Petition for Writ of Certiorari — Mission Insurance v. United States

Supreme Court brief1983

Ask Donna

What actually matters in this document.

Text

Rupreme Court, U8

FILED

92-1517 | MAR 16 1933

No. 7 | 9

OFFICE OF TRE CLERS

— ee eee

IN THE

Siygreuw Curt of the United States

OCTOBER TERM, 1992

W. M. SCHLOSSER COMPANY, INC.,

Petitioner,

V.

SCHOOL BOARD OF FAIRFAX COUNTY, VIRGINIA,

Respondent.

Petition for a Writ of Certiorari to the

United States Court of Appeals

for the Fourth Circuit

PETITION FOR WRIT OF CERTIORARI

HERMAN M. BRAUDE

Counsel of Record

ROGER C. JONES

BRAUDE & MARGULIES, P.C.

1025 Connecticut Ave., N.W.

Suite 200

Washington, D.C. 20036

(202) 293-2993

Counsel for Petitioner

WILSON - EPES PRINTING Co., INC. - 789-0096 - WASHINGTON, D.C. 20001

QUESTION PRESENTED

Whether the Federal Arbitration Act preempts a state

rule of statutory construction, which precludes enforce-

ment of a contract arbitration provision, where the state

has statutorily conveyed the power to contract but is

silent on the power to agree to an arbitration provision

within a contract?

(i)

TABLE OF CONTENTS

QUESTION PRESENTED

TABLE OF AUTHORITIES

OPINIONS BELOW

JURISDICTION

CONSTITUTIONAL AND STATUTORY PROVI-

SIONS INVOLVED .

STATEMENT OF THE CASE

A. Statement of Facts .

B. The Proceedings Below ..........

REASONS FOR GRANTING THE WRIT

I. VIRGINIA CANNOT NULLIFY THE EF-

FECT OF THE FEDERAL ARBITRATION

ACT ON SCHOOL BOARDS WHERE IT

STATUTORILY CONVEYS THE POWER TO

CONTRACT BUT IS SILENT ON THE

POWER TO AGREE TO A CONTRACT AR-

BITRATION PROVISION

Il. THE RULE OF LAW CREATED BY THE

FOURTH CIRCUIT’S APPLICATION OF

THE DILLON RULE IN THIS CASE DI-

RECTLY CONFLICTS WITH SECTION 2 OF

THE FEDERAL ARBITRATION ACT, IN

VIOLATION OF THE SUPREMACY

CLAUSE = eae

CONCLUSION

(iii)

Page

13

18

iv

TABLE OF AUTHORITIES

Cases Page

Boogher v. Stifel, 825 S.W.2d 27 (1992) 15

City of Atlanta v. Brinderson Corp., 799 F.2d 1541

(11th Cir, 1986) oo 11

County of Middlesex v. Gevyn Constr. Corp., 450

F.2d 53 (1st Cir. 1971), cert. denied, County of

Middlesex v. Gevyn Constr. Corp., 405 U.S. 955,

92S. Ct. 1176, 31 L. Ed. 232 (3972) ............ 12

Dean Witter Reynolds, Inc. vy. Byrd, 470 U.S. 2138,

105 S. Ct. 1238, 84 L. Ed. 2d 158 (1985) 10

District of Columbia v. Bailey, 171 U.S. 161, 18

S. Ct. 868 (1897) ixetennas nnn am? 10

Johnson Controls, Inc. v. City of Cedar Rapids,

713 F.2d 370 (8th Cir. ee, 7,16

King County v. Boeing Co., 18 Wash. App. 595, pa

570 P.2d 713 (1977) ae 12

Lindon City v. Engineers Construction Co., 636

P.2d 1070 (Utah eee EI GE 12

Metropolitan Atlanta Rapid Transit Authority,

251 Ga. 15, 303 S.E.2d 1 (1983), vacated, 465

U.S. 1016, 104 S. Ct. 1263, 19 L. Ed. 670, deci-

sion on remand, 253 Ga. 219, 320 S.E.2d 742

a... Seen ene hen) hel bh) eh So a 8

Moses H. Cone Memorial Hosp. v. Mercury Con-

struction Corp., 460 U.S. 1, 103 S. Ct. 927, 74

L. Ed. 2d 765 SEE seal ncetsegaay oe 16

Saturn Distribution Corp., U8. ——, 11]

S. Ct. 516, 112 L. Ed. 2d 527 (1990) 7,14

Southland Corp. v. Keating, 465 U.S. 1, 104 S. Ct.

852, 79 L. Ed. 2d 1 (1984) ............. amin! 7,10, 15,17, 18

W’.M. Schlosser Co., Inc. v. School Board ef Fair-

fax County, Va., 980 F.2d 253 (4th Cir. 1992) ___ 1,7

Statutes

9U.S.C.Sectionl] eeeuh coceeuuaccatae toes 2

9U.S.C. Section2. enc slbsmatsnaeedatketbehaale: 3,6, 13, 14

9U.S.C.Section4.. eee iesetinmauee tes 2

Vv

TABLE OF AUTHORITIES—Continued

9 U.S.C. Section 15

28 U.S.C. Section 1254

28 U.S.C. Section 1291 .

28 U.S.C. Section 1332

Va. Code Section 22.1-71

Sup. Ct. R. 13.1

Sup. Ct. R. 13.4

IN THE

Supreme Comet of the United States

OCTOBER TERM, 1992

No.

W. M. SCHLOSSER COMPANY, INC.,

. Petitioner,

SCHOOL BOARD OF F'AIRFAX COUNTY, VIRGINIA,

Respondent.

Petition for a Writ of Certiorari to the

United St. es Court of Appeals

for the Fourth Circuit

PETITION FOR WRIT OF CERTIORARI

Petitioner respectfully prays that writ of certiorari

issue to review the judgment and opinion of the United

States Court of Appeals for the Fourth Circuit, in the

case captioned W.M. Schlosser Co., Inc. v. School Board of

Fairfax County, Va., 980 F.2d 253 (4th Cir. 1992).

OPINIONS BELOW

The opinion of the Court of Appeals for the Fourth

Circuit is reported at 980 F.2d 253, and is reprinted in

the Appendix hereto, pp. la-13a.

The Order of the United States District Court for the

Eastern District of Virginia (Hilton, J.) denying Peti-

tioner’s Petition to Compel Arbitration and the transcript

for the petition hearing are reprinted in the Appendix

hereto, pp. 16a, 17a-26a.

2

The initial decision and Order of the magistrate judge

of the United States District Court for the Eastern Dis-

trict of Virginia, denying Petitioner’s Petition to Compel

Arbitration and the transcript for the petition hearing

are also reprinted in the Appendix hereto, pp. 27a,

28a-32a.

. JURISDICTION

Invoking federal diversity jurisdiction under 28 U.S.C.

Section 1332, Petitioner filed a Petition to Compel Arbi-

tration in the United States Distriet Court for the East-

ern District of Virginia, pursuant to 9 U.S.C. Section 4,

The dispute between the parties is the subject of a writ-

ten arbitration agreement, which is governed by the

Federal Arbitration Act, 9 U.S.C. Section 1 et seq. By

Order dated December 13, 1991, the district court af-

firmed the decision of the magistrate judge, which denied

Petitioner’s Petition to Compel Arbitration.

This decision was appealed to the United States Court

of Appeals for the Fourth Circuit, pursuant to the pro-

visions of 28 U.S.C. Section 1291 and 9 U.S.C. Section 15.

The court of appeals affirmed the decision of the district

court by decision dated November 18, 1992. On Decem-

ber 16, 1992, the court of appeals denied Petitioner’s

Petition for Rehearing and Suggestion for Rehearing En

Bane and, by Mandate of the court, the November 18,

1992 judgment took effect as of December 23, 1992.

The jurisdiction of this Court to review the judgment

of the Fourth Circuit Court of Appeals is invoked under

28 U.S.C. Section 1254(1). This Petition is being dock-

eted within 90 days from the entry of the order denying

Petitioner’s petition for rehearing and the date by which

the judgment of the court of appeals took effect, in

accordance with Supreme Court Rules 13.1 and 13.4.

3

CONSTITUTIONAL AND STATUTORY

PROVISIONS INVOLVED

U.S. Constitution, Article 4, Clause 2:

This Constitution and the laws of the United States

. shall be the supreme law of the land....

9 U.S.C Section 2. Validity, irrevocability, and en-

forcement of agreements to arbitrate

A written provision in any maritime transaction or

a contract evidencing a transaction involving com-

merce to settle by arbitration a controversy there-

after arising out of such contract or transaction, or

the refusal to perform the whole or any part thereof,

or an agreement in writing to submit to arbitration

an existing controversy arising out of such a con-

tract, transaction, or refusal, shall be valid, irrevoca-

ble, and enforceable, save upon such grounds as exist

at law or in equity for the revocation of any contract.

Virginia Code, Section 22.1-71. School board consti-

tutes body corporate; corporate powers.—The duly

appointed members shal! constitute the school board.

Every such school board is declared a body corporate

and, in its corporate capacity, is vested with all

the powers and charged with all the duties, obliga-

tions and responsbilities imposed upon school boards

by law and may sue, be sued, contract, be contracted

with and, in accordance with the provisions of this

title, purchase, take, hold, lease and convey school

property, both real and personal. School board mem-

bers appointed by district or otherwise shall have no

organization or duties except such as may be assigned

to them by the school board as a whole.

STATEMENT OF THE CASE

This appeal arises from a decision of the United States

Court of Appeals for the Fourth Circuit affirming the

district court’s denial of a Petition to Compel Arbitra-

tion, which was filed pursuant to the Federal Arbitration

Act (“FAA”). The appeal raises a significant policy

———

4

issue under the FAA and the U.S. Constitution Suprem-

acy Clause concerning preemption of a state rule of

statutory construction (7.e., the “Dillon Rule’) that was

held to preclude enforcement of a contract arbitration

provision, despite the decisions of numerous other state

supreme courts and federal circuit courts which have held

to the contrary when confronted with issues similar in

nature.

A. Statement of Facts

In June 1988, Petitioner, W. M. Schlosser Company,

Inc. (“Schlosser”), entered into a contract (“Contract’’)

with Respondent, the School Board of Fairfax County,

Virginia (“School Board” and/or “Owner’’) for the per-

formance of certain construction renovation work relat-

ing to the Falls Church High School (the “Project”).

(Appendix p. 37a). The Contract, which was written by

the School Board, consists of a number of documents in-

cluding the American Institute of Architects (“AIA”)

Standard Form of Agreement Between Owner and Con-

tractor, ALA Document A101, January 1974 Ed.; General

Conditions of the Contract for Construction, AIA Docu-

ment A201, April 1970 Ed. (“General Conditions”) ; and

Supplementary Conditions. These Contract documents are

reprinted in the Appendix at pp. 37a-133a.

With respect to the arbitration provision in question,

Articles 2.2.7 and 2.2.10 of the Contract General Condi-

tions specifically provide:

2.2.7 Claims, disputes and other matters in question

between the Contractor and the Owner relating to the

execution or progress of the Work or the interpreta-

tion of the Contract documents shall be referred

initially to the Architect for decision which he will

render in writing within a reasonable time.

» * * s

2.2.10 Any claim, dispute or other matter that has

been referred to the Architect ... shall be subject to

5

arbitration upon the written demand of either party.

However, no demand for arbitration of any such

claim, dispute or other matter may be made until

the earlier of:

9210.1 The date on which the Architect has

rendered his written decision, or

2 The 10th day after the parties have

presented their evidence to the Archi-

tect or have been given a reasonable

opportunity to do so, if the Architect

has not rendered his decision by that

date.

(Emphasis added) (Appendix pp. 54a-55a).

During the course of the Contract, Schlosser’s perform-

ance was hindered, disrupted, impacted and delayed due

to the actions, inactions and active interference of the

Owner. As a result, Schlosser’s Contract performance

was extended 209 calendar days and Schlosser suffered

significant additional costs and damages. (Appendix

p. 35a).

On August 3, 1990, Schlosser submitted to the Owner

a claim for its additional costs and damages, in the total

amount of $1,152,941.00. Since the claim related to the

“execution or progress of the work,” Schlosser also sub-

mitted a copy of the claim to the architect for his deci-

sion, consistent with Article 2.2.7 of the General Condi-

tions. (Appendix p. 35a).

Schlosser then waited a reasonable time for the archi-

tect to issue a decision. In accordance with Article 2.2.10

of the General Conditions, when the architect failed to

render a decision on Schlosser’s claim, Schlosser submitted

to the Owner a written demand for arbitration. (Ap-

pendix pp. 35a-36a, 136a).

The Owner failed to respond to Schlosser’s demand for

arbitration. (Appendix p. 36a). Therefore, Schlosser

filed a Petition to Compel Arbitration in the U.S. District

Court for the Eastern District of Virginia, invoking the

6

court’s diversity of citizenship jurisdiction pursuant to

28 U.S.C. Section 1332. (Appendix pp. 38a, 34a).

B. The Proceedings Below

A hearing on Schlosser’s Petition to Compel Arbitra-

tion was held before Magistrate Judge Brinkema. (Ap-

pendix pp. 28a-32a). In denying Schlosser’s petition, the

Magistrate concluded that Virginia law does not empower

school boards to enter into arbitration agreements with

respect to construction contract claims, notwithstanding

their power to contract. (Appendix p. 32a). The court

also concluded that Schlosser’s claim was not subject to

an arbitration agreement. (Appendix p. 3la).

Schlosser appealed the Magistrate’s ruling to a district

court judge and a hearing before the Honorable Claude

M. Hilton was conducted on December 13, 1991. Judge

Hilton also found that, despite their power to contract,

school boards in Virginia do not have authority to agree

to arbitrate and that, in any event, the arbitration clause

had been removed from the Contract. (Appendix p. 26a).

Based on these erroneous findings, Judge Hilton affirmed

the Magistrate’s prior decision. (Appendix p. 16a).

Schlosser appealed the district court’s decision to the

United States Court of Appeals for the Fourth Circuit.

On November 18, 1992, the court of appeals issued the

opinion of Judges Luttig, Phillips and Niemeyer. The

court declined to rule on the issue of whether the Con-

tract contained an arbitration clause. Instead, the court

held:

(1) Based on the “Dillon Rule” of strict construction,

Virginia school boards do not possess the power to

agree to arbitrate contract disputes and that such

power cannot be implied from the school board’s

power to contract; and

(2) The “Dillon Rule” is not preempted by the Fed-

eral Arbitration Act since it falls within the excep-

tion of 9 U.S.C. Section 2 as, “a rule of general ap-

7

plicability that defines and invalidates all ultra vires

acts of local governing bodies.”

W.M. Schlosser Co., Inc. v. School Board of Fairfax

County, Va., 980 F.2d 253, 256, 257, 259 (4th Cir. 1992}.

(Appendix pp. la, 7a, 8a, 12a-13a).

On December 1, 1992, Schlosser filed a Petition for

Rehearing and Suggestion for Rehearing En Banc. By

Order dated December 16, 1992, the court of appeals

denied this petition, without opinion. (Appendix p. 14a).

Thereafter, by Mandate issued December 23, 1992, the

November 18, 1992 judgment of the court of appeals took

effect as of December 23, 1992. (Appendix p. 15a).

REASONS FOR GRANTING THE WRIT

The Fourth Circuit’s decision creates a rule of law that

directly conflicts with the federal substantive law created

by the FAA, standing as an obstacle to the accomplish-

ment and execution of the full purposes and objectives

of Congress in implementing the FAA. Pursuant to this

rule of law, arbitration provisions in contracts with Vir-

ginia school boards are rendered completely unenforce-

able, even where the arbitration provision is governed by

the FAA. Petitioner respectfully submits this outcome is

in direct conflict with and ignores the Court’s decision in

Southland Corp. v. Keating, 465 U.S. 1, 104 S. Ct. 852,

79 L. Ed. 2d 1 (1984), as well as the Fourth Circuit’s

own opinion in Saturn Distribution Corp. v. Williams,

905 F.2d 719 (4th Cir. 1990), cert. denied, Williams v.

Saturn Distribution Corp., —— U.S. , 111 S. Ct.

516. 112 L. Ed. 2d 527 (1990) and the opinion of the

Eighth Circuit in Johnson Controls, Inc. v. City of Cedar

Rapids, 718 F.2d 370 (8th Cir. 1983).

As recognized in Southland Corp., by “enacting [sec-

tion] 2 of the federal | Arbitration] Act, Congress declared

a national policy favoring arbitration and withdrew the

power of the states to require a judicial forum for the

resolution of claims which the contracting parties agreed

8

to resolve by arbitration.” 465 U.S. at 10. In doing so,

this Court noted that, “Congress has thus mandated the

enforcement of arbitration agreements” and that “con-

tracts to arbitrate are not to be avoided by allowing one

party to ignore the contract and resort to the courts.”

465 U.S. at 7 and 10.

The Court also noted that there are only two limita-

tions on the enforceability of arbitration provisions gov-

erned by the FAA. First, such provisions must be in

writing and part of a contract, “evidencing a transaction

involving commerce”; and second, such clauses may be

revoked only upon “grounds as exist at law or in equity

for the revocation of any contract.” 465 U.S. at 10-1]

and 16, n.11. [Emphasis added]. There is nothing else

in the Act to indicate the “broad principle of enforce-

ability is subject to any additional limitations under state

law.” 465 U.S. at 11. Further, where state law directly

conflicts with Section 2 of the Federal Arbitration Act, it

violates the Supremacy Clause of the U.S. Constitution.

465 U.S. at 10.

The instant case raises a preemption issue similar to

that raised in Southland Corp.’ Although it does not

' The instant case is also similar to the unsettled questions of law

raised in Local Division 732, Amalgamated Transit Union v. Metro-

politan Atlanta Rapid Transit Authority, 251 Ga. 15, 303 S.E.2d 1

(1983), vacated, 465 U.S. 1016, 104 S. Ct. 1263, 79 L. Ed. 670,

decision on remand, 253 Ga. 219, 320 S.E.2d 742 (1984). In Local

Division 732, the Metropolitan Atlanta Rapid Transit Authority

(“MARTA”) withdrew from binding interest arbitration with the

Union contending that under Georgia law arbitration agreements

were revocable at will. The Georgia Supreme Court agreed. 251

Ga. at 18-19, 303 S.E.2d at 4.

