Petition — Sewell v. Phillips Petroleum Co.

Supreme Court brief1981

Ask Donna

What actually matters in this document.

Text

. fi

| Supreme Court, U. a

Fil ED

DEC 8 1980

Go

—

3

—

Peony

©

fe.

MICHAEL ROD

in the Supreme Court of the

Hnited States

OcToBER TERM, 1980

GLENN H. SEWELL,

Petitioner,

v.

PHILLIPS PETROLEUM COMPANY,

a Delaware Corporation,

Respondent.

PETITION FOR A WRIT OF CERTIORARI

TO, OR FOR AN ORDER REQUIRING

EN BANC REVIEW BY, THE

UNITED STATES COURT OF APPEALS

FOR THE TENTH CIRCUIT

SAMUEL KING

301 Gump & Ayers Building

2120 South 1800 East

Salt Lake City, Utah 84106

Attorney for Petitioner,

801-486-3751

RAY R. CHRISTENSEN

900 Kearns Building

Salt Lake City, Utah 84101

Attorney for Respondent

801-355-3431

QUESTIONS PRESENTED FOR REVIEW

In this case, one party or the other submitted an

intentionally misleading brief in order to lead the Circuit

Court into a mistaken opinion. The Court acknowledged

this happened, but refused to review to determine

whether its opinion was in error, whether it had followed

the false brief, and so refused to review whether it had

done justice or injustice.

From this factual context, the following issues arise:

I. When an appellate court buys the Brooklyn

Bridge from a man in a checkered suit, what duty has

it to rectify the situation

II. Is it not the duty of an appellate court to

wrestle with the tar baby of attorney misconduct, when

only by doing so can it be assured that it has not done

injustice to a litigant?

III. Is it appropriate for an appellate court, when

it acknowledges that it does not know the facts of the

case due to it being misled as to them by one attorney

or the other, to dispose of the case on the basis that by

referring the matter of misconduct to an outside agency

over which it has no control, here a Bar Commission,

it is doing justice ?

IV. When an appellate court has to face the fact

that it has been misled, is it appropriate for that appel-

late court to refuse to review the Findings of Fact of

the trial judge on second, non-jury trial, and to deny

any hearing on the issue of fraud on the court on a

it

motion pursuant to Rule 60(b) (3) FRCP.

V. Due process. As a litigant’s interest in a judg-

ment is a constitutionally protected property right, does

due process entitle him to have his case factually re-

viewed on appeal?

VI. Encouraging candor by litigants. Whether it

is the duty of an appellate court, when it acknowledges

that one party or the other has attempted to mislead it,

to determine what misconduct has occurred and deal

with the offenders appropriately, so that such conduct

is discouraged, so that the stature of the law and the

courts is not diminished and to serve as a warning that

appellate briefs must be candid so appellate courts can

more expeditiously and accurately perform their func-

tions.

VII. Punitive damages. Whether punitive dam-

ages are not appropriate to deter an intentional industry-

wide labor practice expressly forbidden by safety laws,

under circumstances in which each violation has a low

probability of death or injury, but the violations are re-

peated so many thousands of times each year that mathe-

matically such consequences are bound to occur

VIII. As the United States Supreme Court acts

as initial reviewer of errors occurring in the first instance

in the United States Circuit Courts, shouldn’t Certiorari

or other appropriate relief, as here return to the Circuit

Court with an order requiring an en banc review, issue

more readily than in cases where appellate courts have

had prior opportunity to correct error occurring at lower

judicial levels ?

111

IX. Does an attorney have the duty to persevere

when his client is the victim of judicial injustice both in

order to do justice to his client, and also to protect the

judicial system of which he is a part?

X. Can it really happen in the federal courts of the

United States that a party can lose a legitirnate case

because an appellate court cannot bring itself to admit

it was misled, and that counsel before it have learned

how to manipulate it?

XI. The Federal Rules of Appellate Procedure,

28(c) FRAP, allow a respondent to freely reject and

restate the facts of a case. Should not this rule be re-

vised to require the respondent, as many state courts

require, to specifically cite to the record for each state-

ment he denies and for such substitution he proposes,

so as to bind him tightly to the facts and make it easier

for the reviewing court to pinpoint and resolve disputes,

and to identify the parties who stray from the record?

(See Utah Rules of Civil Procedure, 75(p) (2) ).

Vv

TABLE OF CONTENTS

Page

OPE BPE MUPEE Ee MEME APE ovcevcccecbiccescsnseccssseceardcuccscecaneces 2

MT IY orice ccscckcccccccnsesacsonacsusnckceeccsceceses. 2

QUESTIONS PRESENTED FOR REVIEW | i

PROVISIONS OF LAW uno... ccccccccccsccesesedecesese. 2

EMRE Me NSIe De OR ACTS occncncncs on cscccccscsesececess. es 3

FEDERAL JURISDICTION IN

MOONE RIUM PANO cov ccdcncncnsesiccesececncsseesecscrcarsz 22

REASONS FOR ALLOWANCE OF WRIT .. 22

CONCLUSION

APPENDIX A-.

First opinion of the Tenth Circuit

I I oe oars cchesnrverccossccssecedens A-!

APPENDIX B—

Opinion of the District Court for the

I ci aia ethaentecce B-1

APPENDIX C—

Second opinion of the Tenth Circuit

PIE OE Fe iano cscs sasctcccceseseceascccoseccose C-1

APPENDIX D—

Uniform Building Code, Chapter 70,

Excavating and Grading 2.0.0...0......cccccccecesseceeee. D-1

APPENDIX E—

OSHA Regulations 2.0.0.0... ccc cccecceccssesseeoeeoes 1-1

Page

APPENDIX F—

Salt Lake Tribune Newspaper Article ............ k-1

APPENDIX G —

Circuit Court Order, Sept. 10, 1980.00.00... G-1

CASES CITED

Buehler v. Whalen and Ford Motor Company,

374 NE2d 460 (Ill. 1977) 000.000.0000 24

Dartmouth College v. Woodard,

a Ltt... . 26

Dayton v. Free, 148 P 408 (Utah 1937) 17

Davis v. Summerfield,

45 SE 654 (N.C. 1908) ooo ccccccccccecccceeeees 17

Funk v. General Motors Corp.,

220 NWe2d 641 (Mich. 1974) 0000. 17

Green v. Shepherd Construction Co.

(N.D. Ga.) as cited in Bollard v.

Volkswagon of America, Inc., 56 FRD 569

at note pp. 582-583 0... scheint 23

Henigan v. Atlantic Refining Co.,

282 FS 667 (E.D. Penn. 1967) _....... 17

Lehnen v. Dickson, 148 U.S. (1893) at 26

Lindler v. District of Columbia,

502 F2d 495 (D.C. Cir., 1974) 0. 17

Nauman v. Harold K. Beecher & Assoc.,

467 P2d 610 (Utah 1970) 0 18

Page

Nelson v. Mecham, 155 F.1 (9th Cir.) 2.0.0.0. 19

Olson v. Hayden Holding Co.,

eS | 17

Parrott v. Ford Motor Company,

52 FRD 120 (D.C. Mo. 1969) ....cccccccccccceececoe. 24

Percival Construction Co. v. Miller and Miller

Auctioneers, 532 F2d 166 (10th Cir., 1976) .... 8

Quinones v. Township of Upper Moreland,

oe vee tee Oe. 2907) .............................. 17

Ross v. Hartman, 139 2d 14 (D.C. App. 1943) .... 18

Rozier v. Ford Motor Company,

578 F2d 1882 (5th Cir. 1978) 0.0... 23

Semanchuck v. Fifth Ave. & Thirty-Seventh St.

Corp., 49 NE2d 507 (N.Y. 1948) oo... 18

Sposito v. Zeitz, 127 NW2d 45 (Wis. 1965) .......... 17

Summers v. Crown Constr. Co.,

458 F2d 998 (C.A. 4, 1974) ooo. ecccccccccceccccccseeee 17

Tennant v. Peoria & P.U.R. Co.,

821 US 29 (1944), reh den 321 US 802 ............ 8

Trecartin v. Mahony Troast Constr. Co.,

87 A2d 349 (NJ. 1952) occ ccccceeeccceccseecsseeseees 17

U.S. v. Jefferson Electric M anufacturing Company,

EY SOTSSISS a 27

U.S. v. Ohio Power Co., 353 US 98 ....... 19

Vit

Page

CONSTITUTIONAL PROVISIONS

Fifth Amendment, United States Constitution .... ii, 26

RULES

Rule 75(p) (2), Utah Rules of Civil Procedure ...... iii

Rule 00th) (8) PCP ooo 1, 2,3

PE M,N Reichman, iii

STATUTES

a te 22

OP UG SRE ah TO a 1, 2

AUTHORITIES

41 AmJr 2d, Ind. Contractors, §83, 37 ...........000.00-.. 18

57 AmJr 2d, Negligence, §24, 25, 36, 40, 239 .......... 18

Restatement of Torts, 2d Edition,

§410, 413, 415, 424, 427, 496EB ooo. 18

MISCELLANEOUS

Uniform MI Ra tno OE CO 8, 12

Occupational Safety and Health Act

NT 8, 12

Bee eae

in the Supreme Court of the

Hnited States

OctTospER TERM, 1980

GLENN H. SEWELL,

Petitioner,

V.

PHILLIPS PETROLEUM COMPANY,

a Delaware Corporation,

Respondent.

PETITION FOR A WRIT OF CERTIORARI

TO, OR FOR AN ORDER REQUIRING

EN BANC REVIEW BY, THE

UNITED STATES COURT OF APPEALS

FOR THE TENTH CIRCUIT

Petitioner, Glenn H. Sewell, respectfully prays

that a Writ of Certiorari issue to review the denial of

his motion for hearing pursuant to Rule 60(b) (3),

FRCP, alternatively for relief under the “All Writs

Act,” 28 USC §1651(a), (b).

Alternatively Petitioner seeks the court enter its

Order requiring the Circuit Court grant Petitioner an

2

en banc hearing of his motion for hearing under Rule

60(b) (3) and 28 USC §1651(a), (b):

Petitioner believes an order of this court requiring

the en banc hearing in the Circuit Court will be ade-

quate for his purposes.

OPINIONS BELOW

The two opinions of the Court of Appeals, unre-

ported, appear in the appendices hereto, the first opin-

ion being Appendix A, and the second as Appendix C.

The opinion of the District Court for the District of

Utah, Central Division, appears as Apendix B.

The Circuit Court order denying petitioner a hear-

ing pursuant to Rule 60(b) (3), FRCP, or relief pur-

suant to 28 USC 1651(a) (b), appears as Annex G.

JURISDICTION

The order of the Court of Appeals, Tenth Cir-

cuit, was dated and entered September 10, 1980, and

this Petition for Certiorari is timely filed within 90 days

of that date. This Court’s jurisdiction is invoked under

28 USC, §1254, 11.

PROVISIONS OF LAW

CONSTITUTION OF THE UNITED STATES,

AMENDMENT V.

