Petition for Writ of Certiorari — Vermont v. Green Mountain Railroad
Supreme Court brief2005
Ask Donna
What actually matters in this document.
Text
6
Connecticut River and on the west side by railroad tracks
and other property. Jd. The Connecticut River in this
area contains valuable fisheries and is a prime
recreational resource. Joint Appendix, Second Circuit, at
85 (hereinafter, “JA-xxx”).
a. The Buffer Zone Condition. In 1997, GMRC
sought an Act 250 permit to construct a 20-foot by 30-foot
office building and to operate a “forest products
distribution yard” at the Riverside site.’ App. 18a. In the
permit application, GMRC proposed a 75-foot buffer zone
along the Connecticut River to satisfy environmental
criteria under Act 250, Vt. Stat. Ann. tit. 10, §§
6086(a)(1)E) & (F) (streams and shorelines). App. 4a.
Because riparian buffers play a crucial role in protecting
rivers such as the Connecticut (JA-089), the Vermont
Agency of Natural Resources recommended that the
buffer zone be enlarged from 75 to 100 feet. App. 4a.
On November 12, 1997, the District #2 Environmental
Commission, which is the state authority that oversees
projects in the Rockingham area, issued Land Use Permit
#2W0038-2 (the “Dash Two” permit). App. 4a. Condition
14 of the permit required:
The permittees shall maintain a 100-foot
undisturbed, naturally vegetated buffer strip with
no mowing or cutting of vegetation between the top
of the bank of the Connecticut River and any
disturbed areas.
App. 18a.
* GMRC did not initially dispute Act 250’s pre-construction
permitting requirement.
7
b. The Salt Shed Permit. In the spring of 1998,
GMRC sought an amendment to its Act 250 permit, called
the “Dash Three” permit application, to construct a 100-
foot by 275-foot salt storage shed. App. 5a. The district
environmental commission issued the Dash Three permit
on January 13, 1999.
In October 1999, GMRC sought another amendment,
the “Dash Three-B” permit application, to modify the size,
type, color and location of the salt storage building. App.
5a. In November 1999, GMRC began construction of the
modified salt storage shed without having obtained a final
Dash Three-B permit. Id.
In January and February of 2000, the State issued two
separate notices of violation to GMRC for various Act 250
violations at the Riverside site, including the construction
of the unapproved salt shed and the storage of materials
within the 100-foot buffer zone.’ App. 5a.
4. Proceedings Below
a. On June 6, 2001, GMRC filed a complaint in federal
district court where it admitted to various Act 250
violations, but claimed that the ICCTA preempted
enforcement of those conditions.’ App. 16a. GMRC also
alleged that, as a railroad, it did not need to obtain an Act
250 permit for future construction, such as a proposed
cement facility at the Riverside site, because any attempt
by the State to -require the railroad to obtain pre-
construction permits was preempted by federal law. Id.
* There is no dispute in this case that GMRC failed to maintain
the buffer zone or that it constructed a salt shed without an
approved permit.
* On June 5, 2001, GMRC filed a similar petition to institute
declaratory proceedings before the STB, which denied the
petition on May 24, 2002. App. 5a-6a.
8
In a motion to dismiss filed on July 17, 2001, the State
argued that Act 250 is not preempted on its face by
Section 10501(b) and that Act 250 has only an incidental
impact on the economic activities of GMRC. App. 16a.
b. The District Court granted in part, and denied in
part, the State’s motion to dismiss: “[T]o the extent the
Defendants ask the Court to dismiss Green Mountain’s
claim that the ICCTA preempts Act 250 under all
circumstances, the motion is granted. Act 250 retains
viability where its provisions do not unduly interfere with
the provisions and purposes of the ICCTA.” JA-020
(District Court’s Ruling on Pending Motions, Sept. 26,
2001) (emphasis added).
On July 15, 2003, the State filed a motion for summary
judgment, and on August 22, 2003, GMRC filed a cross-
motion for summary judgment. The State restated its
argument that Section 10501(b) does not preempt Act 250
in this case because Act 250 does not unduly burden the
railroad.
In a decision dated December 15, 2003, the District
Court contradicted its earlier order and held that the
State “may not apply a law like Act 250 so as to require
pre-construction approval and permitting.” App. 28a. It
granted GMRC’s cross-motion for summary judgment and
denied the State’s motion for summary judgment. App.
32a. The State appealed.
c. The Second Circuit affirmed on April 14, 2005,
stating that the ICCTA “expressly preempts ‘remedies
provided under Federal and State law.” App. 2a. It
further found that the plain language of Section 10501
“reflects clear congressional intent to preempt state and
local regulation of integral rail facilities.” App. 15a.
9
The court held that “the permitting process itself” was
preempted as applied to railroads because “the railroad is
restrained from development until a permit is issued; the
requirements for the permit are not set forth in any
schedule or regulations that the railroad can consult in
order to assure compliance; and the issuance of the permit
awaits and depends upon the discretionary ruling of a
state or local agency.” App. 11a.
The court rejected the State’s arguments that Act 250 is
not preempted on its face and that the court should assess
the actual impact of any conditions imposed. App. 1la. It
held, instead, that preemption applied even if there were
“permit applications affecting railroad facilities that could
be promptly approved without the slightest imposition on
rail operations.” Jd. The court therefore found it
unnecessary to “conduct a fact-based inquiry weighing the
economic impact of Act 250’s permitting process upon
Green Mountain.” App. 15a.
It likewise disagreed that only economic regulations —
i.e., direct economic regulations or those that have a
substantial economic impact — are preempted by the
ICCTA. App. 13a. The court found the distinction “not
useful” because the permitting process “necessarily
interferes” with GMRC’s ability to construct facilities and
conduct economic activities. App. 13a-14a.
Finally, the court was unmoved by the State’s argument
that the district court’s decision leads to illogical
consequences. The State argued that because the
activities at issue are ancillary projects and not under the
STB’s regulatory authority, they would be subject to no
environmental review whatsoever if Act 250 were
preempted. Despite this gap in regulatory coverage, the
Court held that Act 250 was per se preempted. -
10
REASONS FOR GRANTING THE PETITION
Since its enactment over ten years ago, federal and
state courts have repeatedly disagreed over the
preemptive force of Section 10501(b) of the ICCTA as it
applies to railroad operations in general, and also as it
applies to ancillary projects — which are not under federal
regulatory control. In this case, the Second Circuit took
an expansive view that stretches the preemptive scope of
the ICCTA beyond its breaking point. Unlike most other
courts, it held that pre-construction permitting programs
are per se preempted.
This Court should grant certiorari for three reasons.
First, this Court should resolve the conflict among the
courts, including a direct split between the Vermont
Supreme Court and its corresponding circuit court of
appeals, on the preemptive scope of Section 10501(b).
Second, this is a recurring issue that goes to the heart of
federal-state relations and that has been fully developed
by the lower courts. Third, the Second Circuit misapplied
this Court’s precedents and erred when it held that
railroads are completely exempt from pre-construction
permitting programs.
I. The Second Circuit’s Decision Is In Sharp
Conflict With Decisions Of Other Courts. Of
Appeals And State Supreme Courts.
Courts across the country are divided over the level of
preemption intended by Section 10501(b).“ The tests
~
* The federal district court for the District of Columbia in
District of Columbia v. 109,205.5 Square Feet of Land, 2005 WL
975745 at *3 (D.D.C. Apr. 21, 2005), recently recognized the
conflict among the courts on the preemptive breadth of Section
10501(b). It stated:
11
applied by the courts to determine preemption
demonstrate a fundamental disagreement over how to
interpret the plain language of Section 10501(b), and,
more specifically, what effect to give the phrase “with
respect to the regulation of rail transportation” as that
phrase is used in that section. The courts have applied
four distinct and conflicting tests when determining the
scope of preemption of Section 10501(b).
First, the Second Circuit in this case interpreted Section
10501(b) to preempt all pre-construction permitting
programs as applied to railroads because they
“necessarily interfere” with a railroad’s ability to
construct facilities and conduct economic activities.’
App. 14a (internal quotations omitted). Relying
extensively on the Ninth Circuit’s ruling in City of
Auburn v. United States, 154 F.3d 1025 (9th Cir. 1998),
cert. denied, 527 U.S. 1022 (1999), the Second Circuit
construed the section expansively, finding “[i]t is difficult
to imagine a broader statement of Congress’s intent to
preempt state regulatory authority over railroad
Courts have been split on the broadness of preemption
under ICCTA; some have held it preempts all state
efforts, City of Auburn [v. United States], 154 F.3d [1025,]
1029-1030 [9th Cir. 1998]; Wis[consin] Cen[tral] Ltd. [v.
City of Marshfield], 160 F. Supp. 2d [1009,] 1013 [W.D.
Wis. 2000], and others have held it applies only to the
regulation of rail transportation. Jowa, Chi. & E. R.R. v.
Wash{ington]. County, 584 F.3d 557, 561 (8th Cir. 2004);
Fla. E. Coast R.R. Co. v. City of West Palm Beach, 266
F.3d 1324, 1331 (11th Cir. 2001).
Presumably unaware of the Second Circuit’s decision seven
days earlier, the district court failed to cite the opinion below.
* The STB, which filed an Amicus Brief in the case below, also
claims that pre-construction permitting requirements are
entirely preempted.
12
operations.” App. 15a. Thus, pursuant to the decision
below, all state and local pre-construction permitting
processes are completely preempted regardless of whether
they delay, interfere, or otherwise impose any burden on
railroad operations.’
Second, the Vermont Supreme Court, in direct conflict
with the decision below, has held that pre-construction
permitting programs are not absolutely preempted.
Instead, the court has required examination of permit
conditions to determine whether they interfere with
railroad operations.
Third, the Eleventh Circuit and the Alaska Supreme
Court have similarly rejected the Second Circuit’s broad
view of preemption. These courts have ruled that Section
10501(b) does not preempt regulations that have only a
minimal or remote impact on rail transportation.
Fourth, the Eighth -Circuit and, most recently, the
North Dakota Supreme Court, have looked to whether the
ICCTA addressed the same issue as the state regulation
in question. These courts have found no preemption
where the ICCTA does not specifically regulate the matter
at issue.
* The Second Circuit’s reliance on City of Auburn, however,
was misplaced because the Ninth Circuit’s ruling turned on the
presence of an additional and broader preemption provision of
the ICCTA that is not at issue here.
” Although not reviewing a pre-construction permitting
program, the Fifth Circuit has also taken a broad view of
preemption under Section 10501(b). See Friberg v. Kansas City
Southern Railway, 267 F.3d 439 (5th Cir. 2001).
13
A. The Decision Below Conflicts With A
Decision Of The Vermont Supreme Court.
The Vermont Supreme Court’s holding in In re Appeal
of Vermont Railway, 769 A.2d 648 (Vt. 2000), directly
conflicts with the decision below. Despite examining a
very similar land use scheme, the Vermont Supreme
Court rejected the notion that Section 10501(b) amounts
to a per se bar to pre-construction permitting
requirements.
In Vermont Railway, an affiliate of GMRC, Vermont
Railway, appealed various permit conditions imposed by
the City of Burlington, Vermont, in connection with a
facility that Vermont Railway operated. Id. at 651.
Some of these conditions included requirements relating
to the proposed expansion and use of a salt shed at that
facility. Id. - The railroad claimed that Burlington’s
zoning ordinances were “preempted entirely” by Section
10501(b). Id. at 650. :
The Vermont Supreme Court refused to find that
Section 10501(b) preempted the imposition of the pre-
construction permitting program. Id. at 654. The court,
citing the STB’s decision in King County, WA, Petition for —
Declaratory Order, S.T.B. Finance Docket No. 32974,
1996 WL 545598 at *4 (1.C.C.) (September 25, 1996),
recognized that “the ICCTA does not usurp the right of
state and local entities to impose appropriate public
health and safety regulation on interstate railroads.” 769
A.2d at 653. The court concluded that this included the
power to protect the environment. Id. at 655 (upholding
* Thus, the STB has acknowledged that not ail state and local
regulation is preempted entirely by Section 10501(b). It
appears, however, to have drawn a distinction with pre-
construction permitting programs. See supra note 5.
14
conditions that were “designed to avert -potential
contamination from the salt shed”).
The court held that “the proper approach” under Section
10501(b) is to determine whether the permit conditions
“stood as an obstacle to the goals of the ICCTA.” 7d. at
655. Only if those conditions “interfere[d] with railway
operations” would they be preempted. Jd. (emphasis in
original); contra GMRC, App. Qa _ (pre-clearance
requirements are preempted because they “unduly
interfere with interstate commerce”). The Vermont
Supreme Court explicitly rejected the railroad’s argument
that any permit condition “necessarily has an economic
impact on its railway operations such that it is
preempted.” 769 A.2d at 654 (emphasis in original).
In reaching its contrary position that pre-construction
permitting programs are per-se preempted, the Second
Circuit relied upon three factors: [1] “the railroad is
restrained from development until a permit is issued; [2]
the requirements for the permit are not set forth in any
schedule or regulation that the railroad can consult in
order to assure compliance; and [3] the issuance of the
permit awaits and depends upon the discretionary ruling
of a state or local agency.” App. 11a.
Yet, Burlington’s Zoning Ordinances (“BZO”), which
were at issue in Vermont Railway, share these same
characteristics. Both Act 250 and Burlington’s Zoning
Ordinances impose pre-construction permitting
requirements. BZO § 4.1.3 (“No land development may be
commenced within Burlington without a zoning permit”);
Act 250, Vt. Stat. Ann. tit. 10, § 6081(a) (“No person shall
. . . commence development without a permit”). Both
have criteria to help guide applicants and reviewing
agencies, but there is no ability to assure that a permit
15
will be issued for certain projects. BZO, § 7.1.6
(development board guided by standards “in conducting
its review and imposing conditions and safeguards”); Vt.
Stat. Ann. tit. 10, § 6066 (conditions and criteria for
granting permits). Both give the permitting authority
discretion to determine whether a project complies with
certain criteria. BZO § 13.1.6(a) (board required to find
that major impact developments will “not result in undue
water, air or noise pollution”); Vt. Stat. Ann. tit. 10,
§ 6086(a)(1) (commission must find that the development
“will not result in undue water or air pollution”).
