Petition — Providence Hospital v. Manhattan Construction Co.
Supreme Court brief1978
Ask Donna
What actually matters in this document.
Text
Supreme Court, U. &.
FILED
ofc 1897/7
AN., CLERK
IN THE
Supreme Court of the United States
OCTOBER TERM, 1977
No. 77-854
PROVIDENCE HOSPITAL,
Petitioner,
versus
MANHATTAN CONSTRUCTION COMPANY OF TEXAS,
K. C. ERNST, ING., CHARLES H. McCAULEY
ASSOCIATES, INC., AND FAIRBANKS-MORSE, INC.
Respondents.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
WILLIS C. DARBY, JR.
Post Office Box 2565
Mobile, Alabama 36601
Counsel for Petitioner
December 12, 1977
SCOFIFLOS' QUALITY PRINTERS, FP O 80% 69006.N % LA 70169 804 822 1611
TABLE OF CONTENTS
Page
LL 11
Introductory Prayer 1
Citations to Opinions Belo 1
GUFIMEIOTIOR „ 6 0 0 6 6 6 6 6 6 6 6 6 6 6 0 0 6 0 6 6 6 66 6 60 2
Questions Presenteedgdgdad cece eee eeenes 2
DPR ee ee e ee lt 0 6 0 3
Statement of the Case 3
Reasons for Granting the Writ
A. The Fifth Circuit So Far Departed
From The Accepted And Usual Course
Of Judicial Proceedings As To Cali
For An Exercise Of This Court's
Power Of Supervision 10
B. The Decision Of TI. Fifth Circuit Is In
Conflict With The Decision Of Other
Courts Of Appeals 12
1. The Decision Below As To Waiver
Of Arbitration Conflicts With A
Decision Of The United States
Court Of Appeals For The Sixth
e actos 12
2. The Decision Below Conflicts
With The Decision Of The United
States Court Of Appeals For The
Tenth Circuit As To The
Deference To Be Given Under
Rule 52(a), F.R.Civ.P., To The Con-
struction Of A Purported “No
ii
TABLE OF CONTENTS (Continued)
Page
resse ses ee seen 15
r ̃ cil aa lal eas bia 15
Appendices
Excerpts from the General Conditions la
United States Code, Title 9 §§2, 3. ............. 6a
Decision of Court of Appeals Da
Decision of Court of Appeals on rehearing ... 30a
Decision of United States District Court 33a
Excerpt from Brief In Support of the
Motions of Providence Hospital to Dis-
rere ! eee eee 70a
Opinion in Germany v. River Terminal Ry.
K A V- nne oo. 73a
Opinion in Burgess Construction Co. v. M.
SO GI BNL. eee cece: 76a
Judgment of the Court of Appeals ............. 86a
TABLE OF CASES
Burgess Const. Co. v. M. Morrin & Son Co.,
Inc,, 526 F. ad 108 (10th Cir, 1975) ............... 14
Crown Coat Front Co. v. United States, 386
R eee 12
General Guar. Ins. Co. v. New Orleans
General Agency, Inc., 427 F. ad 924 (Sth Cir.
Germany v. River Terminal Ry. Co., 477 F.2d
. cccccdowcddbecscce ccccce 13
ill
TABLE OF CASES (Continued)
Page
Kulukundis Shipping Co. v. Amtorg Trading
Corp., 126 F. ad 978 (2d Cir, 1940)))))) 10
Republic Steel Corp. v. Maddox, 379 U. S. 650...... 12
Shanferoke C. & B. Corp. v. Westchester 8.
Corp., 293 U.S. 449, affirming 70 F.2d 297 (2d
Cle. 2GBE . e 00 666 6 66 6 6 6 6 6 6 6 6 0 666 6 6 6 6 6 6 6 6 66 10
Sims v. City of Birmingham, 254 Ala. 598
(10600 ·ꝛ „„ 11
Thompson v. St. Louis-San Francisco Ry. Co.,
113 F.Supp. 900 (N. D. Ala. 106 0)))) 11
United States v. Blair, 321 U. 8. 70 6.12
United States v. Callahan Walker Const. Co.,
%. . 6 6 „ „ „ „ 6 „ „ 6 6 6 6 6 6 6 6 6 0 12
United States v. Howard P. Foley Co., 320 U.S.
12•9„57» . f 14
United States v. Joseph A. Holpuch Co., 328
Deer. ...e eee ee ee ee eee 6.12
United States v. Rice, 317 U.S. 1 eee 6,14
United States v. Second National Bank of
North Miami, 502 F. ad 535 (Sth Cir. 1974)........ 14
United Steelworkers of America v. American
Mfg. Co., 363 U. 8. 6 — 12
United Steelworkers of America v. Enter-
prise Wheel and Car Corp., 363 U.S. 6 12
United Steelworkers of America v. Warrior
and Gulf N. Co., 363 U. 8. B74 dꝙiVrn; - 12
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1977 *
No.
PROVIDENCE HOSPITAL,
Petitioner,
versus
MANHATTAN CONSTRUCTION COMPANY OF
TEXAS, E. C. ERNST, INC., CHARLES !1.
McCAULEY ASSOCIATES, INC., AND
FAIRBANKS-MORSE, INC..
Respondents.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
The petitioner, Providence Hospital (Providence),
respectfully prays that 2 writ of certiorari issue to
review the judgment and opinion of the United States
Court of Appeals for the Fifth Circuit, entered in this
proceeding on May 9, 1977 and on rehearing on
September 14, 1977.
The opinion of the Court of Appeals reported at 551
F. ad 1026, appears in the Appendix hereto, infra, page
9a; the opinion of the Court of Appeals on rehearing,
reported at 559 F.2d 268, appears in the Appendix
hereto, infra, page 31a. The opinion of the District
Court reported at 387 F.Supp. 1001, appears in the
Appendix hereto, infra, page 34a.
JURISDICTION
The opinion of the Court of Appeals was entered on
May 9, 1977. A timely petition for rehearing was grant-
ed in part on September 14, 1977; and this petition for
certiorari was filed within ninety (90) days of
September 14, 1977. This Court’s jurisdiction is in-
voked under 28 U.S.C. §1254(1). The jurisdiction of the
District Court was invoked under 28 U.S.C. §1332.
QUESTIONS PRESENTED
1. Does a defendant forfeit benefits of a contractual
dispute settlement procedure requiring arbitration as
a prior condition to suit by moving to dismiss a con-
tract claim, never presented to arbitration, for failure
to state a claim upon which relief can be granted?
2. Are courts bound by contractual provisions
specifying time limitations on filing and appealing
claims and restricting remedies where a party to the
contract waives the forum of arbitration?
3. Is the construction by a district court of a pur-
ported “no damage” clause in a construction contract
entitled to deference unless clearly erroneous under
Rule 52(a) F.R.Civ.P.?
3
STATUTORY PROVISIONS INVOLVED
United States Code, Title 9. Arbitration“ §§2, 3, and
4, appear in the Appendix hereto, infra, pages 6a and
8a.
-
STATEMENT OF THE CASE
On July 29, 1968, Providence and Manhattan Con-
struction Company of Texas (Manhattan) entered into
a construction contract for additions and
modifications to hospital facilities of Providence
(Finding 2, App. 36a).! The construction was aided bya
$1,000,000 - ral 2, App.
). contract incorporated General Conditions“
developed by the United States Public Health Service
and approved by the United States Budget Bureau for
use on federally assisted hospital projects (App. 1a, A.
441).
The General Conditions provided:
1. a two step procedure for settlement of all
claims of the Owner or Contractor arising
in connection with the contract by sub-
mission to the architect for a written deci-
sion, with the right to appeal to arbitration
pursuant to the standard Form of Arbitra-
tion Procedure of the American Institute of
Architects (App. 1a-2a);
i Citations to “Finding” and “Conclusion” are to the opinion of
the District Court: citations to “Decision” are to the opinion of the
Court of Appeals; citations to “Opinion on reh. are to the
— ml pe Sra pe to App. aretothe
SS See are to the printed Appendix in
4
2. “if the Architect fails to make a written
decision .. . within ten days after written
request for same... either party may then
demand arbitration” (App. 2a);
3. “any demand for arbitration shall be made
within thirty days after the dispute has
arisen if practicable” (App. 3a);
4. “the decision of the arbitrators shall be a
p ior condition to any right of legal ac-
tion” (App. 2a); and,
5. a remedy of an extension of time for com-
pletion of the contract occasioned by
delays caused by the Owner (App. 5a-6a).
