Petition for Writ of Certiorari — Roanoke River Basin Ass'n v. Hudson

Supreme Court brief1992

Ask Donna

What actually matters in this document.

Text

9l- 84 Buoreme Court, U.S,

BEQRD No. _C PILED

Lt NOV 12 1998

IN THE | OFFICE OF THE CLERK

Supreme Court of the Gnited States

October Term, 1991

ROANOKE RIVER BASIN ASSOCIATION

and STATE OF NORTH CAROLINA,

Petitioners,

COLONEL RONALD E. HUDSON, in his official capacity as

Norfolk District Engineer, THE CITY OF VIRGINIA BEACH

VIRGINIA,

Respondents.

PETITION FOR WRIT OF CERTIORARI

TO THE UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

Patrick M. McSweeney Lacy H. Thornburg

Counsel of Record Attorney General

Michael V. Hernandez Alan S. Hirsch

McSWEENEY, BURTCH Special Deputy

& CRUMP, P.C. Attorney General

Post Office Box 1443 N.C. DEPT. OF JUSTICE

11 South Twelfth Street Post Office Box 629

Richmond, VA 23212 Raleigh, NC 27602

(804) 783-6800 (919) 733-5725

Counsel for Petitioner Counsel for Petitioner

Roanoke River Basin State of North Carolina

Association

Appellate Printing Services * 523 East Main Street * Richmond, VA 23219 * (800) 642-7789

QUESTIONS PRESENTED FOR REVIEW

I. Is the Corps of Engineers ("the Corps")

required to explain how its mitigation condition will

eliminate the environmental effects of a proposed project

when it relies om: mitigation to avoid preparing an

Environmental Impact Statement (EIS)?

II. Is the Corps required in a National

Environmental Policy Act (NEPA) case to make information

on which it relies available for public review and comment

before it makes a decision not to prepare an EIS?

III. Is the Corps required to provide a complete

explanation of a computer model on which it has relied once

substantial questions about the model have been raised?

IV. Has the Corps improperly interpreted and

applied binding regulations of the Council on Environmental

Quality which govern whether an EIS must be prepared?

LIST OF PARTIES BELOW

APPELLANTS-PLAINTIFFS: Roanoke River Basin

Association and State of North Carolina.

PLAINTIFFS: Counties of Bertie, Granville, Halifax,

Martin, Northampton, Vance, Warren & Washington, North

Carolina; Counties of Charlotte, Halifax & Mecklenburg,

Virginia.

APPELLEES-DEFENDANTS: Ronald E. Hudson, in his

official capacity as Norfolk District Engineer; Wayne A.

Hanson, in his official capacity as Wilmington District

Engineer; Joseph K. Bratton, Lieutenant General, in his

official capacity as the Chief of Engineers of the United

States Army Corps of Engineers; William R. Gianelli, in his

official capacity as Assistant Secretary of the United States

Department of the Army; John O. Marsh, in his official

Capacity as Secretary of the United States Department of the

Army; and the City of Virginia Beach, Virginia.

ll

Uesiee

TABLE OF CONTENTS

QUESTIONS PRESENTED FOR REVIEW ...... i

LIST OF PARTIES BELOW ........2seeees ii

TABLE OF AUTHORITIES ............... Vii

OPINIONS DELIVERED IN THIS CASE

Pe BPeee MPP CPU ow ce tt tt ee ]

GROUNDS UPON WHICH THE JURISDICTION

OF THIS COURT IS INVOKED ....\4........ l

STATUTES AND REGULATIONS

INVOLVED IN THIS CASE ............... 2

SrAlemen: Of THE CASE ..........2.2-. 2

I. CE 2

A. The Roanoke River System .. 3

B. Albemarle-Roanoke Striped

a aa Re 7

Il. Nature Of The Case And Prior

as Soo as os + 9 + 2 12

REASONS FOR GRANTING THE WRIT ...... 24

ill

Il.

III.

IV.

The Opinion Below Is In Error And In

Conflict With Decisions Of The Ninth

Circuit Regarding The Need To

Explain Specifically How Mitigation

Will Eliminate Potentially Significant

Environmental Impacts. .........

The Opinion Below Is In Error And In

Conflict With The Rule Adopted By

This Court That Critical Information

On Which The Agency Relies Must Be

Made Available For Review And

Comment Before The Agency Makes

DA kek ee oe ee ee

The Opinion Below Is In Error And In

Conflict With Decisions Of The

District Of Columbia Circuit

Requiring Agencies to Provide A

Complete Analytical Defense Of

Modeling Which Has_ Been

a ee

The Opinion Below Is In Error And In

Conflict With Decisions Of Other

Courts of Appeals Implementing The

CEQ Regulations Which Govern

Whether An EIS Must Be Prepared.

A. Controversy --

40 C.F.R. § 1508.27(b)(4)

B. Uncertainty --

40 C.F.R. § 1508.27(b)(5)

1V

26

38

44

49

C. Cumulative Impacts --

40 C.F.R. §§ 1508.7

& 1508.27(b)(7) .......

(A ek eee hee ee eae sess

APPENDIX A

R iV i lation v :

940 F.2d 58 (4th Cir. 1991) .............

APPENDIX B

State of North Carolina v. Hudson,

731 F. Supp. 1261 (E.D.N.C. 1990) .......

APPENDIX C

Order dated February 2, 1990,

State of North Carolina v. Hudson,

No. 84-36-CIV-5 (E.D.N.C. 1990) ........

APPENDIX D

State of North Carolina v. Hudson,

665 F. Supp. 428 (E.D.N.C. 1987) ........

APPENDIX E

Order dated July 7, 1987,

State of North Carolina v. Hudson,

No. 84-36-CIV-5 (E.D.N.C. 1987) ........

APPENDIX F

ie EO © is 0 0 a kek oe 8 es Heo

APPENDIX G

P.L. 100-589, 102 Stat. 2984 (1988)

Lie | Ne er yer e ae ae

APPENDIX H

DAT OEE see bicsseccececvene 165a

APPENDIX I

8 ee a ee 166a

APPENDIX J

ar ae arr 167a

APPENDIX K

oS a er 168a

APPENDIX L

Co 8 169a

oY i er 169a

Co Rs a 170a

vi

TABLE OF AUTHORITIES

Alabama Power Co. v. Costle,

GO Fae eee Cais Ss BT ct ee et ae 38

567 F.2d 1016 (D.C. Cir. 1977), cert. denied,

Ge CES. Goa caeendecceceneacs 38

wman Tran ion Vv

Arkansas-Best Freight System, Inc.,

a 34

Oj F Virinia Beact k ke Ri

Basin Association, 776 F.2d 484 (4th Cir. 1985) ... 15

Conner v, Burford, 848 F.2d 1441 (1988),

cert, denied, 489 U.S. 1012 (1989) ........... 46

Eagle-Picher Industries v. U.S. EPA,

tae Cee ee ea Ee RO See et te 38

Ely v. Velde, 451 F.2d 1130 (4th Cir. 1971) ... 34, 39

Foundation for North American Wild Sheep v.

U.S. Dept. of Agriculture,

681 F.2d 1172 (th Cir. 19962) .........26- 45, 50

Foundation on Economic Trends v. Heckler,

587 F. Supp. 753 (D.D.C. 1984),

aff'd in part, vacated in part on other grounds,

Fae Cae Be Ga Ss BD bc vee ee ee 47, 50

Fritiofson v. Alexander, 772 F.2d 1225 (1985) .... 52

Vil

Gee v. Hudson, 746 F.2d 1471, 22 ERC 1213

(4th Cir. 1984) cert. denied, 471 U.S. 1058 (1985) .. 54

ing Fi mv midt,

626 F.2d 1068 (Ist Cir. 1980) .............. 37

Hanly v. Kleindienst,

471 F.2d 823 (2d Cir. 1972),

cert. denied, 412 U.S. 908 (1973) .......... 43, 52

Jones v. Gordon, 792 F.2d 821 (9th Cir. 1986) 27, 45, 50

LaFlamme v. FERC, 852 F.2d 389 (1988) .. 27, 44, 53

ee Wame ERE Ge Gs SD gw ke ce ee 43

Marsh v. Oregon N R r ncil,

Se ee I cc cue e eee ce anees 35, 37

McLouth Steel Prod. Corp. v. Thomas,

oer Gk ee oe re 34 _

Minnesota Public Interest Research Group v. Butz,

ra 43

National Wildlife Federation v, Marsh,

568 F. Supp. 985 (D.D.C. 1983) ........... 34, 37

Natural Resources Defense Council, Inc. v. Herrington,

Fae ee Bs a SE 6 6 ose eran ewe ks 38

North Carolina Environmental Policy Institute v. EPA,

Sel F.20 1250 C60) Cir, TSG) 2. wc tec cw ws 34

viii

ee ee

Pension Benefit Guaranty Corp. v. LTV Corp.,

LID DS. G2. Be CHRSUe oc cee cee 34, 35, 37

pec Pf Gis f+ A Re rn 43

Roanoke River Basin Association v. Hudson,

940 F.2d 58 (4th Cir. 1991) .............. passim

R nv. Methow Vall itizen ncil,

8 ae a ee 27, 36

Sierra Club v. Costle,

657 F.2d 298 (D.C. Cir. 1981) ............ 34, 38

Sierra Club v. Morton,

ee | Ds a | ar 35

Sierra Club v, Peterson,

Tid Fae 1609 OC. Cir. 1963) 2... wc cc ce es 43

Sierra Club v, U.S. Forest Service,

843 F.2d 1190 (9th Cir. 1988) ....... 43, 44, 49, 50

Silva v. Lynn, 482 F.2d 1282 (1st Cir. 1973) ..... 35

Small Refiner Lead Phase-Down Task Force v.

U.S. EPA, 705 F.2d 506 (D.C. Cir. 1983) ..... 38, 40

outh Carolina ex rel. Tindall v. Block,

717 F.2d 874 (4th Cir. 1983),

cert. denied, 465 U.S. 1080 (1984) ........... 34

State of North Carolina v. Hudson,

665 F. Supp. 428 (E.D.N.C. 1987) ......... 1, 16

iX

State of North Carolina v. Hudson,

731 F. Supp. 1261 (E.D.N.C. 1990) ...... 1, 10, 50

Steamboaters v. FERC, 759 F.2d 1382

reh. denied, 777 F.2d 1384 (9th Cir. 1985) ...... 27

wnshi iW Ww

Public Service Electric & Gas Co..

ee ee eee 43

See ue Bee es Gy TT ch hace ec cece ee 34

Webb v. Gorsuch, 699 F.2d 157 (4th Cir. 1983) . 49, 54

STATUTES

Ee De a 5) oil os eee ces 1

I OS neh cs cae ene 3

SOE OE cn oc v ek eke en eS 3

URE OU. 5. iis ees ete 12

EM ah ons ee 12

OE BE Fisk oie ce oe 2, 42

1 USS. OO Ook... ok 5 oo ok ce ccs 3

P.L. 100-589, 102 Stat. 2984 (1988) .... 2, 8, 47, 51

P.L. 101-640, 104 Stat. 4604 (1990) ...... 8, 48, 51

x

FEDERAL REGUALATIONS

UR ik on ck cee 2, 37

ee oo i eens aces 2, 36

i ei veri in jeep hae 2, 36

ie ee es a eee 2, 36

a Pee ee a wee ee passim

xi

OPINIONS DELIVERED IN THIS CASE

BY THE LOWER COURTS

The United States District Court for the Eastern

District of North Carolina has delivered two opinions in this

case, which can be found at 665 F. Supp. 428 and 731 F.

Supp. 1261. The United States Court of Appeals for the

Fourth Circuit delivered an opinion, which can be found at

940 F.2d 58. Each is reprinted in the Appendix.

GROUNDS UPON WHICH

THE JURISDICTION OF THIS COURT IS INVOKED

The judgment of the Court of Appeals was entered on

July 3, 1991. Timely petitions for rehearing with

suggestions for rehearing en banc were denied on August 20,

1991. This petition for a writ of certiorari is timely filed

within ninety days of this latter date. The jurisdiction of this

Court is invoked under 28 U.S.C. § 1254(1).

STATUTES AND REGULATIONS

INVOLVED IN THIS CASE

42 U.S.C. § 4332

P.L. 100-589, 102 Stat. 2984 (1988) [§ 5 only]

33 C.F.R. § 325.3

40 C.F.R. § 1500.1

40 C.F.R. § 1506.6

40 C.F.R. § 1507.1

40 C.F.R. § 1508.3

40 C.F.R. § 1508.7

40 C.F.R. § 1508.27

Each is reprinted in the Appendix.

STATEMENT OF THE CASE

I. Background

This dispute concerns a proposal by the City of

Virginia Beach, Virginia ("Virginia Beach") to construct a

85-mile long water supply pipeline that would enable

Virginia Beach to withdraw up to 60 million gallons per day

2

(mgd) of water from Lake Gaston, which straddles the

boundary between Virginia and North Carolina. The State

of North Carolina and the Roanoke River Basin Association

have challenged the Corps’ decision to permit this proposed

pipeline on several grounds, principally that no EIS was

prepared as required by the National Environmental Policy

Act ("NEPA"), 42 U.S.C. §§ 4321 et seg. The jurisdiction

of the District Court was invoked pursuant to 28 U.S.C.

§ 1331 (federal question) and 28 U.S.C. § 1361

(mandamus).

A. The Roanoke River System

Lake Gaston is part of the Roanoke River system that

drains approximately 9,600 square miles of North Carolina

and Virginia. The river rises in southwestern Virginia, flows

generally in a southeasterly direction to northeast North

Carolina, and eventually empties into Albemarle Sound on

the Atlantic. Several tributaries of the Roanoke pass through

south central Virginia and north central North Carolina.

3

ee

There are six major dams on the Roanoke River

system, three of which are in the general vicinity of the

North Carolina-Virginia border. Proceeding downstream,

these are the John H. Kerr Reservoir, Lake Gaston and

Roanoke Rapids Lake. Kerr Reservoir is by far the largest

of the three and is operated by the Corps of Engineers for

flood control, hydropower and low-flow regulation. Lake

Gaston and Roanoke Rapids Lake are owned and operated by

Virginia Electric & Power Company (VEPCO) as peaking

hydropower facilities. The three other dams -- Philpott,

Smith Mountain and Leesville -- are upstream of Kerr. JA

49 1a.!

The Wilmington (N.C.) District of the Corps operates

Kerr Dam and Reservoir according to a "Rule Curve,” which

is a plan for seasonal reservoir level fluctuations designed to

provide the greatest overall benefit to all competing interests.

| "JA" refers to the Joint Appendix filed with the Fourth Circuit.

4

JA 493a. The Corps attempts to balance the two principal

project purposes (i.e., flood control and power production),

as well as other purposes (e.g., downstream flow

augmentation and recreation). JA 1483a. The parties agree

that there is already insufficient water in Kerr Reservoir

during dry periods to satisfy these competing interests. Brief

of federal defendants and City of Virginia Beach filed with

the Court of Appeals ("Br.") at 41; see also JA 539a, 1837a;

Stip. 18.?

VEPCO operates its Gaston and Roanoke Rapids

projects in accordance with a license from the Federal

Energy Regulatory Commission (FERC), which requires

minimum releases for the protection of water quality and

aquatic life. JA 45la-470a. ‘rhose mandated minimum

releases from Roanoke Rapids range from 1,000 cubic feet

. "Stip.” refers to the joint stipulations submitted by the parties to

the Supplemental Administrative Record. These stipulations are on file

with the Eastern District of North Carolina.

5

ee

per second (cfs) during the winter to 2,000 cfs from mid-

spring through September. The FERC license also requires

VEPCO, in accordance with an agreement between the

Wilmington District of the Corps, the North Carolina

Wildlife Resources Commission and VEPCO, to release

augmented flows each spring during the time of spawning by

Striped bass downstream of Roanoke Rapids if adequate

storage for that purpose is available at Kerr. When water is

available between March 1 and April 15, the Corps raises the

water level in Kerr Reservoir to 302 feet (above mean sea

level) to accumulate sufficient water to allow flow

augmentation for striped bass spawning activity below

Roanoke Rapids during the spring. JA 397a.

Most of the water in Lake Gaston and Roanoke

Rapids Reservoir comes from Kerr because 92.6% of the

flow at Roanoke Rapids Dam is attributable to inflows above

Kerr Dam. JA 699a; see also JA 841a-858a. Consequently,

the releases made at Roanoke Rapids Dam are almost entirely

dependent on what Kerr makes available.

B. Albemarle-Roanok i

The Albemarle-Roanoke striped bass population,

which is a part of the anadromous Atlantic stock, differs

from almost all other striped bass populations in that it

travels a great distance upstream to spawn. This is because,

unlike other river systems, there are no tidal currents in the

lower reaches of the Roanoke River to support the semi-

buoyant eggs. Spawning Roanoke River striped bass must

depend on adequate river flows to keep the eggs from settling

to the bottom and dying. JA 1440a.

Spawning occurs each spring in the rapids below

Roanoke Rapids Dam about 130 miles from the mouth of the

river. Under good conditions, the eggs are carried

downstream and hatch before reaching Albemarle Sound at

a location where adequate food (zooplankton) is available for

the larvae. SR 11.01.°

The Albemarle-Roanoke stock has experienced a

dramatic decline during the last two decades. SR 11.22,

11.24. Congress concluded in 1988 that this particular

population "may soon reach a level from which recovery will

be exceptionally difficult." P.L. 100-589, §5(a)(2), 102

Stat. 2984. The cause of the decline is complex,

multifaceted and not fully understood. Id. Accordingly,

Congress commissioned the United States Fish and Wildlife

Service to conduct a report on the causes of the decline of

the striped bass stock. Jd. Subsequently, Congress ordered

the Corps to reevaluate the impacts of the proposed project

in light of that report. See P.L. 101-640, §413, 104 Stat.

4604, 4651 (1990).

> "SR" refers to exhibits within the Supplemental Administrative

Record, which is on file with the Eastern District of North Carolina.

