Petition for Writ of Certiorari — North Dakota and South Dakota v. United States Army Corps of Engineers (No. 05-611)
Supreme Court brief2005
Ask Donna
What actually matters in this document.
Text
5
Construction of Missouri River dams came at a price.
They were built “at great cost to the upper Missouri basin
states and their inhabitants.” Robert E. Beck, A Book
Review of River of Promise, River of Peril: The Politics of
Managing the Missouri River, 1 Great Plains Nat. Re-
sources J. 477, 479 (1996). South Dakota lost 520,000
acres to the reservoirs and North Dakota sacrificed 584,060
acres. Id. Huge amounts of rich farm land as well as towns
were inundated. Flooding riparian lands upset “it/he
ecological balance of the entire region, and that of the
Dakotas in particular.” Michael L. Lawson, Dammed
Indians: The Pick-Sloan Plan and the Missouri River
Sioux, 1944-1980, at 194 (1982). “The inundation of
precious forests and bottomlands not only eliminated the
natural wildlife habitat but also created serious erosion
problems.” Jd. Lake Sakakawea’s cut banks erode at rates
as high as 19 feet a year. JA 07287. The Mandan, Hidatsa,
and Arikara Nation describes the erosion as “‘extensive.’”
Id. Thus, the loss of agricultural land in the upper basin
continues and unstable banks expose and destroy sacred
and cultural sites. JA 08421-22, 08434-44 (Tribal Stmts.).”
For their sacrifices, the upper basin states were to
receive massive irrigation projects. E.g., ETSI Pipeline
Project v. Missouri, 484 U.S. 495, 508 (1988); James River
Flood Control Ass'n v. Watt, 553 F.Supp. 1284, 1287
(D.S.D. 1982). This promise remains unfulfilled. E.g.,
ETSI Pipeline, 484 U.S. at 509, n.5; North Dakota, 270
* Citations to “JA” are to the Joint Appendix filed with the court
below. Unless otherwise noted, all Joint Appendix citations are to the
Corps’ 2004 Final Environmental Impact Statement. Citations to “ND
App.” are to the appendix North Dakota filed with the court below
F.Supp.2d at 1129. Without question, “the upper basin
states and ... tribes have been short-changed in the
management of the Missouri River.” Beck, supra, at 490.
Though the promised irrigation never occurred, up-
stream states developed the reservoirs into recreation
destinations. JA 07390; North Dakota, 270 F.Supp.2d at
1129. The primary attraction is fishing. JA 07392. The
reservoirs are world class sport fisheries. North Dakota, 270
F.Supp.2d at 1129; JA 07363. Anglers in turn support busi-
nesses near and on the road to the reservoirs. JA 07390.
The economic value provided by Missouri River recrea-
tion is significant, even though it has yet to fully develop.
The Corps sets the river’s annual recreation value at $87
million. JA 07198. South Dakota sets the annual value of its
Missouri River fishery at $51 milion. North Dakota, 270
F. Supp. 2d at 1130. North Dakota calculates the annual
value of Lake Sakakawea’s fishery to be at least $23 million.
Id. at 1129; JA 00133-35 (Schultz Aff.). Low elevations can
cost the states millions of dollars a year. Jd. at 00134-35.
Upstream facilities have other important purposes. For
example, the dams produce hydropower worth $674 million a
year. JA 07195-96. Hydropower generating capacity depends
on water elevations in the reservoirs, that is, the “head.” JA
07385. As the elevation declines the head decreases, drop-
ping generating capacity proportionally. Jd. The more water
retained in the reservoirs, the better able the Corps can
satisfy the Flood Control Act’s hydropower objectives. See,
e.g., JA 05081 (NAS Study); JA 00033 (GAO Report).
The lower basin’s attempt to develop a viable down-
stream navigation industry has failed. Despite the fact that
years ago the government built in the lower basin a naviga-
tion channel and continues to maintain it, navigation,
which requires “lavish amounts of water, [has] not devel-
oped into an enterprise of noticeable size or need.” John H.
Davidson & Thomas Ear! Geu, The Missouri River and
Adaptive Management: Protecting Ecological Function and
Legal Process, 80 Neb. L. Rev. 816, 836 (2001). Maintain-
ing a navigation channel costs the Corps about $7 million
a year, see JA 07274, while the navigation industry has an
annual value of only $9 million. JA 07195. Missouri River
commerce delivers less than 1% of the river’s economic
benefits. See JA 07193-98, 07859. The $7 million it costs
the public to maintain a navigation channel is near the
diminishing industrys $9 million value. Indeed, the
industry may have an annual value of only $1-2 million.
Thorson, supra, at 125 n.13.
The industry is not only small, it has been declining
for some time, “will continue to decline greatly, and is of
little, if any, net economic value.” South Dakota v. Ubbe-
lohde, CIV No. 02-3011, Prelim. Inj. at 7-8 (D.S.D. May 14,
2002). Navigation tonnage peaked in 1977 at 3.3 million
tons. JA 07408. Less than two million tons of commercial
goods have been transported annually since 1988, and in
2002 and 2003 only 1.1 million tons were transported. JA
08701 (Master Manval). The Missouri, despite its volume
of water, its length, and the money spent on it, carries
much less commerce than many other rivers. JA 01351-52
(Stearns Report). For example, from 1940 to 1996 Missis-
sippi River commerce rose from 30 million to 520 million
tons. JA 07411.
A district court describes the economic value of down-
stream navigation as “rather meager.” South Dakota v.
Ubbelohde, CIV No. 02-3011, Prelim. Inj. at 7 (D.S.D. May
14, 2002). Commentators describe the industry as “mori-
bund,” “an experiment that has failed,” and “the army’s
8
bad joke.” Brian Morris, Unanswered Prayers: The Upper
Missouri River Basin States Take on the U.S. Army Corps
of Engineers, 68 N.D. L. Rev. 897, 935 (1992); Davidson &
Geu, supra, at 836; Lawson, supra, at 187. But under the
ruling below, relying on an incorrect reading of the 1944
Act, the Missouri River is to be managed largely for a
stagnant navigation industry, at the expense of other more
valuable and widespread uses.
D. Litigation History
While the allure of trophy walleye drives upstream
recreation, the walleye cannot survive without its primary
food source, the rainbow smelt. The smelt spawn occurs
each spring when the smelt lay their eggs near the sur-
face. South Dakota v. Ubbelohde, 330 F.3d 1014, 1021 (8th
Cir. 2003). If the water recedes the eggs will die after a few
minutes of exposure to the air. Jd. A successful smelt
spawn requires stable or rising water. In 2002 the Corps
threatened to destroy the smelt and sacrifice upstream
fisheries by sending water downstream for navigation. If
the smelt population crashed, the economic consequences
would be devastating. JA 00135 (Schultz Aff.); North
Dakota, 270 F.Supp.2d at 1130. The threat to the smelt
triggered litigation. App. at 6.
To protect its spawn, South Dakota obtained an
injunction prohibiting the Corps from drawing down South
Dakota reservoirs. /d. In response, the Corps intended to
draw down North Dakota's Lake Sakakawea and Mon-
tana’s Ft. Peck Reservoir. To protect their fisheries, these
two states obtained injunctions. Jd. A successful smelt
spawn, however, is not the Dakotas only concern. “Water
levels are a key factor in use of the lakes ... At low lake
9
levels, some boat ramps are unusable.... For aesthetic
reasons, some visitors are less likely to frequent lakes . . .
Certain kinds of fishing and hunting are dependent upon
lake levels.” JA 07390.*
After the upstream states sued, Nebraska filed an
action in the District of Nebraska. The State of Missouri
intervened. The Nebraska District Court ordered the
Corps to comply with its 1979 Missouri River Master
Manual. App. at 6. Faced with several injunctions, the
Corps appealed.
In 2003 and while the appeal was pending, Montana
dismissed its suit but new suits were filed. Private down-
stream interests, led by Blaske Marine, Inc., sued federal
agencies and the upper basin states. See App. at 36, 59-60,
65-68, 75-87. Among their claims were challenges to
walleye stocking programs in the upper basin and agency
decisions under the Endangered Species Act (“ESA”),
NEPA, and the 1944 Flood Control Act. North Dakota
brought a second suit. Lake Sakakawea’s draw down
* Low water has interrupted drinking water supplies. In November
of 2003 North Dakota communities on Lake Oahe lost their water.
About 10,000 Sioux County residents and the towns of Fort Yates,
Cannon Ball, and Porcupine were affected. M. Albrecht, Reserve
Supplies Are Running Dry, Bismarck Trib. 1A (Nov. 26, 2003). See also
JA 08430 (Tribal Stmt.) In 2003 a week-long dredging project protected
the city of Mandan’s intake. L. Donovan, Mandan Water In Jeopardy,
Bismarck Trib. 1A (Sept. 24, 2003); R. Hinton, Dredging Should Be
Finished Next Week, Bismarck Trib. 1 (Sept. 30, 2003). The small town
of Garrison spent $400,000 to secure its Lake Sakakawea water supply.
L. Donovan, Garrison's Water Supply Secure For Now, Bismarck Trib.
1B (Jan. 9, 2005). South Dakota's Cheyenne River Sioux Tribe’s water
intakes are threatened by low reservoir levels. JA 08397. The Corps
states that more water supply disruptions can be expected if water
levels decline further, “particularly” in the upper basin. ND Appx. at 28
(2004-05 AOP). See also JA 08409 (Tribal Stmt.).
10
removed so much water that the lake’s cold water habitat
— on which the walleye as well as the salmon depend — was
in jeopardy. As the lake dwindles, the temperature of
deeper water rises to a point that threatens the cold water
habitat and risks violating water quality standards
adopted by North Dakota under the federal Clean Water
Act. E.g., JA 07665-66; ND Appx. at 26 (2004-05 AOP).
North Dakota asserted that high releases from Lake
Sakakawea violated the state’s water quality standards.
The district court ultimately dismissed North Dakota’s
suit. North Dakota v. United States Army Corps of Engi-
neers, 320 F.Supp.2d 873 (D. Minn. 2004). The Eighth
Circuit affirmed. 418 F.3d 915. North Dakota intends to
file a petition for certiorari in that case. Also in 2003
environmental groups, led by American Rivers, filed suit
in the District of Columbia, asserting that the government
violated the ESA by failing to protect three species that
need Missouri River habitat for survival — the pallid
sturgeon, the piping plover, and the least tern. App. at 10-
11.
Thus, seven suits were filed in five different districts
over the Corps’ river management — the South Dakota,
North Dakota, Nebraska/Missouri, and Montana suits in
2002, and the 2003 Blaske Marine, No:th Dakota, and
American Rivers suits.’ Additional parties intervened in
some of the suits. For example, the Mandan, Hidatsa, and
Arikara Nation — a North Dakota Indian tribe — inter-
vened, as did the Missouri River Energy Services — a
coalition of Midwestern cities owning electric utilities. The
Nebraska Public Power District became a litigant.
* In the litigation below, federal jurisdiction was founded on 28
U.S.C. § 1331.
11
In the summer of 2003 the litigation was consolidated
in the District of Minnesota. App. at 11. Also that summer,
the Eighth Circuit issued a decision on the Corps’ appeal
of the 2002 injunctions. South Dakota v. Ubbelohde, 330
F.3d 1014 (8th Cir. 2003). Relying primarily on E7SI
Pipeline, the court ruled that while the 1944 Flood Control
Act requires the Corps to balance all uses, it gives naviga-
tion a priority. Jd. at 1019-20.
North Dakota and South Dakota filed a petition for
certiorari. The federal government opposed the petition.
North Dakota v. Ubbelohde, No. 03-935, Brief of the
Federal Respondents in Opposition (Mar. 2004). It argued
that the Dakotas misread Ubbelohde. Id. at 13-15. It
asserted that the court of appeals had not interpreted the
1944 Flood Control Act to give navigation a priority. Jd. at
14. The government also argued that the decision was
interlocutory. Ubbelohde reviewed injunctions and “did not
render a final judgment on the merits.” Jd. at 16. The
government next argued that the Corps would soon issue 4
revised Master Manual that would likely make “importanv
changes” in the Corps’ river management. Jd. at 17.
Missouri, Nebraska, and a downstream organization, MO-
ARK Association, also opposed the petition. The petition
was denied. 541 U.S. 987 (2004).
While the petition was pending litigation continued in
the lower courts. Summary judgment motions were filed
with the district court in Minnesota. It issued its decision
in June of 2004. App. at 89. (Earlier, it had ordered the
Corps to issue a new Missouri River Master Manual,
which the Corps did in March of 2004. App. at 35 n.1.) The
district court agreed that the Flood Control Act does not
set priorities. “The Missouri River cannot be operated in a
vacuum, but rather the Corps must consider, evaluate, and
12
balance all interests in its operation of the Missouri
River.” App. at 88. The “Pick’ Plan did not rank any river
interests above another,” and the “‘Sloan’ Plan does not
dictate a priority of river interests.” App. at 40. Further, it
ruled that the Flood Control Act itself “does not require a
particular outcome, but rather ... [ajll river interests
must be considered and evaluated to ‘secure the maximum
benefits’ to river interests.” App. at 41. The Corps is not
obligated to maintain any minimum water levels or
seasons for navigation. App. at 41-42. On appeal, however,
the Eighth Circuit gave downstream navigation a priority,
describing it as a “dominant function.” Ubbelohde, 330
F. 3d at 1019-20.
The litigation that began in 2002 was only the most
recent round. In 1990 the Upper Basin States sued the
Corps. South Dakota v. Hazen, 914 F.2d 147 (8th Cir.
1990). They sued again in 1991. JA 00267 (South Dakota v.
Bornhoft). Missouri and the MO-ARK Association sued the
Corps in 1997. Missouri v. Craig, 978 F.Supp. 902 (W.D.
Mo. 1997), vacated, 163 F.3d 482 (8th Cir. 1998). Missouri
nad also sued in 1992. Jd. at 906 (Missouri v. Bornhoft). In
1999 a tribe sued over the effects of fluctuating waters on
grave sites. Yankton Sioux Tribe v. U.S. Army Corps of
Engineers, 194 F.Supp.2d 977, 983 (D.S.D. 2002). Litiga-
tion over the Corps’ management and the Flood Control
Act’s proper interpretation has been protracted and
requires resolution by this Court.
s
13
REASONS FOR GRANTING THE PETITION
A. Introduction
The Court should grant certiorari for two reasons.
One, the court below, in ruling that navigation is a “domi-
nant function” rewrote the 1944 Flood Control Act. In
doing so it improperly relied on misleading dictum in ETS]
Pipeline Project v. Missouri, 484 U.S. 495 (1988), a case in
which competing water uses were not at issue. Given the
variety and importance of uses to which the Missouri is
put — municipal drinking water, commercial navigation,
recreation, farmland irrigation, industrial water supply,
and power generation — it is essential that the Court
clarify and confirm Congress’ direction for water alloca-
tions among the basin states. They and their citizens are
entitled to have the erroneous dictum in ETSI Pipeline
corrected so that the Corps can properly manage the river.
Two, the Court should grant certiorari because the court
below ignored the United States’ understanding of the Act.
The United States, through its Corps of Engineers — which
has considerable experience managing the river - has
concluded that the Act requires an equitable © alancing of
all uses. That fair, eminently sensible interpretation is
undermined by the court below and its misreading of the
Act.
At its heart, this matter is about allocating the Mis-
souri River among seven states. Errors by the court below
give the lower basin’s barge industry an inordinate
amount of the river’s water. This Court’s authority is
needed to interpret the statute at the source of the long-
standing dispute over one of America’s premier resources.
14
B. The court of appeals misread the Flood Control
Act
1. The 1344 Flood Control Act. The Act can be
readily reviewed to assess whether it sets priorities. Its
relevant provisions are not lengthy. App. at 90-112. No-
where in the Act does it relegate recreation or hydropower
or any other use to secondary status. Nowhere in the Act
does the phrase “dominant function” appear. Nowhere does
Congress state that navigation has f-“‘ority over other
uses. If it imposes any restriction, it restricts navigation.
Navigation works are to be “operated consistently” with
the “economic use of the waters ... by other users.” App.
at 90. The ruling below does not implement this require-
ment. It does the opposite, allowing the river to be oper-
ated inconsistently with other interests.
Further, the Act incorporates the Joint Report. App. at
97. The Joint Report states that developing the basin
under the two plans “will secure the maximum benefits for
flood control, irrigation, navigation, power, domestic and
sanitary purposes, wildlife, and recreation.” App. at 109.
The Report does not set priorities. Uses are not divided
into first class and second class, primary and secondary.
There is no hierarchy. As the United States asserts in the
brief it filed with the court below: “The text of the [Act]
nowhere gives priority to navigation over other uses.”
Brief of Federal Defendants-Appellees at 36 (Feb. 2005).
The district court agreed, finding that the Act “does not
require a particular outcome,” but rather that the “maxi-
mum benefits” for all river interests must be secured. App.
at 41. The Corps is not obligated to maintain “minimum
navigation flows or season lengths.” App. at 41.
15
Independent entities do not find a navigation priority
in the Act. The Government Accounting Service did not
find one, JA 00041 (GAO 2000 Report), nor did the Con-
gressional Research Service. JA 00002-03 (CRS 1992
Report). A Department of the Interior Regional Solicitor
concluded that the Act and its legislative history “lend no
support” for a navigation priority. JA 02198 (1992 Letter).
See also JA 05097 (NAS).
2. The Ubbelohde decision. The court below stated
that it did not need to consider arguments about the Act
because it had considered the statute in its 2003 Ubbe-
lohde decision. “In Ubbelohde, we relied on the Supreme
Court’s decision in ETSI Pipeline ... and the legislative
history ... to determine that ‘[t}he dominant functions of
the Flood Control Act were to avoid flooding and to main-
tain downstream navigation.’” App. at 15.
The analysis in Ubbelohde — upon which allocating
Missouri River water now rests — is but one paragraph.
