No. 80-434
In the Supreme Gourt of the Hnited States
OCTOBER TERM, 1980
SMITHKLINE CORPORATION, PETITIONER
Vv.
ELMER B. STAATS, COMPTROLLER GENERAL
OF THE UNITED STATES,
AND
UNITED STATES OF AMERICA
ON CONDITIONAL PETITION FOR A WRIT OF
CERTIORARI BEFORE JUDGMENT TO THE
UNITED STATES COURT OF APPEALS FOR
THE THIRD CIRCUIT
BRIEF FOR THE RESPONDENTS
IN OPPOSITION
WADE H. McCreg, Jr.
Solicitor General
ALICE DANIEL
Assistant Attorney General
MICHAEL KIMMEL
ROBERT KAPLAN
Altorneys.
Department of Justice
Washington, D.C. 20530
(202) 633-2217
Iu the Supreme Court of the United States
OCTOBER IJERM, |Y8U
No. 80-434
SMITHKLINE CORPORATION, PETITIONER
Vv.
ELMER B. STAATS, COMPTROLLER GENERAL
OF THE UNITED STATES,
AND
UNITED STATES OF AMERICA
ON CONDITIONAL PEIIIION FOR A WRIT OF
CERTIORARI BEFORE JUDGMENT IO THE
UNITED STATES COURT OF APPEALS FOR
THE THIRD CIRCUIT
BRIEF FOR THE RESPONDENTS
IN OPPOSITION
QUESTIONS PRESENIED
1. Whether the Comptroller General’s request for
access to petitioner’s records pursuant to 10 U.S.C.
2313(b) and 41 U.S.C. 254(c) was invalid because of the
purpose underlying the request.
2. Whether, with respect to a negotiated government
contract in which a fixed price was set on the basis of the
commercial market price and without reference to
incurred costs, the Comptroller General is authorized by
10 U.S.C. 2313(b) and 41 U.S.C. 254(c) to examine the
contractor’s records of its costs, including its unallocated
costs, where government payments under the contract are
used to detray those costs.
iil
TABLE OF CONTENTS
Page
CII WHIT... cinsinchinscscstigdbccssislabinectetentanepiaiiink l
F MNATINNUINIL Wiss n.<sincscsuiispsatcasienensdeica inicsshbaiuastiabaenigts l
tHE vescxercaveshsebersennssoescnscunhensesqeioiehannnnmpenaeaioemmant |
PI hia scisids ine seisinsidiniiniateinantnasnediaaoin ae
EC IPMIMEIID: sivnscocdsccdesnrisesesescronnsmedennabaitesdbbacsssetadipebnes 20
TABLE OF AUTHORIIIES
Cases:
Bristol Laboratories v. Staats, 620 F. 2d
17, petition for cert. pending,
No. 80-264 (filed Aug. 21, 1980) ................. 5, 6
Eli Lilly & Co. v. Staats, 574 F. 2d
904, cert. denied, 439 U.S.
DE iniscnsh akitndis soscbincsabtiiedte 4, 6, 10, 11, 14, 16, 18
Greene v. McElroy, 300 U.S. 474 wcccccccccseeeees 19
Hannah v. Larche, 363 U.S. 420 .........cccccesseeeees 19
Hewlett-Packard Co. v. United States,
385 F. 2d 1013, cert. denied,
tS RE Ippon ew 3-4, 10, 13, 16
Johnson v. Fleet Corp., 280 U.S. 320 ............06 19
McCulloch v. Sociedad Nacional de
Marineros de Honduras, 372
FT ED scnnndntinsiicelaabsinet een Mins citanilaliacebs 19
Merck & Co. v. Staats, Civil Action
No. 74-1447 (D.D.C. Aug. 12, 1977),
appeals pending, Nos. 79-1435,
79-1438 (D.C. Cir., argued Feb. I[1,
1980), conditional petition for cert.
