Petition — Paducah Associates, Ltd. v. Indiana Insurance
Supreme Court brief1981
Ask Donna
What actually matters in this document.
Text
MAR 413 j98)
ALEXANDER L. STEVaS. |
CLERK
tens teeat
No.
In the Supreme Court of the United States
October Term, 1980
PADUCAH ASSOCIATES, LTD.,
Petitioner,
VS.
INDIANA INSURANCE COMPANY
and
ALL PRIDE DEVELOPMENT CORPORATION,
Respondents.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
Dona.p D. WEINSTEIN (Counsel of Record)
and
BERNARD L, BALKIN
A. MorGAN HICKENLOOPER of
SANDLER, BALKIN, HELLMAN & WEINSTEIN
Professional Corporation
3130 Broadway, Third Floor
Kansas City, Missouri 64111
Telephone: (816) 753-3525
Counsel for Petitioner
March 13, 1981
E. L. Menvenwatt, INc., 926 Cherry Street, Kansas City, Mo. 64106, (816) 421-3030
QUESTIONS PRESENTED
1. Whether arbitrators acting under a binding ar-
bitration clause in a construction contract may, with agree-
ment of the parties, reserve issues from their award, leav-
ing to the parties the right to assert such issues before a
Federal District Court independent of the award.
2. Whether a judgment entered by a Federal District
Court in an arbitration award confirmation action pur-
suant to The Federal Arbitration Code is binding upon
the parties thereto such that an issue there determined
may not be relitigated or form the basis for a conflicting
summary judgment in a subsequent action between the
Same parties on the same subject matter before a second
District Court because of the doctrines of res judicata and
law of the case.
3. Whether a federal District Court may grant sum-
mary judgment under Federal Rules of Civil Procedure
Rule 56 on the basis of a claim of a contractual waiver of
a claim before an arbitration board, when there is a gen-
uine issue of fact that there was no such waiver.
4. Whether summary judgment which results in for-
feiture of a claim is the appropriate form of relief under
The Federal Arbitration Code with regard to a claim
which may be arbitrable under a written arbitration agree-
ment, but which comes before a United States District
Court without having been first submitted to arbitration.
ITI
TABLE OF CONTENTS
1. Questions Presented oo... ccocccccececeeeeeeeeeecoeccee I
2. Table of Contents o.........o.n.c.ccccceccccccccechccsoesecoceseseeseses III
3. Table of Authorities 20.0.0... ccccccccccccccecceceeeeceseeeeen., V
4. Opinions Below 20000000000... aceaehieeaeenaemenacaatie 2
I I cs cscsspanennnnsroserannaummraceccevese 2
6. Statutory Provisions and Rule of Civil Procedure
ee 2
7. Statement of Case—
a. Contract and Initial Suit by Paducah ........ 3
b. Proceedings Before Board of Arbitrators... 4
c. Confirmation of Arbitration Award ............ 6
d. Proceedings Subsequent to Confirmation... 6
e. Proceedings Before the Circuit Court of
SI eee ee 8
8. Reasons for Granting Writ—
1. The Decision of the Court of Appeals for
the Sixth Circuit Conflicts With Decisions
by Other Circuit Courts Regarding Waiver
of Arbitration and Regarding the Power of
Arbitrators to Reserve Questions for Sub-
Bequent Litigation ..................-cccacecsecceccsecsesee 9
2. The Decision Below Raises a Significant
Question Regarding the Application of the
Federal Arbitration Code Which Should
Be Resolved by This Court 0.0.0.0... 12
3. The District Court Below Has So Far
Departed From the Accepted and Usual
Course of Judicial Proceedings As to Call
for an Exercise of This Court’s Power of
PIII eden enacsessevenssxinexaucssvaeoencummernteantens 14
PREVIOUS PAGE WAS BLANK
ee I Teta nn yere OF: sR hk et tee 21
1”. Appendices—
a. Order, United States Court of Appeals for
the Sixth Circuit (Affirming District
NNR ects en ren ae Al
b. Memorandum Opinion and Order and
Judgment, United States District Court
for the Western District of Kentucky ........ A3
c. Disposition of Pending Motiens for Sum-
mary Judgment, United States District
Court for the Southern District of Ohio .... All
d. Order, United States Court of Appeals
for the Sixth Circuit (denying rehearing)
senoseailanaanacibeaananeatadldbtigestadd racsegtss ay Saige daiendcnamieateede baci A28
e. Statutory Provisions and Rule of Civil
Procedure Involved o00........cecccececcesecceceesees A29
Table of Authorities
CASES
Almacenes Fernandez, S.A. v. Golodetz, 148 F.2d 625
Se SY eed ee 15
American Locomotive Co. v. Chemical Research Corp.,
171 F.2d 115 (6th Cir. 1948) ooo ccccccccccccccceeeeeeees 15
American Locomotive Co. v. Gyro Process Co., 185
FOG SIG (Gt Cir, 1QGD) onnccincccccccccncncececsccesescocecsvcecssese. 15,17
Brown v. Bridgeport Rolling Mills Co., 245 F. Supp. 41
Oe | __) aaeaeny Re inter eo ee ee 19
Burton-Dixie Corporation v. Timothy McCarthy Con-
struction Co., Inc., 436 F.2d 405 (5th Cir. 1971) ...... 10, 15
Cornell & Co. v. Barber & Ross Co., 360 F.2d 512, 123
Wd. PADD. TOC, BPG (UGOB) nan ccccsensesvocnnsseseseacadeceresecsoeseesce, 17
Vv
Hannevig v. R. W. J. Sutherland & Co., 256 Fed. 445
(2d Cir.), cert. den., 249 U.S. 612 (1919) oo. 17
James L. Saphier Agency, Inc. v. Green, 190 F. Supp.
713 (S.D. N.Y.), aff’d, 293 F.2d 769 (2d Cir. 1961) ... 19
Kentucky River Mills v. Jackson, 206 F.2d 111, 47 A.L.R.
2d 1331 (6th Cir.), cert. den., 346 U.S. 887 (1953) ........ 18
Lundgren v. Freeman, 307 F.2d 104 (9th Cir. 1962) Liotbe ae
Order of Rwy. Conductors and Brakemen v. Clinchfield
R. R. Co., 407 F.2d 985 (6th Cir. 1969) 200. 17
Reid Burton Construction, Inc. v. Carpenters District
Council of Southern Colorado, 614 F.2d 698 (10th
RN SE -Sisitancssbeea ti eemenstiacnivenohieamsaceeceons a oes 10, 15, 17
United States v. U.S. Smelting, Refining & Mining Co.,
SOO WB, BOG (1BGO) nica csccnccsccccsscsececcossacvecsvecseceeenecacensess. 20
U.S. Plywood Corp. v. Hudson Lumber Co., 127 F.
Supp. 489 (S.D. N.Y. 1954) ool cececcceceeceeeeseee. 19
Volunteer Elec. Co-op v. TVA, 139 F. Supp. 22 (E.D.
Tenn. 1954), aff’d per curiam, 231 F.2d 446 (6th Cir.
No.
In the Supreme Court of the United States
October Term, 1980
PADUCAH ASSOCIATES, LTD.,
Petitioner,
VS.
INDIANA INSURANCE COMPANY
and
ALL PRIDE DEVELOPMENT CORPORATION,
Respondents.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
The petitioner, Paducah Associates, Ltd.. respectfully
prays that a Writ of Certiorari issue to review the judg-
ment and opinion of the United States Court of Appeals
for the Sixth Circuit in this proceeding.*
*The names of all parties to this proceeding below appear in
the case caption.
OPINIONS BELOW
The decision of the Court of Appeals, reported at 636
F.2d 1219, appears in full in the Appendix hereto at pages
Al through A2. This decision affirms the decision of
the United States District Court for the Western District
of Kentucky entered September 12, 1978, which District
Court decision has not been reported and appears in the
Appendix hereto at pages A3 through Al0. This petition
also concerns a decision of the United States District Court
for the Southern District of Ohio entered March 14, 1977,
which decision has not been reported and appears in the
Appendix hereto at pages All through A27.
JURISDICTION
The judgment of the Court of Appeals for the Sixth
Circuit was entered on November 13, 1980. A timely Peti-
tion for Rehearing was filed and was denied on December
15, 1980 (Appendix, p. A28), and this petition for a writ of
certiorari was filed within ninety (90) days of that date.
Jurisdiction of this Court is invoked under 28 U.S.C.
§1254(1).
STATUTORY PROVISIONS AND RULE OF
CIVIL PROCEDURE INVOLVED
This case involves construction and application of 9
U.S.C. $§3, 9, 10 and 11, portions of the Federal Arbitration
Code, and Rule 56, Federal Rules of Civil Procedure.
The full text of the above-cited provisions are printed
in the Appendix hereto at pages A29 through A34.
STATEMENT OF THE CASE
This case arises out of a dispute involving a construc-
tion contract between Paducah Associates, Ltd., petitioner
herein and appellant and plaintiff below (hereinafter called
“Paducah”) and All Pride Development Corporation, re-
spondent herein and appellee and defendant below (here-
after called “All Pride’). Indiana Insurance Company,
respondent herein and appellee and defendant below (here-
after called “Indiana’’) was surety under a contract bond
in which All Pride was principal and Paducah was obligee
pursuant to All Pride’s contract with Paducah. This dis-
pute has passed through five distinct phases, each of which
must be discussed in some detail to provide an adequate
understanding of this somewhat complex case.
The Contract and Initial Suit by Paducah
Paducah, a Kentucky Limited Partnership, filed suit
on August 19, 1974, in McCracken Circuit Court, McCracken
County, Kentucky against All Pride and Indiana, both
Indiana corporations. In its pleading, Paducah alleged
that it had entered into a contract with All Pride on
October 10, 1973, whereby All Pride was to provide the
labor and material necessary to perform the on-site con-
struction of a motel in Paducah, Kentucky, in accordance
with certain plans and specifications. Paducah further
alleged that as a condition of this contract, All Pride
secured, from Indiana, a contract bond naming All Pride
as principal, Paducah as obligee, and Indiana as surety,
which bond was to indemnify Paducah against loss or
damage arising by reason of the failure of All Pride to
perform the construction contract. Paducah further al-
leged that All Pride defaulted in performance of the con-
struction contract and that Indiana, as surety, undertook
4
to provide financial assistance to All Pride and to perform
the terms and conditions of the construction contract to
completion; but that subsequently, in August of 1974,
Indiana discontinued providing financial assistance, aban-
doned its performance and gave notice to Paducah that it
intended to file a mechanic’s lien upon the real property
which was the site of the motel.