“No person shall be . . . deprived of life, liberty,

or property without due process of law... .”

UNIFORM BUILDING CODE (UBC) is Ap-

pendix D.

3

OCCUPATIONAL SAFETY AND HEALTH

ACT (OSHA) is Appendix E.

28 USC §1651(a) (b).

Rule 60(b) (3), FRCP.

Rule 75 (p) (2) Utah Rules of Civil Procedure.

STATEMENT OF FACTS

As petitioner had a fair trial, but was denied due

process in the Circuit Court, this Statement of Facts

must cover the actual facts of the accident, and also

the events on appeal that led to dismissal of his case.

The interstices possible to alter a cases facts at

the appellate level are the crux of this petition.

At trial, the judge and jury hear the testimony, and

counsel are locked into argument and law consistent

with that testimony.

To the contrary, on appeal the court knows nothing

of the facts, and must rely on the briefs for the facts

and for the law appropriate to those facts.

This case is a study in how an appellate court can

be manipulated.

It is also a study in how difficult it is for the appel-

late court to acknowledge that it can be manipulated.

Here, a jury verdict, subsequently factually affirm-

ed by the trial judge at second trial rested on the testi-

mony of the respondent's own executives and employees.

The prevailing party, petitioner here, appealed,

even though he had won, claiming that not only should

he have had the general and special damages awarded

4

by the jury, but also punitive damages which the trial

judge refused to allow to go to the jury.

The appeal was important to respondent, the com-

pany, because the precedent to be announced by the

United States Circuit Court of Appeals would probably

stop a financially rewarding work practice that the com-

pany had carried out continuously for many years. The

practice would be stopped by the circuit decision be-

cause it was illegal and unsafe, producing deaths and

injuries. The facts of the case themselves are quite clear,

not complex, and they support the injured workman,

petitioner.

Recognizing the complexities an appellate court has

in evaluating facts, the company, through its lawyers,

simply filed a fictional brief. In that brief, every im-

portant fact was intentionally altered, the workman’s

theory of law which was valid, was modified into a

strawman theory which was not valid, the fact that the

work was illegal was supressed in the company’s brief,

so that in sum the Circuit Court was faced with a brief

setting forth a set of facts unrelated to the facts at trial,

and wrote its opinion not realizing that the work project

was illegal, and did not realize that the company in-

sisted the work be done, by the independent contractors

that it used, in that illegal manner.

The Circuit Court relying in good faith chose be-

tween two irreconcilably conflicting briefs by adopting

the fictional brief and wrote its opinion based thereon.

This resulted in an appellate opinion contrary to the

jury verdict.

5

On non-jury retrial, the trial judge summarized the

facts showing them clearly to be in favor of the working

man and opposed to the company’s position. The trial

judge, however, referred the matter back to the Circuit

Court for further consideration stating that he was

bound by is opinion of dismissal.

On second appeal, heard by a three judge panel,

the Circuit Court had before it the Findings of Fact

of the trial judge and also Petitioners brief meticu-

lously outlining the falsities of the company’s position in

its prior brief. It affirmed its first opinion.

Based thereon, one judge dissented stating, “There

has been a miscarriage of justice.”

The concurring judge agreed factually with the dis-

sent but nevertheless sided with the writer of the ma-

jority opinion for two reasons. First, he acknowledged

that the briefs were irreconcilable and that one attorney

or the oth r had misled the court, but dealt with this by

referring the matter to the State Bar Commission of the

attorneys as a solution to the ethical problem. In so

doing he lost sight of the fact that he was denying

justice to one party and rewarding the misleading party

with a judicial victory. Second, he ruled that the second

appeal was simply a belated attempt at rehearing of the

first appeal and so ineffective. Nevertheless, he sided

factually with the dissenting opinion.

The writer of the majority opinion had written the

original majority opinion, and refused absolutely to re-

view the findings of fact of the trial judge on second

6

trial, stating remariably that there was no new evidence

to be reviewed.

On subsequent submission of the matter to the Utah

State Bar Commission, it refused to review the conduct

of the Company's attorney, he being a past president of

the State Bar Association, (see Appendix F) but

bought Petitioner's attorney before it on charges of un-

ethical conduct for having filed a brief in which he com-

plained of misconduct of opposng counsel. After ex-

haustive factual hearing, the attorney was exonerated,

it appearing that all of his charges of misconduct were

specifically documented.

Accordingly, the case is one where a jury, a trial

judge, a State Bar Commission and two appellate judges

acknowledge that the petitioner has a_ legitimate

case and is entitled to his verdict.

Only the single judge author of the majority opin-

ion persists alone in the view that the case was properly

decided by him on the first appeal.

When Petitioner filed his Rule 60(b) (3) Motion

on review, the Circuit Court, acting though two judges,

the majority and concurring judges, refused to recon-

sider the matter nor to submit it to the Circuit Court

for en banc review as prayed, and summarily dismissed

the working man’s motion without hearing before a re-

sponsive brief from Respondent had even been filed.

Petitioner's back was broken by a cave-in of a dirt

excavation wall 11 feet high, at a service station owned

>

by Respondent. The excavation was to be used to house

a gasoline tank. It’s walls were vertical, neither sloped

nor shored.

To avoid repetition, the reader is referred to the

findings of Trial Judge Anderson, Appendix B and to

the dissenting opinion of Circuit Judge Doyle, Appen-

dix C. The heart of these findings was stated by Judge

Anderson as follows:

“Here the defendant company had vast experi-

ence in excavation and installation work, had an

engineering department trained in precisely this

kind of work and in this very community had pre-

viously contacted for many such jobs and been

familiar with the local law requiring sloping. Not-

withstanding, the company drew plans for the

work leaving out the sloping, an expensive addi-

tion, and put it out to bid. The trial court was

persuaded that under such circumstances, where

the company gained an economic benefit from

putting out a job for bid with a drawing of the

work without sloping, an issue of whether this

was negligence of the company should be pre-

sented to the jury, the theory being that such may

be an exercise of control that would deprive the

company of protection of the contract placing

responsibility with the independent contractor,

but without making the company the plainiff’s

employer.”

The fundamental concept to be applied in under-

standing the factual problems at the appellate level is

that on appeal, the party not entitled to favorable re-

view candidly admit evidence supporting the opposing

party. Petitioner was entitled to such favorable review.

8

Tennant v. Peoria & P.U.R. Co., 8321 US 29 (1944),

reh den 321 US 802, Percival Construction Co. v. Mill-

er and Miller Auctioneers, 532 F.2d 166 (10th Cir.,

1976).

The evidence taken a: trial which led to Judge

Anderson’s factual conclusions was not admitted by re-

spondent on appeal. As conclusions grow from evidence,

this led the Circuit Court to wrong conclusions when

it adopted the companies brief as the basis for its de-

cision.

This specific testimony must be reviewed.

The job was illegal.

The Uniform Building Code was first enacted

in 1924, and since has been generally adopted nation-

wide. It requires as a mandatory condition that no

excavation over 5 feet deep be made without first

obtaining an excavation permit. This permit will not

issue unless the application indicates adequate detail

for sloping or shoring to insure that the excavation can

be done safely. OSHA has similar requirements. Be-

cause OSHA is enforceable by government, not private

litigants, its use at trial was evidentiary of safe labor

practice rather than the mandatory standard imposed

by the UBC.

Because the excavation admittedly conformed with

neither the Uniform Building Code nor OSHA, the

company stipulated at trial to pertinent excerpts from

9

those being received as physica! exhibits by the jury.

They were appended verbatim to petitioner's original

brief on appeal, and are appended here as appendices

“D’ and “E.”

The independent contractor, Mr. Eckman, hired by

the Company to do the job was per se negligent due to

his violation of the safety law.

The only question at trial was whether respondent

shared in Kckman’s negligence.

The company’s brief on appeal never mentions

either the UBC or OSHA. This was for a purpose.

Its intent to mislead the Circuit Court is clear. The

UBC was the law of the case. There was no possible

legitimate manner in which the company could omit

dealing with it in its brief. To do so though could well

have led the appellate court to find the company was

liable on a theory of non-delegable duty imposed by law.

Omitting this law from its brief was comparable to

an auto accident litigant hiding on appeal that he ad-

mitted at trial that he ran a red light, and instead pre-

senting his case on appeal as one of negligence being

solely a matter of reasonable conduct as the only legal

issue in a case with no traffic controls present.

In this, the company brilliantly succeeded.

Having been guided away from the basic, manda-

tory safety law of the case, the Circuit Court addressed

itself to customary negligence issues such as the exist-

10

ence of known dangers, and never recognized the cen-

tral fact that the work was specifically illegal.

The Circuit Court in its opinion, made no refer-

ence to the Uniform Building Code at all, and indicated

no awareness that the project was illegal from the out-

set because of the failure to obtain the excavation

permit, and in process of work by failing to have the

excavation walls either sloped or shored.

In this, it followed respondent's brief which made

no reference at all to the Uniform Building Code, but

referred only vaguely to “technically required local ord-

inances.” This omission of the Uniform Building Code

and its specific requirements is reflected in the appellate

opinion which indicates generally that if any laws were

to have been complied with the contractor was to havc

done that.

Just as the Circuit Court failed to understand the

basic and specific illegality of the project, its finding

that respondent could reasonably rely on the contractcr

to comply with whatever general laws there were, was

also based on respondent’s brief which so stated, rather

than the evidence.

On this point, the evidence was substantial. The

contractor, Mr. Eckman, had over 30 years’ experience

in this specific line of work. Respondent's personnel

who testified were a construction inspector, Mr. How-

ell, with over 20 years’ experience, his superior, Mr.

Neuzil, in charge of these projects for three states, and

ll

his superior, Mr. Cameron, who was in charge of the

entire Western States Marketing Region.

All of these witnesses testified that without a single

exception respondent had never required the mandatory

excavation permit from its contractors.

This course of conduct covered over 20 years and

thousands of projects. Throughout that period, the com-

panies written contract required its contractors to obtain

the permit, but the company never in practice enforced

the contract, but instead invariably approved and paid

for work done illegally without the permit.

Accordingly, this contractual provision was abso-

lutely waived by Respondent. Its purpose was to avoid

the cost of sloping or shoring, and the simple mechanism

it used was to avoid giving notice of its excavations to

local government. It had learned it could succeed in

this practice because as the excavations are only open

one or two days, they would escape inspection.

For Respondent to admit either that the work was

illegal, or that it invariably required that the work be

done that way, would be virtually a confession of judg-

ment, as it would not then be entitled to the innocent

landowners exemption from liability.

On appeal, to avoid that consequence, the company

stated repeatedly that it relied in entire good faith on

the contract provision requiring the contractor to “ob-

tain all necessary permits,” and in good faith, believed

he would do so.

