Appendix — Mt. Hope Asphalt Corp. v. Zagata
Supreme Court brief1998
Ask Donna
What actually matters in this document.
Text
ee ee et POPE res Pie 8 OPE RTT reopen EE IT STENT: vies!
la
APPENDIX A — DECISION AND JUDGMENT OF THE
SUPREME COURT OF NEW YORK APPELLATE
DIVISION, SECOND JUDICIAL DEPARTMENT
FILED MARCH 16, 1998
SUPREME COURT OF THE STATE OF NEW YORK
APPELLATE DIVISION :
SECOND JUDICIAL DEPARTMENT
AD2d
Argued — October 27, 1997
ae: eee
MYRIAM J. ALTMAN, J.P.
WILLIAM D. FRIEDMANN
GABRIEL M. KRAUSMAN
LEO F. McGINITY, JJ.
96-08219
In the Matter of Mt. Hope Asphalt Corp., a/k/a Mount Hope
Asphalt Corp., and Barbara Petrosky, as Executrix of the Estate
of Frank Petrosky, petitioners, v. Michael Zagata, etc., et al.,
respondents.
DECISION & JUDGMENT
Proceeding pursuant to CPLR article 78, inter alia, to
review so much of a determination of the Commissioner of the
Department of Environmental Conservation as, inter alia, after
2a
Appendix A
a hearing, determined that the petitioners violated
Environmental Conservation Law 27-0707, 6 NYCRR 360-1.7,
and Navigation Law 173 and 175, and imposed penalties and
fines against them, denied the application of the petitioner Mt.
Hope Asphalt Corp., a/k/a Mount Hope Asphalt Corp., for a
certificate to operate an afterburner, and revoked the permit of
the petitioner Mt. Hope Asphalt Corp., a/k/a Mount Hope
Asphalt Corp., to construct and test a rehydration chamber.
ADJUDGED that the determination is confirmed insofar
as reviewed and the proceeding is dismissed, on the merits,
with costs.
In order to annul an administrative determination made
after a hearing, a court must conclude that the record lacks
substantial evidence to support the determination (see, Matter
of Pell v. Board of Educ., 34 NY2d 222, 231). The petitioners’
contention that the determination of the Commissioner of the
Department of Environmental Conservation (hereinafter the
DEC) was not supported by substantial evidence is without
merit. The testimony of the witnesses for the DEC established
the facts necessary to sustain the charges that the petitioners
had violated Special Conditions 4.13 and 5.13 of the permit,
had discharged petroleum at the Mt. Hope facility in violation
of the Navigation Law, and are unfit and unsuitable to hold
DEC permits. The penalties immposed were not so
disproportionate to the offenses committed as to be shocking
to one’s sense of fairness (Matter of Pell v Board of Educ.,
supra).
March 16, 1998
3a
Appendix A
We have reviewed the petitioners’ remaining contentions
and find them to be without merit.
ALTMAN, J.P.,. FRIEDMANN, KRAUSMAN and McGINITY,
JJ., concur.
4a
Appendix A
96-082119
DECISION & ORDER ON MOTION
In the Matter of Mt. Hope Asphalt Corp., a/k/a Mount Hope
Asphalt Corp., and Barbara Petrosky, as Executrix of the Estate
of Frank Petrosky, petitioners, v Michael Zagata, etc., et al.,
respondents.
Motion by the petitioners in a proceeding pursuant to CPLR
article 78 which was transferred to this court by order of the
Supreme Court, Nassau County, entered June 6, 1996, to
substitute as a petitioner Barbara Petrosky, as the executrix of
the estate of the deceased petitioner Frank Petrosky.
Upon the papers filed in support of the motion and the
papers filed in relation thereto, it is
ORDERED that the motion is granted, and the caption of
the above-entitled case is amended accordingly.
ALTMAN, J.P., FRIEDMANN, KRAUSMAN and McGINITY,
JJ., concur.
ENTER:
Martin H. Brownstein
Clerk
March 16, 1998
Sa
APPENDIX B — ORDER OF TRANSFER,
ENTERED JUNE 6, 1996
SHORT FORM ORDER
SUPREME COURT — STATE OF NEW YORK
Present: HON. THOMAS A. ADAMS
JUSTICE
TRIAL/IAS, PART 20
NASSAU COUNTY
INDEX NO. 32468/95
MT. HOPE ASPHALT CORP., et al
Plaintiff(s),
- against -
MICHAEL ZAGATA, et al
Defendant(s).
This is an Article 78 proceeding wherein petitioner sets
forth a question specified in CPLR 7903(4) i.e., whether the
determination which was made as a result of a hearing was
supported by substantial evidence (see decision and order dated
September 7, 1995, annexed as Exhibit A to the order to show
cause). Respondent has moved to dismiss the first, second,
fourth and sixth causes of action by raising “objections in point
of law” pursuant to CPLR 7804(f).
6a
Appendix B
Upon consideration of the record submitted, this Court finds
that the determination of the objections raised by the respondent
will not terminate this proceeding. [CPLR 7804(g).]
Accordingly, pursuant to the provisions set forth in CPLR
7804(g), this matter should be transferred to the Appellate
Division for disposition of the substantial evidence issue and
all other issues raised in this proceeding.
In view of the foregoing, respondent is directed to serve
and file an answer within twenty (20) days from the date of
this order and upon filing such answer, the matter will be
remitted to the Appellate Division, Second Department.
DATED MAY 31, 1996 s/ [illegible]
J.8.C.
7a
APPENDIX C — DECISION AND ORDER OF THE NEW-
YORK STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION DATED SEPTEMBER 7, 1995
STATE OF NEW YORK:
DEPARTMENT OF ENVIRONMENTAL
CONSERVATION
Consolidated Hearing In the Matter of Alleged Violation
of Articles 19 and 27 of the New York Environmental
Conservation Law and Parts 201, and 360 of Title 6 of the
Official Compilation of Codes, Rules and Regulations of the
State of New York, and Proceedings to Revoke All Permits
Now Held by and Deny All Applications for Permits Filed by,
DEC. Nos. 1-5445-93-09,
1-4722-01052/00003-0,
1-4722-01052/00004-0,
AND
BENEFICIAL USE DETERMINATION
MT. HOPE ASPHALT CORP., a/k/a MOUNT HOPE
ASPHALT CORP.
and
FRANK PETROSKY, Individually,, and In His Capacity
as an Officer of MT. HOPE ASPHALT CORP., a/k/a
MOUNT HOPE ASPHALT CORP.,
Respondents.
8a
Appendix C
DECISION AND ORDER
WHEREAS:
1. Staff of the Region 1. Office of the New York State
Department of Environmental conservation (“Staff”) duly
served a Notice of Hearing and Complaintupon Respondents,
thereby initiating an administrative enforcement hearing.
Separately, Staff issued a notice of intent to revoke a permit
held by Respondent Mt. Hope Asphalt Corp. (“Mt. Hope”),
revoke a Beneficial Use Determination issued to Mt. Hope and
deny its application for permit renewal.
2. Pursuant to a ruling by Administrative Law Judge
(“ALJ”) Kevin J. Casutto, issued on November 10, 1994, the
two actions were consolidated. An evidentiary hearing on the
consolidated action was commenced on January 3, 1995, at the
Department’s Region 1 Office, Stony Brook, New York, and
continued on January 4th, Sth, 9th, 10th, 11th, 12th, 17th, 18th,
19th, 20th and January 25, 1995.
3. Staff appeared and was represented at the hearing by
Assistant Regional Attorneys Louise Aja and Udo Drescher,
Region I Office, Stony Brook, New York. Respondent Mt. Hope
Asphalt Corp. appeared and was represented by Farrell, Fritz,
Caemmerer, Cleary, Barnosky & Armentano, P.C., EAB Plaza,
West Tower (14th Floor), Uniondale, New York 11556-0120,
Sanford Strenger, Esq., of counsel, and Respondent Frank
Petrosky appeared and was represented by Zimmer & Mazzei,
400 Townline Road, Hauppauge, New York 11788, Timothy,
P. Mazzei, Esq., of counsel.
9a
Appendix C
4. Upon review of the record and the Consolidated Hearing
Report (the “Report”) of ALJ Casutto (copy attached), I hereby
adopt its Findings, Conclusions and Recommendations as my
own.
5. I concur with the ALJ’s recommendation concerning
relief for the reasons stated in the Report. I find Respondent
Mt. Hope unsuitable and unfit to engage in the activities for
which it is currently permitted.
6. Concerning the Beneficial Use Determination which
Respondent Mt. Hope received, 6 NYCRR §5202.2(d) required
Respondents to comply with ai! conditions of Mt. Hope’s Permit
to Construct EP2. Therefore, compliance with the Permit to
Construct was a condition upon which the Beneficial Use
Determination was made. Respondents’ receipt, storage and
processing of petroleum-contaminated soil from sites in New
Jersey was not authorized by the Permit to Construct EP2, and
consequently, was not within the scope of authority of the
Beneficial Use Determination made by Department Staff.
7. Iconcur in the ALJ’s ruling which limited Staff's cause
of action in complaint paragraph B7 to address only those
reporting violations alleged to have occurred after May 8, 1992.
NOW THEREFORE, having considered this matter, it is
ORDERED that:
I. Respondents Mt. Hope and Petrosky have violated
Special Conditions (4)(B) and (5)(B) of Respondent Mt. Hope’s
Permit to Construct EP2; ECL §27-0707 and 6 NYCRR 360-
1.7; and Navigation Law §1.73 and Navigation Law §175.
10a
Appendix C
II. Respondent Mt. Hope and Respondent Frank Petrosky,
individually and in his capacity as an officer of Respondent
Mt. Hope Asphalt Corp., with joint and several (iability, shall
pay a penalty in the amount of Sixty Three 7 housand, Four
Hundred ($63,400.00) Dollars, and an additional penalty of Ten
Thousand ($10,000.00) Dollars is hereby assessed against
Respondent Mt. Hope, due and payable within thirty (30) days
of service of a conformed copy of this Order upon Respondents.
II]. The charges against Respondents Mt. Hope and
Petrosky, of violating Special Permit Condition (5)(e) (Permit
to Construct EP2), ECL §17-0501, 6 NYCRR 613.8 are hereby
dismissed.
IV. Respondents shall immediately cease importing any
additional materials to the site and perform remedial
investigation, remediation and closure of the Site in accordance
with the recommendations of, and subject to the approval of,
Department Staff.
V. Respondent Mt. Hope’s Permit to Construct EP4 (#1-
4722-01052/00004-0) is hereby revoked and its permit
application for all; Certificate to Operate EP2 (#1-4722-01052/
00003-0) is hereby denied. In effect, revocation and denial of
Respondent Mt. Hope’s permit and permit application render
the Beneficial Use Determination void, because the BUD was
conditioned upon Respondents’ operation of the Calverton
facility.
VI. All communications between Respondents and
Department Staff concerning this order shall. be made to: Ray
Cowen, Region I Regional. Director, New York State
Department of Environmental Conservation, Loop Road,
Building 40, Stony Brook, New York, 117902356.
lla
Appendix C
VII. The provisions, terms and conditions of the Order
shall bind Respondents, their agents, servants, employees,
successors and assigns and all persons, firms and corporations
acting for or on behalf of Respondents.
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION
MICHAEL ZAGATA, COMMISSIONER
s/ Michael Zagata
Dated: Albany, New York
September 7, 1995
To: Sanford Strenger, Esq.
Farrell, Fritz, Caemmerer,
Cleary, Barnosky & Armentano
EAB Plaza
Uniondale, NY 11556-0120
Timothy P. Mazzei, Esq.
Zimmer & Mazzei
400 Townline Road
Hauppauge, NY 11788
Louise M. Aja, Esq.
Assistant Regional Attorney
Region 1, NYSDEC
Building 40, SUNY Campus
Stony Brook, NY 11790-2356
12a
Appendix C
Mt. Hope Asphalt Corp.
(a/k/a Mount Hope Asphalt Corp.)
395 Nugent Drive
Calverton, NY 11933
Frank Petrosky
President
Mt. Hope Asphalt Corp.
(a/k/a Mount Hope Asphalt Corp.)
395 Nugent Drive
Calverton, NY 11933
Frank Petrosky
c/o Mt. Hope Asphalt Corp.
395 Nugent Drive
Calverton, NY 11933
Frank Petrosky
21 Andiron Lane
Brookhaven, NY 11917
“az. ee ae ee ee ee
13a
Appendix C
STATE OF NEW YORK
DEPARTMENT OF ENVIRONMENTAL
CONSERVATION
50 Wolf Road
Albany, New York 12233-1550
Consolidated Hearing In the Matter
o Of «
Alleged Violation of Articles 17, 19 and 27 of the New
York State Environmental Conservation Law (ECL) , and Parts
203, 360 and 613 of Title 6 of the Official Compilation of Codes,
Rules and Regulations of the State of New York, and the
Navigation Law of the State of New York, by
MT. HOPE ASPHALT CORP.,
a/k/a MOUNT HOPE ASPHALT CORP.,
AND
FRANK PETROSKY
INDIVIDSUALLY AND IN HIS CAPACITY
AS AN OFFICER OF
MT. HOPE ASPHALT CORP., a/k/a
MOUNT HOPE ASPHALT CORP.
RESPONDENTS.
DEC NOS. 1-4722-01052/00003-01
1-4722-01052/00004-0
AND
BENEFICIAL USE DETERMINATION
14a
Appendix C
HEARING REPORT
= by mn
s/ Kevin J. Casutto
Kevin J. Casutto
Administraive Law Judge
SUMMARY
This hearing report addresses a consolidated action
concerning alleged violations of water, air, and solid waste law
and regulation, and Navigation Law and regulation by
Respondents, and Staff’s intent to revoke and deny
Respondents’ permits and permit applications based upon the
alleged violations and Respondents, other relevant history.
Respondents opposed Staff's notice of intent to revoke their
permit to construct an air pollution source, revoke a Beneficial
Use Determination authorizing the use of petroleum-
contaminated soil for the production of hot asphalt, and deny
their permit application for a Certificate to Operate an air
pollution source. Respondents presented a direct case
attempting to show that the use of petroleum-contaminated soil
in the production of hot asphalt was a new process, and a
“learning experience” for both Respondents and Staff. Further,
Respondents assert they did not commit any regulatory or
statutory violation in operation of their facility but instead,
continually sought to cooperate with Staff.
The report concludes that Respondents Mt. Hope and
Petrosky, violated Special Conditions (4)(B) and (5)(B) of
Respondent Mt. Hope’s Permit to Construct an air pollution
” 15a
Appendix C
source referred to as EP2; ECL §27-0707 and 6 NYCRR 360-
1.7; and Navigation Law §§173 and 175. The report further
concludes that the charges against Respondents Mt. Hope and
Petrosky, of violating Special Permit Condition (5)(E) (Permit
to Construct EP2), ECL §17-0501, 6 NYCRR 613.8 should be
dismissed.
Although staff sought a penalty of $1.4 million, the report
recommends a monetary penalty in the amount of $63,400.00
be assessed against Respondent Mt. Hope and Respondent Frank
Petrosky, individually and in his capacity as an officer of
Respondent Mt. Hope Asphalt Corp., jointly and severally, and
that an additional penalty of $10,000.00 be assessed against
Respondent Mt. Hope.
Further, the report recommends finding that Respondent
Mt. Hope is unsuitable and unfit to hold Departmental permits.
Respondent Mt. Hope’s Permit to Construct EP4 (#1-4722-
01052/000040) should be revoked and and its permit application
for a Certificate to Operate EP2 (#1-4722-01052/00003-0)
should be denied. Respondents should be ordered to cease
importing any additional materials to the site, and ordered to
perform remedial investigation, remediation and closure at the
site pursuant to NL §173, ECL Article 27 and 6 NYCRR Part
360.
PROCEEDINGS
Pursuant to Articles 70 and 71 of the Environmental
Conservation Law of the State of New York (“ECL”) and Part
622 of Title 6 of the Official Compilation of Code, Rules and
Regulations of the State of New York (“6 NYCRR”) , a
consolidated administrative enforcement/permit revocation/
l6a
Appendix C
permit denial hearing was held before Administrative Law
Judge (“ALJ”) Kevin J. Casutto, New York State Department
of Environmental Conservation, Office of Hearings. The
hearing was held on January 3, 1995, and was continued on
eleven additional dates, concluding on January 25, 1995, in
the New York State Department of Environmental Conservation
(“DEC” or the “Department”) Region 1 Regional Office, Loop
Road, Building 40, Stony Brook, New York 11790-2356.
Following the hearing, the ALJ set a schedule for filing
initial and reply memoranda. The complete hearing transcript
was received by the Office of Hearings on February 15, 1995.
The parties, initial memoranda were received on or before
March 13, 1995, and the hearing record was closed on March
27, 1995 with receipt of the parties’ reply memoranda.
Introduction
Respondent Mt. Hope Asphalt Corp., a/k/a Mount Hope
Asphalt Corp. (“Mt. Hope”) has operated a facility at Nugent
Drive, Calverton, New York using virgin materials to produce
hot asphalt, for approximately 22 years. In or about July, 1990,
Thomas Accardi of Disposal Technologies, Inc. (“Accardi” and
“Disposal Technologies,” respectively) approached the New
York State Department of Environmental Conservation (“the
Department” and “Staff”, respectively) Region I Staff with his
concept of using No. 2 fuel oil-contaminated soil in the asphalt
manufacturing process in place of virgin material, and staff
approved the concept, under certain conditions. By late August,
1990, Mr. Accardi approached the Department’s Division of
Air with a proposed application to implement his concept. This
application was on behalf of Respondent Mt. Hope and sought
authority to modify Mt. Hope’s certificate to operate its existing
17a
Appendix C
asphalt plant at Calverton, Long Island (the “facility”) to
authorize the processing of contaminated soil through the
asphalt plant’s dryer for incorporation into asphalt products.
