Petition — Newport News Shipbuilding & Dry Dock Co. v. United States
Supreme Court brief1978
Ask Donna
What actually matters in this document.
Text
—_——_ -— —- —- ——
IN THE
Supreme Court, U. S,
FILED
1978
AGL RODAK, JR., CLERK
Supreme Court of the Unite
Ocrover Term, 1977
No. 77-1696
NeEwrvort NEWS SHIPBUILDING AND Dry Dock ComPANY.
AND TeENNECO INC., Petitioners,
Vv.
Unirep States or America, Respondent.
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
——
WituiAM McL. Ferouson
225- 28th Street
Newport News, Virginia 23607
K. Martin Worruy
JoHN G. DeGooyver
Mark Svutuivan IIT
JoHN H. SpeELLMAN
JEFFREY M. PerrasH
Larry H. MircHe.yi
HAMEL, Park, McCase & SaunpERS
1776 F Street, N.W.
Washington, D.C. 20006
Counsel for Petitioners
FCR
STORY
CLADS: LITTON, NEWPORT NEWS SEEK SUPREME COURT
REVIEW ON FRAUD INDICTMENT , FRIGATE SETTLEMENT
Two shipbuilders, unhappy with rulings by the U.S. Court of Appeals for
the Fourth Circuit, are ésking the Supreme Zuxe Court to become involved in
their claims battles with the Navy.
Newport News Shipbuilding and Dry Dock Co. tupammk seeks review of the
(721 FCR A-19)
appea ls court's reamns that the Government isn't bound by the settlement negotiated
by Gordon Rule requiring the Navy to pay an edditional $22.7 million for
construction of the DICN4] xuetemupqottet «4 nuclear-powered guided missile
frigate. (Newport News Shipbuilding and Dry Dock Co, and Tenneco Inc. v.
U.S., Sup. Ct. No. 77-16%, petition filed, 5/26/78)
Litto Sy stems Chuo. wants the Court to consider ak the lower court's
(729 FCR C-1)
muctutemxteet finding/theat the Yovernment's implied threst to continue mm e fraud
atrce J To had '
indictment unless Litton, reopened an ASBCA case in which it jon a $17 million
judgement, doesn't require dismissal of the indictment .
U.S., Sup. Ct. No. 771689, petition filed, 5/26/78)
(Litton Sy stens, Inc. v.
In the Newport News case, the district court held that the parties had ax
agreed to the settlement and tint the Justice Department, having refused to
aor
participate in the negotiations , was estopped to deny it. The court of appeals,
however, found no basis Sor, estoppel and said that the Attorney General had authority
4 °
to disapprove the prepexxix “proposed compromise,®
The Fourth “ircuit decision temtwwre-tamet, Newport News states in its putt
is The Tirst Ove iY
petition, holding that an ujency of the United “tetes lacks the power, without
a a
approval of the Attorney General, to take action otherwise authorized by law, if
that action has the effect of mooting pending litigation.
The Attorney General's authority is ba _sed on 28 U.S.C. Sections 516 and
519, which state that the "conduct of litigation” is reserved to the Justice
Bepartment and that the Attorney General is to “superivise all litigation®
involving the Government. Executive Orier 6166 authorizes the Attorney Generel
to compromise litigation/
The Attorney Seneetgpgey ine Gntimmnattan, has no authority
ot News rmeintoains.
bey@nd that delegated to nin, fs Since the Defense Department and the Navy have the
authority to contract for ships regardless of whether the United States and a
shipbuilder are in litigation, exercise of that agency authority can't be
vetoed by the Attorney General.
In S & E Contractors v. U.S., 406 U.S. 1 (426 FCR Sp Supp), the Court
rejected the argument that the Attorney General was authorized, under 28 #ixix
fit tiodikipdsas Bx
executive officers. "'Where the responsibility for rendering a decision is
U.S.C. 516 and 519, to override the decisions of other
vested in a coordinate branch of Government, the duty of the Department of
Justice is to implement that decision and not to repudiate it,'® the Court
stated.
Litton, in its peitition, complains of an abuse of the Sovernment's
5
dual role as defendant in a contract action and criminal prosecutor,
4 A indictment
he a ot appeals characterized wry threat as “plea bargaining” and
-similar to omer. ween permitted in Bordenkircher v. Hayes, @idum 6 °.Ct. 463,
>
—
axx
“ut, in plea bargaining, Litton argues, nothing is involved beyond the
criminal Le its fair and mx expeditious administration. The
"extortionate discussions" between Litton and the Government prosecutors eset
A
the ASBCA case had none of the ch... :*eristics of plea bargaining book ith
fegard. *
term is used in Bordenkircher, xtetex
In a case such as the present one, mmoctmcemnteramtkxex in contrast to
every case involving plea bargaining, the Sovernment's role as a fair contractor,
bound by contract law - the rules governing contract disputes, is a crucial
an
factor, Litton states, Jy vacating the trdal court's }mempmeatimarboox
"proper disciplining" of the “overnment for its extortion and vindictiveness,
the appeals court “gave the green light for abusé in the future.”
Er ere te er ear
INDEX
Page
I a Sa ee a id 1
ES ok Seo or ee seeensounseriee 2
CN TU oo cc oc ccvccccccdcccsecccccecens 2
ConsTITUTIONAL AND Statutory Provisions Invotvep.. 2
FeperaL Rute or Civic Procepure INVOLVED ......... 3
ee ee eaeeheeuas haere 3
Reasons ror GRANTING THE Writ
I. The holding of the Court of Appeals, that a de-
partment or agency of the United States can take
no action rendering pending litigation moot with-
out the approval of the Attorney General, con-
travenes law and public policy and presents im-
portant questions of federal law requiring reso-
ES Ge SY ES ddcnudcccectcsaceeueseees 15
A. The decision below conflicts with decisions of
RES ers Prer ake
B. The decision below conflicts with a decision of
the United States Court of Appeals for the
RR SE a et ele ae prae eee 19
C. The decision below contravenes the public
policy in favor of compromise of litigation
and threatens the efficiency of the executive
and judicial branches of the federal govern-
EG SEC GK 0G ad an ee edeeesebendehsckheenss 20
II. The decision of the Court of Appeals is based on
a standard of review inconsistent with the deci-
sions of this Court and the Federal Rules of Civil
ee ee es Le bane ee edieeeeeese 21
EE RE er Ee were 29
ii Index Continued
Page
BOM, oc nccesesnsntessesitesseseeeeeeeee la
A. Opinion of the United States Court of Appeals
for the Fourth Circuit. .......ccccccscccvcees la
B. Opinion and Order of the United States Dis-
trict Court for the Eastern District of Vir-
GE. ccccccseedvnesentecesuue ene 13a
C. Constitutional and Statutory Provisions In-
CURUGED ce cccccccocccesceciceeekueusete 47a
D. Rule 52(a) of the Federal Rules of Civil Pro-
GUD, 0 00 0k. ceeveecesesednedeenee 53a
E. August 29, 1975 Order of the United States
District Court for the Eastern District of Vir-
GM, cccccccccecesevevensedeeedenenee 54a
CITATIONS
CASES:
Commissioner v. Duberstein, 363 U.S. 278 (1960) ...22, 26
The Confiscation Cases, 74 U.S. (7 Wall.) 454 (1869) . 18
The Grey Jacket, 72 U.S. (5 Wall.) 342 (1867) ...... 19
Leonard v. United States Postal Service, 489 F.2d 814
(Set Gi, BOWe occcccnccscssceuanseuns mane 19, 20
Lockheed Shipbuilding & Construction Co., 75-2 BCA
DRED 00060000060080 60000 000nn ene 15
S & E Contractors v. United States, 406 U.S. 1 (1972) 18, 19
United States v. Morris, 23 U.S. (10 Wheat) 246
(ERED ccccccccsnecesgechetesennennaae 18, 19
United States v. National Ass’n. of Real Estate
Boards, 339 U.S. 485 (1950) ...............- 21, 22, 23
United States v. Oregon State Med. Soc., 343 U.S.
SD CUUUED cccccecnevcssescusiunensneee 22, 23
United States v. Sandstrom, 22 F. Supp. 190 (N.D.
Cin, SGD 0 o+cceneseeseccnsnnsarenaneeeene 19
Umted States v. Singer M fg. Co., 374 U.S. 174 Soa . 21
United States v. United States Gypsum Co., 333 U.S.
See CHOU cicccctscccescenacuenneneneeeee 21
United States v. Yellow Cab Co., 338 U.S. 338 (1949) .21, 22
Wiliams v. First National Bank, 216 U.S. 582 (1910) .. 20
Zenith Radio Corp. v. Hageltine Research, Inc., 395
Uae BOO GHREED cccccescvecesesecessmee 21, 22
— ‘
Citations Continued iii
Page
Unritep States ConstitTvuTion:
U.S. Constitution, Art. I, §8, Cl. 13 ................ 2,15
STaTuTEs:
EEE EESES SESS SS OPP PPOTOLTETTET TLE TY 2,15
10 UB.C. $6 18B(a), (b), (4) .cccccccccccccccccccees 2,15
EES ESSELTE SESE POP TETTTTTTT EET Y 2
19 U.S.C. § 2308(a)(2), (b)(4) .... cece eee eeees 2,15
10 U.S.C. §$ 2304(a)(13)-(14) .... cece ccc eee eens 3,15
cic ee sececcccceccsccccces 3,15
EEE ESTES ISS OPO OTTTOTT TELE TTT TT 3,15
EEE SES IEP PET OTTTTTETTTTTET YE 3, 16, 18
EET OTTTTTTTTTTT TTT Te 3, 16, 18
Bee e sac cceceecscoccccccccece 2
eee coc c ccd ccccesceccecocceces 3
EE SLES SEES IPP ETTOTTETTET TET 3, 15
FeperaL Ruues or Crvm Procepure:
Fed. R. Civ. P. 52(a) .......... <> + 2/3, 21, 22, 23, 25, 28
REGULATIONS:
ES EES ETE CETTULETTEE ETE EE 15
Executive OrpERs:
Ex. Ord. 6166, June 10, 1933 .............. cee eeeee. 17
IN THE
Supreme Court of the United States
OcrToBeR TERM, 1977
No.
NEwportT NEws SHIPBUILDING AND Dry Dock CoMPANY,
AND TENNECO INc., Petitioners,
Vv.
Unirep States oF America, Respondent.
PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
The Petitioners, Newport News Shipbuilding and
Dry Dock Company (‘‘Newport News’’) and Tenneco
Inc., respectfully pray that a writ of certiorari be
issued to review the judgment and opinion of the
United States Court of Appeals for the Fourth Cir-
cuit entered in this proceeding on February 27, 1978.
OPINIONS BELOW
The opinion of the Court of Appeals, reported at
571 F.2d 1283, is reproduced in its entirety as Adden-
dum A hereto, pp. la-12a. The opinion of the United
e States District Court for the Eastern District of Vir-
ginia, which is not reported, is reproduced in its en-
-tirety as Addendum B hereto, pp. 13a-46a.
2
JURISDICTION
The judgment of the Court of Appeals for the
Fourth Circuit was entered on February 27, 1978, and
this petition for certiorari is filed within 90 days of that
date. This Court’s jurisdiction is invoked under 28
U.S.C. § 1254(1).
QUESTIONS PRESENTED
1, Whether agency action, taken pursuant to duly
delegated authority, can be set aside by the Attorney
General solely because it would have the effect of com-
promising or rendering moot pending litigation in
which the Attorney General represents such agency.
2. Whether a Court of Appeals can substitute its
judgment as to a District Court’s findings of fact,
made on the basis of depositions, documentary evi-
dence and concessions of counsel before the District
Court, concerning the meaning and extent of compli-
ance with an order of the District Court entered at the
request of both parties.
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED
The following constitutional and statutory provi-
sions involved are reproduced in Addendum C hereto,
pp. 47a-52a.
U.S. Constitution, Art. I, §8, Cl. 13
10 U.S.C. §131
10 U.S.C. §133(a),(b),(d)
10 U.S.C. § 134
10 U.S.C. § 2303(a) (2),(b) (4)
ee a
3
10 U.S.C. § 2304(a) (13)-(14)
10 U.S.C. § 5011
10 U.S.C. § 5031
28 U.S.C. § 516
28 U.S.C. §519
50 U.S.C. § 401
FEDERAL RULE OF CIVIL PROCEDURE INVOLVED
Rule 52(a) of the Federal Rules of Civil Procedure
is reproduced as Addendum D hereto, p. 53a.
STATEMENT
This action was brought by the United States in the
United States District Court for the Eastern District
of Virginia on August 29, 1975, under 28 U.S.C. § 1345,
for specific performance of an alleged contract for the
construction of a nuclear-powered guided missile frig-
ate designated DLGN-41.‘ Work continued on the
DLGN-41 pursuant to a court order consented to by
the parties and requiring them to negotiate their dif-
ferences in good faith. Nearly one year later the parties,
through their duly authorized agents, arrived at what
the negotiators on both sides believed to be an agree-
ment settling the litigation. Upon Petitioners’ motion
the District Court enforced this settlement agreement,
ruled that the United States had acted in bad faith,
and dismissed the case. On appeal by the United States,
the Court of Appeals for the Fourth Circuit reversed.
1 The Navy has changed the designation DLGN to CGN and the
terms ‘‘DLGN-41’’ and ‘‘CGN-41’’ have been used interchange-
ably in the pleadings, evidence and arguments before the courts
below.
4
Petitioners now seek review by this Court of the action
of the Court of Appeals.
Background—Pre-August 29, 1975
On December 21, 1971, Newport News entered into
a contract (Contract Modification P00007) with the
United States Navy for the construction of three nuc-
lear-powered guided missile frigates designated as
DLGN’s 38, 39, and 40, [App. 5; App. Ex. 1-27].* The
contract included a provision captioned ‘‘Option for
Increased Quantity’? [App. Ex. 27] which stated in
part that the Navy had an option, exercisable before
February 1, 1973, for the construction of an additional
such frigate, the DLGN-41.
On February 1, 1973, the parties executed a docu-
ment, Contract Modification P00018, which purported
to extend the ‘‘Option for Increased Quantity’’ on new
terms to February 1, 1975, but only if certain prior
conditions were met. [App. Ex. 28-40]. One such condi-
tion was that the parties ‘‘negotiate in good faith to
reach an agreement as rapidly as possible” on various
matters, eight of which were specifically enumerated in
the modification and upon which the parties had pre-
viously been unable to agree. [App. Ex. 31-32]. Almost
a year passed in which the Navy made no effort to ne-
gotiate. [App. Ex. 233-35; also see Affidavit of F.
Hunter Creech, dated August 29, 1975, pp. 4-8 (Record
29-33) ]. In 1974, Newport News made repeated, un-
successful attempts to get the Navy to negotiate and
agree on such matters. [App. Ex. 233-35; also see Affi-
davit of F. Hunter Creech, dated August 29, 1975, pp.
* References are tc the Appendix, Appendix Exhibits and Record
before the Court of Appeals.
5
4-8 (Record 29-33)]. Also, despite the fact that the
Navy had made over 300 separate drawing design and
specification changes for the three earlier ships then
under construction and even though the option related
to an ‘‘Increased Quantity’’, the Navy repeatedly re-
fused to incorporate such changes into the drawings
and specifications for the DLGN-41. [App. Ex. 234;
also see Affidavit of F. Hunter Creech, dated August
29, 1975, pp. 3-9 (Record 28-34) ]. Meanwhile Newport
News undertook certain preliminary work on the
DLGN-41.
Finally in August 1974, Newport News formally ad-
vised the Navy that for numerous reasons—including
the Navy’s refusal to fulfili its obligations to negotiate
under Modification P00018—Newport News regarded
the option to be a nullity, void and of no legal effect.
(App. 142, 595; also see Affidavit of F. Hunter Creech,
dated August 29, 1975, pp. 6-8 (Record 31-33) ]. Never-
theless, the Navy purported to exercise the option by
notice to Newport News on January 31, 1975. [App.