12

In so stating, the company kicked 20 years’ of experi-

ence under the carpet, and falsified the testimony of

its own personnel. Its submitted to the appellate court

facts that would win even though they were contrary

to the testimony of its own witnesses.

Thus, the appellate court’s finding that “Eckman

was under a contractual duty to comply with proper pro-

cedures,” is mistaken, a vital mistake of fact which

changes the entire posture of the case.

The appellate court failed to realize that the written

contract with proper immunizing language for respond-

ent, had no function other than to immunize, because it

had no relationship at all to respondent's invariable,

actual trade practice.

Perhaps the most startling example of intentional

falsifying bore on the issue of illegality of the work as

found by the trial judge to be known by the company.

The UBC and OSHA requirements are part of

standardized nation wide law. Both Mr. Cameron and

Mr. Neuzil testified precisely that they knew these re-

quirements and knew this job was illegal as were all the

jobs like it. UBC is, after all, “Uniform.”

The company could not admit it knew the job was

illegal and still maintain its posture of good faith reli-

ance that it believed the job was proceeding legally.

Accordingly, in an incredible distortion of the

record, it stated in its appellate brief that it did not

know and had no reason to know the “technically re-

13

quired local ordinances” and left these, if any, to the

contractor. The Circuit accepted this as true.

Having disposed of the specific requirements of

law as being the legal standard, the company had to

persuade the appellate court that there was no claim

against it arising for negligence from known dangers.

It did this by falsifying the facts relating to the

accident itself.

The original Circuit Court opinion found that the

work project was safe, in stable soil, and had no in-

herent hazards. In so finding, again it quoted respon-

dent's brief which stated, “There was no evidence as to

the cause of the cave-in,” that the excavation was in

“clay, which is stable,” that no person who saw the

excavation was aware of any hazards and that the ex-

cavation was safe.

Again, the testimony at trial was different from that

claimed by defendant.

Petitioner had a key witness, qualified as an expert

in soil mechanics, who testified that cave-ins are inevit-

able in excavations, the only question being whether

they will occur when a worker is in the excavation doing

his work of leveling its base so that the fuel tank can

sit solidly. The expert’s testimony was that moist soil

is plastic, and that almost all underground soil is moist.

He further testified that because soil weighs over 100

pounds per cubic foot, the pressure applied at the bot-

14

tom of an 11 foot excavation by the weight of earth

above it acts on the plastic character of the bottom earth

to force it to bulge out into the unsupported area. As

it bulges, it moves downward separating it from the

earth above, which then caves in.

This hazard analysis was confirmed by respondent’s

Mr. Neuzil, who has a degree in engineerng.

Mr. Neuzil testified on direct examination as a re-

spondent witness, that he thought the excavation safe.

On cross-examination, he not only made the above

quoted admission of his knowledge of the hazards of

cave-ins in general, but also admitted that he had been

so concerned about the safety of this particular excava-

tion that he had gone by the night before, but never-

theless did nothing, because he was bound by the in-

dustry practice of never sloping or shoring.

Again, the company had a problem, as to admit

that the project was unsafe, and it knew it was unsafe,

would probably lose the case.

Accordingly, it hid this evidence, and in its brief

on appeal, urged the project was safe as follows.

Petitioners key expert completely disappeared

from respondent’s brief, his testimony never mentioned,

and the impeaching izstimony by Mr. Neuzil was sim-

ilarly omitted. This, in turn, led the Circuit Court to

its mistaken conclusion that the work project was safe.

In fact, it stated,“ Mr. Neuzil was concerned about the

15

safety of an open pit and felt the excavation was safe

to work in.” It entirely missed the actual evidence.

Yet another instance of misleading is that Judge

Andrson and Judge Doyle both referred to respondent's

economic gains by omitting sloping and shoring. At

trial, appellant proved respondent had economic control

of the manner of work.

The Circuit Court stated, to the contrary, that re-

spondent paid for sloping and shoring. Respondent's

brief so claimed. What was the evidence?

The contractor, Mr. Eckman, had 42 of these jobs

to do at the time for respondent, had completed and

been paid for a number of them, and all had been un-

sloped and unshored.

Mr. Neuzil added to this. He prepared the draw-

ings and costs for the jobs, and then Mr. Cameron ap-

proved these before they were let out for actual bid.

Both men admitted that the jobs made no allowance for

the cost of sloping or shoring, made no allowance in the

size of excavation shown in the drawings for the space

involved in sloping or shoring, and any bid including

the cost of sloping and shoring would be too high and

not accepted by the company.

Mr. Mathis, partner of Mr. Eckman, testified that

if he included the cost of sloping and shoring in a bid,

he would not get the job, and if he included the cost _

16

as an extra during course of work, he would not be paid.

Thus, Judge Anderson's and Doyle’s findings are

supported by the record, while the Circuit Court, led by

respondent, is clearly in error on the vital point of re-

spondent paying for sloping or shoring.

Mr. Cameron was in charge of the department

which paid the contractors. He admitted that he

couldn't remember a single instance in his entire

experience with respondent in which he had paid for

the full scale sloping or shoring required by law.

Why did the company state in its brief that it would

pay for the cost of sloping or shoring when the evidence

was opposite

Again, this is simply another pivotal fact. The im-

portance of this fact cannot be overstated.

If the company admitted that, through the eco-

nomic coercion of refusal to pay for safety work, it knew

its contractors would do the project without such work,

then its claim that it expected the contractors to do the

work safely would be utterly impeached. This would

lead it to liability on the theory that it had an actual

and effective control of the unsafe manner of work by

control of the economic circumstances under which the

work was done. The Circuit missed this issue too.

The law considered by the Circuit Court and ap-

plied by it in its original opinion had similar miscon-

ceptions.

17

Petitioner had made no claim that respondent had

actual physical control of the contractor during the day

to day work. Petitioner’s theory was that such was im-

material because the character of the work had been en-

tirely shaped by respondent's plans, and economic

policies.

The knowledgeable landowner is liable when, as

here, every act done by the contractor was approved by

the landowner, if such acts are illegal or unsafe.

Funk v. General Motors Corp., 220 NW2d 641 (Mich.

1974)

Olson v. Hayden Holding Co., 70 P2d 463 (Utah 1937)

Dayton v. Free, 148 P 408 (Utah 1914)

Trecartin v. Mahony Troast Constr. Co., 87 A2d 349

(N.J. 1952)

Henigan v. Atlantic Refining Co., 282 FS 667 (E.D.

Penn. 1967 )

Quinones v. Township of Upper Moreland, 293 F 2d 743

(3d Cir., 1961)

Sposito v. Zeitz, 127 NW2d 45 (Wis. 1965)

Summers v. Crown Constr. Co., 453 F2d 998, (C.A. 4,

1974)

Lindler v. District of Columbia, 502 F2d 495 (D.C.

Cir., 1974) .

Davis v. Summerfield, 45 SE. 654 (N.C. 1903)

18

Semanchuck v. Fifth Ave. & Thirty-Seventh St. Corp.,

49 NE2d 507 (N.Y. 1943)

Nauman v. Harold K. Beecher & Assoc., 467 P2d 610

(Utah 1970)

Ross v. Hartman, 139 F 2d 14 (D.C.App. 1943)

41 AmJur 2d, Ind. Contractors, §33, 37

57 AmJur ud, Negligence, §24, 25, 36, 40, 239

Restatement of Torts, 2d Edition, §410, 413, 415, 424,

427, 496E

In respondent’s brief, it omitted petitioner's cited

cases, but instead set up a straw-man in which the issue

at trial was actual physical control by respondent of the

contractor, demonstrated that petitioner had not proved

this, and so argued that it was entitled to a reversal of

the jury verdict.

The Circuit Court in its opinion did not mention

petitioner's cases but only respondent's cases, based its

decision on lack of actual control, and commented in

passing that petitioner's other legal theories had not been

established. It stated factually that “on this record”

petitioner did not have a case.

That petitioner’s brief simply was not given ade-

quate reading by the Circuit Court when it wrote its

opinion is clear.

The matter now turns to post-appeal events.

19

On receiving the initial Circuit Court opinion, peti-

tioner chose to return in compliance with its mandate

to the trial court. Because the Circuit Court entirely

missed the salient facts of the case and petitioner's

theory of law, petitioner's research convinced him that

Judge Anderson could act in regard to those, the man-

date applying only to facts and theories it had covered.

U. S. v. Ohio Power Co., 353 US 98; Nelson v. Me-

cham, 155 F.. 1 (9th Cir.).

On retrial, Judge Anderson dismissed stating spec-

ifically that he had to do so because he had no choice

under the appellate opinion, but then set out the actual

facts of the case to serve as a guide to the appellate

court on its reconsideration, these facts being in dia-

metric opposition to those originally found by the Cir-

cuit and as submitted to it by respondent.

On the second appeal, petitioner submitted a brief

very precisely documenting the discrepancies between

the trial testimony and respondent's brief.

In its final and second opinion, the Circuit Court

dismissed petitioner's case with prejudice stating that

it had previously ruled on the facts and did not need to

review them. It refused to consider, review or even

mention Judge Anderson’s findings of fact.

The concurring opinion acknowledged that Judge

Doyle's dissent was prot#bly accurate on the facts, but

indicated that it was not the duty of the appellate court

to review conflicting charges between counsel and so

concurred to form a majority.

20.

The dissenting opinion found that on the facts peti-

tioner had an entirely legitimate case, that he had been

denied justice in appellate court and that his case should

be reinstated.

Petitioner then filed for Writ of Ceriorari to the

Supreme Court which was denied.

Petitioner then filed again with the Circuit Court

for review based on fraud on the court and himself.

It is from the peremptory Genial of that motion

that he now petitions for relief.

Two other actions of the Company on appeal serve

to illustrate the practiced case, and immunity from re-

prisal, with which it maneuvered the Circuit Court.

One was that it filed a motion to dismiss the first

appeal of petitioner on the ground that it was improp-

erly filed.

Petitioner responded with a short brief that pointed

out that the companies own citations supported peti-

tioner, and that the motion was groundless.

The Circuit Court agreed as it dismissed the com-

panies motion per curiam.

In so doing the court awarded no fees, imposed

no sanctions.

Thereby the company was the winner as its mo-

21

tion had stalled the legal machinery for months. One

of the major advantages a corporate litigant has over an

individual is staying power, and here the company gain-

ed a time advantage. The delay also gave it secondary

gain — if it couldn't avoid an adverse ultimate prece-

dent, by delay it could continue its work practice longer.

This gain persists today, five years after trial.

The second action of maneuver was the use of

Workmans Compensation laws as a defense to the law-

suit.

The company raised it as a defense in its answer

It then waived the issue at pretrial and trial because it

could only claim to be a third party beneficiary of the

Workmans Compensation ban against suit against an

employees employer if it admitted that it was in actual

control of the immediate employer.

