Amicus Curiae Brief — Orff v. United States
Supreme Court brief2005
Ask Donna
What actually matters in this document.
Text
No. 03-1566
In The
Supreme Court of the United States
°
FRANCIS A. ORFF, et ai.,
Petitiorers,
V.
UNITED STATES OF AMERICA, et al.,
Respondents.
e
On Writ Of Certiorari To The
United States Court Of Appeals
For The Ninth Circuit
e
BRIEF OF CENTRAL ARIZONA
WATER CONSERVATION DISTRICT,
MARICOPA-STANFIELD IRRIGATION &
DRAINAGE DISTRICT, CENTRAL ARIZONA
IRRIGATION AND DRAINAGE DISTRICT
AND ARIZONA DEPARTMENT OF
WATER RESOURCES AS AMICI CURIAE
IN SUPPORT OF RESPONDENTS
+
MARVIN S. COHEN*
SACKS TIERNEY PA.
4250 North Drinkwater Blvd.,
4th Floor
Scottsdale, AZ 85251-3647
(480) 425-2600
*Counsel of Record for
Amici Curiae
{Additional Counsel On Inside Cover]
COCKLE LAW BRIEF PRINTING CO (800) 225-6964
OR CALL COLLECT (402) 342-2831
DOUGLAS K. MILLER
General Counsel
CENTRAL ARIZONA WATER
CONSERVATION DISTRICT
23636 North Seventh Street
Phoenix, AZ 85080-3020
(623) 869-2333
PavtL R. ORME
General Counsel
MARICOPA-STANFIELD IRRIGATION &
DRAINAGE DISTRICT AND CENTRAL ARIZONA
IRRIGATION AND DRAINAGE DISTRICT
1000 Orme Rd., HC 63, Box 3042
Maver, AZ 86333-3042
(623) 465-0445
W. PATRICK SCHIFFER
Chief Counsel
ARIZONA DEPARTMENT OF WATER RESOURCES
500 North Third Street
Phoenix, AZ 85004
602) 417-2420
MARK A. MCGINNIS
SALMON, LEWIS & WELDON, P.L.C.
2850 East Camelback Road, Suite 200
Phoenix, AZ 85016
(602) 801-9060
Attorneys for Central Arizona Irrigation
and Drainage District
DONALD M. PETERS
MILLER, LASoTA & PETERS, PLC
5225 North Central, Suite 235
Phoenix, AZ 85012
(602) 248-2900
Attorneys for Maricopa-Stanfield Irrigation
& Drainage District
TABLE OF CONTENTS
Page
TABLE OF CONTENTS o.oo... cccccccccccccescecceceeseceecseceees, i
TABLE OF AUTHORITIES .00.00.....cccccceccececcecceceececeeeen. iii
IDENTITY AND INTEREST OF AMICI CURIAE ...... 1
Central Arizona Water Conservation District .......... 2
Maricopa-Stanfield Irrigation & Drainage District
and Central Arizona Irrigation and Drainage Dis-
SnINIniAiindithssathdbebenieabscetbensensounisernccsceeesoseseucoseeseeess
I. SECTION 8 OF THE 1902 RECLAMATION
ACT DOES NOT APPLY TO COLORADO
RIVER WATER DELIVERED THROUGH
THE CENTRAL ARIZONA PROJECT...............
A. The Law of the River .......0....ccccccccccccecceseess
The Colorado River Compact................
The 1928 Boulder Canyon Project Act....
Arizona v. California ...........ccccccccceccesees
The 1968 Colorado River Basin Project
i deiiiibiniiiiasindesiecebesesenenteeneeesmsnsieecsone. nes
II. THE FACTS AND LAW APPLICABLE TO
FARMERS IN THE CENTRAL VALLEY PRO-
JECT ARE DIFFERENT FROM THOSE AP-
PLICABLE TO FARMERS IN THE CENTRAL
ARIZONA PROJECT..............cccccccsesescscesessesecsees
i cseeumsorenemeuees
e SF NS
co on Ww
il
TABLE OF CONTENTS -— Continued
Page
The Orff Petitioners ............::::::seeeeeeeeees 19
Smiths in ArizOna...........ccccrccocccsesccesssees 22
California v. United States, Nevada v.
United States, Nebraska v. Wyoming,
and Tches Vv. FO ..........ccccccccsssseseessereseees 22
B. The Allen Orchards Case.........::::::sccseeeeeeees 26
C. Contractual Provisions ..............:::cceeeseeeeeees 28
TET. CONCLUSION .......ccccccscccsscccscscccccscessesssessseseeees 29
ill
TABLE OF AUTHORITIES
Page
CASES
Arizona v. California, 373 U.S. 546 (1963).........0...... passim
Bryant v. Yellen, 447 U.S. 352, reh’g denied, 448
eae ee CETTE iciestasesssciidaliciiadidnnbonteiitaieiatindsditasisdsbeiebese 24, 25
California v. United States, 438 U.S. 645
SEP UTIE ocnsicaniehdecdeaniiasianiernitincinaiiamadiniiilie oabiendiied 21, 22, 23, 24, 25
City of Fresno v. California, 372 U.S. 627 (1963)....... 23, 24
Fox v. Ickes, 137 F.2d 30 (D.C. Cir. 1943)....0.... eee eee 27
H.F. Allen Orchards v. United States, 749 F.2d 1571
es NE Ma ictendihecibctnietihiaisarthiaidesdccinhianiiristiiiicisdau 11, 21, 26, 27
Ickes v. Fox, 300 U.S. 82 (1937).............ccccceeeeeeeees 21, 22, 26
Ivanhoe Irr. Dist. v. McCracken, 357 U.S. 275 (1958) .. 23, 24
John E. Smith, et al. v. Central Arizona Water
I 3
Long v. Salt River Valley Water Users’ Ass’n, 820
Se Ce I II ITT i inciceecsiccintiserrsnictiaiieesmnsniieinntnienndntaaidiliees 25
Nebraska v. Wyoming, 325 U.S. 589 (1945).......... 21, 22, 26
Nevada v. United States, 463 U.S. 110, reh’g denied,
Re es ED siciitittriinitiiiitnittiiccidiidaisiaiiininntans 19, 21, 22, 26
Wyoming v. Colorado, 259 U.S. 419 (1922), decree
paceted, SES U.S. GES (1GB7).......ccccccccocccccsccoccccccscescssess 13
FEDERAL STATUTES AND RULES
Sy I i ON I I a icincsesciensinilieitcsenciteiteiinpiinabaniliiintsiaiala 1
ee St iicstdiniesincniiinarineniensisuniiisainidinbiaisimaiiaitiei 9,10
ii acenicaineiisiisaiintiiiintitniascniniatiaiieiieeiatats 9, 10, 20
iV
TABLE OF AUTHORITIES — Continued
Page
BE, Be i vnctttctctescscestsensccinsssccacnvsnsenssnnsinns 14, 23
GT, Be cctccseitccetccccnsscccccesincsesnnseerenenaneinannnsictnaions 14
I , Bi ct ecsccsntctcscccscinsecncnsecesseneseceensnsnanionsnnessassin 15
GTI AE, Be FE cccciccccecscctescccecscnsssccsesnccsenessanscnssane 19
TE, © isd ssncciceccescncsccessnscccessccnsccssinisarsetnanciavese 19
1902 Reclamation Act, 32 Stat. 388, § 8 ...........0....... passim
Colorado River Compact reprinted in. Ariz. Rev.
RI, Fitts, © Ge cccescccicdsescscecsceustscnssscssosacasevasesesneneses 14
1928 Boulder Canyon Project Act, 45 Stat. 1057,
I I ccccasimncsiednencmnnicanansdbonemianiesnndinniuabiatentidasainiddicisianien passim
1968 Colorado River Basin Project Act, 88 Stat. 885....... 19
Arizona Water Settlements Act, P.L. 108-451.......0............ 1
I TID cscscseichivstetiiaiindsicencbinhiaciesoieiieadanationsinaiaeaeabiiaetiteiads 5
III, cali ia leaeiieiligeidadanniinsnmieiniansenembedubuniines 8
I BNI... <s:cciissincadiinninitininesedsaecaiasunnsadinianainapbadunniesconianiniti 5
ARIZONA CONSTITUTION AND STATUTES
i Ce i TR TE © sccicnuveiccionsencaseieineciemsninnhaiinineanninienn 1
Ariz. Rev. Stat. Ann. § 45-103(B) .................:sseeceseeeeeeeeees 2,8
Ariz. Rev. Stat. Ann. § 45-105(A)(Q) ........ cece eeeeeeeeeeeneeees 7
Ariz. Rev. Stat. Ann. §§ 45-107(A)(1) and (2)............::eeees 8
en 15
Ariz. Rev. Stat. Ann. § 45-1302 to -1310 ............. eens 11
Baier, Tiers Tbe, Bem. FB GiB esc ccccccscoccnascscvcsccesscsocsesssneses 14
TABLE OF AUTHORITIES -— Continued
Page
Ariz. Rev. Stat. Ann. §§ 48-3701 to 3738.....00.....cccccccceseeeeeee 2
Ariz. Rev. Stat. Ann. §§ 48-3702, 48-2901.0.00........cccccceeceeees 1
OTHER AUTHORITIES
Contract for Delivery of Water (“Lake Mead
Contract”), reprinted in Ariz. Rev. Stat. Ann.
RRR USER Ee Nr EP RAC ROSS EE Teno HDC L OER OE A 15
Waters and Water Rights § 47.01(b), at 671 (R.
Sa ci aii a 14
1
IDENTITY AND INTEREST OF AMICI CURIAE'
Three of the amici curiae are defendants in lawsuits
filed by a small group of farmers in two central Arizona
irrigation districts claiming that they are intended benefi-
ciaries of the districts’ Central Arizona Project (“CAP”)
Agricultural subcontracts for Colorado River water. The
lawsuits seek to prevent their irrigation districts from
relinquishing high-priced long-term subcontract water for
low-cost, medium-term water contracts. The relinquish-
ment of the subcontract water is an essential element of
the comprehensive and landmark settlement of CAP water
allocations and repayment obligations and water rights
claims of two major Arizona Indian communities (“Settle-
ment”). The Settlement is embodied-in and authorized by
the recently enacted Arizona Water Settlements Act, P.L.
108-451 (“Settlements Act”).
One of the lawsuits filed by the farmer group is a
federal action against amicus Central Arizona Water
Conservation District (““CAWCD”), now pending on appeal
in the Ninth Circuit (“Federal Case”). The other is a state
* Because the Central Arizona Water Conservation District, thé
Maricopa-Stanfield Irrigation & Drainage District and the Central
Arizona Irrigation and Drainage District are political subdivisions and
municipal corporations of the State of Arizona, they are not required to
obtain consents of the parties to the filing of this brief, and are not
required to make disclosures under U.S. Sup. Ct. R. 37.4, 37.6. Ariz.
Rev. Stat. Ann. §§ 48-3702, 48-2901; Ariz. Const. art. 13, § 7. The
Arizona Department of Water Resources is the agency of the state with
responsibilities for surface water and interstate stream matters with its
own legal staff. It should qualify as a “similar entity” under Rule 37.4.
However, amici are filing with the Court the consents of all parties.
This brief was not authored in whole or in part by counsel for any
party; no person or entity, other than the amici, has made a monetary
contribution to the preparation or submission of this brief.
2
court action against amici Maricopa-Stanfield Irrigation &
Drainage District (“MSIDD”) and Central Arizona Irriga-
tion and Drainage District (“CAIDD”) that is the subject of
a petition for special action recently filed with the Arizone
Supreme Court (“State Case”). See Maricopa Stanfield
Irrigation & District, et al., v. Robertson, Arizona Supreme
Ct. No. CV-04-0385-5A. App. 21.
The fourth amicus is the Arizona Department of
Water Resources (the “Department”), the agency for the
State of Arizona with general control and supervision of
surface water, its appropriation and distribution. Ariz.
Rev. Stat. Ann. § 45-103(B).
The purpose of this amici brief is to support the
Respondents and advise the Court that the issues pre-
sented in the State Case and Federal Case arise from facts
and law that differ, in important ways, from the facts and
law in Orff. The Orff Petitioners’ brief is predicated on
their asserted ownership of appurtenant water rights
under Section 8 of the 1902 Reclamation Act. Congress, in
Section 5 of the 1928 Boulder Canyon Project Act, ex-
empted post-1928 Colorado River water rights from the
application of Section 8. Amici, in this brief, urge the
Court to recognize the important differences between the
issues presented by Orff and the issues currently under
review in the Federal Case and State Case.
Central Arizona Water Conservation District
The Central Arizona Water Conservation District is a
multi-county water conservation district and a political
subdivision in Arizona that has contracted with the United
States for the operation and repayment of the Central
Arizona Project, a federal reclamation project. See Ariz. Rev.
3
Stat. Ann. §§ 48-3701 to -3738.* The CAP annually delivers
to water users in central and southern Arizona 1.5 million
acre feet of Arizona’s entitlement to Colorado River water’
CAWCD was the defendant in case No. CIV 03-0505 in
the United States District Court for the District of Ari-
zona, John E. Smith, et al. v. Central Arizona Water
Conservation District. The plaintiffs in the Federal Case
(hereinafter, “Smiths”) were landowners in two Arizona
irrigation districts - MSIDD and CAIDD (collectively, the
“Irrigation Districts”). Each of the Irrigation Districts was a
party to an Agricultural subcontract with CAWCD and the
United States (“Subcontract”) pursuant to which the
District was to purchase and receive Colorado River water
through the CAP. Smiths were not parties to the Subcon-
tracts, but asserted in the-litigation that they were third-
party beneficiaries. On September 12, 2003, Judge Earl H.
Carroll ruled that Smiths were not third-party beneficiaries
and dismissed the case. App. 1. Smiths have appealed to the
Ninth Circuit, matter No. 03-16962. The appeal has been
fully briefed and is currently pending before that court.
Maricopa-Stanfield Irrigation & Drainage District
and Central Arizona Irrigation and Drainage District
MSIDD and CAIDD are irrigation districts in Pinal
County, Arizona and are parties to long-term Agricultural
* CAWCD and the Secretary in 1972 entered into a Master
Repayment Contract for the delivery of Colorado River water through
the CAP and for the repayment of the allocable costs of the Project. This
Contract was superseded and replaced by the 1988 Master Contract.
See App. 94, and { 9 Joint Statement of Facts, App. 88.
* For the purposes of this brief, the term “Colorado River water”
means post-1928 Colorado River water released from Hoover Dam
pursuant to the Boulder Canyon Project Act of 1928.
4
CAP Subcontracts with the United States and CAWCD.*
App. 159. The Subcontracts provide for the delivery of
Colorado River water to the Irrigation Districts and
govern the terms of its purchase by each Irrigation Dis-
trict. The individual landowners within the Irrigation
Districts were not parties to the Subcontracts.
The farmers in the Irrigation Districts have never
been able to afford to buy CAP water at the price set by
the Subcontracts. For that reason, neither District has
ever received any CAP water pursuant to its Subcontract.
Exhibit A to CAIDD Statement of Facts, Affidavit of Paul
Orme, 7 9, App. 205. In 1993, when construction of the
CAP was completed, the Irrigation Districts advised
CAWCD that they could not afford to pay the price dic-
tated by the Subcontracts. The Irrigation Districts and
CAWCD dealt with the problem by entering into ten-year
Excess Water Contracts in 1994 that allowed the Districts
to purchase “excess” CAP water at affordable rates. Id.
The Irrigation Districts did receive CAP water pursuant to
the Excess Water Contracts. Those agreements expired at
the end of 2003. Ibid; CAIDD Statement of Fats, {{ 16-
23, App. 197-200.
In 2002, CAWCD entered into the Arizona Water
Settlement Agreement (“Settlement Agreement”) with the
Arizona Department of Water Resources and the United
meted
‘ The Subcontracts with the Irrigation Districts were entered into
__pursuant to the Master Repayment Contract. Except for the names of
each District and subarticle 4.13(a) stating the amount of the Subcon-
tractor’s water entitlement, the terms of the Subcontracts of the
Irrigation Districts are identical. Joint Statement of Facts, J 18, App.
89.
5
States through the Secretary of the Interior (“Secretary”).’
App. 60. The Settlement Agreement established the
processes for implementing the Settlement embodied in
the Settlements Act enacted by Congress on November 17,
2004 and signed by the President on December 10, 2004.
CAWCD, in December 2002 pursuant to the Settlement
Agreement, adopted a new policy for marketing excess
water to irrigation districts. Under this policy, the districts
were offered new contracts for the purchase of excess CAP
water at low rates through 2030 in exchange for relin-
quishment of their CAP Agricultural Subcontract alloca-
tions. Districts could retain Subcontract water rights, but
no district would be allowed to purchase excess CAP water
at the low price until it had ordered and paid the full price
for any Subcontract water it had retained. See Settlement
Agreement, subparagraphs 6.3, 6.4, App. 70-71.
Pursuant to the Settlement Agreement, CAWCD
offered a package of benefits to each Irrigation District in
exchange for relinquishment of its subcontract rights Id.
{1 7, 8, App. 72-75. Both of the Irrigation Districts held
elections to determine whether landowners favored the
District’s relinquishment of subcontract water rights in
return for the various benefits that were offered. A major-
ity of the votes cast in each of the Irrigation Districts
favored the proposed relinquishment. CAIDD Statement of
Facts, Affiaavit of Paul Orme, {{ 18, 24, App. 207-208.
In 2001, Smiths with approximately thirty-nine other
landowners, filed a civil action in the Pinal County Superior
* While the United States did not execute the Settlement Agree-
ment in 2002, the Settlements Act authorizes and directs the Secretary
to execute the Settlement Agreement. See § 2 (34), § 106(a)(2).
6
Court against the Irrigation Districts. Smith et al. v.
Maricopa-Stanfield Irrigation & Drainage District, et al.,
No. CV 2001-00924.° The action sought to prevent the
Irrigation Districts from relinquishing any of the CAP
Subcontract water in which Smiths claimed appurtenant
ownership interests.’ Over two hundred landowners joined
the Irrigation Districts in defending against Smiths in the
State Case.
In December, 2003, Smiths moved for partial sum-
mary judgment. The Irrigation Districts and defendant
landowners filed cross-motions for summary judgment. On
November 16, 2004, the trial court entered its minute
entry ruling granting summary judgment to Smiths. App.
14. The state trial court held that rights to Colorado River
water under the CAP subcontracts were appurtenant to
Smiths’ land and that rights under each of the Agricul-
tural CAP Subcontracts were contractually vested in the
landowners and enforceable by them. The trial court also
held that the landowners were intended third-party
beneficiaries of the CAP Subcontracts and that an Irriga-
tion District could not modify its Subcontract in any way
that would affect a landowner’s purported appurtenant
rights without that landowner’s consent.
