Supplemental Brief — Alcan Aluminum Corp. v. United States
Supreme Court brief1997
Ask Donna
What actually matters in this document.
Text
————
Supreme Court, US,
FILED
6 MAY 21 1997
NO. 96-1494 OFFICE OF THE CLERK
IN THE
Supreme Court of the United States
October Term, 1997
ALCAN ALUMINUM CORPORATION,
Petitioner,
Vv.
UNITED STATES OF AMERICA,
Respondent.
PETITION FOR WRIT OF CERTIORARI TO THE UNITED STATES
COURT OF APPEALS FOR THE THIRD CIRCUIT
SUPPLEMENTAL BRIEF
ON NEW AUTHORITY
Lawrence A. Salibra, II
Counsel of Record
Alcan Aluminum Corporation
6060 Parkland Boulevard
Mayfield Heights, OH 44124-4185
(216) 423-6918
Attorney for Petitioner
Alcan Aluminum Corporation
a nh at te treet ee Be et oa
ARGUMENT
On March 14, 1997, Alcan Aluminum Corporation
filed a petition with this Court requesting a Writ of
Certiorari to the United States Court of Appeals for
the Third Circuit, seeking the resolution of pivotal
issues of CERCLA liability. Alcan’s petition asserted,
inter alia, a clear conflict between the First and Eighth
Circuits on the one hand and the Second and Third
Circuits on the other, as to whether a CERCLA
plaintiff must demonstrate a causal connection
between a defendant’s waste and the incurrence of
response costs as a predicate to § 107(a) liability. On
April 21, 1997, the Court of Appeals for the Fifth
Circuit sided with the position taken by the First and
Eighth Circuits in Licciardi v. Murphy Oil USA, Inc., No.
96-30202, 1997 U.S. App. LEXIS 7920, printed in the
Appendix at A-1. Because Licciardi sharply conflicts
with the Third Circuit’s decision in this case, and
exacerbates the conflict among the circuits regarding
CERCLA causation, we call it to the Court’s attention
in this Supplemental Brief.
As we noted in our petition, in Dedham Water Co.
v. Cumberland Farms Dairy, 889 F.2d 1146 (1st Cir.
1989) and Farmland Indus. v. Morrison-Quirk Grain
Corp., 987 F.2d 1335, 1340 (8th Cir. 1993), the First
and Eighth Circuits respectively coicluded that a
prerequisite to CERCLA liability was that the plaintiff
demonstrate a causal connection between the
CERCLA hazardous substances and the response
costs. The Second and Third Circuits, however, do
not require a causal connection between the CERCLA
hazardous substances and the response costs
because they believe that the plaintiffs burden of
proof would be too difficult. See United States v. Alcan
Aluminum Corp., 990 F.2d 711, 721 (2d Cir. 1993) and
2
United States v. Alcan Aluminum Corp., 964 F.2d 252,
265 (3d Cir. 1991) (the present case).
In Licciardi, the Fifth Circuit joined the First and
Eighth Circuits by requiring a showing of causation
between the CERCLA hazardous substances and the
response costs as a prerequisite to CERCLA liability.
The Fifth Circuit’s decision in Licciardi is in
irreconcilable conflict with the decision of the Third
Circuit in the present case, which imposed joint and
several liability on Alcan for the release of below
background metal compounds notwithstanding the
fact that the undisputed evidence established that
there were no metal problems of any kind at the
Butler Tunnel site and there were no CERCLA
hazardous substances in the Alcan Emulsion which
were identified as a basis for a CERCLA response
action.
Licciardi is particularly relevant to the present
petition because it involved lead, one of the same
elemental metals contained in the Emulsion. Like
the lead in the Emulsion--in fact, like all of the metal
compounds in the Emulsion--the lead in Licciardi did
not breach the toxic concentration leaching
procedure (“TCLP”) standard. As the Fifth Circuit
pointed out, EPA does not consider such metal
hazardous because it is not capable of leaching out
of the soil. Id. at *5. Moreover, the lead level in the
Emulsion was far below background levels, whereas
the lead level in Licciardi was above background
levels. Id. at *6.
The district court in Licciardi had imposed
CERCLA liability on the defendant in the same
manner that the Third Circuit imposed liability on
Alcan--exclusively based on that fact that hazardous
substances were released without any proof that the
|
3
release did or could cause response costs. The
district court in Licciardi concluded that liability could
be imposed under CERCLA provided there was a
release of hazardous substances above background
levels.' Id. at *4.