In the course of the project Manhattan, pursuant to
paragraph 31(c) of the General Conditions, requested
extensions of time from the Architect; some were
allowed, some denied (Finding 4, App. 37a; Finding 16,
App. 42a). In November, 1968, a dispute arose over the
sewage ejection system. “Manhattan requested an ex-
tension on its contract. . . because of this delay, but its
request was denied by the Architect” (Finding 24, App.
44a). In January, 1969, a dispute arose over Palco bed
light fixtures (Finding 47, App. 49a); “Manhattan re-
quested a 59 day extension. no extension was
granted (Finding 49, App. 49a).
E. C. Ernst, Inc. (Ernst), Manhattan's electrical sub-
contractor, commenced this action on October 28, 1970,
against Manhattan, Providence, Fairbanks-Morse,
Inc. (Fairbanks), an Ernst supplier, and Charles H.
McCauley Associates, Inc. (McCauley), the architect;
Ernst sought damages, declaratory and injunctive
relief concerning the emergency generator (A. 1-48).
On November 27, 1970, Manhattan answered, claim-
ing damages from Ernst, McCauley, Providence and
Fairbanks for delays associated with the emergency
generator? (A. 49-54).
On December 16, 1970, Providence moved (1) to dis-
miss the complaint of Ernst against Providence for
failure to state a claim, (2) to dismiss the claims of
Manhattan against Providence for failure to state a
claim, and (3) “to stay further proceedings. . . because
this cause will not be ready for judicial determination
until such time as Manhattan has performed its
obligations under the construction contract with
Providence” (A. 54-79).
On December 17, 1970, in the BRIEF IN SUPPORT
OF THE MOTIONS OF PROVIDENCE HOSPITAL TO
DISMISS AND TO STAY, Providence raised the dis-
pute settlement procedure of the General Conditions
in support of Providence’s motion to dismiss and stay
Manhattan's cross-claim against Providence (Deci-
sion, App. 26a). Argument in the BRIEF IN SUPPORT
OF THE MOTIONS OF PROVIDENCE HOSPITAL TO
DISMISS AND TO STAY concerning Manhattan is
reproduced in the Appendix hereto, page 70a, infra.
Providence argued that the General Conditions
provided for arbitration of disputes between
Providence and Manhattan such as the emergency
generator system dispute, that Manhattan’s damages
2 .- LIT
6
(if any) could have been mitigated or avoided by
prompt demand for arbitration, and that the cross-
claim should be dismissed because the General Con-
ditions provided a complete and reasonable means to
resolve such disputes, which “ ‘must be exhausted
before relief is sought in the courts’ ’, quoting United
States v. Blair, 321 U.S. 730, 736. Providence cited Unit -
ed States v. Joseph A. Holpuch Co., 328 U.S. 234, 240 to
the effect that, if a contractor fails to exhaust his con-
tractual dispute settlement procedures, the court is
then obligated to outlaw his cleims, whatever may be
their equity. To do otherwise is to rewrite the con-
tract.’ Providence also raised Paragraph 31(c) of the
General Conditions, which provided for equitable ad-
justment for “delays in the completion of the work due
to.. . acts of the Owner” in that “the Architect. . shall
ascertain ... the extent of the delay and extend the
time for completing the work” and argued that the con-
tractual provision for extension of time on account of
delays by the owner precluded any right of the con-
tractor to collect damages for such delays, under Unit-
ed States v. Rice, 317 U.S. 61.
On December 22, 1970, the District Court granted
Providence’s December 16, 1970, motion to dismiss the
complaint of Ernst as to Providence (A. Docket En-
tries, p. 2). On January 11. 1971, Manhattan filed its
FIRST AMENDED ANSWER AND CROSS-CLAIM;
on January 13, 1971, Providence moved to dismiss the
cross-claim of Manhattan against Providence, as
amended January 11. 1971, for failure to state a claim
(A. 90-91).
On January 15, 1971, the District Court held the
Providence motion to stay of December 16, 1970, moot
(A. Docket Entries, p. 2).
7
On January 27, 1971, Manhattan filed its SECOND
AMENDED ANSWER AND CROSS-CLAIM which
again amended the cross-claim against Providence,
set forth the arbitration provision of the General Con-
ditions and alleged (incorrectly) that Manhattan had
demanded arbitration of the decision of the architect
not to accept the proposed emergency generator and
damages for delay, and further alleged (incorrectly)
that “Providence and McCauley refused to arbitrate”
(A. 94-98). In fact, no demand for arbitration was ever
filed (Decision, App. 26a, n. 38).
On February 4, 1971, after 5 days of testimony pre-
sented by Ernst and Fairbanks on the sufficiency of
the emergency generator, the District Court held that
the Fairbank’s emergency generator failed to meet
the requirements of the specifications.” (Finding 5,
App. 37a).
Manhattan amended its cross-claim against
Providence on May 17, 1971 (A. 106-09), July 30, 1971
(A. 113-33) and April 13, 1973 (A. 280-309). None of the
claims of Manhattan concerned the sewage ejection
problem (Finding 11, App. 40a-41a).
On October 22, 1971, Providence moved to dismiss
the claims of Manhattan against Providence, filed on
July 30, 1971, for failure to state a claim (A. 150).
On February 23, 1972, the District Court held
Providence’s January 13, 1971, motion to dismiss
claims of Manhattan moot (A. Docket Entries, p. 6). On
May 30, 1972, the District Court denied Providence’s
October 22, 1971, motion to dismiss the July 30, 1971,
claims of Manhattan (A. Docket Entries, p. 7).
On August 10, 1972, 19 months after tie District
Court had dismissed all Ernst claims against
Providence, the District Court allowed Ernst to amend
its complaint to claim $450,000 damages against
Providence (A. 168).
Providence answered the Manhattan cross-claims
of April 13, 1973, setting out the exclusivity of the dis-
pute settlement procedure as a remedy for Manhattan
against Providence, and setting out the effect of para-
graph 31(c) of the General Conditions in confining
Manhattan to an extension of the contract time as an
exclusive remedy for delays allegedly caused by
Providence (A. 309-52),
Providence made no claim against Manhattan for li-
quidated damages; such issue “was framed by the
[District] Court in its pretrial order” (Finding 11, I.
App. 41a; Finding 14, App. 42a). Providence did plead
over against McCauley for indemnification on the
claims asserted by Manhattan against Providence
(Finding 11, I, App. 41a). Providence participa‘ed in
discovery and in the trial in January and February,
1971, on the sufficiency of the emergency generator
while its motions to dismiss Manhattan's claims were
pending, and after Providence’s motions to dismiss
were denied. Providence counterclaimed against
Ernst and cross-claimed against Fairbanks, but not
against Manhattan. Providence had no arbitration
agreement with any party other than Manhattan.
On December 11, 1974, after a forty day trial which
commenced on August 6, 1973 (Finding 8, App. 38a),
the District Court, without specifying any reason, dis-
missed the claims of Ernst and Manhattan against
*
Providence for money damages (Conclusion of Law
13, App. 68a). The District Court charged Providence
with 65 days of delay in connection with the sewage
ejection system [which was not mentioned in any
pleading] (Finding 25, App. 44a-45a, and 29-1/2 days
delay in connection with the Palco light fixtures,
which was first mentioned in the cross-claim of
Manhattan filed January 27, 1971 (Finding 49, App.
49a-50a, A. 92-99) and held that Providence should not
deduct liquidated damages for such days of delay from
the amount due Manhattan (Finding 25, App. 44a-45a;
Finding 49, App. 49a-50a; Conclusion of Law 5, App.
67a). The District Court found that “Providence filed
motions to dismiss for failure to arbitrate certain of
the elements of controversy which were denied by the
Court” (Finding 126, App. 65a). The District Court did
not find that Providence failed to timely file such
motions or that such motions failed to raise the ar-
bitrability of Manhattan's claims against Provi-
dence. The District Court concluded
During the litigation the contention was
made by Providence that Manhattan's claim
should be held in abeyance or denied because
of failure to resort to arbitration. Providence's
entitlement to arbitration is permissive and
cannot operate to deny to a party its right to
present its claim in a court of law. A litigant
cannot fail to invoke permissive arbitration
provisions of a contract and then attempt to
advance this failure as a defense to claims
asserted against it. (Conclusions 8, App. 67a).