Ex. 46-46a]. Newport News immediately notified the
Navy that it considered the alleged option and its pur-
ported exercise to be void and unenforceable, but ex-
pressed its continuing interest in reaching a mutually
acceptable arrangement for construction of the DLGN-
41. [App. Ex. 47]. Upon discovering shortly thereafter
that the Navy had previously determined (in October
1974) that the total cost of the DLGN-41 would exceed
the appropriation then available therefor, Newport
News advised Navy that it considered the purported
exercise of the option invalid for the additional reason
that it violated the Anti-Deficiency Acts. [App. Ex.
358-63 ].
6
In light of the Navy’s insistence that Newport News
proceed with construction, and Newport News’ insist-
ence that it had no obligation to do so, the parties en-
tered into a January 31, 1975 Memorandum of Under-
standing which was subject to cancellation by either
party at the end of 30 days and pursuant to which: (a)
Newport News agreed to continue its work on the
DLGN-41 for the time being; (b) the Navy agreed to
pay for subsequent work as it had for past work; (c) the
parties agreed not to institute any action in any admin-
istrative or judicial tribunal ; and (d) the parties agreed
‘‘to negotiate in good faith to reach an agreement as
rapidly as possible to modify those contract provisions
requiring amendment or to take other appropriate ac-
tion.’’ [App. Ex. 49-50; App. 145, 598].
Notwithstanding its initial agreement to discuss all
issues between the parties, the Navy refused in early
1975 to negotiate with respect to the validity of the
option or on any matters other than the eight items
enumerated in Modification P00018 without some show-
ing of government fault or unless new consideration
flowed to the government. [App. 121-22, 148-50, 300;
App. Ex. 236-39, 358-67]. In June 1975, the Navy re-
fused to make any further payments for work being
done by Newport News under the Memorandum of
Understanding. [App. 53, App. Ex. 238-39]. The Navy
also refused to agree with a request previously made
by Newport News that the Navy join it in asking for an
opinion of the General Accounting Office with respect
to the sufficiency of the available appropriation. [ App.
46-48, 51-53, 58-60, 63-66; App. Ex. 52]. Since Newport
News was prohibited by the terms of the Memorandum
of Understanding from seeking such an opinion on its
own, it exercised its right to terminate the Memoran-
7
dum of Understanding effective August 27, 1975, and
on that day filed a request with the General Account-
ing Office for an opinion on the anti-deficiency ques-
tions. [App. 52-53, 62]. Newport News also advised
the Navy that ‘‘[p]ending a resolution of the questions
as to the validity of the option and its exercise, all ma-
terial procurement, shop fabrication and other prelim-
inary work on the DLGN41 which has been continuing
pursuant to the Memorandum of Understanding will
be suspended and the DLGN41 construction effort will
not begin.’’ [See Affidavit #2 of Vincent F. Ewell,
dated August 29, 1975, Appendix A, Exhibit M, p. 10
(Record 168) ].
August 29, 1975—March 7, 1977
On August 29, 1975, the government brought this
action for an injunction to compel Newport News to
construct the DLGN-41, and the District Court heard
argument on the government’s Motion for Temporary
Restraining Order. [ App. 14-77].’ After a hearing and
recess, during which counsel for the parties engaged in
extensive discussion, the parties by counsel entered into
a stipulation which, at the request of counsel, was en-
tered as an order of the District Court in lieu of a Tem-
porary Restraining Order. [Addendum E hereto, pp.
54a-55a]. This order required Newport News to con-
tinue its efforts with respect to the DLGN-41, required
the Navy to pay for those efforts in the same manner as
under the Memorandum of Understanding, and re-
quired that the changes made in the plans and speci-
* The government was represented by Mr. Jeffrey Axelrad, United
States Department of Justice, and by Mr. E. Grey Lewis, United
States Department of Navy.
8
fications for DLU.N’s 38, 39 and 40 be incorporated into
the plans and specifications for DLGN-41. Addition-
ally, after reciting Newport News’ contention as to the
invalidity of the option and its exercise, the order pro-
vided :
‘‘The parties agree to negotiate in good faith
to reach an agreement as rapidly as possible to
modify those contract prewisions requiring amend-
ment or to take other appropriate action.’’ [Ad-
dendum E hereto, p. 54a]
At the time this order was entered, counsel for the
Department of Justice and the Navy assured the Dis-
trict Court that, ‘‘Mr. E. Grey Lewis [General Coun-
sel of the Navy] on behalf of the Navy has agreed to
undertake to ensure the Navy’s obligation hereunder.’’
[App. 70-71, 150]. In response to a question from the
court, Mr. Lewis confirmed his and the Navy’s assump-
tion of this obligation. [App. 71].
The Navy did not carry out its obligations under the
stipulation and order to negotiate in good faith with
Newport News during the succeeding 11 months. The
Navy failed to provide Newport News with informa-
tion essential to meaningful negotiations, and also or-
dered Mr. Lewis, who was responsible for its obliga-
tions under the consent order, out of the settiement ne-
gotiations in October 1975. [App. 152, 155-58]. The
Deputy Secretary of Defense subsequently determined
that from the date of the court order until July 1976,
the Navy did not negotiate in good faith on the DLGN-
41 dispute. [App. Ex. 253]. A subsequent negotiator of
the Navy, Mr. Gordon W. Rule, who was appointed in
July 1976, also characterized the Navy as having had
during such period a ‘“‘complete adversary attitude,
complete lack of good faith, at all times a lack of good
faith.’’ [App. 345-49].
The Navy’s failure to negotiate in good faith caused
Newport News to file a motion in the District Court on
July 13, 1976, requesting, among other things, that the
government be ordered to comply with its obligations
under the August 29, 1975 order. [App. 112-17]. The
Deputy Secretary of Defense held a meeting in his of-
fice within hours after the Newport News motion was
filed, as a result of which Gordon W. Rule was ap-
pointed to negotiate with Newport News concerning
the DLGN-41 dispute. [App. 286-88, 294; App. Ex.
251, 256, 277]. Newport News was subsequently advised
of Mr. Rule’s appointment and repeatedly told by the
Navy that he had complete authority to resolve this
controversy. [App. 222-23, 240-41, 291-92, 295, 306-07,
358, 373-75]. Mr. Rule was appointed with the knowl-
edge and concurrence of the Department of Justice,
and Justice confirmed Newport News’ understanding
that Mr. Rule had authority ‘‘to resolve all issues be-
tween the parties.’’ [App. Ex. 277; App. 639-39a, 658].
Following Mr. Rule’s appointment, both he and the
Department of Justice requested that Newport News
withdraw its July 13, 1976 motion because of Mr.
Rule’s appointment as negotiator. [ App. 224-25, 294-95,
639-39a]. Acting on government representations that
Mr. Rule had been appointed with full authority to
reach agreement with Newport News resolving all is-
sues between the parties, Newport News requested that
the District Court hold the July 13 motion in abey-
ance pending further advice from Newport News.
[App. 225, 639a, 658].
Immediately following Mr. Rule’s appointment, he
and Newport News commenced negotiations in good
10
faith to reach an agreement resolving the issues in dis-
pute between the parties. [App. 223-29, 291-300]. Con-
siderable information and data were requested from,
and provided by, Newport News. [Jd.]. On August 19,
1976, Gordon W. Rule received a contracting officer’s
warrant granting him:
‘‘Unlimited authority with respect to negotiations
with Newport News rnin po | and Dry Dock
Company for construction of CGN 41 under Con-
tract N00024-70-C-0252.”’ [App. Ex. 276; App. 230,
301, 306-07, 361, 374-75].
On the morning of August 20, 1976, Mr. Rule and other
representatives of the Navy met with representatives
of Newport News and an agreement was reached as to
all substantive matters in issue, which was subsequently
upheld by the District Court. [App. 230-35, 248, 300-06,
312-13, 407, 409, 460-61; App. Ex. 482; Addendum B
hereto, pp. 13a-46a]. With the concurrence of the Navy,
Newport News issued a press release announcing the
settlement. [App. 236-38].
After reaching agreement on August 20, 1976, the
parties began work on a written document expressing
the terms of their agreement. [App. 239, 241-44, 307,
313-14]. At the same time, persons within the Navy
eommenced efforts to disavow the agreement and to
place purported restrictions on Mr. Rule’s authority.
[ App. 236-41, 243-45, 309-14, 320-23, 358-66, 372-74, 447-
51; App. Ex. 502, 528]. Notwithstanding these efforts,
Mr. Rule, on behalf of the Navy, and Mr. Dart, on
behalf of Newport News, executed a final written con-
tract modification on October 7, 1976, constituting a
written settlement agreement. Mr. Rule’s contracting
officer’s warrant was immediately thereafter revoked.
li
[App. 197, 333-34, App. Ex. 279]. Deputy Secretary
of Defense Clements then found the agreement to be
a reasonable resolution to the dispute and sent the
agreement to the Attorney General for implementa-
tion. [Addendum B hereto, pp. 27a, 35a]. The Attorney
General subsequently, however, purported to disap-
prove the settlement and refused to recognize its va-
lidity. [Addendum B hereto, p. 27a].
Newport News thereupon filed a Motion for Entry
of Judgment (on the ground that the case had been
settled by the agreement with Mr. Rule) or, In the
Alternative, for Dismissal with Prejudice (on the
ground of bad faith on the part of the government in
failing to carry out the District Court’s order). [ App.
192-248].
The Decisions Below
In a March 8, 1977 Memorandum Opinion and Or-
der, the District Court held that the parties had reached
an agreement on August 20, 1976, the government was
bound by its agreement, and the government had acted
in bad faith. Accordingly, the District Court granted
Newport News’ motion and dismissed the case. [Ad-
dendum B hereto, p. 46a].
The District Court supported its decision by making
extensive findings of fact based on a voluminous record,
containing testimony, affidavits and documentary evi-
dence, and the appearance and concessions of counsel
before it. The court found that: Deputy Secretary
Clements appointed Mr. Rule as chief negotiator with
authority to bind the United States to a compromise
agreement, and, on August 19, 1976, the Navy had
issued Mr. Rule a contracting officer’s warrant grant-
ing him ‘“‘unlimited authority”’ to negotiate with New-
port News concerning the dispute; serious negotiations
12
had begun July 15, 1976, and continued on an almost
daily basis through August 20, 1976; on August 20,
1976, the parties came to an oral agreement on all of
the outstanding substantive issues concerning the CGN-
41 and agreed to prepare a written agreement; and that
the parties intended to be bound by their August 20,
1976, agreement. [Addendum B hereto, p. 23a-25a]. On
the basis of these findings, the District Court con-
cluded that a binding agreement between the parties
existed on August 20, 1976.
The District Court made additional findings of fact
concerning the conduct of the government and the De-
partment of Justice in the settlement negotiations. It
found that the government had agreed on three sepa-
rate occasions to negotiate in good faith to resolve all
its differences with Newport News: when it entered
into the January 31, 1975 Memorandum of Under-
standing; when it sought entry of the August 29, 1975
consent order; and when Mr. Rule was appointed and
Newport News was induced to request the District
Court to stay action on Newport News’ July 13, 1976
motion. [Addendum B hereto, pp. 19a; 14a, 21-22a,
39a; 23a-24a, 39a]. The court found that in August
1975, the Department of Justice had represented to it
that the United States was bound to negotiate in good
faith and had joined with Newport News and requested
the court to enter its August 29, 1975 consent order.
[Addendum B hereto, pp. 21a-22a, 39a]. At that time
the Department of Justice stipulated to the court that
the Navy’s General Counsel would ‘‘undertake to en-
sure the Navy’s obligation’’ to negotiate pursuant to
the consent order. [Addendum B hereto, pp. 22a, 39a].
The court further found that, the United States
through the Department of Justice had made ‘‘a de-
liberate decision not to seek an immediate judicial de-
Bie oe es
13
termination of its rights under the disputed option
contract’’ when it requested entry of the August 29,
1975, consent order. [Addendum B hereto, p. 39a]. The
Department of Justice was found to have reaffirmed its
agreement when it consented to the appointment of
Mr. Rule. [Addendum B hereto, p. 40a]. The Depart-
ment of Justice refused to participate directly in any
negotiations for the next seventeen months. [ Adden-
dum B hereto, p. 15a]. On the basis of these findings the
court held the United States ‘‘estopped to deny the
authority of the Department of Defense to bind the
United States to a compromise agreement.’’ [Jd.].
Notwithstanding the government’s commitment to
negotiate the resolution of all differences in good faith,
the District Court found that the government ‘‘utterly
failed”’ to so negotiate until Mr. Rule’s appointment.
[Addendum B hereto, p. 14a]. It found that: the
Navy had ignored not only its own January 31, 1975
Memorandum of Understanding, but the August 29,
1975 consent order as well [Addendum B hereto, p.
22a]; it had ordered the General Counsel of the Navy
to stop negotiating in October of 1975 [Addendum B
hereto, pp. 22a-23a]; and the Navy made efforts to un-
dermine Mr. Rule’s authority after August 20, 1976.
[Addendum B hereto, pp. 25a-27a]. The court further
found that Navy’s position that it would only negotiate
the eight items originally listed in Modification P00018
was ‘‘incredible’’ since language expressly limiting
the negotiations to those items was expressly excluded
from the final version of the January 31, 1975 Memo-
randum of Understanding. [Addendum B hereto, p.
20a]. The court stated that it would not have entered
the August 29, 1975 consent order had it been aware
14
that the government would later attempt to assert that
it was not required to negotiate all differences. [ Adden-
dum B hereto, p. 14a].
On the basis of these findings of fact, as well as others
recited in its opinion, the District Court held the par-
ties had agreed to a settlement, the government and
the Department of Justice were estopped to deny it,
and the government had acted in bad faith towards
the court and Newport News.
The government appealed the District Court’s de-
cision to the United States Court of Appeals for the
Fourth Circuit which reversed the lower court in a
February 27, 1978 decision and remanded the case to
the District Court for further proceedings consistent
with the court’s opinion. [Addendum A hereto, p. 10a].
The Court of Appeals set aside the District Court’s
findings of an August 20, 1976 agreement notwithstand-
ing its concurrence in the trial court’s finding that on
“that date ‘‘the parties reached what Rule and the
Shipyard’s negotiators considered to be an oral agree-
ment in principle... .’’ [Addendum A hereto, p. 3a].
Ignoring the specific findings of the District Court and
without citing any principles of law involved, the Court
of Appeals concluded that the Department of Justice
decision not to take part in the settlement negotiations,
standing alone, did not constitute ‘‘a sufficient basis
for invoking estoppel.’’ [Addendum A hereto, p. 8a].
Conceding that the underlying facts were not in dispute
[Addendum A hereto, pp. 5a, 10a], and that there was
no need for an evidentiary hearing on the motion to en-
force the settlement [Addendum A hereto, p. 5a], the
Court of Appeals nevertheless held that a summary
disposition of the case on the grounds of bad faith by
the government towards the court at that time was
Na oe, antral
15
inappropriate because there was a controversy as to
the inferences that could be drawn from the undisputed
underlying facts. [Addendum A hereto, p. 10a].
I, THE HOLDING OF THE COURT OF APPEALS, THAT A DE-
PARTMENT OR AGENCY OF THE UNITED STATES CAN
TAKE NO ACTION RENDERING PENDING LITIGATION
MOOT WITHOUT THE APPROVAL OF THE ATTORNEY
GENERAL, CONTRAVENES LAW AND PUBLIC POLICY AND
PRESENTS IMPORTANT QUESTIONS OF FEDERAL LAW
REQUIRING RESOLUTION BY THIS COURT.
The decision of the Court of Appeals in this case
marks the first time that any federal court has held
that a department or agency of the United States lacks
the power, without approval of the Attorney General,
to take action otherwise authorized by law, if that ac-
tion has the effect of mooting pending litigation.
The Department of Defense and the Navy have spe-
cific authority and responsibility for the procurement
of vessels for the fleet. U.S. Const. Art. I, § 8, Cl. 13;
10 U.S.C. §§ 131, 133(a), (b), (d), 2303(a) (2), (b) (4),
2304(a)(13)-(14), 5011, and 5031; 50 U.S.C. §401;
Lockheed Shipbuilding & Construction Co., 75-2 BCA
111,566 at 55,213-15, 17. That authority was exercised
when Gordon W. Rule was appointed as a contracting
officer pursuant to 32 C.F.R. § 1-405.2. On August 20,
1976, Mr. Rule, in his capacity as a duly designated
contracting officer, and Newport News reached an
agreement for the construction of the vessel known as
the DLGN-41. On October 7, 1976, the parties entered
into a contract modification which was approved by
Deputy Secretary of Defense Clements as ‘‘a reason-
ble resolution to this complex matter.’’ [ App. Ex. 259].