The U.S. Supreme Court held its ruling on the Union’s petition

for certiorari until it ruled in Southland Corp. It then vacated the

Georgia Supreme Court’s decision and remanded for reconsidera-

tion. 104 S. Ct. 1263. Despite this Court’s ruling, the Georgia Su-

preme Court reentered its earlier judgment, ruling that “MARTA’s

consent to arbitrate the terms and conditions of a new collective

bargaining agreement was an unlawful delegation of legislative

9

involve a statute, as was the case in Southland Corp.,

the Fourth Circuit’s application of a common law rule of

strict statutory construction, results in direct conflict

with Section 2 of the Federal Arbitration Act, precluding

enforcement of the arbitration clause contained in the

parties’ contract.

I. VIRGINIA CANNOT NULLIFY THE EFFECT OF

THE FEDERAL ARBITRATION ACT ON SCHOOL

BOARDS WHERE IT STATUTORILY CONVEYS

THE POWER TO CONTRACT BUT IS SILENT ON

THE POWER TO AGREE TO A CONTRACT ARBI-

TRATION PROVISION

Virginia Code Section 22.1-71 defines the general pow-

ers and duties of school boards, as follows:

Every such school board is declared a body corporate

and, in its corporate capacity, is vested with all the

authority” because it exceeded MARTA’s statutory authority. 253

Ga. at 222, 320 S.E.2d at 745. In doing so, the Georgia Supreme

Court believed that the state’s restriction on public body arbitra-

tion agreements fell within the exception in Section 2 of the FAA

for defenses “applicable to all other contracts.” 253 Ga. at 223, 320

S.E.2d at 745.

Much like the Fourth Circuit reasoned in the instant case, the

Georgia Supreme Court reasoned that absent an express grant of

statutory authority to agree to arbitration provisions, despite the

existence of the statutory power to contract, the arbitration provi-

sion within the agreement was unenforceable because it constituted

an unlawful delegation of authority, which was a general contract

defense under the “savings clause” in Section 2 of the FAA. Before

this controversy between the Georgia Supreme Court and the U.S.

Supreme Court could ultimately be resolved, the parties settled their

case.

Unquestionably, the lack of explicit authority to agree to arbitra-

tion (despite the authority to contract) is not a ground that exists

at law or in equity “for the revocation of any contract.” 465 U.S.

at 16, n.11. Rather, as in Southland Corp., and as in this case, it is

“merely a ground that exists for revocation of arbitration provisions

in contracts” with Virginia school boards, which is in direct conflict

with and is preempted by the FAA. 465 U.S. at 16, n.11.

10

powers and charged with al] the duties, obligations

and responsibilities imposed upon school boards by

law and may sue, be sued, contract, be contracted

With, «

The plain language of this statute gives to school boards

the power to contract. in a corporate capacity as well as

the power to sue and be sued. This power implicitly in-

cludes the power to “gree to arbitration provisions within

such contracts. The Fourth Cireuit’s decision to the con-

trary, based on erroneous application of the “Dillon Rule”

of strict Statutory construction, is illogical and ignores

the fact that the purpose of the Federal Arbitration Act

is to place arbitration agreements “upon the same fvot-

ing as other contracts, where | they | belong.” Dean

Witter Re ynolds, Ine. v. Byrd, 470 US. 213, 219, 105

S. Ct. 1238, 84 L. Ed. 24 158 (2985) (citing: H.R. Rep.

No. 96, 68th Cong. Ist Sess. 1 (1984) '. See also, South-

land Corp. v, Keating, 465 U.S. , 17 0h) continued, 104

S. Ct. 852, 79 L. Ed. 2d 1 (1984).

The issue of whether the power to arbitrate contract

disputes may be implied from the power to contract

‘granted to quasi public corporations, such as Virginia

school boards) was decided almost 100 years ago by this

Court in District of Columbia v. Bailey, 171 U.S. 161, 18

S. Ct. 868 (1897). The sailey Court squarely addressed

application of the “Dillon Rule” on this issue, stating:

50, also, the power of a municipal corporation to

arbitrate arises from its authority to liquidate and

settle claims, and the rule on this subject is thus

stated by Dillon (Mun. Corp. 4th ed. sec. 478) -

‘As a general proposition, municipal corporations

have, unless specially restricted, the same powers to

liquidate claims and indebtedness that natural per-

sons have, and from that source proceeds power to

adjust all disputed claims, and when the amount is

ascertained to pay the same as other indebtedness.

It would seem to follow therefrom that a municipal

corporation, unless disabled by positive law, could

1]

submit to arbitration all unsettled claims with the

same liability to perform the award as would rest

upon a natural person, provided, of course, that such

power be exercised by ordinance or resolution of the

corporate authorities.’ |[Hmphasis added].

171 U.S. at 172.

The Bailey Court then went on to reason:

In the early case of Brady v. Brooklyn, 1 Barb. 584,

589, the power of a municipal corporation to submit

to arbitration was ascribed to the capacity to con-

tract, with a liability to pay, and it was held that

corporations have al] the powers of ordinary parties

aus With respect to their contracts, except when they

are restricted cepressly, or by necessary implication.

In the case of minor public officials or corporations,

such as selectmen and school districts, the power to

arbitrate has been clearly rested upon the existence

of the right to adjust and settle claims of the particu-

lar character which had been submitted to arbitra-

tion. Die ve. Dummerston, 19 Vermont 262; Walnut

v. Rankin, 70 Iowa 65. Indeed, the proposition that

an independent agreement to submit to an award

must depend for its validity upon the existence of

the right to contract is so elementary that further

citation of authority to support it is unnecessary.

i lumphasis added}.

171 U.S. at 172.

Citing Bailey, the Eleventh Circuit in City of Atlanta

v. Brinderson Corp., T99 F.2d 1541 (11th Cir. 1986),

recognized :

The general rule is that, in the absence of statutory

prohibition, a municipal corporation has the power

to submit both present and future disputes to arbi-

tration. Annot. 20 A.L.R. 30, 569, 572 (1968) Am.

Jur. 2d, Arbitration and Award, Section 68 pp. 659-

571 (1962). Such a power is incident to its capacity

to contract oy make settlements, and its power to sue

and be sued. See, generally, McQuillin, 17 Mun, Cor.

12

Section 48.20 (3rd Ed.); City of Hartford v. Amen-

can Arbitrators Ass’n., 174 Conn. 472, 391 A.2d 187

(1978); E.E. Trip Excavating Contractor, Ine. v.

The County of Jackson, Michigan, 60 Mich. App. 221,

230 N.W.2d 556 (1975). | Emphasis added].

799 F.2d at 1543."

Based on this sound reasoning, the Brinderson court

held that with respect to the City of Atlanta:

| Their] power to arbitrate is ascribed to the capacity

to contract. Accordingly, the City has the incident

and necessarily implied power to arbitrate.

799 F.2d at 1543. See also, County of Middlesex ».

Gevyn Constr. Corp., 450 F.2d 58, 55 (1st Cir. 1971),

cert. denied, County of Middlesex v. Gevyn Constr. Corp.,

405 U.S. 955, 92 S. Ct. 1176, 31 L. Ed. 232 (1972)

(county recognized to have implied power to arbitrate

contract claims based on its power to contract).*

2The Supreme Court of Utah reached the same conclusion in

Lindon City v. Engineers Construction Co., 636 P.2d 1070, 1074

(Utah 1981). Citing the Supreme Court of Washington in King

County v. Boeing Co., 18 Wash. App. 595, 570 P.2d 713, 717 (1977),

the Lindon court acknowledged that:

Arbitration is a contractual remedy for the settlement of dis-

putes by extrajudicial means. It is a remedy freely bargained

for by the parties, and ‘provides a means of giving effect to the

intention of the parties, easing court congestion, and providing

a method more expeditious and less expensive for the resolution

of disputes.’ There is a strong public policy in favor of such

remedy. ...

The Lindon court further reasoned that:

There appears to be no ‘public policy’ or other good reason why

persons effectively and by contract, should not be able to agree

to an out-of-court settlement.

7 * * ”

The trend toward such inter se agreements without resort to

litigation, reflects a good, practical way to resolve disputes.

636 P.2d at 1073.

3’ Numerous state supreme courts have also concluded that the

power of municipal and/or quasi public corporations to arbitrate

13

The Fourth Circuit’s holding, therefore, on the issue

of whether Virginia school boards have the power to

agree to arbitrate is clearly in error. The Fourth Cir-

cuit’s application of the Dillon Rule defies logic, the Dillon

Rule itself and well established law. It also nullifies the

import and effect of the Federal Arbitration Act, which

attempts to place arbitration agreements on the same

footing as contracts, where they belong. See, Dean Witter

Reynolds, Inc., supra, 470 U.S. at 219.

Il. THE RULE OF LAW CREATED BY THE FOURTH

CIRCUIT'S APPLICATION OF THE DILLON RULE

IN THIS CASE DIRECTLY CONFLICTS WiTH

SECTION 2 OF THE FEDERAL ARBITRATION

ACT, IN VIOLATION OF THE SUPREMACY

CLAUSE

In specifically addressing the preemption issue, the

Fourth Circuit stated that the Dillon Rule, “is a rule of

general applicability that defines and invalidates al] uw/tra

vires acts of local governing bodies.” 980 F.2d at 259

The court concluded, therefore, “as ‘a general rule of

contract formation,’ it constitutes a ‘ground as exist/s

at law or in equity for the revocation of any contract,’

within the meaning of 9 U.S.C. Section 2 {and} as such.

it falls within the exception to Section 2’s general mile

of enforceability of arbitration provisions, and therefore

is not preempted by the FAA {citations omited}.” 980

F.2d at 259.

In reaching this conclusion, the court failed to recog-

nize the distinction between a rule of statutory construe-

tion ‘such as the Dillon Rule: and the result that may

flow from application of the rule. While the Dillon Rule.

by itself, is not subject to preemption, the result flowing

from the court’s misapplication of the Dillon Rule in this

case is subject to preemption. Essentially, the Court’s

is implied from their power to contract, sue and be sued. See,

generally, Annotation, 20 A.L.R. 3d 569. Power of Municipal Cor-

poration to Submit to Arhitration.

14

reasoning process in this case creates a rule of law that

goes solely to the arbitration provision in the School

Board’s contract and not to contracts, generically, as con-

templated by 9 U.S.C. Section 2. Further the preemption

issue created by the end result stemming from this rule

of law cannot be avoided by the court merely saying the

Dillon Rule is simply a “rule of general applicability.”

The Fourth Circuit’s decision in this case is also com-

pletely inconsistent with their decision in Saturn Distribu-

tion Corp. v. Williams, 905 F.2d 917 (4th Cir. 1990),

cert. denied, Williams v. Saturn Distribution Corp.,

US. , 111 S. Ct. 516, 112 L. Ed. 2d 527 (1990).

In Saturn, Judges Chapman and Wilkinson recognized

with respect to 9 U.S.C. Section 2 that, “with few limita-

tions, if a state law singles out arbitration agreements

and limits their enforceability it is preempted.”* As

stated in Saturn:

State laws are subject to preemption not only if they

directly contradict federal law, but also if they stand

‘as an obstacle to the accomplishment and execution

of the full purposes and objectives of Congress.’

(Citation omitted]. The language of the FAA re-

quires that states place no greater restrictions upon

arbitration provisions than they place upon other con-

tractual terms.

. ao . *

The Commissioner argues that the scope of FAA pre-

emption is limited to laws covering existing arbitra-

tion agreements, and does not extend to laws that

prohibit or regulate the formation of arbitration

agreements. We disagree. [Emphasis in original].

905 F.2d at 722-723.

The result flowing from the Fourth Circuit’s misappli-

eation of the Dillon Rule in this case, however, creates

4 The Court proffered as possible exceptions, “fraud or the sort

of overwhelming economic power which can render an agreement

unconscionable.” 905 F.2d at 727.

15

precisely such a rule of law in Virginia as applied to

arbitration provisions in contracts with local school

boards. Under Southland Corp. and Saturn preemption

would only occur, using the Dillon Rule, where a school

board did not have the power to contract and the power

to sue and be sued in the first instance. Then, and only

then, would the Dillon Rule fall within the savings clause

in section 2 of the FAA as a defense applicable to all

contracts.

Even more troubling, however, is the notion that the

Fourth Circuit’s decision will allow the state to do by

silence what it cannot do by statute. For example, if

Virginia Code Section 22.1-71 granted school boards the

power to contract but expressly provided that, “arbitra-

tion provisions to resolve contractual disputes, contained

in such contracts, are unenforceable,” then under South-

land Corp. v. Keating, 465 U.S. 1, 16-17, 104 S. Ct.

852, 79 L. Ed. 2d 1 (1984), such a statute would be

preempted.°

Since, however, Virginia Code Section 22.1-71 is silent

as to arbitration (although it includes the power to con-

tract and to sue and be sued) the Fourth Circuit permits

the Dillon Rule of strict construction to revoke and render

®° The Missouri Court of Appeals recognized this logic in Boogher

v. Stifel, 825 S.W.2d 27, 29 (Mo. 1992). In Boogher, the plaintiff

argued his claims under the Missouri Human Rights Act were not

arbitrable because the Federal Age Discrimination in Employment

Act, did not expressly provide for arbitration. Citing Southland

Corp., the Boogher Court reasoned that, “a state law which at-

tempts to preclude enforcement of an arbitration agreement in a

contract involving interstate commerce would be in conflict with the

FAA and, therefore, in violation of the supremacy clause.” 825

S.W.2d at 29. Thus, the Boogher, Court concluded:

Plaintiff’s argument is flawed because the Missouri Legislature

could not enact a provision of the MHRA which precludes arbi-

tration without violating the supremacy clause. Under the

FAA, plaintiff’s age discrimination suit brought under the

MHRA is subject to compulsory arbitration pursuant to his

agreement.

825 S.W.2d at 29.

16

unenforceable the arbitration clause contained in the par-

ties’ contract. This result is not only illogical but it

allows contravention of the Federal Arbitration Act de-

spite the fact that the Act constitutes, “a congressional

declaration of a liberal federal policy favoring arbitra-

tion agreements, notwithstanding any state substantive or

procedural policies to the contrary.” Moses H. Cone

Memorial Hosp. v. Mercury Construction Corp., 460 U.S.

1, 24, 103 S. Ct. 927, 941, 74 L. Ed. 2d 765 (1983). See

also, Southland Corp., supra, 465 U.S. at 16 (“In creat-

ing a substantive rule applicable in state as well as fed-

eral courts congress intended to foreclose state... at-

tempts to undercut the enforceability of arbitration

agreements”).

When confronted with a similar situation, the Eighth

Circuit Court of Appeals in Johnson Controls, Inc. v. City

of Cedar Rapids, lowa, 713 F.2d 370, 376 (8th Cir.

1983) rejected contravention of the Federal Arbitration

Act, applying federal substantive law over state law.

In Johnson Controls the city’s contentions, which are not

unlike the School Board’s contentions in this case, were

rejected by the court:

The city claims that at the time this contract was

entered into, lowa law rendered executory arbitra-

tion agreements generally unenforceable. [Citations

omitted]. Iowa law also provides that municipalities

are without power to make contracts that are incon-

sistent with state law. [Citations omitted]. Thus,

the city asserts that if the contract is construed as

providing for mandatory arbitration, the contract

would be ultra vires and void under Iowa law.

e ” * *

The city’s argument is misplaced. The arbitration

act was specifically enacted to reverse antiquated

state rules of law that make arbitration agreements

revocable at will any time prior to the issuance of

the arbitration award. {Citations omitted} Because

federal substantive law preempts state laws govern-

17

ing the enforceability of arbitration agreements in

interstate contracts, the present contract is not unen-

forceable under applicable federal law. Hence, con-

struing the contract as providing for mandatory

arbitration would not be against controlling federal

public policy. To the contrary, federal policy favors

arbitration in interstate contracts.

713 F.2d at 376.

Pursuant to this Eighth Circuit decision, a state law

relating to contract formation which would render an

arbitration provision ultra vires and void (as the court

construed the Dillon Rule in this case) is preempted by

federal substantive law created by the Federal Arbitra-

tion Act. Further, as recognized in Johnson Comtrols,

even if a state law prohibits a municipal corporation

from entering into an arbitration agreement, the Federal

Arbitration Act displaces the state’s power over the activi-

ties of two parties in interstate commerce. 713 F.2d at

381. Based on this reasoning, the Fourth Circuit’s deci-

sion in the instant case results in inconsistency with the

Kighth Circuit’s decision in Johnson Controls.

Although predating the U.S. Supreme Court’s decision

in Southland Corp. v. Keating, 465 U.S. 1, 104 S. Ct.

852, 79 L. Ed. 2d 1 (1984) (1984), the court’s rationale

in Johnson Controls accords completely with the court’s

decision in Svuthland Corp. As recognized by the South-

land Corp. Court, in enacting Section 2 of the Federal

Arbitration Act, Congress declared a national poliey

favoring arbitration and withdrew the power of the states

to require a judicial forum for the resolution of claims

that the contracting parties agreed to resolve by arbitra-

tion. 465 U.S. at 12-13. Certainly, the Fourth Cireuit’s

application of the Dillon Rule in the instant case to re-

quire a judicial forum notwithstanding the arbitration

clause contained in the parties’ contract is contrary to not

only the purpose and intent of the Federal Arbitration

Act but also the law as stated by the United States

Supreme Court.

18

CONCLUSION

The Fourth Cireuit’s decision in this case not only

ignores this Court’s holding in Southland Corp. v. Keat-

ing, 465 U.S. 1, 104 S. Ct. 852, 79 L. Ed. 2d 1 (1984)

and the Supremacy Clause of the U.S. Constitution, it

also creates precedent which substantially erodes federal

substantive law created by the Federal Arbitration Act.

By allowing a state rule of statutory construction to stand

as a complete obstacle to the enforcement of an arbitra-

tion provision, the Fourth Circuit is permitting states

to accomplish by silence that which they cannot accom-

plish by express statute. Federal substantive law requires

the enforcement of an arbitration provision where, as in

this case, they are part of a contract which involves in-

terstate commerce. To the extent a state rule of statutory

construction precludes enforcement of such an arbitra-

tion provision, then its application violates the Supremacy

Clause of the U.S. Constitution and it is preempted by

the Federal Arbitration Act. In order to avoid inconsist-

ent decisions between the circuits and to provide guidance

for parties invoking the Federal Arbitration Act in state

court proceedings, it is important for this Court to finally

address and resolve the significant issue raised by this

case, which involves conflicting federal substantive law

and state law with respect to the validity and enforce-

ability of a contract arbitration provision.

Respectfully submitted,

HERMAN M. BRAUDE

Counsel of Record

ROGER C. JONES

BRAUDE & MARGULIES, P.C.

1025 Connecticut Ave., N.W.

Suite 200

Washington, D.C. 20086

(202) 293-2993

Counsel for Petitioner

APPENDICES

tas

a aN 2 ll CARMINA is alt OP CR iin tai Sis tie ead tthe i eK, Meson

la

APPENDIX A

UNITED STATES COURT OF APPEALS

FOURTH CIRCUIT

No. 92-1008

W.M. SCHLOSSER COMPANY, INCORPORATED,

Plainti ff-A ppellant,

¥.