The Fifth Circuit affirmed the District Court's con-
clusion that Providence had waived arbitration,
although not because the arbitration was per-
missive’; but because Providence actively defended
10
the claims of Manhattan and Ernst and cross-claimed
against Ernst and Fairbanks for fraud associated with
the emergency generator, while Providence's motions
to dismiss or stay were pending or after they were de-
nied (Decision, App. 26a; Opinion on reh., App. 31a).
The Fifth Circuit, without specifying any reason, re-
versed the District Court's denial of Manhattan's
claim for damages against Providence, directing the
District Court to award Manhattan actual delay dam-
ages arising from Providence’s mistakes on the
sewage ejection and bedlight fixture problems” (Deci-
sion, App. 26a).
REASONS FOR GRANTING THE WRIT
A.
The Fifth Circuit So Far Departed From The
Accepted And Usual Course Of Judicial
Proceedings As To Call For An Exercise Of
This Court's Power Of Supervision.
This case exemplifies the continuing hostility of
some courts to arbitration and contractual substan-
tive remedies. See Kulukundis Shipping Co. v. Am-
torg Trading Corp., 126 F. ad 978, 982-85 (2d Cir. 1942).
1. The District Court's finding that Providence waiv-
ed its right to arbitration because of the failure of
Providence to invoke arbitration is in conflict with
Shanferoke C. & S. Corp. v. Westchester S. Corp., 293
U.S. 449, 453-54, adopting the rationale of Learned
Hand below, 70 F. d 297 at 299, as well as Genera!
Guar. Ins. Co. v. New Orleans General Agency, Ino.
427 F. ad 924, 928 (Sth Cir. 1970). The Fifth Circuit recog-
11
nized that Providence’s motion to dismiss raised the
exclusivity of arbitration (Decision, App. 26a), but
held that Providence waived its right to demand ar-
bitration by actively defending the claims of Manhat-
tan while such motions were pending and after they
were denied. The Fifth Circuit equates defending an
unfounded claim to “invoking ... litigation
machinery” (Opinion on reh., App. 32a). The General
Conditions make “the decision of the arbitrators. ..a
prior condition to any right of legal action (App.
2a). Under Alabama substantive law. submission
of disputes to arbitration ... must be complied with
before an action may be brought on the contract”
where, as here, arbitration was a condition precedent
to suit under the contract. Sims v. City of Birming-
ham, 254 Ala. 598, 610 (1950); see also Thompson v. St.
Louis-San Francisco Ry. Co., 113 F.Supp. 900
(N. D. Ala. 1953) (motion to dismiss granted). Certainly,
the Federal Arbitration Act, which expresses an over-
riding federal policy favoring arbitration by making
arbitration agreements enforceable, was not intended
to preempt state substantive law requiring arbitration
as a condition precedent to suit, and thereby to allowa
party to avoid contractually required arbitration.
2. The Fifth Circuit likewise displayed a similar
hostility to a contractual substantive limitation on the
remedy available. Paragraph 31(c) of the General Con-
ditions of the Providence — Manhattan contract limit-
ed Manhattan's remedy for delays caused by
Providence to an extension of the contract completion
time. The District Court so construed the Providence
— Manhattan contract, by granting Manhattan an ex-
tension of time (Conclusion 5, App. 67a) but denying
damages for delays caused by Providence (Conclusion
13, App. 68a). The Fifth Circuit vacated without ex-
planation (Decision, App. 26a), effectively rewriting
the Providence — Manhattan contract. Compare Unit-
ed States v. Joseph A. Holpuch Co., 328 U.S. 234, 240
(the “court is then obliged to outlaw his claims, what-
ever may be their equity. To do otherwise is to rewrite
the contract.)
3. The rationale of Crown Coat Front Co. v. United
States, 386 U.S. 503, 511-12, that a government con-
tractor must seek the relief provided for under the con.
tract or be barred from any relief in the courts”,
previously enunciated in United States v. Callahan
Walker Const. Co., 317 U.S. 56, 61; United States v.
Blair, 321 U.8. 730, 735; United States v. Joseph A.
Holpuch Co., 328 U.S. 234, 239-40; and applied to labor
agreements in Republic Steel Corp. v. Maddox, 379
U.S. 650, and the Steelworker Trilogy cases,’ appears
equally applicable to private construction contracts
providing their own remedies and forum.
4
, .
The Decision Of The Fifth Circuit Is In Con-
flict With The Decision Of Other Courts Of
Appeals.
J.
The Decision Below As To Waiver Of Arbitra-
tion Conflicts With A Decision Of The United
States Court of Appeals For The Sixth Circuit.
3 United Steelworkers of America v. American Mig. Co., 363 U.S.
United Steelworkers of America v Warrior and Gulf N Co.
8. 574, United of America v. Enterprise Whee!
Car Corp. 363 U.S. 583.
13
In Germany v. River Terminal Ry. Co., 477 F. ad 546
(6th Cir. 1973), (App. 73a), the Sixth Circuit held that a
motion to dismiss a cross-claim for failure to state a
claim upon which reiief could be granted” properly
raised arbitration and further held that waiver of an
agreement to arbitrate “may not be inferred from the
fact that a party does not rely exclusively on the ar-
bitration provisions of a contract, but attempts to meet
«l) issues raised in litigation between it and another
party to the agreement.” The extent of the conflict
between the Fifth Circuit and the Sixth Circuit is
evidenced by the refusal of the Sixth Circuit to allow
River Terminal to withdraw its arbitration defense on
appeal “in the interest of concluding the dispute as
rapidly as possible” because “the courts are con-
cerned that the salutary results of the policy ex-
pressed in the Federal Arbitration Act be realized.”
447 F.2d at 548 (App. 75a).
The Decision Below Conflicts With The Deci-
sion Of The United States Court of Appeals
For The Tenth Circuit As To The Deference To
Be Given Under Rule 52(a), F.R.Civ.P., To The
Construction Of A Purported “No Damage
Clause By The District Court.
The Fifth Circuit vacated without discussion the
decision of the District Court denying Manhattan
damages for delays caused by Providence (Decision,
App. 26a). The District Court granted Manhattan an
extension of contract completion time for such delays
(Conclusion 5, App. 67a), but denied damages (Conclu-
sion 13. App. 68a).
14
The District Court implicitlys found that the
Providence — Manhattan contract contained a no
damage clause limiting Manhattan's remedy for
delays caused by Providence to contract time exten-
sion. Paragraph 31(c) of the Genera! Conditions of the
Providence — Manhattan contract is substantial
evidence upon which the District Court could make
such a finding. See United States v. Rice, 317 U.S. 61;
United States v. Howard P. Foley Co., 329 U.S. 64.
The Fifth Circuit gave no deference to the decision of
the District Court construing the Providence —
Manhattan contract to contain a no damage” clause,
as the Fifth Circuit likewise made no reference in
another portion of the decision below to the similar
decision of the District Court construing the Manhat-
tan — Ernst contract to contain a no damage” clause
(Decision, App. 12a-13a). The Fifth Circuit did not ap-
ply the “clearly erroneous” standard in review, which
is compelled by Rule 52(a), F.R.Civ.P.
The failure of the Fifth Circuit to give Rule 52(a) def-
erence is directly contrary to the decision of the Tenth
Circuit in Burgess Const. Co. v. M. Morrin & Son Co.,
Inc., 526 F. ad 108 (10th Cir. 1975), (App. 76a). The Tenth
Circuit in affirming the district court's construction of
a no damage” clause in Burgess Const. Co. held the
standard of review to be whether the decision was
“clearly erroneous” 526 F. ad 108. 115( 1975), (App. 83a).
4 As the Fifth Circuit has in United States v Second
National Bank of North Miami, 502 F.2d 536, % (Sth Cir. 1974)
implicit findings are nevertheless entitled to Rule 52(a) deference
—
_
—
15
CONCLUSION
For these reasons, a writ of certiorari should issue to
review the judgment and opinion of the Fifth Circuit.