8

From 1971 through 1988, the amount of water which

the Corps made available for striped bass spawning was

governed by a 1971 Memorandum of Understanding between

the Corps, VEPCO and the North Carolina Wildlife

Resources Commission. JA 443a-450a. To the extent water

was available, the Corps would make releases from Kerr

Reservoir sufficient to provide a flow of 6,000 cfs

downstream of the Roanoke Rapids Dam during the period

in which bass were expected to spawn -- the 51 days from

April 27 to June 15. JA 451la-470a. However, there was

often insufficient water for this purpose. JA 539a.

There had been "concern among several agencies for

some time that the existing flow regime during the spawning

season has contributed to or even caused the collapse of the

Roanoke-Albemarle stock since the late 1970s." JA 1830a.

Indeed, as early as 1980, the National Marine Fisheries

Service (NMFS) "advised the Corps that current water flow

releases on the Roanoke River were adversely impacting the

9

anadromous striped bass resource” and that "[t]he present

flow regime is inadequate to protect striped bass." JA

1376a-1377a. NMEFS has repeatedly affirmed this position.

Id.

The Roanoke River Water Flow Committee, which

includes striped bass experts from federal and_ state

agencies,* concluded that a substantially longer period of

augmented flows is necessary to preserve striped dass. The

Committee recommended that a new, longer flow regime be

adopted "to control the flow of the Roanoke River between

* Both the District Court and the Fourth Circuit made unwarranted,

disparaging assertions about the Flow Committee. See 940 F.2d at 62

n.3, 65, infra at 13a-14a n.3, 24a-25a; 731 F. Supp. at 1269, infra at

56a-59a. It is simply not true that petitioners formed the Committee, or

that the Corps did not assist the Committee in its work. In fact, the

Wilmington District of the Corps was an active participant in the

Committee’s work and contributed to its report. See JA 1422a-1424a,

1426a, 1429a, 1920a; Stip. 07. Furthermore, the Committee was formed

under the aegis of the National Marine Fisheries Service. li is an

independent organization with specific expertise in the issues involved in

this case. The contrary assertions by the lower courts are mistakenly

based on a complaint by the Norfolk District of the Corps, which has no

responsibility for flows in the Roanoke River, that it was not made a

member. See JA 1418a-1419a.

10

March 1 to June 30 [122 days] of each year." JA 1422a.°

Under this recommendation, target flows would range from

8,500 cfs in March to 5,300 cfs at the end of June.

Minimum flows would decrease from 7,543 cfs in March to

3,058 cfs at the end of June. However, the Corps and

VEPCO could not provide sufficient water to meet those

standards. JA 1423a. Therefore, all parties agreed to a

compromise flow regime "curtailed both in time (April 1 to

June 15), and in magnitude of low and high flows." Id.

The final version of the compromise flow regime was

proposed to the Committee by the Wilmington District in

September, 1988. JA 1915a-1930a. The Committee noted

that it "remains concerned that [this compromise] flow

regime does not adequately address low flow augmentation

for striped bass during dry years . .. ." JA 1429a.

* The Committee found that both very high flows and very low

flows were detrimental to striped bass. Therefore, it proposed “target”

flows, and maximum and minimum acceptable flows. Because a 60 mgd

withdrawal would have a negative impact during low flow conditions, it

is only those conditions that are discussed here.

1]

Nevertheless, because the compromise flow regime was so

markedly superior to the prior practice, every agency that

made comments to the Committee agreed that the

compromise regime should be implemented. JA 1423a.

The Corps and VEPCO were able to maintain flows

set by the compromise flow regime for a large portion of the

curtailed 1988 spawning period. Preliminary (JA 1423a) and

final results from the 1988 spawning season indicated the

highest abundance of juvenile bass since 1976, a fact the

agencies attributed to the improved flow regime. JA 1368a,

1687a, 1794a.

Il. Nature Of nd Prior Pr in

On July 15, 1983, Virginia Beach applied for a Corps

permit under 33 U.S.C. §§ 403 and 1344 for the

construction of its proposed pipeline. The proposed 60 mgd

withdrawn from Lake Gaston would be used by the cities of

Virginia Beach (48 mgd), Chesapeake (10 mgd), and

12

Franklin (1 mgd) and Isle of Wight County (1 mgd). The

pipeline would originate at Pea Hill Creek, about 400 yards

north of the Virginia-North Carolina state line, and terminate

85 miles east at water lines owned by the City of Norfolk,

Virginia.

Following several public hearings, the Norfolk

District published a proposed Final Environmental

Assessment (EA) and a proposed Finding of No Significant

Impact (FONSI) on December 7, 1983. On January 9,

1984, the Corps affirmed its FONSI, published a Statement

of Findings (SOF), and issued the permit to Virginia Beach.

In those documents, the Corps concluded that the project

would not have a significant effect on the environment, that

the permit could be issued without preparation of an EIS,

and that the project was in the public interest.

Virginia Beach also sought a contract with the

Wilmington District to purchase 10,200 acre/feet of storage

in Kerr Reservoir. JA 359a-38la. The purpose of the

13

—" |

contract has alternately been described as 1) providing

Virginia Beach with water to release downstream if its 60

mgd withdrawal caused the water level in the Roanoke River

to fall below minimum permissible levels (WR 1, 42),° and

2) providing water to compensate for flows taken from

striped bass during spawning season. JA 1810a, 1819a.

The Wilmington District adopted the EA of the Norfolk

District and issued its FONSI on January 13, 1984. The

contract was approved by the Corps on January 30, 1984.

JA 359a-38 la.

On January 12, 1984, the State of North Carolina

filed this action against the Corps of Engineers in the Eastern

District of North Carolina. The Roanoke River Basin

Association and twelve counties in North Carolina and

Virginia intervened as plaintiffs on June 20, 1984. Virginia

° "WR" refers to exhibits to the Wilmington District Administrative

Record. These exhibits are on file with the Eastern District of North

Carolina.

14

Beach was permitted to intervene as a defendant on

December 3, 1985.’

The amended complaints challenged the Corps’

issuance of the pipeline permit and the water supply

allocation contract. Plaintiffs alleged that the Corps

improperly refused to prepare an EIS prior to issuing the

permit and entering the contract, and failed to conduct a

proper public interest review. On cross-motions for

summary judgment, the District Court considered the

certified administrative record as supplemented by the

parties, and issued an opinion on July 7, 1987. Although the

court affirmed the decision of the Corps in several respects,

” The day the permit was issued (three days before North Carolina

sued the Corps), Virginia Beach filed a declaratory judgment suit in the

Eastern District of Virginia against the Roanoke River Basin Association,

several of its directors and officers, and the Governor of North Carolina,

seeking an order declaring that the permit issued for its pipeline project

was lawful and valid. On the Governor's appeal of an interlocutory

order regarding personal jurisdiction, the Fourth Circuit ruled that the

Virginia Beach action must be dismissed or transferred to the Eastern

District of North Carolina. City of Virginia Beach v. Roanoke River

Basin Association, 776 F.2d 484, 489 (4th Cir. 1985). That action was

trausferred on November 14, 1985, and then dismissed as duplicative on

December 17, 1985.

15

———

- women ae ee

PP a

it found that the Corps arbitrarily analyzed the potential

environmental effects of the project on striped bass, and also

arbitrarily conducted its public interest review regarding the

extent of Virginia Beach’s need for water. The court

directed the Corps to:

l. As a part of its NEPA review make an

independent assessment of the effects of the

proposed project on striped bass to determine

whether the preparation of an EIS is required

or whether any mitigative measures are

necessary; and, ;

& As a part of its public interest review make a

determination of the extent of Virginia

Beach’s water needs.

665 F. Supp. at 450, infra at 152a. The District Court

retained jurisdiction to review the Corps’ further analysis.

On June 6, 1988, the Norfolk District distributed for

comment a draft Supplement{al] Environmental Assessment

(SEA) and a Revised Finding of No Significant Impact

(RFONSI), which again concluded that the proposed project

would not have a significant impact on striped bass and that

16

an EIS was not required. JA 1065a-108la. On July 7,

1988, the Wilmington District adopted the striped bass

portions of the Norfolk draft SEA and published its own

draft RFONSI. JA 1093a-1096a.

In making its decisions, the Corps relied heavily upon

computer modeling done by its Wilmington District. See JA

1805a-1848a. The Corps did not disclose at least two

important documents containing critical staff analyses of this

modeling until after its final decision. JA 1675a, 1857a.

The first document was an October 5, 1988 memorandum

which the Corps has contended provided a complete

analytical defense to plaintiffs’ criticisms of the Corps’

mode’ JA 1675a. That memorandum contained substantial

new information never previously available to the public.

This included discussion of a "preliminary determination"

that overall the compromise flow regime would be more

easily maintained than the prior regime. The second

document was the "preliminary determination" itself, which

17

ae

was initially prepared by the Corps’ Wilmington District in

1988, but never made publicly available or referred to in the

SEA or any documents circulated for comment. JA 1857a.

These were two principal documents on which the SSOF and

RFONSIs were based. JA 1836a, 1837a. The State of

North Carolina, the Roanoke River Basin Association, and

the rest of the interested public never had the opportunity to

comment on this vital information.

Despite being deprived of crucial information, state

and federal agencies with striped bass expertise, independent

fisheries biologists, the parties and others submitted

extensive, critical comments.* Each of the resource

agencies advised the Corps that the probable impact on

striped bass would be significant and that an EIS should be

. See JA 1375a-1390a, 1393a-1406a, 1413a-1416a, 1433a-1446a,

1459a-1468a, 1477a-1528a, 1421a-143la, 1615a-1620a, 1645a-1646a,

1647a-1648a, 1675a-1680a, 1915a-1919a; SR 115, 117.

18

prepared. For example, the U.S. Fish and Wildlife Service

(USFWS) stated:

"In view of the significance of the impacts identified

regarding the proposed activities, i.e., reallocation of

the water supply in Kerr Reservoir and withdrawal of

60 mgd from the Roanoke system, the Service

believes that the preparation of an Environmental

Impact Statement is appropriate.” JA 1462a.

The National Marine Fisheries Service (NMFS) wrote:

"Considering these recommended changes in water

flow management, the City of Virginia Beach’s

project is a high risk proposal. It should not be

permitted without a full scale Environmental Impact

Statement, examining its effects on striped bass under

the enhanced augmented flow regime in light of all

other factors affecting the system.” JA 1386a.

The North Carolina Wildlife Resources Commission said:

"We believe removal of 60 mgd is likely to cause

severe damage to striped bass in the Roanoke River.

The Corps’ tentative conclusions to the contrary are

not scientifically supportable.” JA 1416a.

The North Carolina Division of Marine Fisheries advised:

"The Division of Marine Fisheries (DMF) strongly

objects to withdrawal of 60 million gallons per day

("mgd") of water from Lake Gaston for Virginia

Beach’s use. A full Environmental Impact Statement

(EIS) is essential and necessary to fully and

19

adequately address numerous impacts of any

withdrawal from the basin on down stream uses, in

particular year round maintenance of the striped bass

population... .

"The preparation of an Environmental Impact

Statement (EIS) is absolutely necessary to properly

address the existing, proposed, and cumulative

impacts of water withdrawal on striped bass life

history in the Roanoke River.” JA 1363a-1364a.

The agencies with striped bass expertise concluded

that an EIS was necessary because river flow is a crucial

factor affecting the Albemarle-Roanoke stock, and that even

under current conditions insufficient water is available. The

NMFS

"conclude[d] that enhanced river flow is extremely

important to the survival of the striped bass

population in the Roanoke River.” JA 1375a.

The USFWS concluded

"that flows may be more significant in determining

reproductive success than other factors.” JA 1462a.

The North Carolina Wildlife Resources Commission noted

that

20

"adequate river flow is essential to the survival of

striped bass. We believe removal of 60 mgd is likely

to cause severe damage to striped bass in the Roanoke

River.” JA 1416a.

The North Carolina Division of Marine Fisheries concluded

that

"the primary problem with the striped bass population

is Roanoke River flow (due to the operation of the

dams) and the resulting water quality is causing high

mortalities in the larval population... .

"Division of Marine Fisheries scientists are concerned

that increasing the frequency and duration of

minimum flow would not only impact the actual act

of spawning, but also affect overall reproduction and

recruitment." JA 1365a-1366a.

The Roanoke River Flow Committee, which consists of

representatives of these agencies and university fisheries

biologists (JA 1920a), advised the Corps that

"river flow has a major impact upon the success of

the striped bass in spawning and on subsequent life

history stages... .

"The Committee concludes that the quantity of water

passing through the Roanoke River system between

March and June of each year has a significant effect

on striped bass and other natural resources

downstream.” JA 1422a, 1424a. :

21

< owed AS

In sum, all commenting agencies with expertise in

fisheries found that river flow was crucial to Albemarle-

Roanoke striped bass (JA 1375a-1390a, 1413a-1416a, 1433a-

1446a, 1459a-1468a); that additional water was needed for

bass survival (JA 1375a-1390a, 1413a-1416a, 1433a-1446a,

1459a-1468a); that when water was released in accordance

with the compromise flow regime, striped bass showed

substantial improvement (JA 1375a-1390a, 1413a-1416a,

1433a-1446a, 1459a-1468a); and that an EIS must be

prepared before the Corps permitted the 60 mgd withdrawal

(JA 1375a-1390a, 1413a-1416a, 1433a-1446a, 1459a-1468a).

Despite these strong, uniformly critical comments, the

Norfolk District on December 21, 1988 issued a final SEA

(JA 1805a-1828a) identical to the draft SEA it had circulated

for comment in June, a final RFONSI (JA 1847a-1848a), and

a Supplemental Statement of Findings (SSOF) (JA 1828a-

1846a). On December 23, 1988, the Wilmington District

adopted the Norfolk SEA and issued its own RFONSI. JA

22

1851a-1854a. In January 1989, each district issued revised

documents, acknowledging errors in the earlier documents,

but changing no conclusions. JA 1849a-1850a, 1855a-1856a.

Despite the fact that the Corps’ findings were so

strongly questioned by the expert resource agencies, the

District Court ruled on February 2, 1990 that the Corps was

not required by NEPA to prepare an EIS prior to allowing

the 60 mgd water withdrawal, and that the Corps’ public

interest review had not been conducted in an arbitrary

manner. North Carolina’s motion for reconsideration was

denied on March 1, 1990. Notices of appeal to the Court of

Appeals followed on April 2 and 3, 1990.

The Court of Appeals affirmed the District Court’s

holding that the Corps could refuse to prepare an EIS. The

Court of Appeals summarily rejected each of petitioners’

arguments, stating that because the Corps considered each of

the issues raised by petitioners, "no more is required." 940

F.2d at 64, infra at 20a. After receiving petitioners’ Petition

23

pk ete Le

Renin ons

for Rehearing and Suggestion for Rehearing En Banc and

requiring respondents to submit a reply, the Court of Appeals

denied reconsideration on August 20, 1991.

REASONS FOR GRANTING THE WRIT

The Court of Appeals decision is in conflict with a

principle established by this Court that an agency must make

critical information on which it relies available to the public

before it reaches a final decision. It is also contrary to

decisions of other courts of appeals regarding the obligation

of an agency to explain its computer modeling once

substantial questions as to its validity have been raised.

The opinion below is in error, and in conflict with

decisions of other courts of appeals, regarding application of

NEPA. The opinion below demonstrates a mistaken view of

the purposes and requirements of the National Environmental

Policy Act -- a view that could frustrate congressional intent

in a wide range of future NEPA cases in the Fourth Circuit.

24

This case is important because of the stakes involved,

but it also demonstrates the continuing confusion and conflict

over when an EIS is required under NEPA, despite this

Court’s recent decisions involving that Act. Until this Court

provides further guidance on the questions presented in this

case, federal agencies will continue to confront inconsistent

judicial interpretations of NEPA’s language in deciding

issues Of substantial national interest involving policies and

programs intended to be implemented nationwide.

The Fourth Circuit has interpreted quite differently

than other courts of appeals NEPA’s test for determining

when a proposed action "significantly affect[s] the human

environment." Its decision regarding the circumstances in

which a mitigation condition will eliminate an otherwise

potentially significant impact is also directly contrary to

decisions of other courts of appeals. There is also conflict

between the Fourth Circuit and other courts of appeals over

the meaning and effect of the Council on Environmental

25

i a |

Quality’s implementing NEPA regulations as they apply to

impacts that are likely to be controversial, uncertain and

cumulative.

I. The Opinion Below Is In Error And In

Conflict With Decisions Of The Ninth

Circuit Regarding The Need To Explain

Specifically How Mitigation Will Eliminate

Potentially Significant Environmental

Impacts.

The Court of Appeals concluded that the Corps had

not acted arbitrarily or unlawfully in declining to prepare an

EIS because of the mitigation condition imposed by the

Corps. The Court of Appeals reached this conclusion even

though the Corps did not make its mitigation condition

available for public comment and never explained specifically

how the condition would mitigate the impact of the project.

The opinion below is in conflict with the holding of the

Ninth Circuit that when an agency intends to rely on

mitigation to justify a finding of no significant impact, it

"must explain exactly how the measures will mitigate the

26

project’s impact.” LaFlamme v, FERC, 852 F.2d 389, 399-

400 (1988); see also Jones v. Gordon, 792 F.2d 821, 829

(9th Cir. 1986); fin. or. 759 F.2d 1382,

1393, reh. denied, 777 F.2d 1384 (9th Cir. 1985)("FERC

fails to explain specifically how the conditions would

mitigate the impact of the project").°

The parties agreed below that "[t]he effectiveness of

the mitigation condition is the single most important issue in

this case." Br. at 14; petitioners’ reply brief at 3. The

Corps contended, and the Court of Appeals concurred, that

the mitigation condition "completely compensat[es]" for the

City’s 60 mgd withdrawal. JA 1838a; see 940 F.2d at 63-

64, infra at 15a-20a. Yet, the respondents conceded below

% The discussion of mitigation in Robertson v. Methow Valley

Citizens Council, 490 U.S. 332 (1989) was in the context of a challenge

to the adequacy of an EIS, as opposed to a decision -- as here -- not to

prepare an EIS on the grounds that a mitigation condition eliminates a

project's adverse environmental impacts. Nevertheless, the requirement

is the same in both situations “that mitigation be discussed in sufficient

detail to ensure that environmental consequences have been fairly

evaluated... .” Id. at 352.