Consequently, the division between the Second Circuit
and the Vermont Supreme Court could not be more stark.
Reviewing virtually identical pre-construction permitting
schemes, the Second Circuit held that these programs are
automatically preempted, while the Vermont Supreme
Court held that the permit conditions imposed must be
evaluated to see whether they interfere with railroad
operations. Whether such pre-construction permitting
programs are preempted under Section 10501(b) thus
depends entirely on which court heard the case. The
ruling of the Second Circuit and that of the Vermont
Supreme Court cannot be reconciled. Such a conflict
requires resolution by this Court.
B. The Decision Below Conflicts With
Decisions Of The Eleventh Circuit And The
Alaska Supreme Court.
The Second Circuit’s decision also conflicts with the
Eleventh Circuit’s decision in Florida East Coast Railway
v. City of West Palm Beach, 266 F.3d 1324, 1339 (11th
Cir. 2001), and the Alaska Supreme Court’s decision in
Native Village of Eklutna v. Alaska R.R., 87 P.3d 41, 57
(Alaska 2004).
16
1. Florida East Coast Railway v. City of West
Palm Beach
At issue in Florida East Coast Railway was whether
Section 10501(b) preempted the zoning ordinances of
West Palm Beach. The Eleventh Circuit found that the
plain language of Section 10501(b) did not reflect broad
congressional intent to preempt all local regulation of rail
transportation. 266 F.3d at 1330-31; contra GMRC, App.
15a (“the plain language of Section 10501 reflects clear
congressional intent to preempt state and local regulation
of integral rail facilities”). Rather, the court determined
that the phrase “with respect to regulation of rail
transportation” placed express limitations on the scope of
preemption of Section 10501(b). 266 F.3d at 1331. The
Eleventh Circuit ruled that Congress had “narrowly
tailored the ICCTA pre-emption provision to displace only
‘Tegulation,’ i.e., those state laws that may reasonably be
said to have the effect of ‘managling]’ or ‘govern[ing]’ rail
transportation . . . while permitting the cantinued
application of laws having a more remote or incidental
effect on rail transportation.” Jd. (citations omitted).
* Numerous state courts have similarly found no preemption
under Section 10501(b) where regulations impose only
incidental burdens on railroads. Jones v. Union Pac. R.R., 94
Cal. Rptr. 2d 661, 666-67 (Cal. Ct. App. 2000) (noting “{[s)tate
and local regulation of Union Pacific's trains is permissible if it
does not interfere with Union Pacific's interstate rail
operations”); Soo Line R.R. v. City of Minneapolis, 625 N.W.2d
834, 836 (Minn. Ct. App. 2001) (designation of roundhouse for
local heritage preservation was not preempted by ICCTA
because designation did not interfere with any plan of railway
to use the roundhouse); State ex rel. Oklahoma Corp. Comm'n v.
Burlington N. and Santa Fe Railway, 24 P.3d 368, 371 (Okla.
Ct. App. 2000) (statute requiring railroads to construct fences
along railway rights-of-way was not preempted by ICCTA).
17
Even though the application of the zoning regulations
might not be “optimally efficient for (the railroad’s]
operations,” the court concluded, the “requirements do not
impede the interstate functioning of the railroad
industry” and could not be considered the “regulation of
rail transportation” under Section 10501(b). Id. at 1339;
contra GMRC, App. 15a (the court “need not conduct a
fact-based inquiry weighing the economic impact of Act
250’s permitting process upon Green Mountain”).
The decision of the Eleventh Circuit directly conflicts
with the ruling below in two key respects. First, the
Eleventh Circuit’s narrow interpretation of the plain
language of Section 10501(b) is diametrically opposed to
the Second Circuit’s broad view. Second, the Eleventh’s
Circuit focus on the impact of the regulation in question
diverges from the Second Circuit’s facial preemption
analysis.
2. Native Village of Eklutna v. Alaska R.R.
The Alaska Supreme Court’s decision in Native Village
of Eklutna v. Alaska R.R. also conflicts with the Second
Circuit’s decision as to whether Section 10501(b)
completely preempts pre-construction permitting
programs.
In Native Village of Eklutna, the Alaska Railroad
Corporation began operation of a quarry on culturally
significant land near Anchorage, Alaska. 87 P.3d at 43-
44. Eklutna, joined by Anchorage, brought suit to enjoin
the railroad from operating the quarry without a
conditional use permit. Jd. The railroad argued that it
was not required to obtain a conditional use permit
because Section 10501(b) preempted the ordinances with
respect to railroad property. Id. at 56.
18 Z
Like the Eleventh Circuit, the Alaska Supreme Court
looked to whether the zoning ordinances had “more than
[an] incidental impact on [the railroad’s] operations.” 87
P.3d at 57. In finding that the regulations and the
conditional use permit requirement were not preempted,
the court recognized that “Congress’s focus on economic
regulation makes clear that it had no intention of
preempting all state or local regulation that touches
railroads in any way.” Id. (emphasis added). The
Alaska Supreme Court stated:
ICCTA’s preemption is aimed at improving the
“nationwide efficiency of the railroad industry,” not
at stopping all regulation that “prevents an
individual firm from maximizing its profits.” Local
regulation may bring some hardship or
inconvenience to a railroad without causing the sort
of economic impact that would trigger preemption.
Id. (footnote omitted); contra GMRC, App. l4a
(permitting process “necessarily interferes with Green
Mountain’s ability to construct facilities and conduct
economic activities”) (internal quotations omitted).
“ Many courts have recognized that Congress’s purpose in
enacting the ICCTA was to preempt only the economic
regulation of railroads by States — not all regulation relating to
railroads. See, e.g., CSX Transp., Inc. v. City of Plymouth, 92 F.
Supp. 2d 643, 658 (E.D. Mich. 2000) (discussing findings of
several courts that have found that the ICCTA “preempts state
law regulation of railroads in an economic sense”), aff'd on other
grounds, 283 F.3d 812 (6th Cir. 2002); Burlington N. Santa Fe
Corp. v. Anderson, 959 F. Supp. 1288, 1296 (D. Mont. 1997)
(holding that the “statutory language and accompanying
legislative record [of the ICCTA] evidence Congress’ clear and
manifest intent to occupy the entire field of economic regulation
of railroad transportation”).
19
Finally, the Alaska Supreme Court acknowledged that
requiring the railroad to get a conditional use permit “will
at least delay the operation of the [project] by the time
needed for the Railroad to obtain a conditional use
permit, and may bar the Railroad’s use of the land
altogether, if the permit is denied.” 87 P.3d at 57 (quoting
Vermont Railway, 769 A.2d at 654). It noted that
“[wlhether this amounts to undue interference with the
Railroad’s operation is a ‘fact-bound determination.” Jd.
Contrary to the reasoning of the Second Circuit, the
Alaska Supreme Court found such factors insufficient to
require per se preemption. Contra GMRC, App. 9Ya-10a,
15a (permitting process preempted because “it can be
time-consuming, allowing a local body to delay
construction of railroad facilities almost indefinitely” and
the court “need not conduct a fact-based inquiry weighing
the economic impact of Act 250’s permitting process upon
Green Mountain”).
Therefore, the test applied by both the Eleventh Circuit
and the Alaska Supreme Court, which looks to the
regulation’s effect on rail transportation, is in conflict
with the Second Circuit’s broad view of both the plain
language and the preemptive scope of Section 10501(b).
C. The Decision Below Conflicts With
Decisions Of The Eighth Circuit And The
North Dakota Supreme Court.
The Second Circuit’s decision is also incompatible with
the Eighth Circuit’s ruling in Jowa, Chicago & Eastern
R.R. v. Washington County, 384 F.3d 557, 561 (8th Cir.
2004), and the North Dakota Supreme Court’s ruling in
Home of Economy v. Burlington Northern Santa Fe R.R.,
694 N.W.2d 840, 846-47 (N.D. 2005). Under the analysis
of these courts, preemption is not required under Section
20
10501(b) unless the ICCTA specifically addresses the
same issue as the state regulation in question.
1. Jowa, Chicago & Eastern R.R. v. Washington
County
In Iowa, Chicago & Eastern R.R., Washington County,
Iowa petitioned the Iowa Department of Transportation
for a ruling that the railroad must pay to replace or repair
four “severely deficient” railroad bridges pursuant to state
statutory law. 384 F.3d at 558. The railroad then sought
a declaratory judgment that the Iowa statute was
preempted by the ICCTA. Id.
In analyzing the preemptive scope of Section 10501(b),
the Eighth Circuit concluded that because the ICCTA did
not address the repair and replacement of railway-
highway bridges, “[ilts silence cannot reflect the requisite
‘clear and manifest purpose of Congress’ to preempt
traditional state regulation” of this kind. Jd. at 561
(quoting CSX Transp., Inc. v. Easterwood, 507 U.S. 658,
664 (1993)). That finding was reinforced by the long-time
federal-state partnership addressing rail safety in the
Federal Rail Safety Act and also by the “traditional state
regulation of public roads and bridges that Congress has
encouraged in numerous other statutes.” Id. The court
explicitly rejected the railroad’s “broad argument that the
ICCTA preempted this type of state regulation of railroad
‘facilities.” Id. (emphasis in original).
2. Home of Economy v. Burlington Northern
Santa Fe R.R.
Similarly, in Home of Economy v. Burlington Northern
Santa Fe R.R., which was decided on April 6, 2005, a
landowner sued a railroad claiming that he had a
common-law right to have the railroad re-open a “grade
crossing” to allow him access to his property. 694 N.W.2d
21 :
840-41. The railroad claimed such common-law actions
were preempted by the ICCTA. The North Dakota
Supreme Court reviewed Section 10501(b) and found, like
the Eighth Circuit, that it preempted only matters that
were specifically addressed in the ICCTA. The court
concluded that Section 10501(b) did not preempt the
landowner’s common-law suit because the ICCTA did not
“explicitly deal with grade crossings.” Id. at 844. On the
contrary, the court recognized that the states possess
“traditional authority regarding grade crossings.” Id. at
846.
The test applied by the Eighth Circuit and the North
Dakota Supreme Court to determine preemption conflicts
with the decision below. These courts took a narrow view
and looked to whether the ICCTA specifically addressed
the state regulation in question, while the Second Circuit
took an expansive view, finding Section 10501(b)
demonstrates “Congress’s intent to preempt state
regulatory authority over railroad operations” —
regardless of whether the ICCTA addresses the exact
issue in question. App. 15a.
In sum, the preemptive scope of Section 10501(b) has
greatly divided state and federal courts of this country.
This Court’s review is necessary to resolve this conflict
among the courts. |
II. This Court Should Resolve A Recurring Issue
Of National Import That Has Been Fully
Developed By The Lower Courts.
This case involves an important and well-developed
issue of federalism that should be determined by this
Court. The decision below severely eviscerates state and
local authorities’ historic police powers, such as enforcing
land use, zoning and environmental regulations, as they
22
are applied to railroads. In addition, this is a recurring
issue that has been subject to ample analyses by the
lower courts so that no further review is necessary before
this Court rules on the matter.
A. This Is An Issue Of Exceptional Importance
That Goes To The Heart Of Federal-State
Relations. |
By holding that the ICCTA displaces all state and local
land use and environmental protections that operate
through pre-construction permit programs, the Second
Circuit has dealt a crippling blow to the ability of states
and localities to protect the environment and to control
development. Although the Second Circuit suggested that
not ali regulations are preempted, the remaining laws do
not protect these areas of concern. See GMRC, App. 10a
(finding that railroads are subject to some local regulation
such as electrical, plumbing and fire codes).
Like Vermont’s use of Act 250, local authorities
traditionally regulate land use and protect the
environment using their own zoning ordinances.
Although municipalities may call the permitting schemes
by different names, including “variances,” “conditional
use permits,” and “non-conforming use permits,” most
municipalities have some type of pre-clearance
requirement for commercial projects. Because most
permitting programs require site-plan or project review
before development, they would likely be preempted
under the Second Circuit’s sweeping decision.
Such land use regulations play a significant role in
protecting the nation’s natural resources. Both Congress
and this Court have recognized the states’ primary role in
regulating land use and preserving the environment. See,
e.g., Solid Waste Agency of Northern Cook County v.
23
United States Army Corps of Eng’rs, 531 U.S. 159, 174
(2001) (the states, not the federal government, exercise
“traditional and primary power over land and water use”).
Furthermore, state and local laws protect numerous
interests that are not directly regulated by federal law,
such as preservation of wildlife habitat and natural areas
and protection of agricultural soils. See Vt. Stat. Ann. tit.
10, § 6086(a\(8) & (9). Eliminating Act 250 and similar
local regulations leaves these interests entirely
unprotected. Although critically important, federal
environmental laws are not intended to, and cannot,
substitute for comprehensive state regulation like Act 250
and other permit processes.
Moreover, the Second Circuit’s decision produces the
illogical result that these types of permitting programs
are preempted regardless of what railroad projects are at
issue. Thus, a railroad can claim that virtually any
project tangentially related to rail transportation is
exempt from regulation. And, as demonstrated by this
case, this means there would be no environmental review
— federal, state or local — over many “ancillary” projects
where the STB has jurisdiction, but no regulatory
authority. See Appeal of Vermont Railway, 769 A.2d at
653 n.* (citing STB acknowledgment that it has only
limited regulatory authority). For example, under the
Second Circuit’s decision, if a railroad wanted to operate
and use a solid waste landfill, or a rock quarry, see, e.g.,
Native Village of Eklutna, 87 P.3d at 56-57, supra pp. 17-
19, at the terminus of or along side a rail line, it would
evade all federal, state and local environmental
permitting requirements. Congress could not have
intended to exempt these “ancillary” projects from all
environmental review, while requiring “core” rail
24
transportation projects to be reviewed by the STB under
the National Environmental Policy Act. 42 U.S.C. §
4332(2\C); 49 C.F.R. § 1105.6.
Nothing in the language or history of the ICCTA shows
that Congress intended to completely displace historic
state police powers that may only touch upon rail
transportation. Environmental regulation by state and
local authorities for projects outside federal regulatory
control is entirely consistent with the federal-state
partnership in environmental protection, with the states’
historic power to regulate in this area, and with the goals
of the ICCTA.
