Opinion — William Cramp & Sons Ship & Engine Building Co. v. United States
Supreme Court brief1910
Ask Donna
What actually matters in this document.
Text
_-
WILLIAM CRAMP AND SONS SHEP AND TENGINEE
BUILDING COMPANY +. UNITED STATES.
APPEAL FROM THE COURT OF CLAIMS,
No. 92. Argued January 19, 20, 1910. Decided February 28, Lolo,
Executive officers are not authorized to entertain and settle claims
for unliquidated damages.
The Secretary of the Navy had power under the acts of June 10, 1896,
¢. 361, 29 Stat. 378, authorizing the budding of the * Alabama,” and
of August 3, ISS6, 6 S49, 24 Stat. 215, to make a change in the
terms of the contract requiring a final release to be given so that
such release should not include claims arising under the contract
which he did not have jurisdiction to entertain, and under a proviso
in the release to that effect the contractors are not barred from
WM. CRAMP & SONS vr. UNITED STATES. 495
216 U.S. Argument for Appellant.
prosecuting their claim before the Court of Claus for unliquidated
damages.
In this case a provision ina government contract having been treated
by both parties as impracticable and therefore waived, the Seere-
tury had power to change the terms of the release required by the
contract, and leave the claims of the contractor to be presented to
the Court of Claims. Cramp & Sons v. United States, 206 0. 8.
LIS, distinguished.
Tnder the Tucker Aet the Court of Claims has jurisdiction of a claim
a
for unliquidated damages under a contract for building a war ves-
sel, where a release had been given by the Secretary of the Navy
with a proviso that it does not include chums arising under the
contract other than those of which the Secretary has jurisdiction,
43. C. Cl. 202, reversed.
Tue facts are stated in the opinion.
Mr. James H. Hayden, with whom Mr. Robert C. Hayden
was on the brief, for appellant:
The contract did not obligate the claimant to relinquish
the claim in suit, or any other claims that might accrue to it
for breach of the contract by the United States. The eon
traet itself was not a release of such claims. “The acceptance
by the claimant of the last payment did not ereate a bar to
the claimant's right of action for the breach committed by
the United States.
Performance by the Government of its covenant to supply
armor failing, the builder's agreement to release went with it
“Tf part of the consideration agreed on be not) performed,
the whole aceord fails.” City of Memphes v. Brown, 20 Wall
og: Bank vo Leech, OF Fed. Rep. 310, bE Smith's Leading
Causes, Sth Am. ed. do.
The elaborate and tautological expressions contained in: the
fifth paragraph of the release do not overcome the particular
words of limitation, contained in the proviso, whieh limited
the operation of the release to claims which the Secretary of
the Navy had jurisdiction to entertain, Teras Ke. R. Co
v. Dashiell, YOS US. 521.
tse es eer pr wt Bt Re
A be BELL 1A aleve ——
A neat Cente RD AION Ni ihe et AD MRE GP a
106 OCTOBER TERM, 1909.
Argument for Appellant. 216 U.S.
The Secretary of the Navy and the Cramp Company were
correct in the opinion expressed by the former and acquiesced
in by the latter that the claim being one for unliquidated
damages is of a kind the Department has no authority under
the law to entertain. By the saving clause which was finally
included in the release they adopted apt words to carry out
their purpose to leave the claim in suit open and unsettled.
Executive officers of the Government cannot entertain such
claims, even when they grow out of contracts made by them.
Op. Atty. Gen., ed. INSEL, S82. See also MeKee v. United
States, 12 C. Cl. 514, 555; Power v. United States, 1S C. Cl.
263. 275: McClure v. United States, 19 C. CL. 1S, 28: Brannen
vy. United States, 20 C. Cl. 219, 223: Pneumatic Gun Carriage
Co. v. United States, 36.C. Cl. 627, 650.
To give the release or the claimant's acceptance of the
last payments the effect claimed for them by the Govern-
ment and given them by the court below, would be to use
them in a way not justified by the terms of the release, or
intended by the parties, and would allow the Government
to commit a fraud. Parmlee v. Lawrence, 44 Mlinois, 405, 4109"
Fire Ins. Assn. v. Wickham, TAL U.S. S64, 576, 582. If the
terms of the release were obscure, which they are not, it
would have to be interpreted in such a way as to carry out
the intent of the parties, to be ascertained from the corre-
spondence which passed between them. United States v.
Peck. 102 U.S. G4: Merriam v. United States, We i". 8. 437,
Ll: United States v. Gibbons, 109 U.S. 200, 208; Chicago &e,
R. Co. v. Denver &e. R. Co., 143 U.S. 596, 609; Nash v.
Towne, 5 Wall. 689, 699.