27

—_ Sa Dee

that the City lacked storage sufficient to provide releases

during striped bass spawning periods "by an amount equal to

the planned withdrawal.” Br. at 19 n.11. The conclusion

that the mitigation condition completely compensates for the

withdrawals, then, is plainly wrong.

The Corps never described any mitigation plan in

either its draft or final documents. Indeed, as the NMFS and

USFWS advised the Corps after the final decision was made:

"NMFS has seen brief reference to mitigation

in two documents, the [SSOF] and the

[Norfolk FONSI]. No details were given, and

NMFS could not evaluate the effectiveness of

mitigation." JA 139a.

"[FWS] could not have directed specific

comments toward mitigation because the FWS

was never provided a specific description of

the mitigation plan by the Corps of

Engineers." JA 145a.

In short, neither the parties nor the striped bass

experts had an opportunity to comment on what the Corps

later described as its "most important finding.” JA 1850a.

28

Yet, remarkably, the RFONSI found that the USFWS and

NMFS have

"never taken issue with the Wilmington

District’s model and there is no reason to

assume that they would find the model results

regarding the effectiveness of the flow

mitigation permit condition to be

controversial.” JA 1849a-1850a.

After the Corps had issued the permit and announced

its mitigation condition, NMFS commented:

"The offer by the City of Virginia Beach to

use its storage is not considered a complete

mitigation plan." JA 140a.

"Lacking a full analysis, we do not consider

this offer to be a mitigation plan.” JA 14la.

At no point has the Corps demonstrated specifically

how the City’s storage would be utilized to eliminate the

project’s impacts. The mitigation condition simply states a

conclusion that the Virginia Beach storage must be used "to

not cause the loss of any augmented spawning flow days

which would otherwise be caused by the City’s withdrawal.”

JA 1838a. Nowhere in the record is there any detailed

29

explanation of the manner in which that result will be

accomplished or whether the City actually has sufficient

storage to assure that result. In fact, the Corps has

elsewhere indicated that such flows will not occur.

According to the Corps, "Virginia Beach will not be

withdrawing water from its storage in Kerr Reservoir during

February through June.” JA 1679a. The Corps also advised

that "[aJt no time will water be released from Kerr

exclusively for withdrawal by the City” (JA 336a) and “that

no water is to be released from Kerr for benefit of Virginia

Beach during droughts. . . . until Kerr Reservoir is at the

bottom of the power pool (presently at 293 m.s.1.).” (Stip.

30; see also JA 1755a-1757a).

In light of the vagueness of the mitigation condition

and the continuing uncertainty about the ability of the City

to provide sufficient storage to meet that condition, it was

error to hold that the "mitigation condition is adequate to

address any possible environmental effects of the pipeline.”

940 F.2d at 63, infra at 15a.'°

Il. The Opinion Below Is In Error And In

Conflict With The Rule Adopted By This

Court That Critical Information On Which

The Agency Relies Must Be Made Available

For Review And Comment Before The

Agency Makes Its Decision.

Closely related to the issue of whether the Corps must

explicate specifically how its mitigation condition will

eliminate an otherwise potentially significant environmental

impact is the issue of whether the Corps was obligated to

10 One indication of the failure of the Court of Appeals to conduct

a searching investigation of the record is its conclusion that commentors

never raised the issue that reductions in flow on already iost days are of

concern. 940 F.2d at 63-64, infra at 18a. This ignores the comment of

the North Carolina Division of Marine Fisheries that:

[e]ven if conditions during a particular year were such that no

days of spawning flows were entirely lost, flows would

nevertheless be reduced throughout the spawning period. There

is already insufficient water in the system to provide reasonable

spawning conditions, and given the fragile condition of the bass

populatio., any loss of water could have an extremely

significant impact.

JA 83la; see also JA 222a, 226a.

31

make available two critical documents on which the Corps

ultimately relied to justify its model and modeling

assumptions. Indeed, the Corps relied on the absence of

comment on "modeling results regarding the effectiveness of

the flow mitigation permit condition” as proof that the issue

was not controversial. JA 1849a-1850a.

As noted above, the Corps shielded crucial modeling

information until after it published its final decision. The

Corps did not disclose at least two important documents

containing critical staff analyses. JA 1675a, 1857a. The

first document was a October 5, 1988 memorandum which

the Corps has alleged provided an analytical defense to

plaintiffs’ criticisms of the Corps’ model. JA 1675a. That

memorandum contained substantial new information never

previously available to the public, including discussion of a

"preliminary determination” that overall the compromise flow

regime would be more easily maintained than the old. The

second document was the "preliminary determination” itself,

32

which was initially prepared by the Corps’ Wilmington

District in 1988, but never made publicly available or

referred to in the SEA or any documents circulated for

comment. JA 1857a. Because the Corps refused to disclose

these documents, the public never had the opportunity to

comment on this vital information.

The Court of Appeals did not dispute that-the Corps

failed to disclose vital information. Rather, it summarily

dismissed petitioners’ argument by asserting that petitioners

did not explain how they were harmed by this shielding of

vital information, and that the court was "satisfied that the

[petitioners] were not prejudiced by any slowness or

incompleteness in the Corps’ disclosure of modeling

information.” 940 F.2d at 65, infra at 25a. This hoiding

squarely conflicts with decisions of this Court, the express

provisions of NEPA and tke binding Council on

Environmental Quality (CEQ) regulations.

33

07m Be teh dite. ar,

ant Os od 2h Sane rd

Pe ee ee ee

This Court has held that the shielding of information

from public review is alone sufficient to invalidate agency

action. Bowman Transportation, Inc, v. Arkansas-Best

Freight System, Inc., 419 U.S. 281, 288 n.4 (1974)." In

a recent case, this Court held that the principle established in

Bowman Transportation did not apply to an action brought

under the Employee Retirement Income Security Act of 1974

("ERISA"). Pension Benefit Guaranty Corp. v. LTV Corp.,

i110 S. Ct. 2668, 2679-81 (1990). The holding in Pension

Benefit was based on the fact that neither ERISA nor the

Administrative Procedure Act specifically provided the public

11 This principle has been implemented by several other federal

courts, including previous panels of the Fourth Circuit. See, e.g., North

Carolina Environmental Policy Institute v. EPA, 881 F.2d 1250, 1258

(4th Cir. 1989); McLouth Steel Prod. Corp. v. Thomas, 838 F.2d 1317,

1323-24 (D.C. Cir. 1988); South Carolina ex rel. Tindall v. Block, 717

F.2d 874, 885 (4th Cir. 1983), cert. denied, 465 U.S. 1080 (1984);

Sierra Club v. Costle, 657 F.2d 298, 333 (D.C. Cir. 1981); U.S. Lines,

Inc. v. Federal Maritime Comm’n, 584 F.2d 519, 540 (D.C. Cir. 1978);

Ely v. Velde, 451 F.2d 1130, 1138-39 (4th Cir. 1971); National Wildlife

Federation v. Marsh, 568 F. Supp. 985, 993-94 (D.D.C. 1983).

34

the procedural right to access to all relevant information. Id.

at 2680.

By contrast, one of the fundamental purposes of

NEPA is to ensure that the public is fully apprised of the

potential environmental effects of major federal actions

before they are finalized. As this Court has stated:

NEPA promotes its sweeping commitment to

"prevent or eliminate damage to the

environment and biosphere” by focusing

Government and public attention on the

environmental effects of proposed agency

action. 42 USC § 4321. By so focusing

agency attention, NEPA ensures that the

agency will not act on_ incomplete

information, only to regret its decision after it

is too late to correct. . . . Similarly, the

broad dissemination of information mandated

eng oe ep RE ee

ee epfiel thaen.

Marsh v, Oregon Natural Resources Council, 490 U.S. 360,

371 (1989) (citations omitted, emphasis added). !?

'2 See also Sierra Club v. Morton, 510 F.2d 813, 820 (Sth Cir.

1975) (NEPA “serves as an environmental full disclosure law”) (quoting

Silva v. Lynn, 482 F.2d 1282, 1284-85 (ist Cir. 1973)).

35

Ta at pastel ct | Mi Lal

The CEQ regulations which implement NEPA

similarly provide:

NEPA procedures must insure _ that

environmental information is available to

public officials and citizens before decisions

are made and before actions are taken. .. .

Accurate scientific analysis, expert agency

comments, and public scrutiny are essential to

implementing NEPA.

™~ ~ Sad

Agencies shall . . . [p]rovide .. . the

availability of environmental documents so as

to inform those persons and agencies who

may be interested or affected.

40 C.F.R. §§ 1500.1(b) & 1506.6(b). These CEQ

regulations are binding on all federal agencies and must be

given substantial deference by reviewing courts. Robertson

v. Methow Valley Citizens Council, 490 U.S. 332, 352-55

(1989); see also 40 C.F.R. § 1507.1. Finally, the Corps’

own regulations state:

The [public] notice should include . . . [aJny

. available information which may assist

interested parties in evaluating the likely

36

impact of the proposed activity . . . on factors

affecting the public interest.

33 C.F.R. § 325.3(a)(13).

By holding that the Corps’ failure to disclose

information was of no consequence, the Court of Appeals

ignored the clear language of these binding regulations and

this Court’s opinion in Oregon Natural Resources. This

Court should grant the writ to decide that, in light of the

express disclosure requirements provided by NEPA and the

binding CEQ regulations, the holding in Pension Benefit does

not apply to NEPA cases.'°

'3 In another NEPA case, the District Court for the District of

Columbia invalidated a Corps permit for failure to disclose a document

on which it relied. National Wildlife Federation v. Marsh, 568 F. Supp.

985, 991-98 (1983); see also Grazing Fields Farm v. Goldschmidt, 626

F.2d 1068, 1072-74 (1st Cir. 1980) (holding that an EIS was inadequate

because information was not made available for public review and

comment).

37

ite thts th Me draak i,

%

5

4

2

4

%

7

5

‘

i

Ill. The Opinion Below Is In Error And In

Conflict With Decisions Of The District Of

Columbia Circuit Requiring Agencies to

Provide A Complete Analytical Defense Of

Modeling Which Has Been Challenged, _

The opinion below conflicts with decisions of the

Court of Appeals for the District of Columbia Circuit which

establish that an agency may rely on a model oniy if the

agency provides a complete analytical defense of the model

and its assumptions. '*

Surprisingly, the opinion below also departs without

explanation from the prior view of the Court of Appeals that

a federal agency obligated to take into account

the values . . . NEPA seek{s] to safeguard,

may not evade that obligation by keeping its

thought processes under wraps. ... To

enable a court to ascertain whether there has

been a genuine, not a perfunctory compliance

is Natural Resources Defense Council, Inc. v. Herrington, 768

F.2d 1355, 1420-22 (D.C. Cir. 1985); Eagle-Picher Industries v. U.S.

EPA, 759 F.2d 905, 921-22 (D.C. Cir. 1985); Small Refiner Lead

Phase-Down Task Force v. U.S. EPA, 705 F.2d 506, 535 (D.C. Cir.

1983); Sierra Club v. Costle, 657 F.2d 298, 332-33 (D.C. Cir. 1981);

Alabama Power Co. v. Costle, 636 F.2d 323, 387-88 (D.C. Cir. 1979);

American Public Gas Ass’n v. Federal Power Comm'n, 567 F.2d 1016,

1039 (D.C. Cir. 1977), cert. denied, 435 U.S. 907 (1978).

38

with NEPA, the [agency] will be required to

explicate fully its course of inquiry, its

analysis, and its reasoning.

Ely v. Velde, 451 F.2d 1130, 1138-39 (4th Cir. 1971).

The Corps simply has not met its burden of

completely defending its model, even though the lengthy

model itself was made a part of the record. JA 1934a-

196la. The Corps has conceded that the model is not self-

explanatory. JA 623a. Although some modeling

assumptions are evident in the model coce and others are

explained in documents never made available to the public

before the final decision (JA 1675a, 1857a), several critical

assumptions have never been explained. For example, the

Corps has never explained how it incorporated the Virginia

Beach water supply on in its modeling or how the use of

that storage was modeled.

The Court of Appeals concluded that the petitioners

were not prejudiced by the failure of the Corps to provide a

complete defense of its computer model. The opinion says

39

mtn ede DS anthem a ales i all 4

Soe TiN nal sctetind Aik

that the petitioners "have not explained what use they expect

to make of [this information]." 940 F.2d at 65, infra at 24a.

Requiring petitioners to demonstrate precisely how

undisclosed information would have been used is unjustified

as a matter of law and fact, and is in conflict with the

decisions of other courts of appeals.

In Small Refiner Lead Phase-Down Task Force v.

U.S. EPA, 705 F.2d 506, 540-41 (D.C. Cir. 1983), for

example, the court held that where an agency provides no

opportunity to reply to its late evidence, such evidence

cannot be relied on by the agency to support its action

with he need for any showi laintiffs of prej

Here, however, petitioners have had no opportunity to

comment on some modeling assumptions because they were

identified only after the Corps revealed its decision and other

modeling assumptions because they have never been

disclosed at all.

40

The holding below that the petitioners were not

prejudiced is also clearly contrary to the record. First, as

noted above, certain critical information has never been

provided to the petitioners and the reviewing courts. How

can a party show what use it would make of information it

has never seen? Second, based on information obtained after

the Corps’ decision, the petitioners and two federal agencies

showed that the mitigation condition would not eliminate the

adverse environmental effects of the withdrawals.’ Their

failure to raise that point before the decision was reached was

the result of the Corps’ failure to explain its modeling and

mitigation condition fully, and to provide the public an

opportunity to comment. What greater or more obvious

showing of prejudice could be made?

'S The Court of Appeals clearly misconstrued the nature of the

controversy, which was never confined to the potential loss of a day of

augmented spawning flows, but rather went to the net reduction in water

for spawning flows where admittedly there are already inadequate flows.

JA 83 la.

41

a

IV. The Opinion Below Is In Error And In

Conflict With Decisions Of Other Courts of

Appeals Implementing The CEQ

Regulations Which Govern Whether An

EIS Must Be Prepared.

NEPA requires all federal agencies to prepare an EIS

for any "major Federal action significantly affecting the

quality of the human environment.” 42 U.S.C. § 4332.

"Significantly" as used in NEPA requires considerations of

both context and intensity. 40 C.F.R. § 1508.27. “Intensity”

is defined by regulation as the “severity of the impact.” 40

C.F.R. § 1508.27(b). In order to determine the severity of

the impact, the Corps was required to evaluate ten specific

factors listed in that regulation, three of which were

particularly relevant to this case:

(4) The degree to which the possible

effects on the quality of the human

environment are likely to be highly

controversial.

(5) The degree to which the possible

effects on the human environment are highly

uncertain or involve unique or unknown risks.

42

(7) | Whether the action is related to other

actions with individually insignificant but

cumulatively significant impacts. Significance

exists if it is reasonable to anticipate a

cumulatively significant impact on the

environment.

"Affecting" means will or may have an effect on. 40 C.F.R.

§ 1508.3. The Corps need not determine that the impact will

be significant. The courts of appeals have uniformly

determined that an agency must prepare an EIS if the impact

of an action may be significant. '®

Given the substantial expert opinion that the project

may adversely affect the environment, particularly the

already stressed striped bass stock, the Corps was required to

prepare an EIS in this case.

'© Louisiana ex rel. Guste v. Lee, 853 F.2d 1219, 1222-23 (Sth

Cir. 1988)(Wisdom, J.); Sierra Club v. U.S. Forest Service, 843 F.2d

1190, 1193 (9th Cir. 1988); Quinonez-Lopez_v. Coco Lagoon

Development Corp., 733 F.2d 1, 2 (ist Cir. 1984); Sierra Club v.

Peterson, 717 F.2d 1409, 1413-14 (D.C. Cir. 1983); Township of Lower

Alesees. Cunsk, x. Rollie Renton Seatie. 0, 85a 687 F.2d 732,

742 (3d Cir. 1982); Ming

498 F.2d 1314, 1320 (8th Cir. 1974); Hanly v. Kleindienst, 471 F.2d

823, 831 (2d Cir. 1972), cert. denied, 412 U.S. 908 (1973).

43

A. Controversy —-

40 C.F.R. § 1508.27(b)(4)

The binding CEQ regulations required the Corps to

consider the degree to which the possible effects on striped

bass are likely to be highly controversial. 40 C.F.R.

§1508.27(b)(4). The Court of Appeals’ decision concerning

the Corps’ finding that this case is not controversial should

be reviewed by this Court for at least three reasons.

First, the opinion below is in direct conflict with the

clear language of this regulation and with decisions of the

Court of Appeals for the Ninth Circuit. The Ninth Circuit

has interpreted this CEQ regulation to require an agency to

prepare an EIS where commenting public agencies and others

with expertise in the subject matter conclude that there may

be a significant impact on the environment.’’

7 See, ¢.g., LaFlamme v. FERC, 852 F.2d 389, 401 (9th Cir.

1988) (public comments about the effect the project would have on the

area necessitated an EIS); Sierra Club v. U.S. Forest Service, 843 F.2d

1190, 1193 (9th Cir. 1988) (EIS required where affidavits and testimony

of conservationists, biologists, and other experts were highly critical of

(continued...)

44

The Corps’ views have been strenuously criticized by

the expert agencies. As explained above, the U.S. Fish and

Wildlife Service (JA 1459a-1468a), the National Marine

Fisheries Service (JA 1375a-1389a), the North Carolina

Wildlife Resources Commission (JA 1413a-1416a), the North

Carolina Division of Marine Fisheries (JA 1363a-1374a), and

the Roanoke River Flow Committee (JA1421la-1431a)'*

provided many explicit and detailed reasons why, contrary to

the Corps’ view, the project may have significant

environmental impact.'? By allowing the Corps to

17(. continued)

the EAs); Jones v. Gordon, 792 F.2d 821, 828-29 (9th Cir. 1986)

(agency cannot avoid EIS by simply disputing public comments regarding

ea Agr tiger adhe 7th a PP eng

1172, 1182 (tb Cir. 1982) (EIS sodas ake sumer "received

numerous responses from conservationists, biologists, and other

knowledgeable individuals, all highly critical of the EA”).

- See also the comments of Professor Roger Rulifson of East

Carolina University (JA 1433a-1458a).

9 See n.15, supra at 41. In fact, the issue of what flows are

needed for striped bass in the Roanoke River has been controversial since

the first impoundment was built in the 1950s. JA 504a.