As the company was not willing to concede this

actual control, it abandoned the defense, producing no

evidence on it at trial, submitting no instruction on it,

and not preserving it previously as a legal issue at pre-

trial.

Having thus utterly waived Workman’s Compensa-

tion as a defense at trial, what did the company do

with that defense on appeal when it needed any defense

it could find ¢

Right.

The company put a third of its appellate brief into

Workman’s Compensation as a viable defense.

yr

22

In so doing it made no mention of its having waived

the issue at trial, no mention of any kind, even though

a party on appeal has a clear duty to bring new or omit-

ted issues to the attention of the appellate court, so that

it can consider not only the issue, but also its standing.

Petitioner filed a rebuttal brief documenting the

waiver, which the Circuit Court accepted because it has

no word on Workman’s Compensation in its opinion.

The companies tactic was justified. It risked noth-

ing. The appellate court didn’t touch the problem of

the companies having deliberately raised an issue as

live rather than dead.

These last two examples don’t deal now directly

with the merits of the case, having been defeated. Their

only relevance is that they show again the willingness

of the companies attorneys to stop at nothing in their

attempt to win.

They also show why lawyers do this — there is no

penalty.

FEDERAL JURISDICTION

IN F<(RST INSTANCE

This case originally was brought in the United

States District Court for the District of Utah, Central

Division, invoking jurisdiction through 28 USC §1332.

REASONS FOR ALLOWANCE OF WRIT

In his concurring opinion, Judge McKay wrote:

“In a growing number of cases, adversarial riv-

alry has degenerated into accusations of un-

ethical conduct.”

23

There was a time after the Rules of Civil Pro-

cedure were first enacted when they served as a breath

of fresh air cleaning the body juris of stagnant growths.

Their high purpose was stated at the very outset

as Rule 1, which has three simple, magnificent, adjec-

tives. Civil litigation was to be “just,” “speedy,” and

“inexpensive.”

Since then, many attorneys and clients have real-

ized that the goals of their particular client are best

served by reversing the three concepts of Rule 1.

In the area of corporate law, for example, a corp-

oration which has a defective product will not want to

yield readily the complete details of the defects. As a

matter of corporate policy, it will want to do everything

in its power to obstruct verdicts against it. This is not

improper on the part of the corporation. It is not bound

by a professional code of ethics, but rather has respons-

ibilities to its stockholders.

Such a corporation will want an attorney who will

serve this corporate policy.

The question is whether the attorney will comply,

or will impose his professional standards.

As an example, the following are four recent cita-

tions involving one of the most respected American

corporations. In these opinions, it could scarcely receive

stronger adverse judicial language. However noth-

ing happened to it nor its counsel. Rozier v. Ford

Motor Company, 573 F 2d 18382 (5th Cir. 1978), Green

24

v. Shepherd Construction Co., (N.D. Ga.) as cited in

Bollard v. Volkswagon of America, Inc., 56 FRD 569,

at note 3 pp. 582-583, Parrett v. Ford Motor Company,

52 FRD 120 (D.C. Mo. 1969), Buehler v. Whalen and

Ford Motor Company, 374 NE2d 460 (Ill. 1977).

The conscientious attorney greatly needs the help

of the courts to tell his client, “No, you can’t get away

with this, you will have your pleadings stricken, and I

will be in trouble with the court.”

Other attorneys have no such moral dilemmas.

Their pragmatic approach is simply to determine what

has to be done to get the job done and do it, the end

justifying the means. ‘They proceed without ethical self-

examination. Ethics are spelled “WIN.”

This burden of holding litigants firmly to Rule 1

must be met by the courts themselves.

The knowledgeable attorney representing prestig-

ious clients knows that he is immune from disciplinary

proceedings by his Bar. Attached as Appendix F is a

newspaper article in Salt Lake City. Utah, in Novem-

ber, 1979. The pertinent item in the article is the state-

men, which was unrebutted, that no member of a pres-

tigious firm in Utah had been subject to Bar sanctions

in the preceding 25 years.

The above reflects only practice in a small state,

but to counsel’s understanding, it is typical of others.

This means that if courts are to protect themselves and

if courts are to assist counsel who have ethical and fi-

25

nancial dilemmas, and control attorneys who don't, the

courts must respond to this “growing number of cases”

by acting affirmatively.

A common tactic is the refusal to admit adverse

facts. The attorney sees that if he admits certain facts,

his client may well lose the case, and then he may well

lose the client. Fictions are substituted for those facts.

As Aaron Burr cynically observed, “The law is that

which is plausibly argued.” The tragedy is that he based

his observation on experience.

Judge McKay referred to the improper “charges

and countercharges of adversial misconduct,” and said

these should be in side briefs so as to not distract from

the main issues.

His wish to keep the mud outdoors is understand-

able, but he failed to make a vital distinction. In some

cases squabbling can be only that, distasteful but unim-

portant conflict. In other cases, and this is what h over-

looked, it is not matter that can be separated from the

main issues because it deals with them directly. That

occurs when the party with a losing case seeks to esca-

late it to a winner by improper tactics.

When that occurs, opposing counsel, to protect his

client and to keep the court from being led into error,

has the positive duty of clearly calling the matter to the

attention of the court.

There is a cheerful side to the judicial scrutiny. It

will frequently lead the court to a right verdict.

26

This case is a classic example. The appellate court

was so far misled that it actually reversed based on the

courts major instruction to the jury on the facts and on

the law, being so far wrong on both fact and law as to be

reversible error. If this were so, surely respondent would

have fought the instruction at trial and on appeal. How-

ever, respondent did, not mention the instruction once

in its brief on appeal.

In petitioner's Petition for Rehearing to the Cir-

cuit Court, he acknowledgd the mechanical difficulty

of the Circuit Court doing minute review of conflicting

argument and suggested that such matter could be re-

ferred to masters, to the trial court, or even to law

schools for an amicus report on the accuracy of the

pleadings.

The Circuit Court chose to do none of these and

allowed the injustice so stingingly attacked by J udge

Doyle in his dissenting opinion to become permanent

by simply dismissing the case.

A chose in action and a judgment are property

rights, and so protected by the Fifth Amendment.

A basic premise of due process of law is that the

court must find what the facts were. Lehnen v. Dick.

son, 148 US 71 (1893) at p. 77. Daniel Webster, in his

argument in the Dartmouth College case, Dartmouth

College v. Woodard, 4 US 518, (1819), declared what

is meant by due process of law is “a law which hears be-

fore it condemns; which proceeds upon inquiry and

renders judgment only after trial.”

27

In the event of irreconcilable conflict between

briefs, it was the duty of the court to accept those facts

most favorable to petitioner. U.S. v. Jefferson Electric

Manufacturing Company, 291 US 386. In the instant

case, the Circuit Court of Appeals failed to review the

findings of the Trial Judge, and refused to examine

the conflicting claims. Nevertheless, it entered its

opinion, denying petitioner his right to favorable review.

Excavation work is dangerous. Fach year there

are casualties in cave-ins. This is a case where a prece-

dent will serve to save lives.

CONCLUSION

For these reasons, a Writ of Certiorari should issue

to review the judgment and opinion of the Tenth Cir-

cuit, or alternatively, that the case be returned to the

Circuit Court for appropriate en banc review.

Respectfully submitted,

SAMUEL KING

301 Gump & Ayers Building

2120 South 1300 Fast

Salt Lake City, Utah 84106

Counsel for Petitioner

December 20, 1979.

ST

APPENDIX A

NOT FOR ROUTINE PUBLICATION

United States Court of Appeals

Tenth Circuit

Nos. 76-1030-31

GLENN H. SEWELL,

Appellant,

V.

PHILLIPS PETROLEUM COMPANY

a Delaware corporation,

Appellee.

Appeal From The

United States District Court

For The District of Utah

Central Division

(D. C. No. C 74-40)

Samuel King, Salt Lake City, Utah, for Appellant.

Ray R. Christensen, of Christensen, Gardiner, Jensen

& Evans, Salt Lake City, Utah, and Chris Wangsgard,

of Van Cott, Bagley, Cornwall & McCarthy, Salt Lake

City, Utah, for Appellee.

Before SETH and HOLLOWAY, Circuit Judges,

and CHII.SON, United States Senior District Judge*

SETH, Circuit Judge.

* Of the District of Colorado,

Sitting by Designation.

A-2

The plaintiff brought this action against the de-

fendant for personal injuries received when part of the

side of an excavation fell on him. The plaintiff was em-

ployed as a laborer by Harvey W. Eckman & Associ-

ates which had contracted with the defendant to install

10,000-gallon underground gasoline storage tanks at

forty-two of defendant’s service stations. The accident

occurred when the plaintiff was working at the bottom

of an excavation eleven and one-half feet deep.

The case was tried to a jury which returned a gen-

eral verdict for plaintiff, who is the appellant. The ap-

peal is taken from the refusal by the trial court to submit

the issue of punitive damages to the jury. The appellee

has taken a cross-appeal on the general verdict on the

ground that the instructions given as to the relationship

between the landowner and an independent contractor

were erroneous.

The defendant provided Eckman with the plans,

drawings, and specification for the installation of the

tanks. The drawings or specifications did not include

shoring or sloping of the walls of the pit. The contract

between the defendant and Eckman provided that the

defendant had the right to inspect the work being done,

and reserved “the right of suspending the whole or any

part of the work to be done hereunder at any time its

best interest appears to be served by so doing.” Eck-

man had the contractual duty to obtain all necessary

permits and to comply with all laws, building regula-

tions, and codes. He was to “diligently perform the

work in accordance with good industry practices and in

A-3

a workmanlike manner” along with the “entire respons-

ibility for examination of the site of the work and for

acquaintance with conditions that may exist or develop

during the term of the contract.” Eckman was also to

adhere to and enforce all safety and fire protection rules

of the defendant during the performance of the work.

Evidence was introduced that the defendant could

also inspect for safety. The defendant's representative

Neuzil knew that the excavation did not conform to

OSHA regulations. Such regulations were not applic-

able to the job. They were considered during the trial

as an expression of opinion as to proper practice. Neuzil

was concerned about the safety of an open pit and felt

that the excavation was safe for men to work in.

There is no question that Eckman was an inde-

pendent contractor. The plaintiff thus sought to impose

liability on the defendant on the theory that a land-

owner had breached a duty to a business invitee; or on

the theory that there was an exception to the inde-

pendent contractor rule because the owner retained con-

trol of the work; or that the work was inherently dan-

gerous.

The plaintiff submitted evidence on a punitive

damages allegation. The allegation was that the de-

fendant had deliberately and wrongfully acted in not

having the excavations shored or sloped and had shown

an indifference as to whether or not others were harmed.

This issue was not submitted to the jury because of in-

sufficient evidence.