B. This Question Will Continue To Challenge
The Lower Courts And They Have Fully
- Developed The Issue.
The Ninth Circuit in City of Auburn v. United States
was the first circuit court of appeals to review the pre-
emptive scope of the ICCTA. In 1999, the United States -
in its brief in opposition to granting certiorari in City of
Auburn, wrote that “the administrative and judicial
process of construing the ICCTA and its effect on state
and local regulation has only recently begun,” and that “it
would be premature for this Court to review questions
about the ICCTA’s preemptive scope before the Board and
the lower courts have had the opportunity to consider the
preemptive question in a variety of concrete factual
settings.” Brief for the Federal Respondents in
Opposition to Certiorari at 11, No. 98-1511, City of
Auburn v. United States.
Courts have now had that opportunity. As recognized
by the North Dakota Supreme Court in Home of Economy,
some courts have broadly construed Congress’s
preemption language in Section 10501(b) and concluded
25
that it preempted state or local laws. See 694 N.W.2d at
844 (citing 9 cases). Other courts have narrowly
construed the section and have concluded that it did not
preempt state or local laws. See id. at 844-45 (citing 6
cases). The matter has been fully vetted by the courts of
this nation.
Given the continued importance of this issue, the
divergent views of all these courts, and the impact of the
Second Circuit’s far-reaching decision, it is now time for
this Court to provide guidance on this issue.
III. The Second Circuit Misapplied This Court’s
Precedents And Reached The Wrong Result.
This Court’s preemption analysis is well established.
The ultimate goal is to ascertain Congress’s intent in
crafting a preemption provision. Medtronic, Inc. v. Lohr,
518 U.S. 470, 485 (1996) (“purpose of Congress is the
ultimate touchstone” in every preemption case). To
determine that purpose, this Court has instructed that
the language of the statute, the statutory scheme, and the
legislative history should be examined. ‘In areas where
states have traditionally exercised their police powers,
even greater care must be taken to assure that
preemption goes no further than Congress intended.
Here, the Second Circuit’s decision incorrectly analyzes
each of the above factors and arrives at a result that can
not be squared with prior decisions of this Court.
The Second Circuit misread the plain language of
Section 10501(b), and erred by not giving effect to every
clause and word of the statute. Bennett v. Spear, 520 US.
154, 173 (1997). Although the Second Circuit purported
to apply a plain language analysis, the court broadly, and
inaccurately, stated that the ICCTA “expressly
preempts ‘remedies provided under Federal and State
26
law.”" App. 2a. The actual wording of Section 10501(b),
however, makes clear that only the remedies set out in
Part A are exclusive. App. 34a (42 U.S.C. § 10501(b))
(remedies “provided in this part . . . are exclusive”); c.f,
Cipollone v. Liggett Group, Inc., 505 U.S. 505, 517 (1992)
(Congress’s “enactment of a provision defining the
preemptive reach of a statute implies that matters beyond
that reach are not preempted”).
In addition, Section 10501(b) contains additional
limiting language overlooked by the Second Circuit.
Congress made the remedies in Part A exclusive, but only
“with respect to regulation of rail transportation.” App.
34a (42 U.S.C. § 10501(b)) (emphasis added). Congress’s
choice to include this language demonstrates its intent to
preempt only state regulation that could be considered
“regulation of rail transportation.” The Second Circuit’s
failure to appreciate the significance of this phrase, which
acts to restrict the preemptive scope of Section 10501(b),
further undermines the court’s legal analysis. See, e.g.,
Florida East Coast Railway, 266 F.3d at 1331 (phrase
“with respect to regulation of rail transportation” places
express limitations on the scope of preemption under
Section 10501(b)).
The Second Circuit also should have considered Section
10501(b) in pari materia with other sections in the
ICCTA. Crawford Fitting Co. v. J. T. Gibbons, Inc., 482
U.S. 437, 445 (1987). Other preemption provisions found
in Part A of title 49 severely undercut the Second
" The court also erred when it stated that the plain language
gave the STB “wide authority” over the facilities at issue in this
case. App. 7a. Although the STB may have jurisdiction, it does
not have regulatory power over the projects. See supra p. 4.
27
Circuit’s broad interpretation of Section 10501(b). For
example, Section 11501, entitled “tax discrimination
against rail transportation property,” states:
The following acts unreasonably burden and
discriminate against interstate commerce, and a
State, subdivision of a State, or authority acting for
a State or subdivision of a State may not do any of
them.
App. 36a (49 U.S.C. § 11501(b)).
This provision would be entirely unnecessary if the
Second Circuit’s broad interpretation of the preemptive
scope of Section 10501(b) were correct. In other words, if
Section 10501(b) represented “Congress’s intent to
preempt state regulatory authority over railroad
operations,” as the Second Circuit asserts (GMRC, App.
15a), Congress would not have needed to expressly
preempt the states’ ability to impose certain taxes on
railroads in Section 11501(b). These activities would have
already béen preempted by Section 10501(b). See also 49
U.S.C. § 11321(a) (exempting railroads “from the
antitrust laws and from all other law” when engaging in
certain activities).
This Court’s decision in Rice v. Santa Fe Elevator
Corp., 331 U.S. 218 (1947), further evidences the Second
Circuit’s misguided analysis. In that case, the Court
examined whether a federal law, which gave a federal
agency wide jurisdiction over the operation of grain
warehouses, preempted state efforts to regulate in that
area. Section 29 of the U.S. Warehouse Act stated that
“the power, jurisdiction, and authority conferred upon
the Secretary of Agriculture under this act shall be
exclusive.” See Id. at 223-24. In finding that certain
claims were not preempted, the Court held:
28
The test, therefore, is whether the matter on
which the State assets [sic] the right to act is in
any way regulated by the Federal Act. If it is, the
federal scheme prevails though it is a more
modest, less pervasive regulatory plan than that of
the State.
Id. at 236.
The Court then analyzed each of the allegations in the
complaint and found that the act “contain[ed] no
‘provisions relating expressly” to several of the matters
at issue. Id. at 237. It concluded that “Congress has
not foreclosed state action by adopting a policy of its
own on these matters,” and found no preemption. Id.
The Rice Court’s analysis demonstrates that the —
Second Circuit’s holding is not supportable. The
requirement that GMRC go through Act 250’s
permitting process does not implicate, much less, clash
with, any of the remedies provided in the ICCTA —~
especially considering that the STB lacks regulatory
authority over the projects at issue. Accord California
Coastal Comm’n v. Granite Rock Co., 480 U.S. 572, 580
(1987) (preemption applies only where “no possible set of
conditions” could be placed on permit that would not
conflict with federal law). -
The Second Circuit decision also fails to adhere to this
Court’s instruction that when “Congress legislates in a
field which the States have traditionally occupied .. .
[courts] start with the assumption that the historic
police powers of the States were not to be superseded by
the Federal Act unless that was the clear and manifest
purpose of Congress.” Rice, 331 U.S. at 230 (emphasis
added); see also CSX Transp., Inc., 507 U.S. at 664. No
clear and manifest purpose to preempt all pre-
29
construction permitting requirements can be inferred
from the language of Section 10501(b).
That conclusion is reinforced by the ICCTA’s
legislative history. See, e.g., Mid-Con Freight Sys. Inc. v.
Michigan Public Service Comm’n, 545 U.S. __, 125
S.Ct. 2427, 2433 (2005) (“Our reading of the text finds
confirmation in historical context”). Contrary to the
view of the Second Circuit, a cursory review of the -
legislative history on the development of the preemptive
scope of Section 10501(b) confirms that Congress sought
to limit the scope of preemption. Initially, the House and
the Senate could not agree on a common version, and a
Committee of Conference was formed to produce a final
bill. The Senate “intend[ed] that those States regulating
intrastate rail transportation continue to be required to
regulate only in a manner consistent with the [Interstate
Commerce Act].” S. Rep. 104-176, at 5, 1995 WL 701522
at *6. The House sought to eliminate the states’ authority
“to administer economic regulation of railroads,” and
further advocated the complete exclusivity of federal
remedies, which was “intended to encompass ll
statutory, common law, and administrative remedies
addressing the rail-related subject matter jurisdiction of
the (STB].”. H.R. Rep. No. 104-311, at 95, 1995
U.S.C.C.A.N. at 807. The House had proposed: “Except as
otherwise provided in this part, the remedies provided
under this part are exclusive and preempt the remedies
provided under Federal or State law.” Id. at 793.
In formulating a compromise, the Committee of
Conference rejected the House’s broader scope, and added
the limiting phrase “with respect to regulation of rail
transportation” to the House’s proposed preemption
clause. The Committee of Conference “clariflied] that the
30
exclusivity is limited to remedies with respect to rail
regulation — not State and Federal law generally.” H.R.
Conf. Rep. 104-422, at 167, 1995 U.S.C.C._A.N. at 852.
Therefore, preemption under Section 10501(b) was never
intended to apply to all state laws that touch on rail
transportation. See, e.g., Florida East Coast Railway, 266
F.3d at 1331 (preemption only extends to “regulation of
rail transportation”).
Finally, the Second Circuit’s faulty decision is further
evidenced by the illogical result it produces. As discussed
above, see supra pp. 23-24, the per se preemption of
permitting programs such as Act 250 allows many
railroad projects to evade state and local environmental
review. Because many of these projects are also outside of
the STB’s regulatory authority, railroads can operate in a
“regulatory void” — completely free of oversight. Congress
could not have intended this conclusion.
By not following this Court’s precedents and failing to
give the phrase “with respect to regulation of rail
“transportation” the limiting effect that Congress
expressly intended, the Second Circuit erred in
concluding that Act 250 was entirely preempted.
CONCLUSION
For all the foregoing reasons, the petition for a writ of
certiorari should be granted.
Respectfully submitted,
WILLIAM H. SORRELL
Attorney General
State of Vermont
JULY 2005
REBECCA M. ELLIS
JEANNIE ELIAS
TIMOTHY B. TOMASI
KEVIN O. LESKE*
Assistant Attorneys General
109 State Street
Montpelier, VT 05609
(802) 828-3171
Counsel for State of Vermont,
Agency of Natural Resources,
and William H. Sorrell, as
Attorney General of Vermont
(*Counsel of Record)
APPENDIX
la
United States Court of Appeals,
Second Circuit.
GREEN MOUNTAIN RAILROAD CORPORATION,
Plaintiff-Appellee,
Vv.
State of VERMONT, Vermont Agency of Natural
Resources and William H. Sorrell, as Attorney General of
the State of Vermont,
Deferdants-Appellants.
No. 04-0366-CV.
Argued: Dec. 6, 2004.
Decided: April 14, 2005.
*639 Jeanne Elias, Assistant Attorney General for the
State of Vermont, (Rebecca M. Ellis, Bridget Asay,
Assistant Attorneys General, on the brief) Montpelier,
VT, for Defendants-Appellants.
Robert B. Luce, (Eric A. Poehlmann, on the brief)
Downs Rachlin Martin PLLC, Burlington, VT, for
Plaintiff-Appellee.
Evelyn G. Kitay (Ellen D. Hanson, General Counsel, on
the brief) Washington, D.C. for Amicus Curiae Surface
Transportation Board.
Robert M. Jenkins III, David M. Gossett, Mayer Brown
Rowe & Maw LLP, Washington D.C.; Louis P. Warchot,
Dennis J. Starks, Association of American Railroads,
Washington, D.C.; George A. Aspatore, Sarah J. Bailiff,
Paul Guthrie, Thomas J. Healey, Paul R. Hitchcock,
Theodore K. Kalick, Robert T. Opal, Louise Anne Rinn,
Peter J. Shudtz, Sidney L. Strickland, Jr., of Counsel, on
submission, for Amicus Curiae Association of American
Railroads.
2a
Before: CARDAMONE, JACOBS, CABRANES, Circuit
Judges.
JACOBS, Circuit Judge.
Green Mountain ~ Railroad Corporation ("Green
Mountain") proposed to build transloading facilities on its
property in Vermont, and brings this action seeking a
declaration that Vermont's environmental land use
statute, Act 250, Vt. Stat. Ann. Tit. 10, § 6001 et seq., is
for that purpose preempted by the Interstate Commerce
Commission Termination Act of 1995, 49 U.S.C. § 10101
et seg. (the "Termination Act"). The State of Vermont, its
Agency of Natural Resources and the.State Attorney
General appeal from a judgment entered in the United
States District Court for the District of Vermont (Murtha,
J.), granting Green Mountain's motion for summary
judgment on the preemption ground. Green Mountain
R.R. Corp. v. Vermont, No. 01-CV-181, 2003 U.S. Dist.
LEXIS 23774, at *2-3 (D.Vt. Dec. 15, 2003).
The Termination Act expressly preempts "remedies
provided under Federal or State law" and vests with the
Surface Transportation Board (the "Transportation
Board"), a federal agency, exclusive jurisdiction over
"transportation by rail carriers" and "the construction ...
of ... facilities ...." 49 U.S.C. § 10501(b). The term
“transportation” includes a “warehouse ... yard, property,
facility, instrumentality, or equipment of any kind related
to the movement of passengers or property, or both, by
rail." 49 U.S.C. § 10102.
"We review a district court's grant of summary
judgment de novo." See Young v. County of Fulton, 160
F.3d 899, 902 (2d Cir.1998). In so doing, we construe the
evidence in the light most favorable to the State as the
non-moving party, and draw all reasonable inferences in
3a
its favor. See *640 Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). For
the reasons that follow, we affirm.
I
Green Mountain is a "rail carrier" as defined by the
Termination Act, 49 U.S.C. § 10102(5), with 52 miles of
track between Rutland, Vermont and Cold River, New
Hampshire. The line serves transhipping industries, 1.e.,
industries that rely on trucks to transport goods from the
rail site for processing elsewhere. Along its rail line in
Rockingham, Vermont, Green Mountain owns a 66-acre
tract known as “Riverside,” bounded by the Connecticut
River on the east. Portions of Riverside are wetlands
unusable for development.