330 F.3d at 1019-20. The first two sentences state: “The
Act also laid out certain substantive interests that it was
to serve. The dominant functions of the Flood Control Act
were to avoid flooding and to maintain downstream
navigation. ETSI Pipeline Project v. Missouri, 484 U.S. 495
(1988).” Id. There was, however, no analysis of ETS] and
its dictum. There was no effort to separate ETSI’s jurisdic-
tional dispute between two agencies from the present and
more fundamental question about allocating the Missouri.
Ubbelohde then discussed legislative history, but the
discussion does not support ETS/’s dictum.
The Act’s dominant functions were expressed re-
peatedly in three Congressional Documents:
Senate Documents 191 [the Sloan Plan] and 247
16
{the Joint Report] and House Document 475 [the
Pick Plan). See Flood Control Act Section 9, 58
Stat. at 891. House Document 475, which repre-
sented one of two competing plans, confirmed
this view, stressing flood control. H.R. Doc. No.
475, 78th Cong., 2d Sess. 28-29 (1944). At the
same time, however, the Act recognizes secon-
dary uses of the River including irrigation, rec-
reation, fish, and wildlife. See Flood Control Act
Section 4, 58 Stat. at 889-90; 33 U.S.C. § 708
[Sec. 6 of the Act); 43 U.S.C. § 390 (Sec. 8 of the
Act]. The House Document just cited noted that
the management plan “would also provide for the
most efficient utilization of waters of the Mis-
souri River Basin for all purposes, including irri-
gation, navigation, power, domestic and sanitary
purposes, wildlife, and recreation.” H.R. Doc. No.
475, supra, at 29. Senate Document 247, which
reconciled the competing proposals, included a
discussion of the purposes of Lake Oahe: “the ir-
rigation of 750,000 acres of land . . . as well as to
provide useful storage for flood control, naviga-
tion, the development of hydroelectric power, and
other purposes.” S. Doc. No. 247, 78th Cong., 2d
Sess. 3 (1944). Thus, the Flood Control Act pro-
vided the Corps with a wide array of interests to
consider in regulating the River.
Id. The court’s opening and conclusory citation to the Pick
Plan, Sloan Plan, and Joint Report makes it impossible to
know what the court relied on in these documents. And
neither the Pick Plan nor the Joint Report use the term
“dominant function” or anything like it. The court then
follows with a reference to “flood control,” which has no
bearing on a navigation priority. It next refers to “irriga-
tion, recreation, fish, and wildlife,” labeling them “secon-
dary” and citing several sections of the Act. None of the
17
sections, however, use the word “secondary” or anything
like it. App. at 94-97. The court then cites the Pick Plan
stating that its objective was to “‘provide for the most
efficient utilization uf waters of the Missouri River Basin
for all purposes, including ... power ... wildlife, and
recreation.’” This supports equitably balancing all uses,
not favoring one use. The court then cites the Joint Report
for the propos*tion that Lake Oahe is to be managed for
“flood control, navigation, the development of hydroelectric
power, and other purposes.” This doesn't present a hierar-
chy of uses. In fact, the Joint Report states that the river
is to be managed to “secure the maximum benefits” for all
uses. App. at 109.
3. The ETSI decision. The primary reason for the
Eighth Circuit’s finding that navigation has a priority is
this Court’s ETSI Pipeline decision. ETSI concerned a
contract signed by the Secretary of the Interior allowing
water withdrawals from Lake Oahe for a slurry pipeline to
move coal from Wyoming to the southeastern United
States. 484 U.S. at 497-98. Downstream states challenged
the Secretary's contracting authority. The case was about a
division of authority between the Corps and Interior. Jd. at
499. See also, id. at 503 (“The crucial provisions here ...
were the sections [in the Act] that set forth the specific
authority allotted to [the Departments of] War and Inte-
rior”). The Court stated that no issue is presented “as to
the relative interests of the United States and South
Dakota in Lake Oahe water.” Jd. at 498 n.2.
The Court ultimately ruled that the Secretary did not
have authority to authorize the withdrawal. /d. at 513-17.
Explicit language in the Flood Control Act supported this
conclusion. Because the Act “speaks directly to the dispute
... [t}]hat is ‘the end of the matter’” Jd. at 517 (citation
18
omitted). And that is where the Eighth Circuit should
have left ETSI; as a decision addressing the contracting
authority of federal agencies. ETSI should not be used to
decide a different issue, that is, whether the Corps, in
operating the river, must favor navigation.
While the “dominant function” language is in ETSI,
484 U.S. at 512, it was used in the context of discussing
only the Sloan Plan. Jd. The Court, however, also referred
to the Pick Plan. It stated that while the Pick Plan
stressed flood control, “its comprehensive list of projects
‘would also provide for the most efficient utilization of the
waters of the Missouri River Basin for all purposes,
including irrigation, navigation, power, domestic and
sanitary purposes, wildlife, and recreation.’” Jd. at 500
(quoting the Pick Plan). The Eighth Circuit could have just
as well selected this statement as the “rule” of ETSI, as
this Court’s interpretation of the Flood Control Act. But
the Eighth Circuit arbitrarily ignored the comment about
the Pick Plan and chose the Sloan Plan comment. It is on
that unfounded selection that allocating the Missouri
River rests. And the Act, of course, is not based on just the
Sloan Plan; it is improper to rely on one plan and ignore
the other. Congress approved both plans, as coordinated by
the Joint Report. App. at 97. Assuming that a review of the
legislative history is even proper, the Eighth Circuit erred
by relying on ETSI’s Sloan Plan comment and ignoring the
Pick Plan reference. It further erred by not acknowledging
that Congress “revised and coordinated” the two plans in
the Joint Report. Jd. As the United States told the court
below:
[The “dominant functions” remark] was made in
the context of the Court’s determination of
whether operation of the Mainstem reservoirs
19
came within the jurisdiction of the Corps or the
Department of the Interior.... The Supreme
Court did not address the issues in this case con-
cerning the Corps’ balancing of competing uses of
water. Thus, the Court’s statement of the ‘domi-
nant function’ in ETSI Pipeline is not dispositive
of how the Corps must operate the Mainstem
System.
Brief of Federal Defendants-Appellees at 35, n.5 (Feb.
2005).
The Court should grant the petition for the same
reason it granted certiorari and reversed prior dictum in a
matter involving the 1928 Flood Control Act. 33 U.S.C.
702c. In Central Green Co. v. United States, 531 U.S. 425
(2001), the Court reconsidered dicta in United States v.
James, 478 U.S. 597 (1986). In James, the Court inter-
preted a section of the 1928 Act limiting the government's
liability for injuries caused by floodwater frou: federal
facilities, but in doing so included in James “confusing
dicta.” Central Green, 531 U.S. at 430. The Court recog-
nized that to correct the lower court's error, it needed to
“resort to the text of the statute,” rather than to dicta in
James. Id. at 431. In reviewing and rejecting its earlier
dictum, the Court revisited the statute’s text — the same
task the Dakotas ask that the Court undertake here — to
correct a lower court’s misreading of a flood contro! stat-
ute.
Also In Central Green, the Court ruled that “to char-
acterize every drop of water that flows through that
immense project as ‘flood water’ simply because flood
control is among the purposes served by the project unnec-
essarily dilutes the language of the statute.” Jd. at 434.
Similarly, the E7TS/ dictum and the Eighth Circuit’s
20
rulings make navigation a priority even though such a
status for navigation does not appear in the statute,
effectively diluting the broad objectives Congress sought to
promote. Once the ETSI dictum is corrected — as dictum
was corrected in Central Green - it is apparent that
Missouri River waters should be allocated on equity rather
than an unfounded priority.
4. The legislative history. The Eighth Circuit also
relied on legislative history. App. at 15. So too did ETSI in
citing the Sloan and Pick Plans. But as explained, the text
of the Flood Control Act does not set forth a priority. It is
clear on that point. A search for Congressional intent in
the legislative history would seem unnecessary. Indeed,
this Court has “repeatedly held” that the authoritative
statement is the statutory text, not legislative history or
other extrinsic material. Exxon Mobil Corp. v. Allapattah
Servs., 125 S.Ct. 2611, 2626 (2005). Legislative history can
be “murky, ambiguous, and contradictory.” Jd. But if the
Act’s legislative history — the Sloan and Pick Plans — is to
be examined, that history does not focus on just naviga-
tion.
The Pick Plan, for example, describes the facilities as
“multiple-purpose.” H.R. Doc. No. 78-475 at 3, 4, 18, 26,
28, 30 (1944). In addition to flood-control, the plan is to
provide for the most efficient use of Missouri River waters
“for all purposes, including irrigation, navigation, power,
domestic and sanitary purposes, wildlife, and recreation.”
Id. at 28-29. See also id. at 16. In transmitting the plan to
Congress, the Corps stated that the plan calls for the
“distribution of appropriate benefits over the entire val-
ley.” Id. at 3. Benef s were to be “great and widespread.”
Id. at 18.
21
Flexibility is emphasized. “Due allowance must be
made for any changed conditions.” Jd. at 3. Water use will
be adjusted to meet the basin’s “changing needs” and “new
economic situations.” Jd. The plan is “flexible.” Id. at 4.
“(P]reference can be given to the functions which contrib-
ute most significantly to the welfare and livelihood of the
people of various parts of the basin.” Jd. at 3. The court
below would turn this on its head and require that the
Corps feature navigation, the use that contributes the
least to the basin.
The Sloan Plan contains similiar statements. The
Secretary of the Interior stated that his agency’s plan
contemplates using the waters “beneficially for multiple
purposes [to stabilize] the agriculture and economy of this
vast basin.” S. Doc. No. 78-191 at 1 (1944). “Substantial
and material benefits would accrue through recreational
use of the waters and facilities proposed.” Jd. at 2. The
Department of the Interior’s Board of Review described
the plan as “comprehensive,” one that would further the
“recreational use of waters [and] conservation of fish and
wildlife,” and as one that will “create exceptional opportu-
nities for expanding the fish and wildlife programs.” Jd. at
10, 13. Significantly, the Sloan Plan, like the Pick Plan,
could be modified as “changes in physical and economic
conditions make necessary.” Jd. at 17. As the Bureau’s
Commissioner stated in a letter included in the Pick Plan,
the river must be managed for “a wide variety of functions,
including ... navigation, irrigation ... hydroelectric
generation ... fish and wildlife preservation and recrea-
tion,” and that the reservoirs should be operated to obtain
“the maximum benefits” for, among other things, fish,
wildlife preservation, and recreation. H.R. Doc. 475, supra
at 6-7.
22
In the brief it filed below, the United States accurately
states:
The legislative history simply does not provide a
basis for giving downstream uses priority over
upstream uses such as hydroelectric power gen-
eration, irrigation, recreation, and support of fish
and wildlife. The legislative history merely shows
that Congress intended that navigation be sup-
ported, a fact not in dispute.
Brief of Federal Defendants-Appellees at 38 (Feb. 2005).
And as the district court found, the Pick Plan “did not
rank any river interests above another,” and the Sloan
Plan “does not dictate a priority of river interests.” App. at
40. In sum, if legislative history is to be used, it contains
numerous passages promoting all interests; it refers to
“multi-purpose” facilities, and a duty to achieve “maxi-
mum benefits” and meet “changing needs.”
C. The United States’ interpretation of the Flood
Control Act
The Eighth Circuit’s ruling that navigation is pre-
ferred differs from the United States’ interpretation of the
Act. The United States agrees with the Dakotas, often
stating that the statute does not give navigation a priority.
In its brief below, the United States described the priority
argument as “extreme.” Brief of Federal Defendants-
Appellees at 32 (}'eb. 2005). The “argument fails because
... the Corps has the discretion to strike a balance among
the interests rec: gnized by the [Act],” a result of the Act’s
“plain language .. . and its legislative history.” Jd. at 28. In
a brief filed with the Eighth Circuit in the Ubbelohde case,
the United States stated: “There is no statement in the Act
or ... in ETSI that navigation is always entitled to a
23
priority over the needs of fish and wildlife.” Consol. Reply
Brief of Federal Defendants-Appellants at 10 (Sept. 2002).
The legislative history does not identify purposes “as
primary or secondary.” Jd. at 1. See also id. at 6, 8-9.
In early 1990's litigation the Department of Justice
wrote North Dakota: “Congress did not assign a priority to
these [project] purposes.” ND Appx. at 54 (Disheroon
Letter). This was confirmed by the Corps Chief of Opera-
tions; this view has “elways been the [Corps] official
position.” Jd. at 66 (Elmore Stmt.) Another Corps official
stated that the Corps must be flexible “‘to meet changing
conditions.’” Jd. at 73 (Sveum Stmt.). See also id. at 72.
The Department of Justice made the same point. Func-
tions must be balanced and “the priorities to be afforded
these project purposes may be revised to take into account
and to accommodate changing environmental and eco-
nomic needs and conditions.” Jd. at 54 (Disheroon Letter).
Thus, the United States has often expressed its
agreement with the Dakotas that there is not a navigation
priority. Its statements are considered and authoritative,
and have been made by Corps officials and the Depart-
ment of Justice. “[C]onsiderable weight should be accorded
to an executive department's construction of a statutory
scheme it is entrusted to administer.” Chevron USA, Inc. v.
Natural Resources Defense Council, 467 U.S. 837, 844
(1984). This rule was applied in ETSI. 484 U.S. at 516-17.
The court below failed to consider the way in which the
Corps interprets its governing statute. It ignored its
agency-deference responsibility.
D. Summary
The court below cited iis 2003 Ubbelohde decision for
finding a navigation priority. Ubbelohde in turn relied on
ETSI. But the Missouri River conflict is far too important
to be settled on such an unsound source. Unfortunately,
the court paid little attention to the Act itself. Had it, it
would have found no priorities or hierarchy. It would have
found that the Act incorporates the Joint Report, which
instructs that the river be managed to “secure the maxi-
mum benefits” for all uses. App. at 109.
Certiorari is warranted because this case, at its heart,
is an inter-state dispute over properly allocating water in
a major river. While this dispute was not brought to the
judiciary in a suit by one state against another, it is akin
to the equitable apportionment cases the Court often hears
under its original jurisdiction. E.g., Texas v. New Mexico,
462 U.S. 554 (1983); Wyoming v. Colorado, 298 U.S. 573
(1936). Controversies between states “present not infre-
quently questions of far-reaching import and of exceeding
difficulty.” Kansas v. Colorado, 206 U.S. 46, 80 (1907). This
dispute involves the Corps’ difficult mission to manage the
river and presents issues of far-reaching import for the
basin’s states and tribes. The “state versus state” nature of
the case should inform the Court’s review of the petition.
Two decades ago the Court deemed the 1944 Flood
Control Act worthy of its attention. In ETSI, the Court
considered an inter-agency dispute over contracting
authority. Today, a far more important Flood Control Act
issue is presented — a dispute among states over allocating
Missouri River waters.
25
CONCLUSION
The petition for a writ of certiorari should be granted.
State of South Dakota
LAWRENCE E. LONG
Attorney General
JOHN P. GUHIN
Counsel of Record
Assistant Attorney General
State Bar 10 No. 653
Office of the Attorney General
500 E. Capitol Avenue
Pierre, SD 57501
Telephone (605) 773-3215
Facsimile (605) 773-4106
Respectfully submitted,
State of North Dakota
WAYNE STENEHJEM
Attorney General
CHARLES M. CARVELL
Counsel of Record
Assistant Attorney General
State Bar ID No. 03560
Office of the Attorney General
500 North 9th Street
Bismarck, ND 58510-4509
Telephone (701) 328-3640
Facsimile (701) 328-4300
Counsel for Petitioners
NOVEMBER 2005
App. 1
421 F.3d 618
United States Court of Appeals,
For The Eighth Circuit
In re: Operation of the Missouri River System Litigation
American Rivers, Inc.; Environmental Defense;
National Wildlife Federation; lowa Wildlife
Federation; Kansas Wildlife Federation;
Montana Wildlife Federation; Nebraska Wildlife
Federation; North Dakota Wildlife Federation;
South Dakota Wildlife Federation; Izaak Walton
League of America, Inc., Appellants,
Vv.
United States Army Corps of Engineers; Les Brownlee,
Acting Secretary of the United States Army; United States
Fish and Wildlife Service; Gale Norton, Secretary of the
United States Department of Interior, Appellees. State of
Nebraska; Nebraska Public Power District; State of Mis-
souri; State of North Dakota; State of South Dakota; Blaske
Marine, Inc.; the Mandan, Hidatsa and Arikara Nation;
Conocophillips Company; Ergon Asphalt and Emulsions,
Inc.; Magnolia Marine Transport Company; Midwest Termi-
nal Warehouse Company, Inc.; Mo-ark Association; Missouri
River Keepers; Missouri River Energy Services Appellees.
State of Nebraska, Appellant,
v.
United States Army Corps of Engineers; Les Brownlee, Acting
Secretary of the United States Army, United States Fish and
Wildlife Service; Gale A. Norton, Secretary of the United States
Department of Interior, Appellees. American Rivers, Inc.; State
of Missouri; State of North Dakota; State of South Dakota;
Blaske Marine, Inc.; the Mandan, Hidatsa and Arikara Nation;
Conocophillips Company, Ergon Asphalt and Emulsions, Inc.;
Magnolia Marine Transport Company; Midwest Terminal
Warehouse Company, Inc.; Mo-ark Association; Missouri River
Keepers; Missouri River Energy Services, Appellees.
App. 2
Nebraska Public Power District, Appellant,
v.
United States Army Corps of Engineers; Les Brownlee,
Acting Secretary of the United States Army; United States
Fish and Wildlife Service; Gale Norton, Secretary of the
United States Department of Interior, Appellees. American
Rivers, Inc.; State of Missouri; State of North Dakota; State
of South Dakota; Blaske Marine, Inc.; the Mandan, Hidatsa
and Arikara Nation; Conocophillips Company, Ergon Asphalt
and Emulsions, Inc.; Magnolia Marine Transport Company;
Midwest Terminal Warehouse Company, Inc.; Mo-ark
Association; Missouri River Keepers; Missouri River
Energy Services, Appellees.
State of Missouri, Appellant,
v.
United States Army Corps of Engineers; Les Brownlee,
Acting Secretary of the United States Army; United
States Fish and Wildlife Service; Gale Norton, Secretary
of the United States Department of Interior, Appellees.
