omitted in printing)___._____._.______- 113 73

Orders extending time to file petitions for certiorari______- 114, 115 73, 74

264722—53——_1

BLURRED COPY

BLEED THROUGH-— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 1

1 In the Court of Claims of the United States

No. 48525

Brncuamton Construction Co., INc., PLAINTIFF

v.

Unrrep States or AMERICA, DEFENDANT

Petition

Filed January 22, 1948

To the Court of Claims of the United States:

The petition of the plaintiff respectfully represents that:

I

1. The plaintiff is, and at all times hereinafter referred to was,

a corporation organized and existing under the laws of the State

of New York, with its principal place of business in Binghamton,

New York.

2. The plaintiff has, at all times, borne true allegiance to the

Government of the United States and has not in any way volun-

tarily aided, abetted or given encouragement to rebellion against

the said government.

2 3. On or about March 29, 1941, the United States Army

Engineer Office at Binghamton, New York, invited bids

for the construction of Flood Protection Project (Section No. 1)

aleng the right bank of the Chemung River within the limits of

the City of Elmira, Chemung County, New York. The plain-

tiff, in response to such invitation, submitted a bid in the fixed

amount of $232,669.30 which, on April 29, 1941, was accepted.

Pursuant to such bid and acceptance, there was subsequently

executed Contract No. W-321-eng-261, dated May 14, 1941 (here-

inafter referred to as the “contract”), a copy of the material

portions of which is annexed hereto. Such contract was an au-

thorized and binding obligation of the defendant.

II

4. Under the provisions of the Act of August 30, 1935, 49 Stat.

1011—the so-called Davis-Bacon Act—the contract was required

to, and did, contain a provision obligating the plaintiff to pay

not jess than the wages determined by the Secretary of Labor to

be prevailing for the corresponding classes of laborers and me-

BLURRED COPY

2 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

chanics employed on projects of a character similar to the contract

work in the territoria! area in which such work was to be per-

formed. In the Specifications for the work covered by the con-

tract, which Specifications, dated March 29, 1941, were issued as

of the date thereof in connection with the advertisement for bids

as the basis upon which such bids were to be made, and which were

appended to and made a part of the definitive contract, the repre-

sentation was made that the Secretary of Labor had determined

the prevailing wage rates in the locality; and such rates were set

forth in Paragraph 1-1 of the Specifications. Among the rates

so given were the following:

3 Designation Wage rate, hourly

Carpenters, journeymen_____--~-~-- a oem A tnt $1. 00

* . * 7 *

Laborers, unskilled__-..---- ee ee 50

Laborers, concrete puddlers..................-...-... . 50

- ” * * 2

5. The plaintiff, acting on the basis of the wage rates stated in

the Specifications, as it was invited and entitled to do, computed

and submitted its bid. Subsequent to the acceptance of such bid

and after the execution of the definitive contract, the plaintiff

discovered that the wage rates for the classifications of labor re-

ferred to above in Paragraph 4 were not in fact the prevailing

rates for such labor as determined by the Secretary of Labor,

neither as of the time of the issuance of the Specifications, the

acceptance of the bid, nor the execution of the contract; and that

the Secretary of Labor in at least one instance, namely, on Feb-

ruary 25, 1941, had determined the prevailing wage rates in the

locality for these classifications of labor on a similar project to be

higher than those stated in the Specifications of March 29, 1941,

as follows:

Designation Wage rate, hourly

Carpentera, SenenegGheR....... 2. ene eee- $1. 125

* . : * *

ON . 55

EASE, GEES Be cncdnnencsemsneenee . 55

- . oe . .

Such determination of the Secretary of Labor was still in effect

and unmodified on March 29, 1941, and the Specifications issued

by the defendant on such latter date were defective and mislead-

ing in failing to reflect such determination.

t 6. Upon commencing work under the contract, the plain-

tiff was unable to procure labor of these classifications at the

rates stated in the Specifications, and was in fact obliged to pay

higher rates, as follows:

BLEED THROUGH— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 3

Designation Wage rate, hourly

Cospestens, OTN. ccwececcccwccecscccscoscoens $1. 125

* . . . .

Laborera, Guekilied......_.............-- “= - ~.625

Laborers, concrete puddlers . 625

- . * * *

7. The plaintiff was entitled to, and did, rely upon the wage

rates stated in the Specifications as being in accordance with the

most recent determinations by the Secretary of Labor of the wage

rates prevailing for the corresponding classes of workmen on

similar projects in the area; and was entitled to, and did, prepare

and submit its bid on this assumption. When, after the accept-

ance of its bid and the execution of the contract, it discovered the

error in the representations made to it, it was entitled to be reim-

bursed at the higher rates which it was required to pay in order to

perform the contract work, to the extent that such higher rates

were equivalent to the prevailing rates fixed by the Secretary of

Labor in her determination of February 25, 1941. The plaintiff

duly requested such reimbursement by appropriate adjustment in

the contract price, but the defendant wrongfully denied such

request.

8. The failure of the defendant so to adjust the contract price

has resulted injury and damage to the plaintiff in the amount of

$8,048.04, payment of which the plaintiff has duly demanded but

which the defendant has wrongfully refused.

5 Ill

9. The 6214¢ hourly wage rate with respect to laborers

(both unskilled and concrete puddlers) which the plaintiff was

obliged in fact to pay in order to procure labor to perform the

contract work was, in fact, the prevailing hourly rate in the locality

at the time of the issuance of the Specifications, the acceptance of

the bid, and the execution of the contract; and the 55¢ rate fixed

in the Secretary of Labor’s determination of February 25, 1941,

was less than the actual prevailing rate at such times. The failure

of the defendant to make an accurate representation in the Specifi-

cations to the plaintiff with respect to the hourly rate actually pre-

vailing at the time of the issuance of the Specifications, was a

breach of the defendant’s obligation to state such prevailing rates

correctly and not to mislead the plaintiff by representing that the

prevailing rates were lower than they were in fact. Because of

the fact that the plaintiff was obliged to pay the 6214¢ prevailing

rate in order to procure labor to perform the contract work, the

plaintiff was entitled, in addition to the claim hereinabove

described under Section II, to be further reimbursed for the dif-

BLURRED COPY

we te

4 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

ference between the 55¢ rate for laborers fixed in the Secretary

of Labor’s determination of February 25, 1941, and the 621,¢

hourly rate actually prevailing at the time of the issuance of the

Specifications, the acceptance of the plaintiff's bid, and the execy-

tion of the contract, which 621¢ rate the plaintiff was required

to, and did, pay. Plaintiff duly requested such reimbursement

but the defendant wrongfully denied such request.

10. The failure of the defendant to make such reimbursemer,

has resulted in injury and damage to the plaintiff in the

6 amount of $5,863.79, payment of which the plaintiff has

duly demanded but which the defendant has wrongfully

refused.

lV

11. Paragraph 7-05 (d) of the Specifications contained a de-

tailed description of the manner in which, and the materials with

which, the concrete involved in the construction was to be finished,

In submitting its bid, the plaintiff was entitled to, and did, rely

upon the statements made in said Paragraph 7-05 (d) in com-

puting the cost to it of finishing such concrete. During the per-

formance of the contract, the defendant ordered and required the

plaintiff to finish the concrete in a manner and with materials not

specified in, or reasonably contemplated by, the Specifications,

with the result that plaintiff was subjected to unauthorized and

unanticipated costs, reimbursement of which was duly requested

by the plaintiff but wrongfully denied by the defendant.

12. The defendant’s wrongful conduct in this respect has

resulted in injury and damage to the plaintiff in the amount of

$7,082.74, payment of which the plaintiff has duly demanded but

which the defendant has wrongfully refused.

V

13. Under the provisions of Paragraph 3-06 of the Specifica-

tions, the plaintiff was required to furnish certain sheeting and

shoring. Subparagraph (c) of said Paragraph 3-06 provided

that such sheeting and shoring was to be measured “by the square

foot of protected area,” and subparagraph (d) of said Paragraph

3-06 provided that payment for sheeting and shoring would

7 be made at the contract unit price of Sixty-five Cents

($0.65) per square foot, as stated in the Schedule of Pay-

ments annexed to and made a part of the contract.

14. In computing its bid, the plaintiff was entitled to, and did,

rely upon the statements contained in Paragraph 3-06 as to the

measurement of sheeting and shoring by the square foot of pro-

tected area, and computed its bid on the basis of square footage

a

BLEED THROUGH- POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 5

of the area required to be protected. During the performance of

the contract, however, the defendant refused to pay the plaintiff

for sheeting and shoring in accordance with the square footage

of the protected area, and, instead, followed an arbitrary and

unauthorized method of measurement, not in accordance with the

Specifications, which resulted in the underpayment of the plaintiff

for sheeting and shoring. Although the plaintiff duly requested

payment of the proper amount as contemplated by the contract,

such request was wrongfully refused by the defendant.

15. The wrongful conduct of the plaintiff in this respect resulted

in injury and damage to the plaintiff in the amount of $14,110.85,

payment of which the plaintiff has duly demanded but which the

defendant has wrongfully refused.

vi

16. Although the plaintiff duly and formally protested to the

Contracting Officer the wrongful actions complained of above, the

Contracting Officer refused to afford the plaintiff any relief, and,

upon appeal to the Chief of Engineers, was upheld by the latter.

Appeals by the plaintiff to the War Department Board of Con-

tract Appeals were, on January 14, 1947, dismissed for an

8 asserted lack of jurisdiction. Except as hereinbefore re-

ferred to in this Paragraph 16, no action on the claims has

been taken by Congress or by any department of the government.

17. The plaintiff is justly entitled to recover from the defendant

the aggregate sum of $35,105.22, after allowing all just credits

and offsets.

18. The plaintiff has made no assignment or transfer of the

claims or any part thereof, and no persons other than the plaintiff

are owners of the claims or of any interest therein.

Wherefore, it is respectfully prayed that judgment be granted

against the defendant and in favor of the plaintiff for the sum of

$35,105.22, together with such costs as may be properly allowable

to it in respect of this suit.

Dove.as, Procror, MacIntyre & Gares,

Attorneys for the Plaintiff, Office and Post Office Ad-

dress, 730 Southern Building, Washington 6, D. C.

9 [Duly sworn to by Malcolmn A. MacIntyre; jurat omitted

in printing. |

10 Exhibit to Petition

U. S. Standard Form No. 23—Rev.

Approved by the Secretary of the Treasury. Revised Sep-

tember 17, 1938. Contract No. W-321-eng-261. Dated May 14,

1941.

BLURRED COPY

6 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO.,, INC,

ConwrTracr

(Construction )

War DEPARTMENT

UNITED STATES ENGINEER OFFICE

Binghamton, New York

(Department)

BrncHamtTon Construction Co. Inc.

MARINE MIDLAND BANK BUILDING

Binghamton, New York

(Contractor)

Contract for Elmira Flood Protection Project (Section No. 1),

Amount, $232,669.30.

Place, Right Bank of Chemung River, Elmira, New York.

CONTRACT FOR CONSTRUCTION

This contract, entered into this 14th day of May 1941, by The

United States of America. hereinafter called the Government,

represented by the contracting officer executing this contract, and

Binghamton Construction Co., Inc., a corporation organized and

existing under the laws of the State of New York, of the city of

Binghamton, in the State of New York, hereinafter called the

contractor, witnesseth that the parties hereto do mutually agree

as follows:

ArrticLe 1. Statement of work.—The contractor shall furnish

the materials, and perform the work for construction of Flood

Protection Project (Section No. 1) along the right bank of the

Chemung River, within the limits of the City of Elmira, Che-

mung County, New York, for the consideration shown on Schedule

of Payments attached hereto, in strict accordance with the

11 specifications, schedules, and drawings, all of which are

made a part hereof and designated as follows: Specifica-

tions: No. 3821-41-15 War Department Appropriation: 21X3113

Flood Control, General Flood Protection Project (Section No. 1)

at Elmira, New York, dated U. S. Engineer Office, Binghamton,

New York, March 29, 1941, with Addendum No. 1, dated April

12, 1941, attached thereto.

Schedules: Payments, in three (3) sheets.

Progress chart marked “Major Operations of Elmira Flood

Protection Section #1 Submitted by Binghamton Constr. Co.”

Drawings: Maps and drawings marked “Southern New York

Flood Control Project, Elmira Flood Protection Project, Section

——

BLEED THROUGH POOR COPY

—_—_

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 7

number one, Elmira, New York, in 32 sheets, designated in para-

graph 1-04 of the specifications cited, as modified by Addendurn

No. 1.

The work shall be commenced within ten (10) calendar days

after the date of receipt by the contractor of notice to proceed and

shall be completed within five-hundred and fifty (550) calendar

days after said date of receipt of notice to proceed.

Arricte 15. Disputes.—Except as otherwise specifically pro-

vided in this contract, all disputes concerning questions of fact

arising under this contract shall be decided by the contracting

officer subject to written appeal by the contractor within 30 days

to the head of the department concerned or his duly authorized

representative, whose decision shall be final and conclusive upon

the parties thereto. In the meantizwe the contractor shall

diligently proceed with the work as directed.

* * + * *

Articié 17. Rate of wages (in accordance with the act of

August 30, 1935, 49 Stat. 1011 (U.S. Code, title 40, sections

12 276a and 276a-1), this article shall apply if the contract is

in excess of $2,000 in amount and is for the construction, al-

teration, and/or repair, including painting and decorating, of a

public building or public work within the geographical limits of

the States of the Union or the District of Columbia).

(a) The contractor or his subscontractor shall pay all mechan-

ics and laborers employed directly upon the site of the work, un-

conditionally and not less often than once a week, and without

subsequent deduction or rebate on any account, the full amounts

accrued at time of payment, computed at wage rates not less than

those stated in the specifications, regardless of any contractual

relationship which may be alleged to exist between the contractor

or subcontractor and such laborers and mechanics; and the scale of

wages to be paid shall be posted by the contractor in a prominent

and easily accessible place at the site of the work. The contracting

officer shall have the right to withhold from the contractor so

much of accrued payments as may be considered necessary by the

contracting officer to pay to laborers and mechanics employed by

the contractor or any subcontractor on the work the difference

between the rates of wages required by the contract to be paid

laborers and mechanics on the work and the rates of wages re-

ceived by such laborers and mechanics and not refunded to the

contractor, subcontractors, or their agents.

(b) In the event it is found by the contracting officer that any

laborer or mechanic employed by the contractor or any subcon-

tractor directly on the site of the work covered by the contract

has been or is being paid a rate of wages less than the rate of

264722—53——_2

BLURRED COPY

8 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

wages required by the contract to be paid as aforesaid, the Goy-

ernment may, by written notice to the contractor, terminate his

right to proceed with the work or such part of the work as to

which there has been a failure to pay said required wages and

prosecute the work to completion by contract or otherwise, and the

contractor and his sureties shall be liable to the Government for

any excess costs occasioned the Government thereby.

* ~ * » a

13 In witness whereof, the parties hereto have executed this

contract as of the day and year first above written.

Approved June 3, 1941.

Tue Unirep States oF AMERICA,

Bv (S) J.C. Marshall,

J. C. MarsHat,

Major, Corps of Engineers,

District Engineer (Official Title).

(S) J. N. Hodges,

J. N. Hopees,

Colonel, Corps of Engineers,

Division Engineer, North Atlantic Division.

BincuamTon Construction Co. Inc.,

Contractor.

[CORPORATE SEAL | By (S) Donaup G. Davis,

Pres., Marine Midland Bank Bldg., Binghamton, New

York (Business Address).

Two witnesses:

(S) Heren G. Cameron.

(S) Joan Minnow.

I, Joseph J. Cox, certify that I am the secretary of the corpora-

tion named as contractor herein; that Donald G. Davis who signed

this contract on behalf of the contractor, was then President of

said corporation; that said contract was duly signed for and in

behalf of said corporation by authority of its governing body,

and is within the scope of its corporate powers.

[CORPORATE SEAL | (S) Joseru J. Cox,

Secretary.

Exhibit to Petition

14 This project is authorized by the act of June 22, 1936

(Public No. 738, 74th Congress (as amended by the act

approved June 28, 1938 (Public No. 761, 75th Congress).