Paducah’s initial pleading was a suit to enjoin Indiana
from filing a lien upon the construction site real property
and a temporary restraining order was granted to Paducah
by the State Court, Thereafter, the case was removed
by Indiana and All Pride to the United States District
Court for the Western District of Kentucky, Paducah
Division, with jurisdiction for such removal being based
upon diversity of citizenship under 28 U.S.C. §§1332 and
1441. The temporary restraining order expired by its
terms and both Indiana and Paducah filed mechanic’s
liens against Paducah’s real property. Paducah filed an
Amended Complaint in October, 1974 and a Second
Amended Complaint in January, 1975, stating in its first
count a complaint of disparagement of its title hindering
its ability to obtain financing by reason of the threatened
mechanic’s liens and in its second count a breach of con-
tract by All Pride under the construction contract and
Indiana under the contract bond. The construction con-
tract contained an arbitration clause which was invoked
by Indiana and All Pride and, on April 11, 1975, Paducah
consented to arbitration.
Proceedings Before Board of Arbitrators
Six days of arbitration hearings were held before
a three-member Board of Arbitrators in the Regional
Offices of the American Arbitration Association, Cincin-
nati, Ohio, during September and October, 1975. No
transcript of the hearings was made, but a Summary of
5
the hearings was prepared by the attorneys for Paducah
based upon their notes, which summary was submitted
to the Board of Arbitrators and counsel for Indiana and
All Pride prior to the Board’s determination. This sum-
mary shows that on the fifth hearing day, October 23,
1975, the arbitrators notified the parties that the Board
would not consider the issue of slander or disparagement
of title in their determination, stating that such question
was outside the submission to them as arbitrators (Appen-
dix p. A7). Following this decision, the parties pro-
ceeded with arbitration and, honoring the arbitrators’ deci-
sion, excluded the issue of slander or disparagement of
title from any further offers of proof and from the ques-
tions briefed before the Board.
The arbitrators entered their award, limiting their
determination to the questions of breach of contract which
they found in favor of Paducah and against both All Pride
and Indiana, specifically finding that Paducah bore no lia-
bility for damages as to either All Pride or Indiana. The
issue of slander or disparagement of title was expressly ex-
cluded from the arbitrators’ award in paragraph seven (7)
thereof, which stated:
7. This award does not determine the right of any
of the parties (the owner, contractor and surety) to
subrogation or indemnification as to any other person
not a party to the arbitration. This award does not
determine the rights of any party to damages or any
other remedy, legal or equitable, which may have
arisen or which may exist outside the arbitration sub-
mission and, specifically, this award does not relate, in
any way, to any claim for damages of any sort which
may exist by reason of the filing of mechanic’s liens
by any of the parties to this arbitration. (Emphasis
added; see Appendix p. A8).
6
Confirmation of Arbitration Award
Paducah filed a suit in the United States District
Court for the Southern District of Ohio to confirm the
arbitration award pursuant to 9 U.S.C. §9, Federal Arbi-
tration Code. Indiana filed a counterclaim seeking modi-
fication of Paragraph 7 of the award, alleging that Paducah
had been obligated to assert its slander of title claim before
the arbitrators and, since Paducah did not rely upon or
assert that claim before the arbitrators, the claim had
been waived and the award should be modified to bar
Paducah from later claiming damages due to slander of
title. Both Paducah and Indiana filed motions for sum-
mary judgment and, in March, 1977, the District Court
handed down its opinion confirming the arbitration award
and, at the same time, dismissing Indiana’s counterclaim
for modification of Paragraph 7.
The District ‘Court held, with regard to Indiana’s
counterclaim, that on the record before the court there
was no evidence that the slander of title claim had ever
been submitted to or considered by the arbitration panel
and, in fact, the record demonstrated that just the opposite
was the case (Appendix p. A23). Moreover, the court
noted that it could not determine that the absence of the
slander of title issue to the panel was solely the respon-
sibility of Paducah and, therefore, it granted Paducah’s
motion for summary judgment as to Indiana’s counter-
claim for modification of the arbitration award (Appen-
dix p. A24).
Proceedings Subsequent to Confirmation
Paducah filed a motion for leave to supplement its
complaint in the pending action before the United States
District Court for the Western District of Kentucky at
approximately the same time it filed its confirmation
7
action in the United States District Court for the Southern
District of Ohio, In March, 1976, Paducah was given
leave to file its supplemental complaint. Paducah as-
serted, in its supplemental complaint, that the arbitration
award had not resolved all disputes between the parties,
specifically referencing Paragraph 7 of the arbitration
award which excluded Paducah’s claim for damages which
might exist by reason of the filing of mechanic’s liens.
Further, Paducah alleged, consistent with the arbitration
award, that neither Indiana nor All Pride was entitled
to any damages against Paducah and that Paducah was
entitled to damages from Indiana on account of its having
wrongfully, willfully and maliciously filed a mechanic’s
lien against Paducah’s property when it knew that it
had no right to do so.
Indiana filed a Motion for Summary Judgment on
the grounds that (1) all issues were or could have been
submitted to arbitration and the arbitration award barred
Paducah’s slander of title action on the grounds of the
doctrine of res judicata; (2) Paducah had waived its claim
based on slander of title by failing to assert it in the
arbitration proceedings; (3) the action was barred by the
applicable statutes of limitation, and (4) Indiana’s filing
of its notice of mechanic’s lien was privileged. Paducah
responded to this motion with suggestions in opposition,
supported by affidavits and exhibits, asserting that gen-
uine issues of material fact remained for trial.
Initially, in July of 1978, the District Court denied
Indiana’s Motion for Summary Judgment, finding that
there were issues of material fact remaining ( Appendix
p. A3). However, on September 12, 1978, the Court
reversed its earlier decision and sustained Indiana’s Motion
for Summary Judgment solely on the ground that Paducah
had waived its right to pursue the slander of title action
= a
8
(Appendix p. A9). Concurrently, the Court ruled that
Paducah’s claim was not barred by res judicata as Indiana
had asserted (Appendix p. A6), but did not address
Indiana’s statutes of limitation or privilege claims. Pa-
ducah filed a Motion for a New Trial, Amendment of the
Court’s Judgment or, in the Alternative, for Reconsidera-
tion of the Court’s Order Sustaining Indiana’s Motion
for Summary Judgment. Thereafter, the District Court
overruled Paducah’s Motion and Paducah appealed to
the United States Court of Appeals for the Sixth Circuit.
Proceedings Before the Circuit Court of Appeals
Paducah asserted, before the Court of Appeals, that
the District Court erred in sustaining Indiana’s Motion
for Summary Judgment on the basis that Paducah had
waived its slander of title claim in that:
1. There was a genuine issue of material fact as to
whether the parties had both agreed to a limitation or
withdrawal of the slander of title issue from arbitration;
or
2. It was established beyond doubt, based upon the
record before the trial court, including the arbitration
awan~d, that either the parties had reserved such issue
for trial in the District Court or that Indiana had waived
its right to demand arbitration of the slander of title
issue;
3. In any event, there was a genuine issue of mate-
rial fact as to whether Paducah had contractually waived
its substantive right to damages for slander of title:
4. Summary judgment, a judgment on the merits.
was an inappropriate form of relief as Indiana’s objection
was to the procedure to be followed and not to the valid-
ity of Paducah’s claim; and
9
5. The claim of waiver had already been asserted
by Indiana in the arbitration award confirmation hearing
before the United States District Court for the Southern
District of Ohio, had been there determined adversely
to Indiana, and therefore was res judicata against Indiana
as to that issue or, at the very least, Indiana was barred
by the doctrine of law of the case.
The Court of Appeals, without addressing the issues
raised by Paducah, adopted and affirmed the District
Court decision in a one line opinion.
REASONS FOR GRANTING WRIT
1. The Decision of the Court of Appeals for the Sixth
Circuit Conflicts With Decisions by Other Circuit
Courts Regarding Waiver of Arbitration and Re-
garding the Power of Arbitrators to Reserve Ques-
tions for Subsequent Litigation.
A. The Court below, by adopting Judge Johnstone’s
District Court Memorandum Order filed September 12,
1978, held that Indiana was entitled to summary judgment
as to Paducah’s slander of title claim for the stated reason
that Paducah had contractually waived its right to assert
this claim by not submitting it to arbitration (Appendix
p. Al). By so holding, the Court, by necessity, con-
cluded that there was no genuine issue of material fact
regarding the slander of title claim remaining for trial
and that, as a matter of law, under Federal Rule 56(c),
Indiana was entitled to judgment based upon the record
before the Court. Basing such a determination upon a
conclusion of waiver on the part of Paducah conflicts
with the principle established in other Circuits that the
question of factual waiver of a right to arbitrate a claim
or waiver of a claim subject to arbitration by a pz ty
10
thereto depends upon the facts of each case and generally
calls for a finding by the trier of facts. Reid Burton
Construction, Inc. v. Carpenters District Council of South-
ern Colorado, 614 F.2d 698 (10th Cir. 1980); Burton-Dizxie
Corporation v. Timothy McCarthy Construction Co., Inc.,
436 F.2d 405 (5th Cir. 1971).
Reid Burton Construction Co., Inc., and Burton-Dizxie
Corporation both dealt with construction contract cases
wherein the defendants were found by the trier of fact
to have factually waived their right to arbitration. In
affirming the finding of waiver, both of the Circuit Courts
of Appeal held:
There is no set rule as to what constitutes a waiver
or abandonment of the arbitration agreement; the
question depends upon the facts of each case and
usually calls for a finding by the trier of facts.
(Loc. Cit. 614 F.2d at 702 citing to 436 F.2d at 408).
Paducah, throughout the course of this litigation in
the courts below, has vehemently asserted that there
remain genuine issues of material fact as to whether or
not it has waived its right to assert its slander of title
claim against Indiana and there has been no evidentiary
finding of a factual waiver by Paducah of such claim.