The Secretary had legislative authority to make a contract
for the construction of the vessel in question and while this
was limited in some partienlars it was broad. He was as free
to exercise his judgment in the modification of the contract
as to the release as he was to make the contract in the he-
winning. United States v. Barlow, 184 U.S. 125; Solomon v.
United States, 1 Wall. 17. Redyield v. Windom, 130 U.S.
ares
WM. CRAMP & SONS vr. UNITED STATES. 497
216 U.S. Argument for the United States.
636. This case is not governed by United States v. Wim.
Cramp & Sons, 206U. 8. LES, known as the * Indiana” case,
It was the builder's right and obviously it was for the best
interest of the United States, as well as its own, to proceed
with the work as best it could, complete it, and sue for dam-
ages caused by the breach. 2 Parsons on Contracts, 679;
Clark vy. United States, 6 Wall. 548; United States v. Speed,
& Wall. 77: United States v. Behan, 0 U.S. 338, 344; Figh
v. United States, 8 C. Cl. 319: Myerle v. United States, 33
C. CL 1: Cornwall v. Henson, 2 Ch. (1900) 298, 300; Hudson
on Building Contracts, 1907, 308, 524: Stubbings Co. v.
Exposition Co., WO TIL App. 200; Nelson v. Pickwick Co.,
SO TL App. 5585: Del Genovese v. Third Ave. R. R. Co., 13
N.Y. App. Div. 4122.8. C., 162 N.Y. 614.
Mr. Assistant Attorney General John Q. Thompson and
Mr. Franklin W. Collins for the United States:
The proviso is net suflicient to confer upon appellant
right of recovery.
The failure of the delivery of the armor by the Government
within the times and in the order required to carry on the
work properly had been fully provided for in the contract in
other ways, and had nothing whatever to do either as con-
sideration or otherwise with the release which was required
by the contract. While the contract itself may not be a
release of such claims as those in suit. it nevertheless provided
for a release of all claims growing out of the contract. Texas
ke. R. Co. v. Dashiell, WYS US. 521.
While the Seeretary of the Navy may have power to direct
the modification of a contract during the progress of the
work he has not after his discretionary powers have ceased
and only a plain ministerial duty remains. The Seeretary
was clothed with authority to close the contract in a_pre-
scribed manner. He could not make the final payment until
a full and final release of all claims was given by the con-
tractor, neither could he modify or change the form of release
VOL. COXVI 82
49S OCTOBER TERM, 1909,
Opinion of the Court. 216 U.S.
required by the contract, but this does not conflict with the
exercise of his discretionary powers in respect to changes and
modifications while the work was in progress,
The courts will not assume to make i contract: for the
parties which they did not choose to make for themselves,
Morgan County v. Allen, 103 U.S. O15; Hudson Canal Co.
v. Penna. Coal Co., 8 Wall. 276: Gavinzel Vv. Crump, 22 Wall.
308; Robbins v. Rollins, 127 U.S. 633: Culliford v. Gonillo,
128 U.S. 158; nor is the court at liberty either to disregard
words used by the parties or to insert words Which the parties
have not made use of. Harrison Vv. Fortlage, 161 U.S. 63:
Calderon vy. Atlas Steamship Co., 170 U.S. 280,
Contracts are to be construed according to the intention
of the parties as expressed: therein, and the courts will dis-
regard the motives, the purposes, or the expectations of a
party thereto if these are not in harmony with the plain im-
port of the words used. See 54 Texas. 65; Clark v. Lillie,
34 Vermont, 405; Noyes v. Nichols, 28 Vermont, 159; Conn
V. Lewis, 15 Kentucky, 66: Hildreth y. Forrest, 27 Kentucky,
217; Shultz v. Johnson, 44 Kentucky, 497; Salmon Falls Mfy.
Co. v. Portsmouth Co., 4G N. H. 249.
Mr. Justice Brewer delivered the opinion of the court.
