Petition for Writ of Certiorari — Southern Natural Gas Co. v. United States
Supreme Court brief1989
Ask Donna
What actually matters in this document.
Text
Supreme Cour, Us
89-123 BILED
sis JUL 21 1989
JOSEPH. SPANIOL, JR,
CLERK
re ee
IN THE
Supreme Court of the United States
OCTOBER TERM, 1989
PARKER TOWING COMPANY, INC.,
Petitioner
versus
UNITED STATES OF AMERICA,
Respondent.
On Writ of Certiorari To The United States
Court of Appeals for the Eleventh Circuit
PETITION FOR WRIT OF CERTIORARI
G. HAMP WZZELLE, Ill
Hand, Arendall, Bedsole,
Greaves & Johnston
P.O. Box 123
Mobile, Alabama 36601
205-432-5511
COUNSEL OF RECORD FOR PETITIONER
PARKER TOWING COMPANY, INC
QUESTIONS PRESENTED
1. Did the Court of Appeals disregard
the settled requirements of maritime law
that a negligent defendant is entitled to
exoneration based upon Act of God only if
it can affirmatively show that the damages
suffered are the result of inevitable
accident which a proper exercise of human
skill and precaution could not have
prevented?
2. Did the Court of Appeals err in
finding that the District Court was clearly
erroneous in rejecting the United States'
affirmative defense of act of God?
3. Should the Court of Appeals give
an understandable explanation of its
reasons, including a reference to the
evidence or lack thereof, in rejecting the
District Court's findings of fact as being
clearly erroneous?
LIST OF PARTIES TO THE PROCEEDING
IN THE COURT OF APPEALS
The below listed entities were parties
to the proceedings in the Court of Appeals:
Warrior & Gulf Navigation Company
Parker Towing Company, Inc.
Southern Natural Gas Company
Hunt Oil Company
Insurance Company of North America
United States of America
Parker Towing Company, Inc. has no parent
company and has the following subsidiaries
and affiliates:
Mobile Drydock, Inc.
Pickens County Port, Inc.
Waterways Forest Products, Inc.
Cargo Handlers, Inc.
Mobile Shipbuilding and Repair, Inc.
Tombigbee Fleeting Service, Inc.
ii
TABLE OF CONTENTS
Page
Questions Presented ........e cee eccces i
Ree GP GAMO BELOW cic cc cacccccves ii
ME PESCIUNUOENEGE Coca cess recsessecces oF
Meee ME BUGCMORACIGS 2. cc ce eee necnes V
CCC UMRRGIN occ e ase scscecesessceess 1
Statement of Jurisdiction ............ 2
BEeMCOMene OF THE CASS 2... cs sescesccves 2
ES PPT Se ee PERRET TETee 19
PCCP Rk G UR GOK BSc eS eacesraseesecs 34
Appendices:
A. Adoption of Warrior & Gulf
Navigation Co. Appendix A -
Eleventh Circuit Opinion
Dated February 6, 1989 ........... A-1
B. Adoption of Warrior & Gulf
Navigation Co. Appendix B -
Eleventh Circuit Denial of
Petition for Rehearing Dated
DRT REE ge sacecnurenscessccs A-2
Cc. Adoption of Warrior & Gulf
Navigation Co. Appendix C -
Southern District of Alabama
Opinion Dated May 18, 1987 ....... A-3
nj
Page
Warrior & Gulf Navigation Co.
Trial Exhibit 33 - Graph of
Upper Pool Elevations at
Bankhead Lock and Dam ..........5.. A-4
Government Trial Exhibit 10C
Graph of Upper Pool Elevations
at Holt Lock and D@M ...ccceccccess A-5
Summary of Gate Elevations,
Pool Elevations, and Cubic Feet Per
Second Discharge at Bankhead
LOCK ONG DOM .ccccccccesesecscesecs A-6
Summary of Gate Elevations,
Pool Elevations, and Cubic Feet Per
Second Discharge at Holt
LOCK And DaM ..cccceccvccseveccves A-7
Comparison of Holt Upper Pool
Elevations as Reflected by Operator's
Log and by Recording Graph ....... A-8
Excerpts from U. S. Army Corps of
Engineers' Manual E-1110-2-3600,
entitled "Reservoir Regulation" .. A-9
lv
TABLE Of A RITIE
Page
CASES:
Amadeo v. Zant, 486 U.S. ot
100 L.Ed.2d 249, 261-62 (1988) ......... 30
Boudoin v. J. Ray McDermott & Co.,
281 F.2d 81, 88 (5th Cir. 1960) .. 19-20,28
Crumady v. The JOACHIM HENDRIK
FISSER, 358 U.S. 423, 429 (1959)
(dissenting OPiniON) .... eee eee eee eeees 31
In Re United States, 425 F.2d 991,
995 (Sth Cir. 1970) wc weeecceveeeeevees 20
Patapsco Scrap Corporation v.