BLEED THROUGH- POOR COPY

>

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 9

No. 321-41-1%

U. S. Enoerneer Orrice,

Binghamton, New York, March 29, 1941.

War Department

Appropriation: 21X3113 Flood Control, General Flood Pro-

tection Project (Section No. 1) at Elmira, New York.

SPECIFICATIONS

Section I. General Provisions

1-01. Location.—The site of the proposed work is along the

right bank of the Chemung River within the limits of the City

of Elmira, Chemung County, New York.

1-02. Work to be Done.—(a) The work provided for herein is

authorized by the act approved June 22, 1936 (Public No. 738, 74th

Congress) as amended by the act approved June 28, 1938 (Public

No. 761, 75th Congress).

(b) The work to be done consists of furnishing all plant, labor,

equipment, and materials, and performing all work required for

the construction of Flood Protection Project (Section No. 1) at

Elmira, New York, and all appurtenant works, complete in strict

accordance with these specifications and maps and contract draw-

ings forming a part hereof. It will consist of the following

major items:

(1) Construction of levee embankments.

(2) Construction of new concrete walls.

(3) Raising an existing wall.

(4) Construction and alteration of sewers, culverts, drains, and

manholes.

* * * * *

15 1-31. Wage and Labor Provisions.—(a) The Secretary

of Labor has determined the minimum wage rates applica-

ble in the locality for the labor classifications anticipated to be

used on the work. In accordance with Article 17 of the contract,

employees at the site shall be paid not less than these wages as

listed below :

Designation Wage rate, hourly

Carpenters, journeymen______ ‘ _.. $1.00

Cement finishers, structures___._.......---_----- 1. 50

Electricians ___- — . 1.12%

Laborers, unskilled__.._._.__.____-__- ae

Laborers, concrete puddlers____--- aa.

Mechanics, heavy equipment_____-_ ee

Oilers, heavy equipment Selb eamiaistacaediip aes ae: |

Operators, air compressors, 160 cubic feet and under SE aren . 85

Operators, air compressors, over 160 cubic feet 1.00

BLURRED COPY

_ —

10 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

Designation Wage rate, hourly

Operators, batcher plant__........-.--------~------~-----------«. $0. 60

Operators, bulidozers_.......--.---......----~---------------... 1.00

Operators, cranes and draglines_-__-.....-..-..-.----~---------.- 1.5

Operators, clamshellis_.........-.......-.---------------------- 1.50

Operators, hand held reck drill_._....._...--.-------------.~--~- 1%

Operators, mixers, under 21E_-.._------ sid aeshididiesehinataatapaioiaanals 1.00

Operators, mixers, 215 and over_.._.......--------.---.----~=--. 1.50

Operators, pet, 4 te. ald GnGer..... - nn nn snes .75

Operators, pump, over 4in-_....-.....--.----~-----------------.. 1.00

Operators, piledrivers.._.......-.....--..--~----=~--~----=----- 1.50

Qperatets, spvels <<. n eevee eee) eC 1.50

Operators, tractors.__.....------------------------------------ 85

Operators, ‘wagon drill, pneumatic i craehgegnsatandigveillaistenteseieghgitdgilleaapintehddials 90

eo | Se ee ee ene ee ee jusbhaeee abeaeanienannesiaie 1

Rieteteertet CPG ok sic cece oon caccenssnnnmereiemabionenge 1.5

DV Qiao occ ici ee bdiraitiin adnan aibamannnbenaeiapin . 55

Welders—Receive the rate prescribed for craft performing opera-

tion to which welding is incidental.

The above list of wages shall be posted by the contractor in a

conspicuous place on the work.

16 (b) In the event that it becomes necessary to employ any

laborer or mechanic whose work is not covered by any of

the classifications in the schedule, he shall be paid not less than

the prevailing rate of wages in the locality where the work is done

for the class of work done by him. Such rate shall be determined

by the contracting officer. In case any dispute arises as to what

are the prevailing rates of wages for work of a similar nature that

cannot be adjusted by the contracting officer, the matter shall be

referred to the Secretary of Labor for determination, and his

decision shall be conclusive on ail parties hereto.

* * * * *

1-38. Approval.—This contract shall be subject to the written

approval of the Division Engineer, North Atlantic Division, and

shall not be binding until so approved.

* * * * *

3-06. Sheeting and Shoring—(a) General—The contractor

shall furnish and place such sheeting, shoring. bracing, or other

approved supports as are indicated on the contract drawings or

directed by the contracting officer for the protection of the work

or adjoining property. The right is reserved to order the installa-

tion of sheeting and shoring where its use is considered advisable

for the safety of the work, and to require such sheeting and shoring

to remain in place when its removal is considered inadvisable.

(b) Procedure.—All sheeting and shoring shall be designed by

the contractor and approved by the contracting officer prior to

installation, but such approval by the contracting officer shall not

relieve the contractor of sole responsibility for damages resulting

from the inadequacy or lack of any sheeting and shoring. The

sheeting and shoring shall be built to provide adequate clearances

ST

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 1]

for minimum interference with construction operations, proper

bracing for stability, and safe conditions around the work. If, in

the opinion of the contracting officer, any methods or meas-

17 ures of the contractor constitute a hazard in any way or are

otherwise improper or inadequate, the contracting officer

will notify the contractor of that fact in writing. If the con-

tractor fails to provide immediately such remedial measures as

are deemed necessary by the contracting officer, such measures

will be provided by the contracting officer at the expense of the

contractor. When sheeting and shoring have served their pur-

and their removal is approved by the contracting officer, they

shall be removed and disposed of. Whether sheeting and shoring

are removed or left in place, all cavities shall be adequately filled.

When approved by the contracting officer, sheeting and shoring

may be used in lieu of excavation to full pay lines.

(c) Measurement.—Sheeting and shoring will be measured by

the square foot of protected area.

(d) Payment.—Except as specified below, payment for all costs

of furnishing and placing sheeting and shoring indicated on the

contract drawings or directed by the contracting officer, and of its

removal and disposal when not left in place, will be made at the

contract unit price for “Sheeting (Including Shoring),” Item

No. 7. Where sheeting and shoring are used at the contractor’s

option and with the approval of the contracting officer, separate

payment will not be made for the sheeting and shoring, but pay-

ment will be made for excavation to the pay lines shown on the

contract drawings as though the cut had been made to such pay

lines.

a » * * *

7-05. Details of Construction.—

(d) Finishing.—Immediately following removal of forms, all

form tie holes shall be filled, protruding fins or other surface ir-

regularities removed by carborundum stone and all other defects

repaired. Where necessary to obtain a suitable surface finish, the

contractor shall remove the form and finish the surfaces when and

as directed by the contracting officer at no additional cost to

18 the Umited States. The curing specified in subparagraph

7-05 (e) following shall be temporarily suspended during

such repairing or finishing as directed. The finished surfaces

shall be free from sand streaks or other defects and the plaste».

ing over of such surfaces will not be permitted. Defective con-

crete shall be repaired by cutting out the unsatisfactory material

and placing new concrete which shall be formed with keys, dove-

tails, and anchors to attach it securely to the other work. This

concrete shall be drier than the usual mixture and shail be thor-

oughly tamped into place. All surfaces of concrete, not covered

BLURRED COPY

a

12 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

by forms, that are not to be covered by additional concrete or

backfill shall have a wood float finish without additional mortar,

and shall be true to elevations as shown on contract drawings,

Striking-off and finishing shall follow closely the placing opera-

tion in order to insure completion before the initial set has taken

place. The contractor will not be permitted to start a pour unless

a sufficient number of qualified finishers are available to fulfill

the above requirements. Care shall be taken to see that all excess

water is removed before making the finish. Other surfaces shall

be brought to the specified finished elevation and left true and

regular as approved by the contracting officer. Where consid-

ered necessary by the contracting officer, or where indicated on the

drawings, joints shall be made carefully with a jointing tool.

Every precaution shall be taken by the contractor to protect fin-

ished surfaces from stains or abrasions. No fire shall be per-

mitted in direct contact with any concrete at any time. Concrete

surfaces or edges likely to be injured during the construction

period shall be properly protected by leaving the forms in place

or by erecting covers satisfactory to the contracting officer.

* * * * *

19 General traverse

Filed March 2, 1948

And now comes the Attorney General, on behalf of the United

States, and answering the petition of the claimant herein, denies

each and every allegation therein contained; and asks judgment

that the petition be dismissed.

(S) H. G. Morison,

Acting Assistant Attorney General.

ETF, JJS.

21 In the United States Court of Claims

[ Title omitted]

Report of commissioner

Filed June 5, 1951

To the Honorable the Chief Judge and Associate Judges of the

United States Court of Claims:

Pursuant to the order of reference in the above-entitled case, the

undersigned Commissioner makes the following report of his

findings of fact:

1. Plaintiff is, and at all times material herein has been, a cor-

poration organized and existing under the laws of the State of New

BLEED THROUGH— POOR COPY

_—_

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 13

York with its principal office and place of business at Bingham-

ton, New York. Since its formation in 1929, it has been engaged

in business as a general contractor.

2. On March 29, 1941, defendant acting by and through the

War Department’s Corps of Engineers’ Office at Binghamton,

New York, invited bids for the construction of Flood Protection

Project (Section No. 1) along the north bank of the Chemung

River, within the limits of the city of Elmira, Chemung County,

New York. In response to said invitation, plaintiff submitted a

bid based upon a unit price applied to the various operations in-

volved in the performance of the work in the total sum of $232,-

669.30. This bid was accepted by defendant on May 14, 1941.

On that date plaintiff and defendant entered into a written con-

tract, No. W-321-eng-261, which was approved June 3, 1941.

On June 5, 1941, defendant gave plaintiff a formal notice to pro-

ceed with the work. Actual work commenced on the site of the

job on June 3, 1941.

3. The contract was performed by plaintiff, and it has been paid

the contract price, as adjusted, for change orders with

22 ~=—the exception of $100 which plaintiff instructed the District

Engineer to withhold, and plaintiff has refused to accept

said $100 from defendant on advice of its counsel.

4. Plaintiff sues for the sum of $35,105.42, the total of three

separate claims, as follows:

Claim for reimbursement of wage rates paid to carpenters,

laborers, and concrete puddlers___-- $13, 911. 83

Claim as regards measuring of sheeting and shoring____________ 14, 110. 85

Clinton Tee GeReREns OF CONCTOUO.. 2.2 ecco cnn nas-- 7, 082. 74

SE ddbvumianttardccsbodeerdaneremmarminnmenmeine 35, 105. 42

Each claim will be discussed separately.

WAGE RATES

5. Before bidding, plaintiff had a copy of the specifications.

Section 1-31 of such specifications reads, insofar as here pertinent,

as follows:

“1-31. Wage and Labor Provisions.—(a) The Secretary of

Labor has determined the minimum wage rates applicable in the

locality for the labor classifications anticipated to be used on the

work. In accordance with Article 17 of the contract, employees

at the site shall be paid not less than these wages as listed below:

Designation wen

Carpenters, journeymen-___-_-_ $1. 00

a & a * *

Laborers, unskilled 50

Laborers, concrete puddlers. .50

BLURRED COPY

14 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

6. Article 17 of the contract reads as follows:

“Arricte 17. Rate of wages (in accordance with the act of

August 30, 1935, 49 Stat. 1011 (U. S. Code, title 40, sections 276a

and 276a-1), this article shall apply if the contract. is in excess of

$2,000 in amount and is for the construction, alteration, and/or

repair, including painting and decorating, of a public building

or public work within the geographical limits of the States of the

Union or the District of Columbia).

“(a) The contractor or his subcontractor shall pay all mechanics

and laborers employed directly upon the site of the work, un-

conditionally and not less often than once a week, and without

subsequent deduction or rebate on any account, the full amounts

accrued at time of payment, computed at wage rates not less than

those stated in the specifications, regardless of any contract-

23 —ual relationship which may be alleged to exist between the

contractor or subcontractor and such laborers and mechan-

ics; an the scale of wages to be paid shall be posted by ‘the con-

tractor in a prominent and easily accessible place at the site of the

work. The contracting officer shall have the right to withhold

from the contracter so much of accrued payments as may be con-

sidered necessary by the contracting officer’ to pay to laborers and

mechanics employed by the contractor or any subcontractor on the

work the difference between the rates of wages required by the

contract to be paid laborers and mechanics on the work and the

rates of wages received by such laborers and mechanics and not

refunded to the contractor, subcontractors, or their agents.

“(b) In the event it is found by the contracting officer that any

laborer or mechanic employed by the contractor or any subcon-

tractor directly on the site of the work covered by the contract

has been or is being paid a rate of wages less than the rate of

wages required by the contract to be paid as aforesaid, the Govern-

ment may, by written notice to the contractor, terminate his right

to proceed with the work or such part of the work as to which

there has been a failure to pay said required wages and prosecute

the work to completion by contract or otherwise, and the con-

tractor and his sureties shall be liable to the Government for any

excess costs occasioned the Government thereby.”

7. On January 31, 1941, the Secretary of Labor furnished to the

Corps of Engineers at its request, for inclusion in the contract

specifications, the schedule of minimum wages in the Elmira area.

Such schedule was included in the specifications and is set out in

finding 5.

8. On June 16, 1941, plaintiff advised the District Engineer

(who was the contracting officer) that the minimum wage rates

provided in the contract specifications were less than the rates

currently prevailing in the Elmira locality for carpenters, labor-

BLEED THROUGH— POOR COPY

=_

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 15

ers (unskilled), laborers (concrete puddlers), and truck drivers.

9. The District Engineer replied on June 27, 1941, stating that

the minimum wage rates were determined in strict accordance with

the applicable law and regulations, and that he could not afford

relief for any differences between wage rates then prevailing in

the area and the minimum rates required by the contract

specifications.

24 10. Plaintiff protested this decision to the Chief of Engi-

neers under date of July 10, 1941, and on August 5, 1941,

plaintiff's appeal was denied by the Chief of Engineers in part

as follows:

“There is no authority in law for this office to question the

correctness of any determination made by the Secretary of Labor

pursuant to the provisions of the above cited act [49 Stat. 1011].

Therefore, I find that the wage rates as established by the Secre-

tary of Labor, and incorporated in the contract specifications,

were the minimum wage rates applicable in the locality for the

labor classifications anticipated to be used on the work.”

11. Plaintiff under date of February 20, 1943, asked defendant

to reconsider its appeal regarding minimum wage rates, and this

was responded to by letter dated April 13, 1943, from the Chief

of Engineers, in part as follows:

“A determination as to the accuracy of the specified wages is

not necessary to a decision in thiscase. The contract by Article 17

and by paragraph 1-31 of the specifications provides that wages

not less than those specified shall be paid. The contract makes no

representation as to the availability of labor nor as to the actual

wage scales that would be in effect. The alleged increased costs

did not result from your contract obligation but from economic

conditions which are ordinary contingencies contemplated under

the terms of the contract. No reason has been shown which would

warrant modification of the previous decision dated August 5,

1941.”

12. On March 4, 1941, the Secretary of Labor furnished to the

Public Buildings Administration of the Federal Works Agency a

schedule of minimum wages in the Elmira area for inclusion in

the bidding specifications and contract for a Federal Housing

Project in Elmira, New York. The prevailing wage rates shown

therein as far as here material were as follows:

Classification Hourly rate

Carpenters, journeymen $1. 125

Laborers, unskilled . 55

13. At the time plaintiff began work on the site, which as indi-

cated in finding 2 was June 3, 1941, it had to pay $0.625 per

25 _— hour for laborers and $1.125 per hour for carpenters. This

264722533

BLURRED COPY

16 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

was the union rate effective April 1, 1941, and the plaintiff

employed only union members. metime in 1942, there was an

increase in union rates for carpenters from $1.125 to $1.25 per

hour, and for laborers from $0.625 to $0.75 per hour. Although

plaintiff paid such increased wage rates, it is not claiming in this

suit any excess over the laborers’ rate of $0.625 and the carpenters’

rate of $1.125 except such overtime as related to the latter rates,

14. Although the plaintiff’s president denied that he had any

knowledge of the prevailing rates for wages in Elmira at the time

of the submission of plaintiff’s bid, and states that he relied upon

the schedule of minimum wage rates included in the bidding speci-

fications, he could have, with very little effort and the exercise

of reasonable prudence, ascertained not only the prevailing rates,

but the impending increase in union rates for carpenters and

laborers which was effective on April 1, 1941.