SCHOOL BOARD OF FAIRFAX COUNTY, VIRGINIA,

Defendant-A ppellee.

Argued Sept. 29, 1992

Decided Nov. 18, 1992

As Amended Jan. 13, 1993

Herman Martin Braude, Braude & Margulies, P.C.,

Washington, D.C., argued (Roger C. Jones, on brief), for

plaintiff-appellant.

Thomas John Cawley, Hunton & Williams, Fairfax,

Va., argued (Stuart A. Raphael, on brief), for defendant-

appellee.

Before PHILLIPS, NIEMEYER, and LUTTIG, Circuit

Judges.

OPINION

LUTTIG, Circuit Judge:

The W.M. Schlosser Company appeals an order of the

district court denying its motions to compel arbitration

and to appoint an arbitrator to resolve its construction

€ ‘

Za

contract dispute with the School Board of Fairfax County,

Virginia. We conclude that regardless of whether the

School Board agreed to arbitrate the dispute in question,

it lacked the legal authority to arbitrate under the laws

of the Commonwealth of Virginia. We therefore affirm.

I.

The relevant facts necessary to the disposition of this

appeal are not in dispute. On June 10, 1988, the W.M.

Schlosser Company [Schlosser], a Maryland corporation,

entered into a contract with the Fairfax County School

Board {the School Board] for the performance of reno-

vation construction at the Falls Church High School. The

contract comprised a number of documents, the most

important of which were two standard construction forms

prepared by the American Institute of Architects, the

AIA Standard Agreement and the AIA General Condi-

tions, and a set of Supplementary Conditions that in-

cluded extensive modifications to the terms of the AIA

standard forms. J.A. at 5-41.

The AIA General Conditions provide for the arbitra-

tion of claims arising under the contract. Article 2.2.7

of the General Conditions stipulates that all disputes be-

tween contractors and owners must first be referred to

the project architect for an initial decision.’ Id. at 14.

Article 2.2.10 states that “ al|ny claim, dispute or other

matter that has been referred to the Architect . . . shall

be subject to arbitration upon the written demand of

either party.” Jd. Finally, Article 7.10, entitled “ARBI-

TRATION,” provides that all contract disputes shall be

arbitrated in accordance with the Construction Industry

Arbitration Rules of the AIA and outlines the arbitration

process. /d. at 20. In the Supplementary Conditions por-

tion of the contract, Schlosser and the School Board left

‘Under Article 2.2.2 of the General Conditions, the project archi-

tect is the agent and representative of the owner, which in this

case is the School Board. J.A. at 14.

3a

Articles 2.2.7 and 2.2.10 unchanged. Jd. at 27. They

deleted Article 7.10 of the AIA General Conditions, how-

ever, in its entirety. /d. at 302

Prior to completion of the Falls Church High School

project, Schlosser alleged that it had been delayed in the

performance of its contract obligations by the School

Board, and on August 3, 1990, it served the Board with a

claim for damages in the amount of $1,152,941. Schlosser

submitted a copy of the claim to the project architect for

an initial adjudication, pursuant to Article 2.2.7 of the

General Conditions. /d. at 3. Several months later, the

architect granted Schlosser a short extension of the time

within which it was required to complete its work, but

denied Schlosser’s damages claim. /d. at 75-79.

On March 27, 1991, Schlosser presented the Board with

a written demand for arbitration pursuant to Article

2.2.10 of the General Conditions. The following day,

invoking the court’s diversity jurisdiction, Schlosser

moved in the district court to compel arbitration and to

designate and appoint an arbitrator under the terms of

the Federal Arbitration Act |FAA|, 9 U.S.C. £8 1 ef seq.

Schlosser’s petition was referred to a federal magistrate

who, after conducting a hearing, denied both of Schlosser’s

motions on the ground inter alia that the School Board

lacked the authority tv arbitrate under Virginia law and

thus that any attempt by the Board to contract to arbi-

trate was unenforceable. J.A. at 103, 105.

Schlosser appealed the magistrate judge’s decision to

the district court. The district court adopted the magis-

* The director of design and construction services for the school

system stated in his declaration that because “neither the [School

Board} nor any of its agents has the authority to enter into arbitra-

tion agreements,” “it is the custom and standing practice of Fairfax

County Public Schools to climinate standard form arbitration provi-

sions contained in construction contracts.” Hanton Decl., J.A. at 70

* Schlosser initially appealed the magistrate’s decision to this

court. We dismissed the appeal for lack of jurisdiction. W_M.

Schlosser Co. v. Fairfax County Sch. Bd., No. 91-2515 (4th Cir

Aug. 2, 1991).

4a

trate’s recommendations, holding that the Board had no

authority under Virginia law to arbitrate contract dis-

putes. /d. at 125-26. This appeal followed.’

II.

A.

The question before the court is whether the School

Board possesses the authority under the laws of the

Commonwealth of Virginia to agree to arbitrate contrac-

tual disputes, for if it does not, then any such agreement

by the Board is unenforceable as. u/tra vires and the

motion to compel arbitration therefore must. be denied.

See Richmond Ry. Co. », Richmond, Ete., 145 Va. 266,

299, 123 S.E. 888, 898 (1926) (“When the contract is

once declared ultra vires, the fact that it is executed does

not validate it, nor can it be ratified so as to make it the

basis of suit or action, nor does the doctrine of estoppel

apply.” ) ; accord Richard L. Deal & Assocs., Inc. ». Com-

monwealth, 224 Va. 61%, 299 S.K.2d 346 (19%3). The

resolution of this question depends in turn upon applica-

tion of the Dillon Rule, a rule of construction applicable

in Virginia when determining the powers of local govern-

ment: “There can be no question that Virginia long has

followed, and still adheres to, the Dillon Rule of strict

construction concerning the powers of local governing

bodies.” Commonwealth +. County Bd., 217 Va. 558, 232

S.E.2d 30, 40 (1977).

* The district court also held that Schlosser and the Board had

not agreed to arbitrate disputes arising out of their contract. Be-

cause we agree with the district court that the Board lacked the

authority to arbitrate contract disputes, we need not and do not

reach this question of contract interpretation.

5 The Virginia Supreme Court first recognized the Rule—some-

times referred to as Dillon’s Rule —in Winchester y. Redmond, 93

Va. 711, 25 S.E. 1001 (1896). The Rule takes its name from John

F. Dillon, a federal circuit judge, chief justice of the Iowa Supreme

Court, and noted law professor. See infra note 6.

Re

va

According to the Dillon Rule, local governing bodies

such as counties, municipal corporations, and school

boards “possess and can exercise only those powers @x-

pressly granted by the General Assembly, those neces-

sarily or fairly implied therefrom, and those that are

essential and indispensable.” * City of Richmond v. Com-

frere Club, 239 Va. 77, 387 S.E.2d 471, 473 (1990) (cit-

ing cases); County Bd. v. Brown, 229 Va. 341, 329 S.B.2d

46%, 470 (1985); see also School Bd. v. Burley, 225 Va.

316, 37%, 302 S.B.2d 53, 55 (1983) (“A school board may

exercise only the power granted it by the General Assem-

bly.” ; Kellam v. School Bd., 202 Va. 252, 117 S.E.2d 96,

98 (1960) ‘school boards “constitute public quasi cor-

porations that exercise limited powers and functions of a

public nature granted to them expressly or by necessary

implication, and none other’). The Rule is strictly con-

strued and strictly enforced by the Virginia Supreme

Court and the court does not liberally recognize govern-

mental powers by implication. See Brown, 329 S.E.2d

at 472 (power to lease realty cannot be implied from

county’s express power to sell or convey realty); Com-

monwealth v, County Bd., 222 S.E.2d at 44 (power to

bargain collectively cannot be implied from expressly

granted powers of school boards to contract, hire employ-

ees, and set terms of employment). significantly, “{ilf

there is any reasonable doubt whether legislative power

exists, that doubt must be resolved against the loca] gov-

erning body.” Confrere Club, 387 S.E.2d at 473 ‘em-

® See Winchester, 93 Va. at 714, 25 S.E. at 1002 (quoting 1 Dillon

on Mun. Corp. § 89 (3d ed.))-

a municipal corporation possesses and ean exercise the follow-

ing powers, and no others: First, those granted in eXPress

words ; Second, those necessarily or fairly implied in or incident

to the powers expressly granted: Third, those essential to the

declared objects and purposes of the corporation, not simply

convenient, but indispensable. Any fair, reasonable doubt con-

cerning the existence of power is resolved by the courts against

the corporation, and the power is denied.

Oa

phases added); accord Stallings v. Wall, 235 Va. 313,

316, 367 S.E.2d 496, 497 (1988).

B.

Schlosser and the School Board agree that the state

constitution does not expressly confer the power to arbi-

trate on Virginia school boards. Both parties also appear

to agree that such a power cannot be considered ‘‘essen-

tial” or “indispensable” to the functioning of school

boards. Therefore, if the power to agree to arbitrate is

not expressly granted by statute or cannot be implied

from a power explicitly conferred on school boards by the

General Assembly, it does not exist.

Schlosser contends that the authority to agree to arbi-

trate is conferred in section 22.1-71 of the Virginia Code.

That statute, which lists the corporate powers of the Com-

monwealth’s school boards, provides that every

school board is . . . vested with all the powers and

charged with all the duties, obligations and responsi-

bilities imposed upon school boards by law and may

sue, be sued, contract, be contracted with and, in ac-

cordance with the provisions of this title, purchase,

take, hold, lease and convey school property. . . .

Va.Code Ann. § 22.1-71 (Michie 1985) (emphasis added).

Schlosser asserts that because the School Board has the

“capacity to centract, [it] .. . clearly has the power to

enter into construction contracts containing arbitration

provisions for the resolution of claims relating to the con-

tract.” Appellant’s Br. at 10-11.7

It is not entirely clear whether Schlosser contends that

the grant of the power to contract in section 22.1-71 is an

express conferral of the power to agree to arbitrate or

7 Alternatively, Schlosser contends that the authority to arbitrate

may be implied from that portion of section 22.1-71 that grants

school boards the power to sue and be sued. Appellant’s Br. at 13,

16. See infra note 10.

~ et

Ta

whether it contends that the power to arbitrate is implied

in the power to contract. While neither contention is

without force, ultimately each fails. Both the Public

Procurement Act, Virginia Code §§ 11-35 et seq., and

section 15.1-508 of the Virginia Code confirm that the

Virginia General Assembly does not consider the grant

of a right to contract as expressly conferring a right to

agree to arbitrate. It is also evident from these statutes,

especially when they are construed strictly as required by

the Dillon Rule, that we are not at liberty to imply such

a right from the School Board’s right to contract.

C.

The Public Procurement Act, which governs the pro-

curement of goods and services by counties, cities, towns,

and school divisions from nongovernmental sources, sets

forth procedures for resolving contract disputes between

public entities and private contractors. Section 11-69 of

the Act requires in relevant part that “[{e]ach public

body ... include in its contracts a procedure for consid-

eration of contractual claims,” and mandates that “|t]he

decision of the public body shall be final and conclusive

unless the contractor appeals. . . .” Appeal of the final

decision of the public body is limited to the “finvocation

of] administrative procedures meeting the standards of

$ 11-71, if available, or in the alternative [to] institu-

tlion] [of] legal action |in the appropriate state court!.”

Va.Code Ann. § 11-69 D. (Michie 1985).. Thus, under

section 11-69 D., contract disputes are to be decided by

the public body itself, with appeal available only through

the public body’s administrative appeal procedure, if one

exists, or to the courts. There is no provision for the

dispute to be decided either initially or on appeal by an

* Section 11-71 allows, but does not require, public bodies to

“establish an administrative procedure for hearing . . . appeals from

decisions on disputes arising during the performance of a con-

tract.” Apparently, the School Board has not adopted any such

procedure.

Su

arbitrator. Indeed, the Act would appear to prohibit, by

negative inference, decision by an arbitrator, who by

definition is neither a representative of the publie body

nor a court of law.”

The fact that the General Asssembly does not provide

for arbitration in the very statute in which it prescribes

the methods for public contract dispute resolution, we

believe, is persuasive evidence that the Assembly does not

regard the right to contract as expressly encompassing

the right to agree to arbitrate. If the Assembly believed

that the right to contract expressly subsumed such a

right, arbitration almost certainly would be included in

section 11-69 D. as one means by which contract disputes

could be resolved.

Our conclusion that the Genera] Assembly does not

consider the right to contract as encompassing such a

right is reinforced by the recent amendment of section

15.1-508 of the Virginia Code to provide expressly that

counties may agree to arbitrate. In 1987, notwithstand-

ing that county officials had Jong been authorized to

contract by section 15.1-105 of the Virginia Code, the

Assembly amended section 15.1-508 to include the foliow-

ing express right to agree to arbitrate: “The governing

body of a county may enter into a written agreement to

submit any existing controversy to arbitration and may

* Schlosser argues that the arbitration provision assertedly em-

bodied in its contract with the School Board satisfies the require-

ment in section 11-69 B. that “each public body shall include in its

contracts a procedure for consideration of contractual claims.” Ses

Appellant’s Br. at 14-15. We disagree. Section 11-69 B. clearly

contemplates that the initial decision of any dispute will be ren-

dered by the public body. See section 11-69 D. (“The decision of

the public body shall be final and conclusive unless the contractor

appeals... .”) (emphasis added). This requirement would appear

to be satisfied, however, by the procedure outlined in Article 2.2.7

of the General Conditions, which pie vides that contract disputes are

to be submitted initially to the project architect, given that the

architect is the School Board’s agent.

4

Qu

erecule a contract which contains a provision to submit

lo arhitration any controversy thereafter arising.” 1987

Va. acts ¢. 483 (emphasis added). This amendment obvi-

ously would have been unnecessary if the legislature

believed that the power to contract conferred in section

15.1-105 expressly included the power to arbitrate.

Finally, our conclusion that the power to contract dos

not by definition include the power to agree to arbitrate

is consistent with decisions of the highest court in Vir-

ginia to have considered the question. See Hanover

County Sch. Bd. v. Gould, (Hanover Cty.Cir.Ct. C-23-

1984, Apr. 4, 1984) ‘holding, on state constitutional]

grounds, that school boards Jack authority to arbitrate) ;

‘f. Spotsylvania County Sch. Bd. v. Sherman Constr.

Corp., 14 Va.Cir. 333 (1989) ‘implicitly assuming that

right to agree to arbitrate not expressly conferred in

right to contract) ; Spotsylvania County Sch. Bd. v. RE.

Lee & Son, Inc., 5 Va.Cir. 48 (1962) (same). But ef.

McKennie v. Charlottesville & Albemarle Ry., 110 Va. 70.

78, 65 S.E. 503 (1909) (municipality’s power to settle

and compromise claims is “a necessary incident to it

right to contract and to sue and be sued’).

Together, the Public Procurement Act, the amendment

to section 15.1-508, and the Virginia authority cited, are

convineing evidence that school boards have not been ex-

pressly accorded the power to arbitrate through the power

to contract in section 22.1-71.

D.

Whether

the power to contract is another question, but one which

—

he power to arbitrate may be implied from

we also believe must be answered in the negative. The

Virginia Supreme Court has consistently rejected elsims

to implied power, absent compelling evidence that the

General Assembly intended that such power be implicit in

power enumerated. See Commonicvcalth v». County Bd.

a

232 S.h.2d at 42 (“In questions of implied power. the

10a

answer is to be found in legislative intent. To imply a

particular power from a power expressly granted, it must

be found that the legislature intended that the grant of

the express also would confer the implied.” (emphasis

added) ).

Schlosser has offered no evidence that the General As-

sembly intended for school boards to have the right to

arbitrate, much less that it intended for such a right to

be implied from the right to contract. Indeed, we believe

that the legislature’s amendment of section 15.1-508 to

confer expressly upon counties the power to agree to

arbitrate disputes, without a corresponding amendment

to section 22.1-71 to accord school boards the same power,

“demonstrates a clear legislative intent to withhold from”

school boards such power.'® See Brown, 329 S.E.2d at

472 ‘inferring legislative intent to withhold from coun-

ties the power to lease government property from fact

that municipal corporations, but not counties, had been

granted a general power to lease property) ; Common-

wealth v. County Bd., 282 S.E.2d at 42-44 (power to

bargain collectively would not be implied from school

boards’ express powers to contract, hire employees, and

set the terms of their employment where legislature had

selectively enacted legislation authorizing collective bar-

gaining but had consistently rejected general authorizing

legislation).'' This intention is underscored by the fact

' Prior to its amendment in 1987, section 15.1-508 only authorized

counties to sue and be sued. A reasonable inference to be drawn

from the fact that the leyislature amended this statute so as to

expressly permit counties to arbitrate is that the legislature did not

believe that the power to arbitrate could be implied from the power

to sue and be sued. Schlosser’s alternative argument that the

authority to arbitrate may be implied from section 22.1-71’s express

grant to school boards of the power to sue and be sued, see supra

note 7, therefore, also fails.

"Cf, Tabler v. Board of Supervisors, 221 Va. 200, 269 S.E.2d 358

(1980) (county’s claimed power to require a minimum cash refund

value on non-alcoholic beverage containers would not be implied

where General Assembly had repeatedly rejected bills authorizing

lla

that the Public Procurement Act, as discussed supra, it-

self appears to forbid arbitration. See Sherman Constr.

Corp., 14 Va.Cir. at 339 (“[T]he contention that local

school boards possess an implied power to submit con-

struction contract disputes to binding arbitration clashes

with the express provisions of the [Public Procurement |

ae.” 35"

Even if we were not convinced that the Virginia legis-

lature does not intend for school boards to have the right

to arbitrate contractual disputes, we would still hold that

such a right cannot be implied. At the very least, the

amendment to section 15.1-508, the terms of the Public

Procurement Act, and the recited caselaw collectively

raise a reasonable doubt as to whether Virginia school

boards possess the authority to execute contracts contatn-

ing arbitration provisions. The Dillon Rule, as noted, re-

quires that any reasonable doubt over whether a particu-

lar power exists be resolved against its existence,

Accordingly, because the Virginia General Assembly

has not expressly conferred upon school boards the power

to arbitrate, and because such a power cannot, under the

Dillon Rule, be implied from the express power to cone

tract. we hold that the School Board lacked the legal

authority to agree to a binding arbitration provision in

its contract with Schlosser. Any agreement to arbitrate,

therefore, was unenforceable.

HI.