* Plaintiffs in the State Case will also be collectively referred to
herein as “Smiths”.
’ Of the 293,795 acre-feet of Agriculcural CAP water potentially
available to the Secretary for the Settlement, up to 180,000 acre-feet
were to be relinquished by the Irrigation Districts. Settlement Agree-
ment, subpara. 4.1.5, Table 5.1.4, App. 64-66, 68. If the two Irrigation
Districts are not able to relinquish this water, the Secretary will not
receive the 197,500 acre-feet required to implement the Settlement.
(293,795 minus 180,000 equals less than 197,500.)
7
On December 14, 2004, the Irrigation Districts and
200 landowners filed a Petition for Special Action with the
Arizona Supreme Court, urging the Court to take special
action jurisdiction because of the state-wide importance of
the case and to reverse the lower court’s ruling. App. 21°
On pages 1 through 5 of the Petition, the elements of the
Settlement and their importance to Arizona are described.
The Arizona Department of Water Resources
The Department is the agency for the State of Arizona
with general control and supervision of surface water, its
appropriation and distribution. Ariz. Rev. Stat. Ann. § 45-
103(B). The Director of the Department is charged with
the duty of prosecuting and defending “all rights, claims
and privileges of this state [the State of Arizona] respect-
ing interstate streams,” which includes the Colorado River.
Ariz. Rev. Stat. Ann. § 45-105(A)(9). |
The Director is also authorized, on behalf of the State
of Arizona, to consult, advise and cooperate with the
Secretary of the United States Department of the Interior
(“Secretary”) in the exercise of the Secretary's authority
under the Boulder Canyon Project Act as well as the
Secretary's authority to contract for the delivery of water
from the main stream of the Colorado River for use within
* Briefs amicus curiae have been filed with the Arizona Supreme
Court in support of the Petition for Special Action by the Arizona
Department of Water Resources, CAWCD, the Gila River Indian
Community, the Cities of Scottsdale, Mesa, Chandler, Glendale, and.
Goodyear, the Hohokam Irrigation & Drainage District and San Carlos
Irrigation & Drainage District, and the Salt River Project.
8
the State of Arizona. Ariz. Rev. Stat. Ann. § 45-107(A)(1)
and (2).
The Department has a strong interest in the trial
court’s ruling in the State Case and in the appellate result
in the Federal Case for two reasons. If landowners are
held to be intended beneficiaries of the Irrigation Districts’
Agricultural CAP Subcontracts, with the power to prevent
relinquishment of Subcontract water, the landmark
Settlements Act cannot be implemented. The Agricultural
CAP Subcontract water voluntary relinquished by agricul-
tural CAP subcontractors (such as the Irrigation Districts)
is to be used by the United States to settle current and
future Indian water claims. If agricultural subcontractors
fail to relinquish sufficient CAP water to enable the
Secretary to make the required reallocations, the Settle-
ment Act will fail.
The Settlement Act also allocates up to 96,295 acre-feet
of relinquished water to the Director of the Department for
future reallocation to Arizona non-Indian municipal and
industrial water users. PL. 108-451, § 104(a\(2). Conse-
quently, the Department has a specific interest in ensuring
that the Settlement Act is implemented.
Summary
The question presented in the Orff petition before this
Court appears, on its face, to be the same question that
was ruled on by the Arizona District Court in the Federal
Case and by the trial court in the State Case. The underly-
ing facts and law in the Orff matter are, however, signifi-
cantly different from the facts and law in the Federal Case
and the State Case. The Orff matter involves the San Luis
Unit of Central Valley Project, a Reclamation project in
9
California on the San Joaquin River that is subject to
Section 8 of the Reclamation Act. Amici express no view as
to whether Section 8 confers on the Orff Petitioners the
rights they assert, but even if it did, the Federal Case and
State Case involve the Central Arizona Project, a Recla-
mation project in Arizona for the delivery of water from
the Colorado River. The delivery of Colorado River water is
not subject to Section 8 of the Reclamation Act.
Amici have a direct interest in ensuring that the
differences between the Orff case and the Arizona cases in
which they are parties are called to the attention of this
Court so that the Court’s decision is made with recognition
of these differences. At stake for the amici and for the
state of Arizona as a whole is the preservation and imple-
mentation of the Settlement twenty years in the making
that was recently authorized by Congress and the Presi-
dent.
¢
SUMMARY OF ARGUMENT
The Orff petition before this Court presents the
question of whether farmers in an irrigation district’ that
is governed by California law and located in a Reclamation
project’ that is subject to Section 8 of the 1902 Reclama-
tion Act (43 U.S.C. §§ 372, 383) are intended third-party
beneficiaries of their irrigation district’s water service and
repayment contracts with the United States.
* Westlands Water District.
The San Luis Unit of the Central Valley Project.
10
The Federal Case and the State Case in which these
Arizona amici are involved present the questions of:
1) whether landowners in an Arizona irrigation dis-
trict receiving Central Arizona Project water are
owners of Colorado River water rights appurte-
nant to their land, and
2) whether they are intended third-party beneficiar-
ies of the master repayment contract between
CAWCD and the Secretary and the Subcontracts
among CAWCD, the Irrigation Districts and the
Secretary.
Petitioners describe the history and scope of the
Reclamation program undertaken by the United States,
through the Secretary and the Bureau of Reclamation
(“Bureau”) beginning in 1902. Petitioners’ Brief on the
Merits, at 4. Although the description is generally accu-
rate, it does not take into account the often unique circum-
stances of the individual Reclamation projects in the
program. For instance, Petitioners cite Section 8 of the
1902 Reclamation Act as support for their assertion that
“(p)roperty rights are a key feature of the Reclamation
program.” Jd. at 3. Section 8 provides that state laws shall
govern the control, appropriation, use ane distribution of
water used in irrigation and that the “right to the use of
water” acquired under state laws “shall be appurtenant to
the land irrigated, and beneficial use shall be the basis,
the measure, and the limit of the right.” Reclamation Act
of 1902, c. 1093, § 8, 32 Stat. 388, 43 U.S.C. §§ 372, 383.
The general effect of Section 8 is that state water law
governs the acquisition of water rights for Reclamation
projects, but Section 8 does not apply to water rights in all
Reclamation projects.
11
In particular, it does not apply to post-1928 rights in
Colorado River water. Post-1928 Colorado River water is
not allocated among the basin states, or between users
within those states, based upon prior appropriation or
other state law principles. Instead, the seven Colorado
River Basin states allocated the river between the Upper
and Lower Basins by interstate compact in 1922;" and
Congress, in the 1928 Boulder Canyon Project Act, 45 Stat.
1057 (“1928 Act”), allocated rights to the river among the
three Lower Basin states (California, Arizona, and Ne-
vada) and granted the Secretary of the Interior expansive
authority to allocate and contract for the delivery of
Colorado River water to the various entities within the
states.
After 1928, Colorado River water could be used only
by contract with the Secretary, not under or pursuant to
state water law. The decision of this Court in Arizona v.
Caifornia, 373 U.S. 546 (1963), clearly confirmed that
Section 8 is superseded by the body of law that governs the
Colorado River, known collectively as “the Law of the
River.”
The Petitioners in Orff base their claim of intended
beneficiary status on their ownership of water rights
appurtenant to their land, pursuant to Section 8; the
decision of the Federal Circuit Court in H.F Allen Or-
chards v. United States, 749 F.2d 1571 (Fed. Cir. 1984);
and other general federal Reclamation court decisions.”
" Reprinted in Ariz. Rev. Stat. §§ 45-1302 to -1310; Boulder
Canyon Project Act § 13(a), (45 Stat. 1057, 1064).
* Amici are not here agreeing with the Orff Petitioners that the
ownership of appurtenant water rights is determinative of third party
beneficiary status. That status is generally determined on the basis of
(Continued on following page)
12
The status of users of Colorado River water in the Central
Arizona Project is, however, clearly not governed by
Section 8 and these non-Colorado River cases. Amici
request that this Court affirm the lower court’s decision. If,
however, the Court reverses that decision, we urge the
Court to recognize in its opinion the fundamental and
important differences between the Central Valley Project
and the Central Arizona Project.
¢
ARGUMENT
I. SECTION 8 OF THE 1902 RECLAMATION ACT
DOES NOT APPLY TO COLORADO RIVER WA-
TER DELIVERED THROUGH THE CENTRAL
ARIZONA PROJECT.
A. The Law Of The River
1. The Colorado River Compact
The Colorado River is a navigable watercourse that
flows through seven states and Mexico. See Arizona uv.
California, 373 U.S. 546, 552 (1963). Non-Indians in
several areas along the Colorado first began diverting
water from the river in the late 1800s. See id. The erratic
nature of the river resulted in alternating periods of floods
and droughts during this time. Jd. at 553. The early
farmers in southern California who had been diverting
Colorado River water through the Alamo Canal, as well as
a few early users in other states, desired to obtain federal
the clear intent of the parties as expressed in the contract. However,
since the focus of Petitioners’ argument is on Section 8 and asserted
appurtenant water rights, amici primarily address those issues in this
brief.
—_—-———
13
funding to build flood control and water storage and
transmission facilities on the river. Jd. At the same time,
residents and potential users outside California were
concerned that the “first in time, first in right” principles
of prior appropriation water law might be applied to the
river, so that the early California users would acquire a
superior right to all or most of the water from the river. Id.
These residents outside California were concerned that
this problem would be further exacerbated if the Federal
Government spent money to promote additional early use
in California.”
To address these concerns, in 1922 representatives of
the seven Colorado River Basin states met for several
months to discuss an agreement to allocate water from the
river. Unable to agree upon an allocation among the
individual states, they settled on an allocation between the
“Upper Basin” (the area above Lee Ferry in the Grand
Canyon) and the “Lower Basin.” This compromise is
embodied in the 1922 Colorado River Compact. See id. at
* See id. at 555-56 (“The prospect that the United States would
undertake to build a national project .. . brought to life strong fears in
the northern basin States that additional waters made available by the
storage and canal projects might be gobbled up in perpetuity by faster
growing lower basin areas, particularly California. .. . These fears were
net. without foundation, since the law of prior appropriation prevailed
in most of the Western States.... In 1922, ... [the United States
Supreme Court] held that the doctrine of prior appropriation could be
given interstate effect... . Nevada, Utah, and especially Arizona were
all [also] apprehensive that California’s rapid declaration of appropriat-
ive claims would deprive them of their just share of basin water
available after construction of the proposed United States project.”)
(citing Wyoming v. Colorado, 259 U.S. 419 (1922), decree vacated, 353
U.S. 953 (1957), which had applied prior appropriation in a dispute
between two states, where both states applied prior appropriation in
their internal water allocation).
—
14
557-58; see also Coiorado River Compact, reprinted in Ariz.
Rev. Stat. Ann. § 45-1311.
Although Arizona’s representative signed the Com-
pact, the Compact required that it be ratified by the
respective legislatures of the signatory states. The Arizona
Legislature refused to ratify the Compact, largely based
upon continued concerns that the Lower Basin’s share of the
river had not been divided among Arizona, California, and
Nevada and the possible implications of prior appropriation
law on such a future division. Arizona v. California, 373
U.S. at 559-60."
2. The 1928 Boulder Canyon Project Act
Congress eventually authorized construction of the
proposed Boulder Canyon Project over Arizona's objection,
passing the Boulder Canyon Project Act in 1928, 45 Stat.
1057, codified at 43 U.S.C. §§ 617-617t. The 1928 Act gave
the Secretary of the Interior control over the allocation of
Colorado River water among the individual states and
among the various entities within those states. The Act
also authorized the Secretary to enter into contracts with
Arizona, California, and Nevada, with an allocation of
Colorado River water as follows: Arizona — 2.8 million
acre-feet (“MAF”); California — 4.4 MAF; and Nevada — 0.3
MAF. See id. § 617c. Arizona entered into a contract with
* “The concept of an allocation between basins quieted the fears of
Upper Basin states that California would grab water to their detriment.
But Arizona, lying largely in the Lower Basin, still feared that the
neighboring Lower Basin state of California would get virtually all the
water that new federal facilities would make available below Lee Ferry.
Consequently, Arizona refused to ratify the compact.” Waters and Water
Rights § 47.01(b), at 671 (R. Beck, ed.) (1996).
15
the Secretary for its 2.8 MAF in 1944. See Contract for
Delivery of Water (“Lake Mead Contract”), reprinted in
Ariz. Rev. Stat. Ann. § 45-1301. Section 5 of the 1928 Act
provided that state law for allocating water did not apply
to post-1928 uses of Colorado River:
The Secretary of the Interior is hereby au-
thorized, under such general regulations as he
may prescribe, to contract for the storage of wa-
ter in said reservoir and for the delivery thereof
at such points on the river and on said canal as
may be agreed upon, for irrigation and domestic
uses. ... No person shall have or be entitled
to have the use for any purpose of the water
stored as aforesaid except by contract made
as herein stated.
43 U.S.C. §617d (emphasis added). Section 5 further
stated that “[clontracts for the use of water ... shall be
made with responsible applicants therefor who will pay
the price fixed by the said Secretary with the view of
meeting the revenue requirements herein provided for.”
Id. § 617d(c).
3. Arizona v. California
The 1928 Act clearly established that Colorado River
water is allocated exclusively by contract with the Secre-
tary. Although this basic tenet of the Law of the River was
set forth in 1928, this Court in Arizona v. California made
it even more clear. The Court discussed the history of
regulation and allocation of the Colorado River and upheld
the Secretary's broad authority to allocate such water
among the three Lower Basin states and between individ-
ual entities in the various states by entering into water
delivery contracts with those entities. The Court stated
16
that, having authorized the use of federal money to build
projects on the Colorado River in the 1928 Act, Congress
clearly established that the Federal Government would
control the use of water from those projects:
Having undertaken this beneficial project, Con-
gress, in several provisions of the [1928] Act,
made it clear that no one should use mainstream
[Colorado River] waters save in strict compliance
with the scheme set up by the Act. Section 5 au-
thorized the Secretary [of the Interior] “under
such general regulations as he may prescribe, to
contract for the storage of water in said reservoir
and for the delivery thereof at such points on the
river * * * as may be agreed upon, for irrigation
and domestic uses * * * .” To emphasize that wa-
ter could be obtained from the Secretary alone,
17
get water. The general authority to make con-
tracts normally includes the power to choose with
whom and upon what terms the contract will be
made. When Congress in an Act grants authority
to contract, that authority is no less than the gen-
eral authority, unless Congress has placed some
limit on it.... Significantly, no phrase or provi-
sion indicating that the Secretary’s contract power
was to be controlled by the law of prior appropria-
tion was substituted either then or at any time be-
fore passage of the Act, and we are persuaded that
had Congress intended so to fetter the Secretary’s
direction, it would have done so in clear and un-
equivocal terms, as it did in recognizing “present
perfected rights” [i.e., those rights acquired prior
to passage of the 1928 Act] in § 6.
§ 5 further declared, “No person shall have or be Id. at 580-81 (emphasis added).
entitled to have the use for any purpose of the ' + ter ,
water stored as aforesaid except by contract h baad eanasng v. California this Court, after discussing
mate on basen chee’ * the Reclamation Act and the 1928 Act, stated:
373 US. at 579-80. ... [W]e hold that the Secretary in choosing be-
tween users within each State and in settling the
Basing its analysis on the express statements by terms of his contracts is not bound by these sec-
tions [e.g., Section 8 of the Reclamation Act] to
follow state law.... While the States were gen-
erally free to exercise some jurisdiction over
Congress in the 1928 Act, the Court reiterated that con-
tracts with the Secretary were the exclusive means to
allocate legal rights to the waters of the Colorado River, these waters before the Act .
both as among the states and among individual users right was subject to re Pedensd P saad
within the states: right to regulate and develop the river....
[W]here the Secretary’s contracts, as here, carry
out a congressional plan for the complete distri-
bution of waters to users, state law has no
place.
These several provisions, even without legis-
lative history, are persuasive that Congress in-
tended the Secretary of the Interior, through
his § 5 contracts, both to carry out the allo-
cation of the waters of the main Colorado .
River among the Lower Basin States and to oe a SODSS Cemphante altel.
decide which users within each State would
18
This Court recognized that federal Reclamation projects
for the use of Colorado River water are inherently different
from other projects and water rights, even those other
projects constructed pursuant to the 1902 Reclamation Act.
With respect to the interstate and international Colorado
River, the Federal Government plays a more pervasive role
in constructing and operating project facilities and promoting
repayment of costs. The Court concluded its description of
the broad authority of the Secretary to contractually allocate
Colorado River waters as follows :
All this vast, interlocking machinery — a
dozen major works delivering water according to
congressional fixed priorities for home, agricul-
tural, and industrial uses to people spread over
thousands of square miles — could function effec-
tively only under unitary management, able to
formulate and supervise a coordinated plan that
could take account of the diverse, often conflicting
interests of the people and communities of the
Lower Basin States. Recognizing this, Congress
put the Secretary of the Interior in charge of these
works and entrusted him with sufficient power,
principally the § 5 contract power, to direct, man-
age, and coordinate their operation. Subjecting the
Secretary to the varying, possibly inconsistent,
commands of the different state legislatures could
frustrate efficient operation of the project and
thwart full realization of the benefits Congress in-
tended this national project to bestow. We are satis-
fied that the Secretary's power must be construed
to permit him, within the-boundaries set down in
the Act, to allocate and distribute the waters of the
mainstream of the Colorado River.
373 U.S. at 589-90.
19
4. The Colorado River Basin Project Act
The Secretary’s exclusive power to allocate the waters
of the mainstream of the Colorado River was reaffirmed in
1968 when Congress passed the Colorado River Basin
Project Act (“1968 Act”), authorizing construction of the
Central Arizona Project. See 43 U.S.C. §§ 1501 to 1556.
The 1968 Act also provided for the Secretary to enter into
“master contracts” for the repayment of CAP construction
costs with a single political subdivision of the State of
Arizona. Id. § 1524. The 1968 Act expressly stated that it
“shall not be construed to alter, amend, repeal, modify, or
be in conflict with” the 1922 Compact, this Court’s 1963
Arizona v. California decision, or other portions of the Law
of the River. 43 U.S.C. § 1551(a).
Il. THE FACTS AND LAW APPLICABLE TO FAR-
MERS IN THE CENTRAL VALLEY PROJECT
ARE DIFFERENT FROM THOSE APPLICABLE
TO FARMERS IN THE CENTRAL ARIZONA
PROJECT.