In any event, there remains a genuine issue of material
fact as to whether any such waiver occurred, including
whether or not this claim was either mutually withheld
from submission to the arbitrators by the parties or re-
served by the arbitrators for subsequent judicial deter-
mination and acceded to by the parties. Clearly, under
the Reid Burton Construction, Inc. and Burton-Dixie
Corporation decisions, these would be questions which
should be decided by the trier of fact and not as a matter
of law under Rule 56(c), Federal Rules of Civil Procedure.
11
It has often been stated that a summary judgment is
not a substitute for a trial of disputed fact issues. Vol-
unteer Elec. Co-op v. TVA, 139 F. Supp. 22 (E.D. Tenn.
1954), aff'd per curiam, 231 F.2d 446 (6th Cir. 1956).
Accordingly, the Court may not try issues of disputed
fact under a Rule 56 motion. Felix v. Young, 536 F.2d
1126 (6th Cir. 1976). Nonetheless, this is precisely what
the trial court has done ar’ the Sixth Circuit has af-
firmed.
B. The decision by the Sixth Circuit in this case
also conflicts with the decision reached in Lundgren v.
Freeman, 307 F.2d 104 (9th Cir. 1962) regarding the
question of whether a board of arbitrators may reserve
issues from their award and leave the parties free to have
the issues so reserved judicially resolved. By holding
that Indiana was entitled to summary judgment as to
Paducah’s slander of title claim, despite the express reser-
vation by the arbitrators of claims for damages arising
out of the filing of a mechanic’s lien by any party to
the arbitration, the Courts below, contrary to the Lundgren
holding, held that the arbitrators may not reserve issues
from their award for later judicial determination.
The Lundgren case involved a construction contract
containing an arbitration clause very similar to that con-
tained in the Paducah-All Pride contract. In that case,
claims by the contractor, Lundgren, for unpaid contract
balances, losses due to defects in plans and specifications,
payment for doing work not called for in the contract
and loss of the builder’s fee were submitted to arbitration
under contract provisions which recited, “All disputes,
claims or questions subject to arbitration under this con-
tract shall be submitted to arbitration. .. .” 307 F.2d
at 108, n. 2. The arbitrators entered their award, but
refused to pass upon claims made by Lundgren for sev-
eral items, reserving decision as to these claims for the
12
United States District Court. The District Court subse-
quently heard and determined these claims and awarded
Lundgren an additional amount. The Ninth Circuit, after
recognizing the arbitrators’ implied authority under a
broad arbitration clause to exclude and reserve certain
issues from their award (loc. cit. 307 F.2d at 110, n. 6),
affirmed the trial court’s incremental award to Lundgren.
It is important to note that the Lundgren court affirmed
the trial court’s award of additional sums in satisfaction
of claims based upon questions reserved by the arbitra-
tion panel even though the construction contract had
provided, as does the contract in the case at bar, that
“all disputes, claims or questions subject to arbitration
under this contract shall be submitted to arbitration. .. .”
Accordingly, the Lundgren court recognized (1) the right
of arbitrators to reserve questions from their award and
(2) the right of parties to have a later judicial determina-
tion of those issues. When the Sixth Circuit was pre-
sented the identical question regarding arbitrators’ reser-
vation of issues, however, it held directly opposite from
the Lundgren Court on this decisive question, without
so much as a word addressing Paducah’s argument re-
garding this issue.
2. The Decision Below Raises a Significant Question
Regarding the Application of the Federal Arbitra-
tion Code Which Should Be Resolved by This
Court.
Paducah submits that Indiana improperly invoked
the remedy of summary judgment before the District
Court when, at best, it was entitled only to a stay of
the proceedings under the Federal Arbitration Code, 9
U.S.C. §3. This section provides the remedy for a party
claiming that an issue is referable to arbitration when
13
that issue has been brought before a court of the United
States and provides as follows:
If any suit or proceeding be brought in any of the
courts of the United States upon any issue referable
to arbitration under an agreement in writing for such
arbitration, the court in which such suit is pending,
upon being satisfied that the issue involved in such
suit or proceeding is referable to arbitration under such
an agreement, shall on application of one of the parties
stay the trial of the action until such arbitration has
been had in accordance with the terms of the agree-
ment, providing the applicant for the stay is not in de-
fault in proceeding with such arbitration.
9 U.S.C. §3.
The courts below have proceeded as though a stay
in the proceedings, as mandated in 9 U.S.C. §3, is merely
an alternative form of relief to summary judgment and
that either may be granted when an issue subject to
arbitration is submitted to the court. Paducah urgently
asserts that 9 U.S.C. §3 gives the court no such choice,
but mandates that the court “shall... stay the trial of
the action until such arbitration has been had .. .” when
confronted with a fact pattern as is presented in this
case.
Clearly, Indiana invoked, the trial court granted, and
the Circuit Court of Appeals affirmed the wrong remedy
if it is accepted that the slander of title issue should
have been submitted to arbitration. At best, upon a
finding that the slander of title issue was subject to
arbitration, the District Court should have stayed the
trial and ordered arbitration. Under 9 U.S.C. $3 and the
policy favoring arbitration which underlies the Federal
Arbitration Code, the court was authorized to do this and
14
nothing more. Thus, it is for this court to decide whether
a District Court may, consistent with the provisions of the
Federal Arbitration Code, grant summary judgment, a
judgment on the merits, amounting to a forfeiture of a
valuable claim, rather than order a stay in the proceedings
when presented an issue which is subject to arbitration,
but which has not been decided by any court, board of
arbitrators or other tribunal.
3. The District Court Below Has So Far Departed
From the Accepted and Usual Course of Judicial
Proceedings As to Call for an Exercise of This
Court’s Power of Supervision.
The District Court has so far departed from the
accepted and usual course of judicial proceedings, and
the Circuit Court of Appeals has sanctioned such depar-
ture, that Paducah has been denied basic due process of
law regarding its slander of title claim and, therefore,
the supervisory power of this Court should be exercised.
These departures have occurred in a number of areas:
First, the courts below have permitted entry of a
summary judgment against Paducah when genuine issues
of material fact remained for trial.
Second, the courts below failed to find that Indiana
had waived its right to demand arbitration of the slander
of title issue by: (1) agreeing to withhold said issue
from the submission to the arbitrators: (2) acquiescing
in the ruling of the arbitrators that such issue had not
been submitted to them and proceeding without objection
to such reservation throughout the arbitration; and (3)
litigating said issue on the merits before the United States
District Court for the Southern District of Ohio.
Third, the courts below based the award of summary
judgment on a finding that Paducah had waived its slan-
15
der of title claim when the question of such waiver had
previously been litigated in the District Court for the
Southern District of Ohio and should have been barred
by the doctrines of res judicata and law of the case.
A. The first contention of error, that summary judg-
ment was improperly granted in that there remained
genuine issues of fact for trial, has been touched upon
above. Paducah has contended throughout the course of
this case that it was under no obligation to submit its
tort claim of slander of title to arbitration under a con-
tractual agreement which applied only to disputes arising
under the contract. Even if it were assumed, however,
that such an obligation did exist, Paducah is still entitled
to a factual determination as to whether or not the con-
tractual agreement to arbitrate this issue had been waived
or modified by the conduct of the parties. The courts
below never indicated the manner in which the alleged
waiver took place other than to refer to the construction
contract provision authorizing arbitration. Clearly the
courts have confused the agreement to arbitrate with the
submission of matters to arbitration. It has often been
held that parties to a contract providing for arbitration
may factually waive the right to arbitrate or may limit
or amend matters to be submitted to arbitration. Reid
Burton Construction, Inc.., supra; Burton-Dixie Corpora-
tion, supra; American Locomotive Co. v. Gyro Process
Co., 185 F.2d 316 (6th Cir. 1950); Almacenes Fernandez,
S.A. v. Golodetz, 148 F.2d 625 (2d Cir. 1945); American
Locomotive Co. v. Chemical Research Corp., 171 F.2d 115
(6th Cir. 1948).
The courts below gave weight to an undated “Second
Stipulation” in granting summary judgment to Indiana
(Appendix p. A7), finding thereon that Paducah had
contractually waived its right to pursue its slander of
16
title claim by submitting all claims to the arbitrators.
A closer examination of this stipulation than was made
below reveals, however, that it in no way refutes Pa-
ducah’s contention that there was no waiver of its right
to have the slander of title claim heard. This stipulation
states that the arbitrators’ award would address “all issues,
claims, or defenses between the parties which are en-
compassed in the pleadings . . . pending in the United
States District Court for the Western District of Ken-
tucky. .. .” (Appendix p. A7). It is important to note
that Paducah’s complaint at that time addressed only
the issue of Indiana’s threatened mechanic’s lien. Pa-
ducah’s slander of title action was not on file at the time
of the arbitration proceedings. It referred to a subsequent
course of events which gave rise to that claim after the
arbitrators had determined that Indiana had no claim
against Paducah by reason of the construction contract
or bond. Secondly, the stipulation refers to submission
of the “claimed rights of Indiana Insurance Company
under the mechanic’s lien. . . .” (Appendix p. A7). This
provision, like the earlier quoted provision does not sup-
port the court’s conclusion of waiver, This portion of
the stipulation, by its terms, refers to Indiana’s rights
under the lien and could not, even by tortured construc-
tion, be twisted to refer to Paducah’s slander of title
claim against Indiana.
Paducah has not had its day in court regarding its
slander of title claim and is entitled to be heard. The
District Court for the Southern District of Ohio recog-
nized that the arbitrators had expressly excluded this
issue from their award and clearly ruled that this issue
had not been determined by the arbitrators and that
Paducah was not barred thereafter from asserting its
slander of title claim (Appendix pp. A23-24). Accordingly,
the only question remaining was not whether Paducah
17
could assert its claim against Indiana for slander of title,
but where such claim should be asserted. By granting
Indiana’s motion for summary judgment, the courts below
have denied Paducah one of the most rudimentary ele-
ments of due process, an opportunity to be heard.
B. Paducah contends, as its second assertion of error,
that the courts below improperly failed to find that
Indiana had waived its right to demand arbitration of
the slander of title issue, A party to arbitration may
not be heard to complain that a claim is barred because
it was not submitted to the arbitrators when the party
has acquiesced in the ruling of the board of arbitrators
that such claim would not be addressed and has continued
without objection throughout the arbitration proceedings.