On October 15, 1976, the modification was sent to the
16
Attorney General for implementation,* but the Attor-
ney General subsequently purported to disapprove the
agreement. [Addendum B hereto, p. 27a].
The Court of Appeals, without elaboration or cita-
tion to any authority which grants the Attorney Gen-
eral power to do more then supervise, compromise and
settle litigation, held that: ‘*The law pertaining to
the Attorney General’s control over cases referred to
the Department of Justice by other agencies of the
government fully sustains his authority to disapprove
the proposed compromise.’’ [Addendum A hereto, p.
9a]. However, contrary to this holding of the Court
of Appeals, the law does not sustain any power in the
Attorney General to veto any action of a department
or agency of the United States which would have the
effect of rendering litigation moot.
The Attorney General’s authority to conduct litiga-
tion on behalf of federal agencies is not inherent,
but rather derives from 28 U.S.C. §§ 516, 519. Neither
of these sections limits the authority of an executive
agency to take actions permitted it by law which would
have the effect of mooting or compromising litigation
which has been referred by the agency to the Depart-
ment of Justice. 28 U.S.C. § 516 states only that the
“conduct of litigation’’ to which the government is a
party and the ‘‘securing of evidence therefor’’ are re-
served to the Department of Justice. Similarly, 28
U.S.C. §519 provides only that the Attorney General
* The court order of August 29, 1975, with respect to the obliga-
tions of the parties as to negotiations and as to construction and
payment pending resolution of the dispute, was stil] in effect, and
it was necessary for appropriate steps to be taken to obtain ratifica-
tion by the District Court of the settlement negotiated pursuant to
that order.
Gian. -
17
will ‘‘supervise all litigation’’ involving the govern-
ment and ‘‘shall direct all United States Attorneys,
Assistant United States Attorneys and special attor-
neys appointed under [28 U.S.C. §543] in the dis-
charge of their respective duties.’’ Executive Order
No. 6166, June 10, 1933, gives the Attorney General
the authority to compromise litigation. No decision has
been found that construes these statutory provisions,
their predecessors, or Executive Order No. 6166 to ex-
tend the Attorney General’s authority beyond: (1) the
overseeing of the conduct of proceedings on behalf of
the United States; (2) the authorizing of Department
of Justice attorneys to appear as counsel of record on
behalf of the United States; and (3) the ability to com-
promise litigation committed to his supervision.
In short, the Attorney General has no authority be-
yond that which is delegated to him. Inasmuch as the
Department of Defense and the Navy have the author-
ity to contract for vessels irrespective of whether the
United States and a shipbuilder are in litigation, the
exercise of that authority cannot be prevented or ve-
toed by the Attorney General. If the Attorney General
is for the first time to acquire authority to block agency
actions, within the scope of the agency’s authority,
which have the effect of settling or mooting litigation,
Petitioners contend that only the Congress can grant it.
At the very least, the decision of the Court of Appeals
holding that existing law grants or sustains such au-
thority requires the review of this Court.
A. The Decision Below Conflicts With Decisions of This Court.
This Court has specifically upheld the power of an
agency to take action, within the scope of its authority,
18
which has the effect of mooting pending litigation.
United States v. Morris, 23 U.S. (10 Wheat) 246
(1825).
In Morris, this Court upheld the authority of the
Secretary of the Treasury to remit a forfeiture during
pending litigation. The plaintiffs, customs collectors
suing in the name of their employer, the United States,
and represented by the Attorney General, brought suit
against a United States Marshal for his failure to sell
a vessel and its goods which had been seized and con-
demned as forfeited for violation of non-intercourse
acts then in existence. After condemnation, but before
execution, and therefore while the matter was still in
litigation, the Secretary of the Treasury remitted the
forfeiture. The marshal then delivered the property
back to the defendants in the condemnation action
pursuant to the Secretary’s grant of remission. This
Court held over objection of the plaintiffs that the
Secretary did not exceed his authority when he remit-
ted the forfeiture during the pendency of litigation
involving validity of the forfeiture. The Morris de-
cision was cited with approval and discussed at some
length by the Court in The Confiscation Cases, 74 U.S.
(7 Wall.) 454, 461-62 (1869).
Moreover, in S & E Contractors v. United States,
406 U.S. 1 (1972), this Court rejected the government
argument that 28 U.S.C. §§ 516, 519 gave the Attorney
General authority to override the decisions of other
executive officers:
“‘[W here the responsibility for rendering a de-
cision is vested in a coordinate branch of Govern-
ment, the duty of the Department of Justice is to
19
om that decision and not repudiate it.’’ /d.
at 13.°
The conflict between the holding of the court below
and the decisions of this Court in Morris and S & E
Contractors fully justifies the grant of certiorari to
review the judgment below.
B. The Decision Below Conflicts With a Decision of the United
States Court of Appeals for the First Circuit.
The Court of Appeals for the First Circuit has taken
a position directly in conflict with the holding of the
court below. Jn Leonard v. United States Postal Ser-
vice, 489 F.2d 814 (1st Cir., 1974), while the litiga-
tion was pending, the Postal Service entered into a
stipulation of settlement. Despite objections of the At-
torney General, the District Court entered judgment.
The Court of Appeals found that, under the special
statutory scheme for the Postal Service, that agency
was authorized to settle litigation. The Court further
stated (at 817 n.7), however:
‘These [cited] cases may establish the proposition
that where the Attorney General has supervision
and control over a particular litigation he is em-
powered to settle that litigation. But we have had
no case pointed out to us, nor have we been able to
discover any, where it has been held that the At-
torney General can block a setiiement agreed to
*An agency cannot, of course, take action which would render
pending litigation moot if it lacks the authority to take such ac-
tion in the absence of litigation. The Grey Jacket, 72 U.S. (5
Wall.) 342 (1867). It has been recognized, howeyer, that this does
not mean that an agency is completely lacking in authority to com-
promise a matter merely because it is in litigation. United States
v. Sandstrom, 22 F. Supp. 190, 191 (N.D. Okla., 1938).
20
by a government agency involved in that litiga-
tion. Such an action on the part of the Attorney
General would not further the policy interest in
giving him power to screen out cases which should
not burden the federal courts. See, FTC v. Claire
Furnace Co., supra. And, at least in some cireum-
stances, it would violate the spirit of S & E Con-
tractors, Inc. v. United States, 406 U.S. 1, 13, 92
S. Ct. 1411, 31 L.Ed. 2d 658 (1972).”’
(emphasis in original)
The position of the Court of Appeals below and tuat
of the First Circuit as to the authority of the Attorney
General to set aside compromises of litigation are in
direct conflict, and this conftict alone justifies the grant
of certiorari to review the judgment below.
C. The Decision Below Contravenes the Public Policy in Favor of
Compromise of Litigation and Threatens the Efficiency of the
Executive and Judicial Branches of the Federal Government.
The decision of the Fourth Circuit in this case, which
affects every party to litigation in which the Attorney
General is involved, contravenes a longstanding pub-
lie policy in favor of compromises of litigation. Wil-
liams v. First National Bank, 216 U.S. 582, 595 (1910).
Such compromises permit a more efficient functioning
of the judicial system. At a time when the number of
cases pending in the federal courts is increasingly an-
nually, impediments to compromises should not be con-
doned, much less approved. Such impediments are also
inappropriate from the perspective of the departments
and agencies of the United States whose own orderly
functioning depends in part on their ability to decide
whether to continue or compromise disputes with pri-
vate parties.
21
Il. THE DECISION OF THE COURT OF APPEALS IS BASED ON
A STANDARD OF REVIEW INCONSISTENT WITH THE
DECISIONS OF THIS COURT AND THE FEDERAL RULES OF
CIVIL PROCEDURE.
The Court of Appeals improperly discharged its
appellate function when it failed to apply the proper
standard of review to the District Court’s findings of
fact and substituted its judgment for that of the lower
court. Both the Federal Rules of Civil Procedure and
decisions of this Court accord finality to trial court
findings of fact unless the findings are clearly errone-
ous. Rule 52(a), Fed. R. Civ. P.; United States v.
United States Gypsum Co., 333 U.S. 364, reh. den., 333
U.S. 869 (1948). Rule 52(a) does not authorize the re-
viewing court to try factual issues de novo and requires
that deference be given to the decisions of the trier of
fact. Zenith Radio Corp. v. Hazeltine Research, Inc.,
395 U.S. 100, 123 (1969).
The duty of a reviewing court is to correct clear
error and to set aside the trial court’s findings of fact
only when a review of the evidence clearly compels a
contrary finding. United States v. Yellow Cab Co., 338
U.S. 338, 342 (1949); United States v. Singer Mfg.
Co., 374 U.S. 174, 194 n.9 (1963). A choice by the trial
court between permissible views of the evidence is not
‘clearly erroneous’’. United States v. Yellow Cab Co.,
supra, at 342. A reviewing court is not given the choice
of substituting its judgment for that of the trial court
simply because it might give the facts another con-
struction or resolve ambiguities differently. United
States v. National Ass’n. of Real Estate Boards, 339
U.S. 485, 495-96 (1950). Instead, Rule 52(a) requires
it to accept the lower court’s findings unless clearly
erroneous, and this is true even though the record is
22
lengthy, contains conflicts in testimony, and includes
quantities of documentary material. United States v.
Oregon State Medical Society, 343 U.S. 326 (1952).
The Rule applies as well to factual inferences drawn
from undisputed facts. Commissioner v. Duberstein,
363 U.S. 278, 291 (1960).
The opinion of the Court of Appeals, which is devoid
of any reference to Rule 52(a) or any holding that the
District Court’s findings of fact were clearly errone-
ous, constitutes precisely the de novo retrial of fac-
tual issues and substitution of judgment which Rule
52(a) and the decisions of this Court prohibit. Zenith
Radio Corp. v. Hazeltine Research, Inc., supra; and
United States v. National Ass’n. of Real Estate Boards,
supra. A reading of the Court of Appeals opinion,
which fails to consider some of the District Court’s
findings and concedes that others are not in dispute,
compels the conclusion that the Court of Appeals did
not regard the trial court’s findings as clearly errone-
ous within the meaning of Rule 52(a). Instead, the
Court of Appeals simply had a different view of the
evidence as to the existence of an agreement on August
20, 1976, the actions of the government constituting
estoppel to deny a settlement, and the bad faith conduct
of the government. Such a difference of opinion is not
sufficient grounds for a reviewing court to set aside a
trial court’s findings where, as in this case, the findings
were made on the basis of a voluminous record, con-
taining testimony, affidavits, and documentary evi-
dence, United States v. Oregon State Medical Society,
supra, and also the appearance and concessions of
counsel before the District Court.
Ms iat a a ee ee
23
The August 20, 1976 Agreement
The District Court found that Mr. Rule had unlim-
ited authority to negotiate a compromise and that set-
tlement discussions commenced on July 15, 1976. [ Ad-
dendum B hereto, pp. 24a-25a]. These discussions con-
tinued for over a month and culminated on August 20,
1976 in an agreement on all substantive matters in
issue. [Addendum B hereto, p. 25a]. The District Court
found that the parties intended to be bound on that
date [Addendum B hereto, p. 25a], and the Court of
Appeals acknowledged that the Navy’s duly authorized
representative, Mr. Rule, and Newport News reached
what they considered to be an agreement. [ Addendum
A hereto, p. 3a]. However, in direct contradiction to its
acknowledgement, the Court of Appeals disagreed with
the trial court and found that the parties did not in-
tend to be bound by their August 20, 1976 agreement.
{Addendum A hereto, p. 6a]. Whatever the reason for
this inconsistency in its opinion, the contradiction dem-
onstrates that the Court of Appeals did not, as indeed
on this record it could not, find that the evidence
clearly compels a contrary finding. The District Court’s
view of the evidence was clearly permissible, and the
Court of Appeals’ rejection of the trial court’s findings
constitutes a substitution of judgment which is pro-
hibited by Rule 52(a) and the decisions of this Court
construing the Rule. See, e.g., United States v. Na-
tional Ass’n. of Real Estate Boards, supra.
Department of Justice Conduct
The District Court held that the Department of Jus-
tice was estopped from disapproving the settlement.
[Addendum B hereto, pp. 15a, 40a]. Its holding was
based on extensive findings of fact that the Depart-
24
ment: (1) made a ‘‘deliberate decision’’ not to go for-
ward with its injunction action, but instead voluntarily
agreed and subjected itself, through the order of the
District Court, to negotiate and to rely upon the Navy
to conduct the negotiations rather than participate it-
self; (2) agreed to and promoted the August 29, 1975
court order and directed Navy officials to conduct nego-
tiations on behalf of the United States and ‘‘to reach an
agreement as rapidly as possible’’; (3) refused to par-
ticipate in negotiations despite its knowledge that the
Navy was not negotiating pursuant to the court order
and was in ‘‘utter default’ prior to Mr. Rule’s ap-
pointment; (4) reaffirmed its agreement when Gordon
Rule was appointed and gave its express approval of
settlement negotiations ; and (5) had exercised its power
to control the litigation by asking the court to enter its
consent order, and having done so, could not repudi-
ate its position. [Addendum B hereto, pp. 39a-41la]. The
August 20, 1976 agreement was negotiated by Gordon
Rule pursuant to a stipulation of the parties which had
been entered as an order of the court at the specific re-
quest of the Department of Justice. [Addendum B
hereto, pp. 21a-25a, 31a]. The opinion below neither dis-
cusses any of these findings, which were fully supported
in the record, nor does it cite any portion of the record
which either is to the contrary or suggests any limita-
tion, exception or reservation in the government’s ac-
tions which would have informed the District Court or
Newport News prior to the August 20 agreement that
the government did not intend to be bound by its ac-
tions. The Court of Appeals’ conclusion that the gov-
ernment was not estopped, without citing either facts in
support of that conclusion or any analysis of applicable
law, is therefore precisely the substitution of judgment
en
25
which the ‘‘clearly erroneous’’ standard was adopted
to prevent.
The Government's Bad Faith
The Court of Appeals also failed to comply with
Rule 52(a) and the decisions of this Court when it held
that summary disposition of the case on the basis of
the government’s bad faith was inappropriate. The Dis-
trict Court held that the government had acted in bad
faith towards the court, as well as towards Newport
News, and dismissed the litigation. The dismissal was
supported by extensive findings of fact concerning the
manner in which the government conducted itself on
and after August 29, 1975, the date on which the gov-
ernment agreed to negotiate in good faith to resolve
the dispute over construction of the DLGN-41 and spe-
cifically requested the District Court to enter an order
requiring it to so negotiate. [Addendum B hereto, pp.
21a-23a, 25a-27a]. The Department of Justice repre-
sented to the District Court that the General Counsel of
the Navy, E. Grey Lewis, would undertake to satisfy
the government’s obligations under the order, and Mr.
Lewis advised the Court that he would do so. [Adden-
dum B hereto, pp. 22a, 39a]. Notwithstanding these as-
surances, the District Court found that on October 29,
1975, Mr. Lewis was ordered by higher Navy officials to
stop all negotiations, and that for the next eleven
months
**. . . the United States totally failed to meet its
obligations to negotiate in good faith, although at
the same time it was receiving the benefits of the
Shipyard’s continued performance under the dis-
puted contract.’’ [Addendum B hereto, p. 23a (em-
phasis in original) ]
26
The District Court further found that during this pe-
riod, the Department of Justice knew that the Navy
was not negotiating and that prior to Mr. Rule’s ap-
pointment ‘‘ Navy officials were in utter default’’ under
this order. [Addendum B hereto, p. 39a]. Both prior
and subsequent to Mr. Rule’s appointment and the
August 20, 1976 agreement, the Navy attempted to un-
dercut his authority and the agreement which resulted
from its exercise. [Addendum B hereto, pp. 25a-27a].