Green Mountain proposed to build facilities at
Riverside to serve the following operations: (1) unloading
bulk salt arriving by rail for local distribution by truck or
for temporary storage in a shed pending distribution; (2)
temporary storage and transport of "non-bulk goods, such
as steel pipe[s]"; and (3) unloading bulk cement arriving
by rail for storage in silos and eventual transport by
truck. Some of these operations are conducted within a
100-foot strip alongside the Green Mountain tracks and
the Connecticut River.
Vermont argues that construction of the transloading
facilities is subject to Act 250, an environmental land use
statute that mandates preconstruction permits for land
development. Permit applications are filed with one of
nine District Commissions that evaluate environmental
impact using ten criteria, including: "undue water or air
pollution,” Vt. Stat. Ann. Tit. 10, § 6086(a)(1), and "undue
adverse effect on the scenic or natural beauty of the area,
aesthetics, historic sites or rare and irreplaceable natural
4a
areas,’ Vt. Stat. Ann. Tit. 10, § 6086(a)(8). The District
Commission's decisions are appealable to Vermont's
Environmental Board; decisions of the Environmental
Board are appealable directly to the Vermont Supreme
Court. Vt. Stat. Ann. Tit. 10, § 6089(a) & (b). Most permit
decisions under Act 250 are issued within 60 days from
the filing of an application. [FN1]
FN1. Green Mountain contends that this expedited
schedule (as cited by the State) applies only to
"minor" amendments to existing permits, whereas
its proposal is likely to be treated as a “major”
application. State statistics collected from January
1998 through December 2002 indicate that the
average timetable for "major" permit applications
was 303.39 days. More than half of landowner
appeals of District Commission decisions to the
Vermont Environmental board took more than nine
months in 2001.
In 1997, PMI Lumber leased part of Riverside and
applied for an Act 250 construction permit. PMI Lumber
proposed to satisfy environmental criteria by a 75-foot
buffer zone along the-river.—The Vermont Agency of
Natural Resources recommended that the buffer be
increased to 100 feet.
A local permitting agency subsequently issued Land
Use Permit # 2W0038-2 (the "dash-2 permit") in the
names of PMI Lumber and Green Mountain. Condition
14 required maintenance of a 100-foot buffer zone. When
PMI Lumber ceased operations at the site, Green
Mountain used it for its transloading activities. Green
Mountain encroached on the buffer zone with a settling
pond, storage of materials, and vehicles.
5a
In Spring 1998, Green Mountain sought to amend the
dash-2 permit to allow construction of a 100-foot by 275-
foot salt storage shed. In January 1999, the State
granted Land Use Permit # 2W0038-3 (the "dash-3
permit"), which stipulated conditions, including that the
shed be rectangular, and either brown or dark green.
Several months later, in October 1999, Green Mountain
applied for another permit *641 amendment (the "dash-
3B permit" application) to modify the size, color and
location of the salt shed. Although no such permit issued,
Green Mountain started construction of its modified salt
shed in November 1999.
In January 2000, the State issued a notice of violation
of the dash-2 permit, citing (among other things) storage
of materials within the 100-foot buffer zone. The State
issued a second notice of violation in February 2000,
alleging construction of the salt shed without the dash-3B
permit.
In Spring 2000, the State conducted hearings on Green
Mountain's dash-3B salt shed permit application. Green
Mountain objected orally and in writing that the State
Environmental Commission lacked jurisdiction to
adjudicate the pending permit application because the
Termination Act, which expressly preempts "remedies
provided under Federal or State law" and vests with the
Transportation Board, a federal agency, exclusive
jurisdiction over "transportation by rail carriers," 49
U.S.C. § 10501, preempts Act 250.
_Faced with the threatened enforcement of Act 250,
Green Mountain filed this suit in June 2001, seeking a
declaration that the Termination Act preempts Act 250.
Simultaneously, Green Mountain requested a declaratory
order to the same effect from the Transportation Board.
6a
The Transportation Board denied the declaratory relief
in May 2002, deferring to the district court. In the
meantime, the State moved to dismiss the district court
action. While that motion was pending, the State issued
the dash-3B permit in August 2001. A month later, the
district court granted the State's motion to dismiss Green
Mountain's facial challenge to the applicability of Act 250,
but ordered “further development of the record" to
determine whether the State's “effort to enforce one or
more conditions of the [dash-2] Permit violates the
[Termination Act] in this particular case." Green
Mountain R.R., No. 1: 01CV181, 2003 U.S. Dist. LEXIS
23774, at *2 (quoting an earlier ruling) (internal
quotation marks omitted).
Following discovery, the parties cross-moved for
summary judgment. On December 15, 2003, the court
granted Green Mountain's motion (and denied the State's
motion) on the ground that “the state's efforts to enforce
Act 250 in this case are preempted under the
[Termination Act]." Id.
II
The question presented is whether the Termination Act
preempts Vermont's Act 250 with respect to the
underlying permit controversy. State law is preempted by
- federal law when: (1) the preemptive intent is " ‘explicitly
stated in [a federal] statute's language or implicitly
contained in its structure and purpose’ "; (2) state law
“actually conflicts with federal law"; or (3) “federal law so
thoroughly occupies a legislative field ‘as to make
reasonable the inference that Congress left no room for
the States to supplement it.' “ Cipollone v. Liggett Group,
Inc., 505 U.S. 504, 516, 112 S.Ct. 2608, 120 L.Ed.2d 407
(1992) (quoting Jones v. Rath Packing Co., 430 U.S. 519,
7a
525, 97 S.Ct. 1805, 51 L.Ed.2d 604 (1977), and Fidelity
Fed. Sav. & Loan Ass'n v. De la Cuesta, 458 U.S. 141,
153, -102 S.Ct. 3014, 73 L.Ed.2d 664 (1982)). The
"ultimate touch-stone" of preemption analysis is
congressional intent: "Congress' intent, of course,
primarily is discerned from the language of the pre- -
emption statute and the statutory framework
surrounding it." Medtronic, Inc. v. Lohr, 518 U.S. 470,
485-86, 116 S.Ct. 2240, 135 L.Ed.2d 700 (1996) (internal
quotation marks omitted).
The Termination Act contains an express. preemption
clause:
Except as otherwise provided in this part, the
remedies provided under this *642 part with respect
to regulation of rail transportation are exclusive and
preempt the remedies provided under Federal or
State law.
49 U.S.C. § 10501(b). The Termination Act Section
10501 vests the Transportation Board with exclusive
jurisdiction over “transportation by rail carriers" and "the
construction, acquisition, operation, abandonment, or
discontinuance of spur, industrial, team, switching, or
side tracks, or facilities, even if the tracks are located, or
intended to be located, entirely in one State." 49 U.S.C. §
10501(b). “Transportation” is expansively defined to
include: “a locomotive, car, vehicle, vessel, warehouse ...
yard, property, facility, instrumentality, or equipment of
any kind related to the movement of passengers or
property, or both, by rail." 49 U.S.C. § 10102(9).
Certainly, the plain language grants the Transportation
Board wide authority over the transloading and storage
facilities undertaken by Green Mountain. See City of
Auburn v. United States, 154 F.3d 1025, 1029-31 (Sth
8a
Cir.1998); see also R.R. Ventures, Inc. v. STB, 299 F.3d
523, 530 (6th Cir.2002) ("{Iif a railroad line falis within its
jurisdiction, the [Transportation Board's) authority over
abandonment is both exclusive and plenary.").
Other federal courts recognize that the Termination
Act preempts most pre-construction permit requirements
imposed by states and localities. See, e.g., City of Auburn,
154 F.3d at 1030-31 (affirming the Transportation Board's
finding that the Termination Act preempted a local
environmental permitting requirement); Soo Line R.R.
Co. v. City of Minneapolis, 38 F.Supp.2d 1096, 1101
(D.Minn.1998) ("The Court concludes that the City's
demolition permitting process upon which Defendants
have relied to prevent [the railroad] from demolishing five
buildings ... that are related to the movement of property
by rail is expressly preempted by the [Termination Act].");
CSX Transp., Inc. v. Ga. Pub. Serv. Comm'n, 944 F.Supp.
1573, 1585 (N.D.Ga.1996) (finding state regulation of
railroad agency closing preempted by the Termination
Act).
For example, the Ninth Circuit concluded, in affirming
a Transportation Board decision, that the Termination
Act preempted state and local environmental regulations
requiring a railway to submit to a permitting process
before making repairs and improvements on its track line.
City of Auburn, 154 F.3d at 1027-28, 1030-31.
"[C)ongressional intent is clear, and the preemption of rail
activity is a valid exercise of congressional power under
the Commerce Clause." Jd. at 1031; see also Ga. Pub.
Serv. Comm'n, 944 F.Supp. at 1580-82.
The Transportation Board has likewise ruled that
"state and local permitting or preclearance requirements
(including environmental requirements) are preempted
9a
because by their nature they unduly interfere with
interstate commerce." Joint Petition for and Declaratory
Order--Boston and Maine Corp. and Town of Ayer, MA,
STB Finance Docket No. 33971, 2001 WL 458685, at *5
(S.T.B. Apr. 30, 2001), affd, Boston & Maine Corp. v.
Town of Ayer, 191 F.Supp.2d 257 (D.Mass.2002)(affirming
the Transportation Board's determination that town's
pre-construction permit requirement was preempted by
the Termination Act); see also Green Mountain R.R. Corp.,
Petition for Declaratory Order, STB Finance Docket No.
34052, 2002 WL 1058001 (S.T.B: May 24, 2002). As the
agency authorized by Congress to administer the
Termination Act, the Transportation Board is " ‘uniquely
qualified to determine whether state law ... should be
preempted' " by the Termination Act. [FN2] *643 Ga.
Pub. Serv. Comm'n, 944 F.Supp. at 1584 (quoting
Medtronic, 518 U.S. at 496, 116 S.Ct. 2240).
FN2. Whether the Transportation Board is entitled
to deference under Chevron U.S.A., Inc. v. Natural -
Res. Def. Council, Inc., 467 U.S. 837, 843-44, 104
S.Ct. 2778, 81 L.Ed.2d 694 (1984) is not material to
the Court's decision. We therefore decline to reach
the issue.
Like the regulations and ordinances consistently struck
down by federal courts and by the Transportation Board,
Act 250 mandates a pre-construction permit. Act 250's
pre-construction permit requirement is preempted for two
reasons: (i) it "unduly interfere[s) with interstate
commerce by giving the local body the ability to deny the
carrier the right to construct facilities or conduct
operations," Town of Ayer, STB Finance Docket No.
33971, 2001 WL 458685, at *5; and (ii‘ it can be time-
consuming, allowing a local body to delay construction of
10a
railroad facilities almost indefinitely. Green Mountain
R.R. Corp., 2003 U.S. Dist. LEXIS 23774, at *13.
Nevertheless, as the district court observed, “not all
state and local regulations are preempted [by the
Termination Act]; local bodies retain certain police
powers which protect public health and safety." Jd. It
therefore appears that states and towns may exercise
traditional police powers over the development of railroad
property, at least to the extent that the regulations
protect public health and safety, are settled and defined,
can be obeyed with reasonable certainty, entail no
extended or open-ended delays, and can be approved (or
rejected) without the exercise of discretion on subjective
questions. Electrical, plumbing and fire codes, direct
environmental regulations enacted for the protection of
the public health and safety, and other generally
applicable, non-discriminatory regulations and permit
requirements would seem to withstand preemption. Cf.
Vill. of Ridgefield Park v. New York, Susquehanna & W.
Ry. Corp., 163 N.J. 446, 750 A.2d 57, 64 (2000) (noting the
Transportation Board's position that: (1) "while state and
local government entities ... retain certain police powers
and may apply non-discriminatory regulation to protect
public health and safety, their actions must not have the
effect of foreclosing or restricting the railroad's ability to
conduct its operations or otherwise unreasonably
burdening interstate commerce"; and (2) “railroads are
exempt from the traditional permitting process but not ...
from most other generally applicable laws").
The legislative history of the Termination Act supports
this approach: "Although States retain the police powers
reserved by the Constitution, the Federal scheme of
economic regulation and deregulation is intended to
lla
address and encompass all such regulation and to be
completely exclusive." See H.R.Rep. No. 104-311, at 96
(1995), reprinted in 1995 U.S.C.C.A.N. 793, 808. We need
not draw a line that divides local regulations between
those that are preempted and those that are not, because
in this case preemption is clear: the railroad is restrained
from development until a permit is issued; the
requirements for the permit are not set forth in any
schedule or regulation that the railroad can consult in
order to assure compliance; and the issuance of the permit
awaits and depends upon the discretionary rulings of a
state or local agency.
Ill
The State's primary appellate argument is that Act 250
cannot be preempted on its face unless there is “no
possible set of conditions that [the permitting authority]
could place on its permit that would not conflict with
federal law." See Cal. Coastal Comm'n v. Granite Rock
Co., 480 U.S. 572, 580, 107 S.Ct. 1419, 94 L.Ed.2d 577
(1987) (applying facial challenge standard in a statutory
preemption case). We disagree. *644 No doubt, there
could be permit applications affecting railroad facilities
that could be promptly approved without the slightest
imposition on rail operations. However, what is
preempted here is the permitting process itself, not the
length or outcome of that process in particular cases. Cf.
Chamber of Commerce v. Lockyer, 364 F.3d 1154, 1169
(9th Cir.2004) (noting that in certain situations federal
law preempts "the act of regulation itself, net the effect of
the state regulation in a specific factual situation”).
California Coastal Commission is easily distinguished on
that basis, as well as on the absence of a preemption
provision. [FN3]
12a
FN3. In California Coastal Commission, a mining
company sought to enjoin a state agency from
requiring the company to obtain a permit to mine on
federal land. The Supreme Court ruled that in the
federal mining statutes, “Congress specifically
disclaimed any intention to pre-empt pre-existing
state authority” and that the federal mining statute
"does not automatically pre-empt all state
regulation of activities on federal lands." 480 U.S.
at 593, 107 S.Ct. 1419. The federal mining statutes
required that land-use plans of the federal agency
charged with administering the federal mining
statutes "provide for compliance with" existing state
and federal environmental laws. Jd. at 587, 107
S.Ct. 1419 (internal quotation marks omitted).