Respectfully submitted,
Willis C. Darby, Jr.
Council for Petitioner
Post Office Box 2565
Mobile, Alabama 36601
PROOF OF SERVICE
I, Willis C. Darby, Jr., the attorney for Providence
Hospital, the petitioner herein, and a member of the
Bar of the Supreme Court of the United States, hereby
certify that on the 12th day of December, 1977, I served
copies of the foregoing Petition for a Writ of Certiorari
to the United States Court of Appeals for the Fifth Cir-
cuit on the several parties thereto by mailing copies in
duly addressed envelopes, with first class postage
prepaid to their respective attorneys of record as
follows:
Attorneys for E. C. Ernst, Inc.
Glower W. Jones, Esquire
SMITH, CURRIE & HANCOCK
2600 Peachtree Center, Harris Tower
233 Peachtree Street, N. E.
Atlanta, Georgia 30303
16
Arthur S. Friedman, Esquire
FRIEDMAN & GASS
99 Park Avenue
New York, New York 10016
Attorney for Manhattan Construction Company of
Texas
David M. Thornton, Esquire
1111 Mid-Continent Building
Tulsa, Oklahoma 74103
Attorneys for Charles H. McCauley Associates,
Inc.
Maurice Bishop, Esquire
BISHOP & CARLTON
_ 327 Frank Nelson Building
Birmingham, Alabama 35203
Clarence V. McDorman, Esquire
LONDON, YANCEY, CLARK & ALLEN
2100 First National Southern
Natural Gas Building
Birmingham, Alabama 25203
Attorney for Fairbanks-Morse, Inc.
Louis E. Braswell, Esquire
Post Office Box 123
Mobile, Alabama 36601
Willis C. Darby, Jr.
Attorney for Providence
Hospital
Post Office Box 2565
Mobile, Alabama 36601
APPENDIX
Excerpts from the General Conditions ........
United States Code, Title 9 §§2, 3. ............
Decision of Court of Appeals ..................
Decision of Court of Appeals on rehearing.....
Decision of United States District Court ......
Excerpt from Brief In Support of the Motions
of Providence Hospital to Dismiss and to
D ̃ D: .. .
Opinion in Germany v. River Terminal Ry.
R ]˙ üN—ʃ—̃ ̃ . ¼—̃—w“]
Opinion in Burgess Construction Co. v. M.
e d ek cenens
Judgment of the Court — er. eee
.. 30a
. . 73a
.. 76a
la
APPENDIX
EXCERPTS FROM GENERAL CONDITIONS
(THE GENERAL CONDITIONS ARE IN EVIDENCE
AS A PART OF PROVIDENCE EXHIBIT 2; THE
GENERAL CONDITIONS ARE REPRODUCED IN
THE APPENDIX AT PP. 57-65).
[A.57]
PHS-143 Form Approved
Rev. 5-64 Budget Bureau No. 68-R-312
GENERAL CONDITIONS
* + *
[A. 58] 5. Supervision. — All work shall be done un-
der the supervision of the Architect designated by the
Owner. The Architect shall determine the amount.
quality, acceptability, and fitness of all parts of the
work, shall interpret the Specifications, Contract
Documents, and any Extra Work Orders, and shall
decide all other questions in connection with the work.
The Architect shall have no authority to approve or
order changes in the work which alter the terms or
conditions of the contract. Upon request, the Archi-
tect shall confirm in writing any oral order, direction,
requirement, or determination.
6. Architect’s Decisions. — (a) It shall be the
responsibility of the Architect to make written
decisions in regard to all claims of the Owner or Con-
tractor and to interpret the Contract Documents on all
questions arising in connection with the execution of
the work.
2a
(b) Except as otherwise specified, all the
Architect's decisions or interpretations of contract re-
quirements are subject to arbitration.
(c) If the Architect fails to make a written deci-
sion or written interpretation of the contract require-
ments on any question within ten days after written
request for same by either party to the contract, either
party may then demand arbitration, in which event
later decision by the Architect shall not stop the ar-
bitration proceedings except with the mutual consent
of both parties to the contract.
7. Arbitration. — (a) It is mutually agreed that all
disputes arising in connection with this contract shall
be submitted to arbitration in accordance with the
provisions of the current standard Form of Arbitra-
tion Procedure of the American Institute of Archi-
tects and that all findings of fact by the arbitrators un-
der this agreement shall be conclusive and binding on
both parties. It is further mutually agreed that the
decision of the arbitrators shall be a prior condition to
any right of legal action which either party to thecon-
tract may have against the other.
(b) The work under this contract shall not be
stopped or delayed in any way during the arbitration
proceedings except by written mutual consent of both
parties to the contract, and such mutual consent shall
stipulate whether extension of the time for completion
of the contract will be authorized by such stoppage or
delay.
(c) Demand for arbitration in connection with
any dispute shall be filed in writing with the Archi-
3a
tect and with the other party to the contract. Any de-
mand for arbitration shall be made within thirty days
after the dispute has arisen if practicable, but, in any
event, no demand for arbitration shall be made after
the date of final payment except in the case of adispute
arising in connection with any guarantee provisions
of the Contract Documents.
(d) The arbitrators hereunder shall have
authority to award to the party whose contentions are
approved as being in conformity with contract re-
quirements such sums as they, or a majority of them,
consider is proper to compensate the injured party for
any loss in connection with the proceedings; and, if
they find that the arbitration proceedings were
demanded without ſeasonable cause, they may in
addition award th jured party damages for delay,
unless precluded by agreement between the contract-
ing parties before arbitration. The arbitrators shall set
their own compensation and determine the total
amount of such compensation and other costs and ex-
penses of the proceedings incurred by them, unless
otherwise agreed prior to the proceedings, and shall
assess the total of the costs of the proceedings upon
either or both parties to the contract in such propor-
tions as they, or a majority of them, may approve.
[A. 61] 31. Owner's Right To Stop Work or Ter-
minate Contract; Delays, Damages. — (a) If (1) the
Contractor shall be adjudged bankrupt or make an
assignment for the benefit of creditors, or (2) a
receiver or liquidator shall be appointed for the Con-
tractor or for any of his property and shall not be dis-
4a
missed within 20 days after such appointment, or the
proceedings in connection therewith shall not be
stayed on appeal within the said 20 days, or (3) the
Contractor shall refuse or fail, after Notice of Warn-
ing from the Architect, to supply enough properly
skilled workmen or proper materials, or (4) the Con-
tractor shall refuse or fail to prosecute the work or any
part thereof with such diligence as will insure its com-
pletion within the period herein specified (or any duly
authorized extension thereof) or shall fail to complete
the work within said period, or (5) the Contractor shall
fail to make payments as specified to persons supply-
ing labor or materials for the work, or (6) the Contrac-
tor shall fail or refuse to regard laws, ordinances, or
the instructions of the Architect or otherwise be guilty
of a substantial violation of any provision of this con-
tract, then, and in any such event, the Owner, upon the
certificate of the Architect that sufficient cause exists
to justify such action, and without prejudice to any
other rights or remedy he may have, may by 10 days
notice to the Contractor, terminate the employment of
the Contractor and his right to proceed, either as to the
entire work or (at the option of the Owner) as to any
portion thereof as to which delay shall have occurred,
and may take [A. 63] possession of the work and com-
plete the work by contract or otherwise, as the Owner
may deem expedient. In such case the Contractor shall
not be entitled to receive any further payment on that
work until the work is finished. If the unpaid balance
of the compensation to be paid the Contractor here-
under shall exceed the expense of so completing the
work (including compensation for additional
managerial, administrative, and inspection services
and any liquidated damages for delay), such excess
shall be paid to the Contractor. If such expense shall
exceed such unpaid balance, the Contractor and his
5a
sureties shall be liable to the Owner for such excess. If
the right of the Contractor to proceed with the work is
so terminated, the Owner may take possession of and
utilize in completing the work such materials, sup-
plies, plant, and equipment as may be on the site of the
work and necessary therefor. The expense incurred by
the Owner as herein provided, and the damage in-
curred through the Contractor's default, shall be cer-
tified by the Architect.
(b) Ifthe Owner does not terminate the right of
the Contractor to proceed, the Contractor shall con-
tinue the work, in which event the Contractor shall
pay to the Owner as fixed, agreed, and liquidated dam-
ages for each calendar day of the delay until work is
completed or accepted the amount as set forth in the
General Requirements section of the specification and
the Contractor and his sureties shall be liable for
the amount thereof.
