Petition for Writ of Certiorari — Cessna Aircraft Co. v. Dalton
Supreme Court brief1998
Ask Donna
What actually matters in this document.
Text
Court, U.S
171930 May 26 t0y
OFFICE OF TH
No. 97- E CLERK
IN THE
Supreme Court of the Anited States
OCTOBER TERM, 1997
THE CESSNA AIRCRAFT COMPANY,
Petitioner.
JOHN H. DALTON, SECRETARY OF THE NAVY,
Respondent.
On Petition for Writ of Certiorari to the
United States Court of Appeals for the Federal Circuit
PETITION FOR WRIT OF CERTIORARI
HERBERT L. FENSTER*
JEREMY M. GRIFFIN
MCKENNA & CUNEO, L.L.P.
1900 K Street, N.W.
Washington, D.C. 20006
(202) 496-7500
Counsel for Petitioner
*Counsel of Reccrd
PRESS OF BYRON S. ADAMS # WASHINGTON, D.C. # 1-800-347-8208
QUESTIONS PRESENTED
Whether an Executive Branch agent can obligate and spend
newly appropriated funds before the President has apportioned
those moneys as required by statutes intended to effect Congress'
plenary authority under Article I, Section 9, Clause 7 of the
Constitution?
Whether a valid contract can exist notwithstanding the fact that
it is based on violations of statutes and regulations governing the
obligation of funds from the Treasury?
Whether a contractor has standing to challenge the validity of a
contract that was based on a violation of statutes and regulations
and that caused financial harm to that contractor?
i
RULE 29.6 STATEMENT
Petitioner The Cessna Aircraft Company is a wholly-owned
subsidiary of Textron Inc.
ill
TABLE OF CONTENTS
QUESTIONS PRESENTED ............::::::ccsesssesessessesneeeeeentntneneneenenes I
RULE 29.6 STATEMENT..........ccccssscssssccsssensstecsresersesnsnossnenesnsees I]
TABLE OF CONTENTS .........:cssscsscscossssssssesssestneeeccsonsessnnsoensees II]
TABLE OF AUTHORITIEG..............::ccsscssseeesseersreserssenseeeeneneeens VI
OPINIONS BELOW .......0::00.0ccccccscsssscssscccsssessvecersssnecsnsvscsnnsonsacores 2
JURISDICTION ...00.0000c:..ccccccccocccssscessseosscsssnesersceosoensnssnscssanerecnssenes 2
CONSTITUTIONAL, STATUTORY AND
REGULATORY PROVISIONS INVOLVED ..........::::essese0 2
STATEMENT OF THE CASE ..........cccccsesecesseneeeeneeseeeseesesneneeenes 3
A. The Statutory Scheme Enacted By Congress To
Implement Article I, Section 9, Clause 7
l. The History Of The Anti-Deficiency Act
y Congress Requires The Executive To Apportion
Appropriated Moneys
i} The Federal Circuit Decision
B. Background Of The Case
3 This Litigation
REASONS FOR GRANTING THE WRIT..........:.::ceeeeee 13
A. The Actions Of The Navair Contracting Officer Frustrated
The Purpose Of Laws Intended To Protect The Treasury.
13
B. This Court's Precedent Hold That Contracts Executed In
Violation Of The Law Cannot Be Enforced. 22
i The Court Of Appeals Ruling On Standing Conflicts W ith
The Law Of This Court And Other Circuit Courts Of
Appeal. 23
COINCLIUISIOIN onc caccsccsccsssccccccesssescrssescsccssserserscssertearessesseearosenonens 27
iV
APPENDIX A (Cessna Aircreft Co. v. Dalton,
MO. 96-4 155 (Ped. Cat. Oct. 6. 1997 cc cicccctipertictossannces la
APPENDIX B (Cessna Aircraft Co. v. Dalton,
ASCBA No. 43196 (March 12, 1993) ..iscscecciccsesscssiseccocsoreess Ib
APPENDIX C (Cessna Aircraft Co. v. Dalton,
ASCBA No. 43196 (September 21, 1995) ow... ee eeeeeeeees le
APPENDIX D (Cessna Aircraft Co. v. Dalton, No. 96-1085
ER COPINEY 2 Fe PRO) ixincctiwcchawinncs cians idan oernebananeiieks ld
APPENDIX E (setting forth verbatim the following
statutory provisions: An Act in addition to the several
acts for the establishment and regulation of the Treasury,
War and Navy Departments, ch. 52, 3 Stat. 567(1820);
An Act making Appropriations for the legislative,
executive, and Judicial Expenses of the Government for
the Year ending the thirtieth of June, eighteen hundred
and seventy one, ch. 251, § 7, 16 Stat. 230, 251 (1870);
An Act Making appropriations to supply deficiencies in
the appropriations for the fiscal year ending June
thirtieth, nineteen hundred and five, and prior years, and
for other purposes, ch. 1484, § 4, 33 Stat. 1214, 1257
(1905); General Provisions of the General Appropriations
Act of 1951, ch. 896, § 1211, 64 Stat. 763, 765 - 768
(1950); 31 U.S.C. §§ 1341, 1511-1519 (1994)) oe. le
APPENDIX F (setting forth verbatim the following
regulatory provisions: Department of Defense Directive
7200.1 (May 7, 1984); Department of Defense
Accounting Manual (Feb. 1988); Navy Comptroller
INE cari seers bo cca siclacie hdauiacealewhcieh aaclacidatobachintanccbkaastaantoas If
Vv
TABLE OF AUTHORITIES
CASES Page
American Farm Lines v. Black Ball Freight Serv., 397
U.S. 532 (1970) 28
Applied Devices Corp. v. United States, 591 F.2d
635 (Ct. Cl. 1979) 26
Association of Data Processing Service Org., v. Camp,
397 U.S. 150 (1970) 27
B.K. Instrument, Inc. v. United States, 715 F.2d 713
(2d Cir. 1983) 27
Cessna Aircraft Co. v. Dalton, No. 96-1185, 126 F.3d
1442 (Fed. Cir. 1997) 2
Chris Berg, Inc. v. United States, 426 F.2d 314 (Ct. te
1970) 26
Clark v. United States, 95 U.S. 539 (1877) 9, 25
Clinton v. City of New York, 118 S. Ct. 1551 (1998) 16
Commissioner v. Asphalt Prod. Co., 482 U.S.
117 (1987) 24
Federal Crop Ins. Corp. v. Merrill, 332 U.S. 380
(1947) 25
Harrington v. Bush, 553 F.2d 190 (D.C. Cir. 1977) 15
Hartford Accident & Indem. Co. v. United States, 127
F. Supp. 565 (Ct. Cl. 1955) 26
Hayes Int'l Corp. v. McLucas, 509 F.2d 247 (Sth
Cir. 1975) 27
Hercules, Inc. v. United States, 116 S. Ct. 981
(1996) passim
Vi
Hooe v. United States, 218 U.S. 322 (1910) 6, 16
Housing and Home Finance, 37 Comp. Gen, 220
(1957) 17
LaBarge Prod., Inc. v. West, 46 F.3d 1547 (Fed.
Cir. 1995) 26
Lynch v. United States, 292 U.S. 571 (1934) 19
National Credit Union Admin. v. First Nat'l Bank &
Trust Co., 118 S. Ct. 937 (1998) 10, 18
Oy v. United States, 61 F.3d 866 (Fed. Cir. 1995)
28
Perkins v. Lukens Steel Co., 310 U.S. 113 (1940)
26, 27
Project Stormfury, 59 Comp. Gen. 369 (1980) 14,17
Rough Diamond Co. v. United States, 351 F.2d 636 (Ct.
Cl. 1965) 26
Scanwell Lab. v. Shaffer, 424 F.2d 859 (D.C.
Cir. 1970) 27
Vil
Secretary of the Air Force. 42 Comp. Gen. 272
(1962) 15
Sutton v. United States, 256 U.S. 575 (1921) 16, 20
Winstar v. United States, 518 U.S. 839 (1996) 19
CONSTITUTION & STATUTES
U.S. Const. art I, § 9, cl. 7 passim
28 U.S.C. § 1254(1) (1994) 2
28 U.S.C. § 1295(a)(10) 13
31 U.S.C. § 1341 passim
31 U.S.C. § 1342 14
31 U.S.C. § 1350 18
31 U.S.C. §§ 1511-1519 passim
41 U.S.C. §§ 601- 609 13
41 U.S.C. § 607(d) 13
Ch. 52, 3 Stat. 568, § 6 (1820 ) ane
Ch. 251, 16 Stat. 251 (1870) 2, 5,6
Ch. 1484, 33 Stat. 1257 (1905) 2, 6
Ch. 896, 64 Stat. 765, § 1211 (1950) » a 5
OTHER AUTHORITIES
CRS. Short-Term Continuing Resolutions: The Dep't of
Defense Experience, 89-579F (Oct. 19, 1989) 23
Davis & Pierce, Administrative Law Treatise, §§ 16.2- 16.3
7
(1994) 27
Fenster, Herbert & Christian Volz, The Anti-Deficiency
Act: Control Gone Astray, 11 Pub. Con. L.J. 155
vit
(1979) 17
GAO, Principles of Federal Appropriations Law, ch. 6,
(1992) 18
GAO/OGC-92-13, Appropriations Law -- Vol. I]
Stith, Kate, Congress’ Power of the Purse, 97
Yale L.J. 1343 5. 6, 14
No. 97-
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1997
THE CESSNA AIRCRAFT COMPANY,
Petitioner,
JOHN H. DALTON,
SECRETARY OF THE NAVY,
Respondent.
On Petition for Writ of Certiorari to the
United States Court of Appeals for the Federal Circuit
PETITION FOR WRIT OF CERTIORARI
Petitioner The Cessna Aircraft Company (“Cessna”) hereby
petitions for a writ of certiorari to review the judgment of the
United States Court of Appeals for the Federal Circuit. The
Federal Circuit ruled that an Executive Branch agent can obligate
and expend funds from the Treasury before completion of the
apportionment process mandated by statute and regulations and
that a private party cannot recover damages arising out of any
violation of those statutes and regulations. In so ruling, the
Federal Circuit held that Cessna lacked standing to challenge the
validity of its contract with the government, even though there is
no dispute that the Navy failed to apportion the moneys as
required by law prior to obligating them to that contract.
~
OPINIONS BELOW
The opinion of the Court of Appeals (App. la) is reported at
126 F.3d 1442 (Fed. Cir. 1997). The opinions of the Armed
Services Board of Contract Appeals (App. 1b, 1c) are reported at
96-1 BCA © 27,996 and 93-3 BCA § 25,912.
JURISDICTION
The Court of Appeals entered judgment on October 6, 1997.
Cescna's timely filed petition for rehearing was denied on
February 27, 1998. App. Id. This Court has jurisdiction under 28
U.S.C. § 1254(1) (1994).
CONSTITUTIONAL, STATUTORY AND REGULATORY
PROVISIONS INVOLVED
Article I, Section 9, Clause 7: "No Money shall be drawn from
the Treasury, but in Consequence of Appropriations made by
Law; and a regular Statement and Account of the Receipts and
Expenditures of all public Money shall be published from time to
time."
The appendix (App. le) sets forth verbatim the following
statutory provisions: 3 Stat. 567(1820); Section 7, 16 Stat. 230,
251 (1870); Section 4, 33 Stat. 1214, 1257 (1905); Section 1211,
64 Stat. 763, 765 - 768 (1950); 31 U.S.C. §§ 1341, 1511-1519
(1994).
The appendix (App. If) sets forth verbatim the following
regulatory provisions: DOD Directive 7200.1 (May 7, 1984);
DOD Accounting Manual (Feb, 1988); Navy Comptroller Manual.
STATEMENT OF THE CASE
This petition asks the Court to review for the first time a
question of profound significance to all persons who contract with
the federal government—whether an Executive Branch official
can disregard statutory and regulatory provisions governing the
disposition of funds appropriated pursuant to Article I, Section 9,
Clause 7 in order to require a contractor to render performance
and the more fundamental question of whether such official can
obligate and expend such unapportioned funds. This case presents
an effort by the Executive Branch to undermine a statute
(requiring the apportionment of funds before they are obligated
and spent) that is the cornerstone of a comprehensive set of
statutes imperative to the effective application of Article I,
Section 9, Clause 7 of the Constitution. "No Money may be
drawn from the Treasury, but in Consequence of Appropriations
made by Law... ." U.S. Const. art. I, §9, cl. 7. With this
statement, the Constitution grants exclusively to the Congress the
power of the purse -- a power that cannot be delegated by the
Legislature. Fidelity to our constitutional form of government
also prohibits both the Executive and Judicial Branches from
disregarding Congress’ plenary authority to control federal
expenditures. That, however, is precisely what has occurred here.
In the name of expediency, a low-level Executive Branch
bureaucrat obligated Treasury funds for a contract by disregarding
constitutionally based statutes and regulations governing how
money must be drawn from the Treasury. Then, bowing to
irrelevant program considerations, the United States Court of
Appeals for the Federal Circuit, the only Article III court likely to
address these issues again, condoned a result whereby such
bureaucrats can disregard these constitutionally based statutes and
regulations with impunity. This result is contrary to Article |,
Section 9, Clause 7 of the Constitution, the statutes enacted to
effectuate the purpose of that Clause, the regulations promulgated
to effect the purpose of those statutes, and instructive opinions of
this Court. This Court, however, has never addressed the
fundamental issue presented here: whether the Executive and
4
Judicial Branches may disregard the manner in which Congress
has determined to control the power of the purse.
The Court should grant the petition for three reasons. First, the
Federal Circuit panel decision in this case allows Executive
Branch officials to circumvent a statutory and regulatory scheme
designed to protect Congress’ "power of the purse." As explained
below, consideration of this issue by this Court is long overdue.
Second, the decision of the Federal Circuit (the only Court of
Appeals likely to consider the issue) conflicts with precedent of
this Court addressing analogous statutes as well as the plain
language of the statutes at issue. Review by this Court, therefore,
is essential to preserving the Congress’ "power of the purse."
Third, the decision conflicts with Supreme Court jurisprudence on
standing, which was necessarily disregarded by the Federal
Circuit in order to reach its holding.
A. The Statutory Scheme Enacted By Congress To
Implement Article I, Section 9, Clause 7
Article I, Section 9, Clause 7, and its implementing laws,
enjoin the Executive from spending money in the name of the
United States except as provided by the Congress. As discussed
below, for nearly two hundred years, the Congress has been
enacting a panoply of Acts designed to protect its prerogative to
control federal expenditures pursuant to Clause 7. These statutes
(principally the Anti-Deficiency Act) and their implementing
regulations prohibit Executive Branch officials from obligating
and expending moneys on behalf of the United States prior to
sufficient funds being appropriated and apportioned. That is, the
passage of an adequate appropriation alone does not free the
Executive to obligate and expend funds from the Treasury. Under
the applicable statutory scheme, funds remain legally unavailable
until the Executive Branch has completed a mandatory series of
actions apportioning an appropriation to ensure that funds will
remain available throughout the fiscal year.
ws
1. The History Of The Anti-Deficiency
Act
The cornerstone of the statutory scheme enacted to preserve
the power of the purse is the Anti-Deficiency Act, 31 U.S.C.
§ 1341. The genesis of this legislation was an 1820 Act entitled,
"An Act in addition to the several acts for the establishment and
regulation of the Treasury, War and Navy Departments." Ch. 52,
3 Stat. 567 (1820) ("the 1820 Act"). App. le. See Kate Stith,
Congress’ Power of the Purse, 97 YALE L.J. 1343, 1370- 1372.
It's purpose was to prevent the Executive Branch from incurring
"coercive" deficiencies that effectively circumvented Congress’
power of the purse. /d. at 1370. Under the terms of section 6 of
the 1820 Act, "no contract shall hereafter be made . . . except
under a law authorizing same, or under an appropriation adequate
to its fulfillment; ..." App. le. With this Act began a long
history of many attempts by the Congress to enjoin the Executive
from disregarding Article I, Section 9, Clause 7. As set forth
below. continued resistance or disregard by the Executive of this
fundamental constitutional tenet continues to this day and in this
case.
The scope of the 1820 Act was clarified and expanded by the
act of July 12, 1870, ch. 251, § 7, 16 Stat. 251 (1870) ("the 1870
Act"). App. le. Under the 1870 Act, no government could
commit to the expenditure in any fiscal year of any amount in
excess of appropriations for that year or involve the government
"in any contract for the future payment of moneys in excess of
such appropriations." Section 7, 16 Stat. 251 (1870). App. le.
Under the terms of the 1870 Act, any contract to pay a sur "in
excess of that limited by Congress" was a nullity. Hooe v. United
States, 218 U.S. 322, 334 (1910). This statute was enacted
specifically to address "the problem" that Executive Branch
officials obligated moneys in advance of appropriations and then
sought deficiency appropriations from Congress, which had little
choice but to provide them. App. 18a. By prohibiting the
Executive Branch from incurring these deficiencies, Congress
sought to ensure that its power of the purse would not be
undermined. See Stith, 97 YALE L.J. at 1371-72.
6
Zz. Congress Requires The Executive To
Apportion Appropriated Moneys
To further restrain the Executive's over-commitment of
funding, the scope of the 1870 Act was expanded by the General
Deficiency Bill of 1905, ch. 1484, § 4, 33 Stat. 1257 (1905) ("the
1905 Act"). App. 2e-3e. The 1905 Act contained two equally
significant new provisions. First, "[a]ll appropriations made for
contingent expenses or other general purposes" had to be
apportioned to ensure availability of funds for the entire fiscal
year. 33 Stat. 1257-58. /d. By requiring that all appropriations
be apportioned, the statute was intended to prevent the Executive
from spending all available funds prior to the end of the fiscal
year and requiring that Congress appropriate additional money in
order to meet the government's needs for the remainder of the
year and to avoid coercive deficiencies. Second, the 1905 Act
established sanctions, including criminal penalties, for those who
ignored its dictates. 33 Stat. 1258. App. 3e. These sanctions
remain in effect today. 31 U.S.C §§ 1518-19 (1994). App. 19e.