before judgment pending, No. 80-416
(filed Sept. 16, 1980) .......ccccccsccceecs 6, 10, 11, 16
LV
Page
Cases—Continued:
Mt. Healthy City Board of Ed. v. Doyle,
A st. AIS beeansisaaseeisstassivescuneabaabebsipntin 12
New Haven Inclusion Cases, 399 U.S. 392 ....... 19
Porear ©. EFM, Bae Uc. BOR. inccccscdenseviniicnitiatn 19
FOR 'Y. LR Bae Wi BO telarisstevicsdesiminn 19
Taylor v. McElroy, 360 U.S. 709 ......ccccccccceeeeees 19
United States v. Abbott Laboratories,
FOE Bee I ern tnieivlgainciasilamminneins 6, 11
United States v. LaSalle National Bank,
GE Wits BUOW. siveisidcsdiniicindaconisteniteiaeabiansaas 12
United States v. Nixon, 418 U.S. 683 ............... 17
Washington v. Fishing Vessel Assn.,
MMT Wille GHA | secnsicctinbehddivsccnannsinscttiibtghladgupmbiebubineen 19
Youngstown Sheet & Tube Co. v. Sawyer,
FED lee SE likncctesariinaiesindisininrtnnaibaidiiitoin 17
Statutes and rule:
BD Cities. RO GUD sispdenseincisvvnssetiniasemndloneaiabedadligtn |
Be SEs I sierissncesssiancindtsintnesniaieiaaetainaeain |
UU SIE Tha. BD sscnincspsensinncdocaindaravidicsnncibiabasmbians 7, 17
Miscellaneous: |
97 Cong. Rec. (1951):
1 RIESE: sicushccsstelices~nesacvoneacslinsnonianbaitancaioummids 8
i; RIEU criascssiuinbinevesnussaqcihecndeibiindemabasaaata 8
Di: NIB TO ~cctcisnisicnctipinirnesometdtiedailindildie 8
Page
Miscellaneous—Continued:
EE scbubsiovivunscnepessbenapesmibigensadsatocenenaiinnsniian 8
RED CA TOG. ZOOS CEBGDD os ccccscvscscccevcsscccsceses 15
Hearings on Comptroller General Reports to
Congress on Audits of Defense Contracts
Before the Subcomm. on Military
Operations of the House Comm. on
Government Operations, 89th
eS een 9, 15
Hearings on Relation of Cost Data to Military
Procurement Before the Subcomm. for
Special Investigations of the House
Comm. on Armed Services, 88th
Cs BD TRIE, COON scncensccncstinteenctccccecs 14, 15
H.R. Rep. No. 791, 82d Cong., Ist Sess.
CREE sistabileadauikencscicckilieaalidacbaiasmiaaiiiilapematcanin 8, 9
S. Rep. No. 603, 82d Cong., Ist Sess.
SETI initsdaieonsinictiidohelitens cine eatedcidatieheialdiandiiliciddaiiianiaiaae 8, 9
OPINION BELOW
The opinion of the district court (Pet. App. la-2la) is
reported at 483 F. Supp. 712.
JURISDICTION
The judgment of the district court, dated January 24,
1980 (Pet. App. la), was entered on January 25, 1980
(C.A. App. 4).! On March 19, 1980 (C.A. App. 5),
petitioner filed a notice of appeal (Pet. App. 1b) to the
United States Court of Appeals for the Third Circuit, and
the case is still pending in that court (No. 80-1464). The
conditional petition for a writ of certiorari before
judgment was filed on September 18, 1980. The
jurisdiction of this Court to review the case by writ of
certiorari before final judgment of the court of appeals is
invoked under 28 U.S.C. 1254(1) and 28 U.S.C. 2101(e).
STATEMEN1
1. In 1973 and 1974, petitioner entered into three
contracts with the Defense Supply Agency of the
Department of Defense and two contracts with the
Veterans Administration for the sale of pharmaceutical
products to the government. Each of the five contracts
was a negotiated fixed-price contract in which the price
was based on petitioner’s published catalogue price for the
particular product; the total price for the contracts was
approximately $3.3 million (Pet. App. 2a, 15a n.7; C.A.
App. 47-51). As required by 10 U.S.C, 2313(b)? and 41
U.S.C. 254c),> each of the contracts contained a standard
“C.A. App.” refers to the joint appendix tiled by the parties in the
court of appeals.
2Lhis provision is applicable to the Delense Supply Agency
contracts.
‘this provision is applicable to the Veterans Administration
contracts.
2
access-to-records clause in which petitioner agreed that
the “Comptroller General of the United States or any of
his duly authorized representatives shall, until the
expiration of three years after final payment under this
contract * * * , have access to and the right to examine
any directly pertinent books, documents, papers, and
records of the Contractor involving transactions related to
this contract” (Pet. App. 3a-4a; C.A. App. 48-53).
In May 1972, the General Accounting Office began “a
two-phase study of the economics and operations of
the pharmaceutical industry” (Pet. App. 7a). In the first
phase of the study, petitioner and five other phar-
maceutical firms agreed to permit GAO officials to visit
and inspect their facilities and operations. The companies
declined, however, to participate in the second phase of
the study, which was designed to enable GAO to examine
"the salient economic and operational aspects of the drug
industry” (ibid.). Because of the companies’ failure to
cooperate, GAO abandoned its plans for the second phase
of the study and proposed “a more modest study” based
on data to be obtained under the foregoing access-to-
records provisions (id. at 8a).
In August 1974, the Comptroller General wrote to the
six companies, including petitioner, to request access to
designated records pursuant to the access-to-records
provisions. The Comptroller General explained that the
request was part of “a review of the procurement of drugs
by agencies of the Federal Government, including the
pricing of drugs and pharmaceuticals procured under
negotiated contracts” (Pet. App. 8a-9a). To that end, the
Comptroller General sought to examine
all books, documents, papers, and other records
directly pertinent to the contracts, which include, but
are not limited to (1) records of experienced costs
3
including costs of direct materials, direct labor,
overhead, and other pertinent corporate costs, (2)
support for prices charged to the Government, and
(3) such other information as may be necessary for
use to review the reasonableness of the contract
prices and the adequacy of the protection afforded
the Government’s interests. |
Pet. App. 9a; C.A. App. 61.