(c) Provided that the right of the Contractor to
proceed shall not be terminated, or the Contractor
charged with liquidated damages because of any
delays in the completion of the work due to unfore-
seeable cause beyond the control and without the fault
or negligence of the Contractor including, but not re-
stricted to, acts of God or of the public enemy, acts of
the Government, acts of the Owner, acts of another
contractor in the performance of a contract with the
Owner, fires, floods, epidemics, quarantine restric-
tions, strikes, freight embargoes, and unusually
severe weather, or delays of subcontractors due to
such causes, if the Contractor shall, within ten days
from the beginning of any such delay (unless the
Owner shall grant a further period of time prior to the
date of final settlement of the contract) notify the
Owner in writing through the Architect of the causes
of delay, who shall ascertain the facts and the extent of
the delay and extend the time for completing the work
when in his judgment the findings of fact justify such
an extension, and his findings of fact thereon shall be
final and conclusive on the parties hereto, subject only
to arbitration as specified herein.
TITLE 9
ARBITRATION
§ 2. Validity, irrevocability, and enforcement of
agreements to arbitrate
A written provision in any maritime transaction or
a contract evidencing a transaction involving com-
merce to settle by arbitration a controversy thereafter
arising out of such contract or transaction, or the
refusal to perforin the whole or any part thereof, or an
agreement in writing to submit to arbitration an ex-
isting controversy arising out of such a contract,
transaction, or refusal, shall be valid, irrevocable, and
enforceable, save upon such grounds as exist at law or
in equity for the revocation of any contract.
July 30, 1947, c. 392, 61 Stat. 670.
7a
§ 3. Stay of proceedings where issue therein
referable to arbitration
If any suit or proceeding be brought in any of the
courts of the United States upon any issue referable to
arbitration under an agreement in writing for such ar-
bitration, the court in which such suit is pending, upon
being satisfied that the issue involved in such suit or
proceeding is referable to arbitration under such an
agreement, shall on application of one of the parties
stay the trial of the action until such arbitration has
been had in accordance with the terms of the agree-
ment, providing the applicant for the stay is not in
default in proceeding with such arbitration.
July 30, 1947, o. 392, 61 Stat. 670.
§ 4. Failure to arbitrate under agreement; petition to
United States court having jurisdiction for
order to compel arbitration; notice and service
thereof; hearing and determination
A party aggrieved by the alleged failure, neglect, or
refusal of another to arbitrate under a written agree-
ment for arbitration may petition any United States
district court which, save for such agreement, would
have jurisdiction under Title 28, in a civil action or in
admiralty of the subject matter of a suit arising out of
the controversy between the parties, for an order
directing that such arbitration proceed in the manner
provided for in such agreement. Five days’ notice in
writing of such application shall be served upon the
party in default. Service thereof shall be made in the
manner provided by the Federal Rules of Civil
Procedure. The court shall hear the parties, and upon
being satisfied that the making of the agreement for
arbitration or the failure to comply therewith is not in
issue, the court shall make an order directing the par-
ties to proceed to arbitration in accordance with the
terms of the agreement. The hearing and proceedings,
under such agreement, shall be within the district in
which the petition for an order directing such arbitra-
tion is filed. If the making of the arbitration agreement
or the failure, neglect, or refusal to perform the same
be in issue, the court shall proceed summarily to the
trial thereof. If no jury trial be demanded by the party
alleged to be in default, or if the matter in dispute is
within admiralty jurisdiction, the court shall hear and
determine such issue. Where such an issue is raised,
the party alleged to be in default may, except in cases
of admiralty, on or before the return day of the notice of
application, demand a jury trial of such issue, and
upon such demand the court shall make an order re-
ferring the issue or issues to a jury in the manner
provided by the Federal Rules of Civil Procedure, or
may specially call a jury for that purpose. If the jury
find that no agreement in writing for arbitration was
made or that there is no default in proceeding there-
under, the prooseding shall be dismissed.If the jury
find that an agreement for arbitration was made in
writing and that there is a default in proceeding there-
under, the court shall make an order summarily
directing the parties to proceed with the arbitration in
accordance with the terms thereof.
July 30, 1947, c. 392, 61 Stat. 671; Sept. 3, 1954, c. 1263,
§ 19, 68 Stat. 1233.
E. C. ERNST, INC. „ MANHATTAN CONST. CO. OF TEXAS 3040
E. C. ERNST, INC., Plaintiff-Appellant
Appellee.
*
MANHATTAN CONSTRUCTION cox.
PANY OF TEXAS, Providence Hospi-
tal, Fairbanke-Morse, Inc., Charles H.
McCauley Associates, Inc, Defend-
ante-Appellees Appellants.
No. 75-1794.
United States Court of Appeals,
Fifth Cireuit.
May 9, 1977.
Parties to a diversity action arising
cuit Judge, held, inter alia, that the sub-
contractor was uded from recover
ing from the because of the
2. Contracts =299%(2)
Subcontractor on hospital construc-
tion project was precluded by “no dam-
age clause in subcontract from recover-
ing from contractor for delays encoun-
tered in work.
3. Contracts @=299(2)
Construction contractor did not
waive its defenses under “no damage”
clause of subcontract by breaching
agreement to assert subcontractor’s
claims for delay damage caused by own-
er or any subcontractor to extent per-
missible under contractor's contracts
with such parties.
delay damages from owner by virtue of
owner's alleged abortive attempt to
change to gravity sewage ejection sys-
tem after contractor had begun work on
10a
47 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
delays in its performance attributable to
such negligence of architect.
7. Arbitration @=47
Owner's architect on hospital con-
struction project was not immune from
liability for delays caused by it by virtue
of its arbitral/quasi-judicial functions
under such contract where its inaction
could fairly be characterized as delay or
failure to decide rather than timely deci-
sion-making.
8. Damages @ 140
Evidence in suit arising out of hospi-
tal construction project supported trial
court's action in awarding subcontractor
$61,626.12 actual damages against suppli-
er of generator system, calculated as dif-
ference between subcontractor's price to
contractor for obtaining and installing
supplier's generator system and contrac-
tors replacement cost in purchasing and
installing substitute system. Code of
Ala, Tit. TA, § 2 71 la)
9. Sales 4119)
Where electric generator supplied to
subcontractor in hospital construction
project proved defective, subcontractor
had contractual claim against supplier
for damages for delay sustained by sub-
contractor as result of such defective
generator.
10. Damages 94
Fact finder is not required to con-
sider wealth of defendant as paramount
in determining amount of punitive dam-
ages to be awarded; his decision to
award such damages should be based on
enormity of wrong and necessity of pre-
venting similar wrongs.
11. Fraud 1
Trial court, in awarding punitive
damages to construction subcontractor
against supplier for supplier's fraud with
respect to generator furnished to subcon-
tractor, did not err in focusing on cost of
generator rather than on supplier's net
12. Indemnity 92)
General rule is that indemnification
agreements contemplate payment for at-
torney fees incurred in litigation with
third parties concerning matter indemni-
fied against, regardiess of whether they
say 80, inclusion of attorney fees is pro-
sumed to have been intent of drafter
—_ agreement explicitly says other-
wise.
13. Indemnity @=9(2)
Where supplier agreed with con-
struction subcontractor to indemnify
subcontractor against all liabilities for
damages or injuries incurred by it, and
for its costs, resulting from supplier's
failure to make timely delivery of speci-
fied materials, subcontractor could recov-
er from supplier all the attorney fees
that it could show were related to its
litigation relating to delays caused by
defective generator obtained from sup-
plier; subcontractor was not entitled to
recover fees expended in pursuit of delay
damages against supplier itself.
14. Damages @*79(1), 80(1)
Liquidated damage provisions in
contracts are enforceable under Alabama
law as long as contractual stipulation is
reasonable and measure of damages at
time of contract was conjectural and un-
certain.
15. Contracts @=300(3)
Under Alabama law, owner was en-
titled to liquidated damages for delay in
completion of construction contract de-
spite fact that it contributed to such de-
= itself. Code of Ala, Tit. TA, 6 2
18.