In or about Spring, 1991, Respoadent Mt. Hope, with the
assistance of Disposal Technologies, Inc. and Thomas Accardi,
sought authority to upgrade its facility for use of petroleum-
contaminated soil in hot asphalt production. The Mt. Hope
application was the first in the State of New York proposing to
process petroleum-contaminated soil in the production of
asphalt. On or about August 9, 1991, Respondent Mt. Hope,
obtained a beneficial use determination (“BUD”) and a Permit
to Construct an afterburner referred to as Emissions Point 2
(application #1-472201052/00003-0; Permit to Construct
Emission Point No. 00002, an afterburner [“EP2”]; “permit to
construct afterburner” or “permit to construct EP2”). Mt. Hope
constructed the afterburner, and in or about October, 1992, Mt.
Hope filed an application for issuance of a Certificate to Operate
a Source of Air Contamination, for EP2.
On January 14, 1993 Respondent Mt. Hope entered into a
Consent order with the Department to resolve certain violations
and to assure continued authority to operate EP2 (Consent Order
#1-507492-06). The Consent Order required, among other
things, construction of a rehydration chamber, Emissions Point
4. Thus, on or about February 16, 1993, Mt. Hope submitted an
application for a Permit to Construct/ Certificate to operate a
Rehydration Chamber, EP4. On July 22, 1993, the Department
issued the Permit to Construct and Test a Rehydration Chamber
(Permit to Construct #1-4722-01052/00004-0 (Emission Point
No.00004, rehydration chamber (“EP4”)]; permit issued July
19, 1993, indicating an expiration date of July 18, 1994).
18a
Appendix C
Earlier, on May 28, 1991 Respondent Mt. Hope entered
into a Consent Order with the Department to resolve violation
of ECL Article 19 and 6 NYCRR Part 201 related to the facility
(Consent Order RI-4570-91-05). On July 18, 1991, Respondent
Mt. Hope entered into a Consent Order with the Department to
resolve violations of ECL Articles 15 and 25, and 6 NYCRR
Part 661, related to another Mt. Hope facility located in
Flushing, Queens, New York. (Consent Order #R2-3559-91-
03).
On September 15, 1993 Staff issued a combined Notice of
Intent to Revoke Mt. Hope’s Permit to Construct the EP4
rehydration chamber, revocation of Mt. Hope’s BUD and denial
of Mt. Hope’s application for a Certificate to Operate EP2 (a
modified facility including the afterburner and rehydration
chamber, which was intended to process petroleum-
contaminated soil in the production of asphalt (“the combined
notice” and hereinafter referred to as the “Permit” aspect of
the consolidated action)).
By letter dated September 28, 1993, pursuant to 6 NYCRR
Parts 621 and 624, Respondents sought a hearing to review
Staff's combined Notice of Intent to Revoke the EP4 permit to
construct (621.14(d)), Denial of Mt. Hope’s application for a
permit to operate EP2 (6 NYCRR 621.7(f)) and BUD
Revocation.
Since autumn, 1993, Respondents have ceased all
production of asphalt at the facility.
* * *
19a
Appendix C
Separately, by Notice of Hearing and Verified Complaint
dated September 17, 1993, duly served upon Respondents, Staff
initiated an enforcement action against Mt. Hope and three
corporate officers, Jay Boyle, Paul Abrams and Frank Petrosky
(hereinafter referred to as the “enforcement” aspect of the
action). The corporate officers were charged in their corporate
and individual capacities. During pre-hearing motion practice
and discovery, Staff withdrew its Complaint against two of the
three corporate officers, Jay Boyle and Paul Adams. Respondent
Frank Petrosky, the third individual respondent, is President of
corporate Respondent Mt. Hope.
On November 10, 1994, upon joint motion of Staff and
Respondents, the two actions were consolidated into a single
action, to proceed under 6 NYCRR 622. The joint motion for
consolidation was granted because the allegations in Staff's
enforcement action are also asserted as a basis for revocation/
denial in Staff's permit action.
Six substantive pre-hearing rulings were issued. On June
22, 1994, a “Ruling on Prehearing Motions” [First Ruling] on
July 12, 1994 a “Ruling on Motion for Reconsideration”
[Second Ruling]; on September 29, 1994 a “Ruling on Motion
for Disqualification and Motion to Dismiss Affirmative
Defenses” [Third Ruling]; on November 1, 1994 a “Ruling on
Motion to Amend Complaint” [Fourth Ruling]; on December
7, 1994 a “Ruling on Motion to Quash” [Fifth Ruling]; and on
December 27, 1994 a “Ruling on Asserted Privileges [Sixth
Ruling].
Staff sought leave to appeal to the Commissioner, from
the second Ruling insofar as it precluded Staff from pursuing a
portion of its cause of action for the time period prior to May
20a
Appendix C
9, 1992. By determination of the Assistant Commissioner for
Hearings, dated August 5, 1994, Staff’s application for
interlocutory appeal was denied. However, Staff was advised
that the issue could be preserved for review at the conclusion
of the proceeding in Staffs closing brief, and Staff has done
so.
Staff’ initial Complaint was ainended twice prior to
hearing. Pursuant to the First Ruling, on July 8, 1994 Staff filed
its first Amended Complaint revising its theory of liability on
one cause of action. In response, Respondents filed an amended
answer dated September 1, 1994. Subsequently, by Order dated
November 3, 1994, the ALJ granted Staff's motion seeking to
file its Second Amended Complaint, adding a new cause of
action. The new cause of action alleges Respondents buried
petroleum-contaminated soil in the parking lot of their asphal'
processing plant located at 395 Nugent Drive, Calverton, New
York, in violation of Navigation Law (“NL”) Article 12, ECL
Article 19 and 6 NYCRR Parts 360 and 613. Staff does not
seek additional monetary penalties for this new cause of action,
but seeks an order of remediation. The new allegations are also
discussed below in the context of the record of compliance/
permit aspect of this consolidated action.
Following issuance of the initial Complaint, in autumn,
1993, the Office of the Suffolk County District Attorney
obtained an indictment against Respondents Mt. Hope and
Petrosky, based at least in part upon activities that are at issue
in this consolidated administrative action. That matter was
pending, pretrial, at the time this administrative consolidated
hearing was held.
istration So teaes
2la
Appendix C
An evidentiary hearing on the consolidated action was
commenced on January 3, 1995, and continued on January 4th,
Sth, 9th, 10th, 11th, 12th, 17th, 18th, 19th, 20th and January
25, 1995. Staff appeared and was represented at the hearing by
Assistant Regional Attorney Louise M. Aja and Assistant
Regional Attorney Udo Drescher, NYSDEC Region | Office,
Loop Road, Building 40, Stony Brook, New York 11790-235¢.
To support its case, Staff presented fourteen witnesses: Kathryn
Murphy, Environmental Program Specialist I., Robert Becherer,
Regional Hazardous Substances Engineer, Sid Caramintzos,
Environmental Engineer 1, Karen Baker (née Munze) , Bureau
of Water Resources, Robert A. Greene, Regional Permit
Administrator, Karen Gomez, Environmental Engineer 2 and
Ray E. Cowen III, Regional Director. From the Office of the
Suffolk County District Attorney, Steven Drielak, Detective
Lieutenant, Commanding Officer, Environmental Crime Unit;
from the Suffolk County Department of Health, George
Mathew, Chemist, Francis J. Amendola, Forensic Scientist,
Madelaine Feindt, Public Health Sanitarian and Scott Mirabella,
Chemist. Also called to testify by Staff were Kathleen Morrison
a former employee of Respondent Mt. Hope, and Richard
Parish, President, Impact Environmental, Inc.
Initially, Respondents Mt. Hope and Petrosky appeared and
were represented by McMillan, Rather, Bennett & Rigano, P.C..,
Barry S. Cohen, of counsel. On or about February 24, 1994,
the law firm of Farrell, Fritz, Caemmerer, Cleary, Barnosky &
Armentano, P.C., EAB Plaza, West Tower (14th Floor),
Uniondale, New York 1 1556-0120, Sanford Strenger, Esq., of
counsel, assumed representation of Respondents. On or about
November 10, 1994, the law firm of Zimmer & Mazzei, 400
Townline Road, Hauppauge, New York 11788, Timothy P.
Mazzei, Esq., assumed representation of Respondent Frank
Petrosky.
22a
Appendix C
Respondent Mt. Hope presented testimony from Jay Boyle,
an employee of Respondent Mt. Hope and Olin C. Braids, Ph.D.
Respondent Petrosky presented no witnesses.
Staffs Position
I. The Notice of Hearing and Complaint
Pursuant to a ruling by the Administrative Law Judge
(“ALJ”), Staff filed the (First) Amended Complaint on July 8,
1994'. The First Amended Complaint was different from the
initial Complaint insofar as it included, in Complaint §C(6)(b),
the allegation that because Respondent had violated a Beneficial
Use Determination, the subsequent receipt and/or processing
and/or disposal of any material without a permit under 6
NYCRR Part 360 was a violation of Part 360.
On September 30, 1994 the Department filed a motion to
amend the First Amended Complaint by adding a new section
“D”. This new section alleges that Respondents violated ECL
Article 17 and 6 NYCRR Part 613 because they caused a
discharge of petroleum through the burial and stockpiling of
petroleum-contaminated soil at the facility on or before
September 16, 1993, and further that Respondents failed to
notify the Department of that discharge. In addition, Staff
alleges that Respondents violated 6 NYCRR Parts 360-
1.7(a)(1)(i) and 360-1.5(a), because the burial and stockpiling
of petroleum-contaminated soil constitutes disposal of solid
waste. Staff asserts that such activities require a solid waste
management facility (“SWMF’”) permit issued pursuant to ECL
1. “Ruling on Prehearing Motions” (First Ruling) from June 22,
1994, at p.7 42.
23a
Appendix C
Article 27 and 6 NYCRR Part 360, which Respondents did not
possess. While the actual penalty amount requested remained
the same as in the First Amended Complaint, new section “D”
of Staff’s Second Amended Complaint seeks remedial
investigation and remediation, i.e., clean-up of all petroleum-
contaminated soil at the facility.
Staff's motion to add the additional cause of action was
granted, and the Second Amended Complaint (hereinafter, the
Complaint”) was deemed served on November 3, 19947.
Staff alleges violations by Respondents in its Second
Amended Complaint, which are summarized as follows:
Complaint Section B;
Violation of ECL Article 19, and6 NYCRR
Part 201
Violation of ECL Article 19, 6 NYCRR §201.2(d)
and Permit to Construct (EP2), Special Permit
Condition #4.B., by Respondents’ receipt and/or
processing on 39 occasions’, of contaminated soil
from sites located in the State of New Jersey which
did not have a NYSDEC-assigned spill number.
Violation of ECL Article 19, 6 NYCRR §201.2(d)
and Permit to Construct (EP2), Special Permit
Conditions #5.B. and 5.E., by failure to maintain,
and failure to submit to the Department on a
2. Fourth Ruling, November 1, 1994.
3. Identified in “Appendix A”, attached to this Hearing Report.
24a
Appendix C
quarterly bass, logs which contained entries for
each of the 39 instances described in the first alleged
violation. (In its closing brief, Staff changed its
position by asserting it has proven 36 of the 39
instances alleged in the Complaint).
Complaint Section C:
Violation of ECL Article 27 and 6 NYCRR
Part 360
Respondents violated ECL §27-0707 and 6 NYCRR
360-1.7, by operating a solid waste management
facility (“SWMF”) by receipt and/or processing and/
or disposal of contaminated soil on the above
referenced 39 occasions, in a manner not consistent
with a Beneficial Use Determination (“BUD”)
issued to Respondent Mt. Hope (issued August 9,
1991); or alternatively, Respondents violated ECL
§27-0707 and 6 NYCRR 360-1.7, because the BUD
did not contemplate receipt and/or processing and/
or disposal of any material from August 7, 1991 to
September 15, 1993. (As noted above, in its closing
brief, Staff changed its position by asserting it has
proven 36 of the 39 instances alleged in the
Complaint).
Complaint Section D:
Violation of Navigation Law Article 12,
ECL Article 17 and 6 NYCRR Parts 360
and 613
Respondents violated Navigation Law §173 and
ECL §17-0501()) by causing a discharge of
i Bi a it ahr ia
a oe Se eee
25a
Appendix C
petroleum at the Mt. Hope facility on or before
September 16, 1993, which violation constitutes a
continuing violation from at least September 16,
1993 to the present.
Respondents violated NL §175 and 6 NYCRR 613.8
by failing to report the facility’s spill to the
Department (now identified by Department spill
number 94-07172).
Respondents violated 6 NYCRR 360-1.7(a)(1)(i)‘,
by continuing storage and disposal of petroleum-
contaminated soil at the Mt. Hope facility, from at
least September 16, 1993 to the present.
Staff maintains that since Respondent Petrosky is the
President of Respondent Mt. Hope and has been responsible
for daily management of Mt. Hope, Respondent Petrosky is
liable for the alleged violations both individually and in his
corporate capacity.
Staff seeks a monetary penalty of $1,081,500.00 from
Respondents, jointly and severally, for these alleged violations,
or in the alternative, pursuant to the ALJ’s Second Ruling, a
monetary penalty of $877,500.00 from Respondents, jointly and
severally (Staff revised its request for monetary penalty slightly
downward in its closing brief) . Staff also seeks an order that
Respondents 1) cease conducting any activities within the
Department’s regulatory authority; 2) submit a remediation plan
and implementation schedule for Staff's approval; and upon
4. Staff alleges violation of this provision by Respondents prior to
and after the regulatory provision was amended, effective October 9,
1993.
26a
Appendix C
approval, remediate and clea up all petroleum-contaminated
soil at the facility, whether buried or above ground; and 3) such
other and further relief as the Commissioner may deem just
and proper.
II. The Combined Notice of Intent to Revoke, Revocation and
Denial
Further, pursuant to Staff’s combined notice and the
allegations set forth in the Complaint that Staff asserts it has
proven at hearing, Staff seeks revocation of all Departmental
authority granted to Respondents to operate the facility, and
denial of all Respondents’ pending applications for continuing
or additional authority to operate, because Respondents are
allegedly unsuitable and unfit to engage in environmental
activities regulated by the Department due to their history of
non-compliance.
By ietter dated September 15, 1993 Staff issued to
Respondent Mt. Hope, a Notice of Permit Denial (regarding
Mount Hope’s application #1-4722-01052/00003-0, for
Certificate to Operate EP2) , Notice of Intent to Revoke (Permit
to Construct #1-4722-01052/00004-0, Emission Point 4,
rehydration chamber) and Revocation of Beneficial Use
Determination (regarding a Beneficial use Determination issued
to Mt. Hope on August 9, 1991). In effect, Staff seeks revocation
of all authority Respondents have been granted to operate the
facility, and denial of all pending applications for additional
or continued authority to operate. The combined notice letter
identifies five factors upon which Staff bases its notice:
(1) violation of Permit to Construct (EP2) permit
condition requiring only use of petroleum-
27a
Appendix C
contaminated soil from sites identified by a
Departmental spill number on 39 occasions;
(2) violation of Permit to Construct permit
condition (EP2 afterburner) requiring maintenance
and quarterly submittal of records to Staff, which
submittals failed to identify 39 instances of receipt
of contaminated soil at the facility;
(3) that commission of the two above referenced
violations rendered the Beneficial Use
Determination invalid on those dates, and therefore
constituted operation without a solid waste
management facility permit on those dates, in
violations of ECL Article 27 and 6 NYCRR 360
(“Part 360”);
(4) failure to comply with audit requirements
imposed by the January 14, 1993 Consent Order;
and
(5) Respondents’ history of non-compliance,
including a July 18, 1991 Consent Order; the January
14, 1993 Consent Order; and six criminal simplified
information issued to L.L.H. Recycled Aggregates
(a company which shares ownership and operations
with Respondent Mt. Hope).
ai lh ali Acta bela
Respondents’ Position
Respondents filed an Answer to the initial Complaint and
cach Amended Complaint. In response to Staff's Second
Amended Complaint, Respondents each filed an Answer dated
28a
Appendix C
October 6, 1993. Those Answers each assert two affirmative
defenses.
First, Respondents each assert as an affirmative defense,
that in the 39 instances when Mt. Hope received petroleum-
contaminated soil from New Jersey sites, the soil had not been
used for stack testing, but had been part of general operations
that had been conducted at the facility as permitted by the
Department. Therefore, Respondents assert that Staff failed to
prove that Mt. Hope violated the ECL or regulations of the
Department in the manner alleged in the Department’s Second
Amended Complaint dated September 30, 1994.
Second, Respondents each assert as an affirmative defense,
that the allegations contained in Section “C” of the Second
Amended Complaint (alleging violations of ECL Article 27 and
6 NYCRR Part 360) were conducted within the authority of
the BUD or, in the alternative, were consistent with the
requirements of ECL Article 27 and 6 NYCRR 360. These
affirmative defenses are discussed below in the context of the
corresponding Complaint allegations.
Respondents assert the record demonstrates that
Respondent Mt. Hope committed no violation of Departmental
regulatory programs, but to the contrary, performed a valuable
service to the public in the manufacture of asphait and the
education of the Department as to how petroleum-contaminated
soil waste can be recycled into an environmentally sound and
beneficial product, hot asphalt.
Further, regarding alleged discharge of petroleum product,
Respondents assert that samples collected and analyzed by
Suffolk County Department of Health Services (“SCDOHS”)
rected sti 7 S
29a
Appendix C
are unreliable due to improper sampling technique, improper
sample analysis method and failure to maintain chain of custody
of the samples.
Respondent Petrosky asserts that Staff failed to establish
that he was individually liable for any violation alleged in
Staff's Complaint. Petrosky further asserts that Staff failed to
prove that he was involved in the day-to-day activities of the
facility, or was involved in the day-to-day operation of the
facility.
Regarding the permit aspect of the consolidated action,
Respondents assert that Staff failed to show that Respondents
are unfit and unsuitable to engage in regulated environmental
activities. Therefore, Respondents assert that Mt. Hope should
receive a Certificate to Operate EP2, at which Mt. Hope may
produce asphalt and asphalt products utilizing petroleum-
contaminated soil as an aggregate and a Permit to Construct
and test EP4, the rehydration chamber. Further, Respondents
assert that the Beneficial Use Determination (“BUD”)
authorizing Mt. Hope to receive, temporarily store and use
petroleum-contaminated soil as an aggregate in asphalt
production, should be continued.