A. Water Rights
1. The Orff Petitioners
The Petitioners in Orff claim their water rights under
California law and the doctrine of prior appropriation as
applied to federal Reclamation projects by Section 8 of the
1902 Federal Reclamation Act. Congress passed the
Reclamation Act for the purpose of having the Federal
Government play a more prominent role in the develop-
ment of the West, particularly with respect to the devel-
opment of water resources. See Nevada v. United States,
463 U.S. 110, 115, reh’g denied, 464 U.S. 875 (1983). At the
same time, however, the states were concerned about
20
Federal interference in internal water matters. For that
reason, Congress included Section 8 of the act, which
provides:
Nothing in this Act shall be construed as af-
fecting or intended to affect or to in any way in-
terfere with the laws of any State or Territory
relating to the control, appropriation, use, or dis-
tribution of water used in irrigation, or any vested
right acquired thereunder, and the Secretary of the
Interior, in carrying out the provisions of this Act,
shall proceed in conformity with such laws, and
nothing herein shall in any way affect any right of
any State or of the Federal Government or of any
landowner, appropriator, or user of water in, to, or
from any interstate stream or the waters thereof.
43 U.S.C. § 383. Therefore, for most federal Reclamation
projects, all water rights must be acquired pursuant to
state law. For those projects, individual users (or a water
users’ associations acting expressly on behalf of those
individual users) follow state-mandated procedures in
order to obtain appropriative rights to water, and those
water rights are allocated on a “first in time, first in right”
basis. In those situations, the fact that an individual owns
land within the boundaries of a federal Reclamation
project does not give that person a right to use water
unless the water right acquisition procedures under state
law have been satisfied.
According to Petitioners, the landowners in the San
Joaquin Valley applied to the State of California to estab-
lish surface water rights on the basis of prior appropria-
tion under California law. In order to proceed with the San
Luis Unit of the Central Valley Project, the landowners
assigned their state applications to the United States,
21
which proceeded to obtain water rights under state law.
See Petitioners’ Brief on the Merits, at 4-6. The contracts
between the Westlands Water District and the United
States contain provisions referring to the farmers’ right to
use the water and indicate a remedy for not receiving the
water “of anyone claiming such right or remedy by or
through the District.” Jd. at 20. Each of the contracts was
made pursuant to the federal Reclamation law, including
Section 8 of the 1902 Act. The Orff Petitioners cite four of
this Court’s decisions for the proposition that the farmers
who apply the water in a Reclamation project to their land
“equitably own, property rights in the water which are
appurtenant to their lands. Nevada v. United States, 463
U.S. 110, 121-28 (1983); California [v. United States, 438
U.S. 645 (1978)] at 664, 653, 665, 667; Nebraska v. Wyo-
ming, 325 U.S. 589, 611-16 (1945); Ickes v. Fox, 300 U.S.
82, 93-96 (1937).” Petitioners’ Brief on the Merits, at 21.
They also rely on Allen Orchards, in which the court
stated: “it was undisputed that appellants [landowner/
farmers] have a property right in the water to the extent
of their beneficial use thereof.” Jd. at 26; Allen Orchards,
749 F.2d at 1576.
The Orff Petitioners summarize their position regard-
ing ownership and appurtenance of the water rights as
follows:
The farmers equitably own the water rights
which were perfected and are preserved by their
use of the very water sold and delivered under
the 1963 contract. They do not simply enjoy an
indirect economic benefit as a result of its use.
They hold a property right in its usage which is
appurtenant to their lands.
Id.
22
2. Smiths in Arizona
The contrast between the Orff Petitioners and Smiths
in the Arizona cases is striking. Smiths made no efforts to
acquire appropriative rights in Colorado River water
under Arizona law and no efforts to assign any such rights
to the United States for the Central Arizona Project.
Unlike the situation in the San Luis Unit of the Central
Valley Project, the Secretary needed no state law water
rights to establish and operate the CAP. Again, unlike the
San Luis Unit, there was no need for a landowner to put
the contract water to use in order to perfect and protect a
state water right. And unlike the San Luis Unit, the
provisions of Section 8 of the 1902 Act do not have any
application to Colorado River water delivered through the
Central Arizona Project. So the bases on which the Orff
Petitioners claim appurtenant water rights simply do not
exist with regard to the Central Arizona Project.
3. California v. United States, Nevada v.
United States, Nebraska v. Wyoming,
and Ickes v. Fox
The four Supreme Court cases Petitioners cite for
their assertion of equitable ownership of appurtenant
water rights all rely on Section 8 and do not involve
Colorado River water.
a. California v. United States
In California v. United States, the dispute involved
rights to the Stanislaus River under the Central Valley
(California) Project. 438 U.S. at 645. The Bureau of Rec-
lamation, on behalf of the Project landowners, applied for
a permit to appropriate water from the California State
23
Water Resources Control Board. Jd. at 652. Although the
controversy in the case involved what conditions the State
Board could impose on the Bureau’s application, there was
no disagreement that Section 8 of the Reclamation Act
required the Bureau to apply for a state law prior appro-
priative right. See id.
Although one could argue that California v. United
States overturned the general holding in Arizona v. Califor-
nia with respect to the 160-acre limitation by “disavow|[ing]
the dictum” from Jvanhoe and City of Fresno,” it cannot be
said that the California v. United States Court overturned
the Arizona v. California decision regarding the suprem-
acy of Section 5 of the 1928 Act over Section 8 of the
Reclamation Act with respect to Colorado River water
delivery rights.
The California v. United States Court itself acknowl]-
edged the independent basis for the Court’s holding in
Arizona v. California:
In Arizona v. California, the States had
asked the Court to rule that state law would con-
trol in the distribution of water from the Boulder
Canyon Project, a massive multistate Reclama-
tion project on the Colorado River. After review-
ing the legislative history of the Boulder Canyon
Project Act, 43 U.S.C. § 617 et seg., the Court
concluded that because of the unique size and
multistate scope of the Project, Congress did not
intend the States to interfere with the Secre-
tarys power to determine with whom and on
what terms water contracts would be made.
* Ivanhoe Irr. Dist. v. McCracken, 357 U.S. 275 (1958); City of
Fresno v. California, 372 U.S. 627 (1963).
24
While the Court in rejecting the States’
claim repeated the language from Ivanhoe
and City of Fresno as to the scope of § 8,
there was no need for it to reaffirm such
language except as it related to the singular
legislative history of the Boulder Canyon
Project Act.
438 U.S. at 674 (emphasis added, citations omitted). Thus,
the California v. United States Court acknowledged that,
as to the allocation and use of Colorado River water, the
specific provisions of Section 5 of the 1928 Act controlled
over the general provisions in Section 8 of the Reclamation
Act.
Courts since California v. United States have agreed
that any criticism or limitation of Arizona v. California in
that opinion related to the scope of Section 8 in a general
sense and not to the interaction between Section 5 and
Section 8. For example, in 1980, this Court was faced with
the 160-acre limitation issue with respect to the Imperial
Valley farmers in California. Bryant v. Yellen, 447 USS.
352, reh’g denied, 448 U.S. 911 (1980). Noting the discus-
sion of Arizona v. California in California v. United States,
the Bryant court stated:
In Arizona v. California, we held that the
[1928 Act] vested in the Secretary the power to
contract for project water deliveries independent
of the direction of § 8 of the Reclamation Act to
proceed in accordance with state law and of the
admonition in § 18 of the [1928 Act] not to inter-
fere with state law. ... In terms of Reclamation
law generally, the import of the Court’s opinion
in this respect was considerably narrowed in
California v. United States, 438 U.S. 645, 98
S. Ct. 2985, 57 L.Ed.2d 1018 (1978), but the
25
latter case did not question the description
of the Secretary’s power under the [1928
Act] itself.
447 US. at 370-71 & n.21 (emphasis added).
The Ninth Circuit came to the same conclusion in an
appeal of a subsequent Arizona case. Long v. Salt River
Valley Water Users’ Ass’n, 820 F.2d 284 (9th Cir. 1987). In
that opinion, the court stated:
Neither section 8 of the 1902 [Reclamation]
Act nor the [1928 Act’s] general statement of in-
tent not to interfere with the states’ rights to
regulate water use within their borders, 43
U.S.C. §617q, requires the Secretary to follow
state law in allocating water among users within
a particular state. Arizona v. California, 373 U.S.
at 585-86, 83 S.Ct. at 1490. The Supreme Court
in California v. United States, 438 U.S. at 674-
75, 83 S.Ct. at 3000-01, disavowed dictum in Ari-
zona v. California, 373 U.S. at 586-87, 83 S.Ct. at
1490-91, that 1902 [Reclamation] Act § 8 did not
require the Secretary to comply with state law in
distributing project water, even when that state
law was not inconsistent with specific federal
statutory requirements. However, the California
v. United States decision “did not question the
description of the Secretary’s powers under [1928
Act] itself.” Bryant v. Yellen, 447 U.S. 352, 370 n.
21, 100 S. Ct. 2232, 2242 n. 21, 65 L.Ed.2d 184
(1980).
820 F.2d at 287 n.4 (emphasis added).
The Arizona v. California decision that Section 5 of
the 1928 Act supersedes Section 8 of the 1902 Reclamation
Act with respect to Colorado River water remains the law.
California v. United States did not address and does not
26
apply to Colorado River Water delivered through the
Central Arizona Project.
b. Ickes v. Fox, Nebraska v. Wyoming,
and Nevada v. United States
Ickes v. Fox established in 1937 that landowners in
the Yakima Project who put Reclamation project water to
beneficial use on their lands acquired an appurtenant
water right under state law. The decision was based on
Section 8 of the 1902 Reclamation Act. In 1945, this Court
cited Ickes with approval-in Nebraska v. Wyoming and
again held that, pursuant to Section 8 of the 1902 Recla-
mation Act, individual landowners who appropriate
Reclamation project water and put it to beneficial use
acquire an appurtenant water right. Neither Ickes nor
Nebraska was held in Arizona v. California in 1963 to be
applicable to the Colorado River.
Again in Nevada v. United States, this Court cited
Ickes and Nebraska in holding that landowners in the
Newlands Reclamation Project held appurtenant benefi-
cial interests in the water rights when the water was put
by them to beneficial use on the land. Section 8 of the 1902
Reclamation Act clearly applied te the Newlands Reclama-
tion Project. That project deals with the Truckee River and
the Carson River. It does not involve any Colorado River
water. The Nevada decision also has no application to the
delivery of Colorado River water.
B. The Allen Orchards Case
The Orff Petitioners cite Allen Orchards as the semi-
nal federal decision establishing the principle that owner-
ship of the water rights in a Reclamation project gives the
27
landowners third-party beneficiary status under the
project’s water service and repayment contracts. In Allen
Orchards, the Federal Circuit Court of Appeals, after
holding that the plaintiff irrigators had failed to state a
claim for relief, stated that the landowner farmers as
“owners” of the water were “intended beneficiaries of the
1945 Consent Decree.” 749 F.2d at 1576. The basis for this
statement that the farmers were owners of the water was
the decision in Fox v. Ickes, 137 F.2d 30 (D.C. Cir. 1943).
There, the court held that irrigators in the Yakima Project
in Washington owned a property right acquired by the
beneficial use of water and went on to state that “the
water-rights here are not based upon the construction or
enforcement of contracts with the government.” Jd. at 35.
The project in Allen Orchards was also the Yakima Project
in Washington - a traditional Reclamation project of the
type described on pages 1-4 of the Petitioner’s Brief on the
Merits where the provisions of Section 8 of the Reclama-
tion Act apply.
The Reclamation project at issue in the Federal Case
and the State Case, in which three of these amici are
involved, is the Central Arizona Project. The CAP is not a
traditional Reclamation project like the Yakima Project.
Because of Section 5 of the 1928 Act, Section 8 does not
apply to Colorado River water. The predicate used by the
Federal Circuit in Allen Orchards for stating that irriga-
tors are intended beneficiaries of Reclamation project
contracts does not exist with regard to Central Arizona
Project water.
28
C. Contractual Provisions
The Orff Petitioners cite a number of provisions in the
contracts between the Bureau and the Westlands Water
District to support their assertion of third-party benefici-
ary status. There are, however, significant differences
between the Westlands contracts and the CAP Agricul-
tural Subcontracts.
¢ The Orff Petitioners rely on Article 15 of the 1963
Westlands contract, which refers to the “right to
any water” furnished thereunder possessed by
any “tract of land or water user” in the district.
Petitioners’ Brief on the Merits, at 28. There is no
such language in the CAP Agricultural Subcon-
tracts. See Subcontract Subarticles 4.1, 4.3, 4.13,
App. 164, 179.
¢ The Orff Petitioners also point to the reference in
Article 9(c) of the Westlands contract to “those”
claiming by, “through or under” the district. Peti-
tioners’ Brief on the Merits, at 30. There is no
such reference in the CAP Agricultural Subcon-
tracts. See Subcontract Subarticle 6.7, App. 189.
¢ The Orff Petitioners assert that references in the
contracts to California law establish that the land-
owners equitably own appurtenant water rights
under the California state law doctrine of prior ap-
propriation and were, as a result, intended benefi-
ciaries under the contracts. Petitioners’ Brief on
the Merits, at 35-36. In contrast, Smiths do not eq-
uitably own appurtenant water rights under the
Arizona doctrine of prior appropriation. That doc-
trine does not apply to the Colorado River after
1928. Only through a contract with the United
States can any right to use Colorado River water
be established. Smiths have no such contract. Nor
have they ever put any Colorado River water
29
received by the Irrigation Districts under their
Subcontracts to any use. The only Colorado River
water the Irrigation Districts have received has
been “excess” CAP water made available under
Excess Water Contracts at a low price, not higher-
priced Subcontract water. See Exhibit A to CAIDD
Statement of Facts, Affidavit of Paul Orme, J 9,
App. 205.
IV. CONCLUSION -
In sum, the arguments presented in the Orff Petition-
ers’ Brief on the Merits are, for the most part, predicated
on their asserted ownership of appurtenant water rights
under Section 8 of the 1902 Act which makes California
law applicable. These arguments do not apply to landown-
ers receiving Colorado River water pursuant to CAP sub-
contracts. Section 8 does not apply, nor does Arizona prior
appropriation law. Whether the Orff Petitioners are or are
not third-party beneficiaries of the Westlands contracts or
the 1963 stipulated judgment, there can be no uniform rule
that landowners in all federal Reclamation projects are
always third-party beneficiaries of contracts between
irrigation districts and the United States. A separate
determination must be made in each case based on the
facts and law applicable to each individual situation.
Amici respectfully request that this Court affirm the
lower court’s decision. If, however, this Court should
decide to reverse the lower court’s decision in the Orff
case, amici request that the opinion specifically acknowl-
edge that its conclusions do not apply to the Central
30
Arizona Project or to Reclamation projects in which the
underlying facts and law differ from those present in Orff.
Respectfully submitted,
MARVIN S. COHEN No. 03-1566
Counsel of Record
SACKS TIERNEY P.A.
4250 North Drinkwater Blvd. In The ;
recite Supreme Court of the United States
Scottsdale, AZ 85251
(480) 425-2633 ,
Attorneys for Amici Curiae FRANCIS A. ORFF, et al.,
January 6, 2005 Petitioners,
Vv.
UNITED STATES OF AMERICA, et al.,
Respondents.
_ On Writ Of Certiorari To The
United States Court Of Appeals
For The Ninth Circuit
— APPENDIX TO AMICI CURIAE BRIEF OF
— CENTRAL ARIZONA WATER CONSERVATION
DISTRICT, MARICOPA-STANFIELD IRRIGATION
& DRAINAGE DISTRICT, CENTRAL ARIZONA
IRRIGATION AND DRAINAGE DISTRICT AND
ARIZONA DEPARTMENT OF WATER RESOURCES
IN SUPPORT OF RESPONDENTS
TABLE OF CONTENTS
Page
September 12, 2003 Opinion of Judge Carroll,
in Smith et al., v. Central Arizona Water Con-
servation District, United States District Court
for the District of Arizona, Case No. CIV-03-
Minute Entry Action, Ruling on Motions for
Summary Judgment, Smith, et al. v. Maricopa-
Stanfield Irrigation & Drainage District, et al.,
Pinal County Superior Court No. CV 2001-
00924 (November 16, 2004) 0.0.00... eeeeeeeees App. 14
. Petition for Special Action, Maricopa-Stanfield
Irrigation & District, et al., v. Robertson, in the
Supreme Court of Arizona No. CV-04-0385-5A.....,App. 21
Arizona Water Settlement Agreement (without
ee eciieanincnntecirstnccinnensceinnipiniinninnéesisinniiasiniainiiiiinns App. 60
Joint Statement of Facts, Smith, et al. v. Mari-
copa-Stanfield Irrigation & Drainage District, et
al., Pinal County Superior Court No. CV 2001-
00924 (January 2, 2002) (relevant excerpts)
ee Ge iticiictnsticinstcdeinccsiennasinenennicimecrns App. 87
Contract No. 14-06-W-245, Contract Between
the United States and the Central Arizona Wa-
ter Conservation District for Delivery of Water
and Repayment of Costs of the Central Arizona
Project, dated December 1, 1988, Exhibit 2 to
Joint Statement of Facts (Amendment No. 1 ta__
Contract No. 14-06-W-245 dated December 15,
.
il
TABLE OF CONTENTS - Continued
Page
Subcontract Among the United States, the
Central Arizona Water Conservation District,
and the Central Arizona Irrigation and Drain-
age District dated November 21, 1983, Exhibit
3 to Joint Statement of Facts................:ccceeeeeees App. 159
Central Arizona Irrigation and Drainage
District’s Statement of Facts, Smith, et al. v.
Maricopa-Stanfield Irrigation & Drainage Dis-
trict, et al., Pinal County Superior Court No. CV
2001-00924 filed December 31, 2003 (relevant
excerpts) (with Exhibit A Affidavit of Paul
I vcscnccessnaneccstenennepinicapnetibaninnnsinsinpansunidibuaiini App. 196
App. 1
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF ARIZONA
John E. Smith and Mary Lou
Smith, husband and wife;
John E. Smith, as Trustee of
the Smith Family Trust;
Pretzer Land and Cattle
, No.
Company, an Arizona corpo-
ration, CIV 03-0505 -PHX-EHC
Plaintiffs,
Vs. (Filed Sep. 12, 2003)
Central Arizona Water
Conservation District,
)
)
)
)
)
)
)
) ORDER
)
)
)
)
)
Defendant. )
Pending before the Court are (1) Defendant’s Motion
to Dismiss [Dkt. 6]; (2) Plaintiffs’ Petition to Abstain and
Remand to State Court [Dkt. 10]; (3) Plaintiffs’ Motion to
Stay Motion to Dismiss [Dkt. 13]; (4) Plaintiffs’ Motion for
Two-Day Extension for Their Supplemental Memorandum
in Support of Their Motion to Abstain’ and Remand and
Their Supplemental Memorandum in Support of Their
Response to Motion to Dismiss by Defendant [Dkt. 34].
