Petition for Writ of Certiorari — Five Star Parking v. Union Local 723, International Brotherhood of Teamsters (No. 07-699)
Supreme Court brief2007
Ask Donna
What actually matters in this document.
Text
Supreme Sour, U5.
riLeD
1 07-699 KEV 25 2007
No. 07- OFFICE OF THE CLERK
IN THE
Supreme Court of the United States
FIVE STAR PARKING,
Petitioner,
v,
UNION LOCAL 723, affiliated with the
INTERNATIONAL BROTHERHOOD OF TEAMSTERS,
Respondent.
On PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES Court OF APPEALS
FOR THE THIRD CIRCUIT
PETITION FOR A WRIT OF CERTIORARI
MICHAEL S. CRYAN
ARENT Fox LLP
1675 Broadway
New York, NY 10019
(212) 484-3900
Altorneys for Petitioner
l
QUESTION PRESENTED
Petitioner Five Star Parking filed a complaint in the
United States District Court for the District of New Jersey
challenging an arbitration award in favor of Respondent
Local 723, Affiliated with the International Brotherhood
of Teamsters that found that Petitioner’s imposition of a
wage after bargaining to an impasse in reopener
negotiations was a violation of their collective bargaining
agreement. The District Court vacated the award on
December 20, 2005, finding that the arbitrator had
exceeded his jurisdiction by deciding issues of unfair labor
practices governed by the National Labor Relations Act
and under the jurisdiction of the National Labor Relations
Board. Respondent appealed to the Third Circuit Court of
Appeals, which reversed the District Court’s decision and
reinstated the arbitrator’s award.
The question presented is this:
When parties to a collective bargaining agreement,
negotiating mandatory terms of bargaining pursuant to an
economic reopener provision in the agreement, reach an
impasse, is the employer's decision to implement its final
offer on impasse a right that is governed by the National
Labor Relations Act and falling under the primary
jurisdiction of the National Labor Relations Board, where
the reopener provision in agreement does not make such
implementation subject to arbitration?
22
STATEMENT PURSUANT TO RULE 29.6
Petitioner, Five Star Parking, has no parent
corporation and no publicly held company owns 10% or
more of its stock.
ii
TABLE OF CONTENTS
Page
QUESTION PRESENTED .................. i
STATEMENT PURSUANT TO RULE 29.6 ... ii
Eanes OP CAPIVESGIN ED Ka scsrnescasacneeabs lil
TABLE OF APPENDICES ......scsccsssencs Vv
TABLE OF CITED AUTHORITIES ......... v1
CPP EIUEUPUNGE OMA iva krenadkac cud Me bab eee 2
STATEMENT OF JURISDICTION .......... 2
RELEVANT PROVISIONS INVOLVED ..... 3
STATEMENT OF THE CASE ...............
wo |
REASONS FOR GRANTING THE PETITION .. 9
A. Decisions of the First, Tenth and D.C.
Circuits Hold That An Employer’s Right
to Implement After An Impasse In
Reopener Negotiations Arises from the
NLA and Is Not Arbitrable ........... 10
1. Decisions of the United States
Supreme Court Define the Rights of
Parties after an Impasse is Reached
in Negotiating a CBA .............. 10
iv
Contents
Page
DO
Decisions of the D.C. Circuit and the
Tenth Circuit Hold that the Right to
Implement at Impasse Arises from
Se PHAGE ce vi 00k os Medaka ak esanes 11
Decisions of the First Circuit Hold
that the Right to Implement at
Impasse is Not Arbitrable ......... 14
OO
B. Decisions of the Eighth Circuit Hold that
the Right to Implement at Impasse arises
from the CBA and is Arbitrable ........ 15
C. The Third Circuit Decision Holds that the
Right to Implement at Impasse arises
both from the CBA and the NLRA and is
PEE 4G a a ack aaah VERE Re vas 17
D. The Dispute in Five Star Parking Would
Not Be Arbitrable Under the Holdings of
the First, Tenth, and D.C. Circuits ...... 18
LMIPEGRTIENEEE, ce kas kaon saan eahanehesees 19
TABLE OF APPENDICES
Appendix A — Opinion Of The United States
Court Of Appeals For The Third Circuit Filed
SE le NS. ein eo hh eae ee er eneiae een ee
Appendix B — Opinion Of The United States
District Court For The District Of New Jersey
Dated December 23, 2005 ........cccccccces
Appendix C - Opinion And Award Of The New
Jersey State Board Of Mediation Dated
PRE Gy Oe Kia oe oko oe rec ke emeeees
Appendix D — Order Of The United States Court
Of Appeals For The Third Circuit Denying
Petition For Rehearing Dated August 29,
ORT E CE TT ECR Ne Ry PT eer ere ee pr hey
Page
vi
TABLE OF CITED AUTHORITIES
Page
Cases
Bricklayers and Allied Crafts Union, Local No.
4 of Minn. v. Associated General Contractors
of Minn., 711 F.2d 90 (8th Cir. 1983) ......... 15
Colorado-Ute Elec. Ass’n, Inc. v. N.L.R.B.,
gee F.20 1392 (10th Cir. 1991) ............. 9, 13, 18
Five Star Parking v. Union Local 723, No. 06-
2012, Slip Copy, 2007 WL 2110716 (3d Cir.
SE wa Cras eve pec tah a bhanake cn ae
Five Star Parking v. Union Local 723, No. 05-
ev-3975, 2005 WL 3502936 (D.N.J. Dec. 23,
Re en a nck ths ees A eet eeas 2
General Drivers and Helpers Union, Local No.
554 v. Mid-Continent Bottlers, Inc. (Omaha
Division), 767 F.2d 482 (8th Cir. 1985) ....... 9,15
Laundry, Dry Cleaning & Dye House Workers
Int'l Union, Local 93 v. Mahoney, 491 F.2d
PRR OUR SFUNS BEE) 5505505 nsecnnsdnceecans 16
Litton Fin. Printing Div., A Div. of Litton Bus.
Sys., Inc. v. NLRB, 501 U.S. 190 (1991) ..... 10
Local Union No. 47, Int'l Bhd. of Elec. Workers
v. N.L.R.B., 927 F.2d 635 (D.C. Cir. 1991) ....9, 11, 18
Cited Authorities
Page
Newspaper Guild of Salem, Local 105 of the
Newspaper Guild v. Ottaway Newspapers,
Iuc., 79 F.3d 12738 (ist Cir. 1996) .......... 9,14, 18
NLRB v. Katz, 369 U.S. 736 (1962) ............ 10
NLRB v. Lion Oil Co. , 352 U.S. 282 (1957) ..10, 11, 12
Speedrack, Inc., 293 N.L.R.B. No. 128 (May 17,
1989)
United Steelworkers v. Warrior and Gulf
Navigation, 363 U.S. 574 (1960) .......... «16
Statutes
ee Bee Sad Sank ee ee ee 2
PAS 5 eae Be.) 4 Rear anE enya ey ere D NT Ore 5
Gis © om D7 .- . Ep ene ere rere 5
ee rs OE 6 56k ok od ee tw oan ee es 5
ee ies Oe Re oR Oh so Se ee ee 5
ee Bigs OE ns ce ck dean eke OLEe eee eee 3,13
Cited Authorities
Rules
Supreme Court Rule 13.1 ......
Miscellaneous
‘eS 4 2) Oo 4 +O 6 42S ED
Opinion and Award in the Matter of the
Arbitration Between Five Star Parking and
IBT Local 723 (Aug. 3, 2005)
Page
bo
bo
]
Five Star Parking (“Five Star”) respectfully
petitions that a Writ of Certiorari be issued to review
the judgment of the United States Court of Appeals for
the Third Circuit entered on July 24, 2007, in order to
resolve a conflict between the D.C. Circuit, the Tenth
Circuit and the First Circuit on the one hand and the
Third Circuit and the Eighth Circuit on the other. The
Eighth Circuit and now the Third Circuit have held that
the Employer’s ability to unilaterally impose its last offer
after an impasse in reopener negotiations is an arbitrable
contractual question. The D.C. Circuit and the Tenth
Circuit have held that under the National Labor
Relations Act (the “NLRA”) an employer has a right to
implement its final offer in reopener negotiations. And
the First Circuit has held that disputes over the right to
implement a final offer after an impasse in negotiations
over new or renewal agreements are not arbitrable
because that right arises under the NLRA and thus falls
under the primary jurisdiction of the National Labor
Relations Board (the “NLRB”). The Court is presented
with a holding that an arbitrator’s jurisdiction pursuant
to a rights arbitration clause includes determining
whether an impasse has been reached in reopener
negotiations. This Court should resolve this important
question of federal labor law.
2
OPINIONS BELOW
The opinion of the United States Court of Appeals
for the Third Circuit is dated July 24, 2007, and it is not
published in the Federal Reporter, but is published at
Five Star Parking v. Union Local 723, No. 06-2012, Slip
Copy, 2007 WL 2110716 (3d Cir. July 24, 2007) (the “Third
Circuit Decision”) (App. la). The opinion of the District
Judge William J. Martini, United States District Court
for the District of New Jersey is dated December 23,
2005, and it is not published in the Federal Reporter,
but is published at Five Star Parking v. Union Local
723, No. 05-ev-3975, 2005 WL 3502936 (D.N.J. Dec. 23,
2005) (the “District Court Decision”) (App. 13a). The
order of the Third Circuit denying the Petition for
Rehearing or Rehearing En Banc was issued on August
29, 2007. (Aug. 29, 2007 Order, App. 65a). The arbitration
award reviewed by the District Court and Third Circuit
in this matter was issued on August 3, 2005. Opinion and
Award in the Matter of the Arbitration Between Five
Star Parking and IBT Local 723 (Aug. 3, 2005) (App. 21a)
STATEMENT OF JURISDICTION
The judgment of the United States Court of Appeals
for the Third Circuit was entered on July 24, 2007.
(App. la). A Petition for Rehearing and for Rehearing
En Banc was timely filed, and was denied on August 29,
2007. (App. 65a). Pursuant to Supreme Court Rule 13.1,
this petition has been filed within 90 days of the denial
of rehearing
The jurisdiction of this Court is invoked pursuant. to
28 U.S.C. § 1254(1).
2]
oO
RELEVANT PROVISIONS INVOLVED
Section 301 of the Labor Management Relations Act,
29 U.S.C. § 185(a) states:
Suits for violation of contracts between an
employer and a labor organization representing
employees in an industry affecting commerce as
defined in this chapter, or between any such
labor organizations, may be brought in any
district court of the United States having
jurisdiction of the parties, without respect to the
amount in controversy or without regard to the
citizenship of the parties.
section 8 of the National Labor Relations Act, 29
U.S.C. § 158 states:
(a) It shall be an unfair labor practice for an
employer—
(1) to interfere with, restrain, or coerce
employees in the exercise of the rights
guaranteed in section 157 of this title;
x x *
(5) to refuse to bargain collectively with
the representatives of his employees, subject
to the provisions of section 159 (a) of this title.
* * *
4
(d) For the purposes of this section, to bargain
collectively is the performance of the
mutual obligation of the employer and the
representative of the employees to meet at
reasonable times and confer in good faith with
respect to wages, hours, and other terms and
conditions of employment, or the negotiation of
an agreement, or any question arising
thereunder, and the execution of a written
contract incorporating any agreement reached
if requested by either party, but such obligation
does not compel either party to agree to a
proposal or require the making of a concession:
Provided, That where there is in effect a
collective-bargaining contract covering
employees in an industry affecting commerce,
the duty to bargain collectively shall also mean
that no party to such contract shall terminate or
modify such contract, unless the party desiring
such termination or modification—
(1) serves a written notice upon the other
party to the contract of the proposed termination
or modification sixty days prior to the expiration
date thereof, or in the event such contract
contains no expiration date, sixty days prior to
the time it is proposed to make such termination
or modification;
(4) continues in full force and effect, without
resorting to strike or lock-out, all the terms and
conditions of the existing contract for a period
of sixty days after such notice is given or until
the expiration date of such contract, whichever
occurs later.
STATEMENT OF THE CASE
Five Star and Local 723, Affiliated with the
International Brotherhood of Teamsters (the “Union”)
are parties to a collective bargaining agreement,
effective August 1, 2002 through July 31, 2008 (the
“CBA”). The CBA pertains to Five Star operations at
Newark Airport for which Five Star employs, and the
Union represents, cashiers, attendants and lot checkers
Five Star is an employer in an industry affecting
commerce, as defined in Sections 501(1) and (3) and 2(2)
of the National Labor Relations Act (the “N LRA”)
(29 U.S.C. § 142(1), (3) and 29 U.S.C. § 152(2)), and within
the meaning of Section 301 of the NLRA (29 U.S.C.
§ 185). The Union is a labor organization representing
employees in an industry affecting commerce, as defined
in Sections 501(1), (3) and 2(5) of the NLRA (29 U.S.C.
§ 142(1), (3), and 29 U.S.C. § 152(5)), and within the
meaning of Section 301 of the NLRA (29 U.S.C. § 185).
The CBA sets forth a grievance procedure, including
provisions establishing specific jurisdictional standards
for arbitration. Article 4 of the CBA allows either party
to submit to arbitration any disputes “involving or
concerning the meaning, interpretation, operation, or
application of any clause of” the CBA. The CBA limits
the jurisdiction of the arbitrator to “the particular
dispute in question” and provides that the arbitrator
6
“shall not have jurisdiction or authority to add to, modify,
detract from, or alter in any way the provisions of this
Agreement or any amendment or any supplement
thereto.” (CBA Art. 4 at 2-3, see App. 23a). There are no
provisions in the CBA that give an arbitrator jurisdiction
to decide issues outside of the CBA. There are no
provisions in the CBA that give an arbitrator jurisdiction
to decide issues under the NLRA, such as whether an
“impasse” has occurred.