2. Petitioner refused to comply with the Comptroller
General’s request. Instead, on February 20, 1975, it
commenced the present action in the United States
District Court for the Eastern District of Pennsylvania
seeking declaratory and injunctive relief to bar GAO from
access to its records. The United States subsequently
intervened as a defendant and filed a counterclaim to
require petitioner to allow the requested inspection (Pet.
App. la-2a, 9a).
Following discovery, the district court on January 24,
1980, granted the government’s motion for summary
judgment and denied petitioner's cross-motion (Pet. App.
la-2la). Contrary to petitioner’s contention that the
Comptroller General’s request had been prompted by the
assertedly improper purpose of “seeking information
concerning profits in the pharmaceutical industry for
dissemination to Congress and the public” (id. at 10a), the
court found, “[oJn the basis of uncontroverted depositions
and affidavits filed by the parties in connection with the
motions for summary judgment” (id. at 2a), “that GAO’s
purpose is to compare cost to price of drugs purchased
under specified contracts to determine the adequacy of the
protections afforded the government in the contract
negotiation process” (id. at 12a). Relying on the legislative
history of the access-to-records statutes and the decision
in Hewlett-Packard Co. v. United States, 385 F. 2d 1013
4
(9th Cir. 1967), cert. denied, 390 U.S. 988 (1968), the
court also concluded that the statutes were intended to
enable GAO “to determine whether * * * there have been
‘improprieties and wastefulness in the negotiation of
contracts,’ or whether * * * the contractor’s costs are ‘out
of line with the contract price’” (Pet. App. 15a-16a).
Accordingly, the court held that the Comptroller
General’s purpose “to review the reasonableness of the
contract prices and the adequacy of the protection
afforded the Government’s interests” (id. at 16a) was “a
purpose authorized by the statutes” (id. at 17a).
In addition, in view of the plain meaning of the statutes
and the Hewlett-Packard decision, the court rejected
petitioner’s argument that the access-to-records provisions
were entirely inapplicable to negotiated fixed-price
contracts in which, as here, the price was based on the
contractor’s catalogue price (Pet. App. 15a n.7).
Finally, in accordance with Hewlett-Packard and Eli
Lilly & Co. v. Staats, 574 F. 2d 904 (7th Cir.), cert.
denied, 439 U.S. 959 (1978), the court held that, at least
with respect to the pharmaceutical industry, the access
provisions are not limited to records of “the direct costs of
manufacturing the drug covered by the contract” but
include “the records of all costs which go into the makeup
of the price of the drug covered in the contract” (Pet.
App. 18a). The court recognized that the direct-cost
“limitation, in the drug industry, would defeat the
purpose of the access-to-records statutes since, as the
[cjourt in £ii Lilly pointed out, manufacturing and
distribution costs of drugs have been estimated to
constitute as little as nine percent of the product’s sale
price” (ibid.). Construing the statutes “in light of their
purpose to permit a determination as to whether costs are
‘out of line with the contract price’” (Pet. App. 18a,
quoting Hewlett-Packard Co. v. United States, supra, 385
5
F.2d at 1016), the court “agree{d] with Eli Lilly’s
reasoning that ‘the access-to-records clauses should be
interpreted so that an item is “directly pertinent” to a
contract if it is a significant input in the price of the
product purchased in the contract’” (Pet. App. 18a).
Pursuant to its opinion, the district court entered
summary judgment for the government and ordered
that the Comptroller General of the United States
and his duly authorized representatives have the right
to examine all books, documents, papers, or records
directly relating to the pricing and cost of producing
items furnished by [petitioner] under the following
contracts ***, including, but not limited to,
records of experienced costs, including costs of
materials, labor, overhead, distribution, research and
development, and marketing, and such other costs as
are directly pertinent to the drugs covered in the
enumerated contracts * * *.
Pet. App. 19a. The court’s order also included “provisions
concerning the confidentiality of records, as agreed by the
parties” (ibid.).
On March 19, 1980, petitioner appealed the district
court’s judgment to the United States Court of Appeals
for the Third Circuit. That appeal is still pending; all
briefs have been submitted, but oral argument has been
deferred by the court of appeals until after the disposition
of this petition (see order of Oct. 22, 1980).
ARGUMEN1
Petitioner initially urges (Pet. 9-10, 18) that the Court
deny the government’s petition for a writ of certiorari in
Staats v. Bristol Laboratories, No. 80-264 (filed Aug. 21,
1980), which presents a related issue concerning GAO’s
access to cost records of pharmaceutical companies
6
pursuant to the access-to-records provisions required by
law. However, petitioner does not contest that there is
currently a conflict in the circuits on the construction of
the access statutes* or that a uniform interpretation of
those statutes is sufficiently important to the proper
administration of the federal procurement system to
warrant this Court’s review (see 80-264 Pet. 8-9). For the
reasons stated below (see page 18, infra) and in the
government’s petition and reply memorandum in Bristol,
we submit that the Court should decide the issue at this
time and not postpone the resolution of the existing
conflict.