A-4

To impose liability on the defendant there must be

shown an exception to the general rule of nonliability for

torts of an independent contractor either through the

exercise by the defendant of control over a delegable

duty, or by showing a nondelegable duty. Dayton v.

Free, 46 Utah 277, 148 P. 408.

On the matter of retained control, the evidence

shows that defendant had the right to inspect the work,

and could stop the work, according to the contract,

+. any time its best interest appears to be served by

so doing.” However this reservation does not of itself

override the general rule of nonliability by control.

United States v. Page, 350 ¥'.2d 28 (10th Cir.). There

was shown no active participation in the work by the

defendant's inspections of the job site. The defendant

never exercised control of the work and Eckman was

under a contractual duty to comply with proper pro-

cedures. Eckman had the basic duty to provide the

plaintiff with a safe place to work and guard against

dangers created by the work. Dayton v. Free, 46 Utah

277, 148 P. 408; Texaco, Inc. v. Pruitt, 396 I°.2d 237

(10th Cir.).

The plaintiff urges that the defendant actively par-

ticipated in the work because the drawings and specifi-

cations did not provide for sloping or shoring. It is

also asserted that the defendant acquiesced in unsafe

practices by its failure to correct them, by accepting the

work complete as evidenced by the payment, and by

having the contract provide that the work be performed

“to the entire satisfaction of the Company Representa-

A-5

tive in accordance with the drawings, plans, and speci-

fications furnished” by the defendant. The plaintiff

argues that by this the defendant was exercising control

over the manner in which the excavation was to be per-

formed, and was inherently dangerous. Dayton v. Free,

46 Utah 277, 148 P. 408.

Evidence was adduced that the bids by Eckman

were made without any allowance for sloping or shoring

and in accordance with the drawings. The contract

specifically provided that Eckman was to obtain all

necessary permits and to comply with all safety regu-

lations. Eckman testified that he was not aware of any

particular sk ping or shoring regulations. He testified

that his bids were based on a normal excavation with

firm soil for stable walls and without any water or other

problems. This particular excavation did have some

water which was pumped out but Eckman thought it

was safe. Eckman testified that if he encountered soil

problems, he would slope to the degree he felt necessary

to provide a safe excavation and the defendant always

paid him for it with no questions asked. The contract

had a provision for extra work. Under these circum-

stances, although the drawings and specifications did

not specify sloping, they in themselves do not show con-

trol in the absence of some affirmative act. United

States v. Page, 350 F.2d 28 (10th Cir. )

The court’s jury instruction No. 18 did not ade-

quately state the necessary “retained and exercised con-

trol” over the work to find liability for the cave-in. The

instruction required that the owner be aware of a known

A-6

risk or should have known and been aware of the con-

tractor's failure to guard against it, and that the owner

reserve the right to stop the work at any time when

safety requirements are not met. The awareness and the

right to stop do not show a “retained and exercised con-

trol” without some other active participation. ‘The in-

struction was clearly erroneous. The defendant, on this

record, did not retain control of the work.

The Utah courts have held that an injured party

has a cause of action against an architect who had know!-

edge or should have known of an unshored trench where

the architect had the contractual right and the duty to

stop the work until the unsafe condition had been

remedied. By the contract the architect was “to super-

vise and inspect all phases of the work being done”

along with the reserved right to stop work for noncom-

pliance. Nauman v. Harold K. Beecher & Associates,

19 Utah 2d 101, 426 P.2d 621. But in the subsequent

case, Nauman v. Harold K. Beecher & Associates, 24

Utah 2d 172, 467 P.2d 610, the court held that there

was insufficient evidence to show a breach of a duty

or conduct below a standard of care for an architect

where the walls of the excavation were sloped and the

plaintiff knew of the conditions and found them to be

safe. In a later case, Peterson v. Fowler, 27 Utah 2d

159, 493 P.2d 997, the court found no duty owed by the

archiect to the injured employee because he had noth-

ing to do with the scaffolding and his duty ran to the

owner to see that the building was properly erected so

that it would be safe for its intended purposes. The

distinction for the existence of a duty is based on one of

A-7

control because in Nauman the architect had the affirm-

ative duty to “supervise and inspect all phases” of the

job, whereas in Peterson he did not have this control.

The plaintiff urges that because the landowner

knew of the failure to slope or shore, it had a duty to

war or correct this violation, aud having failed to do

so, the landowner is liable for injuries to business visit-

ors. The landowner is under a duty to warn or guard

against concealed or latent conditions of danger on the

premises of which he has or ought to have knowledge

and of which the employee has none. Texaco, Inc. v.

Pruitt, 396 F.2d 237 (10th Cir.) ; Titan Steel Corp. v.

Walton, 365 I'.2d 542 (10th Cir.). Yet the danger of

the excavation is not inherent in the premises them-

selves, but it is a danger which arose from the prosecu-

tion of the work itself. Furthermore the danger of an

excavation caving in is not concealed or latent, and the

plaintiff had knowledge of this danger.

As for nondelegable duties which are described as

being “inherently dangerous work,” an excavation of

this type is not inherently dangerous although there are

safety precautions to be taken. Work that is inherently

dangerous is work that will probably, and not merely

may, cause injury if proper precautions are not taken.

Dayton v. Free, 46 Utah 277, 148 P. 408. Predict-

ability makes for a fine distinction between probably

and may, but this excavation does not fall under the

former. Furthermore, this Circuit has expressed “serious

doubts as to whether the doctrine of nondelegable duty

as here involved applies to injuries to employees of the

A-8

independent contractor.” United States v. Page, 350 F.

2d 28 (10th Cir.). Dayton was cited by Page to sup-

port this proposition by its dictum.

The plaintiff urges that it was error for the trial

judge to refuse to instruct the jury on the issue of puni-

tive damages. The trial judge found that the evidence

did not develop an issue on punitive damages. Smith

v. Mill Creek Court, Inc., 457 F.2d 589 (10th Cir.).

We must agree with this view because in order to

justify an award of punitive damages in Utah, there

must be a wrongful invasion of the plaintiff's rights

which was done wilfully and maliciously. Palombi v.

D & C Builders, 22 Utah 2d 297, 452 P.2d 325; Amoss

v. Broadbent, 30 Utah 2d 165, 514 P.2d 1284. It de-

pends not on the classification of the wrongful act but

on the manner and intent with which it was done. Pow-

ers v. Taylor, 14 Utah 2d 152, 379 P.2d 380. In any

event, the defendant owed no duty to plaintiff.

The judgment of the trial court is REVERSED,

and the case is remanded for a new trial.

APPENDIX B

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF UTAH

CENTRAL DIVISION

GLENN H. SEWELL,

Plaintiff,

v.

PHILLIPS PETROLEUM COMPANY,

a Delaware corporation,

Defendant.

ORDER OF DISMISSAL WITH PREJUDICE

OF PLAINTIFF’S COMPLAINT

In Lieu of Findings of Fact and

Conclusions of Law

No. C74-40

Defendant is a major petroleum producer and

entered into a contract with Eckman & Associates, Inc.,

for the installation of gasoline tanks at a service station

at 702 East 3300 South in Salt Lake City, Utah. The

contract provided the contractor was to be an independ-

ent contractor and to provide the materials and labor,

get the necessary licenses, and observe all laws in exca-

vating the premises and installing the tanks. The con-

tract further provided the contractor was to have com-

plete control over the work.

Plaintiff was an employee of Eckman and working

on the excavation when a cave-in occurred causing in-

juries for which this action was brought. There had

B-2

been no sloping of the sides of the excavation as local

law required. ‘he plans for the work were provided by

the defendant and contained no requirement of sloping.

A representative of defendant had visited the project

occasionally and the company, from much past experi-

ence, reasonably could expect bidders would follow the

plan provided. No Phillips representative was present

when it happened.

The trial court first granted defendant's motion for

summary judgment, holding the plaintiff's employer was

an independent contractor and defendant, under applic-

able law, was insulated from any responsibility.

Upon a motion for reconsideration the trial court

became persuaded it was a case that presented a jury

question. Here the defendant company had vast experi-

ence in excavation and installation work, had an engin-

eering departinent trained in precisely this kind of work

and in this very community had previously contracted

for many such jobs and been familiar with the local law

requiring sloping. Notwithstanding the company drew

plans for the work leaving out sloping, an expensive

addition, and put it out to bid. The trial court was per-

suaded that under such circumstances, where the com-

pany gained an economic benefit from putting out a job

for bid with a drawing for the work without sloping,

an issue of whether this was negligence of the company

should be presented to the jury, the theory being that

such may be an exercise of control that would deprive

the company of the protection of the contract placing

responsibility with the independent contractor, but with-

out making the company the plaintiff's employer.

B-3

The case was presented to the jury and plaintiff

was awarded a verdict of $25,000. Plaintiff appealed

the court’s dismissal of the claim of punitive damages

and defendant cross-appealed, contending there were no

issues of fact for the jury and that, as a matter of law,

judgment should be entered in favor of defendant no

cause of action on plaintiff's complaint. The case was

argued to the Court of Appeals in November, 1976, and

on March 21, 1977, the Court handed down its de-

cision reversing the judgment and remanding the case

for a new trial.

Thereafter the trial court met with counsel for the

parties to hold a pretrial in preparation for a retrial. It

was stipulated that all of the evidence had been pre-

sented at the first trial and that the matter should be

presented to the trial court, based on the records and

- brief of counsel, for its decision.

The court has carefully reviewed the facts in the

record, the ruling of the Circuit Court of Appeals for

the Tenth Circuit, the briefs of counsel and, deeming

itself fully advised, enters the following as its ruling

and verdict in the matter.

IT IS HEREBY ORDERED that defendant

be granted a verdict of no cause of action on plaintiff's

complaint.

The court believes that under the facts and the law

provided by the Circuit this is the only verdict that

could be entered. On page 3 of the opinion of the Ap-

pellate Court the Court ruled:

B-4

There is no question that Eckman was an inde-

pendent contractor.

To impose liability on the defendant there

must be shown an exception to the general rule

of non-liability for torts of an independent con-

tractor either through the exercise by the defend-

ant of control over a delegable duty, or by show-

ing a non-delegable duty.

The opinion then proceeds to demonstrate that

neither of the two alternatives is present in this case.

It follows, therefore, that plaintiff can establish no

basis for liability.

In holding that the defendant retained no control

of the work (over a delegable duty), the Court said:

There was shown no active participation in the

work by defendant’s inspections of the job site.

The defendant never exercised control of the

work and Kckman was under a contractual duty

to comply with proper procedures.

* * *

[a]lthough the drawings and specifications did

not specify sloping, they in themselves do not

show control in the absence of some affirmative

act.

+ * &

The defendant, on this record, did not retain con-

trol of the work. (Emphasis added. )

Since the parties have no more evidence to pre-

sent, this ruling is determinative in this alternative.