Because the mining company sought injunctive
relief “before discovering what conditions the
Coastal Commission would have placed on the
permit," the Court concluded that the mining
company's "case must stand or fal] on the question
whether any possible set of conditions attached to
the Coastal Commission's permit requirement
would be pre-empted." Jd. at 588, 107 S.Ct. 1419.
Vermont failed to raise explicitly this facial
preemption argument with the district court. As a
result, the district court's opinion does not discuss -
California Coastal Commission. Generally, we do
not consider an issue raised for the first time on
appeal. See Silverman v. Mut. Benefit Life Ins. Co.,
138 F.3d 98, 103 (2d Cir.1998). However, Vermont
points out that, although it never cited to California
Coastal Commission in its submissions to the
district court, it preserved this issue for appellate
13 a
review by arguing, in its August 2001 reply to Green
Mountain's oppusition to its motion to dismiss, that
to succeed on its facial preemption claim, Green
Mountain was obligated to show “that there are no
circumstances under which Act 250 could be found
constitutional," and did not press the argument
thereafter because it believed that the district court
adopted the State's positiori on facial preemption
when it stated, granting in part the State's motion
to dismiss: “to the extent the [State] ask[s] the
Court to dismiss Green Mountain's claim that the
[Termination Act] preempts Act 250 under all
circumstances, the motion is granted."
"The facial/as-applied distinction would be relevant
only if we might find some applications of the statute
preempted and others not.... [WJhere a state statute is in
direct conflict" with a federal statute “or one of its
processes,” the “focus is the act of regulation itself, not the
effect of the state regulation in a specific factual
situation.” Lockyer, 364 F.3d at 1169.
IV
The State argues that Act 250 withstands preemption
because it is an environmental, rather than economic,
regulation. The distinction is not useful. "[I]f local
authorities have the ability to impose ‘environmental’
permitting regulations on the railroad, such power will in
fact amount to ‘economic regulation’ if the carrier is
prevented from constructing, acquiring, operating,
abandoning, or discontinuing a line." City of Auburn, 154
F.3d at 1031. Green Mountain serves industries that rely
on trucks to transport goods from the rail site for
processing; so the proposed transloading and storage
facilities are integral to the railroad's operation and are
l4a
easily encompassed within the Transportation Board's
exclusive jurisdiction over "rail transportation."
Notwithstanding the environmental goals of the
legislation, Act 250's permitting process "necesserily
interfere[s]" with Green Mountain's “ability to construct
facilities and conduct economic activities." Green *645 —
Mountain R.R. Corp., 2003 U.S. Dist. LEXIS 23774, at
*13.
Vv
The State argues that Ace Auto Body & Towing, Ltd. v.
City of New York, 171 F.3d 765 (2d Cir.1999), compels a
different conclusion. In Ace Auto Body, this Court held
that the section of the Termination Act relating to motor
carrier operations (49 U.S.C. § 14501) did not preempt
New York's police power to suppress the practice of
“chasing,” whereby tow trucks compete for business by
racing ("often recklessly") to accidents broadcast on police
radio frequencies. Ace Auto Body, 171 F.3d at 769, 779.
The State's reliance on Ace Auto Body is misplaced. The
federal preemption language at issue in that case
provides that a state or municipality "may not enact or
enforce a law ... related to a price, route, or service of any
motor carrier ... with respect to the transportation of
property." Jd. at 770 (quoting 49 U.S.C. § 14501(c\(1)).
The Court held that the "related to” phrase focused the
preemption on economic regulations and reflected
congressional intent to leave the state's historic police
powers undisturbed where “only incidental economic
burdens can be discerned." Id. at 774. We concluded that
the chasing regulations were “sufficiently safety-oriented"
while having no more than an incidental economic effect
on the industry. Id.
15a
In contrast to the federal statute at issue in Ace Auto
Body, the plain language of Section 10501 reflects clear
congressional intent to preempt state and local regulation
of integral rail facilities. "It is difficult to imagine a
broader statement of Congress's intent to preempt state
regulatory authority over railroad operations." Ga. Pub.
Serv. Comm'n, 944 F.Supp. at 1581 (holding that the
Termination Act preempted state regulation of railroad
agency closing). We therefore need not conduct a fact-
based inquiry weighing the economic impact of Act 250's
permitting process upon Green Mountain; based on the
facts before the Court, the State's effort to regulate rail
transportation through the Act 250 pre-permitting
process is necessarily preempted by the Termination Act.
CONCLUSION
For the foregoing reasons, we affirm the judgment of
the district court.
404 F.3d 638
16a
UNITED STATES DISTRICT COURT
- DISTRICT OF VERMONT
GREEN MOUNTAIN RAILROAD
CORPORATION
V.
STATE OF VERMONT, VERMONT AGENCY OF
NATURAL RESOURCES, AND WILLIAM H. SORRELL,
as Attorney General of the State of Vermont
RULING ON CROSS MOTIONS FOR
S x ME
(Papers 52 and 63)
This case involves the extent to which, consistent with
the Interstate Commerce Commission Termination Act of
1995 (hereinafter "ICCTA"), the State of Vermont and its
Agency of Natural Resources (collectively referred to as
"defendants" or the "state") may apply its environmental
regulation statute, Act 250, to the Green Mountain
Railroad Corporation's (hereinafter "Green Mountain")
use and expansion of its facilities in Rockingham. The
state argues the railroad’'s activities must comply with
Act 250 and all permits issued thereunder. Green
Mountain's position is any application of Act 250 is
preempted by the ICCTA.
On July 17, 2001, the state moved to dismiss the
plaintiff's facial challenge to the applicability of Act 250
for failure to state a claim upon which relief can be
granted. See Defendants’ Motion to Dismiss or, in the
Alternative, to Abstain (Paper 9) at 1. Finding this
17a
preemption issue “requires case-by-case analysis," the
Court held: "[T]o the extent the defendants ask the Court
to dismiss Green Mountain's claim that the ICCTA
preempts Act 250 under ail circumstances, the motion is
granted.. | However, whether the defendants’ effort to
enforce one or more conditions in the 1997 Permit violates
the ICCTA in this particular case requires further
development ofthe record . . ." Ruling on Pending
Motions (Paper 21) at 8, 10. ;
Having provided the Court with a record supplemented
by affidavits and discovery, the parties have filed cross
motions for summary judgment. Upon review of the
undisputed, material facts, the Court finds the state's.
efforts to enforce Act 250 in this case are preempted
under the ICCTA. Therefore, for the reasons discussed
below, Green Mountain's Motion for Summary Judgment
is GRANTED, and the state defendants' Motion for
Summary Judgment is DENIED.
I. Background
On a motion for summary judgment, the moving party
has the initial burden of informing the Court of the basis
for its motion and of identifying the absence of any
genuine issue of material fact. See, e.g., Chambers v.
TRM Copy Centers,, Corp., 43 F.3d 29, 36 (2d Cir. 1994).
Where, as here, a motion for summary judgment is
supported by affidavits or other documentary evidence,
the party opposing that motion must set forth specific
facts showing there is a genuine, material issue for trial.
See Rexnord Holdings, Inc. v. Bidermann, 21 F.3d 522,
526 (2d Cir. 1994). Only disputes over facts which might
affect the outcome of the suit under the governing law
preclude the entry of summary judgment. See Anderson v.
Liberty Lobby, Inc., 477 U.S. 242, 248 (1986).
18a
Upon review of the record, the Court finds the following
material facts undisputed. Green Mountain has 52 miles
of track between Rutland, Vermont and Cold River, New
Hampshire. See generally Verified Statement of Jerome
Hebda (hereinafter "Hebda Statement"Xappended to
Paper 65 as Ex. A). It primarily operates as an interstate
freight railroad, although it derives approximately 10
percent of its revenue from passengers. See Hebda
Statement at para. 3.
About six years ago, in an attempt to expand its
business and increase profitability, Green Mountain
acquired 62 acres of land to add to its existing site in
Rockingham known as "Riverside." Riverside now is
approximately 66 acres and is bounded on the west by a
state highway and Green Mountain's railroad line and on
the east by the Connecticut River. Green Mountain uses
Riverside as a yard for transloading freight between
trains and trucks and for storing freight and railroad
equipment. See, e.g., Hebda Statement at paras. 4, 8.
The Riverside site is within the jurisdiction of
Vermont's District #2 Environmental Commission
(hereinafter the “District 2 Commission"). On November
12, 1997, Green Mountain and its then tenant, PMI
Lumber Transfer, Inc. (hereinafter "PMI"), obtained from
the District 2 Commission Permit #2W0038-2 (hereinafter
the "Dash 2 Permit"). See Dash 2 Permit (appended to
Paper 55, Affidavit of April Hensel, as Ex. C). The Dash 2
Permit authorized the construction of a 20-foot by 30-foot
office building and the operation of a forest products
distribution yard. See Dash 2 Permit at 1. It also
contained 27 conditions, including: "The permittees shall
maintain a 100-foot undisturbed, naturally vegetated
buffer strip with no mowing or cutting of vegetation
19a
between the top of the bank of the Connecticut River and
any disturbed areas." Dash 2 Permit at para. 14. PMI left
Riverside in 1998, and Green Mountain continued using
the site for transloading activities. See Hebda Statement
at para. 8.
On January 13, 1999, the District 2 Environmental
Commission issued Green Mountain Permit #2W0038-3
(hereinafter the "Dash 3 Permit"), which authorized the
railroad to construct a salt storage shed, conveyor pit, rail
siding and truck scale at Riverside. See Dash 3 Permit
(appended to Paper 55, Affidavit of April Hensel, as Ex.
E) at 1. The Dash 3 Permit contained 24 conditions,
including that the storage shed be rectangular, next to
the rail, and either brown or dark green. See Dash 3
Permit at para. 19.
Green Mountain eventually abandoned the Dash 3
Permit project as originally proposed and, on October 14,
1999, submitted another permit application, which the
District 2 Commission delineated permit application
#2W0038-3B (hereinafter the "Dash 3B permit"). See
Dash 3B Permit Application (appended to Paper 55,
Affidavit of April Hensel, as Ex. F). The Dash 3B Permit
Application included a proposal for a new salt siding
project and a different salt shed to be built in a different
location from the one first proposed in the Dash 3 Permit.
Although no final "Dash 3B Permit" was issued, Green
Mountain built its proposed salt transload and storage
shed.
On January 24, 2000, the District 2 Commission issued
Green Mountain a notice of alleged violation of several
conditions of the Dash 2 Permit, primarily relating to the
failure to maintain the 100-foot buffer zone. Specifically,
the state asserts the railroad has conducted prohibited
20a
activities in the buffer zone, including storing brick,
lumber and train parts, permitting the entry of vehicles
in the zone, and arranging for the installation of utility
poles. See Notice of Alleged Violation (appended to Paper
55, Affidavit of April Hensel, as Ex. G). Several weeks
later, on February 8, 2000, it issued a notice of violation
to Green Mountain for its construction of the "Dash 3B"
salt shed without a permit. See Notice of Alleged
Violation (appended to Paper 55, Affidavit of April
Hensel, as Ex. H). |
Anticipating an unfavorable outcome in _ state
administrative proceedings, in October 2001, and again in
February 2002, Green Mountain requested a declaratory
order from the Surface Transportation Board (hereinafter
"STB"). Through those requests, it sought permission to
continue construction at Riverside to permit it to
transload bulk cement and otherwise expand its
operations. According to Green Mountain, its proposed
facility requires construction of a spur track within the
100-foot buffer zone. Citing this Court's enforcement
authority and its intent to resolve these issues without
referring the matter, the STB declined to issue the
requested declaratory order. See In re Green Mountain,
Railroad Corp., STB Finance Docket No. 34052, 2002 WL
1058001 (ICC)(May 24, 2002) (appended io Paper 65 at
Ex. S).
In December 2002, Green Mountain requested a
declaratory ruling from Vermont's District Environmental
Coordinator as to whether its proposed construction of
cement silos and a utility building requires an
amendment to its existing Act 250 permit or whether the
project falls within a statutory exception to the permit
requirement. The District Coordinator determined an
2la
amendment to the permit was required, and Green
Mountain appealed the jurisdictional opinion to the
Environmental Board. The Environmental Board held a
hearing on Green Mountain's appeal on June 25, 2003,
and ultimately affirmed the District Coordinator's
advisory opinion. See Declaratory Ruling #422 (appended
to Paper 65 as Ex. I) at 8, sections B and C.
According to Green Mountain's president, Jerome
Hebda, the expansion of Riverside that has thus far been
completed has been "modestly successful." See Hebda
Affidavit at para. 5 (In 1997, Green Mountain originated
and terminated 416 carloads; by 2000, that number had
nearly doubled). Nevertheless, Mr. Hebda maintains the
state's Act 250 requirements are economically
detrimental to the railroad's operations. He explains:
[T]he circumstances now faced by GMRC [Green
Mountain] are not the same as those we faced in
1997, when PMI and GMRC jointly sought Act 250
authority to construct an office building and forest
' products distribution yard at Riverside. The
expansion of GMRC's Riverside business since that
time requires that GMRC utilize its property more
extensively than appeared to be necessary in 1997.
Ground storage of goods that have arrived by rail
and await removal by truck, or which arrive by
truck and await loading into rail cars, is an
essential part of our business and requires more
land as the business grows. Our customers have
requested rate quotations from GMRC that include
transloading and temporary storage of goods
between rail and truck shipments, and GMRC has
provided such rates in order to attract and retain
the business. . . . Moreover, storage areas must be
22 4
interspersed with passageways for vehicular access
and must be situated as closely as possible to rail
tracks in order to minimize the distance and time
consumed in the removal of shipments from railcars
and the loading of shipments into railcars... .
Electric service is needed at the site to provide
electric power and illumination during short days.
Depriving GMRC of the use of all land at Riverside
within 100 feet of the Connecticut River would not
only bring business growth to a standstill, but limit
GMRC's ability to handle existing business.
Hebda Statement at para. 22.
II. Discussion
A. Act 250 as a Preclearance Statute
Act 250 is Vermont's land use statute. It was enacted to
protect the state's environmental resources and to
preserve its public lands. See Southview Assoc. v.