Cornell & Co. v. Barber & Ross Co., 360 F.2d 512, 123
U.S. App. D.C. 378 (1966); American Locomotive Co.
v. Gyro Process Co., supra. Defects in arbitration pro-
ceedings may be waived by a party’s acquiescence in the
arbitration despite knowledge of the defect. Order of
Railway Conductors and Brakemen v. Clinchfield Rail-
road Co., 407 F.2d 985 (6th Cir. 1969). When no proof
is presented to a board of arbitrators in connection with
a claim arguably subject to a broad arbitration clause,
the parties remain free to litigate such claim in court.
Hannevig v. R. W. J. Sutherland & Co., 256 Fed. 445 (2d
Cir.), cert. den., 249 U.S. 612 (1919). Moreover, ‘the
right to demand arbitration of an issue, or to assert
failure to arbitrate as a defense, may be waived by in-
voking the jurisdiction of a court as to such issue or
by participating in the litigation of it. Reid Burton Con-
struction, Inc., supra,
It is clear from the record below that Indiana acqui-
esced in the arbitrators’ ruling excluding the slander of
title question from the arbitration determination and
18
continued to participate in the arbitration proceedings
without objection. Indiana, throughout the arbitration
proceedings presented evidence and made arguments re-
garding the issues submitted to the board, but remained
silent as to any claim that the arbitrators were not
properly determining the issues submitted to them. When
the question arose as to the propriety of the submission
to the board, it was incumbent upon Indiana to raise
its concerns before the appropriate court. Kentucky
River Mills v. Jackson, 206 F.2d 111, 47 A.L.R.2d 1331
(6th Cir.), cert. den., 346 U.S. 887 (1953). Nonetheless,
it was not until Paducah filed its motion to confirm the
arbitration award in the District Court for the Southern
District of Ohio, months after the arbitrators’ award was
made, that Indiana for the first time, argued that the
slander of title claim should have been submitted to the
board of arbitrators. Moreover, in making such argu-
ment, Indiana did not request that the confirmation pro-
ceedings be stayed penuing arbitration of this issue, but
rather joined this issue by way of a counterclaim, in-
voking the jurisdiction of the court, and litigated it to
conclusion with an ultimate resolution in Paducah’s favor.
Clearly, Indiana waived its right to assert in the courts
below that the slander of title claim should have been ar-
bitrated based on the above-cited cases. Nonetheless, the
courts below granted and affirmed a summary judgment
in favor of Indiana. If allowed to stand, the decision of the
courts below would amount to a sanction of the proposition
that a party to arbitration may sit silently by while the
board of abritrators proceeds erroneously, only to spring
from ambush, claiming failure to arbitrate, months or even
years later when the other party seeks to assert its rights.
This has not been and should not be the law under facts as
are presented here and this Court should exercise its super-
19
visory power to ensure that this is not the law applied to
this case. Justice demands nothing less.
C. Paducah respectfully asserts, as its third conten-
tion of error, that the courts below erred in not barring
Indiana’s claim of waiver on the grounds of the doctrines
of res judicata and law of the case. An award of a board
of arbitrators generally has the effect of a judgment and
a judgment entered upon confirmation of such an award
is a judgment on the merits. U.S. Plywood Corp. v. Hudson
Lumber Co., 127 F. Supp. 489 (S.D. N.Y. 1954). A judg-
ment entered in prior proceedings which overrules a motion
to vacate or modify the provisions of an arbitration award
is res judicata or at least collateral estoppel by judgment
as to all issues involving the validity of the award in a
subsequent action. Brown v. Bridgeport Rolling Mills Co.,
245 F.Supp. 41 (D. Conn. 1965); James L. Saphier Agency,
Inc. v. Green, 190 F.Supp. 713 (S.D. N.Y.), aff'd, 293 F.2d
769 (2d Cir. 1961). |
The issue of waiver raised by Indiana in support of its
Motion for Summary Judgment was raised by it in its
counterclaim to Paducah’s confirmation suit before the
District Court for the Southern District of Ohio. This
counterclaim was a motion to modify the arbitration award
and the court, with regard to said counterclaim, granted
summary judgment in favor of Paducah and against In-
diana (Appendix p. A24). No appeal of this decision was
taken and it, therefore, became final. Accordingly, the
courts below erroneously permitted Indiana to reassert its
claim of waiver when such claim had already been litigated
to a final decision adversely to Indiana in the District Court
for the Southern District of Ohio and should have been
barred by the doctrine of res judicata.
Equally applicable to these facts is the doctrine of law
of the case. Briefly stated, this doctrine says that if an
20
appellate body has passed on a legal question and re-
manded the case for further proceedings, the legal ques-
tions so determined will not be differently determined in
a subsequent appeal of the case. United States v. U.S.
Smelting, Refining & Mining Co., 33f U.S. 186 (1950). In
the present case, the appellate body was the United States
District Court for the Southern District of Ohio which was
authorized to confirm, modify or vacate the arbitration
award. 9 U.S.C. §§9, 10, 11. The issue of waiver raised
by Indiana in support of its Motion for Summary Judg-
ment below was the same as it raised before that court
in support of its Counterclaim. The District Court for the
Southern District of Ohio discussed this issue at length in
Part II of its opinion (Appendix pp. A22-24) and concluded,
as a matter of law: (1) that the arbitrators had specif-
ically excluded the issue of slander of title from their
award; (2) that the issue had not been submitted to the
board of arbitrators for consideration; (3) that the blame,
if any, for not submitting this issue to the arbitrators could
not be laid exclusively at the feet of Paducah; (4) that
Paducah was not thereafter barred from having its slander
of title claim heard; and, therefore, (5) that no modifica-
tion of the arbitration award would be permitted. Ac-
cordingly, the District Court for the Western District of
Kentucky, when confronted with the same issues as had
already been finally determined by the District Court for
the Southern District of Ohio, was bound by the earlier
determination and should have denied Indiana’s Motion
for Summary Judgment. Its failure to do so was plain
error in that the court determined the issue of waiver dif-
ferently than had the District Court for the Southern Dis-
trict of Ohio and, thus, failed to follow the law of the
case. As the Circuit Court of Appeals for the Sixth Cir-
cuit has sanctioned this failing, it falls to this Court to ex-
ercise its supervisory power to correct this error and set
right the manifest injustice done thereby to Paducah.
21
CONCLUSION
For the foregoing reasons, a writ of certiorari should
issue to review the judgment and opinion herein of the
United States Court of Appeals for the Sixth Circuit.
Respectfully submitted,
DonaLp D. WEINSTEIN (Counsel of Record)
and
BERNARD L, BALKIN
A. Morcan HICKENLOOPER of
SANDLER, BALKIN, HELLMAN & WEINSTEIN
Professional Corporation
3130 Broadway, Third Floor
Kansas City, Missouri 64111
Telephone: (816) 753-3525
Counsel for Petitioner
Al
APPENDIX
APPENDIX A
79-3157
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
PADUCAH ASSOCIATES, LTD.,
Plaintiff-Appellant,
V.
INDIANA INSURANCE COMPANY and ALL PRIDE
DEVELOPMENT CORPORATION,
Defendants-Appellees.
ORDER
(Filed November 13, 1980)
Before: LIVELY and ENGEL, Circuit Judges and PECK,
Senior Circuit Judge
Paducah Associates appeals from an order of the dis-
trict court dismissing its diversity claim of slander of title
against defendants Indiana Insurance Company and All
Pride Development Corporation. All three parties had
entered into a construction contract that contained a broad
arbitration clause. A breach of contract dispute arose and
the parties agreed to arbitration. Paducah did not pursue
its slander of title claim before the arbitration panel. The
district court granted summary judgment, finding that Pa-
ducah had waived its slander claim by failing to pursue its
claim at arbitration.
For the reasons set forth in the memorandum opinion
of United States District Judge Edward H. Johnstone, filed
in the district court September 12, 1978,
A2
IT IS ORDERED that the judgment of the district
court be and it is hereby affirmed.
ENTERED BY ORDER OF THE COURT
/s/ John P. Hehman
Clerk
A3
APPENDIX B
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF KENTUCKY
AT PADUCAH
Civil Action No. 74-89-P
PADUCAH ASSOCIATES, LTD.,
Plaintiff,
V.
INDIANA INSURANCE CO. and ALL-PRIDE
DEVELOPMENT CoO.,
Defendants.
MEMORANDUM OPINION
(Entered September 12, 1978)
This slander-of-title action stands before the Court on
a motion by Indiana Insurance Company (hereinafter “In-
diana”) for summary judgment. Previously, we denied the
motion because of a then-perceived genuine issue as to
a material fact. For the reasons discussed below, the
motion is now granted.
The expansive record in this case may be summarized
in the following relevant chronology. In 1973 the parties
entered into a contract for the construction of a motel in
Paducah, Kentucky. The plaintiff, Paducah Associates
(hereinafter “Paducah’’), was the owner of the motel.
All-Pride Development Company, the contractor, was to
perform the actual construction, with Indiana acting as
the surety. Included in the agreement was a broad arbi-
tration clause:
All claims, disputes and other matters in question aris-
ing out of, or relating to, this Contract or the breach
A4
na
thereof . . . shall be decided by arbitration in accor-
dance with the Construction Industry Arbitration Rules
of the American Arbitration Association then obtain-
ing, unless the parties mutually agree otherwise. This
agreement to arbitrate shall be specifically enforce-
able under the prevailing arbitration law. The award
rendered by the arbitrators shall be final, and judg-
ment may be entered upon it in accordance with
applicable law in any court having jurisdiction thereof.
Sometime after work commenced, disputes arose among
the parties as to their performance and obligations under
the contract. When efforts to resolve the differences
proved unsuccessful, Paducah brought suit in McCracken
Circuit Court alleging various contract breaches and also
seeking equitable relief against the threatened filing of a
mechanic’s lien by All-Pride and Indiana on the subject
property of the contract. The state court issued a restrain-
ing order against the filing of the lien.
The defendants then removed the action to this Court
and, after the restraining order expired, filed a mechanic’s
lien statement against the plaintiff's property on Septem-
ber 20, 1974. Following Paducah’s second amended com-
plaint and Indiana’s invocation of the arbitration clause,
the parties agreed to arbitrate their disputes, despite Pa-
ducah’s initial objections. The arbitrators entered an
award for the contract claims on December 24, 1975, but
they did not address the mechanic’s lien issue. The
award was confirmed by the United States District Court
for the Southern District of Ohio.