As to the possibility of its being a situation of a

non-delegable duty, the Appellate Court said:

B-5

As for nondelegable duties which are described

as being “inherently dangerous” . . . this Circuit

has expressed “serious doubts as to whether the

doctrine of nondelegable duty as here involved

applies to injuries to employees of the independ-

ent contractor.”

In concluding the opinion, the Court added:

In any event, the defendant owed no duty to

plaintiff. (Emphasis added. )

With the parties stipulating there is no more evi-

dence to present, under the opinion of the Circuit there

is nothing left to try.

Judgment, therefore, should be, and is, entered for

defendant, no cause of action on plaintiff's complaint.

DATED this 20th day of September, 1977.

ALDON J. ANDERSON

United States District Judge

APPENDIX C

NOT FOR ROUTINE PUBLICATION

United States Court of Appeals

Tenth Circuit

No. 77-2072

GLENN H. SEWELL,

Appellant,

V.

PHILLIPS PETROLEUM COMPANY,

a Delaware corporation,

Appellee.

Appeal From The

United States District Court

For The District Of Utah

Central Division

(D.C. No. C 74-40)

Samuel King, Salt Lake City, Utah, for Appellant.

Ray R. Christensen, of Christensen, Gardiner, Jensen

& Evans, Salt Lake City, Utah, and Chris Wangsgard,

of Van Cott, Bagley, Cornwall & McCarthy, Salt Lake

City, Utah, for Appellee.

Before SETH, Chief Judge, DOYLE and McKAY,

Circuit Judges.

SETH, Circuit Judge.

C-2

We previously considered this case in Sewell v.

Phillips Petroleum Company, Inc., Nos. 76-1030-31

(10th Cir. March 21, 1977). We held there that the

crucial “retained control” jury instruction for imputing

liability to an owner for injuries caused by a negligent

independent contractor was erroneous, and that the

evidence clearly failed to support plaintiff's alternative

theories for imposing liability on the defendant. We

reversed the general verdict in favor of plaintiff and re-

manded for a new trial. The parties stipulated to the

trial judge on remand that no issue remained to be deter-

mined and agreed to submit the liability issue to the

trial judge on the basis of the trial record. They also

agreed that if the trial judge found in favor of plaintiff

on the liability issue, then the case would proceed to a

jury for a determination of damages. Since there was

no further evidence to be presented, the trial judge

entered judgment for the defendant in light of our

holding.

Appellant complains here that he was entitled to

judgment as a matter of law, and that our previous hold-

ing relied on misstatements of the facts in the defend-

ant’s brief. He also maintains entitlement to remand

on the punitive damages issue which we considered and

denied in our previous holding.

We believe it unnecessary to reiterate the relevant

facts because they are discussed in detail in our prev-

ious holding. The case involved a suit for damages for

injuries sustained by plaintiff while working in an ex-

cavated eleven-foot hole. Plaintiff was employed by

C-3

Harvey W. Eckman & Associates which had contracted

with the defendant to install 10,000-gallon gasoline stor-

age tanks at defendant’s gasoline stations. Plaintiff's

principal theory at trial was that defendant “retained and

exercised control” over the contractor’s work and was

therefore liable for plaintiff's injuries. The relevant jury

instruction failed to explain the necessity for “active

participation” by the defendant as required by Utah

law United States v. Page, 350 F.2d 28 (10th Cir.) ;

Dayton v. Free, 148 P. 408 (Utah). We noted further

that no evidence presented at trial indicated the de-

fendant could be held liable under this theory or the

alternative theories.

Appellant raises here the same issues discussed

previously. No further evidence was produced on re-

mand. We see no purpose in repeating the basis for

our previous holding. Appellant’s arguments are simply

unpersuasive.

We do address, however, the contention that the

previous holding relied on misstatements in the defend-

ant's brief. The record clearly shows a lack of evidence

supporting the “retained control” theory. Furthermore,

on plaintiff's alternative business invitee theory, the

danger arose from the work performed on the premises

and was readily apparent to the plaintiff. Defendant

was under no duty to guard against such an obvious

danger. Texaco, Inc. v. Pruitt, 396 F.2d 237 (10th

Cir.). Appellant's contention has no merit because the

record provides the evidence necessary for determining

that defendant was not liable as a matter of law.

C-4

No. 77-2072 — GLENN H. SEWELL, Appellant,

vs. PHILLIPS PETROLEUM COMPANY, Ap-

pellee.

McKAY, Circuit Judge, concurring in the result:

Although I believe that the dissenting opinion may

correctly characterize the result which should have been

reached in the prior appeal brought in this case, I be-

lieve the instant appeal is in substance only a much-

belated petition for rehearing. Rightly or wrongly, the

issues that divide the other panel members were de-

cided in the earlier appeal, and the time for asking this

court's reconsideration of its determination has long

since expired. All purported defects in the earlier dis-

position would have been known to appellant during the

period in which filing for rehearing would have been

timely. I therefore agree with the decision to affirm.

Nonetheless, I believe a troubling subsidiary mat-

ter should be addressed. There appears to be a sub-

stantial likelihood that disciplinary proceedings are in

order. If counsel for appellant is correct, counsel for

appellee deliberately misstated material facts to this

court in the brief he filed in the prior appeal. If counsel

for appellee is correct ,counsel for appellant has leveled

false charges of serious professional impropriety against

a member of the bar. Both charges are extremely grave.

If either is true, disciplinary sanctions are in order.

We have not investigated the charges and counter-

charges raised in this case, nor is such an undertaking

C-5

the proper responsibility of this court in the first in-

stance. I am, however, mailing a copy of this opinion

to the Commissioners of the Utah State Bar, of which

both attorneys are members, for their appropriate dis-

position. I will also direct the clerk of this court to

supply the Commissioners with copies of the relevant

materials.

In a growing number of cases, adversarial rivalry

has degenerated into accusations of unethical conduct.

‘This court will not tolerate false charges of this variety.

Neither will it abide the filing of dishonest statements

by practitioners. We expect the highest standard of

care by attorneys in correctly citing facts and cases.

If necessary, when deliberate or grossly negligent mis-

citations occur, we will strike the briefs and leave the

clients who are damaged thereby to malpractice rem-

edies. We intend to apply an equal standard to false

accusations of unethical conduct.

When misstatements of the type discussed here do

occur, opposing counsel should note the errors in a re-

sponsive brief. Misconduct should not be so character-

ized in the briefs on appeal, lest the argument shift to

focusing on the integrity of practitioners rather than the

substantive issues raised in the appeal. Where the mis-

statements suggest the likelihood of misconduct, oppos-

ing counsel should file a charge with the appropriate

bar authorities. We will ourselves be alert to whether

the challenged statements suggest the propriety of dis-

ciplinary proceedings and will, as in the instant case,

initiate appropriate action when the opposing attorney

has not already done so.

C-6

Having outlined our views in this matter generally,

we repeat that we express no view at this time concern-

ing which attorney is correct in the instant dispute. We

assume that the matter will be resolved in a more ap-

propriate forum so that the rights of the litigants will

not be further affected by this controversy.

I am authorized to state that Chief Judge Seth con-

curs in the views expressed in this opinion on the matter

of professional misconduct on the part of attorneys who

practice before us.

No. 77-2072 — GLENN H. SEWELL v. PHIL-

LIPS PETROLEUM COMPANY

DOYLE, Circuit Judge, dissenting.

I respectfully dissent.

This case was appealed on a previous occasion. It

was reversed and remanded for a new trial. ‘The panel,

with the exception of Chief Judge Seth, was different

on the prior appeal.

The complaint was originally filed in this case on

Kebruary 8, 1974. Plaintiff was injured as a result of

the cave-in of an excavation wall in a pit in which he

was working. This excavation was made on behalf of

Phillips Petroleum Company, the defendant herein.

The depth of this was 116”. The sides, however, were

perpendicular and it is said that this is what caused it

to cave.

C-7

It is not disputed that both the Uniform Building

Code which was in effect in Salt Lake City and also

OSHA, the United States agency, which was con-

cerned with employee safety, required sloping and shor-

ing. See United States v. Dye Construction Company,

510 F.2d 78 (10th Cir. 1975).

In this instance the pit was excavated for the pur-

pose of installing a gasoline storage tank at a retail serv-

ice station. An independent contractor performed the

work. However, he did not apply for a permit. Had

he done so there would have been an inspection to-

gether with orders requiring the sloping in accordance

with the city ordinance and OSHA regulations.

The evidence established that the particular ex-

,cavation was one of a large number in Salt Lake City

by Phillips in order to store unleaded gasoline. Phillips

was fully aware of the manner of excavating and was

aware that it was illegal. There was evidence to show

that proceeding without a permit and not sloping or

shoring was the policy of Phillips. The evidence also

showed that Phillips furnished the blueprint or plan for

the excavation and installation of the tank. This called

for a pit with perpendicular walls.

Plaintiff made the mistake of appealing the trial

courts denial of punitive damages. The defendant

cross-appealed the judgment on the merits. This court

rejected plaintiffs appeal and adopted that of Phillips.

The theory was that Phillips was shielded by the inde-

pendent contractor concept.

C-8

The source of this disagreement goes back to the

first appeal following the original trial of the case. The

trial had been to a jury in early October 1975. On that

occasion special interrogatories were submitted to the

jury, and as a consequence of the jury's responses a

verdict in the amount of $25,000 was returned in favor

of the plaintiff. In answering the interrogatories, the

jury responded that the defendant Phillips Petroleum

Company was the proximate cause of the injury to the

degree of 100%. Judgment was entered accordingly.

The appeal which is referred to above followed.

This court reversed in an opinion filed March 21,

1977. It emphasized that Mr Eckman had been em-

ployed by Phillips under an explicit contract which pro-

vided that he was an independent contractor. He was

to dig an 11’6” pit in which the gasoline tank would be

placed. In general, this court's opinion followed the

proposition that in order to impose liability on the de-

fendant, considering that Eckman was an independent

contractor, it would have to appear that an exception

existed to nonliability for torts of an independent con-

tractor. The court went on to find that such exception

was not present.

The basis on which the verdict was rendered at the

trial was that Phillips, in truth, controlled the project ;

that it was hazardous to fail to perform sloping and

shoring in a pit this deep; that such sloping and shoring

was required by the County of Salt Lake and also

by OSHA, a federal agency. It was also brought out

that Phillips was fully aware of the fact that these pre-

C-9

cautions which were required by law had not been

taken. Indeed, Phillips prepared the drawings and

specifications which called for a perpendicular pit and

which did not provide for sloping or shoring. It was

also shown that this particular contractor was regularly

employed, had excavated a large number of these in

accordance with Phillips’ plans, and with the full knowl-

edge of Phillips. ‘These facts resulted in Phillips having

independent responsibility for the injury.