Respondents conclude that the alleged violations against
Respondent Mt. Hope and Respondent Petrosky should be
dismissed, and Certificates to Operate Mt. Hope’s afterburner,
EP2, and its rehydration chamber, EP4, with petroleum-
contaminated soil should be granted.
30a
Appendix C
Findings of Fact
1. Background
1. Respondent Mt. Hope Asphalt Corp., a/k/a Mount Hope
Asphalt Corp. (“Mt. Hope”) is a corporation with offices for
the transaction of business at Nugent Drive, Calverton, New
York. Respondent Mt. Hope has operated a facility at that
location for approximately 22 years, using virgin materials to
produce hot asphalt.
2. Respondent Frank Petrosky is President of corporate
Respondent Mt. Hope.
3. In or about July, 1990, Thomas Accardi of Disposal
Technologies, approached the Department’s Region I Staff with
his concept of using No. 2 fuel oil-contaminated soil in the
asphalt manufacturing process in place of virgin material.
4. Thomas Accardi was a principal of Disposal
Technologies, Inc.
. 5. By late August, 1990, Accardi approached Staff of the
Department’s Division of Air with an application on behalf of
Respondent Mt. Hope to implement his concept of using No. 2
fuel oil-contaminated soil in the asphalt manufacturing process
in place of virgin material. Accardi sought authority to modify
Mt. Hope’s Certificate to Operate its existing asphalt plant at
Calverton, Long Island (the “facility”) to authorize the
processing of contaminated soil through the asphalt plant’s
dryer for incorporation into asphalt products.
ms
a, Pes ln” Mls
PME MP item ome 8.
3la
Appendix C
6. The Mt. Hope application was the first in the State of
‘New York proposing to process petroleum-contaminated soil
in the production of asphalt.
7. Staff approved the concept, with certain conditions. On
or about August 9, 1991, Respondent Mt. Hope, obtained a
beneficial use determination (“BUD”) and a Permit to Construct
an afterburner referred to as Emissions Point 2 (“Permit to
Construct afterburner” or “Permit to Construct EP2”). The BUD
and Permit to Construct EP2 specified conditions under which
the Accardi/Mt. Hope proposal was authorized.
8. The expiration date of the Permit to Construct EP2 was
August 6, 1992. At Respondents’ request, the permit was later
amended by extending the expiration date to September 21,
1992. The purpose of this extension was to provide additional
time for Respondents to conduct the EP2 stack test.
9. The cover letter to the Permit to Construct, dated August
9, 1991, was a Beneficial Use Determination (issued pursuant
to 6 NYCRR 360-1.2[a][4][vii][a]).
10. Prior to issuance of the Permit to Construct EP2, a
two-day stack test was conducted at the facility on November
7, 1990 and November 9, 1990.
11. Respondent Mt. Hope constructed the EP2 afterburner
and conducted a stack test of the afterburner on August 26,
1992.
12. In or about October, 1992. Mt. Hope filed an
application for issuance of a Certificate to Operate EP2, a
Source of Air Contamination.
32a
Appendix C
II. The Enforcement Action
13. Staff initiated an enforcement action against
Respondents Mt. Hope and three corporate officers, Jay Boyle,
Paul Abrams and Frank Petrosky, by Notice of Hearing and
Verified Complaint dated September 17, 1993, duly served upon
Respondents (hereinafter referred to as “the enforcement”
action).
14. The three corporate officers were charged both in their
corporate and individual capacities. Staff withdrew its
Complaint against Jay Boyle and Paul Adams, during pre-
hearing motion practice and discovery.
15. Following issuance of the initial Complaint, in autumn,
1993 the Office of the Suffolk County District Attorney
obtained an indictment against remaining Respondents Mt.
Hope and Petrosky, based at least in part upon the same
activities that are at issue in this consolidated administrative
action. That matter was pending, pre-trial, at the time this
consolidated hearing was held.
16. Since autumn, 1993, Respondents have ceased all
production of asphalt at the facility.
A. Violation of ECL Articles 19 and 27, and 6 NYCRR Part
201 and 360
17. Respondent Mt. Hope maintained logbooks at the
facility, contemporaneous records that identify the type of
material received by the facility, the date received, origin of
the material (the site the material came from), the NYSDEC
Spill Number, the quantity of material received on the dates
ude naa
33a
Appendix C
indicated, cumulative total material received, invoice number
and date billed.
18. On at least 36 occasions from on or about November
13, 1991 to on or about September 17, 1992, Respondent Mt.
Hope received and/or processed contaminated soil from sites
located in the State of New Jersey. (See Hearing Report
Appendix A).
19. For the 36 occasions from on or about November 13,
1991 to on or about September 17, 1992 that, Respondent Mt.
Hope received and/or processed contaminated soil from sites
located in the State of New Jersey, Mt. Hope’s logbooks contain
seven digit numbers similar to Departmental spill numbers,
under the column heading, “NYSDEC Spill No.”. Further,
Respondent Mt. Hope’s files also contain seven digit numbers
similar to Departmental spill numbers.
20. The New York State Department of Environmental
Conservation does not issue spill numbers for spills occurring
outside the State of New York. None of the 36 New Jersey
sites had a NYSDEC-assigned spill number.
21. The New Jersey Department of Environmental
Protection has never issued seven digit spill numbers. Instead,
since 1991, spill numbers issued by that Department contain
only ten, eleven or twelve digits.
22. The New Jersey Department of Environmental
Protection does not assign a New Jersey case number to all
sites where petroleum-contaminated soil is generated. Approval
of the New Jersey Department of Environmental Protection is
required prior to any transportation of petroleum-contaminated
34a
Appendix C
soil to locations outside the State of New Jersey. Further, the
office within the New Jersey Department of Environmental
Protection that oversees the disposal of petroleum-contaminated
soil outside of the State of New Jersey, does not require the
assignment of a New Jersey DEP case number.
23. No Staff member authorized or otherwise allowed
Respondent Mt. Hope to receive, store or process petroleum-
contaminated soil from New Jersey.
24. No permit variance had been granted to Respondent
Mt. Hope and no permit modification had been issued to
Respondent Mt. Hope to authorize receipt, storage or processing
of petroleum-contaminated soil from New Jersey.
25. The analytical reports comprising pre-marked Exhibits
169-198 (excluding Exhibits 172 and 198), were maintained as
business records in the offices of Respondent Mt. Hope and
had been removed from those offices pursuant to search warrant
by the Suffolk County District Attorney. __
26. The analytical reports comprising Exhibits 163 through
198 (except for Exhibits 169, 171, 180 and 182), contained
laboratory analyses which indicated that the respective material
was non-hazardous pursuant to the Quality Assurance/Quality
Control (QA/QC) provisions of Mt. Hopes Permit to Construct
EP2. Further, all the those analyses were conducted by a New
York certified laboratory.
27. Regarding Exhibits 169, 171, 180 and 182, the
original reports maintained at Respondent Mt. Hope’s offices
had contained laboratory analyses, but copies which Staff
received from the District Attorney’s Office by Staff lacked
those analyses.
35a
Appendix C
28. Exhibits 212 A, B and C, are three quarterly reports
submitted by Respondent Mt. Hope to Department Staff. These
quarterly reports do not contain any entries indicating that
Respondent Mt. Hope received and processed petroleum-
contaminated soil from New Jersey on 36 occasions between
November 1991 and September 1992.
29. However, Respondent Mt. Hope’s log books do contain
entries indicating that Mt. Hope received and processed
petroleum-contaminated soil from New Jersey on 36 occasions
between November 1991 and September 1992.
B. Violation of Navigation Law Article 12, ECL Article ]7
and 6 NYCRR Parts 360 and 613
The Suffolk County Department of Health Services Soil Samples
30. Pursuant to a search warrant obtained by the office of
the Suffolk County District Attorney, members of the Suffolk
County Department of Health Services obtained soil samples
at the facility on September 16, 1993.
31. It was raining intermittently on September 16, 1993
during the soil sample collection process.
32. A back-hoe used for excavation of sampling points
was decontaminated at each sample point.
33. Many photographs were taken to document the location
of each sample point.
34. Although an asphalt surface was penetrated to obtain
samples in the “parking lot” area of the facility, no asphalt
particles were collected in the sample bottles.
36a
Appendix C
35. The SCDOHS Sanitarian actually collecting soil
samples wore two pair of gloves, and replaced the outer gloves
after completing sampling collection at each sample point.
36. After a SCDOHS Sanitarian obtained a sample, it was
placed in a sample bottle. A new bottle was used to collect
each soil sample.
37. The sample bottle was then sealed and the exterior was
cleaned, if necessary. The Sanitarian then handed the sample
directly to SCDOHS laboratory personnel, who preserved each
sample in its own plastic bag, in a cooler.
38. One of the two SCDOHS laboratory personnel present
on site were in physical custody of the samples, during the entire
day of sample collection. After sample collection was
completed at the site, SCDOHS laboratory personnel brought
the sample cooler to the SCDOHS van. |
39. Inside the van, the laboratory staff performed a final
count of samples taken. Then, the laboratory personnel
transported the sample cooler, with samples, to the county
laboratory.
40. Laboratory receipt of the samples was documented by
entries in a logbook. Each sample was assigned a laboratory
number, sealed in plastic and kept in a locked refrigerator,
located in a locked “evidence room” at the laboratory.
41. SCDOHS personnel completed “Chain of Custody”
forms detailing exactly who had custody of the samples
throughout each day.
37a
Appendix C
42. Analytical results of five of the soil samples obtained
by SCDOHS at the facility on September 16, 1993 show high
levels of petroleum constituents in certain locations. The five
SCDOHS samples are identified as 6MF, 7MFI, 18MF, 20MF
and 21MF.
43. SCDOHS Chemist Amendola used the federal
Environmental Protection Agency “8240” methodology to
analyze the soil samples for presence of petroleum constituents.
44. Amendola employed three variations from the EPA
8240 methodology when analyzing the samples. He used a
capillary column, rather than a packed column; he calculated
the analysis using external calibration instead of internal
calibration; and lastly, he did not heat the samples to 40 degrees
centigrade.
45. The variation of use of a capillary column rather than
a packed column under the EPA 8240 methodology was
specifically approved by the New York State Department of
Health as an acceptable variation from the EPA recommended
methodology.
46. Regarding his use of external calibration, Amendola
recalculated the analysis of four of the five Samples using
internal calibration, at a later date. The results using internal
calibration indicate a higher level of contamination of petroleum
constituents in all four samples, than did the external calibration
analysis method.
47. Heating the samples to 40 degrees centigrade would
have produced greater violation of the sample, and would have
yielded slightly higher analysis results than was obtained absent
heating of the soil samples.
38a
Appendix C
48. Some sample analysis results are stamped “Some
surrogate standard values are below acceptable levels”.
49. Staff submitted no evidence to show that any testing
of groundwater indicated a contravention of Departmental water
quality standards.
50. Neither Respondent Mt. Hope nor Respondent
Petrosky ever reported a petroleum discharge to the Department.
51. Once Staff learned of the petroleum discharge at the
facility, Gomez prepared a spill report for the facility and
obtained a spill number from the Department’s spill hotline.
Respondent Petrosky
52. Respondent Petrosky regularly held himself out to Staff
as the individual to be contacted in matters involving Mt. Hope
Asphalt Corp. Also, Petrosky maintained an office at Mt. Hope’s
offices located at the facility, he was regularly on-site, he
regularly met with Department personnel during Staff's site
visits to the Mt. Hope facility, and he regularly responded to
Staff's concerns. For example, it was Petrosky that responded
to Staff's concerns about dust at the facility by having the road
between the offices and the facility paved.
53. Respondent Petrosky certified Mt. Hope documents,
stating that the petroleum-contaminated soil indicated therein
was recycled and made into road paving materials.
54. Respondent Petrosky, in his capacity as President of
Respondent Mt. Hope, signed the two Consent Orders
concerning the facility.
39a
Appendix C
55. Respondent Petrosky also regularly attended virtually
all meetings with Department Staff at the Department’s Region
1 Offices and at the Mt. Hope Asphalt Corp. facility, on behalf
of Mt. Hope.
Ill. The Permit Action
56. By letter dated September 15, 1993 Staff issued to
Respondent Mt. Hope, a Notice of Permit Denial (regarding
Mount Hope’s application #1-4722-01052/00003-0, [Certificate
to Operate Emission Point No.00002, an afterburner)), Notice
of Intent to Revoke Permit (Permit to Construct #1-4722-01052/
00004-0 [Emission Point No. 00004, rehydration chamber]),
and Revocation of Beneficial Use Determination (regarding the
Beneficial Use Determination issued to Mt. Hope on August 9,
1991; (hereinafter, “the combined notice”, hereinafter referred
to as “the permit” action]).
57. The combined notice letter identifies five factors upon
which Staff bases its notice:
(1) violation of Permit to Construct (EP2) permit
condition requiring only use of petroleum-
contaminated soil from sites identified by a
Departmental spill number on 39 occasions;
(2) violation of Permit to Construct permit
condition (EP2 afterburner) requiring maintenance
and quarterly submittal of records to Staff, which
submittals failed to identify 39 instances of receipt
of contaminated soil at the facility;
(3) that commission of the two above referenced
violations rendered the Beneficial Use
40a
Appendix C
Determination invalid on those dates, and therefore
constituted operation without a solid waste
management facility permit on those dates, in
violations of ECL Article 27 and 6 NYCRR 360
(“Part 360”);
(4) failure to comply with audit requirements
imposed by the January 14, 1993 Consent Order;
and
(S) Respondents’ history of non-compliance,
including a July 18, 1991 Consent Order; the January
14, 1993 Consent Order; and six criminal simplified
information issued to L.L.H. Recycled Aggregates
(a company which shares ownership and operations
with Respondent Mt. Hope) .
The Falsified Analytical Report and Signature
58. Richard Parish has been employed as President of
Impact Environmental for approximately five years.
59. In mid-1991, Impact Environmental was retained as a
consultant to Disposal Technologies.
60. Impact Environmental, in its consultant capacity to
Disposal Technologies, performed sampling on behalf of Mt.
Hope, and sent the samples to appropriate laboratories for
analysis. Upon receiving the analysis from the laboratory, the
analysis would be forwarded to Disnosal Technologies under
Parish’s cover letter.
UES
PSO ey NPR ast
4la
Appendix C
61. Regarding the Ideal Aluminum site, 100 West 7th
Street, Bayonne, New Jersey, 116.71 tons of material was
received by Respondent Mt. Hope on December 24, 1991.
62. An analytical report for this material exists in the form
of a letter dated December 31, 1991, addressed from Parish on
behalf of Impact Environmental to Disposal Technologies at
the Mt. Hope facility address.
63. Exhibit 170, regarding the Ideal Aluminum Site, is
comprised of copies of documentation maintained by
Respondent Mt. Hope at its facility. The original documents
were obtained pursuant to search warrant by the office of the
Suffolk County District Attorney,
64. Information reported in the Ideal Aluminum analytical
report/letter states, “[b]ased on our investigation of 12-24-9]
the contaminated material is non-hazardous pursuant to the
standards promulgated by the New York State Department of
Environmental Conservation. All informaticz reported by the
client was confirmed by either Freedom of Information
Legislation and/or inspection.”
65. The Ideal Aluminum analytical report contains what
purports to be Parish’s signature. In fact, it is not his signature.
Further, the letter was not prepared by Parish or by Parish’s
office, Impact Environmental.
66. The Ideal Aluminum analytical report and Signature
are not genuine, but were falsified. It is impossible to know
whether the material described therein, received by Respondent
Mt. Hope, was truly non-hazardous petroleum-contaminated
soil.
42a
Appendix C
Respondent Mt. Hope’s History of Consent Orders
67. On May 28, 1991 Respondent Mt. Hope-entered into a
Consent order with the Department to resolve violations of ECL
Article 19 and 6 NYCRR Part 201, for commencing
construction to install the afterburner at the facility as an air
pollution control device, without the required Permit to
Construct. Under the Consent Order, signed by Respondent
Frank Petrosky in his capacity as President of Mt. Hope, a
$500.00 penalty was imposed upon Respondent Mt. Hope.
(Consent Order R1-4570-91-05).
68. On July 18, 1991 Respondent Mt. Hope entered into a
Consent Order with the Department regarding Mt. Hope’s
asphalt manufacturing plant located in Flushing, Queens, New
York. That Consent Order resolved violations of ECL Articles
15 and 25, and 6 NYCRR Part 661, by Respondent Mt. Hope
for allowing stone sand screenings to enter regulated navigable
waters and tidal wetlands without the required permits. Under
the Consent Order, signed by Mt. Hope’s Treasurer, Paul
Abrams, a $10,000.00 penalty and an order requiring
remediation was imposed upon Respondent Mt. Hope. (Consent
Order #R2-3559-91-03).
69. On January 14, 1993 Respondent Mt. Hope entered
into a Consent Order with the Department to resolve certain
violations at the facility and to assure continued authority to
operate EP2 (Consent Order 1 1-5074-92-06). The January, 1993
Consent order required construction of a rehydration chamber,
EP4. This Consent Order also required dissolution of the Mt.
Hope - Accardi/Disposal Technologies relationship.
70. The January, 1993 Consent Order also required Mt.
Hope to dissolve the Mt. Hope - Accardi /Disposal Technologies
43a
Appendix C
relationship (Consent Order. Schedule, A, Section IV) , and to
comply with detailed financial auditing requirements (Consent
Order Schedule A, Section V), including an affidavit from a
Certified Public Accountant certifying that it performed an
investigation of Respondent Mt. Hope’s records regarding
Thomas Accardi’s relationship to Mt. Hope. Consent Order
1-5074-92-06.
71. On or about February 16, 1993, Mt. Hope submitted
an application for a Permit to Construct/Certificate to Operate
a Rehydration Chamber, EP4. On July 22, 1993, the Department
issued the Permit to Construct and Test a Rehydration Chamber,
EP4 (permit issued July 19, 1993, indicating an expiration date
of July 18, 1994).