The CBA sets wage rates for the time period from
August 1, 2002 until July 31, 2004. The CBA does not set
wage rates for the period from August 1, 2004 through
the expiration of the CBA on July 31, 2008. The CBA
also contains a reopener provision that allows either
party, by giving written notice, to reopen the terms of
the CBA “solely for the purpose of renegotiating
concerning wages and monetary fringe benefits, but for
no other purpose.” On June 18, 2004, the Union gave
Five Star notice of wage reopener bargaining pursuant
to the reopener provision. Five Star agreed to negotiate
with the Union and the parties commenced a series of
negotiations concerning wage rates.
Five Star proposed a 12-and-one-half percent
(12.5%) reduction in wage rates, explaining that
operational costs necessitated the downward wage
adjustment. The Union rejected the offer. Negotiations
continued. The Union demanded confidential financial
data from Five Star covering all Five Star facilities (not
limited to Newark Airport). Five Star made financial
informa* on concerning Newark Airport available to the
Union but declined to provide data for facilities other
than Newark Airport. The Union refused to continue
7
participating in the negotiations and purported to
withdraw its request for wage reopener. Having rejected
Five Star’s proposal at several meetings and through
correspondence, the Union never changed its position
or exhibited any willingness to alter its position on wage
rates or even to engage in further discussions. Five Star
determined that the parties had reached an impasse and
implemented its last and final offer, the 12.5% wage rate
reduction, on September 17, 2004.
The Union submitted the alleged unfair labor
practice charge to the National Labor Relations Board
(the “NLRB”). The Union withdrew its charge before
the NLRB.
The Union then invoked the grievance procedure of
the CBA and pursued arbitration. From the outset of
the arbitration, Five Star maintained that the arbitrator
lacked jurisdiction to decide issues under the NLRA.
Five Star specifically stated that the arbitrator lacked
jurisdiction to decide the question of whether an
“impasse” occurred.
The Award was issued on August 3, 2005. While in
some parts of the Award, the arbitrator disclaimed any
authority or intention to determine the issue of
“impasse,” the text of the award and the issue decided
make clear that the only issue determined in the
arbitrator’s opinion was that no “impasse” existed under
the NLRA. After stating this labor-law determination,
the Award simply declares in conclusory terms that Five
Star breached the CBA, never identifying any provision
of the CBA that Five Star allegedly violated.
d
On August 11, 2005, Five Star filed in the District
Court a Complaint and a motion to vacate the Award.
On December 20, 2005, the District Court issued an
Order granting Five Star’s motion to vacate the Award,
denying Five Star’s motion for attorneys’ fees, and
denying the Union’s motion in its entirety, on the grounds
that the “arbitrator exceeded his jurisdiction” by
“failling| to ground his decision in any provision of the
CBA.” (App. 17a-18a). The District Court found that the
arbitrator had based his decision entirely on whether
an impasse had been reached and not on a construction
of any term or provision of the CBA, and that whether
an impasse had been reached was a question of federal
labor law to be decided by the NLRB. (App. 17a-19a).
The Union filed a notice of appeal to the Third Circuit
on January 19, 2006. The Third Circuit issued an opinion
on July 24, 2007 rcinstating the arbitrator’s award.
(App. 12a). The Third Circuit decision held that the
arbitrator had the authority to determine whether an
impasse existed. (App. 10a-12a). A timely petition for
Pancl Rehearing and Rehcaring En Banc was denied on
August 29, 2007. (App. 65a-66a).
This Court should now consider the Petitioner’s
claim that a CBA that allows for rights, but not interest,
arbitration does not permit an arbitrator to decide
whether an impasse has been reached in economic
reopener negotiations. The Court is now presented with
the opportunity to clarify the law attendant Lo reopener
negotiations and the arbitrability of disputes that arise
thereunder.
9
REASONS FOR GRANTING THE PETITION
The Third Circuit Decision highlights a disagreement
among the Circuit Courts of Appeals on several issues
related to the arbitrability of disputes concerning
economic reopener negotiations. The D.C. Circuit and
the Tenth Circuit, as well as the NLRB, have held that
when an employer and a union negotiate pursuant to an
economic reopener provision in the CBA, the NLRA
allows the employer to unilaterally implement its final
offer after bargaining to a good faith impasse. Local
Union No. 47, Int'l Bhd. of Elec. Workers v. N.L.R.B.,
927 F.2d 635, 643-644 (D.C. Cir. 1991); Colorado-Ute Elec.
Ass’n, Inc. v. N.L.R.B., 9389 F.2d 1392, 1404 (10th Cir.
1991). The First Circuit has held that after negotiating
over new or renewal agreements to an impasse, the
employer's right to implement is not arbitrable because
it falls under the jurisdiction of the NLRB. Newspaper
Guild of Salem, Local 105 of the Newspaper Guild v.
Ottaway Newspapers, Inc., 79 F.3d 1278, 1283-84 (1st
Cir. 1996).
In contrast, the Eighth Circuit in General Drivers
and Helpers Union, Local No. 554 v. Mid-Continent
Bottlers, Inc. (Omaha Division), 767 F.2d 482, 485 (8th
Cir. 1985), and the Third Circuit in this case, both held
that the operation of reopener agreements and the
remedies thereunder arise from the CBA and are
arbitrable.
10
Decisions of the First, Tenth and D.C. Circuits
Hold That An Employer’s Right to Implement
After An Impasse In Reopener Negotiations
Arises from the NLRA and Is Not Arbitrable
1. Decisions of the United States Supreme Court
Define the Rights of Parties after an Impasse
is Reached in Negotiating a CBA
This Court has held that when parties negotiate
mandatory terms of a new or renewal CBA to a good
faith impasse, the NLRA grants the employer the right
to unilaterally implement its last offer. See, e.g., Litton
Fin. Printing Div., A Div. of Litton Bus. Sys., Ine. v.
NLRB, 501 U.S. 190, 198 (1991) (employer may
unilaterally implement after impasse when negotiating
a replacement for an expired CBA); NLAB v. Katz, 369
U.S. 736, 745 (1962) (employer may unilaterally
implement after impasse when negotiating the terms of
an initial CBA). This Court has also held that when an
impasse has been reached in reopener negotiations, the
Union retains its right to strike unless the CBA
expressly waives that right. NLRB v. Lion Oil Co., 352
U.S. 282, 2938-294 (1957). However, this Court has not
yet extended its decision in Lion Oil to its logical
conclusion that when parties to a CBA negotiating
pursuant to a reopener provision reach a good faith
impasse, both parties retain all of their economic
weapons including the employer’s right to unilaterally
implement its final offer.
11
2. Decisions of the D.C. Circuit and the Tenth
Circuit Hold that the Right to Implement at
Impasse Arises from the NLRA
In international Brotherhood of Electrical Workers,
the D.C. Circuit extended the holding of Lion Oil to
include the rights of employers. It held that an
employer’s right to implement its final offer after an
impasse in reopener negotiations arises from the NLRA
and that in order to waive that right, the CBA must
evidence a “clear agreement” to preclude the use of such
“economic leverage.” 927 F.2d at 642-644.
In that case, an employer and union entered into
negotiations pursuant to a wage reopener provision in
their CBA, and after reaching an impasse, the employer
implemented its final offer. Jd. at 639-40. After the union
filed an unfair labor practice complaint, an
administrative law judge (“ALJ”) and the NLRB both
found that the employer had a right, under Section &(d)
of the NLRA, that after an impasse in reopener
negotiations the parties could resort to any of the
economic weapons available to them when bargaining
for a new or renewal agreement, including the right to
lock-out, strike, or unilaterally implement final offers.
Id. On appeal to the D.C. Circuit Court of Appeals, the
union argued that the contractual language of the
reopener provision precluded the right to implement.
Id. at 643. The union pointed to the language of the
reopener which provided for reopening “only for the
purpose of negotiating ... changes” and that
“{algreement reached as a result of such reopening shall
become effective as of January 1.” Jd. The union argued
that because the provision required “negotiating” and
+
A bent
provided for an effective date for the subsequent
“agreement”, the reopener provision merely allows the
renegotiation of terms “while leaving the existing terms
and conditions fully effective until mutual agreement on
a modification is reached.” /d. at 643-44. The D.C. Circuit
disagreed with the union and upheld the orders of the
ALJ and NLRB.
The D.C. Circuit found that “the employer’s
obligation to bargain over a reopened wage term carries
with it the right to implement a final wage offer upon
genuine impasse” and that “curtailing the right...
‘would turn reopencr bargaining into little more than a
charade that would barely differentiate it from the kinds
of discussion that may lawfully occur even in the absence
of a reopener.’” /d. at 644 (quoting Speedrack, Inc., 293
N.L.R.B. No. 128, at 4-5 (May 17, 1989) (emphasis
added)). The D.C. Circuit drew a distinction between the
discussions that parties can engage in throughout the
course of their relationship and negotiations pursuant
to areopener provision that are governed by the NLRA.
The D.C. Circuit followed the reasoning of the NLRB in
Speedrack, which in turn followed the reasoning of this
Court in Lion Ol. Id. at 642-45. In Lion Oil, this Court
construed the term “expiration date” in Section 8(d)(1)
and (4) of the NLRA as applying both to expiration of
fixed-term contracts and to date on which the terms of a
contract are opened pursuant to a reopener provision.
Lion Oil, 352 U.S. at 289-90. The NLRB in Speedrack,
relied on that construction to find that when a reopencr
provision is invoked, the CBA is effectively terminated
with respect to the reopened terms and the parties may
then resort to the same economic weapons available to
them when bargaining a new or renewal agreement.
13
Speedrack, 293 N.L.R.B. No. 128, at 2. The D.C. Circuit
adopted the NLRB’s presumption that reopener
bargaining is the functional equivalent of bargaining in the
absence of a contract with respect to the reopened terms,
and as such, the parties retain the same leverage.
In Colorado-Ute, the Tenth Circuit also held that an
employer’s right to implement its final offer after reaching
a good faith impasse in reopener negotiations arises from
the NLRA. 939 F.2d at 1404-05. In that case, after
bargaining to an impasse in reopener negotiations the
employer implemented its final offer and the union initiated
a strike. /d. at 1398-1400. The parties continued to bargain
after the impasse and the union then filed a complaint
alleging that the employer had violated Section 8(a)(5) of
the NLRA by, inter alia, “unlawfully implementing the
terms of its wage offer during negotiations.” Jd. The ALJ
found that the employer acted within its rights, but the
NLRB found that though the employer had the right to
implement at impasse, that the substance of this final offer
was one that could not be implemented unilaterally.
Id. at 1399-1400.
The Tenth Circuit reversed, finding that there were
no such restrictions on an employer’s right to implement
on impasse. /d. at 1403-05. Further, it found that the right
to implement arose from the NLRA, limited only by the
NLRA’s requirement that the employer bargain in good
faith. Jd. at 1404, 29 U.S.C. § 158(d). The Tenth Circuit's
decision not only held that the employer has the right to
implement at impasse in reopener negotiations and that
the right arises from the NLRA, but also that operation of
that right—whether negotiations were in good faith—
is also governed by standards set by the NLRA. /d. at
1404-05.
14
3. Decisions of the First Circuit Hold that the
Right to Implement at Impasse is Not
Arbitrable
While the decisions of the D.C. and Tenth Circuits
discussed above establish the right to implement after
an impasse in reopener provisions, they do not address
the arbitrability of disputes over those rights or ove
the operation of reopener provisions in general.
However, “[ilt is well-settled that the NLRB enjoys
primary jurisdiction over disputes involving unfair labor
practices... .” Ottaway Newspapers, 79 F.3d at 1283. The
First Circuit has held, in a dispute involving negotiating
a renewal CBA, that a dispute over the right to
implement at impasse was not arbitrable because it
arises solely from the NLRA and not from the CBA itself.
Id. at 1283-1284.
In Ottaway Newspapers, the parties negotiated a
renewal to an expired CBA. /d. at 1275-76. After an
underwhelming employer proposal that included
proposed layoffs, the union filed a demand for arbitration
with the American Arbitration Association, a complaint
in the U.S. District Court for the District of Massachusetts
seeking an order to compel arbitration, and an unfair
labor practice complaint with the NLRB. /d. at 1276.
The District Court denied the union’s request because
no layoffs had been made and stated that if layoffs were
made after the conclusion of negotiations, that could
constitute an unfair labor practice under the jurisdiction
of the NLRB. Jd. A week after the District Court’s
decision, the union appealed to the First Circuit. Jd. at
1277. A week after the appeal, the employer declared an
impasse and stated an intent to implement its last offer.
15
Id. The union then amended its complaint with the
NLRB to challenge the unilateral implementation by the
Employer. /d.
On appeal, the union argued that pursuant to a rights
arbitration provision, an arbitrator could determine the
scope of negotiations over a renewal agreement. In doing
so, the union contended, “the arbitrator would not be
dictating the terms of the successor agreement; instead
it would be determining whether [a provision governing
negotiating successor agreements] imposes an obligation
to negotiate in good faith.” Jd. at 1280-81. The First
Circuit disagreed, finding that there is no “meaningful
distinction” between arbitrating the scope of negotiations
and arbitrating the terms. Both are interest arbitration.
Id. at 1281. The First Circuit went on to hold that
questions of whether an impasse had been reached and
whether the employer bargained in good faith arise all
“fall squarely within the NLRB’s primary jurisdiction
as they are essentially extra-contractual claims” that
arise under the NLRA. /d. at 1285.