45

summarily dismiss these substantial expert views rather than

weibiiis an EIS to fully assess them, the opinion below

creates a clear conflict with prior decisions of the Ninth

Circuit.

Second, the opinion below is also in conflict with a

decision of the Ninth Circuit that the requirement to prepare

an EIS is not eliminated so long as substantial questions

remain regarding the effectiveness of the mitigation

condition. Conner v. Burford, 848 F.2d 1441, 1450 (1988),

cert, denied, 489 U.S. 1012 (1989). That there is a

substantial controversy over the effectiveness of the

mitigation is obvious. JA 114a-115a, 139a-42a. Contrary

to the statement by the Corps in its SSOF (JA 1838a), the

mitigation condition would not compensate completely for

the City’s withdrawals, as respondents now concede. Br. at

19n.11. Because flows would be affected even with the use

of the City’s storage, the Corps was obliged, as NMFS and

USFWS urged, to conduct a cumulative impact analysis of

46

this remaining impact together with all past, present and

reasonably foreseeable conditions affecting the same resource

before deciding whether an EIS was required. See infra at

52-54. The Corps failed to do so here.

Third, the opinion below also creates a conflict with

a decision of the Court of Appeals for the District of

Columbia that preparation of an EIS is particularly important

when public controversy over the effects of the project are

coupled with congressional investigation of the matter under

consideration. Foundation on Economic Trends v, Heckler,

587 F. Supp. 753, 756 (D.D.C. 1984), aff'd in part, vacated

in part on other grounds, 756 F.2d 143 (D.C. Cir. 1985).

Congress found in 1988 that

the striped bass and the aquatic environment

of the Albemarle Sound-Roanoke River basin

presently are being significantly affected by

combined but not fully understood

causes. ...

P.L. 100-589, §5(a)(5), 102 Stat. 2984, 2985, 16 U.S.C.

§1851 note. Accordingly, Congress required the Corps to

47

reevaluate the impacts of the proposed pipeline in light of a

study to be completed by the U.S. Fish and Wildlife Service

later this year. See P.L. 101-640, §413, 104 Stat. 4604,

4651 (1990). These actions by Congress, coupled with the

substantial expert opinion that the project may have adverse

environmental impacts, demonstrate that the level of

controversy is such that an EIS must be prepared.

The Court of Appeals nevertheless dismissed the

above arguments by saying:

The Corps of Engineers should consider the

comments of other agencies, but it need not

defer to them when it disagrees. The Corps

addressed the specific comments of the other

agencies, and explained why it found them

unpersuasive. No more is required.

940 F.2d at 64, infra at 20a. This view demonstrates a

fundamental misunderstanding of the purpose of NEPA, the

function of an EIS and the requirements of 40 C.F.R.

§1508.27(b)(4). As implemented by the CEQ regulations,

NEPA requires federal agencies to prepare an EIS when

48

faced with substantial conflicting opinions from experts.

NEPA’s objective would be frustrated if agencies were

allowed to disregard opposing opinions before conducting the

more rigorous investigation and analysis involved in the

preparation of an EIS.”°

B. Uncertainty --

40 C.F.R. § 1508.27(b)(5)

The CEQ regulations also mandate consideration of

the degree to which the effects of the proposed withdrawals

are "highly uncertain or involve unique or unknown risks."

40 C.F.R. § 1508.27(b)(5). Applying this regulation, other

courts of appeals have held that an agency faced with such

20 Compare Sierra Club v. U.S. Forest Service, 843 F.2d 1190,

1193 (9th Cir. 1988) (expert comments disputing an agency’s conclusion

that there will be no significant impact establish "precisely the type of

‘controversial’ action for which an EIS must be prepared") with Webb

vy. Gorsuch, 699 F.2d 157, 160 (4th Cir. 1983) (“conflicting expert

opinion . . . is for the administrative agency and not the courts to

resolve"). Both cases involved agency decisions not to prepare an EIS;

the latter fails to recognize the distinction between expert disputes while

an EIS is being prepared where the agency must resolve the conflict, and

expert disputes at the stage where the agency decides whether to prepare

an EJS and where it must apply the CEQ controversy test under 40

C.F.R. §1508.27(b)(4).

49

ne Nhe SR aed ARSON awl Rabin. Okt Deliae Bardi a at 2 Do ee!

uncertainty must prepare an EIS. See U.S. Forest Service,

- 843 at 1194; Jones v. Gordon, 792 F.2d 821, 829 (9th Cir.

1986); Foundation on Economic Trends v. Heckler, 756

F.2d 143, 153-54 (D.C. Cir. 1985); Foundation for North

American Wild Sheep v. U.S. Dept. of Agriculture, 681

F.2d 1172, 1182 n.47 (9th Cir. 1982).

The Corps recognized the uncertainty involved here.

JA 1813a, 1823a, 1838a. So did the District Court. 731 F.

Supp. at 1272, infra at 68a-69a (whether there will be dire

consequences in the event of a severe drought "remains to be

seen").

The extensive expert comments which questioned the

Corps’ views also demonstrate that the effects of this project

are highly uncertain. Moreover, the Court of Appeals

overlooked the important fact that Congress found that the

striped bass stock is being significantly affected by unknown

causes, and that the proposed pipeline project should be

reassessed after the Fish and Wildlife Service completes its

50

striped bass study later this year. P.L. 100-589, §5, 16

U.S.C. §1851 note (1988); P.L. 101-640, §413, 104 Stat.

4604, 4651 (1990). Congress would not have enacted such

legislation if it believed that the effects of this project were

certain. These acts of Congress, coupled with the comments

of the experts reflecting the controversy over the effects of

the project, demonstrate that the level of uncertainty required

the Corps to prepare an EIS.”!_ The opinion below is in

conflict with this binding CEQ regulation and with the

decision of other courts of appeals applying it.

71 The Court of Appeals stated that the commentors did not provide

enough “evidence” or "information" to support their views about the

potential environmental impacts of the proposed pipeline project. 940

F.2d at 63-64, infra at 15a. Aside from the fact that this view ignores

the extensive data and analyses submitted by commentors (see, e.g., JA

83la, 1363a-1389a, 1393a-1397a, 1413a-1416a, 1421a-143la, 1433a-

1468a, 1477a-1515a, 1537a-1540a, 1603a-1609a, 1915a-1919a) and the

congressional findings on this matter, it also overlooks the fact that the

impact of the project has not yet occurred. It is difficult to perceive what

further “evidence” of significant impacts the commentors were-required

to offer. Both the Corps and the experts who disagreed with the Corps

necessarily made informed predictions based upon their expertise in an

area of unusual complexity, controversy and uncertainty.

51

icsembantitesd iisanein Baten,

c. Cumulative Impacts --

40 C.F.R. §§ 1508.7

& 1508.27(b)(7)

The application by the Court of Appeals of the CEQ

regulation requiring agencies to consider cumulative effects

[40 C.F.R. §§ 1508.7 & 1508.27(b)(7)] before deciding

whether to prepare an EIS is in conflict with decisions of

other courts of appeals. The Court of Appeals held that the

Corps had discharged its duty in this respect by finding that

1) “the small effect of the City’s project on stream flows

should not have any significant effect on striped bass,” and

2) "any improvement in environmental conditions would be

[un]likely to improve the striped bass population.” 940 F.2d

at 65, infra at 23a.

In Hanly v. Kleindienst, 471 F.2d 823, 831 (2d Cir.

1972), cert. denied, 412 U.S. 908 (1973), the court ruled

that an agency must consider whether "even a slight increase

in adverse conditions that form an existing environmental

milieu may [be] significant." The Fifth Circuit in Fntiofson

52

y. Alexander held that an agency must consider "the overall

impact that can be expected if individual impacts are allowed

to accumulate" before deciding whether an EIS is required.

772 F.2d 1225, 1245 (1985)(emphasis added). In LaFlamme

vy. FERC, the Ninth Circuit held that the CEQ regulations

prohibit evaluation of a project’s impacts in isolation, and

require an analysis of the net impact that all existing and

reasonably foreseeable conditions may have on a basin’s

resources, before a decision not to prepare an EIS can be

justified. 852 F.2d 389, 402 (1988).

In this case, the Corps merely recited that several

factors (including flows, overfishing and water quality) may

affect striped bass. It concluded that “overfishing probably

was the principal reason for the collapse of this fishery." JA

1835a. Nevertheless, it found that the withdrawals could

affect striped bass if 1) there is a continuous relationship

between flow and striped bass recruitment and 2) overfishing

is stopped. Id.

53

A tee tin el abba yh lt

Pere eer weet

fe le Cre A eee ate Serena ome te SAE bet eS coseonn ees

Despite acknowledging that the withdrawals might

have an adverse effect on striped bass in the future, the

Corps made no effort to conduct a cumulative impact

analysis as mandated by 40 C.F.R. § 1508.27(b)(7) to

determine the overall impact of the proposed withdrawals

(even though they might be insignificant in themselves) when

added to all existing and reasonably foreseeable conditions

affecting striped bass.??_ Instead, it relied entirely on its

mitigation condition to obviate the need for such analysis.

JA 1835a-1838a.

-_

22 In approving this narrow view of the cumulative impact analysis

requirement, the Court of Appeals was clearly following its earlier

decisic xs on the issue. Gee v. Hudson, 746 F.2d 1471, 22 ERC 1213

(4th Cir. 1984) (Table No. 84-1172), cert. denied, 471 U.S. 1058 (1985)

(White, Brennan & Marshall, JJ., dissenting); Webb v. Gorsuch, 699

F.2d 157, 161 (4th Cir. 1983).

54

CONCLUSION

Seldom does a single opinion reach as many

conclusions that are in conflict with principles established by

this Court or with decisions of other courts of appeals as

does the opinion below. This case involves a matter of great

importance to Virginia and North Carolina -- the future use

of a substantial amount of water from an interstate water

system. More important, however, is the need for this Court

to address the unresolved conflicts over NEPA issues raised

by this case, as well as the unresolved conflict over the

obligation of federal agencies to make information available

to the public for review and comment before they reach final

decisions. The lower courts will continue to be in disarray

over these issues until such resolution occurs. This case

presents an excellent vehicle for that purpose. A writ of

certiorari should be granted.

55

Respectfully submitted,

ROANOKE RIVER BASIN ASSOCIATION

Patrick M. McSweeney

Counsel of Record

Michael V. Hernandez

McSWEENEY, BURTCH & CRUMP, P.C.

Post Office Box 1463

| 11 South Twelfth Street

Richmond, Virginia 23212

(804) 783-6800

STATE OF NORTH CAROLINA

Lacy H. Thornburg

Attorney General

Alan S. Hirsch

Special Deputy Attorney —_

General

N.C. DEPARTMENT OF JUSTICE

Post Office Box 629

Raleigh, N.C. 27602

(919) 733-5725

DATED: November 18, 1991

56

APPENDIX A

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

ROANOKE RIVER BASIN ASSOCIATION,

Plaintiff-Appellant,

and

STATE OF NORTH CAROLINA;

COUNTIES OF BERTIE, GRANVILLE,

HALIFAX, MARTIN, NORTHAMPTON,

VANCE, WARREN & WASHINGTON,

NORTH CAROLINA; COUNTIES OF

CHARLOTTE, HALIFAX & MECKLENBURG,

VIRGINIA,

Plaintiffs.

v. No. 90-3049

RONALD E. HUDSON, in his

official capacity as Norfolk

District Engineer, WAYNE A. HANSON,

in his official capacity as

Wilmington District Engineer;

JOSEPH K. BRATTON, LT. GEN., in his

official capacity as the Chief of

Engineers of the U.S. Army Corps of

Engineers; WILLIAM R. GIANELLI,

in his official capacity as Asst.

Secretary of the U.S. Dept. of the

Army; JOHN O. MARSH, in his official

| capacity as the Secretary of the U.S.

Dept. of the Army; THE CITY OF

la

VIRGINIA BEACH,

Defendants-Appellees.

NATIONAL WILDLIFE FEDERATION; NORTH

CAROLINA WILDLIFE FEDERATION,

Amici Curiae.

__ aan

STATE OF NORTH CAROLINA,

Plaintiff-Appellant,

and

COUNTIES OF BERTIE, GRANVILLE,

HALIFAX, MARTIN, NORTHAMPTON,

VANCE, WARREN & WASHINGTON,

NORTH CAROLINA; ROANOKE RIVER

BASIN ASSOCIATION; COUNTIES OF

CHARLOTTE, HALIFAX & MECKLENBURG,

VIRGINIA,

Plaintiffs.

v. No. 90-3050

RONALD E. HUDSON, in his

official capacity as Norfolk

District Engineer, WAYNE A. HANSON,

in his official capacity as

Wilmington District Engineer;

JOSEPH K. BRATTON, LT. GEN., in his

official capacity as the Chief of

Engineers of the U.S. Army Corps of

Engineers; WILLIAM R. GIANELLI,

in his official capacity as Asst.

Secretary of the U.S. Dept. of the

Army; JOHN O. MARSH, in his official

Capacity as the Secretary of the U.S.

Dept. of the Army; THE CITY OF

VIRGINIA BEACH,

Defendants-Appellees.

3a

NATIONAL WILDLIFE FEDERATION; NORTH

CAROLINA WILDLIFE FEDERATION,

Amici Curiae.

Appeals from

the United States District Court

for the Eastern District of North

Carolina, at Raleigh.

W. Earl Britt, District Judge.

(CA-84-36-5-CIV-WE)

Argued: February 7, 1991

Decided: July 3, 1991

Before: HALL and NEIMEYER, Circuit Judges, and

KISER, United States District Judge for the Western District

of Virginia, sitting by designation.

Affirmed by published opinion, Judge Kiser wrote the

opinion, in which Judge Hall and Judge Neimeyer joined.

COUNSEL

ARGUED: Alan S. Hirsch, Special Deputy Attorney

General, NORTH CAROLINA DEPARTMENT OF

JUSTICE, Raleigh, North Carolina, for Appellant State of

North Carolina; Patrick M. McSweeney, McSWEENEY,

Sa

BURTCH & CRUMP, P.C., Richmond, Virginia, for

Appellant Roanoke River Basin Association. George A.

Somerville, MAYS & VALENTINE, Richmond, Virginia;

Robert L. Klarquist, Lands and Natural Resources Division,

UNITED STATES DEPARTMENT OF JUSTICE,

Washington, D.C., for Appellees. ON BRIEF: Lacy H.

Thornburg, Attorney General, NORTH CAROLINA

DEPARTMENT OF JUSTICE, Raleigh, North Carolina, for

Appellant State of North Carolina; Michael V. Hernandez,

McSWEENEY, BURTCH & CRUMP, P.C., Richmond,

Virginia, for Appellant Roanoke River Basin Association.

John F. Kay, Jr., M. Scott Hart, Susan Warriner Custer,

MAYS & VALENTINE, Richmond, Virginia; George W.

Van Cleve, Acting Assistant Attorney General, Glen R.

Goodsell, J. Carol Williams, UNITED STATES

DEPARTMENT OF JUSTICE, Washington, D.C.; Margaret

Person Currin, United States Attorney, Stephen A. West,

Assistant United States Attorney, Raleigh, North Carolina,

Leslie L. Willey, City Attorney, Jeffry A. Sachs, Assistant

City Attorney, CITY OF VIRGINIA BEACH, Virginia

Beach, Virginia; John R. Jordan, Jr., Robert R. Price,

JORDAN, PRICE, WALL, GRAY & JONES, Raleigh,

North Carolina, for Appellees. S. Elizabeth Birnbaum,

NATIONAL WILDLIFE FEDERATION, Washington,

D.C., for Amici Curiae.

Sa

OPINION

KISER, District Judge:

The State of North Carolina and the Roanoke River

Basin Authority have appealed a decision of the Army Corps

of Engineers to issue a permit to the City of Virginia Beach,

Virginia to construct a water intake structure and pipeline

that would divert sixty million gallons of water a day from

Lake Gaston, a lake that is part of the Roanoke River

system, approximately 85 miles to connect to Virginia

Beach’s water supply. Our review, like that of the district

court, is limited to a determination of whether the Corps’

decision was "arbitrary, capricious, otherwise not in

accordance with law, or unsupported by substantial

evidence." 5 U.S.C. § 706(2). We conduct the review

without giving deference to the district court’s decision.

VAGA v.- Donovan, 774 F.2d 89, 93 (4th Cir. 1985). We

affirm the district court’s findings that the Army Corps of

Engineers complied with all appropriate statutory provisions.

6a

ee re WTR ete ae.

I. Background’

Virginia Beach is the largest city in Virginia, and has

an inadequate supply of potable water. Aside from five

emergency wells intended for contingency use only, Virginia

Beach depends entirely on the City of Norfolk for its water.

The city has suffered from recurrent water shortages, and has

been forced to ration water on several occasions. After

considering several alternatives, Virginia Beach decided that

its best water source for the future would be a pipeline from

Lake Gaston.

On July 15, 1983, Virginia Beach applied to the

Norfolk District of the Army Corps of Engineers for a

permit to construct a water intake structure, pier, boathouse

and ramp in the Pea Hill Creek tributary of Lake Gaston in

Brunswick County, Virginia, and a sixty-inch inside diameter

' The procedural history and legal and factual background are set

forth in detail in two district court decisions in this case, North Carolina

v. Hudson, 665 F. Supp. 428 (E.D.N.C. 1987) (Hudson I), and 731 F.

Supp. 1261 (E.D.N.C. 1990) (Hudson II), and we will not undertake

repeating those details here.

Ta

concrete pipe to extend to Norfolk’s water treatment

facilities. The pipeline would carry up to sixty million

gallons per day (mgd). Eighty percent of the water would go

to the city of Virginia Beach, and the remainder to nearby

towns and counties. |

The pipeline, like all construction affecting navigable

waters within the United States, required permission from the

Army Corps of Engineers. 33 U.S.C. § 403. On October

11, 1983, the Norfolk, Virginia District Corps issued a draft

Environmental Assessment (EA) and a preliminary Finding

of No Significant Impact (FONSI) for public review and

comment. After holding three public hearings, and allowing

the required 30 day comment period, the Norfolk District

Corps issued the requested permit on January 9, 1984.