Incorporated as part of the General Provisions of the General
Appropriations Act of 1951, ch. 896, § 1211, 64 Stat. 763, 765-68
(1950) ("the 1950 Act"), the 1950 Act revised and subdivided the
Anti-Deficiency Act and related laws in a manner largely
consistent with their current structure. Compare Section 1211, 64 -
Stat. 765-66 with 31 U.S.C. §§ 1341, 1512-19 (1994). App. 3e-
9e; 10e-19e. Most importantly for present purposes, new
subsections further defined the apportionment process, including
the manner in which that apportionment process must occur. See
31 U.S.C. §§ 1512-14. App. 12e-l6e. See generally, GAO/OGC-
92-13 Appropriations Law -- Vol. Il, at 6-72 - 6-99 ("the GAO
Accounting Manual").
31 U.S.C. § 1512 requires apportionment of all funds available
for obligation for a limited period of time in order to avoid the
need for supplemental appropriations:
9]
i
Except as provided in this subchapter, an appropriation
available for obligation for a definite period shall be
apportioned to prevent obligation or expenditure at a rate that
would indicate a necessity for a deficiency or supplemental
appropriation for the period.
31 U.S.C. § 1512(a). App 12e.!/ After funds have been
apportioned by the Office of Management and Budget, the
statutory process continues. Funds must be "allocated" by the
executive agency, and then "suballocated" within the agency. 31
U.S.C. §§ 1512-1514. App. 12e-16e. Only when this process has
occurred can an officer of the Government /egally obligate funds
from the Treasury:
An officer or employee of the United States Government or
of the District of Columbia government may not make or
authorize an expenditure or obligation exceeding (1) an
31 U.S.C. § 1517(a). App. 18e-19e. Thus, under the statutory
scheme enacted by Congress to protect its power of the purse,
Executive officials are prohibited from entering into contracts and
from authorizing or creating obligations or expenditures in excess
of amounts apportioned and administratively subdivided below
the apportionment level.
To further ensure compliance with the statutory scheme, 31
U.S.C. § 1514(a) requires Executive agencies to implement
regulations to effectuate the mandated apportionment process,
which have the force and effect of law. App. I5e. For the
l/ 31 U.S.C. § 1513(b) designates the President as the apportioning
official. The President delegated this responsibility the Director of the
Bureau of the Budget (now the Director of the Office of Management
and Budget) pursuant to Exec. Order No. 6166, § 16 (June 10, 1933).
8
Department of Defense ("DOD"), these regulations are contained
in DOD Directive 7200.1, dated May 7, 1984 and the DOD
Accounting Manual. DOD Directive 7200.1 restricts authority to
obligate funds to the amount that has been apportioned and
forbids obligations in excess of the amount apportioned. App.
13f-14f. That prohibition is further reinforced by the DOD
Accounting Manual, which states the following:
For apportioned funds, a violation of DOD Directive
7200.1 is a violation of 31 U.S.C. § 1517. (reference (v)).
Since DOD Directive 7200.1 was issued pursuant to 31 U.S.C.
§ 1517, it has the force an effect of law.
DOD Accounting Manual at 21-5. App. 18f.
The Navy, too, has implemented a similar regulatory scheme,
which is set forth in the Navy Comptroller Manual ("NCM"). The
NCM imposes a sequential funding process whereby funds first
are apportioned, then allocated to the Secretary of Defense, and
then allotted, suballotted, and committed through the chain of
command in the Navy. NCM 073002. App. 22f. Once this
process is completed, a Navy contracting officer then may /egally
obligate funds to a Navy contract.
3. The Federal Circuit Decision
The requirement for apportionment of any appropriated funds
prior to their being obligated and expended on a government
contract is a fundamental principle of federal funding law. The
decision of the United States Court of Appeals for the Federal
Circuit is in conflict with that principle. Under the Federal
Circuit's existing decision, a subordinate agency official can
obligate moneys prior to their being apportioned without violating
31 U.S.C. § 1517 even though the President would be precluded
from ensuring that those moneys are spent so as "to achieve the
most effective and economical use,” as required by 31 U.S.C.
§ 1512. App. 12e-13e.
9
Moreover, under the Federal Circuit's decision, violation of the
apportionment statutes has no effect on the legality of the contract
arising out of that very violation. See App. 26a-27a. That notion
is contrary to precedent established by this Court over a century
ago. See Clark v. United States, 95 U.S. 539 (1877).
Notwithstanding that precedent, the Court of Appeals decision
would permit agents for a procuring activity within a subordinate
executive department to disregard statutes and regulations with
impunity whenever expediency and parochial self-interest
warranted doing so, and the contractor, not the government, must
bear the financial consequences of the agency's conduct.
The very contractor that must bear the burden of the
government agent's disregard for the law would have no standing
to complain about that violation if the decision of the appeals
court remains the law. App. 26a-27a. The rationale for the court's
opinion on this score is essentially that laws governing the
expenditure of money for government contracts are of no
consequence to the contractor that is to receive those funds. /d.
Since the laws were not intended for the benefit of the contractor
they have no standing. Bul see National Credit Union
Administration v. First Nat'l Bank & Trust Co., 118 S. Ct. 927,
935 (1998). But this Court has recently ruled that such a contract
may be abrogated by the government, and therefore the interest of
a contractor is compelling. See Hercules, Inc. v. United States,
116 S. Ct. 981 (1996).
B. Background Of The Case
Cessna and the Navy entered into a contract that had a number
of pertinent characteristics for present purposes. First, the
contract was funded with annual appropriations -- the Navy was
required to obligate funds each year to the contract, after Congress
had appropriated those funds. App. 4c. Asa result, the Navy was
required to comply with the statutes and regulations governing the
obligation of those funds. These include the foregoing
apportionment statutes, the subdivision statutes, and the
regulatory provisions that were promulgated as required by 31
U.S.C. § 1514, which have the force and effect of law. One such
10
regulatory provision was the DOD Accounting Manual, which
states in part that "apportionments and reapportionments by OMB
are required before funds may be obligated." App. 23a. There is
no dispute that the Navy obligated funds before they were
apportioned.
On May 10, 1983, the Navy awarded Cessna a contract that
was administered by the Naval Air Systems Command
("NAVAIR"). App. 2c. The Navy funded the contract with
operations and maintenance ("O&M") moneys. App. 3c. These
are one-year funds that can be expended only for services
performed in the fiscal year for which the funds are appropriated.
App. 3c. The contract had a basic performance period of five
program years, fiscal years ("FYs") 1984-1988. See App. Sc. It
also had a provision for one three-year option for FYs 1989-1991.
App. 4c.
As of September 30, 1988, Congress had not passed and the
President had not signed the DOD appropriations bill for FY
1989, which would fund DOD activities for the fiscal year
beginning on October 1, 1988. App. 12c. At the conclusion of a
September 30 meeting between representatives of Cessna and
NAVAIR, the NAVAIR contracting officer obtained from the
NAVAIR Comptroller a funding sheet that would be necessary to
obligate the funds necessary to exercise the first option. App.
12c. The Financial Accounting Data ("FAD") sheet that was post-
dated to October | and contained the following proviso:
"EXECUTION OF THIS DOCUMENT IS CONTINGENT ON
CONGRESSIONAL PASSAGE OF THE FY-89 DOD
APPROPRIATION ACT OR OTHER AUTHORITY." App. 5b-
6b.
On the morning of Saturday, October 1, 1988, after the end of
the 1988 fiscal year, the contracting officer's supervisor told the
contracting officer that he did not know whether the
appropriations bill had been signed into law. App. 6b. Later, a
NAVAIR supervisor called the Navy's Chief of Information office
at the Pentagon to determine whether the President had signed the
11
bill. No one answered the telephone. The supervisor then called a
local radio station, where someone told him the defense
appropriations bill was one of several bills that the President had
signed into law. App. I4c. The supervisor then left a message on
the contracting officer's answering machine, stating that the
President had signed the bill. Jd.
When the contracting officer received the message, she went to
her office. Alone in her office, she took the FAD sheet given to
her by the Comptroller's office, and proceeded to alter it by
whiting out the proviso. App. 6b. She then redrew the vertical
lines on the form over the white out to hide her alteration of the
document from Cessna. App. 6b. She had neither sought nor
received any authority to alter the document. Nor was she aware
of whether or not funds were actually available with which to
exercise the option.2/ See App. 6b; 14c. She signed the option
exercise modification and addressed the document to Cessna.
App. 6b; 14c.
Through her actions, the contracting officer purported to
obligate more than $22 million to fund the first option year. App.
6b. At the time she took this action, FY 1989 funds had not been
apportioned, allocated, suballocated, or committed, as required by
law and regulation. App. 24b.
By letter dated October 7, 1988, Cessna formally notified the
contracting officer the option exercise was ineffective. App. 17c.
Cessna stated that it would continue to perform contract-type
services and would submit a proposal to the Navy that would
address payment for continued services. App. 17c. The
contracting officer responded to Cessna's October 7, 1988 letter
2; Only the NAVAIR Comptroller could “commit” the funds, a step
necessary before her obligation of them, and he had not done so. NCM
€ 073001. App 20-21f.
12
by letter dated December 7, 1988. App. 19c. In this letter, she
took the position that the option was properly exercised, thereby
directing Cessna to continue performance. App. 19c. Cessna
continued to perform services until September 30, 1991, when the
option period ended. The Navy continued to demand and accept
services during the three year purported option period.
C. This Litigation
On April 8, 1991, Cessna submitted a certified claim to the
contracting officer pursuant to the Contract Disputes Act, 41
U.S.C. §§ 601-609 (1994). App. 10a. The contracting officer
denied the claim, and Cessna appealed the decision to the Armed
Services Board of Contract Appeals ("ASBCA") pursuant to 4]
U.S.C. § 607(d). App. lla. The adverse decision of the ASBCA
was then appealed to the United States Court of Appeals for the
Federal Circuit under 28 U.S.C. § 1295(a)(10). App. 12a. On
October 6, 1997, the Federal Circuit issued an opinion adverse to
Cessna. App. la. Cessna timely filed a petition for rehearing.
That petition was denied on February 27, 1998. App. Id.
REASONS FOR GRANTING THE WRIT
A. The Actions Of The Navair Contracting Officer
Frustrated The Purpose Of Laws Intended To Protect
The Treasury.
This case raises legal issues concerning the Anti-Deficiency
Act and its subordinate statutes. The Comptroller General has
explained the genesis of the Act as follows:
The Anti-deficiency Act was born as 4a result of
Congressional frustration at the constant parade of deficiency
requests for appropriations it was receiving in the 19th century
and early 20th century, generated, it believed, by the lack of
foresight and careful husbanding of funds by Executive branch
agencies. (See Annals of Congress 10th Cong., 2d Sess.
1809.) A consistent theme runs through myriad pages of floor
debates and reports on supplemental appropriation bills: The
Congress was tired of receiving appropriation requests which it
could not, in good conscience, refuse because the agency had
legally or morally committed the United States to make good
on a promise. We term such commitments "coercive
deficiencies" because the Congress has little choice but to
appropriate the necessary funds.
Project Stormfury, 59 Comp. Gen. 369, 372 (1980).
In response to repeated unfunded obligations made by the
Executive Branch, Congress has over the course of nearly two
hundred years enacted a series of laws (currently codified as the
Anti-Deficiency Act and related statutes) governing the manner in
which the Executive may spend money. See 31 U.S.C. §§ I511-
1519, 1341-1342; see generally Stith, 97 YALE L.J. at 1370-1372.
Congress’ exclusive and plenary power to authorize the
expenditure of United States funds is granted by the Constitution.
U.S. Const. art 1, § 9, cl. 7. Thus, the Act and its subordinate
statutes serve as a statutory mechanism to enforce Congress’
14
constitutional right to control the power of the purse. They enjoin
the Executive from spending money in the name of the United
States except as provided by the Congress. See Harrington vy.
Bush, 553 F.2d 190, 194-95 (D.C. Cir. 1977); Secretary of the Air
Force 42 Comp. Gen. 272, 275 (1962).
Each step in the appropriation and apportionment process is a
condition precedent that must be satisfied by the Executive
Branch prior to its entering into contracts or obligating any money
from the Treasury. Strict adherence to these rules is therefore
necessary to preserve Congress’ power of the purse -- the ability
to place conditions on the manner in which money is to be used.
If the laws are not strictly enforced, Congress’ ability to control
the appropriations process becomes illusory.
By adopting the Anti-Deficiency Act and the supporting
statutory scheme, Congress made clear that the Executive Branch
may not /egally obligate funds until authorized government
officials complete an ordered, mandatory series of actions. For
the sake of expediency, a low-level bureaucrat disregarded these
constitutionally based statutes and regulations. For similarly
irrelevant practical considerations, the Federal Circuit, the court
before which these issues almost exclusively arise, declined
strictly to enforce the very statutes disregarded with impunity.
The Federal Circuit's reasoning is certainly contrary to
instructive opinions of this Court, such as Hercules, 116 S. Ct. at
987, wherein this Court held that the Anti-Deficiency Act must be
strictly construed. However, this Court has never squarely
addressed the aspect of the power of the purse presented in this
case: whether and Executive Branch official can disregard the
apportionment process mandated by Congress to effect Article I,
Section 9, Clause 7. Prior Supreme Court cases have dealt with
the Executive's cavalier attitude towards the Anti-Deficiency Act's
appropriation condition precedent. See, e.g, Hooe v. United
States, 218 U.S. 322 (1910) (executive officer is without authority
to bind government to pay amounts in excess of appropriations);
15
Sutton v. United States, 256 U.S. 575 (1921) (Secretary of War
obligation authority limited to amount specifically appropriated).
The case of Clinton v. City of New York, 118 S. Ct. 1551
(1998), which is currently pending before the Court, raises an
issue similar to (and certainly as important as) the one presented
here: the constitutionality of the Line Item Veto Act, in which
Congress has delegated to the Executive certain authority over
appropriated moneys. While both cases address delegation of
control over the purse strings, the Clinton case will leave
unresolved by this Court the issue of whether an Executive
Branch official can disregard the limits placed on that Branch by
the Congress before obligating and expending money. Moreover,
since the issue presented here almost always arises in the
procurement context, only the Federal Circuit is likely to espouse
an appellate view on the subject. For the reasons set forth herein,
that view is constitutionally flawed, but it will likely go
unchallenged except upon review by this Court.
The pending issue lies at the heart of Congress’ constitutionally
granted control of appropriations. Although based on a complex
set of statutes, the mandatory process that was violated by the
Executive official is clearly defined by those statutes. First,
Congress must appropriate the funds. 31 U.S.C. § 1341(a)(1)(B).
Second, the President, through the Office of Management and
Budget, must apportion the funds, i.e., distribute budgeted
amounts to the Executive Branch agencies. 31 U.S.C. § 1512.
Third, the executive agency must allocate, allot, and suballot the
apportioned funds down to the subagency level. 31 U.S.C. §§
1512-14. Fourth, the agency must commit the funds to a contract.
Id. Then, and only then, may a contracting officer legally obligate
funds to a contract. 31 U.S.C. § 1517. None of these steps,
starting with apportionment was followed and the Federal
Circuit's decision effectively gave every contracting officer carte
blanche to usurp each regulatory step.
To emphasize the importance of these rules, Congress directed
the Executive Branch to promulgate implementing regulations
|
16
that also require compliance with this mandatory sequential
process. 31 U.S.C. § 1514(a). Regulations issued pursuant to
section 1514(a) have the force and effect of law, and compliance
with those regulations is mandatory because section 1517
prohibits the violation of such regulations. Thus, violation of the
Act, its subordinate statutory provisions, and the implementing
regulations each constitute a violation of the apportionment
statutes. See Housing and Home Finance, 37 Comp. Gen. 220
(1957),3/
As still one more means of ensuring that the Executive Branch
will follow these requirements and avoid "coercive
deficiencies,"*/ Congress also prohibited the Executive Branch
from accepting voluntary services. 31 U.S.C. § 1342. The
prohibition on voluntary services precludes agencies from
accomplishing the same result indirectly "by accepting ostensibly
‘voluntary’ services, and then presenting Congress with the bill."
GAO, Principles of Federal Appropriations Law, ch. 6, at 56
(1992).
Finally, in recognition of the importance of the principles
underlying the Anti-Deficiency Act, Congress imposed a criminal
Se
3/ DOD's implementing regulations are contained in the DOD
Accounting Manual and DOD Directive 7200.1, dated May 7, 1984. The
Navy's further implementing regulations include those set out in the
Navy Comptroller Manual ("NCM"), Navy Comptroller Instructions, and
NAVAIR Instructions.
4/ The Comptroller General defines "coercive deficiencies" as
“appropriation requests which [the Congress] could not, in good
conscience, refuse because the agency had legally or morally committed
the United States to make good on a promise." 59 Comp. Gen. at 372;
see Herbert L. Fenster and Christian Volz, The Anti-Deficiency Act:
Control Gone Astray, 11 PUB. CON. L.J. 155 (1979 ).
17
penalty on government employees who violate the act. 31 U.S.C.
§ 1350.
Sy
The Federal Circuit let stand the underlying factual finding
that the Navy did obligate funds before they were apportioned.
The court then refused to grant Cessna any relief on the grounds
that the provisions disregarded were intended to benefit only the
Government, necessarily understood to mean the Executive. In
reaching that result, the Federal Circuit's decision conflicts with
existing precedent of this Court, and rests on grounds rejected in
case law of this Court. See National Credit Union Admin. v. First
National Bank & Trust Co., 118 S. Ct. 927 (1998). In effect, the
Federal Circuit has resurrected a law of standing that has been
dead for twenty years. Because the Federal Circuit's opinion
condones the Navy's behavior, Executive bureaucrats may violate
statutes and regulations with impunity. The Federal Circuit then
left to the contractor, not the government, the consequences of the
government's illegal conduct.
Under the Federal Circuit's reasoning, the contractor would
have to continue performing even though the government could
(or must) abrogate the contract. See Hercules, Inc. v. United
States. 116 S. Ct. 981 (1996). Under applicable case law, if only
the government can avoid the contract, then the contract should be
unenforceable due to lack of mutuality of obligations. See, e.g.,
Lynch v. United States, 292 U.S. 571, 579 (1934) ("When the
United States enters into contract relations, its rights and duties
therein are governed generally by the law applicable to contracts
between individuals."); see also, Winstar v. United States, 518
U.S. 839 (1996). However, under the Federal Circuit's holding,
the contractor lacks standing to determine the legality of its own
contract.