Maryland Shipbuilding & Drydock Co.,
268 F.2d 817, 819 (4th Cir. 1959) ...... 20
The LOUISIANA, 70 U.S. (3 Wall)
Tt? es a ere tr 19
The ROB, 122 F.2d 312, 313
(2nd Cir. 19G1) wecccececcscseesccessces 20
The WILLIAM E. REIS, 152 F.
673, 676 (6th Cir. 1907) wn. ceweeeenees 20
Warrior & Gulf Navigation Company v.
United States, 864 F.2d 1550,
petition for rehearing denied,
875 F.2d 874 (llth Cir. 1989) ..... 1,24,32
Zubik v. Zubik, 384 F.2d 267,
269-70 (3rd Cir. 1967) wc ccccnevccecees 20
STATUTES:
28 U.S.C.
28 U.S.C.
46 U.S.C.
« $ TS254C1) wevcce
, §§ 471, et seq.
*“eeeeesee####*%* # *#
OPINIONS BELOW
The opinion of the Court of Appeals
for the Eleventh Circuit dated February 6,
1989, review of which is sought by this
Petition for Writ of Certiorari, is
captioned Warrior & Gulf Navigation Company
v. United States and is reported at 864
F.2d 1550 and is reprinted as Appendix A to
the petition filed by Warrior & Gulf
Navigation Company ("WGN") and adopted as
Appendix A hereto. A petition for rehear-
ing and suggestion of en banc consideration
was denied by the Eleventh Circuit on April
25, 1989, and that denial is reported at
875 F.2d 874 and is reprinted as Appendix B
to the petition filed by WGN and adopted as
Appendix B hereto. The opinion of the
District Court for the Southern District of
Alabama dated May 18, 1987, is unreported
but is reprinted as Appendix C to the
petition filed by WGN and adopted as
eu
Appendix C hereto.
STATEMENT OF JURISDICTION
The opinion of the Eleventh Circuit,
the review of which is sought, was rendered
on February 6, 1989. Petitions for
rehearing were timely filed and were denied
by order of the Eleventh Circuit dated
April 25, 1989, and entered on that date.
No order _ been requested or entered
granting an extension of time within which
to petition for writ of certiorari.
Jurisdiction to review the Judguent in
question by writ of certiorari is conferred
upon this court by the provisions of 28
U.S.C. § 1254(1).
STATEMENT OF THE CASE _
This appeal arises out of a decision
of the United States District Court for the
Southern District of Alabama following a
lengthy non-jury trial of the issue of
2
liability only in five consolidated cases.
Involved in the proceedings were claims by
Warrior & Gulf Navigation Company ("WGN"),
Hunt Oil Company ("Hunt"), Southern Natural
Gas Company ("Sonat"), Insurance Company of
North America, and Parker Towing Company,
Inc. ("Parker") against the United States
for damage resulting from the domino effect
of the M/V CADDO's tow's colliding with the
U. S. Highway 82 By-Pass Bridge, which
spanned the Black Warrior River downstream
from Holt Lock and Dam. The claimants,
other than WGN, had also asserted claims
for these damages against WGN, but all of
these claims except Parker's were settled
prior to trial. Parker also asserted a
claim against the United States for the
loss of its barge PTC 135 and her cargo as
a result of that barge's being broken away
from her moorings upstream from Holt by
strong currents, whose force and effect
were greatly increased by the negligence of
3
the United States in the operation of the
Bankhead and Holt Dams on the Black wartioe
River. Other claims between Parker and the
United States were also asserted but they
are not relevant to this petition for writ
of certiorari. The District Court had
jurisdiction of all cases pursuant to 28
U.S.C. § 1333 and specific jurisdiction
against the United States as a defendant
pursuant to 46 U.S.C. §§471, et seq.
After a lengthy trial involving many
witnesses and exhibits, Senior Judge Daniel
H. Thomas found that the CADDO's tow's
striking the bridge and the PTC 135's
breaking away from her moorings were caused
by the sole negligence of the United States
in the operation of its locks and dams. On
appeal, the Court of Appeals for the
Eleventh Circuit reversed Judge Thomas '
opinion, holding that he was clearly
erroneous in determining that the negli-
-
gence of the United States proximately
caused the damages, the Court of Appeals
instead substituting its finding that the
unprecedented rain was the inevitable cause
of the chain of events in the case.
Petitions for rehearing were filed and
denied.
The claims in this litigation all
arise out of damages to vessels and
shoreside facilities which occurred on the
morning of December 3, 1983, on the Black
Warrior River in the general vicinity of
Tuscaloosa, Alabama. The Corps of
Engineers operates the following three
facilities on the Black Warrior River in
this area, which are listed in order from
upriver to downriver: Bankhead Lock and
Dam, located at Mile 365; Holt Lock and
Dum, located at Mile 347, ‘and Oliver Lock
and Dam, located at Mile 338. In addition
to the locks which allow vessels to
>
navigate the river, Bankhead and Holt have
spillway gates which can be raised and
lowered to regulate the height of the river
and the flow of the current, whereas Oliver
has a fixed dam with no moveable spillway
gates. The Brookwood (Drummond) facility
where Parker's barge PTC 135 had been
moored for over a week is located seven
miles upstream from Holt at Mile 354, and
the U. S. Highway 82 By-Pass Bridge, which
WGN's Tug CADDO's tow struck, is located at
Mile 341.5, which is five and one-half
miles downstream from Holt.