The pipeline would also require reallocation of

storage in Kerr Reservoir, upriver from Gaston Lake, from

power to water supply. This change required the approval

of the Wilmington, North Carolina District Corps of

8a

Engineers. On January 13, 1984, the Wilmington District

Corps adopted the EA prepared by the Norfolk District, and

issued a FONSI concluding that the proposed reallocation of

storage would have no significant environmental impact.

The State of North Carolina filed this suit on January

12, 1984, seeking to prevent the pipeline from being

constructed. The Roanoke River Basin Authority, eight

. counties in North Carolina and four counties in Virginia later

intervened as plaintiffs.

Virginia Beach initiated a declaratory judgment action

in the Eastern District of Virginia on January 9, 1984 (three

days before the North Carolina action was initiated), seeking

a declaratory judgment that the permit and contract were

valid. That action in transferred to the Eastern District of

North Carolina after this Court determined that the Virginia

district court had no personal jurisdiction over the Geverncr

of North Carolina, a named defendant. City of Virginia

Beach v, Hudson, 776 F.2d 484 (4th Cir. 1985). The action

9a

was later dismissed because Virginia had raised all of the

same arguments as an intervenor in the case filed by North

Carolina. Hudson I, 665 F. Supp. at 433.

On July 7, 1987, Chief Judge Britt issued his first

ruling. He approved most of the findings of the Corps, but

_remanded the matter to the Norfolk District Corps for further

inquiry on two issues; (1) to conduct an additional

investigation of the effects of the proposed project on

anadromous striped bass to determine whether an

Environmental Impact Statement (EIS) would be required;

and (2) to make a determination of the extent of Virginia

Beach’s water needs. Hudson I. In response to this order,

the Corps filed a pclae Environmental Assessment,

a Supplemental Statement of Findings (SSOF), and a Revised

Findings of No Significant Impact (RFONSI). The Corps

reissued the permit, adding a new mitigation condition to:

maintain sufficient flow during bass spawning season. On

February 2, 1990, Judge Britt issued a final decision

10a

fn ee ne tok

approving the permit. Hudson II. The matter is now ripe

for appeal.

Ii. nvironmen

A. Possible Impact on Striped Bass

Appellants challenge the Corps’ decision not to

prepare an EIS in light of the possible impact that the

pipeline might have on the striped bass population of the

Roanoke River. An EIS must be prepared for any "major

Federal action significantly affecting the quality of the human

environment." 42 U.S.C. § 4332. Ifa mitigation condition

eliminates all significant environmental effects, no EIS is

required. C.A.R.E. Now, Inc, v. F.A.A., 844 F.2d 1569,

1573 (11th Cir. 1988). The Corps has assumed that the

project is a major federal action, and we shall defer to this

determination. See Hudson I, 665 F. Supp. at 438. The

only issue, then is whether the withdrawal of 60 mgd from

Gaston Lake might significantly affect the environment.

lla

The Council on Environmental Quality has defined

the term "significantly." 40 C.F.R. § 1508.27(b).

"[(S]ignificantly” as used in NEPA requires

considerations of both context and intensity.

Appellants assert that three of ten listed measurements of

intensity are present in this case, and that these require that

an EIS be conducted.”

(4) The degree to which the possible effects

on the quality of the human environment are

likely to be highly controversial.

(5) The degree to which the possible effects

are highly uncertain or involve unique or

unknown risks.

(7) Whether the action is related to other

actions with individually insignificant but

cumulatively significant impacts. Significance

exists if it is reasonable to anticipate a

cumulatively significant impact on the

environment.

. Amicus claims that several other factors are also present. The

considerations required by the listed definitions tend to overlap, and the

evidence supporting amicus’ claim is essentially the same as that cited by

appellants.

12a

Appellants claim that the level of controversy concerning the

effect of the project on the striped bass population requires

an EIS. The Corps found that the mitigation condition

would eliminate the causes of the controversy. We find that

the Corps’ determination was supported by the record and,

therefore, is not arbitrary and capricious.

Since 1971, the Corps has required the operators of

upriver dams to release sufficient water to maintain Kerr

Lake at a level between 299.5 and 302 feet during spawning

season, which typically runs from April 26 to June 15. Kerr

Lake, in turn, releases to Gaston which, in turn, releases to

Roanoke Rapids. This release is intended to maintain a level

of 13 feet in the river at Weldon, downstream from Roanoke

Rapids Dam. J.A. 1807. In 1988, at the recommendation

of the Roanoke River Water Flow Committee,’ the increased

* The Committee was formed after the case was remanded to the

Corps for a further determination of the environmental impact on bass.

The district court noted that “the formation of a committee of ‘experts’

to deal with a question of the flow of water in a river without inviting

(continued...)

13a

flow period was augmented to run from April | to June 15,

and also modified so that flow levels more closely replicate

conditions prior to impoundment of Kerr Reservoir in 1953.

For a variety of reasons, the dam releases have sometimes

been insufficient to maintain the required flow levels on

some days during the augmented flow period. The Corps

determined that the best measure of possible impact on the

bass population of the pipeline would be the number of

additional "lost flow” days, where the river level is below

the required level. The Corps then found that the pipeline

would cause, at most, one additional "lost flow” day every

seven years, where the stream level would fall below the

prescribed limits under the 1971 standard. J.A. 1836.

The Corps believed that one lost flow day every seven

years would have no significant effect on the bass population.

3(.. continued)

the Corps, the acknowledged “expert” in such matters, raises some doubt

about the impartiality of the committee and the credibility of its

findings.” Hudson I], 731 F. Supp. at 1269. Nonetheless, the Corps

considered its recommendations in the SSOF. J.A. 1837-38.

l4a

Indeed, it pointed to some evidence suggesting that spawning

increases during years of relatively low flow. J.A. 1808.

However, it recognized that the effect of one additional low

flow day every seven years might be controversial and, if

this were to occur, an EIS might be required.

To avoid even a slight increase in the number of lost

flow days, the Corps directed that Virginia Beach use storage

water it purchased in Kerr meenreals (upstream from Gaston

Lake), instead of water already dedicated to the augmented

spawning flows, to offset all downstream effects of its

withdrawals. J.A. 1838. The Corps found that this

mitigation condition would eliminate all possible effects of

the pipeline. The district court found that the Corps’

mitigation condition is adequate to address any possible

environmental effects of the pipeline.

Appellants and amicus believe that the mitigation

condition is insufficient for several reasons. First, it

addresses only the problem of the number of low flow days.

1Sa

A continuous decrease of the flow by 60 mgd might affect

the bass population, even if the number of low flow days

was unchanged. Second, it assumes that sufficient storage

water will be available in Kerr Lake to maintain the lake

level. Finally, the mitigation condition was not made public

until the final report, so there was no opportunity for public

comment or criticism.

The Corps based its mitigation condition on an

entirely reasonable assumption: That the number of lost flow

days is the best measure of the effect of the pipeline on the

bass population. Plaintiffs generally supported this

assumption in the arguments that they submitted to the Corps

by focusing on lost flow days as being the decisive factor in

determining any adverse impact on the spawning season.

For example, the North Carolina Division of Marine

Fisheries asserted, "The loss of even the last day of a

spawning period could well result in production of a poor

16a

year class rather than a normal or exceptional year class."*

J.A. 830-31. The United States Fish and Wildlife Service,

the E.P.A. and the Sierra Club also filed comments based on

the same assumption. None of those commenting provided

evidence suggesting that the flow levels as currently set were

insufficient. The absence of evidence to the contrary

virtually compels the conclusion that a lower flow above the

required level will have no significant environmental affect.

The same organization suggested that "any loss of water

could have an extremely significant impact,” but it provided

no evidence to back up this claim.

The mitigation condition also does not address the

4 The Corps did consider this comment, and after examining the

supporting evidence, concluded that it was completely unsupported. J.A.

1810.

> Indeed, the modified flow regime introduced in 1988 reduced the

required flow through the April 26-June | period, while raising the level

for the April 1-25 period. This suggests that lowering the flow within

the augmented range is not considered to be problematic. The Corps also

found that very high flows “tend to be associated with lower juvenile

abundance indices.” J.A. 1809.

17a

problem that flow on days already lost will be even lower.

Again, all of those commenting assumed that a low flow day

was detrimental to bass spawning, and presented no

information on the effect of lowering the flow on days when

the level was already below the required amount. An issue

never presented to the Corps "must not be made the basis for

overturning a decision properly made after an otherwise

exhaustive proceeding.” Vermont Yankee Nuclear Power

Corp. v. NRDC, 435 U.S. 519, 558 (1976). The Corps’

failure to consider an effect that was not brought to its

attention cannot be faulted.®

Appellants and amicus also argue that in the event of

a prolonged drought, Virginia Beach’s storage capacity in

Kerr Lake might be insufficient to comply with the

© The Corps also argued in its brief with this Court that the

pipeline would have no effect at all on river levels during the lost flow

days. Because it did not make this argument in the RFONSI and the

other administrative rulings, it will not be considered here. Motor

Vehicle Manufacturers Ass’n v. State Farm Mutual Ins., 463 U.S. 29,

43 (1983).

18a

mitigation condition. Virginia Beach submitted a Project

Hydrologic Model to demonstrate that the greatest need for

water in the past 75 years would have required only 54% of

Virginia Beach’s storage capacity. J.A. 712-13. The Corps

verified this model, and found it to be persuasive. J.A. 1810.

This determination is not arbitrary and capricious.

Finally, appellants complain that the mitigation

condition was not available for public comment. This

objection is spurious. The proposed use of Virginia Beach’s

storage Capacity to augment the river’s flow was described in

the draft Supplemental Environmental Analysis that was

presented for public sisihiaiiia on June 6, 1988. J.A.

1065, 1071. The mitigation condition required Virginia

Beach to provide water, while the draft simply assumed that

the water would be available for that purpose. The Corps’

decision to make the mitigation condition mandatory means

that the modified permit protects the appellants’ interests (and

the striped bass) more completely than the proposal available

19a

for comment.

Several of those commenting from North Carolina,

and two federal agencies, the Fish and Wildlife Service and

the National Marine Fisheries Service, believed that the

effect on the striped bass population is sufficiently uncertain

that an EIS should be conducted. Appellants argue that the

fact that disinterested federal agencies request that an EIS is

proof that the effect is “controversial,” so that the Corps

abused its discretion in refusing to commission an EIS.

However, the existence of a disagreement as to whether an

EIS should be commissioned is not by itself grounds for a

court to require an EIS. Rucker v. Willis, 484 F.2d 158,

162 (4th Cir. 1973). The Corps of Engineers should

consider the comments of other agencies, but it need not

defer to them when it disagrees. The Corps addressed the

specific comments of the other agencies, and explained why

it found them unpersuasive. No more is required.

20a

B. Effect on Water Quality

Appellants’ claim that the Corps did not adequately

consider the effect of the pipeline on downstream water

quality is also without merit. The Corps based its conclusion

on the fact that there would be no quality affect on

conditions during times of relatively low flow, as well as

average flow conditions. J.A. 174. It found that the

withdrawal may increase the total number of days with

relatively iow flow, but that the effect on the quality of the

water would be insignificant. J.A. 174. This finding is

supported by the record, and is not arbitrary and capricious.

Although there may be some impact, if it is not significant,

then an EIS is not required. 42 U.S.C. § 4332(C)(2);

Hudson I, 665 F.Supp. at 439.

2la

i Failure to Consider Cumulative

I F Withd

40 C.F.R. §1508.27(b)(7) requires that the Corps

consider whether a project’s environmental effects may be

cumulatively significant in conjunction with other

environmental conditions that are reasonably foreseeable,

even if they are not significant by themselves. Appellants

and amicus assert that the Corps failed to make this analysis,

and that the cumulative effect of this withdrawal of water, in

conjunction with anticipated growth of irrigation, population

and industry in the Roanoke River basin, may have a

significant effect on water quality.

In fact, the Corps did consider whether there would

be an cumulative effects on water quality. It concluded that

the effects of the withdrawal of water, coupled with

anticipated downstream pollution, would not be significant.

J.A. 174. It further found that additional pollution in the

Roanoke River was not reasonably foreseeable, and that there

22a

was not reason to believe that irrigation withdrawals from the

river would increase in the future. J.A. 1843. -All of these

findings are adequately supported by the administrative

record, and are neither arbitrary nor capricious.

Plaintiffs and amicus argue that the Corps failed to

consider the cumulative effect of the pipeline on the striped

bass population. They note that the striped bass population

has been declining for some time, in part, because of

overfishing. It claims that even if the pipeline’s effect on

bass population might be insignificant in itself, it may

exnouibege the overfishing and other stresses on the bass.

The Corps fully considered this sei in the SSOF.

It found that because of the overfishing, "the small effect of

the City’s project on stream flows should not have any

significant effect on striped bass." J.A. 1835. It further

found that any improvement in environmental conditions

would be likely to improve the striped bass population.

There is adequate basis for this finding in the record, and it

23a

is not arbitrary and capricious. The Corps has discharged its

duty to consider the cumulative effects of the pipeline with

other existing or foreseeable environmental conditions.

D. —— ,

The appellants claim that the computer model used by

the Corps was made available to the public only days before

the end of the comment period on the proposals. This

alleged failure to disclose information made a challenge to

the model more difficult to prepare. The appellants concede,

however, that they received the computer model shortly

before the public comment period ended. They have not

explained what use they expect to make of the "the complete

articulation of underlying modeling assumptions" that they

claim they have never received. It is clear from the record

that appellants had ample information available to them to

mount a challenge to the Corps’ permit. For example, they

were able to form a committee of experts, the Roanoke River

24a

Water Flow Committee, working without assistance from the

Corps, that created its own models and made

recommendations on river flow that were fully considered by

the Corps. Hudson II, 731 F.Supp. at 1269. We are

satisfied that the appellants were not prejudiced by any

slowness or incompleteness in the Corps’ disclosure of

modeling information.

III. Public Inter

Appellants also assert that the Corps failed to consider

the public interest impact of the pipeline in North Carolina,

in violation of 33 C.F.R. § 320.4(a). The public interest

analysis conducted by the Corps examined estimates of the

population growth for Virginia Beach over the next 40 years,

and concluded that the pipeline ones will be necessary to

meet the needs of Virginia Beach’s fast-growing population.

J.A. 1842. The district court examined the same data, and

concluded that even with the pipeline, Virginia Beach may

25a

soon find itself with an inadequate water supply. Hudson II,

731 F.Supp. at 1272.

Appellants argue that the Corps acted in an arbitrary

and capricious manner when It considered future population

growth of Virginia Beach, but not future increased water

needs downstream in North Carolina. However, the Corps

considered future needs in North Carolina in both the

original SOF and the SSOF it wrote on remand. It found in

1984 that although large corporations were considering

building a wood pulp plant and a coal-burning power plant

along the Roanoke River, these projects were not firmly

committed. J.A. 191. Accordingly, it would be

inappropriate to consider the impact of the pipeline on these

projects. On reconsideration in 1988, the Corps found that

the coal burning plant would not be built, and that the paper

manufacturer "is not appreciably closer to deciding to

construct a new plant.” J.A. 1843. It, therefore, again

concluded that it was not reasonably foreseeable that these or

26a

any other industrial plants would be appreciably affected by

the pipeline. It also found that the need for water for

agricultural irrigation varied widely from year-to-year, but

that because the principle irrigated crop is tobacco, a crop

for which acreage is controlled by the federal government,

it was not reasonable that agricultural irrigation would be

affected by the new plant.

Appellants’ claim that the Corps considered growth

only in Virginia Beach and not in North Carolina is

incorrect. it considered the potential for growing water

needs in both areas, and concluded that increased need was

foreseeable for Virginia Beach, and not reasonably

foreseeable for North Carolina. This finding is adequately

supported by facts in the record, and is not arbitrary and

capricious. North Carolina’s objection appears to be that if

Virginia Beach builds the pipeline, then 60 million gallons of

water a day will be unavailable for future use in North

Carolina at some point in the far future. This is true, but it

27a

is insufficient to stop the project. The Corps properly

discharged its duty to conduct a public policy review.

IV. Conclusion

Gaston Lake pipeline is a controversial project

because it will remove a substantial amount of water from

one river basin to a distant area. However, there is no

longer any controversy concerning either the environmental

effects on the Roanoke River, or the need for a new supply

of water in Virginia Beach, in both absoluie terms and

relative to the needs of northeastern North Carolina. The

Army Corps of Engineers properly considered all factors that

it was required to consider before issuing a permit. Its

decision to issue a permit for the project shall not be

disturbed.

28a

APPENDIX B

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF NORTH CAROLINA

RALEIGH DIVISION

No. 84-36-CIV-5

STATE OF NORTH CAROLINA,

et al.,

plaintiffs,

v. MEMORANDUM

OPINION

COLONEL RONALD E. HUDSON,

et al.,

defendants.

The City of Virginia Beach, Virginia is seeking

permission from the United States Corps of Engineers (the

Corps) to construct a sixty-inch pipeline some 84.5 miles

across southern Virginia and withdraw up to 60 million

gallons of water per day (mgd) from Lake Gaston for the

purpose of meeting its municipal water supply needs. After

the Corps made a decision to issue the permits needed by

Virginia Beach to accomplish the project, this action was

begun by the State of North Carolina, the Roanoke River

29a

Basin Association (RRBA) and several counties in Virginia

and North Carolina for judicial review of the decision of the

Corps. Thereafter, this court conducted a review of the

Corps’ decision and rendered a decision on 7 July 1987,

State _of North Carolina _v. Hudson, 665 F.Supp. 428

(E.D.N.C. 1987).

I. PROCEDURAL HISTORY

After a thorough review of the Administrative Record

and consideration of the arguments and briefs of all parties,

the court remanded the matter to the Corps. The court’s

decision was very specific on the scope of the further review

which was mandated:

On remand, the Corps shall:

1. Asa part of its NEPA review make

an independent assessment of the effects of

the proposed project on striped bass to

determine whether the preparation of an EIS

[Environmental Impact Statement] is requried

or whether any mitigative measures are

necessary; and,

2. As a part of its public interest

30a

review make a determination of the extent of

Virginia Beach’s water needs.

Hudson, 665 F.Supp. at 450.