Schlosser, perhaps anticipating our holding, contends

that the Federal Arbitration Act preempts application of

regulation of beverage containers) ; see also Deal, 299 S.E.2d at 347-

49 (Commonwealth could not be bound to arbitration agreement by

its agents absent specific legislation authorizing such agents to

submit disputes to arbitration).

“2 RE. Lee & Son, supra, summarily concluded otherwise, but

without citation to authority and without discussion of the limited

avenues for dispute resolution authorized in the Public Procurement

Act.

12a

the Dillon Rule.’ It argues that any state law, such as

the Dillon Rule, that prohibits enforcement of an arbitra-

tion agreement runs afoul of the FAA because the FAA

“is a congressional declaration of a liberal federal policy

favoring arbitration agreements, notwithstanding any

State substantive or procedural policies to the contrary,”

Moses H, Cone Memorial Hosp. v. Mercury Constr. Corp.,

460 U.S. 1, 24, 103 S.Ct. 927, 941, 74 L.Ed.2d 765

(1983), which requires that federal courts “rigorously

enforce agreements to arbitrate,” Dean Witter Reynolds

Inc. v. Byrd, 470 U.S, 218, 221, 105 S.Ct. 1238, 1243, 84

L.Ed.2d 158 (1985). This argument is unavailing.

The FAA does embody “a national policy favoring

arbitration.” Southland Corp. v. Keating, 465 U.S. 1, 10,

104 8.Ct. 852, 859, 79 L.Ed.2d 1 (1984). This policy is

enunciated broadly in section 2 of the FAA, which pro-

vides in pertinent part that

[a] written provision in... a contract evidencing

a transaction involving commerce to settle by vrbi-

tration a controversy thereafter arising out of such

contract or transaction, ... shall be valid, irrevoca-

ble, and enforceable, save upon such grounds as exist

at law or in equity for the revocation of any contract.

9 U.S.C. § 2 (emphases added). And we have held that

“|tlhe language of [section 2] requires that states place

no greater restrictions upon arbitration provisions than

they place upon other contractual terms,” and that gen-

erally, “if a state law singles out arbitration agreements

and limits their enforceability it is preempted.” Saturn

Distrib, Corp. v. Williams, 905 F.2d 719, 722 (4th Cir.)

(emphasis added; footnote omitted), cert. denied, ——~

U.S. ——-, 111 S.Ct. 516, 112 L.Ed.2d 527 (1990). In

Saturn, for example, we invalidated a provision of the

Virginia Motor Vehicle Dealer Licensing Act which pro-

hibited automobile manufacturers and dealers from enter-

ing into agreements that included mandatory alternative

“This Constitution, and the Laws of the United States... shall

be the supreme Law of the Land...” U.S. Const. Art. VI cl, 2.

’

18a

dispute resolution provisions. We held that the provision

was preempted by the FAA because it “singleid| out

arbitration clauses and unreasonably burden|ed] the abil-

ity to form arbitration agreements.” 905 F.2d at 723.

The Dillon Rule, however, does not single out and dis-

proportionately burden arbitration provisions. It is a

rule of general applicability that defines and invalidates

all ultra vires acts of local governing bodies. Unlike the

provision drawn into question in Saturn, the Rule is not

“an idiosyncratic rule specific to arbitration agreements,”

but is instead “merely an unremarkable part of Vir-

ginia’s general laws of contract formation.” Jd. at 725.

As “a general rule of contract formation,” Supak & Sons

Mfg. Co. v. Pervel Indus., Inc., 593 F.2d 135, 1387 (4th

Cir.1979), it constitutes a “ground|] as exist{s] at law

or in equity for the revocation of any contract,” within

the meaning of 9 U.S.C. § 2. As such, it falls within the

exception to section 2’s general rule of enforceability of

arbitration provisions, and therefore is not preempted by

the FAA. See Perry v. Thomas, 482 U.S. 483, 492 n. 9,

107 S.Ct. 2520, 2527 n. 9, 96 L.Ed.2d 426 (1987) (under

the FAA, “state law, whether of legislative or judicial

origin, is applicable if that law arose to govern issues

concerning the validity, revocability, and enforceability of

contracts generally”) (emphasis in original) ; Supak, 593

F.2d at 137 (“Section 2 [of the FAA] dictates the effect

of a contractually agreed-upon arbitration provision, but

it does not displace state law on the general principles

governing formation of the contract itself.”).

IV.

For the reasons set forth, the appellant’s motions to

compel arbitration and to appoint an arbitrator were

properly denied. The decision of the district court is

therefore affirmed.

AFFIRMED,

l4a

APPENDIX B

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

No. 92-1008

W. M. SCHLOSSER COMPANY, INCORPORATED,

Plaintiff-A ppellant

zy

Vv.

SCHOOL BOARD OF FAIRFAX COUNTY, VIRGINIA,

Defendant-A ppellee

| Filed December 16, 1992]

On Petition for Rehearing with Suggestion

for Rehearing In Banc

Appellant has filed a petition for rehearing with sug-

gestion for rehearing in banc. No member of the Court

requested a poll on the suggestion for rehearing in banc,

and the original judicial panel voted to deny the petition

~ for rehearing.

The Court denies the petition for rehearing with sug-

tion for rehearing in bance.

Entered at the direction of Judge Luttig, with the con-

currence of Judge Phillips and Judge Niemeyer.

For the Court,

s/ Bert M. Montague

Clerk

;

a a

15a

APPENDIX C

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

No. 92-1008

CA-91-4-M

W M SCHLOSSER Co INC

Vv.

SCHOOL BOARD

[Filed December 23, 1992]

MANDATE

The judgment of this Court dated 11/18/92 takes ef-

fect today.

BERT M. MONTAGUE

Clerk

l6a

APPENDIX D

IN THE UNITED STATES DISTRICT COURT

FOR THE EASTERN DISTRICT OF VIRGINIA

ALEXANDRIA DIVISION

Civil Action No. 91-0004-M

W. M. SCHLOSSER Co., INC.,

Plaintiff,

v.

THE COUNTY SCHOOL BOARD OF FAIRFAX, VIRGINIA,

Defendant.

ORDER

This matter came before the Court on the plaintiff’s

appeal of the Magistrate Judge’s order of April 5, 1991.

For reasons stated from the bench, it is hereby

ORDERED that the decision of the Magistrate Judge

is AFFIRMED.

s/ Claude M. Hilton

United States District Judge

Alexandria, Virginia

December 13, 1991

17a

APPENDIX E

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF VIRGINIA

ALEXANDRIA DIVISION

C.A. No. 91-4-M

W. M. SCHLOSSER Co., et al.,

-VS-

THE COUNTY SCHOOL BOARD OF FAIRFAX COUNTY,

Defendant.

HEARING ON MOTIONS

December 13, 1991

Before: Claude M. Hilton, Judge

APPEARANCES:

Roger C. Jones, Counsel for the Plaintiff

Thomas J. Cawley, Counsel for the Defendant

[2] THE CLERK: Civil action 91-4-M, William

Schlosser Company, Inc. versus the County School Board

of Fairfax County, of Fairfax, Virginia, I am sorry.

This matter comes on for motions.

Are counsel ready, please?

MR. JONIES: Good morning. Your Honor. My name

is Roger Jones, and I represent the petitioner, William

Schlosser Company.

a

bw

la

After somewhat of a circuitous journey, this matter

comes before you on appeal from Magistrate Brinkema’s

order denying the petition to compel arbitration under

the Federal Arbitration Act. There is really two issues

in this appeal. The first issue is whether the contract in

question contains an arbitration provision. And the see-

ond issue involves whether the school boards in Virginia

have the power to enter into contracts containing arbi-

tration provisions. And I would like to take them one at

a time.

On the first issue, a little background. Schlosser is a

general contractor in Maryland, and they entered into a

lump sum contract with the County School Board here in

Fairfax to do some renovation work on the Falls Church

High School. That contract was a 1974 AIA modified

standard form contract. And it contained in Article

2.2.7 a requirement that claims and disputes relating to

the exectuion or progress of the work be submitted to

the architect for his 13] decision. In Article 2.2.10 of

the contract it said the architects, those claims and dis-

putes would be subject to arbitration.

I think the conflict here with this issue stems from the

fact that Article 7.10 of the contract involving the proce-

dure for arbitration which was to be conducted at the

American Arbitration Association under the standard

form ATA agreement was deleted in the supplementary

conditions to the contract. Basically the supplementary

conditions said delete the content of Article 7.10. It did

not say, delete the arbitration requirement. And it did

not say, this contract is not subject to arbitration.

THE COURT: But it did say that there would be no

damages to be recovered for delay.

MR. JONES: Well—

THE COURT: That is right behind the leading—

MR. JONES: That issue, Your Honor, I think is an

issue that is not an issue in this petition. This is a peti-

tion to compel arbitration, not a hearing on the merits

of the case itself.

19a

THE COURT: Why would that be a hearing on the

merits? | mean, if you found the contract provided you

couldn’t recover the damages asked for in your complaint,

you wouldn’t send the case to arbitration, would you?

MR. JONES: The arbitrators would have the ultimate

'4| decision-making authority to decide whether the dam-

ages claimed by petitioner in an arbitration forum were

appropriate and proper, not the Court. The arbitration

agreement would divest the Court of deciding the merits

of the case, and it would be for the arbitrators to decide.

That’s what agreements to arbitrate are all about.

And that’s what the Federal Arbitration Act is all about,

liberally construing agreements to arbitrate.

THE COURT: I don’t disagree with what you are

saying the law is. But I find it difficult to believe that if

you have got a contract that says you can’t get damages

at all, that you then appoint an arbiter and send that

to arbitration for them to determine a contract.

MR. JONES: Well, as Your Honor probably knows,

there are numerous exceptions to what we call the no

damage for delay clause in the contract. A recent one in

this court which recognizes some of those exceptions, such

as those involved with amounts of interference with the

contractor’s work, bad faith and fraud. And at the arbi-

tration hearing those are all issues that could be delved

into and presented to the arbitrators factually for the

arbitrators to determine whether the no damage for delay

clause is enforceable or not enforceable.

THI COURT: All right.

MR. JONES: I would submit to the Court that the

[5] agreement in this particular action is complete on its

face, it is unambiguous. There is an arbitration provi-

sion. I think the Schoo] Board recognizes the contract

contains an arbitration provision, although they charac-

terize it as an accidental reference left in the contract.

The second issue involves whether school boards have

the power to enter into contracts containing arbitration

provisions, if you will. And the petitioner contends that

OK

20a

Virginia Code Section 22.1-71, which gives school boards

their power to contract as well as the power to sue and

be sued, gives the School Board in this case the power to

enter into the construction contract in question which

contains an arbitration provision relating to the resolu-

tion of disputes for the particular construction work to be

performed.

There are a couple of Supreme Court cases, Dean

Witter and Southland Corporation which suggests that

the purpose of the Federal Arbitration Act is to put

agreements to arbitrate on the same footing as contract

agreements, they are one in the same. And they want to

give agreements to arbitrate the same force and effect as

a contract agreement. There is also a D.C. Circuit case,

I think it is called Pierce, cites the same proposition.

For that reason the petitioner believes the School Board

had the power clearly to enter into this contract, and

they had the power to enter into this contract which [6]

contained an arbitration provision governing resolution

of disputes relating solely to the contract itself,

Now, the School Board has raised severa] issues. The

first issue goes to how the Virginia Code Section 22.1-71

is construed. The School Board would argue that under

the Dillon Rule that statute has to be strictly construed.

And because that statute doesn’t say school boards have

the power to arbitrate, rather it only says school boards

have the power to contract, under Dillon Rule of con-

struction, school boards don’t have the power to enter

into agreements to arbitrate.

Petitioner would contend in response to that issue that

the statute does on its face say school boards have the

power to contract. The Supreme Court has said that

contracts are one in the same with agreements to arbi-

trate. And for that reason the statute gives the School

Board the power to enter into contracts containing arbi-

ration clauses.

There is a case that was issued by the Supreme Court

of Virginia called Arlington County which interpreted

2la

application of the Dillon Rule. And also looked at a rule

called the reasonable selection of method rule. The Dillon

Rule is whether the power exists. And the reasonable

selection of method rule is whether the power has been

properly executed.

The Dillon Rule is a rule of strict construction. [7]

The reasonable selection of method rule is a rule that is

liberally construed in favor of the method chosen.

The petitioner would submit that the statute gives the

power to enter into the contract, and the agreement with

the arbitration is a reasonable method to execute that

power to contract. Arbitration provisions are fairly com-

mon in the construction industry. It is a way of having

complex construction cases resolved by arbitrators who

often are familiar with construction and technical aspects

of construction. And for that reason, many of the stand-

ard contracts in the construction industry, including all

of the AIA standard contracts, contain arbitration provi-

sions and the parties agree to arbitrate their disputes

relating to the construction work rather than litigate

their disputes.

Finally, the School Board has cited a number of cases

that deal with arbitration agreements entered into with

the School Board, really the collective bargaining agree-

ments containing arbitration agreements. And in those

rare cases, those two or three of them, the Supreme Court

of Virginia has said that Article 8, Section 7 of the

Virginia Constitution empowers the school boards to su-

pervise their teaching staff, so to speak, and it would be

an unconstitutional divestiture of that power granted by

the Virginia Constitution to allow an arbitrator to decide

policy concerning the teaching staff.

[8] The cases all rationalize that where an agreement,

in those cases it was a collective bargaining agreement,

divest to an arbitrator to promulgate and establish pol-

icy, that is ununconstitutional act. In this case we are

not talking about promulgation or application of policy.

In this case we are dealing with one specific contract for

|

22a

the renovation of certain work at a school, There is 2

claim that relates to the contract itself and nothing else.

And the parties have agreed to arbitrate that claim under

the mutual provision of the contract. The arbitrator’s de-

cision is not going to set policy for the School Board on

any other construction contracts, it is just going to de-

cide the issues of the claim in question.

For that reason the petitioner would ask the Court to

sustain its appeal and enter an order compelling arbitra-

tion in this dispute.

Thank you.

MR. CAWLEY: Good morning, Judge Hilton. Tom

Cawley for the Fairfax County School Board.

Your Honor, I think it is important to realize the con-

text under which the deletion in question occurred here.

Mr. Jones describes the deletion in 7.10 and then describes

the fact that a couple of sections, 2.2.9, I think 2.2.10

were left in. He doesn’t point out, however, that the

section that was deleted by the School Board was en-

titled [9] Arbitration, and is the basic arbitration provi-

sion in an AIA general condition. It is entitled Arbitra-

tion and has and says, all claims. disputes and other

matters arising out of, et cetera, shall be sent to arbitra-

tion. And then it gives the procedures for actually arbi-

trating or utilizing the arbitration process. It says that

the American Arbitration Association processes will be

used and the construction rules of the American Arbitra-

tion Association will be employed.

All of that is taken out. And what happened is that

the sections that weren’t deleted had to go, were buried

really in the section on architects. And many sections

into the section on architects there was this section that

says appeals from architects’ decisions could be arbitrated.

Moreover, when the original petition was filed we filed

an affidavit from the Director of Design and Construction

of the school system that pointed out that the school sys-

tem has never arbitrated. That there is no language or

no document that ever evidenced any intention to arbi-

23a

rate. That the first word arbitration that ever occurred

in the dealings between these two parties occurred when

there was a demand for arbitration filed the next day by

this petition. And that in fact this contractor has con-

tracted with the School Board in the past and of course

had no arbitration provision.

So, I think it is clear in the first instance that [10]

there was no intention of the parties to have any sort of

arbitration. And it would be absurd to think that the

parties would delete the basic arbitration provision that

explains how things would be arbitrated and how they

would come about and the procedures for accomplishing

that and then say that parenthetically some unstructured

method of arbitration would be used to appeal architects’

decisions.

Moreover, as Your Honor points out, it would be espe-

cially ironic if the very section that replaced the arbitra-

tion section, which was a no damage for delay clause,

then became the very substance of the claim that is sup-

posed to be sent to arbitration.

But going bevond that point, the fact of the matter is

that in Virginia there simply is no power on the part of

school boards to arbitrate. And Mr. Jones said that the

Dillion Rule of construction is a rule of construction

construing statutes. And while sometimes it is used to

construe statutes, more fundamentally the Dillion Rule

I think is a rule to construe powers, to construe whether

or not local government has a particular power.

And obviously, and I know Your Honor is familiar with

this, but the Commonwealth versus Arlington County

case, which was a Commonwealth versus Arlington

County and Arlington County School Board case, dis-

cussed at length the application of the Dillon Rule of the

construction of powers [11] to try to determine what

powers a local school division in a local county govern-

ment would have. With respect to school boards, that case

said school boards exercise limited powers and functions

a

24a

of a public nature granted to them expressly or by neces-

sary implication and none other.

And I think the thing that is so dispositive on this

question of whether school boards have the power to arbi-

trate is the fact that in 1987 the General Assembly de-

cided to give to county governments the right to arbitrate.

And they did so by amending 15.1-508, which talks, which

follows the basic section about how counties may sue and

be sued, et cetera. And they added this language, the

governing body of a county may enter into a written

agreement to submit any existing controversy to arbitra-

tion and may execute a contract which contains a provi-

sion to submit to arbitration any controversy thereafter

arising.

Now, whether you look at the Dillon Rule of construc-

tion or you even use just basic contract principles, in-

clusio unius est exclusio alterius I believe it is, it seems

to me clear that if the counties are expressly given the

power to arbitrate and school boards can point to no

statute that gives them a similar power, it would be

impossible to say under either contract construction prin-

ciples or the Dillon Rule that school boards have the power

to arbitrate.

(12] And that analysis in fact was utilized by the Su-

preme Court of Virginia in that case of Arlington County

versus Brown where the County of Arlington argued that

it had the power to enter into a lease. And it said, well,

we have the power to transfer land, we have the power

to sell. Therefore. we must have the power to lease. And

the Supreme Court pointed out that cities expressly had

the power to lease under Virginia law. And, therefore, if

cities expressly had the powers to lease, and the county

couldn’t point to a similar power, then clearly the inten-

tion of the legisltaure was not to grant a similar power.

I think it is clear that the school boards in Virginia

don’t enjoy the power to arbitrate.

Finally, the Federa! Arbitration Act doesn’t change

that result. Now, the Federal Arbitration Act would have

25a

an impact on a specific statute in a state that singled out

arbitration and was designed to prevent it. But it does

not have an impact on general contractual provisions

which might have the effect of not having an arbitration

provision in a contract.