In the alternative, petitioner contends that if the Court
grants the petition in Bristo/, it should also grant the
instant conditional petition for a writ of certiorari before
judgment to consider two issues that are not involved in
Bristol and do not present a conflict in the circuits.
Petitioner argues, first, that the Comptroller General’s
request for access was invalid because it was motivated by
an improper purpose, and, second, that the access-to-
records provisions are simply inapplicable and afford no
access whatever in circumstances in which, as here, nei-
ther the negotiation nor the performance of the contract
related to the contractor’s costs.> As we discuss below,
4Petitioner acknowledged in the court of appeals (SmithKline Br.
45) that there is a “square{] * * * conflict among the Circuits” in
light of Eli Lilly & Co. v. Staats, 574 F, 2d 904 (7th Cir.), cert.
denied, 439 U.S. 959 (1978), United States vy. Abbott Laboratories,
597 F. 2d 672 (7th Cir. 1979), and Bristol Laboratories v. Staats, 620
F. 2d 17 (2d Cir. 1980), petition for cert. pending, No. 80-264 (filed
Aug. 21, 1980). See also Pet. 10 n.19; Pet. App. 12a; Conditional
Petition for Certiorari Before Judgment in Merck & Co. v. Staats,
No. 80-416 (filed Sept. 16, 1980), at 9, 10.
‘Petitioner further argues (Pet. 9, 15) that the access-to-records
provisions do not encompass records of its unallocated costs
notwithstanding the fact that payments by the government pursuant
j
however, these arguments are without merit and have
been rejected by every court of appeals that has
considered them. The petition thus offers no reason to
expand the carefully drawn issue presented in Bristol to
include questions that have not divided the circuits and
are not otherwise deserving of this Court’s review, and it
falls far short of the requisite showing for certiorari before
judgment “that the case is of such imperative public
importance as to justify the deviation from normal
appellate practice and to require immediate settlement in
this Court.” Sup. Ct. R. 18. Accordingly, the conditional
petition for a writ of certiorari before judgment should be
denied.
1. Petitioner asserts (Pet. 7) that the access-to-records
provisions authorize the Comptroller General to inspect a
contractor’s records “only for narrow and _ specific
purposes. Access was permitted..to audit cost data
submitted in connection with specific negotiated con-
tracts, in order to detect fraud or, overreaching * * *.”
Notwithstanding petitioner's assertion, however, the
access provisions are not confined to discrete audits of
individual contracts in order to detect fraud and
overreaching.°
to the contract are used to defray those costs and, as petitioner
acknowledged in the court of appeals (SmithKline Br. 42-43),
“unassigned costs have an impact on the price charged for the
company’s products, in the sense that the company’s overall income
must recover both the costs directly assigned and the pooled costs
which have not been assigned.” This is the precise question presented
by the government’s petition in Bristv/. As we explain in the petition
and reply memorandum in that case, petitioner's argument represents
an erroneous construction of the access provisions and should be
rejected by. this Court. In any event, to the extent that petitioner
wishes to be heard on this issue, it should seek to participate as an
amicus curiae in Bristol rather than pursue the instant petition tor
certiorari betore judgment.
Unlike petitioner, Bristol has “agree|d| that it is obliged by the
terms of the contracts to provide access to [certain] records” (80-264
8
By their terms, the access-to-records provisions contain
no limitation of the sort advanced by petitioner. Rather,
they apply to all government contracts negotiated
pursuant to designated statutory authority. Nothing in the
language of the provisions narrows their scope to
unrelated audits of specific contracts or restricts their
objectives to the elimination of fraud and overreaching.
The legislative history of the access-to-records statutes
also refutes petitioner’s interpretation. This history has
been canvassed in the government’s petition in Bristol
(80-264 Pet. 10-11) and need not be repeated here. We
emphasize, however, Congress’s concern that “negotiated
contracts *** require close supervision and con-
trol* ** .” H.R. Rep. No. 791, 82d Cong., Ist Sess. 2
(1951); S. Rep. No. 603, 82d Cong., Ist Sess. 2 (1951).
Among other things, Congress feared that “aside from
any intentional liberality on the part of the Government
contracting officer, there is every chance in the world that
the Government will come out on the short end of the
deal.” 97 Cong. Rec. 13198 (1951) (remarks of Rep.
Hardy). See also id. at 13377 (remarks of Rep. Hoffman
and Rep. Hardy). The debates contain repeated references
to the need to determine whether prices in negotiated
contracts were excessive, extravagant, or wasteful, and
Congress “clearly understood * * * that there are a lot of
other situations besides those involving fraud which might
be uncovered” (id. at 13199 (remarks of Rep. Hardy)).
For instance, as one type of “information which would be
vital in a study of a contract” (id. at 13376), Represen-
tative Hardy offered the following illustration:
Pet. App. 8a) even though, as in the instant case, GAO had not
requested the records in connection with a formal audit and had no
specific grounds to believe that traud or overreaching had occurred
with respect to the contracts.