The defendants released the mechanic’s lien on Jan-
uary 26, 1976. Paducah then filed a supplemental com-
plaint in this Court on March 12, 1976, seeking damages
for slander of title arising from the mechanic’s lien. There
followed Indiana’s present motion for summary judgment.
A5
Indiana relies on three arguments to support its mo-
tion: (1) the slander-of-title claim is barred by the stat-
ute of limitations; (2) the filing of the mechanic’s lien was
privileged; and (3) the slander-of-title claim is barred by
the principles of res judicata or waiver. We shall confine
our discussion to the third argument.
Indiana contends that Paducah had an opportunity to
submit its slander-of-title claim to the arbitrators. Hav-
ing failed to do so, it is barred by the principles of res
judicata from now asserting that claim in this Court.
Despite an earlier ambiguity on this point, the parties now
agree that the slander-of-title claim was never submitted
to the arbitrators for decision.
We conclude that the doctrine of res judicata does not
apply to these facts. Generally, the doctrine precludes
relitigating not only those matters which were actually in-
volved in a prior proceeding but also those that might
have been presented. Mayer v. Distel Tool & Machine Co.,
596 F.2d 798 (6th Cir. 1977); Coogan v. Cincinnati Bar
Association, 431 F.2d 1209 (6th Cir. 1970). It has been
held that the doctrine applies to arbitration proceedings.
Bower v. Eastern Airlines, Inc., 214 F.2d 623 (3rd Cir.
1954); Overseas Motors Inc. v. Import Motors Limited, Inc.,
375 F.Supp. 499 (E.D. Mich. 1974), aff’d, 519 F.2d 119 (6th
Cir. 1975), cert. denied, 423 U.S. 987, 96 S.Ct. 395 (1975).
However, an important distinction must be made.
Res judicata bars a party from retrying the same cause
of action, even if he has neglected to present all possible
issues or theories of recovery. Buta party may still litigate
an entirely separate cause of action. Thus, the central
issue is the meaning of a “cause of action.” Three princi-
pal definitions have been cited. F. James, Civil Procedure
553-554 (1965). Under the narrowest definition a cause
of action is a single remedial right. Consequently, a single
A6
injury might give rise to several successive suits based
on different theories of recovery. A broader, more modern
definition is a single breach of a primary duty. Under
this test, one occurrence might give rise to several causes
of action but only for independent breaches of duty, not
merely different theories of recovery. The third defini-
tion is cast in terms of factual unity:
The narrowest version of this view would require that
the same evidence support both actions. A broader
version, however, would not require identity of evi-
dence but would define “cause of action” broadly to
include the group of operative facts pragmatically de-
termined by the court as those which should be treated
asaunit... Id. at 554.
Even under this broad definition, we think that Paducah’s
contract cause of action is distinct from its slander-of-title
claim. Factually, the two claims might be supported by
some common evidence, and certainly the filing of the
mechanic’s lien was a contract-related act. “However, the
mere fact that the two actions relate to the same subject
matter does not necessarily establish that they are on the
same cause of action.” 46 Am. Jur. 2d Judgments §407
(1969). As to the two actions under discussion, there is a
factual relationship but not factual unity. Surely, a plain-
tiff might wish to join both claims in the same suit, but
permissive joinder is not the test. The mechanic’s lien
was not filed until disagreements over the contract arose.
Whatever claim for damages this may have given Paducah
did not depend solely on the underlying contract disputes.
We do not find the requisite factual coherence so as to
apply the rule of res judicata.
We do conclude, however, that Paducah has waived
its right to pursue its slander-of-title action in this court.
As noted earlier, the arbitration clause required that all
A7
claims relating to the contract be submitted to arbitration.
When Indiana invoked that clause, the parties arranged for
arbitration proceedings. In the record there is an undated
“Second Stipulation” Stating that all claims and disputes
had been submitted to the arbitrators:
The parties hereby agree that all issues between
them have been submitted. to arbitration including...
any and all issues, claims, or defenses between the
parties which are encompassed in the pleadings in the
case of Paducah Associates, Ltd., Plaintiff, vs. Indiana
Insurance Company and All-Pride Development Com-
pany, Defendants, pending in the United States Dis-
trict Court for the Western District of Kentucky ...
and the claimed rights of Indiana Insurance Company
under the Mechanic’s Lien claim filed in the Office of
the McCracken County Clerk, Paducah, McCracken
County, Kentucky, dated September 20, 1974.
Paducah had never asserted a slander-of-title claim by that
name in the pleadings prior to arbitration, though it had
sought equitable relief against the filing of the lien. Yet a
summary transcript of the arbitration hearing demon-
strates that slander of title had emerged as a possible issue
for consideration:
Hardy (arbitrator): Submission does not include
any damages arising from the filing of the mechanic’s
lien claim.
Hardy says slander of title question not before
arbitrators, i.e., whether not in good faith and known
not to be in good faith. (Arbitration transcript, p. 48)
Thus, on the one hand the parties had stipulated that all
issues had been submitted to arbitration, but it is un-
disputed that the slander-of-title claim was not presented
by Paducah, even though it was a live dispute. Paragraph
7 of the Award of the Arbitrators bears out this point:
A8
This award does not determine the rights of any party
to damages or to any other remedy, legal or equitable,
which may have arisen or which may exist outside the
arbitration submission and, specifically, this award
does not relate, in any way, to any claim for dam-
ages of any sort which may exist by reason of the
filing of mechanic’s liens by any of the parties to this
arbitration.
Given that state of affairs, we hold that Paducah has
contractually waived its right to bring the present action.
Both parties have cited the case, Lundgren v. Freeman, 307
F.2d 104 (9th Cir. 1962), to support their positions. In
that case, Lundgren, a builder, had contracted with a school
district to build various structures and facilities. Prior
to completion, the school district terminated the contract
upon the advice of architects. Lundgren then sued the
school district for unpaid balances and joined a claim
against the architects for interference with his perform-
ance of the contract and for other damages, including
damage to reputation and credit. His claim against the
school district was submitted to arbitration pursuant to
an arbitration clause similar to the present one. The
eventual] arbitration award was confirmed by the district
court, and later the court ruled that no issue remained
between Lundgren and the school district. On appeal,
Lundgren argued that further issues did remain because
he had sustained special damages such as loss of reputa-
tion and loss of credit standing. The court held that the
arbitration award barred further proceedings: “The
short answer to this contention is that Lundgren never
claimed such damages in his complaint against school
district. The stipulation was to arbitrate ‘the issues be-
tween the parties.’” Lundgren v. Freeman, supra at 115.
Whatever the factual differences between that case and
the instant one, Lundgren can fairly be cited for the prop-
A9
osition that a contractual stipulation to arbitrate al] issues
bars the later presentation of new claims.
Paducah, however, cites Lundgren for another facet
of the case. The court held that Lundgren could maintain
an action against the architects for damages arising from
acts that exceeded their authority as agents for the school
district. But Lundgren’s suit against the architects was
never submitted to arbitration in the first place, Fur-
thermore, the court stated that “insofar as architects acted
as agents or quasi-arbitrators, Lundgren has elected his
remedy and cannot now recover from them any of the
damages passed upon by the arbitrators, whether allowed
or disallowed by them.” Lundgren v. Freeman, supra at
119. Consequently, this holding does little to advance
Paducah’s argument.
CONCLUSION
Broad arbitration agreements manifest a desire to
arbitrate disputes rather than resort to the courts. Georgia
Power Co. v. Cimarron Coal Corp., 526 F.2d 101 (6th Cir,
1975), cert. denied, 425 U.S. 952, 96 S.Ct. 1727 (1976).
Paducah had the opportunity to press its slander-of-title
claim before the arbitrators. In light of its failure to
exercise that right, coupled with the signed stipulation
that all issues had been submitted to arbitration, we hold
that Paducah has waived its right to seek judicial deter
mination of that claim.
Accordingly, the motion of the defendant, Indiana In-
surance Company, for summary judgment is granted. A
separate order is this day entered.
DATED: September 6, 1978.
/s/ Edward H. Johnstone
Edward H. Johnstone
Judge, United States District
Court
Al0
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF KENTUCKY
AT PADUCAH
Civil Action No. 74-89-P
PADUCAH ASSOCIATES, LTD.,
Plaintiff,
Ve
INDIANA INSURANCE CO., and ALL-PRIDE
DEVELOPMENT CO.,
Defendants.
ORDER AND JUDGMENT
(Entered September 12, 1978)
The defendant, Indiana Insurance Company, having
moved the Court for summary judgment, and the Court
having entered its memorandum opinion and being other-
wise sufficiently advised,
IT IS HEREBY ORDERED AND ADJUDGED that
the defendant’s motion be, and it is hereby SUSTAINED.
This is a final and appealable judgment and there is
no just cause for delay.
DATED: September 6, 1978.
/s/ Edward H. Johnstone
Edward H. Johnstone
Judge, United States District
Court
All
APPENDIX C
UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF OHIO
WESTERN DIVISION
No. C-1-76-47
PADUCAH ASSOCIATES, LIMITED
Plaintiff,
VS.
INDIANA INSURANCE COMPANY
and
ALL PRIDE DEVELOPMENT CORPORATION,
Defendants.
DISPOSITION OF PENDING MOTIONS
FOR SUMMARY JUDGMENT
(Filed March 14, 1977)
This was once a relatively simple action to confirm
an arbitration award pursuant to 9 U.S.C. § 9. The defen-
dant Indiana Insurance Company then filed a counterclaim
seeking modification of the award of the Arbitrators with
reference to possible subsequent claims by the plaintiff
against the defendant. The plaintiff thereafter amended
its complaint to seek modification of the actual amount
awarded by the arbitrators to the plaintiff. The cause is
now before the Court upon cross-motions for summary
judgment.
* * % 4 * * +
A discussion of the factual and procedural events of
this case is necessary before one may come to grips with
the muddled legal issues.
Al2
In October of 1973 the plaintiff Paducah Associates
(Paducah) contracted with All-Pride Development Cor-
poration (All-Pride) for a motel construction project. The
defendant Indiana Insurance Company (Indiana) executed
a performance bond at approximately the same time. In
May of 1974 All-Pride developed financial difficulties and
requested assistance from Indiana Insurance. Indiana paid
subcontractors and All-Pride payroll employees until Au-
gust of 1974, when it ceased all payments.