All other objections by plaintiffs to the decision’ of

the Corps were rejected. The court retained jurisdiction and

directed the Corps to file with the court the results of its

reconsideration and the record supporting its decision. The

Corps has complied and the matter is now before the court

for review of the supplemental record.”

The record includes a Supplemental Environmental

Assessment (SEA), a Supplement Statement of Findings

(SOF) and a Revised Finding of No Significant Impact

, Actually there were two decision of the Corps under review.

One, by the Norfolk District, to issue a permit to construct a water

intake structure and pipeline in Lake Gaston to extend to Suffolk,

Virginia, and the other, the Wilmington District, to enter into a water

storage reallocation contract for Kerr Reservoir.

> The record consists of twenty-three volumes of material consisting

of 165 documents, most of which are multi-page. In addition, the parties

have, by stipulation, added another three volumes containing in excess

of fifty documents. One of the briefs filed with the court suggests that

the record compiled on remand is twice the size of the original record.

3la

(RFONSI).* The Corps concluded that Virginia Beach’s

withdrawal of water from Lake Gaston will have no

significant impact on the human environment, that an

environmental impact statement (EIS) is not necessary, and

that the amount of the proposed withdrawal, 60 mgd, is

needed.

II. BACKGROUND

In order to evaluate the potential for harm to the

striped bass population from the withdrawal of water from

Lake Gaston, it is necessary to understand the Roanoke River

Basin and its interconnected system of lakes as well as the

history and habits of striped bass.

3 The Norfolk and Wilmington Districts each filed a RFONSI

addressing their separate areas of responsibility, although the Wilmington

District based its RFONSI on the Norfolk District’s findings.

32a

A. THE ROANOKE RIVER SYSTEM

The Roanoke River is formed at the confluence of the

North and South Forks in Montgomery County, Virginia and

flows generally in a southeasterly direction until it empties

into the Albemarle Sound in northeastern North Carolina.

Dams have been constructed on the river for both flood

control and hydroelectric purposes, resulting in the formation

of many lakes, the lower three of which, Kerr, Gaston and

Roanoke Rapids, are important for this discussion. (Philpott

and Smith Mountain are upstream from Kerr and are not

directly affected by the project, although the amount of water

released from them does affect the amount of water in the

Kerr Lake Reservoir.) Kerr Lake (also known as Buggs’

Island Lake) lies mostly in Virginia and is controlled by the

Wilmington District of the Corps. Lake Gaston, just

downstream of Kerr, lies mostly in North Carolina and is

controlled by Virginia Power Company (VEPCO). Roanoke

Rapids Lake is entirely in North Carolina, lies downstream

33a

of Gaston, and is also controlled by VEPCO.

By use of the dams, the flow of water can be

restricted from the natural flow of the river during times of

flood or high water conditions and increased during drought

or low water conditions. Thus, more uniformity in stream

flow can be accomplished than would occur naturally.

Nevertheless, wide fluctuations still occur.

All three of the dams are operated primarily for peak

power projection although other goals -- flood control, lake

levels, and river flow -- are also considered. It is the flow

of the river below the last dam, Roanoke Rapids, that is of

primary con-ern when considering the impact of the project

on striped bass. As the flow of the river below Roanoke

Rapids Dam is entirely dependent on natural rainfall and

releases from the lake at the dam, the river theoretically, of

course, could dry up. This condition is prevented, however,

by the license issued to VEPCO by the Federal Energy

Regulatory Commission (FERC) which requires minimum

34a

releases at the Roanoke Rapids Dam in amounts which vary

throughout the year. Releases of at least 1,000 cubic feet per

second (cfs) are required from November through March,

2,000 cfs from April through September, and 1,500 cfs in

October. VEPCO always has enough water to meet these

requirements because the Corps is required by hydropower

contracts with VEPCO and Carolina Power & Light Co.

(CP&L) to make releases which, when combined with

natural drainage into Lake Gaston and Roanoke Rapids Lake,

average at least 545 cfs (352 mgd) more than VEPCO’s

minimums during every month of the year. Depending on

its Own power generation needs, VEPCO may store this

surplus in Lake Gaston and Roanoke Rapids Lake for short

periods of time and release it during peak electricity demand

hours. The average flow of water through Roanoke Rapids

Dam is 8,153 cfs.

The flow of water at Roanoke Rapids Dam is

augmented during the striped bass season pursuant to the

35a

terms of a 1971 Memorandum of Understanding (MOU)

among the Wilmington District of the Corps, VEPCO and

the North Carolina Wildlife Resources Commission

(NCWRC). Under this agreement the Corps is required to

release stored water in Kerr Lake between elevations of

299.5 and 302 feet, mean sea level, during the spawning

season so as to maintain, when possible, a minimum stage of

13 feet below the Roanoke Rapids Dam. This release equals

an outflow from the Roanoke Rapids Dam of approximately

5700-6000 cfs. The agreement require the augmented flow

for a period of 50 days, which lasts from approximately 26

April until 15 June, although NCWRC determines the exact

date.

Kerr is the largest of the three lakes and is the

primary storage facility in the system. In an average year,

Kerr’s level fluctuates 12 feet, but in any given year it may

fluctuate by as much as 27 feet, between elevations of 293

36a

and 320 feet. The Corps makes every effort to maintain

Kerr’s level at the 293 minimum, but it is occasionally

unable to do so and still releases the amounts required by its

contract with the power companies. At those times, if the

power companies agree, the Corps releases only enough

water from Kerr to meet VEPCO’s required releases at

Roanoke Rapids.

B. STRIPED BASS

The anadromous’ striped bass® is an important sport

and commercial fish native to the eastern seaboard, thriving

in both salt and fresh water. They migrate in spring from

their natural habitats in the sounds and ocean up rivers and

streams to spawn. Each year this ritual is repeated by striped

4 320 feet is the top of the spillway at Kerr Lake.

° To distinguish from the landlocked striped bass found in Kerr

Lake.

© Also known as Rockfish.

37a

bass migrating from the Albemarle Sound up the Roanoke

River to the vicinity of Weldon, just downstream from the

Roanoke Rapids Dam, where the eggs are laid. It is thought

that successful spawning is dependent upon higher-than-

normal river flows as the turbulence caused by the high

water keeps the eggs buoyant until they become hardened and

naturally attain near-neutral buoyancy.’

There has been a significant decline in the population

of striped bass for many years. The problem has been

addressed by governmental and private groups on the state

and national level in an effort to stope the decline of, and

hopefully restore, this valuable natural resource. No

consensus has been reached on the cause or causes of the

decline although pollution, fishing pressure and interference

with the spawning process are thought to be major

7 This principle was stated as a fact in the original record before

the court but the validity of the thesis seems to be questioned in the

Supplemental Record (SR). See SEA, SR 157.

38a

contributors.

I. SUPPLEMENTAL ENVIRONMENTAL

ASSESSMENT

The SEA filed by the Corps analyzes all of the

materials collected and concludes that the withdrawal by

Virginia Beach of up to 60 mgd from Lake Gaston will have

no impact, let alone a significant impact, on the spawning of

striped bass in the Roanoke River. Colonel Thomas,® the

district engineer of the Corps’ Norfolk District, separately

addresses some of the factors which have been suggested to

have had some effect on the decline of the population of

striped bass. His analysis of the data presented makes a

convincing argument that the primary cause of the decline is

overfishing. By correlating and anal: zing data concerning

the rate of flow at Roanoke Rapids Dam, he demonstrates

that "[t]he conventional thinking for years... that more

water is better . . . may not have been entirely beneficial to

8 Colonel J.J. Thomas, successor to Colonel Hudson.

39a

the striped bass." SEA, SR 157, p. 4. He also effectively

rebuts the suggestion that fluctuations in the rate of ilow

probably had an adverse effect on spawning activity.

To plaintiffs’ contention that the loss of even one day

of the minimum augment flow could have a severe impact on

the success of spawning, Colonel Thomas demonstrated

through data analysis that spawning has historically been

practically completed by the first of June and concluded that

"[t]heoretically, the period from June 1-June 15 could be lost

from the end of a spawning season with a subsequent loss of

only 1% of the spawned eggs, on average." SEA, SR 157,

p. 6.

The 1983 Final Environmental Assessment (FEA),

based on a model of the City of Virginia Beach, stated that

the project would cause a loss of the last day of the spawning

flows in one out of four years and the last two days once out

of 25 years. Following, remand, Virginia Beach offered to

utilize the volume of storage in Kerr Lake which it purchased

40a

from the Corps in such a way as to eliminate the loss of any

days of spawning flows due to its project. The SEA makes

note of this offer and states further:

To demonstrate this capability, the

Wilmington District prepared a mathematical

hydrologic model of the river and reservoirs

using daily flow records for the period of

record. This model showed that the City’s

project (without using the City’s storage in

Kerr Reservoir) would cause a loss of the last

day of the spawning flows in one out of seven

years and no years with a loss of two days or

more. (It should be noted that this last day

may well occur prior to June 15, since 50

days of flow are not always available.) The

small extent of the impact is due mainly to the

small size of the City’s withdrawal (60 mgd

maximum) compared to the spawning season

flows (6000 cfs = 4000 mgd). Use of the

City’s storage to restore lost days caused by

the project would result in a maximum

drawdown not exceeding 0.15 foot within

Kerr Reservoir from elevation 299.5 feet to

299.35 feet on the average of once every

seven years.... This volume of water is so

mall in comparison to the volume of the three

reservoirs that even during the worst drought

of record, coinciding with complete

compensation from the City’s storage in Kerr

during an entire 50-day spawning period, and

at the maximum withdrawal rate (60 mgd),

flows from the Roanoke Rapids dam would

4la

never be caused to drop below their FERC

minimums at any later time during the

drought. Water levels would not be affected

in either the Gaston or Roanoke Rapids

reservoirs, and the maximum drawdown due

to the project in Kerr Reservoir would be only

an additional 0.15 foot. It is apparent, then,

that the City’s project would have no effect on

Virginia Power’s ability to meet FERC

minimum releases and that, with the use of

Virginia Beach’s storage, all project effects on

flow during the striped bass spawning season

can be eliminated.

SEA, SR 157, p.6.

SUPPLEMENTAL STATEMENT OF FINDINGS

The SSOF filed by the Corps in response to this

court’s order of 7 July 1987 states that all available

information, including data contained in the SEA and

comments received from federal, state and local agencies,

and the general public had been evaluated. The SSOF

contains a summary of the evaluation and the Corps’

conclusion. Most important to this review is the conclusion

by Colonel Thomas that any environmental impacts "would

42a

be non-significant in the context of NEPA.” SEA, SR 158,

p.10. Colonel Thomas further states:

However, it is appropriate for me to consider

what would happen if I’m wrong. I recognize

that striped bass are an important resource in

North Carolina and elsewhere, and that much

effort has been directed by Congress and

Federal and State agencies toward their

restoration. I also recognize that this project

has received a tremendous amount of public

attention over the last few years, and that

public perception may be a legitimate concern

even when it is not supported by fact.

Therefore, I find it appropriate to amend the

City’s permit to require as a condition that

they must allow the Wilmington District,

Corps of Engineers to utilize the storage

which the City has purchased in Kerr

Reservoir during the period of the striped bass

augmented spawning flows to not cause the

loss of any augmented spawning flow days

which would otherwise be caused by the

City’s withdrawal. By completely

compensating for their withdrawal during the

spawning season, this will virtually eliminate

the possibility of any adverse effects of even

minimal significance which this project could

cause during the critical life stages of the

Roanoke/Albemarle striped bass.

SSOF, SR 158, p.10.

43a

V. THE CORPS’ NEED ANALYSIS

Upon remand the Corps invited submissions regarding

water supply analyses and projections of deficits for Virginia

Beach (the Norfolk water system) and Southside Hampton

Roads through the year 2030. The State of North Carolina,

the City of Virginia Beach and the Virginia State Water

Control Board responded. These submissions were evaluated

by the Corps which concluded that Virginia Beach’s need is

at least the 60 mgd for which a withdrawal permit is sought.

Colonel Thomas placed great reliance on a 1984 study by the

Corps which found a 55 mgd deficit in Hampton Roads and

in the James Water Supply Plan of the Virginia State Water

Control Board which found a 2030 deficit in the Norfolk -

Virginia Beach - Chesapeake - Portsmouth - Suffolk area of

between 49 and 81 mgd. With regard to the latter study the

SSOF stated:

The water system of these five cities represent

the total pool of existing supplies from which

Virginia Beach’s needs could be met. The 49

44a

mgd figure represents that amount of water

which would be needed to avoid "storage

depletion” (i.e., running completely out of

water after having instituted voluntary

conservation, followed by mandatory water

use restrictions, followed by rationing). The

81 mgd figure represents the amount needed

to avoid having to impose any but voluntary

conservation. These figures also assume that

the distribution systems of the entire five-city

area would be completely interconnected and

that each city would fully share all of its

water with all of its neighbors. The former is

correct in large part already, and further

interconnection will encounter problems with

diminishing returns. The different water

sources and the independent operation of the

municipal utilities would tend to preclude the

total and equal sharing of water that can be

achieved with complete efficiency only in

theory. For these reasons the actual five-city

deficits will probably be slightly more than

these theoretical deficits projected by the

Board.

SSOF, SR 158, p. 13.

VI. APPLICAB ATUT RE ATION

As the court stated in its prior review, four statutes

and their implementing regulations are pertinent: The Rivers

45a

and Harbors Appropriation Act of 1899, 33 U.S.C.A. § 403

(1986); the Clean Water Act, 33 U.S.C.A. §§ 1251-1376

(1986); the Water Supply Act of 1958, 43 U.S.C.A. §§

390b-390f (1986); and the National Environmental Policy

Act of 1969 (NEPA); 42 U.S.C.A. §§ 4321-4347 (1977).

Pursuant to section 10 of the Rivers and Harbors Act of

1899, 33 U.S.C.A. §403 (1986), the Corps of Engineers is

responsible for evaluating proposed construction projects in

the navigable waters of the United States. seo 404 of the

Clean Water Act, 33 U.S.C.A. § 1344 (1986), gives the

Corps jurisdiction to issue permits for the discharge of

dredged or fill materials into the navigable waters of the

United States. The Water Supply Act authorizes the Corps

to reallocate water storage in federal reservoirs such as Kerr

Reservoir. 43 U.S.C.A. § 39b (1986). In exercising the

authority granted by these three statutes, the Corps must also

comply with the prerequisites of NEPA.

46a

A. NEPA

Congress enacted NEPA to oblige federal agencies to

consider the environmental consequences of proposed actions

in the decision-making process, thereby insuring "fully

informed and well-considered" decisions. Strycker’s Bay

Neighborhood Council, Inc, v. Karlen, 444 U.S. 223, 228

(1980) (per curiam) (quoting Vermont Yankee Nuclear

wer Vv i .

435 U.S. 519, 558 (1978)). Pursuant to section 102(2)(C)

or the Act, 42 U.S.C.A. § 4332(2)(C), a federal agency has

the duty to prepare a detailed environmental statement,

known as an environmental impact statement (EIS), on every

major federal action significantly affecting the quality of the

human environment. In order to determine which actions

trigger this provision, the Corps has promulgated regulations

to implement NEPA, 33 C.F.R. pt. 230 (1986). The Corps

is Simultaneously governed by the Council on Environmental

Quality (CEQ) regulations construing and implementing

47a

NEPA, 40 C.F.R. pis. 1500-1508 (1986).

These implementing regulations outline Corps

procedure for evaluating a proposal. Before issuing a permit

the Corps must prepare an environmental assessment (EA) to

determine whether the proposed action would significantly

affect the quality of the human environment, thereby

requiring preparation of a comprehensive EIS. 33 C.F.R.

pt. 230, app. B(8)(a). Typically, the EA is a brief

evaluation, normally not exceeding fifteen pages, of the

likely environmental effects of a proposal, the need for and

the alternatives to the proposed action. 33 C.F.R. §230.9(c)

and 33 C.F.R. pt. 230, app. B(8)(a). When the district

engineer concludes that a project will not significantly affect

the quality of the human environment, he must prepare a

FONSI presenting the reasons for this conclusion. 33

C.F.R. § 230.10 and 33 C.F.R. pt. 230, app. B(8)(c).

48a

B. | PUBLIC INTEREST REVIEW AND OTHER

CORPS REGULATIONS

In addition to the regulations implementing NEPA,

the Corps has adopted regulations which serve as guidelines

for the evaluation of all regulatory permit applications. 33

C.F.R. pt. 320 (1986). Chief among these regulations in 33

C.F.R. §320.4(a) which requires the Corps to undertake a

general "public interest review" to decide whether a permit

should issue. In this review the Corps must evaluate a

proposal’s overall impact on the public interest, balancing the

"benefits which reasonably may be expected to accrue...

against its reasonably foreseeable detriments." 33 C.F.R.

§ 320.4(a).

The decision whether to issue the permit depends on

the outcome of this balancing of factors. A permit is to be

granted unless the district engineer determines that it will be

contrary to the public interest. 33 C.F.R. §320.4(a)(1).

When the decision on the permit application is made the

49a

district engineer must include the results of his public interest

review in the Statement of Findings, a document which must

be prepared in all permit decisions not requiring preparation

of an EIS. 33 C.F.R. § 325.2(a)(6) (1986).

Vil. CONTENTIONS

Both North Carolina and RRBA devote most of their

arguments to the striped bass issue. Each contends that the

Corps’ analysis is flawed and not supported by expert

opinion. They argue that the Corps failed to utilize data on

a new flow regime using instead an outdated flow regime.

The Corps’ conclusions regarding the effect of fishing on the

striped bass problem are disputed, and the Corps is taken to

task for failing to consider cumulative impacts in its analysis.

- RRBA also contends that the Corps ignored important

findings by the United States Congress. Additionally, both

parties attack the Corps’ determination of the extent of

Virginia Beach’s need.

50a

VIII. STANDARD OF REVIEW

The applicable review standard is found in the

Administrative Procedure Act which provides in pertinent

part:

The reviewing court shall --

(2) hold unlawful and set aside agency

action, findings, and conclusions found to be -

(A) arbitrary, capricious, an abuse of

discretion, or otherwise not in accordance

with law;

(D) without observance of procedure

required by law.