9
Another vivid example of how this authority
would enable the GAO to do an effective job involves
a study which my Subcommittee on Government
Operations has been making on pricing practices in
the procurement of automotive parts. We found one
situation where the Government was buying parts
from an automobile dealer who, in turn, was getting
them from a parts distributor who, in turn, was
getting them from a small tool shop. Naturally, the
price paid by the Government included profits upon
profits and completely wasteful administrative and
handling costs. It would be difficult, if not impossi-
ble, for GAO to detect such a situation without the
right afforded in this bill.
Id. at 13198. All of these statements of congressional
intent plainly extend beyond the audit of particular
contracts to uncover fraud and belie petitioner’s con-
stricted construction of the access-to-records statutes.’
Contrary to petitioner’s argument, those courts of ap-
peals to consider the question have held that the access-
7We also note the Comptroller General’s statement to Congress
that “any abuses discovered by the General Accounting Office in
exercising the authority contained [in the bill] promptly will be
brought to the attention of the proper officials, and, if warranted, to
the attention of the Congress.” H.R. Rep. No. 791, supra, at 5;
S. Rep. No. 603, supra, at 4. As GAO subsequently explained:
[he fact that, in final analysis, we may not be able to question the
legality of particular contract transactions does not preclude our
reporting to the Congress and to the responsible administrative
agencies that such transactions are wasteful or extravagant or
that a particular contract transaction illustrates the need for an
improvement in existing procurement or management
procedures.
Hearings on Comptroller General Reports to Congress on Audits of
Defense Contracts Before the Subcomm. on Military Operations of
the House Comm. on Government Operations, 89th Cong., Ist Sess.
48 (1965) (statement of Comptroller General Campbell).
10
to-records provisions authorize the Comptroller General
to examine a contractor’s records in order to assess the
reasonableness of the price charged the government and
the adequacy of the protections afforded the government
in negotiated procurements. See Eli Lilly & Co. v. Staats,
574 F. 2d 904, 914-915 (7th Cir.), cert. denied, 439 U.S.
959 (1978); Hewlett-Packard Co. v. United States, 385
F. 2d 1013, 1016 (9th Cir. 1967), cert. denied, 390 U.S.
988 (1968); see also Merck & Co. v. Staats, Civil Action
No. 74-1447 (D.D.C. Aug. 12, 1977), slip op. 3-4 (80-416
Pet. App. 3c-4c), appeals pending, Nos. 79-1435, 79-1438
(D.C. Cir., argued Feb. 11, 1980), conditional petition for
cert. before judgment pending, No. 80-416 (filed Sept. 16,
1980). In Eli Lilly, the court expressly rejected the
argument that the access-to-records provisions “were
designed only to uncover ‘improprieties in the negotiation
of Government contracts,” concluding instead “that
controlling fraud was not the only purpose of the
legislation and that another concern of the legislators was
with excessive pricing” (574 F. 2d at 914). Similarly, the
court in Hewlett-Packard also held that the access
provisions were not limited either to audits of individuai
contracts or to suspected fraud (385 F. 2d at 1016):
Production costs directly pertain to that subject
matter, because if out of line with the contract price,
the contract may have been an inappropriate means of
meeting this particular procurement need of the
Government. While this appraisal could not affect
these particular contracts, it could lead to the use of
other methods of meeting future procurement
needs. * * *
Hewlett-Packard contends, in effect, that the sole
purpose of the examination right accorded by section
2313(b) and clause 10 of these contracts, is to enable
the Comptroller General to find out whether the
|
particular contracts which give rise to the examination
had been performed in accordance with their terms
and whether the contracting officer had been
defrauded or misled in entering into the contract.
We find nothing in the words of the statute, its
legislative history, or administrative interpretation, or
in the impact of other statutes, which supports this
view. On the contrary, it seems to us that if such a
limited scope of examination had been intended by
Congress it would have found the means to so
indicate. The term “contract” could have been given a
restricted meaning, or the scope of the permissible
examination could have been specifically limited to
lines of inquiry relevant to the legality and faithful
performance of the particular contract giving rise to
the examination.
In the present case, the district court determined, after
“resolvjing] in favor of [petitioner] any doubt concern-
ing whether there is a genuine issue of material fact”
(Pet. App. lla), that “[t]he uncontroverted factual
record * * * establishes that GAO’s purpose is to com-
pare cost to price of drugs purchased under specified
contracts to determine the adequacy of the protections
atforded the government in the contract negotiation
process” (id. at 12a; see also id. at 16a-17a).*In light of the
’ [he district court’s determination in this regard was clearly correct
and amply supported by the “uncontroverted depositions and
altidavits filed by the parties in connection with the motions for
summary judgment” (Pet. App. 2a). See, e.g., C.A. App. 58, 60-61a,
116, 123, 124-125, 202-203, 211, 231-233, 408. In addition, every court
to consider the purpose underlying the Comptroller General's
requests to the pharmaceutical companies has agreed that, at the
least, it consisted in part of the intention to review the reasonableness
of the contract prices and the adequacy of the protection afforded the
Government’s interest” (Pet. App. |6a). See United States v. Abbott
Laboratories, 597 F. 2d 672, 674 (7th Cir. 1979); Eli Lilly & Co. v.