In rejecting Cessna’s arguments that the NAVAIR official
violated the governing statutes by obligating moneys before they
were apportioned, the Court of Appeals distinguished 31 U.S.C.
§ 1341(a), which prohibits the government from incurring
obligations in advance of appropriations, from 31 U.S.C §§ 1511-
18
1519, the apportionment provisions of the Anti-Deficiency Act.
The court did so on the grounds that unlike section 1341(a),
sections 1511-1519, contain no timing limitations, and because
section 1517 "says nothing about incurring obligations prior to
carrying out the apportionment process." App. 25a. To the
contrary, the sections are not distinguishable. In fact, the
operative language "distinguished" by the court is virtually
identical.
Section 1341(a)(1) provides as follows:
An officer or employee of the United States Government or
of the District of Columbia government may not (A) make or
authorize an expenditure or obligation exceeding an amount
available in an appropriation or fund for-the expenditure or
obligation.
Section 1517(a) provides as follows:
An officer or employee of the United States Government or
of the District of Columbia government may not make or
authorize an expenditure or obligation exceeding (1) an
apportionment.
The only difference between section 1341(a), in which the
appeals court recognizes the order of precedence, and section
1517(a)(1), in which the court finds none, are the words that
follow "exceeding." Section 1341 deals with obligating amounts
exceeding an appropriation, and section 1517 addresses the
obligation of amounts exceeding an apportionment. Aside from
that difference, i.e., the pertinent step in the funding process, the
two provisions are identical. Both prohibit the obligation of
moneys in advance of the specified event in the funding process.
The Federal Circuit also relied on the notion that obligating
and expending funds before they are apportioned means that they
were not obligated in excess of an apportionment. Logic dictates
a a i ca a a a a ae
1 ab alle
19
that if the Executive official can avoid the prohibition against
obligating funds in excess of an apportionment by simply
obligating them before they are apportioned, the apportionment
provision becomes meaningless. The actions of the low-level
bureaucrat have deprived the President, the Secretary of Defense,
the Secretary of the Navy, and the Commander of NAVAIR of
their rights and obligations to determine the appropriate use of the
funds involved.
Rather than strictly construe the apportionment statute, the
Federal Circuit defined "in excess of" to mean not just more than
but also after. If that were the case, then an Executive Branch
official could also obligate and expend moneys before they are
even appropriated since doing so would not be "in excess” of an
appropriation. That interpretation would squarely contradict this
Court's holding in Sutton v. United States, 256 U.S. 575, wherein
the Court held that the Secretary's authority was limited to the
amount appropriated.
Recently, the Supreme Court has made very clear that the
Anti-Deficiency Act is to be construed strictly. According to the
Court, the meaning of the Act is plain: it prohibits the government
"from entering into a contract for future payment of money in
advance of, or in excess of, an existing appropriation.” Hercules,
116 S. Ct. at 987. Given this Court's interpretation of section
1341(a) and that provision's language in common with section
1517. there is but one correct interpretation of section 1517: it
prohibits the government "from entering into a contract for the
future payment of money in advance of or in excess of, an
existing [apportionment.]" See id. at 987 (emphasis added). The
Court of Appeals ruling to the contrary cannot be reconciled with
either the plain wording of the statute or the Hercules decision.
Similarly, 31 U.S.C. § 1512 expressly requires that
appropriated funds be apportioned. This necessarily means that
no use of funds -- even though appropriated -- may be made
before apportionment -- an understanding of the law that is shared
by the government. In implementing these statutory
20
requirements, the DOD Accounting Manual specifically states
that tunds must be apportioned before they may be obligated:
An apportionment or reapportionment is a_ distribution
made by OMB [Office of Management and Budget] of
amounts available for obligation in an appropriation or fund
account. Except in certain instances . . . apportionments and
reapportionments by OMB are required before funds may be
obligated.
App. 23a (emphasis added).>/ The reason for this requirement is
clear: OMB (as the delegee of the President) may decide to delay
or otherwise alter an expected apportionment. And, if obligations
are made before the apportionment, those obligations may, in fact,
have no support in apportioned funds. By allowing the NAVAIR
contracting officer to obligate funds before the President has
apportioned them, the Court of Appeals would permit a
subordinate agent to usurp the President's obligation to impound
those funds and similarly would usurp the authority of those
officials having allocation and commitment responsibilities.
Clearly, this was not what the Congress intended when it
designated the President, who in turn designated the Director of
OMB, as the sole authority to apportion moneys. The same holds
true for regulatory process implemented by the Department of
Defense. After funds are allocated to the Secretary of Defense,
regulations required then to be allotted, suballotted and committed
down through the chain of command to the Contracting Officer.
NCM 4 073002(2). App. 24f.
Consistent with that reasoning, the Navy's own regulations do
require apportionment before obligation. The NCM imposes a
5
DOD Directive 7200.1 similarly states that obligation authority is
restricted to the amount that has been apportioned, and emphasizes that
obligations are not authorized in excess of the amount apportioned. App.
7f, 13f-14f
oe Oa ie
21
sequential funding process whereby funds first are apportioned,
then allocated to the Secretary of Defense, and then allotted,
suballotted, and committed through the chain of command in the
Navy. NCM 4 073002(2). App. 24f. Under this regime, a
contracting officer may not obligate funds until a// of the proper
preceding steps in the sequential funding approval chain have
been completed. The NCM expressly states the apportionment
process "is the initial step in the budget execution phase." NCM 4
073100. App. 28f.
The Congressional Research Service has confirmed this
requirement that funds must be apportioned before they are
obligated:
When full-year defense appropriations have been enacted,
military agencies, installations, and activities do nol
immediately have the authority to obligate the Federal
Government to spend money. The Anti-Deficiency Act (31
U.S.C. 1511 et seg.) requires that funds . . . be apportioned or
distributed to the military departments. (Emphasis added. )
CRS. Short-Term Continuing Resolutions. The Department O}
Defense Experience, at 8, 89-579F (Oct. 19, 1989).
Nonetheless, the Court of Appeals ruled that funds could be
obligated before they are apportioned, notwithstanding the laws as
written. When the Board of Contract Appeals declined to enforce
the funding laws and regulations, it candidly admitted to a fear
that holding the Navy responsible for a violation of the statutory
and regulatory requirements would "wreak havoc" on the federal
procurement process. App. 33b. Because of this erroneous and
irrelevant perceived practical effect, the Board concluded that "it
is unreasonable to read the apportionment statutes to require the
Government to halt all contractual actions when OMB takes its
statutorily allotted time to discharge its apportionment duties."
Id. In short, the Board allowed perceived practical concerns to
subvert Congress’ requirement that the Executive Branch comply
with the law before obligating funds. While the court did not
7
~~
admit to such a fear, the reasoning provided evidences that it
placed perceived practical considerations above the dictates of the
law.
Neither the Board nor the court may bend or ignore the law
because of potential implications of the outcome. See
Commissioner v. Asphalt Prods. Co., 482 U.S. 117, 121 (1987).
This Court made this point very clearly in its recent Hercules
decision by giving the Act its literal meaning. This Court ruled
that "the Act bars agreements for which there has been no
appropriation," unless a statute expressly permitted an exception
to the Anti-Deficiency Act. 116 S. Ct. at 988 n.10. Rather than
applying the Act so as to give effect to Congress’ intent, and to
enforce Congress’ constitutional power of the purse, the Court of
Appeals ignored the Act and gave effect to the Navy's fears about
the practical consequences of requiring the Navy to follow the
law.
It is apparent that concern over the practical consequences of
the decision affected the way the court chose to read the law. The
court concluded funds may be obligated in advance of an
approved apportionment even while it agreed that funds could not
be obligated in excess of an approved apportionment. App. 24a-
25a. This conclusion is inherently inconsistent. In the absence of
an apportionment, the amount of apportioned funds is zero. At
that point, any obligation would exceed the apportioned amount,
and so would be illegal.
B. This Court's Precedent Hold That Contracts Executed
In Violation Of The Law Cannot Be Enforced.
As was explained above, once funds have been apportioned,
they must be allocated and committed before they can be
obligated. Accordingly, the option exercise was ineffective
because the contracting officer acted without authority when she
purported to obligate funds in order to exercise the option: she
usurped the authority of OMB to apportion funds, the authority of
the Comptroller of the Navy to allocate funds, and the authority of
the NAVAIR Comptroller to commit funds.
NE Le Te TI ae nS oe
}
bo Wieden Tie aie Se ia
23
For over a hundred years the law has been that a contract in
violation of the law is a nullity. In Clark v. United States, 95 U.S.
$39 (1877), the owner of a vessel had entered into an oral contract
under which the government would put the vessel to use to
determine whether it would satisfy its needs, would pay a
specified daily rate for use of the vessel and would be responsible
for the vessel while in its possession. While in the government's
possession, the vessel was destroyed. The owner sought recovery
in the Court of Claims. This Court held that the oral contract
violated the statutory requirement that all contracts be in writing,
and that the oral contract was therefore not enforceable.
In this case, the contract was executed by the government in
violation of federal funding laws. As such there can be no
enforceable contract. Stated another way, the contracting officer
had no authority to exercise the option because doing so was in
violation of the apportionment statutes. It is a basic rule that any
action taken by a government employee in absence of authority is
a nullity. ~See Federal Crop Ins. Corp. v. Merrill, 332 U.S. 380
(1947). Accordingly, no valid contract was brought into existence
when the contracting officer required Cessna to perform work
based on the obligation of funds that had not been apportioned.
C. The Court Of Appeals Ruling On Standing Conflicts
With The Law Of This Court And Other Circuit
Courts Of Appeal.
The Court of Appeals dismissed Cessna’s arguments that
NAVAIR's actions were in violation of the Anti-Deficiency Act
and Navy regulations implementing that Act. The court found no
violation of the Act, which for the reasons explained above was
erroneous, and ruled that any violations of the regulations
implementing the Act were of no consequence because Cessna
was not entitled to rely upon the Navy's compliance with these
laws. Presumably, the court's reasoning would apply to violations
of the Anti-Deficiency Act as well. In either case, to deny Cessna
any relief, the Court of Appeals resurrected a rule of standing that
was repudiated nearly thirty years ago.
24
The court's decision in this respect relies upon stale case law:
Rough Diamond Co. v. United States, 351 F.2d 636 (Ct. Cl. 1965).
See App. 26a. The court's 1965 decision in Rough Diamond
expressly relied upon the Supreme Court's even earlier 1940
decision in Perkins v. Lukens Steel Co., 310 U.S. 113 (1940), as
do ultimately all the other cases cited to by ihe Court of
Appeals.® By relying upon the Perkins line of cases, the Court of
Appeals turned back the clock on the law of standing.
In Perkins, the Court ruled that a disappointed bidder had no
legal right to complain about the government's violation of the
Walsh-Healy Act, because the Act was for the "sole benefit" of
the government, and any violation of the Act therefore conferred
no legal rights on the contractor. 310 U.S. at 129. Two decisions
issued in 1970 make it clear that Perkins no longer reflects the
state of the law.
First, the D.C. Circuit decided Scanwell Laboratories v.
Shaffer, 424 F.2d 859 (D.C. Cir. 1970), where the court held that a
disappointed bidder has standing to challenge the legality of a
contract award, regardless of the nature of the statute or regulation
the government allegedly violated in conducting the procurement.
Second, the Supreme Court soon thereafter explicitly restated the
law on standing in Association of Data Processing Service
Organization v. Camp, 397 U.S. 150 (1970). In reversing the
appeals court's reliance upon Perkins, the Court adopted the
current standing test, and implicitly reyected the old test adopted
in Perkins, by stating "the existence or non-existence of a ‘legal
6/ Hartford Accident & Indemnity Co. v. United States, 127 F. Supp.
565, 567 (Ct. Cl. 1955) (citing Perkins); Applied Devices Corp. v. United
States, 591 F.2d 635, 640 (Ct. Cl. 1979) (citing Rough Diamond), Chris
Berg, Inc. v. United States, 426 F.2d 314, 317 (Ct. Cl. 1970) (citing
Hartford), and LaBarge Products, Inc. v. West, 46 F.3d 1547, 1552 (Fed.
Cir. 1995) (citing Rough Diamond and Chris Berg).
25
interest’ is a matter quite distinct from the problem of standing.”
Id. at 153 n.1.
After Camp, many courts have recognized that the legal right
test established by Perkins no longer applies, and by extension,
the cases resting on Perkins no longer are good law. See, @.g.,
B.K. Instrument, Inc. v. United States, 715 F.2d 713, 719 (2d Cir.
1983) ("[t]he Court in Data Processing repudiated the [ Perkins]
‘legal right’ doctrine as a test of standing. . . ."); Hayes Int'l Corp.
vy. MeLucas, 509 F.2d 247, 254-55 (Sth Cir. 1975) ("While
Perkins has not been expressly overruled by the Supreme Court,
the ‘legal interest’ test for standing has largely been abandoned.").
See generally Davis and Pierce, Administrative Law Treatise
§§ 16.2-16.3 (1994). Recently, this court expressly held that
standing was not dependent upon whether a statue was intended to
benefit the plaintiff. National Credit Union Admin., 118 S. Ct. at
1938.
By resurrecting the Perkins line of cases, the Federal Circuit
brought back from the dead a standing rule which the decisions of
other circuit courts of appeal and the Supreme Court indicate had
been long gone. Confusing the matter further is the length to
which the court went in ruling Cessna had standing to pursue its
claim based upon the Anti-Deficiency Act. App. }3a-17a. But
later. the court relies upon out of date standing cases to pull the
rug from out under this ostensible holding on standing, by stating
contractors do not have any legal interests protected by the Anti-
Deficiency Act. Which Is to say, contractors do not have standing
to challenge Anti-Deficiency Act violations.
Tne Court of Appeals relies upon American Farm Lines Vv.
Black Ball Freight Service, 397 U.S. 532 (1970) for the notion
that an agency "always" can relax its rules when those rules are
26
not intended to benefit the public. App. 27a.’/ But through
inadvertence or otherwise, the Court of Appeals does not state the
complete rule established by this Court. In particular, the
appellate court does not address the exception relevant here,
namely, that an agency may not violate its rules when this would
cause "substantial prejudice to the complaining party." American
Farm Lines, 397 U.S. at 539 (quoting NLRB v. Monsanto Chem.
Co., 205 F.2d 763, 764 (8th Cir. 1953). See also Oy v. United
States, 61 F.3d 866, 875 (Fed. Cir. 1995). Cessna obviously was
prejudiced in a very substantial way by the Navy's violations of
the provisions at issue -- it was forced to continue contract
performance at a substantial loss.
7/ American Farm Lines involved rules obviously of a procedural
nature, and were developed by the agency without any requirement to do
so. Here, the Navy was dealing with substantive rules made applicable
Statute. f
27
CONCLUSION
For the reasons set forth above, this Court should grant the
petition for a writ of certiorari.
Respectfully submitted,
HERBERT L. FENSTER*
JEREMY M. GRIFFIN
MCKENNA & CUNEO, L.L.P.
1900 K Street, N.W.
Washington, D.C. 20006
(202) 496-7500
Counsel for Petitioner
*Counsel of Record
May 28, 1998
APPENDIX
EAE IO PITRE
ETRE EOS IIR LILIE ELE LOINC ISS SRI he
eae a ei sin Tale at EEE REEL E Sees ah aa
The CESSNA AIRCRAFT COMPANY, Appellant,
v.
John H. DALTON, Secretary of Navy, Appellee.
No. 96-1185.
United States Court of Appeals,
Federal Circuit.
Oct. 6, 1997.
Rehearing Denied; Suggestion for Rehearing In Banc
Declined Feb. 27, 1998.
Contractor appealed from decision of the Armed Services
Board of Contract Appeals, 1993 WL 89795, 1995 WL
575173, denying contractors’ claims that Navy failed to
exercise, in proper and timely manner, options under
contract. The Court of Appeals, Schall, Circuit Judge, held
that: (1) contractor's claim for additional compensation for
work performed during three-year option period arose under
Contract Disputes Act (CDA) and was within Board's
jurisdiction; (2) Antideficiency Act did not prohibit funds
from being obligated before they were both appropriated by
Congress and apportioned by Executive Branch; (3)
provision of Navy contract requiring Navy to exercise option
to renew "not later than 1 October, 1988" permitted Navy to
exercise option on that date; and (4) although Navy deviated
from Cancellation of Items clause in drafting contract
schedule that gave Navy until day after contract expired to
exercise option to renew, without first obtaining proper
authority to do so, contractor could not rely on deviation in
arguing that Navy's exercise of options for two fiscal years
were ineffective.
Affirmed.
[1] UNITED STATES k73(15)
393k73(15)
Conclusions of law of Armed Services Board of Contract
Appeals are reviewed de novo; such legal conclusions
include grants of summary judgment. Contract Disputes Act
of 1978, § 10(b), 41 U.S.C.A. § 609(b).
[2] UNITED STATES k73(15)
393k73(15) ;
Decision of the Armed Services Board of Contract
Appeals on finding of fact may not be set aside unless
opponent can meet its burden establishing that finding is
arbitrary, capricious, so erroneous as to necessarily imply bad
faith, or not supported by substantial evidence. Contract
Disputes Act of 1978, § 10(b), 41 U.S.C.A. § 609(b).
[3] UNITED STATES k73(9)
393k73(9)
Contractor's claim for additional compensation for work
performed during three- year option period arose under
Contract Disputes Act (CDA) and was within jurisdiction of
Armed Services Board of Contract Appeals, although
contractor argued that Navy violated Antideficiency Act and
attendant regulations and sought compensation from Navy
based upon theory of implied-in-fact contract for services
rendered during option years. Contract Disputes Act of 1978,
§ 8(d), 41 U.S.C.A. § 607(d); 31 U.S.C.A. § 1341.
[4] UNITED STATES k62
393k62
3a
Generally, Antideficiency Act prohibits government
officials and employees from making expenditures or
incurring obligations in excess of available appropriations or
in advance of appropriations. 31 U.S.C.A. § 1341.
[4] UNITED STATES k82(1)
393k82(1)
Generally, Antideficiency Act prohibits government
officials and employees from making expenditures or
incurring obligations in excess of available appropriations or
in advance of appropriations. 31 U.S.C.A. § 1341.