B. Decisions of the Eight Circuit Hold that the Right
to Implement at Impasse arises from the CBA and
is Arbitrable
The Fighth Circuit, alternatively, has found that
implementation at impasse is a creature of the CBA, and,
as such, is arbitrable. See, e.g., Mid-Continent Bottlers,
767 F.2d at 485; Bricklayers and Allied Crafts Union,
Local No. 4 of Minn. v. Associated General Contractors
of Minn., 711 F.2d 90 (8th Cir. 1983). In Mid-Continent
Bottlers, the parties reached an impasse after
negotiating pursuant to a reopener provision. /d. at 484.
16
After the employer unilaterally implemented its final
offer, the union brought an action for breach of the
contract in the U.S. District Court for the District of
Nebraska. /d. After the District Court’s decision in favor
of the union, the employer appealed, claiming that
District Court lacked jurisdiction because the claim was
subject to a broad rights arbitration provision in the
CBA. Id. The Eighth Circuit agreed with the employer
that the right to implement “existed under the contract”
and “presented a controversy over interpretation of or
adherence to the bargaining agreement.” Jd. at 485. In
allowing an arbitrator to address the employer’s
implementation after impasse, the Eighth Circuit did not
once mention the NLRA.
In Laundry, Dry Cleaning & Dye House Workers
Int'l Union, Local 93 v. Mahoney, after the parties
negotiated wages to an impasse pursuant to a reopener
provision, the union sought arbitration. 491 F.2d 1029,
1030 (8th Cir. 1974). The CBA contained provisions for
resolving grievances, including through arbitration, and
also contained a limitation that an arbitrator did not have
the authority to “add to, subtract from, or change the
terms of the contract.” /d. at 1031. The Eighth Circuit
in this case upheld the decision of the District Court that
the wage dispute was arbitrable. Citing this Court’s
decision in United Steelworkers v. Warrior and Gulf
Navigation, 363 U.S. 574 (1960), the Eighth Circuit held
that absent any express provision excluding a matter
from arbitration, any disputes arguably under a CBA
containing an arbitration provision are arbitrable.
Mahoney, 491 F.2d at 1032. The Eighth Circuit
recognized concerns that its decision will make all mid-
term wage disputes arbitrable, but points out that
17
parties seeking to exclude this type of dispute from
arbitration can include language to that effect in the
CBA. Id. at 1033. The decision did not once mention the
NLRA.
C. The Third Circuit Decision Holds that the Right
to Implement at Impasse arises both from the
CBA and the NLRA and is Arbitrable
The Third Circuit’s decision in Five Star Parking
diverges from those of the First, Tenth and D.C. Circuits
by finding that disputes over the operation of reopener
provisions arise both from the NLRA and the CBA, thus
converting the primary jurisdiction of the NLRB into
concurrent jurisdiction. (App. 11a-12a). In this case, after
Five Star implemented its final offer after declaring an
impasse in reopener negotiations, the parties agreed to
arbitrate whether the CBA had been breached.
(App. 22a). Five Star made clear, however, that it was
not willing to arbitrate the existence of an impasse,
because that was a matter of federal labor law and not a
question under the CBA. (App. 15a). After the arbitrator
found that Five Star had breached the CBA by failing to
negotiate to an impasse, the District Court vacated the
Award, holding that the only issue decided by the
arbitrator was the existence of an impasse, a term to be
interpreted by the NILRB and not by an arbitrator
operating under a rights arbitration clause. (App. 17a-
19a). The Third Circuit reversed. (App. 12a). While it
agreed with the District Court that “the concept of
impasse and whether the parties bargained in good faith”
raised questions of unfair labor practices, it also believed
that the terms of the reopener provision itself were in
dispute and provided an independent basis for the
18
arbitrator’s jurisdiction. (App. lla-12a). The Third
Circuit held that because the reopener clause
contemplated that the parties “negotiate”, the arbitrator
could decide that a failure to negotiate was a violation of
the CBA. Id.
D. The Dispute in Five Star Parking Would Not Be
Arbitrable Under the Holdings of the First, Tenth,
and D.C. Circuits
In Five Star Parking, the Third Circuit found that
an arbitrator operating under a rights arbitration
provision had the authority to interpret the word
“negotiation” in an economic reopener provision to
require something different than what the NLRA
requires. Applying the standards discussed in
International Brotherhood of Electrical Workers,
Colorado-Ute and Ottoway Newspapers, the meaning of
the terms within the reopener provision are governed
by the NLRA. The requirement to negotiate in good faith
arises from the NILRA, and the text would need to
evidence a clear agreement to limit the rights provided
to the parties under the NLRA. Since the text
demonstrates no such agreement to limit Five Star’s
right to implement at impasse or to modify the good
faith requirement, the dispute over Five Star’s
implementation at impasse is a question for the NLRB
and not within the jurisdiction of an arbitrator.
19
CONCLUSION
Based on the conflicting decisions of the Circuit Courts
described above, employers and unions are placed in an
untenable position that requires resolution by this Court.
Employers and unions need guidance concerning the
applicability of federal labor law to the context of reopener
negotiations. This Court has made clear that when
employers and unions bargain to impasse, the parties are
entitled to resort to their respective economic weapons,
the employer to implementing its most recent offer and
unions to the right to strike. Many courts find that these
rights arise under the NLRA and fall under the primary
jurisdiction of the NLRB and that arbitration of these
rights amounts to impermissible interest arbitration, while
other courts find that because the reopener provision
appears in the CBA, its language, and thus rights attendant
to the negotiations, is arbitrable even in the absence of an
interest arbitration provision. This issue presents a
question of overriding importance because it affects
reopener bargaining nationwide. Indeed, absent resolution
by this Court, reopener bargaining may become a
“charade” rather than an important part of the collective
bargaining process. Finally, clarity is needed concerning
the status of reopener provisions and the respective rights
and obligations of employers and unions under these
widely-used occasions of collective bargaining.
For the foregoing reasons a writ of certiorari should
be granted.
Respectfully submitted,
MICHAEL 8. CRYAN
ARENT Fox LLP
1675 Broadway
New York, NY 10019
(212) 484-8900
Attorneys for Petitioner
APPENDIX
la
APPENDIX A — OPINION OF THE UNITED STATES
COURT OF APPEALS FOR THE THIRD CIRCUIT
FILED JULY 24, 2007
UNITED STATES COURT OF APPEALS
FOR THE THIRD CIRCUIT
No. 06-2012
FIVE STAR PARKING
v.
UNION LOCAL 728, affiliated with the
International Brotherhood of Teamsters,
Appellant.
Argued March 28, 2007
Filed July 24, 2007
Before RENDELL, BARRY and CHAGARES, Circuzt
Judges.
OPINION OF THE COURT
CHAGARES, Circuit Judge.
Appellant International Brotherhood of Teamsters
Union Local 723 (the “Union”) appeals from an Order of
the United States District Court for the District of New
Jersey entered on December 21, 2005 which vacated an
arbitration award favorable to the Union. For the reasons
expressed below, we will reverse the District Court and
remand with instructions to confirm the award. |
~
2a
Appendix A
I.
Appellee Five Star Parking (“Five Star”) manages
and operates parking lots at Newark Liberty
International Airport. The Union represents employees
at Five Star’s Newark Airport parking facilities. Five
Star and the Union are parties to a collective bargaining
agreement (“CBA”). The CBA provides that unresolved
grievances may be submitted to arbitration for final,
binding resolution. Article 4 Section 1 of the CBA defines
the scope of arbitration as including: “Any controversy,
claim, dispute or grievance arising between the Company
and the Union or any Employee, involving or concerning
the meaning, interpretation, operation, or application
of any clause of this Agreement, or by a breach or
threatened breach of this Agreement.” A101. An
arbitrator’s power to resolve grievances, found at Article
4(i), is
limited to the particular dispute in question
and [the arbitrator] shall be bound and
governed by the provisions of this contract and
restricted to its application to the facts
presented to him. ... The arbitrator shall not
have jurisdiction or authority to add to, modify,
detract from, or alter in any way the provisions
of this Agreement or any amendment or any
supplement thereto.
A102. In other words, an arbitrator is limited to resolving
disputes over “rights” in the CBA and shall not engage
in what is known as “interest” arbitration—the creation
of new rights not previously contemplated by the parties.
~
3a
Appendix A
The CBA does not include procedures to resolve an
“impasse.” Impasse is not mentioned in the CBA.
Five Star and the Union negotiated specific wages
for cashiers, traffic attendants, valet attendants and lot
checkers. These wage rates are reflected in Schedule A
of the CBA and were in effect from August 1, 2002 to
July 31, 2003. After the first year, the CBA provided for
3% wage increases across the board to commence on
August 1, 2003 and continue until July 31, 2004.
Thereafter, the CBA was silent as to wage increases;
presumably wages were to remain static unless further
wage negotiation took place. To this end, the CBA
contained a “re-opener” provision which permitted the
parties to re-negotiate wages as of August 1, 2004 and
again as of August 1, 2006 with 60 days notice to the
other party. The Union agreed that “during such periods
of re-opener, the no-strike, no lockout provisions of this
Agreement shall remain in full force and effect.” A117.
On June 18, 2004, the Union invoked the re-opener
provision. The Union sought a $1.00 per hour wage
increase in each succeeding year of the CBA-2004 to
2008. The parties met briefly on July 20, 2004 for their
first negotiation session. At the July 20 meeting, which
lasted about one hour, Five Star indicated that its labor
costs were exceeding the budget provided to the Port
Authority of New York and New Jersey (“Port
Authority”) and that the Port Authority was going to
request new bids for the management of the Newark
facilities. Five Star sought a 12.5% reduction in labor
costs.
4a
Appendix A
The parties met again on August 3, 2004 for
approximately one hour. The Union indicated it was not
interested in negotiating a regressive contract and
sought financial data from Five Star as proof that it was
operating over budget. On August 9, 2004, counsel for
Five Star responded by sending the Union a letter
summarizing Five Star’s financial condition, but without
supporting financial data. In the letter, Five Star stated
that it “wants to avoid any unilateral action consequent
to a good faith impasse in negotiations .” A123.
The Union replied by letter dated August 13, 2004,
in which it reiterated that it would not “bargain against
itself.” A128. Addressing Five Star’s contention that the
Port Authority might replace Five Star as manager of
the Newark Airport parking facilities, the Union stated,
“(ijn several months, it is possible that Five Star Parking
will not be at this facility. Thus, it is hard, as indicated
at the meeting, for Local 723 to negotiate concessions to
the collective bargaining agreement for a Company that
may no longer be at this facility and then be left with
those concessions for the new vendor coming in.” /d. The
Union further stated that Five Star was obligated to
bargain in good faith and to date, no bargaining had
occurred—only Five Star’s unilateral demand that labor
costs be reduced by 12.5%. Finally, the Union made a
second request for financial information covering the
period from July 2002 to August 2004. Ultimately, it
appears that financial information pertaining to the
Newark facility was made available to the Union, but
not financial information concerning Five Star’s other
operations.
Sa
Appendix A
On August 27, 2004, in writing, Five Star reiterated
its proposal for wage reductions and indicated that “[ilf
the Union continues to insist upon conditioning
negotiations upon receiving financial information that it
is not by law entitled to, and declines to resume
negotiations on September 3, 2004, a date offered by the
Union, the Company will deem the parties to be at an
impasse. Accordingly, it will be free to implement
unilaterally its pending and oft repeated proposal to
reduce rates of pay.” A29.
On September 1, 2004, the Union wrote to Five Star
indicating that it was withdrawing its request for re-
opener and would file an unfair labor practice charge
with the National Labor Relations Board (“NLRB”) and
file for arbitration if Five Star unilaterally implemented
a wage reduction.
On September 2, 2004, Five Star declared an
impasse. On September 14, 2004, the Union filed an
unfair labor practice charge with the NLRB alleging that
Five Star violated section 8(a)(1) and (5) of the National
Labor Relations Act (“N LRA”). Prior to a ruling by the
NLRB, however, the Union voluntarily withdrew its
charge.
On September 17, 2004, Five Star implemented a
12.5% wage reduction for all employees. On September
21, 2004, the Union filed a grievance contesting Five
Star’s unilateral implementation of the wage decrease
as a violation of Article 20 and Schedule A of the CBA.
The grievance stated, “On September 17, 2004, Five Star
6a
Appendix A
Parking unilaterally, without negotiations, without
‘impasse’ in negotiations, implemented a [12.5%] wage
reduction.” A137. The case proceeded to arbitration.
At the arbitration hearing, the parties stipulated to
the issue to be decided: “Did the Employer violate
Article 20 and Schedule A’ of the Agreement when on
September 17, 2004, Five Star Parking implemented a
wage reduction?” A238. Five Star argued that the
arbitrator lacked jurisdiction over the dispute because
resolution required a determination of whether an
impasse occurred. According to Five Star, determining
whether an impasse occurred requires interpretation of
the NLRA, something only the NLRB can do.
1. Article 20 states, in pertinent part: “Section 1: The rates of
pay shall be in accordance with [Schedule] A annexed hereto and
made a part hereof.” A112.
Schedule A list rates of pay for the different job classifications.
A118.
Seetion 2(a) of Schedule A is entitled “Future Pay Increases”
and states: “For the period commencing August 1, 2003 and
continuing until July 31, 2004, all employees shall receive an across-
the-hoard increase in their respective personal hourly rates of pay
equal to three percent (3%). It is agreed, however, that the actual
effective date shall be the first day of the first pay period falling on
or after August 1, 2003.” 7d. Section 2(b) states: “In accordance
with the provision of Article 12 of this Agreement, this Agreement
may be reopened by either party as of August 1, 2004 and August 1,
2006, but solely for the purpose of negotiating concerning rates of
pay and other monetary benefits, but for no other purposes, without
exception.” /d.