On the night of December 2-3, 1983,
the Tug CADDO, with six barges in tow, was
the third of three WGN tugs to proceed
downstream through Holt Lock, departing the
lock at sometime between 1:45 a.m. and 2:03
a.m. She struck the bridge at 2:30 a.m.,
resulting in the breakup of her tow. While
other WGN tugs in the vicinity were
r
Le)
assisting the CADDO, their barges broke
loose, and, as a result, WGN lost numerous
barges and their cargoes, and damage was
caused to Sonat's and Hunt's facilities
downstream from Oliver and also to two of
Parker's barges, the PTC 216 and PTC 235,
which were in a tow just downstream from
Oliver. The trial court found that the
damages of WGN, Hunt, and Sonat, and
Parker's damages to the PTC 216 and PTC 235
all stemmed from the domino effect of the
CADDO's tow's colliding with the bridge and
its breakup. (Conclusion of Law 6)
(Future references to the findings of fact
and nen conclusions of law which are
contained in the Record at R1-27 and in
Appendix C hereto will be cited as "F of F"
and "C of L".) The basic facts as stated
above have not been disputed by any party
on appeal, although there is, of course,
dispute as to whether or not the govern-
ment's negligence was the cause of the
7
CADDO's tow's colliding with the bridge.
In its opinion, the Eleventh Circuit
reversed the trial court's award of all
damages to Parker against the United
States, including the damages to the PTC
216 and PTC 235. With respect to its claim
for the damages to the PTC 216 and PTC 235,
Parker incorporates herein the statement of
facts of WGN in its petition for writ of
certiorari.
The language contained in C of L 6
taken by itself implies that all of
Parker's claims resulted from the domino
effect of the CADDO's tow's colliding with
the bridge, and the Court of Appeals
apparently accepted this implication as
being correct. It is, however, totally
incorrect as is reflected by the language
contained thereafter in C of L 8 wherein
the district court stated in part as
follows:
This leaves the problem of Barge
PTC 135 and the cost incurred in
its removal from the spillway
gates at Holt. [The United
States had claimed recovery for
this cost but abandoned that
claim in its appellate brief. ]
i The Court finds, however,
that the negligence of the United
States in the operation of the
spillway gates proximately caused
the breakaway of the PTC 135.
Parker is therefore entitled to
recover in full for its damages
incurred in connection with the
loss of the PTC 135 and its
cargo.
It is blatantly obvious that the CADDO's
tow's striking the bridge five miles
downstream from Holt could not have caused
the PTC 135 to break away from her moorings
seven miles upstream from Holt.
Instead, the PTC 135 was broken from her
mooring by the strong currents at Brook-
wood, the strength of which was substan-
tially increased by the negligence of the
Corps of Engineers in operating the
spillway gates at Bankhead and Holt ina
9
manner ccntrary to its established regula-
tions by negligently and unnecessarily
storing large amounts of water above the
dams and then rapidly opening the gates and
releasing this stored energy.
Attached hereto as Appendices D & E
are copies of WGN Ex. 33 and Government Ex.
10C, respectively, which reflect the
heights of the Bankhead and Holt upper
pools (also refered to as Bankhead and Holt
Lakes) at relevant times. WGN Ex. 33
reflects that Bankhead Lake commenced
rising at 6:00 p.m. on December 2nd and
rose steadily and continuously until
midnight for a height of approximately .8
of a foot. This substantial rise in
Bankhead Lake, which is approximately three
times as large as Holt Lake, caused the
lock tender who went off duty at 11:00 p.m.
on December 2nd to advise his relief that
they had a "runaway river", that he had
10
been opening gates since 10:15 p.m., and
that additional gates would have to be
opened. (R5--926-27) Maximum opening of
the gates at Bankhead is 13.5 feet (WGN Ex.
7), but, despite this early knowledge, the
gates at Bankhead were not opened above
three feet until almost 1:00 a.m. and were
not opened to full flow until 4:18 a.m.
(WGN Ex. 9) The discharge rate at an
opening of three feet at Bankhead is
approximately 56,500 cubic feet per second
("cfs"), whereas the discharge rate at full
flow is 189,900 cfs. (WGN Ex. 7) Appen-
dices F & G are compilations of the gate
openings, upper pool elevations according
to the gate operator's logs, and cfs
discharges of Bankhead and Holt, respec-
tively, and Appendix H is a comparison of
the Holt pool elevations recorded in the
operator's log with the Corps' recording
graph. The data upon which these appen-
dices is based is contained in WGN Exs. 7,
il
9, 11, and 13 and Government Ex. 10C.