American Rivers, Inc.; State of Nebraska; Nebraska
Public Power District; State of North Dakota; State
of South Dakota; Blaske Marine, Inc.; the Mandan,
Hidatsa and Arikara Nation; Conocophillips Company;
Ergon Asphalt and Emulsions, Inc.; Magnolia Marine
Transport Company; Midwest Terminal Warehouse
Company, Inc.; Mo-ark Association; Missouri River
Keepers; Missouri River Energy Services, Appellees.
The Mandan, Hidatsa and Arikara Nation, Appellant,
v.
United States Army Corps of Engineers; Les Brownlee,
Acting Secretary of the United States Army; United States
Fish and Wildlife Service; Gale Norton, Secretary of the
United States Department of Interior, Appellees. American
Rivers, Inc.; Environmental Defense; National Wildlife
Federation; Iowa Wildlife Federation; Kansas Wildlife
Federation; Montana Wildlife Federation; Nebraska
App. 3
Wildlife Federation; North Dakota Wildlife Federation;
South Dakota Wildlife Federation; Izaak Walton League of
America, Inc.; State of Nebraska; Nebraska Public Power
District; State of Missouri; State of North Dakota; State of
South Dakota; Blaske Marine, [nc.; Conocophillips Com-
pany; Ergon Asphalt and Emulsions, Inc.; Magnolia
Marine Transport Company; Midwest Terminal Warehouse
Company, Inc.; Mo-ark Association; Missouri River Keep-
ers; Missouri River Energy Services, Appellees.
Blaske Marine, Inc.; Conocophillips Company;
Ergon Asphalt and Emulsions, Inc.; Magnolia
Marine Transport Company; Midwest Terminal
Warehouse Company, Inc.; Mo-ark Association;
Missouri River Keepers, Appellant,
Vv.
United States Army Corps of Engineers; Les Brownlee,
Acting Secretary of the United States Army; United
States Fish and Wildlife Service; Gale Norton, Secretary
of the United States Department of Interior, Appellees.
American Rivers, Inc.; Environmental Defense; National
Wildlife Federation; lowa Wildlife Federation; Kansas
Wildlife Federation; Montana Wildlife Federation;
Nebraska Wildlife Federation; North Dakota Wildlife
Federation; South Dakota Wildlife Federation; Izaak
Walton League of America, Inc.; State of Missouri;
State of North Dakota; State of South Dakota; the
Mandan, Hidatsa and Arikara Nation; Missouri
River Energy Services, Appellees.
Nos. 04-2737, 04-2774, 04-2785,
04-2794, 04-2878 and 04-2994.
Submitted: April 11, 2005.
Filed: Aug. 16, 2005.
Peter Hennigan, argued, Minneapolis, MN, for Appel-
lant American Rivers, et al.
App. 4
Thomas Wilmoth, argued, Lincoln, NE, for Appellants
State of Nebraska and NE Public Power District.
William Bryan, argued, Asst. Atty. Gen., Jefferson
City, MO, for Appellant State of Missouri.
Robert Vincze, argued, Denver, CO, for Appellant
Blaske Marine, et al.
Daniel Israel, argued, Boulder, CO, for Appellant The
Mandan, Hidatsa and Arikara Nation.
Rebert H. Oakley, argued, U.S. Dept. of Justice,
Washington, DC, for Federal defendants.
James A. Maysonett, argued, U.S. Dept. of Justice,
Washington, DC, for Wildlife and Marine Resources.
Charles M. Carvell, argued, Attorney General’s Office,
Bismarck, ND, for Appellee State of North Dakota.
Diane Best, argued, Pierre, SD, for Appellee State of
South Dakota.
Robert J. Vineze, argued, Denver, CO, for Appellee
Mo-ark.
Before WOLLMAN, BEAM, and GRUENDER, Circuit
Judges.
GRUENDER, Circuit Judge.
In these consolidated appeals, various parties chal.
lenge the operation of the Missouri River main stem
reservoir system by the United States Army Corps of
Engineers (“the Corps”) and associated wildlife assess-
ments produced by the United States Fish and Wildlife
App. 5
Service (“FWS”). The district court’ granted summary
judgment to the Corps and FWS and their named individ-
ual officers (collectively “the Federal Defendants”) on all
claims. For the reasons stated below, we dismiss three
claims as moot and affirm the judgment of the district
court on all remaining claims.
I. BACKGROUND
The Missouri River originates in Montana and runs
through North Dakota, South Dakota, Nebraska, Iowa,
Kansas and Missouri before emptying into the Mississippi
River. In its natural state, the river subjected the sur-
rounding basin to extensive flooding every spring. With
the Flood Control Act of 1944 (“FCA”), Congress author-
ized the construction of a dam and reservoir system on the
upper river to control the flooding. In addition to flood
control, the FCA envisioned that the reservoirs would
provide water for local irrigation projects, steady release
into the river during the summer months to support
downstream navigation, hydroelectric power generation
and lake recreation. The FCA delegated construction and
management of the main stem reservoir system to the
Corps.”
The current challenges to the Corps’ operation of the
system arise from two directions. First, a persistent drought
" The Honorable Paul A. Magnuson, United States District Judge
for the District of Minnesota.
* The main stem dams and reservoirs are Fort Peck Dam (Fort
Peck Lake) in Montana, Garrison Dam (Lake Sakakawea) in North
Dakota, and Oahe Dam (Lake Oahe), Big Bend Dam (Lake Sharpe),
Fort Randall Dam (Lake Francis Case) and Gavins Point Dam (Lewis
and Clark Lake) in South Dakota.
App. 6
in the Missouri River basin has led to a recurring conflict
between upstream and downstream water-use interests.
In 2002, the Corps planned to release water from Lake
Oahe into the river to maintain downstreaya navigation
throughout the summer. South Dakota, fearing a negative
impact on the seasonal fish spawn in Lake Oahe and
concordantly on the reservoir’s sport fishing industry,
obtained an injunction in federal district court preventing
the Corps from lowering any reservoir in South Dakota
until after spawning season. When the Corps decided to
lower Lake Sakakawea instead, North Dakota obtained a
similar injunction. Not to be outdone, Montana obtained
an injunction to prevent releases from Fort Peck Lake. In
response, Nebraska obtained an injunction ordering the
Corps to make the required releases to support navigation
as called for by the Corps’ Missouri River Main Stem
Reservoir System Master Water Control Manual (“1979
Master Manual”).
In a consolidated appeal of these injunctions, we ruled
that the FCA vested the Corps with discretion to balance
the competing water-use interests. South Dakota v. Ubbe-
lohde, 330 F.3d 1014, 1027 (8th Cir.2003). Because the
FCA’s legislative history and its interpretation by the
Supreme Court “indicate [] that the Corps’s primary
concerns should be flood control and navigation,” we
upheld the Corps’ decision to follow the 1979 Master
Manual and draw down the reservoirs to support down-
stream navigation. Jd. at 1032.
The second point of conflict has been that flood pre-
vention and steady summer flows for downstream naviga-
tion disrupt the natural habitat of protected bird and fish
species in the Missouri River ecosystem. In litigation initially
separate from the Ubbelohde cases, environmental groups
App. 7
have attempted to force the Corps to operate the system to
produce more “natural” river flows to benefit the protected
species. To understand the current stances of the parties
in this litigation, it is necessary to review in some detail
the Corps’ previous attempts to accommodate competing
interests while developing its operating procedures.
The Corps sets forth its general operational gui’ -iines
for the Missouri River reservoir system in a Master
Manual and the operational details for each year in an
Annual Operating Plan. The first Master Manual was
published in 1960 and revised in 1973, 1975 and 1979. The
year 1987 brought the onset of the first persistent drought
in the region since the reservoir system had become fully
operational. Because it found that the operational proce-
dures in the 1979 Master Manual were not well-tailored to
handle a persistent drought, the Corps began the revision
process for what would become the 2004 Master Manual.
The operation of the reservoir system also brings the
Corps within the provisions of the Endangered Species Act
(“ESA”). Under the ESA, if a government agency concludes
that a proposed action may “jeopardize the continued
existence” of any protected species or adversely affect its
critical habitat, the agency must prepare a Biological
Assessment and consult with the FWS. ESA § 7, 16 U.S.C.
§ 1536. The FWS then issues a Biological Opinion (“BiOp”)
describing how the action will affect the species, based on
the “best scientific and commercial data available.” Jd. at
§ 1536(aX(2). If the FWS concludes that the proposed
action would cause jeopardy to an endangered or threat-
ened species, the BiOp must include a Reasonable and
Prudent Alternative which would allow the agency to
implement the desired action while avoiding jeopardy to
the species. Id. at § 1536(b\(3XA). Finally, if it appears
App. 8
incidental “take” will occur even if the Reasonable and
Prudent Alternative is implemented, the BiOp must
include an Incidental Take Statement setting conditions
under which the agency may proceed while avoiding
Id. at § 1536(b)\4).
The Corps followed the above process with three
protected species in the Missouri River basin: the pallid
sturgeon, a fish listed as endangered since 1990; the least
tern, a migratory bird listed as endangered since 1985;
and the piping plover, a migratory bird listed as threat-
ened since 1985. The pallid sturgeon spends its entire life
tributaries, while the tern and plover both nest in the
summer on sparsely vegetated sandbars along the rivers.
In 2000, the FWS issued a Biological Opinion (“2000
BiOp”) finding that the Corps’ proposed operation of the
reservoir system was likely to jeopardize the continued
existence of the three species.
The FWS found that the harm to the species resulted
from the alteration of the river's natural hydrograph.“
Before the construction of the dams, the hydrograph had
two prominent components: the “spring rise” and “su™i:mer
low flow.” The “spring rise” refers to extremely high flows
rage nag eaten tutelage Decor According to
the 2000 BiOp, the spring rise provided a biological
* The ESA prohibits “taking” of endangered species. “The term
‘take’ means to harass, harm, pursue, hunt, shoot, wound, kill, trap,
capture, or collect, or to attempt to engage in any such conduct.” ESA
§ 3(14), 16 U.S.C. § 1532(19).
* A river's “hydrograph” is the variation in water level at each
point along its channel! over the course of time.
App. 9
spawning cue for the pallid sturgeon and enabled the river
to capture protein-rich nutrients from the floodplain and
from wetland habitat not connected to the river channel
during other seasons. In concert with the summer low
flow, the spring rise also provided seasonal connectivity to
the off-channel wetland habitat, making calm, shallow
pools available to the pallid sturgeon for spawning, nurs-
ery and feeding areas. Lower elements of the food chain
also were forced to congregate in the remaining pools,
providing easy summer feeding for the protected species.
In addition, the spring rise scoured and flushed sandbars.
When the now-sparsely-vegetated sandbars were exposed
by the summer low flow, the resulting lack of cover for
concealed predators allowed terns and plovers to nest
there safely
The Corps’ operation of the reservoir system, gener-
ally capturing water in the upstream reservoirs to elimi-
nate spring flooding and releasing water throughout the
summer and fall as necessary to enable downstream
navigation and restore reservoir capacity for the following
spring, eliminated the spring rise and summer low flow
from the hydrograph. The Reasonable and Prudent Alter-
native included with the 2000 BiOp (“2000 BiOp RPA”)
stated that “higher spring and lower or declining summer
flows than now exist™ were “an integral component of the
* The 2000 BiOp presented data from Corps models showing that,
with the reservoirs and channel improvements in place, the “natural
hydrograph” today would be expected to produce a spring rise of 80 Kefs
(Kefs = thousand cubic feet per second) and a summer low flow of 10
Kefs at the Gavin's Point Dam, the final reservoir release point into the
lower river. Under the 1979 Master Manual, flow at that point was
typically maintained steadily between 30-35 Kefs from March through
November. The 2000 BiOp RPA called instead for a spring rise from
Gavin's Point totaling 50-55 Kefs to be implemented about once every
(Continued on following page)
App. 10
measures to avoid jeopardy” to the three protected species.
The 2000 BiOp RPA also mandated habitat restoration, a
' comprehensive species and habitat monitoring program,
and an adaptive management framework to “implement,
evaluate, and modify the components of the RPA in re-
sponse to variable river conditions, species responses, and
increasing knowledge base.”
In an attempt to support downstream water-use
interests despite the continuing drought in the basin, the
Corps released a draft Annual Operating Plan for 2003
that did not incorporate the flow changes from the 2000
BiOp RPA. Environmental interest groups filed suit under
the ESA in the United States District Court for the Dis-
trict of Columbia to enjoin operations under that plan. At
the Corps’ request, the FWS then issued a supplemental
biological opinion (“the 2003 Supplemental BiOp”) that
ratified the Corps’ plan to avoid the 2000 BiOp RPA flows
for the period of May 1 through August 15, 2003, with the
understanding that operations after 2003 would be consis-
tent with the 2000 BiOp. Before the district court, how-
ever, the Corps revealed that it had no intention of
ensuring that its future operations would so comply. Am.
Rivers v. United States Army Corps of Eng’rs, 271
F.Supp.2d 230, 253 (D.D.C.2003). In addition, the district
court held that it was improper for the FWS to focus on
the effects that the proposed action would have on the
protected species during 2003 only, rather than on all
future effects of the proposed action, and that the 2003
three years, and an annual summer low flow of 25 Kefs, ramped down
to 21 Kefs from mid-July through mid-August. The flow required for
minimum support of downstream navigation is about 28.5 Kefs,
depending upon the accompanying inflow from downstream tributaries.
App. 11
Supplemental BiOp failed to articulate a reasonable
explanation for its departure from the analysis in the 2000
BiOp. Id. at 254-57. Therefore, the district court granted
the injunction and ordered the Corps to comply with the
summer low flow provisions of the 2000 BiOp. Jd. at 263.
Citing a conflict with this Court’s Ubbelohde holding that
required operation consistent with the 1979 Master
Manual, the Corps initially failed to comply with the
injunction and was held in conditional contempt. See Am.
Rivers v. United States Army Corps of Eng’rs, 274
F.Supp.2d 62 (D.D.C.2003). Two days later, the Federal
Judicial Panel on Multi-District Litigation consolidated all
litigation regarding the operation of the Missouri River
main stem reservoir system, including new suits by the
parties involved in Ubbelohde, in the District of Minnesota
(“MDL court”). On the order of that court, the Corps
complied with the summer low flow provisions of the 2000
BiOp RPA for the brief remainder of the 2003 summer
period.
At that point, the Corps prepared a new Biological
Assessment with the goal of finding a way to avoid jeop-
ardy to the protected species without following the 2000
BiOp RPA flow requirements. In the fall of 2003, the Corps
presented the new Biological Assessiment to the FWS and
requested a new Biological Opinion. In response, the FWS
issued an Amendment to the 2000 BiOp (“the 2003
Amended BiOp”). The 2003 Amended BiOp RPA permitted
the Corps to avoid the summer low flow requirement on
the condition that it construct 1,200 additional acres of
shallow water habitat for the pallid sturgeon. In addition,
it gave the Corps two more years to experiment with
alternatives to a spring rise. If the Corps could not pro-
duce an acceptable alternative plan, the RPA imposed a
App. 12
default spring rise of reduced magnitude beginning in the
spring of 2006.
The Corps continued to develop the 2004 Master
Manual by complying with the provisions of the National
Environmental Policy Act (“NEPA”). See 42 U.S.C. §§ 4321
et seq. NEPA requires the preparation of a detailed Envi-
ronmental Impact Statement (“EIS”) for every major
federal action that will significantly affect the quality of
the environment. 42 U.S.C. § 4332(C). The EIS must also
evaluate alternatives to the proposed action. Jd. In this
case, the Corps compared five potential water control
plans in its EIS before adopting the Preferred Alternative,
a plan consistent with the 2003 Amended BiOp, as the
basis for the 2004 Master Manual. The MDL court trun-
cated the NEPA public-comment-and-review period and
ordered all plaintiffs in this litigation to amend their
complaints to address the 2004 Master Manual and 2004
Annual! Operating Plan.
After the issuance of the 2004 Master Manual and
2004 Annual Operating Plan, various parties filed motions
for summary judgment. The district court granted sum-
mary judgment to the Federal Defendants on all claims on
the bases that (1) the FCA does not create a non-
discretionary duty in the Corps to maintain minimum
navigation flows or a minimum length for the navigation
season, and (2) the discretionary decisions made by the
Federal Defendants in balancing water-use interests
under the FCA and in avoiding jeopardy to the protected
species were not arbitrary and capricious.
The parties now make various arguments on appeal.
The states of Missouri and Nebraska and the Nebraska
Public Power District (“NPPD”) argue that the 2004
App. 13
Master Manual violates a non-discretionary duty of the
Corps under the FCA to maintain river flow sufficient to
support uninterrupted downstream navigation throughout
the navigation season. Nebraska and NPPD also argue
that the 2003 Amended BiOp is in conflict with the pur-
ported FCA minimum-flow requirement, while Missouri
argues that the 2003 Amended BiOp violates the ESA
because it will eliminate some pallid sturgeon habitat in
the lower Missouri River. American Rivers, the National
Wildlife Federation, several state Wildlife Federations and
the Izaak Walton League of America (collectively “Ameri-
can Rivers”) argue that the 2003 Amended BiOp is arbi-
trary and capricious because it does not insure against
jeopardy to the three protected species. In addition,
American Rivers contends that the EIS was faulty because
the Corps failed to explain why the Preferred Alternative
was superior to another evaluated alternative. Blaske
Marine, ConocoPhillips Company, Ergon Asphalt & Emul-
sions, Inc., Magnolia Marine Transport Company, Midwest
Terminal Warehouse Company, Inc., MO-ARK Association
and Missouri River Keepers (collectively “Blaske Marine”)
argue that a supplemental EIS is required for a contingent
summer low flew that the Corps still has the discretion to
implement. Finally, the Mandan, Hidasta and Arikara
Nation (“the Nation”) contends that the Corps must
operate Lake Sakakawea (Garrison Dam) for the economic
benefit of the Nation’s members.