Bongartz, 980 F.2d 84, 89 (2d Cir. 1992). The Act
establishes a statewide pertitting process for various
forms of land development. Sce 10 V.S.A. § 6001-6108.
When implementing Act 250, the state attempts to
coordinate maximum economic development with
minimal environmental impact. As applied, however, Act
250 establishes a preclearance permitting process; a
development subject to Act 250 cannot proceed until it
has received state approval and an Act 250 permit. See In
re Spring Brook Farm Found., Inc., 164 Vt. 282, 285
(1995)("Vermont's land use law, Act 250, requires a
permit prior to the commencement of any development.”)
When Green Mountain and PMI, a _ non-railroad
business, jointly operated at Riverside, the site arguably
had been partially subject to Act 250 regulation, as least
so far as PMI's activities were concerned. Now, as a rail
23 a
carrier operating alone at Riverside, Green Mountain's
activities are subject to oversight under the ICCTA, 49
U.S.C. §§ 10101 et seq., as administered by the STB, 49
U.S.C. § 10501.
The plaintiff maintains all conditions included in
permits issued pursuant to Act 250 now are preempted by
the ICCTA, and the state cannot enforce its permits or
require a new permit for the proposed Riverside
expansion. "State law is preempted by federal law only
when 1) a federal statute expressly preempts state action,
2) state law is in direct conflict with federal law, or 3)
federal regulation is pervasive in the field." Omva, Inc. v.
Vermont, 80 F. Supp. 2d 211, 217 (D. Vt. 2000) (citing
Cipollone v. Ligaett Group, Inc.,, 505 U.S. 504, 516
(1992)).
The ICCTA contains the following preemption provision:
The jurisdiction of the [STB] over
(1) transportation by rail carriers, and the remedies
provided in this part with respect to rates,
classifications, rules (including car_ service,
interchange, and other operating rules), practices,
routes, services, and facilities of such carriers; and
(2) the construction, acquisition, operation,
abandonment, or discontinuance of spur, industrial,
team, switching, or side tracks, or facilities, even if
the tracks are located, or intended to be located,
entirely in one State,
is exclusive. Except as otherwise provided in this
part, the remedies provided under this part with
respect to regulation of rail transportation are
exclusive and preempt the remedies provided under
Federal or State law.
49 U.S.C. § 10501(b).
By this provision, Congress granted the STB broadened
preemptive jurisdiction over facilities that are an integral
part of railroad transportation. See City of Auburn v.
United States, 154 F.3d 1025, 1029-31 (9th Cir. 1998); see
also CSX Trans. Corp. v. Georgia Pub. Serv. Comm'n, 944
F. Supp. 1573, 1585 (N.D. Ga. 1996)(ICCTA preempts
state regulatory authority over rail agency closings).
When addressing the preemptive scope of 49 U.S.C. §
10501(b), courts have found most zoning ordinances and
local land use permit requirements are preempted. See,
e.q., Railroad Ventures, Inc. v. STB, 299 F.3d 523, 530
(6th Cir. 2002)"if a railroad line falls within its
jurisdiction, the STB's authority over abandonment is
both exclusive and plenary"); CSX Transp., Inc. v. City of
- Plymouth, 92 F. Supp. 2d 643, 659 (E.D. Mich. 2000)"if
there is to be a limit on the amount of time that a train is
preempted because they necessarily interfere with a rail
permitted to block a crossing, it must come from the
federal government”), affd, 283 F.3d 812 (6th Cir. 2002);
see also Guckenberg v. Wisconsin Cent. Ltd., 178 F. Supp.
2d 954, 959 (E.D. Wis. 2001) (common law nuisance claim
is preempted where suit “seeks to proscribe activity ... on
[railway's] side track").
Specifically, courts have noted that preclearance
requirements, including environmental requirements, are
carrier's ability to construct facilities and conduct
economic activities. "To the extent the state law is viewed
as having the effect of requiring the railroad to undergo
substantial capital improvements, [it] is preempted by the
Interstate Commerce Commissicn Termination Act.” CSX
Transp., 92 F. Supp. 2d at 658.
25a
Nevertheless, not all state and local regulations are
preempted; local bodies retain certain police powers which
protect public health and safety. See Dakota, Minnesota
& Eastern R.R. Corp. v. South Dakota, 236 F. Supp. 2d
989, 1011 (D.S.D. 2002) (state eminent domain statute
which requires railroad to provide free easement to utility
companies is not preempted by ICCTA); Laviqne v. CXS
Transp., Inc:, 2002 WL 1424808 (Mich. App. 2002)
(affirming trial court's granting-of an easement by
necessity over tracks for access to plaintiff's property). For
example, the Vermont Supreme Court has found certain
City of Burlington zoning ordinances are not preempted
by the ICCTA, including "control activities such as
routing of trucks leaving the facility," and “vonditions
designed to avert potential contamination from the salt
shed" because such regulations do not interfere with
railroad operations, but rather address matters within a
municipality's traditional police pewers. See In re
Vermont Ry., 171 Vt. 496 (2000). The parameters of
ICCTA preemption have been elucidated in some STB
decisions as well As the agency charged with
administering the ICCTA, the STB's interpretation of the
statute and its preemptive reach is entitled to
consideration. See Chevron U.S.A., Inc. v. Natural Res.
Def. Council, Inc., 467 U.S. 837, 843-44 (1984); In re
Vermont Ry., 171 Vt. at 500.
In Joint Petition for Declaratory Order-Boston and
Maine Corp. and Town of Aver, STB Finance Docket No.
33971, 20C1 WL 458685 (ICC) at *5-6 (Apr. 30, 2001), the
STB provided guidance as to how 49 U.S.C. § 1051(b)
applies to state and local regulation of an existing facility.
In part, the STB opined:
26 a
Court and agency precedent interpreting the
statutory preemption provision have made it clear
that, under this broad preemption regime, state and
local regulation cannot be used to veto or
unreasonably interfere with railroad operations.
Thus, state and local permitting or preclearance
requirements (including environmental
requirements) are preempted because by their
nature they unduly interfere with interstate
commerce by giving the local body the ability to
deny the carrier the right to construct facilities or
conduct operations. . . .
This does not mean that all state and local
regulations that affect railroads are
preempted ... . [S]tate and local regulation is
permissible where it does not interfere with
interstate rail operations, and localities retain.
certain police powers to protect public health and
safety. For example, non-discriminatory
enforcement of state and local requirements such as
building and electrical codes generally are not
preempted .... While a locality cannot require
permits prior to construction, the courts have found
that a railroad can be required to notify the local
government “when it is undertaking an activity for
which another entity would require a permit” and to
furnish its site plan to the local government. .
Furthermore, a town may seek court enforcement of
voluntary agreements that the town had entered
into with a railroad, notwithstanding section
10501(b), because the preemption provisions should
not be used to shield the carrier from its own
commitments, and "voluntary agreements must be
27a
seen as reflecting the carrier's own determination
and admission that the agreements would not
unreasonably interfere with interstate commerce.” .
Finally, nothing in section 10501(b) is intended to |
interfere with the role of state and local agencies in
implementing Federal environmental statutes, such as
the Clean Air Act. . . . Thus, the lack of a specific
environmental remedy at the Board or under state and
local laws (as to construction projects such as this, over
which the Board lacks licensing power) does not mean
that there are no environmental remedies under other
Federal laws.
Of course, whether a particular Federal environmental
statute, local land use restriction, or other local regulation
is being applied so as to not unduly restrict the railroad
from conducting its operations, or unreasonably burden
interstate commerce, is a fact-bound question.
Accordingly, individual situations need to be reviewed
individually to determine the impact of the contemplated
action on interstate commerce and whether the statute or
regulation is being applied in a discriminatory manner, or
being used as a pretext for frustrating or preventing a
particular activity, in which case the application of the
statute or regulation would be preempted. (citations and
footnotes omitted).
Thus, local governments may require railroads such as
Green Mountain, in advance of construction, to “share
their plans with the community, when they are
undertaking an activity for which another entity would
require a permit... ." Id. at *7; see also 49 C.F.R. §
1105.1 et seq. (administrative rules which ensure the
STB's consideration of environmental and energy factors
28 a
under federal laws like NEPA). It is clear that, in cases
such as this one, they may not apply a law like Act 250 so
as to require pre-construction approval and permitting.
Such a procedure is preempted by the ICCTA. See Cities
of Auburn and Kent, Wa.-Petition for Declaratory Order-
Burlington Northern Railroad Co-Stampede Pass Line,
STB Finance Docket No. 33200, 1997 WL 362017
(ICC)(July 1, 1997) (state or local permitting process for
prior approval of project, even an environmental review
process, is preempted).14
B. The Salt Shed
The state, in part, contends Green Mountain built a salt
shed prior to obtaining an Act 250 permit and continues
to use the salt shed without a permit. See Defendants’
Reply Memorandum (Paper 66) at 13. This claim is
somewhat confusing in that the Dash 3 Permit authorizes
"the construction and operation of a 100-foot by 275-foot
salt storage shed, conveyor pit, rail siding and truck
scale." See Dash 3 Permit at 1. In any event, as discussed
supra, the state cannot order Green Mountain to obtain
an Act 250 permit prior to constructing a salt shed
because this action would operate as a prohibited
preclearance requirement.
The January 13, 1999 permit also provides, "[t]he
building shall be either brown or dark green in color to
mitigate the visual impact of its 300 [foot] length." Dash 3
Permit at para. 19. The Dash 3 Permit Application later
proposed the building would be an "“earthtone" or
“sandstone” color. See Dash 3B Application at criterion 8.
The state maintains the roof of the salt shed is "beige"
and does not comply with the permit's requirement of
being either "brown" or "dark green.” See Defendants'
Memorandum of Law (Paper 53) at 17 n.5.
29 a
At most, this appears to be a de minimis transgression.
Green Mountain argues that, to comply with the state's
"color demand," it “would essentially have to scrap the old
shed and construct a new one." Plaintiffs Memorandum
of Law (Paper 64) at 23. Any order requiring substantial
“renovation or destruction to the salt shed because of its —
color would obviously unduly interfere with rail
operations and thereby run afoul of the ICCTA. In any
event, assuming this "color" requirement is similar to a
non-discriminatorily-applied planning and zoning
requirement which the STB has suggested is within local
discretion, the Court concludes that the color "tan" is
sufficiently "brown" or "“earthtone" so as to be in
compliance with the Dash 3 Permit's requirement.
C. Planned Cement Silo and Spur Track
Green Mountain also has proposed improvements at
Riverside which include a rail siding, a new roadway, four
22foot-diameter silos to hold cement, ramps, and a 12' x
20' office and utility building. If operated as planned, the
cement cargo will arrive in hopper cars, be dumped into a
pit, moved by a conveyor belt into a silo, and then
dispensed from the silo to trucks for distribution.
According to Green Mountain, this project "requires
alterations to existing rail track, a truck scale, and
modification of vehicular access, and - like the salt shed
siding - will involve less than 10 acres of disturbed land."
See Paper 64 at 14.
The cement silos Green Mountain has proposed to
construct for use by a transloading customer will have a
500-ton capacity, the equivalent of five rail cars, and will
approach 100 feet in height. If necessary, the railroad will
employ sound barriers to diffuse undue noise. See Hebda
Statement at para. 14. The Green Mountain customer
30a
which plans to use these silos will generate approximately
$180,000 per year in revenue. See Hebda Statement at
para. 16. Green Mountain also explains that it plans
to construct a 1000 foot spur track to enhance commercial
flexibility for its customers. See Hebda Statement at para.
19.
"[WIhen section 10501(b) grants the STB exclusive
jurisdiction over ‘transportation by rail carriers’," it
logically includes the yard, property, facilities, and any
intermodal equipment used in connection with a railroad,
or related to the movement of passengers or property."
Soo Line R.R. Co. v. City of Minneapolis, 38 F. Supp. 2d
1096, 1099 (D. Minn. 1998). While the state has the right
to review these plans, it cannot, consistent with ICCTA
preemption, require Green Mountain to secure Act 250
permits before commencing construction.
C. The Buffer Strip
Condition 14 of the Dash 2 Permit requires Green
Mountain to maintain a 100-foot undisturbed, naturally
vegetated buffer strip with no mowing or cutting of
vegetation between the top of the bank of the Connecticut
River and any disturbed areas. This condition was
renewed in the Dash 3 Permit. It is undisputed that
Green Mountain's activities and construction have
disturbed portions of the strip.
According to the plaintiff, of the approximately 66 acres
at the Riverside site, about 31 acres are unusable
wetlands. Of the remaining 35 acres, the state-imposed
buffer zone consumes approximately 19 acres, thereby
severely restricting the railroad's ground storage capacity
and other usable land. Green Mountain also states that
its current use of the buffer zone to store materials is
necessary to carry out its rail activities. See Paper 65 at
3la
para. 20. According to Green Mountain, these facts
demonstrate the buffer zone's undue interference with its
rail operations. See Plaintiffs Reply (Paper 69) at 4 and
n.3.
It is undisputed that Riverside is located near the
Connecticut River, a valuable environmental and
recreational resource. According to the state, the buffer
zone protects the fish habitat, prevents erosion of the
stream bank, helps maintain water quality, and provides
an aesthetic benefit. Nevertheless, maintenance of this
buffer zone necessarily has an economic impact on Green
Mountain's ability to expand its business. Under similar
circumstances, both courts and the STB have determined
that state environmental regulations, however laudable,
are preempted under the ICCTA. See supra at Section IIA
Il. Conclusion
To the extent the state is applying Act 250 to Green
Mountain's plans as a preclearance permitting process, its
actions are preempted by the ICCTA. The state, however,
is not without remedies. It may require prior notification
of proposed projects and seek voluntary compliance with
applicable Act 250 standards. It may also have standing
to seek compliance with applicable federal laws, such as
the Clean Air Act and the Clean Water Act. See Joint
Petition, 2001 WL 458685 at *5 ("nothing in section
10501(b) is intended to interfere with the role of state and
local agencies in implementing Federal environmental
statutes .. .").
Green Mountain's Motion for Summary Judgment is
GRANTED. The state's Motion for Summary Judgment is
DENIED. SO ORDERED.