The government's manuals for the
operation of Bankhead and Holt provide for
continuing communication between Bankhead
and Holt to "[aid] in the operation of Holt
Lock and Dam by providing an indication of
expected inflows" (WGN Ex. 7, q 6-3) and
state that the exchange of data "may be
helpful in anticipating gate operating
requirements." (WGN Ex. 11, { 26) Despite
these provisions, "[T]jhe testimony of the
Corps witnesses at trial was confusing and
conflicting as to when Bankhead warned Holt
that an unprecedented volume of water was
on the way south from Bankhead. The third
shift lock tender at Holt testified that
Bankhead did not warn him of its actions
[substantial gate raisings] until ‘it was
almost too late' and the water had already
hit him by surprise." (F of F 40)
12
The substantial rise at Holt began
around 11:00 p.m., and by 3:00 a.m. the
pool there had risen to a peak of 190.2
feet (Government Ex. 10C), which is 3.2
feet above the maximum reservoir height of
187 feet. (WGN Ex. 11, { 23) Holt is
designed so that "the proper manipulation
of the gates will maintain the pool at
[187] for all inflows up to 393,000 cfs."
The manual further provides that the "gates
will be operated . . . in order to maintain
the reservoir between elevations 186 and
187 except during floods with inflows in
excess Of spillway capacity." (WGN Ex. ll,
q26) The inflow into Holt Lake from
Bankhead never exceeded 152,000 cfs prior
to 3:00 a.m. (Appendix C, WGN Ex. 9, & WGN
Ex. 7, charts 9-13). The inflow into Holt
Lake was about the same from rain as it was
from Bankhead except possibly for the very
early hours of the morning when the
exhibits reflect much lower discharge
13
rates. (R4--740-41, R6--1468) Conse-
quently, during the time that Holt Lake was
rising, the total maximum inflow into Holt
Lake of slightly over 300,000 cfs was
substantially below the discharge capacity
of 393,000 cfs.
The iock operator at Holt, however,
neglected to open his gates sufficiently
early as required by the manuals in order
to maintain Holt Lake at or Lzlow the
maximum permitted elevation. By 1:40 a.m.,
he had raised his gates to a height of only
six feet, producing a discharge of 99,770
cfs. (Appendix G, WGN Ex. 13 & WGN Ex. ll,
Charts 7-11) At 2:20 a.m., the gates were
raised to twelve feet at Holt, producing a
discharge of 199,460 cfs and were ulti-
mately raised at 4:30 a.m. to the maximum
opening utilized that night of an average
of slightly over seventeen feet, producing
a discharge of 264,340 cfs. These records
14
unquestionably supported and in fact
demanded the trial court's finding that the
operator at Holt "violated the undisputed
Corps requirement that the gates be opened
as soon as the upper pool exceeds the
elevation of 187" and that "Holt was not
operated as a run-of-the-river dam is
Supposed to be operated during this
critical period of time" as the operator
was devoting the time "to locking three
southbound Warrior & Gulf tugboats through
Holt, ignoring the flood descending from
Bankhead." (F of F 43) After locking the
last boat through at 1:40 a.m., the
operator discovered that his pcol had risen
alarmingly and immediately began opening
gates as fast as he could. (F of F 43)
Even after the pool at Holt had crested at
3:00 a.m., the Holt operator continued to
open gates from approximately 13 feet to
approximately 17 feet, increasing the
discharge from approximately 217,000 cfs to
15
approximately 264,000 cfs.
The maximum discharges from Bankhead
and Holt occurred from approximately 4:30
a.m. to 6:00 a.m. (Appendices F & G), and
the current at Brookwood was reported to be
ten m.p.h. (R4--833-35) at 5:30 a.m. It
was probably well after 3:00 a.m. that the
PTC 135 most likely broke loose. (Govern-
ment's Appellant Brief at 30-31) At 6:00
a.m., the PTC 135 struck Holt Dam seven
miles dcwnstream from Bankhead where she
had been moored. (F of F 49)
Dr. Neil Grigg, a highly qualified
hydrologist, testified that the lock
operators at Holt and Bankhead could have
brought their pool levels down below the
maximum level earlier by opening the gates
earlier which would have reduced the
necessity to have opened the gates as high
as they did later in the morning between
16
3:00 a.m. and 6:00 a.m. Opening the gates
earlier would have avoided the necessity to
open the gates so high later, resulting in
substantially less current at Brookwood
than did in fact occur between 3:00 a.m.
and 6:00 a.m. (R4--676-683, 771-774) Joe
Henline, an independent tug boat pilot,
testified that big openings at Holt and
Bankhead will create very strong currents
between the two and that the current gets
strong, not when the river is'rising, but
when the gates are opened to allow the
current to start moving through. (R3--395-
401) Even Mr. Rounsaviile, the Corps' star
company-line witness, acknowledged that
water was stored above Holt until approx-
imately 3:00 a.m. (R6--1229-30) and that
from 4:30 a.m. to 6:00 a.m. the gates were
opened very wide, resulting in the dramatic
falling of the pools and the passing ofa
lot more water than would have passed
17
through if the dams had not been there.