Il. DISCUSSION
“We review de novo a grant of summary judgment,
applying the same legal standards used by the district
court.” Voyageurs Nat'l Park Ass’n v. Norton, 381 F.3d 759,
763 (8th Cir.2004). We review the actions of the Corps and
App. 14
FWS under the Administrative Procedure Act “to deter-
mine whether they are ‘arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.’™
Ubbelohde, 330 F.3d at 1027 (quoting 5 U.S.C. § 706(2)(A)).
An arbitrary and capricious action is one in which:
the agency has relied on factors which Congress
has not intended it to consider, entirely failed to
consider an important aspect of the problem, of-
fered an explanation for its decision that runs
counter to the evidence before the agency, or is so
implausible that it could not be ascribed to a dif-
ference in view or the product of agency expertise.
Cent. S.D. Coop. Grazing Dist. v. Sec’y of the United States
Dep't. of Agric., 266 F.3d 889, 894 (8th Cir.2001) (quoting
Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins.
Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443
(1983)). “If an agency's determination is supportable on
any rational basis, we must uphold it.” Voyageurs Nat'l
Park Ass'n, 381 F.3d at 763. “When the resolution of the
dispute involves primarily issues of fact and analysis of
the relevant information ‘requires a high level of technical
expertise, we must defer to the informed discretion of the
responsible federal agencies.’” Friends of the Boundary
Waters Wilderness v. Dombeck, 164 F.3d 1115, 1128 (8th
Cir.1999) (quoting Marsh v. Oregon Natural Resources
* Nebraska and NPPD argue that the Corps has attempted to
evade judicial review under the Administrative Procedure Act by
stating in a letter that it did not intend for the 2004 Master Manual to
be considered a binding regulation. We established in Ubbelohde that
the 1979 Master Manual was binding and subject to judicial review. 330
F.3d at 1027-30. The Corps has conceded, both in district court and in
its briefs on appeal, that the 2004 Master Manual is stil] binding on the
Corps and subject to judicial review.
App. 15
Council, 490 U.S. 360, 377, 109 S.Ct. 1851, 104 L.Ed.2d
377 (1989)).
A. The Corps’ FCA Duty to Support Down-
stream Navigation
Missouri, Nebraska and NPPD (collectively “the
downstream parties”) argue that the 2004 Master Manual
is not in accordance with law because, under certain
drought conditions, it calls for canceling the navigation
season in order to hold water in the reservoirs for the
benefit of recreation. The MDL court concluded that the
FCA imposes no duty to maintain a minimum level of
downstream navigation independent of consideration of
other interests. We agree.
This Court has already addressed thoroughly the
balance of interests under the FCA. In Ubbelohde, we
relied on the Supreme Court's decision in ETSI Pipeline
Project v. Missouri, 484 U.S. 495, 108 S.Ct. 805, 98
L.Ed.2d 898 (1988), and the legislative history of the FCA
to determine that “(t]he dominant functions of the Flood
Control Act were to avoid flooding and to maintain down-
stream navigation,” while “the Act recognizes secondary
uses of the River including irrigation, recreation, fish, and
wildlife.” Ubbelohde, 330 F.3d at 1019-20. However, the
FCA does not set forth what level of river flow or length of
navigation season is required to make navigation “domi-
nant” over a “secondary” interest such as recreation.
Instead, “the courts can review the Corps’s decisions to
ensure that it considered each of these interests before
making a decision,” but “the Act does not provide ... a
method of deciding whether the balance actually struck by
the Corps in a given case is correct or not.” /d. at 1027.
App. 16
The downstream parties challenge the provisions of
the 2004 Master Manual referred to as “navigation pre-
cludes.” The amount of water stored in the entire reservoir
system is checked on March 15 and July 1 of each year. If
total system storage falls below the “volumes ... that
allow the System to function to meet authorized purposes
during significant multi-year drought periods,” navigation
support is reduced or eliminated for that year. 2004
Master Manual § 7-03. The EIS estimates, based on the
modeling of historical data from 1898 to 1997, that the
selected navigation-preclude volumes will lead to the
elimination of the entire navigation season only in the four
worst drought years out of every one hundred years, and
to a navigation season shortened from eight-plus months
to less than seven months only in the eight worst drought
years out of every one hundred. Under these circum-
stances, we cannot say that the Corps failed to consider
downstream navigation before making its decision.’
Appellees North Dakota and South Dakota argue that
because damage to the recreation industry would have a
" The Corps states in § 7-01 of the 2004 Master Manual that in the
FCA, “Congress did not assign a priority to these purposes” of “flood
control, navigation, irrigation, hydropower, . . . recreation, and fish and
wildlife. ...” To the contrary, as we clearly stated in Ubbelohde, the
FCA has been interpreted to hold flood control and navigation domi-
nant and recreation, fish and wildlife secondary. Ubbelohde, 330 F 3d at
1019-20. If, due to extreme conditions, the Corps is faced in the future
with the unhappy choice of abandoning flood control or navigation on
the one hand or recreation, fish and wildlife on the other, the priorities
established by the FCA would forbid the abandonment of flood control
or navigation. While we hold today that the 2004 Master Manual does
not “abandon” navigation, we do not rule out the possibility that some
more limited degree of support for flood control or navigation in the
future could be held to constitute “abandonment” of these dominant
functions. See also infra note 9.
App. 17
more dramatic negative economic impact than would
damage to the navigation industry, recreation should
receive special priority. Nothing in the text or legislative
history of the FCA suggests that Congress intended the
priority of interests under the FCA to shift according to
their relative economic value. Arguments based on the
wisdom of the priorities established by the FCA must be
addressed to Congress."
The Corps’ balancing of water-use interests in the
2004 Master Manual is in accordance with the FCA.
Because the 2004 Master Manual does not evidence a
failure to consider the support of downstream navigation,
it is not arbitrary and capricious. Therefore, we affirm the
grant of summary judgment to the Corps on this claim.
B. The Corps’ Duty to Consult with the FWS
under ESA § 7
Nebraska and NPPD argue that it was not in accor-
dance with law for the Corps to engage in the ESA § 7
consultation process with the FWS regarding the opera-
tion of the reservoir system. They contend that the ESA
* Appellee South Dakota also argues that the O’Mahoney-Millikin
Amendment, 33 U.S.C. § 701-1(b), prioritizes the retention of water in
the reservoirs over downstream navigation. The MDL court granted
summary judgment against South Dakota on this issue, and South
Dakota did not appeal. We, therefore, construe South Dakota’s argu-
ment in opposition to the appellant downstream parties to be that the
O’Mahoney-Millikin Amendment would forbid, for the purposes of
supporting navigation, any further lowering of the navigation-preclude
volumes beyond those implemented in the 2004 Master Manual.
Because we find against the appellant downstream parties on this issue
on other grounds, we need not address appellee South Dakota's
argument.
App. 18
does not apply to the operation of the reservoir system
because ESA compliance would interfere with downstream
navigation, a project purpose that is mandated by statute
such that the Corps has no discretion in meeting it. See 50
C.F.R. § 402.03 (“Section 7 [of the ESA] and the require-
ments of this part apply to all actions in which there is
discretionary Federal involvement or control.”) (emphasis
added).
Case law supports the contention that environmental
~- and wildlife-protection statutes do not apply where they
“would render an agency unable to fulfill a non-
discretionary statutory purpose or require it to exceed its
statutory authority. For example, in National Wildlife
Federation v. United States Army Corps of Engineers, 384
F.3d 1163 (9th Cir.2004), the Ninth Circuit held that the
Corps’ operation of four dams on the Snake River did not
violate the Clean Water Act. The challenged noncompli-
ance with water standards was caused by “the existence of
the dams and not any discretionary method of operating
the dams,” and the Clean Water Act could not be construed
to supersede “the Corps’s operation of the dams consistent
with the purposes stated by Congress.” Jd. at 1178-79.
Similarly, in Platte River Whooping Crane Critical Habitat
Maintenance Trust v. FERC, 962 F.2d 27 (D.C.Cir.1992), the
Federal Energy Regulatory Commission (FERC) was
authorized by statute to issue annual licenses to hydro-
power providers on the Platte River. The enabling statute
forbade alteration of the terms of an annual license with-
out agreement from the licensee. Environmental groups
sued FERC, arguing that the ESA required the imposition
of wildlife-protection terms in the licenses. The court held
that the ESA did not apply to the licenses because the ESA
did not authorize FERC to override the statutory prohibition
App. 19
on altering the licenses. Jd. at 32-34. In effect, Platte River
Whooping Crane affirmed that the ESA does not apply
where an agency has no statutory authority to act with
‘i
Cases such as National Wildlife Federation and Platte
River Whooping Crane are inapposite to the instant case,
however, because compliance with the ESA does not
prevent the Corps from meeting its statutory duty under
the FCA to support downstream navigation. As we stated
above, the FCA does not mandate a particular level of
river flow or length of navigation season, but rather allows
the Corps to decide how best to support the primary
interest of navigation in balance with other interests. The
2004 Master Manual demonstrates that the Corps can
comply with the elements of the 2003 Amended BiOp RPA
while continuing to operate the dams “consistent with the
purposes stated by Congress” in the FCA.” Natl Wildlife
Fed'n, 384 F.3d at 1179.
Because the Corps is able to exercise its discretion in
determining how best to fulfill the purposes of the reser-
voir system’s enabling statute, the operation of the reser-
voir system is subject to the requirements of the ESA. It
was therefore in accordance with law for the Corps to
consult with the FWS to produce the 2003 Amended BiOp.
We affirm the grant of summary judgment to the Federal
Defendants on this claim.
* It follows that if future circumstances should anse in which ESA
compliance would force the Corps to abandon the dominant FCA
purposes of flood control or downstream navigation, the ESA would not
apply. See supra note 7.
App. 20
C. Mootness of Claims Based on Summer
Low Flow
Several of the claims against the Federal Defendants
challenge the conditional summer low flow element of the
' 2003 Amended BiOp RPA. The Federal Defendants argue
that these claims are now moot because the Corps has
successfully completed the mechanical construction of
1,200 acres of shallow water habitat, which permits the
Corps to avoid the summer low flow requirement.” The
Corps has announced that it has no plans to implement
summer low flows in the foreseeable future. Missouri,
NPPD and Blaske Marine counter that because the Corps
retains the discretion to implement the summer low flow
in any given year under its adaptive management frame-
work, these claims fall within the “capable of repetition,
yet evading review” exception to mootness. Ubbelohde, 330
F.3d at 1023 (quoting Weinstein v. Bradford, 423 U.S. 147,
149, 96 S.Ct. 347, 46 L.Ed.2d 350 (1975)).
We conclude that the claims based on summer low
flow are moot. The “capable of repetition, yet evading
review” exception “applies when two conditions are met:
‘(1) the challenged action [is) in its duration too short to be
fully litigated prior to cessation or expiration, and (2)
there [is) a reasonable expectation that the same com-
plaining party [will] be subject to the same action again.’”
Id. (quoting Spencer v. Kemna, 523 U.S. 1, 17, 118 S.Ct.
978, 140 L.Ed 2d 43 (1998)).
” American Rivers has challenged the successfu! completion of the
1,200 acres in the MDL court. The MDL court dismissed the suit
without prejudice for procedural reasons. That dismissal has been
separately appealed to this Court, Docket No. 06-1200, end is still
pending.
App. 21
In this case, it appears that the 30-day duration of a
summer low flow period, particularly if it is implemented
with little prior warning, is too short to be fully litigated
prior to expiration. However, there is no reasonable
expectation that the Corps will implement the 2003
Amended BiOp summer low flow in the future. Although a
“‘party need not show with certainty that the situation
will recur,’” a “speculative possibility is not a basis for
retaining jurisdiction over a moot case.” McCarthy v.
Ozark Sch. Dist., 359 F.3d 1029, 1036 (8th Cir.2004)
(quoting Van Bergen v. Minnesota, 59 F.3d 1541, 1547 (8th
Cir.1995)). We are aware that the 2003 Amended BiOp
requires the Corps to be ready to implement summer low
flows as low as 21 Kefs in the future if monitoring reveals
that the alternate measures are not benefitting the pro-
tected species as expected. Nevertheless, as we discuss
later in this opinion, at this point there is no reason to
doubt the utility of those alternate measures. Therefore,
“we find nothing to suggest a likelihood” that the Corps
will decide to implement a summer low flow in future
years. McCarthy, 359 F.3d at 1036.
Because there is no reasonable expectation at this
point in time that the Corps will implement the 2003
Amended BiOp summer low flow in the future, we con-
clude that the following claims are moot: (1) NPPD’s claim
that the FWS failed to consider the economic feasibility of
the summer low flow requirement in developing the 2003
Amended BiOp; (2) Missouri’s claim that the loss of shal-
low water habitat for larval and juvenile pallid sturgeon in
central Missouri state resulting from summer low flow
constitutes an impermissible “take” of the sturgeon under
ESA §9; and (3) Blaske Marine’s NEPA claim that a
supplemental EIS is required for the 2003 Amended BiOp
App. 22
summer low-flow requirement. We vacate the MDL court's
grant of summary judgment to the Federal Defendants on
these claims and instruct the MDL court to dismiss these
claims without prejudice.
D. The Validity of the 2003 Amended BiOp
NPPD argues that the 2003 Amended BiOp is invalid
because the FWS violated regulations applicable to Bio-
logical Opinions. American Rivers challenges the 2003
Amended BiOp on the grounds that the 2003 Amended
BiOp RPA contradicts its own factual findings and the
administrative record and does not insure against jeop-
ardy to the protected species.
1. The Environmental Baseline for tne 2003
Amended BiOp
NPPD contends that the FWS used an improper
environmental! baseline in producing the 2003 Amended
BiOp. “The environmental baseline includes the past and
present impacts of all Federal, State, or private actions
and other human activities in the action area....” 50
C.F.R. § 402.02. Jeopardy to the protected species result-
ing from the proposed action is measured relative to the
species’ status under the baseline. Jd. The FWS used a
“run-of-the-river” baseline in which the dams and physical
channel modifications are assumed to be in place, but all
floodgates are assumed to be wide open, with no flow
control. NPPD argues that normal operation under the
1979 Master Manual was the proper baseline because it is
a “past impact” of a separate federal action and would
continue to control operations absent the proposed action.
Because continued operation under the 1979 Master
App. 23
Manual would cause the protected species’ chances of
recovery to deteriorate, its inclusion in the baseline would
tend to eliminate a finding of jeopardy for any proposed
action.
According due deference to the FWS’ interpretation of
its own regulations, Friends of the Boundary Waters
Wilderness, 164 F.3d at 1121, we agree with the FWS that
hypothetical continued operation under the previous
version of the Master Manual in future years, as the
alternative to the proposed action of updating the Master
Manual, does not in any sense constitute a “past impact”
of federal action. As the district court recognized, this
argument is essentially a different twist on the argument
that the Corps has no discretion in operating the reservoir
system. If the FCA mandated that the Corps must manage
the system to enable, for example, a barge of specific size
riding a specific depth below the waterline to navigate the
river between Sioux City and the Mississippi River at all
times between April 1 and December 1, there would be
some merit to including that non-discretionary condition
in the environmental baseline along with the permanent
physical presence of the dams and channel modifications.
However, given that the FCA “clearly gives a good deal of
discretion to the Corps in the management of the River,”
Ubbelohde, 330 F.3d at 1027, we cannot say that it was
arbitrary and capricious for the FWS not to include a
specific operational profile in the environmental baseline.
Therefore, we affirm the grant of summary judgment to
the Federal Defendants on this claim.
App. 24
2. Use of the Best Scientific and Commercial
Data Available
NPPD argues that the FWS did not rely on the best
scientific data available in its efforts to create a “normal-
ized” hydrograph in the 2003 Amended BiOp RPA. “In
formulating its biological opinion, [and] any reasonable
and prudent alternatives ... the [FWS] wili use the best
scientific and commercial data available.” 50 C.FR.
§ 402.14(g)(8); see 16 U.S.C. § 1536(a)(2).
To create a normalized version of the summer low flow
portion of the natural hydrograph, the 2003 Amended
BiOp calls for low flows beginning in July. NPPD directs
our attention to a United States Geological Survey report
in the administrative record showing that, before con-
struction of the dams, the lowest summer flows usually
occurred between August and early October. NPPD con-
tends that this incongruity evidences a failure to use the
best scientific data available to formulate the 2003
Amended BiOp.
The administrative record as a whole shows that the
FWS did not ignore the best scientific data on the summer
low flow in formulating the 2003 Amended BiOp. For
example, in a document e-mailed by the FWS to new
members of the 2003 Amended BiOp development team in
November 2003, the FWS recognized that “/tjhe historic
hydrograph began to fall at Gavins Point in mid-June and
reached it’s [sic] lowest levels in the fall months,” but
indicated that the FWS proposal would end the low flow
period in August because higher releases in the fall were
necessary “to evacuate any excess water [from the reser-
voirs) prior to the next water year.” The FWS then stated
that, “[w]hile this approach is not a perfect fit to the
historic hydrograph, we believe that it sufficiently mimics
App. 25
... the natural hydrograph” to have the necessary benefi-
cial effect on the protected species.
The FWS has never found that an exact replication of
the natural hydrograph was necessary to avoid jeopardy to
the protected species, and the record shows “a rational
connection between the facts found and the decision made”
about the timing of the low flow period. Gifford Pinchot
Task Force v. United States Fish & Wildlife Serv., 378 F.3d
1059, 1065 (9th Cir.2004). Therefore, we affirm the grant
of summary judgment to the Federal Defendants on this
claim.
3. The Consistency of the 2003 Amended BiOp
Factual Findings and the RPA for the Pal-
lid Sturgeon
American Rivers argues, on the basis of the factual
findings in the 2003 Amended BiOp and the administra-
tive record underlying it, that the conditional replacement
of the 2000 BiOp RPA summer low flow requirement with
the mechanical construction of 1,200 additional acres of
artificial shallow water habitat for the pallid sturgeon is
arbitrary and capricious.