Dated at Brattleboro, Vermont, this 15 day of
December, 2003. :
32a
United States District Court-
District of Vermont
GREEN MOUNTAIN RAILROAD CORPORATION,
Plaintiff,
v.
STATE OF VERMONT, VERMONT. AGENCY OF
NATURAL RESOURCES, and WILLIAM H. SORRELL,
as Attorney General of the State of Vermont,
Defendants.
JUDGMENT IN A CIVIL CASE
CASE.NUMBER: 1:01-CV-181cft
0 Jury Verdict. This action came before the Court for
trial by jury. The issues have been tried and the jury has
rendered its verdict.
X Decision by Court. This action came to trial or
hearing before the Court. The issues have been tried or
heard and a decision has been rendered.
IT IS ORDERED AND ADJUDGED that pursuant to
the Court's Ruling on Cross Motions for Summary
Judgment (Paper No. 70) filed December 15, 2003,
plaintiffs Cross-Motion for Summary Judgment (Paper
No. 63) is GRANTED and defendants’ Motion for
Summary Judgment (Paper No. 52) is DENIED.
JUDGMENT is hereby entered for plaintiff Green
Mountain Railroad Corporation against defendants State
of Vermont, Vermont Agency of Natural Resources, and
William H. Sorrell.
RICHARD PAUL WASKO
Clerk
Date: December 16, 2003
33 a
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED
U.S. Const. Art. VI cl. 2:
This Constitution, and the Laws of the United States
which shall be made in Pursuance thereof; and all
Treaties made, or which shall be made, under the
Authority of the United States, shall be the supreme Law
of the Land; and the Judges in every State shall be bound
thereby, any Thing in the Constitution or Laws of any
State to the Contrary notwithstanding.
United States Code
Title 49. Transportation
Subtitle IV. Interstate Transportation
Part A. Rail
Chapter 105. Jurisdiction
§ 10501. General jurisdiction
(a)(1) Subject to this chapter, the Board has jurisdiction
over transportation by rail carrier that is--
(A) only by railroad; or
(B) by railroad and water, when the transportation is
under common control, management, or arrangement for
a continuous carriage or shipment.
(2) Jurisdiction under paragraph (1) applies only to
transportation in the United States between a place in—
(A) a State and a place in the same or another State as
part of the interstate rail network;
(B) a State and a place in a territory or possession of the
United States;
34a
(C) a territory or possession of the United States and a
place in another such territory or possession;
(D) a territory or possession of the United States and
another place in the same territory or possession;
(E) the United States and another place in the United
States through a foreign country; or
(F) the United States and a place in a foreign country.
(b) The jurisdiction of the Board over--
(1) transportation by rail carriers, and the remedies
provided in this part with respect to rates, classifications,
rules (including car service, interchange, and other
operating rules), practices, routes, services, and facilities
of such carriers; and
(2) the construction, acquisition, operation, abandonment,
or discontinuance of spur, industrial, team, switching, or
side tracks, or facilities, even if the tracks are located, or
intended to be located, entirely in one State,
is exclusive. Except as otherwise provided in this part,
the remedies provided under this part with respect to
regulation of rail transportation are exclusive and
preempt the remedies provided under Federal or State
law.
(cX1) In this subsection--
(A) the term "local governmental authority"--
(i) has the same meaning given that term by section
5302(a) of this title; and
(ii) includes a person or entity that contracts with the
local governmental authority to provide transportation
services; and
35a
(B) the term "mass transportation" means transportation
services described in section 5302(a) of this title that are
provided by rail.
(2) Except as provided in paragraph (3), the Board does
not have jurisdiction under this part over mass
transportation provided by a local governmental
authority.
(3)(A) Notwithstanding paragraph (2) of this subsection, a
local governmental authority, described in paragraph (2),
is suvject to applicable laws of the United States related
to--
(i) safety;
(ii) the representation of employees for collective
bargaining; and
(iii) employment, retirement, annuity, and unemployment
systems or other provisions related to dealings between
employees and employers.
(B) The Board has jurisdiction under sections 11102 and
11103 of this title over transportation provided by a local
governmental authority only if the Board finds that such
governmental authority meets all of the standards and
requirements for being a rail carrier providing
transportation subject to the jurisdiction of the Interstate
Commerce Commission that were in effect immediately
before January 1, 1996. The enactment of the ICC
Termination Act of 1995 shall neither expand nor contract
coverage of employees and employers by the Railway
Labor Act, the Railroad Retirement Act of 1974, the
Railroad Retirement Tax Act, and the Railroad
Unemployment Insurance Act.
36 2
United States Code
Title 49. Transportation
Subtitle IV. Interstate Transportation
Part A. Rail
Chapter 115. Federal-state Relations
§ 11501. Tax discrimination against rail
transportation property
(b) The following acts unreasonably burden and
discriminate against interstate commerce, and a State,
subdivision of a State, or authority acting for a State or
subdivision of a State may not do any of them:
(1) Assess rail transportation property at a value that has
a higher ratio to the true market value of the rail
transportation property than the ratio that the assessed
value of other commercial and industrial property in the
same assessment jurisdiction has to the true market
value of the other commercial and industrial property.
(2) Levy or collect a tax on an assessment that may not be
made under paragraph (1) of this subsection.
(3) Levy or collect an ad valorem property tax on rail
transportation property at a tax rate that exceeds the tax
rate applicable to commercial and industrial property in
the same assessment jurisdiction.
(4) Impose another tax that discriminates against a rail
carrier providing transportation subject to the jurisdiction
of the Board under this part.
37a
VERMONT STATUTES ANNOTATED
TITLE TEN. Conservation and Development
CHAPTER 151. State Land Use and Development
SUBCHAPTER 1. General Provisions
§ 6001 Definitions
When used in this chapter:
(3)(A) "Development" means:
(i) The construction of improvements on a:tract or tracts
of land, owned or controlled by a person, mvolving more
than 10 acres of land within a radius of five miles of any
point on any involved land, for commercial or industrial
purposes in a municipality that has adopted permanent
zoning and subdivision bylaws.
(ii) The construction of improvements for commercial or
industrial purposes on more than one acre of land within
a municipality that has not adopted permanent zoning
and subdivision bylaws.
(iii) The construction of improvements for commercial or
industrial purposes on a tract or tracts of land, owned or
controlled by a person, involving more than one acre of
land within a municipality that has adopted permanent
zoning and subdivision bylaws, if the municipality in
which the proposed project is located has elected by
ordinance, adopted under chapter 59 of Title 24, to have
this jurisdiction apply.
(iv) The construction of housing projects such as
cooperatives, condominiums, or dwellings, or construction
or maintenance of mobile homes or trailer parks, with 10
or more units, constructed or maintained on a tract or
tracts of land, owned or controlled by a person, within a
radius of five miles of any point on any involved land, and
within any continuous period of five years.
38 a
(v) The construction of improvements on a tract of land
involving more than 10 acres that is to be used for
municipal, county or state purposes. In computing the
amount of land involved, land shall be included that is
incident to the use such as lawns, parking areas,
rozdways, leaching fields and accessory buildings.
(vi) The construction of improvements for commercial,
industrial or residential use above the elevation of 2,500
feet.
(vii) Exploration for fissionable source materials beyond
the reconnaissance phase or the extraction or processing
of fissionable source material.
(viii) The drilling of an oil and gas well.
(B) Notwithstanding the provisions of subdivision (3)(A) of
this section, if a project consists exclusively of any
combination of mixed income housing or mixed use and is
located entirely within a downtown development district
designated pursuant to 24 V.S.A. § 2793, "development"
means:
(i) Construction of mixed income housing with 100 or
more housing units or a mixed use project with 100 or
more housing units, in a municipality with a population of
20,000 or more.
(ii) Construction of mixed income housing with 50 or more
housing units or a mixed use project with 50 or more
housing units, in a municipality with a population of
10,000 or more but less than 20,000.
(iii) Construction of mixed income housing with 30 or
more housing units or a mixed use project with 30 or more
housing units, in a municipality with a population of
5,000 or more and less than 10,000.
39 a
(iv) Construction of mixed income housing with 2C or
more housing units or a mixed use project with 20 or more
housing units, in a municipality of less than 5,000.
(v) Construction of 10 or more units of mixed income
housing or a mixed use project with 10 or more housing
units where the construction involves the demolition of
one or more buildings that are listed on or eligible to be
listed on the state or national register of historic places.
(C) For the purposes of determining jurisdiction under
subdivisions (3)(A) and (3)(B) of this section:
(i) Housing units constructed by a person partially or
completely outside a designated downtown development
district shall not be counted to determine jurisdiction over
housing units constructed by a person entirely within a
designated downtown development district.
(ii) Within any continuous period of five years, housing
units constructed by a person entirely within a designated
downtown district shall be counted together with housing
units constructed by a person partially or completely
outside a designated downtown development district to
determine jurisdiction over the housing units constructed
by a person partially or completely outside the designated
downtown development district and within a five-mile
radius.
(iii) All housing units constructed by a person within a
designated downtown development district within any
continuous period of five years, commencing on or after
the effective date of this subdivision, shall be counted
together.
(iv) In the case of a project undertaken by a railroad, no
portion of a railroad line or railroad right-of-way that will
not be physically altered as part of the project shall be
40a
tA ae ew eee p vedas WAS Gidley ~-Sawada UAVS STs LUE
case of a project undertaken by a person to construct a
‘rail line or rail siding to connect to a railroad’s line or
right-of-way, only the land used for the rail line or rail
siding that will be physically altered as part of the project
shall be included in computing the amount of land
involved.
VERMONT STATUTES ANNOTATED
TITLE TEN. Conservation and Development
CHAPTER 151. State Land Use and Development
SUBCHAPTER 4. Permits
§ 6081 Permits required; exemptions
(a) No person shall sell or offer for sale any interest in any
subdivision located in this state, or commence
construction on a subdivision or development, or
commence development without a permit. This section
shall not prohibit the sale, mortgage or transfer of all, or
an undivided interest in all, of a subdivision unless the
sale, mortgage or transfer is accomplished to circumvent
the purposes of this chapter.
***
(i) The repair or replacement of railroad facilities used for
transportation purposes, as part of a _ railroad's
maintenance, shall not be considered to be substantial
changes and shall not require a permit as provided under
subsection (a) of this section, provided that the
replacement or repair does not result in the physical
expansion of the railroad's facilities.
*: FILED
4 4 : ee
(~Y SEP 2 6 205
No. 05-89 OFFICE OF THE CLERK
In the Supreme Court of the Anited States
STATE OF VERMONT, e¢ al.,
Petitioners,
Vv.
GREEN MOUNTAIN RAILROAD CORPORATION,
Respondent.
On Petition for a Writ of Certiorari to the
United States Court of Appeals for the Second Circuit
BRIEF FOR THE RESPONDENT IN OPPOSITION
ROBERT B. LUCE ROBERT M. JENKINS III
ERIC A. POEHLMANN Counsel of Record
Downs Rachlin Martin DAVID M. GOSSETT
PLLC Mayer, Brown, Rowe &
Courthouse Plaza _ _ Maw LLP
199 Main Street 1909 K Street, NW
P.O. Box 190 Washington, DC 20006
Burlingion, VT 05402 (202) 263-3000
ERIC R. BENSON ANDREW P. GOLDSTEIN
6A Hillside Lane McCarthy, Sweeney &
Westford, VT 05494 Harkaway, P.C.
2175 K Street, NW
Washington, DC 20037
Counsel for Respondent
- = WASHINGTON, D. C. 20001
QUESTION PRESENTED
The ICC Termination Act of 1995 (“ICCTA”), Pub. L.
No. 104-88, 109 Stat. 803, codified in relevant part at 49
U.S.C. §§ 701-727, 10101-11908, amended and expanded
the scope of the Interstate Commerce Act’s express preemp-
tion provision. As amended, the statute specifies:
The jurisdiction of the [Surface Transportation
Board (“STB”)] over—
(1) transportation by rail carriers * * *, and
(2) the construction, acquisition, operation,
abandonment, or discontinuance of spur, indus-
trial, team, switching, or side tracks, or facilities
*x
is exclusive. Except as otherwise provided in this
part, the remedies provided under this part with re-
spect to regulation of rail transportation are exclu-
sive and preempt the remedies provided under Fed-
eral or State law.
49 U.S.C. § 10501(b). The question presented is whether lo-
cal or state governments may require railroads to participate
in pre-construction permitting programs before undertaking
rail transportation activities and operations that, pursuant to
this provision, fall within the STB’s “exclusive” jurisdiction.
ii
RULE 29.6 STATEMENT
Resmeadent Green Mountain Railroad Corporation
(“Green Mountain”) has no parent corporations and no pub-
licly held company owns 10% or more of its stock. Green
Mountain is one of five shortline railroads that share com-
mon ownership and that together comprise the Vermont Rail
System. The four other railroads in the Vermont Rail System
are the Vermont Railway, Inc., The Clarendon and Pittsford
Railroad Company, the Washington County Railroad Com-
pany, and the New York & Ogdensburg Railway Co., Inc.
The recently formed Otter Creek Railroad Company is also
part of the Vermont Rail System, but has not yet applied for
STB licensure. ‘
QUESTION PRESENTED
RULE 29.6 STATEMENT
TABLE OF AUTHORITIES
STATEMENT
A. The History Of Railroad Regulation. .................
Bs WOME © PAGE 9 sociales cdssscciseiccscaresusedivicsonsahs
Cee CN ia os niich cesses ccenabbssisessece
REASONS FOR DENYING THE PETITION
I.
II.