[5] UNITED STATES k79
393k79
Pi sacl aca a aN et My ve
As far as government contracts are concerned,
| Antideficiency Act bars federal employee or agency from
4 entering into contract for future payment of money in
j advance of, or in excess of. existing appropriation. 31
US.C.A. § 1341.
: [6] UNITED STATES k79
393k79
page ay eee
Antideficiency Act did not prohibit funds from being
? obligated before they were both appropriated by Congress
and apportioned by Executive Branch. 31 US.C.A. §§ 1341,
1512, 1517.
[7] UNITED STATES k62
393k62
Contracting officer's exercise of option to renew Navy
contract after funds were appropriated by Congress did not
violate Antideficiency Act, even though funds were obligated
4a
before they were apportioned by Executive Branch. 31
U.S.C.A. §§ 1341, 1512, 1517.
[8] UNITED STATES k70(35)
393k70(35)
Provision of Navy contract requiring Navy to exercise
option to renew "not later than 1 October, 1988" permitted
Navy to exercise option on that date, even though underlying
contract expired on September 30; Navy's ability to exercise
option was not tied to original performance period of the
contract.
[9] UNITED STATES k70(35)
393k70(35)
Contractor was not compelled to perform voluntary
services when Navy contract expired and Navy did not
exercise option to renew until the next day; to the extent that
contractor maintained personnel and equipment at site during
period in question, it did not show that Navy either requested
or compelled it to do so or that Navy accepted those services
in violation of statute prohibiting voluntary services. 31
U.S.C.A. § 1342.
[10] UNITED STATES k70(35)
393k70(35)
Although Navy deviated from Cancellation of Items
clause in drafting contract schedule that gave Navy until day
after contract expired to exercise option to renew, without
first obtaining proper authority to do so, contractor could not
rely on deviation in arguing that Navy's exercise of options
running for two fiscal years were ineffective, since >
Cancellation of Items clause was primarily for benefit of
government. 48 C.F.R. § 17.109(a).
Sa
*1443 Herbert L. Fenster, McKenna & Cuneo, L.L.P.,
Denver, CO, argued for appellant. With him on brief were
Michael T. Janik and David Kasanow, Washington, DC.
Geoffrey C. Cook, Attorney, Commercial Litigation
Branch, Civil Division, Department of Justice, Washington,
DC, argued for appellee. With him on brief were Frank W.
Hunger, Assistant Attorney General, and David M. Cohen,
Director.
Before LOURIE, CLEVENGER, and SCHALL, Circuit
Judges.
SCHALL, Circuit Judge.
The Cessna Aircraft Company ("Cessna") appeals from
March 12. 1993 decision of *1444 Armed Services Board of
Contract Appeals ("Board") on cross-motions for partial
summary judgment in Cessna Aircraft Co., ASBCA No.
43196. 93-3 BCA § 25,912, 1993 WL 89795 (Mar. 12, 1993)
(Cessna I ). Cessna also appeals from Board's September 21,
1995 decision following a hearing in same case, 96-1 BCA §
27.966, 1995 WL 575173 (Sept. 21, 1995) (Cessna II). In
those decisions, Board denied Cessna’s claims that Naval Air
Systems Command of United States Navy ("Navy" or
"NAVAIR") failed to exercise, in a proper and timely
manner, certain options under a contract between Cessna and
Navy. We affirm.
BACKGROUND
I.
This appeal arises out of Contract No.
Ni00019-83-C-0090, awarded to Cessna by Navy, under
which Cessna was required to provide training, and related
technical and maintenance support, for undergraduate naval
6a
flight officers at U.S. Naval Air Station in Pensacola, Florida.
See Cessna I, 93-3 BCA at 128,876. [FN1]
FN1. We addressed other claims that Cessna made
arising out of the same contract in Dalton v. Cessna Aircraft
Co., 98 F.3d 1298 (Fed.Cir. 1996).
The contract called for Cessna to provide flight training
services during five program years, commencing August 1,
1984, and ending September 30, 1988. Cessna I, 93-3 BCA at
128.876. Each program year ended on last day of
government's fiscal year, September 30. Id. In addition,
contract contained an option provision allowing Navy to
extend contract performance for three additional years. Id.
Section H-6 of contract Schedule, entitled "Exercise of
Option,” established conditions on Navy's exercise of option.
Section H-6 provided as follows:
Pursuant to "Option to Extend Services"
clause, option for three years will be
exercised, if at all, in writing by a unilateral
modification to this contract issued by
Contracting Officer, Naval Air Systems
Command, not later than 1 October 1988.
Id. Each option year ran from October | to September 30;
that is, first option year ran from October 1, 1988 to
September 30, 1989, second option year ran from October 1,
1989 to September 30, 1990, and third option year ran from
October 1, 1990 to September 30, 1991. Cessna I, 93-3 BCA
at 128.876. The Navy had to notify contractor of availability
of funds for second and third option years.
The timing of this notification was addressed by section
H-8 of contract Schedule, entitled "Multiyear Procurement,"
which stated that:
ee
7a
If three year option is exercised, date within which
contracting officer
... Will notify Contractor of availability of
funds sufficient for performance of
requirements for the Second Option Year
(Fiscal Year 1990) is 1 October 1989. Third
Option Year (Fiscal Year 1991) is 1 October
1990.
Id. at 128.877. The contract further incorporated by
reference, inter alia, two Defense Acquisition Regulation
("DAR") provisions concerning multiyear aspects of contract.
The first, named "Cancellation of Items" clause, addressed
cancellation of contract based on a lack of availability of
funds. This clause stated in pertinent part:
(b) As used herein, term "cancellation" means that
Government is canceling, pursuant to this clause, its
requirements for items as set forth in Schedule for all fiscal
years (1 October - 30 September) subsequent to that in which
notice of cancellation is provided. Such cancellation shall
occur only if Contracting Officer (i) notifies Contractor that
funds will not be available for contract performance for next
succeeding fiscal year and any subsequent fiscal year; or (11)
fails to notify Contractor prior to beginning of next
succeeding fiscal year that funds have been made available
for performance in succeeding fiscal year.
DAR § 7-1903.33(d). [FN2] A related clause addressed
contract execution once funds became available. It stated in
pertinent part that:
FN2. The DAR has since been replaced by the Federal
Acquisition Regulation ("FAR"). The analogous FAR
provision is 48 C.F.R. § 52.217- 2 (1996).
8a
Upon availability to Contracting Officer of funds for
performance of requirements in *1445 next succeeding fiscal
year, Contracting Officer shall notify Contractor in writing of |
amount of funds available for contract performance in next
succeeding fiscal year and contract shall be modified |
accordingly.
DAR § 7-1903.33(c). [FN3]
FN3. No FAR provision analogous to section
7-1903.33(c) currently exists.
The contract was awarded on May 10, 1983. Sometime
in either late March or early April of 1988, during final
program year of original five-year term of contract, Cessna
contacted contracting officer ("CO") to inquire about whether
Navy intended to exercise three year option. Cessna II, 96-1
BCA at 139,686. In response, by letter dated April 18, 1988,
CO informed Cessna that Navy did intend to exercise option,
stating that:
1. You are hereby notified of our intent to
exercise option for three option years under
Contract N00019-83-C-0090. Pursuant to
Special Provision H-6, "Exercise of Option,"
we will exercise option for three option
years, if at all, not later than 1 October 1988.
Id.
On August 3, 1988, during negotiation meetings
concerning unrelated claim for equitable adjustment made by
Cessna, Cessna again raised issue of when Navy intended to
exereise option. Id. At that time, Cessna expressed its view
that option had to be exercised before October 1, 1988. Id.
On September 26, 1988, in a telephone conversation between
9a
CO and a Cessna official, CO asked whether, because
October 1, 1988 was a Saturday, it would be acceptable for
option to be exercised on October 3, 1988. Cessna II, 96-1
BCA at 139,687. The Cessna official responded that October
3 would be a problem and that Cessna needed to receive
exercised option on October 1. Id. CO informed Cessna
official at that time that she would exercise option via
facsimile on October 1. Id.
During period September 27-30, 1988, in midst of further
negotiations regarding Cessna's equitable adjustment claim,
Cessna reiterated its view that Navy had to exercise option by
September 30, 1988, while the Navy contended that it had
until October 1. Id. As of September 30, 1988, the
Department of Defense Appropriation Act, 1989, Pub.L. No.
100-463, 102 Stat. 2270 (1988), from which the contract at
issue would be funded, had been passed by Congress but had
not yet been signed by the President. Cessna II, 96-1 BCA at
139.687. On September 30, the CO informed Cessna that the
option would be faxed on October 1. Id. at 139,688.
Anticipating the passage of the appropriation act, on
September 30, 1988, a NAVAIR budget analyst executed a
"Financial Accounting Data Sheet"--used to make funds
available for obligation--with the proviso "EXECUTION OF
THIS DOCUMENT IS CONTINGENT ON
CONGRESSIONAL PASSAGE OF THE FY89
APPROPRIATION ACT OR OTHER AUTHORITY.” Id. at
139,687-88.
On October 1, 1988, after receiving word from a
NAVAIR division director that the President had signed the
appropriation act, the C O executed the necessary contract
modification, deleted the proviso from the Financial
Accounting Data Sheet, and faxed the modification and data
sheet to Cessna. Id. at 139,688. Cessna personnel found the
10a
faxed version of the modification and data sheet on Monday,
October 3, 1988. Cessna II, 96-1 BCA at 139,689.
By letter dated October 7, 1988, Cessna took the position
that the purported modification was ineffective. Id. The letter
further stated that Cessna would continue to provide services
and would submit a proposal for continuation of the work.
Id. at 139,689-90. On December 5, 1988, Cessna submitted a
proposal to the Navy for providing services for the three
option years. Id. at 139,690. In its letter, Cessna stated that
it was proceeding under the assumption that its services
would soon be embodied in a definitive contract. By letter
dated December 7, 1988, the CO responded that the option
was exercised properly on October 1, 1988, and instructed
Cessna to continue performance in accordance with the
contract as modified by the option. Cessna II, 96-1 BCA at
139,690. Cessna provided services throughout the three year
option period. Similar to the first option year, for the second
and third option years, pursuant to section H-8 of the
contract, the Navy transmitted the appropriate *1446
modifications on October 1, 1989, and October 1, 1990,
respectively.
LN Pee eee Te SEE eT i SST Pa
IT.
In April of 1991, Cessna submitted a certified claim to
the CO, as revised in June of 1991, seeking approximately
$25.7 million as additional compensation for work performed
during the three year option period. The CO neither issued a
final decision nor informed Cessna when such decision
would be issued within the sixty day time limit of Section
6(c) of the Contract Disputes Act ("CDA"), 41 U.S.C. §
605(c). [FN4] Cessna appealed this deemed denial to the
Board. [FN5]
lla
FN4. Section 605(c)(2) provides that "[a] contracting
officer shall, within sixty days of receipt of a submitted
certified claim over $100,000-- (A) issue a decision; or (B)
notify the contractor of the time within which a decision will
be issued." 41 U.S.C. § 605(c)(2) (1994).
FNS. Section 605(c)(5) of the CDA provides in pertinent
part that "[a]ny failure by the contracting officer to issue a
decision on a contract claim within the period required will
be deemed to be a decision by the contracting officer denying
the claim and will authorize the commencement of the appeal
or suit on the claim as otherwise provided in this chapter."
41 U.S.C. § 605(c)(5) (1994).
Before the Board, Cessna argued, inter alia, that: (i) the
CO violated the Antideficiency Act and attendant regulations
by obligating funds for the first and third years of the
three-year option period prior to apportionment and
allocation of the funds (Counts I and XIII); (ii) the CO's
actions in deleting the proviso on the Financial Accounting
Data Sheet rendered the option exercise ineffective (Count
III); (iii) the Navy failed to exercise the option, in a timely
manner, such that the contract was canceled (Count V); (iv)
by exercising the option on October 1, 1988, the Navy
required Cessna to provide voluntary services in violation of
the Antideficiency Act (Count VI); and (v) the second and
third option years were canceled because the CO did not
‘ssue a notice of funds availability prior to the beginning of
the succeeding fiscal year (Counts VIII and XI). [FN6]
Cessna I, 93-3 BCA at 128,880-81. In Count XIV, Cessna
sought to recover compensation for services rendered during
the option years based upon a theory of implied-in-fact
contract. Cessna II, 96-1 BCA-at 139,683.
12a
FN6. While Cessna made other claims before the Board,
those claims are not relevant to the present appeal and are not
discussed in this opinion.
In due course, the parties filed cross-motions for
summary judgment with respect to Counts I, III, VIII, XI],
and XIII. The Board granted the Navy's motion for summary
judgment as to Counts I, III, and XIII, and denied summary
judgment to both sides on Counts VIII and XI. Cessna I, 93-3
BCA at 128,911. After a hearing on the merits, the Board
issued a decision denying Cessna relief on Counts V, VI,
VIII, and XI. See Cessna II, 96-1 BCA at 139,683, 139,701.
In sum, the Board denied Cessna relief as to all of its claims
pertinent to its appeal. This appeal followed.
DISCUSSION
I.
Pursuant to the CDA, 41 U.S.C. §§ 601-613 (1994), we
review decisions of the Board under the following standard:
the decision of the agency board on any
question of law shall not be final or
conclusive, but the decision on any question
of fact shall be final and conclusive and
shall not be set aside unless the decision is
fraudulent, or arbitrary, or capricious, or so
grossly erroneous as to necessarily imply
bad faith, or if such decision is not
supported by substantial evidence.
41 U.S.C. § 609(b).
[1] The Board's conclusions of law are reviewed de novo.
See Ingalls Shipbuilding, Inc. v. Dalton, 119 F.3d 972, 975
(Fed.Cir.1997). Such legal conclusions include grants of
13a
summary judgment. See Confederated Tribes of Colville
Reservation v. United States, 964 F.2d 1102, 1107
(Fed.Cir.1992) (noting that the grant of summary judgment is
a legal conclusion).
[2] The Board's decision on a finding of fact may not be
set aside unless the appellant can meet its burden of
establishing that the finding is arbitrary, capricious, so
erroneous as to necessarily imply bad faith, or not supported
by substantial evidence. Erickson Air Crane Co. v. United
States, 731 F.2d 810, 814 (Fed.Cir.1984); see William F.
Klingensmith, Inc. v. United States, 731 F.2d 805, *1447 809
(Fed.Cir.1984); J.M.T. Mach. Co. v. United States, 826 F.2d
1042, 1046 (Fed.Cir.1987). On appeal, Cessna makes the
following contentions: (i) the Board erred in sustaining the
Navy's actions in obligating funds in advance of carrying out
the apportionment process (Counts I and XIII); (ii) the Board
incorrectly concluded that the option was properly exercised
even though the CO deleted the proviso on the Financial
Accounting Data Sheet (Count III); (iii) the Board
erroneously determined that the option was timely exercised
(Count V); (iv) the Board erred in concluding that the Navy
did not require Cessna to perform voluntary services (Count
VI); and (v) the Board incorrectly refused to give precedence
to the Cancellation of Items clause and therefore erred in
concluding that the second and third option years of the
contract were not canceled (Counts VIII and XI). For the
reasons set forth below, we reject Cessna's arguments.
I.
[3] Before reaching the merits of the appeal, we must
address a preliminary issue raised by the Navy. Before the
Board, the Navy argued that Cessna lacked standing to
contest matters relating to the Navy's compliance with
———————
l4a
funding statutes. The Board rejected this challenge to its
jurisdiction. The Board noted that under the CDA, it had
jurisdiction "to decide any appeal from a decision of a
contracting officer ... relative to a contract made by its
agency." Cessna I, 93-3 BCA at 128,881 (citing 41 U.S.C. §
607(d)). The Board concluded that Cessna's appeal related to
its contract with the Navy and that therefore Cessna's
standing to bring the appeal and the Board's jurisdiction to
decide it were "grounded in the provisions of the CDA." Id.
As it did before the Board, the Navy argues that the
Antideficiency Act does not provide Cessna with a private
right of action. Thus, it asserts that Cessna's appeal from the
Board's decision regarding Counts I, III, VI, and XIII should
be dismissed because those counts involve claims relating to
the government's funding of its contractual obligations, and
no private right of action exists under the Antideficiency Act
with respect to such matters. Quoting from Hagan v. United
States, 229 Ct.Cl. 423, 671 F.2d 1302 (1982), the Navy
argues that the Antideficiency Act "sets forth its own
discipline and penalties, and does not rely on private
enforcement through Tucker Act litigation." Id., 671 F.2d at
1305. We disagree.
As the Board noted, pursuant to 41 U.S.C. § 607(d), it has
jurisdiction "to decide any appeal from a decision of a
contracting officer ... relative to a contract made by its
agency." Cessna I, 93-3 BCA at 128,881. Section 607(d)
further provides that, "[i]n exercising this jurisdiction, the
agency board is authorized to grant any relief that would be
available to a litigant asserting a contract claim in the United
States Court of Federal Claims."
Like the Board, we view Cessna's claims as "grounded in
the CDA.” Cessna's contract with the Navy was governed by
the CDA, and it was under the CDA that Cessna submitted its
|
15a
claim to the contracting officer for additional compensation
for work performed during the three year option period. The
fact that Cessna argues that the Navy violated the
Antideficiency Act and attendant regulations and the fact that
Cessna seeks compensation from the Navy based upon a
theory of implied-in-fact contract for services rendered
during the option years do not mean that Cessna is seeking
relief under the Antideficiency Act.
In Gould, Inc. v. United States, 935 F.2d 1271
(Fed.Cir.1991), Gould, Inc. ("Gould") was awarded a
five-year contract by the Navy to build tactical radios. Id. at
1272. During contract performance, Gould encountered
unanticipated difficulty in designing a radio that met the
contract's performance requirements. Id. As a result, it
submitted a claim to the contracting officer seeking to
recover the costs it allegedly incurred in achieving adequate
design. Id. Gould based its theory of recovery in part on the
contention that the government had violated 10 U.S.C. §
2306(h)(1), by failing to supply a "stable design" for a
multiyear procurement. According to Gould, this meant that
the contract was illegal from its inception. Gould, 935 F.2d at
1272. After the contracting officer denied the claim, Gould
appealed to the United States Claims Court. [FN7] In due
course, *1448 the court granted the government's motion to
dismiss under Rule 12(b)(4) of the court, for failure to state a
claim upon which relief could be granted. Id. at 1273. On
appeal by Gould, we vacated the dismissal and remanded the
case for further proceedings. Id. at 1276. In so doing, we
held that Gould's complaint contained sufficient facts to state
a claim upon which relief could be granted. Id. at 1275-76.