15. Since plaintiff has lost some of its original payroll records

(which would identify the class of work performed by an em-

ployee), it is not possible to verify plaintiff's claim for $13,911.83

from its books and records. It will be possible, however, in the

event that the Court should conclude that plaintiff is entitled to

recover, to reconstruct such payrolls for carpenters and laborers

and to establish with reasonable accuracy the amount of such

recovery. For the foregoing reason, no finding is made as to the

amount of plaintiff's damage on the claim for reimbursement of

wage rates for carpenters and laborers over and above the

minimum wage rates set out in finding 5.

SHEETING AND SHORING

16. The contract specifications provide in part as follows:

“Section I

“1-14. Work Areas.—* * *

“(b) The contractor shall be responsible for trespassing upon, or

damage to, public and private lands and roads, bridges, buildings,

chimneys, and utilities in or adjacent to the work and access areas

resulting from any act or omission on his part, including damage

caused by disturbance of foundations while conducting any

26 operation within the work area. The contractor shall take

special precautions to prevent injury to existing structures

while working in the vicinity of the Hygeia plant, Brand build-

ing, greenhouse, gas regulation house, private dwellings, and

all other buildings and structures located at or close to the edge

of the work area. He shall take similar precautions in the vicinity

of the pole line crossing the levee at West Hudson Street, the water

BLEED THROUGH POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 17

main at approximate Station 176+37, all power facilities at the

Hygeia plant, and any other utilities which will not be relocated.

* ” * * a

“(d) The garage and other property of the Hygeia Refrigerat-

ing Company are within the work area, and the activities of this

company will be carried on during construction of the project.

The contractor shal] cooperate with this company during all con-

struction operations in order to preserve its access and permit

its operations to be conducted with a minimum of interference

by the contractor. The contractor shall perform the necessary

construction on the company’s property in the least practicable

time. He shall provide bracing or other protection satisfactory

to the contracting officer for the garage wall against which the

new wall is placed. The garage and other property within the

work area shall be restored to a condition satisfactory to the con-

tracting officer upon completion of the permanent work in that

area.

* * a * *

“Section III

“3.03. Excavation—Common. * * *

“(b) Procedure—(1) General—Excavation—Common shall

be performed in accordance with subparagraph 3-01 (c). Exca-

vation around bridge piers and abutments, existing walls, build-

ings, chimneys, transformers, power lines, utilities, sewers, cul-

verts, and other existing structures shall be executed with all due

precautions, satisfactory to the contracting officer, for safe-

guarding the structures. (See paragraphs 1-14.) Where special

work is required to prevent undermining existing structures, it

shall be done in accordance with detailed plans prepared by the

contractor and approved by the contracting officer, but such

approval shall not relieve the contractor of responsibility for

damages which may result from the failure of the temporary pro-

tection. Where excavation operations endanger the stability

of existing or new structures, sheeting and shoring shall

27 __— be installed at the locations indicated on the drawings or

directed by the contracting officer. The contractor shall

be responsible for safety of such structures. (See subparagraph

(3) below and paragraph 3-06.) * * *

* * * * *

“(3) Sewers, Culverts, and Drains.—The contractor shall fur-

nish and install sheeting and shoring in all trenches where the

depth exceeds 6 feet. * * *

bd * * * 7.

BLURRED COPY

—Y

18 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

“3-06. Sheeting and Shoring—(a) General—The contractor

shall furnish and place such sheeting, shoring, bracing, or other

aproved supports as are indicated on the contract drawings or

directed by the contracting officer for the protection of the work

or adjoining property. The right is reserved to order the instal.

lation of sheeting and shoring where its use is considered advisable

for the safety of the work, and to require such sheeting and shor-

ing to remain in place when its removal is considered inadvisable.

(b) Procedure.—AlJ sheeting and shoring shall be designed by

the contracter and approved by the contracting officer prior to

installation, but such approval by the contracting officer shall not

relieve the contractor of sole responsibility for damages resulting

from the inadequacy or lack of any sheeting and shoring. The

sheeting and shoring shall be built to provide adequate clearances

for minimum interference with construction operations, proper

bracing for stability, and safe conditions around the work. If, in

the opinion of the contracting officer, any methods or measures

of the contractor constitute a hazard in any way or are otherwise

improper or inadequate, the contracting officer will notify the con-

tractor of that fact in writing. If the contractor fails to provide

immediately such remedial measures as are deemed n

the contracting officer, such measures will be provided by the con-

tracting officer at the expense of the contractor. When sheeting

and shoring have served their purpose and their removal is ap-

proved by the contracting officer, they shall be removed and dis-

posed of. Whether sheeting and shoring are removed or left in

place, all cavities shall be adequately filled. When approved by

the contracting officer. sheeting and shoring may be used in lieu

of excavation to full pay lines.

“(c) Measurement.—Sheeting and shoring will be measured by

the square foot of protected area.

28 “(d) Paymeni.—F.xcept as specified below, payment for

all costs of furnishing and placing sheeting and shoring

indicated on the contract drawings or directed by the contracting

officer, and of its removal and disposal when not left in place, will

be made at the contract unit price for ‘Sheeting (Including

Shoring),’ Item No. 7. Where sheeting and shoring are used at

the contractor's option and with the aproval of the contracting

officer, separate payment will not be made for the sheeting and

- shoring, but payment will be made for excavation to the pay lines

shown on the contract drawings as though the cut had been made

to such pay lines.”

17. The schedule of payments incorporated into the contract

in suit provided in item 7 that the plaintiff was to be paid for

sheeting (including shoring) on a quantity of 9,200 square feet

at the rate of 65 cents per square foot, or a total of $5,980.

BLEED THROU GH— POOR COPY

———

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 19

18. Section I, paragraph 1-05, provides in pertinent part as

follows:

“1-05. Quantities—The following estimate of quantities is

given only to serve as a basis for comparison of bids and for de-

termining the amount of consideration of the contract. Within

the limits of available funds, the contractor will be required to

perform the entire quantity of work necessary to complete the

work specified in paragraph 1-02 hereof, be it more or less than

the amounts herein estimated.

* * * * *

“Item No. 7 Sheeting (Including Shoring) 9,200 Sq. Ft.”

* * * . .

19. As the work progressed, the plaintiff placed sheeting and

shoring necessary for the protection of the work as well as that

necessary for the protection of existing buildings and structures.

Payment was made on account of such sheeting and shoring, as

well as the other work performed by the plaintiff, on monthly

estimates prepared by defendant’s resident engineer and given to

plaintiff’s superintendent together with a payment voucher for

execution on behalf of plaintiff. The plaintiff executed such pay-

ment vouchers and forwarded them along with each monthly esti-

mate for payment by the defendant’s paying office. On the second

such monthly estimate forwarded with a payment voucher by

plaintiff, an item of 438 square feet of sheeting, including

29 + shoring, appears under item 7. On subsequent monthly

estimates supporting payment vouchers, under item 7 ap-

pears a figure covering additional sheeting, including shoring.

The plaintiff accepted monthly payments on such payment vouch-

ers without question as to the manner of computation of the sheet-

ing (including shoring) item until the final estimate was

received by the plaintiff showing a total of 10,152 square feet.

20. After all of the work under the contract had been performed,

the defendant, through the resident inspector, forwarded proposed

final estimate on January 21, 1943. On January 28, 1943, plain-

tiff’s superintendent, Mr. Bernard Gabriel, went to the office of

the District Engineer at Syracuse, New York, and conferred with

a representative of thut official concerning claims for additional

payments on various contract items including sheeting and shor-

ing. Following this conference, the plaintiff received a letter

dated February 1, 1945, from the District Engineer in which it is

stated that:

“In computing pay quantities the following methods were used

by this office.

“Sheeting—Computations based on field measurements of

length and height of sheeting placed.”

BLURRED COPY

20 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

21. The plaintiff was paid at the rate of 65 cents per square foot

for 10,152.1 square feet of sheeting and shoring. Of this amount

6,738.2 square feet was for the protection of the work, and 3,413.9

square feet was for the protection of property. The plaintiff

claims that it should have been paid for 32,899 square feet, 8,094

square feet for the protection of the work, and 24,805 square feet

for the protection of property.

As to the sheeting and shoring required for the protection of

the work, it is plaintiff’s position that the protected area was the

area of side walls of trenches excavated where sheeting was placed.

The difference between the quantity of sheeting and shoring for

the protection of the work claimed by the plaintiff and that al.

lowed by the defendant is shown by defendant’s Exhibit 22, which

is in evidence and made a part hereof by reference, to relate to

items Aland A2. Onall other items concerning sheeting placed

for protection of the work, the allowance was as great or greater

than that claimed, except for 50 square feet of sheeting claimed at

the Walnut Street Bridge, which the defendant allowed

30 under sheeting placed for the protection of property. The

evidence is not satisfactory as to the measurements by

which either the amount claimed or allowed was computed.

As to the sheeting and shoring required for the protection of

the property, plaintiff's claim is based not upon the amount of

sheeting or shoring placed, but rather upon the ground area cov-

ered by the buildings and structures so protected. The ground

area of the buildings and structures which was protected by sheet-

ing and shoring is shown below:

Ground area of buildings and structures as to which sheeting and shoring

was provided

Square feet

MIA TNA acai cncctecn aa clases pee ranma ana aaiten 175x 68 11,906

WEIL. WEI este i ete ae BEER SESE eee NE 315x 6 1,890

BR RARE ONE Sele tvs Sak ee Se ene aE Te eg 54x60 3,240

Ua I a 35 x 25 875

ine! Rk 5 Renee > Cnn oes 30 x 30 900

Geesnews ([Wam 6a). ....... 240x245 = 6, 000

TONE eee ee ag cenit bes Ae ee 24, 805

22. The plaintiff on February 9, 1943, wrote to the District

Engineer requesting that the defendant recompute the allowance

for sheeting and shoring.

“* * * by ascertaining the square footage of the area protected

by the work performed under this item, pursuant to paragraph

3-06 subdivision (c) and that we be paid therefor at the unit price

of said item. * * *”

The defendant reviewed plaintiff protests and on February 18,

1943, wrote plaintiff that the item had been measured and com-

puted in strict accordance with the provisions of the contract

BLEED THROUGH— POOR COPY

_ — -

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 21

specifications, and the contractor was invited to present additional

facts or computations for consideration.

23. The plaintiff failed to accept this invitation but rather by

letter dated February 24, 1943, returned a final release of claims

wherein was listed an exception to the method of computing the

final quantity of sheeting and shorting.

24. Receipt of the release was acknowledged by letter dated

March 5, 1943, and the plaintiff was advised of his further rights

of appeal under Article 15 of the contract.

25. On March 19, 1943, plaintiff appealed the decisions of the

contracting officer to the Secretary of War, and on July 31, 1944,

the appeal was denied. This denial reads in part as follows:

31 “You allege that the method used by the contracting

officer in computing the pay quantities for sheeting (in-

cluding shoring) was incorrect. Paragraph 3-06 (c) of the con-

tract specifications states that sheeting and shoring, ‘* * * will

be measured by the square foot of protected area.’ The record

shows that the pay quantities of sheeting placed adjacent to exist-

ing structures were determined by measurements to specific

payment lines where such lines are shown on the drawings. Where

specific payment lines were not indicated, the quantities were

computed by using the length of the area actually sheeted and the

difference in elevation between the top of the sheeting and the

bottom elevation of the adjacent structures. The pay quantities

for sheeting not placed adjacent to any existing structure were

computed by multiplying the difference in elevation between the

ground surface and the bottom elevation of the trench by the

length of the area sheeted. You assert that because of the

liability imposed by paragraph 1-14 (b) of the specifications

for damages to structures in or adjacent to the work, including

damages caused by disturbance of foundations, that the term

‘protected area’ as used in paragraph 3-06 (c) must be construed to

mean the ground area occupied by the adjacent structures and that

the computation of pay quantities for sheeting placed to protect

such structures must be based on the area thereof. As noted above

the payment lines shown on the drawings for sheeting and shoring

placed adjacent to the structures clearly indicate that the parties

did not intend that payment should be made on the basis of the

ground area of the buildings. Furthermore, the estimates [sic]

pay quantity of sheeting was only 9,200 square feet, approximately

10% less than the quantity of 10,152 square feet for which payment

was made and only about 30% of the quantity for which payment

is claimed. The contract does provide, as contended by you, that

the quantities specified are only estimates. However, the build-

ings which were to be protected were clearly indicated on the

contract drawings. The combined ground area of the buildings

asics icaiahieasietbaiestisasi

BLURRED COPY

a ieee

22 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

alone, aside from the other locations where the plans indicated

sheeting was to be placed, is about 214 times the total area for

which it was estimated sheeting would be required. The payment

lines indicated on the drawing and the discrepancy between the

ground area of the buildings and the estimated quantity of the

sheeting should have put you on notice that the Government did

not intend that the pay quantities of sheeting and shoring placed

adjacent to existing structures would be computed on the

32 __ basis of the ground area of such structures. No objection

has been made of the method employed by the contracting

officer in computing pay quantities for sheeting not placed ad-

jacent to structures. As the ground area occupied by a structure

has no direct relation to the cost of placing sheeting and shoring

adjacent to it, there would appear to be no reason to compute the

pay quantities of sheeting placed adjacent to such structures on

the basis of the ground area occupied and to compute the pay

quantities of sheeting not so placed on an entirely different basis,

Under paragraph 1-14 (b) of the specifications you are liable

for damages to land as well as to structures. If your contention

that the pay quantities of sheeting placed adjacent to existing

structures must be computed on the basis of the ground occupied

by said structures were to prevail, it would logically follow that

the pay quantities for sheeting not placed adjacent to any existing

structure should be computed on the basis of the land area pro-

tected, even though such area might conceivably comprise many

acres. Such as [sic] interpretation is obviously absurd. It is

my finding that the methods employed by the contracting officer

for computing the pay quantities of sheeting and shoring were

correct.”

CONCRETE FINISHING

26. Article 15 of the contract provides as follows:

“Article 15. Disputes—Except as otherwise specifically pro-

vided in this contract, all disputes concerning questions of fact

arising under this contract shall be decided by the contracting

officer subject to written appeal by the contractor within 30 days

to the head of the department concerned or his duly authorized

representative, whose decision shall be final and conclusive upon

the parties thereto. In the meantime the contractor shall

diligently proceed with the work as directed.”

Section i-20 of the general provisions of the contract specifica-

tions provides:

“1-20. Claims, Protests, and Appeals.—(a) If the contractor

considers any work demanded of him to be outside the require-

ments of the contract or if he considers any action or ruling of the

a

BLEED THROUGH POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 23

contracting officer or of the inspectors to be unfair, the contractor

shall without undue delay, upon such demand, action, or ruling,

submit his protest thereto in writing to the contracting officer,

stating clearly and in detail the basis of his objections.

33 The contracting officer shall thereupon promptly investi-

gate the complaint and furnish the contractor his decision,

in writing, thereon. If the contractor is not satisfied with the

decision of the contracting officer, he may, within thirty days,

appeal in writing to the Chief of Engineers, whose decision shall

be final and binding upon the parties to the contract. Except for

such protests or objections as are made of record in the manner

herein specified and within the time limit stated, the records,

ruling, instructions, or decisions of the contracting officer shall

be final and conclusive.

“(b) The Chief of Engineers has been designated by the Secre-

tary of War as his duly authorized representative to make final

decision and to take other action where the terms of the contract

require that such decision or action shall be ‘by the Head of the

Department concerned or his duly authorized representative.” Al]

appeals from decisions of the contracting officer authorized under

the contract shall, therefore, be addressed to the Chief of Engi-

neers, U. S. Army, Washington, D. C. The appeal shall contain

all the facts or circumstances upon which the contractor bases his

claim for relief and should be presented to the contracting officer

for transmittal within the time provided therefor in the contract.”

Pertinent provisions of the contract specifications, Section VIT,

dealing with the subject “Concrete” are quoted below:

Section VII. Concrete

* * * ok *”

“7,03. Proportioning and Mixing.—* * *

“(b) Proportioning. * * *

“(2) Control.—The exact proportions of all material entering

into the concrete shall be as directed by the contracting officer.