TABLE OF CONTENTS
THERE IS NO CONFLICT AMONG THE
LOWER COURTS OVER WHETHER
SECTION 10501(6) PREEMPTS PRE-
CONSTRUCTION PERMITTING PROCESSES
AS APPLIED TO RAIL TRANSPORTATION
ACTIVITIES AND FACILITIES THAT FALL
WITHIN THE STB’S EXCLUSIVE
Fane Ie Es lasaelsnsesctitiblininanscthaidbeneninnasanseciplonpanentnnn
PETITIONERS’ POLICY ARGUMENTS FOR
REVIEW ARE BASELESS. ....0.:cjecsscnsconcestnssonsseseses
Ill. THE SECOND CIRCUIT WAS PLAINLY
CORRECT IN HOLDING PETITIONERS’
PERMITTING PROCESS TO BE PREEMPTED
BE ES IF Pi edincroneesescelppinawesceniplaatoceasegbiakiceeessibe
CONCLUSION
iii
SORTER ET HEHEHE EEE THEE TEH ETE SESE TERETE
PESO R SESE SSE EET ETERS TESTE ESE EESEEE EH ESE SESE ESTES ESHER EE SE
SPOTS EEE EEE EE EE EEE EEE EET EE ETE EEE EEE EEEEEEEE ESSER EEE EOE ES
Metin |
ae 7
asian 13
TABLE OF AUTHORITIES
Page(s)
CASES
Cal. Coastal Comm'n v. Granite Rock Co.,
A C8 IED issn sain tessicctvccisieenitcinen toSqeigihinssibaaiiilion 29
Canadian Nat’l Ry. Co. v. City of Rockwood,
2005 WL 1349077 (E.D. Mich. June 1, 2005)............... 15
Cedarapids Inc. v. Chicago Cent. & Pac. R.R.,
265 F. Supp. 2d 1005 (N.D. Iowa 2003) .........eccsceeeeeee 15
Chicago & N.W. Transp. Co. v. Kalo Brick & Tile Co.,
Te U8 UE iid strrcesnsnstcigh ih disologhbuasheniniaaien 2,3
City of Auburn v. United States, 154 F.3d 1025
Ply SP isi vclnahsincsisatiaidiinveaiensesbanennenbbiagsesct passim
City of Lincoln v. STB, 414 F.3d 858 (8th Cir. 2005) .... 20, 21
City of Stafford v. ICC, 69 F.3d 535 (Sth Cir. 1995) ........... 25
CSX Transp., Inc. v. City of Plymouth,
92 F. Supp. 2d 643 (E.D. Mich. 2000) ............ecceesseeee 30
CSX Transp., Inc. v. Ga. Pub. Serv. Comm'n,
944 F. Supp. 1573 (N.D. Ga. 1996) .0......cccceeeees $,a3,15
CSX Transp., Inc. v. Williams,
TE DE Gr as Gk, NOD scknipnsstsinescsctesenbcsncoccnstpnses 30
Detroit/Wayne County Port Auth. v. ICC,
Ft EGG Ce. LGD sins sssesin titans haitacctattiatn 26
Fla. E. Coast Ry. v. City of West Palm Beach,
266 F.3d 1324 (11th Cir. 2001)......... cc cssessseeess 18, 19, 20
Flynn v. BNSF Corp., 98 F. Supp. 2d 1186
SOR PII Ge crcsieshisiihnsshctinn<ckantatasineincenniabosansnshiinhelioa 15
Friberg v. Kansas City S. Ry. Co., 267 F.3d 439
es EE Do wintiesicecss nsicieinienncnbivicsaedonessapatalananuiiiall 14
iv
TABLE OF AUTHORITIES-CONTINUED
Page(s)
G&T Terminal Packaging Co. v. Consol. Rail Corp.,
ee ae At Gs SOIT iitccsessciiernonsssgudeasinirscoseicecs 25
Hi Tech Trans, LLC v. New Jersey, 382 F.3d 295
I I I ico tatactaas can ctodasiag eae nansetadbinrnaestni 14,17
Home of Economy v. Burlington N. Santa Fe
R.R., 694 N.W.2d 840 (N.D. 2005) 0.0... eeeees 20, 21
Bs V. ROE, SEG 2 OO CAFE D vnncciccksccsnsccctasbanscecsaitincnses 3
Ill. Commerce Comm'n v. ICC, 879 F.2d 917
8, Re tae an erage 3, 26
In re Appeal of Vermont Railway,
FOP BiB GAB CVE. FIO) on sicinsnsencsnciiercrsesccsexcences 16, 17, 18
In re Spring Brook Farm Found., Inc.,
pe Re. aS 3) ee Ee eer tee 7
Iowa, Chicago & E. R.R. v. Washington
County, 384 F.3d 557 (8th Cir. 2004) .0..... ee. 20, 21
Morales v. Trans World Airlines, Inc.,
NN ied ictchitininbinasisipdiiseasodasehanennccts 24, 25
Native Vill. of Eklutna v. Alaska R.R. Corp.,
87 P.3d 41 (Alaska 2004)... .cccsecesscsscsesesseeeceeees 19, 20
Norfolk & W. Ry. Co. v. Am. Train
Dispatchers Ass’n, 499 U.S. 117 (1991) .....cceceseceseees 29
Norfolk S. Ry. Co. v. City of Austell, 1997 WL
1113647 (N.D. Ga. Aug. 18, 1997)... cece eceeceseeee 15
Pittsburgh & Lake Erie R.R. Co. v. Ry. Labor
Executives Ass'n, 491 U.S. 490 (1989) .......ccccccseeseeeeeeee l
Rice v. Santa Fe Elevator Corp.,
Se Be RRR ai icaies oe ar eS 29
TABLE OF AUTHORITIES-CONTINUED
Page(s)
Schneidewind v. ANR Pipeline Co.,
ED rie A IE el virtcicesicionsdapititeenenntansnatsonixtasesoen 25
Soo Line R.R. v. City of Minneapolis,
38 F. Supp. 2d 1096 (D. Minn. 1998) ...... cece ceeeeeeeee 15
Texas & Pac. Ry. Co. v. Abilene Cotton Oil Co.,
PE ir OTN sites ccthehccsadla siilintasccociennshihcotocinsticinthades 3
Texas & Pac. Ry. Co. v. Gulf; Colorado &
Santa Fe Ry., 270 U.S. 266 (1926)..........scccsscssssserseseees 26
Transcon. Gas Pipe Line Corp. v. State Oil & Gas Bd.
Of Miss., 474 U.S. 409 (19GB). ....-.....ccccrecesnsssscossccesessaces 25
United States v. Locke, 529 U.S. 89 (2000) ..........cccscesseseees 30
Vill. of Ridgefield Park v. New York, Susquehanna
& W. Ry. Corp., 750 A.2d 57 (N.J. 2000)..............06 12, 15
Wis. Cent. Ltd v. City of Marshfield,
160 F. Supp. 2d 1009 (W.D. Wisc. 2000) .............. cee 15
AGENCY DECISIONS
Borough of Riverdale—Petition for Declaratory
Order—The New York, Susquehanna, & W. Ry.
Corp., STB Fin. Dkt. No. 33466, 1999 WL
715272 (served Sept. 10, 1999).........cc.ccccsssesesssereses 15, 16
Cities of Auburn & Kent, WA—Petition for
Declaratory Order—Burlington N. R.R. Co.—
Stampede Pass Line, STB Fin. Dkt. No. 33200,
1997 WL 362017 (served July 2, 1997)...............004 16, 26
City of Detroit v. Canadian Nat'l Ry. Co.,
CIC ON i. “ase 25, 26
vi
_TABLE OF AUTHORITIES-CONTINUED
Page(s)
City of Stafford v. S. Pac. Transp. Co., \CC Fin.
Dkt. No. 32395, 1994 WL 613381 (served
PO iy SE Nice dicicivicniacnuatanseinm tlacuadiccosdassigiccedie 25
Green Mountain R.R. Corp.—Petition for
Declaratory Order, STB Fin. Dkt. No. 34052,
2002 WL 1058001 (served May 28, 2002).......... 9, 10, 12
Hi Tech Trans, LLC—Petition for Declaratory
Order—Hudson Cty., NJ, STB Fin. Dkt. No.
34192, 2002 WL 31595417 (served Nov. 20, 2002)...... 17
Joint Petition for Declaratory Order—Boston &
Maine Corp. & Town of Ayer, MA, STB Fin.
Dkt. No. 33971, 2001 WL 458685 (served ~
PE Bi BOD icin bi eisai soneadigspha vasiesinstadinididiitaoas 10, 22
Joint Petition for Declaratory Order—Boston &
Maine Corp. & Town of Ayer, MA, STB Fin.
Dkt. No. 33971, 2001 WL 1174385 (served
FR BS RANI rte aN RNAY HON REE D DE: ARR ES 15
N. San Diego County Transit Dev. Bd.—Petition for
Declaratory Order, STB Fin. Dkt. No. 34111,
2002 WL 1924265 (served Aug. 21, 2002)..............000: 15
Union Pac. R.R.—Petition for Declaratory Order—
Rehabilitation of Mo.-Ks.-Tx. R.R. Between
Jude and Ogden Junc., TX, STB Fin. Dkt.
No. 33611, 1998 WL 525587 (served Aug. 21, 1998) .. 26
STATUTES, RULES AND REGULATIONS
FFs WT isicdahananlasnscicnnsdamcactsdeuithinnietaishdinabanninaaibs 8
49 U.S.C. § 10102(9)......... ee piss baleibiseheabantbainaneil passim
Se Sas: FS sas scihscctsdevdbeacsabadcawnsnissshinnedcecentlGbcidmsateibionncons 4
Vii
TABLE OF AUTHORITIES-CONTINUED
Page(s)
ee ne ae “
49 U.S.C. § 10501(b)..........00000 Bi aha Cet 3s passim
ne ON se 17
kN , Se ct ON aL: 6, 26
I 4
I Oe ORION oni 2
PRET 6 MOUNT NOON oi iii ince 2
SD ON RRS ORE nti ea ee a eater 7
USC. 6 100000) (1907)... 26
eae sea aes. 3
rr oe BTL LOL LS , ecemmmneneereeert tence 2
EERSTE ILE, 29
Dn RE LEGIT IAT SEE 14
eee NIST os 2
REI SRA aie ee PA Che 28
NR NN os 28
BRASS Ea ARR Rao A case 28
SS SEBEL LEE TOOL TM 12
Federal Railroad Safety Act of 1970, Pub. L. No.
a 20
ICC Termination Act of 1995 (“ICCTA”), Pub. L.
No. 104-88, 109 Stat. 803, codified in relevant
part at 49 U.S.C. §§ 701-727, 10101-11908........... passim
Vill
TABLE OF AUTHORITIES-CONTINUED
Interstate Commerce Act of 1887 (“ICA”),
Pub. L. No. 49-104, 24 Stat. 379... ecsseseseeeee
National Environmental Policy Act (“NEPA”),
S2US.C; B86 4521-AT Oaks
Railroad Revitalization and Regulatory Reform
Act of 1976, Pub. L. No. 94-210, 90 Stat. 31......
Staggers Rail Act of 1980, Pub. L. No. 96-448, 94
ahs, Bei diciabsscimnnsiplabahatohsingasitbadiphhdessanpibadatnaiiatnanies
Transportation Act of 1920, Pub. L. No. 66-152,
Oe tO itd aintictligintscbccahinhigabinidauascamsaciedaneed
Act 250, codified at Vt. Stat. Ann. Tit. 10
IE MI ance sicendesineh dnadasteprebiacinstensichaalassaoentisch
Vt. Stat. Amn. Tit. 10 § 6084 oo... seccesccosscsssseeee
Vt. Stat. Ainn. Tit. 10 § 6085 .o.cccccccsscsscsssessseessoee
Vt. Stat. Ann. Tit. 10 § 6085(C)...c.ccccecccsescsseseenees
Vt. Stat. Ain. Tit. 10 § 6086 ......cc.cccscsscsesessseseeeee
Vt. Stat. Ann. Tit. 10 § 6086(a)(1) ....scssssccsseseoeee
Vt. Stat. Ann. Tit. 10 § 6086(a)(8) ......-..cse..0se--
Vt. Stat. Ann. Tit. 10 § 6086(C)......cscccscsesesssesennee
Vt. Stat. Ainn. Tit. 10 § 6089 ....ccsccccsscsssecsseeseeee
Ps 1 BS) A | Sain Ce nod
MISCELLANEOUS
H.R. ConF. REP. No. 104-422 (1995),
reprinted in 1995 U.S.C.C.A.N. 850..........0000005
ix
Page(s)
.... passim
TABLE OF AUTHORITIES-CONTINUED
Page(s)
H.R. REP. No. 104-311 (1995), reprinted in 1995
Re ADs FOR cities ciienineeddcoccsanniaceaniinsicncbiaiangetl passim
is BUEN, SAPO FOP CE ks a saccicoccitgoasoliscabadiccsnoinall 4, 23, 24
BRIEF FOR THE RESPONDENT IN OPPOSITION
As the court of appeals ably demonstrated, 49 U.S.C.
§ 10501(b) precludes states or localities from requiring rail-
roads to participate in pre-construction permitting processes
for rail transportation activities and operations that fall within
the exclusive jurisdiction of the Surface Transportation
Board (“STB” or “Board”). Although petitioners identify
numerous cases that they assert conflict with the Second Cir-
_cuit’s decision on this question, in fact there is no such dis-
agreement; rather, every court to consider the issue has so
held, as has the STB.
Petitioners have never disputed that the facilities Green
Mountain proposed to construct in-this case fall within the
scope of the STB’s jurisdiction over rail transportation activi-
ties and operations—as both the district court and the court of
appeals found. Every court to consider the applicability of a
state permitting statute to rail transportation facilities within
the STB’s jurisdiction has concluded that the state permitting
system is preempted by Section 10501(b). The cases that pe-
titioners assert conflict with the decision below have instead
involved a different, fact-bound question: whether specific
activities undertaken by a railroad fell within the statutory
definition of rail “transportation,” and thus within the exciu-
sive jurisdiction of the STB. That issue is distinct from
whether a state may require a railroad to participate in a prior
permitting scheme for rail transportation activities or facili-
ties that unquestionably do fall within the STB’s jurisdiction.
Thus, these cases in no way conflict with the decision below,
and there is no reason for this Court to grant review.
STATEMENT
A. The History Of Railroad Regulation.
1. Congress has extensively regulated the nation’s rail-
road system for over a century. See Pittsburgh & Lake Erie
R.R. Co. v. Ry. Labor Executives Ass'n, 491 U.S. 490, 510
(1989); City of Auburn v. United States, 154 F.3d 1025, 1029
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.