FN7. The Claims Court was renamed the Court of
Federal Claims pursuant to § 902 of the Federal Courts
l6a
Administration Act of 1992, Pub.L. No. 102- 572. 106 Stat.
4506. 4516 (1992), effective October 29, 1992.
Upon remand, the government filed a motion to dismiss
for lack of jurisdiction. The Court of Federal Claims granted
the motion. The court read Gould's complaint as based solely
on a contract with the United States but at the same time as
alleging that there was no "stable design" and that the
contract was illegal. Under these circumstances, the court
reasoned, the only possible basis for contract jurisdiction was
a contract implied in law, but such a contract was not within
the court's jurisdiction. Gould, Inc. v. United States, 29 Fed.
Cl. 758, 761 (1993). Again, Gould appealed.
On appeal, we held that the trial court had erred in
dismissing Gould's complaint for lack of jurisdiction. Gould,
Inc. v. United States, 67 F.3d 925 (Fed.Cir.1995). Noting
that Gould relied on its underlying contract with the Navy as
a basis for jurisdiction in the Court of Federal Claims, we
stated that "there is no question that Gould's complaint
alleges the existence of express contract, albeit one entered
into allegedly in violation of 10 U.S.C. § 2306(h)(1)(D)." Id.
at 929. Weconcluded: "This is sufficient ... to confer
jurisdiction in the Court of Federal Claims.” Id. We also
concluded: "[{E]ven if Gould's allegations of express contract
are insufficient, Gould's amended complaint, when viewed in
a light most favorable to Gould, alleges the existence of
implied-in-fact contract--a separate basis for jurisdiction in
the Court of Federal Claims." Id. at 930. Accordingly, we
again vacated the trial court's decision and remanded the case
for further proceedings.
Similarly, in this case, Cessna argues that the Navy's
actions in exercising the option in 1988 violated the
Antideficiency Act, thereby rendering the option exercise
inoperative and canceling the contract. However, Cessna
17a
contends, because it supplied services that the Navy accepted
and from which the Navy benefited, after all legal
requirements had been met (because the appropriations
process had been completed), it is entitled to recover under
implied-in-fact contracts for each of fiscal years 1989, 1990,
and 1991. Under these circumstances, Cessna has put forth a
cognizable claim for relief. See American Telephone and
Telegraph Co. v. United States, 124 F.3d 1471, 1479
(Fed.Cir.1997) ("An implied-in-fact contract arises when, in
the absence of express contract, the parties’ behavior leaves
no doubt that what was intended was a contractual
relationship permitted by law."). Cessna's claims in Counts I,
III, VI, and XIII were properly before the Board. [FN8]
FN8. The Navy's reliance on Hagan is misplaced. In that
case, the plaintiff, Richard Hagan, sought monetary recovery
for services provided while serving on a grievance panel.
Hagan, 671 F.2d at 1304. Hagan alleged that the government
violated the prohibition against its acceptance of voluntary
services under 31 U.S.C. § 665(b)--the predecessor to present
31 U.S.C. § 1342--which made it illegal for him to sit on the
grievance panel. Id. at 1305. The United States Court of
Claims noted that there was no express contract, and it also
rejected any theory of implied-in-fact contract because there
plainly was no consensual agreement between Hagan and the
government for Hagan's services. Id. at 1304. By contrast, in
this case, Cessna made a nonfrivolous allegation that the
government violated a statute, thus rendering the contract
void, and that the services Cessna provided during the option
years were done so under a consensual! agreement with the
government, thereby giving rise to implied- in-fact contract.
Having concluded that Cessna's claims on appeal with
respect to Counts I, II], VI, and XIII are properly before us,
we turn to the merits.
18a
Il]
By way of background, the Anti-deficiency Act finds its
origins in a statute enacted in 1870, known as the Act of July
12, 1870, ch. 251, § 7, 16 Stat. 230, 251. The statute
addressed the problem that Executive Branch officials were
obligating funds before they were appropriated by Congress,
and then making deficiency requests for appropriations
*1449 that Congress had little choice in deciding because
government agencies had basically committed the United
States to make good on its promises. See, e,g., 59 Comp.
Gen. 369, 372 (1980).
[4][5] The present version of the Act, found at 31 U.S.C.
§ 1341 (1994), [FN9] provides in pertinent part as follows:
FN9. While the central provision of the Act
is found at 31 U.S.C. § 1341, other
provisions have been passed to supplement
this provision, including 31 U.S.C. §§ 1342,
1501-1519 (1994).
§ 1341. Limitations on expending and obligating amounts
(a)(1) An officer or employee of the United States
Government or of the District of Columbia government may
not -
(A) make or authorize expenditure or obligation
exceeding amount available in appropriation or fund for the
expenditure or obligation;
19a
(B) involve either government in a contract or obligation
for the payment of money before appropriation is made
unless authorized by law.
Generally, the Act prohibits government officials and
employees from making expenditures or incurring
obligations in excess of available appropriations or in
advance of appropriations. See Blackhawk Heating &
Plumbing Co. v. United States, 224 Ct.Cl. 111, 622 F.2d 539,
542 n. 4 (1980). As far as government contracts are
concerned, the Act "bars a federal employee or agency from
entering into a contract for future payment of money in
advance of, or in excess of, existing appropriation." Hercules
Inc. v. United States, 516 U.S. 417, ----, 116 S.Ct. 981, 987,
134 L.Ed.2d 47 (1996).
By its terms, the Antideficiency Act restricts the ability of
the government to enter into multi-year contracts because
funds generally cannot be obligated beyond the current fiscal
year. This led to problems in the area of military
procurement, as described in the following passage from a
Senate Report:
Some services and supplies now being procured with
appropriations available for only 1 year require substantial
investment by the contractor for equipment having a useful
life longer than 1 year, or extensive investment in the hiring
and training of personnel. These contracts are for such
activities as base maintenance, aircraft and equipment
overhaul, vehicle repair, and pilot training. If the contractor
can obtain only a 1-year contract, his quoted price must cover
all these expenses or he runs the risk of never recovering his
unamortized investment if he loses the contract for the
ensuing year or years. In such circumstances, however, a
successful contractor is in a position to underbid competitors
in later years since the competitors must include in their bid
20a
prices the same initial investment costs that the contractor |
confronted. As a result, competition is reduced and the :
Government can be overcharged in later years.
S. Rep. No. 90-1313, at 1-2 (1968), reprinted in 1968
U.S.C.C.A.N. 2480, 2480-81.
To address these concerns, 10 U.S.C. § 2306(g) was
enacted; it permits the government to enter into specified |
types of military procurement contracts having performance
periods of up to five years, with option to extend |
performance by a period not exceeding three additional years.
[FN10] If funds are not in fact appropriated in a subsequent
*1450 fiscal year, section 2306(g)(3) provides that the
"contract shall be canceled or terminated."
FN10. Section 2306(g) provides in relevant part:
(g)(1) The head of an agency may enter into contracts for
periods of not more than five years for the following types of
services (and items of supply related to such services) for
which funds would otherwise be available for obligation only
within the fiscal year for which appropriated -
(C) specialized training necessitating high quality
instructor skills (for example, pilot and other aircrew
members; foreign language training);
whenever he finds that -
(i) there will be a continuing requirement for the services
consonant with current plans for the proposed contract
period;
2la
(ii) the furnishing of such services will require a
substantial initial investment in plant or equipment, or the
incurrence of substantial contingent liabilities for the
assembly, training, or transportation of a specialized work
force; and
(iii) the use of such a contract will promote the best
interests of the United States by encouraging effective
competition and promoting economies in operation.
(2) In entering into such contracts, the head of the agency
shall be guided by the following principles:
(B) Consideration shall be given to the desirability of
obtaining an option to renew the contract for a reasonable
period not to exceed three years, at prices not to include
charges for plant, equipment and other nonrecurring costs,
already amortized.
[6] Cessna's first contention is that the Antideficiency
Act, in combination with its implementing regulations and
certain other funding statutes, prohibits funds from being
obligated before they have been both appropriated by the
Congress and apportioned by the Executive Branch. [FN11]
Cessna argues that 31 U.S.C. § 1512, which requires that
appropriated funds be apportioned, [FN12] and 31 U.S.C. §
1517, which prohibits government officials or employees
from authorizing obligations that exceed apportionment,
22a
[FN13] prevent the obligation of funds, even if appropriated,
before they have been apportioned. As a general matter,
Cessna maintains that permitting funds to be obligated in
advance of apportionments is inconsistent with prohibiting
funds from being obligated in excess of apportionments. If
no apportionment has been made, Cessna contends, any
obligation necessarily exceeds the approved apportionment
(of zero).
FN11. Cessna further contends that the funds must be
allocated, allotted, and suballotted to the subagency level,
and that the agency must commit the funds to a contract,
before funds can be obligated to a contract.
FN12. Section 1512(a) provides:
(a)Except as provided in this subchapter, an
appropriation available for obligation for a definite period
shall be apportioned to prevent obligation or expenditure at a
rate that would indicate a necessity for a deficiency or
supplemental appropriation for the period. An appropriation
for an indefinite period and authority to make obligations by
contract before appropriations shall be apportioned to achieve
the most effective and economical use. An apportionment
may be reapportioned under this section.
FN13. Section 1517(a) provides that "[a]n officer or
employee of the United States Government ... may not make
or authorize an expenditure or obligation exceeding--(1) an
apportionment."
23a
As further support for its position, Cessna points to the
Department of Defense ("DOD") Accounting Manual, page
22-6, paragraph 4a, which states that:
An apportionment or reapportionment is a
distribution made by OMB [Office of
Management and Budget] of amounts
available for obligation in appropriation or
fund account. Except in certain instances, ...
apportionments and reapportionments by
OMB are required before funds may be
obligated.
(emphasis added). In addition, Cessna cites to the Navy
Comptroller Manual ("NCM"), paragraphs 073002(2) and
073100, [FN14] as establishing *1451 a particular funding
process wherein the first step is to apportion funds, after
which they are allocated to the Secretary of Defense, and
then allotted, suballotted, and committed to the Navy. Cessna
asserts that because the CO attempted, on October 1, 1988, to
exercise the option and to obligate funds before they had
been apportioned, she acted without authority and the option
exercise therefore was ineffective.
FN14. Paragraph 073002(2) states that:
On the basis of the enacted Department of the Navy
appropriations, the Treasury Department prepares
appropriation warrants which, after being countersigned by
the General Accounting Office, are forwarded to the
Department of the Navy as certification that the specific
amounts are available for obligation and expenditure. Fund
availability is established through compliance with
procedures for submission, review, and Office of Secretary of
Defense (OSD)/Office of Management and Budget (OMB)
approval of apportionments and/or financial plans. In
24a
conjunction with the apportionment procedure, the Office of
the Assistant Secretary of Defense (Comptroller) establishes
the authorized level of obligation and expenditure for each
appropriation, as well as any controls or limitations required
below the appropriation level, as a means of requiring
compliance with the terms of approved programs and
budgets. In passing obligational authority (as an allocation or
as a limitation within operating budget authority) to other
echelons of command, the Comptroller creates administrative
subdivisions of appropriated funds with clearly defined
responsibility for 31 U.S.Code 1517 violations, 1.e., for the
creation of any obligation or making of any expenditure in
excess of an apportionment or reapportionment, or of an
amount specified in an administrative subdivision thereof.
The process of distributing financial authority is continued
through the chain of command in the form of suballocations,
allotments, operating budgets, or operating targets.
Allotments, as well as the specified obligational authority
within operating budgets, constitute administrative
subdivisions of appropriated funds, subject to the sanctions
of the Anti-Deficiency Act (31 U.S.Code 1518 and 1519) for
the holders of allotments or operating budgets. Operating
targets (e.g., those established for individual ships by type
commanders) are administrative limitations of funds for
which the legal responsibility is retained by the grantor.
Paragraph 073100 states, in pertinent part, that "[t]he action
required to obtain release of appropriated funds by means of
the apportionment process is the initial step in the budget
execution phase."
We reject Cessna's arguments. As noted above, 31
U.S.C. § 1341(a) prohibits the government from making
expenditures or incurring obligations before funds have been
appropriated. However, as for the apportionment process,
addressed by 31 U.S.C. §§ 1511-1519, no such timing
SL gp il tate Ty ke Bae Se tt ns aE
25a
limitation exists. For example, section 1512 merely requires
appropriations to be apportioned to prevent obligations at
rates that could result in the need for a deficiency or
supplemental appropriation. Section 1513 provides a time
table for carrying out the apportionment process, but is silent
on the issue of whether the apportionment process must be
carried out before obligations can be incurred. For its part,
section 1517 prohibits government officials or employees
from authorizing obligations that exceed apportionments, but
says nothing about incurring obligations prior to carrying out
the apportionment process. In sum, the relevant statutory
provisions do not prohibit government agencies from
incurring contractual obligations before completing the
apportionment process. The remaining sections pertaining to
apportionments are similarly silent.
This same reasoning applies to paragraphs 073002(2) and
073100 of the NCM; these paragraphs say nothing about the
timing of incurring obligations versus carrying out the
apportionment process. Therefore, they are of no assistance
to Cessna. In addition, we note that paragraph 022064 of the
NCM, entitled "Availability of Funds Prior to
Apportionment," contemplates the possibility of incurring
obligations before apportionment. It states:
After the beginning of the fiscal year and
prior to the specific allocation of funds
pursuant to apportionment to the head of the
responsible office ... the head of the
responsible office is authorized by the
Comptroller of the Navy to suballocate
funds and to issue allotments under any
appropriation act of such fiscal year in such
amounts as will not exceed the amount
contained in the appropriation warrant or the
26a
request for apportionment and allocation
submitted to the Comptroller of the Navy....
Upon issuance of the approved budget
activity allocations pursuant to
apportionment, the limitations of such
allocations will apply to all suballocation
and allotment action taken prior to the
receipt of such budget activity allocations.
The provision permits allotments and suballotments to be
issued before apportionment, with restrictions as to their
amounts. It would logically follow that obligations may also
be incurred, with the same amount restrictions.
Finally, we turn to the DOD Accounting Manual,
paragraph 4a, page 22-6 ("paragraph 4a"). Initially, we
assume, without deciding here, that this provision could be
properly considered a regulation. We must still determine
whether the provision is a binding regulation, whose breach a
contractor may assert against the government. The primary
intent of a statute or regulation must be to protect or benefit a
class of persons in order for that class to be able to bring suit
against the government for violating the statute or regulation.
See generally Rough Diamond Co. v. United States, 173
Ct.Cl. 15, 351 F.2d 636, 640, 642 (1965). We have stated
that "if government officials make a contract they are not
authorized to make, in violation of a law enacted for the
contractor's protection, the contractor is not bound by
estoppel, acquiescence, or failure to protest." LaBarge
Prods., Inc. v. West, 46 F.3d 1547, 1552 (Fed.Cir.1995)
(citing Chris Berg, Inc. v. United States, 192 Ct.Cl. 176, 426
F.2d 314, 317 (1970) and Rough Diamond, 351 F.2d at
639-43); see Applied Devices Corp. v. United States, 219
Ct.Cl. 109, 591 F.2d 635, 640-41 (1979). However, if the
primary intended beneficiary of a statute or regulation is the
27a
government, then a private party cannot complain about the
government's failure to comply with that statute or *1452
regulation, even if that party derives some incidental benefit
from compliance with it. See Rough Diamond, 351 F.2d at
642; Hartford Accident & Indemnity Co. v. United States,
130 Ct.Cl. 490, 127 F.Supp. 565, 567 (1955).
In this case, paragraph 4a is primarily intended to benefit
the government, not contractors such as Cessna. The
provision is best described as internal operating provision for
the management of funds within the agency. In Blackhawk
Heating & Plumbing Co. v. United States, 224 Ct.Cl. 111,
622 F.2d 539 (1980), the Court of Claims rejected the
argument that the Antideficiency Act places restrictions not
only on the amount being appropriated, but also on the
administrative divisions made with respect to the
appropriations. Id., 622 F.2d at 552 n. 9. The court stated
that such administrative barriers "are purely of in-house
accounting nature and, as such are irrelevant to any
determination respecting the availability of appropriated
funds." Id. Paragraph 4a encourages Navy officials to follow
particular administrative procedures to ensure that obligated
funds are properly accounted for, thereby preventing officials
from obligating more funds than have been appropriated.
We also find instructive the Supreme Court's reasoning in
American Farm Lines v. Black Ball Freight Service, 397 U.S.
532, 90 S.Ct. 1288, 25 L.Ed.2d 547 (1970). In that case, the
Interstate Commerce Commission ("ICC") had promulgated
rules pertaining to processing applications for granting motor
carriers temporary operating authority. Id. at 534, 90 S.Ct. at
1290. One of those rules required applicant for such
authority to submit with its application a supporting
statement containing certain specified information. Id. In the
application of one motor carrier, the supporting statement
28a ~
accompanying the application failed to contain some of the
required information. Id. at 537, 90 S.Ct. at 1292. In due
course, despite the application's deficiencies, the ICC granted
the motor carrier temporary operating authority. American
Farm Lines, 397 U.S. at 536, 90 S.Ct. at 1291. This grant
was challenged by other motor carriers on the ground that the
ICC failed to "require strict compliance with its own rules.”
Id. at 537, 90 S.Ct. at 1291. In upholding the ICC's decision,
the Court noted that the rules in question were not intended
to confer important procedural benefits on individuals in the
face of unfettered agency discretion. Id. at 538-39, 90 S.Ct.
at 1292. Therefore, the Court stated, there was no reason to
depart from the general principle that " '[i]t is always within
the discretion of ... administrative agency to relax or modify
its procedural rules adopted for the orderly transaction of
business before it when in a given case the ends of justice
require it.'" Id. at 539, 90 S.Ct. at 1292 (quoting NLRB v.