(R6--1278-79)
The Government did not offer any
evidence at all to show what the currents
would have been in the river where the PTC
135 broke loose between Holt and Bankhead
if the Government had operated its dams
properly as required by its own requla-
tions.
In fact, although the Government's
expert hydrologist Dr. Peck modeled the
river, not only from Holt downstream to
Oliver, but also from Holt upstream to
Rankhead (R6--1432-33, 1433-35), he did not
testify with respect to the currents or
conditions between Holt and Bankhead, where
the PTC 135 incident occurred, and the
Government offered into evidence only his
model below Holt and not his model above
Holt.
ARGUMENT
In reaching its decision, the Court of
Appeals totally ignored the extensive
maritime jurisprudence on the subject of
act of God, or inevitable accident, relying
instead upon two Alabama decisions, of
which one was not cited in any appellate
brief and the other was cited for a totally
different proposition than that asserted by
the court. The United States Supreme Cource
in The LOUISIANA, 70 U.S. (3 Wall) 164, 173
(1865) clearly established that a defendant
relying upon inevitable accident, or act of
God, must show that the accident was "the
resuit of inevitable accident, or a vis
major, which human skill and precaution,
and a proper display of nautical skill
could not have prevented." The Fifth
Circuit in Boudoin v J. Ray McDermott &
Co., 281 F.2d 81, 88 (5th Cir. 1960) stated
as follows:
19
[Tjhe law is clear
that "the burden ‘is heavily upon
the [defendant] asserting such a
defense,' .. . Such [defendant]
‘must exhaust every reasonable
possibility which the circum-
stances admit and show that in
each they did all that reasonable
care required.'"
These basic principles have been previously
applied uniformly by the courts of appeals
in maritime cases. The ROB, 122 F.2d 312,
313 (2nd Cir. 1941); Zubik v. Zubik, 384
F.2d 267, 269-70 (3rd Cir. 1967); Patapsco
Scrap Corporation v. Maryland Shipbuilding
& Drydock Co., 268 F.2d 817, 819 (4th Cir.
1959). In Re United States, 425 F.2d 991,
995 (5th Cir. 1970); The WILLIAM E. REIS,
152 F. 673, 676 (6th Cir. 1907). The
present case contains a factual variation
from most act of God decisions, because, in
most of those cases, the party asserting
act of God as a defense is the owner of a
vessel which has broken away from her
20
moorings and which is presumed to be
negligent since its moving vessel has
struck a fixed object. In the present
case, the situation is reversed in that
Parker, the owner of the PTC 135 which
broke away from her moorings, was found by
the trial court not to be guilty of
negligence (C of L 10), and the Government
not only was found to be negligent by the
trial court but did not dispute that
negligence in its appellate brief, con-
tending only that its negligence had not
proximately caused the damages. Because of
this unique situation, caution is required
in order to recognize that the burden of
proving act of God is on the party who
relies on the act of God defense, which may
not be the drifting vessel.
In its opinion, the Eleventh Circuit
merely states, relying upon an Alabama
decision, that a negligent party will be
21
exonerated from liability if the act of God
would have produced the same damage
irrespective of the party's negligence.
The opinion does not contain any discussion
of what proof exists in the record to
support the Government's affirmative
defense. The opinion instead only asserts
in conclusionary fashion that the unprece-
dented rain rather than the Government's
negligence was the inevitable cause of the
chain of events. Furthermore, the opinion
fails to recognize in any manner that the
incident involving the PTC 135 was not a
part of the chain of events resulting from
the collision of the CADDO's tow with the
bridge.
The Eleventh Circuit repeatedly refers
to the "unprecedented rainfall" as if the
mere fact that the rainfall was unprece-
dented provided a defense to the United
States. Pursuant to the applicable
22
maritime law, however, the question is not
whether the rainfall was unprecedented but
rather whether the Corps of Engineers
personnel could have prevented the damage
by the proper exercise of reasonable care.
As set forth above, the trial court found
that "the negligence of the United States
in the operation of the spillway gates
proximately caused the breakaway of the PTC
135." (C of L 8) The United States did
not seriously challenge the district
court's finding that it was negligent, and
the Eleventh Circuit did not find that the
trial court was clearly erroneous in
concluding that the United States was
negligent.