72. On November 29, 1990, the Department’s then-
Director of the Division of Solid Waste issued a memorandum
for intra-agency purposes, to the Department Staff’s Regional
Solid Waste Engineers, regarding beneficial use of petroleum-
contaminated waste soil as an aggregate in asphalt production.
Conclusions of Law
1. Respondents are both “persons” within the meaning of
ECL §19-0107.
2. Thomas Accardi. and Disposal Technologies, Inc., were
agents for Respondent Mt. Hope.
3. Respondents did not operate the EP2 afterburner, an
air contamination source, in accordance with Respondent Mt.
Hope’s August 7, 1991 Permit to Construct because
Respondents regularly violated Special Condition (4)(B) of the
permit.
44a
Appendix C
4. Respondents’ affirmative defense that Special Condition
(4)(B) only applied to stack tests is without merit. The
limitations and requirements set forth in the Permit to Construct
EP2, Special Condition (4})(B), applied to Respondents’
operation of the facility throughout the period during which
the permit was valid.
5. “Processing” of petroleum-contaminated soil, as that
term is used in Permit to Construct EP2, Special Condition (4)
(B), includes “receipt” of petroleum-contaminated soil for
purposes of processing.
6. Each “Job” (or site) identified in the Complaint is taken
to represent an allegation of one incident of receipt of
petroleum-contaminated soil, even though the record establishes
that for at least some of the proven violations, Respondent Mt.
Hope did, in fact, receive a number of shipments of
contaminated soil over a period of days or weeks for particular
jobs.
7. For the 36 New Jersey job sites identified in Exhibits
163 through 198, petroleum-contaminated soil from sites
located in the State of New Jersey was received and processed
by Respondent Mt. rope.
8. For the 36 New Jersey sites identified in Exhibits 163
through 198, the spill numbers used by Respondents in their
logbooks and files are fabricated spill numbers. Those spill
numbers were not issued by the New Jersey Department of
Environmenial Protection or by the Department.
9. Respondents fabricated these spill numbers to create
the appearance that Respondents were operating within the
45a
Appendix C
authority of Respondent Mt. Hope’s Permit to Construct EP2
and BUD.
10. Respondent Mt. Hope intentionally omitted entries
from three quarterly reports (August 15, 1991 to March 31,
1992; April 1, 1992 to June 30, 1992: and July 1, 1992 to
September 30, 1992, respectively) regarding petroleum-
contaminated soil it received and processed from the 36 New
Jersey sites. Respondent Mt. Hope did so because it knew that
such activities exceeded the scope of authority of its Permit to
Construct EP2 and BUD. Respondents thereby violated Special
Permit Condition (5)(B), and consequently 6 NYCRR
§201.2(d), on three occasions.
11. Carlson Associates is not applicable regarding
computation of monetary penalty in the present action.
However, the provisions of ECL Article 71 are relevant and do
provide for a continuing violation of ECL Article 27. ECL §71-
2703(1). Staff has properly asserted a continuing violation of
ECL §27-0707 and 6 NYCRR 360-1.7, for operating a solid
waste management facility without a permit from November
17, 1991 (the first date of receipt of soil from a New Jersey
site) to September 17, 1992 (the last date of receipt of soil from
a New Jersey site).
Applicability of the Beneficial Use Determination
12. Respondents’ receipt storage and processing of
petroleum-contaminated soil from sites in New Jersey was not
authorized by the Permit to Construct EP2.
13. Compliance with the Permit to Construct EP2 was a
condition upon which the Beneficial] Use Determination was
46a
Appendix C
premised. Therefore, Respondents’ receipt. Storage and
processing of petroleum-contaminated soil from sites in New
Jersey was not within the scope of authority of the Beneficial
Use Determination.
14. A permit issued pursuant to 6 NYCRR Part 360 is
required for these activities.
15. Because Respondent Mt. Hope acted outside the scope
of authority of the BUD, Mt. Hope operated a solid waste
management facility without a permit, in violation of 6 NYCRR
§3601.7(a)(1)(ii). Respondent Mt. Hope’s receipt, storage and
processing of petroleum-contaminated soil from sites in the
State of New Jersey, absent a solid waste management facility
permit constituted operation of a solid waste management
facility without a permit, a violation of 6 NYCRR §360-1.7
(-\<1}Gi), a continuing violation of 6 NYCRR §360-
1.7(a){1)(ii), from November 17, 1991 to September 17, 1992.
The Falsified Ideal Aluminum Analytical Report
16. Respondent Mt. Hope prepared the falsified analytical
report and falsified Parish’s signature regarding the Ideal
Aluminum site.
17. Respondent Mt. Hope is responsible for the false report
and false signature as a matter of law, since either Mt. Hope or
its agent created the falsified document.
18. However, Staff failed to establish a record through
Parish, or any other witness, challenging the authenticity of
the other 35 exhibits in the series. Exhibits 163 through 198.
47a
Appendix C
19. Exhibit 8, an internal. Departmental memorandum,
does not constitute a generic beneficial use determination
because by its own terms, the memorandum requires a
determination whether or not the activity conforms with the
generic beneficial use criteria identified in the memorandum.
20. When Respondent Mt. Hope violated Special
Conditions (4)(B) and (5)(B) of the permit to construct the
afterburner, it violated 6 NYCRR §201.2(d) . Those activities
were beyond the scope of authority of the BUD and required a
SWMF permit.
The Petroleum Discharge
21. For purposes of NL §173, Staff need not prove that
discharged petroleum constituents did, in fact, flow into the
groundwater.
22. Respondents’ challenges to sampling methodology are
rejected.
23. All three variations to the 8240 EPA methodology
employed by SCDOHS Chemist Amendola in analyzing the
five samples, would, if anything, result in a false low test result,
thereby indicating a lesser presence of petroleum constituents
than would analysis of that sample under the EPA recommended
methodology without variation.
24. Respondents’ speculative contentions regarding
asphalt contamination as a result of rain run-off into the test
pits, or asphalt particles falling into the test pits, is rejected in
light of the detailed sampling process described in the record.
Rainfall during field sample collection had no impact on the
soil that was being sampled.
48a
Appendix C
25. An adequate chain of custody was maintained for
samples 6MF, 7MF, 18MF, 20MF and 21MF.
26. The phrase “Some surrogate standard values are below
acceptable ievels”, stamped on some analysis results, means
that the full surrogate level was not identified in the test result.
Therefore, those test results probably under-report presence of
substances for which the test was intended. Thus, the stamped
language on a sample result indicates that the results obtained
by the laboratory are an under-representation of the actual
petroleum contamination level in the sample.
27. A petroleum discharge occurred during Mt. Hope’s
tenure at the site. This ongoing discharge of petroleum
constitutes a continuing violation of NL §173 from at least
September 16, 1993 to the present.
28. The fact that the discharge may have been petroleum-
contaminated soil as opposed to a liquid form of petroleum is
not relevant. Analysis of the five SCDOHS samples
demonstrates a petroleum discharge occurred at the facility at
some time prior to the date of sample collection.
29. Staff's contention that Respondent Mt. Hope took
specific intentional or deliberate acts causing the discharge is
rejected.
30. Respondents’ failure to report the spill to the
Department constitutes a violation of NL §175 and 6 NYCRR
§613.8.
ee de ey ee eee a hee
49a
Appendix C
Respondent Petrosky
31. Respondent Frank Petrosky was President and day-to-
day manager of Mt. Hope Asphalt Corp. He was a high
managerial agent of corporate Respondent Mt. Hope, and was
in a position to prevent the corporate violations that occurred
regarding receipt and processing of contaminated soil from New
Jersey sites.
32. Therefore, Respondent Frank Petrosky is liable for the
violations of the corporation both in his Capacity as President
of Mt. Hope and also individually.
DISCUSSION
I. Applicable Statutory and Regulatory Provisions
Jurisdiction and authority to initiate this administrative
action is based upon Environmental Conservation Law §3-0301.
(1)(i), (1), (m), (n) and (0), ECL §3-0301(2)(h), ECL Articles
17, 19, 27 and 71 and Navigation Law, Article 12.
ECL §17-.0501(1) provides that it is unlawful for any
person, directly or indirectly, to throw, drain, run or otherwise
discharge into such waters organic or inorganic matter that shall
cause or contribute to a condition in contravention of the
standards adopted by the department pursuant to ECL §17-0301.
ECL §27-0707 provides that no person shall commence
operation, including site preparation and construction, of a new
solid waste management facility until such person has obtained
a permit pursuant: to ECL Article 27, Title 7.
50a
Appendix C
NL §172(8) and 6 NYCRR §613.1(8) provide that a
discharge is any intentional or unintentional action or omission
resulting in the releasing, spilling, leaking, pumping, pouring,
emitting, emptying or dumping of petroleum into the waters of
the state or onto lands from which it might flow or drain into
said waters, or into waters outside the jurisdiction of the state
when damage may result to the lands, waters or natural
resources within the jurisdiction of the state.
NL §173 provides that the discharge of petroleum is
prohibited.
NL §175 provides that any person responsible for causing
a discharge shall immediately notify the Department pursuant
to the rules and regulations established by the department, but
in no case later than two hours after the discharge. Failure to
so notify shall make persons liable to the penalty provisions of
§192.
6 NYCRR Part 201.2(d) provides that a person who owns
or operates an air contamination source shall construct, modify,
test, install and operate such source in accordance with all
conditions of the applicable permit to construct or certificate
to operate.
6 NYCRR §360-1.2(a)(2)(i) provides that, “material is
discarded if it is abandoned by being (i) disposed of”.
6 NYCRR §360-1.2(a)(3) provides that “[A] material is
disposed of if it is discharged, deposited, injected, dumped,
spilled, leaked or placed into or on any land or water so that
such material or any constituent thereof may enter the
environment or be emitted into the air or discharged into
groundwater or surface water”.
OT PPE TRUE” ee
Sla
Appendix C
6NYCRR §360-1.2(a)(4)(vii) states that materials that the
Department has determined are being beneficially used,
including materials that are incorporated into a manufacturing
process to produce a marketable product, are not solid waste
for the purposes of 6 NYCRR Part 360. (eff. December 31,
1988 to October 8, 1993: compare, current 6 NYCRR §360-
1.2(a)(4)(vii)).
6 NYCRR §360-1.2(b)(145) A solid waste management
facility is defined as “any facility” employed beyond the initial
solid waste collection process and managing solid waste... .”.
Solid waste is defined as “all putrescible and nonputrescible
materials or substances, except as described in paragraph (4)
of this subdivision, that are discarded or rejected ...” (6
NYCRR §360-1.2(a)(1)
6 NYCRR §360-1.5(a) provides that no person shall dispose
of solid waste in the State of New York, except at a disposal
facility exempt from the requirements of Part 360, ora disposal
facility authorized to accept such waste.
6 NYCRR §360-1.7(a)(1)(ii) provides that no person shall
operate a solid waste management facility, except in accordance
with a valid permit to operate that facility issued pursuant to 6
NYCRR Part 360, except as otherwise provided in Part 360,
Il. The Relationship Between Mt. Hope and Disposal
Technologies, Inc. _
Respondents assert that Disposal Technologies, Inc.
(“Disposal Technologies”) and its principal, Thomas Accardi
(“Accardi”; collectively, “Disposal Technologies”), never acted
as agents for Mt. Hope, but instead were independent
52a
Appendix C
contractors. Respondents further assert that Disposal
Technologies was solely responsible for preparation of the
incomplete quarterly reports, and that Respondents were not
aware of any omission in the reports.
Lastly, Respondents assert that when they learned that
Thomas Accardi/Disposal Technologies, Inc. had been
misrepresenting other business information to them,
Respondents terminated the Mt. Hope-Accardi/Disposal
Technologies relationship. Therefore, Respondents conclude
they should not be penalized or suffer loss of their authority to
operate the Mt. Hope facility, due to illegal acts or omissions
of Accardi/Disposal Technologies.
Dissolution of this relationship was a condition of the
January, 1993 Mt. Hope Consent Order. However, during the
time period at issue for the 39 New Jersey transactions alleged
in the Complaint, the Mt. Hope-Disposal Technologies
relationship did exist. In February, 1991 Mt. Hope identified
Disposal Technologies, Inc. and Accardi as its consultant.
Subsequently, Mt. Hope authorized Disposal Technologies to
prepare and submit the quarterly reports on behalf of Mt. Hope.
It is undisputed that the quarterly reports at issue were prepared
by Disposal Technologies from information either developed
by Disposal Technologies from Mt. Hope’s records, or provided
by Respondent Mt. Hope.
Whether the quarterly reports were prepared or filed by a
member of the Disposal Technologies’ staff or the Mt. Hope
Asphalt staff is irrelevant at law. Respondent Mt. Hope, the
permittee, is solely responsible for assuring compliance with
all applicable laws, regulations and permit conditions associated
with its asphalt operation. NYSDEC v. Ten Mile-River Holding,
53a
Appendix C
Ltd., M.A.C. Sand and Gravel, Inc. and Aldo Colella, Decision
of the Commissioner, August 11, 1994 [It is immaterial whether
MAC is characterized as an agent or as an independent
contractor. Very simply put, TMR as the permittee is primarily
responsible for assuring compliance with al] applicable laws,
regulations and permit conditions associated with its mining
operation].
Regardless of whether the Mt. Hope-Disposal Technologies
relationship may have dissolved at some future time, during
the time period at issue in the Complaint, Thomas Accardi and
Disposal Technologies, Inc. were agents for Respondent Mt.
Hope, as discussed above. Disposal Technologies, through
Accardi, attended meetings with Staff on behalf of Respondent
Mt. Hope. During Katy Murphy’s nine site visits, she usually
met with Respondent Petrosky, sometimes with Accardi. In
addition, Disposal Technologies (and Accardi) maintained
offices in the series of interconnected trailers located at Mt.
Hope’s facility, which also housed Mt. Hope. Mt. Hope and
Disposal Technologies were the sole business entities located
at Mt. Hope’s facility.
Respondents assert that the mere fact they offered no
explanation as to why they submitted incomplete quarterly
reports, identifying only New York materials, does not establish
intent. Respondents assert they may reasonably have had
legitimate business purposes for maintaining such records.
However, also in evidence is proof that Respondent Mt. Hope
falsified spill numbers to give the impression that only spills
identified by a NYSDEC Spill Number were being brought into
the facility. A review of Exhibits 163 through 198 shows that
these fabricated spill numbers initially appeared on documents
generated by Disposal Technologies. However, even if Mt.
54a
Appendix C
Hope employees unwittingly copied these seven digit “spill
numbers” from the Disposal Technologies documents into the
log book maintained by Mt. Hope, Mt. Hope is responsible for
the acts of Accardi/Disposal Technologies.
Kathleen Morrison, a Mt. Hope employee, testified that
when Murphy conducted site visits at the facility and reviewed
logbooks, Murphy would be shown the original logbooks’. The
logbooks are contemporaneous records that identify the type
of material received by the facility, the site the material came
from and the quantity of material received on the dates
indicated. The third column in Exhibit 84 indicates “NYSDEC
Spill No.” and lists a seven digit spill number for each entry,
including entries for materials Respondent Mt. Hope received
from the State of New Jersey®. The second column in Exhibit
86 indicates “Spill No.” and lists a seven digit spill number for
each entry for materials accepted from the State of New Jersey’.
5. Exhibits 84 and 86 are photocopies of the original documents.
6. For example, Exhibit 84, page 2, line 6 (matching Exhibit 165)
page 2, lines 17 and 18 (matching Exhibit 163), page 2, line 22 (matching
exhibit 164), page 2, line 36 (matching Exhibit 166), page 3, line 9
(matching Exhibit 167), page 3, line 10 (matching Exhibit 168), page 3,
line 15 (matching Exhibit 169), page 3, line 16 (matching Exhibit 170),
page 4, line 3 (matching Exhibit 173), page 4, line 5 (matching Exhibit
172), page 4, line 12 (matching Exhibit 174), page 4, line 13 (matching
Exhibit 175), page 4, line 18 (matching Exhibit 177), page 4. line 19
(matching Exhibit 176), page 4, lines 26 and 29 (matching Exhibit 171),
page 4, line 34 (matching Exhibit 180), page 4, line 37 (matching Exhibit
179), page 4, line 41 (matching Exhibit 181) and page 5, line 13
(matching Exhibit 178)).
7. For example, Exhibit 86, page 2, lines 14 and 26 (matching
Exhibit 189), page 3, line 6 (matching Exhibit 191), page 3, line 10
(Cont'd)
55a
Appendix C
The Department issues seven digit spill numbers, whereas the
State of New Jersey does not.
Respondent Mt. Hope (or Disposal Technologies, Inc.)
fabricated these spill numbers. The spill numbers were not
issued by the New York State Department of Environmental
Conservation. Furthermore, the spill numbers are not legitimate
spill numbers issued by the New Jersey State Department of
Environmental Protection. Respondents provided no ;
explanation for these fabricated spill numbers, other than to
assert that Accardi/Disposal Technologies created the fabricated
numbers, autonomously, as part of their plan to deceive both
Mt. Hope and the Department.
Further, Respondent Mt. Hope fabricated the spill,
numbers, with the intent to deceive the Staff members who
might inspect the log books. When Department personnel
reviewed the log books maintained at the facility, they saw
seven digit numbers appearing to be NYSDEC spill numbers
and presumed that Respondent Mt. Hope was only accepting
petroleum-contaminated soil from sites located in the State of
New York, in conformance with its permit.
Therefore, even if Respondents’ argument is accepted that
Accardi/Disposal Technologies filed incomplete quarterly
reports absent Respondents’ knowledge or consent, Respondent
Mt. Hope is liable for Accardi’s acts. Whether in fact it was
(Cont'd)
(matching Exhibit 192), page 3, line 26 (matching Exhibit 193), page 3,
line 30 (matching Exhibit 190), page 5, line 9 (matching Exhibit 194),
page 5, line 17 (matching Exhibit 195), page 5, line 25 and page 17, line
13 (matching Exhibit 196), pag 15, line 2 (matchiv:g Exhibit 197), and
page 17, line 25 (matching Exhibit 198).
56a
Appendix C
Respondent Mt. Hope or Thomas Accardi/Disposal
Technologies, Inc., that fabricated the seven digit spill numbers
resembling legitimate NYSDEC spill numbers for the 36 New
Jersey sites listed in Mt. Hope’s logbooks, Respondent Mt. Hope
is ultimately liable, as a matter of law.