The opinion of this court remanded the case for a

new trial. However, the trial judge concluded that he

was unable to conduct a new trial in view of the de-

cision. The court proceeded to enter an order of dis-

missal of the complaint with prejudice. In that order

of dismissal it was pointed out that the contract pro-

vided that the contractor was to be an independent con-

tractor, who would provide the necessary materials and

labor, get the necessary licenses and observe all laws in

excavating the premises and installing the tanks. The

wording of the contract also provided that the con-

tractor was to have complete control over the work.

While plaintiff, the order continued, was working

on the excavation, a cave-in occurred causing his in-

juries. “There had been no sloping of the sides of the

excavation as local law required. The plans for the

work were provided by the defendant and contained no

requirement of sloping.” A representative of defendant

had visited the project occasionally and the company,

from past experience, could expect bidders would follow

the plan provided. No Phillips’ representative was

present when it happened.

C-10

The trial court wrote that it had first granted the

defendant's motion for summary judgment on the basis

that defendant was insulated from responsibility, but

upon reconsideration it became persuaded that it was

a case that presented a jury question considering that

the defendant company had vast experience in excava-

tion and installation work, had an engineering depart-

ment trained in this kind of work, and “in this very

community had previously contracted for many such jobs

and been familiar with the local law requiring sloping,

not withstanding that the company drew plans leaving

out sloping, an expensive addition, and put it out to bid.”

The court said that since the company had gained an

economic benefit from putting out a job for bid with a

drawing for the work without sloping, the issue of

whether this was negligence should be presented to the

jury, on the theory that such may be an exercise of

control that would deprive the company of the protec-

tion of the contract which placed responsibility with the

independent contractor. The court then went on to say:

The case was presented to the jury and plaintiff

was awarded a verdict of $25,000. Plaintiff appealed

the court's dismissal of the claim of punitive damages

and defendant cross-appealed, contending there were

no issues of fact for the jury and that, as a matter of

law, judgment should be entered in favor of defendant

no cause of action on plaintiff's complaint. The case

was argued to the Court of Appeals in November, 1976,

and on March 22, 1977, the Court handed down its de-

cision reversing the judgment and remanding the case

for a new trial.

C-1l

Thereafter the trial court met with counsel for the

parties to hold a pretrial in preparation for a retrial. It

was stipulated that all of the evidence had been pre-

sented at the first trial and that the matter should be

presented to the trial court, based on the records and

brief of counsel, for its decision.

The court has carefully reviewed the facts in the

record, the ruling of the Circuit Court of Appeals for

the Tenth Circuit, the briefs of counsel and, deeming

itself fully advised, enters the following as its ruling and

verdict in the matter.

IT IS HEREBY ORDERED that defendant

be granted a verdict of no cause of action on plaintiff's

complaint.

The court believes that under the facts and the law

provided by the Circuit this is the only verdict that

could be entered. On page 3 of the opinion of the Ap-

pellate Court the Court ruled:

There is no question that Eckman was an inde-

pendent contractor.

To impose liability on the defendant there must

be shown an exception to the general rule of non-

liability for torts of an independent contractor

either through the exercise by the defendant of

control over a delegable duty, or by showing a

non-delegable duty.

The opinion then proceeds to demonstrate that

neither of the two alternatives is present in this case.

It follows, therefore, that plaintiff can establish no basis

for liability.

C-12

In holding that the defendant retained no control

of the work (over a delegable duty), the Court said:

There was shown no active participation in the

work by defendant's inspections of the job site.

The defendant never exercised control of the

work and Eckman was under a contractual duty

to comply with proper procedures.

[a]lthough the drawings and specifications did

not specify sloping, they in themselves did not

show control in the absence of some affirmative

act.

The defendant, on this record, did not retain con-

trol of the work. (Emphasis added.)

Since the parties have no more evidence to present,

this ruling is determinative in this alternative.

As to the possibilty of its being a situation of a

non-delegable duty, the Appellate Court said:

As for nondelegable duties which are described

as being “inherently dangerous” . . . this Circuit

has expressed “serious doubts as to whether the

doctrine of nondelegable duty as here involved

applies to injuries of” employees of the independ-

ent contractor.”

In concluding the opinion, the Court added:

In any event, the defendant owed no duty to

plaintiff. (Hmphasis added. )

With the parties stipulating there is no more evi-

dence to present, under the opinion of the Circuit there

is nothing left to try.

C-13

Judgment, therefore, should be, and is, entered for

defendant, no cause of action on plaintiff's complaint.

DATED this 20th day of September, 1977.

I have quoted and shown the trial court’s opinion

on remand in detail for the reason that it shows, in my

opinion, that the trial court was somewhat startled to

receive this court’s opinion, and I must confess that I

had similar feelings when I first heard the case on the

present appeal. My first exposure to the case was the

occasion of oral arguments on the second appeal.

Being of the opinion that there has been a miscar-

riage of justice, it is my conclusion that the judgment

of the district court should be at this time reinstated in

the interest of justice. Such action has been taken on

past occasions.

The reason for my dissent is my conviction that the

concept of independent contractor is capable of shroud-

ing a great many sins; that it will not succeed where, as

here, a statute or ordinance imposes a duty to provide

specified safeguards or precautions for the safety of

others. This is expressed in the Restatement of the

aw Second, § 424, which provides:

Precautions Required by Statute or Regulation

One who by staute or by administrative regula-

tion is under a duty to provide specified safe-

guards or precautions for the safety of others is

subject to liability to the others for whese pro-

tection the duty is imposed for harm caused by

the failure of a contractor employed by him to

provide such safeguards or precautions.

C-14

So, under this principle, the owner will not be

heard to say that it was the duty of the contractor to

fulfill the duties imposed by statute This is because the

duty is on the owner to comply with the law and he can-

not pass the buck. If he could, avoidance would be

quite simple. The owner could avoid the law by enter-

ing an airtight contract with an “independent con-

tractor.”

The guiding principles are set forth in somewhat

more detail and clarity in an annotation reported in 41

Am. Jur. 2d, Independent Contractors § 37 (1968), at

799-780:

Generally speaking there are many situations

in which a person cannot absolve himself from

liability by Dcadien his duties to an independ-

ent contractor. An employer has a nondelegable

duty with respect to the taking of precautions

during work which is dangerous in the absence

of such precautions, which is inherently or in-

trinsically dangerous, or which from its nature is

likely to render the premises dangerous to in-

vitees, and also has a nondelegable duty with re-

spect to the conduct of ultrahazardous work.

Where a person, either by contract or by law,

owes an obligation to another, he cannot escape

liability for negligence in performance of such

obligation by delegating the duty 'to an independ-

ent contractor. Thus, if a statute or ordinance

requires a person to take certain precautions

when work is being done, and such precautions

are not taken, it is no defense that an independ-

ent contractor was employed to do the work and

that the failure to take the precautions was due

to the contractor’ negligence. Likewise, one

who, by a specific agreement, undertakes to do

C-15

some particular thing, or to do it in a certain

manner, cannot, by employing an independent

contractor, avoid responsibility for an injury re-

sulting from the nonperformance of any duty or

duties which, under the express terms of the

agreement or by implication of law, are assumed

by the cn at An exception to the general

rule of nonliability of an employer for the negli-

gence of an independent contractor or the latter’s

servants exists where the employer has assumed

a contractual obligation to perform the work.

At bar we have an activity which is inherently haz-

ardous. The hazard is recognized by statute and ordin-

ance. In addition, we have an owner who provides

plans which do not attempt to adopt safeguards. In

fact, it knowingly encourages the doing of the work

without taking safeguards. Phillips would be liable for

the failure of the contractor to follow its orders. It is

certainly liable where the contractor follows its orders

and thereby creates the risk.

One recent example is that which occurred in

Pierce v. Cook & Co., Inc., 518 F.2d 720 (10th Cir.

1975). In Pierce v. Cook, supra, the action was for

wrongful death in an automobile collision. The truck

driver had been hauling wheat for the defendant-ap-

pellee in the case, Cook & Co., Inc. The trial court

entered summary judgment. This was appealed and af-

firmed by this court. The judgment became final in

1971. The accident had actually happened in 1968.

Relief was sought in the federal court based upon a

change of law in the Oklahoma state court. The Okla-

homa Supreme Court had overruled the prior decision

C-16

which had strictly applied the independent contractor

rule and had concluded that where there is a foresee-

able risk of harm to others unless precautions are taken,

one who is regularly engaged in a commercial enter-

prise as an integral part of the business is responsible

for failure to exercise care in selecting a competent car-

rier. Failure to do so rendered him liable.

When this change of law was announced, a motion

for relief was filed by the aggrieved party under Rule

60(b). Notwithstanding that this court’s prior decision

had become final in 1971, relief was granted following

presentation of the case to this court en banc. ‘The cause

had been removed to federal court, and after the state

court rule was changed, we held in an opinion by Judge

Breitenstein that in this extraordinary condition, the

plaintiff was the victim of an injustice, and although we

did not reverse the decision of the trial court, we com-

mended the Rule 60(b) motion to it.

While an appellate court will generally refuse to

reopen a final judgment entered in a prior appeal, it will

do so when substantial justice warrants. See 9 Moore’s

Federal Practice { 110.25[2], at 274-75 (2d ed. 1975).

The law of the case doctrine bars a second review of

established law unless compelling circumstances war-

rant the action.

The Supreme Court has long recognized that an

appellate court may review its earlier decision in a case

and reopen that case when circumstances warrant it.

See Messenger v. Anderson, 225 U.S. 486 (1912).

C-17

Bromley v. Crisp, 561 F.2d 1351, 1363 (10th Cir.

1977), cert. denied, 435 U.S. 908 (1978), recognized

that this court could depart from its own earlier de-

cision in the identical case when circumstances war-

ranted such departure.

Other circuits have also recognized that where cir-

cumstances warrant reopening of an earlier appellate

decision in the same case, such procedure may be pur-

sued.

The Kighth Circuit has said that the earlier judg-

ment will not be disturbed unless clearly erroneous and

manifestly unjust See Wrist-Rocket Mfg. Co. v. Saund-

ers Archery Co., 578 F.2d 727, 730-31 (8th Cir. 1978).

The Fifth Circuit has said that a second review is

permissible “if considerations of substantial justice war-

rant it.” Lehrman v. Gulf Oil Corp., 500 F.2d 659, 663

(5th Cir. 1974), cert. denied, 420 U.S. 929 (1975).

Clearly a prior decision is not to be reopened and re-

versed except upon the basis of cogent reasons and to

avoid manifest injustice. See Terrell v. Household

Goods Carriers’ Bureau, 494 F.2d 16, 19-20 (5th Cir.),

cert. dismissed, 419 U.S. 987 (1974).