Staats, supra, 574 F. 2d at 910; Merck & Co. v. Staats, supra, slip op.
4 (80-416 Pet. App. 4c).
12
foregoing authorities, the court’s conclusion that this was
“a purpose authorized by the statutes” (id. at 17a) is
manifestly correct.? And, since the Comptroller General’s
request was predicated on a proper purpose, it is
immaterial whether, as petitioner alleges, he was
motivated by any additional purposes that, arguendo,
would not be sufficient by themselves to sustain the
validity of the request. See, e.g., United States v. LaSalle
National Bank, 437 U.S. 298, 313-317 (1978); Mt. Healthy
City Board of Ed. v. Doyle, 429 U.S. 274, 285-287 (1977).!°
9Because the district court here correctly decided that
“GAO seeks [petitioner’s] records for the cost-price comparison
authorized by the statutes” (Pet. App. 16a), it is unnecessary in this
case “to determine, as did the Seventh Circuit in Eli Lilly, supra,
that an industry-wide public information study is an authorized
purpose for a GAO inquiry” (id. at 17a).
'0We also doubt that petitioner should be heard to question these
alleged additional purposes for GAO's request. Petitioner “concedes
that it voluntarily executed the contracts at issue in this case with full
knowledge of the access-to-records provisions contained in each
contract” (Pet. App. 10a), and the Comptroller General has now
invoked those provisions to seek access to records for a purpose
authorized by Congress. No rule of law excuses a party from
performing 4 contract because it does not approve of the other party’s
purpose in demanding performance, and petitioner should not be
allowed to inquire further into the Comptroller General’s motives.
Moreover, we disagree with petitioner's repeated characterization
that these alleged additional purposes were “improper.” Even if
petitioner were correct in arguing that the access-to-records
provisions do not authorize a GAO research study, it would not
follow that access to the records should be barred. Petitioner confuses
an “improper” motive with a motive that is perfectly legitimate but
not a sufficient ground, standing alone, for access. [here has been no
suggestion that a research study is forbidden by law or “improper” in
any similar way. The most that petitioner can say is that the
Comptroller General could not compel private parties to cooperate in
such a project. But no principle of law torbids the Comptroller
General from using, for purposes of a research study, information
lawtully obtained pursuant to some other power.
For these reasons, the decisions cited by petitioner for the
proposition that “powers granted to the Government for one
13
2. Petitioner further contends that, under the access-to-
records provisions, “GAO should be afforded access only
to data that are the subject of negotiations or are relied
upon by the government agencies responsible for
awarding the contracts” (Pet. 7) and that no “cost records
can be ‘directly pertinent’ to contracts which are not cost-
based” (id. at 14).'!! This construction of the access
provisions is untenable and has been consistently rejected.
Petitioner has pointed to nothing in the language of the
statutes or their legislative history that would justify such
a grudging interpretation of the access provisions. On the
contrary, petitioner’s construction would defeat the
congressional objective to guard against waste, ex-
travagance, and excessive pricing (see pages 8-9, supra).
Petitioner’s costs, even if neither directly the basis for the
contract price nor the subject of discussions prior to
execution of the contract, are nevertheless critical to an
assessment of the advisability of continued adherence by
the government to the negotiated procurement methods
employed here. If petitioner’s total costs are substantially
lower than the prices paid by the government, the
Comptroller General may recommend that the Depart-
ment of Defense and the Veterans Administration adopt
different procurement practices in the future. See Hewlett-
Packard Co. v. United States, supra, 385 F. 2d at 1016
(“[w]hile this appraisal could not affect these particular
contracts, it could lead to use of other methods of meeting
purpose * * * [may not be] utilized for other purposes” (Pet. 13) are
inapposite. In each of those cases, the government’s request rested on
a purpose that the court held was not authorized by the governing
statute. None of the cases involved access requested pursuant to
contract tor. a purpose sanctioned by law, and none held that an
otherwise legitimate request was rendered invalid and unenforcible
because of the asserted existence of mixed purposes.
'‘'Once again, in contrast to petitioner's position, Bristol conceded
that it was required by the access provisions to furnish certain cost
records in these circumstances (see note 6, supra).
14
future procurement needs”). And, as the court explained
in Eli Lilly & Co. v. Staats, supra, 574 F. 2d at 915, the
“argument that Congress could not have intended to
inquire into wastefulness in contracts such as the one here
in which the drugs were supplied to the Government ‘at a
fixed price at or below the wholesale market price’
* * * ignores the fact that the information sought by the
Government may show that the prices it paid were
nevertheless much too high.”!2
Furthermore, petitioner’s construction is at odds with
the administrative interpretation adopted by GAO, which
is entitled to judicial deference and which Congress,
although aware of the agency’s position, has never
disapproved. See 80-264 Pet. 16-17. This issue appears to
have first been contested by Hewlett-Packard in resisting
GAO access to its cost records. See Hearings on Relation
of Cost Data to Military Procurement Before the
Subcomm. for Special Investigations of the House
Comm. on Armed Services, 88th Cong., Ist Sess. 15-23
'2This consideration is well illustrated by the testimony of GAO
General Counsel Robert Keller betore a congressional subcommittee:
The catalog prices on Government orders [under sole source
procurement for klystron tubes} frequently exceeded the
company’s current cost of production by more than 100 percent.