The 2003 Amended BiOp incorporated findings from
the 2000 BiOp and stated that “[uljntil a semblance of the
normalized hydrograph is restored and habitat is gener-
ated and maintained through reestablishment of these
[ecological] processes, listed species will continue to
decline.” In addition, the executive summary of the 2003
Amended BiOp summarizes, with regard to the pallid
sturgeon:
The proposed accelerated habitat restoration
program in the Lower Missouri River will have
App. 26
little benefit to the pallid sturgeon without a con-
current or subsequent change in operations to
provide a more normalized hydrograph to (1)
provide the spawning cues that are critical for
pallid sturgeon reproduction and (2) allow larvae
and juveniles to move into shallow water habitat.
American Rivers contends that the above statements,
and others like them in the administrative record, show
that the FWS was irrational in abandoning any semblance
of half of the natural hydrograph, the summer low flow, in
exchange solely for habitat construction. However, evi-
dence in the record adequately explains the decision made
by the FWS. First, Appendix A of the Corps’ 2003 Biologi-
cal Assessment, entitled “New Information Since the 2000
BiOp,” includes the results of extensive modeling of the
river showing that the proposed 2000 BiOp summer low
flow would be expected to increase suitable shallow water
habitat by 1,189 acres over that existing during regular
summer service flows. The creation of 1,200 acres of
habitat, therefore, provides the same total acreage of
accessible calm, shallow pools during regular summer
service flows as the 2000 BiOp summer low flow would
have produced. Second, the 2003 Amended BiOp RPA
retains a spring rise requirement, and the Corps must
tailor the spring rise to provide the necessary biological
spawning cues and floodplain connectivity with the shal-
low water habitat. Third, the 2003 Amended BiOp RPA
requires the Corps to monitor the pallid sturgeon popula-
tion and collaborate with the FWS to adjust these meas-
ures if necessary. Finally, the avoidance of summer low
flow preserves the existing Lisbon chute shallow water
habitat, the only site in the river where larval pallid
sturgeon occur naturally, from potential damage.
App. 27
American Rivers argues that the 2003 Amended BiOp
did not state that the mechanical construction of 1,200
acres was designed to replace the additional acreage that
would have resulted from summer low flow. American
Rivers contends that this rationale is therefore an imper-
missible post hoc rationalization by counsel. “[(C]ourts may
not accept appellate counsel's post hoc rationalizations for
agency action.” Motor Vehicle Mfrs., 463 U.S. at 50, 103
S.Ct. 2856. However, there is no requirement that every
detail of the agency’s decision be stated expressly in the
2003 Amended BiOp. The rationale is present in the
administrative record underlying the document, and this
is all that is required. Mo. Coalition for the Env't v. Corps
of Eng’rs of the United States Army, 866 F.2d 1025, 1031
(8th Cir.1989), overruled on other grounds, Goos v. ICC,
911 F.2d 1283 (8th Cir.1990). Therefore, the Federal
Defendants’ rationale is not an impermissible post hoc
rationalization.
We conclude that the Federal Defendants have dem-
onstrated a rational connection between the facts in the
record and the decision to substitute 1,200 mechanically
constructed acres of shallow water habitat for the 1,189
acres that would have been created by the 2000 BiOp
summer low flow. Therefore, we affirm the grant of sum-
mary judgment to the Federal Defendants on this claim.
4. The Consistency of the 2003 Amended BiOp
Factual Findings and the RPA for the Least
Tern and Piping Plover
American Rivers argues that the elimination of the
2000 BiOp RPA spring rise and summer low flow require-
ments for the benefit of the least tern and piping plover is
arbitrary and capricious. The 2000 BiOp flow requirements
App. 28
for the tern and plover were premised on factual findings
that a spring rise was necessary to scour vegetation from
sandbars, while the summer low flow would expose the
resulting sparsely vegetated sandbars for safe nesting.
The 2003 Amended BiOp RPA replaced the spring rise and
summer low flow requirements with increased focus on the
mechanical construction and clearing of sandbar habitat
for the birds and adjustment of flow levels during the
nesting season to minimize the potential for flooding nests.
In making these changes in the 2003 Amended BiOp,
the FWS had the benefit of a new Corps analysis of the
river’s geomorphological processes. The Corps’ computer
models indicated that, given the man-made alterations to
the river channel, a spring rise as envisioned in the 2000
BiOp would not produce scoured sandbar habitat for use
by the tern and plover. In fact, the models showed that
those flows were more likely to reduce the quality of
previously available habitat.
The 2003 Amended BiOp also included information
about tern and plover populations that was not available
for the 2000 BiOp. The updated information included the
fact that “recent counts of least terns (approximately
12,305 terns in 2003) exceed the overall recovery objective
of 7,000 birds,” although geographic distribution and
population stability goals were not yet satisfied. Regarding
the recovery goal for piping plovers, the 2003 Amended
BiOp stated that “[iJn 2001, the Missouri River exceeded
this recovery goal for the first time. It was also exceeded in
2002 and 2003.”
Based on this new information, it was rational for the
FWS to conclude that the 2000 BiOp spring rise and
summer low flow elements were not necessary to avoid
App. 29
jeopardy to the tern and plover, and to instruct the Corps
to focus its resources on the mechanical construction of
habitat, monitoring and adaptive management.
American Rivers cites the lack of conclusive proof in
the administrative record that the mechanically con-
structed sandbars will develop into an ecologically func-
tional habitat for the plover and tern. American Rivers
contends that, without such conclusive proof, the 2003
Amended BiOp RPA fails to satisfy the ESA § 7 require-
ment that the plan “insure” against jeopardy to the listed
species. This argument fails because, while the proposed
mitigation measures must insure against jeopardy to the
protected species if they work as injended, while there
must be a rational reason to expect them to work as
intended, and while they must in fact be possible to
implement, there is no requirement for the FWS to ensure
the overall success of the plan. See Southwest Ctr for
Biological Diversity v. United States Bureau of Reclama-
tion, 143 F.3d 515, 523-24 (9th Cir.1998). We also note that
the 2003 Amended BiOp requires the Corps to monitor
closely the performance of the mechanically constructed
sandbar habitat and test methods of improving the mix of
organic material in the sandbars.
Finally, American Rivers cites its own experts for the
contention that the higher-magnitude 2000 BiOp RPA
spring rise would be more beneficial to the protected
species than the default spring rise in the 2003 Amended
BiOp RPA. We need not address that contention:
(The FWS) was not required to pick the first rea-
sonable alternative [it] came up with in formulat-
ing the RPA. [It] was not even required to pick
the best alternative or the one that would most
effectively protect the [species] from jeopardy.
App. 30
The [FWS] need only have adopted a final RPA
which complied with the jeopardy standard and
which could be implemented by the agency.
Southwest Ctr. for Biological Diversity, 143 F.3d at 523
(quotation omitted).
“Because there was a rational connection between the
facts found in the [BiOp] and the choice made to adupt the
final RPA, and because we must defer to the special
expertise of the FWS in drafting RPAs that will suffi-
ciently protect endangered species,” the decision to elimi-
nate the 2000 BiOp flow changes from the 2003 Amended
BiOp RPA for the plover and tern was not arbitrary and
capricious. Jd. We affirm the grant of summary judgment
to the Federal Defendants on this claim.
E. Selection of the Preferred Alternative in
the EIS
American Rivers argues that the Corps’ selection of
the Preferred Alternative (“PA”) was arbitrary and capri-
cious because the Corps did not sufficiently explain why
the PA was superior to plan GP2021, favored by American
Rivers. Plan GP2021 included the spring rise and summer
low flow prescribed by the 2000 BiOp RPA, while the PA
became the 2004 Master Manual.
The EIS contains summary statements about the
selection of the PA, such as:
The Corps believes that the PA, when combined
with the other measures . . . , conserves more water
in the upper three lakes during extended droughts,
meets the needs of ESA-listed fish and wildlife spe-
cies, is consistent with the Corps’ responsibilities
App. 31
under environmental laws and tribal trust re-
sponsibilities, and provides for the Congression-
ally authorized uses of the System.
American Rivers argues that because plan GP2021 also
generally meets those same criteria and outperforms the
PA with respect to wildlife concerns, the Corps’ decision to
select the PA has not been sufficiently explained. “[A]n
agency must cogently explain why it has exercised its
discretion in a given manner.” Motor Vehicle Mfrs., 463
US. at 48, 103 S.Ct. 2856.
NEPA requires an agency to present the EIS alterna-
tives in comparative form, “sharply defining the issues and
providing a clear basis for choice among options by the
decision-maker and the public.” 40 C.F.R. § 1502.14. In
this case, the EIS included a detailed comparative analysis
of the effects of all five alternatives on a wide range of
interests including fish and wildlife resources, flood
control, water supply, hydropower, recreation and naviga-
tion. This analysis, presented in a series of tables, enables
the reader to compare the relative effectiveness of each of
the alternatives, as required by NEPA. For example, the
Federal Defendants point to tables showing the strong
superiority of the PA over plan GP2021 in maximizing
summer revenue from reservoir hydropower production
while creating far less risk of disruption for downstream
summer power generation. The tables also show that the
PA outperforms plan GP2021 in the areas of navigation,
groundwater damage and floodplain crop damage. “If the
adverse environmental effects of the proposed action are
adequately identified and evaluated, the agency is not
constrained by NEPA from deciding that other values
outweigh the environmental costs.” Robertson v. Methow
App. 32
Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835,
104 L.Ed.2d 351 (1989).
Contrary to what American Rivers seems to suggest,
there is no further NEPA or Administrative Procedure Act
requirement to repackage the information in the summary
tables into prose one-to-one comparisons of the PA with
each of the other alternatives. We conclude that the
comparisons provided in the EIS “cogently explain why
[the Corps] has exercised its discretion in a given manner.”
Motor Vehicle Mfrs., 463 U.S. at 48, 103 S.Ct. 2856. There-
fore, we affirm the grant of summary judgment to the
Federal Defendants on this claim.
F. Claim of the Mandan, Hidasta and Arikara
Nation Regarding the Management of
Lake Sakakawea
The Nation claims that the Corps has failed to choose
the FCA — and ESA-compliant reservoir management plan
that best spurs economic self-sufficiency for the Nation's
members and protects the Nation’s cultural resources. The
Nation seeks a court order to enjoin the Corps to correct
these “deficiencies.” The MDL court dismissed the Nation's
claim for lack of Article ITI standing.
To show Article III standing, a plaintiff must demon-
strate (1) an “injury in fact” that is both “concrete and
particularized” and “actual! or imminent, not conjectural or
hypothetical,” (2) “a causal connection between the injury
and the conduct complained of,” and (3) a likelihood, as
opposed to mere speculation, “that the injury will be
redressed by a favorable decision.” Lujan v. Defenders of
Wildlife, 504 U.S. 555, 560-61, 112 S.Ct. 2130, 119 L.Ed.2d
351 (1992) (quotations omitted).
App. 33
The Nation articulates its members’ general interest
in the operation of Lake Sakakawea, including an interest
in the economic health of the sport fishing industry located
there. However, the Nation does not articulate how reser-
voir operations under the 2004 Master Manual cause an
injury to the Nation that can be redressed by a favorable
court decision. There is nothing in the amended complaint,
for example, stating why reservoir operation under the
2004 Master Manual, which is more sensitive to reservoir
recreation needs during prolonged droughts than was the
1979 Master Manual, will damage the viability of Lake
Sakakawea’s sport-fishing industry. Furthermore, if we
were to do exactly as the Nation requests in its amended
complaint and order the Corps to re-formulate the 2004
Master Manual in a manner that, given FCA and ESA
constraints, would best “spur Tribal self sufficiency and
economic development and protect Indian trust assets,” it
is not at all clear what outcome could be adjudged to
comply with our order. The Nation simply has not set forth
a “concrete and particularized” injury that is likely to be
redressed by such an order. Lujan, 504 U.S. at 560-61, 112
S.Ct. 2130. Therefore, we affirm the dismissal of this claim
for lack of Article [II standing.
G. Extra Record Materials Offered by Ameri-
can Rivers
Nebraska challenges the submission of three declara-
tions by American Rivers that were not part of the admin-
istrative record. The MDL court apparently considered
Nebraska's motions to strike these declarations to be moot.
Because we affirm the grant of summary judgment to the
Federal Defendants on American Rivers’ claims, we also
find Nebraska's motions to strike to be moot.
App. 34
Ill, CONCLUSION
On the following three claims, we vacate the MDL
court’s grant of summary judgment to the Federal Defen-
dants and instruct the MDL court to dismiss without
prejudice: (1) NPPD’s claim that the FWS failed to con-
sider the economic feasibility of the summer low-flow
requirement in developing the 2003 Amended BiOp; (2)
Missouri's claim that the loss of shallow water habitat for
larval and juvenile pallid sturgeon in central Missouri
resulting from summer low flow constitutes an impermis-
sible “take” of the sturgeon under ESA § 9; and (3) Blaske
Marine’s NEPA claim that a supplemental EIS is required
for the 2003 Amended BiOp summer low-flow require-
ment. On all other claims, we affirm the judgment of the
MDL court.
App. 35
UNITED STATES DISTRICT COURT
DISTRICT OF MINNESOTA
In re: Operation of the Missouri River
System Litigation 03-MD-1555 (PAM)
MEMORANDUM AND ORDER
This matter is before the Court on various Motions for
Summary Judgment. This case arises out of the manage-
ment of the Missouri River, which flows from Montana to
Missouri. Pursuant to the Flood Control Act of 1944
(“FCA”), the United States Army Corps of Engineers
(“Corps”) manages the river and its reservoirs. In conjunc-
tion with its responsibilities under the FCA, the Corps
developed a more detailed management plan, the “Mis-
souri River Main Stem Reservoir System Master Water
Control Manual” (“Master Manua]”). The Master Manual
was first developed forty years ago, and has been revised
three times, in 1973, 1975 and 1979. In the late 1980s, the
Corps began to revise the Master Manual again. Finally,
after fifteen years and repeated delays, the Corps issued a
revised Master Manual on March 19, 2004.’ The Corps
* Revision of the Master Manual is an extensive and lengthy
process that requires the Corps to consult with various agencies and
comply with various regulations and procedures. Prior to the issue of
the new Master Manual, the Corps must issue a Final Environmental
Impact Statement (“Final EIS”), and allow 30 days for public review
and comment as required by the National Environmental Policy Act
(“NEPA”). Here, the Court shortened the NEPA review period to two
weeks and required the Corps to issue a revised Master Manual on
March 19, 2004. On March 1, 2004, ine Corps requested a waiver of the
NEPA review period, which the Environmental Protection Agency
(“EPA”) granted “fo: compelling reasons of national policy.” From the
outset, the Court refuses to entertain any Motions attacking the
(Continued on following page)
App. 36
also issued the 2004 Annual Operating Plan (“AOP”) on
March 19, 2004.
Over the last several years, the Missouri River has
experienced prolonged drought conditions. The Corps has
been forced to make difficult decisions regarding the
allocation of water to the different interests in the basin.
As a result, interested parties filed lawsuits in various
districts, seeking to protect their interests. See American
Rivers v. U.S. Army Corps of Eng’rs, File No. 1:03-241
(D.D.C.); Nebraska v. Ubbelohde, 8:02-217 (D. Neb.)
Blaske Marine, Inc. et al. v. Norton, File No. 8:03-142 (D.
Neb.); North Dakota v. Ubbelohde, File No. 1:02-59 (D.
N.D.); South Dakota uv. Ubbelohde, File No. 3:02-3011 (D.
S.D.). In July 2003, the multi-district litigation panel
consolidated these actions and transferred them to this
Court. In re Operation of the Missouri River Litig., File No.
03-1555 (PAM). Pursuant to the Court's scheduling order
and as a result of the coordinated efforts of the parties, the
issues presented in these various cases are now before this
Court. This Memorandum and Order disposes of al! claims
before the Court.
BACKGROUND
A. The Parties
The parties involved in this action include: (1) the
states of North Dakota, South Dakota, Montana, Ne-
braska, and Missouri; (2) Blaske Marine, Coalition to
Protect the Missouri River, ConopcoPhillips Company,
sufficiency of the NEPA review period and dismisses al! claims pertain-
ing io this issue
App. 37
Ergon Asphalt & Emulsions, Inc., Magnolia Marine
Transport Company, Midwest Area River Coalition 2000,
and Midwest Terminal Warehouse Company, Inc. (collec-
tively “Blaske Marine”); (3) MO-ARK Association and
Missouri River Keepers (collectively “MO-ARK”); (4)
American Rivers, Environmental Defense, National
Wildlife Federation, various state Wildlife Federations,
and Izaak Walton League of America (collectively “Ameri-
can Rivers”); (5) Missouri River Energy Services (“MRES”);
(6) Nebraska Public Power District (“NPPD”); (7) the
Mandan, Hidasta and Arikara Nation (“the Nation”); and
(8) the Corps, Fish and Wildlife Service (““FWS”), and
various directors, secretaries and officers of these two
government agencies (collectively “Federal Defendants”).
Because of their competing interests, it is difficult to
classify each party as a Plaintiff, Defendant, or both.
Rather, the claims can be categorized into four different
topics: (1) Flood Control Act (“FCA”) claims; (2) Endan-
gered Species Act (“ESA”) claims; (3) NEPA claims; and (4)
collateral claims. The Court will address each topic in
turn.
B. The Revision of the Master Manual
In 1990, pursuant to the Endangered Species Act
(“ESA”), the Corps conducted its first consultation with
the FWS on the effects of its Missouri River operations on
endangered and threatened species.’ In 2000, the Corps
* An endangered species is “in danger of extinction throughout all
or a significant portion of its range.” 16 U.S.C. § 1532(6). A threatened
species is “likely to become an endangered species within the foresee-
able future throughout all or a significant portion of its range.” 16
U.S.C. § 1632(20).
App. 38
again consulted with the FWS. Following these consulta-
tions, the FWS issued the 2000 Biological Opinion (“2000
BiOp”), that concluded that the Corps’ proposed river
operations for 2000 were likely to jeopardize three species:
the endangered least tern, the threatened piping plover,
and the endangered pallid sturgeon. (Fish and Wildlife
Service Administrative Record (“FWS AR”) 1237 at 29216-
17.) The 2006 BiOp included a Reasonable and Prudent
Alternative (“RPA”), designed to avoid jeopardy to the
tern, plover and sturgeon. Specifically, this RPA recom-
mended a spring rise and low summer water flow regime,
in conjunction with habitat construction, to avoid jeopardy.