7a
Appendix A
The arbitrator sustained the grievance by an Opinion
and Award dated August 38, 2005. The arbitrator
concluded that “[b]ased on the facts in evidence, there
is no question that the Employer’s action of September
17, 2004, in reducing the employer’s [sic] wages was
violative of the collective bargaining agreement.” A55.
Later in the opinion, the arbitrator reiterated that “[t]he
Employer’s unilateral action of reducing the wages of
bargaining unit members was in violation of the
Agreement.” A58. Five Star was ordered to pay back
pay to all employees whose wages were reduced.
In dealing with Five Star’s jurisdiction argument,
the arbitrator identified the “gravemen [sic] of the
Union’s argument [as being] that the Employer
unilaterally implemented a 12.5% wage reduction. All
other issues of a statutory nature are not before me....
My only determination will be whether or not the
contract was violated.” A52-A53. However, the arbitrator
commented, “I find it extremely difficult to accept the
Employer’s argument that an impasse existed after
approximately two, maybe three, hours of bargaining,”
and “[bJased upon all of the evidence and voluminous
documentation presented by both parties, I am not
convinced that an impasse existed.” A54. Finally, the
arbitrator explained,
When an employer proposes a wage reduction
that is agreed to by a Union that is a
concession. Concessionary bargaining
produces some interesting results. However,
in the instant matter, the Employer never
8a
Appendix A
allowed the negotiations process to really
move forward or to pick up steam to see where
they could reach some type of common ground.
They simply said, we will not give you the
additional financial information you are asking
for, and if you do not show up for the
September 3, 2004 negotiating session we are
declaring an impasse. Accordingly, they
declared an impasse and reduced the wages
of the employees.
What is before me is that the Employer’s
action breached the Agreement. I have
already determined that it did.
It breached the Agreement because there was
no impasse. ... I can’t accept the limited time
spent in bargaining as a basis for the
Employer’s authority to reduce the wages of
the bargaining unit members.
A56-A57.
Five Star moved to vacate the arbitration award
before the District Court. The Union cross-moved for
summary judgment to confirm the award. The District
Court vacated the arbitration award, concluding that
“the arbitrator exceeded his jurisdiction in granting the
arbitral award. An arbitrator’s role is to interpret the
terms of the CBA rather than to decide issues of unfair
9a
Appendix A
labor practices. The latter is governed by the NLRA and
under the jurisdiction of the NLRB.” A6 (citation
omitted). Here, according to the District Court, the
arbitrator failed to ground the decision in any provision
of the CBA. Instead, the arbitrator decided that the
parties had not reached an impasse and therefore Five
Star violated the CBA by instituting a wage reduction.
The District Court held that the arbitrator’s decision
rested improperly and exclusively on its interpretation
of the concept of “impasse.” The Union appealed.
Il.
The District Court exercised jurisdiction pursuant
to section 301 of the Labor Management Relations Act
(“LMRA”), 29 U.S.C. § 185 and 28 U.S.C. § 1331. The
final order of the District Court vacating the arbitration
award disposed of all the Union’s claims. Our jurisdiction
is premised upon 28 U.S.C. § 1291.
We exercise plenary review over the District Court’s
ruling. Major League Umpires Ass'n v. Am. League of
Prof’l Baseball Clubs, 357 F.3d 272, 279 (3d Cir.2004).
Arbitration awards enjoy a strong presumption of
correctness. We will uphold an arbitration award that
“draws its essence from the collective bargaining
agreement.” /d. at 280 (citations omitted). Although an
arbitrator’s interpretation of a collective bargaining
agreement is accorded substantial deference, it may be
vacated if the arbitrator demonstrates manifest
disregard for the collective bargaining agreement. /d.
“Manifest disregard for the CBA is established when
10a
Appendix A
the arbitrator’s award is totally unsupported by
principles of contract construction.” /d. (internal
quotations and citations omitted). As long as an
“arbitrator is even arguably construing or applying the
contract and acting within the scope of his authority,’
the fact that ‘a court is convinced he committed serious
error does not suffice to overturn his decision.’” Eastern
Associated Coal Corp. v. United Mine Workers of Am.,
Dist. 17, 5381 U.S. 57, 62, 121 S.Ct. 462, 148 L.Ed.2d 354
(2000) (quoting United Paperworks Int'l Union AFL-
CIO v. Misco, Inc., 484 U.S. 29, 38, 108 S.Ct. 364, 98
L.Ed.2d 286 (1987)). Here, it is clear that the arbitrator
acted within the scope of his authority and committed
no error in construing and applying the CBA.
Consequently, we will uphold his decision.
ITf.
The District Court vacated the arbitration award
based on its perception that the arbitrator lacked
jurisdiction to decide the issue of whether impasse
existed and also because it concluded that the arbitrator
“failed to ground his decision in any provision of the
CBA.” A7. The District Court rightly recognized that
“[wlhile it is true that, for purposes of efficiency and
economy, an arbitrator may at times hear issues
pertaining to unfair labor practices, this is only
permissible when the arbitrator decides NLRA issues
in addition to issues of contract interpretation.” /d.
(citing Carey v. Westinghouse Electric Corp., 375 U.S.
261, 271, 84S8.Ct. 401, 11 L.Ed.2d 320 (1964)). There was
clearly an unfair labor practice issue here dealing with
lla
Appendix A
the concept of impasse and whether the parties bargained
in good faith. Because the District Court seemingly
understood that the issue of impasse could have been
decided by an arbitrator if there were also issues of
contractual interpretation in dispute, the outcome of this
appeal depends on whether there was an arbitrable
contractual issue at stake rather than merely on whether
the arbitrator could or could not decide the issue of impasse.
By stipulating to the issue to be decided by the
arbitrator, “Did the Employer violate Article 20 and
Schedule A of the Agreement when on September 17, 2004,
Five Star Parking implemented a wage reduction?,” it is
abundantly clear that Five Star agreed from the outset that
the grievance was arbitrable and that it related to Article
20 and Schedule A of the CBA. The arbitration clause
broadly provides for arbitration of “[a]ny controversy,
claim, dispute or grievance arising between the Company
and the Union or any Employee, involving or concerning
the meaning, interpretation, operation or application of any
clause of this Agreement, or by a breach or threatened
breach of this Agreement.” The wage re-opener provision
in Schedule A of the CBA expressly requires that the
parties negotiate; a refusal or failure to negotiate therefore
would be a breach of the CBA.
The fact that the parties did not provide for even cost-
of-living adjustments to salaries after July 31, 2004, but
instead provided for wage re-opener negotiations is
compelling evidence that they considered negotiation to
be the sine qua non of that contractual provision. Although
declaring an impasse in bad faith implicates the NLRA,
l2a
Appendix A
the statutory requirement to negotiate in good faith
overlaps the parties’ express contractual agreement to
“negotiat{e] concerning rates of pay.” [t therefore fell upon
the arbitrator to interpret the meaning of “negotiat[e]
concerning rales of pay” in the wage renegotiation context
because this involved or concerned “the meaning,
interpretation, operation or application of [a] clause of this
Agreement, or... a breach or threatened breach of this
Agreement.” Thus, we conclude that there was a bona fide
contractual dispute and the issue was properly before the
arbitrator. See Carey, 375 U.S. at 271; see also Collyer
Insulated Wire, 192 N.L.R.B. 887 (1971).
The arbitrator declared an intent to decide whether
there was a breach of contract, and in so deciding, found
that the parties failed to negotiate pursuant to the express
terms of Schedule A of the CBA. The award merely returns
the salaries to the status quo by ordering Five Star to pay
back the amounts wrongly deducted therefrom. It does not
set new salaries for the parties. The arbitrator did not
engage improperly in interest arbitration, see
Pennsylvania Power Co. v. Electrical Workers, Local 272,
886 Fi2d 46, 48-49 (3d Cir.1989), but rather acted within the
scope of his authority to construe and apply the CBA.
For the foregoing reasons, we conclude that the
arbitration award draws its essence from the CBA and
should not be disturbed. Accordingly, we will reverse the
District Court’s Order of December 20, 2005, and remand
to the District Court with instructions to confirm the
arbitration award in favor of the Union.
l3a
APPENDIX B — OPINION OF THE UNITED
STATES DISTRICT COURT FOR THE DISTRICT
OF NEW JERSEY DATED DECEMBER 23, 2005
UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEW JERSEY
No. 05-CV-3975 (WJM)
FIVE STAR PARKING,
Plaintiff,
V.
LOCAL 723,
Defendant.
December 23, 2005
OPINION
MARTINI, J.
THIS MATTER comes before the Court on Plaintiff
Five Star Parking’s (“Five Star’s”) motion to vacate an
arbitration award and Defendant Local 723’s (“the
Union’s”) cross-motion for summary judgment to
confirm the arbitration award. This Court heard oral
arguments on November 3, 2005. For the reasons stated
below, this Court GRANTS Plaintiff’s motion to vacate
and enjoin enforcement of an August 3, 2005 arbitration
award, DENIES Plaintiff’s motion for attorney’s fees,
and DENIES Defendant’s motion in its entirety.
l4a
Appendix B
I. Background:
This is a labor dispute between Five Star, which
operates parking garages, and the Union, an employees
union representing cashiers, traffic attendants, valet
attendants, and lot checkers employed by Five Star at
Newark Airport.
The parties are signatories to a Collective Bargaining
Agreement (“CBA”), which governs the period from August
1, 2002 until July 31, 2008. Although the CBA set specific
wage rates for the period from August 1, 2002 until July
31, 2004, it did not set wage rates for the period after August
1, 2004. Thus, on June 18, 2004, pursuant to terms in the
CBA, the Union requested wage reopener bargaining.
Negotiations did not go smoothly. Five Star expressed
its intention to reduce wages in light of the fact that its
operating costs far exceeded the budget approved by the
Port Authority of New York and New Jersey. The Union
rejected Five Star’s proposal. Further, in a letter dated
August 18, 2004, the Union demanded disclosure of Five
Star’s financial documents and stated its intention to file
an unfair labor practice charge with the National Labor
Relations Board (“NLRB”) should Five Star unilaterally
reduce wages. Five Star took the position that the parties
had reached an “impasse,” and on September 17, 2004,
implemented a 12.5% wage reduction.’ In response, on
1. Under the NLRA, when negotiations reach an impasse,
the employer is free to implement changes in employment terms
unilaterally so long as the changes have been previously offered
to the Union during bargaining. Saunders House v. NLRB, 719
F.2d 683 (3d Cir.1983). Otherwise, if no impasse exists, such a
unilateral change constitutes a violation of sections &(a)(1) and
(5) of the NLRA. NLAB v. Katz, 369 U.S. 736, 748 (1962).
lSa
Appendix B
September 21, 2004, the Union submitted a grievance to
the NLRB, alleging unfair labor practices.
According to Five Star, the NLRB reviewed the
Union’s grievance and expressed its intention to rule
against the Union. Five Star also alleges that, in lieu of
receiving an adverse decision, the Union withdrew its
grievance and commenced an arbitration proceeding.
The Union does not dispute either of these allegations.
Upon commencement of the arbitration proceeding,
the parties jointly submitted to the arbitrator the issue
of whether Five Star had violated the CBA. At the same
time, Five Star contested the arbitrator’s jurisdiction
to decide on the question of whether the parties had
reached an impasse. Five Star argued that, since the
issue of impasse arose under the National Labor
Relations Act (“N LRA”), it fell under the jurisdiction of
the NLRB. The arbitrator disagreed and instead found
that the arbitration clause of the CBA was far-reaching
enough to give him jurisdiction to decide the issue.”
In deciding on the merits of the Union’s claim, the
arbitrator found that the parties had not reached a
bargaining “impasse,” and that therefore Five Star had
not been free to implement a unilateral wage reduction.
He concluded that Five Star had violated the CBA by
2. Article 4, Section 1 of the CBA, the arbitration clause of
the agreement, covers “la]ny controversy, claim, dispute or
grievance arising between the Company and the Union or any
employee, involving or concerning the meaning, interpretation,
operation or application of any clause of this agreement, or by a
breach or threatened breach of this agreement.”
16a
Appendix B
decreasing wages. The arbitrator issued a cease and
desist order and further awarded the Union employees
back pay for the period during which wages had been
reduced.
Five Star has not complied with the award. Instead,
it has moved to vacate the award on the following
grounds: (1) the arbitrator exceeded the scope of his
authority in deciding on the issue of impasse; (2) even if
Five Star had agreed to arbitrate disputes involving the
NLRA, the arbitrator misinterpreted the statute in
finding the parties had not reached an impasse; and
(3) the arbitrator incorrectly found that the CBA
required Five Star to pay a set wage after August 1, 2004.
II. Standard of Review
As a general matter, district courts have little
authority to upset arbitrators’ awards. United Transp.
Union Local 1589 v. Suburban Transit Corp., 51 F.3d
376, 379 (3d Cir.1995). When dealing with a labor dispute,
if an arbitration award is not in “manifest disregard” of
the contract and “draws its essence” from the contract,
it should be enforced by a reviewing court. Major League
Baseball Players Ass’n v. Garvey, 532 U.S. 504 (2001);
WR. Grace & Co. v. Local Union 759, 461 U.S. 757 (1983).
Where an arbitrator’s decision fails to draw its essence
from the CBA, however, the award must be vacated.
See Citgo Asphalt Refining Co. v. Paper, Allied-Indus.,
Chem. & Energy Workers Int'l Union, 385 F.3d 809, 815
(3d Cir.2004).
17a
Appendix B
III. Analysis
Turning first to jurisdictional issue, the record
before this Court demonstrates that the arbitrator
exceeded his jurisdiction in granting the arbitral award.
An arbitrator’s role is to interpret the terms of the CBA
rather than to decide issues of unfair labor practices.