The contractor shall provide all equipment necessary to positively

determine and control the actual amounts of all material entering

into the concrete. The proportions will be changed whenever, in

the opinion of the contracting officer, such change becomes neces-

sary to obtain the specified strength and the desired density, uni-

formity and workability, and the contractor will not be

compensated because of such changes, except for an increase in

the specified minimum unit paste content, as provided herein as

follows: In the event it is determined by the contracting officer

that concrete of the desired quality cannot be obtained with the

264722—53__-4

BLURRED COPY

a

24 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

specified gradation of aggregates conforming fully to the specifi-

cations and the specified minimum unit cement content,

34 he may direct an increase in the unit paste content by the

addition of Portland cement, in which case compensation

will be made therefor at the cost to the contractor of the cement

delivered f. o. b. carrier at the site of the work, plus $0.40 per

barrel. *

* * x * *

“7-05. Details of Construction.—(a) Forms.—* * *

“(4) Removal.—Forms shall not be removed without the ap-

proval of the contracting officer, and al] removal shall be accom-

plished in such manner as will prevent injury to the concrete.

Forms shall not be removed from walls and vertical faces before

the expiration of 2 days, except when specifically authorized by the

contracting officer. When, in the opinion of the contracting offi-

cer, conditions on the work are such as to justify it, forms may be

required to remain in place for longer periods.

* * * * *

“(d) Finishing—Immediately following removal of forms, all

form tie holes shall be filled, protruding fins or other surface

irregularities removed by carborundum stone and all other defects

repaired. Where necessary to obtain a suitable surface finish, the

contractor shall remove the forms and finish the sufaces when and

as directed by the contracting officer at no additional cost to the

United States. The curing specified in subparagraph 7-05 (e)

following shall be temporarily suspended during such repairing

or finishing as directed. The finished surfaces shall be free from

sand streaks or other defects and the plastering over of such sur-

faces will not be permitted. Defective concrete shall be repaired

by cutting out the unsatisfactory material and placing new con-

crete which shall be formed with keys, dovetails, and anchors to

attach it securely to the other work. This concrete shall be drier

than the usual mixture and shall be thoroughly tamped into place.

All surfaces of concrete, not covered by forms, that are not to be

covered by additional concrete or backfill shall have a wood float

finish without additional mortar, and shall be true to elevations

as shown on contract drawings. Striking-off and finishing shall

follow closely the placing operation in order to insure completion

before the initial set has taken place. The contractor will not be

permitted to start a pour unless a sufficient number of qualified

finishers are available to fulfill the above requirements. Care

shall be taken to see that all excess water is removed before

35 making the finish. Other surfaces shall be brought to the

specified finished elevation and left true and regular as

approved by the contracting officer. Where considered necessary

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 25

by the contracting officer, or where indicated on the drawings,

joints shall be made carefully with a jointing tool. Every pre-

caution shall be taken by the contractor to protect finished surfaces

from stains or abrasions. No fire shall be permitted in direct

contact with any concrete at any time. Concrete surfaces or

edges likely to be injured during the construction period shall be

properly protected by leaving the forms in place or by erecting

covers satisfactory to the contracting officer.”

27. Section 1, paragraph 1-11, Work Covered by Contract

Price, provides as follows:

“1-11, Work Covered by Contract Price.—The contractor shall,

under the contract prices, furnish and pay for all materials, equip-

ment, and labor for all permanent, temporary, and incidental

work, furnish all accessories, and do everything which is necessary

to carry out the contract in good faith, which contemplates every-

thing comy ieted, in proper working order, of good materials with

skillful workmanship, accurately fitted, properly assembled, and

connected.”

28. The placement of concrete began on August 20, 1941, and

placement was made from time to time during that construction

season until October 24, 1941. During this time monoliths Nos.

1 through 17 were poured. The first concrete which was placed

above the foundation and as to which the plaintiff’s claim for

finishing relates was commenced on September 5, 1941.

29. From the time that the forms were stripped from the ex-

posed concrete lifts above the foundation, the defendant’s field

representatives complained to Mr. Gabriel, plaintiff’s superin-

tendent, of the poor faces on the exposed concrete. After mono-

liths Nos. 1 through 17 had been poured and the forms stripped

from the concrete, there were rust stains showing from the water

pipes used in curing, and the concrete faces showed numerous

blemishes, pockmarks and honeycombs. Protruding fins had not

been removed, and the form tie rods holes had not been filled.

30. Prior to October 29, 1941, defendant complained to plain-

tiff regarding the tie holes not being plugged as re-

36 quired by paragraph 7-05 (d) of the contract specifications.

31. Under date of July 28, 1941, plaintiff transmitted to

defendant some revised prints covering certain form details in the

construction of the wall and which made reference to the proposed

use of certain porcelain tubes or cylinders for the purpose of

putting bolts through said porcelain cylinders which could act as

spreaders and thereby increase or lessen the width of the forms.

32. Defendant, by letter dated August 4, 1941, approved plain-

tiff's revised prints subject to certain provisions which in part

provided :

BLURRED COPY

a

26 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

“(e) The approval as indicated above is predicated on produc-

ing a finished concrete surface as contemplated in contract speci-

fications, and the right is reserved to require necessary revisions

in your form construction to provide uniform finished surfaces on

all exposed faces.”

33. On October 15, 1941, defendant objected to the further use by

plaintiff of visible porcelain tubes which gave the appearance of

an unfinished job.

34. Under date of November 15, 1941, defendant wrote plaintiff

regarding the unused porcelain tubes and therein stated that plain-

tiff would be allowed to use these tubes on unexposed concrete

wall surfaces and would be paid for the remaining unused

porcelain tubes.

35. The defendant has allowed payment for porcelain tubes

which were delivered by plaintiff to defendant but not used on the

job.

36. On October 20, 1941, the contracting officer addressed and

forwarded the following letter to the plaintiff:

“Reference is made to Par. 7-05 (d), Finishing of Concrete

Surfaces, of your Contract No. W-321-eng-261 for the construe-

tion of the Elmira Flood Protection Project, Section 1.

“I have examined the concrete work constructed to date under

your contract and find that it has not been finished in accordance

with the provisions of the contract specifications. You are di-

rected to correct these deficiencies at once. My field representa-

tives will indicate the defective work and furnish details of the

required corrective measures.”

37 37. By letter dated October 29, 1941, defendant’s Resi-

dent Engineer forwarded a detailed statement of corrective

measures to be taken by the contractor in two parts, the first

relating to the treatment of monoliths Nos. 1 through 17 which

had then been placed, and the second relating to the treatment

of concrete which had not then been placed. The detailed state-

ment of corrective measures provides as follows:

“METHOD OF TREATING EXISTING WORK

“The surface to be treated will be scrubbed with a wire brush

where necessary to clean out defective areas.

“Mix one part portland cement with two parts fine sand (sim-

ilar to that used on the project from which particles retained

on the No. 16 sieve has been removed) with water sufficient to

produce a grout having the consistency of very thick paint. If

necessary, white portland cement shall be added, replacing an

equal quantity of standard cement, in a quantity sufficient to give

a color equal to the concrete in the project. A test of the pro-

cedure and color will be made on a panel which is to be covered

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 27

with backfill. This mixture shall be carefully worked out so that

no difference in color will result from the grout. This mixture

shall be allowed to set for 45 minutes before being used. The

surface of the concrete to be treated shall be thoroughly wet, after

which the grout shall be applied with a brush or cloth completely

filling air bubbles and holes. Immediately after applying the

out scour the wall vigorously with a cork or wood float. The

grout shall then be allowed to set partially for an hour or two,

depending on the weather, until it has hardened sufficiently so

that it can be scraped from the wall with the edge of a steel trowel

without removing the grout from the small air holes. Next allow

the surface to dry thoroughly one to two hours or more depending

on the weather until the initial set occurs and rub it vigorously

with a burlap bag to completely remove any dried grout. There

shall be no visible film of grout remaining after this rubbing.

The entire cleaning operation for any monolith shall be completed

the same day it is started. The entire exposed surface of the

monolith shall be treated in this manner. If any dark streaks

or spots remain after this operation they shall be rubbed lightly

with a fine carborundum stone. This rubbing must be carefully

done to avoid changing the texture of the concrete.

38 “After the grout has become thoroughly set (24 hours

in warm weather and 48 hours in cold weather) curing will

commence and continue for at least seven days. Curing shall be

accomplished by covering finished surfaces promptly with damp

burlap or cotton quilts. (Heating will not be necessary on old

walls.)

“METHOD OF TREATING NEW CONCRETE WORK

“The forms on work that is to be exposed shall be removed

as soon as it is possible to do so without injury to the concrete.

In warm weather (minimum 65° F., average 75° F.) this will

be approximately 24 hours after the completion of placing. In

colder weather the forms should be allowed to remain in place

approximately 48 hours.

“Immediately after the forms have been removed all fins or

other projections shall be broken off with a carborundum stone or

other suitable tool which will remove the projections without

marring the surrounding surfaces. Filling of form tie holes shall

be concurrent with the removal of fins, etc. This operation shall

be separate from general finishing and shall be accomplished

with retempered mortar. This mortar shall have the same sand-

cement ratio as the concrete in the original work. Sufficient water

shall be added to make a dry mixture. This mortar shall be

thoroughly mixed, allow to set for one hour and then remixed

before being used. The material shall be thoroughly tamped

BLURRED COPY

a

28 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

into the tie holes and care shall be taken not to smear or deface

the surrounding surfaces. Other patching of honeycomb or sim-

ilar defects shall also be accomplished with sand-cement mortar

as described above. All patches shall bond witk the steel rein-

forcement and shall, if feasible, be dovetailed to the existing work.

Dish shaped patches with sloping sides shall not be permitted.

“Upon completion of repair work as outlined above, the entire

exposed surface shall be treated as follows:

“A thin sand-cement mortar shall be applied to the entire sur-

face with a steel trowel. This mortar shall be composed of one

part cement and two parts sand to which water shall be added until

the mortar has the consistency of very thick paint. If necessary,

white cement shall be used replacing an equal quantity of regular

cement so that the dry mortar will have the same color as the

concrete in the structure. Panels shall be experimented with on

concrete surfaces which will be covered in order to assure this

similarity in color. This application shall be sufficiently

39 vigorous to insure the complete filling of all pock marks

or other blemishes. The sand for this mortar shall be the

sand as regulaly [sic] used in the concrete work except that the

sizes retained on a No. 16 sieve shall be removed. The mortar

applied to the concrete surface shall be allowed to set for one hour

and the surplus shall then be removed by scraping the surface

lightly with the edge of a steel trowel or steel float. After the

lapse of sufficient time to allow initial set or hardening of the

mortar, the surface shall be vigorously rubbed with Clean Dry

Burlap which shall entirely remove the mortar on the surface

of the concrete. Initial curing shall be commenced immediately

after this operation and shall consist of covering the finished sur-

face with Clean Wet Burlap. Normal water curing will com-

mence 12 hours jater. Finishing of concrete surfaces shall be

completed in the minimum possible time and in no case shall the

finishing be extended over more than a 12 hour period. (This is

specified because the color of the finished surface may vary with

atmospheric conditions and make blending with adjacent finished

surfaces difficult.) ”

38. Upon receipt of the letter and its enclosure referred to in

the foregoing finding, the plaintiff on October 31, 1941, addressed

the following letter to the contracting officer :

“Receipt is acknowledged of your letter of October 29th relative

to certain finishing which you desire us to do on the concrete al-

ready placed on this project. It seems wise at this time to review

briefly, for the record, the procedure which has previously taken

place and which must therefore be responsible for the appearance

of these concrete walls. Before reviewing this procedure, let me

state that we are already proceeding to do as directed in your

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 29

letter of October 29th, and that we will at all times proceed with

any of your instructions, our desire, however being, of course,

that we be protected insofar as the matter of reimbursement to us,

for any expenses plus normal profit incurred in carrying out any

such instructions, is concerned.

“The aggregates used in the Elmira work, gravel, sand, and

cement, were all previously approved by your representatives and

accepted for this work. The water is the same as that used by the

people of Elmira for drinking water and has also been approved by

your representatives. The characteristics of the mixture, insofar

as the porportion [sic] of the component parts, was set by your

representatives after exhaustive tests on their part. The

40 form lining used was approved by your representatives and

the forms themselves compare in construction very favor-

ably as to strength, appearance, etc., with any used in the district,

and this we have on the authority of the Acting Chief of Opera-

tions. We come, therefore, to the mixing and placing of the con-

crete, and at all times these procedures have been directly and

completely under the control of your representatives. No latitude

has been allowed us for the carrying out of any opposing ideas we

may have had in this work, ideas which may or may not have se-

cured a better result, but in any event we were not allowed to try

them out. We must, therefore, in view of all the above, respect-

fully suggest that the responsibility for any result which may not

appeal to you, does not lie on our shoulders.

“It is our understanding that costs are being kept by your repre-

sentatives as well as by ourselves on the additional expense that is

now accruing because of the finishing operations which you have

directed, and that on the conclusion of these operations a satis-

factory settlement will be reached to reimburse us for this expense.

If this understanding is not in accordance with yours, we should

appreciate being advised at once.

“Your consideration and advice on all the above will be ap-

preciated.”

39. After monoliths Nos. 1 through 17 were treated in accord-

ance with the procedure outlined for existing work, the plaintiff

submitted on November 27, 1941, a request for the payment of the

sum of $864.07 covering the cost of such work. This sum resulted

after an allowance of $111.75 had been deducted as the cost of

filling form tie rod holes.

On December 10, 1941, the contracting officer by letter acknowl-

edged receipt of the above letter and stated as follows:

“TI find that the finishing treatment required on your job is

well within the intent of paragraph 7-05 (d), and I cannot con-

sider additional payment for this work.”

BLURRED COPY

a

30 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

Following receipt of the above letter, Mr. Fred Davis, vice

president of plaintiff, conferred with the District Engineer on

December 15, 1941. After this conference, the plaintiff addressed

the following letter to the contracting officer :

“Asa result of a conference held this morning with the District

Engineer, Mr. Samples, and myself, my understanding of the con-

clusions reached at this conference is outlined below.

“1. I understand that our company is not giving up any of

41 _—our rights to future consideration of our claim for the cost

of the treatment of the walls constructed during 1941 by

reason of not appealing at this time the decision of the District

Engineer outlined in his letter of December 10th.

“2. That consideration will be given to payment by the United

States for any increase in our costs because of any change in the

kind of aggregates composing the concrete mixtures or because

of any change that may be prescribed in handling the concrete.

“3. That the treatment of the walls in the future will be modi-

fied, in that treatment will be required only on the land side of the

walls except that at bridge approaches where treatment shall be

on both sides of the walls for a distance of three or four monoliths

from the bridge approach; such treatment shall immediately fol-

low the removal of the forms and shall consist of rubbing the con-

crete with carborundun [sic] stone and brushing with a light

coat of mortar if required. It will also, of course, be necessary

for us to block the holes at the form tie rods.

“We would appreciate knowing as to whether your understand-

ing is in general accordance with the above.”

40. The contracting officer replied by letter of December 29,

1941, as follows:

“Reference is made to your letter dated December 15, 1941,

regarding your understanding of conclusions reached at a con-

ference in my office on December 15, 1941, on concrete construction

at the Elmira Flood Protection Project, Section No. 1, Contract

No. W-321-eng-261.

“Using the same numerical index as used in your letter you are

advised that conclusions reached in the conference were as follows:

“1. Your right of appeal from my decision on payment for

wall treatment is established in Article 15 of the contract.

“2. Any redesign of concrete mixtures or required changes in

methods of handling concrete not within the scope of specifications

which causes increased cost will be cause for consideration of

increased payments to you.

“3. Treatment of walls will be required on the landside of all

walls and on the streamside of walls approximately 100 feet up-

stream and downstream of all bridges, approaches, or other sim-

ilar places where relatively close scrutiny is easily attained. In

BLEED THROUGH— POOR COPY

, a

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 3]

addition to the above treatment regular patching of tie rod holes,

replacing unsatisfactory spots, repair of honeycombs, etc.,

42 will be required on all surfaces in accordance with specifica-

tion requirements.”