And those clearly enunciated principles are found in

the Supak case by the Fourth Circuit. In that case there

Was a situation where a buyer in in South Carolina was

buying materials from a New York supplier, and in the

confirmation of sale the New York supplier when he

would send the [13] confirmation of sale would put in

that the parties agreed to arbitrate. And that case, when

there was a dispute as to whether they had to go to

arbitration, was determined under UCC 2-207 which says

that in a confirmation of sale, if there is a material

change in the terms, then those material changes don’t

give rise to a new contract. Or don’t become a contractual

provision. And there the other side said, well, the Fed-

eral Arbitration Act requires this arbitration to go for-

ward.

And the Fourth Circuit said, no, it doesn’t. This is not

a situation where we have a singling out of a statute

that is intended to do away with the right to arbitrate.

It is a basic rule of construction of contracts which

causes the situation where there is no arbitration provi-

sion, and it would apply to many things that might be

material changes.

You compare that case to the Saturn case where a

Virginia statute which did single out arbitration was

struck down because of the fact that there was to that

extent pre-emption by the Federal Arbitration Act. But

the Federal Arbitration Act is not designed to, as one

court said, to occupy the entire field of arbitration. And

it does permit by its own terms an exception that permits

arbitration except upon such grounds as exist at law or in

equity for the revocation of any contract.

That’s what we have here. We have a general [14]

contractual provision, which is the Dillon Rule, which

VARY

prevents school boards from arbitrating. And, therefore,

there is no federal pret Daypt hon On that issue,

And we would ask that the decision of Magistrate

Syinkema be upheld,

rite COURT: All right. Well, TE find that it) was

the intent of the parties that the arbitration clause be

removed from. this. contra lt was removed. The pri-

mary arbitration clause was taken out of the contract.

fh went even further when they took it out and said they

couldn’t even make a claim for these kinds of damages.

It is just clear the intent of the parties was to take

out the arbitration provisions in the contract even though

it may have been mentioned in passing in another area or

two of the contract.

I also find the School Board doesn’t have any authority

to arbitrate in Virginia,

I do not find the decision of the magistrate to be

clearly erroneous, and it will be affirmed.

MR. CAWLEY: Thank you, Yeur Honor.

HEARING CONCLUDED

27a

APPENDIX F

IN TH UNITED STATES DISTRICT COURT

FOR THE EASTIERN DISTRICT OF VIRGINIA

ALMXANDRIA DIVISION

Civil Action No, 91-4-M

W. M. SCHLOSSER COMPANY, INC

Pla intiff,

THE COUNTY SCHOOL BOARD

OF FAIRFAX COUNTY, VIRGINIA,

Defendant.

i Filed April » 199]

ORDER

For the reasons stated in open court, petitioners Mi

tions to Designate an Arbitrator and f an Order to

Compel Arbitration are DENIED.

The Clerk is directed to forward conic (orde)

ty counsel of record

lontered this 5th day of A) ril, 1991.

Leonie M. Brinke)

LEONIE M. B TA

| ec \I f r

APPENDIX G

IN THE UNITED STATES DISTRICT COURT

FOR THE EASTERN DISTRICT OF VIRGINIA

ALEXANDRIA DIVISION

Civil Action Number 91-4-M

W. M. SCHLOSSER COMPANY, INC.,

Petitioner,

VS.

THE COUNTY SCHOOL BOARD

OF FAIRFAX COUNTY, VIRGINIA,

Respondent.

Friday, April 5, 1991

Courtroom IV

United States District Courthouse

Alexandria, Virginia

The above-entitled matter came on to be heard before

THE- HONORABLE LEONIE M. BRINKEMA, United

States Magistrate, in und for the United Siates District

Court for the Eastern District of Virginia, beginning at

10:59 o’clock a.m.

APPEARANCES:

On Behalf of the Petitioner:

ROGER C. JONES, ESQUIRE

BRAUDE & MARGULIES, P.C.

[2]

On Behalf of the Respondent:

THOMAS J. CAWLEY, ESQUIRE

HUNTON & WILLIAMS

a ee ee

29a

3] PROCEEDINGS

THE CLERK: Civil action 91 dash 4 M, W.M.

Schlosser Company versus The County Board of Fairfax

County.

MR. JONES: Good morning, Your Honor.

THE COURT: Good morning.

MR. JONES: Roger Jones on behalf of the Petitioner.

THE COURT: I’m sorry; the door was slamming.

MR. JONES: I’m sorry; Roger Jones on behalf of

the Petitioner, W.V. Schlosser.

THE COURT: And for the County?

MR. CAWLEY: Excuse me; Thomas Cawley for the

School Board, Your Honor.

THE COURT: All right; now, this comes before me

on two motions of the Petitioner, one to designate an

arbitrator and one for an order to compel arbitration.

MR. JONES: That’s correct, Your Honor.

THE COURT: I’ve looked at both your pleadings.

I understand that the School Board’s position is, number

one, that it was certainly their intent when they entered

this contract that arbitration not be a part of the

contract.

(4] And they’ve cited to a miscellaneous provision

within the contract which negates, in their opinion, arbi-

tration.

I understand you're saying that they only negated a

particular portion of the A.I.A. contract.

MR. JONES: Negated not really a portion; the pro-

cedure by which arbitration is pursued under the A.I.A.

contract, that procedure is that the American Arbitra-

tion Association—

Article seven point ten that was deleted simply deleted

that procedure. The supplementary condition did not say

arbitration is deleted from this contract.

It just said delete article seven point ten. The under-

lying arbitration agreement in article two, two point two

point ten, is still intact.

That wasn’t deleted by any supplementary condition.

a

30a

THE COURT: But of course what I have here is a

—this is sort of a classic contract problem. I have two

parties to a contract. There is language in dispute.

One side says, ‘We didn’t intend for that.’ And they’re

also saying further, ‘We’re not legally able—|5]we

couldn’t contract that, even if we wanted to.’

You’re saying, ‘This is what the parties agreed to.’

And furthermore, ‘You can do it under the law.’

MR. JONES: Well, I think if you read the provisions

consistent with each other and compatible with each

other, which is black letter contract law, if you read

article two point two point ten, that claims relating to

execution and the progress of the work which had been

referred to the architect are subject to arbitration.

You read the supplementary condition deleting article

seven point ten as deleting the procedure to proceed with

that arbitration at the American Arbitration Association.

And it just leaves—it doesn’t—there’s no method pre-

scribed in that contract for arbitration, which is okay.

The Federal Arbitration Act then sets up a procedure

where they can go to court and have designated arbi-

trators.

There’s a lot of reasons why parties might want to

delete the procedure of arbitration under triple A. It’s

expensive.

[5| Over the years, it’s—it’s taking more time now.

THE COURT: I’m curious; were you the attorneys

involved in negotiating the contract?

MR. CAWLEY: No, Your Honor.

THE COURT: No; so, neither of you knows what

the—have you talked with the various negotiators as to

what their understanding was at the operation of that

provision?

MR. CAWLEY: Your Honor, I am counsel for The

School Board. And in general—lI’ve been counsel for The

School Board for 15 years—and we’ve always advised

them that they don’t have the right to arbitrate.

3la

The particular formatien of this contract was done—I

believe the architect had something to do with it and the

staff was involved.

But I don’t believe there were attorneys on either side,

to my knowledge.

MR. JONES: No; the Petitioner in this case is a

Maryland company. He’s coming here to Virginia to do

some renovation work on a high school.

If there was a dispute about execution or the progress

of the work, I’m sure that they intended to have [7] it

submitted to arbitration versus going to trial with a

Jury in Fairfax County.

Arbitration may be a more impartial way of resolving

any sort of dispute between the parties.

THE COURT: All right; well, I’ve read the contract

that you all attached to the pleadings. And I’ve looked

at your briefs real carefully.

I can’t grant the motion. I am convinced, as I read the

law, that Mr. Cawley’s argument is the better of the two.

I don’t think—there certainly is unclarity as to what

the parties intended with the language of the contract.

But I think that the case law and the argument made

as to the legal ability of The School Board to contract

for arbitration is the sounder of the two arguments.

So, I’m going to deny your motion to designate an

arbitrator and the motion to compel arbitration.

MR. JONES: And just so I understand, it’s based on

the fact that

THE COURT: I’m not at all clear that the parties

intended—

[8] MR. JONES: Okay.

THE COURT: From my reading of the contract, I

don’t think it was the intent of at least one party to the

contract to allow for arbitration.

I think they attempted to do that with the language

that may not have been as artfully drafted as it should

have been to make it crystal clear that there is no arbi-

tration available in this contract.

32a

And secondly, I don’t think that Virginia law em-

powers school boards to enter into that kind of an arbi-

tration agreement.

MR. JONES: Notwithstanding the provisions of the

Virginia Code 22—

THE COURT: That’s correct.

MR. JONES: -—point 1 dash 71?

THE COURT: That’s correct; I don’t think it applies

to the school boards.

All right, sir?

MR. JONES: Thank you.

MR. CAWLEY: Thank you, Judge Brinkema.

[9] (Whereupon, at approximately 11:06 o’clock a.m.,

the hearing in the above-entitled matter was concluded.)

33a

APPENDIX H

IN THE UNITED STATES DISTRICT COURT

FOR THE EASTERN DISTRICT OF VIRGINIA

ALEXANDRIA DIVISION

Miscellaneous No. 91-0004-M

W.M. SCHLOSSER COMPANY, INC.

2400 5ist Place

Hyattsville, Maryland 20781,

Petitioner,

v.

THE COUNTY SCHOOL BOARD OF

FAIRFAX COUNTY, VIRGINIA

10700 Page Avenue

Fairfax, Virginia 22030

Respondent.

Serve:

JANE TIMIAN

Clerk, Fairfax County School Board

10700 Page Avenue

Fairfax, Virginia 22030

PETITION FOR ORDER TO COMPEL ARBITRATION

1. Petitioner, W.M. Schlosser Company (‘Schlosser’),

is a Maryland corporation with its principal place of busi-

ness in Hyattsville, Maryland. Petitioner is engaged in

the business of construction contracting as a general con-

tractor.

2. Respondent is the School Board of Fairfax County,

Virginia (hereinafter sometime referred to as the

“Owner”’’),

34a

3. This Petition is filed pursuant to the provisions of

9 U.S.C. $4 for an Order to Compel Arbitration of a

claim, which is the subject of a written arbitration agree-

ment that is governed by the Federal Arbitration Act, 9.

U.S.C. $1, et seg. since the underlying transaction in-

volves interstate commerce and is between parties of

different states. Respondent has failed and refused to

arbitrate said claim.

4. This Court has jurisdiction pursuant to the provi-

sions of 28 U.S.C. § 1332, based upon diversity of citizen-

ship and since the amount in controversy exceeds $50,000,

exclusive of interest and costs.

5. All conditions precedent for the filing of this Peti-

tion have been satisfied.

6. On or about June 10, 1988, Respondent entered into

a Contract with Petitioner (hereinafter the “Contract”’),

for the performance of certain construction renovation

work relating to Falls Church High School (hereinafter

the “Project”). The Project is located in Fairfax County,

Virginia. A copy of said Contract, with its General and

Supplementary Conditions, is attached hereto as Ex-

hibit A.

7. The Contract provides in pertinent part:

2.2.7 Claims, disputes and other matters in question

between the Contractor and the Owner relating to

the execution or progress of the work or the inter-

pretation of the Contract documents shall be referred

initially to the architect for decision which he will

render in writing within a reasonable time.

* * + *

2.2.10 Any claim, dispute or other matter that has

been referred to the architect ... shall be subject to

arbitration upon the written demand of either party.

However, no demand for arbitration of any such

claim, dispute or other matter may be made until

the earlier of:

35a

2.2.10.1 The date on which the architect has ren-

dered his written decision, or

.2 The 10th day after the parties have pre-

sented their evidence to the architect or

have been given a reasonable opportunity

to do so, if the architect has not rendered

his decision by that date. [Emphasis

added].

8. During the course of the Contract, Schlosser’s per-

formance was hindered, disrupted, impacted and delayed

due to the actions, inactions and active interference of

the Owner. The Owner’s conduct in this regard consti-

tuted a breach of the Owner’s Contract obligations. As

a result of the Owner’s breaches of Contract, Schlosser’s

Contract performance was extended 209 calendar days

and Schlosser suffered significant additional costs and

damages.

9. On or about August 3, 1990, Schlosser submitted to

the Owner a claim for its additional costs and damages

stemming from the extended Contract performance, in

the total amount of $1,152,941. In accordance with Arti-

cle 2.2.7 of the Contract, Schlosser also submitted a copy

of this claim to the architect for his decision.

10. On or about October 9, 1990, the Owner advised

Schlosser that Schlosser’s claim was being reviewed by the

architect. By letter dated January 10, 1991, Schlosser

noted to the Owner that its claim, “was initially copied

to the architect and we expect his decision on our entire

claim, in accordance with the Contract requirements.” A

copy of this letter is attached hereto as Exhibit B. De-

spite the fact that a reasonable time has elapsed, the

architect has failed to render in writing a decision on

Schlosser’s claim.

9. In accordance with Article 2.2.10 of the Contract,

on March 27, 1991, Schlosser submitted to the Owner a

written Demand for Arbitration with respect to their

|

36a

claim for extended Contract performance. A copy of this

Demand for Arbitration is attached hereto as Exhibit C.

To date, the Owner has failed to respond to this Demand

for Arbitration.

10. By separate motion, filed contemporaneously here-

with, Petitioner also seeks this Court to designate and

appoint an impartial arbitrator(s) pursuant to 9 U.S.C.

Ss

3 ©,

WHEREFORE, Petitioner, W.M. Schlosser Company,

Inc. respectfully requests this Court to enter an Order

directing that arbitration of Petitioner’s claim proceed in

the manner provided for in the parties’ Arbitration

Agreement and as required by the Federal Arbitration

Act, and for such other and further relief as this Court

deems just and appropriate.

Respectfully submitted, -

By: /s’ Roger C. Jones

Rear? C. JONES

Va. Bar No. 25256

BRAUDE & MARGULIES, P.C.

1828 L Street, N.W.

Suite 900

Washington, D.C. 20036

Counsel for Plaintiff

W.M. Schlosser Company, Inc.

Dated: 3.28.91

37a

EXHIBIT A

THE AMERICAN INSTITUTE OF ARCHITECTS

| Loco}

AIA Document A101

STANDARD FORM OF AGREEMENT BETWEEN

OWNER AND CONTRACTOR

where the basis of payment is a

STIPULATED SUM

This Document Has Important Legal Consequences:

Consultation With An Attorney Is Incouraged With

Respect To Its Completion Or Modification

Use only with the latest Edison of AIA Document A201,

General Conditions of the Contract for Construction.

This document has been approved and endorsed by

The Associated General Contractors of America.

AGREEMENT Contract #090-88-RE-599

made this 9th day of June in the year of Ninteen Hun-

dred and Eighty-Eight

BETWEEN the Owner:

The County School Board of Fairfax County, Virginia

10700 Page Avenue

Fairfax, Virginia 22030

and the Contractor:

W. M. Schlosser Company, Ince.

2400 S51st Place

Hyattsville, Maryland 20781

—

38a

the Project:

Renewal of

Falls Church High School

the Architect:

The Fairfax Architects, P.C.

246A West Broad Street

Falls Church, Virginia 22046

The Owner and the Contractor agree as sei forth below.

ARTICLE 1

THE CONTRACT DOCUMENTS

The Contract Documents consist of this Agreement, Con-

ditions of the Contract (General, Supplementary and

other Conditions), Drawings, Specifications, all Addenda

issued prior to execution of this Agreement and all Modifi-

cations issued subsequent thereto. These form the Con-

tract, and all are as fully a part of the Contract as if

attached to this Agreement or repeated herein. An

enumeration of the Contract Documents appears in Arti-

cle 7.

ARTICLE 2

THE WORK

The Contractor shall perform all the Work required by

the Contract Documents for the provision of all labor,

materials, equipment and services necessary for the re-

newal of the existing building at Falls Church High

School, 7521 Jaguar Trail, Falls Church, Virginia 22042.

ARTICLE 3

TIME OF COMMENCEMENT AND COMPLETION

The Work to be performed under this Contract shall be

commenced on or about June 10, 1988 and shall be sub-

stantially completed on or before August 31, 1989.

39a

The project shall be constructed in phases. The Architect

shall determine and certify when the work is substantially

completed for each phase. Work shall commence and be

substantially completed on or before the dates shown in

section 01010 entitled summary of the work, Paragraph

3.1.B, “Schedule for Delivery of the Work”. Should the

work not be substantially completed by the dates specified

for each phase, it is understood and agreed that there will

be deducted the sum of $200.00 for each phase, per con-

secutive calendar day, as liquidated damages, but not as

a penalty, for each day’s delay thereof until substantial

completion of each phase is certified by the Architect.

Should the totai project not be substantially completed by

August 31, 1989, it is understood and agreed that there

will be deducted the further sum of $600.00 per consecu-

tive calendar day, in addition to any other sum due here-

under for the total project, as liquidated damages, but not

as a penalty, for each day’s thereof until substantial com-

pletion is certified by the Architect and accepted by the

Owner.

ARTICLE 4

CONTRACT SUM

he Owner shall pay the Contractor for the performance

of the Work, subject to additions and deductions by

Change Order as provided in the Conditions of the Con-

tract, in current funds, the Contract Sum of nine million

three hundred seventy six thousand dollars ($9,376,000)

consisting of:

$8,777,000 Base Bid

599,000 Alternate No. 1

$9,376,000

ARTICLE 5

PROGRESS PAYMENTS

Based upon Applications for Payment submitted to the

Architect by the Contractor, the Owner shall make prog-

40a

ress payments on account of the Contract Sum to the

Contractor as provided in the General and Supplementary

and Special Conditions.

“The form for each progress payment shall be the Fairfax

County School Board’s ‘Requisition for Partial Payment’

and will be obtained from the School Board’s Design and

Construction Department. The form shall be completed

in detail and submitted in six (6) copies. The Owner

shall make a Progress Payment to the Contractor on the

basis of a duly certified and approved. estimate of the

work performed during the preceding calendar month

under this contract, but to insure proper performance of

this contract, the Owner shall retain five (5) percent of

the amount of each estimate properly allocable to labor,

materials and equipment incorporated in the work and

ten (10) percent of the amount of each estimate properly

allocable to materials and equipment suitably stored at

the site until final completion and acceptance of all work

covered by this contract. The Contractor shall include a

similar provision limiting retainage on progress pay-

ments in all subcontracts it enters into pursuant to the

Contractor’s performance of this Contract.”

ARTICLE 6

FINAL PAYMENT

Final payment, constituting the entire unpaid balance of

the Contract Sum, shall be paid by the Owner to the

Contractor Thirty (30) days after Substantial Comple-

tion of the Work unless otherwise stipulated in the Gen-

eral and Supplementary Conditions, provided the Work

has been satisfactorily completed, the Contract totally

completed, and a tinal certificate for Payment has been

issued by the Architect.