Notwithstanding the foregoing findings of fact,
among others, evidencing the bad faith of the govern-
ment towards the District Court, the Court of Appeals
held that ‘‘summary disposition’’ of the case was ‘‘in-
appropriate’’. [Addendum A hereto, p. 10a]. The Court
of Appeals conceded that ‘‘the underlying facts were
not in dispute,’ but held that the inferences to be
drawn from them were in controversy as to the mean-
ing of the clause ‘‘to take other appropriate action”’
which was contained in the stipulation and court order
of August 29, 1975. [Id.] This Court has held that in-
ferences drawn from undisputed facts can be set aside
only if clearly erroneous. Commissioner v. Duberstein,
supra. However, the Court of Appeals opinion notes
only that a controversy existed as to those inferences,
but nowhere states that the inferences drawn by the
District Court were so clearly in error as to compel a
reversal of the District Court’s conclusion that the case
should be dismissed because of the government’s bad
faith.
A fundamental defect in the Court of Appeals opin-
ion is that the District Court judge was not only the
trier of fact, but also a party to the order and had no
doubt as to its intended scope. The District Court en-
tered the order at the request of both parties ‘‘believ-
— eee ee
Oh es 8 er ie Cr ti ee st ee
dee
27
ing that all good faith attempts to reach a settlement
should be encouraged.’’ [Addendum B hereto, p. 21a}.
The transcript of the hearing at which the order of
August 29 was issued shows that the court was con-
cerned with the total dispute between the parties, in-
cluding the validity of the option and its exercise and
not just the specific items enumerated in Modification
P00018 as to which the government later claimed it was
limited to negotiate. [App. 14, 34-38, 56]. Before the
order was issued, the court inquired of Mr. David
James, one of the government’s counsel, about the
scope of negotiations under the Memorandum of Un-
derstanding which contained the identical ‘‘take other
appropriate action’’ language.
‘*THE Court: ... does this memorandum of un-
derstanding contemplate the responsible people in
a number more than one on each side sitting down
and arbitrating the problems that apparently have
beset you ?
a James: Yes, Your Honor... .’’ [App. 30,
Nowhere in the proceedings was there any suggestion
that negotiations were to be limited to only some of
the issues.® In its opinion dismissing the litigation for
failure to comply with the August 29, 1975 order by
negotiating all matters in dispute, the District Court
stated:
‘“‘Had we been aware that the Government would
later attempt to assert that it was not required to
so negotiate, this Court would rover have entered
* After the order of August 29, 1975 was entered, Assistant
Secretary of Navy Bowers directed ‘‘negotiations with Newport
28
the stipulated agreement of the parties to nego-
tiate as an order. We would have moved the par-
ties along to a swift adjudication of the validity
of the disputed contract.’’ [Addendum B hereto,
p. 14a]
In short, there was no dispute as to either the facts
or the inferences to be drawn from them as to the obli-
gations of the Government to the District Court to ne-
gotiate all items in dispute. To hold otherwise is to con-
clude that neither the District Court nor the parties
knew what was meant by the stipulation and order, and
that is a conclusion supported by neither logic nor the
record in this case. Accordingly, the District Court’s
dismissal, which was within its discretion and sup-
ported by an uncontradicted factual record, should
have been upheld.
The opinion of the Court of Appeals evidences ap-
plication of a far less stringent standard of review
than that required by Rule 52(a), and this Court, in
the exercise of its supervisory responsibilities, should
grant certiorari to rectify this error.
News in good faith on all matters contained in the stipulation set
forth in the court order’’—which stipulation recited Newport
News’ claim of invalidity of the option exercise [App. 75]—and
further specifically directed that settlement be reached in such
negotiations on the ‘‘CGN-41 Option validity.’’ [App. 633 (empha-
sis added) |. It was later that Navy attempted to limit the scope of
the negotiations to the eight items in P00018.
wet Oe eee Bes wt at
Dcpenaetere te Metie te A
NO Oe
29
CONCLUSION
For these reasons the petition for writ of certiorari
should be granted.
Respectfully submitted,
WiiuiaM McL. Freravson
225 - 28th Street
Newport News, Virginia 23607
K. Martin Wortry
JoHN G. DeGooyer
Mark Su.tuivan ITI
JOHN H. SpPeLLMAN
JEFFREY M. PerrasH
Larry H. MircHern
HaMEL, Park, McCazne & SAuNDERS
1776 F Street, N.W.
Washington, D.C. 20006
Counsel for Petitioners
May 1978
ADDENDUM
- a
oa
la
ADDENDUM A
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
No. 77-1748
Unitep States or America, Appellant,
v.
Newport News SuHipsurtpine anp Dry Dock Company,
anp Tenneco, Inc., Appellees.
Appeal from the United States District Court for the
Eastern District of Virginia, at Newport News. John A.
MacKenzie, District Judge.
Argued October 4, 1977 Decided February 27, 1978
Before Haynswortn, Chief Judge, Butzner, Circuit Judge,
and Frevp, Senior Circuit Judge.
Patricia N. Blair, Attorney, Civil Division, Department of
Justice (Barbara Allen Babcock, Assistant Attorney Gen-
eral; William B. Cummings, United States Attorney;
Leonard Schaitman & Stuart E. Schiffer, Attorneys, Civil
Division, Department of Justice on brief) for appellant;
K. Martin Worthy (John G. DeGooyer, Mark Sullivan, ITI,
John H. Spellman, Jeffrey M. Petrash, Larry H. Mitchell,
Hamel, Park, McCabe & Sanders; William McL. Ferguson,
Ferguson & Mason on brief) for appellees.
Butzner, Circuit Judge:
The United States appeals from an order of the district
court enforcing an oral settlement purportedly reached
between the Department of the Navy and the Newport
2a
News Shipbuilding and Drydock Co., and dismissing as
moot the government’s suit for specific performance of a
contract for construction of a vessel. We vacate this order
because we conclude that the parties’ negotiators did not
settle the case orally and because the Attorney General,
whose approval was essential, rejected the terms that were
ultimately reduced to writing.
T
a
This litigation arises from the Navy’s attempt to exercise
an option for construction of the DLGN-41, the fourth ship
in a class of nuclear powered guided missile frigates. As
part of an agreement to negotiate a number of disputed
matters, the final date for exercising this option was ex-
tended to February 1, 1975. In the meantime, the Navy
authorized the shipyard to start preconstruction work. In
August 1974, however, the shipyard notified the Navy that
for a variety of reasons it considered the option invalid.
The Navy disagreed, and on January 31, 1975, it formally
undertook to exercise the option. The parties then signed
a memorandum of understanding obligating the shipyard to
continue its preconstruction work while they negotiated. In
August 1975, the shipyard exercised its right to cancel the
memorandum of understanding because it was dissatisfied
with the progress of the negotiations.
As a result of the cancellation, the Navy filed this suit
seeking specific performance of the contract and a tempo-
rary restraining order directing the shipyard to resume
work on the vessel. At a hearing on August 29, 1975, the
district court adopted as its order a stipulation by the par-
ties providing for continued work on the ship, for contin-
ued payment for work performed, and for negotiations “in
good faith to reach an agreement as rapidly as possible to
modify those contract provisions requiring amendment or
to take other appropriate action.”
3a
The shipyard, again dissatisfied with the Navy’s nego-
tiating tactics, filed a motion on July 13, 1976, for enforce-
ment of the court’s order to negotiate in good faith. It also
sought to have its obligation to continue work suspended
until the Navy complied. The Navy countered by designat-
ing as its negotiator Gordon W. Rule, an experienced ci-
vilian official in the procurement office. In view of this de-
velopment, the shipyard requested the court to reserve rul-
ing on its motion.
Rule began negotiating with the shipyard on July 15,
1976, and subsequently the Navy issued him a contracting
officer’s warrant granting him “unlimited authority with
respect to negotiations.” On August 20, 1976, the parties
reached what Rule and the shipyard’s negotiators consid-
ered to be an oral agreement in principle which the Navy
later estimated would increase the cost of the ship by about
22.7 million dollars.
The shipyard prepared a written first draft of the oral
agreement which Rule received on August 30, 1976. The
negotiators then met on several occasions to discuss revi-
sions. A second draft was circulated on September 27, 1976,
and further discussions concerning revisions were held. On
October 7, 1976, the shipyard executed a third draft of the
agreement and sent it to Rule. Although Rule sigaed the
draft as presented by the shipyard, he conditioned his exe-
cution of the document by the following provisions set forth
in his letter returning it to the shipyard:
(i) That ultimate approval must be received from
Deputy Secretary of Defense Clements, and
(ii) That escalation under this Mod [i.e., modifica-
tion of the contract] will be paid by the Government
on the basis of the contractor’s actual experience or
the BLS Indices times 1.25, whichever is less.
On October 15, 1976, Deputy Secretary Clements for-
warded a copy of the compromise to the Attorney General
4a
with the recommendation that it be approved. The Attor-
ney General, however, disapproved it on November 24,
1976.
During the negotiations dissension had arisen concern-
ing the scope of Rule’s duties. Rule thought he possessed
plenary authority both to negotiate and to bind the govern-
ment to any agreement he reached. Immediately after his
appointment, he told the shipyard that this was the extent
of his power. The Navy agreed that Rule possessed un-
limited authority to negotiate, but it denied granting him
unreviewable authority to bind the government to a settle-
ment. Alerted by a news report that the shipyard consid-
ered the law suit to have been settled on August 20, Rule’s
superiors explicitly cautioned him several times that any
agreement he reached would require approval by higher
authorities. The Navy also informed representatives of
the shipyard about the necessity for review and approval.
Rule himself appears to have recognized that his au-
thority was not as unrestricted as he first supposed. In a
memorandum dated October 5, 1976, he submitted the pro-
posed agreement to the Chief of Naval Material for ap-
proval and referred to obtaining “final review and ap-
proval” from the Oftice of General Counsel of the Navy.
Finally, the letter addressed to the shipyard accompany-
ing Rule’s executed copy of the agreement expressly con-
ditioned his execution of the document on approval by Dep-
uty Secretary Clements.
Shortly after Rule executed the agreement, and even be-
fore the Deputy Secretary transmitted his recommendation
to the Attorney General, the shipyard moved the district
court to enforce the compromise and dismiss the govern-
ment’s action for specific performance. In the alternative,
it moved to dismiss the action on the ground that the Navy
had failed to negotiate in good faith.
The court considered the shipyard’s motion to enforce the
settlement without conducting an evidentiary hearing. Re-
oa re he oe ae
5a
lying on affidavits and discovery depositions, it found that
Rule had authority to bind the government to the settle-
ment he negotiated; that agreement was reached orally on
August 20, 1976, and subsequently memoralized; that Dep-
uty Secretary Clements approved the agreement; and that
the Attorney General “is estopped to deny the settlement.”
II
We find no reversible error in the Navy’s complaint that
the district court should have held an evidentiary hearing
on the motion to enforce the settlement. When there is no
real dispute about the facts, a court has inherent power to
enforce summarily a compromise terminating pending liti-
gation. Meetings & Expositions, Inc. v. Tandy Corp., 490
F.2d 714, 717 (2d Cir. 1974). The only conflict of any sig-
nificance concerned Rule’s duties. We have some doubt that
the law and the evidence support the conclusion that the
Deputy Secretary vested him with authority to commit the
Navy to the expenditure of additional millions of dollars
for the construction of the vessel. This issue, however, is
not material to our decision. The uncontradicted evidence
establishes that by August 25, the Navy had notified the
shipyard of the necessity for review and approval of any
settlement Rule negotiated. The critical question therefore
is whether the August 20 oral agreement was a binding
settlement as the shipyard insists and the district court
found.
III
Parties to contractual negotiations may enter into an
enforceable oral contract that is later to be expressed in
writing if, intending to be bound, they reach agreement on
all major issues. Orient Mid-East Great Lakes Service v.
International Export Lines, Ltd., 315 F.2d 519, 522-23
(4th Cir. 1963); In Re: ABC-Federal Oil & Burner Co.,
290 F.2d 886, 889-90 (3d Cir. 1961); 1 A. Corbin, Contracts
§§ 29, 30 (1963) ; Restatement (Second) of Contracts §§ 26,
6a
32 (Tent. Draft, 1973). Applying this principle to the un-
contradicted facts discloses that the parties did not intend
to commit themselves irrevocably to an oral » itlement of
the case on August 20. First, the draft agreement pre-
pared by the shipyard after the August 20 negotiating ses-
sion contained an escalation clause that computed payments
by using indices prepared by the Bureau of Labor Sta-
tistics from data concerning steel vessel construction
throughout the country. The Navy soon determined, how-
ever, that the shipyard’s actual costs had increased less
than the BLS indices. In subsequent discussions Rule in-
sisted that the escalation clause be changed to award pay-
ments based on the shipyard’s actual experience or 1.25 of
the BLS indices, whichever was less. Estimating that the
difference between the two clauses amounted to about 9.4
million dollars, Rule aptly characterized this issue as sub-
stantive. The final draft submitted to Rule on October 7
retained the shipyard’s version of the escalation clause, and
Rule expressly conditioned his execution of the draft on
acceptance of the government’s position. Although the ship-
yard had represented during the negotiations that it would
relent if this issue “became . . . the hinge point” for the
whole settlement, it did not accede to the condition Rule
imposed. In January 1977, at the hearing on enforcement of
the August 20 oral agreement, it pressed for the clause
awarding the higher escalation payments.
The shipyard’s final draft was essentially an offer of set-
tlement. Rule accepted this offer subject to a condition con-
cerning the escalation clause. Under these circumstances,
the following principle of law applies: ‘‘when an offer or a
counteroffer is accepted subject to a condition or reserva-
tion, neither party is bound to an agreement until the con-
dition or reservation has been withdrawn or satisfied.’’
Orient Mid-East Great Lakes Service v. International Ex-
port Lines, Ltd., 315 F.2d 519, 522 (4th Cir. 1963).
hh ore
We. OR Oe POs ——_ Sar
OSS So a ES
7a
Second, by his letter of October 8 transmitting the exe-
cuted agreement to the shipyard, Rule indicated that he did
not intend the government to be bound either by the results
of the Angust 20 negotiations or by his execution of the
final draft. In this letter he conditioned his execution of the
document by the statement that ‘‘ultimate approval must
be received from Deputy Secretary of Defense Clements.”’
To sustain its thesis that the August 20 agreement bound
the government, the district court construed this condition
to mean that Deputy Secretary Clements must ‘‘approve
the document as memorializing the compromise agreement
between the parties.’’ This restrictive view of the Secre-
tary’s function is not supported either by the plain lan-
guage of the letter or by any action of the Deputy Secre-
tary. He played a far more responsible role than simply
determining whether the executed document prepared by
the shipyard conformed to the terms of the oral negotia-
tions. Moreover, the Deputy Secretary did not undertake to
commit the government to the settlement that Rule had
negotiated. In his letter to the Attorney General of October
15, 1976, which is set forth as an appendix, he recognized
that final approval rested with the Attorney General.
IV
Title 28 U.S.C. §§ 516 and 519 authorize the Attorney
General to supervise all litigation involving an agency of
the government unless the law otherwise directs. As an
incident to this broad grant, he has authority to agree to
dismissal of actions brought by the government. See Con-
fiscation Cases, 74 U.S. (7 Wall) 454, 458 (1868). His au-
thority to compromise and settle any case referred to the
Justice Department was expressly confirmed by §5 of
Executive Order No. 6166, June 10, 1933, 5 U.S.C. § 901.*
* Section 5 of Executive Order No. 6166 provides in part:
As to any case referred to the Department of Justice for
prosecution or defense in the courts, the function of decision
8a
Notwithstanding these well established principles, the
district court held that the Attorney General was estopped
from disapproving the settlement for two reasons. First, it
noted that during oral argument the Department of Justice
stipulated that when Rule was appointed he had authority
to bind the United States. The government, however, pro-
tests that it made no such stipulation or concession. It
points to portions of the transcript where it specifically de-
nied that Rule could bind the government while recogniz-
ing that he had authority to negotiate with the shipyard.
The shipyard in its brief does not claim that the govern-
ment made such a concession, and we have been unable to
find it in the record.