On August 19, 1974, the plaintiff filed suit against
All-Pride and Indiana in McCracken Circuit Court, Mc-
Cracken County, Kentucky. That action was removed to
the United States District Court for the Western District of
Kentucky. The defendant Indiana then invoked the man-
datory arbitration clause of the bond contract, and a num-
ber of issues were submitted to the arbitrators. The ar-
bitration panel conducted five days of hearings - September
16-18 and October 22-23 of 1975.
On October 17, 1975, after the September arbitration
hearings, but before the October hearings, subcontractors
holding mechanic’s liens on the Paducah/All-Pride project
filed suits in McCracken Circuit Court to enforce those
liens against Paducah and Indiana Insurance in an action
styled Cole Lumber and Supply Co., Inc. v. McBride, Civil
No. 14,876. The lienholders sought to enforce their claims
against property held by Paducah and against the bond
given by Indiana to Paducah.' There is still a dispute be-
tween Paducah and Indiana as to whether the arbitration
panel considered the liens of all the subcontractors in
making its award, an issue discussed infu.
1. In Kentucky a subcontractor may, in certain circum-
stances, directly sue a surety on a bond to which it is not a party,
but to which it is a third-party beneficiary.
Al3
On December 24, 1975, the arbitration panel issued
an award of damages in favor of Paducah and against
Indiana in the amount of $159,842.12. plus interest of ap-
proximately $12,000. The amount due by the surety In-
diana to Paducah was computed by deducting credits paid
by the surety to All-Pride’s subcontractors during May-
August, 1974 ($165,000) from the total amount of the bond,
i.e. $325,000. While the focal issue in the arbitration was
whether or not the surety’s liability was limited to the
original amount of the bond, the plaintiff iow apparently
challenges not only the determination that Indiana’s li-
ability was limited to $325,000, but also the allowance of
the credits for the funds advanced to All-Pride’s subcon-
tractors in May-August of 1974.
On January 26, 1976, Indiana, rather than paying the
amount of the award directly to Paducah, interpled $173,-
795 into the Cole Lumber and Supply action in McCracken
Circuit Court. In interpleading that amount the defendant
Indiana claimed the sum represented the total liability
which it had on the bond as determined by the arbitration
panel, a position which it continues to assert in this action.
This action was filed by the plaintiff on February 38,
1976, asking for confirmation of the arbitration award and
the entry of a judgment on the award amount declared
due to it by Indiana in the arbitration award. The pri-
mary purpose of such a motion for confirmation and judg-
ment would be to establish whether the defendant In-
diana had discharged its liability as set forth in an ar-
bitration award by interpleading the amount of the award
rather than tendering it directly to Paducah.
The defendant Indiana answered the complaint in this
action on February 25, 1976 by stating, inter alia, that
it had interpleaded the amount into the McCracken County
Al4
Court in the Cole Lumber suit. The defendant also
counter-claimed, asking for a modification of the arbitra-
tion award to reflect the consideration and disposition of
any possible slander of title action by the plaintiff Paducah
against it.
On June 7, 1976, the plaintiff and defendant, together
with most, if not all, of the individual subcontractor-lien-
holders in the McCracken County suit, entered into a stip-
ulation which permitted the interpleaded funds to be drawn
down by Paducah Associates. The drawn-down funds
were thereafter to be paid at a rate of 75 cents on each
dollar of claimed debt to the individual subcontractor-
lienholders, who would then release their liens upon the
real property of Paducah. The stipulation provided in
relevant part:
1. Defendant, Indiana .. . has filed a counter-
claim and cross-claim interpleader ... and on J anuary
26, 1976 deposited . . . the sum of $173,755.00 alleg-
ing that this fund represents the full extent of its lia-
bility and a contract bond which it executed on behalf
of All-Pride Development Corporation as determined
by an award in arbitration between Paducah .. . and
Indiana ...and All-Pride....
2. That Thomas Vernier, Receiver for the de-
fendant, Paducah . . . has moved to be substituted as
party-defendant for Paducah . . . in this cause and
claims the entire amount of the deposit in .. . the
Court as the property of the defendant Paducah .. .
as the award in arbitration.
10. That, except as stipulated . . . all the parties
hereto reserve their claims, rights, causes of action
and defenses as asserted in the pleadings in this cause.
Al5
11. That the plaintiffs and defendants . . . stip-
ulate with the defendant Thomas Vernier, that upon
final determination of their claims against Indiana...
under the . . . bond, from any amount assessed in
their favor against Indiana .. . the unpaid principal
balance of their respective claims shall first be paid
to them and the remainder of such award shall be
paid to the defendant Thomas Vernier as Receiver
of Paducah...
Based on that Stipulation, the McCracken County
Court issued an order approving the draw-down by Vernier
as Receiver for Paducah,? and the distribution of those
funds to the named creditors. The Order does not ad-
judge the limits of Indiana’s liability, and specifically re-
serves the claims and defenses asserted to all parties, not-
withstanding the draw-down and distribution. Indiana is
specifically held to have no objection to distribution prior to
the determination of liability, since it was liable for at least
the amount interpled to the claimants, { 9, Cole Lumber &
Supply Co., Inc. v. McBride, Order of June 7, 1976, Civil
Action No. 14,876 (McCracken, Kentucky, Circuit Court.
Division No. I).
There appears to be no dispute that the interpled fund
was drawn down by Paducah’s receiver and paid out to
the creditors, who thereafter released their liens against
Paducah’s real property.
On July 7, 1976, five months after the date of the
original complaint and six and one-half months after the
arbitration award was issued, the plaintiff moved for
leave to amend its complaint to include a petition for
2. The Court notes that Paducah was, and still is, in receiver-
ship, yet the receiver is not a party to this action. Since the
defendant has not sought to raise the issue, the Court need not
decide whether the proper party in interest is before it.
Al6
modification, correction or vacation of the arbitration
award. An order granting leave was issued on September
29, 1976.
This Court is now asked to consider and act upon three
issues. First, should the arbitration award be modified as
to the damages which were awarded to Paducah. Second,
should the award be modified to reflect the disposition
of certain claims for disparagement of title apparently
raised by the plaintiff against the defendant in another
court and action other than the present one. Third, was
the impleader of the award amount by the defendant In-
diana proper satisfaction of the arbitration award to the
plaintiff.
I. The Arbitration Award: Damages
The plaintiff has asked this Court to amend - or vacate
- that part of the arbitration award which credited Indiana
with the amounts which it had paid to subcontractors of
All-Pride from May to August of 1974. The plaintiff
also apparently challenges the arbitration panel’s limitation
of Indiana’s liability to the amount of the bond, contending
that under applicable law, if the defendant surety had
undertaken the performance of the contract, its liability
was not limited to the amount of the bond.
The power of this Court to modify or vacate the arbitra-
tion award in question is governed by 9 U.S.C. §§ 10 and 11.
Modification or correction of an award under § 11 is
limited to three circumstances, only one of which is rele-
vant to the plaintiff's claim. Under § 1l(a) an evident
material miscalculation may be corrected by the Court,
as may an evident material mistake in the description of
any person, thing, or property. In the present case the
plaintiff's challenge to the amount awarded by the arbitra-
tion pane! is not based upon any miscalculation, evident
Al7
or otherwise. except to the extent that the plaintiff alleges
that the computations were not consistent with either the
law or the panel’s own findings. Put another way, given
the premise the various credits could be allowed and the
various interest penalties assessed in the manner set forth
by the panel, the calculations are at least mathematically
correct. To that extent, there is no basis for modification
or correction under § 11, at least so far as the plaintiff's
claims are concerned.
Title 9 U.S.C. § 10 provides for the vacation of an
arbitration award in a number of circumstances, one of
which is applicable to the plaintiff’s claims. Section 10(d)
provides that where arbitrators exceed their powers, or
so imperfectly execute them that a material, final and
definite award upon the subject matter submitted was
not made, the Court may vacate it. In the particular con-
text of arbitrations which are challenged because the
arbitrators erred as to findings of fact or law, the general
rule is that mere errors on the part of an arbitrator will
not support the Court’s vacation of an award, Wilko v.
Swan, 346 U.S. 427, 436-437 (1953); Sobel v. Hertz, Warner
& Co., 469 F.2d 1211, 1214 (2nd Cir., 1972). Put another
way, only manifest disregard for the law or a lack of funda-
mental rationality will be grounds for vacating an award,
Swift Industries, Inc. v. Botany Industries, Inc., 466 F.2d
1125, 1131 (8rd Cir. 1972) (fundamental rationality); Bell
Aerospace Co., Division of Textron, Inc. v. Local 516, Int.
Union, United Auto, Aerospace & Agri. Implement Workers,
356 F.Supp. 354, 356 (S.D. N.Y., 1973), aff'd in part, rev’d
in part 500 F.2d 921 (2nd Cir. 1974).
Both parties have submitted to this Court extensive
exhibits concerning the facts and law submitted to the
arbitration panel and provided more than ample comment
upon the allegations of (in)consistency of the award and
the law; the knowledge of the arbitrators; and the legal
Al’
principles applicable to the parties and the bond contract
in this action. The Court must, however, make the award
itself as the focal point of any consideration of a motion
to vacate.
The award states that, pursuant to the contractor’s
(All-Pride’s) request, the surety (Indiana) extended fi-
nancial assistance to the contractor, which was in default
({ 4), but that the agreement did not constitute an election
by Indiana to perform the remainder of the contract ({ 8)
and that there was no intention by the surety or the con-
tractor that the surety waive the maximum obligation of
its bond ($325,000). The award also states that the surety
is entitled to no damages against the owner (Paducah),
either by way of set off, assignment or subrogation ({ 13).
Those findings by the arbitration panel are, after ex-
amining the applicable law as cited both to the arbitrators
and the Court, not only fundamentally rational, but also
appear to be correct as a matter of law. At any rate, the
Court finds no manifest disregard for the law in that part
of the award, and it will not be vacated or modified. The
total liability of Indiana is $325,000.