I. Background
Plaintiffs John E. Smith, Mary Lou Smith, and the
Smith Family Trust are landowners in Maricopa-Stanfield
Irrigation and Drainage District (“MSIDD”). Plaintiff
Pretzer Land and Cattle Company is a landowner in
Central Arizona Irrigation and Drainage District
(“CAIDD”). MSIDD and CAIDD are collectively referred to
as the “Irrigation Districts.”
App. 2
The Arizona legislature created Defendant Central
Arizona Water Conservation District (“CAWCD”) in 1971.
CAWCD was formed in relevant part to contract with the
United States to finance reimbursement of construction
and operation of Central Arizona Project (“CAP”) to the
federal government. In connection with that responsibility,
CAWCD was authorized to subcontract with the Irrigation
Districts who in turn could levy property taxes on land-
owners in their districts to subsidize its operating ex-
penses and assist CAWCD in meeting its repayment
obligations to the United States. See A.R.S. §§ 48-3701 et
seq.
In 1968, Congress passed the Colorado River Basin
Project Act (“Project Act.”) The Project Act authorized
construction of the CAP to store and deliver 2.8 million
acre-feet of Colorado River water to Arizona and western
New Mexico for irrigation as well as Municipal and Indus-
trial (“M&I”) use. See 43 U.S.C. §§ 1501, 1521.
On December 15, 1972, the United States and
CAWCD entered into a contract. (“Master Contract”),
under which the United States agreed to build CAP, and
CAWCD agreed to repay its allocable costs.’ On November
21, 1983, the Irrigation Districts executed subcontracts
(“Subcontracts”) with CAWCD and the United States.
CAWCD agreed to deliver non-Indian Agriculture (“NIA”)
priority CAP water to the Irrigation Districts in return for
payment of the Operation, Maintenance and Replacement
' The first action before this Court dealt with the repayment costs
under the Master Contract. Cent. Ariz. Water Conservation Dist. v.
United States, 32 F. Supp. 2d 117 (D. Ariz. 1998). (“Repayment litiga-
tion.”) :
App. 3
costs (“OM &R”) for the water delivered.’ Plaintiffs there-
after executed a Memorandum of Understanding (“MOU”)
with the Irrigation District they were members of The
United States and CAWCD were not parties to the MOU
and never approved the MOU.
Under the MOU, signatory landowners agreed to
execute agricultural water service contracts provided that
“the right to receive Project Water ... will form a part of
the appurtenances to the Lands; such water is a direct
benefit to the Lands and the covenants of Landowner to
pay for said water and other obligations under the Con-
tract shall run and bind said Land.” [Plaintiffs’ Response
to Motion to Dismiss, Dkt. 11, p.8]. Each MOU also pro-
vided that each signatory landowner would grant immedi-
ate possession and convey to the irrigation districts the
landowners’ wells, pumping equipment, appurtenances,
rights and privileges under the Arizona Groundwater
Management Act. ~
By 1990, CAIDD and MSIDD were unable to pay the
entire debt or pay full cost for CAP water. CAIDD filed
bankruptcy, and MSIDD restructured its debt with its
bondholders and the United States. In order to restructure
the CAP repayment scheme, CAWCD entered into a letter
agreement with Irrigation District subcontractors (includ-
ing CAIDD and MSIDD) for the water years 1994-2003.
* CAWCD asserts that under the original Subcontracts MSIDD
and CAIDD are obligated to pay the fixed OM&R costs for all CAP
water to which the districts are entitled, whether the water is ordered
or not. The Subcontracts also contained provisions regarding converting
from agricultural to M&I water use and provided contingencies for the
re-allotment of water should CAWCD be unable to deliver the Irrigation
Districts contracted allotment.
App. 4
Following the policy, the Irrigation District waived its
rights to receive agricultural water pursuant to the Sub-
contract, and its right to convert (from agricultural) to
M&I use. In exchange, CAWCD waived its right to receive
fixed OM&R payments and penalties, and sold excess CAP
water to the districts at essentially energy only cost* The
practical result of the letter agreement was to make CAP
water affordable to landowners within the districts.
The Repayment litigation was a complex dispute,
between the United States and CAWCD over the repay-
ment of the cost of constructing the CAP canal. The parties
entered into a stipulation terminating the_litigation upon
the occurrence of a number of conditions.* One of the
conditions is the relinquishment and the transfer of NIA
CAP water to the Gila River Indian Community and to the
Tohono O’odham Nation. The inducement for NIA districts
(like CAIDD and MSIDD) to permanently relinquish their
water rights under the Subcontract for some or all of the
land in their district is 9(d) debt relief; Reclamation
Reform Act exemption, and excess CAP water delivered to
them by CAWCD at essentially energy only rates through
the year 2030 (for the land which the Subcontract rights
are relinquished). As to the land for which there is no
relinquishment, the Subcontract rights and obligations
would remain in effect.
* The United States was not a party to the letter agreements and
challenged the validity of them in the Repayment litigation.
* Defendants and Interveners allege that if Plaintiffs are successful
in preventing MSIDD from relinquishing the Subcontracts, the
settlement package of the Repayment litigation will fail because one of
the conditions of the settlement package (that 197,500 acre feet of CAP
water be available to the United States to deliver to Indian tribes) will
not be possible.
App. 5
Plaintiffs filed suit in Pinal County Superior Court in
March 2003 seeking declaratory relief under Arizona’s
Uniform Declaratory Judgments Act’ See A.R.S. §§ 12-
1831 et seq. Plaintiffs’ claim relied upon alleged vested
property rights to Reclamation water based on the Federal
Reclamation Act of 1902, the Boulder Canyon Project Act,
(“Boulder Canyon Project”), and all amendatory and
supplementary Acts. See. e.g, 43 U.S.C. § 372 et seq., 43
U.S.C. §617 et seg. Defendant asserts this Court has
original jurisdiction pursuant to 28 U.S.C. § 1331 and
removed pursuant to 28 U.S.C. § 1441.
Plaintiffs contend a justiciable controversy exists
because Plaintiffs have vested property rights in Arizona’s
Colorado River entitlement by reason of the CAP Subcon-
tracts. Plaintiffs further assert CAWCD cannot interfere
with Plaintiffs’ rights to receive CAP water, and that
CAWCD is obligated to deliver CAP water to MSIDD or
CAIDD for the Plaintiffs’ benefit. Plaintiffs allege they are
third-party beneficiaries to the Subcontract and thus have
standing. Defendant asserts Plaintiffs fail to state a claim
upon which relief can be granted because there is neither
a direct contractual relationship between Defendant and
Plaintiffs, nor are Plaintiffs intended beneficiaries to
either the Subcontracts or the Master Contract. Fed. R.
Civ. Pro. 12(b)(6). Alternatively, Defendant moves to
dismiss because Plaintiffs failed to join the United States,
an indispensable party. Fed. R. Civ. Pro. I 2(b)(7), 19.
* In March of 2003 Plaintiffs filed a separate suit in Pinal County,
Superior Court against CAIDD and MSIDD seeking to prevent the
districts from relinquishing the Subcontracts, which they allege created
legally and equitably vested appurtenant rights of Plaintiffs to receive
NIA priority CAP water. The case is currently pending.
App. 6
II. Analysis
Plaintiffs fail to cite any controlling authority for the
proposition that the court should stay the Motion to
Dismiss pending the resolution of the Motion to Abstain or
Remand. Thus, the Court will address both the Motion to
Dismiss and the Motion to Remand.
A. Remand 7
“An action filed in state court may be removed only if the
district court could have exercised jurisdiction over the
action if originally filed there,” Duncan v. Stuetzle, 76 F.3d
1480, 1485 (9th Cir. 1996) (citing Caterpillar Inc. v. Wil-
liams, 482 U.S. 386, 392, 107 S.Ct. 2425, 2429 (1987)).
“The district courts shall have original jurisdiction of all
civil actions arising under the Constitution, laws, or
treaties of the United States.” 28 U.S.C. § 1331. Plaintiffs
base their claims of vested property rights to Colorado
River reclamation water on § 8 of the Reclamation Act of
1902° and support this claim with references to Congres-
sional intent from the Boulder Canyon Project Act, 43
U.S.C. § 617 et. seg., and the Colorado River Basin Project
Act, 43 U.S.C. § 1501 et seg. The only question of state law
Plaintiffs assert is their entitlement to a declaratory
judgment of their rights under contracts to which they are
not parties. The contracts in question (the Master Con-
tract and the Subcontracts) are based on federal Reclama-
tion law and the United States is a party to both contracts.
* “The right to the use of water acquired under the provisions of
this Act shall be appurtenant to the land irrigated, and beneficial use
shall be the basis, the measure, and the limit of the right.” 43 U.S.C.
§ 372.
App. 7
A declaration of Plaintiff’s rights under these contracts
involves interpretation of a contract “arising under”
federal Reclamation law, and thus is a federal question.
Additionally, Plaintiffs argue this case should be
remanded because “the legislative history of the heclama-
tion Act of 1902 makes it abundantly clear that Congress
intended to defer to the substance, as well as the form, of
state water law.” California v. United States, 438 U.S, 645,
675, 98 S.Ct. 2985, 3001 (1978). The legislative history of
the Reclamation reiterates this sentiment but also con-
templates that only the Federal government can build the
“reservoirs and main line canals” necessary to reclaim the
arid desert tands for settlement and that “the cost of
constructions so far as possible (should) be repaid by the
land reclaimed.” Jd. (citing HR., Doc, No. 1 (1901)). The
federal government has not been fully repaid for the cost
of construction of the CAP canal by the Irrigation Districts
or the benefitted landowners. The subcontracts entered
into by CAIDD and MSIDD attempt to repay the cost of
construction, and Plaintiffs’ suit undermines their efforts
to do so. Nothing within the text of the Reclamation Act of
1902, subsequent Reclamation acts, or any Arizona or
federal case law decisions supports the idea that Plaintiffs
should be entitled to reclamation water without paying the
cost of the project that made the water attainable. Because
Plaintiffs seek a declaration of their rights under a con-
tract to which the United States was a party, state law is
not controlling. Plaintiffs fail to cite any exceptional
circumstances that would make remand appropriate.
App. 8
B. Abstention
In the alternative to remanding; Plaintiffs ask this
Court to stay this action pending resolution of proceedings
in state court. Plaintiffs argue “wise judicial administra-
tion ... counsels that decision of the federal question be
deferred until the potentially controlling state-law issue is
authoritatively put to rest.” United Gas Pipe Line Co. v.
Ideal Cement Co., 369 U.S. 134, 135-36, 82 S.Ct 676, 677
(1962) (citing Leitner Minerals Inc. v. United States, 352
U.S. 220, 228-29, 77 S.Ct 287, 292 (1957)). United Gas
involved the interpretation of an Alabama state License
Code and the intent of the Alabama State legislature in
enacting the Code. Leitner involved the interpretation of a
Louisiana statute. As the present case involves neither
interpretation of a state statute, nor a federal constitu-
tional issue which can be deferred pending a state court
decision, abstention under United Gas or Leitner is not
warranted.
Plaintiffs also call for an abstention under the Colo-
rado River doctrine, when “federal review of the question
in a case and in similar cases would be disruptive of state™
efforts to establish a coherent policy with respect to a
matter of substantial policy concern.” Kern-Tulare Water
Dist. v. City of Bakersfield, 828 F.2d 514, 516 (9th Cir.
1987). “The circumstances permitting the dismissal of a
federal suit due to the presence of a concurrent state
proceeding for reasons of wise judicial administration are
considerably more limited that the circumstances appro-
priate for abstention.” Colorado River Water Conservation
Dist v. United States, 424 U.S.-800, 818, 96 S.Ct. 1236,
1246 (1976). Plaintiffs urge an “inquiry into the scope of
the pending state court proceeding” maybe necessary
before a district court removes a case from state court.
_ App. 9
Brillhardt v. Excess Ins. Co. of America, 316 U.S. 491, 495,
62 S.Ct. 1173, 1176 (1942). The proceedings in state court
involve a contractual dispute between Plaintiffs and the
respective irrigation districts, MSIDD or CAIDD, in which
they are members. Plaintiffs filed separate lawsuits
against the irrigations districts and CAWCD in Pinal
County Superior Court.
In this case, Plaintiffs seek a declaration of their property
rights under the Master Contact, based on federal Recla-
mation laws between the United States and CAWCD, and
the Subcontracts, also based on federal Reclamation law,
between the United States, CAWCD and either MSIDD or
CAIDD. “Federal law governs the interpretation of con-
tracts entered into pursuant to federal law where the
government is a party.” O’Neill v. United States, 50 F.3d
677, 682 (9th Cir. 1995) (citing Kennewick Irrigation Dist.
v. United States, 880 F.2d 1018, 1032 (9th Cir. 1989)).
“Federal courts have a ‘virtually unflagging obligation’ to
exercise the jurisdiction conferred on them ... a district
could nonetheless abstain from the assumption of jurisdic-
tion over a suit in ‘exceptional’ circumstances.” Wilton v.
Seven Falls Co., 515 U.S. 277, 284 115 S.Ct 2137, 2141
(1995) (citing Colorado River, 424, U.S. at 813, 818-820, 96
S.Ct. 1236, 1246-1248 (1976)).’
——
"In Wilton, the Court stated several circumstances that would
support a*finding of exceptional circumstances, including “the absence
of any proceedings in the District Court...and the prior participation of
the Federal Government in related state proceedings.” Jd. at 284, 115
S.Ct at 2141. The interpretation of the Master Contract and Subcon-
tracts, where CAWCD, the irrigation districts and the United States
were parties or interveners, has already been the subject of a lengthy
proceeding in this Court.
App. 10
“Several factors must be considered in deciding whether
the exceptional circumstances are present that make it
proper to apply Colorado River abstention. These factors
are: (1) which court first assumed jurisdiction over the
property in dispute; (2) the inconvenience of the federal
forum; (3) the desirability of avoiding piecemeal litigation;
and (4) the order in which jurisdiction was obtained.”
American Intern. Underwriters (Philippines), Inc. v.
Continental Ins. Co., 843 F.2d 1253, 1257 (9th Cir. 1988)
(citing Colorado River, 424 U.S. at 818, 96 S.Ct. at 1246-
47), While the state court first assumed jurisdiction, the
federal forum is not inconvenient because counsel for both
Plaintiffs and Defendant reside in Maricopa county.
Moreover, no danger of piecemeal litigation exists as
Plaintiffs themselves filed two separate lawsuits. An
abstention under Colorado River would be inappropriate.
C. Motion to Dismiss
CAWCD seeks dismissal of this action for failure to
state a claim and failure to join an indispensable party.
CAWCD argues Plaintiffs fail to state a claim for declara-
tory relief because they are neither parties nor third party
beneficiaries to the federal contracts at issues. Alterna-
tively, CAWCD seeks dismissal because Plaintiff’s have
failed to join the United States an indispensable party.
Because this Court concludes Plaintiffs have failed to state
a claim, it need not reach the alternative basis for dis-
missal.
Plaintiffs argue that under Arizona law they are
entitled to seek a declaratory judgment, even if they are
not parties to the contract in question, A.R.S. §§ 12-1831 et
seq.; See Foster v. Thunderbird Irrigation Water Delivery
App. 11
District of Pinal County, 125 Ariz. 324, 609 P.2d 594 (App.
1980), Trico Electric Cooperative Inc. v. Ralson, 67 Ariz.
358, 196 P.2d 470 (1948). “A plaintiff, however, in order to
be entitled to relief; must have a legal, protectible interest
... his pleading must present a state of facts showing he
has a present legal right against the defendant” Riley v.
Cochise County, 455 P.2d 1005, 1009 (Ariz. App. 1969).
“When the defendant has no power to affect the plaintiff’s
right, no controversy is present.” Jd. at 1010. In Foster, the
defendant was in violation of a specific statute regarding
the installation of water meters, which the defendant had
the ability to control. In Trico, the court held that users of
water and electric energy supplied by a public utility may
question the validity of a contract affecting such utility
service under the Arizona Declaratory Judgment Act.*
Here, Defendant is not disturbing the delivery of water;
Plaintiffs are seeking a declaration of their vested prop-
erty rights under a contact to which Defendant is merely a
party. Defendant has no power to affect Plaintiffs’ alleged
rights.
In order to entitle Plaintiffs to a declaration of their
rights under the Arizona Declaratory Judgment Act,
A.R.S. §§ 12-1831 et seg., a legal relationship in which
Plaintiffs have a definite interest must exist. Morris v.
Fleming, 625 P.2d 334, 336, 128 Ariz. 271, 273 (Ariz. App.
1980). Plaintiffs argue they are intended beneficiaries of
the Master Contract and Subcontract because they have
the equivalent interest of present perfected rights (PPR’s)
* In Trico, Plaintiffs alleged, and the court agreed, that Defendant
Trico Elec. Corp. had entered into an option agreement (which affected
utility service) that was outside the powers conferred on the corporation
by its charter.
App. 12
to Colorado River water. “The Supreme Court has defined
PPR’s as those rights to water from the Colorado River
system existing as of June 25, 1929.” Mohave Valley
Irrigation & Drainage Dist. v. Norton, 244 F.3d 1164, 1165
(9th Cir. 2001); see also Arizona v. California 373 U.S. 340,
341, 83 S.Ct. 755, 756 (1964). Plaintiffs proffer no argu-
ment as to why their rights are legally analogous to PPR’s.
The CAP canal, which enables water to be delivered to
Plaintiffs, was not authorized until 1968.
“To sue as a third-party beneficiary of a contract, the
third party must show that the contract reflects the
express or implied intention of the parties to the contract
to benefit the third party.” Klamath Water Users Protective
Ass’n v. Patterson, 204 F.3d 1206, 1211 (9th Cir. 2001).
“Parties that benefit from a government contract are
generally assumed to be incidental beneficiaries, and may
not enforce the contract absent a clear intent to the con-
trary.” Id. (citing Restatement (Second) of Contracts § 313
(2)). “Government contracts often benefit the public, but
individual members of the public are treated as incidental
beneficiaries unless a different intention is manifested.”
Restatement § 313 cmt. a. “An incidental beneficiary
acquires ... no right against the promisor or the promise.”
Id. § 315.
Plaintiffs have failed to show they are more than
incidental beneficiaries of either the Master Contract or
the Subcontracts.
Accordingly,
IT IS ORDERED that Plaintiffs’ Motion to Stay
Defendant’s Motion to Dismiss [Dkt. 13] is DENIED.
App. 13
IT IS FURTHER ORDERED that Plaintiffs’ Motion
to Abstain and Remand [Dkt 10-1, 10-2] is DENIED.
IT IS FURTHER ORDERED that Defendant’s
motion to Dismiss [Dkt. 6] is GRANTED, and this action
is hereby dismissed.
IT IS FURTHER ORDERED that Plaintiffs’ Motion
for Two-Day Extension for Their Supplemental Memoran-
dum in Support of Their Motion to Abstain and Remand
and Their Supplemental Memorandum in Support of Their
Response to Motion to Dismiss by Defendant [Dkt. 34] is
GRANTED.