(Id. at 29229-32.)
In April 2003, the Corps consulted with the FWS
again on the Corps’ proposed operations for 2003. The
FWS then issued a supplemental Biological Opinion,
concluding that although the proposed operations for 2003
deviated from the RPA in the 2000 BiOp, the proposed
operations were justified. The District Court of the District
of Columbia disagreed, and granted a preliminary injunc-
tion ordering the Corps to comply with the 2000 BiOp. See
American Rivers v. U.S. Army Corps of Eng’rs, 271
F. Supp. 2d 230 (D.D.C. 2003). In November 2003, the
Corps again consulted with the FWS. The FWS then
amended the 2000 BiOp. (2003 Amended Biological Opin-
ion (hereinafter “2003 Amended BiOp”) at FWS AR 1457.)
The FWS again concluded that jeopardy would result to
the plover, tern and the sturgeon, and proposed a new
RPA. The 2003 RPA contained three separate parts, each
part applicable to a single species.
As noted above, the Corps issued the 2004 Master
Manual on March 19, 2004. The 2004 Master Manual,
along with the 2004 AOP, are based on the 2003 Amended
App. 39
BiOp. In accordance with NEPA, the Corps issued the
Final EIS for the 2004 Master Manual on March 5, 2004.
This Court truncated the public comment and review
period for the 2004 Master Manual. Therefore, on March
19, 2004, pursuant to Court Order, the Corps issued the
2004 AOP, 2004 Master Manual, and Record of Decision
(“ROD”). The issues in this litigation involve both the
substance of the 2004 Master Manual and the procedures
the Corps used to formulate the 2004 Master Manual.
DISCUSSION
This case involves the interplay of the Corps’ obliga-
tions under the FCA, ESA and NEPA. The FCA authorizes
the Corps to operate the Missouri River by balancing a
variety of river interests. The ESA seeks to protect and
conserve endangered and threatened species and their
habitats. NEPA requires agencies to consider and evaluate
the potential environmental consequences that may result
from an agency action. The Corps must consider both
competing river interests and its legal obligations in the
operation of the Missouri River.
A. The Flood Control Act of 1944
1. Navigation and Flood Control
The FCA provides for the management of the Missouri
River and its reservoirs. Pub. L. No. 78-534, 58 Stat. 887
(1944). The FCA is the product of the “Pick-Sloan” plan.
The “Pick” Plan, submitted to Congress by the Corps,
proposed the construction of reservoirs to effectively
control flooding, but also acknowledged that “|t/he devel-
opment of such a comprehensive plan involves adjustment
of many factors of flood control, navigation, irrigation,
App. 40
hydroelectric power production and numerous other
functions of water conservation and management.” H.R.
Doc. No. 78-475 at 6 (1944). The “Pick” Plan did not rank
any river interest above another, but rather seeks to
provide the “widest range of multiple benefits” and “to
contribute most significantly to the welfare and livelihood
of the largest number of people.” Jd. at 7. The “Sloan”
Plan, submitted to Congress by the Bureau of Reclama-
tion, proposed the construction of reservoirs “for the
purposes of storing water, and re. asing it during periods
of low flow ... [sjuch reservoirs will contribute to flood
control ... aid navigation ... enlarge the supply of water
generation of electrical energy.” S. Doc. No. 78-191 at 18
(1944). The “Sloan” Plan does not dictate a priority of river
interests, but rather seeks to provide a “basin-wide plan
most likely to yield the greatest good to the greatest
number of people.” Jd. at 17. The “Sloan” Plan declared
that any plan for operation of the river must “recognize all
beneficial uses of waters, weigh their relative values, and
make a compromise, from a basin-wide viewpoint, in each
instance of conflict.” Jd. at 21. These two plans combined
to develop one plan for the river's operation, the “Pick-
Sloan” Plan. S. Doc. No. 78-247 (1944). This “unified” plan
was intended to “secure the maximum benefits for flood
control, irrigation, navigation, power, domestic and sani-
tary purposes, wildlife, and recreation” in the Missouri
River. Jd. at 5; See Id. at 2.
Courts acknowledge that the “dominant” functions of
the FCA include flood control and downstream navigation,
but they also acknowledge that other river interests
should similarly be provided for. ETSI Pipeline Project v.
Missouri, 484 U.S. 495, 512 (1988); See also South Dakota
App. 41
v. Ubbelohde, 330 F.3d 1014, 1019-20 (8th Cir. 2003). The
Eighth Circuit acknowledged that the FCA requires that
“the Corps must strike a balance among many interests,
including flood control, navigation and recreation.” Ubbe-
lohde, 330 F.3d at 1019, 1027. The Corps’ obligations
under the ESA are within the scope of these “many inter-
ests.” See American Rivers, 271 F. Supp. 2d at 252. Be-
cause of this balance, the Court may only review the
Corps’ actions to ensure that the Corps considered all river
interests when formulating a given plan. Jd. at 1027. The
language of the FCA does not require a particular out-
come, but rather that the Corps consider all interests in its
operations. Jd. There is no language in either caselaw or
legislative history that dictates that the Corps must
always maintain a particular water level or specific water
season in its river operations. All river interests must be
considered and evaluated to “secure the maximum bene-
fits” to river interests. The Court finds that the FCA does
not impose a non-discretionary duty to maintain minimum
navigation flows or season lengths. The Corps’ prioritiza-
tion of river interests is discretionary.
However, the Corps is not entitled to abandon these
interests; it must consider and balance river interests to
achieve maximum benefits. Some parties propose that
navigation is abandoned under the 2004 Master Manual,
because in the event that by March 15 total system stor-
age is below 31 million acre-feet, the 2004 Master Manual
provides that flows be reduced such that the navigation
season is eliminated for that particular water year. As the
Corps points out, however, the FCA requires it to defer to
upstream consumptive uses in the event these uses “con-
flict” with downstream navigation. See 33 U.S.C. § 701-
l(b). In the rare event that this condition presents itself,
App. 42
the 2004 Master Manual’s elimination of the navigation
season ensures that upstream consumptive uses are given
deference as required by law. The Court finds that the
2004 Master Manual complies with the FCA.
The priority that the Corps gives the competing river
interests is a discretionary function, and subject to the
ESA. If Congress intended to require that the Corps
always maintain minimum levels of navigation or a
specific navigation season, then Congress must amend the
FCA accordingly. Absent any evidence to the contrary, the
Court concludes that prioritization of river interests is
discretionary.
2. Ambiguity of the Master Manual
Ubbelohde declared that the 1979 Master Manual
limited the Corps’ discretion to operate the Missouri River.
330 F.3d at 1029. As a result, Ubbleohde found that judi-
cial review of the Corps’ decisions was appropriate. Jd. In
reaching that conclusion, the Eighth Circuit relied on a
combination of three considerations: (1) the language of
the manual itself; (2) the corresponding agency regulations
at 33 C.F.R. § 222.5; and (3) the Corps’ treatment of the
manual. Jd. (citing Northwest Nat'l Bank v. Dep't of the
Treasury, 917 F.2d 1111, 1116-17 (8th Cir. 1990)). Unlike
the 1979 Master Manual, the 2004 Master Manual ex-
pressly states that “the Master Manual! has been amended
to clearly reflect the Corps’ intent that it not be considered
a binding regulation.” (2004 Master Manual, at Introduc-
tion.) The Corps essentially is attempting to reserve the
right to vary operations from those set forth in the Master
Manual, in the event that changed conditions or unfore-
seen circumstances require it to do so. The Corps insists
App. 43
that the FCA, its regulations, and the Ubbelohde decision
permit it to retain such discretion in its operations. Mis-
souri, Nebraska, and the NPPD insist that this discretion
is expressly prohibited by Ubbelohde.
Missouri, Nebraska and NPPD misinterpret the
discretion the Corps seeks to retain. The Corps does not
intend to disregard the Master Manual and thus operate
the River with unfettered discretion. To the contrary, the
Corps seeks to retain the discretion to deviate from the
2004 Master Manual in the event that unforeseen circum-
stances arise. The Corps cannot anticipate and provide for
all possible circumstances affecting river operations.
Although historical patterns provide some insight into
future circumstances, the Corps simply cannot predict the
future. If the Corps was prohibited from varying its
operations from the Master Manual to adjust for unfore-
seen circumstances, and instead was required to conform
to a Master Manual that did not contemplate a given
situation, the Corps would arguably violate its obligations
under the FCA and Ubbelohde to properly balance river
interests.
However, the Court does not construe this discretion
to permit the Corps to perpetually evade judicial review.
The Eighth Circuit determined that the 1979 Master
Manual could serve as a basis for court review. Ubbelohde,
330 F.3d at 1929-30. Although the Eighth Circuit made
this determination in part by examining the language of
the 1979 Master Manual, it also relied on the regulations
governing the Corps’ promulgation of the Master Manual.
Particularly, these regulations “are not the types of proce-
dures one would expect in the promulgation of an internal,
non-binding agency guideline.” Jd. at 1029; 33 C.F.R.
§ 222.5. Therefore, pursuant to Ubbelohde, this Court
App. 44
determines that the 2004 Master Manual may likewise
serve as a basis for judicial review. The 2004 Master
Manual, like the 1979 Master Manual, is binding on the
Corps to the extent that the parties may seek judicial
review to ensure that the Corps’ operations conform to the
2004 Master Manual. The Corps acknowledges that it
must abide by the 2004 Master Manual, and that any
permanent amendment to the existing provisions of the
2004 Master Manual must go through the procedures
contained in 33 C.F.R. § 222.5. (Fed. Defs.’ Reply Mem. in
Supp. of Mot. on FCA and NEPA at 12.) The Court ac-
knowledges that the Corps must be permitted to vary its
operations in the event that changed circumstances
require it to do so, but similarly holds that this discretion
does not eliminate the propriety of judicial review of the
lawfulness of the agency action. Therefore, the 2004
Master Manual satisfies the procedural requirements of
Ubbelohde and the FCA.
3. Recreational Interests
South Dakota maintains that the FCA subordinates
navigation to upstream uses of irrigation and domestic
water supply. The “O’Mahoney- Millikin Amendment,” 33
U.S.C. § 701-1(b) states:
The use for navigation, in connection with the
operation and maintenance of such works herein
authorized for construction, of waters arising in
states lying wholly or partly west -f the ninety-
eighth meridian shal] be only such use as does
not conflict with any beneficial consumptive use,
present or future, in States lying wholly or partly
west of the ninety-eighth meridian, of such waters
App. 45
for domestic, municipal, stock water, irrigation,
mining or industrial purposes.
This provision requires that when a conflict between
upstream consumptive uses and downstream navigation
exists, upstream consumptive uses receive deference.
South Dakota does not argue that the 2004 Master Man-
ual does not serve these consumptive uses. Rather, South
Dakota argues that the 2004 Master Manual is in “con-
flict” with South Dakota’s consumptive beneficial uses,
because the 2004 Master Manual allows for lower levels in
reservoirs such that South Dakota may be required to
build extensions to irrigation lines or extend intake
structures for drinking water at these reservoirs.
South Dakota’s argument lacks merit. The statute is
not designed to pretect against these kind of difficulties,
but rather designed to “prohibit destruction of state-
created water rights without any compensation at all, by
the assertion of an overriding federal easement for naviga-
tion.” Turner v. Kings River Conservation Dist., 360 F.2d
184, 192 (9th Cir. 1966) (interpreting 33 U.S.C. § 701-1).
Moreover, requiring South Dakota to build extensions for
irrigation lines or drinking water is not in “conflict” with
South Dakota's consumptive beneficial uses, because there
is no destruction or denial of South Dakota's water rights.
Kansas v. United States, File No. 00-4153, 2000 WL
1665260 (D. Kan. Sept. 29, 2000) (finding that mere
“potential threat” that Corps’ drainage of water from three
reservoirs would deny adequate drinking water or inter-
fere with industrial purposes insufficient to constitute
“conflict” with Corps’ actions). In fact, the 2004 Master
Manual sets forth the minimum levels required to be
maintained in the upstream reservoirs, and a “sufety
cushion” that ensures that these reserveir levels are
App. 46
maintained even under drought conditions. (See 2004
Master Manual, §§ VII-10 to VII-11 & Treble VII-3.) The
2004 Master Manual complies with the FCA.
4. Conclusion
The Corps’ Motion for Summary Judgment on FCA
claims is granted. Moticns by South Dakota, Nebraska,
NPPD, Missouri and Blaske Marine Plaintiffs are denied.
B. The Endangered Species Act and Related
Claims
The ESA seeks “to provide a means whereby the
ecosystems upon which endangered species and threat-
ened species depend may be conserved,” and “to provide a
program for the conservation of such ... species.” 16
U.S.C. § 1531(b). The ESA prohibits any person, including
federal agencies, to “take” a listed endangered species. 16
U.S.C. § 1538 aX 1B). “Take” means to “harass, harm,
pursue, hunt, shoot, wound, kill, trap, capture, or collect.”
16 U.S.C. § 1532(19).
In the event that its proposed action may jeopardize a
listed species, the Corps must prepare a “biological as-
sessment” evaluating both the species in the action area as
well as the potentia) effects the proposed action may have
on the species in the action area. See 50 C.F.R. § 402.02
(defining biological assessment). A proposed action will
“jeopardize” the species if it “reasonably would be ex-
pected, directly or indirectly, to reduce appreciably the
likelihood of both the survival and recovery of a listed
species in the wild by reducing the reproduction, numbers,
or distribution of that species.” Jd. If the Corps concludes
that its proposed actions may adversely affect the listed
App. 47
species, then it must initiate consultation with the FWS.
This consultation is required to “insure” that the Corps’
proposed action “is not likely to jeopardize the continued
existence of any endangered or threatened species or
result in the destruction or adverse modification of habitat
of such species.” 16 U.S.C. § 1536(a)2).
After this consultation, the FWS must prepare and
issue a Biological Opinion (“BiOp”) to the Corps. 16 U.S.C.
§ 1536(bX3). The BiOp must set forth the FWS’s opinion,
with supporting information, detailing how the Corps’
proposed actions will affect the species. 16 U.S.C.
§ 1536(bX 3A). In the event that the FWS concludes that
jeopardy to the species will result, the FWS must also set
forth a RPA. Jd. A RPA is an alternative action “that can be
implemented in a manner consistent with the intended
purpose of the action,” within the Corps’ legal authority. 50
C.F.R. § 402.02. A RPA must also be economically and
technologically feasible for the Corps to implement. /d.
The RPA is designed to avoid the likelihood of jeopardizing
the continuing existence of the species. Jd. If the FWS
concludes that either the Corps’ proposed action or the
implementation of a RPA may still result in an incidental
take of the species, the FWS must also include an Inciden-
tal Take Statement (ITS") in the BiOp. 16 U.S.C.
§ 1536(b\4); 50 C.F.R. § 402.14(i) (setting forth require-
ments for ITS). An incidental take statement identifies the
impact that the take will have on the species, identifies
“reasonable and prudent measures” (“RPM”) considered
necessary to minimize the impact, and sets forth the terms
and conditions required to implement the RPMs. /d. If the
Corps’ action is otherwise in compliance with the terms
and conditions set forth in the ITS, any action that harms
App. 48
a listed species will not be considered a “take” under the
ESA. 16 U.S.C. § 1536(0).
Because the ESA makes no specific provision for
judicial review of final agency actions, the scope of the
review is governed by the Administrative Procedures Act
(“APA”), 5 U.S.C. § 701 et seq. The Court reviews an
agency action to determine if it was “arbitrary, capricious,
an abuse of discretion or otherwise not in accordance with
law.” 5 U.S.C. § 706(2XA). If the agency decision fails to
articulate a satisfactory explanation for its conclusions,
relies on factors which Congress did not intend for it to
consider, or fails to consider an important aspect of the
problem, that decision is arbitrary and capricious. Motor
Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463
U.S. 29, 43 (1983). Under this standard, the Court's review
is narrow, evaluating whether the decision was based on a
consideration of relevant factors and whether there has
been a clear error of judgment. Marsh v. Oregon Natural
Res. Council, 490 U.S. 360, 378 (1989). The Court should
defer to the agency so long as the agency's interpretation
of the evidence was reasonable. Jd. The Court may not
substitute its judgment for that of the agency. Citizens to
Preserve Overtone Park, Inc. v. Vole, 401 U.S. 402, 416
(1971).
* American Rivers and other parties argue that Federal Defen-
Peet map tee ner par pg ag Nl eee a
Amended BiOp is a “reversal” of the 2000 BiOp. The Court disagrees.
The law does not require that Federal Defendants provide extensive
justification for the Corps’ decision. Rather, the decision must be
“rational,” providing “permissible reasons” for the change American
Rivers v. U.S. Army Corps of Eng'rs, 271 F. Supp. 2d 230, 266-66
(D.D.C. 2003).
App. 49
1. Claims by American Rivers
American Rivers contends that the Corps should
maintain river operations pursuant to the 2000 BiOp. As a
result of the 2000 ESA consultations, the FWS issued the
2000 BiOp that concluded that the Corps’ proposed opera-
tions would cause jeopardy to the tern, plover and stur-
geon. The RPA in the 2000 BiOp recommended that the
Corps vtilize both water flows and habitat construction,
among other elements, to avoid jeopardy to the plover, tern
and sturgeon. (FWS AR 1237 at 29232.) In November
2003, the Corps and the FWS reinitiated consultation
under the ESA. The FWS then issued the 2003 Amended
BiOp, which again concluded that the Corps’ proposed
operations would cause jeopardy to the plover, tern and
sturgeon. The 2003 Amended BiOp recommended a multi-
ple species RPA to avoid such jeopardy. The RPA has
individual sections allocated to each one of the species. In
particular, the 2003 RPA no longer requires both flow
modification and habitat construction to avoid jeopardy to
the plover aud tern. The sturgeon RPA maintains both
flow changes and habitat construction, though modified
somewhat from the 2000 BiOp RPA.