The crux of the plaintiff's claim is that, assuming the
surety did not undertake to perform the contract, thereby
limiting its liability to the bond of $325,000, Indiana’s lia-
bility cannot be reduced by the $165,157.88 paid out on
behalf of All-Pride in the face of the finding in Award § 13,
i.e., that the surety is entitled to no damages against the
owner by way of set-off, assignment or subrogation.
First, it is not clear to the Court from these pleadings
whether, as a matter of law, the amounts paid by a surety
to a contractor to keep such a contractor “afloat” before
undertaking performance of the contract can legitimately
be credited against ultimate liability on the amount of
Al19
the bond. It is not clear, therefore, whether the arbitration
panel ruled correctly as a matter of law. That point is not,
as previously noted, controlling in the consideration of a
motion to vacate or modify.
Secondly, and more to the point, it is not clear that
the arbitration panel knew the law and proceeded to dis-
regard it. The plaintiff’s position is that the parties both
agreed that the panel could go one of two ways. The panel
could find that the surety had undertaken performance,
waiving the limits of the bond. In such a situation, the
surety could naturally claim the payments it made on
behalf of All-Pride, but would be liable for a much larger
total amount. The plaintiff contends that the only other
option available to the panel was to find that the plaintiff
has not undertaken to perform the contract, had not waived
the amount of the bond as the limit of its liability, and
consequently was liable for the amount of the bond, $325,-
000. So far, all the parties are in agreement.
The plaintiff next argues that if the defendant surety
did not elect to perform, it must pay the entire amount
of the bond, regardless of any amounts already advanced to
the contractor All-Pride. Put another way, the plaintiff
contends that the arbitration panel could not deduct the
$165,000 advanced by Indiana to the subcontractors “for
the benefit of the owner” in 1974; that both parties agreed
that it was the law that such credits could not be de-
ducted; and that the panel knew that such credits could
not be deducted. The plaintiff cites to § 13 of the award,
which declares that the surety had no right of damages
against the owner (Paducah), “either directly or by way
of set-off, assignment or subrogation,” as evidence that the
panel knew it had only one of two choices in computing
the award. The plaintiff concludes that the award of the
$165,000 credit is in manifest disregard of the law as the
A20
arbitration panel knew it. See Post-Hearing Memorandum
Brief of Paducah Associates, Ltd. at p. 16 (Exhibits at-
tached to Second Affidavit of Alan H. Lobley, Docket No.
25).
Were the plaintiff correct in its assertion that both
parties agreed both to the law as it applied to the credits
claimed by Indiana and that the arbitration panel knew that
it could compute damages in relation to those credits in
only one of two ways, this Court might then be required to
examine the “fundamental rationality” of the award and
determine whether the arbitration panel manifestly dis-
regarded the law.
An examination of the submissions to the arbitration
panel reveals, however, that Indiana had consistently
argued for a third method of computing its remaining lia-
bility to Paducah. The pre-hearing brief of Indiana In-
surance Company (Exhibit 2 attached to Second Affidavit
of Alan H. Lobley, Docket No. 25), at page 2, claims from
the very outset that it was released from liability to the
owner to the extent of the $160,000 it had already paid
under the bond. Indiana also argues, at page 8 of that
same brief, that such payments were made pursuant to the
contractual provisions of the bond. It is clear beyond
question that the surety was contending at arbitration (1)
that its total liability was limited to $325,000, the amount
of the bond, and (2) that its liability to Paducah was to be
reduced by the amount already advanced under the bond
provisions.
Whether Indiana was correct as a matter of law is a
question which this Court need not consider. It is suf-
ficient for purposes of review under 9 U.S.C. § 10 that
the arbitration panel was faced with three different legal
theories of recovery and chose one. Whether correct or
not, there was no “manifest disregard for the law.” The
A21
Court further specifically finds that the award manifests
a fundamental rationality. Without attempting to decipher
the law of suretyship, it appears to this Court that pay-
ments made by the surety on behalf of the owner may be
deducted from the amount of a bond in determining the net
amount owing by the surety to the assured.
The plaintiff's arguments with respect to the alleged
inconsistency between { 13 of the findings and the award
are not persuasive. The disallowance of damages for
Indiana as against the owner Paducah is consistent with
the crediting of payments made by the surety on behalf of
Paducah. Indiana had advanced at arbitration items of
damages against Paducah separate and distinct from the
claim that it had already advanced amounts under the
bond to subcontractors. Those claims for damages related,
at least in part, to the alleged breaches of contract by
the owner Paducah discussed and ruled on in favor of
Paducah in paragraphs 5 and 6 of the Award findings,
The findings and award of the arbitration panel will
not be disturbed as to the credits of funds previously ad-
vanced by Indiana for the benefit of Paducah in computing
the net liability of Indiana to Paducah.
II. Defendant’s Counterclaim for Modification
or Correction of the Award
The plaintiff has moved for Summary judgment as to
the defendant’s motion to modify the wording of the award.
The plaintiff’s counterclaim recites that Paducah was re-
quired under the terms of the bond to submit all of its
claims to arbitration; that Paducah submitted a claim to
the arbitration panel; that it did not rely upon or assert
any claim for slander of title to the arbitrators and that
the arbitration award is “in error” to the extent that it
does not reflect the submitted ;stipulation of the parties
=
A22
that all claims and other questions between the parties
arising out of the contract or the breach thereof were to
be submitted to that arbitration.
The defendant seeks to incorporate additional language
into the order reflecting the arbitration panel’s disposition
of only certain issues - as opposed to all claims arising in
this dispute - because Paducah did not assert such claims.
The plaintiff’s motion for summary judgment is based
in part upon the assertion that not only did the parties not
submit the issue of slander of title to the arbitration panel,
but that the defendant apparently admitted that the slander
of title issue had been specifically excluded by the arbi-
trators at the hearings. The plaintiff also proffered the
exhibits attached to the plaintiff's amended complaint
herein as evidence that the slander of title issue had not
been submitted by either party.
The defendant has replied that it expressly denied
the plaintiff's request for an admission that the arbitration
panel had ruled the slander of title issue to be outside
of the submissions of either party, and concluded that there
are no facts before the Court upon which to predicate a
summary judgment.
The state of the pleadings on this issue are particularly
muddled. The Court will attempt to unravel, without
breaking, the threads of issues, arguments and exhibits.
FIRST, it is axiomatic under Rule 56 that there must
be no issues of material fact and the moving party must
be entitled to judgment as a matter of law.
SECOND, the party opposing the motion may not rest
upon its pleadings as to fact issues, and must come for-
ward with affidavits or other appropriate submissions if it
wishes to demonstrate that issues of fact remain, Rule
A23
96(e), F.R.Civ.P., Williams v. B. & O. R. Co., 303 F.2d 323,
324 (6th Cir., 1962): see generally 10 Wright & Miller
Federal Practice and Procedure $ 2739.
One of the alleged “fact issues” relevant to this motion
is the alleged admission by the defendant of “Plaintiff's
First Request for Admissions herein, Item +2, Second
Summary, pages 37 and 48.” Neither the request nor the
admission (or denial) are before this Court.’ The Court
cannot, therefore, consider the allegations that the defen-
dant either admitted or denied, in a request for admiss-
sions, the fact that the panel had specifically excluded
the slander of title issue from consideration. That de-
termination is without prejudice to the relevancy - if any -
of the fact that the arbitration panel did or did not so
state that it was not deciding the slander of title issue at
the hearing.
What is before the Court is verified evidence of the
submissions by the parties to the arbitrators: the undated
second stipulation of the parties to the arbitrators (Ex-
hibit 11 to the second affidavit of Alan H. Lobley, Docket
No. 25); the previously-stated undisputed chronology of the
mechanic's lienholder suits, which were filed after the first
arbitration hearing had been completed; and the state-
ment of the arbitration award specifically excluding the
slander of title issue from its consideration (€ 7). The
Court concludes that, on the present record, there is no
evidence that the slander of title issue was presented to
the arbitration panel, or that they considered it. The
record demonstrates that just the opposite occurred. Given
that undisputed state of facts, the defendant cannot suc-
3. On the off chance that either or both of these items are
buried within the mass of documents provided by the parties,
it may be noted that no identification or Citation to an exhibit
has been provided to the Court.
A24
cessful.y maintain that the arbitration award §| 7 is mani-
festly in disregard of the law or that it lacks fundamental
rationality.
It appears, furthermore, that there is no evidence at
this time as to where, when or even if the slander of title
issue has ever been raised. It certainly is not clear from
these pleadings that any slander of title action had ever
commenced in any Court, let alone by the time issues were
to have been submitted to the arbitration panel. If such
an action did exist before the arbitration commenced, this
Court could not, on this record, lay the blame, if any, ex-
clusively at the feet of Paducah. Claims by subcon-
tractors other than those submitted by either Paducah or
Indiana to the arbitration panel apparently escaped de-
tection prior to the filing of the Cole Lumber suit in Mc-
Cracken County on October 17, 1975.
To conclude, there is no evidence of a “manifest dis-
regard of law” or of any lack of fundamental rationality in
the arbitration award’s treatment of possible claims for
damages arising from mechanic’s lien as set forth in § 7
of the award, and no modification (under § 11) or vaca-
tion (under § 10) may be awarded as to the counterclaim
of the defendant Indiana. Summary judgment will be
granted to the plaintiff as to the defendant’s counterclaim,
and the counterclaim will be dismissed.
III, Discharge of Arbitration Award
This Court is in a peculiar position in relation to the
request of Paducah to confirm the arbitration award and
to enter a judgment thereon. The Court has no problem
with a confirmation consistent with the preceding parts of
this opinion, nor any reluctance in entering a judgment
thereon. The crux of the problem is determining whether
the drawing-down of the interpleaded funds in the Cole
2 a
A25
Lumber case constitutes a discharge of - or at least a credit
towards - the amount due.
A review of the current status of the impleaded funds
reveals the following facts:
1. Indiana has interpleaded the amount of the award
plus the interest due up to and including the date of
interpleader.
2. Indiana claims that the amount interpleaded into
Court is the entire amount owing under the bond as
fixed by the arbitration.
3. Paducah claims the entire amount of the interpled
funds is owing to it under the arbitration award.
4. Paducah, Indiana and the lien creditors have stip-
ulated to the distribution of the interpled funds with-
out prejudice to the rights of the parties to finally ad-
judicate claims in the suit (except that the lien cred-
itors were to release their liens upon Paducah real
property ).