The second reason the district court assigned for its rul-
ing is that the Justice Department took no action to fulfill
its obligation to negotiate in good faith pursuant to the
court’s order ‘‘except through its implicit delegation of
any authority it had to settle this litigation to the Depart-
ment of Defense.’’ We conclude that this reason does not
provide a sufficient basis for invoking estoppel.
The negotiations concerning settlement of the litigation
between the shipyard and the Navy covered many technical
issues about the construction of the vessel, the computation
of its cost, and a feasible date for its delivery. It was there-
fore reasonable for the Justice Department attorneys to
leave discussion of these complex subjects to Navy officials
who had the expertise to deal with them. But another im-
portant question was whether the government should press
its suit for specific performance of the initial contract in-
stead of compromising, in view of the millions of dollars
involved. The answer to this question depended on careful
analysis of the strength of the government’s claim from
whether and in what manner to prosecute, or to defend, or to
compromise, or to appeal, or to abandon prosecution or defense,
now exercised by any agency or officer, is transferred to the
Department of Justice.
> nee ae
9a
both evidentiary and legal standpoints. In turn, the dis-
closures of that survey had to be weighed against the re-
sults of Rule’s negotiations. The final product of this study
was an assessment of the litigative risk.
The Attorney Generai did not, either personally or
through his subordinates, delegate to Rule the authority to
make this critical decision. Moreover, Deputy Secretary
Clements, who was the source of Rule’s authority, under-
stood that the responsibility for evaluating the litigative
risk and consequently for ultimately approving or disap-
proving the settlement remained with the Attorney Gen-
eral. We therefore conclude that the record does not sup-
port the court’s ruling that the Attorney General was
estopped. The law pertaining to the Attorney General’s
control over cases referred to the Department of Justice by
other agencies of the government fully sustains his author-
ity to disapprove the proposed compromise.
V
As an alternative ground for dismissing the govern-
ment’s suit for the specific performance of the construction
contract, the district court held that the government was
barred by the doctrine of unclean hands because it did not
negotiate in good faith. The controversy about the govern-
ment’s negotiating tactics centers on the parties’ August 29,
1975, stipulation which was incorporated in the court’s
order. In view of the dispute about the validity of the
Navy’s option, the parties stipulated that they would ‘‘ne-
gotiate in good faith to reach an agreement as rapidly as
possible to modify those contract provisions requiring
amendment or to take other appropriate action.’’ The nub
of the issue is the clause ‘‘to take other appropriate ac-
tion.’’ The shipyard contends that this language was in-
tended to impose a duty on the parties to renegotiate the
basic contract for the construction of the vessel. Although
there was some difference of opinion in its ranks about the
meaning of the language, the Navy asserted, at least until
the time Rule was appointed its chief negotiator, that it
10a
was required to bargain over the basic contract only if the
shipyard offered some new legal consideration or demon-
strated governmental responsibility justifying more favor-
able terms.
The Navy’s claim of good faith is altogether consistent
with paragraph five of the stipulation, which provided,
‘‘This stipulation and any action taken by either party pur-
suant hereto shall be without prejudice to the rights or
legal positions of either party.’’ The Navy was not obli-
gated to abandon its legal position in order to demonstrate
good faith bargaining if its insistence was sincerely held.
NLRB v. Almeida Bus Lines, Inc., 333 F.2d 729, 731 (1st
Cir. 1964). Although the underlying facts were not in dis-
pute, there was a controversy as to the inferences that
could properly be drawn from them. In the context of this
controversy, the clause ‘‘to take other appropriate action’”’
is ambiguous; there is a genuine dispute about its meaning.
Under these circumstances, summary disposition of the
case on the basis of the defense of unclean hands is inap-
propriate. American Fidelity and Casualty Co. v. London
and Edinburgh Insurance Co., 354 F.2d 214, 216 (4th Cir.
1965),
The judgment of the district court is reversed, and the
case is remanded for further proceedings consistent with
this opinion.
SO a Re OEE ARR A Ee eee
lla
APPENDIX
Tue Deputy Secretary or Derense
WASHINGTON, D.c. 20301
15 October 1976
The Honorable Edward Levi
Attorney General
Department of Justice
Washington, D.C. 20530
Dear Mr. Levi:
This letter forwards a proposed settlement of the CGN-41
litigation negotiated pursuant to Court Order. As you
know, I have been deeply committed to efforts to settle the
Navy’s on-going disputes with the shipbuilding industry
and have undertaken a number of initiatives to this end. In
a meeting on 13 July 1976, Senior Navy Officials, with my
approval, appointed Mr. Gordon W. Rule of the Naval
Material Command as the principal negotiator of this par-
ticular matter. Mr. Rule has negotiated a proposed modi-
fication to the contract with Newport News, attachment (1),
on the CGN-41.
In view of the long-standing, acrimonious, and disruptive
controversy between the Navy and its sole present new con-
struction surface nuclear warship contractor, I consider it
vital to the national defense that this dispute be resolved as
quickly as possible. I consider the proposed modification a
reasonable resolution to this complex matter.
Attachment (2) provides a comparative financial esti-
mate of the proposed settlement. While attachment (2)
indicates a difference of $22.7M I believe it is reasonable
to assume that a Court might grant Newport News, as a
minimum, an extension of the existing escalation coverage
to an achievable contract delivery date (e.g., August 1980) ;
consequently, the difference in the settlement could be re-
12a
duced another $7.5M, to $15.2M. We have not included any
other assessment of litigative risk since this is a matter
under your purview. Quantifying the latter could further
reduce or eliminate the $15.2M differential noted above.
In any event, the District Court instructed the parties as
follows: ‘‘The parties agree to negotiate in good faith to
reach an agreement as rapidly as possible to modify those
contract provisions requiring amendment or to take other
appropriate action.’’ Mr. Rule, in the spirit of this order,
negotiated a contract modification which, if approved,
would undoubtedly facilitate the construction of the badly
needed CGN-41.
Accordingly, I am forwarding the results of these nego-
tiations for your approval and such legal action as may be
necessary to obtain ratification.
/3/ W. P. Clements, Jr.
Attachments
ee eee ee ee ee een ee
ale A i et Na ali a 5 Mate DP ll Men, Ae
13a
ADDENDUM B
IN THE UNITED STATES DISTRICT COURT
FOR THE E\asteRN District or VIRGINIA
Newport News Division
Crviz, Action
No. 75-88-NN
Unitep States or Amenica, Plaintiff
v.
Newport News Surpsurtpine anp Dry Dock Company, and
Tenneco Inc., Defendants
Memorandum Opinion
I
JURISDICTION AND Parties
The plaintiff, the United States of America, has brought
this action seeking specific performance of a shipbuilding
contract it purports to have entered into with the defendant,
Newport News Shipbuilding and Dry Dock Company (the
Shipyard). Defendant, Tenneco Inc. is the parent corpora-
tion of the Shipyard, and its liability is allegedly based on
its guarantee of the Shipyard’s contractual duties.
The Court has jurisdiction pursuant to 28 U.S.C. § 1345.
II
Nature oF THE Motion Berore THE CouRT AND THE
Court’s REeso.uTIon or THE Issues PResENTED
The Shipyard here contends that a valid compromise
agreement has been reached between itself and the United
States which moots and settles all of the issues presented
l4a
in the Government’s action; it moves for an entry of judg-
ment to enforce the settlement and to dismiss this litiga-
tion, and in the alternative, for a dismissal with prejudice
of the Government’s action because of its bad faith toward
this Court and the defendants. The United States main-
tains that it has negotiated towards the settlement in good
faith, but that any agreement reached between the Shipyard
and the Government is invalid for a variety of reasons.
We have no problem with the case and hold that a com-
promise agreement has been reached; that it is binding on
the United States; that the matters before the Court are
moot; and that judgment should be entered enforcing the
settlement and thus dismissing the litigation.
We find that the United States voluntarily bound itself,
contractually and by the consent order of this Court, to
negotiate in good faith to resolve all of the disputes be-
tween itself and the Shipyard with respect to the construc-
tion of the DLGN-41. The United States utterly failed, until
the appointment of Gordon Rule, to so negotiate in good
faith. It insists that it was only required to negotiate cer-
tain items and not all of the matters that are in dispute.
This false insistence evidences the Government’s complete
bad faith toward this Court and the Shipyard. The Govern-
ment, as well as the defendants, had every right to seek a
quick judicial determination of their respective rights un-
der the disputed contract. However, the parties agreed to
an order entered in this Court, on August 29, 1975 and
again a year later, that judicial action should be stayed to
allow the parties to negotiate in good faith to resolve all
their differences. Had we been aware that the Government
would later attempt to assert that it was not required to so
negotiate, this Court would never have entered the stipu-
lated agreement of the parties to negotiate as an order. We
would have moved the parties along to a swift adjudication
of the validity of the disputed contract.
ee
ee ee ee ee eee ees es
*. Sgete we
l5a
We conclude that sovereign immunity does not deprive
this Court of jurisdiction to declare that the compromise
agreement here binds the United States. The Department
of Defense, in this case, delegated its executive authority
to Gordon Rule to bind the United States to an agreement
which compromises and settles the rights of the parties to
this suit. We need not reach the issue whether it would have
been proper for the Department of Defense, once the dis-
puted contract became the subject of litigation, to nego-
tiate a compromise agreement without the consent and ap-
approval of the Department of Justice. That issue is not
before the Court because the Department of Justice repre-
sented to this Court, in August, 1975, that the United States
would be bound to negotiate in good faith, and yet we find
that the Department of Justice has refused to directly par-
ticipate in any of the negotiations over the past seventeen
months. The United States here is estopped to deny the
authority of the Department of Defense to bind the United
States to a compromise agreement.
We find that the United States is fully bound to the com-
promise agreement negotiated on August 20, 1976 between
Gordon Rule, for the Government, and the Shipyard. This
agreement is evidenced by the documents executed by Rule
which memorialize the prior oral agreement. The documents
which speak to the compromise agreement are Contract
Modification P00037 and Rule’s cover letter imposing two
conditions.
These documents satisfy any statute of frauds require-
ment. There was a meeting of the minds of the parties on
August 20, 1976; there is adequate consideration to support
this compromise agreement; and failure to provide cost of
pricing data does not invalidate the agreement. We find
that Deputy Secretary of Defense Clements, who initiated
the negotiation efforts, has approved the compromise agree-
ment.
l6a
III
Tuer Facts
A
The Disputed Contract: June 25, 1970 to August 25, 1975
This acrimonious confrontation between the United
States Navy and the Newport News Shipyard over the con-
struction of the DLGN-4i, a nuclear-powered guided mis-
sile frigate, a high priority national defense item, is consid-
erably affected by the public interest.
On June 25, 1970 the Navy entered into a contract (Con-
tract N00024-70-C-0252) with the Shipyard for the precon-
struction preparation necessary for the construction of a
nuclear guided missile frigate, DLGN-38. This contract also
contained an option exercisable by the Navy for the actual
construction of the DLGN-38.
Subsequently various documents, identified as Contract
Modifications P0001 et seq., have been executed and en-
larged the scope of the original contract, and modified its
terms. The most important of these, for our purposes, are
Contract Modifications P0007, P00018, P00024, and P00037.
They raised issues upon which the parties disagree as to
their legal effects.
P0007 was executed on December 21, 1971. a “
avy purported to exercise its construction options for the
means ant two ships of the same class, the DLGN-39
and 40. In addition, P0007 in Article 28 granted the Navy
two options for the construction of two additional ships of
the same class, the DLGN-41 and DLGN-42, the options to
be exercised by February 1, 1973 and February 1, 1974
respectively. The Shipyard does not admit these legal
effects.
On February 1, 1973 the parties executed P00018. The
United States maintains that this document amended Ar-
ticle 28 to extend the time for the exercise of the construc-
RE:
17a
tion options for DLGN-41 and DLGN-42 by two years. Two
provisions are important for our purposes. One is the op-
tion provision which the Navy purported to exercise which
states:
On or before 1 February 1975, the Government, by
modification to this contract, may require the con-
tractor to construct and deliver DLGN 41, but only if
the Government, by modification to this contract, by
1 December 1973, authorizes the contractor to expend
funds in an amount of $29,062,200 for material pro-
curement, shop fabrication, and other preliminary
work.
The second relevant provision states:
The Parties agree to negotiate in good faith to reach
an agreement as rapidly as possible on the provisions
of this contract which require modification in order to
express the agreement of the parties as to new option
provisions for DLGN 41 and DLGN 42. Therefore, such
contract modification will:
(i) establish a target cost, a target price, a ceiling
price, and a share ratio within the profit-cost
envelope set forth below for each option so ex-
ercised separate from that for the other ships
under this contract, and revise Article 7, entitled
“Limitation or Contractor’s LiaBiuity ror Cor-
RECTION OF Derects” to provide a limitation on
the Contractor’s liability for correction of de-
fects for each vessel to two percent (2%) of the
initial Target Price for that vessel,
(ii) provide for a total final negotiated cost pursuant
to Article 5 hereof entitled “Incentive Price Re-
vision (Firm Tarcet)” separate from that for
DLGN 38, 39 and 40 combined,
(ili)
(iv)
(v)
(vi)
(vii)
(viii)
18a
establish escalation tables separate and different
from those for the DLGN 38, 39 and 40 com-
bined,
modify the payment provision as necessary to
provide payment for DLGN 41 and 42 separate
from DLGN 38, 39, and 40,
revise the project milestones in Articles 17 for
DLGN 41 and 42,
establish a fixed fee, and other terms and condi-
tions on account of the work which may be re-
quired by the Option Conditions described be-
low which will be effective until the correspond-
ing option is exercised, or the work, which may
have been continued pursuant to the direction
of the Contracting Officer, stops,
contain a provision for computing equitable ad-
justment on account of changes in the Longshore-
men and Harbor Workers’ Act, the Federal In-
surance Compensation Act, state workmen’s com-
pensation, unemployment, disability compensa-
tion and public liability acts occurring since
June of 1970, and
revise Schedule “A” to provide for DLGN 41
and DLGN 42 equipment delivery schedules the
same as those listed for DLGN 39.
If, despite the best efforts of both parties, the afore-
said agreement is not executed before the Govern-
ment exercises either or both options, the parties agree
that interim billings will be in accordance with the
terms and conditions of the payment provision for the
DLGN 38, 39 and 40 using the maximum profit-cost
envelope ... until such time as the aforesaid agree-
ment is reached, said interim billings not to exceed total
incurred costs for DLGN 41 and DLGN 42.
19a
On November 29, 1973 the parties executed P00021. The
United States maintains that modification extended the de-
livery dates for the DLGN-41 and DLGN.-42 to October
1978 and June 1979 respectively, in return for an exten-
sion of the date by which the Navy must provide funding
for the preconstruction work on the DLGN-41 and DLGN-
42 in order to exercise the options for actual construction.
On February 27, 1974 the Navy executed P00022 which re-
cites that the Shipyard is authorized to expend 35 million
dollars to accomplish the preconstruction work on the
DLGN-41. The bulk of this authorization was a prerequi-
site under Article 28 to an exercise of the DLGN-41 con-
struction option.
The Shipyard does not agree with the Government as to
the legal effects of these modifications, and maintains, and
we find as a fact, that it notified the Navy during August
1974 that it no longer considered the DLGN-41 option to
be valid.
The Navy was well aware of the Shipyard’s position
when, on January 31, 1975, it executed P00024 which re-
cites that the Navy exercises its construction option for the
DLGN.-41. In fact, the Shipyard and the Navy agreed, prior
to the execution of P00024, that an agreement, which was
contained in a document entitled a Memorandum of Under-
standing, would become effective on February 3, 1975. Un-
der this agreement, which was to remain in effect for at
least thirty days and to continue until one party had given
forty-eight hours’ notice, the Shipyard agreed to continue
the preconstruction work for the DLGN-41, and each party
agreed
... to negotiate in good faith to reach an agreement as
rapidly as possible to modify those contract provisions
requiring amendment or to take other appropriate
action. [Emphasis added.]