American Rivers submits numerous arguments
challenging the validity of the 2003 Amended BiOp.
American Rivers contends that the FWS’s elimination of
flow changes in the 2003 RPA applicable to the plover and
tern is arbitrary and capricious, and that the changes
made to the sturgeon RPA are also arbitrary and capri-
cious in violation of the ESA. American Rivers also main-
tains that the 2003 Amended BiOp violates the ESA
because it does not “insure” against jeopardy. As a result,
because the Corps fails to follow the 2000 BiOp, American
App. 50
Rivers contends that the Corps’ actions “take” the plover,
tern and sturgeon in violation of the ESA.
a. Plover and Tern RPA
The 2000 BiOp recommended that a spring rise and
low summer flow were necessary to avoid jeopardy to all
three species. The 2003 Amended BiOp adopts many of the
findings and conclusions of the 2000 BiOp, including the
habitat construction will prevent jeopardy to the species.
(FWS AR 1457 at 33714, 33736.) However, unlike the 2000
RPA, the 2003 RPA eliminates the requirement that both
flow modifications and habitat construction are essential
to avoid jeopardy to the plover and the tern. Instead, the
2003 RPA contains additional elements, such as a drought
conservation plan, Gavins Point dam summer releases,
accelerated construction of shallow water habitat, and
adaptive management, that together avoid jeopardy to the
plover and tern. (FWS AR 1451 at 33187.)
The 2003 Amended BiOp relies on updated informa-
tion: (1) completion of a report by the National Academy of
Sciences’ National Research Council, “The Missouri River:
Exploring the Prospects for Recovery;” (2) analysis of the
reservoir releases pursuant to the 2000 RPA; (3) continued
monitoring and study of listed species; (4) use of a new
model to better analyze use of reservoir habitat by the tern
and plover; and (5) the critical habitat designation of the
plover in October 2002. (FWS AR 1291 at 31065.) Particu-
larly relevant to the plover and the tern is the new infor-
mation relating to the analysis of the 2000 RPA and the
continued monitoring of the species since the 2000 BiOp.
(Id.) Since the 2000 BiOp, both the plover and the tern
App. 51
populations have experienced some improvement. (FWS
AR 1457 at 33701, 33704.) Further, analysis of the imple-
mentation of the 2000 BiOp RPA indicated that intended
habitat objectives could not be achieved, and that in fact,
spring and summer flows specified in the 2000 BiOp RPA
actually impeded the development of sandbar habitat
essential to plover and tern survival. (FWS AR 1457 at
33545.)
Elimination and degradation of both plover and tern
habitat contribute to the declining status of the species.
The 2000 RPA proposed both spring and summer flows
and habitat construction to “restore, maintain, and create
sandbar habitat for terns and plovers.” (FWS AR 1290 at
31040; See FWS AR 1237 at 29230.) However, the Corps
sets forth, and the FWS adopts, that the “alluvial geomor-
phic process” indicated that spring and summer flows
would not create sandbar habitat but would potentially
destroy beneficial sandbar habitat. (FWS AR 1290 at
31040; FWS AR 1290 at 31067; FWS 1457 at 33545.)
Therefore, the Corps proposed, and the FWS agreed, that
the elimination of spring and summer flows coupled with
the addition of new RPA elements, would continue to avoid
jeopardy to the plover and the tern. American Rivers does
not point to any evidence that indicates that the only
possible way to avoid jeopardy to the plover and the tern is
to implement flow changes and habitat construction. The
FWS modified the RPA to prevent further degradation to
the plover and tern habitat. Although American Rivers
may disagree with the FWS’s conclusions, the FWS has
App. 52
articulated a rational basis for its decision to eliminate
spring and summer flow changes from the 2003 RPA.‘
American Rivers also argues that the FWS improperly
evaluated the effects on the plover and tern from the
Corps’ proposed operations. The Court disagrees. Although
the FWS utilized a “worst-case-scenario analysis” for both
the plover and the tern, the FWS also considered both the
historical effects and cumulative and indirect effects of the
Corps’ proposed operations on the plover and tern. (FWS
AR 1287; FWS AR 1540; FWS AR 1457 at 33608-30;
33634-42; 33683-85.) The baseline adopted by the FWS is
proper.
b. Sturgeon RPA
The sturgeon RPA retains both flow modifications and
habitat construction. The 2003 RPA proposes higher
summer flows than the summer flows required in the 2000
RPA. The 2000 RPA states that “(s}ummer flows shall be
decreased ... te an interim target of 25 Kcefs by June 21,
and held at 25 Kefs until July 15... on July 15, the flows
shall be stair-stepped down to a flow of 21 Kefs until
August 15.” (FWS AR 1237 at 29230.) The 2003 RPA
proposes that for 2004, “summer habitat flow[s) [shall be]
no greater than 25 Kcfs beginning no later than July 1,
* Even so, the 2003 RPA does not eliminate flow changes alto-
gether. Although it may not specifically require the implementation of
flow changes in order to preserve the plover and the tern, the RPA
requires the Corps to develop a water plan that includes e spring rise
and low summer flow. In the event the Corps fails to develop such a
by March 1, 2006, a default water plan that includes both a spring
rise and low summer flow must be implemented. (FWS AR 1457 at
3376 1-62.)
App. 53
2004 lasting for a minimum of 30 days at its lowest point.”
(FWS AR 1457 at 33760.) The 2003 RPA also allows the
Corps to develop its own water flow regime, no later than
March 1, 2006, but provides a default plan in the event the
Corps is unsuccessful. This default plan states that:
“(bleginning on or about June 15, 2006 but no later than
July 1, 2006 the Corps shall begin reducing flows to
provide a minimum 30 day summer low flow release of no
greater than 25 Kefs.” (Jd. at 33762.) The Court disagrees
with American Rivers’ assertion that this change in
summer flows is arbitrary and capricious. The 2003
Amended BiOp RPA prevents low summer flows from
exceeding 25 Kefs, and as the Corps points out, the effect
at operating at 25 Kefs instead of 2i Kefs is minimal.
Moreover, these modifications are further complemented
by the implementation of other elements in the 2003 RPA.
American Rivers also argues that the 2003 RPA delays
implementation of a spring rise, which was required by
the 2000 RPA. The Court disagrees. The 2000 RPA permit-
ted a spring rise only in the event that river conditions
allowed such a rise. (FWS AR 1237 at 29230.) The 2003
RPA similarly permits a spring rise provided water condi-
tions are favorable. (FWS AR 1457 at 33760-61.) In 2004,
because of unfavorable water conditions, there was no
spring rise. Whether a spring rise will occur in 2005
depends on the status of water conditions in 2005. The
2003 RPA does not delay spring rise, but rather requires it
under favorable conditions, similar to the requirements of
the 2000 RPA. Moreover, under the 2003 RPA, the Corps
“shall, if hydrologic conditions are suitable, initiate an
experimental spring pulse to assist and inform the process
for establishing a long-term flow plan.” (FWS AR 1457 at
33760-61.) Unlike the 2000 RPA, the 2003 RPA requires an
App. 54
annual spring rise, provided conditions are favorable.
American Rivers’ argument that the Corps has delayed a
spring rise is without merit.
American Rivers also complains that the magnitude of
the spring rise in the 2003 RPA is greatly reduced from the
2000 RPA. In the 2000 RPA, the spring rise was included
to provide a spawning cue for the sturgeon, and to create
and maintain sandbar habitat for the plover and the tern.
Although the 2003 RPA does not require a spring rise of
the same absolute magnitude as the 2000 RPA, it requires
a bimodal spring rise. Water flows do not effectively
construct habitat for the plover and the tern, and a bi-
modal spring pulse may provide greater spawning cues for
the sturgeon. (FWS AR 1457 at 33761, 33765; FWS AR
1291 at 31067-72.) Any change in flood plain connectivity
as a result of a lower absolute magnitude is also minimal.
(Corps AR 1332 at 45605.) Although the spring rise in the
2003 RPA may differ from that in the 2000 BiOp, it is not
unlawful.
American Rivers also contends that the accelerated
construction of shallow water habitat is improper. Both
the 2000 BiOp and the 2003 Amended BiOp recommend
that the Corps develop twenty to thirty acres of shallow
water habitat per mile of the Missouri River, in an effort to
sustain the continued survival of the sturgeon. Although
lower flows contribute to the creation of shallow water
habitat, such flows do not create enough shallow water
habitat to ensure the sturgeon’s viability. The 2003
Amended BiOp thus included a measure that requires the
Corps to artificially construct shallow water habitat in an
effort to meet habitat standards. The Corps is currently
operating to construct such artificial habitat, and intends
to continue such operations in the future. (FWS AR 1290
App. 55
at 31057.) This accelerated construction, in conjunction
with other RPA elements, is an appropriate measure.
c. “No Jeopardy” Finding
American Rivers submits that the 2003 Amended
BiOp is arbitrary and capricious because it does not insure
against jeopardy. American Rivers argues that it is not
“reasonably certain” that (1) required flow changes will
occur; (2) congressional funding will be sufficient to im-
plement artificial habitat construction; and (3) artificial
habitat construction will be effective. The FWS’s no
jeopardy finding need only rely on a plan that is reasona-
bly certain to be implemented. Nat Wildlife Fed’n v. Natl
Marine Fisheries Serv., 254 F. Supp. 2d 1196, 1213 (D. Ore.
2003).
American River argues that the 2003 Amended BiOp
proposes flow changes that are not “reasonably certain” to
occur. The 2003 Amended BiOp requires the Corps to
develop, over the next two years, an appropriate flow
regime that implements spring and summer flows to
protect the sturgeon. In the event the Corps fails to de-
velop this plan, the RPA sets forth a default flow plan that
implements both spring rise and lower summer flows.
Because the 2003 Amended BiOp requires that such
changes be implemented at the latest by March 1, 2006,
the Court finds that there is a reasonable certainty that
such flow changes will take effect.
American Rivers also argues that the artificial con-
struction of sandbar habitat for the plover and the tern is
an unproven mitigation measure, and thus reliance on
such construction was arbitrary and capricious. The record
reflects that the FWS knew, considered and evaluated both
App. 56
the negative and positive effects of artificial sandbar
habitat construction. There is no evidence to suggest that
the Corps will fail to implement the measures the FWS
recommends. The Corps is further required, in addition to
constructing habitat, to continuously monitor and evaluate
effects on the plover and the tern, and modify operations
as required. Though American Rivers disputes the ulti-
mate success of artificial sandbar habitat creation on
plover and tern populations, concerns of uncertainty are
inevitable in any action an agency may take. Such con-
cerns are insufficient to invalidate the 2003 Amended
BiOp. Reasonable certainty only applies to the possibility
of implementation, not to the overall success of the par-
ticular measure. The record supports that the FWS con-
sidered both the positive and negative effects of such
measures, and thus rationally concluded, in conjunction
with the other RPA elements, that this measure would
avoid jeopardy to the species. Nothing more is required by
the FWS.
American Rivers also argues that the Corps lacks
appropriate funding to complete this habitat construction.
By its nature, a RPA must be capable of implementation,
both economically and technologically. 50 C.F.R. § 402.02.
American Rivers points to no evidence to suggest that the
Corps will be economically prevented from implementing
this RPA. The speculative nature of congressional appro-
priations is insufficient to render the RPA arbitrary and
capricious.
The Court finds that the FWS’s 2003 Amended BiOp
and its RPA are not arbitrary and capricious. The FWS
has provided a rational connection between the facts and
the choice made. Motor Vehicles, 463 U.S. at 43. Therefore,
App. 57
the 2003 Amended BiOp and its RPA do not violate Section
7 of the ESA.
d. The Corps’ Actions Result in a Take
American Rivers also argues that the Corps’ adoption
of the 2003 RPA jeopardizes the species and results in a
“take” of the species, in violation of the ESA. After consult-
ing with the FWS, the Corps has an independent duty to
insure that its actions satisfy the ESA. 16 U.S.C.
§ 1536(a)(2). Essentially, the Corps’ decision to rely on the
2003 Amended BiOp must not be arbitrary and capricious.
Because the Court finds that the 2003 Amended BiOp is
valid, the Corps’ reliance on the 2003 Amended BiOp is
likewise valid.
Section 9 of the ESA prohibits a “take” of the endan-
gered or threatened species. 16 U.S.C. § 1538. American
Rivers argues that the 2003 Amended BiOp and RPA take
the plover, tern and the sturgeon. However, the ESA
permits that any taking, in compliance with the Incidental
Take Statement (“ITS”), “shall not be considered to be a
prohibited taking” of the species. 16 U.S.C. § 1536 (02).
The 2003 Amended BiOp includes an ITS for the plover,
tern, and sturgeon. (FWS AR 1457 at 33769-90.) The
Corps has an absolute defense to a Section 9 claim so long
as its operations are in accordance with the 2003 BiOp and
the terms and conditions of the ITS. American Rivers fails
to demonstrate that the Corps’ operations are contrary to
the 2003 Amended BiOp and its ITS, and therefore there
is no violation of the ESA.
App. 58
2. Claims by Nebraska and NPPD
Nebraska and NPPD (“Nebraska Parties”) claim that
the FWS and Corps improperly consulted under the ESA,
resulting in an improper 2003 Amended BiOp and RPA.
They contend that the environmental! baseline used in the
2003 Amended BiOp is improper because it fails to include
non-discretionary operations such as minimum flow levels.
They further assert that the 2003 RPA is invalid because
its proposed restoration of a natural hydrograph runs
contrary to the Corps’ obligations under the FCA. Because
the Court concludes that the Corps does not have a non-
discretionary duty to maintain minimum water flows, and
that the Corps’ operations are subject to the ESA, these
arguments fail.
The Nebraska Parties further argue that the 2003
RPA is not economically feasible, because it improperly
compromises both water supply and hydropower benefits
to the Nebraska Parties. However, the requirement that a
RPA be “economically and technologically feasible” only
requires that the Corps have the resources and technology
necessary to implement the RPA. See Kandra v. United
States, 145 F.Supp. 2d 1192, 1207 (D. Or. 2001). This
argument is likewise without merit.
The Nebraska Parties also argue that the 2003
Amended BiOp and RPA are arbitrary and capricious
because they are not based on the best scientific data
available. The 2003 Amended BiOp proposes to restore
some of the river’s natural hydrograph to water flows.
According to the Nebraska Parties, this proposal bears no
resemblance to the river’s natural hydrograph, as set forth
in the U.S. Geological Survey (“USGS”). (FWS AR 915 at
14687-885.) The 2003 Amended BiOp does not strictly
App. 59
require the natural hydrograph contained in the USGS,
but rather suggests that some “semblance” of the natural
hydrograph be restored. (FWS AR 1457 at 33551.) The
FWS need only recommend a RPA that prevents jeopardy,
and there is no evidence that an immediate and complete
restoration of pre-dam flows is the only way to prevent
such jeopardy. The fact that the FWS chose not to propose
a plan contained in one report is insufficient to render the
FWS’s decision arbitrary and capricious. The Nebraska
Parties’ Motions fail.
3. Claims by Blaske Marine Plaintiffs and Mi )
Blaske Marine and MO-ARK (collectively, “Blaske
Marine Plaintiffs”) and Missouri submit that the Corps
should operate the Missouri River as required by the 1979
Master Manual. Both Blaske Marine Plaintiffs and Mis-
souri argue that the Corps violates the ESA because the
low summer flows set out in the 2003 Amended BiOp
eliminate some areas of shallow water habitat for the
sturgeon in the lower Missouri River. They thus argue
that this removal of habitat constitutes a “take” under the
ESA. As noted above, however, because the Corps is
operating the River pursuant to the 2003 Amended BiOp
and the ITS, it has an absclute defense to any Section 9
claim. 16 U.S.C. § 1536(0). Blaske Marine Plaintiffs and
Missouri argue that the ITS does not apply to the elimina-
tion of habitat on the lower Missouri River, because the
ITS does not specifically reference and connect reduced
spawning to reduced downstream water flows, and there-
fore the Corps cannot use the ITS as a defense to a claim
based on this situation. The ITS anticipates a loss in
spawning and nursery habitat “because of significantly
reduced sediment transport and deposition.” (FWS AR
App. 60
1457 at 33784.) The complete language of the ITS, ow-
ever, establishes that the decrease in downstream water
flow affects the transport and deposition of sediment in
the lower Missouri River, thereby affecting the habitat of
the sturgeon in this point of the River. /d. Thus, the [TS
addresses the effect on the sturgeon in the lower Missouri
River, and provides an absolute defense to this ESA claim.
Even without this defense, however, there is no
violation of the ESA. Blaske Marine Plaintiffs and Mis-
souri fail to demonstrate that low summer water flows
result in a “take” of the sturgeon. They argue that the low
summer flows significantly modify or degrade the habitat,
which actually kills or injures the sturgeon. See Babbitt v.
Sweet Home Chapter of Communities for a Great Oregon,
515 U.S. 687, 697 (1995). Though the parties concede that
lower flows decrease shallow water habitat in this particu-
lar area of the river, Blaske Marine Plaintiffs and Missouri
fail to set forth any evidence that this habitat modification
actually causes any injury to the sturgeon. Blaske Marine
Plaintiffs and Missouri fail to acknowledge that the FWS
considered this argument in the 2003 Amended BiOp, and
concluded that although lower summer flows may result in
a reduction of shallow water habitat in the lower Missouri
River, there is no evidence that such action will actually
kill or injure the sturgeon. (FWS AR 1457 at 33784.)
Blaske Marine Plaintiffs and Missouri fail to consider the
effects on the sturgeon of increasing water flows on other
areas of the river. Moreover, the slight reduction in habitat
in the lower river does not negate the fact that the 2003
Amended BiOp results in am overall net gain in the
amount of shallow water habitat on the Missouri River. In
fact, lower flows in the 2003 RPA reduce habitat in the lower
Missouri River by approximately 200 acres compared to the
App. 61
1979 Master Manual RPA, while the overall increase of
shallow water habitat on the entire Missouri River under
the 2003 RPA compared to the 1979 Master Manual RPA is
approximately 1,189 acres. (FWS AR 1291 at 31077,
31079.) Absent some evidence that injury will result to the
sturgeon, Blaske Marine Plaintiffs and Missouri's Motions
on this point are denied.