0. Paducah has, rursuant to Court order based on the
stipulation, drawn down the interpled funds and dis-
tributed them to the lien creditors.
6. The McCracken County Court has not determined
whether Indiana is liable to the subcontractors as
third-party beneficiaries to the bond beyond and aside
from any arbitration determination as between Pa-
ducah and Indiana.
7. The McCracken Court has not determined whether
the entire amount of the interpled funds is due to
Paducah.
One other important fact enters into this determina-
iton: The asserted third-party beneficiaries of the bond,
A26
i.e., the Kentucky subcontractors of All-Pride, were not
parties to the arbitration now being considered by this
Court. Given this set of facts, it cannot be said whether
or not Indiana has discharged its obligation under the arbi-
tration award.
Should the McCracken Circuit Court find that Indiana
has obligations under the bond to any or all of the sub-
contractors, then, to the extent those awards were paid
out by Paducah from the drawn-down funds in the registry
of the Court, the drawn-down funds would not have satis-
fied the amounts which the arbitration panel awarded as
between Paducah and Indiana. The Court here notes and
emphasizes that its confirmation of the arbitration award
operates only to fix the amounts due as between those two
parties, and does not in any way adjudicate claims raised
by creditor subcontractors under Kentucky law and in a
Kentucky court.
On the other hand, should the McCracken Circuit Court
find that none of the creditor subcontractors have valid
claims against Indiana and that the drawn-down funds
were properly paid to Paducah in satisfaction of the claim
raised in that Court by Paducah that it was due the funds
in satisfaction of the arbitration award, this Court would
find the award satisfied. There are, of course, other pos-
sible resolutions of the dispute over the interpled funds
which this Court can neither anticipate nor could it speak
to at this time. Suffice it to say that the determination
of the discharge of the judgment and any order of execution
by this Court must await the determination of the claims
and rights of the parties in the Cole Lumber action.
The defendant Indiana has argued in its reply memo
that under Kentucky law none of the subcontractors may
sue as third-party beneficiaries to the particular type of
bond at issue. That is not a question which is properly
A27
before this Court. The Kentucky Court must properly
answer that question, and this Court would be most pre-
sumptive to hazard any opinion upon that point of law.
CONCLUSION
The award in the arbitration between Paducah and
Indiana is confirmed pursuant to 9 U.S.C. § 9.
The defendant’s motion for summary judgment as to
the plaintiff's claims for amendment of the amount of the
award is granted, and the plaintiff’s cross-motion for sum-
mary judgment on that same issue is denied.
The plaintiff's motion for summary judgment as to
the defendant’s counterclaim seeking to amend § 7 of the
award is granted, and the defendant’s counterclaim is dis-
missed.
The parties may submit a judgment consistent with
this memo. Execution upon any judgment will be stayed,
however, pending the resolution of claims in Cole Lumber
& Supply Co., Inc. v. McBride, Civil Action No. 14,876, Mc-
Cracken Circuit Court, Kentucky.
/s/ Timothy Morgan
United States District Judge
A28
APPENDIX D
79-3157
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
PADUCAH ASSOCIATES, LTD.,
Plaintiff-Appellant,
V.
INDIANA INSURANCE COMPANY and ALL PRIDE
DEVELOPMENT CORPORATION,
Defendants-Appellees.
ORDER
(Filed December 15, 1980)
Before: LIVELY and ENGEL, Circuit Judges and PECK,
Senior Circuit Judge
Appellant having filed a petition for rehearing with
this court, and this court having considered said petition
and being duly advised in the premises,
IT IS ORDERED that the petition for rehearing be and
it is hereby denied.
ENTERED BY ORDER OF THE COURT
/s/ John P. Hehman
Clerk
A29
APPENDIX E
STATUTORY PROVISIONS AND RULE OF CIVIL
PROCEDURE INVOLVED
9 U.S.C.
§ 3. Stay of Proceedings where issue therein referable
to arbitration
If any suit or proceeding be brought in any of the
courts of the United States upon any issue referable to
arbitration under an agreement in writing for such
arbitration, the court in which such suit is pending,
upon being satisfied that the issue involved in such
suit or proceeding is referable to arbitration under
such an agreement, shall on application of one of the
parties stay the trial of the action until such arbitration
has been had in accordance with the terms of the
agreement, providing the applicant for the stay is not
in default in proceeding with such arbitration.
$ 9. Award of arbitrators; confirmation; jurisdiction:
procedure
If the parties in their agreement have agreed that
a judgment of the court shall be entered upon the
award made pursuant to the arbitration, and shall spec-
ify the court, then at any time within one year after
the award is made any party to the arbitration may
apply to the court so specified for an order confirming
the award, and thereupon the court must grant such
an order unless the award is vacated, modified, or
corrected as prescribed in sections 10 and 11 of this
title. If no court is specified in the agreement of the
parties, then such application may be made to the
United States court in and for the district within
A30
which such award was made. Notice of the applica-
tion shall be served upon the adverse party, and there-
upon the court shall have jurisdiction of such party as
though he had appeared generally in the proceeding.
If the adverse party is a resident of the district with-
in which the award was made, such service shall be
made upon the adverse party or his attorney as pre-
scribed by law for service of notice of motion in an
action in the same court. If the adverse party shall
be a nonresident, then the notice of the application
shall be served by the marshal of any district within
which the adverse party may be found in like manner
as other process of the court.
§ 10. Same; vacation; grounds; rehearing
In either of the following cases the United States
court in and for the district wherein the award was
made may make an order vacating the award upon
the application of any party to the arbitration—
(a) Where the award was procured by corrup-
tion, fraud, or undue means.
(b) Where there was evident partiality or cor-
ruption in the arbitrators, or either of them.
(c) Where the arbitrators were guilty of miscon-
duct in refusing to postpone the hearing, upon suf-
ficient cause shown, or in refusing to hear evidence
pertinent and material to the controversy; or of any
other misbehavior by which the rights of any party
have been prejudiced.
(d) Where the arbitrators exceeded their powers,
or so imperfectly executed them that a mutual, final,
and definite award upon the subject matter submitted
was not made.
Bk at
A31
(e) Where an award is vacated and the time with-
in which the agreement required the award to be made
has not expired the court may, in its discretion, direct
a rehearing by the arbitrators.
§ 11. Same; modification or correction; grounds; order
In either of the following cases the United States
court in and for the district wherein the award was
made may make an order modifying or correcting the
award upon the application of any party to the arbitra-
tion—
(a) Where there was an evident material mis-
calculation of figures or an evident material mistake
in the description of any person, thing, or property
referred to in the award.
(b) Where the arbitrators have awarded upon a
matter not submitted to them, unless it is a matter not
affecting the merits of the decision upon the matter
submitted.
(c) Where the award is imperfect in matter of
form not affecting the merits of the controversy.
The order may modify and correct the award, so
as to effect the intent thereof and promote justice be-
tween the parties.
Federal Rules of Civil Procedure
Rule 56. Summary Judgment
(a) For Claimant. A party seeking to recover
upon a claim, counterclaim, or cross-claim or to ob-
tain a declaratory judgment may, at any time after
the expiration of 20 days from the commencement of
the action or after service of a motion for summary
judgment by the adverse party, move with or without
A32
supporting affidavits for a summary judgment in his
favor upon all or any part thereof.
(b) For Defending Party. A party against whom
a claim, counterclaim, or cross-claim is asserted or a
declaratory judgment is sought may, at any time, move
with or without supporting affidavits for a summary
judgment in his favor as to all or any part thereof.
(c) Motion and Proceedings Thereon. The mo-
tion shall be served at least 10 days before the time
fixed for the hearing. The adverse party prior to
the day of hearing may serve opposing affidavits.
The judgment sought shall be rendered forthwith if
the pleadings, depositions, answers to interrogatories,
and admissions on file, together with the affidavits, if
any, show that there is no genuine issue as to any ma-
terial fact and that the moving party is entitled to a
judgment as a matter of law. A summary judgment,
interlocutory in character, may be rendered on the
issue of liability alone although there is a genuine
issue as to the amount of damages.
(d) Case Not Fully Adjudicated on Motion. If
on motion under this rule judgment is not rendered
upon the whole case or for all the relief asked and a
trial is necessary, the court at the hearing of the motion,
by examining the pleadings and the evidence before
it and by interrogating counsel, shall if practicable as-
certain what material facts exist without substantial
controversy and what material facts are actually and
in good faith controverted. It shall thereupon make
an order specifying the facts that appear without sub-
stantial controversy, including the extent to which the
amount of damages or other relief is not in controversy,
and directing such further proceedings in the action
A33
as are just. Upon the trial of the action the facts so
specified shall be deemed established, and the trial
shall be conducted accordingly.
(e) Form of Affidavits; Further Testimony; De-
fense Required. Supporting and opposing affidavits
shall be made on personal knowledge, shall set forth
such facts as would be admissible in evidence, and shall
show affirmatively that the affiant is competent to tes-
tify to the matters stated therein. Sworn or certified
copies of all papers or parts thereof referred to in an
affidavit shall be attached thereto or served therewith.
The court may permit affidavits to be supplemented or
opposed by depositions, answers to interrogatories, or
further affidavits. When a motion for summary judg-
ment is made and supported as provided in this rule, an
adverse party may not rest upon the mere allega-
tions or denials of his pleading, but his response, by
affidavits or as otherwise provided in this rule, must
set forth specific facts showing that there is a genuine
issue for trial. If he does not so respond, summary
judgment, if appropriate, shall be entered against him.
(f) When Affidavits are Unavaiiable. Should it
appear from the affidavits of a party opposing the
motion that he cannot for reasons stated present by
affidavits facts essential to justify his opposition, the
court may refuse the application for judgment or may
order a continuance to permit affidavits to be ob-
tained or depositions to be taken or discovery to be
had or may make such other order as is just.
(g) Affidavits Made in Bad Faith. Should it ap-
pear to the satisfaction of the court at any time that
any of the affidavits presented pursuant to this rule
are presented in bad faith or solely for the purpose of
—
A34
delay, the court shall forthwith order the party em-
ploying them to pay to the other party the amount of
the reasonable expenses which the filing of the affi-
davits caused him to incur, including reasonable at-
torney’s fees, and any offending party or attorney may
be adjudged guilty of contempt.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.