4la

ARTICLE 7

MISCELLANEOUS PROVISIONS

7.1 Terms used in this Agreement which are defined in

the Conditions of the Contract shall have the meanings

designated in those Conditions.

7.2 The Contract Documents, which constitute the en-

tire agreement between the Owner and the Contractor,

are listed in Article 1 and, except for Modifications issued

after execution of this Agreement, are enumerated as

follows:

(List below the Agreement, Conditions of the Contract

(General, Supplementary, and other Conditions), Draw-

ings, Specifications, Addenda and accepted Alternates,

showing page or sheet numbers in all cases and dates

where applicable.

Standard Form of Agreement Between Owner & Contrac-

tor, AIA Document A101 January 1974.

General Conditions of the Contract for Construction, AIA

Document A201 April 1970.

Specifications: See attached pages 1 through 3, pages 1,

li.

Drawings: Civil C-1 through C-4

Architectural A-0 through A-60

Structural S-1 and S-2

Mechanical M-1 through M-88

Plumbing P-1 through P-34

Electrical E-1 through E-51

Addenda: Addendum No. 1 dated May 13, 1988.

Addendum No. 2 dated May 18, 1988

Addendum No. 3 dated May 20, 1988

Addendum No. 4 dated May 23, 1988

Addendum No. 5 dated May 24, 1988

Accepted: Base Bid and Alternate No. 1

_

42a

This Agreement executed the day and year first written

above. This Agreement, under seal, is executed in 4

counterparts each deemed as original.

OWNER

The County School

Board of Fairfax

County, Virginia

s {[lIllegible|

Chairman

s Jane Timion

Clerk of the School

Joard SEAI

CONTRACTOR

W.M. Schlosser Company,

Inc.

s’ [Illegible]

President

s’ [Illegible]

Corporate Secretary |SEAL}

43a

Section 00700

General Conditions

THE AMERICAN INSTITUTE OF ARCHITECTS

| Loco |

AIA Document A201

GENERAL CONDITIONS OF THE CONTRACT

FOR CONSTRUCTION

This Document Has Important Legal Consequences:

Consultation With An Attorney Is Encouraged With

Respect To Its Modification

TABLE OF ARTICLES

1. CONTRACT 9. PAYMENTS AND

DOCUMENTS COMPLETION

2. ARCHITECT 10. PROTECTION OF

PERSONS AND

8. OWNER PROPERTY

4. CONTRACTOR 11. INSURANCE

5. SUBCONTRACTORS 12. CHANGES IN THE

6. SEPARATE WORK

CONTRACTS 18. UNCOVERING AND

7. MISCELLANEOUS CORRECTION OF

PROVISIONS WORK

8. TIME 14. TERMINATION OF

THE CONTRACT

This document has been approved and endorsed by

The Associated Gencral Contractors of America.

SSS aaa

tda

INDEX

Acceptance of Defective or Non-Conforming Work 13.3

Access to Work 2.2.0

Accident Prevention 2.2.4, 18

Addendum, Definition of 1.1.1

Additional Costs, Claims for 12.2.1

Additional Work ' 12

Administration of the Contract 2.2

Agreement, Extent of Bee.

Allowances, Cash A.S.7

Applications for Payment 2.2.5, 9.2.1, 9.3.1, 9.3.3, 9.4.1,

9.4.2, 9.6.1, 9.6.7, 9.7.2

Arbitration, Owner-Contractor Claims and

Disputes 2.2.6 through 2.2.12, 7.19

ARCHITECT 2

Architect, Definition of 2.1

Architect's Access to the Work 2.2.0

Architect's Authority 22.2, 23.12, 32:14, 2.2.04; S84, keh

Architect’s Authority to Reject Work yy Ae

Architect’s Decisions 2.2.6 through 2.2.12

Architect's interpretations 1.2.5, 2.2.6 through 2.2.11, 12.1.6

Architect's Full-Time Project Representative 2.2.16

Architect’s States a2

Architect’s Visits to Site 2.2.3, 2.2.4, 2.2.16, 7.8, 9.7

Bonds. Contract (Performance, Labor and Material

Payment) 1.5

Builder’s Risk Insurance (See Property Insurance) ii.a

Cash Allowances 1.8.1

Certification for

Payment 2.2.5, 2.2.15, 5.4.2, 9.4, 9.3.1, 9.6.1, 9.7. 2

CHANGES IN THE WORK 12

Changes, Minor 2.2.14, 12.3

Change Orders 2.2.14, 4.8.1, 12.1

Change Orders, Definition of 12.1.2

Claims and Disputes Between the Contractor and the

Owner 2.2.6 through 2.2.12, 7.10

Claims for Additional Cost or Time 8.3.2, 8.3.3, 12.1.6,

IS, Lee

Claims for Damages ..1.4, 8.3

Claims of the Subcontractor 5.3. 1.4

A4fia

Cleaning up A.16,6.4

(‘odes A.7.2. 18.2.3

Commencement of the Work 7.0.4, 6.hoe

Communications 2.2.2, 3.2.4, 4.9.1, 4.17

COMPLETION, PAYMENTS AND 9g

Completion Substantial 2.2.15, 8.1.3, 8.2.3. 9.7

Contract, Definition of 1.1.2

Contract Bonds 7.6

CONTRACT DOCUMENTS |

Contract Documents, Copies Furnished and

Ownership of 1.3

Contract Documents, Definition of se

Contract Documents, Execution, Correlation,

intent and interpretation |.2

Contract Modifications Be ee Ae

(Contract Sum, Changes of lak, Dee

Contract Sum, Definition of 9.1.1

Contract Termination by Contractor 14.1

Contract Termination by Owner 14.2

Contract Time 214

Contracts, Separate e

CONTRACTOR 4

Contractor, Definition of 4

Contractor, Stopping the Work by the 2

Contractor, Termination of the Contract by the {

Contractor’s Liability Insurance te

Contractor’s Relations with Subcontractors | 2.4.3.3

Contractor’s Responsibility for Protection

and Safety 2

Contractor’s Responsibility for Those Performing

the Work !

Contractor’s Review of Contract Documents 2.2, 4.2

Contractor’s Superintendent 1.9.1, 10.2.5

Contractor’s Supervision and Construction

Procedures 1.3

Contractors, Mutual Respensibilit f 3.2

Copies Furnished of Drawings and Specifications 3.1

Correction of Work 3.2

Cutting and Patching of Work ie

Cutting and Patching Under Separate Contracts :

46a

eRe “Soe SN a cinerssenasdannasnuinetnannecsmmeneencns 7.4, 8.3

I Se ac nccaccspunnanenssesumenbneeasceccascsersscieeiens 8.3.4

I III WOE. oo ceccs ce nanecseaenctsbedinssiusnernineanacncrercesennnh a ne

LEFT ATE TON RCL SY OTRO ROE 4.16, 6.4

Deductions for Uncorrected Work .......................-........-... 18.8.1

Defective or Non-Conforming Work,

I I a aaa neon presser tka a entsranntenieaniecienmnenes 13.3

Delays and Extension of Time ...................2.........:.22:00000+- 8.3

Documents, Execution of the Contract _.......... oy Sat ala 12.1

Drawings and Specifications at the Site ........000........... 4.12

Drawings and Specifications, Ownership of ............. RRA 1.3.2

Drawings, Arrangement of ......................---...--2-00-+- a 1.2.4

Drawings as Written Interpretations —......................... 1.2.5

EES OOO Sele SE AS SR EON Ord hat Re 3.2.2

Emergencies ...... Ee LANE ON TMLee SURE LL ROD Pe WD 10.3

Execution, Correlation, Intent and Interpretations of

Py ae oe > a an ea anne rere 12

I RE eo 7a a gene asm ca neaisendencneeds 8.3, 12.1

ER RI ie SEATS ED: Ee aL TO CEPOL NNT LD. 12

I MO IN oro csc on sarreseessssencicencnrcstacaeseomtreansstcaes 9.6

re I ee rn daeaaniee anpaueneataea tana 1.2.5, 12.3, 12.4

I te ope venservastn cee meeneueananentenroavanennaad ees 9.7

Fire, Extended Coverage, Vandalism and Malicious

I I oar ccs tts ccc seccnneeena acne . ea

Governing Law ..... nL PRE seiisnaie siaasaainteupatiareeeeae 7.1

enn I od 3, sas ss erece onan nnmeci nee paaeesoanseeameaaaes 7.5

Guarantee ......- "UEP ARERR ea a A santana actadesmecerenciacs 9.3.3, 13.2.2

I ero oe aaa es eskne aceee hag eeeaeetaicas 4.18

Information and Services Required of the Owner ene 3.2

Inspection _.......... Reeiaiakbacae ican tka cd aniveen deca terenmmartareses 2.2.15, 7.8, 9.7

Instructions to the Contractor eee eae Nese eanl see B tere 2.2.2, 3.2.4

INSURANCE .......... eee ae a lenient 11

Insurance, Builders Risk (See Property

a do erence etn cu anoens meee Abate y 11.3.1

Insurance, Contractor’s Liability —........................ aces 11.1

Insurance, Fire, Extended Coverage, Vandalism, and

Whatieiee TEIMCMAGE onc.n..ncncecceecnccccccenc.sccsscccrvencsesscessssns: _ 11.3.1

I. TI A I ogocia cra nes seeesaotev nce s recennenangstaeaesnye 11.4

Insurances, Owner® LARDITIGY .......00:0icc<e.-0021--00cessepseeeeeneeses 11.2

’

47a

Insurance, Property _............... Jas Spnsilaciccsta serait ats cote 11.3

PROUT RNCR, TIRE TOURING nnn ci ccsccsencnsccdecct oe 11.3.5

Insurance, Steam Boiler and Machinery .......................... 11.3.2

Ie cases davecsees ka Couette antiennicimecntd adlcaa a eskiedcasinabe ea iar aaa 7.9.1

Interpretaitons and Decisions

Oe Se I Sincere cree 2.2.6 through 2.2.12

Interpretations, Written ........... laucaeseae 1.1.1, 1.2.6, 12.3, 12.4

DARD CUNT BG isis ves evans cce nt cneevse trends ecccesonrlinnss 4.4, 4.5

Labor and Material Payment Bond .......... eset ail 7.5

BE oncte octane Hei W heel esc AS Berens 4.6, 4.7, 7.1, 10.2

| RN Be Sena Ae tA and caankonteto BRa eta aati o elitors 9.7.3, 9.7.5

Re OE Une TRONS 28k eee Caine 11.4.1

SON, | eNO I oo 58 oh ek cncsacwsnacnnnevassua veneer metoens 4.4, 4.5

Minor Changes in the Work ................................ 1.1.1, 12.3, 12.4

MISCELLANEOUS PROVISIONS ...............2.2.<...2005.:--. 7

Wiodiemtiome Co TH COURTING ncn cic ciica csc lecccccc ieee 11.1, 12

Mutual Responsibility of Contractors —_......................... 6.2

Non-Conforming Work, Accepance of

I NE poh o saspuansacastuiabeeshasennsanende 13.3.1

Notice of Testing and Inspections ..................... ecccecuentee 7.8

PHOUEOR CO PTOCWOG annie ncenccsscecescivscccnsseaes: acetone ueuaalanaenea 8.1.2

ee I occ ees tc cucentncaeenianteaieeceions acer dS oA 13

Notices, Permits, Fees and ...............................- eas 4.7

3B] -_ SERRRM Ren nme aU an Nene Sitewir™ a ee eee Le eae ie 3

CE Br ON ooo ecerseneians ncerstee cra crenerweastcnmneene 3.1

Owner, Termination of the Contract by the 0.000000... 14.2

Owner’s Information and Service |....................-.-...... oho 3.2

Owner’s Liability Insurance __..... ns 2

Owner’s Right to Carry Out the Work . eee 3.4

Owner’s Right to Clean Up _. . Lae heen 4. 16. 2.6.4

Owner’s Right to Award Separate Contracts Dye mctenretes 6.1

Owner’s Right to Stop the Work .......... ieee ae 3.3

Ownership of Drawings and Spectifications ey

SIS G5E | WU oe econ aches svessasacaencaccs nwsctagecsacates a. he

Patching of Work Under Separate Contracts _ ........... 6.3

Payments, Royalties and _....... cacacsaoeeaavcncaaetwhiesees a ane

PAYMENTS AND COMPLETION - See 9

Payment, Applications for 2a.8, 9.2.1, 9, 3. 1, 9.3 3 3, 9.4.1,

9.4.2, 9.5.1, 9.6.1, 9.7.2

a

48a

Payment,

Certificates for ..........2.2.5, 2.2.15, 5.4.2, 9.4, 9.5.1, 9.6.1, 9.7.2

Sn) PURINE ONE 2 sac cacucseusscdnaccumaeeal eee en 9.6

I oe oat ppaun rere ccr vue cyccecbewastisarcde ad eee 2.2.18, 9.7

rn ar IIS... co... cece ca dnconceasaceracaamseua neers 9.3, 9.4

PUPS GO BURCONEPRCIONS ........0c..<csccesccceccssncsescassecssesees 5.4

NE I ooo acorns casncivecacaren abepeadan omen enemies 9.5

Performance Bond ..... dad tad hecho cetsiie sce ehertan erence 7.5

Payments, Fees and Notices .......................----..-sseseeceeeeceeeee 4.7

PERSONS AND PROPERTY, PROTECTION OF........ 10

ene I CUNT ooo concn cencecsn covncesconccasencecececcers 8.2

ry. TN oo ecco scyctvccvcccteeceue Sse hecaran orien 9.3, 9.4

Sunn: 5 III 05088 8 re, Lena ae oS 4.11

I I no ee eee 1.1.4

Project Loss or Damage Insurance ........0.......002.00000000- ac ALO

Project Representatives, Full-Time .........00.....0.00000000...... 2.2.16

eI RI oo cgsiciosusnassbatendinse neice saulbanmsiaass 11.3

PROTECTION OF PERSONS AND PROPERTY........ 10

SINNED. «=. susconaunssucdipunsonckoeeuasteae aicthaidliieaat 4.7.2, 10.2.2

EIN OE FU EM voce scciccccasceveesccsnesscnevensaneeses Av secdaaevuned 2.2.12, 13.2

Releases of Waivers and Liens ..........00000..... EAL 9.7.3, 9.7.5

Responsibility for Those Performing the Work ........4.10, 9.7.1

IE GOIN Cont Tt te 2 oe ee eee oe seenal 5.4.2, 9.7.3, 9.7.4

Review of Contract Documents by the Contractor....1.2.2, 4.2

Royalties and Patents ............ Pibaeeie asdicctidentedemnsalte 7.7

Rights and Remedies .................... A AOR ANS AI SIs 4 7.6

EREOCY GL FOEMOTIE GIN PODGTED ovvivicsssccisececccessonsssscsensceresns 10.2

Safety Precautions and Programs .............................. 2.8.4, 10.1

Samples, Shop Drawings and ........................-.se000000+- 2.2.18, 4.13

a A eee a eee aa AS Coa 9.2

Schedules, Progress .................. a eckakiaiueliemmenawaiite FS OS 4.71

AE OE POW EPR BOD vnissh vinssccsesnkcecdsvestsasaaseagseowsurs 6

Separate Contracts, Owner’s Right to Award ................ 6.1

Shop Drawings and Samples ..................................-. 2.2.13, 4.13

I ce te ee gut ay anes weuca can decmakeea weed iat 4.14.1

Special Hazards Insurance Spend eenateepaesmcecuueckaca teas sausage 11.3.5

Specifications, Organization of .........................0..cccccscss00. 1.3.4

Steam Boiler and Machinery Insurance .......................... 11.3.2

IY SPIE, Cw ahdueocegaeueheonansubeneurnvocneianenasl 3.3

I I 7 I ss. sacs cnansvnndereneusaabeniensipcapanetenpbevmtaanennake 5

49a

Subcontractor, Claims of ......................cccccccccccccoseccoccceeeeee 5.3.1.4

Subcontractor, Definition of Res: 5.1.1

Subcontracts, Award of ES AEA een, Se ER ER ine 1.2.4, 5.2

Subcontractual Relations 0. 5.3

Substantial Completion and Final Payment ._...._ 2.2.15, 9.7

Substantial Completion, Date of 2.2.15, 8.1.3, 8.2.3

Sub-subcontractor, Definition of 5.1.2

Subsurface Conditions ........................cccccccsccsssccooscscecsceesese 12.1.6

Successors and Assigns _____. FAL ae Rm Pays enol 7.2

Supervision and Construction Procedures Bre ah do VALS TP 4.3.1

Superintendent, Contractor’s 4.9.1, 10.2.5

Surveys ......... Re Then erasnrest Aripe ee eee Ee , week

Mr tecicAaate ese Renter et ela tn ee te 4.6

Termination by the en Reine apetea len Dae ee Sanam tte 14.1

Termination by the Owner __. See ee,

TERMINATION OF THE CONTRACT. ARES A Pas 14

NE Ricco ctaceesoecertteaceustokecenc ee, sie AIM, bonis de 2.2.12, 7.8

filets peeps Ais «I eRe Mae BS RA ARR Rt oF arro8 8

Time, Definition of . mi Neatentartaxeuttte eee 8.1

Time, Delays and Extensions of . did parca hoe OLR) 8.3, 12.1, 12.2

Title of Work . noes Wm RAM ate JAR 9.1.3

UNCOVERING AND CORRECTION OF WOFK __. 13

Uncovering of Work scedotzéhenaas BS a tach Ne gf

2) |. ene ees nf Tee BOONE SN Pay SPR Se 12, 1.3, 12.1.5

RPO A ia cs ars nice ksh edict eee 4.14

Ee CI GE oe oooh ans casancacadanetsset amceeet 9.2

Waiver of Claims by the Contractor... 9.7.6

Waiver of Claims by the Owner ......................---ecccccceccceeee 9.7.5

fly. |) MOOR Ise ee Fe

Words, Recognized Meanings of ue eNcereatea eens 1.2.3

Work, Definition of ars Beixtcésouraeee

TN, BIO sss scosccaccccssncsatvn e<bsaparstieai dade aekue 7.3

50a

GENERAL CONDITIONS OF THE CONTRACT

FOR CONSTRUCTION

ARTICLE 1

CONTRACT DOCUMENTS

1.1 DEFINITIONS

1.1.1 THE CONTRACT DOCUMENTS

The Contract Documents consist of the Agreement, the

Conditions of the Contract ‘General, Supplementary and

other Conditions), the Drawings, the Specifications, all

Addenda issued prior to execution of the Contract, and

all Modifications thereto. A Modification is (1) a written

amendment to the Contract signed by both parties, (2) a

Change Order, (3) a written interpretation issued by the

Architect pursuant to Subparagraph 1.2.5, or (4) a

written order for a minor change in the Work issued by

the Architect pursuant to Paragraph 12.3. A Modification

may be made only after execution of the Contract.