Some attempts to negotiate were made by both parties;
however, they failed because of the parties’ disagreement
20a
over the meaning of the phrase, “or take other appropriate
action.” The same language was incorporated into the
Court’s order of August 29, 1975. Certain elements in
the Navy maintain that this phrase did not obligate the
Navy to negotiate outside of the eight specific items which
the Navy was already obligated in February 1975 to nego-
tiate pursuant to P00018. We find this contention to be in-
eredible in light of the drafters’ deliberate rejection of
language which would have specifically limited negotiations
to those eight areas contemplated by P00018, and in light
of the fact that the Shipyard consistently maintained that
the exercise of the DLGN-41 option was invalid.
On May 28, 1975 the Navy sent the Shipyard a letter ad-
vising the Shipyard of the Government’s maximum accept-
able position. This Navy position basically was that the
exercise of the DLGN-41 construction option was valid and
therefore the Navy was not required to negotiate outside of
the eight items in P00018; this meant no change in the
October 1978 delivery date or the production schedule, no
change in target cost, profit, or ceiling price, and no change
in the incentive formula. The Navy would not negotiate
outside of the eight items to accomplish a modification of
the contract unless the Shipyard could prove that it was
entitled to an equitable adjustment due to Government re-
sponsibility, or the Shipyard could furnish new considera-
tion.
The disputed contract for the construction of the DLGN-
41 is a fixed-price, incentive-type contract, with a cost-price
envelope defined in terms of a target cost, target profit,
target price, and ceiling price as follows:
Target cost $ 76,050,000
Target profit + 9,691,000
Target price + 85,741,000
Ceiling price $ 100,951,000
2la
The contract compensation provisions also contain adjust-
ment and escalation clauses for the contingencies that ac-
tual costs may exceed target costs, and that there may be
inflation of labor and material costs.
. On August 25, 1975 the Shipyard notified the Navy that
it was exercising its right to cancel the Memorandum of
Understanding, and that all preconstruction work on the
DLGN-41 would be suspended as of August 27, 1975.
B
The Court’s Order: August 29, 1975 to July 13, 1976
On August 29, 1975 the United States filed in this Court
its complaint and a motion for a preliminary injunction and
a temporary restraining order. On that same day, a hear-
ing was heid before the Court on the motion for a tempo-
rary restraining order. It was at this hearing that the Court
first became aware of the positions of the parties. The
Shipyard maintained that the exercise of the DLGN-41
construction option was invalid because: (1) there were in-
sufficient appropriations, that the exercise was in contra-
vention of 41 U.S.C. §11(a), 31 U.S.C. § 665(a), and the
Armed Services Procurement Regulations (ASPR) : (2) the
Navy had failed to notify the Shipyard of the specifications
for the DLGN-41; and (3) under various legal theories, the
option was unenforceable, e.g. commercial impracticability.
After arguments on the TRO motion and a brief recess,
the parties asked the Court to allow an agreement, which
had been reached between the parties, to be read into the
record and to be entered as an Order of the Court. The
Court, believing that all good faith attempts to reach a
settlement should be encouraged, agreed. This Order, by the
Court, mooted the TRO issue and stayed the judicial pro-
ceedings. It directed, first, that the Shipyard would imme-
diately resume the preconstruction work and proceed to
22a
undertake construction of the DLGN-41. The Navy agreed
to pay for such work. In addition, all changes he. etofore
made in the specifications for the earlier DLGN-38, 39 and
40 were to be considered as incorporated into the specifica-
tions for the DLGN-41, and the parties agreed to negotiate
in good faith the appropriate equitable adjustments for all
specification changes. Second, it stated that:
The parties agree to negotiate in good faith to reach
an agreement as rapidly as possible to modify those
contract provisions requiring amendment or to take
other appropriate action.
Third, the parties agreed to urge the Comptroller General
to expedite his opinion on the issues previously submitted
by the Shipyard concerning whether the exercise of the
DLGN-41 construction option violated 41 U.S.C. §11(a),
31 U.S.C. § 665(a), or the ASPR’s.
Mr. Jeffrey Axelrad, representing the United States and
the Department of Justice, stipulated to the Court that E.
Grey Lewis, the Navy’s General Counsel, would “under-
take to ensure the Navy’s obligation” to negotiate under
the Order.
Unfortunately, the United States’ agreement to negotiate
has been undercut by the existence of diverse points of
view within the Navy, with the result that the record dis-
closes, without possible peradventure, that the United States
has fully and totally ignored not only its own February,
1975 agreement, but also the Order of this Court, that ne-
gotiations in good faith should ensue. Even before the Mem-
orandum of Understanding took effect on February 3, 1975
there was an effort within the Navy to limit negotiations
only to certain items listed in P00018. Although counsel
for the United States, Mr. Axelrad, in open court acknowl-
edged that the Navy’s General Counsel would ensure the
Navy’s compliance, on October 29, 1975, Mr. Lewis, that
- aids Maca
23a
Generai Counsel, was ordered by higher Navy officials to
stop all negotiations.
Despite the Navy’s appointment of two succeeding chief
negotiators, we find that in the eleven months following
our August 29, 1975 Order, the United States totally failed
to meet its obligations to negotiate in good faith, although
at the same time it was receiving the benefits of the Ship-
yard’s continued performance under the disputed contract.
C
Rule’s Appointment and the Compromise
Agreement: July 13, 1976 to date
On July 13, 1976 the Shipyard instituted, by a motion, an
effort to enforce the United States’ agreement to negotiate
in good faith and it asked the Court to suspend the Ship-
yard’s obligation under the Order of August 29, 1975, to
continue work on the DLGN-41 until the United States did
undertake to negotiate in good faith to resolve all disputes
between the parties concerning the DLGN-41.
On that same date, July 13, 1976, Gordon Rule was sum-
monsed, with others, to the office of Deputy Secretary of
Defense Clements to a meeting concerning the DLGN-41 dis-
pute. The United States has claimed executive privilege
concerning certain Government minutes of meetings, docu-
ments, and records of conversations, which frankly the
Court has viewed with an eye to ruling thereon. However,
there is ample evidence in the record, to which no privilege
is asserted, to justify our findings of fact that:
1. Gordon Rule was appointed by the Deputy Secretary
of Defense as chief negotiator for the DLGN-41 dispute
with the authority to bind the United States to a compro-
mise agreement. In fact, the United States admitted this
fact during its argument on January 13, 1977.
24a
2. Deputy Secretary Clements instructed Rule that he
wanted to see four items negotiated in any DLGN-41 com-
promise agreement: (a) a new escalation clause; (b) a new
“changes in the law” clause; (c) a new ceiling price; and
(d) a new delivery schedule.
3. Rule was appointed as chief DLGN-41 negotiator in
direct response to the Shipyard’s filing of its July 13, 1976
motion.
4. Deputy Secretary of Defense Clements specifically
called this meeting of July 13, 1976 for the purpose of prod-
ding the Navy to reach a DLGN-41 compromise agreement
with the Shipyard. In tuis regard Clements instructed the
high Navy officials in attendance that they should there-
after meet with him on a daily basis to keep him informed
of Rule’s progress in negotiating a compromise.
5. The Shipyard interpreted the appointment of Rule as
an indication of the United States’ willingness to negotiate,
for the first time, in good faith. As a result, the Shipyard
asked this Court, on July 19, 1976, to stay action on its
July 13, 1976 motion.
6. On July 16, 1976 Assistant Secretary of the Navy
Bauers issued a memorandum which designated Rule as the
Navy’s chief DLGN-41 negotiator. On August 19, 1976 the
Navy issued Rule a Certificate of Appointment as Contract-
ing Officer which recited that he had ‘‘unlimited authority’”’
to negotiate with the Shipyard concerning the DLGN-41
negotiator. On August 19, 1976 the Navy issued Rule a Cer-
tificate of Appointment as Contracting Officer which recited
that he had ‘‘unlimited authority’’ to negotiate with the
Shipyard concerning the DLGN-41 contract dispute. It is
significant that Bauers’ memorandum recites that Rule was
appointed, after consultation with the Department of Jus-
tice, to deal directly with the Shipyard, without the in-
volvement of the Department of Justice, and that Rule was
to be assisted by the Navy’s General Counsel.
25a
7. Rule is a high ranking civilian Navy employee who is
normally assigned as the Director of the Procurement Con-
trol and Clearance Division in the Office of the Chief of
Naval Material. It is his job function to approve or disap-
prove the business clearance on all Navy procurement con-
tracts. He is referred to as the ‘‘top civilian contracting
officer in the Navy.’’ Rule had previously signed for the
United States an unrelated contract modification involving
over $1,037,000,000.
8. Serious negotiations between Rule and the Shipyard
began on July 15, 1976, continued on an almost daily basis,
and resulted on August 20, 1976 in an oral agreement be-
tween Rule and the Shipyard on all of the outstanding sub-
stantive issues concerning the construction of the DLGN-41,
including those specifically charged to him by Secretary
Clements. The negotiators agreed that a written document,
to be labelled Contract Modification P00037, would confirm
and memorialize the terms of the August 20, 1976 agree-
ment.
9. On August 20, 1976 the parties orally agreed to a
change in the delivery date from October 1978 to August
1980, to a new escalation clause appropriate to the new
delivery date, to new and separate fringe benefits and en-
ergy cost provisions, and to agree later on a new ‘‘changes
in the law’’ provision as they were already obligated to do
under the earlier P00018.
10. At the completion of the August 20, 1976 meeting the
parties intended themselves to be bound by the agreement
reached and only contemplated a memorialization of this
agreement in a written document.
Despite the United States’ admission that Rule was ini-
tially appointed with full authority to bind the United
States, an effort was mounted within the Navy before
August 20, 1976 to undercut Rule’s specific authority, and
to bring it under further Navy scrutiny. Even in the face of
that internal Navy effort, such action would not have re-
26a
voked Rule’s authority as granted by the Deputy Secretary .
of Defense on July 13, 1976, and by Assistant Secretary of .
the Navy Bauers, on July 16, 1976, and as expressed as
‘‘ynlimited”’ in the Contracting Officer’s warrant issued.
Further Navy efforts to undermine Rule’s authority oc-
curred after the agreement was reached on August 20, 1976.
On August 30, 1976 an Admiral Michaelis sought to appoint
a review panel of three Navy persons, and purported to
grant them the sole final authority to bind the Navy to a
compromise agreement.
On August 23, 1976 Rule met with Deputy Secretary
Clements and reported to him that an agreement had been
reached with the Shipyard on August 20, 1976. On August
25, 1976 Admiral Reich, a top consultant to Clements, ap-
proved a press release announcing that a settlement agree-
ment had been reached.
A final draft, setting forth the agreement as reached on
August 20, 1976, was prepared by the Shipyard, and signed
by Rule, subject to two conditions, on October 7, 1976, at
6:00 P.M. On the morning of October 8, 1976, Rule was
called to his immediate superior’s office where he was
handed a document which stated:
... you do not have the authority to bind the Govern-
ment contractually on the proposed modification to
CGN-41 contract until the legal and business reviews
have been completed ....
This document, although dated October 7, 1976, was re-
ceived by Rule on the morning of October 8th.
Rule delivered Contract Modification P00037 to the Ship-
yard but expressly conditioned his execution and delivery
of the document on the conditions that:
(1) Clements approve the document as memorializing
the compromise agreement between the parties; and
(2) the labor escalation clause contained in P00037 be
modified to provide that the Shipyard would receive the
27a
lesser of its actual experience in escalated labor costs, or
125% of the Bureau of Labor Statistics indices. These con-
ditions were dictated to a secretary, in the presence of the
Shipyard’s agent, and later incorporated in the cover letter
for the executed P00037.
Later, on October 8, a memorandum from a Navy Cap-
tain Thompson was sent to Rule’s office, reciting that Rule’s
warrant as a Contracting Officer was revoked.
On October 15, 1976 Deputy Secretary of Defense Clem-
ents forwarded a copy of the writings executed by Rule to
Attorney General Levi. In his cover letter Clements states
that the writings present ‘‘a reasonable resolution of this
complex matter.’’ He further states:
In any event, the District Court instructed the parties
as follows: ‘‘The parties agree to negotiate in good
faith to reach an agreement as rapidly as possible to
modify those contract provisions requiring amendment
or to take other appropriate action.’’ Mr. Rule, in the
spirit of this order, negotiated a contract modification
which, if approved, would undoubtedly facilitate the
construction of the badly needed CGN-41.
The Department of Justice has since informed the Court
that the Attorney General would disapprove the Rule
compromise agreement and contends that therefore there
is no compromise agreement binding on the United States.
IV
Conciusions or Law
A
The United States’ Failure to Act in Geod Faith
toward this Court and the Shipyard
Even if there is a valid contract the breach of which
would entitle the aggrieved party to a damage remedy at
law, the specific performance of that contract is not a mat-
ter of right under either federal or state law. The granting
28a
of the remedy of specific performance rests in the sound
discretion of the trial court, which is to exercise its discre-
tion according to the established principles of equity and
the facts of the case, Williston on Contracts § 1418 (3rd
Ed., 1976 Supplement) citing among other cases, Manufac-
turers’ Finance Co. v. McKay, 294 U.S. 442, 55 S.Ct. 444
(1934); Barnes v. Sind, 341 F.2d 676 (4th Cir. 1965);
Raney v. Barnes Lumber Corp., 195 Va. 956, 970, 81 S.E.2d
578, 586 (1954).
A fundamental equity principle is that one who asks for
specific performance of a contract must have ‘‘clean
hands’’; he must have acted in a fair and equitable fashion
with respect to the party against whom he seeks to have the
contract enforced.
Long before the Navy purported to exercise its option
rights on January 31, 1975, the Shipyard informed the
Navy that it considered the DGLN-41 construction option to
be void. If this litigation had proceeded to trial, this Court
would have been required to pass on the validity of the
original DLGN-41 option provision. However, the Court’s
decision today that the subsequent compromise agreement
is binding on the United States moots this issue and settles
this litigation.
Certain personalities within the Department of the Navy
have taken the position that the Navy should not negotiate
with the Shipyard on the matters required to be negotiated
pursuant to the January 31, 1975 Memorandum of Under-
standing and, of more importance to us, this Court’s Order
of August 29, 1975. The Navy was not coerced by anyone,
including this Court, to agree to negotiate in good faith to
resolve the DLGN-41 dispute. The Government, if it were
80 positive of the validity of the original option provision,
_ could have had this Court’s final adjudication of the valid-
ity of that provision within%six or seven months after the
filing of its complaint. However, the United States, through
its Department of Justice, represented to this Court that
no immediate adjudication of the validity of the disputed
29a
option provision was desired, but rather that good faith
efforts would be undertaken by the Navy to resolve this dis-
pute through an out-of-court compromise agreement, and
that while the Court’s Order remained in effect the Ship-
yard would be obligated to continue its construction of the
DLGN-41, despite its contention that the exercise of the
option contract was invalid.
If that group within the Navy which disapproved of any
negotiations or settlement of the DLGN-41 dispute had at-
tained ascendancy in the Navy’s decision-making hierarchy,
they could have asked this Court to revoke its Order of
August 29, 1975, and to proceed to adjudicate the validity
of the exercise of the option. This did not occur. Instead the
official position of the Government was that good faith ne-
gotiations to resolve all of the DLGN-41 dispute were de-
sired, while certain Navy elements were even then under-
cutting the progress of any efforts toward good faith nego-
tiation. We do not decide whether it was in the best inter-
ests of the United States to negotiate or to litigate the
DLGN-41 dispute; we only conclude that the Navy, and the
United States, has not acted in good faith. For this reason,
the United States does not have clean hands to ask this
Court to specifically enforce the original DLGN-41 con-
struction option.
B
A Declaratory Judgment that the United States is
Bound by the Compromise Agreement is Justified
The United States has raised numerous legal objections
to the validity and enforceability of the August 20, 1976
compromise agreement. These cbjections include: (1) that
sovereign immunity deprives the Court of jurisdiction to
declare that the United States is bound by a compromise
agreement which settles and moots this action; (2) that
Rule lacked authority to bind the United States; (3) that
the August 20, 1976 agreement is unenforceable because it
30a
was oral; (4) that there has been no meeting of the minds;
(5) that the compromise agreement is void because of the
Shipyard’s failure to provide the Government with cost
and pricing data; (6) that Rule could not bind the United
States without the approval of the Attorney General; and
(7) that the compromise agreement is not supported by
adequate consideration. While we consider some of these
charges to be of no moment, nevertheless, we separately ad-
dress each of these legal objections and conclude that none
of them prevent the compromise agreement from binding
the United States.