The Eleventh Circuit's opinion
contains no discussion of the Corps of
Engineers' operation of the dams and what
the Corps could have done to avoid the
damages. The opinion does contain the
23
statement that "the flow out of the dam was
matching the flow into the lake above the
dam," 864 F.2d at 1554, but this statement
is in direct conflict with the undisputed
evidence as to the inflows and discharges
as detailed above in the statement of facts
with respect to the periods of time
relevant to the breakaway of the PTC 135
from her moorings. If the outflows had
equalled the inflows, the levels of the
lakes would have remained constant, but
they varied greatly, exceeding the maximum
allowable elevations, as is visibly
demonstrated by the graphs contained in
Appendices D and E. Basically, the Court
of Appeals simply concluded without any
informative discussion that "the unprece-
dented rain, rather than the Army Corps of
Engineers' operation of the Black Warrior
River lock and dam system, was the in-
evitable cause of the chain of events in
this case." 864 F.2d at 1554. Obviously,
24
the rainfall was the initial motivating
force in causing the PTC 135 to break away
from its moorings, just as hurricanes and
other natural phenomena were the initial
motivating forces in all of the inevitable
accident cases cited above. In those
cases, however, the courts properly
analyzed the evidence to determine whether
or not the negligent defendants had carried
their heavy burden of proving that they did
all they reasonably could to prevent the
. damage.
Although the rainfall was a very
substantial factor in producing the
currents in che river, clear and substan-
tial evidence, as set forth in the state-
ment of the facts, demonstrates that the
Corps of Engineers' negligence in impro-
perly storing tremendous quantities of
water above the dams rather than allowing
them to flow through as required by a run-
25
of-the-river project and in subsequently
releasing this stored energy by opening the
gates wider than should have been necessary
resulted in a substantial increase in the
current. In contrast to this very con-
vincing evidence which was clearly accepted
by the trial judge, who saw and heard the
witnesses testify, the United States
offered no evidence at all to show what the
currents and forces involved would have
been if the government had operated the
locks and dams in the manner required by
its own regulations and by the exercise of
due care.
Furthermore, while the rainfall may
have been unprecedented, it clearly was not
unforeseen, and the Corps of Engineers
specifically recognized the great potential
for damage that could result from improper
operation of the gated spillways during
heavy floods and storms. In the Corps of
26
Engineers' Manual EM-1110-2-3600 (WGN
Exhibit 15) entitled "Reservoir Regula-
tions," a portion of which is reproduced as
Appendix I, the Corps specifically notes
that experience has shown that significant
damages may arise when reservoir releases
during floods are greater than would have
occurred under natural conditions prior to
construction of the reservoir. Accord-
ingly, the manual states that one of the
objectives of the operation of the spill-
ways is to prevent peak rates of reservoir
release that would exceed the runoff
conditions that would have occurred without
the construction of the reservoir. To
accomplish this objective, the manual
provides for the opening of the spillway
gates before the reservoir has exceeded its
storage capacity in order to limit the
increase in outflow to an acceptable value.
In light of the Corps' recognition of the
potential damage that could result from the
27
operation of the dams, it is certainly
clear that its lock operators had the same
duty to exercise due care to prevent damage
as the ship master in Boudoin, supra, 281
F.2d at 84-85. Nevertheless, the lock
operators were not even familiar with the
written manuals regarding the operation of
the dam and had not been trained in
accordance with the Corps of Engineers'
mandates contained therein. (F of F 30)
A review of the trial court's opinion
reflects that the court conducted a
detailed analysis of the evidence presented
with regard to the Corps of Engineers'
negligence and found that that negligence
proximately caused the breakaway of the PTC
135. The very convincing testimony of Dr.
Grigg, the highly qualified hydrologist,
and Joe Henlein, an experienced independent
tug boat pilot, virtually demanded this
conclusion. Their testimony was further
28
supported by the acknowledgment of the
Corps of Engineers' Mr. Rounsaville that
the Corps' actions resulted in a dramatic
falling of the pools and the passage of a
lot more water through the dams during the
time of the PTC 135 incident than would
have occurred prior to the construction of
the dams. In opposition to this over-
whelming evidence, the Corps of Engineers
offered nothing to carry its heavy burden
of proof and even deciined to present any
testimony from its expert hydrologist with
respect to currents or conditions at the
area where the PTC 135 incident occurred.
The Eleventh Circuit's opinion does
not set forth in any meaningful manner the
facts or evidence upon which the court
based its faulty determination that the
trial court was clearly erroneous with
respect to the PTC 135. This Court
recently stated in reversing another
29
ee
opinion of the Eleventh Circuit in which it
had held the trial court's findings clearly
erroneous as follows:
Indeed, the Court of
Appeals identified no evidence in
the record--aside from the fact
that the memorandum eventually
was discovered--that contradicted
the District Court's conclusions
about the concealment and
availability of the memorandum.
The Court of Appeals therefore
should not have set aside as
clearly erroneous the District
Court's findings on these
matters.
Amadeo v. Zant, 486 U.S. , 100 L.Ed.2d
249, 261-62 (1988). There are several
valid reasons why Courts of Appeals should
identify the evidence or lack thereof in
the record upon which they base a reversal
of the trial court's findings. In the
first place, common courtesy to the
district judge, who in this case had spent
substantial time hearing the evidence and
writing his forty page opinion, demands
such an explanation. This point was
30
Clearly recognized as applicable even to
the Supreme Court by Justice Harlan in his
dissent in Crumady v. The JOACHIM HENDRIK
FISSER, 358 U.S. 423, 429 (1959) (dis-
senting opinion), wherein he stated as
follows:
When this Court reverses a
Court of Appeals, particulary on
issues of fact, I think the lower
court is at least due an under-
standable explication of the
reasons.