The latter is governed by the NLRA and under the
jurisdiction of the NLRB. United Steelworkers of
America v. Enterprise Wheel and Car Corp., 363
U.S. 593, 597 (1960) (“an arbitrator is confined to
interpretation and application of the collective
bargaining agreement”); Graphic Arts Int'l v. Haddon
Craftsmen, 796 F.2d 692 (3d Cir.1986) (finding arbitrator
properly decided only claims arising under CBA and
declining jurisdiction on “naked” NLRA claim). With
regard to the issue of whether parties involved in labor
negotiations have reached an impasse, courts have found
that the question of impasse arises under the NLRA and
should be decided by the NLRB. See Newspaper Guild
of Salem v. Ottoway Newspapers, Inc., 79 F.3d 1273 (1st
Cir.1996) (finding no error in district court refusal to
order arbitration of whether impasse existed because
allowing arbitration would allow party to circumvent
NLRB); Local Union No. 884 v. Bridgestone/Firestone,
Inc., 61 F.3d 1347 (8th Cir.1995) (finding question of
impasse not covered by CBA arbitration clause and
therefore not to be raised before arbitrator); see also
U.A. 198 Health & Welfare, Education & Pension Funds
v. Rester Refrigeration Service, Inc., 790 F.2d 423 (Sth
Cir.1983) (expressing view that NLRB is “particularly
qualified,” because of specialized expertise, to decide
18a
Appendix B
whether parties have reached an impasse).’? While it is
true that, for purposes of efficiency and economy, an
arbitrator may at times hear issues pertaining to unfair
labor practices, this is only permissible when the
arbitrator decides NLRA issues in addition to issues of
contract interpretation. See Carey v. Westinghouse
Electric Corp., 375 U.S. 261 (1964); Int'l Harvester Co.,
138 N.L.R.B. 923 (1962). To permit otherwise would
render the NLRB largely superfluous.
In this case, the arbitrator failed to ground his
decision in any provision of the CBA. Upon deciding the
parties had not reached an impasse, he simply concluded
that Five Star had violated the CBA by instituting a wage
reduction.’ The arbitrator’s decision, as far as this Court
3. The Union cites a number of cases which purportedly
stand for the proposition that an arbitrator can decide the issue
of impasse. Ilowever, none of those cases apply here, either
because the arbitrator in those cases grounded his decision in
specific provisions of the CBA, e.g., Edna H. Pagel, Inc., v.
Teamsters Local Union 595, 667 F.2d 1275 (9th Cir.1982), or
because the NLRB had issued a decision on the impasse issue
prior to arbitration, e.g., Yorkaire, Inc. v. Sheet Metal Workers
Int'l Ass’n, 758 F.Supp. 248 (F.D.Pa.1990).
4. “I find it extremely difficult to aecept the
Employer’s argument that an impasse
existed after approximately two, maybe
three, hours of bargaining.
I cannot accept the limited time spent in
bargaining as a basis for the Employer's
(Cont'd)
19a
Appendix B
ean discern, rested wholly on his interpretation of the
NLIRA term “impasse” and the effect of Five Star’s wage
reduction given his finding there was no impasse. There
is no indication that the arbitrator grounded his decision
on an interpretation of provisions within the CBA.
Based on this holding, this Court finds it unnecessary
to address Five Star’s other arguments.
V. Conclusion:
This Court finds that the arbitrator did not have
jurisdiction to decide the issue of impasse, and that his
decision otherwise failed to draw its essence from the
CBA. Accordingly, this Court grants Five Star’s motion
to vacate the award of the arbitrator and to enjoin
enforcement of the award. It also denies the Union’s
motion in its entirety. See AFGE v. FLRA, 850 F.2d 782
(D.C.Cir.1988) (affirming vacatur of arbitral award
where arbitrator did not have jurisdiction to hear a
(Cont’d)
authority to reduce the wages of the bargaining
unit members. Accordingly, there is no question
in my mind that the Employer’s action
breached the agreement.”
Five Star Parking v. IBT Local 723, No. 04-0250, 32, 35 (2005)
(Restaino, Arb.).
5. This Court is mindful of the broad language of the
arbitration clause in the CBA. It nevertheless finds the clausc is
not broad enough to confer jurisdiction upon an arbitrator to
decide on a naked NLRA claim.
20a
Appendix B
dispute). Further, this Court, finding that the Union did
not litigate in bad faith, vexatiously, or for oppressive
’
reasons, denies Five Star’s request for attorney’s fees.
Kane Gas Light and Heating Co. v. Int'l Bhd. of Firemen
and Oilers, Local 112, 687 F.2d 673 (3d Cir.1982).
2la
APPENDIX C - OPINION AND AWARD OF THE
NEW JERSEY STATE BOARD OF MEDIATION
DATED AUGUST 3, 2005
NEW JERSEY STATE BOARD OF MEDIATION
CASE NO. 04-0250
In the Matter of the Arbitration Between
FIVE STAR PARKING,
EMPLOYER
AND
IBT LOCAL 728,
UNION
OPINION AND AWARD
PROCEDURAL BACKGROUND
The parties in this dispute are signatories to a
collective bargaining agreement dated August 1, 2002,
through July 31, 2008. The grievance filed by IBT Local
723, hereinafter referred to as the Union, on behalf of
all bargaining unit employees, alleges that Five Star
Parking, hereinafter referred to as the Employer/FSP
violated the terms of the Agreement.
The grievance was timely processed through the
grievance procedure, and a request was made to the New
or
22a
Appendix C
Jersey State Board of Mediation to submit a panel of
arbitrators. On January 3, 2005, the undersigned was
appointed arbitrator.
A hearing was held on May 4, 2005, at the offices of
the NJSBM. At the hearing, each party had a full and
complete opportunity to present evidence and testimony
on their behalf, to examine and cross-examine witnesses
under oath and to argue their respective positions.
Capable, competent counsel represented each party and
both parties elected to submit post-hearing briefs.
Due to business and personal circumstances, the
parties were granted extensions to submit their
respective briefs. Both briefs were received on June 22,
2005. The hearing was officially closed on June 27, 2005.
ISSUE
The parties stipulated to the following issue:
Did the Employer violate Article 20 and Schedule A
of the Agreement when on September 17, 2004, Five Star
Parking implemented a wage reduction? If so, what shall
be the remedy?
23a
Appendix C
RELEVANT CONTRACTUAL PROVISIONS
ARTICLE 4 -GRIEVANCE PROCEDURE
Section 1: Any controversy, claim, dispute or
grievance arising between the Company and the Union
or any Employee, involving or concerning the meaning,
interpretation, operation, or application of any clause of
this Agreement, or by a breach or threatened breach of
this Agreement, shall be settled in the following manncr:
(i) The arbitrator shall be limited to the
particular dispute in question and shall be
bound and governed by the provisions of this
contract and restricted to its application to the
facts presented to him involved in the
grievance. The arbitrator shall not have
jurisdiction or authority to add to, modify,
detract from, or alter in any way the provisions
of this Agreement or any amendment or any
supplement thereto.
ARTICLE 9- MANAGEMENT RIGHTS
Section 1: The management of the Company and the
discretion of the working force are vested solely and
exclusively in the Company and shall not in any way be
abridged except by specific restrictions as are set forth
in this Agreement.
Section 2: The Union recognizes that the
management of the Company’s business includes, but is
24a
Appendix C
not limited to, the assignment and direction of the
working force, the determination of the number and
qualifications of Employees to be employed or retained
by the Company, the right to hire, suspend, discharge,
discipline, promote, demote or transfer Employees, to
make operational improvement, to maintain reasonable
and proper discipline and the right to release Employees
because of lack of work or for other proper reasons are
vested exclusively in the Company. It is understood that
the Union does not waive its rights, under the grievance
procedure, to question any arbitrary action deemed
unjust. It is understood that a position or classification
of employment may be abolished.
Section 3: The Union recognizes that in
consideration of the commitments assumed by the
Company in this contract the management has, among
others, the right to require from all employees efficient
service in the performance of their dutics.
Section 4: The Union agrees that its officers, agents
and members shall not oppose or interfere, directly or
indirectly, with the legitimate or reasonable efforts of
the Company to train Employees, to improve the skill
and ability of the Employees, to make operational
improvement to maintain reasonable and proper
discipline and efficiency, and to make economic
improvements in the operation of its business.
Section 5: Management may do bargaining unit
work during meal periods, breaks or for training
purposes or emergencies, provided the manager uses his/
her own bank when in a cashier’s lane.
25a
Appendix C
Section 6: Employees may be required to perform
temporary work other than their primary jobs.
Employees must perform all such duties assigned to
them. When employees are assigned to perform a job in
a higher paying classification, the affected employee
shall receive the higher rate of pay for the day. When
employees are assigned to perform a job in a lower
paying classification, the affected employee shall receive
the higher rate of pay for the day.
Section 7: If at any time during the term of the
Company’s Agreement with the Port of New York and
New Jersey Authority to operate the parking facility
mentioned in Article 2 is terminated, Company shall have
the right to terminate the employment of all of the
Employees covered under this Agreement without
liability.
Section 8: The foregoing enumeration of
management rights shall not be deemed to exclude other
rights of management not specifically set forth, the
Company therefore retaining all rights not otherwise
specifically covered by this Agreement, irrespective of
whether or not the same have been heretofore exercised.
ARTICLE 12 -STRIKES AND LOCKOUTS
Section 1: During the term of this Agreement, the
Union will not strike (including sympathy strikes),
engage in work stoppages, slow down, picketing at or
near the Company’s premises. The Company during the
life of this Agreement, will not lock out any Employee.
26a
Appendix ©
ARTICLE 32 -TERM OF AGREEMENT
This Agreement shall become effective August 1,
2002 and shall remain in effect to and including July 31,
2008, and from vear to year thereafter unless notice of
desire to amend or terminate is given in waiting by one
party to the other sixty (60) days prior to the expiration
date of this Agreement. It is agreed, however, that as of
August 1, 2004, and August 1, 2006, this agreement may
be reopened by either party (upon sixty (60) days of
written notice) solely for the purpose of renegotiating
concerning wages and monetary fringe benefits, but for
no other purpose. It is further agreed that during such
periods of re-opener, the no strike, no lockout provisions
of this Agreement shall remain in full force and effect
as shall all other non-monetary terms and conditions
hereof.
SCHEDULE ‘A’
(Per Hour)
2(a) Future Pay Increases: For the period
commencing August 1, 2003 and continuing until July
31, 2004, all employees shall receive an across-the-board
increase in their respective personal hourly rates of pay
equal to three (3%) percent. It is agreed, however, that
the actual effective date shall be the first day of the first
period falling on or after August 1, 2003.
(b) In accordance with the provision of Article 12 of
this Agreement, this Agreement may be reopened by
either party as of August 1, 2004 and August 1, 2006,
27a
Appendix C
but solely for the purpose of negotiating concerning rates
of pay and other monetary benefits, but for no other
purposes, without exception.
SUMMARY OF FACTS
On August 1, 2002, the Employer became the
contractor for the New York/New Jersey Port Authority
(Port Authority) to manage parking lots and garages at
Newark Liberty International Airport. FSP’s
responsibility is to manage the parking lots and collect
revenues, which are submitted to the Port Authority.
Article 32, Schedule A of the Agreement indicates
that there would be a wage reopener effective August 1,
2004, and provides that either party could reopen the
contract upon sixty (60) days written notice for the
purposes of renegotiating wages and monetary benefits.
On June 18, 2004, counsel for the Union sent a letter
to counsel for FSP requesting a wage reopener. This was
introduced as Joint Mxhibit 4. On July 20, 2004, a meeting
was held concerning negotiations for the wage reopener.
Present for the Unicon were Union counsel, David
Grossman, Union Secretary-Treasurer, John Humphrey,
and Shop Stewards, Daisy Cruz and Ross Lynch.
Representing the Company was Allen G. Siegel, counsel
for the Employer, District Manager, Jermane Sahoe,
Regional Manager, Ken Oldum, and Operations Manager,
Michael Joseph.
28a
Appendix C
At that meeting, Mr. Siegel as the spokesperson for
FSP indicated that the Port Authority was about to
request bids for the parking lot manager at Newark
Liberty International Airport (NLIA). He further
indicated that the operational costs of FSP at NLIA were
greater than the budget that was being provided from
the Port Authority.
Another negotiation session was scheduled for
August 3, 2004. Mr. Siegel indicated that the Employer
was rejecting the Union’s wage reopener proposal. He
further indicated that FSP was operating at
approximately twelve percent (12%) over the budget that
they had received from the Port Authority.
Lisa Caldwell, who has been working at NLIA as a
cashier and is also a shop steward for the Union took
contemporaneous notes of the August 3, 2004 negotiating
session. Those notes were introduced as Union
Exhibit 1.
At the August negotiating session, Mr. Humphrey
indicated that the Union was not interested in
negotiating a recessive contract because that recessive
contract would be the starting point for a new bidder/
vendor. He suggested that negotiations be placed on hold
until sometime in late September 2004 so the parties
would know whether or not FSP had been selected by
the Port Authority to remain as the parking lot manager.
29a
Appendix C
Based upon the fact that the Employer was raising
an issue that its operating budget was higher than the
money received from the Port Authority, the Union
requested the financial data of FSP.
On August 13, 2004, Mr. Grossman sent a letter to
Mr. Siegel indicating that the Union was seeking FSP’s
financial information covering the period of January 1,
2002, through August 138, 2004.
Mr. Siegel responded that case law is legion that the
Employer is obligated to submit information only about
the facility in question. Therefore, the Employer,
through Mr. Siegel, indicated they would not comply with
any financial information beyond NLIA.
On August 26, 2004, the Union again reiterated its
request for the Employer’s financial information.