IT IS FURTHER ORDERED that the Motion of
Marathon Farming Investments L.L.C. and Maricopa
Stanfield Landowners Association Members to Intervene
is DENIED as moot. [Dkt. 20].
IT IS FURTHER ORDERED that the Clerk enter
judgment in favor of Defendants and that Plaintiffs take
nothing by this action.
DATED this 11th day of September, 2003,
/s/ Earl H. Carroll
Earl H. Carroll
United States District Judge
App. 14
IN THE SUPERIOR COURT
PINAL COUNTY, STATE OF ARIZONA
DATE: 11/08/2004
Filed in Court
Record
Date Filed: 11/16/2004
Time Filed: 10:21 AM
HON KRISTI YOUTSEY RUIZ,
KELLY MARIE ROBERTSON CLERK
Division: 3 By
Court Reporter: NONE BARBARA J. NICLOY
Deputy Clerk.
JOHN E SMITH, et al., )CV200100924
Plaintiff(s), MINUTE ENTRY
ACTION:
pe ) RULING ON
)R
-STANFIELD
aes SM MIN AGE ) MOTION(S)/ISSUE(S)
DISTRICT, et al., ‘
Defendant(s). )
PRESENT:
The Court having considered the arguments and the
motions of the parties as well as the differing views of the
law clerks, does FIND for the plaintiffs on the requests
made prior to oral argument in early August of 2004. The
Court notes there are new pending matters and this
finding does not address those concerns. While the issue is
complex and plaintiffs’ counsel will be allowed to submit
proposed findings of facts and conclusions of law not
inconsistent with this minute entry, the Court makes the
App. 15
following simplified observations in holding for the plain-
tiff:
PLAINTIFFS’ MOTION FOR SUMMARY JUDGEMENT
The Plaintiffs move for Summary Judgment on two
counts. Count One is a complaint for Special Action. The
Plaintiff landowners ask the Superior Court of the State of
Arizona (the Court) to issue an order prohibiting Mari-
copa-Stanfield Irrigation and Drainage District (MSIDD)
and Central Arizona Irrigation and Drainage District
(CAIDD) from entering into negotiations for a new con-
tract with the Central Arizona Water Conservation Dis-
trict (CAWCD). Count Two is a request for Declaratory
Judgment. The landowners also ask the Court to issue an
order enforcing the existing contracts between the
CAWCD, MSIDD and CAIDD, as well as the contracts
between the individual landowners and MSIDD and
CAIDD (the Districts).
STATEMENT OF FACTS
There are five contracts that relate to the parties of this
case. First, the master contracts are repayment contracts
between the United States and the CAWCD for the costs
of diverting water through the Central Arizona Project
(CAP) canals and its features. Second, in the subcontracts,
CAWCD and the United States entered into individual
contracts with various Arizona entities for the delivery of
CAP water. The districts, MSIDD and CAIDD, were
organized to deliver water, including CAP water, to
individual landowners. Third, the Districts entered into
memoranda of understanding (MOUs) with the individual
landowners. Fourth, following the MOUs, the individual
App. 16
landowners, including the plaintiffs, entered into service
contracts with the Districts. Prior to the service contracts,
the plaintiffs’ lands were certified by the State of Arizona
as land qualifying for Irrigation Grandfathered Rights.
Finally, interim contracts were created on ten year terms
when the Districts and the landowners realized the costs
of the service contracts were too expensive.
FINDINGS AND AUTHORITIES
PLAINTIFFS ARE ENTITLED TO RELIEF, BECAUSE
THEY ARE AFFECTED BY THE VALIDATED SUB-
CONTRACTS
A. CAP Water is Acquired Under the Provisions of
The Reclamation Act of 1902.
If CAP water is “water acquired under the provi-
sions of this Act,” then the right to CAP water
runs appurtenant to the land. 43 U.S.C. § 8, The
Court in Arizona v. California, 573 U.S. 546
(1963), interpreted the Boulder Canyon Project
Act, which allocates 2.8 million acre-feet of Colo-
rado River water to Arizona, as a supplement to
the Reclamation Act. The Boulder Canyon Project
Act authorizes the Secretary of the Interior to al-
locate and store Colorado River water subject to
the provisions of the reclamation law. Id. at 584.
The Boulder Canyon Project Act does not provide
alternatives to the appurtenant rights
at issue. 43 U.S.C. §617. The Colorado River
Basin Project Act followed in 1968. 43 U.S.C.
§ 1524(b\(1). This act authorized CAP construc-
tion, authorized the Secretary of the Interior to al-
locate water to central Arizona, and authorized
subcontracts. Id. The preamble to the subcon-
tracts refers to the Reclamation Act. Therefore,
App. 17
the CAP water that reaches the plaintiffs is “water
acquired under the provisions” of the Reclamation
Act and the rights run appurtenant to the land.
B. Application
The service contracts, that are secondary to the
subcontracts, were created between the districts
and the plaintiffs. The contracts allow the dis-
tricts to use water from the landowners’ grand-
fathered groundwater and irrigation wells. The
service contracts also specify that the landowners
are entitled to receive CAP water as well as
ground water. Because the CAP water is ac-
quired under the provisions of the Reclamation
Act and the plaintiffs entered into these service
contracts, they are contractually vested with the
right to convert one acre-foot of NIA CAP water
for M & I purposes if the water is not required
for irrigation. As stated above, the rights vested
in the individual landowners are attached to the
land. 43 U.S.C. § 8. If the districts enter into new
subcontracts, modify the existing subcontracts,
or relinquish the existing subcontracts, the Dis-
tricts will infringe upon the plaintiffs’ rights to
convert CAP water for M & I purposes, as well as
making the land unsuitable for commercial agri-
culture, thus decreasing the value of the land.
SINCE CAP WATER IS ATTACHED TO THE LAND,
THEN CAWCD, MSIDD, AND CAIDD CANNOT
CHANGE THE VESTED CONTRACTURAL RIGHTS OF
THE PLAINTIFFS WITHOUT THEIR CONSENT.
C. Arizona Law Applies to the Validation Proceed-
ings and the Subcontracts.
State law applies to the design, construction
and completion of the Reclamation projects. The
App. 18
Reclamation Act creates property rights in the
landowners who receive the project water; there-
fore, because property law is vested in state
courts, the water rights laws of the state apply.
California v. United States, 438 U.S. 645, 677
(1978). The landowners made payments and
complied with obligations of the service con-
tracts, so they are vested with a right to perpet-
ual use of the CAP water that is appurtenant to
their land. Ickes v. Fox, 300 U.S. 82, 94 (1937).
The United States Supreme Court in Ickes also
found that state law applies. Jd. The Supreme
Court held that “the appropriations under state
law were made to the individual landowners
pursuant to the procedure which Congress pro-
vided in the Reclamation Act ... [and] we are
dealing here only with an allocation, through the
States, of water rights among appropriators.”
Nebraska v. Wyoming, 325 U.S. 589, 615 (1975).
a. Arizona Declaratory Statutes are Liberally
Construed
“Under the declaratory judgment act a justi-
ciable controversy exists if there is ‘an asser-
tion of a right, status or legal relation
in which the plaintiff has a definite interest
and a denial of it by the opposing party.”
McMann v. City of Tucson, 202 Ariz. 468,
474, 47 P.3d 672, 678 (2002). Arizona’s De-
claratory Judgment Act is to be liberally con-
strued and administered. Podol v. Jacobs, 65
Ariz. 50, 54, 173 P.2d 758, 761 (1946). In
Trico Electric Cooperative, Inc. v. Ralston, 67
Ariz. 358, 366, 196 P.2d 470, 474 (1948), the
plaintiffs were granted the right to “question
... the validity of the contract (to which they
were not a party) affecting such utility ser-
vice, determined by a declaration of the
App. 19
rights, status and legal relations there-
under.” The Trico case was determined by a
declaration of rights under the subcontracts
affecting the plaintiffs water service. Jd.
Plaintiffs are Third Party Beneficiaries to
the Validated Subcontracts.
Sole beneficiary status is not necessary for
the plaintiff landowners to be determined
third party beneficiaries. Nahom v. Blue
Cross & Blue Shield of Arizona, Inc., 180
Ariz. 548, 552, 885 P.2d 1113, 1117 (1994).
The plaintiffs are the intended beneficiaries
of the subcontracts between the Districts
and CAWCD, because the subcontracts were
created to provide means for distribution of
CAP water to agricultural landowners, a
class in which the plaintiffs fit. “Irrigation
districts are organized for the direct private
benefit of their landowners and taxpayers.
As such, they [the landowners] are required
to help pay for the irrigation system and are
entitled to a proportionate share of the wa-
ter for irrigation of their lands ....” Post v.
Wright, 37 Ariz. 105, 117, 289 P. 979, 983
(1930). The court in Estate of Jennifer A.
Bell v. American Motorist Insurance Co., 181
Ariz. 124, 126, 888 P.2d 1311, 1313 (1995),
determined that the plaintiffs’ situations
cannot be changed without their consent.
The court in Estate of Bell looked to the Re-
statement (Second) of Contracts § 311 (1979)
and ruled that two parties cannot modify
the agreement at the expense of a third be-
cause the plaintiffs have materially changed
their position and relied on the subcon-
tracts. Id. The plaintiffs have materially
changed their position by paying taxes
App. 20
toward CAP’s expenses as well as giving up
their grandfathered water usage rights.
Therefore, the plaintiffs are entitled to a
declaration of rights under the subcontracts.
CONCLUSION
The rights vested in the plaintiffs run appurtenant to their
land; therefore, the Districts have no authority to modify
or create new contracts that will affect those rights with-
out the plaintiffs’ consent. The Court grants Summary
Judgment in favor of the Plaintiffs.
Mailed/distributed copy: 11/17/2004
cc:
J GORDON COOK
ROBERT R BERK
MARVIN S COHEN
M BYRON LEWIS
DONALD M PETERS
DANIEL L MUCHOW
GRAHAM M CLARK
MARK S BOSWELL
STEPHEN P SHADLE
DAVID A FITZGIBBONS
DAVID L DECKER
ROGER C DECKER
PAUL A RELICH
DANIEL P STRUCK
LOUIS W BARASSI
GARY A WOLF
LAW OFFICES OF GARY WOLF
504 S STONE AVENUE
TUCSON AZ 85701
App. 21
IN THE SUPREME COURT OF
THE STATE OF ARIZONA
MARICOPA-STANFIELD
IRRIGATION & DRAINAGE
DISTRICT, an Arizona municipal
corporation; CENTRAL ARIZONA
IRRIGATION AND DRAINAGE
DISTRICT, an Arizona municipal
corporation; and approximately
two hundred landowners,
Petitioners,
Vv.
THE HONORABLE KELLY
MARIE ROBERTSON, Judge
of the Pinal County Superior
Court, Respondent,
and
JOHN E. SMITH, et al.,
Respondents-Real Parties
in Interest.
No.
Pinal County Superior
Court
No. CV 2001-00924
PETITION FOR SPECIAL ACTION
Donald M. Peters, 005929
Susan A. Cannata, 013787
MILLER LaSOTA & PETERS, PLC
5225 North Central, Suite 235
Phoenix, AZ 85012
Telephone: (602) 248-2900
Attorneys for Maricopa-Stanfield
Irrigation & Drainage District
App. 22
Richard N. Morrison, 005269
M. Byron Lewis, 002047
Mark A. McGinnis, 013958
SALMON, LEWIS & WELDON, PLL.C.
2850 East Camelback Road, Suite 200
Phoenix, Arizona 85016
Telephone: (602) 801-9060
Attorneys for Central Arizona
Irrigation and Drainage District
Marvin S. Cohen, 000923
SACKS TIERNEY P.A.
4250 North Drinkwater Blvd.
Suite 400
Scottsdale, Arizona 85251
Telephone: (480) 425-2633
Attorneys for Approximately
Two Hundred Landowners
TABLE OF CONTENTS
Re ee
SSE NE FAL ITD TAO
Ny OE IE eicecncremiseesscissssncasnnestaseninnmsencen
ee
Argument
I.
This Court Should Accept Jurisdiction of This
Special Action — Petitioners Do Not Have An
Adequate Remedy By Appeal.....................:06+.
The Trial Court Erred in Ruling That Plain-
tiffs Are Intended Beneficiaries of the Sub-
SII «100 sisins aden esaeemeeasaaimaianinenicaaenenth
A. The Trial Court Should Not Have
Reached the Merits of Plaintiffs’ Third-
Party Beneficiary Claim .....................00068
19
23
IIT.
App. 23
1. Plaintiffs Are Collaterally Estopped
From Making a Third-Party Benefici-
Se cnacisicdeui ceceniesdinstnetentiiit tle ing
2. Indispensable Parties Were Not
Joined in the Trial Court ....................
B. Federal Law Establishes that Plaintiffs
Are Not Intended Third-Party Benefici-
C. Even if Arizona Law Applied to the Is-
sue, Plaintiffs Would Not Be Intended
Third-Party Beneficiaries ........................
EERE R ARR NIe Ai RuMewit me MEO leer
The Trial Court Erred in Finding that the
Rights to Water Under the Districts’ CAP
Subcontracts Were Appurtenant to Plaintiffs’
Land and that Plaintiffs Had Individualized
Rights Under those Subcontracts...................
A. Post-1928 Rights to Water from Reclama-
tion Projects on the Lower Colorado River
Can Only Be Acquired by Contract............
B. Section 8 of the 1902 Reclamation Act
Does Not Apply to This Case....................
C. Plaintiffs Have No Individual Rights to
I i
i eee
EBERLE LAIN TEETER LN A RAOL OLE EOE ARTE
24
25
27
30
32
33
App. 24
TABLE OF AUTHORITIES
Cases
Page(s)
Arizona v. California, 373 U.S. 546 (1963)..............0. 35-38
Basurto v. Utah Construction & Mining Co., 15
Ariz.App. 35, 485 P.2d 859 (App. 1971)..........:.csceeeeees 31
Berberich v. United States, 5 Cl. Ct. 652 (1984),
aff'd, 770 F.2d 179 (Fed. Cir. 1985)..........:cccceseeeeereeeees 31
Bledsoe v. Goodfarb, 170 Ariz. 256, 823 P.2d 1264
(1991), appeal after remand, 179 Ariz. 469, 880
P.2d 689 (1994), review denied, (Sept. 20, 1994)............. 7
Bryant v. Yellen, 447 U.S. 352, reh’g denied, 448
EE, GRE CIID cctenteccsnceccccsmnesccncsncsatiscnsnsenanesncncenssecnsinntn 38
California v. United States, 438 U.S. 645 (1987)......... 37-
City of Phoenix v. Superior Court (Kleven Constr.),
184 Ariz. 435, 909 P.2d 502 (App. 1995), corrected
Clough v. Wing, 2 Ariz. 371, 17 P. 453 (1888) ..............00
Coburn v. City of Dyersburg, 774 S.W.2d 610 (Tenn.
App. 1989)............ccccccccscsrsccoscsrcrsscscrssssrscssseesssssssssossooes
Green v. Superior Court, 132 Ariz. 468, 647 P.2d
I, CD ecsesicccsneteninssschontasnsnsninennianiemnemnnintansiannncumainn
Hawkins v. Risley, 984 F.2d 321 (9th Cir. 1993)...............
Kennewick Irr. Dist v. United States, 880 F.2d 1018
Ee: TI... siichianncsintiienmiigeinenibamniininetaiinniniebonis
Klan th Water Users Protective Ass’n v. Patterson,
2( 1 F.3d 1206 (9th Cir. 1999), cert. denied, 531
Sirens STITT... snidepeesieminateiibateneiannadecntianedentiie
Long v. Salt River Water Users’ Ass’n, 820 F.2d 284
Cs Cie FIG Picccecceccncccececastcntencesetassinanntiininisnsetnansensenssans
App. 25
Orff v. United States, 358 F.3d 1137 (9th Cir.), cert
granted, 125 S. Ct. 309, 73 USLW 3228, 73
EF ERIN netre emer eRe IEE 28
Post v. Wright, 37 Ariz. 105, 117, 289 P. 979 (1930).......... 30
Robi v. Five Platters, Inc., 838 F.2d 318 (9th Cir.
FEISS TEATS We RON DOO OTT TI aD DUT 25
San Carlos Apache Tribe v. Superior Court, 193
Ariz. 195, 972 P.2d 179 (1999)...............cccccccccocoscecssscceee 39
Siler v. Superior Court, 83 Ariz. 49, 316 P2d 296
Re RST eee een OT ee ae 26
State ex rel. Dept. of Economic Sec. v. Powers, 184
Ariz. 235 908 P.2d 49 (App. 1995) uo. .cccccccccceeeeeceeeeeee 24
Travelers Indemnity Co. v. Household Int'l Inc., 775
A Ca, ics rnstccseccccnesnccenaccnnceconees 27
Western Water Service Sys. v. Superior Court, 120
Ariz. 90, 584 P.2d 554 (1978)................ccccccccssssccssssssscevees 8
Federal Statutes
Arizona Water Settlements Act, P. L. 108-451......... 1 et seq.
Te a a Le ey 34
LEA A eR 35, 38
State Statutes and Constitutional Provisions
Arizona Constitution, Article 6, § 5(4) .....ccccccccccsceeseeeeeees 1
gt |S SS io a ae ee 40
InN an TUITE olinrhilacincicaricdathuiticsnieiiestsinterhceiheiiinismememniiitiidiessliataies 39
I 4
LS TESTER ena ae IC TT 10
Eo ec ee a eae 10
App. 26
Other Authorities
Beli: DR BD... ciisssconssvliteninanintsdsininnnereatensiieennenaniins 26
Federal Practice and Procedure § 4433 (1981) .............06+ 25
Restatement (Second) of Contracts, § 313 ............:.sseeeeeeees 31
Restatement (Second) of Contracts, §§ 304 and 311,
JURISDICTIONAL STATEMENT
This is a petition for special action arising out of a
grant by the Pinal County Superior Court of a motion for
partial summary judgment in a civil action. This Court
has jurisdiction over this matter pursuant to Article 6,
§ 5(4) of the Arizona Constitution. The decision vi Respon-
dent Judge Robertson would enjoin two irrigation districts
from relinquishing Central Arizona Project (“CAP”) sub-
contract water without the consent of every landowner.
Unless the decision is overturned, it will not be possible to
implement the important and historic water settlements
embodied in the Arizona Water Settlements Act. That Act
was passed by Congress on November 17, 2004, and signed
by the President on December 10, 2004. [App. 1.]
The Arizona Water Settlements Act
The benefits to Arizona of these settlements include,
among others:
The two irrigation districts directly at issue in this special action
are Petitioners Maricopa-Stanfield Irrigation & Drainage District
(“MSIDD”) and the Central Arizona Irrigation and Drainage District
(“CAIDD”). MSIDD and CAIDD are referred to herein collectively as
“the Districts.”