11.2 THE CONTRACT

The Contract Documents form the Contract. The Con-

tract repiesents the entire and integrated agreement be-

tween the parties hereto and supersedes all prior negatia-

tions, representations, or agreements, either written or

oral, including the bidding documents. The Contract may

he amended or modified only by a Modification as defined

in Subparagraph 1.1.1.

11.8 THE WORK

The term Work includes all labor necessary to produce

the construction required by the Contract Documents, and

all materials and equipment incorporated or to be in-

corporated in such construction.

en

5la

11.4 THE PROJECT

The Project is the total construction designed by the

Architect of which the Work performed under the Con-

tract Documents may be the whole or a part.

12 EXECUTION, CORRELATION, INTENT AND

INTERPRETATIONS

1.2.1. The Contract Documents shall be signed in not

less than triplicate by the Owner and Contractor. If

either the Owner or the Contractor or both do not sign

the Conditions of the Contract. Drawings, Specifications,

or any of the other Contract Documents, the Architect

shall identify them.

1.2.2 By executing the Contract, the Contractor repre-

sents that he has visited the site, familiarized himself

with the local conditions under which the Work is to be

performed, and correlated his observations with the re-

quirements of the Contract Documents.

1.2.3. The Contract Documents are complementary, and

what is required by any one shall be as binding as if re-

quired by all. The intention of the Documents is to in-

clude all labor, materials, equipment and other items as

provided in Subparagraph 4.41 necessary for the proper

execution aid completion of the Work, it is not intended

that Work not covered under any heading, section, branch,

class or trade of the Specifications shall be supplied unless

it is required elsewhere in the Contract Documents or is

reasonably inferable therefrom as being necessary to pro-

duce the intended results. Words which have well-known

technical or trade meanings are used herein in accord-

ance with such vecognized meanings.

1.2.4 The organization of the Specifications into divi-

sions, sections and articles, and the arrangement of

Drawings, shall not control the Contractor in dividing

the Work among Subcontractors or in establishing the

extent of Work to be perfurmed by any trade.

52a

1.2.5 Written interpretations necessary for the proper

execution or progress of the Work, in the form of draw-

ings of otherwise, will be issued with reasonable prompt-

ness by the Architect and in accordance with any sched-

ule agreed upon. Either party to the Contract may make

written request to the Architect for such interpretations.

Such interpretations shall be consistent with and reason-

ably inferable from the Contract Documents, and may be

effected by Field Order.

1.3 COPIES FURNISHED AND OWNERSHIP

1.3.1 Unless otherwise provided in the Contract Docu-

ments. the Contractor will be furnished, free of charge,

ll copies of Drawings and Specifications reasonably nec-

essary for the execution of the Werk. .

1.3.2. All Drawings, Specifications and copies thereof

furnished by the Architect are and shall remain his prop-

erty. They are not to be used on any other project, and,

with the exception of one contract set for each party to

the Contract are to be returned to the Architect on re-

quest at the completion of the Work.

ARTICLE 2

ARCHITECT

2.1 DEFINITION

21.1 The Architect is the person or organization lic-

ensed to practice architecture and identified as such in

the Agreement and is referred to throughout the Con-

tract Documents as if singular in number and masculine

in gender. The term Architect means the Architect or his

authorized representative.

2.1.2 Nothing contained in the Contract Documents shall

create any contractual relationship between the Architect

and the Contractor.

58a

2.2 ADMINISTRATION OF THE CONTRACT

22.1 The Architect will provide general Administration

of the Construction Contract, including performance of

the functions hereinafter described.

2.2.2 The Architect will be the Owner’s representative

during construction and until final payment. The Archi-

tect will have authority to act on behalf of the Owner to

the extent provided in the Contract Documents, unless

otherwise modified by written instrument which will be

shown to the Contractor. The Architect will advise and

consult with the Owner, and all of the Owner’s instruc-

tions to the Contractor shall be issued through the

Architect.

2.2.3 The Architect shall at all times have access to the

Work wherever it is in preparation and progress. The

Contractor shall provide facilities for such access so the

Architect may perform his functions under the Contract

Documents.

2.2.4 The Architect will make periodic visits to the site

to familiarize himself generally with the progress and

quality of the Work and to determine in general if the

Work is proceeding in accordance with the Contract

Documents. On the basis of his on-site observations as

an architect, he will keep the Owner informed of the

progress of the Work, and will endeavor to guard the

Owner against defects and deficiencies in the Work of the

Contractor. The Architect will not be required to make

exhaustive or continuous on-site inspections to check the

quality or quantity of the Work. The Architect will not

be responsible for construction means, methods, tech-

niques, sequences or procedures, or for safety precautions

and programs in connection with the Work, and he will

not be responsible for the Contractor’s failure to carry

out the Work in accordance with the Contract Documents.

2995 Based on such observations and the Contractor’s

Applications for Payment, the Architect will determine

_

54a

the amounts owing to the Contractor and will issue Cer-

tificates for Payment in such amounts, as provided in

Paragraph 9.4.

2.2.6 The Architect will be, in the first instance, the

interpreter of the requirements of the Contract Docu-

ments and the judge of the performance thereunder by

both the Owner and Contractor. The Architect will,

within a reasonable time, render such interpretations as

he_may deem necessary for the proper execution or prog-

ress of the Work.

2.2.7 Claims, disputes and other matters in question be-

tween the Contractor and the Owner relating to the execu-

tion or progress of the Work or the interpretation of the

Contract Documents shall be referred initially to the

Architect for decision which he will render in writing

within a reasonable time.

2.2.8 All interpretations and decisions of the Architect

shall be consistent with the intent of the Contract Docu-

ments. In his capacity as interpreter and judge, he will

exercise his best efforts to insure faithful performance

by both the Owner and the Contractor and will not show

partiality to either.

2.2.9 The Architect’s decisions in matters relating to

artistic effect will be final if consistent with the intent

of the Contract Documents.

2.2.10 Any claim, dispute or other matter that has been

referred to the Architect, except those relating to artistic

effect as provided in Subparagraph 2.2.9 and except any

which have been waived by the making or acceptance of

final payment as provided in Subparagraphs 9.7.5 and

9.7.6, shall be subject to arbitration upon the written

demand of either party. However, no demand for arbitra-

tion of any such claim, dispute or other matter may be

made until the earlier of:

2.2.10.1 The date on which the Architect has rendered

his written decision, or

5dDa

.2 the tenth day after the parties have presented

their evidence to the Architect or have been

given a reasonable opportunity to do so, if the

Architect has not rendered his written decision

by that date.

2.2.11 If a decision of the Architect is made in writing

and states that it is final but subject to appeal, no de-

mand for arbitration of a claim, dispute or other matter

covered by such decision may be made later than thirty

days after the date on which the party making the de-

mand received the decision. The failure to demand arbi-

tration within said thirty days’ period will result in the

Architect’s decision becoming final and binding upon the

Owner and the Contractor. If the Architect renders a

decision after arbitration proceedings have been initiated,

such decision may be entered as evidence but will not

supersede any arbitration proceedings unless the decision

is acceptable to the parties concerned.

2.2.12 The Architect will have authority to reject Work

which does not conform to the Contract Documents.

Whenever, in his reasonable opinion, he considers it nec-

essary or advisable to insure the proper implementation

of the intent of the Contract Documents he will have

authority to require special inspection or testing of the

Work in accordance with Subparagraph 7.8.2. whether

or not such Work be then fabricated, installed or com-

pleted. However, neither the Architect’s authority to act

under this Subparagraph 2.2.12, nor any decision made

by him in good faith either to exercise or not to exercise

such authority, shall give rise to any duty or responsibil-

ity of the Architect to the Contractor, any Subcontractor,

any of their agents or employees, or any other person

performing any of the Work.

2.2.13 The Architect wil! review Shop Drawings and

Samples as provided in Subparagraphs 4.13.1 through

4.13.8 inclusive.

56a

2.2.14 The Architect will prepare Change Orders in

accordance with Article 12, and will have authority to

order minor changes in the Work as provided in Sub-

paragraph 12.3.1.

2.2.15 The Architect will conduct inspections to deter-

mine the dates of Substantial Completion and final com-

pletion, will receive and review written guarantees and

related documents required by the Contract and assem-

bled by the Contractor and will issue a final Certificate

for Payment.

2.2.16 If the Owner and Architect agree, the Architect

will provide one or more Full-Time Project Representa-

tives to assist the Architect in carrying out his responsi-

bilities at the site. The duties, responsibilities and limita-

tions of authority of any such Project Representative

shall be as set forth in an exhibit to be incorporated in

the Contract Documents.

2.2.17 The duties, responsibilities and limitations of au-

thority of theArchitect as the Owner’s representative dur-

ing construction as set forth in Articles 1 through 14

inclusive of these General Conditions will not be modified

or extended without written consent of the Owner, the

Contractor and the Architect.

2.2.18 The Architect will not be responsible for the acts

or omissions of the Contractor, any Subcontractors, or

any of their agents or employees, or any other persons

performing any of the Work.

2.2.19 In case of the termination of the employment of

the Architect, the Owner shall appoint an architect

against whom the Contractor makes no reasonable objec-

tion whose status under the Contract Documents shall be

that of the former architect. Any dispute in connection

with such appointment shall be subject to arbitration.

57a

ARTICLE 3

OWNER

3.1 DEFINITION

3.1.1 The Owner is the person or organization identified

as such in the Agreement and is referred to throughout

the Contract Documents as if singular in number and

masculine in gender. The term Owner means the Owner

or his authorized representative.

3.2 INFORMATION AND SERVICES REQUIRED OF

THE OWNER

3.2.1 The Owner shall furnish all surveys describing

the physical characteristics, legal limits and utility loca-

tions for the site of the Project.

3.2.2 The Owner shall secure and pay for easements for

permanent structures or permanent changes in existing

facilities.

3.2.3. Information or services under the Owner’s control

shall be furnished by the Owner with reasonable prompt-

ness t6 avoid delay in the orderly progress of the Work.

3.2.4 The Owner shall issue all instructions to the Con-

tractor through the Architect.

3.2.5 The foregoing are in addition to other duties and

responsibilities of the Owner enumerated herein and espe-

cially those in respect to Payment and Insurance in Arti-

cles 9 and 11 respectively.

3.3 OWNER’S RIGHT TO STOP THE WORK

3.3.1 If the Contractor fails to correct defective Work

or persistently fails to supply materials or equipment in

accordance with the Contract Documents, the Owner may

order the Contractor to stop the Work, or any portion

thereof, until the cause for such order has been elimi-

nated.

58a

3.4 OWNER’S RIGHT To CARRY OUT THE WORK

3.4.1 If the Contractor defaults or neglects to carry out

the Work in accordance with the Contract Documents or

fails to perform any provision of the Contract, the Owner

may, after seven days’ written notice to the Contractor

and without prejudice to any other remedy he may have,

make good such deficiencies. In such case an appropriate

Change Order shall be issued deducting from the pay-

ments then or thereafter due the Contractor the cost of

correcting such deficiencies, including the cost of the Ar-

chitect’s additional services made necessary by such de-

fault, neglect or failure. The Architect must approve

both such action and the amount charged to the Contrac-

tor. If the payments then or thereafter due the Contrac-

tor are not sufficient to cover such amount, the Contractor

shall pay the difference to the Owner.

ARTICLE 4

CONTRACTOR

4.1 DEFINITION

4.1.1 The Contractor is the person or organization iden-

tified as such in the Agreement and is referred to

throughout the Contract Documents as if singular in

number and masculine in gender. The term Contractor

means the Contractor or his authorized representative.

4.2 REVIEW OF CONTRACT DOCUMENTS

4.2.1. The Contractor shall carefully study and compare

the Contract Documents and shall at once report to the

Architect any error, inconsistency or omission he may

discover. The Contractor shall not be liable to the Owner

or the Architect for any damage resulting from any such

errors, inconsistencies or omissions in the Contract Docu-

ments. The Contractor shall do no Work without Draw-

ings. Specifications or Modifications.

59a

4.3 SUPERVISION AND CONSTRUCTION PROCE-

DURES

4.3.1 The Contractor shall supervise and direct the

Work, using his best skill and attention. He shall be

solely responsible for all construction means, methods,

techniques, sequences and procedures and for coordinat-

ing all portions of the Work under the Contract.

4.4 LABOR AND MATERIALS

4.4.1 Unless otherwise specifically noted, the Contractor

shall provide and pay for all labor, materials, equipment,

tools, construction equipment and machinery, water, heat,

utilities, transportation, and other facilities and services

necessary for the proper execution and completion of the

Work.

4.4.2 The Contractor shall at all times enforce strict

discipline and good order among his employees and shall

not employ on the Work any unfit person or anyone not

skilled in the task assigned to him.

4.5 WARRANTY

4.5.1 The Contractor warrants to the Owner and the

under this Contract will be new unless otherwise speci-

fied, and that all Work will be of good quality, free from

faults and defects and in conformance with the Contract

Documents. All Work not so conforming to these stand-

ards may be considered defective. If required by the

Architect, the Contractor shall furnish satisfactory evi-

dence as to the kind and quality of materials and equip-

ment. 7

4.6 TAXES

4.6.1. The Contractor shall pay all sales, consumer, use

and other similar taxes required by law.

-

60a

4.7 PERMITS, FEES AND NOTICES

4.7.1 The Coniractor shall secure and pay for all per-

mits, governmental fees and licenses necessary for the

proper execution und completion of the Work, which are

applicable at the time the bids are received. It is not the

responsibility of the Contractor to make certain that the

Drawings and Specifications are in accordance with ap-

plicable laws, statutes, building codes and regulations.

4.7.2. The Contractor shall give all notices and comply

with all laws, ordinances, rules, regulations and orders

of any public authority bearing on the performance of

the Work. If the Contractor observes that any of the

Contract Documents are at variance therewith in any re-

spect, he shall promptly notify the Architect in. writing,

and any necessary changes shall be adjusted by appropri-

ate Modification. If the Contractor performs any Work

knowing it to be contrary to such laws, ordinances, rules

and regulations, and without such notice to the Architect,

he shall assume full responsibility therefor and shall bear

all costs attributable thereto.

4.8 CASH ALLOWANCES

4.8.1 The Contractor shall include in the Contract Sum

all allowarces stated in the Contract Documents. These

allowances shall cover the net cost of the materials and

equipment delivered and unloaded at the site, and all ap-

plicable taxes. The Contractor’s handling costs on the

site, labor, installation costs, overhead, profit and other

expenses contemplated for the original allowance shall be

included in the Contract Sum and not in the allowance.

The Contractor shal’ cause the Work covered by these

allowances to be performed for such amounts and by such

persons as the Architect may direct, but he will not be

required to employ persons against whom he makes a rea-

sonable objection. If the cost, when determined, is more

than or less than the allowance, the Contract Sum shal!

be adjusted accordingly by Change Order which svil! in-

6la

clude additional handling costs on the site, labor, installa-

tion costs, overhead, profit and other expenses resulting

to the Contractor from any increase over the original

allowance.

4.9 SUPERINTENDENT

4.9.1 The Contractor shall employ a competent superin-

tendent and necessary assistants who shall be in attend-

ance at the Project site during the progress of the Work.

The superintendent shall be satisfactory to the Architect,

and shall not be changed except with the consent of the

Architect, unless the superintendent proves to be unsatis-

factory to the Contractor and ceases to be in his employ.

The superintendent shall represent the Contractor and

all communications given to the superintendent shall be

as binding as if given to the Contractor. Important com-

munications will be confirmed in writing. Other commu-

nications will be so confirmed on written request in each

ease,

4.10 RESPONSIBILITY FOR THOSE PERFORMING

THE WORK

4.10.1. The Contractor shall be responsible to the Owner

for the acts and omissions of all his employees and all

Subcontractors, their agents and employees, and all other

persons performing any of the Work under a contract

with the Contractor.

4.11 PROGRESS SCHEDULE

4.11.1 The Contractor, immediately after being awarded

the Contact, shall prepare and submit for the Architect’s

approval an estimated progress schedule for the Work.

The progress schedule shall be related to the entire

Project to the extent required by the Contract Documents.

This schedule shall indicate the dates for the starting and

completion of the various stages of construction and shall

be revised as required by the conditions of the Work,

subject to the Architect’s approval.

62a

4.12 DRAWINGS AND SPECIFICATIONS AT THE

SITE

4.12.1 The Contractor shall maintain at the site fer the

Owner one copy of all Drawings, Specifications, Addenda,

approved Shop Drawings, Change Orders and other Modi-

fications, in good order and marked to record all changes

made during construction. These shall be available to the

Architect. The Drawings, marked to record all changes

made during construction, shall be delivered to him for

the Owner upon completion of the Work.

4.13 SHOP DRAWINGS AND SAMPLES

4.13.1 Shop Drawings are drawings, diagrams, illustra-

tions, schedules, performance charts, brochures and other

- data which are prepared by the Contractor or any Sub-

contractor, manufacturer, supplier or distributor, and

which illustrate some portion of the Work.

4.13.2. Samples are physical examples furnished by the

Contractor to illustrate materials, equipment or work-

manship, and to establish standards by which the Work

will be judged.

4.13.38 The Contractor shall review, stamp with his ap-

proval and submit, with reasonable promptness and in

orderly sequence so as to cause no delay in the Work or

in the work of any other contractor, all Shop Drawings

and Samples required by the Contract Documents or sub-

sequently by the Architect as covered by *Modifications.

Shop Drawings and Samples shall be properly identified

as specified, or as the Architect may require. At the time

of submission the Contractor shall inform the Architect

in writing of any deviation in Shop Drawings or

Samples from the requirements of the Contract Docu-

ments.

4.13.4 By approving and submitting Shop Drawings and

Samples, the Contractor thereby represents that he has

determined and verified all field measurements, field con-

struction criteria, materials, catalog numbers and similar

68a

data, or will do so, and that he has checked and coordi-

nated each Shop Drawing and Sample with the require-

ments of the Work and of the Contract Documents.

4.13.5 The Architect will review and approve Shop

Drawings and Samples with reasonable promptness so as

to cause no delay, but only for conformance with the de-

sign concept of the Project and with the information given

in the Contract Documents. The Architect’s approval of a

separate item shall not indicate approval of an assembly

in which the item functions.