On August 27, 2004, Mr. Siegel (see Joint Exh. 11)
indicated, “The Company Is not pleading an inability
to pay. However, the Company is no longer willing to
sustain the cumulative losses that it is experiencing at
Newark”. In order to curtail these unreasonable losses,
the Company proposed and is again proposing an
across-the-board reduction of twelve and one half
percent (12'2%) in all of the wage rates and other
monetary items that are within the scope of the pending
reopener, be made effective as of the first day of the first
pay period falling on or after September 1, 2004.”
30a
Appendix C
Mr. Siegel indicated that, this proposal was made to the
Union at the August 3, 2004, meeting and again in his
letter to Mr. Grossman of August 5, 2004.
Mr. Siegel further indicated, “/fthe Union continues
to insist upon conditioning negotiations upon receiving
financial information that it is not by law entitled to,
and declines to resume negotiations on September 3,
2004, a date offered by the Union, the Company will
deem the parties to be at an impasse. Accordingly, it
will be free to implement unilaterally its pending and
oft repeated proposal lo reduce rates of pay, and all other
monetary items encompassed by the reopener, effective
with the first day of the first pay period on or after
September 1, 2004, by twelve and one half percent
(121%) across-the board.”
Mr. Siegel indicated that he urges the Union to bear
in mind that the Agreement does not give the Union the
right to strike. Moreover, “The Union’s continued
insistence upon being given financial information that
it is not entitled to, as a condition of meeting, constitutes
a violation of Section 8(b)(3) ofthe NLRA. The Company
has no desire to engage in any dispute with the Union,
and has made every good faith effort to avoid such a
confrontation. Regrettably, the Union does not appear
to share this sentiment.”
On September 1, 2004, Mr. Grossman wrote to Mr.
Siegel and indicated that the Union’s notice given for
the wage reopener was defective. The Union withdrew
its request for the reopener (see Joint Exh. 14) and
3la
Appendix C
indicated that it intended to file an unfair labor practice
charge with the NLRB and file for arbitration, if FSP
unilaterally implemented a wage reduction.
On September 2, 2004, Mr. Siegel sent a letter to
Mr. Grossman indicating that the parties were at a
bargaining impasse. (See Joint Exh. 14).
On September 17, 2004, the Employer implemented
a twelve and one half percent (122 %) reduction in wages
only. It did not reduce everyone’s wages. The wage
reduction was effective for the pay period beginning
September 5, 2004. FSP only reduced wages for
employees making more than $9.00 per hour.
On September 21, 2004, the Union submitted a
grievance concerning the unilateral implementation of
the wage decrease without bargaining. (See Joint Exh.
2).
These are the essential uncontroverted facts in the
matter at bar and the issue now comes to me for
resolution.
POSITIONS OF THE PARTIES
For the Employer
The Employer boldly asserts that “The grievance
should be dismissed as there 1s no award that the
arbitrator could issue in this matter that would ‘draw
its essence’ from the Agreement.”
32a
Appendix C
The Employer takes the position that the grievance
does not rise under the Agreement. The grievance form
on its face asserts that the grievance arises because the
parties were at a lawful bargaining impasse. In other
words, the Employer contends that the arbitrator is not
being asked to apply or interpret the parties’ collective
bargaining agreement, but rather to interpret and apply
the National Labor Relations Act.
The Employer also contends that impasse is a legal
term that is interpreted and applied by the NLRB unless
an arbitrator is given contractual authority to rule on
that subject matter. Such is not the case here.
The Employer contends that, “The correct, 7f not
legally mandated, resolution of this matter 2s for the
arbitrator to dismiss it.” The Employer takes that
position because it was made manifest by the Union itself
when it framed the issue to be resolved by the Arbitrator.
The Employer argues that they stipulated to the issue
as presented by the Union and offered no objections.
From the outset, it should be emphasized that the
gravemen of the Union’s grievance is that FSP
implemented the wage reduction “without impasse in
negotiations.”
The Employer strongly argues that “whether an
impasse existed or not, is not a matter of contract
interpretation, rather it is a matter addressed to the
National Labor Relations Act, Section 8(a)(5) to be
interpreted by the National Labor Relations Board.”
33a
Appendix C
The Employer argues that the language of the
Agreement at Article 4, Section 1 establishes that, “Any
controversy, claim, dispute or grievance arising between
the Company and the Union or any employee, involving
or concerning the meaning, interpretation, operation
or application of any clause of this Agreement or by a
breach or threatened breach of this Agreement, shall be
settled in accordance with the contracted grievance
procedure, which procedure includes arbitration.”
However, the Employer contends that the arbitration
provision precludes the arbitrator from addressing the
issue stipulated to by the parties. The Employer
contends that the language of the Agreement at
subsection 1(i) indicates that, “The arbitrator shall be
limited to the particular dispute in question and shall
be bound and governed by the provisions of this contract
and restricted to its application to the facts presented
to him involving the grievance. The arbitrator shall not
have jurisdiction or authority to add to, modify, detract
from or alter in any way the provisions of this
Agreement or any amendment or supplement thereto.”
FSP argues that there is no reference in the
Agreement to impasse or to any authority granted to
the arbitrator to apply or interpret the law that is applied
in cases of impasse. The Employer argues that it is not
uncommon for parties to a collective bargaining
agreement to grant to an arbitrator the authority to
interpret or apply the law or matters outside the four
corners of the parties’ Agreement. However, that was
not done in this case.
34a
Appendix C
Moreover, the grievance submitted by the Union as
Exh. J-2 does not require the Arbitrator to interpret any
provisions of the Agreement. It simply asked him only
to interpret the National Labor Relations Act and
specifically Section 8(a)(5) thereof and to assess conduct
in that framework alone.
The Employer strongly argues that all of the conduct
involved in the instant matter occurred outside the
Agreement. Moreover, should the arbitrator award the
Union any relief, he would be engaging in interest
arbitration, which he manifestly cannot do without the
consent of the parties.
On April 20, 2004, Mr. Siegel submitted a motion for
the instant matter to be dismissed, or in the alternative,
that there be a summary award in favor of FSP.
On April 25, 2005, the undersigned wrote to
Mr. Siegel with a copy to Mr. Grossman stating in part
that, “J am not willing to be liberal and grant your
motion based upon an ex parte partial record. At the
hearing scheduled for May 4, 2005, you certainly have
the right to amplify your extensive documentation.
Moreover, the Union must be given an opportunity to
present its case in chief and quite possibly refute your
arguments. Accordingly, your motion to dismiss the
instant matter is denied as is your motion for summary
judgment.”
The Employer argues that any arbitration award
must draw its essence from the Agreement. This
35a
Appendix C
principle and its vitality are not novel and FSP
references the seminal U.S. Supreme Court decision in
Steelworkers v. Enterprise Wheel and Car Corp., 363
U.S. 593 (1960) in which the court said, “An arbitrator
is confined to interpretation and application of the
collective bargaining agreement; he does not sit to
dispense his own brand of industrial justice. He may,
of course, look for guidance from many sources, yet his
award is legitimate only so long as it draws it essence
from the collective bargaining agreement. When the
arbitrator’s words manifest an infidelity to this
obligation, courts have no choice but to refuse
enforcement of the award.”
The Employer argues that at the outset of the
hearing, the Union urged the Arbitrator to consider the
issue of the Union’s failure to comply with Section 8(d)
of the NLRA. In other words, the Union is asking for
relief because it did not comply with Section 8(d) and,
therefore, FSP as well, did not comply with Section 8(d).
Thus, the Union argues that there is no valid reopener.
The Employer contends, “This is an astounding
contention in light of the fact that the Union is urging
relief based on its own non-compliance with the statute.
In essence, the Union is contending that it should be
allowed to benefit from its own mistakes.”
The Employer argues that case law developed by
the NLRA and the Court of Appeals established that
the burden of complying with Section 8(d) rests
exclusively with the party initiating negotiations and that
the other party is not similarly obligated. “Jt is
36a
Appendix C
undisputed that it was the Union that commenced the
bargaining process and, thus, it Is clear that the Union
cannot now complain or seek comfort from the fact that
neither it nor FSP may have technically complied with
the provisions of Section 8(d).”
“The Employer contends that this is the identical
contention made to the NLRB when the Union filed
Section 8(a)(5) and (1) charges against FSP. Those
charges were, at the request at the NLRB, withdrawn
in lieu of dismissal.”
Moreover, the issue of impasse is equally apposite
for this contention since the arbitrator would not be
interpreting the Agreement or the conduct of the parties
in applying the Agreement, but would, rather, be
interpreting and applying the National Labor Relations
Act. “This authority is not granted to the arbitrator by
the agreement or the parties. Hence, no award based on
Section 8(d) could possibly draw its essence from the
Agreement.”
The FSP argues, “Assuming, arguendo, that the
arbitrator could decide the issue of impasse, the
undisputed facts established that such an impasse’ was
reached by the parties.”
The Employer argues that the record contains all of
the correspondence of parties and Minutes of the two
bargaining sessions. The Employer argues that the
charges filed by the Union with the NLRB were
withdrawn by the Union because the withdrawal was
37a
Appendix C
requested by the Board in lieu of dismissal. “Jn any
event, it is obvious that the Board, on the facts in the
record here, declined to issue a complaint or initiate
any proceedings against FSP in connection with the
wage reduction.”
The Employer contends that while the NLRB was
making its investigation, the agent assigned contacted
Mr. Siegel and stated that the Unions charges were
based essentially on two grounds: (1) FSP did not comply
with the provisions of Section 8(d) requiring various
notices attendant to contract negotiations; and (2) FSP
failed and refused to give the Union its company-wide
financial statements, though FSP readily agreed to give
such information limited to its operations at Newark
Airport and its relationship with the Port Authority of
New York and New Jersey.
The Employer argues that, “Jn advance of the
arbitration hearing convened on Wednesday, May 5,
2005, in its motion to dismiss papers, the Employer
submitted voluminous exhibits and arguments in
support of its position that there was indeed and in law
a bargaining impasse that allowed the Employer to
institute its last and final ‘offer’ to reduce wages by
twelve and one half percent (12'42%).”
The Employer contends that it was the Union’s
position in its refusal to engage in good faith negotiations
that led to the instant issue because the Union
conditioned further bargaining sessions on receiving
company-wide financial statements.
38a
Appendix C
At the hearing of May 4, 2005, the Employer
contends that the Union made a new and fanciful
contention that must be addressed and refuted. The
Union contended anew that FSP was not legally
permitted to institute its last and final offer because
there was an alleged agreement at the negotiating
meeting of August 3, 2004, to the effect that the parties
would maintain the status quo pending further
negotiations following the decision made by the Port
Authority as to the identity of the parking operator
following its bidding process.
The Employer strongly argues that it should be
immediately born in mind that this contention on its face
is absurd. The record reflects that there was undisputed
testimony that the bidding process would take at least
six months, and the Employer was sustaining a direct
cash loss of at least $100,000.00 per month out of its own
pocket. It is illogical and bizarre to think that the
Employer would have agreed to continue this stiff cash
loss of nine more months and incur an; “ditional loss of
close to $900,000.00.
The Employer strongly contends that the “whole
purpose for proposing the wage cut was to curtail these
gigantic cash losses.”
The Employer contends that, “To substantiate ils
position, the Union proffered two employee witnesses,
both shop stewards. One witness claims that she made
contemporaneous notes, which were admitted into
evidence. The Employer suggests that these Minutes
39a
Appendix C
were either inauthentic or were not made
contemporaneously. This conclusion is manifest by
several factors:
(1) Management notes are consistent and
unambiguous as well as largely undenied.
The notes of management were kept by the
undersigned counsel and were promptly
transcribed following the negotiation
SESSIONS;
(2) The Union’s witnesses, to be
charitable, were vague with virtually no
recollection of anything else that was said at
the meeting.”
On cross-examination “both witnesses frequently
admitted that they could not remember any of the
critical or material content of the discussions that
occurred at the meeting. The most frequent responses
were ‘I don’t know or I don’t remember’. They only
remember the single report that was the basis for the
Union’s newest assertion concerning the agreement for
a negotiating hiatus that would have generated an
additional cash loss of at least $900,000.00. On the other
hand, FSP submitted its notes of the meeting which
directly contradict the Union’s position; notes that were
maintained by counsel.”
Moreover, FSP witness Kenneth Oldum, the
Company’s Regional Manager, who was present at the
negotiations, had clear and unambiguous recollection of
the comments that were made.
40a
Appendix C
Furthermore, assuming arguendo, that such an
agreement was in fact made, it is black letter law that
there is no enforceable agreement on any single issue
unless and until there is an agreement on the entire
package or a lawful impasse. Ilence, “F'S?’ was
empowered to withdraw the alleged agreement that the
parties wait until the Port Authority completed the bid
process, because an impasse was eventually reached that
did not include that alleged understanding. It is
familiar law that the duty to bargain in good faith does
not mean that agreement must be reached.”
The Employer argues that when bargaining to
impasse fails to produce an agreement on a particular
matter, management is allowed to take unilateral action
consistent with its proposal in bargaining.
The Employer contends that in numerous
communications with Mr. Grossman, FSP told the Union
that it was interested unconditionally in continuing the
bargaining and finding some solution to their impasse.
The Union adamantly refused all such entreaties unless
and until FSP provided to the Union the financial
statement of the Company at large. This was stated as a
condition precedent to any meeting. Nevertheless,
another meeting was indeed scheduled for September
3, 2004, in a last-ditch effort to reach an accommodation.
The Union summarily canceled this meeting and
repeated its refusal to meet in the absence of the
I;mployer’s company-wide financial information to which
it was not entitled.
4la
Appendix C
The record clearly and unequivocally reflects that
FSP’s agreement to continue negotiations at the
September 3™ meeting was unconditional.