The Fifth Circuit reversed. It effectively rejected
the view of the Second and Third Circuits that the
causation element of CERCLA § 107(a) simply relates
to causation of a release and not to causation of
response costs. The Fifth Circuit also refused to
adopt the position of the Second and Third Circuits
that liability automatically attaches to the release of
any amount of hazardous substances:
While Amoco [Oil Co. v. Borden, Inc.] allows a
CERCLA plaintiff to prove that response costs
were caused by a release without resort to an
applicable standard of justification, bare proof
that there was a release is not enough; as we
have explained, liability does not attach to the
release of ‘any quantity of a hazardous
substance.’
Id. at *6 quoting Amoco Oil Co. v. Borden, Inc., 889
F.2d 664, 670-71 (5th Cir. 1989). The Fifth Circuit
opined that the hazardous substances released must
pose a “threat te the public or the environment.” Id.
Noting that the defendant’s lead was not TCLP toxic
and that no expert had attempted to link the lead with
groundwater tests that demonstrated contamination,
‘Even the district court appears to have limited its
imposition of liability to the release of above background
hazardous substances, whereas the Second and Third
Circuits would impose CERCLA liability for the disposal of a
substance like garden soil containing metal compounds at
background levels.
4
the Fifth Circuit concluded that the plaintiffs had not
made a prima facie case for liability. Id. at *5-6.
Hence, the Licciardi decision tips the balance in favor
of Alcan on this fundamental issue and we ask that
the Court give it due consideration.
CONCLUSION
For all of the reasons contained in this
Supplemental Brief as well as the reasons contained
in the Petition of Writ of Certiorari, Petitioner Alcan
Aluminum Corporation respectfully requests that this
Honorable Court grant its Petition for Wnt of
Certiorari.
Respectfully submitted,
Lawrence Anthony Salibra, II
Counsel of Record
Alcan Aluminum Corporation
6060 Parkland Boulevard
Mayfield Heights, OH 44124-4185
(216) 423-6918
Attorney for Petitioner
Alcan Aluminum Corporation
A-1
JAMES J LICCIARDI; AGATHA LICCIARDI SPERA;
MARY ANN DISALVO LICCIARDI, wife of James J.
Licciardi; MARY ANN LICCIARDI NAVO, wife of and;
BENJAMIN NAVO,
Plaintiffs-Appellants-Cross-Appellees,
V.
MURPHY OIL USA INC..,
Defendant-Appellee-Cross-Appellant.
No. 96-30202
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
1997 U.S. App. LEXIS 7920
April 21, 1997, Decided
PRIOR HISTORY: [*1] Appeal from the United States
District Court for the Eastern District of Louisiana. 93-
CV-490-N. Edith Brown Clement, U.S. District Judge.
DISPOSITION: REVERSED.
COUNSEL: For AGATHA LICCARDI SPERA,
BENJAMIN NAVO, JAMES J LICCIARDI, MARY ANN
DISALVO LICCIARDI, wife of James J Licciardi, MARY
ANN LICCIARDI NAVO, wife of and Plaintiffs-
Appellants-Cross-Appellees: Michael A Fenasci, New
Orleans, LA. Manuel A Fernandez, New Orleans, LA.
For MURPHY OIL USA INC, Murphy Oi USA
Incorporated, Defendant-Appellee-Cross-Appellant:
James F Shuey, Frilot, Partridge, Kohnke & Clements,
New Orleans, LA. George A Frilot, III, Robert Beattie
McNeal, Frilot, Partridge, Kohnke and Clements, New
Orleans, LA.
A-2
JUDGES: Before HIGGINBOTHAM, SMITH, and
BARKSDALE, Circuit Judges.
OPINION: PER CURIAM:
I
From 1991 through 1993, the Licciardis hired a
number of environmental testing and consulting firms to
take and test environmental samples from their property
located adjacent to Murphy Oil’s Meraux refinery in
Louisiana. Armed with results of these tests, the
Licciardis filed suit under § 107 of the Comprehensive
Environmental Response, Compensation, and Liability
Act, 42 U.S.C. § 9607, alleging that the samples
demonstrate that Murphy contaminated their property
with leaded tank bottoms and refinery sludge in
violation of environmental law. !
[*2]
The bench trial was bifurcated into lability and
damages phases. Following the liability phase, the
district court entered its findings. The court found that
a certain “black tarry substance” from a sample taken
from the Licciardis’ property came from Murphy’s
refinery, finding that the level of lead concentration in
the soil at the testing site exceeded background levels.
The court held that defendant’s release of the substance
caused plaintiffs’ response costs. The district court
observed that the “presence of any hazardous
substances [above background levels] on plaintiffs’
property is sufficient to justify their incurring response
costs.” After ordering briefs from the parties on
1The Licciardis also made certain state law claims in their
complaint. The district court was unable to find sufficient
support for these state-law lost profit claims, and decided
that portion of the case for Murphy. The Licciardis have not
appealed, so we do not revisit that decision here.