App. 27
¢ Settlement of claims of the Gila River Indian
Community filed in the Gila Adjudication to more
than two million acre-feet of water that have for
more than twenty years been a cloud on the water
rights of users in and residents of the Salt and
Gila River valleys and on the groundwater use
rights of the Districts [App. 1, Title IT];’
* Settlement of claims of the Tohono O’odham Na-
tion filed in 1976 in federal court, which sought to
enjoin the pumping of groundwater in the entire
Tucson area [App. 1, Title III];
¢ Settlement of a long-standing dispute over Ari-
zona’s obligation to repay costs of the construction
of the CAP and a reduction of Arizona’s obliga-
tions by $650 million [App. 1, Title I];
¢ Allocation to CAP Municipal and Industrial sub-
contractors of an additional 65,000 acre-feet of
CAP water and extension of the term of their sub-
contracts from 50 years to 100 years [App. I, Title
I);
¢ Decrease in the cost of CAP water for farmers in
the Districts from $76 per acre-foot to $28 per
acre-foot for a cumulative thirty-year benefit of
over $80 million for each District [App. 14, J 28];
¢ Forgiveness of approximately $130 million of Dis-
trict debt to the United States, and relief to the
farmers from restrictive limitations on CAP water
* See In re General Adjudication of All Rights to Use Water in the
Gila River System and Source, Maricopa County Superior Court, Nos.
W-1 through W-4 (“Gila Adjudication”). An acre-foot equals 325,851
gallons of water. The two million acre-feet claimed by the Gila River
Indian Community is more than the entire normal flow of the Gila and
Salt Rivers. [App. 53]
App. 28
use under various federal statutes. [App. 14, 7 29;
App. 2, Exhibit 7.2]
The settlement package embodied in the Arizona Water
Settlements Act will be referred to herein as “the Settlement.”
The Settlement has been characterized by Senator John
McCain as being “of vital importance to Arizona’s produc-
tive future.” [App. 4, at 1.] Senator Jon Kyl has stated that
the Settlement “could ultimately be nearly as important to
Arizona’s futvre as was the authorization of the Central
Arizona Projec itself.” [App. 5, at A18.] See also App. 6-8.
The Importance of Agricultural CAP Water to the
Settlement
The cornerstone of the Settlement is the voluntary
relinquishment by agricultural CAP subcontractors of
subcontract allocations of CAP water that will be used by
the United States to settle Indian water claims. Since
completion of the CAP in 1993, none of the irrigation
districts with CAP subcontracts has been able to purchase
Agricultural subcontract water because it was prohibi-
tively expensive. [App. 14, {7 16-18.]
The CAP is administered by a three-county entity
known as the Central Arizona Water Conservation
District (““CAWCD”). See A.R.S. §§ 48-3701 to -3783.
CAWCD responded to the irrigation districts’ inability to
afford water at the subcontract rate by making excess
CAP water available to the districts at affordable prices
for ten years. [App. 14, 4 19-21.) In 2002, in order to
obtain CAP water for the Secretary of the Interior (“Sec-
retary”) to implement the Settlement, CAWCD offered a
package of benefits to each district in exchange for
relinquishment of its subcontract water rights. [App. 14,
App. 29
{1 24-30.) Both of the Districts held elections to deter-
mine whether landowners favored relinquishing the
Districts’ rights to subcontract water in return for the
various benefits that were offered. A majority of votes in
both Districts favored the proposed relinquishment. [App.
14, J 32; App. 17, J 5.)
This CAWCD proposal and the program for implemen-
tation of the Settlement are contained in the Arizona
Water Settlement Agreement (“Settlement Agreement”)’
among CAWCD, the Arizona Department of Water Re-
sources, and the United States, acting through the Secre-
tary. [App. 2.] The Arizona Water Settlements Act
authorized and directed the Secretary to execute the
Settlement Agreement on behalf of the United States. The
Settlement Agreement provides for the Secretary to use
197,500 acre-feet of Agricultural Subcontract water for
reallocation to the Gila River Indian Community, the
Tohono O’odham Nation, and other Indian tribes in set-
tlement of pending water rights claims. [App. 1,
§ 104(a)(1)(A); App. 2, 199.2, 13.2.] If Agricultural subcon-
tractors do not relinquish sufficient CAP water to enable
the Secretary to make such reallocations, the Settlement
Agreement and all of the settlements embodied in the
Arizona Water Settlements Act will fail. [App. 1, 2.]
The Civil Action in the Trial Court
The civil action which is the subject of this petition
was filed in 2001 in the Final, County Superior Court
by some dissident landowners (cullectively, “Plaintiffs”).
. The Arizona Water Settlement Agreement is defined in § 2(32) of
the Arizona Water Settlements Act as the “Master Agreement.”
App. 30
Plaintiffs sought to prevent the Districts from relinquish-
ing any of the CAP Subcontract water in which Plaintiffs
claimed appurtenant ownership interests. [App. 10.) Of
the 293,795 acre-feet of Agricultural CAP water poten-
tially available to the Secretary for the Settlement, up to
180,000 acre-feet were to be relinquished by the Districts.
[App. 2, 15.1.4.] If the two Districts are not able to relin-
quish this water, the Secretary will not receive the 197,500
acre-feet required to implement the settlement. [Jd.]
In December, 2003, Plaintiffs moved for partial
summary judgment. [App. 11.] The Districts and defen-
dant landowners filed cross-motions for summary judg-
ment. [App. 13, 15, 16.] After extensive briefing, the court
heard argument on August 6, 2004. [App. 11-48.) On
November 16, 2004, the trial court issued its minute entry
ruling granting summary judgment to Plaintiffs. A copy of
that minute entry is attached to this Petition as Exhibit A.
The court held that the rights to Colorado River water
under the CAP subcontracts are appurtenant to Plaintiffs’
land and that rights under each of the CAP Subcontracts
are contractually vested in the landowners and enforce-
able by them. The trial court also held that the landown-
ers are intended third-party beneficiaries of the CAP
subcontracts and that a District cannot modify the subcon-
tract in any way that will affect a landowner’s appurte-
nant rights without that landowner’s consent.
This Petition for Special Action
Petitioners seek a special action in the Supreme Court
- of Arizona because the trial court’s ruling is an urgent
matter of state-wide importance and great public interest.
There are no factual issues; an appeal would not provide
App. 31
an adequate remedy; the trial court’s ruling contradicts a
ruling by the United States District Court for the District
of Arizona in a case involving the same Subcontracts and
some of the same parties; and final resolution in a prompt
manner is required.
If the lower court’s decision is not overturned soon,
Arizona and CAWCD will not be able to implement and
complete the Settlement before the time limits set in the
Act. See Section I of the Argument, infra.
Petitioners seek relief in this Court rather than the
Court of Appeals because of the urgent need for speedy
and final resolution of this matter of state-wide impor-
tance. Petitioners recognize that the acceptance of special
action jurisdiction is highly discretionary. In a number of
cases involving matters of state-wide significance where
an appeal would not provide adequate or speedy relief, this
Court has accepted jurisdiction.
In Bledsoe v. Goodfarb, 170 Ariz. 256, 823 P2d 1264
(1991), appeal after remand, 179 Ariz. 469, 880 P.2d 689
(1994), review denied (Sept. 20, 1994), this Court accepted
special action jurisdiction to review a grant of partial
summary judgment that concerned the doctrine protecting
owners and operators of irrigation canals from liability
because it raised issues of state-wide significance. The
issues raised in the present case concerning the historic
settlements embodied in the Act are at least as important
as the protection of owners and operators of irrigation
canals from liability.
In accepting special action jurisdiction in Western
Water Service Sys. v. Superior Court, 120 Ariz. 90, 91, 584
P.2d 554, 555 (1978), to review a superior court grant of
App. 32
partial summary judgment that declared a statutory triple
damage provision unconstitutional, this Court stated:
This Court has the power to issue writs of review
pursuant to the Constitution, Article 6, § 5, sub-
sec. 4. It will accept jurisdiction and grant relief
by way of special action if the issues raised are of
sufficient importance to justify the review re-
quested. ... Jurisdiction was accepted here be-
cause we concluded that the trial court’s granting
of a motion for partial summary judgment is
without precedent or support in the law and can-
not be justified.
Here, the trial court’s granting of the motion for partial
summary judgment was without precedent or support in
law and cannot be justified. In addition, if the ruling is not
promptly overturned, water settlements of historic impor-
tance to the State of Arizona will fail.
This Court, rather than the Court of Appeals, is the
appropriate forum for the resolution of the issues raised by
this Petition. The decision of Respondent Judge Robertson
would enjoin the Districts from relinquishing their CAP
subcontracts without the consent of every landowner in
each District. A decision by Division Two of the Court of
Appeals in a special action challenging Judge Robertson's
ruling, although of precedential value, might not have
binding effect in Division One. Many of the other irriga-
tion districts that have already relinquished their CAP
subcontracts as part of the Settlement are in Maricopa
County, to-wit: Chandler Heights Citrus Irrigation Dis-
trict, Queen Creek Irrigation District, San Tan Irrigation
District, and Tonopah Irrigation District [App. 2, { 5.1.4.]
Having learned of Judge Robertson’s ruling in this litiga-
tion, a landowner in any of these districts could assert in
App. 33
the Maricopa County Superior Court the same claims
made by Plaintiffs here. On review of the decision in that
case, Division One of the Court of Appeals would not be
bound by the decision of Division Two.
Furthermore, this Court has previously recognized the
need for direct interlocutory review to this Court in important
water matters. In 1989, this Court adopted a Special
Procedural Order for Interlocutory Appeals and Certifica-
tions from the Gila Adjudication. [App. 51.] In that order,
the Court noted that “[elarly appellate review may avoid
wasteful trial court proceedings, may result in substantial
savings of time or expense, or may for other reasons be in
the interests of justice.” Id. at 7. In 1991, the Court
adopted a subsequent Special Procedural Order for Ap-
proval of Federal Water Rights Settlements, Including
Those of Indian Tribes. [App. 52.] That order provides that
decisions on approval of Indian water rights settlements
are subject to immediate interlocutory review by this
Court. Id. § D(7), at 8. Although those orders are not
strictly applicable to this Petition because it does not arise
directly from the Gila Adjudication, the considerations
supporting those orders weigh heavily in favor of this
Court accepting this Petition, particularly in light of the
fact that the trial court ruling at issue in this Petition
effectively obliterates water rights settlements for two
major Indian tribes that took decades to achieve.
The Arizona Legislature has also recognized the
importance of finality in matters involving CAP contracts.
A.R.S. § 48-3734 provides that review of an action to
validate a CAP contract shall be by special action directly
to this Court. In essence, Plaintiffs’ lawsuit was a pre-
emption of the contract validation process established
in A.R.S. § 48-3731 et seg. With the completion and
App. 34
implementation of the Settlement at stake, it is of the
utmost importance that the issues raised in this Petition
be resolved speedily and finally.
STATEMENT OF THE ISSUES
The central issue in this case is whether irrigation
districts must obtain the express individual consent of
each landowner in the district to modify agreements that
specify the terms by which the districts receive water from
the Central Arizona Project. The resolution of that issue
turns on two subsidiary issues: (1) whether individual
landowners are intended third-party beneficiaries of the
Subcontracts pursuant to which irrigation districts receive
water from the Central Arizona Project; and (2) whether,
by virtue of applicable water law, individual landowners
have acyuired vested rights, appurtenant to the land, to
receive water pursuant to those Subcontracts.
SUMMARY OF ARGUMENT
The trial court rendered summary judgment that
individual landowners within the Districts have legal and
contractual rights to receive water from the CAP under a
CAP Agricultural subcontract. The trial court ruled that
the Districts cannot, without the express individual
consent of each landowner, modify the terms of the sub-
contracts pursuant to which the Districts are entitled to
receive CAP water.
The trial court’s ruling that each landowner is an
intended third-party beneficiary of subcontracts among
the Districts, the Secretary, and CAWCD was barred by
collateral estoppel and the absence of indispensable
App. 35
parties. That ruling is also demonstrably incorrect as a
matter of law. The trial court’s ruling that the right to CAP
water is vested in the landowners by operation of law rests
on a fundamental misunderstanding as to the law that has
governed the allocation of water from the Lower Colorado
River for decades.
STATEMENT OF FACTS
The Parties
Two of the Petitioners in this matter, MSIDD and
CAIDD, are irrigation districts in Pinal County. The
remaining Petitioners consist of approximately two hun-
dred landowners (“Landowners”) within those Districts
who were parties defendant in the trial court proceedings.
The Landowners supported the positions taken by the
Districts in the trial court. The Landowners are more
specifically identified in Exhibit B.
The Respondents-Real Parties in Interest consist of
landowners within the Districts who were plaintiffs in the
trial court (“Plaintiffs”). The Respondents-Real Parties in
Interest are more specifically identified in Exhibit C.
* Soon after oral argument on the motions, each of the Plaintiffs
with CAP-eligible land within CAIDD sold its land. [App. 49.E.] Thus,
as of this time, there are no Plaintiffs who own land within CAIDD that
is eligible to receive CAP irrigation water, regardless of the outcome of
this dispute. In MSIDD, a number of the Plaintiffs have also sold their
land but some Plaintiffs from that District still have standing to assert
the claims that have been raised in this matter. [App. 50.]
App. 36
Background
In 1972, CAWCD and the Secretary entered into a
Master Repayment Contract for the delivery of Colorado
River water through the CAP and for the repayment of the
allocable costs of the Project. [App. 9, Exhibits 1, 2.] In
1983, pursuant to the Master Repayment Contract, the
Districts each entered into a long-term subcontract regard-
ing CAP water with the Secretary and CAWCD. [App. 9,
Exhibits 3, 4.] The agreements that allocate the water to
the Districts and that govern the terms of its purchase are
generally referred to as the Subcontracts. The landowners
within the Districts were not parties to the Subcontracts.
The central fact about the Subcontracts, which have a
term until 2043, is that the farmers in the Districts have
never been able to afford to buy water at the price set by
those agreements. In 1994, CAP infrastructure and water
costs caused CAIDD to file for municipal bankruptcy
protection. [App. 14, 7 18.] Because Subcontract water has
never been affordable, neither District has ever received a
drop of CAP water pursuant to its Subcontract. [App. 14,
{ 28; App. 29, at 2.]
The Subcontracts contain a formula for determining
the price that the Districts must pay for CAP water
delivered under the Subcontracts. [App. 9, Exhibits 3, 4.]
In 1993, when construction of the CAP was completed, the
Districts advised CAWCD that they could not afford to pay
the price dictated by the contractual formula for the water.
[App. 14, 44 16-18.] The Districts and CAWCD dealt with
the problem by entering into ten-year letter agreements
that allowed the Districts to purchase “excess” water at
affordable rates. [App. 14, {9 19-23.] Those agreements
have now expired.
App. 37
The Settlement Agreement provides the opportunity
for the Districts to relinquish the Subcontract rights that
they have never been able to afford to exercise in return
for substantial benefits. The Settlement Agreement
contemplates that the United States will acquire the
agricultural Subcontract allocation that MSIDD, CAIDD,
and other irrigation districts have agreed to relinquish.
[App. 2, 4 9.2.) The first 197,500 acre-feet of water avail-
able for reallocation will be reallocated as follows:
¢ 102,000 acre-feet to the Gila River Indian Commu-
nity
e 28,200 acre-feet to the Tohono O’odham Nation
¢ 67,300 acre-feet to be retained by the Secretary to
be reallocated in future Arizona Indian water set-
tlements.
(Id.] The remaining 96,295 acre-feet of relinquished water
will be allocated to the Arizona Department of Water
Resources in trust for future reallocation to Arizona non-
Indian municipal and industrial water users.
In return for agreeing to relinquish their Subcontract
rights, the Districts would obtain a number of significant
concessions and benefits, MSIDD would be relieved from
approximately $70 million in debt related to the construc-
tion of its facilities. [App. 2, Exhibit 7.2.] CAIDD would be
relieved from approximately $60 million of similar debt.
(Id.; App. 14, { 29.] Both Districts wov'd enter into new
agreements with CAWCD that would enable them to
purchase low-cost excess CAP water until 2030. [App. 14,
{ 27.) The present value of this reduction in the cost of
CAP water is approximately $80 million for each District.
Potential and pending claims against the Districts by Indian
tribes for groundwater depletion would be resolved. [App. 14,
App. 38
q 30.) The Districts would also be relieved of obligations
under the Reclamation Reform Act. [App. 14, { 30.)
The Subcontract rights that the Districts have agreed
to relinquish are essentia! to the Settlement. The Settle-
ment Agreement provides that the United States may
terminate the Settlement if the water available for reallo-
cation is less than 197,500 acre-feet. [App. 2, J 13.2.] If the
trial court’s order stands and MSIDD and CAIDD cannot
relinquish their allocations, the water available for reallo-
cation will constitute less than the required 197,500 acre-
feet. [App. 2, at table 5.1.4; id., subparagraph 5.2.3.)
As they did in entering into the Subcontracts in 1983,
both Districts held landowner elections regarding the
proposed relinquishment of Agricultural CAP Subcontract
allocations pursuant to A.R.S. §§ 48-2977 and -2978. [App.
14, J 32; App. 17, 9 5.] The vote in both Districts showed
that the owners of a majority of the land voting favored
the relinquishment. [App. 14, 9 32; App. 17, 75.) The
elected board of each District approved the proposed
relinquishment agreements. [App. 14, | 35; App. 17, J 7.]
This lawsuit had already been filed. The relinquishment
agreements signed by both Districts were conditioned on
the final outcome of this case. [App. 14, J 26; App. 17, J 7.]
A few landowners in each District opposed the Settle-
ment. With the consent of the Secretary and CAWCD, both
Districts gave landowners the option of acquiring by
assignment an individual right to purchase water accord-
ing to the terms of the Subcontracts. [App. 29, at 2.) This
otion required the assignee landowner to pay the full
Subcontract price for the assigned Subcontract water. [Jd.]
Only one of the Plaintiffs in CAIDD made a request for
such an assignment. That request was untimely. [/d.] Only
App. 39
two landowners in MSIDD, neither of which is a Plaintiff,
chose to accept the offer of an assignment. [/d.] To date, no
Subcontract has as yet been executed by either putative
assignee.
The Legal Proceedings
Approximately 41 of the dissident landowners brought
the legal action in 2001 in Pinal County Superior Court.
[App. 10.] Plaintiffs requested special-action and declara-
tory relief to prohibit the Districts from relinquishing the
Districts’ Subcontract rights. [Jd.]. They argued that the
proposed relinquishment of rights under the Subcontracts
would infringe on their individual water rights. [Jd.]