Ill. The Enforcement Action
The Stipulations
The parties agreed to two factual stipulations during the
hearing. The first stipulation concerned the admission into
evidence of 27 exhibits which allegedly constituted analytical
reports of shipments of soil originating from the State of New
Jersey that had been received at Mt. Hope’s Calverton facility.
These analytical reports constitute pre-marked Exhibits 169-
198, in evidence, excluding Exhibits 172 and 198. The parties
stipulated that those 27 exhibits were maintained as business
records in the offices of Respondent Mt. Hope and had been
removed from those offices by the Suffolk County District
Attorney. Also, the parties stipulated that all of the analytical
reports (Exhibits 163 through 198), except for Exhibits 169,
171, 180 and 182, contained laboratory analyses which indicated
that all material was nonhazardous pursuant to the Quality
Assurance/Quality Control, (QA/QC) provisions of the Permit
to Construct EP2. Further, all the analyses were conducted by
a New York certified laboratory. With respect to Exhibits 169,
171, 180 and 182, Respondents asserted that the original reports
maintained at Mt. Hope’s offices had contained laboratory
analyses, but the copies received back from the District
Attorney’s Office by Staff lacked copies of those analyses.
The second stipulation entered into by the parties concerned
Exhibit No. 312, an affidavit of John Strong of the State of
—
57a
Appendix C
New Jersey Department of Environmental Protection. In sum
and substance, the affidavit states that the New Jersey
Department of Environmental Protection does not utilize a
system which contains a 7-digit spill number. The parties
stipulated that: (1) a New Jersey case number is not assigned
to all sites where petroleum-contaminated soil is generated;
(2) New Jersey Department of Environmental Protection
approval is required prior to ; 4y transportation of petroleum-
contaminated soil from the State of New Jersey, and (3) the
office that oversees the disposal of petroleum-contaminated soil
Outside of the State of New Jersey does not require the
assignment of a New Jersey DEP case number.
A. The Charge of Violation of ECL Article 19, and 6
NYCRR Part 20]
1. Alleged Violation of ECL Article 19, 6 NYCRR
§201.2(d) and Permit to Construct (EP2, the
afterburner), Special Permit Condition (4)(B), by
Respondents’ receipt and/or processing on 39 occasions
of contaminated soil from sites located in the State of
New Jersey which did not have a NYSDEC-assigned
spill number.
Staff alleges in Complaint §B that Respondents received
and/or processed contaminated soi] from sites located in the
State of New Jersey which did not have a NYSDEC-assigned
spill number on 39 occasions from on or about November 13,
1991 to on or about September 17, 1992. (The 39 occasions
identified in the Complaint are identified in Hearing Report
Appendix A).
58a
Appendix C
6 NYCRR Part 201 is promulgated pursuant to ECL Article
19*. Respondents are both “persons” within the meaning of ECL
§19-0107. Pursuant to 6 NYCRR §201.2(d), “a person who
Owns or operates an air contamination source shall construct,
modify, test, install and operate such source in accordance with
all conditions of the applicable permit to construct or certificate
to operate.” Staff asserts that Respondents did not construct,
test, install and operate their afterburner, an air contamination
source, in accordance with Respondent Mt. Hope’s August 7,
1991 Permit to Construct EP2, because they regularly violated
special condition (4)(B) of that permit’.
Special Condition (4)(B) of Respondent Mt. Hope’s Permit
to Construct an afterburner (Permit #1-473-00135/00002-0,
hereinafter referred to as “Permit to Construct the afterburner”
or “Permit to Construct EP2”) provides at page 6, that “[o]nly
contaminated soil from sites identified by a NYSDEC assigned
spill number shall be processed at the facility”.
Staff asserts that the limitation created by Special Condition
(4)(B) was necessary, to assure Staff would be able to review
all necessary information regarding the source and constituents
of petroleum-contaminated soil to be received and processed
at the facility. Staff asserts it would thereby be able to control
the risks that Respondents’ operation would otherwise pose to
human health and the environment.
8. See ECL §19-0301 and §19-0305, respectively.
9. The permit number of the Permit to Construct EP2, was changed
on June 2, 1992, to #1-4722-01052/00001-0.
59a
Appendix C
Respondents’ A ffirmative Defense
However, Respondents assert an affirmative defense that
the Permit to Construct EP2 created two distinct Categories of
authority for operation of the facility; one category of “operation
for testing purposes” and another category of “operation for
preparation for stack testing”. Subsequent to issuance of the
EP2 Permit to Construct, a second stack test of the facility with
its afterburner (EP2) installed, was conducted on August 26,
1992'°,
The first page of the permit states, under the caption
“Description of Authorized Activity”:
Construct and test emission point 00002, an air
Oxidation unit (afterburner), for the Purpose of
reducing air emissions from existing asphalt facility
and to allow use of petroleum-contaminated soil as
aggregate. The new emission point will replace
existing emission point 00001. Operate emission
point 00002 for the purposes of preparation for stack
text (sic). (emphasis added).
The caption identifying Special Condition Section (4) is
“Operation for Testing Purposes”. Respondents assert that this
heading limits the scope of Special Condition (4)(B), to
“operation of the facility for testing purposes”, as opposed to
authority granted by the first page of the permit, “operation in
preparation for testing”.
10. Prior to issuance of the Permit to Construct EP2, a two-day
Stack test was conducted at the facility on November 7 and 9, 1990.
60a
Appendix C
Respondents assert that the only restriction placed upon
Mt. Hope under Special Condition (4)(B) concerns that soil
which was to be used during Mt. Hope’s actual stack test(s).
They assert the Permit to Construct EP2 did not restrict all
receipt and processing of contaminated soil to that which had a
NYSDEC spill number assigned to the site of origination of
the soil. Instead, Respondents assert that authority granted by
the first page of the permit authorized Mt. Hope to generally
operate utilizing non-hazardous petroleum-contaminated soil
irrespective of source of origin.
Respondents further assert that the authority granted by
Special Condition (4)(B), read together with the heading to
Special Condition Section (4), limited Mt. Hope to specific
chemical compounds to be present in the soils which were to
be-a part of the stack test only, to ensure that emission test data
obtained would be as broad as possible.
Lastly, Respondents assert that Staff presented no evidence
to establish that Mt. Hope did not comply with the provisions
of Special Condition (4)(B) during the August 26, 1992 stack
test. Therefore, Respondents conclude that Staff failed to prove
that there was noncompliance with Special Condition (4)(B).
In response, Staff asserts that Special Condition Section
(3), entitled “Emission Testing and Certificate to Operate
Application”"' identifies conditions applying to the stack testing
procedure, and that Section (4) applies to all authorized
activities, generally.
Staff asserts that the heading for permit Section 4 was
created to clarify to the permittee, Respondent Mt. Hope, that
11. Exhibit 135, Permit to Construct, page 4.
6la
Appendix C
the Permit to Construct EP2 was not to be construed for any
operations other than for preparing for the afterburner stack
test and conducting that stack test. Additionally, Staff asserts
the Section 4 heading was created to clarify that any further
operation would not be authorized because the permit issued
to Respondent Mt. Hope was not a Certificate to Operate, but
instead, a Permit to Construct. F inally, Staff asserts the evidence
shows that at no time did any staff member authorize
Respondents to receive, store or process petroleum-
contaminated soil from New Jersey. Further, Staff granted no
permit variance or modification. The expiration date of the
Permit te Construct EP2 was August 6, 1992. At Respondents’
request, Staff amended the permit by extending the expiration
date to September 21 , 1992, to provide Respondents additional
time to conduct the stack test. That permit amendment stated:
“No modification of permit or special conditions.”"? Therefore,
the amendment to the Permit to Construct EP2 was limited to
an extension of the permit’s time period, and did not affect
other substantive conditions of the permit.
Respondents’ affirmative defense that Special Condition
(4) (B) only applied to stack tests is without merit because the
distinction drawn by Respondents is misplaced. Respondents
understood that the permit issued was a Permit to Construct,
not the Certificate to operate which they hoped to obtain at
soine future date. The permit conditions, when read as a whole,
are reasonably construed to mean that “authority for operation
to prepare for stack testing” is within the broader authority to
“performing the stack test”. Accordingly, the limitations and
requirements set forth in the Permit to Construct EP2, Special
12. Exhibit 146.
62a
Appendix C
Condition (4)(B), applied to Respondents’ operation of the
facility throughout the period during which the permit was valid.
By analogy to statutory construction, the title is not part of
the statute. People ex rel. Commonwealth Insurance Co. v
Coleman, 121 NY 542, 25 NE 51 (1890); Petition of Trustees
of New York & Brooklyn Bridge, 72 NY 527 (1878); People ex
rel. Cucinatta v Burger, 54 Misc. 2d 92 (1967); National
Enerdrill Corp v Crown Drilling, Inc., 119 Misc. 2d 162 (1983).
The text of a statute must take precedence over the title; the
title should not be used to nullify or limit the text of the statute.
Squadrito v Griebsch, 1 NY2d 471, 136 NE2d 504 (1956);
People v Arriaga, 45 Misc. 2d 399 (1965); Neumann v New
York, 137 AD 55 (1910); Wells v New York State Department
of Transportation, 90 Misc. 2d 535; Morabito v Hagerman Fire
District, 128 Misc. 2d 340 (1985).
Lastly, Paragraph (B)(6) of the Second Amended
Complaint alleges a violation for “receipt and/or processing”.
Respondents assert that Special Condition (4)(B) does not
contain a prohibition as to “receipt” of contaminated soil, but
only as to “processing”. Respondents conclude that no violation
can be attributed to Mt. Hope based upon noncompliance with
Special Condition (4)(B) for “receipt” of contaminated soil.
This allegation does not create separate liability for
“receipt” and for “processing”. However, “processing”
reasonably includes “receipt” for purposes of processing.
Therefore, if Respondents received the materials for processing,
then Staff's allegations based upon noncompliance with Special
Condition (4)(B) are proper. If Respondents received the
materials for some purpose other than processing, they were
acting outside the authority of the Beneficial Use
63a
Appendix C
Determination, unless they could show otherwise, as discussed
in Report Section B, below, and therefore were in violation of
ECL Article 27 and 6 NYCRR Part 360.
The 39 New Jersey Sites
Staff's allegations identify 39 New Jersey sites, and
essentially allege one transaction of receipt of contaminated
soil from each site. However, Respondents explained at hearing
that they refer to each generator of contaminated soil, by site,
as one “job”. Respondents further explained that they would
normally receive a number of shipments of contaminated soil
over a period of days or weeks, for each “Job” or site. Therefore,
Staffs allegations, identifying 39 New Jersey sites, potenually
represent more than 39 occasions of receipt by Mt. Hope of
petroleum-contaminated soil. However, since Staff did not
allege multiple occasions of receipt by Respondent Mt. Hope
for any particular “Job” or site, each “job” (or site) identified
in the Complaint is taken to represent an allegation of one
incident of receipt of petroleum-contaminated soil, even though
the record establishes that for certain sites, Respondent Mt.
Hope did, in fact, receive a number of shipments of
contaminated soil over a period of days or weeks.
Staff presented documentary evidence at hearing showing
that on at least 36 occasions Mt. Hope accepted and processed
petroleum contaminated soil froin sites located in New Jersey”.
Respondent Mt. Hope concedes that it received and
processed petroleum-contaminated soil from New Jersey in 33
of 39 incidents alleged in the Complaint, and further, that for
13. Exhibits 163-198.
64a
Appendix C
those 33 incidents soil did not originate from a site identified
by a NYSDEC spill number.
Exhibits 163 through 198 contain documentation, including
receipts for petroleum-contaminated soil for each of the 36 sites.
These receipts each contain a Disposal Technologies Inc. logo
on top and a statement toward the bottom that the “Disposal
Facility” is Mount Hope Asphalt. These exhibits also contain
non-hazardous material manifests which state that the
contaminated soil is “destined for recycling”'*. Exhibits 194,
195 and 198 include certifications by Frank Petrosky stating
that the petroleum-contaminated soil indicated therein was
recycled and made into “road paving materials”.
Respondents’ witness, Jay Boyle, admitted that Mt. Hope
processed petroleum-contaminated soil from New Jersey sites
until Respondents received Robert Becherer’s August 28, 1992
reply to Respondents’ request to accept petroleum-contaminated
soil from a certain New Jersey site referred to as the Picatinny
Arsenal site. Finally, Mt. Hope’s logbooks indicate receipt of
petroleum-contaminated soil from 36 New Jersey sites. Based
on this evidence, it reasonable to conclude that for the 36 New
Jersey job sites identified in Exhibits 163 through 198,
petroleum-contaminated soil from the State of New Jersey was
received and processed by Respondent Mt. Hope.
Staff asserts that for the 36 incidents identified by Exhibits
163 through 198, the petroleum-contaminated soil was not
identified by a NYSDEC-assigned spill number, because the
Department does not issue spill numbers for spills occurring
outside the State of New York. Staff further asserts that Exhibits
199 and 312 show that the spill numbers used by Respondents
14. See, for example, Exhibit 163, page 5.
65a
Appendix C
in their logbooks and files are false, and were fabricated by
Respondents to create the appearance that Respondents were
operating within the authority of their permit. Exhibit 199 is
an affidavit of Departmental employee Angela Chieco,
Environmental Engineer II, stating in sum and substance that
she is the Department’s spill file database custodian, and
providing the actual spill locations within New York State, for
which spill numbers identified in Exhibits 163 through 198 were
actually assigned. Exhibit 312 is an affidavit of New Jersey
Department of Environmental Protection employee John Strong
which states, in sum and substarice, that New Jersey Department
of Environmental Protection does not utilize a system which
contains a seven-digit spill number.
In the Permit to Construct EP2, the requirement of a
“NYSDEC assigned spill number” means that the Department
Staff must be the source of origin for the spill number.
Consequently, in Exhibit 84, as in other documentary evidence
in this consolidated action, seven digit spill numbers
purportedly identifying New Jersey petroleum-contaminated
soil have been fabricated by Respondent Mt. Hope. Further,
the seven digit numbers appearing in the column heading
“NYSDEC SPILL No.” are not spill numbers issued by the State
of New Jersey, because, New Jersey has never issued seven
digit spill numbers, and since 1991 has issued only ten, eleven
or twelve digit spill numbers. Respondent Mt. Hope has
assigned fabricated spill numbers to all New Jersey jobs
identified in Exhibit 84, under a column heading indicating
“NYSDEC SPILL No.”
66a
Appendix C
2. Alleged violation of ECL Article 19, and 6 NYCRR
§201.2(d) and Permit to Construct (EP2), Special Permit
Conditions (5)(B) and (5)(E), by failure to maintain,
and failure to submit to the Department on a quarterly
basis, logs which contained entries for each of the 39
instances described in the first alleged violation.
Special Condition (5)(B) of Mt. Hope’s permit to construct
an afterburner provides at page 5, in pertinent part, that:
“A log containing an entry for each delivery of
contaminated soil ta the focility must be maintained.
Within 30 days of the end of each calendar quarter,
a copy of the log must be submitted to the NYSDEC
... Each log entry must include the following items:
ae
.
NYSDEC spill number, and name of involved
individual from NYSDEC oil spill response team;
2. Location of spill site;
3. Quantity of soil to be removed;
4. Type of fuel contaminating the soil;
5. Source and method of contamination;
6. Name and address of facility where spill occurred;
7. Total percent hydrocarbons;
8. Copy of sample analysis;
9. Shipping papers showing the following items...
(emphasis added).
Special Condition (5)(E) of Mt. Hope’s permit to construct
an afterburner provides at page 5, in pertinent part, that all
records required by the permit must be kept on-site at the facility
and must be available for inspection by Staff.
67a
Appendix C
During the hearing, for purposes of clarification, the parties
referred to the handwritten logs maintained at Mt. Hope’s
facility as the “log books” and referred to the quarterly log
submittals required to be filed with Staff as the “quarterly
reports”. However, under Special Permit condition (5)(B), the
identical information kept in Respondent Mt. Hope’s log book
was required to be submitted to Department Staff in the
quarterly reports. Thus, this permit condition sets forth the
requirement that all information being maintained by
Respondent Mt. Hope in its log book was to be submitted at
quarterly intervals to Department Staff as Respondent Mt.
Hope’s quarterly report for that time period.
Mt. Hope’s logbooks for the time period at issue were
required to be reported to Staff during three calendar quarters.
Exhibits 212 A, B and C, are the quarterly reports submitted
by Respondents to Staff (August 15, 1991 to March 31, 1992;
April 1, 1992 to June 30, 1992; and July 1, 1992 to September
30, 1992, respectively). These quarterly reports do not contain
any entries indicating that Mt. Hope received and processed
petroleum-contaminated soil from New Jersey on 36 occasions
between November 1991 and September 1992. However, Mt.
Hope’s log books do contain those New Jersey entries. Exhibits
84 and 86. Therefore, although Respondent Mt. Hope was
required to submit quarterly reports to the Department
indicating all petroleum-contaminated soil deliveries to the
facility, Mt. Hope excluded the 36 New Jersey entries from its
submittals in violation of Special Condition (5) (B) of the Permit
to Construct (and consequently, 6 NYCRR §201.2[d]).
Respondents assert that Robert Becherer specifically
instructed Mt. Hope not to file many documents required under
the Permit to Construct, including the quarterly reports, because
68a
Appendix C
documents submitted were too voluminous. However, the
record shows that Becherer instructed Respondents not to file
copies of sample analyses and shipping papers, required by
Special Permit condition (5)(B)(8) and (9).
Regarding Special Condition (5)(E), Staff has failed to
show that all documents were not maintained on-site and
available for Staff inspection. In fact, the record is quite clear
that on a number of occasions, Murphy inspected the logbooks
and viewed pages indicating receipt of petroleum-contaminated
soil from New Jersey sites.
Concededly, special Permit Condition (5)(B) does not
distinguish between the iog required to be maintained at the
facility pursuant to Special Permit Conditions (5)(B) and (E) ,
and documents required to be submitted with the log under
Special Condition (5)(B)(8) and (9). Still, the record does not
establish that Becherer instructed Respondents not to file
quarterly reports, required by Special Permit Condition (5)(B).