41. On February 9, 1943, the plaintiff filed a protest with the

contracting officer listing five items of claim but not including

the claim for concrete finishing. This was replied to by letter

of February 18, 1943, by the contracting officer, in which the fol-

lowing statement is made:

“In view of the fact that your letter and this reply are repeti-

tions of previous protests and decisions, and that no progress is

apparent in the settlement of this dispute, it is suggested that, in

event you elect to prosecute this matter further, you arrange to

present detailed facts, computations, etc., either by letter or at a

conference in this office.”

On February 24, 1943, the plaintiff forwarded an executed copy

of a release dated February 19, 1943, a copy of which is in evidence

as plaintiff’s exhibit 7 and made a part hereof by reference. In

this release, the plaintiff excepted a claim by reason of concrete

finishing operations

“* * * in a manner and to an extent not required by the con-

tract plans and specifications. * * *”

The plaintiff suggested in the letter transmitting the release

that $100 be withheld from payment due it on its final estimate.

In this letter the plaintiff also discussed the concrete finishing

claim and protested the sums allowed for the concrete items

in the final estimate and requested an opportunity to submit

detailed data as to the cost of performing this “additional” work.

42. The contracting officer on March 5, 1943, sent the following

letter to plaintiff :

“Receipt is acknowledged of your letter dated February 24,

1943, transmitting executed copies of standard release form for

Contract No. W-321-eng-261, and an application for reconsidera-

tion of a previous appeal, addressed to the Chief of Engineers,

relative to minimum wage rate.

“Reference is made to the exceptions listed in your formal re-

lease to Contract No. W-321-eng-261, and you are advised, as

follows, as to the action taken by this office relative to the various

claims.

“(a) The decision relative to additional payment for

43 work in connection with treatment of concrete surfaces, was

given in letter from this office dated December 10, 1941.

Reference is made to letter from this office dated December 29,

1941, informing you of your right to appeal the decision of this

office as established in Article 15 of the contract. As no appeal

264722585

BLURRED COPY

mr

32 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

was made as per Article 15 of the contract, it is considered that

your right to appeal has been forfeited.

“(b) A decision relative to the other exceptions to the release;

namely, payment of Sheeting (Including Shoring) Contract Item

No. 7; payment of Copper, Contract Item No. 28, and payment of

Contract Item No. 6, Removal—Walls, Slabs, Paving, Building

Foundations (Concrete or Masonry) was given in letter from this

office dated February 18, 1943.

“Your right of appeal from my decision on payment of the

items covered in paragraph (b) above is established in Article 15

of the contract. The time allowed for appeal will expire thirty

days from date of this letter.

“You are further advised that a voucher is being prepared for

your signature for the partial estimate now due, less $100.00, as

requested in your letter of February 19, 1943.”

43. The plaintiff on March 19, 1943, appealed the decision of

the contracting officer of February 18, 1943, and claimed in addi-

tion to the sheeting and shoring item and other items not here

material, a concrete finishing item of $7,082.74 of which $862.42

was claimed for the finishing of monoliths Nos. 1 through 17 as to

which the detailed statement of corrective measures related to the

Method of Treating Existing Work, and $6,220.32 was claimed for

the finishing of all other work as to which finishing was performed

pursuant to the Method of Treating New Concrete Work con-

tained in such detailed statement.

The contracting officer on June 2, 1943, forwarded his findings

of fact on the plaintiff's claim to the Chief of Engineers. So far

as here material, this finding of fact provides as follows:

“4. With reference to finishing concrete surfaces (paragraph

3a above), the contractor was required, in accordance with the

contract specifications, to finish exposed concrete wall surfaces.

The contractor offered verbal] and written protests all of which

were duly considered prior to the District Engineer’s decision

dated December 10, 1941 (Exhibit F), which denied the contrac-

tor’s request for additional payment. After a conference in

44 the District Engineer’s office on December 15, 1941, the

contractor forwarded the letter of the same date which he

quotes on page 8 of his appeal. The District Engineer in turn

with letter dated December 29, 1941 (Exhibit G), replied to the

contractor’s letter of December 10, 1941, and denied his request

for additional compensation. The contractor was advised of his

further rights of appeal under Article 15 of the contract. Records

of this office do not disclose any further correspondence on this

item of complaint prior to receipt of the final release (Exhibit Q),

which was returned with letter dated February 24, 1943 (Ex-

hibit D).”

BLEED THROUGH— POOR COPY

— .

UNITED STATES V8. BINGHAMTON CONSTRUCTION CO., INC. 33

On April 29, 1944, the contracting officer forwarded a supple-

ment to his findings of fact dated June 2, 1943, to the Chief of

Engineers. It provided as follows:

“1, The following facts concern that portion of the contractor’s

appeal pertaining to the finishing of concrete surfaces and is sup-

plementary to the facts presented in paragraph four of Findings

of Fact, dated 2 June 1943.

“2, Operations under the subject contract were commenced on

3 June 1941. Placement of concrete commenced on 19 August

1941 and a total of 955 cubic yards of Class A concrete, Item 20,

wes placed through 24 October 1941, the date concrete operations

were suspended for the winter season. During the first season

the contractor after the removal of forms did not attempt to patch

holes or remove surface irregularities from the exposed concrete

surfaces as required by paragaph 7-05d of the contact specifica-

tions. The District Engineer on 15 October 1941 inspected the

site of the work and verbally directed that immediate action be

taken to remedy the unsightly condition presented by the unfin-

ished concrete surfaces. The contractor was formally directed by

letter dated 20 October 1941 (attached as Inclosure No. 1) to cor-

rect the surface deficiencies in a manner to be indicated by the

resident engineer. The resident engineer by letter dated 29 Octo-

ber 1941 (see page 10 of contractor’s appeal) furnished the con-

tractor a complete set of instructions for the guidance of the

contractor. Two procedures were outlined ; the first pertained to

finishing concrete placed and cured under the contract prior to the

issuance of said instructions, the second procedure outlined a more

timely method of finishing to be applied on subsequent work. The

contractor complied with the instructions as outlined and by letter

dated 27 November 1941 (attached as Inclosure No. 2) pre-

45 sented a bill in the amount of $864.07 for finishing 5,330

sq. ft. of concrete surface. The District Engineer by letter

dated 10 December 1941 (Exhibit F of Findings of Fact) denied

the contractor’s request for additional payment on the grounds

that the work performed was within the intent of the specification.

The subsequent history is as outlined in paragraph 4 of the original

Findings of Fact dated 2 June 1943.”

44. Thereafter on June 19, 1944, the plaintiff filed with the

yom Engineers a memorandum in further support of its

appeal.

45. The Acting Chief of Engineers by letter of July 31, 1944,

forwarded to plaintiff his decision denying the plaintiff’s appeal

which provided in pertinent part as follows:

“You claim additional compensation in the amount of $7,082.74

for finishing concrete in a manner allegedly not required by the

contract specifications. It is not now contended by you that an

BLURRED COPY

Ty

34 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

appeal was taken within thirty days from the date of the contract-

ing officer’s decision denying your claim in the amount of $862.42

for finishing concrete erected in 1941 as required by paragraph

1-20 of the contract specifications. Thus further consideration of

this item is precluded. In regard to the item of $6,220.32 for

finishing concrete erected in 1942, the only question involved is

whether instructions issued by the Contracting Officer for said

work exceed the requirements of the contract. An examination

of the applicable provisions of the specifications and the instruc-

tions issued by the contracting officer clearly show that the claim

for this item was properly denied. Paragraph 7-05 (d) of the

specifications requires you to finish the concrete surfaces, ‘* * * as

directed by the contracting officer * * * without any compensa-

tion in addition to that provided in the contract unit prices for

concrete. This provision does not obligate you to comply with

arbitrary instructions issued by the contracting officer. It does

require you, however, to comply with any reasonable instructions

of the contracting officer and to finish the concrete in a sightly

and workmanlike manner. The instructions issued by the con-

tracting officer for finishing ‘new concrete work’ are reasonable

and represent the minimum requirements for a workmanlike job.

Your appeal for additional compensation for finishing concrete is

therefor denied.”

A reconsideration of the appeal was thereafter requested on

behalf of the plaintiff and on October 1, 1946, the Chief

46 of Engineers reaffirmed the action by the Acting Chief of

Engineers of July 31, 1944, referred to above.

46. The plaintiff appealed the decision of the Chief of Engineers

to the War Department Board of Contract Appeals. The presi-

dent of this Board on January 10, 1947, as the Authorized Rep-

resentative of the Secretary of War, dismissed the appeals follow-

ing the decision of the Board which found that it had no jurisdic-

tion to entertain them.

47. On monoliths Nos. 1 through 17, 5,330 square feet of con-

crete surface was treated in accordance with the direction of the

contracting officer. The plaintiff by its letter of November 27,

1941, claimed a total of $864.07 for such surface treatment, item-

ized as follows:

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 35

Labor

Oct. 27/41 to and incl. Nov. 18/41

mn

FS ap ESSee

SSRERaS

124 hours @ $1.50 per hour

127 hours @ $1.25 per hour

522.5 hours @ $0.75 per hour.

20 hours @ $1.87 per hour

5 hours @ $2.25 per hour

6 hours @ $0.80 per hour

4 hours @ $1.125 per hour

Total labor 57

Less clean and plug form tie rod holes, 149 hrs, @ $0.75

| ee —111. 75

Balance due a/c labor. 682, 82

Rent of scaffold (swinging) ah 18. 00

Material of built scaffold______ 15. 00

2 carborundum stones 2. 50

2 trowels. 1.70

8 wire brushed [sic] 1.80

2 plaster brushes 2.10

2 bags cement 1.19 |

1 bag cement (white) 2. 50 |

0.2 ton sand 0. 40 |

Compension [sic] and other insurances @ $8.423 per hundred |

dollars of pay roll 57. 51

Total labor, material and accessories 785. 52 |

10% on the above to allow for overheads and profit 78. 55 |

IE 864. 07 |

47 No proof of damages relating to the claim was made

other than the claim itself.

48. The plaintiff claims as the extra cost to it of the concrete

finishing during 1942, in accordance with the directions of the con- |

tracting officer relating to new work, the sum of $6,070.19 itemized

as follows:

| SES eee $5, 934. 64

| | eee " 100. 00

Small tools______- 50. 00

Compensation, P. L. & P. D., $7.24 per H. of P. R 429. 67

State unemployment, 2.7% Ps 160. 24

Social Security, 1% 59. 35

| pate 6, 733. 90

Profit, 10%-_--_-_ aes ae 673. 39

Total 7, 407. 29

Chargeable to work as called for in the specifications, 27,944 S. F.

@ $.05 per S. F., incl. all insurances, bonds, profit, etec.._.__.__-- 1, 397. 20

Balance __ ™ 6, 010. 08

det achanietsnchinch 60. 10

Total Claimed, 1942 6, 070. 19

BLURRED COPY

a

36 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

It is noted that in the computation above a credit of five cents

per foot is allowed by plaintiff as the cost which it feels is properly

chargeable to it for the finishing according to the contract specifi-

cations.

Excepting such credit shown, the entire claim is based upon

labor cost and other costs in turn based upon the cost of labor

with the further exception of $150 for material and labor. Since

as the secretary of the plaintiff testified, certain original pay roll

records have been lost due to some cause beyond his knowledge, it

is not possible to verify the extra cost of concrete finishing in 1942

relating to new work.

Respectfully submitted.

Wut E. Day,

Commissioner.

49 Proceedings following filing of Commissioner's report

On August 24, 1951, plaintiff filed a motion for leave to amend

the petition.

On September 4, 1951, the court entered the following order on

said motion:

“Motion to amend petition allowed insofar as it modifies or

increases the amounts claimed, and overruled otherwise.”

On December 5, 1951, plaintiff filed its first amgnded petition,

which is as follows:

51 In the Court of Claims of the United States

[Title omitted. ]

First amended petition

Filed December 5, 1951

To the Court of Claims of the United States:

The amended petition of the plaintiff respectfully represents

that:

I

1. The plaintiff is, and at all times hereinafter referred to was,

a corporation organized and existing under the laws of the State

of New York, with its principal place of business in Binghamton,

New York.

2. The plaintiff has, at all times, borne true allegiance to the

Government of the United States and has not in any way volun-

tarily aided, abetted or given encouragement to rebellion against

the said government.

BLEED THROUGH=— POOR COPY

—_ -

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 37

52 3. On or about March 29, 1941, the United States Army

Engineer Office at Binghamton, New York, invited bids for

the construction of Flood Protection Project (Section No. 1)

along the right bank of the Chemung River within the limits of

the City of Elmira, Chemung County, New York. The plaintiff,

in response to such invitation, submitted a bid in the fixed amount

of $232,669.30 which, cn April 29, 1941, was accepted. Pursuant

to such bid and acceptance, there was subsequently executed Con-

tract No. W-321-eng-261, dated May 14, 1941 (hereinafter re-

ferred to as the “contract”), a copy of the material portions of

which is annexed hereto. Such contract was an authorized and

binding obligation of the defendant.

II

4. Under the provisions of the Act of August 30, 1935, 49 Stat.

1011—the so-called Davis-Bacon Act—the contract was required

to, and did, contain a provision obligating the plaintiff to pay not

less than the wages determined by the Secretary of Labor to be

prevailing for the corresponding classes of laborers and mechan-

ics employed on projects of a character similar to the contract

work in the territorial area in which such work was to be per-

formed. In the Specifications for the work covered by the con-

tract, which Specifications, dated March 29, 1941, were issued as

of the date thereof in connection with the advertisement for bids

as the basis upon which such bids were to be made, and which were

appended to and made a part of the definitive contract, the repre-

sentation was made that the Secretary of Labor had determined

the prevailing wage rates in the locality; and such rates were set

forth in Paragraph 1-31 of the Specifications. Among the rates

so given were the following:

Designation Wage rate, hourly

Carpenters, journeymen aati las linia $1. 00

s + t * a

Laborers, unskilled a - 50

Laborers, concrete puddlers me . vo

s * * e te

5. The plaintiff, acting on the basis of the wage rates stated

in the Specifications, as it was invited and entitled to do, com-

puted and submitted its bid. Subsequent to the acceptance of such

bid and after the execution of the definitive contract, the plaintiff

discovered that the wage rates for the classifications of labor

referred to above in Paragraph 4 were not in fact the prevailing

rates for such labor as determined by the Secretary of Labor,

neither as of the time of the issuance of the Specifications, the

Sin isieinisigbonbiemninnatci

BLURRED COPY

38 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

acceptance of the bid, nor the execution of the contract; and that

the Secretary of Labor in at least one instance, namely, on March

4, 1941, had determined the prevailing wage rates in the locality

for these classifications of labor on a similar project to be higher

than those stated in the Specifications of March 29, 1941, as

follows:

Designation Wage rate, hourly

Coapemiets, FOO MOG.. 2.0. 212i niin ows $1. 125

* * + &

Laborers, unskilled______---_- . 55

Laborers, concrete puddlers . 55

+. * os a es

Such determination of the Secretary of Labor was still in effect

and unmodified on March 29, 1941, and the Specifications issued

by the defendant on such latter date were defective and misleading

in failing to reflect such determination.

54 6. Upon commencing work under the contract, the plain-

tiff was unable to procure labor of these classifications at

the rates stated in the Specifications, and was in fact obliged to

pay higher rates, as follows:

Designation Wage rate, hourly

Carpenters, journeymen_._._-_-_---- = $1. 125

* * - - .

eS, re ssbesmsiarenninnninnesioninn ee . 625

Laborers, concrete puddlers " a

* o * 2 e

7. The plaintiff was entitled to, and did, rely upon the wage

rates stated in the Specifications as being in accordance with the

most recent determinations by the Secretary of Labor of the wage

rates prevailing for the corresponding classes of workmen on

similar projects in the area; and was entitled to, and did, prepare

and submit its bid on this assumption. When, after the acceptance

of its bid and the execution of the contract, it discovered the error

in the representations made to it, it was entitled to be reimbursed

at the higher rates which it was required to pay in order to per-

form the contract work, to the extent that such higher rates were

equivalent to the prevailing rates fixed by the Secretary of Labor

in her determination of March 4, 1941. The plaintiff duly re-

quested such reimbursement by appropriate adjustment in the

contract price, but the defendant wrongfully denied such request.