This case was initially stayed because of uncertainty
as to whether the Gila River Indian Community water
settlement would go forward. [App. 55.] The stay was
lifted in early 2003. [App. 56.] At that time, the trial court
ruled that the landowners within the Districts were
indispensable parties to this action and ordered them
joined. [App. 56.] Most were. The majority of the landown-
ers who were joined took no active role in the action. About
two hundred twenty landowners, most of whom are
Petitioners here, took an active role, opposing the claims
by Plaintiffs and supporting the position of the Districts.
[App. 15, 26, 33, 35.]
Subsequently in March 2003, Plaintiffs sued CAWCD
in state court. CAWCD removed the action to federal
district court. [App. 29, Exhibit 1.] As in their case against
the Districts, Plaintiffs alleged in the federal case that the
proposed relinquishment of rights under the Subcontracts
by the Districts would infringe on rights to that water
which they enjoyed individually. [Jd.] In November 2003,
App. 40
Judge Earl Carroll dismissed Plaintiffs’ action for-failure
to state a claim upon which relief could be granted. [/d.]
Judge Carroll held that, because Plaintiffs were not
parties to the Subcontracts and were not intended third-
party beneficiaries of those agreements, they could not
obtain relief against CAWCD concerning the proposed
modification of the Subcontracts. (Jd. at 4, 9-10.]
In late 2003, Plaintiffs filed a motion for partial
summary judgment in the present case. [App. 11.] Shortly
thereafter, the Districts and Landowners filed cross-
motions for summary judgment. [App. 13, 15, 16.] After
extensive briefing and oral argument, Judge Robertson
granted Plaintiffs summary judgment on November 16,
2004. [Ex. A.] Judge Robertson held, contrary to long-
established law relating to the Colorado River, that Plain-
tiffs had acquired vested rights to Subcontract water by
operation of law. [/d.] In addition, contrary to what Judge
Carroll had ruled, the trial court held that Plaintiffs were
intended third-party beneficiaries of the Subcontracts and
that their consent was required before those agreements
could be modified. [/d.]
ARGUMENT
I. THIS COURT SHOULD ACCEPT JURISDIC-
TION OF THIS SPECIAL ACTION - PETI-
TIONERS DO NOT HAVE AN ADEQUATE
REMEDY BY APPEAL. 7
This case involves issues of law that are of state-wide
importance. The importance of these issues was fully
explained in the Jurisdictional Statement and will not be
repeated here. The inadequacy of the remedy by appeal
App. 41
was not explained in the Jurisdictional Statement and is
the subject of this portion of the Argument.
There is a serious risk that an appeal would not
provide relief from the trial court’s ruling in time to
salvage the Settlement. The stakes are too high for that
risk to be taken.
Petitioners cannot appeal until there is a final judg-
ment in the trial court. That may be two to three months
away. An appeal to Division Two of the Court of Appeals
might consume an additional twelve to eighteen months. A
petition for review by either party might mean that the
appeal from the trial court’s order would not be completed
for over two and a half years.
At that point, this case might or might not be over.
Both sides to this dispute appear to believe that this case
is suitable for resolution by summary judgment. If an
appellate court were to disagree and decide that a trial as
to some issue is necessary, a complete resolution might be
years away.
The Arizona Water Settlements Act establishes a firm
deadline of December 31, 2007, for satisfaction of a num-
ber of prerequisites to implementation of the Settlement.
[App. 1, § 207(c)(2).] If that deadline is not met, federal
authorization for the Settlement will expire. The allotted
time might appear to be ample. It will not be if the neces-
sary steps are delayed by the appeal of this case. The
prerequisites to completion of the Settlement are numer-
ous, complicated, interrelated and fragile. _
(1) The Arizona Legislature must pass legislation to
establish certain programs for protecting groundwater
under the Gila River Indian Reservation and under the
App. 42
Tohono O’odham Reservation. [App. 1, § 207(c)(1)(I).] The
Legislature must also enact legislation to implement a
groundwater protection program in the Upper Gila River
basin. [/d.]
The Legislature has many demands on its attention.
It must establish priorities. The trial court in this case has
declared that a necessary component of the Settlement —
i.e., the relinquishment of the Districts’ CAP Subcontracts
— is illegal. As long as the cloud of the lower court’s ruling
remains, it could be difficult to get the Legislature to enact
legislation to implement a settlement that a Pinal County
Superior Court Judge has pronounced dead.
(2) After the Legislature passes the required legisla-
tion, whenever that might be, the final dismissal of several
court cases pending in federal district court in Tucson
must be ordered. [App. 1, § 302(b).] Those eases cannot be
dismissed until notification to class members has been
provided. The federal court in Tucson cannot proceed with
class notification of the proposed dismissal of those actions
while the trial court’s ruling stands and the viability of the
Settlement remains in question. ;
(3) The settlement of claims by the Gila River Indian
Community and the Tohono O’odham Nation must be
submitted to the Gila Adjudication Court and approved.
[App. 1, § 207(c)(1)(G).] It is estimated that it may take as
much as a year to obtain approval after the applications
are filed. Unforeseen complications or disputes could delay
the completion of that step even further. If application for
approval of the settlements was made while the trial
court’s ruling remains in effect, the existence of that ruling
would become an issue in the Adjudication proceeding and
App. 43
inhibit the Adjudication Court’s review of the two Indian
water claims settlements.
(4) Each District must initiate and complete valida-
tion proceedings in Pinal County Superior Court, in which
all interested parties will have an opportunity to challenge
the legality of the agreements to relinquish water. See
generally A.R.S. §§ 48-3731 to 48-3734. As long as Judge
Robertson’s ruling stands, such proceedings cannot be
meaningfully conducted. Plaintiffs would presumably
contend that the illegality of the proposed agreements is
res judicata by virtue of Judge Robertson’s ruling. The
Districts therefore would not be able to address any other
legal objections that interested parties might have until
the issues raised in this case are resolved. In addition,
pursuant to section 29.5.2 of the Gila River Indian Com-
munity’s Water Rights Settlement Agreement, this specific
case must be resolved in the Districts’ favor before their
obligations under the Settlement are enforceable. [App. 3,
§ 29.5.2.]
An appeal might resv't in a final ruling in 2006, 2007
or even later. That ruling might or might not fully resolve
the controversy. Several complicated steps must be taken
between the time this controversy is fully resolved and the
end of 2007. Arizona cannot afford to run the risk that the
Settlement will fail because of court delays.
An appeal would not provide the timely relief required
here. Petitioners have no “equally plain, speedy and
adequate remedy by appeal.” ARPSA 1. City of Phoenix v.
Superior Court (Kleven Constr.), 184 Ariz. 435, 436, 909
P.2d 502, 503 (App. 1995), corrected (1996); Green v.
Superior Court, 132 Ariz. 468, 470, 647 P2d 166, 168
(1982).
App. 44
II. THE TRIAL COURT ERRED IN RULING THAT
THE PLAINTIFF LANDOWNERS WERE IN-
TENDED BENEFICIARIES OF THE SUBCON-
TRACTS.
The trial court concluded on the basis of Arizona law
that Plaintiffs were intended third-party beneficiaries of
the Subcontracts. [Ex. A at 4.] The trial court further held
that, because Plaintiffs were third-party beneficiaries, the
Districts could not modify the Subcontracts without
Plaintiffs’ consent. |Jd.] This decision was erroneous.
A. The Trial Court Should Not Have Reached the
Merits of Plaintiffs’ Third-Party Beneficiary Claim
For two reasons, the trial court should not have
reached the merits of the third-party beneficiary issue.
One reason is that Plaintiffs were collaterally estopped
from making that argument. The second reason is that all
of the parties to the Subcontracts were indispensable with
regard to that claim. Two of the parties to the Subcon-
tracts had not been joined.
1. Plaintiffs Are Collaterally Estopped From
Making a Third-Party Beneficiary Claim.
Plaintiffs had previously sued CAWCD over the same
issues that Plaintiffs raised in this case. Judge Carroll of
the United States District Court held in September 2003
that Plaintiffs were not third-party beneficiaries of the
Subcontracts and dismissed their complaint. [App. 29,
Exhibit 1.]
Collateral estoppel or issue préclusion is applicable
when (1) the issue or fact to be litigated was actually
litigated in a previous suit; (2) final judgment was entered;
App. 45
(3) the party against whom the doctrine is to be invoked
had a full opportunity to litigate the matter and actually
did litigate it; and (4) the resolution of the issue was
essential to the prior judgment. State ex rel. Dept. of
Economic Sec. v. Powers, 184 Ariz. 235, 237, 908 P.2d 49,
51 (App. 1995). Judge Carroll’s opinion itself establishes
that all of these requirements were satisfied in this in-
stance. [App. 29, Exhibit 1.]
Plaintiffs contended that collateral estoppel did not
apply because they were appealing Judge Carroll’s deci-
sion to the Ninth Circuit. The pendency of Plaintiffs’
appeal, however, did not suspend the collateral estoppel
effect of Judge Carroll’s ruling. Federal law controls when
the preclusive effects of a federal judgment are asserted in
a state proceeding. See C. Wright, A. Miller & E. Cooper,
Federal Practice and Procedure § 4433, at 310 (1981).
Under federal law, the pendency of an appeal does not
suspend the issue-preclusion effect of a judgment. Robi v.
Five Platters, Inc., 838 F.2d 318, 327 (9th Cir. 1988);
Hawkins v. Risley, 984 F.2d 321, 324 (9th Cir. 1993).
Although the issue of collateral estoppel was briefed
and argued, the trial court made no mention of it when
issuing a ruling that was directly at odds with the prior
ruling of the federal district court. [Ex. A at 4.]
2. indispensable Parties Were Not Joined in
the Trial Court.
All of the parties to the Subcontract were indispensa-
ble parties with regard to Plaintiffs’ third-party benefici-
ary claim. Two of the three parties to each Subcontract —
i.e., the United States and CAWCD - were not joined in
the trial court.
App. 46
A motion that raised this defect in parties was pend-
ing when the trial court granted summary judgment. That
motion has still not been formally decided by the trial
court. The court’s decision to rule on the merits without
addressing the defect in parties, however, constituted an
implicit denial of the motion. The fact that there has been
no formal ruling on this issue by the trial court does not
preclude this Court from addressing the issue. The ab-
sence of indispensable parties may be raised for the first
time on appeal. Siler v. Superior Court, 83 Ariz. 49, 54, 316
P.2d 296, 300 (1957).
Third-party beneficiary rights are contract rights. See
9 Corbin on Contracts § 779J (Interim ed. 2002). The trial
court’s conclusion that Plaintiffs are intended beneficiaries
of the Subcontracts means that individual landowners can
enforce the Subcontracts directly against the United
States and CAWCD. See Restatement (Second) of Con-
tracts § 304. It means that individual landowners can veto
changes to the Subcontracts under certain circumstances.
Id. § 311, comment g. By allowing a non-party to the
Subcontract to prohibit contract modifications, the trial
court effectively impeded the ability of all three contract-
ing parties to modify their agreement by consent. The trial
court’s ruling therefore impaired the interests of the
absentees. See Ariz. R. Civ. P. 19(a).
Because the trial court rendered a ruling that was
contrary to the prior federal court ruling, the parties to the
Subcontracts are now subject to inconsistent adjudications
concerning the rights and obligations that arise under
their agreements. That fact provides a separate basis for
concluding that the United States and CAWCD are neces-
sary parties. Jd.
App. 47
“[A] contracting party is the paradigm of an indispen-
sable party.” Travelers Indemnity Co. v. Household Int'l,
Inc., 775 F. Supp. 518, 527 (D. Conn. 1991). The trial court
erred in deciding contractual rights and obligations when
two of the three parties to the contracts at issue were not
present to defend their interests.
B. Federal Law Establishes that Plaintiffs Are
Not Intended Third-Party Beneficiaries.
Yet another problem with the trial court’s ruling was
that the trial court applied the wrong body of substantive
law to the issue. The United States is a party to the
Subcontracts. Federal law determines whether someone is
a third-party beneficiary of a contract to which the United
States is a party, Klamath Water Users Protective Ass’n v.
Patterson, 204 F.3d 1206, 1210 (9th Cir. 1999), cert. denied,
531 U.S. 812 (2000); see also Kennewick Irr. Dist. v. United
States, 880 F.2d 1018, 1032 (9th Cir. 1989) (federal law
controls the interpretation of a contract entered into
pursuant to federal law when United States is a party).
The federal district court had properly applied federal law
when it concluded that Plaintiffs were not intended
beneficiaries of the Subcontracts. [App. 29, Exhibit 1.] The
trial court, without addressing the choice-of-law issue,
applied Arizona law to the third-party beneficiary analy-
sis. [Ex. A at 4.]
Under the federal law that should have been applied,
Plaintiffs were not third-party beneficiaries of the Subcon-
tracts. Parties that benefit from a government contract are
generally assumed to be incidental beneficiaries unless the
contract evidences a clear intent to the contrary. Klamath,
204 F.3d at 1211 (holding that water users were not
intended beneficiaries of a reclamation contract); accord
App. 48
Orff v. United States, 358 F.3d 1137, 1145-47 (9th Cir.),
cert. granted, 125 S. Ct. 309, 73 USLW 3228, 73 USLW
3235 (2004).°
The thirty-six-page Subcontracts between the Dis-
tricts, the United States, and CAIDD are almost entirely
silent about the landowners. Nothing in the Subcontracts
expressly or implicitly indicates that the landowners
within the Districts were to have intended-beneficiary
status.
Plaintiffs argued that section 4.3(i) of the Subcontract,
commonly known as the “conversion” provision, shows that
landowners were intended to have enforceable rights.
[App. 11; App. 20; App. 29, at 19-21; App. 47.] Agricultural
CAP water is cheaper than municipal and industrial water
and, by law, agricultural water can only be provided to
eligible users. [See App. 9, Exhibit 3, § 4.3(i); App. 9,
Exhibit 4, § 4.3(i).] Section 4.3(i) provides that if the use of
particular land were to change from agricultural to mu-
nicipal and industrial (e.g., subdivisions), that land would
remain eligible to receive CAP water but a new agreement,
with higher water rates and involving other parties, would
be required. The conversion provision ensured that ineli-
gible lands would not receive agricultural water and that
* Certiorari was granted in Orff to resolve an apparent conflict
between Orff and the decision in H. F. Allen Orchards v. United States,
749 F.2d 1571 (Fed. Cir. 1984), cert. denied, 474 U.S. 818 (1985), which
held that certain landowners were third-party beneficiaries of a water
contract. H. F. Allen is distinguishable from the present case because it
was agreed in H.F. Allen that the landowners owned the water rights
governed by the contract. In any event, the test used in Orff to deter-
mine third-party beneficiary status accords with the Restatement view,
as discussed hereafter, and it is unlikely that the Supreme Court will
articulate a materially different test.
App. 49
the Districts would not pay low agricultural rates to serve
what were in fact municipal and industrial water users.
Section 4.3(i) never mentions landowners. The land-
owner is given no role in the conversion of water from
agricultural to municipal and industrial purposes. The fact
that landowners could, as a practical matter, trigger
certain consequences under the Subcontracts by retiring
their land from fanning does not mean that they had
rights under those agreements. The conversion provision
does not come close to reflecting a “clear intent” to “grant
[the landowners] enforceable rights” as required by federal
law. Klamath, 204 F.3d at 1211.
C. Even if Arizona Law Applied to the Issue,
Plaintiffs Would Not Be Intended Third-Party
Beneficiaries.
Incorrectly applying Arizona law, the trial court based
its third-party beneficiary holding on two premises. One
was that “the subcontracts were created to provide means
for distribution of CAP water to agricultural landowners, a
class in which the plaintiffs fit.” [Ex. A at 4.] Although the
purposes of the various parties to the Subcontract were
more varied and complex than such a statement indicates,
the statement was substantially correct.
The trial court then cited a decision by this Court that
observed that
irrigation districts are organized for the direct
private benefit of their landowners and taxpay-
ers. As such, they are required to help pay for the
irrigation system and are entitled to a propor-
tionate share of the water for irrigation of their
App. 50
lands, as also any profits accruing from the op-
eration of the system.
Post v. Wright, 37 Ariz. 105, 117, 289 P. 979, 983 (1930),
quoted in Ex. A at 4. Based on the overall purpose of the
Subcontracts and the language from Post v. Wright, the
trial court concluded that Plaintiffs were intended benefi-
ciaries and that the agreements could not be modified
without their consent.
Neither Post v. Wright nor any other Arizona decision
has established such an impractical test for third-party
beneficiary status. The statement in Post v. Wright that
landowners are entitled to a proportionate share of water
speaks to the relationship between an irrigation district
and its landowners. That case did not say or imply that
each individual landowner in an irrigation district has the
right to veto modifications of contracts between the irriga-
tion district and third parties.
Petitioners are not aware of any Arizona decisions
that address the test for determining whether someone is
a third-party beneficiary of a government contract. Cf.
Basurto v. Utah Construction & Mining Co., 15 Ariz.App.
35, 485 P.2d 859, 863 (App. 1971) (identifying general test
for third-party beneficiary status). The Restatement view
is that, although government contracts often benefit the
public, individual members of the public are treated as
incidental beneficiaries unless a different intention is
manifested. Restatement (Second) of Contracts § 313,
comment a; see also id., illustration B. Only when such a
contract manifests a clear intent to grant individual
citizens enforceable rights can a citizen claim to be an
intended third-party beneficiary. See Berberich v. United
States, 5 Cl. Ct. 652, 656 (1984), aff’d, 770 F.2d 179 (Fed.
App. 51
Cir. 1985); Coburn v. City of Dyersburg, 774 S.W.2d 610,
612 (Tenn. App. 1989).
The trial court’s contrary holding would apparently
give rise to a rule that, whenever a contract with a public
entity is ultimately for the sake of the public entity’s
constituents, those constituents are intended beneficiaries.
That rule would make the citizenry intended beneficiaries
of most governmental contracts. That would mean that
each citizen could sue to enforce such contracts and that,
at least in some cases, each citizen could block any pro-
posed changes to such contracts. See Restatement (Second)
of Contracts §§ 304 and 311, comment g. The patent
unworkability of such a rule explains why no court ap-
pears ever to have adopted it, except for the trial court in
this case.
D. Summary
In a case involving the very same Plaintiffs and the
very same issues, a federal court had already held that
Plaintiffs.were not intended beneficiaries of the Subcon-
tracts. The trial court nonetheless revisited and accepted
an argument that Plaintiffs were collaterally estopped
from making. The trial court ignored the absence of
indispensable parties. It applied the wrong substantive
law. It then reached the wrong result pursuant to a ra-
tionale which, if generally applied, would significantly
impair governmental operations. If the trial court’s ruling
stands, the parties to the Subcontracts will be subject to
flatly contradictory and irreconcilable adjudications
concerning the rights and obligations created by those
agreements. That ruling should not stand.