Such common courtesy should also be
extended to the litigants involved, and to
their counsel, who deserve an explanation
for the court's action. Clearly, such an
explanation should create a higher regard
by the public in general for the functions
and actions of the Courts of Appeals and
the judicial system in general. Further-
more, in this particular case, and possibly
in many others, if the Court of Appeais had
attempted to set forth the basis of its
31
a
ruling rather than merely expressing an
unfounded conclusion, it very possibly
would have discovered its own error as it
would have realized that the evidence in
this case does not support the visceral
feeling upon which it must have based its
conclusion. The mere recitation by the
Court of Appeals of the talismanic phrase,
"after a thorough review of the record",
864 F.2d at 1554, should not deprive Parker
and the other petitioners of their right to
reinstatement of the findings of fact and
judgment thereon in their favor, which were
unquestionably more than adequately
Supported by a permissible view of the
evidence.
With respect to the reversal of the
trial court's finding of liability on
behalf of the Government for the damages
resulting from the CADDO incident, in-
cluding the damage to the PTC 216 and PTC
32
235, Parker relies upon the arguments of
WGN in its Petition for Writ of Certiorari.
33
CONCLUSION
A major underlying issue presented by
this petition is a factual matter which is
normally not an appropriate subject for
consideration by the Supreme Court.
Unfortunately, however, the Court of
Appeals for the Eleventh Circuit exceeded
the bounds of its scope of review in
substituting its own finding, which was not
Supported by the evidence, for the finding
of the District Court, which was clearly
Supported by the evidence. Furthermore, in
making this unwarranted substitution of its
own findings of fact, the Court of Appeals
totally neglected to provide an explanation
for its finding or to cite the evidence or
lack thereof in support of its finding. In
the federal judicial system, the District
Court is the appropriate court to make
findings of fact, and petitioners respect-
fully request the Supreme Court to exercise
34
exercise its supervisory authority over the
Court of Appeals to correct its improper
usurpation of the District Court's
function. Additionally, the Court of
Appeals failed to follow the clear and
settled body of maritime law with respect
to the affirmative defense of act of God
and the burden of proof with respect
thereto, and petitioner respectfully
requests this Court to reinstate those
settled maritime principles and eliminate
the present conflict between the decision
of the Eleventh Circuit and the decisions
of other Courts of Appeal and the Supreme
Court on this matter.
Respectfully submitted,
G. HAMP UZZELK&, I
Attorney and Counsel of
Record for Petitioner Parker
Towing Company, Inc.
35
APPENDIX A
Parker adopts Appendix A to the
Petition for Writ of Certiorari filed by
Warrior & Gulf Navigation Co. as its
Appendix A.
APPENDIX B
Parker adopts Appendix B to the
Petition for Writ of Certiorari filed by
Warrior & Gulf Navigation Co. as its
Appendix B.
Packer adopts Appendix C to the
Petition for Writ of Certiorari filed by
Warrior & Gulf Navigation Co. as its
Appendix
A-3
r eee FSET pagurr og
pecw mos
bee ood ; 7 commana —~ “meneeen wwe -essed Dmsso
eheeeabes
ecre
erPpet
@sPrir
oP
eepsc
eb rst
euvare
orase
BEST AVAILABLE COPY
_—
ag
>
os
=
-_ —-
—
ae
— a — smatell
adde& by
r_Cautisel]
:
APPENDIX
(Time
Park
-— am om
+
7
--i}+-—
_
=
4
L '
uw
, SS ee
T
“|
T
245
pba
Aw s
PS ee ee
om
ES Eo?
—— —- —-—4—, -- ——
=
==
a
—ae
4
a
—
=
AT: : see ol
>
———— od
a
a.
=
>
haadbend
—
CO
—.
cml
=<
—_
=r
wr
CO
APPENDIX F
89L‘89T
GLZ‘°ELT
006’68T
6€S‘S9T
7S9’TST
91S‘0ZT
780’80T
919’00T
TLb’ZL
66%'9S
G1z‘Zb
9b1 ‘LZ
00z’9
aSuWHOSIG
GQNOOES udd
L9° SZ
89° SZ
OT°SSZ
€ET°SSZ
ST°SSZ
ST°SSZ
GT°SSZ
60°SSZ
GT°SSZ
80°SSZ
7T°SSZ
S0°*SSZ
G6°%SZ
SOT S.HudOL
-wdddO udd
NOILWA@Ta
Laada SIdnD TOOd awdaddN
Lo°?tT
6L°2T
os’eT
9E°OT
L$‘S
€v°9
t2£°S
6¢°S
4°
98°72
OT’?