On September 24, 1896, the appellant entered into a eon-
tract with the United States for the building of an ironelad.,
wterwards known as the “Alabama.” The contract Was au-
thorized by act of Congress of June 10, 1896. ¢, 399, 29 Stat,
361,378. Under this act and that of August 3, ISS6, 6. S49. 24
Stat. 215, to which it refers, the Secretary of the Navy was
charged with the duty of supervising the contract on behalf of
the United States. After the completion of the vessel and the
payment of the stipulated amount there was something
asserted to be due to the building company as unliquidated
damages on account of extra work caused by the United
States, for which it brought suit in the ( ‘ourt of Claims. That
WM. CRAMP & SONS ¢. UNTEED STATES. 109
216 U.S. Opinion of the Court.
court found the amount to be $49,792.66. Relying upon the
decision of this court ina case between the same parties for
also the building of an ironelad, the * Indiana,’ (nited States
v. Wm. Cramp & Sons Co., 206 US. LES, the Court of Claims
rendered judgment for the defendant. The controversy in
this, asin the prior case, turns upon the effect of a release. In
that it was in this form:
“The William Cramp and Sons Ship and Engine Building
Company, represented by me, Charles TH. Cramp. president
of said corporation, does hereby for itself and its suecessors
and assigns, and its legal representative, remise, release and
forever discharge the United States of and from: all and all
manner of debts, dues, sum and sums of money, accounts,
reckonings, claims, and demands whatsoever, in law or in
equity, for or by reason of, or on account of, the construction
of said vessel under the contract aforesaid.”
Here the same terms of release are used, but they are fol-
lowed by this proviso:
* Provided, that this release shall not be taken to inelude
claims arising under the said contract other than those whieh
the Secretary of the Navy had jurisdiction to entertain.”
That release was executed on May ES, ESO6: this on April 19,
1901. We held that the former release settled all disputes
between the parties as to claims “under or by virtue” of the
contract. Evidently the proviso was incorporated with the
purpose of accomplishing some change in the effect of the
release. That) purpose is diselosed by prior correspondence.
On February 13, L901, the Seeretary of the Navy, answering
a letter enclosing a elaim for extra work of S66,975.25, writes:
“TP have to state that while, from a easual consideration of
the matter, it might seem proper that the papers should he
referred to the bureaus concerned for examination and report,
Moappears, after a careful consideration of the subjeet, that
the claim, being for unliquidated damages, is of a kind the
department has ne authority ander the law to entertain.”
To which the company replied, suggesting this proviso:
oU0 OCTOBER TERM, 1909.
Opinion of the Court. 216 ULS.
«
“Provided, That nothing herein shall operate as a waiver of
this company’s right to sue for and recover judgment in the
Court of Claims for damages incurred or losses sustained by the
company in the prosecution of the contract work which were
oceasioned by delays or defaults on the part of the United
States ?—
and adding, in response to the statement of the Secretary,
“that the claim beine for unliquidated damages, is of a kind
the department has neo authority under the law to entertain;”
that the act of March 3. ISS7, ©. 359, 24 Stat. 505. known as
the “Tucker Act.” vests the ( ‘ourt of Claims with jurisdiction
to hear and determine sich claims. Some further correspond-
ence followed between the parties, which culminated in iu
letter from the company, enclosing the release as finally exe-
cuted, and saving:
“This (release) contains a Clause which excepts from the
operation of the release claims arising under the contract,
Which you, as Secretary of the Navy, had not jurisdiction to
entertain.”
It is well understood that executive officers are not author-
ized to entertain and settle claims for unliquidated damages,
Opinion of Attorney General Taney, in which he SUVS:
“Tf the navy commissioners have refused to take the bread
from Mr. Stiles. according to their contract. When he had pre-
pared it of the quality called for by the agreement, it is not
in the power of the executive branch of the Government. to
liquidate and pay the damages he may have sustained. — If
he has been dammnified by the officers of the ( movernment, Con-
gress alone ean redress the injury.” (Opinions. ed. IS41, pp.
SS2): MeNWee vo United Slates, 12. C. Cs. OON, 555-558.
In Power v. United States, ISC. Cs. 265, 275, the court thus
diseussed the matter:
“The Secretary of the Interior coneurred in the opinion that
the claimant was equitably entitled te damages, and that he
should be invited te furnish proof of the extent of his injury;
but did not agree that the damages could. be adjusted in
WM. CRAMP & SONS +. UNITED STATES. 501
216 U.S. Opinion of the Court.
the department. He proposed to submit the case to Con-
gress,
“In this conclusion that the department had no authority
to settle such a claim the Secretary was right. The laws
regulating the payment of money from the Treasury, in the
current business of the Government, are reviewed at length
by our brother Richardson in his opinion in MeNee's Case,
12 Ct. Cl R555. He shows clearly that the laws provide
only for the settlement and payment of accounts. An account
is something which may be adjusted and liquidated by an
arithmetical computation. One set of Treasury officers exam-
ine and audit the accounts. Another set is entrusted with
the power of reviewing that examination, and with the further
power of determining whether the laws authorize the payment
of the account when liquidated. But no law authorizes treas-
ury Officials to allow and pass in accounts a number not the
result of arithmetical computation upon a subject within the
operation of the mutual part of a contract.