8. The failure of the defendant so to adjust the contract price

has resulted in injury and damage to the plaintiff in the amount of

$9,525.44, payment of which the plaintiff has duly demanded but

which the defendant has wrongfully refused.

BLEED THROU GH— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 39

55 Ill

9. The 6214¢ hourly wage rate with respect to iaborers (both

unskilled and concrete puddlers) which the plaintiff was obliged

in fact to pay in order to procure labor to perform the contract

work was, in fact, the prevailing hourly rate in the locality at

the time of the issuance of the Specifications, the acceptance of

the bid, and the execution of the contract; and the 55¢ rate

fixed in the Secretary of Labor’s determination of March 4, 1941,

was less than the actual prevailing rate at such times. The

failure of the defendant to make an accurate representation in

the Specifications to the plaintiff with respect to the hourly rate

actually prevailing at the time of the issuance of the Specifications,

was a breach of the defendant’s obligation to state such prevailing

rates correctly and not to mislead the plaintiff by representing

that the prevailing rates were lower than they were in fact.

Because of the fact that the plaintiff was obliged to pay the 6214¢

prevailing rate in order to procure labor to perform the contract

work, the plaintiff was entitled, in addition to the claim herein-

above described under Section II, to be further reimbursed for

the difference between the 55¢ rate for laborers fixed in the Secre-

tary of Labor’s determination of March 4, 1941, and the 6214¢

hourly rate actually prevailing at the time of the issuance of the

Specification, the acceptance of the plaintiff's bid, and the execu-

tion of the contract, which 6214¢ rate the plaintiff was required to,

and did, pay. Plaintiff duly requested such reimbursement but

the defendant wrongfully denied such request.

10. The failure of the defendant to make such reimbursement

has resulted in injury and damage to the plaintiff in the amount of

$6,071.94, payment of which the plaintiff has duly demanded but

which the defendant has wrongfully refused.

56 IV

11. Paragraph 7-05 (d) of the Specifications contained a de-

tailed description of the manner in which, and the materials with

which, the concrete involved in the construction was to be finished.

In submitting its bid, the plaintiff was entitled to, and did, rely

upon the statements made in said Paragraph 7-05 (d) in com-

puting the cost to it of finishing such concrete. During the per-

formance of the contract, the defendant ordered and required the

plaintiff to finish the concrete in a manner and with materials not

specified in, or reasonably contemplated by, the Specifications,

with the result that plaintiff was subjected to unauthorized and

unanticipated costs, reimbursement of which was duly requested

by the plaintiff but wrongfully denied by the defendant.

BLURRED COPY

a

40 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

12. The defendant’s wrongful conduct in this respect has re-

sulted in injury and damage to the plaintiff in the amount of

$6,934.26, payment of which the plaintiff has duly demanded but

which the defendant has wrongfully refused.

V

13. Under the provisions of paragraph 3-06 of the Specifica-

tions, the plaintiff was required to furnish certain sheeting and

shoring. Subparagraph (c) of said Paragraph 3-06 provided

that such sheeting and shoring was to be measured “by the square

foot of protected area”, and subparagraph (d) of said Para-

graph 3-06 provided that payment for sheeting and shoring

would be made at the contract unit price of Sixty-five Cents

($0.65) per square foot, as stated in the Schedule of Payments

annexed to and made a part of the contract.

57 14. In computing its bid, the plaintiff was entitled to,

and did, rely upon the statements contained in Paragraph

3-06 as to the measurement of sheeting and shoring by the square

foot of protected area, and computed its bid on the basis of square

footage of the area required to be protected. During the perform-

ance of the contract, however, the defendant refused to pay the

plaintiff for sheeting and shoring in accordance with the square

footage of the protected area, and, instead, followed an arbitrary

and unauthorized method of measurement, not in accordance with

the Specifications, which resulted in the underpayment of the

plaintiff for sheeting and shoring. Although the plaintiff duly

requested payment of the proper amount as contemplated by the

contract, such request was wrongfully refused by the defendant.

15. The wrongful conduct of the plaintiff in this respect resulted

in injury and damage to the plaintiff in the amount of $14,785.55,

payment of which the plaintiff has duly demanded but which

the defendant has wrongfully refused.

VI

16. Although the plaintiff duly and formally protested to the

Contracting Officer the wrongful actions complained of above, the

Contracting Officer refused to afford the plaintiff any relief, and,

upon appeal to the Chief of Engineers, was upheld by the latter.

Appeals by the plaintiff to the War Department Board of Con-

tract Appeals were, on January 14, 1947, dismissed for an asserted

lack of jurisdiction. Except as hereinbefore referred to in this

Paragraph 16, no action on the claims has been taken by Congress

or by any department of the government.

BLEED THROUGH POOR COPY

-

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 41

58 17. The plaintiff is justly entitled to recover from the

defendant the aggregate sum of $37,317.19, after allowing

all just credits and offsets.

18. The plaintiff has made no assignment or transfer of the

claims or any part thereof, and no persons other than the plaintiff

are owners of the claims or of any interest therein.

Wherefore, it is respectfully prayed that judgment be granted

against the defendant and in favor of the plaintiff for the sum of

$37,317.19, together with such costs as may be properly allowable

to it in respect of this suit.

JEROME BEAvupRIAs,

Attorney for Plaintiff, Office and Post Office Address,

83-85 Warburton Avenue, Yonkers 2, New York.

59 [Duly sworn to by Jerome Beaudrias; jurat omitted in

printing. ]

60 [Contract omitted. Printed side page 10 ante.]

64 [Specifications omitted. Printed side page 14 ante.]

71 Argument and submission of case

On April 8, 1952, the case was argued and submitted on merits

by Mr. Jerome Beaudrias for plaintiff, and by Mr. James J.

Sweeney for defendant.

73 Special findings of fact, conclusion of law and opinion of

the court by Whitaker, J.

Filed October 7, 1952

Mr. Jerome Beaudrias for the plaintiff.

Mr. James J. Sweeney, with whom was Mr. Assistant Attorney

General Holmes Baldridge, for the defendant.

The Court, upon the evidence, the report of Commissioner Wil-

liam E. Day, and the briefs and argument of counsel, makes the

following

Special findings of fact

1. Plaintiff is, and at all times material herein has been, a

corporation organized and existing under the laws of the State

of New York with its principal office and place of business at

Binghamton, New York. Since its formation in 1929, it has

been engaged in business as a general contractor.

BLURRED COPY

— , a

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

2. On March 29, 1941, defendant, acting by and through the

War Department’s Corps of Engineers’ Office at Binghamton,

New York, invited bids for the construction of Flood Protection

Project (Section No. 1) along he north bank of the Chemung

River, within the limits of the city of Elmira, Chemung County,

New York. In response to said invitation, plaintiff submitted a

bid based upon a unit price applied to the various operations in-

volved in the performance of the work in the total sum of $232,

669.30. This bid was accepted by defendant on May 14, 1941,

On that date plaintiff and defendant entered into a written

contract, No W-321-eng-261, which was approved June 3,

74 1941. On June 5, 1941, defendant gave plaintiff a formal

notice to proceed with the work. Actual work commenced

on the site of the job on June 3, 1941.

3. The contract was performed by plaintiff, and it has been paid

the contract price, as adjusted, for change orders with the excep-

tion of $100 which plaintiff instructed the District Engineer to

withhold, and plaintiff has refused to accept said $100 from de-

fendant on advice of its counsel.

4. Plaintiff sues for the sum of $37,317.19, the total of three

separate claims, as follows:

Claim for reimbursement of wage rates paid to carpenters la-

borers, and concrete puddlers_____-__---------------------- $15, 597. 38

Claim as regards measuring of sheeting and shoring__.._______ 14, 785. 55

Claim for finishing of concrete 6, 934. 26

Total 37, 317. 19

Each claim will be discussed separately.

WAGE RATES

5. Before bidding, plaintiff was furnished a copy of the specifi-

cations. Section 1-31 of such specifications reads, insofar as

here pertinent, as follows:

“1-31. Wage and Labor Provisions—(a) The Secretary of

Labor has determined the minimum wage rates applicable in the

locality for the labor classifications anticipated to be used on the

work. In accordance with Article 17 of the contract, »mployees

at the site shall be paid not less than these wages as listed below:

Designation Wage rate, hourly

Carpenters, journeymen $1. 00

* s e e e

Laborers unskilled 0. 50

Laborers, concrete puddlers_ 0. 50

> * s s eo

ee

BLEED THROUGH=— POOR COPY

_—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 43

6. Article 17 of the contract reads as follows:

“ArTicLeE 17. Rate of wages (in accordance with the act of

August 30, 1935, 49 Stat. 1011 (U. S. Code, title 40, sections 276a

and 276a-1), this article shall apply if the contract is in excess of

$2,000 in amount and is for the construction, alteration, and/or

repair, including painting and decorating, of a public building

or public work within the geographical limits of the States of the

Union or the District of Columbia).

75 “(a) The contractor or his subcontractor shall pay all

mechanics and laborers employed directly upon the site

of the work, unconditionally and not less often than once a week,

and without subsequent deduction or rebate on any account, the

full amounts accrued at time of payment, computed at wage rates

not less than those stated in the specifications, regardless of any

contractual relationship which may be alleged to exist between

the contractor or subcontractor and such laborers and mechanics;

and the scale of wages to be paid shall be posted by the contractor

in a prominent and easily accessible place at the site of the work.

The contracting officer shall have the right to withhold from

the contractor so much of accrued payments as may be considered

necessary by the contracting officer to pay to laborers and me-

chanics employed by the contractor or any subcontractor on the

work the difference between the rates of wages required by the

contract to be paid laborers and mechanics on the work and the

rates of wages received by such laborers and mechanics and not

refunded to the contractor, subcontractors, or their agents.

“(b) In the event it is found by the contracting officer that any

laborer or mechanic employed by the contractor or any subcon-

tractor directly on the site of the work covered by the contract

has been or is being paid a rate of wages less than the rate of

wages required by the contract to be paid as aforesaid, the Govern-

men* may, by written notice to the contractor, terminate his right

to proceed with the work or such part of the work as to which there

has been a failure to pay said required wages and prosecute the

work to completion by contract or otherwise, and the contractor

and his sureties shall be liable to the Government for any excess

costs occasioned the Government thereby.”

7. On October 22, 1940, the Elmira business agent of the United

Brotherhood of Carpenters and Joiners of America, Local 532,

wrote to the United States Engineer’s Office in Binghamton,

New York, to inform it that the wage scale for carpenters would

be increased as of January 1, 1941, from $1 per hour to $1.125 per

hour. On October 29, 1940, the District Engineer acknowledged

receipt of this letter.

a

44 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC,

8. On January 31, 1941, the Secretary of Labor furnished to

the Corps of Engineers at its request, for inclusion in the contract

specifications, the schedule of minimum wages in the Elmira area,

Such schedule, which is set out in finding 5, was included

76 ‘in the specifications which were furnished to plaintiff prior

to the computation of its bid. As stated in finding 2, in-

vitations for bids were issued on March 29, 1941, and plaintiff’s

bid was accepted on May 14, 1941.

9. On March 4, 1941, the Secretary of Labor furnished to the

Public Buildings Administration of the Federal Works Agency a

schedule of minimum wages in the Elmira area for inclusion in

the bidding specifications and contract for a Federal Housing

Project in Elmira, New York. The prevailing wage rates shown

therein, in pertinent part, were as follows:

Classification Hourly rate

Carpenters, journeymen____----------~-------------- $1. 125

Laborers, unskilled_____._----_--_-- 55

10. Plaintiff employed only union labor on this project. At

the time plaintiff began work on the site on June 3, 1941, it had

to pay $U.625 per hour for laborers and $1.125 per hour for car-

penters. The carpenter wage rate had been put into effect by the

union on January 1, 1941, and the laborer wage rate on April

1, 1941.

11. On June 16, 1941, plaintiff advised the District Engineer

(who was the contracting officer) that the minimum wage rates

provided in the contract specifications were less than the rates

currently prevailing in the Elmira locality for carpenters, laborers

(unskilled), laborers (concrete puddlers), and truck drivers.

12. The District Engineer replied on June 27, 1941, stating that

the minimum wage rates were determined in strict accordance

with the applicable law and regulations, and that he could not

afford relief for any differences between wage rates then prevailing

in the area and the minimum rates required by the contract

specifications.

13. Plaintiff protested this decision to the Chief of Engineers

under date of July 10, 1941, and on August 5, 1941, plaintiff's

appeal was denied by the Chief of Engineers in part as follows:

“There is no authority in law for this office to question the cor-

rectness of any determination made by the Secretary of Labor

pursuant to the provisions of the above cited act [49 Stat. 1011].

Therefore, I find that the wage rates as established by the Secre-

tary of Labor, and incorporated in the contract specifica-

77 ~—‘ tions were the minimum wage rates applicable in the

locality for the labor classifications anticipated to be used

on the work.”

BLEED THR OUGH=— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 45

14. Plaintiff under date of February 20, 1943, asked defendant

to reconsider its appeal regarding minimum wage rates, and this

was responded to by letter dated April 13, 1943, from the Chief

of Engineers, in part as follows:

“A determination as to the accuracy of the specified wages is

not necessary to a decision in this case. The contract by Article

17 and by paragraph 1-31 of the specifications provides that wages

not less than those specified shall be paid. The contract makes no

representation as to the availability of labor aor as to the actual

wage scales that would be in effect. The alleged increased costs did

not result from your contract obligation but from economic con-

ditions which are ordinary contingencies contemplated under the

terms of the contract. No reason has been shown which would

warrant modification of the previous decision dated August 5,

1941.”

15. Paragraph 1-12 of the Standard Government Form of In-

vitation for Bids, a copy of which was furnished to plaintiff, pro-

vides as follows:

“Investigation of Conditions.—Bidders are expected to visit the

locality of the work and to make their own estimates of the facili-

ties needed, the difficulties attending the execution of the pro-

posed contract, including local conditions, availability of labor,

uncertainties of weather, and other contingencies. In no case

will the Government assume any responsibility whatever for any

interpretation, deduction, or conclusion drawn from the examina-

tion of the site. At the bidder’s request, a representative of the

Government will point out the site of the proposed operations.

Failure to acquaint himself with all available information con-

cerning these conditions will not relieve the successful bidder of

responsibility for estimating the difficulties and costs of success-

fully performing the complete work.”

16. If plaintiffs president had investigated wage rates, he

could have ascertained that the prevailing wage for carpenters

was $1.125 per hour, and that the prevailing rate for unskilled

labor was $.55 per hour, with an advance to $.625 per hour, effec-

tive as of April 1,1941. Also, before inviting bids on this project,

the District Engineer could have ascertained that the Sec-

78 retary of Labor had made a new determination of the pre-

vailing wage rates for Elmira on March 4, 1941.

17. Because plaintiff was required to pay $1.125 per hour to

carpenters instead of $1 per hour, as shown in the bid proposal and

contract wage schedule, its labor costs were increased $3,786.68.

Similarly, plaintiff's labor costs for unskilled laborers and con-

crete puddlers were increased $3,576.54 as the result of the pay-

ment of the $0.55 per hour rate instead of the $0.50 per hour rate

BLURRED COPY

46 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

specified in the contract wage schedule. The total of these

amounts, which includes plaintiff’s increased payroll insurance

and taxes, is $7,363.22.

SHEETING AND SHORING

i8. The contract specifications provide in part as follows:

SEOTION I

“1-14. Work Areas.—* * *

“(b) The contractor shall be responsible for trespassing upon,

or damage to, public and private lands and roads, bridges, build-

ings, chimneys, and utilities in or adjacent to the work and access

areas resulting from any act or omission on his part, including

damage caused by disturbance of foundations while conducting

any operation within the work area. The contractor shall take

special precautions to prevent injury to existing structures while

working in the vicinity of the Hygeia plant, Brand building,

greenhouse, gas regulation house, private dwellings, and all other

buildings and structures located at or close to the edge of the work

area. He shall take similar precautions in the vicinity of the pole

line crossing the levee at West Hudson Street, the water main at

approximate State 176+37, all power facilities at the Hygeia

plant, and any other utilities which will not be relocated.