Monsanto Chem. Co., 205 F.2d 763, 764 (8th Cir.1953)): see
also Contel Page Servs., Inc., ASBCA No. 32100, 87-1 BCA
© 19,540, at 98,736, 1986 WL 20366 (1986) (finding that a
FAR regulation requiring the CO to determine that funds
were available before exercising option related to internal
procedures and did not create any rights in the contractor, and
therefore the CO's failure to make the determination would
not render the exercise of the option ineffective). Paragraph
4a represents such internal procedural rule. Cessna may not
rely on this provision as evidence that the government
violated the Antideficiency Act in obligating funds before
they were apportioned.
[7] Thus, we hold that the CO's exercise of the option did
not violate the Antideficiency Act even though funds were
obligated before they were apportioned. [FN15]
|
'
:
29a
FN15. As noted, Cessna also contends that the option
exercise was deemed ineffective because the CO acted
without authority in deleting the proviso on the Financial
Accounting Data Sheet and then exercising the option.
Cessna's contention is without merit. The proviso provided
that execution of the data sheet was conditioned upon the
passage of the relevant appropriation act. This condition was
automatically satisfied when the President signed the
appropriation act. Therefore, in substance, the condition had
been satisfied, and it made no difference whether or not the
CO deleted the proviso before executing the data sheet.
‘.
[8] Cessna next contends that section H-6--the option
clause that required the Navy to exercise the option "not later
than 1 October 1988"--must be interpreted to have required
the Navy to exercise the option by September 30, 1988,
which the Navy failed to *1453 do. First, Cessna argues that
because funding for the original contract term expired at
midnight on September 30, 1988, the contract ceased to exist
at that point and "[o]nce the contract ceased to exist, the
option ceased to exist." Therefore, the deadline for proper
exercise of the option had to be September 30, 1988.
Second, Cessna contends that permitting the Navy to exercise
the option on October 1, 1988, would yield illegal result.
Cessna states that the Navy forced it to provide services
between midnight on September 30, 1988, when funding
ceased under the original contract, and the evening of
October 1, 1988, when the option was purportedly exercised.
Requiring Cessna to perform services in the absence of a
contractual obligation would violate the prohibition against
voluntary services set forth in 31 U.S.C. § 1342. [FN16] In
this case, Cessna contends, such services included providing
the support needed in order to fly aircraft and operate flight
30a
simulators, retaining personnel at the site, and performing
maintenance services to maintain aircraft, radar, simulators,
spare parts, etc. Cessna states that in order to sustain the
validity of the contract, the option clause should be
interpreted to have required the Navy to exercise the option
by September 30, 1988.
FN16. Section 1342 provides in pertinent part that "[ajn
officer or employee of the United States Government ... may
not accept voluntary services for [the] government or employ
personal services exceeding that authorized by law except for
emergencies involving the safety of human life or the
protection of property.” 31 U.S.C. § 1342 (1994).
We disagree. First, the option clause states that the Navy
had to exercise the option "not later than 1 October 1988."
We give effect to a plain reading of the clause, which is that
the Navy had up until and including October 1, 1988, to
exercise the option. See McAbee Constr., Inc. v. United
States, 97 F.3d 1431, 1435 (Fed.Cir.1996); Triax-Pacific v.
Stone, 958 F.2d 351, 354 (Fed.Cir.1992). Furthermore, the
option did not cease to exist just because the original term of
performance under the contract expired at midnight on
September 30, 1988. Rather, the option remained viable until
October 1, 1988, on which date it was exercised by the Navy.
The Navy's ability to exercise the option was not tied to the
original performance period of the contract.
[9] Neither was Cessna compelled to perform voluntary
services between midnight on September 30 and the evening
of October 1, 1988. The Board made a finding of fact that
"there is no evidence that the Navy proposed, directed or
encouraged Cessna to incur rental and subcontractor costs.”
Cessna II, 96-1 BCA at 139,699. Cessna has not shown that
the finding is unsupported by substantial evidence. See
Koppers Co. v. United States, 186 Ct.Cl. 142, 405 F.2d 554,
3la
557-58 (1968). Moreover, to the extent that Cessna may
have maintained personnel and equipment at the site during
the period in question, it has not shown either that the Navy
requested or compelled it to do so or that the Navy accepted
those services in violation of section 1342. Rather. Cessna
itself chose to perform these services in anticipation that the
Navy might exercise the option on October 1, 1988. Not
having accepted the services, the government is not
responsible for subsidizing them. [FN17]
FN17. Cessna further argues that even if the Navy had
until October 1, 1988, to exercise the option, Cessna did not
receive notice of the option exercise until October 3. 1988.
rendering the option exercise untimely. In that regard,
Cessna challenges the Board's finding of fact that Cessna and
the CO reached an agreement that sending the option
modification by facsimile would be acceptable, and Cessna
also challenges the Board's reliance on the Navy's statement
to Cessna personnel on September 30 to wait by their
facsimile machines on October | to receive the option
exercise. See Cessna II. 96-1 BCA at 139,698.
We disagree. A Cessna official acknowledged that the
parties had an established practice of faxing modifications.
Cessna II, 96-1 BCA at 139,688. Therefore. notice was
effective upon receipt of the facsimile at Cessna's office on
October 1, even though Cessna personnel chose not to be in
the office at that time to receive the facsimile. See id. at
139,689. Furthermore, to the extent that Cessna's arguments
are directed to witness credibility determinations of the
Board, we find no compelling reason to alter those
determinations. In that regard, we have stated that credibility
determinations are "virtually unreviewable.” Statistica. Inc.
v. Christopher, 102 F.3d 1577, 1583 (Fed.Cir. 1996).
[10] Cessna's final argument is that the Navy's exercise of
the second and third option *1454 years, on October 1, 1989,
and October 1, 1990, respectively, were ineffective. Cessna
contends that the Cancellation of Items clause of the contract
conflicts with section H-8 of the contract Schedule because
the former clause stated that the contract was canceled if the
CO did not notify the contractor prior to the beginning of the
next succeeding fiscal year that funds were available for
performance in the succeeding year, while the latter clause
permitted the CO to notify Cessna of the availability of funds
on the first day of the succeeding fiscal year. In basic terms,
Cessna asserts, the Cancellation of Items clause required the
Navy to provide it notification by September 30, 1988, while
section H-8 gave the Navy until October 1.
Furthermore, Cessna argues that the Cancellation of
Items clause was a mandatory clause required to be included
in all multi-year contracts pursuant to DAR § 1-322.6(c),
{[FN18] and that section H-8 constitutes a deviation from the
Cancellation of Items clause under DAR § 1-109.1(i). [FN19]
Under those circumstances, says Cessna, DAR § 1-109.2
required that the Navy obtain authority before implementing
the deviation, which was not done. [FN20] Cessna asserts
that the failure to obtain a deviation rendered section H-8
unenforceable and that therefore the Navy's exercise of the
second and third option years was ineffective.
FN18. Section 1-322.6(c) states that DAR §
7-1903.33(d)--the Cancellation of Items clause--must be
included in multi-year service contracts. The analogous FAR
provision is 48 C.F.R. § 17.109(a) (1996).
FN19. Section 1-109.1(i) defines deviation to include the
situation where "a contract clause is set forth in ASPR
33a
[Armed Services Procurement Regulation] for use verbatim.
[and] a contract clause covering the same subject matter
which varies from the ASPR coverage [is used]." The
analogous FAR provision is 48 C.F.R. § 1.401 (1996).
FN20. Section 1-109.2 states that deviations from the
regulations affecting only one contract or procurement may
be authorized provided that (i) the circumstances justify a
deviation, and (ii) written notice of the deviation is furnished
to particular agency officials. The analogous FAR provision
is 48 C.F.R. § 1.403 (1996).
We reject Cessna's arguments. Initially, as a contractual
matter, section H-8 took precedence over the Cancellation of
Items clause. In that regard, the Order of Precedence clause
of the contract stated as follows:
In the event of inconsistency in this contract, unless
otherwise provided herein, the inconsistency shall be
resolved by giving precedence in the following order: (a) the
Schedule (excluding the Specifications); (b) General
Provisions; (c) the other provisions of the contract whether
incorporated by reference or otherwise; and (d) the
Specifications and (e) the Contractor's proposal No.
CMP-1351.
In this case, section H-8 was found in the contract's
schedule, while the Cancellation of Items clause was a
general provision. See Cessna II, 96-1 BCA at 139,699.
However, as Cessna points out, we must further consider the
propriety of including section H-8 in the contract at all
because it deviated from the DAR-mandated Cancellation of
Items clause, and the Navy did not seek authorization for its
inclusion.
34a
Cessna's argument on this point suffers from the same
defect as its first contention on appeal--that appropriated
funds must be apportioned before they are obligated. We
conclude that the primary purpose behind the Cancellation of
Items clause is to protect the government's interest by
encouraging government officials to monitor the availability
of funds for each fiscal year and to provide notice to
contractors accordingly. Consequently, the clause may not
form the basis for a contractor's right of action. In order for
contract performance to continue each year, the Cancellation
of Items clause required that the CO notify the contractor that
funds would be available for the succeeding fiscal year, act
which inherently required the CO to first ensure that
sufficient funds are in fact available. See DAR §
7-1903.33(d).
In ITT Federal Lab., A Division of IT&T Corp., ASBCA
No. 12987, 69-2 BCA © 7849, at 36,490, 1969 WL 788
(1969), rev'd on other grounds, 197 Ct.Cl. 11, 453 F.2d 1283
(1972), the contract in dispute contained two clauses: (i) a
Limitation of Price and Contractor Obligations clause, which,
in general, required the contracting officer to notify the
contractor when funds became available for the succeeding
program year, and limited the contractor's *1455 obligations
until such notice was given; and (ii) a Cancellation of Items
clause, which was substantively the same as the Cancellation
of Items clause at issue in this case. ITT, 69-2 BCA at
36,485-86. The Board referred to these provisions
collectively as "notice of availability of funds” provisions.
Id. at 36,490. In the course of deciding whether the
government had complied with these notice provisions, the
Board determined that a primary purpose of the provisions
was "to give [the government] control over the timing of
future expenditures of appropriated funds, a provision
MT ere
35a
necessary in the light of the practices by which C ongress
exercises budgetary control." [FN21] Id.
FN21. The Board in ITT also stated that another primary
purpose was "to relieve [the contractor] of any obligation to
incur production costs for successive years until funds were
assured from which to pay [it]." ITT, 69-2 BCA at
36,485-86. However, this stated purpose related not to the
contract's Cancellation of Items clause, but rather related to
its Limitation of Price and Contractor Obligations clause,
subsection (d), which stated in pertinent part that "[t]he
Contractor is not obligated to incur costs for the performance
required for any Program Year after the first unless and until
he has been notified in writing by the Contracting Officer of
an increase in availability of funds.” ASPR §
1-322.4(a)(1966).
The Navy apparently deviated from the Cancellation of
Items clause in drafting section H-8 without first obtaining
the proper authority to do so. However, because the
Cancellation of Items clause is primarily for the benefit of the
government, Cessna may not rely on the deviation in arguing
that the Navy's exercise of the options for fiscal years 1990
and 1991 was ineffective. Thus, Cessna is bound by section
H-8, and there is no dispute that the Navy fully complied
with the section.
CONCLUSION
For the foregoing reasons, the decision of the Board is
affirmed.
COSTS
Each party shall bear its own costs.
AFFIRMED.
DC2 6152431.1 05/27/98 06:49 PM
1b
Appeal of Cessna Aircraft Company
Under Contract No. N00019-83-C-0090
March 12, 1993
APPEARANCE(S) FOR THE APPELLANT
Herbert L. Fenster, Esq.
Michael T. Janik, Esq.
Jeffrey P. Hildebrant, Esq.
McKenna & Cuneo
Washington, D.C.
APPEARANCE(S) FOR THE GOVERNMENT
Arthur H. Hildebrandt, Esq.
Navy Chief Trial Attorney
Douglas P. Hinds, Esq.
Associate Chief Trial Attorney
Evadne Sanichas, Esq.
Senior Trial Attorney
Ronald L. Fouse, Esq.
Trial Attorney
—
OPINION BY ADMINISTRATIVE JUDGE TING
ON CROSS-MOTIONS FOR SUMMARY JUDGMENT
Cessna Aircraft Company (Cessna) entered into a multiyear contract for
training Undergraduate Naval Flight Officers (UNFO) with the Navy.
Following the 5-program years of the contract, the Navy exercised an
option to continue the contract for another three years. Cessna alleges
that the exercise of the option was ineffective and submitted a $25
million claim for performance of contract services during the option
period. This appeal was docketed upon failure of the contracting officer
to issue a decision on Cessna's certified claim.
Cessna has filed a motion for partial summary judgment of 11 of 15
counts in its complaint. In Counts I, II, II], !V and VII, Cessna invokes
violation of various funding laws and regulations as grounds for invali-
dating the option exercise. In Counts VIII, IX, X, XI, XII and XIll,
Cessna invokes violation of funding laws and regulations as alternate
grounds for invalidating the Navy's notices of funds availability required
to be issued to continue the Second and Third Option Years should the
Board uphold the option exercise.
The Navy has cross moved for summary judgment on the same 11
counts.
2b
The Navy considers funding contracts as internal ‘housekeeping’ matters,
and challenges Cessna's legal ‘standing’ to bring such matters before the
Board. We view the Navy's standing argument as going to our
jurisdiction to hear and decide issues which relate to the validity of the
Navy's option exercise and notices of funds availability. This
jurisdictional challenge will be more thoroughly addressed at the outset
of our decision.
The Board entertained a full day of oral argument on 10 December 1992.
GENERAL UNDISPUTED FACTS
1. On 10 May 1983, the Naval Air Systems Command (‘NAVAIR, ' 'the
Navy’ or 'the Government’) awarded Contract No. N00019-83-C-0090
(the ‘0090 contract’) to Cessna Aircraft Company (Cessna) (R4, tab 1).
The contract required Cessna to provide training services for
undergraduate naval flight officers at the U.S. Naval Air Station,
Pensacola, Florida, during five program years, commencing | August
1984, and ending 30 September 1988 (R4, tab | at 5-1 to 5-9). Each
program year ended on the last day of the Government's fiscal year (FY),
i.e., 30 September.
2. The 0090 contract required Cessna to provide, among other equipment
and services, 'services to assist in Radar and Navigation training of
Undergraduate Naval Flight Officers. These services shall consist of an
annual rate of 17,000 airborne training service hours . . . on Contractor-
furnished radar equipped aircraft of common configuration. The radar
equipped aircraft shall meet the requirements of the ‘Functional
Description, Undergraduate Naval Flight Officer (UNFO) Training
System,’ Attachment (1)... .’ (R4, tab 1 at 2-1) Paragraph 1.1, ‘Scope,’ of
Attachment (1) provides that 'The system consists of airborne training
services utilizing commercial aircraft, associated radar, an Air-to-Air
Intercept Radar Training Device, a Ground Radar Mapping Training
Device, all maintenance (aircraft and trainers), full logistics support and
required instructor pilot services.’ (R4, tab 1 at 146) ~
3. The contract 'SCHEDULE' contained at Section H-5 the 'Option To
Extend Services' clause prescribed by DAR 7-1903.22 (29 APR 1977).
This clause provided:
The Government may require the Contractor to continue to perform any
or all items of service under this contract within the limits stated in the
Schedule. The Contracting Officer may exercise this option, at any time
within the period specified in the Schedule, by giving written notice to
the Contractor. The rates set forth in the Schedule shall apply to any '
extension made pursuant to this option provision unless provision for
appropriate price adjustment has been made elsewhere in this contract.
3b
(R4, tab | at 7-13)
4. Section H-6, 'Exercise Of Option,’ of the contract Schedule provided:
Pursuant to the ‘Option to Extend Services- Clause, the option for the
three option years will be exercised, if at all, in writing by a unilateral
modification to this contract issued by the Contracting Officer, Naval Air
Systems Command, not later than 1 October 1988.
(R4, tab | at 7-13)
5. The First Option Year (FY 1989) ran from | October 1988 to 30
September 1989. The Second Option Year (FY 1990) ran from 1 October
1989 to 30 September 1990. The Third Option Year (FY 1991) ran from
1 October 1990 to 30 September 1991. (R4, tab | at 5-9 to 5-11)
6. Section H-9 of the contract Schedule is entitled ‘Cancellation Ceiling.’
It established cancellation ceilings for program years two through five of
the five-year base period. It also established cancellation ceilings for
years two and three of the three-year option period. Under Section H-9, If
the Government exercised the three-year option, $29 million would be
the cancellation ceiling 'if second and following option years are
cancelled,’ and $26.5 million would be the cancellation ceiling ‘if third
option year is cancelled.' (R4, tab | at 7-17)
7. The notice requirement contained in Section H-8 of the contract,
entitled 'Multiyear procurement’ provides in part:
If the three year option is exercised, the date within which the
contracting officer . . . will notify the Contractor of the availability of
funds sufficient for performance of the requirements for the
Second Option Year (Fiscal Year 1990) is 1 October 1989.
Third Option Year (Fiscal Year 1991) is 1 October 1990.
(R4, tab | at 7-16)
8. The General Provisions of the contract incorporated by reference, the
‘Disputes’ clause (1980 JUN)\(DAR 7-103. 12(a)), and the ‘Availability Of
Funds’ clause (1962 SEP) (DAR 7-104.9] (a)), among others. The
‘Availability of Funds' clause provides:
Funds are not presently available for this procurement. The
Government's obligation hereunder is contingent upon the availability of
appropriated funds from which payment for the contract purposes can be
made. No legal liability on the part of the Government for payment of
any money shall arise unless and until funds are made available to the
Contracting Officer for this procurement and notice of such availability,
to be confirmed in writing by the Contracting Officer, is given to the
Contractor.
9. A ‘Financial Accounting Data Sheet’ -- DD Form No. 1140 -- is used
4b
by the Navy to commit funds to a contract. On 30 September 1988, the
expiration date of the 0090 contract, a NAVAIR budget analyst executed
a Financial Data Sheet, post-dating it to | October 1988 with the proviso
that ‘EXECUTION OF THIS DOCUMENT IS CONTINGENT ON
CONGRESSIONAL PASSAGE OF THE FY 89 APPROPRIATION
ACT OR OTHER AUTHORITY.’ (R4, tab 7) The amount of funds cited
on the form was $22,576,253. The fund amount cited did not cover the
$29 million potential cancellation liability for the second and following
option years under Section H-9 of the contract Schedule.