“Claims for unliquidated damages require for their settle-
ment the application of the qualities of judgment and disere-
tion. They are frequently, perhaps generally, sustained by
extraneous proof, having no relation to the subjects of the
contract, Which are common to both parties: as, for instance,
proof concerning the number of horses and the number of
wagons, and the length of time that would have been required
in performing a given amount of transportation. The results
to be reached in sueh cases ean in no just sense be ealled an
account, and are not committed by law to the control and de-
cision of Treasury accounting officers,
* Asis well said by Judge Richardson, in the opinion already
referred to (12. C. Cs. 556), this construction ‘would ex-
clude claims for unliquidated damages, founded on negleet or
breach of obligations or otherwise, and so, by the well-defined
and accepted meaning of the word ‘account’ and the sense in
Which the same and the words ‘aceounting’ and ‘aecountine
officers” appear to be used in the numerous seetions of the
502 OCTOBER TERM, 1909.
Opifion of the Court. 216 U.S.
numerous acts of Congress wherein they occur, it would seem
that the aecounting officers have no jurisdiction of such claims
except in special and exceptional cases, in which it has been
expressly conferred upon them by special or private acts. And
such has been tke opinion of five Attorneys General—all who
have officially advised the executive officers on the subject.
Attorney General Taney, in 1832, whose opinion is referred to
by his successors in office; Attorney General Nelson in IS44
(4 Opins. 327); Attorney General Clifford in 1847 Opins.
627); Attorney General Cushing in L854 (6 Opins. 524); and
Attorney General Williams in 1872 (14 Opins. 24). And the
same views were expressed by this court in 1866 (Carmack et al.
v. United States, 2 Ct. Cl. R. 126, 140.) McClure v. United
States, 19 Id. 28-29: Brannen v. United States, 20 Id, 219, 225-
224; 4 Opin. Attorneys General, 327-3828; [d. 626, 630.”
But it is contended that the contract, independently of
the release, provided for a settlement of all matters growing
out of the delay in the completion of the vessel, although this
is in apparent conflict with the opening statement of the Goy-
ernment in its brief, for there it says: “The issue here is
whether the proviso in that release saves the contractor from
the final and complete surrender of his right to reeover on the
claims set out in the petition.” But this, although it: indi-
eates the views of the Government of the question at issue,
does not preclude it from presenting other matters, and it
insists that by the third clause in the contract, the vessel,
when completed without the armor, was to. be subjected to
a trial provided for in a subsequent clause of the contract,
and a board of naval officers appointed by the Secretary of the
Navy was to determine the deduction from the total price
of the vessel under the contract if completed with armor. — It
further contends that by the ninth clause of the contract the
matter of possible delay was recognized by the Secretary of
the Navy, and his determination as to the effect thereof was
to be conclusive. Now it may be said that both the con-
tractor and the Government had the right to insist upon the
WM. CRAMP & SONS v. UNITED STATES. 503
216 U.S. Opinion of the Court.
delivery of the vessel when it was completed without the armor,
and that the deduction in price should then be settled by the
board of officers appointed by the Secretary. [t may vilso be
conceded that the Government could have insisted upon a
release in the form specified in the contract, but neither the
company nor the Government insisted on the delivery of the
vessel at the time it was launched and before it was armored.
The Government left the vessel with the company, waiting for
armor to be put on—armor which it had not then been able
to secure and tender to the company, and when the ques-
tion arose as to asettleoment it did not insist upon a release as
specified in the contract. This contract was plainly treated
by both parties as impracticable, and therefore waived. evi-
dently from his letter of February 13, 1901, the Secretary was
of the opinion that, equitably, there was something due to
the company, and yet, realizing that that question was not
one for his determination, in order that full justice might be
done, he consented to a change in the terms of the release, and
this he had power to do. Salomon v. United States, 19 Wall.
17: United States ex rel. Redfield v. Windom, 37 U.S. 6386;
United States v. Barlow, St US. 128, Toe.
By the * Tucker Act” jurisdiction is conferred upon the Court
of Claims “to hearand determine =... allckuims
for damages, liquidated or unliquidated, in cases not sounding
in tort.”
It results therefrom that a release executed in aecordance
with the terms of the contraet would have extinguished all
claims of the company against the United) States growing
out of the contract (206 U.S. EIS): that the Seeretary of the
Navy had ne power to pass upon and adjudicate claims for
unliquidated damages: that he had power to accept a release
such as was given, and that the proviso left for determination
in the courts claims for unliquidated damages growing out of
the contract: that under the Tucker Act the Court of Claims
had jurisdiction to inquire into and determine elaims for
unliquidated damages, and that upon the facts found: there
EEE = eee
out OCTOBER TERM, 1909.
®yllabus. 216 U.S.
is due to the company from the United States for extra work
caused by the United States the sum of 549,792.66.
The judgment of the Court of Claims ts reversed and the case
remanded to that court, with instructions to enter judgment
Jor that amount.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.