The Employer argues that this course of negotiations
established that the parties were clearly at impasse. The
testimony and documentation in the record amply
demonstrates that the impasse in fact did exist.
The Employer argues that the issue of impasse is
significantly impacted, if not disposed of by the Union’s
insistence on being supplied with the overall company-
wide financial statements of FSP.
As indicated and argued in the FSP motion to
dismiss, the Union is not entit'ed to financial statements
at all unless the Employer pleads poverty or an inability
to pay. The record clearly and unequivocally establishes
that this is not the case and the Employer has never
said that they had an inability to pay. “They specifically
said that they were over the budget within NLIA and
they needed to make a reduction of twelve and one half
percent (124%) on all wages and monetary benefits as
established in the wage reopener in the Agreement.”
The Employer argues that if special circumstances
exist, the Union has the right to demand further financial
information from the Employer. Here, there has been
no showing that any special circumstance existed. In
other words, the Union is attempting to boot strap its
request for financial information about the NLIA facility
and review the Employer’s company-wide financial data.
42a
Appendix C
The Employer contends that based on the largely
“undisputed record evidence and exhibits submitted
into evidence, it is manifest that this case addresses only
statutory interpretation and that respectfully, the
arbitrator has not been granted authority under the
parties’ Agreement to construe the statutory law, bul is
restricted to the controversy arising out of the
Agreement itself. Moreover, assuming arguendo that the
arbitrator can determine the issues of impasse and are
in compliance with NLRA’s Section 8(d), the largely
undisputed record evidence and authorities establish
that there was a lawful impasse.”
Accordingly, the Employer asks that the grievance
be dismissed in its entirety.
For the Union
The Union argues that the grievance submitted on
September 21, 2004, on behalf of all bargaining unit
members is arbitrable. The Agreement between the
Union and the Employer contains a very broad grievance
and arbitration clause.
Article 4, Section 1 specifically provides:
“Any controversy, claim, dispute or
grievance arising between the Company and
the Union or any employee involving or
concerning the meaning, interpretation,
operation or application of any clause of this
Agreement, or by a breach or threatened
43a
Appendix C
breach of disagreement, shall be settled in the
following manner...”
Considering the breadth of the grievance clause,
which includes alleged breaches of the collective
bargaining agreement, the arbitrator is empowered to
devermine arbitrability and determine that this
grievance concerning a unilateral implementation of a
wage decrease was a breach of the collective bargaining
agreement.
In support of this position, the Union references U.S.
Supreme Court decision United Steelworkers of America
v. Warroor Gulf Navigation Co., 363 U.S. 574, 582-583,
880 S.Ct. 1347, 4 L.Ed.2d 1409 (1960) which states:
“In order to arbitrate, the particular
grievance should not be denied unless it can
be sard with positive assurance that the
arbitration clause is not susceptible of an
interpretation that covers the asserted
dispute. That should be resolved in favor of
coverage. Absent an express provision
excluding a particular grievance from
arbitration or the most forceful evidence of a
purpose to exclude the claim ... the matter
should go to arbitration.”
The Union asserts that arbitration is the quid pro
quo for not being able to strike during the wage reopener
44a
Appendix C
period. The Union argues that the language of the wage
reopener found in Article 32 specifically states that:
“It is further agreed that during the
periods of the reopener, the no-strike, no-
lockout provisions of this Agreement shall
remain wn full force and effect as shall all
other non-monetary terms and conditions
thereof.”
In the normal case where there is a wage reopener,
at the conclusion of negotiations and impasse is reached,
the Union would then be free to engage in a strike.
However, based upon the above-referenced language, the
Union was not able to engage in a strike because a
no-strike clause remained in effect during the period of
the reopener.
The Union’s letter of September 3, 2004, indicated
that it “believed that it had the right to strike at the
implementation of the wage decrease. The Union
contends that the Employer’s argument is misplaced
that they would be precluded from engaging in a strike
when the Company implemented its wage decrease.”
The Union contends that the guid pro quo for any
no-strike or no-lockvut provision is arbitration, which
clearly places the instant dispute within the arbitrator’s
jurisdiction to determine the appropriate wage reopener.
The Union argues that the fact that it filed an unfair
labor practice with the National Labor Relations Board
45a
Appendix C
concerning the Employer’s unilateral implementation of
the wage decrease and then subsequently withdrew
same, does not constitute a waiver or an estoppel of
arbitration.
The Union contends that the filing of an unfair labor
practice charge against the Employer does not abrogate
the right of arbitration of a dispute under a collective
bargaining agreement.
The Arbitrator has jurisdiction over a grievance
relating to the amount of wages due employees under
alleged promise by the Employer, despite the fact that a
charge of a violation of the NLRA by the Employer was
filed with the NLRB, where the Board has dismissed
the charge on the ground that the alleged violation
occurred more than six (6) months prior to the filing of
the charge; moreover, the subject of the dispute involves
an issue that by its nature does not fall peculiarly within
the province of the NLRB.
The Union contends that when a “Union files with
the NLRB with a claim that an Employer has refused
to bargain a mandatory subject of bargaining, the
normal practice of the NLEB is to defer the matter to
arbitration. The Union argues that most parties, in the
interest of settling their dispute as speedily and
efficiently as possible, choose to by-pass the NLRB and
place the matter before an Arbitrator.”
The Union references a series of cases where
arbitrators have determined that an employer has
46a
Appendix C
breached the collective bargaining agreement by
unilaterally implementing a change to a mandatory
subject of bargaining.
The Union strongly argues that the “E’mployer
failed to bargain in good faith, improperly declared
impasse and improperly implemented a wage reduction
in bad faith. The Union argues that they are not asking
the Arbitrator to find that the Company engaged in a
violation of the NLRA, they willingly concede that is
within the exclusive jurisdiction of the NLRB. However,
even though a matter may be deemed to be an unfair
labor practice charge within the scope of the NLRB, the
Arbitrator has the authority to address a unilateral
implementation concerning a mandatory subject of
bargaining that is part of the collective bargaining
agreement.”
The Union agrees the Arbitrator must first turn to
the Agreement itself. However, the Arbitrator may refer
to external law to supplement if contract ambiguities or
uncertainties arise. Bad faith in bargaining must be
inferred from a party’s conduct at or away from the
bargaining table. The Union argues that it is well settled
that unilateral decisions made by an Employer during
the course of a collective bargaining relationship
concerning matters that are mandatory subjects of
bargaining are regarded as per se refusals to bargain.
The Union references the fact that the duty to
bargain in good faith does not mean that an agreement
must be reached. In citing NLRB cases developing labor
47a
Appendix C
law and other citations, the Union agrees that where
bargaining to impasse fails to produce an agreement on
a matter, management is privileged to take unilateral
action consistent with its proposals in bargaining. To that
extent, the “Union contends that the existence or non-
existence of impasse is normally put in issue when, after
negotiations have been carried on for a period of time,
the positions of the parties become fairly fixed and talks
reach a point of stalemate. Therefore, before an employer
may lawfully make unilateral changes, impasse must
exist. Impasse, according to the Union, occurs after
good-faith negotiations have exhausted the prospects of
concluding an agreement.”
In the matter at bar, at best, the parties met for two
(2) hours. There was a meeting on July 20, 2004, wherein
the Union gave its proposals. There was a meeting on
August 3, 2004, wherein the Employer rejected the
Union’s proposal and discussed items, including a need
to reduce costs, but made no counter-proposal.
The Union strongly argues that it was the consensus
of both Local 723 and FSP that negotiations be held in
abeyance until mid-September to find out whether FSP
would have continued in the bid as the contract for the
parking services at NLIA. In support of this, the Union
references the testimony of Mr. Oldam, the Regional
Manager of FSP who specifically testified that he
anticipated negotiations to be face-to-face. Additionally,
he admitted that FSP did not make a counter-proposal
at the August 3, 2004, meeting, that he anticipated that
48a
Appendix C
the next meeting would be face-to-face negotiations in
mid-September of 2004.
The Union argues that Instead of that occurring,
counsel for the Employer, through correspondence,
attempted to negotiate a wage reduction of twelve and
one half percent (124%%) on all monetary benefits. The
Union refused to bargain via correspondence. Moreover,
the Union demanded financial information, which FSP
refused to provide.
Regardless of how this matter is viewed, the Union
strenuously argues that there was no bargaining
concerning the Company’s twelve and one half percent
(122%) counter-proposal.
The Company, by letter dated September 2, 2004,
declared an impasse, even though there was no
bargaining. The Company then, on September 17, 2004,
implemented a twelve and one half percent (12%%)
reduction on wages only. That was not what the Company
proposed. The Company only impacted those employees
who were making more than $9.00. That was not
proposed. The wage reduction that FSP implemented
on September 17, 2004, was greater than the wage
increase that they had provided to the employees for
their collective bargaining agreement for the first two
(2) years of the collective bargaining agreement. In fact,
it reduced the wages below the rates that were
established when FSP came into the facility in August
of 2002.
49a
Appendix C
The Union contends that FSP improperly declared
impasse on this matter and unilaterally implemented the
wage reduction.
Additionally, the Union argues that FSP has engaged
in bad faith bargaining and implemented the wage
reduction in bad faith.
The Union argues that the notice sent to the
Employer on June 18, 2004, for a reopener for August 1,
2004, was not within the sixty (60) day notice as
established in Article 32 of the Agreement. The Union
contends, “/t is a maxim of contract interpretation that
the language which is clear and unequivocal must be
given effect even though the parties may disagree as to
its meaning. The parties to a contract are charged with
full knowledge of its provisions and the significance of
its language. Thus, unambiguous language must be
enforced even if the result is contrary to the expectation
of one of the parties.”
The Union argues that their notice was defective and,
furthermore, no notice was provided to either the New
Jersey State Board of Mediation or the Federal
Mediation and Conciliation Service. Clearly, the notice
was defective and negotiations for reopener should not
have occurred.
The Union argues that the grievance was timely filed
and that arbitrators have held that one cannot expect to
file a grievance until one is aware of the action upon
which the grievance is based. In this respect, the Union
50a
Appendix C
argues that a party sometimes announces its intention,
“To do a given act, but does not do so or culminate the
act until a later date. In such situations, arbitrators
have held that the occurrence, for purposes of applying
the time limits, is the date upon which the action is
actually taken.”
The Union argues that even though there were
announcements in the correspondence of August of 2002
of F'SP’s intent to reduce monetary benefits by twelve
and one half percent (12'2%) across-the-board, it is not
until September 17, 2004, when they actually reduced
the wages. At that point in time the incident occurred
giving rise to the filing of the grievance.
The Union argues that the Employer had ample
opportunity to challenge arbitrability through the
grievance steps but did not do so until the hearing. While
there is no specific contract language on this point, the
Union contends that it is “a well-established principle
in similar circumstances that the failure to raise the
arbitrability issue until the hearing is a waiver of that
argument. The Union argues that most arbitrators rule
that a Company’s failure promptly to object to the lack
of timeliness, and indeed the Company going forward
with the grievance procedure amounts to a waiver of
the procedural time requirements.” Thus, any argument
concerning arbitrability or untimeliness must be deemed
waived because it was not raised prior to the hearing.
The Union argues that the instant matter should be
deemed a class action in a continuing grievance. The
Sla
Appendix C
grievance was filed on behalf of the entire bargaining
unit that was affected by this wage decrease, except for
those who are making $9.00 or less as new hires. The
Union contends that the wage decrease implemented was
discriminatory because it only impacted upon those
Union members who were employed with FSP when the
original collective bargaining agreement was negotiated
in August of 2002. Moreover, the Union strongly argues
that FSP never proposed to impact only those wage
earners making more than $9.00 per hour. The
Employer’s proposal was an across-the-board decrease
for all members of the bargaining unit.
The Union argues that the matter at bar is a
continuing grievance. It is the Union’s position that
every day that FSP continues to pay the decreased wage
rate, it is violating the collective bargaining agreement.
Thus, the grievance is a continuing grievance. The Union
argues that the instant matter applies to all affected
employees, who were, or are, employed by FSP from
September 5, 2004 to the present.
The Union contends that the Arbitrator has a
remedial authority to grant damages. The Union
suggests that cmpowering the Arbitrator to resolve
disputes, the parties are generally considered to have
given authority to grant adequate monetary relief for
contract violations where the Arbitrator finds the
gricvance has merit, even though the contract does not
specifically authorize that remedy.
52a
Appendix C
Monetary damages in arbitration normally
correspond to specific monetary losses. Make whole
awards may include recovery of lost wages.
Compensatory awards have also been used where an
employer unilaterally institutes changes to the terms and
conditions of employment or in the benefits established
by the Agreement, or where an employee improperly
subcontracts or contracts out bargaining unit work.
The principle that empowered the “Arbitrator to
resolve disputes cloaks the Arbitrator with the authority
to make the aggrieved party whole has been well
established by arbitrable precedent as far back as 1974.
To restrict arbitrators to remedies specifically set forth
in a contract would negate arbitration as a method of
dispute settlement or result in cluttering contracts with
numerous liquidated damage provisions that would
invite more trouble than they would prevent. Even
though the contract is silent, the arbitrator has the
authority to award monetary damages to employees for
F'SP’s breach of the Agreement.”
The Union contends that the Employer’s transcribed
notes from the July 20, 2004, meeting and the August 3,
2004, meeting must be dismissed. There was no tape
recording in the negotiations conference room to the
Union’s knowledge. The Union did not authorize a tape
recording at the negotiation sessions. The idea that there
are notes that are being transcribed is disturbing to the
Union.
S3a
Appendix C
The Union argues that the Employers counsel has
submitted his notes as part of its motion to dismiss.