* oJ s * a7

“(d) The garage and other property of the Hygeia Refrigerat-

ing Company are within the work area, and the activities of this

company will be carried on during construction of the project.

The contractor shall cooperate with this company during all con-

struction operations in order to preserve its access and permit its

operations to be conducted with a minimum of interfer-

79 ence by the contractor. The contractor shall perform the

necessary construction on the company’s property in the

least practicable time. He shall provide bracing or other protec-

tion satisfactory to the contracting officer for the garage wall

against which the new wall is placed. The garage and other prop-

erty within the work area shall be restored to a condition satis-

factory to the contracting officer upon completion of the permanent

work in that area.

& * * * s

“SEOTION III

“3.03. Excavation—Common. * * *

“(b) Procedure. (1) General. Excavation—Common shall

be performed in accordance with subparagraph 3-01 (c). Exca-

vation around bridge piers and abutments, existing walls, build-

BLEED THROUGH— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 47

ings, chimneys, transformers, power lines, utilities, sewers, cul-

verts, and other existing structures shall be executed with all due

precautions, satisfactory to the contracting officer, for safeguard-

ing the structures. (See paragraph 1-14.) Where special work

is required to prevent undermining existing structures, it shall

be done in accordance with detailed plans prepared by the con-

tractor and approved by the contracting officer, but such approval

shall not relieve the contractor of responsibility for damages

which may result from the failure of the temporary protection.

Where excavation operations endanger the stability of existing or

new structures, sheeting and shoring shall be installed at the

locations indicated on the drawings or directed by the contract-

ing officer. The contractor shall be responsible for the safety of

such structures. (See subparagraph (3) below and paragraph

3-06.) **_* *

* * * * *

“(3) Sewers, Culverts, and Drains.—The contractor shall fur-

nish and install sheeting and shoring in all trenches where the

depth exceeds 6 feet. * * *

* * ” * of

“3-4. Sheeting and Shoring.—(a) General—The contractor

shall furnish and place such sheeting, shoring, bracing, or other

approved supports as are indicated on the contract drawings or

directed by the contracting officer for the protection of the work or

adjoining property. The right is reserved to order the installa-

tion of sheeting and shoring where its use is considered

8) advisable for the safety of the work, and to require such

sheeting and shoring to remain in place when its removal is

considered inadvisable.

“(b) Procedure.—All sheeting and shoring shall be designed by

the contractor and approved by the contracting officer prior to

installation, but such approval by the contracting officer shall not

relieve the contractor of sole responsibility for damages resulting

from the inadequacy or lack of any sheeting and shoring. The

sheeting and shoring shall be built to provide adequate clearances

for minimum interference with construction operations, proper

bracing for stability, and safe conditions around the work. If,

in the opinion of the contracting officer, any methods or measures

of the contractor constitute a hazard in any way or are otherwise

improper or inadequate, the contracting officer will notify the

contractor of that fact in writing. If the contractor fails to pro-

vide immediately such remedial measures as are deemed necessary

by the contracting officer, such measures will be provided by the

contracting officer at the expense of the contractor. When sheet-

ing and shoring have served their purpose and their removal is

BLURRED COPY

48 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

approved by the contracting officer, they shall be removed and

disposed of. Whether sheeting and shoring are removed or left

in place, all cavities shall be adequately filled. When approved by

the contracting officer, sheeting and shoring may be used in lieu

of excavation to full pay lines.

“(c) Measurement.—Sheeting and shoring will be measured by

the square foot of protected area.

“(d) Payment.—Except as specified below, payment for all

costs of furnishing and placing sheeting and shoring indicated on

the contract drawings or directed by the contracting officer, and of

its removal and disposal when not left in place, will be made at the

contract unit price for “Sheeting (Including Shoring) ,” Item No.

7. Where sheeting and shoring are used at the contractor’s option

and with the approval of the contracting officer, separate payment

will not be made for the sheeting and shoring, but payment will

be made for excavation to the pay lines shown on the contract

drawings as though the cut had been made to such pay lines.”

19. The schedule of payments incorporated into the contract in

suit provided in item 7 that the plaintiff was to be paid for sheeting

(including shoring) on a quantity of 9,200 square feet at the rate of

65 cents per square foot, or a total of $5,980.

81 20. Section 1, paragraph 1-05, provides in pertinent part

as follows:

“1-05. Quantities—The following estimate of quantities is

given only to serve as a basis for comparison of bids and for de-

termining the amount of consideration of the contract;. Within

the limits of available funds, the contractor will be required to

perform the entire quantity of work necessary to complete the

work specified in paragraph 1-02 hereof, be it more or less than

the amounts herein estimated.

* + + * *

“Item No. 7 Sheeting (Including Shoring) 9,200 Sq. Ft.”

. * * * *

21. As the work progressed, the plaintiff placed sheeting and

shoring necessary for the protection of the work as well as that

necessary for the protection of existing buildings and structures.

Payment was made on account of such sheeting and shoring, as

well as the other work performed by the plaintiff, on monthly esti-

mates prepared by defendant’s resident engineer and given to

plaintiff's superintendent together with a payment voucher for

execution on behalf of plaintiff. The plaintiff executed such pay-

ment vouchers and forwarded them along with each monthly esti-

mate for payment by the defendant’s paying office. On the second

such monthly estimate forwarded with a payment voucher by

plaintiff, an item of 438 square feet of sheeting, including shoring,

BLEED THROUGH— POOR COPY

_

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 49

| "appears under item 7. On subsequent monthly estimates sup-

porting payment vouchers, under item 7 appears a figure covering

additional sheeting, including shoring. The plaintiff accepted

monthly payments on such payment vouchers without question as

to the manner of computation of the sheeting (including shoring)

item until the final estimate was received by the plaintiff showing

a total of 10,152 square feet.

92. After all of the work under the contract had been performed,

the defendant, through the resident inspector, forwarded pro-

d final estimate on January 21, 1943. On January 28, 1943,

plaintiff’s superintendent, Mr. Bernard Gabriel, went to the office

of the District Engineer at Syracuse, New York, and conferred

with a representative of that official concerning claims for addi-

tional payments on various contract items including sheet-

82 ingand shoring. Following this conference, the plaintiff

received a letter dated February 1, 1943, from the District

Engineer in which it is stated that:

“In computing pay quantities the following methods were used

by this office.

“Sheeting—Computations based on field measurements of

length and height of sheeting placed.”

23. The plaintiff was paid at the rate of 65 cents per square foot

for 10,152.1 square feet of sheeting and shoring. Of this amount

6,738.2 square feet was for the protection of the work, and 3,413.9

square feet was for the protection of property. The plaintiff

claims that it should have been paid for 32,899 square feet, 8,094

square feet for the protection of the work, and 24,805 square feet

for the proptection of property.

As to the sheeting and shoring required for the protection of the

work, it is plaintiff's position that the protected area was the

area of side walls of trenches excavated where sheeting was placed.

On many items concerning sheeting placed for protection of the

work, the allowance was as great or greater than that claimed, ex-

cept for 50 square feet of sheeting claimed at the Walnut Street

Bridge, which the defendant allowed under sheeting placed for

the protection of property. The evidence is not satisfactory as to

the measurements by which either the amount claimed or allowed

was computed.

As to the sheeting and shoring required for the protection of the

property, plaintiff’s claim is based not upon the amount of sheet-

ing or shoring placed, but rather upon the ground area covered

by the buildings and structures so protected. The ground area

of the buildings and structures which was protected by sheeting

and shoring is shown below:

BLURRED COPY

—

50 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

Ground area of buildings and structures as to which sheeting and shoring

was provided

Square

eet

rent TI 65 iene sin oe secnneneensecnen 175 x 68 11, 900

NN i oan resign ppeerespa elmo beeeen ener saan 815 x 6 1, 890

Ge CE FEF nk cin ss eens 54 x 60 3, 240

House (Connolly Ave.) ...........---~--~-~------..-- 35 x 25 875

Florist Shop (Walnut St.) ------------- See EEA 30 x 30 900

eI 0 WR TIE oe atc kienmrnawc ou 240 x 25 6, 000

| ean ee 24, 805

83 24. The plaintiff on February 9, 1943, wrote to the Dis-

trict Engineer requesting that the defendant recompute the

allowance for sheeting and shoring.

“* * * by ascertaining the square footage of the area protected

by the work performed under this item, pursuant to paragraph

3-06 subdivision (c) and that we be paid therefor at the unit price

of said item. * * *”

The defendant reviewed plaintiff's protests and on February 18,

1943, wrote plaintiff that the item had been measured and com-

puted in strict accordance with the provisions of the contract

specifications, and the contractor was invited to present additional

facts or computations for consideration.

25. The plaintiff failed to accept this invitation but rather by

letter dated February 24, 1943, returned a final release of claims

wherein was listed an exception to the method of computing the

final quantity of sheeting and shoring.

26. Receipt of the release was acknowledged by letter dated

March &, 1943, and the plaintiff was advised of his further rights

of appeal under Article 15 of the contract.

27. On March 19, 1943, vlaintiff appealed the decisions of the

contracting oflicer to the Secretary of War, and on July 31, 1944,

the appeal was denied. This denial reads in part as follows:

“You allege that the method used by the contracting officer in

computing the pay quantities for sheeting (including shoring)

was incorrect. Paragraph 3-06 (c) of the contract specifications

states that sheeting and shoring, ‘* * * will be measured by the

square foot of protected area.’ The record shows that the pay

quantities of sheeting placed adjacent to existing structures were

determined by measurements to specific payment lines where such

lines are shown on the drawings. Where specific payment lines

were not indicated, the quantities were computed by using the

length of the area actually sheeted and the difference in elevation

between the top of the sheeting and the bottom elevation of the ad-

jacent structures. The pay quantities for sheeting not placed

adjacent to any existing structure were computed by multiplying

the difference in elevation between the ground surface and the bot-

tom elevation of the trench by the length of the area sheeted. You

BLEED THROUGH— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 51

assert that because of the liability imposed by paragraph 1-14

(b) of the specifications for damages to structures in or

84 adjacent to the work, including damages caused by dis-

turbance of foundations, that the term ‘protected area’ as

used in paragraph 3-06 (c) must be construed to mean the ground

area occupied by the adjacent structures and that the computation

of pay quantities for sheeting placed to protect such structures

must be based on the area thereof. As noted above the payment

lines shown on the drawings for sheeting and shoring placed adja-

cent to the structures clearly indicate that the parties did not. in-

tend that payment should be made on the basis of the ground area

of the buildings. Furthermore, the estimates [sic] pay quantity

of sheeting was only 9,200 square fee approximately 10% less

than the quantity of 10,152 square feet for which payment was

made and only about 30% of the quantity for which payment is

claimed. The contract does provide, as contended by you, that the

quantities specified are only estimates. However, the buildings

which were to be protected were clearly indicated on the contract

drawings. The combined ground area of the buildings alone,

aside from the other locations where the plans indicated sheeting

was to be placed, is about 214 times the total area for which it was

estimated sheeting would be required. The payment lines indi-

cated on the drawing and the discrepancy between the ground

area of the buildings and the estimated quantity of the sheeting

should have put you or notice that the Government did not intend

that the pay quantities of sheeting and shoring placed adjacent to

existing structures would be computed on the basis of the ground

area of such structures. No objection has been made of the

method employed by the contracting officer in computing pay

quantities for sheeting not placed adjacent to structures. As the

ground area occupied by a structure has no direct relation to the

cost of placing sheeting and shoring adjacent to it, there would

appear to be no reason to compute the pay quantities of sheeting

placed adjacent to such structures on the basis of the ground area

occupied and to compute the pay quantities of sheeting not so

placed on an entirely different basis. Under paragraph 1-14 (b)

of the specifications you are liable for damages to land as well as

tostructures. If your contention that the pay quantities of sheet-

ing placed adjacent to existing structures must be computed on

the basis of the ground occupied by said structures were to prevail,

it would logically follow that the pay quantities for sheeting not

placed adjacent to any existing structure should be computed on

the basis of the land area protected, even though such area

might conceivably comprise many acres. Such as [sic]

85 interpretation is obviously absurd. It is my finding that

BLURRED COPY

=,

52 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

the methods employed by the contracting officer for computing

the pay quantities of sheeting and shoring were correct.”

CONCRETE FINISHING

28. Article 15 of the contract provides as follows:

“ArticLte 15. Disputes—Except as otherwise specifically pro-

vided in this contract, all disputes concerning questions of fact

arising under this contract shall be decided by the contracting

officer subject to written appeal by the contractor within 30 days

to the head of the department concerned or his duly authorized

representative, whose decision shall be final and conclusive upon

the parties thereto. In the meantime the contractor shall dili-

gently proceed with the work as directed.”

Section 1-20 of the general provisions of the contract. specifi-

cations provides:

1-20. Claims, Protests, and Appeals.—(a) If the contractor

considers any work demanded of him to be outside the require-

ments of the contract or if he considers any action or ruling of

the contracting officer or of the inspectors to be unfair, the con-

tractor shall without undue delay, upon such demand, action, or

ruling, submit his protest thereto in writing to the contracting

officer, stating clearly and in detail the basis of his objections. The

contracting officer shall thereupon promptly investigate the com-

plaint and furnish the contractor his decision, in writing, thereon.

If the contractor is not satisfied with the decision of the contract-

ing officer, he may, within thirty days, appeal in writing to the

Chief of Engineers, whose decision shall be final and binding upon

the parties to the contract. Except for such protests or objections

as are made of record in the manner herein specified and within

the time limit stated, the records, ruling, instructions, or decisions

of the contracting officer shall be final and conclusive.

“(b) The Chief of Engineers has been designated by the Secre-

tary of War as his duly authorized representative to make final

decision and to take other action where the terms of the contract

require that such decision or action shall be ‘by the Head of the

Department concerned or his duly authorized representative.” All

appeals from decisions of the contracting officer authorized under

the contract shall, therefore, be addressed to the Chief of Engi-

neers, U. S. Army, Washington, D.C. The appeal shall contain

all the facts or circumstances upon which the contractor

86 bases his claim for relief and should be presented to the

contracting officer for transmittal within the time provided

therefor in the contract.”

Pertinent provisions of the contract specifications, Section VII,

dealing with the subject “Concrete” are quoted below:

BLEED THROUGH— POOR COPY

—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 53

SECTION VII. CONCRETE

* * * ~ *

“7.03. Proportioning and Mixing.—* * *

“(b) Proportioning. * * *

“(2) Control.—The exact proportions of all material entering

into the concrete shall be as directed by the contracting officer.

The contractor shall provide all equipment necessary to positively

determine and control the actual amounts of all material entering

into the concrete. The proportions will be changed whenever, in

the opinion of the contracting officer, such change becomes neces-

sary to obtain the specified strength and the desired density,

uniformity and workability, and the contractor will not be com-

pensated because of such changes, except for an increase in the

specified minimum unit paste content, as provided herein as

follows: In the event it is determined by the contracting officer

that concrete of the desired quality cannot be obtained with the

specified gradation of aggregates conforming fully to the specifi-

cations and the specified minimum unit cement content, he may

direct an increase in the unit paste content by the addition of

Portland cement, in which case compensation will be made there-

for at the cost to the contractor of the cement delivered f. o. b.

carrier at the site of the work, plus $0.40 per barrel.

* * * * *

“7_05. Details of Construction.—(a) Forms.—* * *

“(4) Removal.—Forms shall not be removed without the ap-

proval of the contracting officer, and all removal shall be accom-

plished in such manner as will prevent injury to the concrete.

Forms shall not be removed from walls and vertical faces before

the expiration of 2 days, except when specifically authorized by

the contracting officer. When, in the opinion of the contracting

officer, conditions on the work are such as to justify it, forms may

be required to remain in place for longer periods.