1
Sovereign Immunity
We need not dwell long on the two sovereign immunity
arguments raised by the United States. By granting judg-
ment for the Shipyard neither do we grant a damages judg-
ment against the United States, nor do we order the equi-
table reformation of a contract to which the United States
is a party. We merely declare that the parties are legally
bound by a compromise agreement. This compromise agree-
ment moots the issue as to whether that prior contract
was enforceable.
Certainly if the facts show that the issues are moot in a
suit brought by the United States for specific performance
of a contract, the Court has jurisdiction, under 28 U.S.C.
§ 1345, to so find, and to dismiss with prejudice the Govern-
ment’s case. It make no practical difference whether the
Court’s judgment is styled a dismissal with prejudice be-
cause of mootness, or a declaratory judgment for the de-
fendant that the settlement agreement is binding. The res
judicata and collaterai estoppel effects are the same.’
1 We find it a little tenuous for the Government, after instituting
this suit in this Court, to now question the jurisdiction of the
Court to hear and determine the whole matter, including a bona
fide settlement of the dispute.
3la
We need not decide whether the enactment on October 21,
1976 of Public Law 94-574, 90 Stat. 2721, which amends 5
U.S.C. § 702, grants this Court any additional jurisdiction
with respect to this litigation.
2
Rule’s Authority
The United States admits that Gordon Rule had complete
and final authority to bind the United States when he was
appointed on July 13, 1976, as chief Navy negotiator in the
DLGN-41 dispute. However, the United States contends
that, subsequent to his appointment and prior to any agree-
ment reached between himself and the Shipyard, his author-
ity was limited to the negotiation of a proposed settlement,
which required the further approval of a higher authority
in the Departments of Defense or Navy, and the approval
of the Attorney General. We disagree.
Gordon Rule was appointed as the Navy’s chief negoti-
ator for the DLGN-41 dispute by Deputy Secretary William
P. Clements during a meeting held in Clements’ office at-
tended by the high-level Department of Defense and Navy
personnei concerned with this dispute with the Shipyard.
Rule’s appointment was in direct response to the Ship-
yard’s having filed a motion to compel the United States to
comply with this Court’s Order of August 29, 1975. It was
Mr. Clements’ stated and recorded belief that the Navy had
failed so far to negotiate with the Shipyard in good faith.
The Department of Justice admits that the Attorney Gen-
eral was aware of this grant of authority to Rule.
The Justice Department attempts now to discredit the
settlement worked ont by Rule. It suggests that Rule did
not act with the best interests of the United States in mind.
We find nothing in the record to svpport this view. In fact,
Rule was apyointed by Clements because of his reputation
in negotiating settlements with contractors. That segment
32a
of the Navy command which was upset at Rule’s appoint-
ment, but was then unable to prevent it, now attempts to
discredit his completed settlement.
On August 19, 1976 Rule was issued a contracting offi-
cer’s warrant signed by Captain Gerald J. Thompson, Dep-
uty Chief of Naval Material. That document stated that
Rule had ‘‘unlimited authority to negotiate with the Ship-
yard concerning the DLGN-41 dispute.’’ This warrant was
not revoked until October 8, 1976. It is incredible to the
Court that the United States now maintains that ‘‘unlim-
ited authority to negotiate for the United States’’ does not
include the authority to bind the United States. This argu-
ment is contrary to the dictates of common sense and the
English language. If the warrant authority did not include
the power to bind the United States, why did certain Navy
officials feel the need to revoke the warrant on October 8,
1976? Rule had signed and delivered the draft setting out
the Contract Modification P00037 prior to this revocation.
3
Statute of Frauds
The United States claims that even if Rule had the au-
thority on August 20, 1976 to bind the United States, any
agreement reached on that date would not be enforceable
because it was oral.
The United States contends that 31 U.S.C. § 200(a) es-
tablishes that an agreement must be evidenced by docu-
ments before it can be binding on the United States. This
provision states in pertinent part:
After August 26, 1954 no amount shall be recorded as
an obligation of the Government of the United States
unless it is supported by documentary evidence of—
(1) a binding agreement in writing between the par-
ties thereto, including Government agencies, in a man-
ner and form and for a purpose authorized by law,
33a
executed before the expiration of the period of availa-
bility for obligation of the appropriation concerned for
specific goods to be delivered, real property to be pur-
chased or leased, or work or services to be peformed ;
or
@ e @
(6) a liability which may result from pending litiga-
tion brought under authority of law; or
(8) any other legal liability of the United States
against an appropriation or fund legally available
thereto.
The Government cites United States v. American Ren-
assance Lines, Inc., 494 F.2d 1059 (1974) where the Court
of Appeals for the District of Columbia Circuit held that
an oral charter agreement was unenforceable against the
United States because of § 200(a). That Court rejected the
argument that § 200(a) was merely ‘‘a recordation statute
to facilitate auditing’’ by Congress of the Executive’s
spending in order to determine future appropriation re-
quirements; rather it held that the statute makes oral con-
tracts with the Government unenforceable. It is unneces-
sary for us to reach the issue whether 4 200(a) is applicable
to the August 20, 1976 compromise agreement for we find
that the requirements of § 200(a) have been met under both
subsections (1) and (6).
Under subsection (1) the oral compromise agreement on
August 20, 1976 is evidenced by the document (Contract
Modification P00037) which Rule signed on October 7, 1976,
and the cover letter of October 8, 1976.
Secondly, the requirements of subsection (6) have been
met. The oral agreement which was reached on August 20,
1976 was negotiated pursuant to this Court’s Order of Au-
gust 29, 1975. This oral agreement entered into by the duly
authorized agents of the parties to this pending litigation
34a
certainly establishes the liability of the parties after this
Court accepts that agreement as the settlement of this
action.
4
Meeting of the Minds
The United States maintains that there was no meeting
of the minds on August 20, 1976 and therefore no binding
agreement. As evidence of this contention they cite the
parties’ agreement that a draft of the agreement be for-
malized. It is well settled that the mere fact that the
parties contemplated a reduction of an oral agreement to
writing does not prevent the agreement from becoming
binding as of the date of the oral agreement. Here, a draft
was agreed to in order to correctly reflect the August
20th oral agreement.
The precise language and operation of the labor costs
escalation clause had been a major item of disagreement
between the parties in the negotiations. The parties agreed
on August 20th to grant the Government the most favor-
able escalation provision as disclosed by the Shipyard’s
actual experience. In the original DLGN-41 construction
option contained in Article 28 of P0007, the Shipyard was
to receive the lesser of its actual experience or 125% of
the Bureau of Labor Statistics’ index for wage costs. The
basic writing signed by Rule on October 7, «.e., Contract
Modification P00037, recited only that the Shipyard would
receive 125% of the BLS index irrespective of its actual
experience; however, Rule conditions his signing and de-
livery of the document on the modification of the writing
to go back and incorporate the same type provision as was
in force in P0007. The Shipyard has agreed. We find that
this modification by Rule of P00037 reflects the substance
of the oral agreement reached by the parties on August
20, 1976. 17 C.J.S., Contracts, § 31.
35a
At the August 20th meeting the parties did not work
out the specific language for a labor cost escalation clause.
At subsequent sessions it was found that all parties were
operating under the mistaken impression that the Ship-
yard was experiencing a rate of increase in labor costs
greater than the BLS index. To give the Government the
best position, the 125% of the BLS index provision was
chosen to reflect the August 20, 1976 agreement. When,
however, by October 7, it became known that the Shipyard
had sometimes been experiencing a rate of increase in
labor costs less than the BLS index, the change in lan-
guage imposed by Rule was appropriate to reflect the
actual August 20, 1976 agreement.
We need not worry whether the parties contemplated
on August 20, 1976 that approval by Deputy Secretary
Clements was necessary to bind the Government, for we
find that Clements, in any case, has granted such approval.
In his letter of October 15, 1976 to Attorney General Levi,
Clements granted his approval to the Rule compromise
agreement. We do not agree with the Government that
Clements must use the magic words ‘‘I approve’’ before
this Court can conclude that Clements in fact has approved
the compromise agreement. Clements stated:
In view of the long-standing, acrimonious, and disrup-
tive controversy between the Navy and its sole present
new construction surface nuclear warship contractor,
T consider it vital to the national defense that this
dispute be resolved as quickly as possible. I consider
the proposed modification a reasonable resolution to
this complex matter.
5
Failure to Provide Cost or Pricing Data
The United States argues that the compromise agree-
ment negotiated between Rule and the Shipyard is not
36a
binding on the Government because the Shipyard failed to
submit cost or pricing data to the Government. This argu-
ment rests on the proposition that such data is required
by Armed Services Procurement Regulations (ASPR)
§ 3-807.3 and by statute, 10 U.S.C. § 2306(f), that the
absence of such data invalidates the agreement, and that
the requirements cannot be waived. 10 U.S.C. § 2306(f)
states in pertinent part:
A prime contractor or any subcontractor shall be re-
quired to submit cost or pricing data under the cir-
cumstances listed below, and shall be required to cer-
tify that, to the best of his knowledge and belief, the
cost or pricing data he submitted was accurate, com-
plete and current—
(2) Prior to the pricing of any contract change or
modification for which the price adjustment is expected
to exceed $100,000, or such lesser amount as may be
prescribed by the head of the agency....
Section 3-807.3 of ASPR [32 C.F.R. § 3.807] implements
this statute and provides:
(a) The contracting officer shall require the contractor
to submit, either actually or by specific identification
in writing, cost or pricing data in accordance with
16-206 of this chapter and to certify by the use of
the certificate set forth in 3-807.4, that, to the best of
his knowledge and belief, the cost or pricing data he
submitted was accurate, complete and current prior to:
(2) the pricing of any modification to any formally
advertised or negotiated contract, whether or not cost
or pricing data was required in connection with the
initial pricing of the contract, when the modification
involves aggregate increases and/or decreases in cost
plus applicable profits expected to exceed $100,000.
37a
The Shipyard has not furnished the Navy the certificate
of cost data as specified by ASPR 3-807.3.
The original cortract (N00024-70-C-0252) contained a
now standard ‘‘Price Reduction for Defective Cost of
Pricing Data’’ clause which reads:
(a) If the Contracting Officer determines that any
price, including profit or fee negotiated in connection
with this contract was increased by any significant
sums because the Contractor . . . furnished incomplete
or inaccurate cost or pricing data not current as cer-
tified in the Contractor’s Certificate of Current Cost
or Pricing Data, then such price shall be reduced
accordingly and the contract shall be modified in writ-
ing to reflect such adjustment.
This provision was included in the contract, as required
by 10 U.S.C. § 2306(f), which states: m
Any prime contract or change or modification thereto
under which such certificate [Certificate of Current
Cost or Pricing Data] is required shall contain a pro-
vision that the price to the Government, including
profit or fee, shall be adjusted to exclude any signifi-
cant sums by which it may be determined by the head
of the agency that such price was increased because
the contractor required to furnish such a certificate,
furnished cost or pricing data which, as of date agreed
upon between the parties . . . was inaccurate, incom-
plete, or non-current. .. .
It appears obvious from these quotations that the submis-
sion of price and cost data is not a preccndition to a find-
ing that the Government is bound by the contract or any
subsequent modification thereof. The failure on the part
of the Shipyard to ultimately furnish complete and accu-
rate price and cost data does not relieve the Government
of its duty to perform under the contract, but rather only
38a
gives it the right to seek a reduction in the price of the
contract to the Government.
Nor need we decide whether the United States has
waived the statutory and contractual requirements that
the Shipyard furnish cost and pricing data. The Govern-
ment cites M-R-S Manufacturing Company v. United
States, 495 F.2d 835, 841 (Ct. Claims 1974) for the pro-
position that a Government agent cannot waive this ‘Te-
quirement. However, this decision supports our conclusion,
for the only relief granted the Government in that case
was a reduction in price.
We note that 10 U.S.C. § 2306(f) provides that no cost
and pricing data is required where
. in exceptional cases . . . the head of the agency
determines that the requirements of this section may
be waived and states in writing his reasons for such
determination.
It might be concluded that Deputy Secretary of Defense
Clements has taken such action as evidenced by his letter
forwarding the compromise agreement to the Department
of Justice.
6
Department of Justice Approval
The United States maintains that this is an instance
where a private contractor asserts that an agreement has
been reached between itself and a federal contracting
agency, here the Department of Defense, which settles civil
litigation involving a government contract, ‘‘notwithstand-
ing the lack of involvement or approval by the Attorney
General,’’ and therefore ‘‘the purported ‘settlement’ must
fail.’’ Plaintiff’s Brief, 37. [Emphasis added.] Such a fact
situation is not before this Court.
39a
Cn August 29, 1975 the Department of Justice stated in
open Court to this Court that the Navy’s General Counsel
would “undertake to ensure the Navy’s obligations” to ne-
gotiate in good faith a settlement of the dispute over the
Shipyard’s construction of the DLGN-41. The United
States, through its Department of Justice, voluntarily
agreed and subjected itself, through the Order of this
Court, to negotiate in good faith, thus making a deliberate
decision not to seek an immediate judicial determination of
its rights under the disputed option contract. At the request
of the Department of Justice this Court incorporated into
its Order of August 29, 1975 the agreement of the United
States to negotiate in good faith.
The Department of Justice decided as evidenced by the
testimony of its counsel, Jeffrey Axelrad, to rely upon the
Navy and not to send any of its officers to di _ ctly partici-
pate in the DLGN-41 negotiations. This remained the posi-
tion of the Justice Department despite the Department of
Justice’s knowledge that the Navy was not in fact nego-
tiating and that Nevy officials were in utter default before
the appointment of Gordon Rule. On July 13, 1976 the Ship-
yard filed in this Court a motion to enforce the Court’s
Order of August 29, 1975. In direct response to the filing
of that motion, the Department of Defense appointed Rule
as its chief negotiator for the DLGN-41 dispute. The De-
partment of Jusitce was aware of Rule’s appointment and
the authority conferred on him,’ and in light of this ap-
pointment requested counsel for the Shipyard not to press
its July 13th motion. This request was granted.
* During oral argument the Department of Justice stipulated
that at the time of Rule’s appointment he had the authority to bind
the United States; however, the Department of Justice maintains
that, subsequent to his appointment, any settlement that he negoti-
ated with the Shipyard became subject to further review and final
approval by the Department of Justice.
40a
The Department of Justice agreed to and promoted the
Court Order of August 29, 1975 that negotiations “to reach
an agreement as rapidly as possible’ on behalf of the
United States should be conducted by the Navy officials, it
reaffirmed this agreement at the time of the appointment of
Rule, and it neglected to fulfill its obligations to this Court
and the Shipyard to ensure good faith negotiations by the
United States, except through its implicit delegation of any
authority it had to settle this litigation to the Department
of Defense. It therefore is estopped to deny the authority
of the Department of Defense officials to approve an agree-
ment which in effects moots or settles this litigation. 15A
Am. Jur. 2d, Compromise and Settlement, § 12.
While we hold the Department of Justice, under its ac-
tion in this case, is estopped to deny the settlement, never-
theless, for appellate purposes we note that in United States
v. Sandstrom, 22 F.Supp. 190 (N.D. Okla. 1938), where the
Attorney General successfully resisted a settlement, that
action was based upon the lack of original authority in the
Secretary of the Interior to act in the first place. That is
not the case here.
We do not decide whether the Department of Justice can
block an agreement reached by another executive agency
which in effect settles litigation, when the Department has
neither participated in nor approved the settlement. Here,
we hold, the Department has participated. However, we
note withovt comment that the Court of Appeals for the
Fourth Circuit has held in Leonard v. United States Postal
Service, 489 F.2d 814 (1974) that the Department of Jus-
tice could not block a compromise agreement reached by
the Postal Service which mooted a claim against it for
employment discrimination, while the case was pending in
the District Court.