*_* *
[T]he prices accepted by the General Services Administration
and paid by the military services were substantially higher than
seem reasonable in relation to the contractors’ costs to
manufacture and sell aircraft tires, and the Government
experienced unnecessary costs in its procurement of these items
* * * of approximately $10.7 million [in 1960] * * *.
Hearings on Relation of Cost Data tv Military Procurement Before
the Subcomm. for Special Investigations of the House Comm. on
Armed Services, 88th Cong., Ist Sess. 7 (1963). See also pages 15-16,
infra.
15
(1963). At that time, and prior to the commencement of
litigation, GAO concluded that it was entitled to examine
cost records regardless of the scope of the original
contract negotiations and that such records were “directly
pertine~t” even though the costs of performance played
no pari in those negotiations. /d. at 21-22.
GAO’s interpretation has been presented to Congress
on several occasions and tully explained in terms of the
legislative history and purpose of the statutes and their
construction by the courts. See, e.g., Hearings on Relation
of Cost Data to Military Procurement Before the
Subcomm. for Special Investigations of the House Comm.
on Armed Services, 88th Cong., Ist Sess. (1963), at 8
(“Our experience indicates the need for careful examina-
tion into the reasonableness of accepting catalog or other
established prices for negotiated procurements * * *. The
fact that a product is listed in a manufacturer’s catalog
and offered to any customer is no assurance that
competition actually is present or that the standard
catalog price is reasonable”), 10-12 (discussing Hewlett-
Packard case), 24-25 (relation between negotiation
process and right of access); Hearings on Comptroller
General Reports to Congress on Audits of Defense
Contracts Before the Subcomm. on Military Operations
of the House Comm. on Government Operations, 89th
Cong., Ist Sess. (1965), at 45-46 (discussing Hewlett-
Packard case), 512 (statement on behalf «f Machinery &
Allied Products Institute discussing GAO’s position); 115
Cong. Rec. 25801 (1969) (GAO memorandum setting
forth the agency’s position, accepted in Hewlett-
Packard, that access “is not limited to that necessary to
determine whether the contracts were performed in
accordance with their terms and whether the contracting
otficer had been detrauded or misled in entering into the
contracts * * *, by what the parties may have considered
16
or not considered in the course of negotiations * * *,
[or] by the fact that the contract was performed by the
delivery of ‘off-the-shelf’ items not specially manufactured
for the contract’).
Finally, with the isolated exception of the now-reversed
decision of the district court in Eli Lilly (see 574 F. 2d at
920, 923, 925), petitioner’s position has been rejected by
every court to address the issue. See Eli Lilly & Co. v.
Staats, supra, 574 F. 2d at 914; Hewlett-Packard Co. v.
United States, supra, 385 F. 2d at 1014, 1016; Merck &
Co. v. Staats, supra, slip op. 2, 4 (80-416 Pet. App. 2c,
4c). See also Pet. 14 n.26; Conditional Petition for
Certiorari Before Judgment in Merck & Co. v. Staats,
supra, at 16. Even in cases of non-cost-based contracts
where negotiations over price did not occur, GAO’s
examination of the contractor’s cost records could well
“lead to the use of other methods of meeting future
procurement needs” (Hewlett-Packard Co. v. United
States, supra, 385 F. 2d at 1016). And, as the court stated
in refuting the same argument in Eli Lilly (574 F. 2d at
913, 914-915):
In interpreting the statutory language, as the
Comptroller General contends, “it is hard to imagine
anything more directly related to a contract than the
‘cost of producing the items covered by it or the
matters going into the makeup of the price” * * *.
* * * * *
[Petitioner’s] argument * * * limit[s] “directly perti-
nent” to an inquiry into what issues were negotiated
at the time of contracting * * *. [his interpretation
apparently is based on the assumption that if the
Government did not negotiate about an issue, it
thereby considered it not to be pertinent. Such an
interpretation might be reasonable if the statutory
standard were that the information must be “directly
17
pertinent” to the negotiation, but the standard is
“directly pertinent” to the contract and plaintiff
offers no reason to suppose that there would be a
reason to negotiate about each item that might have
a significant effect on the seller’s cost or perfor-
mance.” * *
In the final analysis, [petitioner’s] suggested
interpretation of examining what was negotiated rests
on its conclusion that Sections 2313 and 254 were
designed only to uncover “improprieties in the
negotiation of Government contracts” * * *. How-
ever, *** controlling fraud was not the only
purpose of the legislation and * * * another concern
of the legislators was with excessive pricing. Given
this latter purpose and our view of the meaning of
“directly pertinent,” the access-to-records clauses
should be interpreted so that an item is “directly
pertinent” to a contract if it is a significant input in
the cost of the product purchased in the contract.