* * * a *

“(d) Finishing.—Immediately following removal of forms, all

form tie holes shall be filled, protruding fins or other surface irreg-

ularities removed by carborundum stone and all other de-

87 fects repaired. Where necessary to obtain a suitable surface

finish, the contractor shall remove the forms and finish the

surfaces when and as directed by the contracting officer at no

additional cost to the United States. The curing specified in sub-

paragraph 7-05 (e) following shall be temporarily suspended

during such repairing or finishing as directed. The finished sur-

faces shall be free from sand streaks or other defects and the

plastering over of such surfaces will not be permitted. Defective

BLURRED COPY

54 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

concrete shall be repaired by cutting out the unsatisfactory mate-

rial and placing new concrete which shall be formed with keys,

dovetails, and anchors to attach it securely to the other work. This

concrete shall be drier than the usual mixture and shall be thor-

oughly tamped into place. All surfaces of concrete, not covered

by forms, that are not to be covered by additional concrete or

backfill shall have a wood float finish without additional mortar,

and shall be true to elevations as shown on contract drawings.

Striking-off and finishing shall follow closely the placing opera-

tion in order to insure completion before the initial set has taken

place. The contractor will not be permitted to start a pour unless

a sufficient number of qualified finishers are available to fulfil]

the above requirements. Care shall be taken to see that all excess

water is removed before making the finish. Other surfaces shall

be brought to the specified finished elevation and left true and

regular as approved by the contracting officer. Where considered

necessary by the contracting officer, or where indicated on the

drawings, joints shall be made carefully with a jointing tool.

Every precaution shall be taken by the contractor to protect fin-

ished surfaces from stains or abrasions. No fire shall be per-

mitted in direct contact with any concrete at any time. Concrete

surfaces or edges likely to be injured during the construction

period shall be properly protected by leaving the forms in place

or by erecting covers satisfactory to the contracting officer.”

29. Section 1, paragraph 1-11, Work Covered by Contract Price,

provides as follows:

“1-11. Work Covered by Contract Price.—The contractor shall,

under the contract prices, furnish and pay for all materials, equip-

ment, and labor for all permanent, temporary, and incidental work,

furnish all accessories, and do everything which is necessary to

carry out the contract in good faith, which contemplates every-

thing completed, in proper working order, of good materials with

skillful workmanship, accurately fitted, properly assembled, and

connected.”

88 30. The placement of concrete began on August 20, 1941,

and placement was made from time to time during that con-

struction season until October 24, 1941. During this time mono-

liths Nos. 1 through 17 were poured. The first concrete which

was placed above the foundation and as to which the plaintiff’s

claim for finishing relates was commenced on September 5, 1941.

31. From the time that the forms were stripped from the ex-

posed concrete lifts above the foundation, the defendant’s field

representatives complained to Mr. Gabriel, plaintiff’s superin-

tendent, of the poor faces on the exposed concrete. After mono-

liths Nos. 1 through 17 had been poured and the forms stripped

from the concrete, there were rust stains showing from the water

ee

BLEED THROUGH— POOR COPY

_—

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 55

pipes used in curing, and the concrete faces showing numerous

blemishes, pockmarks, and honeycombs. Protruding fins had not

been removed, and the form tie rod holes had not been filled.

32. Prior to October 29, 1941, defendant complained to plaintiff

regarding the tie holes not being plugged as required by para-

graph 7-05 (d) of the contract specifications.

33. Under date of July 28, 1941, plaintiff transmitted to defend-

ant some revised prints covering certain form details in the con-

struction of the wall and which made reference to the proposed

use of certain porcelain tubes or cylinders for the purpose of

putting bolts through said porcelain cylinders which could act

as spreaders and thereby increase or lessen the width of the forms.

34. Defendant, by letter dated August 4, 1941, approved plain-

tiff’s revised prints subject to certain provisions which in part

provided :

“(e) The approval as indicated above is predicated on pro-

ducing a finished concrete surface as contemplated in contract

specifications, and the right is reserved to require necessary revi-

sions in your form construction to provide uniform finished sur-

faces on all exposed faces.”

35. On October 15, 1941, defendant objected to the further use

by plaintiff of visible porcelain tubes which gave the appearance

of an unfinished job.

36. Under date of November 15, 1941, defendant wrote plaintiff

regarding the unused porcelain tubes and therein stated that

89 plaintiff would be allowed to use these tubes on unexposed

concrete wall surfaces and would be paid for the remaining

unused porcelain tubes.

87. The defendant has allowed payment for porcelain tubes

which were delivered by plaintiff to defendant but not used on the

job.

38. On October 20, 1941, the contracting officer addressed and

forwarded the following letter to the plaintiff:

“Reference is made tu Par. 7-05 (d), Finishing of Concrete

Surfaces, of your Contract No. W-321-eng-261 for the construction

of the Elmira Flood Protection Project, Section 1.

“TI have examined the concrete work constructed to date under

your contract and find that it has not been finished in accordance

with the provisions of the contract specifications. You are di-

rected to correct these deficiencies at once. My field representa-

tives will indicate the defective work and furnish details of the

required corrective measures.”

39. By letter dated October 29, 1941, defendant’s Resident

Engineer forwarded a detailed statement of corrective measures

to be taken by the contractor in two parts, the first relating to

the treatment of monoliths Nos. 1 through 17 which had then been

BLURRED COPY

a is

56 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

placed, and the second relating to the treatment of concrete which

had not then been placed. The detailed statement of corrective

measures provides as follows:

“METHOD OF TREATING EXISTING WORK

“The surface to be treated will be scrubbed with a wire brush

where necessary to clean out defective areas.

“Mix one part portland cement with two parts fine sand (similar

to that used on the project from which particles retained on the

No. 16 sieve has been removed) with water sufficient to produce

a grout having the consistency of very thick paint. If necessary,

white portland cement shall be added, replacing an equal quantity

of standard cement, in a quantity sufficient to give a color equal

to the concrete in the project. A test of the procedure and color

will be made on a panel which is to be covered with backfill. This

mixture shall be carefully worked out so that no difference in color

will result from the grout. This mixture shall be allowed to set

for 45 minutes before being used. The surface of the con-

90 crete to be treated shall be thoroughly wet, after which the

grout shall be applied with a brush or cloth completely

filling air bubbles and holes. Immediately after applying the

grout scour the wall vigorously with a cork or wood float. The

grout shall then be allowed to set partially for an hour or two,

depending on the weather, until it has hardened sufficiently so

that it can be scraped from the wall with the edge of a steel

trowel without removing the grout from th: small air holes.

Next allow the surface to dry thoroughly one or two hours or more

depending on the weather until the initial set occurs and rub it

vigorously with a burlap bag to completely remove any dried grout.

There shall be no visible film of grout remaining after this rub-

bing. The entire cleaning operation for any monolith shall be com-

pleted the same day it isstarted. Theentire exposed surface of the

monolith shall be treated in this manner. If any dark streaks or

spots remain after this operation they shall be rubbed lightly

with a fine carborundum stone. This rubbing must be carefully

done to avoid changing the texture of the concrete.

“After the grout has become thoroughly set (24 hours in warm

weather and 48 hours in cold weather) curing will commence and

continue for at least seven days. Curing shall be accomplished

by covering finished surfaces promptly with damp burlap or cot-

ton quilts. (Heating will not be necessary on old walls.)

“METHOD OF TREATING NEW CONCRETE WORK

“The forms on work that is to be exposed shall be removed as

soon as it is possible to do so without injury to the concrete. In

iiciissisittsieatanimsiiesiataaisl

BLEED THROUGH— POOR COPY

.

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 57

warm weather (minimum 65° F., average 75° F.) this will be

approximately 24 hours after the completion of placing. In

colder weather the forms should be allowed to remain in place

approximately 48 hours.

“Immediately after the forms have been removed all fins or

other projections shall be broken off with a carborundum stone or

other suitable tool which will remove the projections without

marring the surrounding surfaces. Filling of form tie holes shall

be concurrent with the removal of fins, etc. This operation shall

be separate from general finishing and shall be accomplished with

retempered mortar. This mortar shall have the same sand-cement

ratio as the concrete in the original work. Sufficient water shall

be added to make a dry mixture. This mortar shall be thoroughly

mixed, allowed to set for one hour and then remixed before being

used. The material shall be thoroughly tamped into the tie

91 _ holes and care shall be taken not to smear or deface the sur-

rounding surfaces. Other patching of honeycomb or simi-

lar defects shall also be accomplished with sand-cement mortar as

described above. All patches shall bond with the steel reinforce-

ment and shall, if feasible, be dovetailed to the existing work.

Dish shaped patches with sloping sides shall not be permitted.

“Upon completion of repair work as outlined above, the entire

exposed surface shall be treated as follows:

“A thin sand-cement mortar shall be applied to the entire sur-

face with a steel trowel. This mortar shall be composed of one

part cement and two parts sand to which water shall be added

until the mortar has the consistency of very thick paint. If

necessary, white cement shall be used replacing an equal quantity

of regular cement so that the dry mortar will have the same color

_. as the concrete in the structure. Panels shall be experimented

with on concrete surfaces which will be covered in order to assure

this similarity in color. This application shall be sufficiently

vigorous to insure the complete filling of all pockmarks or other

blemishes. The sand for this mortar shall be the sand as regulaly

[sic] used in the concrete work except that the sizes retained on a

No. 16 sieve shall be removed. The mortar applied to the concrete

surface shall be allowed to set for one hour and the surplus shall

then be removed by scraping the surface lightly with the edge of

a steel trowel or steel float. After the lapse of sufficient time to

allow initial set or hardening of the mortar, the surface shall be

vigorously rubbed with Clean Dry Burlap which shall entirely

remove the mortar on the surface of the concrete. Initial curing

shall be commenced immediately after this operation and shall

consist of covering the finished surface with Clean Wet Burlap.

Normal water curing will commence 12 hours later. Finishing

of concrete surfaces shall be completed in the minimum possible

BLURRED COPY

58 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

time and in no case shall the finishing be extended over more than

a 12 hour period. (This is specified because the color of the fin-

ished surface may vary with atmospheric conditions and make

blending with adjacent finished surfaces difficult.) ”

40. Upon receipt of the letter and its enclosure referred to in

the foregoing finding, the plaintiff on October 31, 1941, addressed

the following letter to the contracting officer :

“Receipt is acknowledged of your letter of October 29th relative

to certain finishing which you desire us to do on the concrete —

already placed on this project. It seems wise at this time

92 to review briefly, for the record, the procedure which has

previously taken place and which must therefore be respon-

sible for the appearance of these concrete walls. Before reviewing

this procedure, let me state that we are already proceeding to do

as directed in your letter of October 29th, and that we will at all

times proceed with any of your instructions, our desire, however

being, of course, that we be protected insofar as the matter of

reimbursement to us, for any expenses plus normal profit incurred

in carrying out any such instructions, is concerned.

“The aggregates used in the Elmira work, gravel, sand, and

cement, were all previously approved by your representatives and

accepted for this work. The water is the same as that used by the

people of Elmira for drinking water and has also been approved

by your representatives. The characteristics of the mixture, inso-

far as the porportion [sic] of the component parts, was set by

your representatives after exhaustive tests on their part. The

form lining used was approved by your representatives and the

forms themselves compare in construction very favorably as to

strength, appearance, etc., with any used in the district, and this

we have on the authority of the Acting Chief of Operations. We

come, therefore, to the mixing and placing of the concrete, and at

all times these procedures have been directly and completely under

the control of your representatives. No latitude has been allowed

us for the carrying out of any opposing ideas we may have had in

this work, ideas which may or may not have secured a better

result, but in any event we were not allowed to try them out. We

must therefore, in view of all the above, respectfully suggest that

the responsibility for any result which may not appeal to you,

does not lie on our shoulders.

“It is our understanding that costs are being kept by your

representatives as well as by ourselves on the additional expense

that is now accruing because of the finishing operations which you

have directed, and that on the conciusion of these operations a

satisfactory settlement will be reached to reimburse us for this

expense. If this understanding is not in accordance with yours,

we should appreciate being advised at once.

BLEED THROUGH— POOR COPY

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 59

“Your consideration and advice on all the above will be

appreciated.”

41. After monoliths Nos. 1 through 17 were treated in accord-

ance with the procedure outlined for existing work, the plaintiff

submitted on November 27, 1941, a request for the payment

of the sum of $864.07 covering the cost of such work.

93 This sum resulted after an allowance of $111.75 had been

deducted as the cost of filling form tie rod holes.

On December 10, 1941, the contracting officer by letter ac-

knowledged receipt of the above letter and stated as follows:

“T find that the finishing treatment required on your job is well

within the intent of paragraph 7-05 (d), and I cannot consider

additional payment for this work.”

Following receipt of the above letter, Mr. Fred Davis, vice

president of plaintiff, conferred with the District Engineer on

December 15, 1941. After this conference, the plaintiff addressed

the following letter to the contracting officer :

“As a result of a conference held this morning with the District

Engineer, Mr. Samples, and myself, my understanding of the

conclusions reached at this conference is outlined below.

“1, I understand that our company is not giving up any of our

rights to future consideration of our claim for the cost of the

treatment of the walls constructed during 1941 by reason of not

appealing at this time the decision of the District Engineer out-

lined in his letter of December 10th.

“2. That consideration will be given to payment by the United

States for any increase in our costs because of any change in the

kind of aggregates composing the concrete mixtures or ecause of

any change that may be prescribed in handling the concrete.

“3. That the treatment of the walls in the future will be modi-

fied, in that treatment will be required only on the land side of the

walls except that at bridge approaches where treatment shall be

on both sides of the walls for a distance of three or four monoliths

from the bridge approach; such treatment shall immediately

follow the removal of the forms and shall consist of rubbing the

concrete with carborundum [sic] stone and brushing with a light

coat of mortar if required. It will also, of course, be necessary

for us to block the holes at the form tie rods.

“We would appreciate knowing as to whether your understand-

ing is in general accordance with the above.”

42. The contracting officer replied by letter of Decembr 29, 1941,

as follows:

“Reference is made to your letter dated December 15, 1941, re-

garding your understanding of conclusions reached at a confer-

ence in my office on December 15, 1941, on concrete construc-

BLURRED COPY

60 UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC.

94 tion at the Elmira Flood Protection Project, Section No. 1,

Contract No. W-321-eng-261.

“Using the same numerical index as used in your letter you

are advised that conclusions reached in the conference were as

follows:

“1. Your right of appeal from my decision on payment for wall

treatment is established in Article 15 of the contract.

“2. Any redesign of concrete mixtures or required changes in

methods of handling concrete not within the scope of specifications

which causes increased cost will be cause for consideration of in-

creased payments to you.

“3. Treatment of walls will be required on the landside of all

walls and on the streamside of walls approximately 100 feet up-

stream and downstream of all bridges, approaches, or other simi-

lar places where relatively close scrutiny is easily attained. In ad-

dition to the above treatment regular patching of tie rod holes,

replacing unsatisfactory spots, repair of honeycombs, etc., will be

required on all surfaces in accordance with specification require-

ments.”

43. On February 9. 1943, the plaintiff filed a protest with the

contracting officer listing five items of claim but not including the

claim for concrete finishing. This was replied to by letter of Feb-

ruary 18, 1943, by the contracting officer, in which the following

statement is made:

“Tn view of the fact that your letter and this reply are repetitions

of previous protests and decisions, and that no progress is ap-

parent in the settlement of this dispute, it is suggested that, in

event you elect to prosecute this matter further, you arrange to

present detailed facts, computations, etc., either by letter or at

a conference in this office.”

On February 24, 1943, the plaintiff forwarded an executed copy

of a release dated February 19, 1943. In this release, the plaintiff

excepted a claim by reason of concrete finishing operations.

“* * * in a manner and to an extent not required by the con-

tract plans and specifications. * * *”

The plaintiff suggested in the letter transmitting the release

that $100 be withheld from payment due it on its final estimate.

In this letter the plaintiff also discussed the concrete finishing

claim and protested the sums allowed for the concrete items

95 in the final estimate and requested an opportunity to submit

detailed data as to the cost of performing this “additional”

work.

44, The contracting officer on March 5, 1943, sent the following

letter to plaintiff:

“Receipt is acknowledged of your letter dated February 2,

1943, transmitting executed copies of standard release form for

BLEED THROUGH— POOR COPY

—_

UNITED STATES VS. BINGHAMTON CONSTRUCTION CO., INC. 61

Contract No. W-321-eng-261, and an application for reconsider-

ation of a previous appeal, addressed to the Chief of Engineers,

relative to minimum wage rate.

“Reference is made to the exception

This text is long and has been trimmed here. Open the source document for the complete record.