We repeat that this is not a case where a federal execu-
tive agency has attempted to usurp the authority of the
Department of Justice to initiate or control litigation in-
4la
volving the United States. Rather all of the negotiations
involving the DLGN-41 between the Shipyard and the Navy
were carried out pursuant to an agreement to which the
Department of Justice officials gave their express approval,
and which, at the express request of the Department of
Justice, was incorporated as an order of this Court.
The purpose of the agreement to negotiate in good faith
to resolve the differences between the parties with respect
to the DLGN-41 was to avoid “vexatious and expensive and,
to the contractor oftentimes, ruinous litigation.” Kihlberg
v. United States, 97 U.S. 398, 401 (1878), as quoted in S é E
Contractors, Inc. v. United States, 406 U.S. 1, 8, 92 S.Ct.
1411, 1416 (1972). Both parties to the agreement ceded their
rights “to seek immediate judicial redress for [their] grie-
vances,” and have bound themselves to proceed with the
construction of the DLGN-41 during the negotiation proc-
ess. Ss ¢ E Contractors, Inc., supra at 1416. “A citizen has
the right to expect fair dealing from his government” with
respect to such an agreement. Jd. at 1417.
There is no contention here that this compromise agree-
ment was arrived at as a result of any fraud or bad faith
on the part of the Shipyard. Jd. at 1419-1420, The Depart-
ment of Justice has exercised its power to control the
United States’ position in this litigation—it did so in ask-
ing this Court to enter a consent order, as a result of which
the United States became bound to negotiate in good faith
to resolve the disputes between the parties concerning the
DLGN -41. Having exercised this power, it cannot now re-
pudiate its decision. It cannot now maintain that another
executive agency has attempted to usurp its control over
litigatioa with the United States.
42a
7
Consideration
United States contends now that the Rule compro-
ont “almost totally one-sided in favor of Newport
News.” It argues that the compromise will cost the Govern-
ment 22 million dollars. In addition it cites the 22-month
deferred delivery date, and the fringe benefits and energy
provisions. [It should be noted that under our construction
of the compromise agreement the labor escalation clause
is the same type as that in the antecedent option contract. ]
The United States concludes that “the only new considera-
tion coming to the Government under the proposed modifi-
cation is that it no longer must assume the litigative risk
inherent in pursuing its present action for specific perform-
ance.” (Plaintiff’s January 7, 1977 Brief, 4.) This argu-
ment must fail for there is ample and sufficient considera-
tion to support a compromise agreeiment if it is based upon
a claim, unliquidated or disputed in good faith, and if the
parties make or promise mutual concessions.
A good statement of the legal requirements in the way
of consideration for establishing a binding compromise
agreement is found in 15A Am. Jur.2d, Compromise and
Settlement, § 13, p. 785:
A compromise, like any other contractual agreement,
must be supported by consideration. If there is @ liqui-
dated and undisputed claim, and if an effort is made
to accomplish an accord and satisfaction through the
payment of an amouut different from what is undis-
putably due, there must generally be some new or ad-
ditional consideration for the accord and satisfaction
to be effective. If, however, there is a disputed or un-
liquidated claim, based upon the parties’ doubts and
uncertainties, and if the parties, for the purpose of
avoiding or putting an end to litigation, agree to re-
43a
solve their differences amicably and by means of mu-
tual concessions, the promise or execution of such con-
cessions by one party constitutes good consideration
for the promise or execution of such concessions by the
other party. Thus, a compromise, as distinguished from
other types of accord and satisfaction, is supported by
good consideration if it is based upon a disputed or
unliquidated claim and if the parties make or promise
mutual concessions as a means of terminating their dis-
pute; no additional consideration is required.
All of the requisites for consideration to support a bind-
ing compromise agreement are found here. The parties dis-
pute in good faith the validity of the antecedent option
agreement and the United States’ purported exercise on
January 31, 1975 for the construction of the DLGN -41; the
parties’ obligations under this antecedent option agreement
were unliquidated. The basic price for the construction of
the DLGN-41 contained in the compromise agreement is
the same as that contained in the antecedent option agree-
ment. And even the antecedent option agreement (Modifi-
cation P00018) required the parties to negotiate in good
faith concerning the inclusion of the DLGN construction
contract of a provision for “computing equitable adjust-
ments on account of changes in various laws,” e.g. Long-
shoremen and Harbor Workers’ Act. The compromise
agreement specifies that it constitutes a full and final settle-
ment of all issues which are the subject of dispute in this
case, t.e. the validity of the Shipyard’s obligation to build
the DLGN-41.
In addition there is a consideration furnished by the Ship-
yard’s release of “[a]ll claims for delay and dela y costs in
the delivery schedule of DLGN-41, resulting from, caused
by or incident to any and all events, including Government
actions or inactions ....’’ We find that the Shipyard has
asserted these “delay” claims in good faith, and that the re-
lease of these claims is not illusory consideration. There is
d4a
some evidence that the Government delayed for more than
a year, from mid-1974 until the August 29, 1975 hearing in
this Court to inform the Shipyard whether it would incor-
porate into the specifications for the DLGN-41 all of the
changes already made in the DLGN-38, 39 and 40. The
Shipyard has alleged that this delay made it impossible to
establish an appropriate schedule for the construction of
the DLGN-41.
The United States argues that compromise agreements to
which the Government is a party require adequate consid-
eration. (Plaintiff’s January 7, 1977 Brief, 4 n.2.) The
United States would have this Court apply a special rule
to Government contracts and ignore the hornbook contracts
law rule that a Court will not review the adequacy of con-
sideration as long as some valid consideration supports the
contract. In the absence of any allegation of fraud or bad
faith on the part of the private contractor, we reject that
role.
None of the cases cited by the United States support its
view that tle Court is to review the adequacy of considera-
tion supporting Government contracts. The cases cited by
the Government did not address the consideration issue,
but rather the issue whether the Government agent had the
actual authority to modify a Government contract.
The law favors the resolution of controversies and un-
certainties through compromise and settlement rather
than through litigation, and it is the policy of the law
to uphold and enforce such contracts if they are fairly
made and are not in contravention of some law or pub-
lic policy.
15A. Am. Jur.2d, Compromise and Settlement, § 5, p. 777,
citing Williams v. First National Bank, 216 U.S. 582, 30
S.Ct. 441 (1909).
45a
An appropriate Order, in accord with this Memorandum
Opinion, will be separately entered this date.
/s/ Joun A. MacKenzie
United States District Judge
Norfolk, Virginia
March 8, 1977
46a
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF VIRGINIA
Newport News Division
(Caption Omitted in Printing)
Order
In accord with a Memorandum Opinion dated and filed
March 8, 1977, and to which reference is made,
It is ORDERED:
(1) That the motion of the defendants to enforce the
compromise and settlement agreement between the parties
is GRANTED.
(2) This action of the plaintiff being therefore moot, the
same is DISMISSED.
/s/ Jouwx A. MacKenzie
United States District Judge
Norfolk, Virginia
March 8, 1977
47a
ADDENDUM C
United States Constitution:
Article I, Section 8, Clause 13:
The Congress shall have Power . .. To provide and main-
tain a Navy;
10 U.S.C. § 131:
The Department of Defense is an executive department
of the United States.
10 U.S.C. §133(a),(b),(d):
(a) There is a Secretary of Defense, who is the head
of the Department of Defense, appointed from civilian
life by the President, by and with the advice and con-
sent of the Senate. A person may not be appointed as
Secretary of Defense within 10 years after relief from
active duty as a commissioned officer of a regular com-
ponent of an armed force.
(b) The Secretary is the principal assistant to the
President in all matters relating to the Department of
Defense. Subject to the direction of the President and
to this title and section 401 of title 50, he has authority,
direction, and control over the Department of Defense.
(d) Unless specifically prohibited by law, the Secre-
tary may, without being relieved of his responsibility,
perform any of his functions or duties, or exercise any
of his powers through, or with the aid of, such persons
in, or organizations of, the Department of Defense as
he may designate.
10 U.S.C. $134:
(a) There are two Deputy Secretaries of Defense,
appointed from civilian life by the President, by and
48a
with the advice and consent of the Senate. A person
may not be appointed as a Deputy Secretary of De-
fense within ten years after relief from active duty as
a commissioned officer of a regular component of an
armed force.
(b) The Deputy Secretaries shall perform such du-
ties and exercise such powers as the Secretary of De-
fense may prescribe. The Deputy Secretaries, in the
order of precedence, designated by the President shall
act for, and exercise the powers of, the Secretary when
the Secretary is disabled or there is no Secretary of
Defens |
(c) The Deputy Secretaries take precedence in the
Department of Defense immediately after the Secre-
tary.
10 U.S.C. § 2303(a) (2),(b) (4):
(a) This chapter applies to the purchase, and con-
tract to purchase, by any of the following agencies, for
its use or otherwise, of all property named in subsec-
tion (b), and all services, for which payment is to be
made from appropriated funds:
. * .
(2) The Department of the Navy.
° . e
(b) This chapter does not cover land. It covers all
other property including—
(4) vessels;
10 U.S.C. § 2304(a) (13), (14):
(a) Purchases of and contracts for property or serv-
ices covered by this chapter shall be made by formal
advertising in all cases in which the use of such method
49a
is feasible and practicable under the existing condi-
tions and circumstances. If use of such method is not
feasible and practicable, the head of an agency, subject
to the requirements for determinations and findings in
section 2310, may negotiate such a purchase or con-
tract, if—
. . *
(13) the purchase or contract is for equipment that
he determines to be technical equipment whose stand-
ardization and the interchangeability of whose parts
are necessary in the public interest and whose procure-
ment by negotiation is necessary to assure that stand-
ardization and interchangeability ;
(14) the purchase or contract is for technical or spe-
cial property that he determines to require a substan-
tial initial investment or an extended period of prepa-
ration for manufacture, and for which he determines
that formal advertising would be likely to result in ad-
ditional cost to the Government by reason of duplica-
tion of investment or would result in duplication of
necessary preparation which would unduly delay the
procurement of the property;
10 U.S.C. § 5011:
The Department of the Navy is separately organized
under the Secretary of the Navy. It operates under the
authority, direction, and control of the Secretary of De-
fense. It is composed of the executive part of the De-
partment of the Navy; the Headquarters, United
States Marine Corps; the entire operating forces, in-
cluding naval aviation, of the United States Navy and
of the United States Marine Corps, and the reserve
components of those operating forces; and all field ac-
tivities, headquarters, forces, bases, installations, activ-
ities, and functions under the control or supervision of
the Secretary of the Navy. It includes the United States
50a
Coast Guard when it is operating as a service in the
Navy.
10 U.S.C. § 5031:
(a) There is a Secretary of the Navy, who is the
head of the Department of the Navy. He shall adminis-
ter the Department of the Navy under the direction,
authority, and control of the Secretary of Defense. The
Secretary is responsible to the Secretary of Defense
for the operation and efficiency of the Department.
After first informing the Secretary of Defense, the
Secretary may make such recommendations to Con-
gress relating to the Department of Defense as he may
consider appropriate.
(b) The Secretary of the Navy shall execute such
orders as he receives from the President relative to—
(1) the procurement of naval stores and mate-
rial ;
(2) the construction, armament, equipment, and
employment of naval vessels; and
(3) all matters connected with the Department
of the Navy.
(c) The Secretary of the Navy has custody and
charge of all books, records, and other property of the
Department.
28 U.S.C. § 516:
Except as otherwise authorized by law, the conduct
of litigation in which the United States, an agency, or
officer thereof is a party, or is interested, and securing
evidence therefor, is reserved to officers of the Depart-
ment of Justice, under the direction of the Attorney
General.
5la
28 U.S.C. § 519:
Except as otherwise authorized by law, the Attorney
General shall supervise all litigation to which the
United States, an agency, or officer thereof is a party,
and shall direct all United States attorneys, assistant
United States attorneys, and special attorneys ap-
pointed under section 543 of this title in the discharge
of their respective duties.
50 U.S.C. § 401:
In enacting this legislation, it is the intent of Con-
gress to provide a comprehensive program for the
future security of the United States; to provide for the
establishment of integrated policies and procedures for
the departments, agencies, and functions of the Govern-
ment relating to the national security; to provide a
Department of Defense, including the three military
Departments of the Army, the Navy (including naval
aviation and the United States Marine Corps), and the
Air Force under the direction, authority, and control
of the Secretary of Defense; to provide that each mili-
tary department shall be separately organized under
its own Secretary and shall function under the direc-
tion, authority, and control of the Secretary of Defense;
to provide for their unified direction under civilian
control of the Secretary of Defense but not to merge
these departments or services; to provide for the estab-
lishment of unified or specified combatant commands,
and a clear and direct line of command to such com-
mands; to eliminate unnecessary duplication in the De-
partment of Defense, and particularly in the field of
research and engineering by vesting its overall direc-
tion and control] in the Secretary of Defense; to pro-
vide more effective, efficient, and economical adminis-
tration in the Department of Defense; to provide for
the unified strategic direction of the combatant forces,
52a
for their operation under unified command, and for
their integration into an efficient team of land, naval,
and air forces but not to establish a single Chief of
Staff over the armed forces nor an overall armed forces
general staff.
53a
ADDENDUM D
Rule 52(a) Fed. RB. Civ. P.:
(a) Errecr. In all actions tried upon the facts with-
out a jury or with an advisory jury, the court shall
find the facts specially and state separately its conclu-
sions of law thereon, and judgment shall be entered
pursuant to Rule 58; and in granting or refusing inter-
locutory injunctions the court shall similarly set forth
the findings of fact and conclusions of law which con-
stitute the grounds of its action. Requests for findings
are not necessary for purposes of review. Findings of
fact shall not be set aside unless clearly erroneous, and
due regard shall be given to the opportunity of the
trial court to judge of the credibility of the witnesses.
The findings of a master, to the extent that the court
adopts them, shall be considered as the findings of the
court. If an opinion or memorandum of decision is
filed, it will be sufficient if the findings of fact and con-
clusions of law appear therein. Findings of fact and
conclusions of law are unnecessary on decisions of mo-
tions under Rules 12 or 56 or any other motion except
as provided in Rule 41 (b).
54a
ADDENDUM E
August 29, 1975. Order of the United States District
Court for the Eastern District of Virginia.
Wuenreas, the Government has giver written notice of
exercise of Option 1, Alternative 2, for the construction of
DLGN-41, under Article 28 of Contract N00024-70-C-0252;
and
Wuereas, the contractor, Newport News Shipbuilding
and Dry Dock Company, has given written notice to the
Government that the Contractor regards the option to be
invalid and its purported exercise ineffectual ;
Now THEREFoRE, in consideration of these premises:
i. The Contractor will immediately resume the pro-
curement of material and the performance of shop fab-
rication and other preliminary work for the DLGN-41
and proceed to undertake construction. Payment for
such work will be made by the Navy on the same basis
as payments were made prior to June 6, 1975. The
Contractor’s and the Navy’s obligations under this para-
graph shall be without prejudice to their legal posi-
tion and contractual rights, including recoupment of
any overpayment.
It is understood by the parties that all of the changes
made in the plans and specifications for DLGN-38,
DLGN-39, and DLGN-40 that are applicable will be in-
corporated in the plans and specifications for DLGN-
41, and the parties agree to negotiate in good faith the
appropriate equitable adjustments for all such changes.
2. The parties agree to negotiate in good faith to
reach an agreement as rapidly as possible to modify
those contract provisions requiring amendment or to
take other appropriate action.
3. Both parties agree to urge the Comptroller Gen-
eral to expedite his opinion on the issues heretofore
oo0a
submitted by the Contractor, and to promptly furnish
a copy of the Comptroller General’s opinion to the
United States District Court for the Eastern District
of Virginia. Either party may assert whatever rights
it may have in respect of such opinion to the Court, and
the Court shall retain jurisdiction in the interim.
4. The United States having represented that suffi-
cient funds are available to make payments to the Con-
tractor under paragraph 1 hereof for a period of at
least one year, the stipulation shall remain in effect
for a period of one year from the date hereof, unless
cancelled or modified by mutual agreement or by Order
of the United States District Court for the Eastern
District of Virginia at the request of either party.
5. This stipulation and any action taken by either
party pursuant hereto shall be without prejudice to the
rights or legal positions of either party.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.