3. Apart from the lack of merit to its substantive
arguments, petitioner has failed to demonstrate that the
instant case warrants the extraordinary course of review
by this Court before judgment in the court of appeals. Pe-
titioner does not contend that the issues it seeks to raise
are “of such imperative public importance as to justify the
deviation from normal appellate practice and to require
immediate settlement in this Court.” Sup. Ct. R. 18.
Compare, e.g., United States v. Nixon, 418 U.S. 683
(1974); Youngstown Sheet & lube Co. v. Sawyer, 343
U.S. 579 (1952). Petitioner does assert, however, that
considerations of sound judicial administration militate in
favor of certiorari betore judgment in this case. We
disagree.
In essence, petitioner seeks to present two questions
that have not divided the courts of appeals and are not
18
otherwise appropriate for this Court’s review. Indeed, the
Court has already declined to hear these very questions in
the absence of such a conflict. See Eli Lilly & Co. v.
Staats, cert. denied, 439 U.S. 959 (1978). Petitioner has
suggested no reason for a different disposition of this case
even after decision by the court of appeals, and certainly
none that would provide sufficient grounds for cir-
cumventing that court by means of certiorari before
judgment.
Prudent judicial administration does not counsel a
contrary result. Notwithstanding petitioner’s apprehen-
sions, it is a distinct possibility, especially in light of Eli
Lilly, that the Court will never need to confront the two
issues raised here. On the other hand, if a conflict does
develop, there will be time enough then to petition for
certiorari at a poi when this Court would have the
benefit of full se ation of the courts of appeals’
divergent views.'? Moreover, insofar as petitioner wishes
to be heard on the question presented in Bristol—as to
which there is currently a conflict in the circuits—it can be
fully accommodated through the opportunity to appear as
an amicus curiae. In sum, to grant the instant petition for
certiorari before judgment, o: to deny the petition in
Bristol with the expectation of subsequently granting
certiorari in SmithKline or Merck after final judgment in
the court of appeals, would needlessly involve the Court in
the resolution of issues that plainly do not warrant review
and is umnecessary to protect petitioner’s legitimate
interests.
'SWe note that petitioner has urged the court of appeals, as one
disposition of the case, to vacate the judgment of the district court
and remand for further factual proceedings on the question of GAO's
purpose in requesting access to petitioner's records (SmithKline Br.
29-34; see also Pet. App. 10a). Ihus, even after the court of appeals
has rendered a decision, it is possible that the case would be
interlocutory in nature and therelore unsuited to review in this Court.
19
Petitioner is not aided in any way by the cases it cites
regarding certiorari before judgment (Pet. 16-17). None of
those cases concerned an attempt, as here, to interject new
and separate issues into a pending proceeding. Rather, in
each of the cited instances, the issues raised in the
respective cases were substantially identical. Moreover, on
each occasion, the decisions under review either involved
the same court of appeals, so that the circuit had already
passed upon the legal question presented in the petition
for certiorari before judgment,'* or pertained to a single
dispute and presented potentially inconsistent legal
obligations that could not be jointly fulfilled by the
parties.'> No comparable circumstances are presented in
this case, and the exceptional procedure for certiorari
before judgment is inappropriate here.!°
'4See Porter v. Dicken, 328 U.S. 252, 254 (1946), and Porter v.
Lee, 328 U.S. 246, 251 n.3 (1946); Johnson vy. Fleet Corp., 280 U.S.
320, 322-325 (1930). See also Jaylor v. McElroy, 360 U.S. 709, 709-
710 (1959), and Greene v. McElroy, 360 U.S. 474 (1959).
'SSee New Haven Inclusion Cases, 399 U.S. 392, 414, 418 (1970);
McCulloch v. Sociedad Nacional de Marineros de Honduras, 372
U.S. 10, 12 (1963). See also Washingion v. Fishing Vessel Assn., 443
U.S. 658, 671-674 (1979); Hannah v. Larche, 363 U.S. 420, 422-423 &
n.3, 428-430 (1960).
'6An analogous situation would exist here if, for example,
petitioner had filed suit in one district court to enjoin GAO’s request
and the government had brought an action in another district co art
to enforce the request; in the event the Court granted certiorari in one
of these cases after judgment in the court of appeals, it might not be
inappropriate (although it would hardly be necessary) to grant
certiorari before judgment in the other case if the litigated issues were
substantially identical and if either the two cases arose in the same
circuit or divergent decisions would impose incompatible legal duties
on the parties. In contrast, the instant petition does not implicate
these considerations in support of certiorari betore judgment.
20
CONCLUSION
The conditional petition for a writ of certiorari before
judgment should be denied.
Respectfully submitted.
WADE H. McCreg, JR.
Solicitor General
ALICE DANIEL
Assistant Attorney General
MICHAEL KIMMEL
ROBERT KAPLAN
Attorneys
NOVEMBER 1980
DOJ-1980-11
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.