The Sixth Circuit has refused to review a prior de-

cision unless a new statute or intervening Supreme

Court decision raises questions as to the viability of the

earlier decision. Hawkes v. Internal Revenue Service,

507 F.2d 481, 482 n.1 (6th Cir. 1974).

C-18

In one instance the First Circuit refused to reopen

a civil case, but recognized that it could be done in the

case in which the previous error constituted a manifest

injustice. White v. Higgins, 116 F.2d 312, 317 (Ist

Cir. 1974).

In the present case the mix-up occurred because of

the fact that the contract between Phillips Petroleum

Company and the independent contractor purported to

place all of the responsibility on the independent con-

tractor, but when the case was tried a far different con-

dition was revealed. It was shown that Phillips in actu-

ality had exercised a good deal of control over the pro-

ject and that it was the author of the plans which took

the less expensive way out, that of not taking steps to

prevent cave-ins. Thus, where it had control of the con-

dition and acted negligently, that is, where it could rea-

sonably foresee that a workman was going to be injured

from this practice, it should be held responsible to the

workman for its own negligent conduct. That is what

the trial court held and that is the correct approach to

the case. It is an approach that is not at odds with Utah

law.

Here we have an activity that was contrary to law,

both local and federal, which plainly created a hazard

and thus the trial court was plainly correct in the first

case in submitting the case to the jury. The jury’s ver-

dict was well founded both in law and in fact. A plain

injustice occurred as a result of the reversal. The trial

court was unable to carry out the mandate which ord-

ered a new trial because the law of the case contained

C-19

in this court’s decision closed the door to a new trial.

There was nothing for the trial court to do except vacate

the judgment based upon the jury verdict and enter

judgment for Phillips, which it did.

In this case the injustice which the litigant has

suffered is clear. There is not and was not any way

which would allow Phillips to shift responsibility to the

contractor. To allow it to do so constituted grave error

which should be corrected.

The case should be reopened in the interest of

justice.

APPENDIX D

UNIFORM BUILDING CODE

CHAPTER 70

IXCAVATING AND GRADING

PURPOSE

Sec. 7001. The purpose of this Chapter is to safe-

guard life, limb, property and the public welfare by

regulating grading on private property.

SCOPE

Sec. 7002. This Chapter sets forth rules and regu-

lations to control excavation, grading and earthwork

construction, including fills and embankments; estab-

lishes the administrative procedure for issuance of per-

mits; and provides for approval of plans and inspection

of grading construction.

PERMITS REQUIRED

Sec. 7003. No person shall do any grading without

first having obtained a grading permit from the Build-

ing Official except for the following:

2. An excavation below finished grade for base-

ments and footings of a building, retaining wall or other

structure authorized by a valid building permit. This

shall not exempt any fill made with the material from

such excavation nor exempt any excavation having an

unsupported height greater than 5 feet after the com-

pletion of such structure.

D-2

8. An excavation which (a) is less than 2 feet in

depth, or (b) which does not create a cut slope greater

than 5 feet in height and steeper than one and one-half

horizontal to one vertical.

DEFINITIONS

Sec. 7005. For the purposes of this Chapter the

definitions listed hereunder shall be construed as speci-

fied in this Section.

EXCAVATION is the mechanical removal of

earth material.

GRADE shall mean the vertical location of the

ground surface.

GRADING is any excavating or filling or com-

bination therof.

GRADING PERMIT REQUIREMENTS

Sec. 7006. (a) Permits Required. Except as ex-

empted in Section 7003 of this Code, no person shall

do any grading without first obtaining a grading permit

from the Buiding Official. A separate permit shall be

required for each site, and may cover both excavations

and fills.

(b) Application. The provisions of Section 301 (b)

are applicable to grading and in addition the application

shall state the estimated quantities of work involved.

(c) Plans and Specifications. When required by

the Building Official, each application for a grading

D-3

permit shall be accompanied by two sets of plans and

specifications, and supporting data consisting of a soil

engineering report and engineering geology report. The

f ‘ns and specifications shall be prepared and signed

by a civil engineer when required by the Building Of-

ficial.

(d) Information on Plans and Specifications.

Plans shall be drawn to scale upon substantial paper or

cloth and shall be of sufficient clarity to indicate the

nature and extent of the work proposed and show in

detail that they will conform to the provisions of this

Code and all relevant laws, ordinances, rules and regu-

lations. The first sheet of each set of plans shall give

the location of the work and the name and address of

the owner and the person by whom they were prepared.

The plans shall include the following information:

1. General vicinity of the proposed site.

2. Property limits and a.curate contours of exist-

ing ground and details of terrain and area drainage

8. Limiting dimensions, elevations or finish con-

tours to be achieved by the grading, and proposed drain-

age channels and related construction.

4. Detailed plans of all surface and subsurface

drainage devices, walls, cribbing, dams and other pro-

tective devices to be constructed with, or as a part of,

the proposed work together with a map showing the

drainage area and the estimated runoff of the area

served by any drains.

APPENDIX E

OSHA REGULATIONS

§1926.651 Specific excavation requirements.

(c) The walls and faces of all excavations in which

employees are exposed to danger from moving ground

shall be guarded by a shoring system, sloping of the

ground, or some other equivalent means.

(e) The determination of the angle of repose and

design of the supporting system shall be based on care-

ful evaluation of pertinent factors such as: Depth of

cut; possible variation in water content of the material

while the excavation is open; anticipated changes in

materials from exposure to air, sun, water, or freezing;

loading imposed by structures, equipment, overlying

material, or stored material; and vibration from equip-

ment, blasting, traffic, or other sources.

(g) All slopes shall be excavated to at least the

angle of repose except for areas where solid rock allows

for line drilling or splitting.

§1926.652

(a) Banks more than 5 feet high shall be shored,

laid back to a stable slope, or some other equivalent

means of protection shall be provided where employees

may be exposed to moving ground or cave-ins. Refer to

Table P-1 as a guide in sloping of banks. Trenches less

than 5 feet in depth shall also be effectively protected

when examination of the ground indicates hazardous

ground movement may be expected.

E-2

(b) Sides of trenches in unsable or soft material,

5 feet or more in depth, shall be shored, sheeted, braced,

sloped, or otherwise supported by means of sufficient

strength to protect the employees working with them.

See Tables P-1, P-2 (following paragraph (g) of this

section }) .

(c) Sides of trenches in hard or compact soil, in-

cluding embankments, shall be shored or otherwise sup-

ported when the trench is more than 5 feet in depth

and 8 feet or more in length. In lieu of shoring, the

sides of the trench above the 5-foot level may be sloped

to preclude collapse, but shall not be steeper than a 1-

foot rise to each 14-foot horizontal. When the outside

diameter of a pipe is greater than 6 feet, a bench of

4-foot minimum shall be provided at the toe of the

sloped portion.

APPENDIX F

‘Should Be Free’

Court Hears Arguments

On Control of Attorneys

By Dave Jonsson

Tribune Staff Writer

Utah lawyers should be free to join or

not to join the Utah State Bar and this

should have no bearing on their right to

practice law, the Utah Supreme Court

was told Monday.

Compulsory membership in the bar is

a violation of attorneys’ rights to

associate or not associate with whom

they wish, attorney Daniel L. Berman

told the court.

The court heard arguments on a

petition signed by 56 attorneys asking

the high court to abolish the

“‘integrated’"’ bar and allow member-

ship to be voluntary. Lawyers now must

be members of the bar before they are

allowed to practice law.

Dues Required

With membership comes the obliga-

tion to pay dues and Mr. Berman

complained ‘‘I don’t think it’s right to

require attorneys to pay fees to support

such things as hiring of lobbyists to

support or oppose legislation.

“The bar paid $10,000 last year for

someone to lobby the Legislature in

opposition. to a bill that would end

— of the bar,”’ Mr. Berman

said.

Integration means that the bar and

Supreme Court are formal partners in

the admission and discipline of the

members of the profession.

‘‘No other profession has a situation

where membership in an organization

is compulsory before a person can

practice his profession,’’ Mr. Berman

said.

Both Offensive

Under the Constitution, he said,

“‘compelled association is just as offen-

sive as compelled disassociation.”

Arguing against the petition was

Harold G. Christensen, former bar

president, who said the bar commission

“thas been very careful in taking

positions on partisan political issues.’’

He noted that the petitioners com-

prise only about 2 percent of the bar’s

3,000 members.

Over the years, Mr. Christensen said,

the partnership between the bar and the

court has been ‘‘a good functioning

system.”’

Better Remedy

“The remedy is not to dissolve the

bar, but to correct the deficiencies

found,’’ Mr Christensen said.

In his brief Mr. Berman told the court

that dues paid by members have gone

into contributions to the International

Women’s Year, to support those oppos-

ing amnesty for Vietnam veterans and

to back certain forms of no-fault

insurance legislation.

‘Discipline of its members has been

weak,’’ Mr. Berman said.

None in 26 Years

“In fact, no lawyer with a major or

significant law firm has been disci-

plined in the past 25 years... they

just go after the criminal violators aan

the oddballs. ae

“It would be naive to think that the

only ethical problems we have are

those that have come to the point of

disciplinary proceedings, ‘‘ Mr. Ber-

man said.

Arguing another position, Steven W.

Allred of the legislative general cour-

sel’s office, asked the court to consider

taking only a ‘‘cautious look”’ at any

requested changes in the current organ-

ization.

APPENDIX G

JULY TERM — SEPTEMBER 10, 1980

Before Honorable Oliver Seth and Honorable Monroe

G. McKay, Circuit Judges.

No. 80-1861

GLENN H. SEWELL,

Petitioner,

VS.

PHILLIPS PETROLEUM COMPANY,

Respondent.

This matter comes on for consideration of the mo-

tion of petitioner requesting the Court to issue a Writ

of Review to review all proceedings in cases Nos. 76-

1030 and 76-1031, the mandates of which issued April

12, 1977, and No. 77-2072, the mandate of which issued

October 9, 1979. Petitioner moves the Court to reverse

its judgment entered August 24, 1979, and enter judg-

ment for him, remanding for new trial on general and

special damages and for other relief. The petitioner sug-

gests en banc review.

Upon consideration whereof, it is ordered:

1. The relief sought by appellant in its motion for

relief filed August 19, 1980, is denied.

2. The panel members did not request a vote on

the suggestion for en banc review.

Judge William E. Doyle, a member of the panel

that rendered the decision sought to be reviewed, did

not participate.

HOWARD K. PHILLIPS

Clerk

ee en ae

CERTIFICATE OF SERVICE

I hereby certify that on this 21st day of December,

1979, three copies of the Petition for Writ of Certiorari

were mailed, postage prepaid, to Ray E. Christensen,

attorney for respondent, 900 Kearns Building, Salt Lake

City, Utah 84101. I further certify that all parties re-

quired to be served have been served.

SAMUEL KING

301 Gump & Ayres Building

2120 South 1300 East

Salt Lake City, Utah 84106

Counsel for Petitioner

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.