16. Arbitration o=23.3
Where owner liquidated claims aris-
ing out of construction contract for two
112
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 3048
and one-half years without raising con-
tractor’s failure to pursue arbitration
provisions of contract, owner waived
right to demand arbitration. 9 U.S. C. A.
let seq., 3.
17. Negligence 54
Contractor on hospital construction
project was entitled to recover from
owner's architect for actual delay dam-
ages arising from architects defective
plane and specifications regarding gener-
ator system, as well as architect's pro-
crastinations in ruling on supplier's sub-
mittals for that system.
18. Federal Courts 869
Trial court was not clearly erroneous
in finding, in suit under contract for con-
struction of hospital, that contractor did
not make out case of fraud by subcon-
tractor regarding generator submittals.
19. Fraud 25901)
Where trial court found that subcon-
tractor’s supplier was guilty of fraud in
its representations concerning electrical
generator’s agility to comply with con-
tract specifications, contractor was enti-
tled to recover actual damages from sup-
plier for such fraud, if it could prove
them. Code of Ala., Tit. 7, § 107 et seq.
20. Damages 268
Construction contractor's claims for
damages for delay in contract for con-
struction of hospital were too uncertain
in amount to qualify for allowance of
prejudgment interest. 28 U.S. C. A.
§ 1961.
21. Contracts 32200
Trial eourt's finding that contractor
in hospital construction project had
failed to coordinate work, leading to liq-
uidated damages for delay to owner, was
not clearly erroneous.
22. Fraud 25801)
Owner was not entitled to recover
damages from subcontractor’s supplier
for latter's proven fraud in generator
submittals under hospital construction
contract where it proved no damages
other than delay, for which it had al-
ready been compensated by supplier
through contractor, and where it had ac-
quired substitute generator.
Appeals from the United States Dis-
trict Court for the Southern District of
Alabama.
Before GODBOLD, McCREE®* and
TJOFLAT, Circuit Judges.
GODBOLD, Circuit Judge:
This complex diversity case arises
from a series of disputes concerning dif-
ficulties encountered during construction
and renovation of a hospital at Mobile,
Alabama. The parties are Ernst, an
electrical subcontractor on the project;
Providence Hospital, the owner; McCau-
ley, the architect; Manhattan, the gener-
al contractor; and Fairbanks-Morse,
Ernst's electrical supplier. After more
than four years of proceedings and a
40-day bench trial, the district court en-
tered its ‘engthy opinion, 387 F.Supp.
1001 (S.L.Ala.1974).
I. Ernst s claim for damages
Ernst’s principal ground for appeal is
the refusal of the district court to award
it damages for delays on the Job caused
by the other four parties’ breaches of
their respective duties to Ernst. These
other parties have paid Providence for
* Judge McCree, of the Sixth Circuit, participated in the oral argument of this case, but did
not participate in this decision.
12a
3049 E. C. ERNST, INC. ». MANHATTAN CONST. CO. OF TEXAS
delays. But they have not paid damages
claimed by Ernst.
A. Ernst s claims against Manhattan
The district court held that Manhat-
tan's failure properly to coordinate and
supervise the activities on the jobsite vi-
olated paragraph 21(c) of the general
conditions of its contract with Provi-
dence, that Manhattan assumed the re-
sponsibility for delays by other subcon-
tractors (as well as its own) under para-
graph 21(b) of the general conditions,
that it failed to schedule double shifts
once delay had set in and thereby
breached the “general requirements” of
that contract, and that it failed to sched-
ule work properly, also in violation of
the general requirements.
{1} Ernst claims that it is entitled to
damages for these delays caused by
Manhattan. Manhattan points to the
following provision of its contract with
Ernst: N
An extension of time for the comple-
tion of this contract is hereby granted
to [Ernst] for a period equal to any
delay caused by MANHATTAN CON-
STRUCTION COMPANY. Such ex-
tension of time shall be in lieu of and
in full satisfaction of any and all
claims whatsoever of [Ernst] against
the MANHATTAN CONSTRUCTION
COMPANY.
This is a reformulation of the common
“no damage” clause in construction con-
tracts whereby one party contractually
limits its own liability for delay dam-
1. The choice of law rules of Alabama apply.
Klaxon Co. v. Stentor Elec. Mfg. Co, 313 U.S.
487, 61 S.Ct. 1020, 85 L.Ed. 1477 (1941). Al-
though it is unclear from the record where the
subcontract was made, this is irrelevant. The
validity of contractual provisions is generally
governed by the law of the place of making,
but the law of the place of full performance
ages. Although the Alabama! courts
have, not ruled on the validity of such
provisions, their validity is now well es-
tablished. See generally Peter Kiewit
Sons Co. . lowa Southern Utilities Co..
355 F.Supp. 376. 396 401 (S.D.lowa
1973).2 Given their harsh effect, courts
will strictly construe such provisions but
generally enforce them absent delay (1)
not contemplated by the parties under
the provision, (2) amounting to an aban-
donment of the contract, (3) caused by
bad faith, or (4) amounting to active in-
terference. Id. at 397. Ernst claims
none of these exceptions, and the delay
by Manhattan does not fit any of them.
{2} Manhattan’s failure to grant
Ernst a time extension was not the
breath of a condition precedent to Man-
hattan’s invoking the “no damage”
clause. The clause makes no reference
to any such requirement for formally
granting an extension; the language “an
extension of time is hereby
granted” seems to suggest the opposite.
The purpose for such a provision would
be to assure Ernst that Manhattan (or
those upstream from Manhattan) would
not sue Ernst for Manhattan's own de-
lays. No one in this case has charged
Ernst for those delays; Manhattan has
already been charged for them under the
liquidated damage formula.
{3} Ernst also claims that Manhat-
tan's failure to comply with a separate
contractual provision operates to negate
the effect of the “no damage” clause.
This separate clause appears to be an
governs where it diffeya from the former. J
R. Watkins Co. » Hill, 214 Ala. 507, 108 So.
244 (1926); accord, First Nat'l Life Ins. Co. v
Fidelity 4 Deposit Co. 525 F.2d 966 (CA5,
1976) (Alabama law).
2. See also cases cited in Annot., 10 A.L.R.2d
801 (1950).
13a
E. C. ERNST, INC. . MANHATTAN CONST. CO. OF TEXAS 3050
agreement by Manhattan to assert
Ernst's claims for delay damage caused
by Providence or any subcontractor, to
the extent permissible under Manhat-
tan's contracts with those parties. We
are not persuaded that the consequences
of breaching this obligation should in-
clude a waiver of the “no damage” de-
fense, which concerns damages for Man-
hat tan s delays.
B. Ernst s claims against Providence
4] Ernst claims damages for the re-
sults of several mistakes made by Provi-
dence on the job. The district court
found that Providence could not recover
liquidated damages for the entirety of
the delay on the job because Providence
had itself created some of the overall
delay by an abortive attempt to change
to a gravity sewage ejection system af-
ter Manhattan had begun work on a
pump system (65 days delay) and by a
refusal! to accept Palco lighting fixtures
in violation of federa! regulations incor-
porated into the contract (29% days).“
Ernst seeks to parlay these findings into
a recovery for itself against Providence,
pointing out that its “follow-on” electri-
cal work was inevitably delayed to its
damage by these same actions.
In order to establish that these actions
breached some duty to it established by
Alabama law, see Twine v. Liberty Na-
tional Life Insurance Co., 294 Ala. 43,
311 So.2d 299, 302 (1975), Ernst asserts a
third-party beneficiary theory, citing
3. Ernst incorrectly includes in the delays at-
tributable to Providence an additional 39-day
period of delayed access by Manhattan to the
old operating room area for renovation work.
The district court found that the old operating
area “had necessarily been kept in operation
until occupancy of the new operating area.”
387 F.Supp. at 1010 This delay was not a
default on Providence s part.
cases imposing owner-gencral contractor
duties and general contractor-subcon-
tractor duties. None of these cases im-
poses a theory of owner-subcontractor
duty. We turn elsewhere in the law of
Alabama to determine the validity of
third-party beneficiary liability on the
facts of this case.
The Alabama courts have made it
clear that one not a party to a contract
cannot generally sue for its breach.
Twine, supra; Watson v. Mills, 275 Ala.