ee°T
67°
SaLVD TZ dO
SaLVS
aADVWUAAY
.9 38 &
§ QV ¢
9 3L
‘TImMd 22? LT
‘Tina 22 61
TIma 32 12
‘tind 3 ET
.9 38 ZT TTMA 3e B
9 38 BT
GWZHANVE
‘Tina 38 Z
.9 28 02
‘9 3 21
‘,9 3e 9
€ 39 OF
‘6 38°24
‘.€ 22
.T 32 9
SaLVWD
¥Z90
0z7S0
8T 0
9EE0
6SZ0
6T70
8070
OvTO
SS00
STt00
6£E7
€Tec
97772
aWnIL
0s9’zSz €°L8T LS°9T .9T 328 Zt *.02 3% 2 ST90
09S‘8SZ L°L8T PI'LtT ,9T 28 OT *.0Z2 2 F 0090
Ove’ v9Z Z°68T vI'LT ,9T 38 OT *.02 38 F O£F0
96E°LEZ L°68T LS° tT .7T 28 G “,.9T 28 6 Oveod
Z¥6'°9TZ 6°88T PI°ET ,ZT 38 OT *.9T 32 BF 00£0
09%’ 66T S°88T 00°2T /7T 228 OT 0zZ0
0S6’S9T 6° L8T CO*OT .OT 28 PT 00Z0
OLL‘66 v’ L8T 00°9 .9 3 PT OvTO
061‘99 7° L8T 00°F .b 2e OT STOO
08L‘SZ vy’ L8I 9E°T 7 ae Gg *.T 28 6 OvEZ
0S0’? O°L8T 1Z° T WE 1h 244
SOT S.uOL
aADUWHOSIG -wudadO dad
GNODaS ad NOILWAZ124 SaALYD
Laaa DIEND 100d uwaddn FOWUAAWV SALVD aWILL
iL'IOH
0 6°98T 6°98T 0660
0 6°98T 6°98T 0060
t’- T° L8T 0°L8T 0€80
t*- y'L8T €°L8T ST90
0 L° Let L°L8t 9090
T*+ T° 681 7° 68T O€%0
0 L°68T L°68T OvE0
e*t- Z°O6T 6°88T 00€0
r 5*t- 8°68T S*88T 0720
- $*t- b° 68T 6°L8T 0020
~ 8°T- 7° 68T p°L8T O¥TO
Z t*= 6° L8T Z7°L8T STOO €8-£-ZT
- ts €°L8T bp’ L8t OVEZ
Ay w*+ 8°98T 0°L8T 0vZZ
: 0 9°98T 9° 98T 0090 €8-Z-ZT
HdWud SOT
ADNAUNAAAIC ONIGUODaY . SHOLWYaAdO aKIL aLva
SNOILWAATA LIOH
APPENDIX I
EXCERPT FROM
UNITED STATES CORPS OF ENGINEERS'
MANUAL EM-1110-2-3600
ENTITLED RESERVOIR AND REGULATION
4-05. OPERATION OF GATED
SPILLWAYS A. General.
Until recent years it was
common practice in the study of
gated spillways to assume that
the reservoir level would not be
permitted to rise above the
static-full-pool elevation near
the dam until all spillway gates
were open, after which reservoir
outflow would be uncontrolled as
long as inflow exceeded the
capacity of the spillway at
static-full-pool elevation.
However, experience in the
operation of gated spillwzys has
shown that significant flood
damages may arise because of the
fact that reservoir releases
under this plan of operation may
be larger during floods cccurring
when the reservoir is full, or
near full, than would have been
the case under natural conditions
before construction of the
reservoir. The operation of
gated spillways because of sudden
increases in the rate of outflow
A-9
may result in damaging flood
wave. For these reasons, insofar
as practicable, reservoirs
controlled by gated spillways
should be designed and operated
to accomplish the following
objectives during periods when
the reservoir is filled or nearly
filled:
(1) Peak rates of reservoir
sed
release during damaging floods
should not exceed peak rates of
the corresponding floods that
would 4 Cc unoff
conditions prevailing before
construction of the reservoir.
(2) The rate of increase in
reservoir releases during a
significant increment of time
should be limited to values that
would not constitute a major
hazard to downstream interests.
b. Methods of Operation.
One of the two basic procedures
discussed below, or combination
thereof, may be followed in
accomplishing the objectives
stated above:
(1) When predictions
indicate that anticipated runoff
from a storm will appreciably
xce e storage ci
emaini i e ir, the
openi spillw ates will be
initiated bef ¢) -
has filled, and will be scheduled
to limit the rate of increase in
fe) Ww cce ble value.
This method of operation
A-10
Fe a
accomplishes the objectives
stated in the preceding para-
graph, but with some sacrifice in
the flood control effectiveness
of storage capacity below the
static-full-pool level.
(2) As an alternative to
the procedure outlined above,
"induced surcharge" storage above
the static-full=pooli—level may be
utilized to exercise partial
control over outflow rates after
the reservoir has filled to the
static-full-pool level.
[Emphasis added. ]
A-11