Instead, Becherer instructed Respondents that copies of certain
supporting documentation required to be filed with the quarterly
report — i.e., copies of sample analyses and shipping papers
— need not be submitted because that documentation became
too voluminous”.
15. Nonetheless, even with respect to sample analyses and shipping
papers, if Respondents intended to rely upon Becherer’s instructions in
contradiction to Special Permit Condition (5)(B)(8) and (9), Respondents
should have sought a permit modification to omit. the filing requirements
of Condition (5)(B)(8) and (9).
69a
Appendix C
B. The Charge of Violation of ECL Article 27 and 6 NYCRR
Part 360
1. Alleged violation of ECL 527-0707 and 6 NYCRR 360-
BE
Staff's Alternative Theory of Liability
Staff asserts that Respondents violated ECL §27-0707 and
6 NYCRR 360-1.7, by operating a solid waste management
facility (“SWMF”) without a permit, by receipt and/or
processing and/or disposal of contaminated soil from New
Jersey on the above referenced 39 occasions.
The First Ruling on pre-trial motions, dated June 22, 1994,
held:
A BUD is a determination by Staff that a particular
waste stream or product made from a waste stream
is a beneficial use of that waste. National Tire
Compaction Service, Inc. (Commissioner Decision,
June 18, 1993... ). A BUD is not a permit but
instead is a determination by Staff which essentially
exempts or excepts the activities or processes
constituting the beneficial use from the 6 NYCRR
360 solid waste permit requirements. Therefore it
is logically inconsistent that a violation of Part 360
(or any other Departmental regulation) would affect
the determination of beneficial use. As such, the
BUD itself cannot be violated.
The First Ruling directed Staff to amend its theory of
liability in Complaint §C, consistent with the above ruling. In
70a
Appendix C
its amended cause of action (Complaint §C), Staff alleges
alternative theories of liability, thereby preserving its original
theory of liability for review by the Commissioner. Staff relies
upon the precedent Jn the Matter of Carlson Associates, et al.
(Commissioner’s Decision, September 1, 1993) in asserting its
pleading in the alternative. Accordingly, Staff asserts that these
activities were in violation of the Beneficial Use Determination
(“BUD”) issued to Respondent Mt. Hope on August 9, 1991
(Staff's original theory of liability, asserting that Respondents
violated the BUD); or alternatively, that Respondents violated
ECL §27-0707 and 6 NYCRR 360-1.7, because the BUD did
not contemplate receipt and/or processing and/or disposal of
any material that Respondents received from August 7, 1991
to September 15, 1993 (Staff's amended theory of liability,
pursuant to the First Ruling, that Respondents’ activities were
outside the authority of the BUD and, therefore, constituted
operation of a solid waste management facility without a
permit).
Respondents contend that the only difference between the
two alternative pleadings, is that in the latter alternative Staff
alleges that a continuing violation occurred as a result of
Respondent Mt: Hope’s receipt of soil from New Jersey.
Respondents assert that Staff's theory in alleging a continuing
violation is in error, and that Carlson Associates is not
applicable to the present action, but is only applicable with
regard to jurisdictional penalty amounts under Article 23 of
the ECL. Respondents further assert that there is no similarity
in the regulatory penalty scheme between Article 23 and Article
27 of the ECL.
Respondents correctly assert that Carlson Associates is not
a precedent regarding computation of penalty. Still, the
Tla
Appendix C
provisions of ECL Article 71 are relevant and do provide fora |
continuing violation of ECL Article 27. ECL §71-2703(l).
Therefore, Staff may properly assert a continuing violation of
Article 27. Staff has asserted a continuing violation of ECL
§27-0707 and 6 NYCRR 360-1.7, for operating a solid waste
management facility without a permit from November 17, 1991
(the first date of receipt of soil from a New Jersey site) to
September 17, 1992 (the last date of receipt of soil from a New
Jersey site).
6 NYCRR §360-1.2(a)(4)(vii) in effect during the period
of time at issue states:
“(4) The iollowing are not solid waste for the
purposes of this Part:
(vii) materials that the department has determined
are being beneficially used, including the following:
(a) materials that are incorporated into a
manufacturing process to produce a marketable
product...”
By letter dated August 9, 1991 Respondent Mt. Hope
received a Beneficial Use Determination (“BUD”) from
Department Staff. This letter is also the cover letter to
Respondent Mt. Hope’s Permit to Construct EP2. The letter
specifically refers to the enclosed Permit to Construct EP2, in
two numbered paragraphs. Pursuant to numbered paragraph (1)
of the letter, “[a]ll operations will be conducted in accordance
with 6 NYCRR Parts ... 201, ...” This language makes
72a
Appendix C
compliance with requirements of 6 NYCRR §201.2(d) a
necessary condition of the beneficial use determination.
6 NYCRR §201.2(d) required Respondents to comply with
all conditions of Mt. Hope’s Permit to Construct EP2.
Therefore, compliance with the Permit to Construct was a
condition upon which the Beneficial Use Determination was
made. Respondents’ receipt, storage and processing of
petroleum-contaminated soil from sites in New Jersey was not
authorized by the Permit to Construct EP2, and consequently,
was not within the scope of authority of the Beneficial Use
Determination made by Department Staff.
Numbered paragraph (2) of the August 9, 1991 cover letter
also requires Respondents to comply with the conditions of the
attached Permit to Construct EP2:
“The contaminated soils will be tested and shown
not to be hazardous wastes under all federal and New
York State definitions. This will be done pursuant
to special conditions of the Air Permit.”
(emphasis added).
The one Special Condition section of the permit that
discusses testing of petroleum-contaminated soil is Special
Condition Section 4. Special Condition (4)(B) requires that
“fo}nly contaminated soil from sites identified by a NYSDEC
assigned spill number shall be processed at the facility.”
Therefore, when Respondent Mt. Hope accepted and processed
petroleum-contaminated soil from sites in New Jersey,
Respondent Mt. Hope was in violation of Special Condition
(4)(B) and consequently, was engaging in activities beyond the
scope of authority of the BUD.
73a
Appendix C
A solid waste management facility is defined as any facility
employed beyond the initial solid waste collection process and
managing solid waste. 6 NYCRR §360-1.2(b) (145). Solid waste
is defined as all putrescible and nonputrescible materials or
substances that are discarded or rejected [except as described
in paragraph (4) of that subdivision]. 6 NYCRR §360-1.2(a)
(1) material is discarded if it is abandoned by being disposed
of. 6 NYCRR §36-1.2[a][2][i]. A material is disposed of if it is
discharged, deposited, injected, dumped, spilled, leaked or
placed into or on any land or water so that such material or any
constituent thereof may enter the environment or be emitted
into the air or discharged into groundwater or surface water.
6 NYCRR §360-1.2(a)(3). Petroleum-contaminated soil is a
solid waste because petroleum product has been discharged into
land to form the petroleum-contaminated soil.
As discussed above, Respondent Mt. Hope did not have
authority under the BUD for its receipt, storage, processing or
disposal of petroleum-contaminated soil from New Jersey sites.
These activities would otherwise require a permit issued
pursuant to ECL Article 27 and 6 NYCRR Part 360. Therefore,
Mt. Hope was required to have a Part 360 permit for those
activities.
Because Respondent Mt. Hope acted outside the scope of
authority of the BUD, Mt. Hope operated a solid waste
management facility without a permit, in violation of 6 NYCRR
§360-1.7(a)(1)(ii). Thus, Respondent Mt. Hope’s receipt (and
processing) of petroleum-contaminated soil from sites in the
State of New Jersey, absent a solid waste management facility
permit, constituted operation of a solid waste management
74a
Appendix C
facility without a permit, a continuing violation of 6 NYCRR
§360-1.7(a)(1)(ii), from November 17, 1991 to September 17,
1992.
The Generic Beneficial Use Determination
Respondents assert that on November 29, 1990, the
Department’s Director of the Division of Solid Waste issued a
generic Beneficial Use Determination for use of petroleum-
contaminated soil as an aggregate in asphalt production.
However, this document is an internal memorandum for intra-
agency purposes from the Division Director to the Department
Staff's Regional Solid Waste Engineers.
Although the subject of the memorandum is “Petroleum-
contaminated soil Beneficial Use Determinations”, the
memorandum explicitly states that, “we recommend that a
submittal be made to identify the project and to verify the
process details so as to give the Department an opportunity to
determine whether or not the activity conforms with the generic
beneficial use criteria or other Part 360 requirements.”
(emphasis added). This internal memorandum does not
constitute a generic beneficial use determination because by
its own terms, the memorandum requires a determination of
whether or not the activity conforms with the generic beneficial
use criteria identified in the memorandum.
In any event, even if Exhibit 8 were construed to be a
generic BUD applicable to Mt. Hope, criteria 3 requires
compliance with any other Departmental regulations, other than
6 NYCRR Part 360, which may apply. As discussed above,
Respondent Mt. Hope has not complied with 6 NYCRR™-
§201.2(d) and the terms of its Permit to Construct EP2.
75a
Appendix C
Therefore, Mt. Hope’s activities in receipt, storage and
processing of petroleum-contaminated soil from 36 New Jersey
sites, would be outside the scope of authority of the generic
BUD.
The Parish Testimony
Respondents assert that Staff failed to prove the soils
received from New Jersey were not non-hazardous, were not
tested by a New York State certified lab, or that these soils
differed in any way from soils received from the State of New
York.
The Parish testimony puts into question the validity of
certain documentation filed or maintained by Respondents
under Parish’s purported signature. Parish testified that he has
been employed as President of Impact Environmental for
approximately five years. In mid-1991, Impact Environmental
was retained as a consultant to Disposal Technologies. Impact
Environmental, in its consultant capacity to Disposal
Technologies, performed sampling on behalf of Mt. Hope, and
sent the samples to appropriate laboratories for analysis. Upon
receiving the analysis from the lab, the analysis would be
forwarded to Disposal Technologies under Parish’s cover letter.
However, Parish testified with respect to at least one such
packet of information, the analytical report (contained within
a cover letter dated December 31, 1991) addressed to Disposal
Technologies at the facility address contains what is purportedly
his signature. In fact, it is not his signature.
The documentation in Exhibit 170, including the report,
concerns material transported from the Ideal Aluminum site
76a
Appendix C
(“Ideal Aluminum”), 100 West 7th Street, Bayonne, New
Jersey, to Mt. Hope,’s facility. The reported information states,
“fbjased on our investigation of 12-24-91 the contaminated
material is nonhazardous pursuant to the standards promulgated
by the New York State Department of Environmental
Conservation. All informai:.n reported by the client was
confirmed by either Freedom of Information Legislation and/
or inspection.” Parish testified that the Ideal Aluminum
analytical report was not prepared by his office, Impact
Environmental. Because the report and signature are not
genuine, it is impossible to know whether the material described
in the analytical report was in fact non-hazardous.
The documentation comprising Exhibit 170 was maintained
at the facility offices by Mt. Hope or Disposal Technologies.
The falsified report is addressed from Richard Parish, Impact
Environmental, to Disposal Technologies, Inc. Further, the
report addresses materials received by Mt. Hope. Therefore, it
is reasonable to conclude that Mt. Hope or Disposal
_ Technologies, acting on Respondents’ behalf, prepared the false
report and falsified the Parish signature.
Respondents assert that Thomas Accardi/Disposal
Technologies acted independently in falsifying the Ideal
Aluminum analytical report. However, Respondents presented
no evidence to support this theory. In any event, Respondent
Mt. Hope is ultimately responsible for the false report and false
signature, as a matter of law, since either Mt. Hope or its agent
created the falsified document.
Staff asserts that based upon Parish’s testimony regarding
Exhibit 170, the veracity of analytical reports in evidence for
all 36 proven incidents must be questioned. Staff asserts that it
77a
Appendix C
is impossible to know whether the material described in each
report was in fact non-hazardous. However, Staff failed to
establish a record through Parish, or other witnesses, regarding
the authenticity of the other exhibits in Exhibit series 163
through 198.
Further, Staff stipulated that all of the analytical reports
for Exhibits 163 through 198, except for Exhibits 169, 171,
180 and 182, contained laboratory analyses which indicated
that all material was non-hazardous pursuant to the Quality
Assurance/Quality Cortcol (QA/QC) provisions of the Permit
to Construct EP2. Further, all the analyses were conducted by
a New York certified laboratory. With respect to Exhibits 169,
171, 180 and 182, Respondents asserted that the original reports
maintained at Mt. Hope’s offices had contained laboratory
analyses, but the copies received back from the District
Attorney’s office by Staff lacked copies of those analyses.
Therefore, except for the Ideal Aluminum analytical report
(Exhibit 170), the other 35 analytical reports and signatures
contained in Exhibits 163 through 198 are deemed to be
genuine, as represented in the respective exhibits, not falsified.
Regarding Exhibits 169, 171, 180 and 182, I credit Respondents’
assertion that the original reports maintained at Mt. Hope’s
offices contained laboratory analyses, but the copies Staff
obtained from the District Attorney’s office lacked copies of
those analyses.
In sum, with respect to the ECL Article 19 violations, when
Respondent Mt. Hope violated Special Conditions (4)(B) and
(5)(B) of the permit to construct the afterburner, it violated 6
NYCRR §201.2(d). Those activities — i.e., receipt of
petroleum-contaminated soil from New Jersey sites on 36
78a
Appendix C
occasions and failure to include those 36 occasions in three
quarterly reports to the Department — were beyond the scope
of authority of the BUD and required a SWMF permit.
C. Violation of Navigation Law Article 12, ECL Article 17
and 6 NYCRR Parts 360 and 613
Staff does not seek any monetary penalty for this
component of its Complaint, but instead seeks an order requiring
further investigation and remediation by Respondents.
Members of the Suffolk County Department of Health
Services, working with the office of the Suffolk County District
Attorney, obtained samples at the facility on September 16,
1993. Staff asserts that the samples and sample analysis show
that Respondents caused a discharge of petroleum through
illegal burial and stockpiling of petroleum-contaminated soil
at the facility, on or before September 16, 1993 and that, this
constitutes a continuing violation.
1. Alleged violation of Navigation Law §173 by causing
a discharge of petroleum at the Mt. Hope facility on or
before September 16, 1993, a continuing violation.
A petroleum “discharge” is defined very broadly under the
Navigation Law. Navigation Law (“NL”) §173 provides that
the discharge of petroleum is prohibited. NL §172(14) defines
petroleum as oil or petroleum of any kind and in any form. NL
§172(8) and 6 NYCRR §613.1(8) define a discharge as:
any intentional or unintentional action or omission
resulting in the releasing, spilling, leaking, pumping,
pouring, emitting, emptying or dumping of
79a
Appendix C
petroleum into the waters of the state or onto lands
front which it might flow or drain into said waters,
or into waters outside the jurisdiction of the state
when damage may result to the lands, waters or
natural resources within the jurisdiction of the state.
NL §175 provides that any person responsible for causing
a discharge shall immediately notify the Department pursuant
to the rules and regulations established by the department, but
in no case later than two hours after the discharge. Failure to
so notify shall make persons liable to the penalty provisions of
§192'.
Navigation Law §181(1) provides that any person who has
discharged petroleum shall be strictly liable, without regard to
fault, for all cleanup and removal costs and all direct and
indirect damages, no matter by whom sustained, as defined in
NL Article 12.
Respondents assert that the record does not support a
finding that groundwater under the facility has been impacted
or is threatened by Mt. Hope’s activities. Therefore,
Respondents conclude that Staff failed to meet its burden of
proof on this cause of action.
In applying the above statutory and regulatory definitions,
Staff need not prove that the petroleum constituents in the
petroleum-contaminated soil did, in fact, flow into the
groundwater. Merrill Transport Co. v. State of New York, 94
A.D.2d 39, 467 N.Y.S.2d 1030, appeal denied, 60 N.Y.2d 555,
16. NYCRR §613.8 further requires that: [A]ny person with
knowledge of a spill, leak or discharge of petroleum must report the
incident to the Department within two (2) hours of discovery .. .”
80a
Appendix C
467 N.Y.S.2d 1030 (while there is nothing in the record to
positively demonstrate that the spilled oil might have flowed
into protected waters, judicial notice can be taken of the
common knowledge that oil can seep through the ground into
surface and groundwater); See, Domermuth Petroleum
Equipment and Maintenance Corp. v. Herzog & Hopkins, Inc.,
111 A.D.2d 957, 490 N.Y.S.2d 54 (3d Dept. 1985) (there is no
need for specific proof that the oil was ever in danger of seeping
into protected water in order to render the above statutes
applicable (referring to NL §§172 and 181)); See, also, Bri-
Mar Corp. v. Town Bd. of Town of Knox, 145 A.D.2d 704, 534
N.Y.S.2d 831 (3d Dept. 1988) (the court distinguishes its
decision in Merrill Transport from its decision in State of New
York v. Schenectady Chemicals, 103 A.D.2d 33, 479 N.Y.S.2d
1010).
Respondents assert that for Staff to sustain their burden of
proof under the Navigation Law claim, Staff must prove by a
preponderance of the evidence that petroleum was, in fact,
discharged; that Mt. Hope was responsible for this discharge;
that Mt. Hope did not have a permit which authorized the
alleged discharge; and that the petroleum was not in a controlled
state in the environment and, therefore, had potential to seep
through the ground into surface and ground water. See, Jn the
Matter of Peterson Petroleum, Inc. (Commissioner’s Decision,
May 25, 1994); See, also, In the Matter of Max Kent
(Commissioner’s Decision, December 7, 1992). The parties’
arguments are examined further below.
The Soil Samples
The SCDOHS collected many samples from the facility
on September 16, 1993. Five of those samples at issue in this
8la
Appendix C
proceeding are identified in the record as 6MF, 7MF, 18MF,
20MF and 21MF, Exhibit 207(a) through (e). Analytical results
of the five samples obtained by SCDOHS at the facility show
high levels of petroleum constituents in certain locations. Staff
asserts that the anaiytical results are accurate and reliable and
should be relied upon as establishing petroleum contamination
in locations at the facility identified by the sampling results.