5 U.S.C.A. § 706(2)(A) & (D) (West 1977). An

interpretation of this standard must begin with the Supreme

Court’s decision in Citizens to Preserve Overton Park, Inc.

v. Volpe, 401 U.S. 402 (1971). In Overton Park the

Supreme Court made clear that the court’s obligation

pursuant to this statute is twofold. The court must consider,

Sla

first, whether the agency acted within the scope of its

authority, and second, whether the actual choice made by the

agency was arbitrary, capricious, an abuse of discretion, or

otherwise not in accordance with law. To make this finding

the court must consider whether the decision was based on a

consideration of the relevant factors and whether there was

a clear error of judgment. This standard of review is highly

differential and the agency decision is "entitled to a

presumption of regularity." Overton Park, 401 U.S. at 415.

The agency must examine the relevant data and

articulate a satisfactory explanation for its action, including

a "rational connection between the facts found and the choice

made." man_T ] Vv nsas-

Freight Systems, Inc., 419 U.S. 281, 285 (1974), reh’g

denied, 420 U.S. 956 (1975) sniiiities a

Lines, Inc. v. United States, 371 U.S. 156, 168 (1962)).

Furthermore, the court may not supply a reasoned basis for

the decision that the agency has not given. Bowman

52a

Transportation, 419 U.S. at 285-86. In Motor Vehicles

Mutual Auto Insurance Co., 463 U.S. 29 (1983), the court

said:

[A]n agency rule would be arbitrary and

capricious if the agency has relied on factors

which Congress has not intended it to

consider, entirely failed to consider an

important aspect of the problem, offered an

explanation for its decision that runs counter

to the evidence before the agency, or is so

implausible that it could not be ascribed to a

difference in view or the product of agency

expertise.

Id. at 43.

In reviewing whether the agency has complied with

the requirements of NEPA, the only role for the court is to

insure that the agency has taken a "hard look" at the

environmental consequences; it cannot "interject itself within

the area of discretion of the executive as to the choice of the

action to be taken." Kleppe v. Sierra Club, 427 U.S. 390,

410 n. 21 (1976). In enacting NEPA, Congress did not

53a

require agencies to elevate environmental concerns over other

appropriate considerations. Baltimore Gas & Electric Co. v.

Natural Resources Defense Council, Inc., 462 U.S. 87

(1983). In applying the arbitrary and capricious standard to

NEPA determinations, the court must engage in a substantial

inquiry to determine whether the agency, in its conclusions,

made a good faith judgment, after considering all relevant

factors, including possible alternative or mitigative measures.

lien tr 2 thle Besicast Dew ‘

Coleman, 555 F.2d 398 (4th Cir. 1977). In passing on the

good faith issue, ihe court may not substitute its judgment for

that of the agency but must only look to see if the official or

agency too a hard look at all relevant factors. In considering

alternatives, the agency need only set forth those alternatives

sufficiently so as to permit a reasoned choice. Coleman, 555

F.2d at 400.

54a

IX. ANALYSIS

A. EFFECT OF THE PROJECT ON

STRIPED BASS

i. The Effect of River Flow

Plaintiffs contend that the conclusions reached by the

Corps are at odds with the conclusions of the National

Marine Fisheries Service (NMFS), the U.S. Fish and

Wildlife Service (USFWS), the North Carolina Wildlife

Resources Commission (NCWRC) and the North Carolina

Division of Marine Fisheries (NCDMF), all of whom

submitted comments to the Corps. Plaintiffs further contend

that the Corps’ analysis is flawed because it used the "old

flow regime” instead of a new one. The “flow regime”

refers to the flow at the Roanoke Rapids Dam during the

spawning season which, as noted earlier, is a period of time

when the FERC mandated flow is highest and the flow is

augmented by the additional water provided under the MOL.

Plaintiffs contend that this regime is outdated and needs to be

55a

changed. Indeed, such is the argument of officials from the

four agencies named above, a fact acknowledged by the

Corps.

After remand of the matter to the Corps in 1987, the

Roanoke River Water Flow Committee (committee) was

formed. The committee consists of representatives of the

four wildlife agencies, a representative from the North

Carolina Department of Agriculture and fisheries biologists

from North Carolina State University and East Carolina

University. Apparently, none of the Corps’ experts were

asked to serve as members of the committee, although a

representative from the Corps was asked to, and did, serve

as an "advisor" to the committee. This committee collected

data and concluded that the 1981 flow regime was inadequate

and that flows much greater than the 2,000 cfs FERC

minimum are necessary before the beginning of the spawning

season in order to attract mature bass to the spawning

grounds and to provide satisfactory conditions for the growth

56a

of plankton, the food source for young striped bass. In

addition, the committee concluded that increased flows are

necessary during the spawning season to stimulate the fish to

release their eggs and after spawning season to transport eggs °

and larvae to their feeding grounds. These findings led the

committee to conclude that an increased period of augmented

flow was necessary. Its first recommendation was for

augmented flow for a period of 122 days between 1 March

and 30 June, ranging from 7543 cfs in March to 3058 cfs at

the end of June. After consultation with the Corps and

VEPCO, however, these dates and rates of flow were revised

downward to provide for lower flows for a shorter period of

time.

In the SSOF, Colonel Thomas made note of and

commented upon submissions of the committee and the

various agencies and acknowledged that "different

conclusions can and have been reached from the same raw

data.” He agreed with some conclusions by the committee

57a

and disagreed with others. Important to this analysis is the

fact that he considered all conclusions. Nothing more was

required. The fact that the Corps did not change its decision

based on those conclusions does not make the decision

arbitrary or capricious. The court finds the Corps’ decision,

in this respect, to be in accordance with the requirements of

the law. The court is particularly impressed with the fairness

-- the lack of arbitrariness -- in the Corps’ treatment of each

contention advanced by plaintiffs based on work of the

committee. This treatment is especially commendable in

view of the fact that those who formed the committee did not

show the same courtesy to the Corps, either in the formation

of the committee or in its functioning. The formation of a

committee of "experts" to deal with a question of the flow’

of water in a river without inviting the Corps, the

9 Even the name of the committee, The Roanoke River Water Flow

Committee, suggests that its primary function is to deal with the flow of

water in the Roanoke River!!

58a

acknowledged "expert" in such matters, raises some doubt

about the impartiality of the committee and the credibility of

its findings. The timing of the committee’s formation

increases those doubts.

Casting aside any doubts arising out of formation of

the committee, however, the court is impressed with the

thoroughness and impartiality of the Corps’ analysis.

Especially when given the presumption of regularity to which

the Corps’ decision is entitled, see Overton Park, 401 U.S.

at 415, the court is convinced that the Corps has adequately

examined the data and articulated a satisfactory explanation

for its decision.

: There can be no doubt that the flow of the Roanoke

River, especially at the Roanoke Rapids Dam, has some

effect on the success or failure of the reproduction of striped

bass. If this valuable resource is to survive, and particularly

if it is to regain its former population level, the best efforts

of all interested parties, including state and federal agencies,

59a

must be asserted. Those efforts have been going on for

many years now and they must continue. The court hopes

that one benefit of this massive and time-consuming lawsuit

will be to focus increased attention on the importance of this

natural resource. Interruptions in the delicat. balances of

nature, whether through pollution, use and abuse of resources

such as water, or through other causes, invariably take a

heavy toll on natural resources, particularly fish and wildlife.

Separate and apart from the work of the committee,

plaintiffs contend that the Corps erred by not accepting the

recommendations of the four expert agencies most directly

concerned with strived bass, USFWS, NMFS, NCDMF and

NCDWR, all of whom expressed the view that a full

environmental impact study should be conducted and an EIS

prepared.'° As noted in this court’s prior opinion, Corps

10 It is at least questionable whether this view prevails when the

mitigation requirement is considered as only one of the agencies,

USFWS, addressed mitigation. SR 102, pp.3-4.

60a

regulations require consultation with these agencies and

accord "great weight” to their views. With good reason,

however, nothing in the regulations, the statutes, or the cases

interpreting either requires the Corps to follow the views of

such agencies. Such a requirement would give the agencies

veto power over Corps decisions. Sierra Club v. Callaway,

499 F.2d 982 (Sth Cir. 1974). In making decisions affecting

specific natural resources it is to be expected that the Corps

should be required to consult with experts in the field and

seriously consider their views. The final decision remains,

as it must, for the Corps.

2. The Effect of Fishing

In its analysis of the decline of the striped bass

population, the Corps considered the effect of fishing and

concluded that overfishing was a significant factor. Plaintiffs

contend that the Corps’ analysis was flawed and that the

effect of fishing was not appropriate for consideration in the

6la

SEA. However, as the Corps said in its SSOF:

The court directed the Corps to address the

effects of the City’s project on striped bass.

Several factors affect, or may affect, the

Roanoke/Albemarle striped bass: recruitment,

natural mortality, fishing mortality, flow,

water quality, etc. Thought of as an equation

with many variables, it is exceedingly difficult

to find the result of altering one variable

without knowing something about the other

variable.

SSOF, SR 158, p.7. The court concurs and feels confident

that had the Corps not considered fishing mortality as well as

the other variables, plaintiffs would now be citing that failure

in support of their position in this case.

Plaintiffs particularly object to the Corps’

consideration of a document of the Atlantic States Marine

Fisheries Commission (ASMFC) contending that it was only

a draft document by a subcommittee of the commission

whose findings have been cast into doubt by later data.

ASMFC has been studying the major striped bass populations

along the East Coast for many years and a subcommittee has

62a

been studying fishing mortality which is defined as "the

measure of that portion of a population which is lost due to

fishing, as opposed to natural mortality (predation, disease,

etc.)." SEA, SR 157, p.10.

USFWS and NMFS disagreed with the findings of the

subcommittee of ASMFC and communicated their opinions

to the Corps. Their disagreement was based, in large

measure, on the successful 1988 spawning season.

Colonel Thomas, in his analysis, recognized that the

document was a draft report of a subcommittee so neither

plaintiffs nor this court have been deceived. In addition, he

considered the opinions of USFWS and NMFS and

concluded in his SSOF that the earlier analysis in the SEA

was correct and that "it [is] unlikely that any improvement in

environmental conditions would substantially improve striped

bass recruitment until the overfishing problem has been

remedied.” SSOF, SR 158, p.7. The court is unable to say

that the Corps’ finding in this respect, or the analysis leading

63a

to it, was arbitrary or capricious.

3. Cumulative Impacts

Plaintiffs complain that the Corps did not consider the

cumulative impacts of potential future uses of the river, such

as municipal, industrial and agricultural withdrawals, on

striped bass. In its first consideration of this matter the

Corps considered other potential uses of the Roanoke River

as they might impact on river flow. The court, in its initial

review, found this part of the Corps’ decision not to be

arbitrary or capricious. Furthermore, the remand order was

specific as to the scope of the additional review required and

it did not include cumulative impacts of potential future uses.

Finally, such future uses remain now, as they did at the first

review, entirely speculative.

4. Congressional Findings

RRBA contends that the Corps ignored important

congressional findings when analyzing the effects of the

project on striped bass. The basis of this contention is a bill

passed by Congress reauthorizing appropriations to

implement the Atlantic Striped Bass Conservation Act. 16

U.S.C.A. § 1851 (West 1985) (the Act). The Act, P.L.

100-589, 102 Stat. 2984 (Nov. 3, 1988), appropriated funds

for a period of three years for the continuation of the

activities authorized by the Act. By appropriating these

funds, Congress reiterated concerns which have been known

for decades, such as the fact that the striped bass populations

have been declining and that many factors, including

overfishing and river flow in the spawning grounds, are

thought to be involved. The Act mandates a study in an

effort to find causes for the decline and solutions to the

problem. It is quite obvious that the concerns addressed in

the Act are the same ones addressed by the Corps in its

65a

assessment, and the court finds no deficiency in the decision

of the Corps on this ground.

If this legislation has any significance in the decision

of the court, it lies in what is not said, rather that in what is

said. As is obvious to all, the project underlying this action

is controversial and has involved the political leaders of

Virginia and North Carolina for at least a decade. This

legislation was passed in 1988, well after the court’s July

1987 decision remanding the matter to the Corps for

reconsideration primarily of the striped bass issue. Thus,

when the Act was passed, Congress knew that striped bass,

the subject of the Act, were also the central focus of this

lawsuit. If Congress had intended that a moratorium be

placed on withdrawals from the Roanoke River pending the

study it mandated or that the Corps or this court should

consider such action, it, no doubt, would have expressed its

intent in the Act.

5. Mitigation

As noted, the Corps ordered mitigation measures, as

a precaution, even though it concluded that the project would

have no significant impact on striped bass. North Carolina

argues that even this measure is insufficient because it is

based on the old flow regime and a flawed model. The

Corps demonstrated, however, that the mitigative measures

will result in no impact by the project under either flow

regime or either model.!!

Courts have permitted the effect of mitigation

measures to be considered in determining whether

preparation of an EIS is necessary. Jones v. Gordon, 792

F.2d 821, 829 (9th Cir. 1986). "[W]hen mitigation

measures compensate for otherwise adverse environmental

impacts, the threshold level of ’significant impacts’ is not

'! The "models" referred to are computer models, one constructed

by the Corps’ Wilmington office and the other by Virginia Beach. The

Corps relied primarily on its own model.

67a

reached so no EIS is required.” C,A,R.E, Now, Inc, v.

F.A.A., 844 F.2d 1569, 1575 (llth Cir. 1988), reh’g

denied, 854 F.2d 1326 (llth Cir. 1988) (citing Cabinet

M ns Wild Scotch 's Peak Grizzly B

Peterson, 685 F.2d 678, 682 (D.C. Cir. 1982)). As the

court said in Cabinet Mountains Wilderness:

NEPA’s EIS requirement is governed by the

rule of reason ... and an EIS must be

prepared only when significant environmental

impacts will occur as a result of the proposed

action. If, however, the proposal is modified

prior to impiementation by adding specific

mitigation measures which completely

compensate for any possible adverse

environmental impacts stemming from the

original proposal, the statutory threshold of

significant environmental effects is not crossed

and an EIS is not required. To require an

EIS in such circumstances would trivialize

NEPA and would ‘diminish its utility in

providing useful environmental analysis for

major federal actions that truly affect the

environment.’

685 F.2d at 682 (citations omitted).

Dire consequences, particularly in the river flow, are

forecast by North Carolina in the event of a severe drought.

68a

Whether that forecast or the Corps’ forecast, that the project

will have no impact on the river flow, is correct remains to

be seen. This court is not an expert on that subject. Neither

is North Carolina. The Corps is. And it is to the Corps that

the Congress has entrusted the final decision. This court’s

sole function is to review the Corps’ decision under the

standard herein set out. Having done so, the court is

convinced that the decision, insofar as it deals with striped

bass, is not arbitrary and capricious. This is especially true

considering the mitigative measure which was ordered.

B. VIRGINIA BEACH’S NEED

Plaintiffs contend that the Corps has not complied

with the court’s mandate to assess Virginia Beach’s need.

Specifically, they contend that pcpulatio: projections which

have been used are too high and that other sources of water

have not been adequately factored into the equation. The

court disagrees. This court’s 1987 Opinion upheld as

69a

reasonable the Corps’ determination that ‘Virginia Beach had

a need for water and remanded only for a determination of

the extent of that need. Upon remand the Corps sought input

from all interested parties and all available sources. Its

analysis of the projections of the amount of water Virginia

Beach will need in 2030 and the amount which will be

available may be flawed in some respects but is not arbitrary

or Capricious. Indeed, this court is convinced that 60 mgd

in 2030 may be insufficient to meet the city’s need after

considering all other reasonably foreseeable sources of water.

As Colonel Thomas stated:

I am convinced that there will never be a

consensus among experts, much less among

those willing to offer an opinion, as to the

extent of Virginia Beach’s water needs. A

cynic would say, ad hominem, that North

Carolina and RRBA, as plaintiffs, are

underestimating the need and Virginia Beach,

as defendant, is overestimating it and, in fact

those parties have said just those things about

each other. It is not sufficient to merely

select a figure in the middle, though, because

potable water is vital to human health and

welfare and such decisions must not be made

70a

so lightly.

SSOF, SR 158, pp.12-13. Colonel Thomas then very

carefully analyzed the available information and contentions

and conciuded that "Virginia Beach needs this 60 mgd

project.” He reached this conclusion only after a searching

analysis which complies with the requirement of an

assessment of the public need for the project.

IX. CONCLUSION

As noted in this court’s earlier opinion, the center of

the controversy here is the interbasin transfer of water. The

controversy is not state against state,'’* but basin against

'2 Such clashes are common within the State of North Carolina

where fourteen interbasin transfers now divert about 40 mgd. One such

dispute currently exists over the proposal of two Wake County towns,

Cary and Apex, to withdraw water from Lake Jordan, in the Cape Fear

Basin, and discharge it into the Neuse River Basin. The News and

Observer, Raleigh, N.C., January 15, 1990, at 1B. Such transfers have

served as a “'lightning rod for disputes among water users in North

Carolina and elsewhere.’” Id. (quoting from the fall issue of Popular

Government magazine, a publication of the Institute of Government,

Chapel Hill, North Carolina).

Tila

basin, the James River Basin against the Roanoke River

Basin. This point is borne out by the fact that many of the

plaintiffs are residents of the State of Virginia. The State of

North Carolina is lead plaintiff but only because more of its

citizens are involved.

It is quite natural for citizens to be concerned with the

withdrawal of water from the basin in the area in which they

live for use in another place. Interbasin transfer not only

eliminates the availability of the water from the basin but it

also has the potential to increase the degree of pollution of

the water remaining in the basin. Nevertheless, whether to

permit interbasin transfer of water is essentially a political

decision.

Water is a necessity of life. It is a valuable resource

which must be protected and conserved and shared by all.

Congress has long recognized the importance of this natural

resource and has passed many acts, some of which are

relevant to this litigation, to conserve it and regulate its use.

72a

Primary responsibility for enforcement and implementation

of the legislation pertinent here lies with the Corps. It has

discharged that responsibility and concluded that the City of

Virginia Beach should be allowed to withdraw up to 60 mgd

from Lake Gaston. This court’s review disclosed that, in

reaching its decision, the Corps has taken a "hard look” at

the environmental consequences, including the potential

effect on striped bass. Kleppe, 427 U.S. at 410. The

Corps’ decision will be upheld. An appropriate order will

issue.