176, 153 So.2d 612 (1963); Land Title
Guaranty Co. v. Lynchburg Foundry Co.,
80 So. 142 (Ala.App.1918). The Alabama
Supreme Court has indicated that the
well-established judge-made requirement
of vertical privity for manufacturers’ lia-
bility should not be overturned except by
legislative act. Compare Harnischfeger
Corp. v. Harris, 280 Ala. 93, 190 S0. 24
286, 290 (1966), with Bishop v. Faroy
Sales, 336 So.2d 1340 (Ala.1976) (Ala-
bama version of UCC 2 318 abolishes
vertical privity). We think judicial def-
erence is equally applicable in the area
of construction contracts.
Third parties may sue on the contract
if the provision is intended for their di-
rect, as opposed to incidental, benefit.
See, C. g., Anderson v. Howard Hall Co.,
278 Ala. 491, 179 So.2d 71 (1965); accord,
Burgreen Contracting Co. v. Goodman,
55 Ala.App. 209, 314 So.2d 284, petition
for cert. stricken, 294 Ala. 199, 314 So.2d
296 (1975). The duties to Manhattan
that Providence breached (the provision
4. The UCC, Ala Code tit. 7A (1966 Recomp.),
does not govern the Providence-Manhattan
construction contract. Ernst's contract to sup-
ply and install electrical equipment may make
it a seller of goods under id. §§ 2 102 and
-106. See Port City Constr. Co. v. Henderson,
48 Ala.App. 639, 266 So.2d 896 (1972). But
Ernst's capacity is irrelevant to the nature of
Providence’s contract with Manhattan.
14
3051 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
for a sewage ejection pump and an
agreement to accept electrical wall fix-
tures of equal quality” to Sunbeam fix-
tures) were not intended for the direct
benefit of the electrical subcontractor
Ernst. In a large construction project
each of the individual contracts is inevi-
tably intertwined with many others, all
devoted to the general goal of finishing
all phases of the project according to the
plans and specifications drawn up by the
architect and within the time period es-
tablished under the prime contract. See
E C. Ernst, Inc. v. General Motors Corp.
482 F.2d 1047, 1055 (CA5 1973). But this
interrelationship by itself does not justi-
fy imposing third-party beneficiary
duties, which flow not from the inevita-
ble consequences of a breach but rather
from the intent of the contracting par-
ties“ Here the agreement stated in
J 21a) of the general conditions that
“(njothing contained in the specifications
or drawings shall be construed as creat-
ing any contractual! relationship between
any subcontractor and the Owner.” See
4 A. Corbin, Contracts § 77, at 2
(1951):
intent requirement is best illustrated by the
type of relationship that does give rise to
party beneficiary liability. This is the
+
*
171
ari
u
16 So.2d 100 (1943).
specifications were found
oe
8
ra
7
3
2 k
i
if
ti
i
5
|
|
:
{I}f two contracting parties
expressly provide that some third par-
ty who will be benefited by perform-
ance shall have no legally enforceable
right, the courts should effectuate the
expressed intent by denying the third
party any direct remedy.
Ernst's effort to proceed against Provi-
dence on a third-party berieficiary basis
must fail.
C. Ernst's claim against McCauley
Is] The district court found that
McCauley, the architect for Providence,
was responsible for (1) refusing to ap-
prove the Palco bedlight fixture applica-
tion and (2) for the emergency generator
system, (a) drawing faulty
specifications“ and (b) failing promptly
to act on submittals.’ Neither the own-
er-architect agreement nor the Provi-
dence-Manhattan contract made any ref-
erence to the measure of liability from
McCauley to Providence. However, the
district cour’ recognized that agents are
liable to their principals for their “defi-
ciencies” * and utilized against McCauley
the liquidated damage measure in the
charged it for delays in the emergency genera-
tor area actually caused by difficulties in hous-
ing the Caterpillar substitute. The court at-
tributed this portion of the delay to McCau-
ley’s defective specifications and charged
McCauley accordingly
7. e., matters referred to him, pursuant to
** 5-6 of the genera! conditions, for a decision
regarding their comphance with the plans and
specifications
. 387 F Supp. at 1928. 033 The court did not
indicate whether it held McCauley liable under
its contract with Providence or under princi-
ples of negligence Compare Daugherty v.
Gulf Shores Motel Inc. 292 Ala 252. 292
So.2d 454 (1974) (contract), with McPheeters
„ Heard. 332 So2d 733 (Ala.Civ.App.1976)
(negligence).
15a
E. C. ERNST, INC. „. MANHATTAN CONST. CO. OF TEXAS 3052
Providence-Manhattan contract because
McCauley was instrumental in including
this provision. 387 F.Supp. at 1033.“
Ernst seeks the benefit uf these findings,
claiming that the delays in these electri-
cal-oriented problems also delayed it.
Ernst claims that it is a third-party ben-
eficiary to the owner-architect agrev-
ment and reinvokes its earlier-dismissed
negligence argument as well.“
McCauley raises two different theories
that it argues prevent Ernst from recov-
ering. The first, and more broadsweep-
ing, of these challenges Ernst’s status as
a third-party beneficiary to the owner-
architect agreement. We have already
described the general rule in Alabama
concerning third-party rights under con-
tracts (in denying Ernst any rights un-
der the owner-<ontractor agreement).
Ernst may sue under the contract only if
the particular provision is intended for
its direct, as opposed to incidental, bene-
fit. The special role of an architect on a
construction project may call for third-
party beneficiary rights here, although
recent cases have specifically rejected
this idea. See, e. g. Detweiler Bros.,
Inc. v. John Graham & Co., 412 F.Supp.
9. This ruling has not been appealed. McCau-
ley’s two-paragraph cross-appea! asserts dif-
ferent grounds for reversal.
18. Ernst also claims that by purchasing a copy
of the plans and specifications prepared by
McCauley it stood in a contractual relationship
with McCauley and can sue for breach of an
ject it. McCauley prepared the plans for Prov-
idence, which paid valuable consideration for
them. Ernst needed them solely because its
subcontract with Manhattan required it to fol-
low them. Ernst could not be deemed a “pur-
chaser” from McCauley to which implied war-
ranties would run simply because it bought a
copy of a document incorporated by reference
in its own contract. Viewed in another light,
416 (E.D.Wash.1976); A. R. Moyer, Inc.
v. Graham, 285 So.2d 397 (Fla. 197g).
See generally Annot., 65 A.L.R.3d 249
(1975). We need not decide the difficult
question whether Alabama would depart
from this rule, for we agree with the
further holdings of the Moyer line of
cases that contsa.‘ual privity is unneces-
sary for recovery on a negligence theory.
As the subcontractor on the project re-
sponsible for the installation of these
two systems, Ernst surely falls within
the scope of the risk created by McCau-
ley’s actions.”
Is] As we have noted, the district
court characterized McCauley's delays as
“deficiencies.” The court did not specify
whether this meant that the firm had
failed to perform adequately under its
contract with Providence, that it had
failed to satisfy an objective standard of
care required under tort principles, or
both. Having ruled in favor of a theory
of recovery based upon negligence, we
have no difficulty in clarifying the dis-
trict court’s findings by deciding that
MeCauley's activities regarding its arbi-
tral responsibilities on the emergency
generator submittals constituted negli-
what Ernst bought was a copy and the sole
warranty was that it was a true copy of the
original.
11. The Moyer holding appears to have been
influenced by the fact that the particular
agreement involved was not part of the record.
(The case arose from certification by a panel
of this court.) While we have the advantage
that the Florida court did not. the McCauley-
Providence agreement sheds little light on the
subject.
12. McCauley insisted at oral argument that,
court absolved Ernst of any fault with respect
to the bedlight and generator matters under
consideration here. .
*
, |
16a
3053 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
gence as a matter of law. They rep-
resent a pattern of procrastination *
which, in view of the interdependence of
effort so vital on a construction project,
falls below the standard of care required
in this situation for professional archi-
tects. However, whether McCauley’s
erroneous rejection of Palco bedlight fix-
tures also constituted negligence is a
closer question that we cannot answer
from our appellate perspective. We
leave this determination for the district
court on remand. For similar reasons,
we remand the question of negligence
with respect to McCauley’s faulty plans
and specifications.