Similar to the argument advanced by the Nebraska
Parties, Missouri also argues that the 2003 Amended BiOp
and RPA are invalid because the FWS and the Corps
improperly consulted under the ESA. Missouri also sub-
mits that the RPA is invalid because it requires the Corps
to violate the FCA by not maintaining minimum flows. As
the Court has previously indicated, the FCA does not
impose a non-discretionary duty to maintain minimum
naviga‘ion flows, so these arguments fail.
Missouri further claims that the mandatory language
in the 2003 RPA is an attempt by the FWS to supercede
the Corps’ authority and to “govern the way that the Corps
manages the River system.” The Court is unpersuaded by
this argument. Missouri fails to cite to any legal authority
that indicates that the existence of mandatory language in
a RPA invalidates it as a matter of law. Moreover, absent
any evidence that either the FWS intends to bind the
Corps to its RPA or that the Corps considers itself bound
by the FWS's RPA, this argument fails.
4. Conclusion
‘uhe Court finds that the 2003 Amended BiOp and
RPA are not arbitrary and capricious and thus are in
accord with the ESA. Likewise, the 2004 Master Manual,
2004 AOP, and ROD do not violate the ESA.
App. 62
C. National Environmental Policy Act Claims
NEPA requires that federal agencies prepare an
Environmental Impact Statement (“EIS”) for every “major
Federal action[] significantly affecting the quality of the
human environment.” 42 U.S.C. § 4332(2)(C); See 42
U.S.C. §§ 4321-4370r. An EIS must examine: (1) the
environmental impacts of the proposed action; (2) the
adverse environmental effects of the action that cannot be
avoided; (3) alternatives to the proposed action; (4) the
relationship between local, short-term uses of the envi-
ronment und the maintenance and enhancement of long-
term productivity; and (5) any irreversible and irretriev-
able commitment of resources that would be involved. 42
U.S.C. § 4332(2XC). Once the EIS is completed, the agency
must prepare a ROD. The Court reviews under NEPA “to
ensure that the agency has adequately considered and
disclosed the environmenta) impact of its actions and that
its decision is not arbitrary and capricious.” Baltimore Gas
& Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87,
97-98 (1983). NEPA ensures that the Corps’ actions are
procedurally valid.
The Corps originally corsidered the impacts of seven
alternatives submitted by different parties. (Final EIS at
4-3 to 4-11; 5-1 to 5-168.) Then, the Corps conducted a
detailed analysis of five different alternatives to the 1979
Master Manual: (1) the Modified Conservation Plan
(“MCP”), which includes increased drought conservation
measures, unbalanced storage among the three upper and
largest lakes in the Mainstem Reservoir System, and a
Fort Peck spring rise approximately every third year, (2)
App. 63
GP1528,° which includes a 15 Kefs spring rise release from
mid-May to mid-June followed by a minimum service flat
release of 28 Kefs that ends on September 1; (3) GP2021,
which has a 20 Kefs spring rise followed by a 25 Kefs
release to mid-July when the release drops to a low of 21
Kefs until mid-August, when it returns to 25 Kefs until
September 1; (4) GP1521, which has a 15 Kefs spring rise
release from mid-May to mid-June followed by a release of
21 Kefs; and (5) GP2028, which has a 20 Kefs spring rise
followed by a 28 Kefs release to mid-May to mid-June
followed by a release of 28 Kefs. (Final EIS at 6-3.) Out of
these five alternatives, the Corps eventually identified a
Preferred Alternative (“PA”) that included “more stringent
drought conservation measures, a more defined methodol-
ogy for unbalancing the upper three lakes, higher non-
navigation season flows, and a planned re-evaluation in 3
years.” (Id. at 8-1.) The 2004 Master Manual and 2004
AOP thus evolve from this PA.
1. Missouri
Missouri argues that Federal Defendants violated
NEPA because the adoption of “adaptive management”
process is improper, and the economic analysis used by the
Corps in choosing the PA is flawed and misleading. Mis-
souri fails to demonstrate that the Federal Defendants’
decisions were arbitrary and capricious.
The Final EIS and the 2004 Master Manual describe
the “adaptive management” process. Adaptive manage-
ment is an approact ‘» tural resources management, in
* “GP” means “Gavius Point” and the two numbers that follow
correspond to the spring release and summer release, respectively.
App. 64
which policy choices are made incrementally. As each
choice is made, data on the effects of these choices are
collected and analyzed in order to assess whether to
retain, reverse, or otherwise alter the policy choice. Mis-
souri maintains that this adaptive management approach
violates NEPA because it permits the Corps to circumvent
the NEPA process when policy choices are modified.
Missouri takes issue with the potential flow changes that
the Corps may undertake in the future. Missouri fails to
point to any evidence that indicates that the Corps intends
to avoid its NEPA obligations by implementing this adap-
tive management approach. To the contrary, the Corps
acknowledges that in the event a major policy change
results, the Corps will be required to comply with NEPA.
(Final EIS at D1-69; Corps AR 1970 at 3.) Absent evidence
that the adaptive management process actually results in
the Corps’ evasion of NEPA obligations, the Court declines
to declare this approach invalid.
Missouri also argues that the Final EIS is flawed
because it incorrectly calculated the value of benefits to
navigation and downstream water supply resulting from
the adoption of the RPA. Missouri essentially contends
that it is impossible for any increased economic benefit to
result to navigation and downstream water supply as a
result of lower downstream water flows. Missouri dis-
agrees with the Corps’ conclusions, but fails to demon-
strate why the Corps’ analysis is arbitrary and capricious.
The Corps comparatively evaluated the economic effects of
the PA to the 1979 Master Manual on a variety of different
river interests, including navigation and water supply.
(See Final EIS 8-10 to 8-49.) The Final EIS was based on
the previous draft EIS and its comments, as well as other
economic studies. Missouri may disagree with the Corps’
App. 65
conclusions and its rationale, but that is insufficient to
argue that the Corps failed to take a “hard look” at the
economic impact of its decision. Friends of the Boundary
Waters Wilderness v. Dombeck, 164 F.2d 1115, 1128 (8th
Cir. 1999) The Corps articulates a rational basis for its
conclusions. Missouri’s disagreement with the Corps’
conclusions is insufficient to render the Final EIS arbi-
trary and capricious.
2. Blaske Marine and MO-ARK
The 2004 AOP requires that the Corps restrict sum-
mer flows from Gavins Point to 25 Kcfs for a period of 30
days beginning July 1, 2004. If the Corps develops 1200
acres of shallow water habitat by July 1,° the Corps may
engage in another consultation with the FWS to determine
how much higher it can adjust summer flows.’ Blaske
Marine and MO-ARK (collectiveiy, “Blaske Marine Plain-
tiffs”) assert that the Corps must prepare a supplemental
EIS discussing the impacts of operating under such
conditions.’ Blaske Marine Plaintiffs also argue that the
* Federal Defendants represented to the Court at oral argument
on May 21, 2004, that the Corps fully intended to successfully complete
this habitat construction by July 1, and that the current stat- of the
construction was on track for such completion. On June 14, 2004,
Federal Defendants informed the Court that construction was complete
and that consultation between the FWS and Corps had begun. The
FWS anticipates that it will issue an opinion relating to 2004 summer
flows on June 22, 2004.
* Any claims relating to the outcome of this consultation between
the FWS and Corps are not ripe for review.
* Blaske Marine Plaintiffs failed to include this claim in their
Compiaint. Consistent with the Court’s oral rulin, «a May 21, 2004, the
Court permits Blaske Marine Plaintiffs to amend their Complaint to
include this claim.
App. 66
default water flow plan set for March 2006 contained in
the 2003 RPA requires a supplemental EIS.
The 2003 Amended BiOp proposes a flow of 25 Kcfs for
30 days beginning July 1, 2004. The 2004 AOP irnmplements
this alternative. The Final EIS issued on March 5, 2004,
evaluated the effects of summer flows at 21 Kefs and at
28.5 Kefs. (Final EIS Table 7-1.) The Final EIS does not
specifically evaluate the effects of flows at 25 Kcfs. How-
ever, flows at 25 Kefs are within the range of alternatives
evaluated by the Corps. The purpose of the Final EIS is to
ensure that the Corps takes a “hard look” at the environ-
mental consequences of a project before taking a major
action. Friends of the Boundary Waters Wilderness, 164
F.3d at1128. An EIS must discuss alternatives to the
proposed action, and the sufficiency of the range of alter-
natives evaluated is subject to the “rule of reason.” Id. The
“rule of reason” requires the Court to determine whether
the Corps has complied with the Final EIS in good faith,
and whether the Final EIS “sets forth sufficient informa-
tion to allow the decision-maker to consider alternatives
and make a reasoned decision after balancing the risks of
harm to the environment against the benefits of the
proposed action.” Jd. The Final EIS need not be exhaus-
tive. Id. The Court finds that although the Final EIS did
not specifically evaluate summer flows at 25 Kefs, the
range of alternatives discussed in the Final EIS encom-
passed such flows. Thus, the Final EIS sufficiently exam-
ined summer flows at 25 Kcfs.
In conjunction with these flow levels, the Corps
anticipates that it will complete construction of 1200 acres
of shallow water habitat by July 1, 2004. Blaske Marine
Plaintiffs contend that construction of this habitat re-
quires a supplemental EIS. In both the 2000 BiOp and the
App. 67
2003 Amended BiOp, the FWS set a goal to develop twenty
to thirty acres of shallow water habitat per mile of the
Missouri River. From years 2000 to 2020, 20,000 acres of
shallow water habitat must be developed. Low summer
flows help to develop shallow water habitat, but not at the
level required to protect the sturgeon. The FWS concluded
that a multi-faceted approach was necessary to achieve its
goals: reservoir operational changes, structural modifica-
tions, and non-structural modifications. The FWS deter-
mined that 4900 acres of shallow water habitat results
from flows at 21 Kefs for a period from mid-July to mid-
August, while 3,717 acres of shallow water habitat results
from full navigation flows of 34.5 Kcfs from mid-July to
mid-August. The difference between shallow water habitat
construction at low flows and at full navigation flows is
thus 1200 acres. If the Corps artificially constructs 1200
acres of shallow water habitat by July 1, depending on its
consultations with the FWS, it may operate at possibly full
navigation flows because the 1200 acres of artificial
habitat construction will compensate for the smaller levels
of shallow water habitat construction at full navigation
flows. Both the 2000 BiOp and the 2003 Amended BiOp
contemplate that artificial habitat construction is neces-
sary to maintain sufficient shallow water habitat. The
Final EIS also acknowledges that artificial shallow habitat
construction is needed to provide enough shallow water
habitat. (Final EIS 7-71.) Moreover, Blaske Marine Plain-
tiffs fail to demonstrate that this shallow water habitat
construction is a “major Federal action[] significantly
affecting the quality of the human environment,” or that a
categorical exclusion does not apply. 42 U.S.C. § 4332; 62
App. 68
Fed. Reg. 2375, 2381 (Jan. 16, 1997). This failure is fatal
to the claim that the FWS must issue a supplemental EIS.
Blaske Marine Plaintiffs also argue that the proposed
default water plan that may potentially take effect in
March 2006, requires a sunplemental EIS. The proposed
default water plan was not evaluated nor considered
under the Final EIS. This default plan takes effect in 2006
only if the Corps fails to develop “a flow management plan
... [that] providels] a spring rise and summer flow which
will provide for the life history needs of the pallid stur-
geon.” (FWS AR 1457 at 33761.) Because neither the
default plan nor any future plan were eveluated under any
of the alternatives contained in the Final EIS, further
NEPA analysis may be required.” 40 C.F.R. § 1502.9(c)(1)
(supplemental EIS required when the “agency makes
substantial changes in the proposed action that are rele-
vant to environmental concerns,” or when there “are
significant new circumstances or information relevant to
environmental concerns and bearing on the proposed
action or its impacts”). However, this issue is not yet ripe
for the Court’s review.
* The Court further notes, based on representations by the
Federal Defendants that 1200 acres have been created, that Blaske
Marine Plaintiffs’ claim on this point is likely moot. Norton v. Southern
Utah Wilderness Alliance, 542 U.S. __., 2004 WL 1301302 (June 14,
2004) (supplemental EIS not required if “major” federal action already
completed); (Sierra Club v. Penfold, 857 F.2d 1307, 1318 (9th Cir. 1988)
(dismissing plaintiffs’ NEPA claim because ordering compliance with
NEPA would have no effect on the already-completed agency action).
* The Court does not intend to make any finding regarding the
Corps’ obligations under NEPA for this potential future action.
App. 69
3. South Dakota
South Dakota argues that the Corps violated NEPA
because it failed to consider the modified “Governors’
Summit Proposal” (a.k.a. “Nebraska Proposal”) in its
analysis of drought conservation measures. South Dakota
also contends that the Corps improperly considered the
interests of the Mississippi River stakeholders in deter-
mining the preferred alternative 1ur drought conservation.
Finally, South Dakota contends that the Corps failed to
consider shortening the navigation season in the spring
rather than in the fall.
The Governors within the Missouri River basin held a
summit meeting in September 2003 to discuss the conflict
over river operations. A sumunit plan was created by those
in attendance. Although this report was not specifically
included in the Final EIS, the range of proposals consid-
ered by the Corps in the Final EIS encompassed the
proposals in the Governor’s Summit Proposal. For exam-
ple, the Governor’s Summit Proposal envisioned that
operations would include low summer flows at 25 Kefs. As
previously discussed, the Final EIS contained an analysis
of low summer flows of 21 Kefs to 28 Kefs, thus encom-
passing flows proposed in the Governor’s Summit Pro-
posal. The Corps is under no obligation to consider each
and every alternative, but rather it must evaluate a
considerable range of alternatives to allow it to “make a
reasoned decision.” Friends of Boundary Waters Wilder-
ness, 164 F.3d at 1128. South Dakota fails to demonstrate
that the Corps’ alleged failure to specifically consider this
report was arbitrary and capricious.
The Corps’ consideration of the impact of the PA on
the Mississippi River was not arbitrary or capricious.
App. 70
NEPA requires that the agency evaluate all foreseeable
impacts of a major federal action. The operation of the
Missouri River impacts the operation of the Mississippi
River. Moreover, South Dakota submits no legal authority
to support its claim that the Corps evaluated too many
considerations.
Finally, South Dakota’s submits that the Corps acted
arbitrarily and capriciously because it failed to adopt an
alternative that shortened the navigation season in the
spring, rather than the fall. According to South Dakota,
shortening the navigation period in the spring preserves
more water in the upstream reservoirs during the essen-
tial fish spawning period. However, the Corps points out
that the greatest infusion of water occurs in the spring. If
the Corps shortened the water season in the spring, it
would do so without considering the water infusions from
winter precipitation and spring flows. Failure to consider
the spring infusion of water flow may result in an unnec-
essary shortening of the navigation season. The decision to
shorten the fall navigation season is made by July 1 of
each navigation year, which allows affected parties to
adjust their operations and interests accordingly. If the
Corps shortens the spring navigation season in March, the
decision to shorten the spring season would have to be
made in December, when it is impossible to judge future
water conditions. South Dakota fails to establish that the
Corps’ alleged failure to consider this alternative is arbi-
trary or capricious. South Dakota’s claims fail.
’ 4. American Rivers
American Rivers asserts that the Corps violated NEPA
because it selected a PA without “adequate explanation.”
App. 71
(Am. Rivers Mem. in Opp’n to FCA/NEPA claims at 4.)
American Rivers contends that the Corps failed to explain
why the PA it selected was superior to the other evaluated
alternatives, in particular GP2021, and thus that the
Corps’ decision is arbitrary and capricious.
NEPA only requires that the Final EIS demonstrate
that the agency in good faith objectively has taken a “hard
look” at the environmental consequences of a proposed
action and alternatives. Friends of the Boundary Waters
Wilderness, 164 F.3d at 1128. The Final EIS must provide
sufficient detail to permit those who did not participate in
its preparation to understand and consider the relevant
environmental influences involved. Finally, an agency’s
consideration of alternatives need only be reasonable. Jd."
“ Under NEPA, the agency:
should present the environmental impacts of the proposal
and the alternatives in comparative form, thus sharply de-
fining the issues and providing a clear basis for choice
among options by the decision maker and the public. ...
[Algencies shall: (a) rigorously explore and objectively
evaluate all reasonable alternatives, and for alternatives
which were eliminated from detailed study, briefly discuss
the reasons for their having been eliminated; (b) devote sub-
stantial treatment to each alternative considered in detail
including the preposed action so that reviewers may evalu-
ate their comparative merits; (c) include reasonable alterna-
tives not within the jurisdiction of the lead agency; (d)
include the alternative of no action; (e) identify the agency’s
preferred alternative or alternatives, if one or more exists,
in the draft statement nd identify such alternative in the
final statement unless another law prohibits the expression
of such a preference; and (f) include appropriate mitigation
measures not already included in the proposed action or al-
ternatives.
40 C-F.R. § 1502.14.
App. 72
The Corps evaluated the five alternatives under four
objectives, to select the PA that:
(1) serve[d] the contemporary needs of the Mis-
souri River Basin and the Nation; (2) complie([d]
with environmental laws, including the [ESA];
(3) serve[d] Congressionally authorized project
purposes; and (4) fulfill[ed) the Corps’ responsi-
bilities to Federally recognized Tribes.
(Final EIS at 8-1.) The Corps ultimately selected a PA that
best met these objectives:
The rationale for selecting the PA is a composite
of analyses, information briefings, technical ex-
pertise, and comments concerning the resources
evaluated as part of the Study. The Corps be-
lieves that the PA, when combined with other
measures ... conserves more water in the upper
three lakes during extended droughts, meets the
needs of ESA-listed fish and wildlife species, is
consistent with the Corps’ responsibilities under
environmental laws and Tribal trust responsibili-
ties, and provides for the Congressionally author-
ized uses of the system.
(Id. at 8-4.) In selecting this PA, the Corps conducted a
detailed analysis of all five alternatives and the