This 2 February 1990.

W. EARL BRITT

United States District Judge

73a

APPENDIX C

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF NORTH CAROLINA

RALEIGH DIVISION

No. 84-36-CIV-5

STATE OF NORTH CAROLINA,

et al.,

plaintiffs,

V. ORDER

COLONEL RONALD E. HUDSON,

et al.,

defendants.

In accordance with the memorandum opinion of even

date herewith, the decision of the United States Army Corps

of Engineers to issue a permit to the City of Virginia Beach,

Virginia, to construct a water intake structure and pipeline in

Lake Gaston to extend to Suffolk, Virginia, and to enter into

a water storage reallocation contract for Kerr Reservoir on

behalf of the United States with the City of Virginia Beach

are affirmed.

This 2 February 1990.

W. EARL BRITT, United States District Judge

74a

APPENDIX D

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF NORTH CAROLINA

RALEIGH DIVISION

No. 84-36-CIV-5

STATE OF NORTH CAROLINA,

et al.,

Plaintiffs,

Vv. MEMORANDUM

PINION

COLONEL RONALD E. HUDSON,

et al.,

Defendants.

This action seeks judicial review of two decisions of

the United States Army Corps of Engineers: (1) to issue a

permit to the City of Virginia Beach, Virginia, nder section

10 of the Rivers and Harbors Appropriation Act of 1899, 33

U.S.C.A. § 1344 (West 1986), to construct a water intake

structure and pipeline in Lake Gaston to extend to Suffolk,

Virginia; and (2) to enter into a water storage reallocation

contract for Kerr Reservoir on behalf of the United States

75a

with the City of Virginia Beach pursuant to the Water Supply

Act of 1958, 43 U.S.C.A. § 390b (West 1986). Plaintiffs,

the State of North Carolina, the Roanoke River Basin

Association (RRBA), four counties located in Virginia and

eight counties located in North Carolina, challenge the

issuance of the permit, contending that it violates the

National Environmental Policy Act (NEPA) of 1969, 42

U.S.C.A. §§ 4321-4347 (1977), the Clean Water Act of

1977, the Rivers and Harbors Appropriation Act of 1899,

the Coastal Zone Management Act, 16 U.S.C.A. §§ 1451-

1464 (West 1985), the Water-Supply Act and the various

federal regulations implementing those statutes. Plaintiffs

allege that the contract was executed in violation of NEPA,

the Water Supply Act, the Clean Water Act and their

implementing regulations. Plaintiffs ask the court to declare

the pipeline construction permit and water supply contract

void and remand the case to the Corps, with directions that

before issuing any new permit or entering into any new water

76a

supply contract the Corps must (1) prepare an environmental

impact statement (EIS) pursuant to section 102(2)(C) of

NEPA and (2) conduct a meaningful public interest review

pursuant to 33 C.F.R. § 320.4 (1986).

A hearing was held on 7 November 1986 on the

parties’ motions for summary judgment, and the case is now

ripe for final disposition on the merits.

I. FACTS AND PRIOR PR DI

The City of Virginia Beach, Virginia (Virginia

Beach), now the largest in the state, is located on the

Atlantic Ocean and in close proximity to other large bodies

of water, such as Chesapeake Bay and the James River. Yet

it suffers from a lack of an adequate supply of potable water

to meet the needs of its citizens. Until recently when five

wells were constructed for contingency use in the event of an

T7a

emergency,' it depended entirely on the City of Norfolk for

its water. The need for water has been especially acute in

times of drought, and on at least three occasions in the last

decade droughts have brought hardship on the citizens and

the implementation of conservation measures, including

rationing. Seeking a permanent solution to its problem,

Virginia Beach engaged in studies of its own and participated

in joint studies with others. Every conceivable source,

including desalting, wastewater reuse, groundwater, lakes

and rivers, was explored before the City decided that its best

alternative for a reliable source was Lake Gaston in the

Roanoke River Basin.

The Roanoke River has its headwaters in the

mountains of Virginia, near the City of Roanoke. It flows

southeasterly, crossing the North Carolina border between

! The wells were constructed following the drought of 1980-81 and

are located within other municipal jurisdictions, Suffolk, Isle of Wight

County and Southampton County. They are intended fo. use only in the

event of an emergency, and their use reverts to the municipalities in

which they lie after contract periods of ten to fifteen years.

78a

linemen

Bracey, Virginia, and Gaston, North Carolina, and empties

into the Albemarle Sound near Plymouth. Over the years

several dams have been constructed on the river for fiood

control and hydroelectric purposes. This has resulted in

several lakes, including Smith Mountain, John H. Kerr,”

Gaston and Roanoke Rapids.

On 15 July 1983 Virginia Beach applied to the

Norfolk District of the Army Corps of Engineers for a

permit to construct a water intake structure, pier, boathouse

and ramp in the Pea Hill Creek tributary of Lake Gaston

located in Brunswick County, Virginia, and a sixty-inch

inside diameter concrete pipe to extend to the City of

Norfolk’s water transport and treatment facilities located in

Suffolk, Virginia, a distance of approximately 84.5 miles.?

The pipeline was proposed to withdraw and transport up to

2 Also known as Buggs Island.

> The City of Norfolk would continue to treat the water derived

from the new source.

79a

a total of sixty million gallons per day (mgd) of water by the

year 2030. Under the- proposal forty-eight mgd would

ultimately be treated for the use of Virginia Beach, ten mgd

for Chesapeake, one mgd for the Isle of Wight County, and

one mgd for Franklin. As part of its application Virginia -

Beach submitted an environmental study prepared by its

consultants intended to assess the probable environmental

impacts of the proposed project and evaluate dereatves to

the proposal.

Over the next several months approximately 6,000

people attended three public hearings in North Carolina and

Virginia where substantial oral and written comments were

presented expressing both support for and opposition to the

proposed project.* On 11 October 1983 the Norfolk District

Corps issued a draft environmental assessment (EA) and a

4 The first hearing was held in Lawrenceville, Virginia, on 25

August 1983 before the issuance of the draft EIS and draft FONSI. The

other two, at Roanoke Rapids, North Carolina, on 14 November 1983

and Virginia Beach, Virginia, on 17 November 1983, were held before

the issuance of the final EIS and final FONSI.

80a

preliminary finding of no significant impact (FONSI) for

public review and comment. On 7 December 1983 the

Corps issued its final EA and FONSI which concluded that

the project would have no significant environmental impacts

and therefore preparation of an EIS was not required by

NEPA. Consistent with Corps regulations a thirty-day public

comment period, which expired on 6 January 1984, was

announced. Comments were received by the Corps in

response to the final EA and FONSI, including comments

submitted by North Carolina and RRBA. On 9 January 1984

the Norfolk District Engineer signed and issued a permit to

Virginia Beach. At the same time he issued a Statement of

Findings (SOF) addressing comments on the EA and FONSI.

Meanwhile, the Wilmington District Corps was

considering a request by Virginia Beach to enter into a water

supply contract pursuant to the Water Supply Act of 1958 to

reallocate storage in Kerr Reservoir from power supply to

water supply. The contract was proposed to reallocate to

8la

Virginia Beach 10,200-acre feet of water storage space in

Kerr Lake which Virginia Beach could require the Corps to

release into Lake Gaston to offset the withdrawal from Lake

Gaston. On 13 January 1984 the Wilmington District

Engineer adopted the EA prepared by the Norfolk District

Engineer and issued a FONSI which concluded that no

significant environmental impacts would result from the

proposed reallocation and therefore an EIS was not required

by NEPA. On 12 January 1984 the City signed the contract

which was approved by the Assistant Secretary of the Army

for Civil Works on 30 January 1984.

On 12 January 1984 the State of North Carolina filed

this suit against Colonel Ronald E. Hudson, District Engineer

for the Norfolk District of the Corps of Engineers; Colonel

Wayne A. Hanson, District Engineer of the Wilmington

District of the Corps of Engineers; Lieutenant General Joseph

K. Bratton, the Chief of Engineers of the Corps of

Engineers; William R. Gianelli, Assistant Secretary of the

82a

United States Department of the Army; and, John O Morris,

Jr., Secretary of the United States Department of the Army.

All defendants are sued in their official capacities. The

complaint alleges that issuance of the pipeline construction

permit was arbitrary and capricious and in violation of

NEPA, the Clean Water Act, the Rivers and Harbors Act,

the Coastal Zone Management Act, the Water Supply Act,

and the federal regulations implementing those acts. On 20

June 1984 the court allowed RRBA, eight counties in North

Carolina and four counties in Virginia to intervene as

plaintiffs. The counties filed a single complaint which

mirrors that of the State of North Carolina.’ RRBA’s

complaint in intervention challenges the issuance of the

pipeline construction permit and also challenges execution of

the water storage reallocation contract between the United

States and Virginia Beach. On 3 December 19854 North

* Hereinafter, references to North Carolina refer to the joint

positions of North Carolina and the twelve counties.

83a

Carolina was allowed to amend its complaint to also

challenge execution of the water storage contract. On 4

December 1985 Virginia Beach was allowed to intervene as

a part defendant.

Meanwhile, on 9 January 1984, Virginia Beach

initiated an action in the Eastern District of Virginia (the

Virginia Beach action) against RRBA and the Governor of

North Carolina seeking a declaratory judgment that the

permit and contract were valid. The governor of North

Carolina moved to dismiss for lack of personal jurisdiction.

The district court held that the governor was amenable to

service of process pursuant to the Virginia long-arm statute,

Va. Code § 8.01-328.1 (Repl. Vol. 1984). An interlocutory

appeal was taken to the United States Court of Appeals for

the Fourth Circuit which ruled that the Virginia long-arm

Statute conferred no jurisdiction for assertion of plaintiffs’

claims over the Governor of North Carolina. City of

Vicsinie Reach vy. Bosncies Bier Botte Ageeciation 716

84a

F.2d 484 (4th Cir. 1985). The court ruled that Virginia

Beach should be given an opportunity to transfer that case to

the Eastern District of North Carolina. On 14 November

1985 Virginia Beach’s motion to transfer was allowed, and

the case became Civil Action No. 85-1625-CIV-5 in this

court. On 2 December 1985 Virginia Beach moved to

consolidate the two actions and to realign the parties

according to their interest. On 17 December 1985 the

motion was denied inasmuch as Virginia Beach had already

intervened in this action and the claims and parties in each

case were identical. The Virginia Beach action was

dismissed, but all discovery previously conducted was made

a part of this action.

On 12 December 1985 the Corps of Engineers filed

the administrative record with the court. On 17 December

1985 the court suspended all discovery and ruled that judicial

review of the Corps’ actions would be confined to the

administrative record consistent with the Administrative

85a

Procedure Act, 5 U.S.C.A. § 706(2)(A) (West 1977).

Disputes concerning the contents of the record were resolved

by the 28 March 1986 order of the court which allowed

limited supplementation of the record.

Virginia Beach has subsequently submitted a

"Supplement to Virginia Beach’s Response to Plaintiffs’

Motions for Summary Judgment” in which it asks the court

to consider Midkiff Affidavit, Exhibit G, an exhibit which is

not part of the administrative record, for the limited purpose

of impeaching arguments made by North Carolina and

RRBA. The _motion is denied. RRBA’s motion to

supplement the record with the same exhibit is also denied.

Il. APPLICABLE STATUTES AND REGULATIONS

Four statutes and their implementing regulations are

pertinent in this judicial review proceeding: The Rivers and

Harbors Appropriation Act of 1899, 33 U.S.C.A. § 403

(1986); the Clean Water Act, 33 U.S.C.A. §§ 1251-1376

86a

(1986); the Water Supply Act of 1958, 43 U.S.C.A. §§

390b-390f (1986); and the National Environmental Policy

Act of 1969 (NEPA), 42 U.S.C.A. §§ 4321-4347 (1977).

Pursuant to section 10 of the Rivers and Harbors Act of

1899, 33 U.S.C.A. § 403 (1986), the Corps of Engineers is

responsible for evaluating proposed construction projects in

the navigable waters of the United States. Section 404 of the

Ciean Water Act, 33 U.S.C.A. § 1344 (1986), gives the

Corps jurisdiction to issue permits for the discharge of

dredged or fill materials into the navigable waters of the

United States. The Water Supply Act authorizes the Corps

to reallocate water storage in federal reservoirs such as Kerr

Reservoir. 43 U.S.C.A. § 390b (1986). In exercising the

authority granted by these three statues, the Corps must also

comply with the prerequisites of NEPA.

A. NEPA

Congress enacted NEPA to oblige federal agencies to

consider the environmental consequences of proposed actions

87a

in the decision-making process, thereby insuring "fully

informed and well-considered"” decisions. Stryker’s Bay

Neighborhood Council, Inc. v. Karlen, 444 U.S. 223, 228

(1980) (per curiam), quoting Vermont Yankee Nuclear

435 U.S. $519 (1978). Pursuant to section 102(2)(C) of the

Act, 42 U.S.C.A. § 4332(2)(C), a federal agency has the

duty to prepare a detailed environmenta. statement, known as

an environmental impact staiement (EIS), on every major

tederal action significantly affecting the quality of the human

environment. In order to determine which actions trigger

this provision, the Corps has promulgated regulations to

implement NEPA, 33 C.F.R. pt. 230 (1986). The Corps is

simultaneously governed by the Council on Environmental

Quality (CEQ) regulations construing and implementing

NEPA, 40 C.F.R. pts. 1500-1508 (1986).

88a

These implementing regulations outline Corps

procedure for evaluating a proposal. Before issuing a permit

the Corps must prepare an environmental assessment (EA) to

determine whether the proposed action would significantly

affect the quality of the human environment, thereby

requiring preparation of a comprehensive EIS. 33 C.F.R.

pt. 230, app. B(8)(a). Typically the EA is a brief

evaluation, normally not exceeding fifteen pages, of the

likely environmental effects of a proposal, the need for and

the alternatives to the proposed action. 33.¢c.F.R. § 230.9(c)

and 33 C.F.R. pt. 230, app. B(8)(a). When the district

engineer concludes that a project will not significantly affect

the quality of the human environment, he must prepare a

FONSI presenting the reasons for this conclusion. 33

C.F.R. § 230.10 and 33 C.F.R. pt. 230, app. B(8)(c).

Section 102(2)(E) of NEPA, 42. U.S.C.A.

§ 4332(2)(E), requires the federal agency to "study, develop

and describe appropriate alternatives” to recommended

89a

courses of action in any proposal involving unresolved

conflicts concerning alternative uses of available resources.

This provision is independent of the standard triggering

preparation of an EIS and is not limited to proposed major

actions significantly affecting the quality of the human

environment. River Road Alliance, Inc. v. Corps of

Engineers of United States Army, 764 F.2d 445 (7th Cir.

1985), cert. denied, U.S. ___, 106 S.Ct. 1283 (1986);

City of New York v ni ment_of

Transportation, 715 F.2d 732 (2d Cir. 1983), cert. denied,

465 U.S. 1055 (1984). However, the smaller the impact of

the proposed action, the less extensive the search for

alternatives is to be expected of the agency. River Road

Alliance, Inc., 764 F.2d at 452.

B. PUBLIC INTEREST REVIEW

AND OTHER CORPS REGULATIONS

In addition to the regulations implementing NEPA,

the Corps has adopted regulations which serve as guidelines

90a

for the evaluation of all regulatory permit applications. 33

C.F.R. pt. 320 (1986). Chief among these regulations is 33

C.F.R. § 320.4(a) which requires the Corps to undertake a

general "public interest review" to decide whether a permit

should issue. In this review the Corps must evaluate a

proposal’s overall impact on the public interest, balancing the

"benefits which reasonably may be expected to accrue...

against its reasonably foreseeable detriments." 33 C.F.R.

§ 320.4(a).

In weighing the public interest, the Corps is to

evaluate the following general criteria: (1) the relative extent

of a public and private need for the proposed project; (2)

where there are unresolved conflicts as to resource use, the

practicability of using reasonable alternative locations and

methods to accomplish the objective of the proposed project;

and, (3) the extent and permanence of the beneficial and/or

detrimental effects which the proposed project may have on

the public and private uses to which the area is suited. 33

9la

C.F.R. § 320.4(a)(2). Furthermore, all factors which may

be relevant to the proposal must be considered, including but

not limited to "conservation, economics, aesthetics, general

environmental concerns, wetlands, cultural values, fish and

wildlife values, flood hazards, floodplain values, land use,

navigation, shore erosion and accretion, recreation, water

supply and conservation, water quality, energy needs, safety,

food and fiber production, mineral needs, considerations of

property ownership, and, in general, the needs and welfare

of the people." 33 C.F.R. § 320.4(a)(1).

The decision whether to issue the permit depends on

the outcome of this balancing of factors. A permit is to be

eranted unless the district engineer determines that it will be

contrary to the public interest.° 33 C.F.R. § 320.4(a)(1).

®° This is the current language of the public interest regulation as

amended on October 5, 1984. 49 Fed. Reg. 39478. At the time of the

Corps’ decision the regulation provided that a permit would issue if the

Corps found the project to be in the public interest. 47 Fed. Reg. 31794

at 31804 (July 22, 1982). However, the original and revised regulations

“describe the same public interest balancing process." 49 Fed. Reg.

39478.

92a

When the decision on the permit application is made the

district engineer must include the results of his public interest

review in the Statement of Findings, a document which must

be prepared in all permit decisions not requiring preparation

of an EIS. 33 C.F.R. § 325.2(a)(6) (1986).

Corps regulations require that the district engineer

consult with the directors of the United States Fish and

Wildlife Service, the National Marine Fishery Service and

the agency responsible for wildlife for the state in which the

work is to be performed and accord "great weight" to their

views on fish and wildlife conservation. 33 C.F.R.

§ 320.4(c); Hough v. Marsh, 577 F. Supp. 74, 81 (D.Mass.

1982). Also the district engineer must consider all comments

received in response to public notice regarding the permit

application. 33 C.F.R. § 325.2(a)(3). Due consideration

must also be given to the official views of the state, regional

or local agencies having an interest over the particular

activity as "a reflection of local factors of the publi

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Petition for Writ of Certiorari — Roanoke River Basin Ass'n v. Hudson · 502 U.S. 1092 | Frix