10. In 1988, | October was a Saturday. On that day, the contracting
officer was told by one of her supervisors that the President had signed
the Department of Defense Appropriation Act, 1989 (Pub. L. 100-463,
102 Stat. 2270 (1988)).
11. Sometime during 1-October 1988, the contracting officer covered
over the budget analyst's proviso with white correction fluid and redrew
the whited-out vertical lines that had been on the Financial Accounting
Data Sheet.
12. Also on 1 October 1988, the contracting officer executed
Modification No. P00027 for the purpose of exercising the three-year
option pursuant to Section H-6 of the 0090 contract. Among the
documents attached to the modification was the whited-out Financial
Accounting Data Sheet. The documents showed that funds ($22,576,253)
were provided for the First Option Year (FY 1989) (R4, tab 2a).
13. At 6:22 p.m., 1 October 1988, the contracting officer by means of
facsimile transmitted to the attention of Cessna’s Vice President for
Finance, at Cessna's facility in Wichita, Kansas, documents described as
‘the modification exercising the three-year multiyear option and
providing funding for FY 89° (R4, tab 9).
14. October 1, 1988, being a Saturday, was not a normal business day for
Cessna (complaint par. 28). Cessna personnel responsible for the 0090
contract found at a telecopy machine at Cessna’s Wichita facility a
facsimile copy of Modification No. P00027, including a copy of the
Financial Accounting Data Sheet, shortly after the facility opened for
business on 3 October 1988.
15. By letter dated 7 October 1988, Cessna advised the contracting
officer that it did not consider that the Navy had validly exercised the
option (R4, tab 11).
16. The contracting officer responded to Cessna's 7 October 1988 letter
by letter dated 7 December 1988. The letter stated in substance that the
option had been effectively exercised and that the 0090 contract remained
in effect (R4, tab 12).
FY 1990 Funding
17. On 29 September 1989, the President signed into law Continuing
5b
Appropriations, 1990, Pub. L. 101-100, 103 Stat. 638 (FY 1990
Continuing Resolution). This law appropriated funds to DoD for FY 1990
under a continuing resolution. Section 102 of the FY 1990 Continuing
Resolution provided that ‘appropriations and funds made available and
authority granted pursuant to this joint resolution shall be available
until..... (c) October 25, 1989... ." Pub. L. 101-100, 103 Stat. 640 (1989)
18. On 1 October 1989, the contracting officer telecopied to Cessna
Modification No. P00034. The modification stated that it provided funds
for the ‘Second Year (FY 1990) of the three year multiyear option
exercised by contract modification P00027 . . . .' Modification No.
P00034 was issued to notify Cessna of the availability of funds for
performance for the Second Option Year. The modification showed
$23,282,519 to have been obligated for contract line items for the Second
Option Year (FY 1990) (R4, tab 2h). It did not fund the Third Option -
Year (FY 1991), nor the $26.5 million cancellation charges for the Third
Option Year.
19. The Department of Defense Appropriations Act, 1990, was enacted
into law on 21 November 1989. Pub. L. 101-165, 103 Stat. 1112 (1989).
FY 1991 Funding
20. On 1 October 1990, the President signed into law Continuing
Appropriations, 1991, Pub. L. 101-403, 104 Stat. 867 (FY 199]
Continuing Resolution). Section 108 of this FY 199] Continuing
Resolution provided that ‘appropriations and funds made available and
authority granted pursuant to title I of this joint resolution shall be
available until . . . (c) October 5, 1990... .' Pub. L. 101-403, 104 Stat.
869.
21. On 1 October 1990, the contracting officer telecopied to Cessna
Modification No. P00038. The modification was ‘to fund the Third Year
(FY 1991) of the three year multiyear option exercised by contract
modification P00027.' Modification No. P00038 was issued to notify
Cessna of the availability of funds for performance for the Third Option
Year. The modification showed $23,866,204 to have been obligated for
contract line items for the Third Option Year (FY 1991). (R4, tab 21)
22. On 9 October 1990, the President signed into law Further Continuing
Appropriations, 1991, Pub. L. 101-412, 104 Stat. 894. Section 108 of this
second FY 1991 Continuing Resolution provided that ‘appropriations and
funds made available and authority granted pursuant to this joint
resolution shall be available until. . .. (c) October 19, 1990... .' Pub. L.
101-412, 104 Stat. 896.
23. The Department of Defense Appropriations Act, 1991, was enacted
into law on 5 November 1990. Pub. L. 101-511, 104 Stat. 1856.
Procedural Posture of the Appeal
24. Cessna initiated an action in the United States District Court for the
6b
District of Kansas on 10 March 1989. The action sought declaratory
judgment under Section 10 of the Administrative Procedure Act, 5 U.S.C.
sec. 702. to the effect that the Navy's exercise of the option was in
violation of the Antideficiency Act, 31 U.S.C. secs. 1341-1342, the
Apportionment statutes, 31 U.S.C. secs. 1511-1519, and Section 8042 of
the DoD Appropriation Act, 1989. By Memorandum And Order of 13
August 1990, the District Court found that Cessna's claim was actually
one for money damages in an amount in excess of $10,000. The Court
denied the Government's motion to dismiss and ordered that the action be
transferred to the United States Claims Court. See Cessna Aircraft Co. v.
United States, 744 F. Supp. 260 (D. Kansas 1990).
25. Cessna submitted a certified claim in the amount of $29,054,615 to
the contracting officer on 8 April 1991. By letter dated 24 June 1991,
Cessna’s Chairman and Chief Executive Officer revised the claim to
$25.706,080, to [correct] an inadvertent error in the bid and development
expense rates used in the previously submitted price proposal . . . [and to
update) the pricing from the earlier submission.’ Cessna’s claim was
recertified as modified.
26. The contracting officer did not issue a decision within 60 days as
required by Section 6(c)(1) of the Contract Disputes Act, 41 U.S.C. sec.
605(c\ 1). Cessna appealed on the basis that its claim was deemed denied
pursuant to 41 U.S.C. sec. 605(c\5) by notice dated 10 July 1991. The
Board docketed the appeal on 11 July 1991. On 21 August 1991, the
Government moved to dismiss the appeal on the ground that no
contracting officer's decision had been issued. The Board denied the
Government's motion on 30 September 1991. Cessna Aircraft Co.,
ASBCA No. 43196, 92-1 BCA par. 24,425.
27. While the Government's motion to dismiss was pending, Cessna filed
on 5 September 1991, APPELLANT'S MOTION FOR PARTIAL
SUMMARY JUDGMENT and MEMORANDUM IN SUPPORT OF
APPELLANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT
and 43 accompanying exhibits (henceforth to be referred to as MOTION
PAPERS 1). Over Cessna's objections, the Board granted two
Government requests for a time extension to file its opposition to
Cessna's motion. "RESPONDENT'S MEMORANDUM IN OPPOSITION
TO APPELLANT'S MOTION FOR PARTIAL SUMMARY
JUDGMENT AND IN SUPPORT OF RESPONDENT'S
CROSS-MOTION FOR PARTIAL SUMMARY JUDGMENT’
(henceforth MOTION PAPERS 2) dated 8 January 1992, was received at
the Board on 14 January 1992.
28. Thereafter, Cessna filed a reply to the Government's opposition and
cross- motion on 13 March 1992 (CESSNA'S REPLY TO THE NAVY'S
OPPOSITION TO CESSNA'S MOTION FOR SUMMARY
c™
te i et Re beth i
aoe ee
7b
JUDGMENT, AND OPPOSITION TO THE NAVY'S CROSS-MOTION
FOR SUMMARY JUDGMENT with 78 exhibits) (henceforth MOTION
PAPERS 3). The Government's reply to Cessna's opposition to the
Government's Cross-Motion was filed on 11 May 1992
(RESPONDENT'S REPLY TO APPELLANT'S OPPOSITION TO THE
NAVY'S CROSS-MOTION FOR SUMMARY JUDGMENT)
(henceforth MOTION PAPERS 4).
29. The Government submitted its Rule 4 file by letter dated 10 January
1992. Its answer to Cessna's complaint was filed by letter dated 17
January 1992 (R4, tab 19). By letter dated 26 May 1992, the Board
granted Cessna leave to file a response to four defenses said to have been
raised for the first time in the Government's MOTION PAPERS 4.
Cessna's response, APPELLANT'S REPLY TO NAVY'S NEW
DEFENSES IN OPPOSITION TO CESSNA'S MOTION FOR PARTIAL
SUMMARY JUDGMENT (henceforth MOTION PAPERS 5), was
received by the Board on 17 July 1992.
30. Concomitantly with the filing of the aforementioned summary
judgment papers, the Government on 14 January 1992 filed its "MOTION
TO DISMISS FOR LACK OF JURISDICTION ALL COUNTS OF
APPELLANT'S COMPLAINT WHICH ALLEGE VIOLATIONS OF
CRIMINAL LAW.’ This was followed by Cessna's opposition
(CESSNA'S OPPOSITION TO NAVY'S MOTION TO DISMISS) filed
on 13 March 1992 and the Government's reply (REPLY TO
APPELLANT'S OPPOSITION TO RESPONDENT'S MOTION TO
DISMISS) filed on 12 May 1992. The Board issued its decision denying
the Navy's Motion to Dismiss on 20 October 1992. Cessna Aircraft Co..
ASBCA No. 43196, 93-_ BCA par. _.
31. By letter dated 11 January 1993, a month after oral argument, Cessna
forwarded ‘APPELLANT'S MOTION FOR LEAVE TO FILE AN
AMENDED COMPLAINT AND TO AMEND APPELLANT'S
MOTION FOR PARTIAL SUMMARY JUDGMENT and
‘MEMORANDUM IN FURTHER SUPPORT OF APPELLANT'S
MOTION FOR PARTIAL SUMMARY JUDGMENT (henceforth
MOTION PAPERS 6). The motion sought to (1) amend Count I of its
complaint and its partial summary judgment motion to ‘include the
allegation that the Navy violated the Antideficiency Act by obligating FY
1989 Navy Operations & Maintenance funds before such funds were
allocated to the Navy by the Secretary of Defense’ ( emphasis added) and
(2) ‘amend its Motion for Partial Summary Judgment to include a request
for an order granting summary judgment on Count XIII.' (MOTION
PAPERS 6 at 1-2) The Board granted Cessna’s motion and instructed the
Navy to respond by 26 February 1993.
Statutory Bases of Cessna's Motion for Partial Summary Judgment
8b
32. Cessna's complaint contained 15 (1 to XV) counts. Eight of the 15
counts alleged violations of 31 U.S.C. sec. 1341 (Antideficiency Act) or
31 U.S.C. sec. 1517 (apportionment statute):
Count No. Statute Allegedly Violated
I 31 U.S.C. sec. 1517(aX1)
ll 31 U.S.C. sec. 1341(aX 1B)
ill 31 U.S.C. sec. 1517(a\(2)
IV 31 U.S.C. sec. 1517(a\{2)
IX 31 U.S.C. sec. 1341(aX 1 A) & (B)
xX 31 U.S.C. sec. 1517(a\{2)
XII 31 U.S.C. sec. 1341(aX 1 A) & (B)
XI 31 U.S.C. sec. 1517(aX{2)
33. 31 U.S.C. sec. 1341 (Limitations on expending and obligating
amounts) provides, in part:
(a1) An officer or employee of the United States Government . . . may
not-
(A) make or authorize an expenditure or obligation EXCEEDING an
amount available in an appropriation or fund for the expenditure or
obligation; or
(B) involve . . . [the United States] government in a contract or
obligation for the payment of money before an appropriation is made
unless authorized by law.
(Emphasis added)
31 U.S.C. sec. 1517 (Prohibited obligations and expenditures) provides
in part:
(a) An officer or employee of the United States Government . . . may
not make or authorize an expenditure or obligation EXCEEDING-
(1) an apportionment; or
(2) the amount permitted by regulations prescribed under section
1514(a) of this title.
(Emphasis added)
The Bases of Cessna’s Motion for Partial Summary Judgment
34. In Count I (Obligation Before Apportionment and Allocation},
Cessna alleges that the contracting officer violated 31 U.S.C. sec.
1517(aX1), DoD Directive 7200.1, and Navy Comptroller Manual
(NCM) pars. 073000 - 073002, because she issued Modification No.
P00027 obligating FY 1989 funds for the first year of the three-year
9b
option period prior to apportionment and allocation of FY 1989 funds
(MOTION PAPERS | at 24-28).
35. In Count I] (Involvement in a Contract Before Appropriation],
Cessna alleges that the contracting officer violated 31 U.S.C. sec.
1341(aX1B) in exercising the option (by Modification No. P00027)
because she ‘involved the government in a contract for payment of money
in FY 1990 and 1991 [Second and Third Option Years] before
appropriations for those years had been made’ (MOTION PAPERS at
29-35).
36. In Count III [Falsified Funding Documents], Cessna alleges that the
contracting officer in ‘whiting-out’ the budget analyst's proviso on the
Financial Accounting Data Sheet was ‘deliberately falsifying an official
government document.’ In its Motion for Partial Summary Judgment,
Cessna suggested that the contracting officer might have violated 18
U.S.C. secs. 1001 and 1008 and ‘an array of other felony statutes
including 18 U.S.C. secs. 287, 471, 472, 495, 461, 648, 653, 666, 912.
1002, 1003, 1016, 1017, 1028, and 1031." (MOTION PAPERS, n.12 at
38) /1 Leaving aside the ‘array’ of criminal statutes Cessna alleges that the
contracting officer might have violated, the crux of Count III is that ‘The
option exercise was ineffective’ because ‘The altered Financial
Accounting Data Sheet was void and did not validly commit funds in
support of the purported option exercise’.
37. In Count IV [Cancellation Charges Exceeded Available Funds in FY
1989), Cessna alleges that the option was ineffectively exercised because
the modification (Modification No. P00027) exercising the option
violated the law (31 U.S.C. sec. 1517, 31 U.S.C. sec. 1514(a) and
implementing regulatio by committing funds for the contingent liability
for cancellation charges ($29 million) in excess of funds ($22,576,253)
authorized for FY 1989. (MOTION PAPERS | at 50-52)
38. In Count VII [Navy Failed to Notify Congress], Cessna alleges that
Section 8042 of the FY 1989 DoD Appropriation Act ‘required the Navy
to submit notice to Congress before extending or renewing for a term of
18 months or more any contract involving aircraft obtained through
‘lease, charter, or similar agreement.” Cessna alleges that the purported
option exercise (Modification No. P00027) was ‘unlawful, invalid, and of
no force or effect’ because the Navy ‘did not notify Congress of its
intention to extend for three years Contract No. 0090.’ (MOTION
PAPERS | at 41-50)
39. in Count VIII [Funding Notice for Second Option Year Was Late],
Cessna alleges that the Second Option Year of the 0090 contract was
automatically cancelled pursuant to DAR sec. 7-1903.33(d) because the
contracting officer did not issue a notice of funds availability for FY
1990 prior to the beginning of the fiscal year (MOTION PAPERS | at
10b
54-56).
40. In Count IX [Funding Notice for Second Option Year Was an
Obligation in Advance of Appropriated Funds), Cessna alleges that in
issuing the funding notice (Modification No. P00034) for the Second
Option Year, the contracting officer obligated funds ($23,282,519) in
advance of appropri- ations in violation of 31 U.S.C. sec. 1341(a)(1 (A)
& (B) because the Continuing Resolution (Pub. L. 101-100) for FY 1990
expressly stated that funds were available only until 25 October 1989
(finding 17; MOTION PAPERS | at 53-54).
41. In Count X [Cancellation Charges Exceeded Available Funds in FY
1990), Cessna alleges that the contracting officer's notice of funding
availability (Modification No. P00034 for $23,282,519) violated 31
U.S.C. sec. 1517 and implementing regulations because ‘it exposed the
government to a contingent liability of up to $26.5 million of cancellation
charges in the event the third option year was cancelled’ (MOTION
PAPERS | at 52).
42. In Count XI [Funding Notice for Third Option Year Was Late],
Cessna alleges that the Third Option Year of the 0090 contract was
automatically cancelled pursuant to DAR sec. 7-1903.33(d) because the
contracting officer did not issue a notice of funds availability for FY
1991 prior to the beginning of the fiscal year (MOTION PAPERS | at
54-56).
43. In Count XII [Funding Notice for Third Option Year Was an
Obligation in Advance of Appropriated Funds], Cessna alleges that in
issuing the funding notice (Modification No. P00038) for the Third
Option Year, the contracting officer obligated funds ($23,866,204) in
advance of appropria- tions in violation of 31 U.S.C. sec. 1341(a)(1 (A)
& (B) because the first Continuing Resolution for FY 1991 stated that
funds were available only until 5 October 1990, and the second
Continuing Resolution for FY 1991 stated that funds were available only
until 19 October 1990 (findings 20,22; MOTION PAPERS | at 53- 54).
The Navy's Cross Motion for Summary Judgment
44. The Navy opposed Cessna's motion and crossed for summary
judgment on al! 10 counts (1, II, 11], 1V, VII, VILL, EX, X, XI, XID) that
Cessna initially moved for summary judgment. In addition, the Navy
moved for summary judgment on Count XIII (MOTION PAPERS 2).
Cessna later amended its motion for partial summary judgment and
cross-moved for summary judgment of count XIII (MOTION PAPERS
6).
45. Count XIII involves the same issue as Count I. In Count XIII
[Funding Notice for Third Option Year Was in Advance of Apportioment
[sic] and Subdivision of Funds), Cessna alleges that the contracting
11b
officer's funding notice (Modification No. P00038) was issued ‘before FY
1991 appropriations were apportioned by OMB, allocated by DOD,
and/or suballocated by the Navy, in violation of 31 U.S.C. sec.
1511-1519 and regulations thereunder,’ and was therefore unlawful,
invalid and of no force or effect.
DECISION
Jurisdiction
In opposition to Cessna's Motion for Partial Summary Judgment, the
Navy contends that Cessna lacked standing to challenge matters relating
to the Navy's alleged 2 yon-compliance with what essentially are ‘funds
control statute[s].'- We view the Navy's standing challenge as going to
our jurisdiction to hear and decide matters relating to funding of
contracts. Cessna derives its right to bring its appeal before us by virtue
of its status as a Government contractor under the Contract Disputes Act.