“Those notes do not indicate whose notes they are and
they do not indicate that they were made
contemporaneously. There was no testimony offered at
the hearing concerning the notes. There was no motion
by FSP during the hearing for the admission of those
notes as evidence.”
The Union contends that while the “Arbitrator has
great leeway regarding granting applications for
submission of evidence — it is clear that without any
foundation laid as to who took the notes, whether or not
they were made contemporaneously, and how they were
transcribed and from what — questions are raised as to
the content and accuracy of the information and
statements contained in those notes. The Union argues
that the notes submitted are merely self-serving
statements that could have been created long after the
actual meetings. Moreover, the actual notes were not
produced to verify the accuracy of the transcribed notes.
Accordingly, the Union objects to those transcribed notes
of the negotiating sessions.”
By way of relief, the Union asks that the grievance
should be granted in its entirety. FSP should be ordered
to immediately cease and desist from paying the
decreased wage rate, which became effective September
17, 2004. All employees’ wages that were affected,
including those employees who have left employment
since the effective date, should be restored to the rate
they were prior to September 17, 2004. The Arbitrator
54a
Appendix C
should award back pay to each of these employees for
the full amount from September 5, 2004, to the date that
FSP actually gives the employees the award of back pay.
The Arbitrator should order interest on the back pay
amounts.
It is specifically requested that the Arbitrator retain
jurisdiction should there be a dispute concerning the
calculation of the back pay award and who may be
entitled to same.
DISCUSSION AND OPINION
As is typically the case in an issue that deals with
contract interpretation, both parties insist that the
language is clear and unambiguous, but disagree as to
the meaning of that clear and unambiguous language.
In the instant matter, the Employer has raised the
issue that the Arbitrator is being asked to interpret and
apply the NLRA. In that context, FSP argues that under
the terms of the Agreement the Arbitrator is not
authorized to rule on that subject matter. Accordingly,
the Employer strongly argues that the Arbitrator cannot
issue an award that would draw its essence from the
Agreement.
To determine if the Agreement grants the Arbitrator
any authority in the instant matter, it is necessary and
appropriate to review the definition of a grievance as
found in Article 4, Section 1. That provision states:
Sa
WF
Appendix C
“Any controversy, claim, dispute or
grievance arising between the Company and
the Union or any employee, involving or
concerning the meaning, interpretation,
operation or application of any clause of this
Agreement, or by any breach or threatened
breach of this Agreement shall be settled in
the following manner...”
Additionally, Section 1(i) states:
“The Arbitrator shall be limited to the
particular dispute in question and shall be
bound and governed by the provisions of this
contract and restricted to its application to
the facts presented to him involved in the
grievance. The Arbitrator shall not have
jurisdiction or authority to add to, modify,
detract from or alter in any way the
provisions of this Agreement or any
amendment or any supplement thereto.”
The Employer raises a novel argument that since
the word impasse does not appear in the collective
bargaining agreement and that the parties have not
granted the Arbitrator any authority to apply or
interpret the law that is applied in cases of impasse, the
instant grievance must fail. The Employer has a high
degree of comfort in espousing that position and pursued
that argument throughout its motion to dismiss as well
as in its post-hearing brief. However, a careful review of
case law and the particular language in the Agreement,
56a
Appendix C
clearly establishes that that comfort level has a short
life expectancy.
The continued vitality of the Employer’s argument
concerning the Arbitrator’s authority in the instant
matter has been set aside by two cases decided by the
United States Supreme Court. The first case, which is
the seminal case within the Steelworkers trilogy,
Steelworkers v. Enterprise Wheel and Car Corp., supra,
clearly states the following:
“An arbitrator is confined to
interpretation and application of the
collective bargaining agreement; he does nct
sit to dispense his own brand of industrial
justice. He may, of course, look for guidance
from many sources, yet his award is
legitimate only so long as it draws its essence
from the collective bargaining agreement.
When the arbitrator’s words manifest an
infidelity to this obligation, courts have no
choice but to refuse enforcement of the award.”
The second case is Alexander v. Gardner/Denver Co.,
415 U.S. 36 (1974), wherein the Court, citing the trilogy
observed (415 U.S. 36 at 53-54):
“If an arbitrable decision is based solely
upon the arbitrator's view of the requirements
of enacted legislation, rather than on an
interpretation of the collective bargaining
agreement, the ‘arbitrator has exceeded the
S7a
Appendix C
scope of the submission’ and the award will
not be enforced. Thus, the arbitrator has the
authority to resolve only questions of
contractual rights, and this authority
remains regardless of whether certain
contractual rights are similar to, duplicative
of, the substantive rights secured by statute.”
The language of the grievance procedure referenced
above speaks of a breach or threatened breach of this
Agreement, and restricts an arbitrator to apply the
Agreement to the facts in evidence clearly are
controlling factors in the instant matter. (emphasis
supplied)
Those highlighted words clearly mean that any
action taken by the Employer with respect to any
language in the Agreement or the application and
interpretation of any language in the Agreement is a
grievable matter subject to binding arbitration. In the
instant matter, the facts presented to me as defined in
Article 4, Section 1(i) clearly and unequivocally establish
that I must review all of those facts to determine whether
or not the contract has been violated. Regardless of the
argument advanced by the Employer, I have the
contractual authority, as set forth by two United States
Supreme Court decisions, to determine whether or not
the contract has been violated in the instant matter.
In fact, at page 3 of its post-hearing brief, in
paragraph 3, the Employer states, “Rather, he is solely
bound and governed by the provisions of the
58a
Appendix C
Agreement.” The determination I reach in the instant
matter is governed by the definition of a grievance and
the facts presented to me as defined within the grievance
procedure.
The gravemen of the Union’s argument is that the
Employer unilaterally implemented a twelve and one half
percent (124%) wage reduction. All other issues of a
statutory nature are not before me. Any argument raised
as to whether or not the reopener was defective or not
properly submitted is irrelevant to the proceedings
before me. My only determination will be whether or
not the contract was violated.
At the July 20, 2004, negotiating session, the Union
submitted its wage reopener proposals in accordance
with Article 32. Those proposals included a dollar per
hour increase each of the remaining years of the
Agreement, a reinstatement of the wage progression
frozen in the second year of the Agreement, health,
welfare and pension increases.
On August 3, 2004, the Employer rejected that
proposal and explained its financial circumstances to the
Union. On August 9, 2004, the Employer sent a three-
page letter to Mr. Grossman in which they indicated their
financial circumstances. They also proposed to reduce
the costs associated with the collective bargaining
agreement by a minimum of twelve and one half percent
(124%).
59a
Appendix C
The Union has the right to demand financial
information based upon the position advanced by the
Employer. The Employer argues that they do not have
an inability to pay, but their circumstances at NLIA are
at such a nature that they cannot continue to sustain a
loss of over $1,000,000.00 per year. Moreover, the
Employer strongly argues that they never agreec to hold
negotiations in abeyance until it was determined if they
would receive the bid to be the manager for the parking
lots at NLIA.
The Union claims that the Employer did agree to
hold negotiations in abeyance. Unfortunately, there is
no written document to offer credence to either position
that the Employer refused to hold negotiations in
abeyance or, in fact, did agree to hold negotiations in
abeyance. Therefore, the only thing that I can look at is
the fact pattern that is before me.
The Union argued that the Employer did not
implement Its proposal of a twelve and one half percent
(12'%%%) decrease across-the-board for all wage rates, and
that way only reduced the wages of employees making
more than $9.00 per hour.
To that extent, the Union has a valid point. If the
wage reduction proposal of the Employer was for all
wage rates as referenced in its October 9, 2004, letter to
Mr. Grossman, then reducing the wage rate of those
making more than $9.00 per hour was disingenuous at
best. Moreover, I find it extremely difficult to accept the
60a
Appendix C
Employer’s argument that an impasse existed after
approximately two, maybe three, hours of bargaining.
If the Employer believed that the Union exceeded
its request for financial information, then the Employer
had legal avenues to appeal that position of the Union.
Logic dictates that if the Union agreed to the Employer’s
proposal of a twelve and one half percent (122%) across-
the-board wage reduction and subsequently FSP lost as
the operator of the parking lots at NLIA, the Union
would have been in a very precarious situation. I fully
agree that the Union would not have accepted that type
of position if they did not know whether or not ISP was
going to continue to be the operator of the parking lots
at NLIA.
Based upon all of the evidence and voluminous
documentation presented by both parties, I am not
convinced that an impasse existed. The fact that the
Union would not agree to the Employer’s wage proposal
of a twelve and one half percent (12'2%) reduction in the
wage rates does not mean that an impasse existed. It
means that the Employer had a financial situation that
they were trying to stop the hemorrhaging, but they
were then required to give information to the Union. The
Employer only gave infcrmation to the Union for NLIA.
Whether they are required to give any information
beyond that is not for me to determine. What is for me
to determine is whether or not the Employer’s action of
implementing a wage reduction breached the collective
bargaining agreement.
6la
Appendix C
Based on the facts in evidence, there is no question
that the Employer’s action of September 17, 2004, in
reducing employer’s wages was violative of the collective
bargaining agreement. The Union asserted that the wage
reducticn impacted only those employees making more
than $9.00 per hour. There is no testimony in the record
to substantiate that position. However, for the purpose
of my Award it does not make any difference if the
Employer’s wage reduction was for employees making
$7.00 per hour, $9.00 per hour or $10.00 per hour. The
simple fact is that they reduced cmployees’ wages
without negotiations.
Think of the enormity of the instant matter. The
Union proposes in accordance with the wage reopener
specific proposals of an economic nature. Subsequently,
the Employer makes a counter-proposal of a wage
reduction. Quite frankly, that is nothing new, novel or
unique in labor relations in the United States. Any
Employer will be asking for wage reductions,
concessions, and rollbacks. That is exactly what has been
occurring for the last 10 or 15 years, especially in the
areas of health insurance. Emnloyers are constantly
asking for concessions or rollbacks.
When an employer proposes a wage reduction that
is agreed to by a Union that is a concession.
Concessionary bargaining produces some interesting
results. However, in the instant matter, the Employer
never allowed the negotiations process to really move
forward or to pick up steam to see where they could reach
some type of common ground. They simply said, we will
62a
Appendix C
not give you the additional financial information you are
asking for, and if you do not show up for the September
3, 2004, negotiating session we are declaring an impasse.
Accordingly, they declared the impasse and reduced the
wages of the employees.
That is the most contorted definition of negotiations
I have ever heard. The negotiations process is a give
and take process. It is a fascinating process that has ups
and downs, hills and valleys, but one that reaches
resolution of the issues to be negotiated. Typically, in
the private sector, when the employer takes the type of
action as presented in the instant matter, Unions usually
call for a strike. The Employer argued that there is a
no-strike clause in the contract, and the Union has no
right to go on strike.
The Employer is correct that Article 12 is a no-strike,
no-lockout clause. However, whether or not the Union
has the right to call for a strike because the itsmployer
breached the Agreement is not for me to determinc. That
matter is not before me. What is before me is that the
Employer’s action breached the Agreement. I have
already determined that it did.
It breached the Agreement because there was no
impasse. The Employer simply said, “we are going to
reduce the wages by twelve and one half percent
(124%). If you don’t agree, we are going to declare an
impasse and implement that wage reduction.” That is
not negotiations. I can’t accept the limited time spent in
63a
Appendix C
bargaining as a basis for the Employer’s authority to
reduce the wages of the bargaining unit members.
Accordingly, there is no question in my mind that
the Employer’s action breached the Agreement. The
question becomes what type of remedy can be developed
based upon the facts in the instant matter.
For the foregoing reasons and having duly heard the
proofs and allegations of the parties, I Award the
following:
AWARD
The grievance is sustained. The Employer’s
unilateral action of reducing the wages of bargaining unit
members was in violation of the Agreement. Five Star
Parking shall cease and desist from paying the decreased
wage rate, which became effective September 17, 2004.
All employees whose wages were reduced, including
those who have left employment since September 17,
2004, shall be awarded back pay for the full amount of
reduction of their salary that was in effect on September
5, 2004, to the day they receive their retroactive pay.
{ am denying the Union’s request for interest.
[I shall retain jurisdiction should there be a dispute
concerning the calculation of the back pay money and
who may be entitled to it.
64a
Appendix C
Gerard G. Restaino
Gerard G. Restaino, Arbitrator
Dated: August 3, 2005
State of New Jersey )
County of Middlesex ) ss:
On this 3" day of August 2005, before me personally
came and appeared GERARD G. RESTAINO to me
known to be the person who executed the foregoing
instrument and he auly acknowledged to me that he
executed the same.
65a
APPENDIX D — ORDER OF THE UNITED
STATES COURT OF APPEALS FOR THE THIRD
CIRCUIT DENYING PETITION FOR
REHEARING DATED AUGUST 29, 2007
UNITED STATES COURT OF APPEALS
FOR THE THIRD CIRCUIT
No. 06-2012
FIVE STAR PARKING
Ve
UNION LOCAL 723, affiliated with the
INTERNATIONAL BROTHERHOOD
OF TEAMSTERS,
Appellant
SUR PETITION FOR REHEARING
Present: SCIRICA, Chief Judge, SLOVITER,
McKEE, RENDELL, BARRY, AMBRO, FUENTES,
SMITH, FISHER, CHAGARES, JORDAN, and
HARDIMAN, Circuit Judges
The petition for rehearing filed by appellee in the
above entitled case having been submitted to the judges
who participated in the decision of this court and to all
the other available circuit judges of the circuit in regular
active service, and no judge who concurred in the
decision having asked for rehearing, and a majority of
the circuit judges of the circuit in regular active service
66a
Appendix D
not having voted for rehearing by the court en banc, the
petition for rehearing is denied.
By the Court,
MICHAEL A. CHAGARES
Circuit Judge
DATED: August 29, 2007
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.