4.13.6 The Contractor shall make any corrections re-

quired by the Architect and shall submit the required

number of corrected copies of Shop Drawings or new

Samples unti*approved. The Contractor shall direct spe-

cific attention in writing or on resubmitted Shop Draw-

ings to revisions other than the corrections requested by

the Architect on previous submissions.

4.13.7 The Architect’s approval of Shop Drawings or

Samples shall not relieve the Contractor of responsibility

for any deviation from the requirements of the Contract

Documents unless the Contractor has informed the Archi-

tect in writing of such deviation at the time of submis-

sion and the Architect has given written approval to the

specific deviation, nor shall the Architect’s approval re=

lieve the Contractor from responsibility for errors or «

omissions in the Shop Drawings or Samples.

4.13.8 No portion of the Work requiring a Shop Draw-

ing or Sample submission shall be commenced until the

submission has been approved by the Architect. All such

portions of the Work shall be in accordance with ap-

proved Shop Drawings and Samples.

4.14 USE OF SITE

4.14.1 The Contractor shall confine operations at the

site to areasepermitted by law, ordinances, permits and

the Contract Documents and shall not unreasonably en-

cumber the site with any materials or equipment.

64a

4.15 CUTTING AND PATCHING OF WORK

115.1 The Contractor shal! do all cutting, fitting or

patching of his Work that may be required to make its

several parts fit together properly, and shall not endanger

uny Work by cutting, excavating or otherwise altering the

Work or any part of it.

1.16 CLEANING UP

1.16.1 The Contractor at all times shall keep the prem-

ives free from accumulation of waste materials or rub-

hish cansed by his operations. At the completion of the

Work he shall remove all his waste materials and rub-

bish from and about the Project as well as all his tools,

construciion gevipment, machinery and surplus materials,

and shall clean all glass surfaces and leave the Work

“broom-clean” or its equivalent, except as otherwise

snecified, ome

110.2 if the Contractor fails to clean up, the Owner

nay de so and the cost thereof shall be charged to the

Contracler as provided in Paragraph 3.4.

iL17 COMMUNICATIONS

4.17.1 The Contractor shall forward all communications

to the Owner through the Architect.

118 INDEMNIFICATION

4.18.1 The Contractor shall indemnify and hold harmless

the Owner and the Architect and their agents and em-

ployees from and against all claims, damages, losses and

expenses inciuding attorneys’ fees arising out of or re-

sulting from the performance of the Work, provided that

any such claim, damage, loss or expenses (1) is attributa-

ble to bodily injury, sickness, disease or death, or to in-

jury to or destruction of tangible property (other than

the Work itself) including the loss of use ‘resulting there-

from, and (2) is caused in whole or in part by any negli-

65a

gent act or omission of the Contractor, any Subcontrac-

tor, anyone directly or indirectly employed by any of

them or anyone for whose acts any of them may be liable,

regardless of whether or not it is caused in part by a

party indemnified hereunder.

4.18.2 In any an@# all claims against the Owner or the

Architect or any of their agents or employees by any em-

ployee of the Contractor, any Subcontractor, anyone di-

rectly or indirectly employed by any of them or anyone

for whose acts any of them may be liable, the indemnifi-

cation obligation under this Paragraph 4.18 shall not be

limited in any way by any limitation on the amount or

type of damages, compensation or benefits payable by

or for the Contractor or any Subcontractor under work-

men’s compensation acts, disability benefit acts or other

employee benefit acts.

4.18.3 The obligations of the Contractor under this Par-

agraph 4.18 shall not extend to the liability of the Archi-

tect, his agents or employees arising out of (1) the prepa-

ration or approval of maps, drawings, opinions, reports,

surveys. Change Orders, designs or specifications, or (2)

the giving of or the failure to give directions or instruc-

tions by the Architect, his agents or employees provided

such giving ow failure to give is the primary cause of the

injury or damage.

ARTICLE 5

SUBCONTRACTORS

5.1 DEFINITION

5.1.1 A Subcontractor is a person or organization who

has a direct contract with the Contractor to perform any

of the Work at the site. The term Subcontractor is re-

ferred to throughout the Contract Documents as if singu-

lar in number and masculine in gender and means a Sub-

contractor or his authorized representative.

66a

5.1.2 A Sub-subcontractor is a person or organization

who has a direct or indirect contract with a Subcontractor

to perform any of the Work at the site. The term Sub-

subeontractor is referred to throughout the Contract Doce-

uments as if singular in number and masculine in gender

and means a Sub-subcontractor or an authorized repre-

sentative thereof.

5.1.8 Nothing contained in the Contract Documents shall

create any contractual relation between the Owner or the

Architect and any Subcontractor or Sub-subcontractor.

5.2 AWARD OF SUBCONTRACTS AND OTHER

CONTRACTS FOR PORTIONS OF THE WORK

5.2.1 Unless otherwise specified in the Contract Docu-

ments or in the Instructions to Bidders, the Contractor,

as soon as practicable after the award of the Contract,

shall furnish to the Architect in writing for acceptance

by the Owner and the Architect a list of the names of the

Subcontractors proposed for the principal portions of the

Work. The Architect shall promptly notify the Contractor

in writing if either the Owner or the Architect, after due

investigation, has reasonable objection to any Subcontrac-

tor on such list and does not accept him. Failure of the

Owner or Architect to make objection promptly to any

Subcontractor on the list shall constitute acceptance of

such Subcontractor.

5.2.2 The Contractor shall not contract with any Sub-

contractor or any person or organization (including those

who are to furnish materials or equipment fabricated to

a special design) proposed for portions of the Work

designated in the Contract Documents or in the instruc-

tions to Bidders or, if none is no designated, with any

Subcontractor provosed for the principal portions of the

Work who has been rejected by the Owner and the Ar-

chitect. The Contractor will not be required to contract

with any Subcontractor or person or organization against

whom he has a reasonable objection.

67a

5.2.3 If the Owner or Architect refuses to accept any

Subcontractor or person or organization on a list sub-

mitted by the Contractor in response to the requirements

of the Contract Documents or the instructions to Bidders,

the Contractor shall submit an acceptable substitute and

the Contract Sum shall be increased or decreased by the

difference in cost occasioned by such substitution and an

Appropriate Change Order shall be issued; however, no

increase in the Contract Sum shall be allowed for any

such substitution unless the Contractor has acted promptly

and responsively in submitting for acceptance any list

or lists of names as required by the Contract Documents

or the instructions to Bidders.

5.2.4 If the Owner or the Architect requires a change of

any proposed Subcontractor or person or organization

previously accepted by them. the Contract Sum shall be

increased or decreased by the difference in cost occa-

sioned by such change and an appropriate Change Order

shall be issued.

5.2.5 The Contractor shall not make any substitution for

any Subcontractor or person or organization who has

been accepted by the Owner and the Architect, unless

the substitution is acceptable to the Owner and the Archi-

tect.

5.8 SUBCONTRACTUAL RELATIONS

5.3.1 All work performed for the Contractor by a Sub-

contractor shall be pursuant to an appropriate agree-

ment between the Contractor and the Subcontractor (and

where appropriate between Subcontractors and Sub-

subcontractors) which shall contain provisions that:

.l preserve and protect the rights of the Owner and

the Architect under the Contract with respect to

the Work to be performed under the subcontract

so that the subcontracting thereof will not preju-

dice such rights;

68a

bo

require that such Work be performed in accord-

ance with the requirements of the Contract Docu-

ments;

.38 require submission to the Contractor of applica-

tions for payment under each subcontract to which

the Contractor is a party, in reasonable time to

enable the Contractor to apply for payment in ac-

cordance with Article 9;

4 require that all claims for additional costs, exten-

sions of time, damages for delays or otherwise

with respect to subcontracted portions of the Work

shal be submitted to the Contractor (via any Sub-

contractor or Sub-subcontractor where appropriate)

in sufficient time so that the Contractor may comply

in the manner provided in the Contract Documents

for like claims by the Contractor upon the Owner;

5. waive all rights the contracting parties may have

against one another for damages caused by fire or

other perils covered by the property insurance de-

scribed in Paragraph 11.3 except such rights as they

may have to the proceeds of such insurance held

by the Owner as trustee under Paragraph 11.3; and

.6 obligate such Subcontractor specifically to consent

to the provisions of this Paragraph 5.3.

5.4 PAYMENTS TO SUBCONTRACTORS

5.4.1 The Contractor shall pay each Subcontractor, upon

receipt of payment from the Owner, an amount equal to

the percentage of completion allowed to the Contractor on

account of such Subcontractor’s Work, less the percentage

retained from payments to the Contractor. The Con-

tractor shall also require each Subcontractor to make

similar payments to his subcontractors.

5.4.2 If the Architect fails to issue a Certificate for Pay-

ment for any cause which is the fault of the Contractor

69a

and not the fault of a particular Subcontractor, the Con-

tractor shall pay that Subcontractor on demand, made at

any time after the Certificate for Payment should other-

wise have been issued, for his Work to the extent com-

pleted, less the retained percentage.

5.4.3 The Contractor shall pay each Subcontractor a

just share of any insurance moneys received by the Con-

tractor under Article 11, and he shall require each Sub-

contractor to make similar payments to his subcontractors.

5.4.4 The Architect may, on request and at his discre-

tion, furnish to any Subcontractor, if practicable, infor-

mation regarding percentages of completion certified to

the Contractor on account of Work done by such Subcon-

tractors.

5.4.5 Neither the Owner nor the Architect shall have any

obligation to pay or to see to the payment of any moneys

to any Subcontractor except as may otherwise be required

by law.

ARTICLE 6

SEPARATE CONTRACTS

6.1 OWNER’S RIGHT TO AWARD SEPARATE CON-

TRACTS

6.1.1 The Owner reserves the right to award other con-

tracts in connection with other portions of the Project

under these or similar Conditions of the Contract.

6.1.2 When separate contracts are awarded for different

portions of the Project, “the Contractor” in the contract

documents in each case shall be the contractor who signs

each separate contract.

6.2 MUTUAL RESPONSIBILITY OF CONTRACTORS

6.2.1. The Contractor shall afford other contractors rea-

sonable opportunity for the introduction and storage of

70a

their materials and equipment and the execution of their

work, and shall properly connect and coordinate his Work

with theirs.

6.2.2 If any part of the Contractor’s Work depends for

proper execution or results upon the work of any other

separate contractor, the Contractor shall inspect and

promptly report to the Architect any apparent discrepan-

cies or defects in such work that render it unsuitable for

such proper execution and results. Failure of the Con-

tractor so to inspect and report shall constitute an ac-

ceptance of the other contractor’s work as fit and proper

to receive his Work, except as to defects which may de-

velop in the other separate contractor’s work after the

execution of the Contractor’s Work.

6.2.3 Should the Contractor cause damage to the work

or property of any separate contractor on the Project, the

Contractor shall, upon due notice, settle with such other

contractor by agreement or arbitration, if he will so set-

tle. If such separate contractor sues the Owner or ini-

tiates an arbitration proceeding on account of any dam-

age alleged to have been so sustained, the Owner shall

notify the Contractor who shall defend such proceedings

at the Owner’s expense, and if any judgment or award

against the Owner arises therefrom the Contractor shall

pay or satisfy it and shali reimburse the Owner for all

attorneys’ fees and court or arbitration costs which the

Owner has incurred.

6.3 CUTTING AND PATCHING UNDER SEPARATE

CONTRACTS

6.3.1 The Contractor shall be responsible for any cut-

ting, fitting and patching that may be required to com-

plete his Work except as otherwise specifically provided

in the Contract Documents. The Contractor shall not

endanger any work of any other contractors by cutting,

excavating or otherwise altering any work and shall not

z

-

‘

7la

cut or alter the work of any other contractor except with

the written consent of the Architect.

6.3.2 Any costs caused by defective or ill-timed work

shall be borne by the party responsible therefor.

6.4 OWNER’S RIGHT TO CLEAN UP

6.4.1 Ifa dispute arises between the separate contractors

as to their responsibility for cleaning up as required by

Paragraph 4.16, the Owner may clean up and charge the

cost thereof to the several contractors as the Architect

shall determine to be just.

ARTICLE 7

MISCELLANEOUS PROVISIONS

7.1 GOVERNING LAW

7.1.1 The Contract shall be governed by the law of the

place where the Project is located.

7.2 SUCCESSORS AND ASSIGNS

7.2.1 The Owner and the Contractor each binds himself,

his partners, successors, assigns and legal representatives

to the other party hereto and to the partners, successors,

assigns and legal representatives of such other party in

respect to all covenants, agreements and obligations con-

tained in the Contract Documents. Neither party to the

Contract shall assign the Contract or sublet it as a whole

without the written consent of the other, nor shall the

Contractor assign any moneys due or to become due to

him hereunder, without the previous written consent of

the Owner.

7.3 WRITTEN NOTICE

7.3.1 Written notice shall be deemed to have been duly

served if delivered in person to the individual or member

72a

of the firm or to an officer of the corporation for whom

it was intended, or if delivered at or sent by registered

or certified mail to the last business address known to him

who gives the notice.

7.4 CLAIMS FOR DAMAGES

7.4.1 Should either party to the Contracts suffer injury

or damage to person or property because of any act or

omission of the other party or of any of his employees,

agents or others for whose acts he is legally liable, claim

shall be made in writing to such other party within a rea-

sonable time after the first observance of such injury or

damage.

7.5 PERFORMANCE BOND AND LABOR AND MA-

TERIAL PAYMENT BOND

7.5.1 The Owner shall have the right to require the Con-

tractor to furnish bonds covering the faithful perform-

ance of the Contract and the payment of all obligations

arising thereunder if and as required in the instruction

to Bidders or elsewhere in the Contract Documents.

7.6 RIGHTS AND REMEDIES

7.6.1 The duties and obligations imposed by the Contract

Documents and the rights and remedies available there-

under shall be in addition to and not a limitation of any

duties, obligations, rights and remedies otherwise im-

posed or available by law.

7.7 ROYALTIES AND PATENTS

7.7.1. The Contractor shall pay all royalties and license

fees. He shall defend all suits or claims for infringement

of any patent rights and shall save the Owner harmless

from loss on account thereof, except that the Owner shall

be responsible for all such loss when a particular design,

process or the product of a particular manufacturer or

73a

manufacturers is specified, but if the Contractor has rea-

son to believe that the design, process or product specified

is an infringement of a pttent, he shall be responsible for

such loss unless he promptly gives such information to

the Architect.

7.8 TESTS

7.8.1 If the Contract Documents, laws, ordinances, rules,

regulations or orders of any public authority having juris-

diction require any Work to be inspected, tested or ap-

proved, the Contractor shall give the Architect timely no-

tice of its readiness and of the date arranged so the

Architect may observe such inspection, testing or ap-

proval. The Contractor shall bear all costs of such inspec-

tions, tests and approvals unless otherwise provided.”

7.8.2 If after the commencement of the Work the Archi-

tect determines that any Work requires special inspec-

tion, testing, or approval which Subparagraph 7.8.1 does

not include, he will, upon written authorization from the

Owner, instruct the Contractor to order such special in-

spection, testing or approval, and the Contractor shall

give notice as in Subparagraph 7.8.1. If such special in-

spection or testing reveals a failure of the Work to com-

ply (1) with the requirements of the Contract Documents

or (2) with respect to the performance of the Work,

with laws, ordinances, rules, regulations or orders of any

publie authority having jurisdiction, the Contractor shall

bear all costs thereof, including the Architect’s additional

services made necessary by such failure: otherwise the

Owner shall bear such costs, and an appropriate Change

Order shall be issued.

7.8.3 Required certificates of inspection, testing or ap-

proval shall be secured by the Contractor and promptly

delivered by him to the Architect.

ST

74a

7.8.4 If the Architect wishes to observe the inspections,

tests or approvals required by this Paragraph 7.8, he will

do so promptly and, where practicable, at the source of

supply.

7.8.5 Neither the observations of the Architect in his

Administration of the Construction Contract, nor inspec-

tions, tests or approvals by persons other than the Con-

tractor shall relieve the Contractor from his obligations

to perform the Work in accordance with the Contract

Documents.

7.9 INTEREST

7.9.1 Any moneys not paid when due to either party

under this Contract shall bear interest at the legal rate

in force at the place of the Project.

7.10 ARBITRATION

7.10.1 All claims, disputes and other matters in question

arising out of, or relating to, this Contract or the breach

thereof, except as set forth in Subparagraph 229 with

respect to the Architect’s decisions on matters relating to

artistic effect, and except for claims which have been

waived by the making or acceptance of final payment as

provided by Subparagraphs 975 and 976 shall be decided

by arbitration in accordance with the Construction In-

dustry Arbitration Rules of the American Arbitration

Association then obtaining unless the parties mutually

agree otherwise. This agreement to arbitrate shall be

specifically enforceable under the prevailing arbitrat:on

iaw. The award rendered by the arbitrators shall be final,

and judgment may be entered upon it in accordance

with applicable law in any court having jurisdiction

thereof.

7.10.2 Notice of the demand for arbitration shall be

filed in writing with the other party to the Contract and

75a

with the American Arbitration Association, and a copy

shall be filed with the Architect. The demand for arbi-

tration shall be made within the time limits specified in

Subparagraphs 2.210 and 2.211 where applicable, and in

all other cases within a reasonable time after the claim,

dispute or other matter in question has arisen, and in no

event shall it be made after the date when institution of

legal or equitable proceedings based on each claim, dis-

pute or other matter in question would be barred by the

applicable statute of limitations.

7.10.3 The Contractor shall carry on the Work and

maintain the progress schedule during any arbitration

proceedings, unless otherwise agreed by him and the

Owner in writing.

ARTICLE 8

TIME

8.1 DEFINITIONS

8.1.1 The Contract Time is the period of time alloted in

the Contract Documents for completion of the Work.

8.1.2 The date of commencement of the Work is the

date established in a notice to proceed. If there is no

notice to proceed, it shall be the date of the Agreement

or such other date as may be established therein.

8.1.3 The Date of Substantial Completion of the Work

or designated portion thereof is the Date certified by the

Architect when construction is sufficiently complete, in

accordance with the Contract Document, so the Owner

may occupy the Work or designated portion thereof for

the use for which it is intended.

8.1.4 The term day as used in the Contract Documents

shall mean calendar day.

76a

8.2 PROCESS AND COMPLETION

8.2.1 All time limits stated in the Contract Documents

are of the essence of the Contract.

8.2.2 The Contractor shall begin the Work on the date

of commencement as defined in Subparagraph 8.1.2. He

shall carry the Work forward expeditiously with adequate

forces and shall complete it within the Contract Time.

8.2.3 If a date or time of completion is included in the

Contract, ii shall be the Date of Substantial Completion

as defined in Subparagraph 8.1.3, including authorized

extensions thereto, unless otherwise provided.

8.3

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.