41 U.S.C. secs. 601-613. That Act defines the term ‘contractor’ as ‘a party
to a Government contract other than the Government,’ and it applies ‘to
any express or Implied contract . . . entered into by an executive agency
for-...; (2) the procurement of services.’ 4] U.S.C. sec. 601(4) and sec.
602(a)(2).
There is no question of Cessna's status as a Government contractor. Nor
is there any question that the 0090 contract is a contract for the
procurement of services within the scope of 41 U.S.C. sec. 602(a)(2).
Furthermore, In accordance with the requirement of 41 U.S.C. sec.
605(c)(1), Cessna submitted a properly certified claim to the contracting
officer. The commencement of the appeal was authorized upon the
failure of the contracting officer to issue a decision in accordance with 4]
U.S.C. sec. 605(c)(5). Cessna Aircraft Co., ASBCA No. 43196, 92-1]
BCA par. 24,425.
As reflected in the contracting officer's decision. belatedly issued on 15
November 1991 (R4, tab 19), the parties’ dispute which gave rise to
Cessna's claim centered on whether the Navy effectively exercised the
three-year option and issued the funds availability notices for the Second
and Third Option Years. The right to exercise the option and the require-
ment to issue the funding notices stemmed from the terms of the 0090
contract. Under the CDA, we have jurisdiction ‘to decide any appeal from
a decision of a contracting officer (1) relative to a contract made by its
agency’ (emphasis added). 41 U.S.C. sec. 607(d). We conclude that this
appeal related to the 0090 contract made by the Navy. Hence, Cessna's
standing to bring this appeal and our jurisdiction to decide it are
grounded on the provisions of the CDA. Cessna Aircraft Co., ASBCA
No. 43196, 93-_ BCA par ___ ; See Ecee Inc. v. Federal Energy
12b
Regulatory Com'n, 645 F.2d at 339, 349-50 (Sth Cir. 1981).
Counts I & XIll
Additional Findings of Fact
Apportionment Statutes And Regulations Relied Upon By Cessna
46. 31 U.S.C. sec. 1512 (Apportionment and reserves) provides in part,
the following:
(a) Except as provided in this subchapter, an appropriation available for
obligation for a definite period shall be apportioned to prevent obligation
or expenditure at a rate that would indicate a necessity for a deficiency or
supplemental appropriation for the period.
47.31 U.S.C. sec. 1514 (Administrative division of apportionments)
provides in part, the following:
(a) . . . the head of each executive agency . . . shall prescribe by
regulation a system of administrative control not inconsistent with
accounting procedures prescribed under law. The system shall be
designed to-
(1) restrict obligations or expenditures from each appropriation io the
amount of apportionments or reapportionments of the appropriation; and
(2) enable the official or the head of the executive agency to fix
responsibility for an obligation or expenditure exceeding an
apportionment or reapportionment.
48. Pursuant to 31 U.S.C. sec. 1514(a), DoD issued DoD Directive No.
7200.1, 7 May 1984. This Directive applies to:
the Office of the Secretary of Defense, the Military Departments, the
Organization of the Joint Chiefs of Staff, the Defense Agencies and the
Uniformed Services University of the Health Sciences (hereafter referred
to collectively as ‘DoD Components’) and includes all civil and military
functions under the direct supervision of a DoD Component.
(MOTION PAPERS | at tab 38) For apportioned funds, a violation of Do
D Directive
7200.1 is a violation of 31 U.S.C. sec. 3/517. Since DoD Directive 7200.
| was
issued pursuant to 31 U.S.C. 1517, it has the force and effect of law. (See
DoD
Accounting Manual, October 1983, MOTION PAPERS 3, tab 46)
49. Paragraph G, 'APPORTIONMENTS,’' of DoD Directive 7200.1,
provides:
1. When appropriations or other funds are required to be apportioned to
a DoD Component under law, a request for the apportionment or
reapportionment shall be prepared and submitted through the ASD(C) to
the Director of OMB. The request shall be in such form and at such time
as the ASD(C) may prescribe to conform with the requirements of the
13b
Director of OMB (see reference (e)).
2. Obligations during any apportionment period must not EXCEED the
amount of the apportionment available for that period or of any
administrative subdivision of the apportionment.
(Emphasis added) (MOTION PAPERS 1, tab 38 at 5-2)
50. Paragraph K, ‘OBLIGATIONS AND EXPENDITURE,’ of DoD
Directive 7200.1, provides in part the following: _
2. Except as provided by subsection K.1.. above, no DoD official shall
authorize (such as, commit) or create any obligation, or make any
expenditure under any appropriation or fund EXCEEDING the
following:
a. The available amount of such appropriation or fund.
b. The available amount of an apportionment or reapportionment or
administrative subdivision thereof.
(Emphasis added) (MOTION PAPERS 1. tab 38 at 5-5 to 5-6)
51. The DoD Accounting Manual defines the terms ‘apportionment’ as
follows:
4. Apportionments and Reapportionments
a. An apportionment or reapportionment is a distribution made by OMB
of amounts available for obligation in an appropriation or fund account.
Except in certain instances, as specified in OMB Circular No. A-34...
apportionments and reapportionments by OMB are required before funds
may be obligated. The distribution of apportionments is part of an overall
financial plan for the year that is based on a forecast of obligations to be
incurred within an appropriation. (OMB's apportioned amount is in
response to a DoD request made on DD Form 1105. ‘Apportionment and
Reapportionment Schedule,’ . . .) Apportionments divide amounts
available for obligation by specific time periods (usually quarters),
activities, projects, objects, or by combinations of these categories.
b. The completed DD Form 1105 showing OMB's apportioned amounts
is normally the source document used to record apportionments and
reapportionments.
(MOTION PAPERS 3, tab 46 at 22-6)
52. Both parties have relied on provisions contained in the Navy
Comptroller Manual! (NCM). A brief discussion of where the NCM
stands in the hierarchy of funding laws and regulations is necessary. 3]
U.S.C. sec. 1514(a) requires executive agencies to prescribe a system of
administrative controls. DoD Directive 7200.1 was issued pursuant to 3]
U.S.C. sec. 1514 and approved by the Director of OMB. The DoD
Directive, in turn, required each DoD Component, including the Navy, ‘to
14b
establish and maintain adequate systems of accounting for positive
control of appropriations and other funds made available.’ The NCM is a
‘regulatory issuance’ of the Navy implementing the DoD Directive. The
DoD Directive is reproduced in its entirety, without change, as Appendix
A, Volume 2, of the NCM. (Supp. R4, tab 30 at encl. 5; see also oral arg.,
tr. 132-34; Navy letter and attachments of 22 January 1993 and MOTION
PAPERS 6). Cessna referred to Paragraph 023004 of the Navy
Comptroller Manual (NCM) which provides in part:
023004 APPORTIONMENTS AND ALLOCATIONS
1. APPORTIONMENT
a. Definition. An apportionment is a determination
by the Director of the Office of Management and Budget as to the
amount of obligations which may be incurred under an appropriation,
fund, or contract authorization during a specific period.
*=* *
c. Apportionments Are Binding. Except under certain circumstances as
prescribed by law, no agency shall authorize expenditures or involve the
Government in any contract or other obligations or commitment for the
future payment of money IN EXCESS of the amount currently available
therefor under the approved or revised apportionment.
(Emphasis added) (MOTION PAPERS 3, tab 48 at 3-2 to 3-3)
53. Referring to NCM par. 073002, Cessna asserts that ‘The NCM
establishes a sequential funding process whereby funds are first
apportioned, then allocated to the Secretary of Defense, and then
suballocated or allotted through the chain of command in the Navy.’
NCM par. 073002(2) provides:
073002 PROCEDURES FOR ESTABLISHING AVAILABILITY
*_* *
2. PURSUANT TO APPROPRIATION ENACTMENTS. On the basis
of the enacted Department of the Navy appropriations, the Treasury
Department prepares appropriation warrants which, after being
countersigned by the General Accounting Office, are forwarded to the
Department of the Navy as certification that the specified amounts are
available for obligation and expenditure. Fund availability is established
Lssemiitenieanniiniiaailaagiiiac ciel
be re,
ee ee ae ah
ncaa oped ainda:
Wadi adi A OAC A
15b
through compliance with procedures for submission, review, and Office
of Secretary of Defense (OSD)/Office of Management and Budget(OMB)
approval of apportionments and/or financial plans. In conjunction with
the apportionment procedure, the Office of the Assistant Secretary of
Defense (Comptroller) establishes the authorized level of obligation and
expenditure for each appropriation, as well as any controls or limitations
required below the appropriation level as a means of requiring
compliance with the terms of approved programs and budgets. In passing
obligational authority (as an allocation or as a limitation within operating
budget authority) to other echelons of command, the Comptroller creates
adminis- trative subdivisions of appropriated funds with clearly defined
responsibility for 31 U.S. Code 1517 violations i.e., for the creation of
any obligations or making of any expenditure IN EXCESS of an
apportionment or reapportionment, or of an amount specified in an
administrative subdivision thereof. The process of distributing financial
authority is continued through the chain of command in the form of
suballocations, allotments, operating budgets, or Operating targets.
Allotments, as well as the specified obligational authority within
operating budgets, constitute administrative subdivisions of appropriated
funds, subject to the sanctions of the Anti-Deficiency Act (31 U.S. Code
1518 and 1519) for the holders of allotments or operating budgets.
Operating targets (e.g., those established for individual ships by type
commanders) are administrative limitations of funds for which the legal
responsibility is retained by the grantor. _
(Emphasis added) (MOTION PAPERS 3, tab 39 at 3-3 to 3-4)
54. According to Cessna, the President has delegated the apportionment
authority to OMB by Executive Orders. /4 Cessna Says that ‘Section
44.10 of OMB Circular A-34 provides that only OMB has the authority
to apportion funds.’ OMB Circular A-34 reiterates the Statutory rule that
an obligation of funds in excess of an apportionment violates the
Antideficiency Act. (MOTION PAPERS | at 25 and tab 37) The Navy
has not disputed these assertions; we find them to be undisputed facts for
purposes of the motion before us.
55. Navy Operation and Maintenance (O & M) funds for FY 1989 were
appropriated by the Department of Defense Appropriations Act, 1989,
enacted into law on |! October 1988. Pub. L. 100-463, 102 Stat. 2270
(1988). Funds appropriated by this Act were not apportioned to DoD
until 20 October 1988. On that date, the Deputy Associate Director for
Nationa! Security, OMB, signed the DD Form 1105 -- "Apportionment
And Reapportionment Schedule ' (MOTION PAPERS at tab 17) We find
the foregoing facts to be undisputed.
Apportionment Statutes And Regulations Relied Upon by the Navy
16b
56. 31 U.S.C. sec. 1513 (Official controlling apportionments) provides
in part, as follows:
(b\1) The President shall apportion in writing an appropriation
available to an executive agency . . . that is required to be apportioned
under section 1512 of this title. The head of each executive agency to
which the appropriation is available shall submit to the President
information required for the apportionment in the form and the way and
at the time specified by the President. The information shall be submitted
not later than the later of the following:
(A) 40 days before the beginning of the fiscal year for which the
appropriation is available; or
(B) 15 DAYS AFTER THE DATE OF ENACTMENT OF THE LAW
BY WHICH THE APPROPRIATION IS MADE AVAILABLE.
(2) The President shall notify the head of the executive agency of the
action taken in apportioning the appropriation under paragraph (1) of this
subsection not later than the later of the following:
(A) 20 days before the beginning of the fiscal year for which the
appropriation is available; or
(B) 30 DAYS AFTER THE DATE OF ENACTMENT OF THE LAW
BY WHICH THE APPROPRIATION IS MADE AVAILABLE,
(c) By the first day of each fiscal year, the head of each executive
department of the United States Government shall apportion among the
major Organizational units of the department the maximum amount to be
expended by each unit during the fiscal year out of each contingent fund
appropriated for the entire year for the department. Each amount may be
changed during the fiscal year only by written direction of the head of the
department. The direction shall state the reasons for the change.
(Emphasis added) In this case the FY 1989 DoD Appropriations Act was
enacted
into law on | October 1988. Thus, 31 U.S.C. sec. 1513(b)(1)(B) and sec.
1513
(b)(2)(B) would apply. We find that OMB had until 31 October 1988, 30
days
after | October 1988, to apportion the funds appropriated by the FY 1989
DoD
Appropriations Act.
57. The Navy brings to our attention a paragraph in the NCM which
deals specifically with ‘AVAILABILITY OF FUNDS PRIOR TO
APPORTIONMENT:
022064 AVAILABILITY OF FUNDS PRIOR TO APPORTIONMENT
—
oe ee ee a ee oe
17b
AFTER THE BEGINNING OF THE FISCAL YEAR AND PRIOR TO
THE SPECIFIC ALLOCATION OF
FUNDS PURSUANT TO APPORTIONMENT to the head of the
responsible office, bureau,
command, and Headquarters U.S. Marine Corps by the Comptroller of
the Navy, the
head of the responsible office is authorized by the Comptroller of the
Navy to
suballocate funds and to issue allotments under any appropriation act of
such
fiscal year IN SUCH AMOUNTS AS WILL NOT EXCEED THE
AMOUNT CONTAINED IN the
appropriation warrant or the request for APPORTIONMENT AND
ALLOCATION SUBMITTED
TO THE COMPTROLLER OF THE NAVY. When an appropriation
warrant has not been
issued, the head of the responsible office is authorized by the Comptroller
of
the Navy to take the same actions under ANTICIPATED appropriations,
for which
he is responsible, WITHIN THE AUTHORIZATION CONTAINED IN
ANY CONTINUING
RESOLUTION ADOPTED BY THE CONGRESS PENDING THE
PASSAGE OF THE APPROPRIATION ACT
under which the appropriation warrant will be issued. Upon issuance of
the
approved budget activity allocations pursuant to apportionment, THE
LIMITATIONS
OF SUCH ALLOCATIONS WILL APPLY TO ALL
SUBALLOCATION AND ALLOTMENT ACTION TAKEN
PRIOR TO THE RECEIPT OF SUCH BUDGET ACTIVITY
ALLOCATIONS.
(Emphasis added) (MOTION PAPERS 2 at tab 2)
58. In opposition to Cessna's motion for summary judgment, and in
support of its cross-motion for summary judgment, the Navy furnished a
declaration from the head of the Resource Allocation Branch, Office of
the Comptroller, Department of the Navy (NAVCOMPT). This
individual had been employed by the Government in various Capacities
for over 32 years. He had been ‘the primary action officer for the
apportionment policy, procedures, and operations for the entire
Department of Defense (Army, Navy, Air Force, and Defense Agency
appropriations. )’ His declaration stated, inter alia:
18b
4. The Department of the Navy (DON) is required to submit
apportionment requests to the Office of the Secretary of Defense (OSD)
within five days of PASSAGE OF AN APPROPRIATIONS ACT (DOD
Budget Guidance Manual 7110-1-M, Part IV, Page 412-5 (attachment
1)). There are no restrictions placed upon DON from issuing quarterly
allocations prior to the beginning of the Fiscal Year so long as the
allocation documents contain an express prohibition against incurring
obligations prior to passage of an Appropriations Act or a Continuing
Resolution, whichever becomes applicable. Any such allocations are
subject to all provisions of such Act or Resolution.
5. Upon passage of an Appropriation Act, funds are immediately
available for obligation (NAVCOMPT Manual, paragraph 022064)...
The requirement for apportionment does not prohibit the obligation of
funds prior to the apportionment action. Apportionment is intended to
regulate the rate of obligations so as to prevent deficiency situations and
the need for supplemental appropriations, and therefore only becomes a
limitation upon approval. (In the absence of apportionment, the agency
receiving the appropriation is not subject to apportionment.) 31 U.S.C.,
section 1513(b), requires that apportionment requests be submitted to
OMB by OSD within 15 days after enactment of an appropriation. OMB
has 30 days after enactment to issue the apportionment. Thus until
apportionment is approved by OMB, no apportionment limitation exists.
Until apportionment by OMB, the amounts requested by DON in its
submittal to OSD are used as an internal limitation by NAVCOMPT. In
its apportionment request, DON includes anticipated obligations during
the initial days of the fiscal year, as well as amounts anticipated to be
required for the remainder of the first quarter of the fiscal year.
6. Once funds are apportioned by OMB, whether under an
Appropriations Act or a Continuing Resolution, the amounts apportioned,
lump sum or time-phased (as in O&MN), are adhered to on all allocation
documents issued by NAVCOMPT and the Chief of Naval Operations
(CNO).
7 . OSD does NOT allocate appropriated funds to the DON. Such funds
are available to the DON for obligation upon passage of enabling
appropriation authority. OSD, like OMB, may choose to limit or regulate
the rate of obligation and/or prohibit certain programs from being
executed for various administrative/legal reasons. Any such limitation(s)
are set forth in memoranda received from OSD which, in the case of
O&MN, are entitled: ‘Obligational Authority.’ As with the Apportionment
(DD-1105), upon receipt of higher level controls (OMB/OSD), these
controls are adhered to. Prior to receipt, there is no restriction on the
incurrence of obligations.
8. Continuing Resolutions appropriate an amount equivalent to the
pritigtsteeahne ik
19b
annual appropriation without regard to the time period actually covered
by the resolution. Thus, a continuing resolution does not limit the
government to entering into contracts valid only for the duration of the
resolution, but rather merely prohibits further new obligations after its
expiration. -
(Emphasis in original) (MOTION PAPERS 3, tab 2)
DECISION
Count I
On | October 1988, the President signed into law the DoD
Appropriations Act for FY 1989. On that day, the contracting officer for
the 0090 contract issued Modification No. P00027 exercising the 3-year
option under the contract. It is undisputed that the funds appropriated by
the Act were not apportioned by OMB until 20 October 1988 (finding
55).
Cessna moves for summary judgment on Count I, contending that the
contracting officer's exercise of the option was ineffective. Cessna alleges
that the contracting officer violated 31 U.S.C. sec. 151 7(aX(1) (an
apportionment statute) (see finding 33), DoD Directive 7200.1
(implementing directive issued pursuant to 31 U.S.C. sec. 1514(a)) (see
findings 47-49) and various paragraphs of the Navy Comptroller Manual
(see findings 52-53) because she issued Modification No. P00027
obligating FY 1989 funds for the first year of the 3- year option period
prior to apportionment and allocation of FY 1989 funds (MOTION
PAPERS | at 24-28).
The Navy opposed Cessna's motion and cro