Respondent Mt. Hope asserts that Staff relies completely
upon the samples and tests conducted by SCDOHS on those
samples. Mt. Hope further asserts that the testimony of Olin
Braids and testimony of Staff witnesses, supports a finding that
no remediation is required. Respondent Mt. Hope asserts that
evidence did not establish that petroleum was discharged.
Respondent Mt. Hope relies upon three factors in support
of this position. First, Mt. Hope relies upon Braids’ opinion
that no definitive tests had been conducted to determine that
there was any potential hazard to groundwater by contamination
at the site. Secondly, Mt. Hope points to Braids’ opinion that
no contamination of the water table had occurred at the facility,
based upon his review of monitoring well data. Lastly,
Respondents assert that Braids’ testimony was not controverted
by any witness presented by Staff. Respondents’ arguments are
addressed more specifically below.
-Sampling Methodology
Respondent Mt. Hope’s challenges to sampling
methodology are invalid, and must be rejected. For example,
Mt. Hope’s assertion that improper sampling methodology was
used which could have permitted particles of asphalt to taint
samples, is speculative; Mt. Hope’s assertion that samples were
82a
Appendix C
maintained at warmer temperatures than required by sampling
methodology would, if anything, result in greater violation of
the samples and, therefore, a false-negative test result.
Additionally, the SCDOHS tock many precautions to
ensure proper sampling methodology was followed during the
sampling collection process. A new bottle was used to collect
each sample; the SCDOHS Sanitarian actually collecting the
sample(s) wore two pair ef gloves, and replaced the outer gloves
after completing samrie collection at each sample point; the
back-hoe used to <xcavate sampling points was cleaned for
decontaminauon at each sample point; and one of the two
SCDOHS laboratory personnel were in physical custody of the
samples, stored in a cooler, the entire day. Many photographs
were taken to document the location of each sample point.
-Sampling Analysis
Respondent Mt. Hope also asserts that SCDOHS
Laboratory staff varied methodology from standard EPA
sampling analysis methodology, thereby invalidating practical
quantification limits established for the standard tests.
Respondent Mt. Hope asserts that variations from the EPA
methodology render the test results suspect and not capable of
confirmation. The lengthy, detailed EPA methodology includes
use of a packed column, internal calibration and heating the
sample to 40 degrees centigrade. However, SCDOHS Chemist
Amendola employed three variations from the EPA 8240
methodology when analyzing the samples. He used a capillary
column, as opposed to a packed column; he calculated the
analysis using external calibration instead of internal
calibration; and lastly, he did not heat the samples to 40 degrees
centigrade.
83a
Appendix C
Nonetheless, Amendola concluded that the results of his
analysis are accurate and reliable. He testified that the variation
of use of a capillary column, as opposed to a packed variation
column under the EPA 8240 methodology, is an acceptable
practice, and in fact, was specifically approved by the New
York State Department of Health as an acceptable variation
from the EPA recommended methodology.
Regarding the calibration variation from EPA 8240
methodology, Amendola subsequently re-calculated the
analysis of four of the five samples at issue using internal
calibration. The four sample analyses re-computed using
internal calibration resulted in a higher level of petroleum
constituents, than did the external calibration results.
Lastly, heating the samples to 40 degrees centigrade, would
have produced greater violation and would have yielded a
slightly higher result than was obtained absent heating of the
samples. In conclusion, all, three variations to the 8240 EPA
methodology met with quality control standards of the New
York State Department of Health, and would, if anything, result
in a false low test result indicating a lesser presence of
petroleum constituents.
-Chain of Custody
Respondents’ claim that SCDOHS failed to maintain an
adequate chain of custody for the five samples. In this case,
Staff offers SCDOHS laboratory analysis of real evidence, the
five soil samples at issue. The evidentiary issue of chain of
custody requires that Staff demonstrate that SCDOHS
accounted for the custody of the evidence from the moment
84a
Appendix C
SCDOHS personnel obtained the evidence until the moment
SCDOHS perscinel analyzed the evidence. Such evidence goes
to weight of evidence and not to admissibility of evidence. See,
generally, People v Julian, 41 NY2d 340, 360 NE2d 1310
(1977).
Once a SCDOHS Sanitarian obtained a sample, it was
placed in a sample bottle. The Sanitarian sealed the sample
bottle and cleaned the exterior, if necessary. The Sanitarian
then handed the sample directly to SCDOHS laboratory
personnel present, at the facility. The laboratory personnel
received the samples from the Sanitarians. One of the two
SCDOHS laboratory personnel were in physical custody of the
samples, preserved in a cooler, during the entire day of sample
collection.
After sample collection was completed at the site, the two
SCDOHS laboratory personnel brought the sample cooler to
the SCDOHS van, where they performed a final count of
collected samples. Then the laboratory personnel transported
the sample cooler, with samples, to the SCDOHS laboratory.
The laboratory documented receipt of the samples by
entries in a SCDOHS laboratory logbook. Each sample was
assigned a laboratory number, sealed in plastic and kept in a
locked refrigerator, located in a locked “evidence room” at the
laboratory. Finally, SCDOHS personnel completed “Chain of
Custody” forms detailing exactly who had custody of the
samples throughout the day.
Staff has demonstrated that an adequate chain of custody
was maintained for the five samples at issue. Respondents’
challenge to chain of custody is therefore rejected.
85a
Appendix C
-Other Challenges to Sampling and Analysis
Respondents assert that rainfall could have tainted the
sampling results, due to run-off contamination from the asphalt
parking lot. However, SCDOHS Sanitarian Feindt provided
opinion testimony that the rain had no impact on the soil that
was being sampled.
Respondents also assert that SCDOHS laboratory personnel
did not know the constituents of asphalt product and, therefore,
could not know if their test results indicated asphalt
contamination of samples or presence of petroleum
contamination. However, this contention assumes possible
asphalt contamination. Feindt testified that she observed a little
bit of asphalt falling into the excavations, but said specifically
that she is certain that no asphalt particles were collected in
the sample bottles. She further stated that the rain was not so
strong as to dislodge any particles and transport them into the
excavations. She saw no soil being washed away by the rain;
she saw no erosion; and the excavations were exposed only for
a short time, while the actual sampling took place. Respondents’
speculative contentions must be rejected in light of the detailed
sampling process described in the record, as elaborated upon
by the Feindt testimony.
Lastly, some sample test results are stamped “Some
surrogate standard values are below acceptable levels”.
Respondents assert this language indicates that the SCDOHS
laboratory failed to recover control elements placed into the
samples during the laboratory sample analyses, and therefore
the laboratory cannot ensure that the test results are accurate.
However, Amendola explained that the stamp means that the
surrogate (control element) level was under-reported by the
86a
Appendix C
sample analysis methodology, and therefore the analysis result
probably under-reported the presence of those substances which
the analysis was intended to identify. In sum, the stamped
language on a sample analysis result indicates that the result
obtained by the laboratory are an under-representation of the
actual contamination level in the sample. This sample analysis
indicating presence of petroleum constituents in the soil samples
was confirmed by another test performed on these samples by
SCDOHS. Total Petroleum analysis also indicated presence of
petroleum constituents in the soil samples.
The Allegation of Petroleum Discharge
Respondents deny that any petroleum discharge occurred
at the facility. However, since Mt. Hope has been operating
the facility for production of hot asphalt for approximately 22
years, and that production process requires use of petroleum
products, it is more likely than not that the discharge occurred
during Mt. Hope’s tenure at the site. This ongoing discharge of
petroleum constitutes a continuing violation of NL §173 since
at least September 16, 1993 to the present. See, Domermuth
Petroleum Equipment and Maintenance Corp. v. Herzog &
Hopkins, 111 A.D.2d 957, 490 N.Y.S.2d 54 (3d Dept. 1985)
[under the Navigation Law, no proof is required for a specific
wrongful act or omission which directly caused the spill in order
to impose liability.)
The fact that the discharge may have been petroleum-
contaminated soil as opposed to liquid petroleum does not alter
the conclusion that analysis of the five SCDOHS samples
demonstrates a petroleum discharge occurred at some time prior
to the date of sample collection, Exhibits 207(a) through (e);
Domermuth, supra.
87a
Appendix C
However, Staff asserts that the record sustains a conclusion
that Respondent Mt. Hope took specific acts causing the
discharge because they paved what is referred to in the record
as the “parking lot area”. This is an area of the facility that had
been used by Mt. Hope to store mounds of raw material, possibly
concrete and/or asphalt from excavated roadways, and was
subsequently paved to create the “parking lot area”. The record
is not clear as to whether the concrete or asphalt was removed
before the parking area was created. Nor is the record clear
whether even if Mt. Hope paved over material it had deposited
previously, such material was petroleum-contaminated soil or
was some other liquid or solid petroleum product.
In any event, in my view of the record, Staff's contention
that Respondents took specific intentional or deliberate acts
causing the discharge can not be sustained. Staff's contention
that Respondents intentionally discharged petroleum, or even
that Respondents were aware of a petroleum discharge at the
facility, is unsupported in the record and must be rejected.
Nonetheless, I find Respondent Mt. Hope liable-for the spill,
and therefore responsible for further investigation and
remediation of the facility.
88a
Appendix C
2. Alleged violation of ECL §17-0501(1) in that the
SCDOHS sample results indicate a petroleum discharge
at Respondent Mt. Hope’s facility.
ECL §17-0501(1) states:
It shall be unlawful for any person, directly or
indirectly, to throw, drain, run or otherwise
discharge into such waters organic or inorganic
matter that shall cause or contribute to a condition
in contravention of the standards adopted by the
department pursuant to section 17-0301.
Respondent Mt. Hope asserts that to establish a violation
under ECL §17-0501(1), the Department must show that
(1) there was a discharge of organic or inorganic matter in
waters of the state, (2) Respondent Mt. Hope was responsible
for the discharge, (3) the discharged petroleum migrated into
the groundwater, and (4) that this discharge caused or
contributed to a condition in contravention of the standards
adopted by the Department pursuant to §17-0301. See, Peterson
Petroleum, Inc., supra, at 9, Max Kent, supra.
Respondent Mt. Hope further asserts that there was no
evidence submitted by Staff of any testing of groundwater which
showed a contravention of Departmental water quality
standards.
Based upon the SCDOHS soil sample analyses, Siaff has
shown by a preponderance of the evidence that a discharge
occurred at the facility, and Mt. Hope was responsible for that
discharge. However, Respondent has correctly identified the
elements of a violation of ECL §17-0501(1). Staff has not
89a
Appendix C
established that the discharged petroleum migrated into the
groundwater or that the discharge caused or contributed to a
condition in contravention of the standards adopted by the
Department pursuant to §17-0301. Peterson Petroleum, Inc.,
supra, Max Kent, supra.
3. Alleged violation of Navigation Law §175 and
6 NYCRR §613.8, which requires that any person who
causes a discharge immediately notify the Department.
Staff asserts Respondents violated NL §175 and 6 NYCRR
§613.8 by failing to report the discharge to the Department.
Initially, Respondent Mt. Hope asserts that 6 NYCRR Part
613, by its very terms, applies only to petroleum storage
facilities with a combined storage capacity of over 1,100 gallons
and facilities licensed under Article 12 of the Navigation Law.
6 NYCRR §613.1(b). Mt. Hope asserts no proof has been
submitted by Staff to demonstrate the facility falls within the
applicability of Part 613. Respondent concludes that based upon
the allegations in the Complaint, 6 NYCRR §613.8 is irrelevant
to the present proceeding because the Mt. Hope facility is not a
petroleum storage facility with a combined storage capacity of
over 1,100 gallons or a facility licensed under Article 12 of the
Navigation Law.
I find that 6 NYCRR Part 613 is not applicable to the instant
action, for reasons cited by Respondent Mt. Hope. However, I
find that Navigation Law Article 12 is applicable. See, NL
§§172(8), 173, 172(14), 175 and 181, discussed above.
Following is a discussion of the Navigation Law cause of action.
90a
Appendix C
Staff relies upon Karen Gomez’s testimony to show that
Respondent Mt. Hope never reported the petroleum discharge
to the Department. Further, Staff asserts that once Staff learned
of the petroleum discharge through its review of the SCDOHS
sample analyses, Karen Gomez prepared a spill report and
obtained a spill number from the Department’s spill hotline.
Staff asserts that Respondents’ failure to report the spill to the
Department constitutes violation of NL §175, because
Respondents were responsible for causing a discharge and failed
to notify the Department.
Respondent Mt. Hope asserts there is no credible proof
that a discharge of petroleum requiring reporting occurred at
the facility. Therefore, Mt. Hope asserts it was under no
obligation to report any discharge to the Department.
Respondent points out that Gomez was presented with a portion
of the SCDOHS soil sample analysis results in or about June,
1994. Further, that although Gomez’s June 17, 1994
memorandum to Regional Director Cowen'’ recommended
remediation of the facility, Gomez did not file a spill report
with the Department’s Central Office, Albany, New York, until
the end of August, 1994. Respondent Mt. Hope asserts that
Gomez reported a spill then, only after receiving specific
instructions to do so from the NYSDEC Region 1 Regional
Director. In sum, Mt. Hope concludes it never knew that a
discharge requiring reporting had occurred, and that in any
event, Gomez (and by implication, Staff) did not treat the
SCDOHS sample analysis results as a high priority.
Since this cause of action is limited to a request for remedial
investigation and remediation only, a determination on the
17. Exhibit 290
9la
Appendix C
allegation of failure to report a discharge is of collateral
importance. Navigation Law §173 prohibits discharge of
petroleum. The SCDOHS sample analysis results for the five
samples at issue demonstrates presence of petroleum product
in the ground at the facility. Therefore, it is reasonable to
conclude that a discharge occurrid at some time prior to
sampling, thereby causing the presence of petroleum product
in the soil. Since Respondent Mt. Hope has operated the facility
for the production of virgin hoi asphalt for more than 22 years,
Respondent Mt. Hope is reasonably responsible for that
discharge. Pursuant to Navigation Law §181(1), Respondent
Mt. Hope is strictly liable for all cleanup and removal costs
associated with the petroleum discharge. -
However, the record before me does not establish how or
when the discharge occurred; or whether the discharge was
liquid petroleum, leachate from contaminated soil, burial of
contaminated soil or some other discharge of petroleum". Staff
asserts that SCDOHS concluded that petroleum-contaminated
soil was buried at the facility, and that Respondents buried the
contaminated soil. However, the testimony of the SCDOHS
witnesses provides no opinion as to what quantity of petroleum
product is present at the facility, how widespread the discharge
is, or the likelihood of how the levels of petroleum identified
in the five samples came to be present in the facility’s soil.
Thus, Staff's assertion that Respondents buried petroleum-
contaminated soil at the facility, must be rejected. Nonetheless,
since a petroleum discharge has been proven, Respondent Mt.
Hope should be directed to perform a remedial investigation
and remediation of the facility.
18. Pursuant to NL §172(14), petroleum is defined as oil, or
petroleum of any kind and in any form.
92a
Appendix C
Lastly, since Staff has failed to prove how or when the
discharge occurred, it would be anomalous to impose any
penalty upon Respondents for failure to report the discharge.
In any event, the reporting allegation, if it had been proven,
would not result in a monetary penalty because Staff seeks no
monetary penalty on this cause of action. Instead, the reporting
violation would have been another factor to be considered, in
the permit aspect of this consolidated action.
D. RESPONDENT FRANK PETROSKY
Staff seeks to impose liability upon Respondent Frank
Petrosky in both his individual and corporate capacities.
Respondents admit Frank Petrosky was President of Respondent
Mt. Hope at all times at issue. However, Respondent Petrosky
asserts that Staff failed to establish that Petrosky was
individually liable for any violation alleged in Staff’s
Complaint. Further, Respondent Petrosky asserts that Staff
failed to prove he was involved in the day-to-day activities of
the facility.
It is well established that a corporate officer may be held
criminally liable for violations of statutes enacted to protect
the public health, safety and welfare, where that officer had
the authority and responsibility to prevent the violation (United
States v. Park, 95 S.Ct. 1903 (1975); United States v.
Dotterweich, 65 S.Ct 134 (1943)). The rationale for holding
corporate officers criminally responsible is more persuasive
where only civil liability is involved (United States v. Hodges
X-Ray, Inc., 759 F.2d 557 (CA 6th Cir, 1985)). The record
demonstrates that Respondent Frank Petrosky held such a
position of authority and responsibility with respect to corporate
Respondent, Mt. Hope Asphalt Corp. (See, Ronald Edgar,
93a
Appendix C
Productive Recycling, Inc., and Productive Recycling Corp.,
Commissioner’s Order, June 18, 1993).
With respect to Petrosky’s role as day-to-day manager of
Mt. Hope, Petrosky regularly held himself out to Staff as the
individual to be contacted in matters involving Mt. Hope
Asphalt Corp. Petrosky maintained an office at Mt. Hope’s
offices located at the facility, he was regularly on-site and he
regularly met with Department personnel, both at the
Department’s Regional office and during Staff's site visits to
the Mt. Hope facility. In fact, the record shows that Petrosky
regularly responded to Staff's concerns, and that Staff contact
with Mt. Hope in all matters regarding the facility, was almost
exclusively directed to Respondent Petrosky. For example, it
was Petrosky that responded to Staff's concerns about dust at
the facility by having the road between the offices and the
facility paved. #
In addition to these indications of Petrosky’s role managing
the day-to-day activities of the facility, he also certified the
Mt. Hope documents stating that the petroleum-contaminated
soil indicated therein was recycled and made into road paving
materials. Exhibits 194, 195 and 198. Lastly, Respondent
Petrosky regularly attended meetings with Department Staff at
the Department’s Region 1 Offices and the Mt. Hope Asphalt
Corp. facility, on behalf of Mt. Hope. In terms of contact
between Staff and Mt. Hope, Petrosky was virtually the
exclusive representative of Mt. Hope, on matters of daily
functioning of the facility and on other matters.