App. 52
Ill. THE TRIAL COURT ERRED IN FINDING THAT
RIGHTS TO WATER UNDER THE DISTRICTS’
CAP SUBCONTRACTS WERE APPURTENANT
TO PLAINTIFFS’ LAND AND THAT PLAIN-
TIFFS HAD INDIVIDUALIZED RIGHTS IN
THOSE SUBCONTRACTS.
As an alternate basis for granting summary judgment,
the trial court found that Plaintiffs had acquired individ-
ual rights to Subcontract water by operation of law. The
trial court held that the Districts’ CAP Subcontracts were
appurtenant to the land within the Districts and that
Plaintiffs therefore had individualized rights to a pro rata
portion of the Subcontract rights. [Ex. A at 1-3.] For these
reasons, the trial court concluded that the Districts could
not modify the Subcontracts without each landowner’s
consent [J/d.]
The trial court applied the wrong law to this issue and
reached an entirely incorrect result. The state law that
governs the acquisition of water rights in connection with
many Reclamation projects does not apply to post-1928
rights in projects involving water from the Lower Colorado
River, including the CAP. Federal law controls the acquisi-
tion of such rights. Such rights can be acquired only
through a contract with the Secretary. Plaintiffs have no
such contract, and they have no individual rights to the
water.
A. Post-1928 Rights to Wate; from Reclamation
Projects on the Lower Colorado River Can Only
Be Acquired by Contract.
Many Reclamation projects in the United States are
governed by rules that were established in the 1902
Federal Reclamation Act, 43 U.S.C. § 383. Section 8 of that
App. 53
Act, upon which the trial court incorrectly relied in its
ruling, provides that the Reclamcation Act is not to be
construed as affecting or interfering with state laws
“relating to the control, appropriation, use, or distribution
of water used in irrigation.” 43 U.S.C. § 383, cited in Ex. A
at 2. The acquisition of water rights in connection with
many Reclamation projects is therefore governed by state
law.
In 1928, however, Congress enacted legislation that
provided a different rule for the Lower Colorado River. The
Boulder Canyon Project Act of 1928 allocated rights to the
Colorado River among the three Lower Basin states
(California, Arizona, and Nevada). The same act gave the
Secretary of the Interior exclusive control over allocating
Lower Colorado River water among the individual states
and among various entities within those states. Section 5
of the act made it clear that rights to water from Reclama-
tion projects on the Colorado River could be acquired only
pursuant to a contract with the Secretary:
The Secretary of the Interior is hereby author-
ized, under such general regulations as he may
prescribe, to contract for the storage of water in
said reservoir and for the delivery thereof at such
points on the river and on said canal as may be
agreed upon, for irrigation and domestic uses. . . .
No person shall have or be entitled to have the use
for any purpose of the water stored as aforesaid
except by contract made as herein stated.
43 U.S.C. § 617d (emphasis added)
The United States Supreme Court acknowledged that
post-1928 rights to Lower Colorado River water could be
acquired only by a contract with the Secretary in Arizona
v. California, 373 U.S. 546 (1963). The Court discussed the
App. 54 App. 55
Id. at 580-81 (emphasis added). The Court also observed
that if Congress had intended that the Secretary’s power
to allocate water contractually would be subject to state-
law water rights, it would have said so. It did not.
Secretary's broad authority to allocate Colorado River
water between individual entities in the affected states by
entering into water delivery contracts with those entities.
The Court noted that Congress had intentionally main-
tained federal control over the allocation of such water:
Having undertaken this beneficial project, Con-
gress, in several provisions of the [1928] Act,
made it clear that no one should use mainstream
[Colorado River] waters save in strict compliance
with the scheme set up by the Act. Section 5 au-
thorized the Secretary [of the Interior] “under
such general regulations as he may prescribe, to
contract for the storage of water in said reservoir
and for the delivery thereof at such points on the
river * * * as may be agreed upon, for irrigation
and domestic uses * * * .” To emphasize that wa-
ter could be obtained from the Secretary alone,
§ 5 further declared, “No person shall have or be
entitled to have the use for any purpose of the
water stored as aforesaid except by contract
made as herein stated.”
Significantly, no phrase or provision indicating
that the Secretary's contract power was to be
controlled by the law of prior appropriation was
substituted either then or at any time before
passage of the Act, and we are persuaded that
had Congress intended so to fetter the Secre-
tary’s discretion, it would have done so in clear
and unequivocal terms, as it did in recognizing
“present perfected rights” [i.e., those rights ac-
quired prior to passage of the 1928 Act] in § 6.
Id.
B. Section 8 of the 1902 Reclamation Act Does Not
Apply to This Case.
The trial court’s ruling in this case was expressly
grounded on Section 8 of the 1902 Federal Reclamation
373 U.S. at 579-80. Act, 43 U.S.C. § 383, which makes state law generally
determinative of water rights in other Reclamation pro-
jects. [Ex. A at 2.] The court in Arizona v. California,
however, held that Section 8 did not apply to post-1928
contracts with the Secretary for Lower Colorado River
water:
The Court went on to state that, based upon Congress’
express statement in the 1928 Act, contracts with the
Secretary were the exclusive means to allocate post-1928
legal rights to the waters of the Lower Colorado River:
These several provisions, even without legisla-
tive history, are persuasive that Congress in-
tended the Secretary of the Interior, through his
§ 5 contracts, both to carry out the allocation of
the waters of the main Colorado River among the
Lower Basin States and to decide which users
within each State would get water. ...
... [Wle hold that the Secretary in choosing be-
tween users within each State and in settling the
terms of his contracts is not bound by these sec-
tions [e.g., Section 8 of the Reclamation Act] to
follow state law.... While the States were gen-
erally free to exercise some jurisdiction over
these waters before the Act was passed, this
App. 56
right was subject to the Federal Government's
right to regulate and develop the river....
[Wlhere the Secretary’s contracts, as here, carry
out a congressional plan for the complete distri-
bution of waters to users, state law has no place.
Id. at 586-88 (emphasis added).
In support of its conclusion, the trial court also cited
California v. United States, 438 U.S. 645 (1987). [Ex. A at
3.] California v. United States did not involve Colorado
River water or the distinct body of law that governs rights
to water from that river. At issue were rights to the Stanis-
laus River under the Central Valley Project in California.
438 U.S. at 645. In that case, Section 8 of the 1902 Recla-
mation Act applied and the landowners were required to
obtain an appropriative right under state law. California
vu. United States sheds no light on the acquisition of water
rights under the distinct rules that apply to the Colorado
River.
California v. United States arguably narrowed some of
the other holdings in Arizona v. California. The court in
California v. United States acknowledged, however, as to
the allocation and use of Colorado River water, the specific
provisions of Section 5 of the 1928 Act controlled over the
general provisions in Section 8 of the 1902 Reclamation
Act. See 438 U.S. at 674; see also Bryant v. Yellen, 447 U.S.
352, 370-71 & n.21, reh’g denied, 448 U.S. 911 (1980)
(California v. United States did not question the descrip-
tion of the Secretary's powers under the 1928 Act); Long v.
Salt River Valley Water Users’ Ass’n, 820 F.2d 284, 287 n.4
(9th Cir. 1987) (same).
App. 57
C. Plaintiffs Have No Individual Rights to Sub-
contract Water.
The Subcontracts give the Districts specified rights to
CAr water. Plaintiffs are not parties to those agreements.
They have no contracts with the Secretary. They therefore
have no individual rights to CAP water. 43 U.S.C. § 617d.
Even if the trial court had been correct in applying
state law to this issue, its ruling would still have been
erroneous. Arizona law provides that water users can
acquire rights to surface water only pursuant to the
doctrine of prior appropriation. See A.R.S. § 45-151; see
also Clough v. Wing, 2 Ariz. 371, 17 P. 453 (1888); San
Carlos Apache Tribe v. Superior Court, 193 Ariz. 195, 972
P.2d 179 (1999). Plaintiffs have never appropriated or
received any Subcontract water. [App. 14, J 37.] No land-
owners in either District have. [Jd.] Because Subcontract
water was priced too high for farmers to use, the Districts
have obtained all the CAP water they have received by
short-term excess water contracts. Plaintiffs would there-
fore have no individual rights to Subcontract water even if
state law were applicable.
D. Summary
Federal law determines how rights to CAP water are
acquired. That law provides that such rights can be
acquired only by contract with the Secretary Plaintiffs
have no such contract, and they have no rights to CAP
water.
App. 58
CONCLUSION
Only prompt relief by this Court can ensure that the
trial court’s erroneous rulings do not derail a major water
settlement. Petitioners request that this Court grant
special action relief directing the superior court to (1)
vacate the grant of summary judgment to Plaintiffs; and
(2) enter summary judgment that Plaintiffs are not in-
tended third-party beneficiaries of the Subcontracts
among the United States, CAWCD and the Districts, and
that Plaintiffs have not acquired individual rights to
receive water pursuant to those Subcontracts under the
law that governs the acquisition of rights to water from
the Lower Colorado River. Petitioners also request an
award of their attorneys’ fees pursuant to A.R.S. § 12-
341.01(A).
December 14, 2004.
/s/ Donald M. Peters
Donald M. Peters
Susan A. Cannata
MILLER LaSOTA & PETERS, PLC
5225 North Central, Suite 235
Phoenix, AZ 85012
Telephone: (602) 248-2900
Attorneys for Maricopa-Stanfield
Irrigation & Drainage District
App. 59
/s/ Mark A. McGinnis
/s/
Richard N. Morrison
M. Byron Lewis
Mark A. McGinnis
SALMON, LEWIS & WELDON, PL.C.
2850 East Camelback Road, Suite 200
Phoenix, Arizona 85016
Telephone: (602) 801-9060
Attorneys for Central Arizona
Irrigation and Drainage District
Marvin S. Cohen
Marvin S. Cohen
SACKS TIERNEY P.A.
4250 North Drinkwater Blvd.
Suite 400
Scottsdale, Arizona 85251
Telephone: (480) 425-2633
Attorneys for Approximately Two
Hundred Landowners
App. 60
Arizona Water Settlement Agreement
This Agreement is among the United States of America,
acting through the Secretary of the Interior (Secretary)
and the United States Bureau of Reclamation, Lower
Colorado Regional Office; and the State of Arizona,
acting through the Arizona Department of Water Re-
sources (ADWR); and the Central Arizona Water
Conservation District (CAWCD), a political subdivision
of the State of Arizona.
1. Recitals of Authority
1.1
1.2
1.3
The United States, acting through the Depart-
ment of the Interior, is entering into this agree-
ment pursuant to the Act of June 17, 1902, 32
Stat. 388, and acts amendatory thereof and
supplementary thereto, including, but not lim-
ited to the Boulder Canyon Project Act of De-
cember 21, 1928 (45 Stat. 1057), as amended,
the Reclamation Project Act of August 4, 1939
(53 Stat. 1187), as amended, the Colorado River
Basin Project Act of September 30, 1968 (82
Stat. 885), as amended, all collectively referred
to as the “Federal Reclamation Laws.”
The State of Arizona, acting through the Ari-
zona Department of Water Resources, is enter-
ing into this agreement pursuant to Arizona
Revised Statutes, Title 45, Ch. 1.
The Central Arizona Water Conservation Dis-
trict is entering into this agreement pursuant
to Arizona Revised Statutes, Title 48, Ch. 22.
App. 61
2. Definitions
2.1
aa 2.2
2.3
2.4
2.5
2.6
2.7
“1983 ROD” shall mean the record of decision
published March 24, 1983, 48 Fed. Reg. 12446.
“Act” shall mean the Arizona Water Settlements
Act of 2002, introduced in the United States
Senate as S.2992 on September 24, 2002.
“CAIDD” shall mean the Central Arizona Irri-
gation and Drainage District, a political subdi-
vision of the State of Arizona.
“CAP” shall mean the Central Arizona Project,
as authorized and constructed pursuant to the
Colorado River Basin Project Act of 1968. For
purposes of this Agreement, CAP shall have the
Same meaning as described in the CAWCD Re-
payment Stipulation.
“CAP Repayment Stipulation” shall mean the
Stipulation Regarding a Stay of Litigation,
Resolution of Issues During the Stay and for
Ultimate Judgment Upon Satisfaction of Condi-
tions, filed pursuant to the order entered on
May 9, 2000 in Central Arizona Wace Conser-
vation District v. United States, et al. No. CIV-
95-625-TUC-WDB (EHC), No. CIV-95-1720-
PHX-EHC (Consolidated Action), United States
District Court for the District of Arizona, and
any amendment or revision thereof.
“Currently Uncontracted M&lI Priority water”
shall mean 65,647 acre-feet of CAP municipal
and industrial priority water that was allocated
in the 1983 ROD but for which a long-term con-
tract has not been entered.
“GRIC Settlement Agreement” shall mean the
Gila River Indian Community Water Rights
Settlement Agreement as defined in the Act.
2.8
2.9
2.10
2.11
2.12
App. 62
“HIDD” shall mean the Hohokam Irrigation
and Drainage District, a political subdivision of
the State of Arizona.
“Hohokam Agreement” shall mean the Agree-
ment Among the United States, the Central
Arizona Water Conservation District, the Ho-
hokam Irrigation and Drainage District, and
the Arizona Cities of Chandler, Mesa, Phoenix
and Scottsdale, dated December 21, 1993.
“Hohokam 9(d) Debt” shall mean that portion of
the debt to the United States incurred by HIDD
under section 9(d) of the Reclamation Project
Act of 1939 that is payable by HIDD under sec-
tion 4.2.2 of the Hohokam Agreement.
“MSIDD” shall mean the Maricopa-Stanfield Ir-
rigation & Drainage District, a political subdi-
vision of the State of Arizona.
“NIA Priority water” shall mean CAP water
having a non-Indian agricultural priority as de-
scribed in subparagraph 8.16 of the GRIC Set-
tlement Agreement.
3. Purpose of this Agreement
3.1
This agreement memorializes the parties’ in-
tended approach to settle all current CAP allo-
cation issues between the United States and
the State of Arizona by agreeing to make cer-
tain quantities of NIA priority water available
to the Secretary for allocation to Indian com-
munities, and certain quantities available to
ADWR to be held in trust for future allocation
by the Secretary to non-Indian users within
Arizona in a manner consistent with the Act.
3.2
App. 63
This agreement also requires a reallocation of
the Currently Uncontracted M&I Priority Wa-
ter, and an allocation of and contract for main-
stream Colorado River water under the Boulder
Canyon Project Act of 1928 to the Mohave
County Water Authority in exchange for the
voluntary relinquishment by Mohave County
Water Authority of certain contractual rights to
NIA Priority water.
4. Quantification of NIA Priority water available
for Contract.
4.1
The parties agree that, for the purpose of enter-
ing into long term contacts and subcontracts for
CAP water under the Colorado River Basin Pro-
ject Act of 1968 and the CAP Stipulation, the
quantity of CAP water available for long-term
contract or subcontract, and the quantity of
NIA priority water available for long term con-
tracts and subcontracts shall be calculated as
follows:
4.1.1 The normal year supply of Colorado River
water available for CAP is deemed to be
1,490,000 acre-feet per year for purposes of
long-term contracting. This supply in-
cludes the CAP Project Water delivered in
accordance with the Ak-Chin Indian Com-
munity Water Rights Settlement Act of
1984, Pub. L. 98-530 (the “Ak-Chin Act”),
and the Salt River Pima-Maricopa Indian
Community Water Rights Settlement Act
of 1988, Pub. L. 100-512 (the “SRPMIC
Act”). Nothing in this agreement shall pre-
clude CAWCD from diverting more than
1,490,000 acre-feet of Colorado River water
in any year, but such excess diversion shall
4.1.2
4.1.3
4.1.4
4.1.5
App. 64
not be available for long-term contract or
subcontract.
To determine the amount of CAP water
available for long-term contract and sub-
contract, canal losses and other operational
losses for the CAP system must be sub-
tracted. For purposes of this agreement,
such losses shall be deemed to be 75,000
acre-feet per year for a normal year supply.
The normal year supply of CAP water
available for long-term contract or subcon-
tract shall be 1,415,000 acre-feet
(1,490,000- acre-feet diverted from the
Colorado River less 75,000 acre-feet of sys-
tem loss).
Of the 1,415,000 acre-feet available for
long-term contract or subcontract, the Sec-
retary allocated 309,828 acre-feet to Indian
uses and 638,823 acre-feet to municipal
and industrial (““M&I”) uses in the 1983
ROD. That left 466,349 acre-feet available
for use by non-Indian agriculture in a
normal year (the “1983 NIA Supply”).
The 1983 NIA Supply was subsequently
reduced as follows:
4.1.5.1 Under the Ak-Chin Act, the Secre-
tary acquired 50,000 acre-feet of
Colorado River water from the
Yuma-Mesa Division of the Gila
Project. After deducting for CAP
system losses (deemed to be 5%),
this acquisition resulted in a de-
crease of 47,500 acre-feet in the
amount of CAP water available for
4.1.5.2
4.1.5.3
4.1.5.4
App. 65
use by non-Indian agriculture in a
normal year.
Under the SRPMIC Act, the Secre-
tary acquired 22,000 acre-feet of
Colorado River water from the
Wellton-Mohawk Irrigation Dis-
trict. After deducting for CAP sys-
tem losses (deemed to be 5%), this
acquisition resulted in a decrease of
20,900 acre-feet in the amount of
CAP water available for use by
non-Indian agriculture in a normal
year.
Under the Fort McDowell Indian
Community Water Rights Settle-
ment Act of 1990, Pub. L. 101-628,
the Secretary acquired the CAP en-
titlement of Harquahala Valley Ir-
rigation District and was
authorized to convert that water
from CAP non-Indian agricultural
priority to CAP Indian priority.
This acquisition resulted in a de-
crease of 33,251 acre-feet in the
amount of CAP water available for
use by non-Indian agriculture in a
normal year.
Under the SRPMIC Act, the Roose-
velt Water Conservation District
(“RWCD”) assigned 5,000 acre-feet
of its CAP entitlement to certain
Arizona cities. That assignment re-
sulted in a corresponding decrease
in the amount of CAP water avail-
able for use by non-Indian agricul-
ture in a normal year.
4.2
App. 66
4.1.5.5 Under an August 7, 1992 agree-
ment among RWCD, the Secretary
and the Gila River Indian Commu-
nity (““GRIC”), RWCD relinquished
the remainder of its CAP entitle-
ment for the use and benefit of
GRIC. That relinquishment re-
sulted in a decrease of 18,600 acre-
feet in the amount of CAP water
available for use by non-Indian ag-
riculture in a normal year.
4.1.5.6 Under the Hohokam Agreement,
the CAP entitlement of HIDD and
certain additional non-Indian agri-
cultural water was subcontracted
to the cities of Chandle