A-3
damages, the trial court awarded the Licciardis $12,337,
the amount which Murphy stipulated to as the
Licciardis’ expense for testing for substances defined as
“hazardous” under CERCLA. Both sides appeal. Murphy
contests any finding of liability while the Licciardis
assert that all of their expenses on sampling and testing
should have been awarded as damages.
I
There are four elements to a CERCLA cost-recovery
action, such as the one here: (1) the site must be a
“facility” under § 9609(9); (2) [*3] the defendant
must be a “responsible person” under § 9607(a); (3) a
release or threatened release of a hazardous
substance must have occurred; and (4) the release or
threatened release must have caused the plaintiff to
incur response costs. Amoco Oil Co. v. Borden, Inc.,
889 F.2d 664, 668 (5th Cir. 1989). The first and
second of these elements are not in issue here.
Murphy is a “responsible person” and its refinery is a
“facility.” The district court correctly noted that lead
is a “hazardous substance” under 40 C.F.R. § 302.4.
In Amoco, we rejected the proposition that CERCLA
“liability attaches upon release of any quantity of a
hazardous substance.” 889 F.2d at 670 (emphasis
original). We explained that the question of whether a
release has “caused” or justified response costs is
tempered by the purpose of the Act. Id. Although we
acknowledged that it is “not the exclusive means of
justifying response costs, [ ] a plaintiff who has
incurred response costs meets the liability requirement
as a matter of law if it is shown that any release
violates . . . any applicable state or federai standard,
including the most stringent.” Id. at 671 (emphasis
original). [*4] However, the district court’s reliance
upon a violation of a standard and Amoco was
misplaced, as we will explain.
A-4
The district court concluded that any lead found in
the sample “exceeding background levels” constituted
a release that caused the Licciardis’ response costs
under CERCLA if the lead came from Murphy’s
refinery. Although the district court did not specify,
the record reflects that its reference to “background
levels” refers to the 1984 U.S. Geological Survey.
The U.S. Geological Survey measures empirical
evidence relating certain topological and geological facts
for a point on the globe. It is not a legal standard. We
are aware of no environmental law, state or federal,
that establishes the U.S. Geological Survey
“background level” as a standard, requirement, or
criterion. Relatedly, it is not clear that the Survey
figure used by the district court was relevant; according
to an expert who testified at trial, the “background
level” relied upon by the district court was established
“30 to 50 miles away from the Meraux refinery.”
The trial court also considered the drinking water
standard and the toxic concentration leaching
procedure (or “TCLP”) standard. According [*5] to
plaintiffs’ expert, the drinking water standard
establishes a legally acceptable limit for lead “at the
tap,” but none of the experts at trial attempted to link
the standard to groundwater tests. Moreover,
plaintiffs’ expert admitted at trial that she had not
carried out any groundwater testing, and that there
was insufficient data to form any opinion that the
Licciardis’ property had been affected by groundwater
migration from the refinery. As for the TCLP standard,
plaintiffs’ expert explained that even if a material
contains lead, EPA does not consider it “hazardous”
unless the lead is capable of “leaching” out of the
taaterial. The TCLP standard, she explained, is an
extraction procedure under which a _ scientist
simulates a landfill environment with rainfall and
acidity controls, then tests for lead in the resulting
A-5
leachate. Plaintiffs admitted in their Supplemental
Post-Trial Memorandum that the “TCLP analysis was
below regulatory levels.” Thus, even though they have
expended significant effort and resources testing their
property and hiring experts, plaintiffs have been
unable to offer any evidence that any regulatory
standard has been breached.
Without the Geological Survey, [*6] the drinking
water standard, or the TCLP standard as possible
bases for finding that Murphy’s release caused
response costs, we ask whether, in the absence of any
other evidence, a finding of hazardous substance
“above background levels” is sufficient to support a
finding that the release caused response costs. As we
explained in Amoco, responsible parties are not liable
unless there is evidence that they “posed [a] threat to
the public or the environment.” While Amoco allows a
CERCLA plaintiff to prove that response costs were
caused by a release without resort to an applicable
legal standard of justification, bare proof that there was
a release is not enough; as we have explained, liability
does not attach to the release of “any quantity of a
hazardous substance.” Id. at 670-71. “The question of
whether a release has caused the incurrence of
response costs should rest upon a factual inquiry into
the circumstances of a case and the relevant factual
inquiry should focus on whether the particular hazard
justified any response actions.” Id. at 670. We have
been pointed to no evidence that the found “release”
justified the response costs. We cannot sustain the
district [*7] court’s finding of liability.
We do not reach the issues regarding the proper
calculation of damages under CERCI.A.
REVERSED.