As President and day-to-day manager of Mt. Hope Asphalt
Corp., Frank Petrosky was a high managerial agent of
Respondent Mt. Hope, and was in a position to prevent the
94a
Appendix C
corporate violations that occurred regarding receipt of
contaminated soil from New Jersey sites. Therefore, Respondent
Frank Petrosky is individually liable for the violations of the
corporation. (See, U.S. Pollution Abatement Services of Oswego
Inc., 763 F.2d 133 (1985); Avory L. Clark v. Pinehill Homes,
112 A.D.2d 755 (4th Dept. 1985); Jn the Matter of Jackson's
Marina, Inc., Gordon Jackson, James H. Rambo, Inc. and
Thomas Samuels, (Commissioner’s order, November 6, 1991).
RELIEF
I. CIVIL PENALTIES
ECL §71-2703(1) provides for a maximum civil penalty in
the amount of Two Thousand Five Hundred ($2,500.00) Dollars
for each violation of ECL Article 27, Title 7, or rules or
regulations issued pursuant thereto, and an additional penalty
of not more than One Thousand ($1,000.00) Dollars for each
day during which such violation continues.
F’ .L §71-1929 provides that any person who violates any
of the provisions of, or who fails to perform any duty imposed
by Titles 1 through 11 inclusive and Title 19 of ECL Article
17, or regulations promulgated pursuant thereto, shall be liable
to a penalty of not to exceed twenty-five thousand dollars per
day for each violation. 6 NYCRR Part 613 was promulgated
pursuant to ECL §§17-0303(3) and 17-1001, et seg. Therefore,
the maximum monetary penalty for a violation of failure to
report a petroleum spill to the Department, is $25,000 through
either the NL as explained below, or through the penalty
provision in ECL §17-1929.
95a
Appendix C
Pursuant to ECL §71-2103(1), except as provided in §71-
2113, any person who violates any provision of ECL Article
19 or any code, rule or regulation which was promulgated
pursuant thereto, shall be liable in the case of a first violation
for a penalty not less that $250.00 nor more than $10,000.00
for said violation, and an additional penalty not to exceed
$500.00 dollars for each day during which such violation
continues. (ECL §71-2103 [eff. November 1, 1984 through
August 3, 1993]; current ECL §71-2103 increases the maximum
daily penalty from $500.00 to $10,000.00, and sets both the
maximum penalty for subsequent violations and the additional
maximum daily penalty for a continuing violation at $15,000.00
[eff. August 4, 1993}).
Navigation Law §181(1) provides that any person who has
discharged petroleum shall be strictly liable, without regard to
fault, for all cleanup and removal costs and all direct and
indirect damages, no matter by whom sustained, as defined in
NL Article 12.
NL §192 provides that any person who violates any of the
provisions of NL Article 12 or any rule promulgated thereunder
or who fails to comply with any duty created by Article 12,
shall be liable to a penalty of not more than twenty-five thousand
dollars of each offense in a court of competent jurisdiction. If
the violation is of a continuing nature each day during which it
continues shall constitute an additional, separate and distinct
offense.
The Commissioner’s Civil Penalty Policy (Enforcement
Directives, No. II, issued 6/20/90) states that undertaking any
action which requires a Departmental permit, without first
obtaining that permit, is always a serious matter, not a mere
96a
Appendix C
technical or paperwork violation, even if the activity is
otherwise in compliance. (Civil Penalty Policy, page 8).
Staff has computed a maximum monetary penalty in excess
of $14,000,000.00, and seeks a monetary penalty in excess of
$1,000,000.00 in its Complaint. In its closing brief, Staff has
modified its request for relief, seeking in excess of
$1,000,000.00 from each Respondent, $327,000.00 of which is
sought to be imposed by joint and several liability upon
Respondents.
A. The Charge of Violation of ECL Article 19 and 6 NYCRR
Part 201
1. Respondents violated ECL Article 19,6 NYCRR §201.2(d)
and Permit to Construct (EP2, the afterburner), Special Permit
Condition #4.B., by Respondents’ receipt and/or processing on
36 occasions, of contaminated soil from sites located in the
State of New Jersey which did not have a NYSDEC-assigned
spill number. Staff has summarized these 36 violations in a
chart in their closing brief (Hearing Report Appendix B). Staff
has proven 36 of 39 allegations set forth in their Complaint
(the three unproven allegations are the sixth, eighth and twelfth
occasions alleged in their Complaint; see Appendix A).
For these violations, Staff seeks a maximum monetary
penalty of $10,000.00 per occasion, a maximum total penalty
of $360,000.00. However, I recommend a substantially reduced
penalty level because although Respondents are ultimately
liable for these violations, in 35 of the 36 occasions proven,
Respondents received material of the kind and quality
authorized to be processed at the facility, but for the fact that
the material originated in New Jersey, rather than New York. I
97a
Appendix C
find these violations to be de minimis with respect to the 35
occasions other than the Ideal Aluminum violation (i.e., Ex.
170). Therefore, I recommend a penalty of $100.00 for each of
the 35 violations. With respect to the Ideal Aluminum violation,
since that analytical report and signature were falsified, I
recommend a maximum penalty of $10,000.00, a total monetary
penalty on this cause of action, of $13,500.00.
2. Staff has proven Violation of ECL Article 19, and 6 NYCRR
§201.2(d) and Permit to Construct (EP2), Special Permit
Conditions (5)(B) and (5)(E), by failure to submit to the
Department on a quarterly basis, logs which contained entries
for 36 of the 39 instances described in the first alleged violation.
The Second Ruling (dated July 12, 1994) limited Staff's cause
of action on to reporting violations alleged to have occurred
after May 8, 1992 (the most recent time period addressed by a
January 13, 1993 Consent Order).
Staff seeks a maximum monetary penalty of $10,000.00
per occasion of unreported receipt, a maximum total penalty
of $360,000.00; or, in the alternative, pursuant to the limiting
Second Ruling, Staff seeks the maximum penalty for ten
occasions of non-reporting that occurred es or, after May 8,
1992, a maximum total penalty of $100,000.00.
I adopt Staff's alternative penalty analysis on this cause of
action, because as indicated in the Second Ruling, the regulatory
and statutory authority cited in the January 14, 1993 Consent
order reporting violations (Consent Order, #1-5074-92-06) and
in Complaint paragraph B7 are the same. Therefore, res judicata
bars relitigation of the reporting cause of action alleged in
Complaint paragraph B7, for the same time period addressed
in the Consent Order. Accordingly, I limited Staff's cause of
98a
Appendix C
action in Complaint paragraph B7, to address only those
reporting violations alleged to have occurred after May 8, 1992
(i.e., the most recent time period addressed by the Consent
Order).
However, in assessing this penalty, I find that Respondents
violated the reporting requirement for three quarterly reports
(Exhibits 212, A, B and C), and that the pattern and number of
reporting omissions in the quarterly reports are aggravating
factors in penalty assessment. Since Respondents repeatedly
omitted reporting of New Jersey sites in the three quarterly
reports, Respondents Mt. Hope and Petrosky should be held
jointly and severally liable for the maximum penalty for the
three occasions of incomplete quarterly reports submitted on
or after May 8, 1992, a total penalty of $30,000.00 on this cause
of action.
B. The Charge of Violation of ECL Article 27 and 6 NYCRR
Part 360
Staff alleges that Respondents violated ECL §27-0707 and
6 NYCRR 360-1.7, by operating a solid waste management
facility (“SWMF”) without a permit, ‘by receipt and/or
processing and/or disposal of contaminated soil on the above
referenced 36 occasions in a manner not consistent with the
Beneficial Use Determination (“BUD”) issued to Respondent
Mt. Hope on August 9, 1991; or alternatively, Respondents
violated ECL §27-0707 and 6 NYCRR 360-1.7, because the
BUD did not contemplate receipt and/or processing and/or
disposal of any material that Respondents received from August
7, 1991 to September 15, 1993.
ECL §71-2703(1) provides for a maximum civil penalty in
the amount of Two Thousand Five Hundred ($2,500.00) Dollars
99a
Appendix C
for each violation of ECL Article 27, Title 7, or rules or
regulations issued pursuant thereto, and an additional penalty
of not more than one Thousand ($1,000.00) Dollars for each
day during which such violation continues.
I find that Respondents’ receipt, processing or disposal of
petroleum-contaminated soil from the State of New Jersey on
36 occasions were activities outside the scope of authority
granted by the BUD. These activities are within the
Department’s solid waste regulatory program. Since the
activities were outside the authority of the Beneficial Use
Determination that Respondents obtained, a solid waste
management facility permit was required for these activities, a
permit which Respondents did not obtain. Therefore,
Respondents violated ECL §27-0707 and 6 NYCRR 360-1.7,
on 36 occasions by receipt of New Jersey petroleum-
contaminated soil absent a Solid Waste Management Facility
Permit. Staff seeks a penalty of $2,500.00 for receipt of the
first New Jersey soil, on November, 17, 1991 and an additional
penalty of $1,000.00 per day for an additional 290 days (through
September 17, 1992), a penalty of $292,00.00.
As discussed above, the 36 occasions of receipt of materials
from New Jersey sites were, in all but one instance, of the kind
an¢, quality authorized to be processed at the facility, but for
the fact that it originated in New Jersey. I recommend a penalty
of $1000.00 for the initial violation and 100.00 per day for the
additional 290 days, a total monetary penalty of $29,900.00 on
this cause of action.
Therefore, the total monetary penalty recommended on the
enforcement aspect of the consolidated action, is $73,400.00.
100a
Appendix C
Il. REMEDIATION
Violation of Navigation Law Article 12,
ECL Article 17 and 6 NYCRR Parts 360 and 613
Staff asserts that Respondents violated Navigation Law
§173 and ECL §17-0501(1) by causing a discharge of petroleum
at the Mt. Hope facility on or before September 16, 1993, a
continuing violation. Staff does not seek any monetary penalty
for this component of its Complaint, but does seek an order
requiring further investigation and remediation. Staff asserts
that Respondents also violated ECL §17-0501(1) in that the
SCDOHS sample results indicate a petroleum discharge at
Respondent Mt. Hope’s facility.
Navigation Law §175 and 6 NYCRR §613.8 require that
any person who causes a discharge immediately notify the
Department. Staff asserts Respondents violated NL §175 and 6
NYCRR §613.8 by failing to report the discharge to the
Department. Staff witness Gomez testified that Mt. Hope never
reported the discharge to the Department. (T. 2191). Once Staff
learned of the discharge, Gomez prepared a “spill report” and
obtained a “spill number” from the Department’s “spill hotline”.
(T. 2179-2186). Staff asserts that Respondents’ failure to report
the discharge to the Department constitutes violations of NL
§175 and 6 NYCRR §613.8.
6 NYCRR §360-1.7(a)(1)(ii) (effective as of October 9,
1993) provides, in pertinent part that: “no person shall construct
or operate a solid waste management facility, or any phase of
it, in accordance with a valid permit issued pursuant to this
Part . . .”. The regulations in existence before October 9, 1993
provide essentially the same substantive requirement, with some
minor differences in wording.
10la
Appendix C
A solid waste management facility is defined as “any
facility employed beyond the initial solid waste collection
process and managing solid waste, including but not limited
to: storage areas or facilities; . . . disposal facilities . . .”. This
definition was not modified by the October 9, 1993 revisions
to Part 360.
Staff asserts that Respondents disposed of petroleum-
contaminated soil through burial at the facility and that
Respondents also continue to store petroleum-contaminated soil
at the facility, in violation of 6 NYCRR §360-1.7 (a) (1) (ii)
[operation of a solid waste management facility without a
permit) and 6 NYCRR §360-1.5(a) [illegal disposal of solid
waste]. As with the other allegations contained in section D of
the Second Amended Complaint, Staff seeks no penalties with
regard to these alleged violations of Part 360, but rather, seeks
an order requiring Respondents to remediate the upper “parking
lot area” and to remove stored petroleum-contaminated soil
from the west side of the stockpile area.
Respondents assert that Staff failed to prove remediation
is necessary. Respondents further assert that any soil stored on
the contaminated-soil pad, remains there lawfully.
The parties stipulated that since September 15, 1993,
Respondents have continuously maintained approximately
2,000 cubic yards of stockpiled petroleum-contaminated soil
on a storage pad at the facility. September 15, 1993 is the date
that authorization to process petroleum-contaminated soil at
this site expired. That authorization had been granted through
Consent Order No.1-5074-92-06, which was modified on
March 23, 1993; July 30, 1993; and August 27, 1993. The final
modification extended the temporary authority to operate until
102a
Appendix C
September 15, 1993. No further extension was granted.
Respondents were advised that they could no longer use
petroleum-contaminated soil for the production of asphalt (See,
letter from Regional Director Ray Cowen to Barry S. Cohen,
Esq., dated September 16, 1993 [Exhibit 310]). Therefore
Respondents’ argument that storage of soil remaining at the
facility is authorized by the extending provisions of SAPA, must
be rejected.
Staff asserts that Mt. Hope’s continued stockpiling of
petroleum-contaminated soil after expiration of its authority
to operate under the Consent Order, constitutes an ongoing
violation 6 NYCRR §360-1.7(a)(1)(i), in that Respondents have
been operating a solid waste management facflity without a
permit.
Based upon SCDOHS analytical soil sample results, Staff
seeks an order requiring Respondents to further investigate and
remediate the petroleum contaminated areas at the facility’.
Staff bases its request for remediation upon its review of the
sample results, consistent with guidance contained in the
Department’s Spill Technology And Remediation Series
(“STARS”), Memo #1 — Petroleum-contaminated soil
Guidance Policy”. Staff also seeks an order requiring
Respondents to remove remaining stored material to an
authorized treatment, storage or disposal facility.
19. Those areas have been identified through SCDHS analysis of
samples 6MF, 7MF, 18MF, 20MF and 21MF.
20. The STARS Memo #1 was issued in August, 1992 by the
Department’s Division of Construction Management, Bureau of Spill
Prevention and Response, in conjunction with the Department’s Division
of Solid Waste.
103a
Appendix C
STARS Memo #1 provides:
If the calculated maximum possible contaminant
concentration in the extract liquid is greater than
the TCLP Extraction Guidance Value, then no
conclusion can be drawn and groundwater quality
protection must be confirmed by actually performing
the TCLP extraction for that contaminant. (STARS
p. 6).
Staff witness Gomez compared the SCDOHS analysis
results to the TCLP Alternative Guidance Values in STARS
Memo #1. Gomez created a chart which identifies samples
indicating presence of petroleum constituents, and indicates
the extent to which guidance values are exceeded?'. She attached
a copy of this chart to her June 17, 1994 memorandum to
Regional Director Ray Cowen. She also provided a copy of
this chart to Respondents by enclosure with her September 6,
1994 letter to Respondents.
STARS Memo #1 was written as a guidance document to
assist Regional Spill Investigators, among others, “in
determining whether soils have been contaminated to levels
which require investigation and remediation” (STARS Memo
#1, page 1). In conformance with this guidance, Staff requests
that Respondents be ordered to further investigate and remediate
the petroleum contamination at the facility.
21. The analysis results that Ms. Gomez refers to in this chart were
calculated using external calibration standards. See Footnote 30 which
shows that the contamination levels were found to be substantially higher
when the results were recalculated using internal calibration standards.
Also, the results of 7MF, after recalculation because of mathematical
error, are still higher than the STARS Memo guidance value (see Exhibit
209, page 4).
104a
Appendix C
Respondent Mt. Hope asserts that Gomez conceded in her
memo of June 17, 1994 that, (i) the SCDOHS samples would
not likely test hazardous by the TCLP method, and (ii)
groundwater has not been impacted, based upon samples taken
from monitoring wells hydraulically downgradient. Gomez also
conceded at the Hearing that none of the Guidance Values
concerning human health, or fish and wildlife under STARS
were exceeded by the SCDOHS results.
Further, Respondent Mt. Hope asserts its expert witness,
Dr. Olin Braids, testified that no definitive tests had been
conducted to determine that there was any potential hazard to
groundwater by contamination at the site and that there was no
groundwater contamination at the facility based upon
monitoring analysis. Mt. Hope concludes that Braids’ testimony
was not controverted by any witness presented by Staff.
However, the evidence consisting of sampling of the
facility performed by the Suffolk County District Attorney’s
office and the Suffolk County Department of Health Services,
shows that a petroleum discharge occurred at the facility, prior
to the sample collection date. Staff asserts this evidence shows
that Respondents buried and thereby discarded additional
petroleum-contaminated soil in the south-eastern area of the
upper parking lot. However, i reject this assertion. (See, p. 49,
supra). Since the facility has been operated by Mt. Hope for
more than 22 years, it is more likely than not, that Mt. Hope is
responsible for the discharge.
The soil sample evidence indicates that a discharge
occurred. However, testimony did not identify the extent of
the discharge. Staff implicitly acknowledges it does not know
the extent of the discharge, in that it seeks an order requiring
105a
Appendix C
further site investigation. Further, the record before me is not
adequate to establish that the discharge occurred by Mt. Hope’s
deliberate burial of petroleum-contaminated soil. Petroleum
constituents have been used at this facility for the past 22 years
for production of hot asphalt. It is possible that the discharge
occurred inadvertently at some time in the past.
Accordingly, I reject Staff's assertion that these facts and
circumstances constitute a basis for remediation as an ongoing
violation of 6 NYCRR §360-1.7(a)(1)(i) in that Respondents
are operating a solid waste management facility without a
permit. Nonetheless, pursuant to NL §181(1), Respondents are
responsible for remediation of the discharge.
III. PERMIT REVOCATION AND DENIAL
In the permit aspect of this consolidated action, Staff seeks
to have Respondent Mt. Hope’s Departmental BUD and permit
revoked and its application for an air Certificate to Operate
EP4, denied. The basis of Staff's revocation and denial action
is its assessment that Respondent Mt. Hope is unsuitable and
unfit to hold environmental permits or engage in activities
within the Department’s purview. Each determination of
suitability and fitness is necessarily specific to the facts and
circumstances of the particular permittee/applicant.
Staff asserts two bases for a determination that Mt. Hope
is unsuitable and unfit to hold Departmental permits:
(1) Complaint violations proven in this consolidated action;
(2) Respondent Mt. Hope’s history of violations, including two
Consent Orders
This text is long and has been trimmed here. Open the source document for the complete record.