7] McCauley’s second line of defense
is more troublesome. It claims that it is
protected from liability for at least some
of its errors by the immunity granted to
architects in performing their arbi-
tral/ quasi- judicial functions. McCauley
makes this immunity argument despite
already having been found liable to
Providence below for the same errors
and having taken no appeal from that
general ruling."* Neither the record be-
low nor the district court’s opinion re-
veals whether or not McCauley asserted
the immunity unsuccessfully in that
court-constructed claim by Providence.
However, McCauley did raise this bar
against the claims of Ernst and Manhat-
13. The nature of McCauley's activities on the
job site is described in detail by the district
court in its findings of fact, 387 F.Supp. at
1018-26. We discuss the particulars of the
generator submittal problems beiow in dealing
with the immunity question.
14. Of course, the mere breach of one's con-
tract does not give rise to liability in tort,
which creates duties by operation of law that
are collateral to those created by agreement of
the parties C & C Prods. Inc. v. Premier
Indus. Corp. 290 Ala. 179, 275 So.2d 124, 130
(1972). See also Berry v. Druid City Hosp.
Bd., 333 So.2d 796 (Ala 1976), reviewed in 7
Cum.L.Rev. 355 (1976), accord, Horton v.
tan below, and it is entitled to a ruling
from this court, as we address these lat -
ter claims, regarding the validity and
scope of the immunity.
The leading Alabama case on immuni-
ty of architects as arbitrators is Wilder
v. Crook, 250 Ala. 424, 34 So.2d 832
(1948). The contractor sued the owner
(the city) and the engineer hired by the
owner to supervise the work, claiming
that the engineer’s ruling as to the con-
tractor’s responsibilities under the con-
tract was incorrect. State law required
that the contractor bring suit in the
county in which a “material defendant”
resided; thus, if the theory of recovery
against the engineer failed, suing in the
engineer’s county of residence would
have been improper. The contractor ar-
gued that the engineer “personally as-
sumed a duty under the [owner-contrac-
tor] contract.” But because the engineer
had acted pursuant to a contractual pro-
vision appointing him the arbiter of all
contractual disputes, the court held that
he enjoyed immunity:
By the terms of the contract R. L.
Kenan was placed in a position some-
what analogous to that of an umpire
or arbitrator. His decisions were ac-
cordingly judicial in nature. Under
the circumstances the authorities ap-
pear to hold that he could not be held
Northeast Ala. Regional Medical Center, Inc.,
334 So.2d 885 (Ala.1976). Here, however, we
have pretermitted whether there is a breach of
a contractual duty owed to Ernst. We reach
our finding of negligence without regard to the
terms of McCauley's contract with Providence.
15. See note 9, supra.
16. The district court framed Providence's
claim on its own through a pretrial order. The
court had previously ordered Providence to
pay over additional contract sums despite the
existence of legal disputes about the adequacy
of performance by various parties.
17a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 3054
liable in damages for failure to exer-
cise care or skill in the performance of
his functions. The same principle
seems to apply even where the deci-
sion is the result of fraud or corrup-
tion.
Id. at 834."
As in Wilder, the owner-contractor
agreement here provides for the archi-
tect’s ruling on questions of contract in-
terpretation:
It shall be the responsibility of the
Architect to make written decisions in
regard to all claims of the Owner or
Contractor and to interpret the Con-
tract Documents on all questions aris-
ing in connection with the execution
of the work.
General Conditions Ga). TVO of
McCauley’s “deficiencies” fit into this ar-
bitral / quasi- judicial category its rejec-
tion of the acceptability of Palco bed-
light fixtures and its long-term set of
rulings on the acceptability of the Fair-
banks emergency generator. However,
with respect to both of these matters,
the question is not the insulation of
McCauley from suit because of a decision
it made but, more accurately phrased, its
immunity from suit for failing, or delay-
ing, in making decisions.
The arbitrator's “quasi-judicial” immu-
nity arises from his resemblance to a
judge. The scope of his immunity
should be no broader than this resem-
blance. The arbitrator serves as a pri-
vate vehicle for the ordering of economic
relationships. He is a creature of con-
tract, paid by the parties to perform a
17. There is no indication that this rationale for
immunity would not extend to suits brought in
tort. indeed, the language “failure to exercise
care or skill seems to apply directly to Ernst's
negligence claim as well See also Broyles v.
duty, and his decision binds the parties
because they make a specific, private de-
cision to be bound. His decision is not
socially momentous except to those who
pay him to decide. The judge, however,
is an official governmental instrumental-
ity for resolving societal disputes. The
partics submit their disputes to him
through the structure of the judicial sys-
tem, at mostly public expen His deci-
sions may be glossed with public policy
considerations and fraught with the con-
sequences of stare decisis. When in dis-
charging his function the arbitrator re-
sembles a judge, we protect the integrity
of his decisionmaking by guarding
against his fear of being mulcted in
damages. Cf. Broom v. Douglass, 175
Ala. 268, 57 So. 860 (1912). But he
should be immune from liability only to
the extent that his action is functionally
judge-like.“ Otherwise we become mes-
merized by words.
In his role as interpreter of the con-
tract and as private decisionmaker, the
arbitrator has a duty, express or implied,
to make reasonably expeditious decisions.
Where his action, or inaction, cun fairly
be characterized as delay or failure to
decide rather than timely decisionmaking
(good or bad), he loses his claim to im-
munity because he loses his resemblance
to a judge. He has simply defaulted on
a contractual duty to both parties.
We are mindful of the problems of
characterization that may attend the dis-
tinction between delay in deciding and
bad judgment in the decision itself. The
idea of a misfeasance-nonfeasance di-
chotomy has been subject to question.
Brown Eng ring Co. 275 Ala 35, 151 So2d
767, 772 (1963).
18. See 6 C.J.S. Arbitration § 74. ai p. 289 & nn
15-16 (1975).
18a
3055 E. C. ERNST, INC. ». MANHATTAN CONST. CO. OF TEXAS
See W. Prosser, Torts § 56, at 339-40
(4th ed. 1971). But with respect to the
generator submittals here, the pattern
seems obvious. The tentative, incongru-
ous, and often contradictory nature of
McCauley’s actions constitutes a default
to all parties in the contractual sense
that we have described.
The tone of McCauley’s course of ac-
tion was set by its first step. Fairbanks’
initial application was met with the one-
sentence equivocal response that the
generator units were “approved provid-
ing that the requirements of the plans
and specifications are met. By Feb-
ruary 1969 McCauley had discovered the
foreign-manufacture problem. In April
it shifted its criticism to the problem of
available spare parts. It then shifted to
a complaint that the engines were not a
sta product and did not meet the
horsepower requirement. It then urged
resubmittal. In the view of the district
court, the result of this last action was
“to start the entire process over again
from the beginning at a time when con-
struction progress was already seriously
impeded.” 387 F.Supp. at 1021. After
it had rejected two more resubmittals,
McCauley wrote Manhattan in Septem-
ber 1969 asking for verified horsepower
tests. McCauley called a meeting at the
end of October, the result of which was
to ask for another submittal, this time
19. But cf. Berry v. Druid City Hosp Bd. 333
So.2d 796, 799-800 (Ala.1976) Shores & Al-
mon, JJ., with Embry, J., & Heflin, C J. con-
curring on this point). While its interpretation
is not free from doubt, Justice Shores’ dictum
in Berry has announced as a rule in Alabama
that one who clearly has a cause of action for
breach of contract can also recover in tort
only if the defendant's action can be character-
ized as misfeasance. Here. we view McCau-
ley’s action as nonfeasance and yet do not
disallow recovery based on negligence. But
Ernst has no separate contractual claim. Even
with a different engine. By now, Man-
hattan had become seriously concerned
about the delays resulting from McCau-
ley's failure to take definitive action.
Three times in December 1969 and Janu-
ary 1970 Manhattan wrote McCauley to
spur the latter to action. MeCauley's
failure to do anything prompted Manhat-
tan to request an unlimited extension of
the completion date because of this lack
of cooperation. Equivocation continued.
At a March 1970 meeting, McCauley
first said that it would accept the gener-
ator subject to tests, then agreed to ac-
cept ii prior to tests. Six days later,
McCauley changed its mind and disap-
proved the system. Even so, not until
May of that year did McCauley finally
ask for a new system, specifying the par-
ticular models that would be acceptable.
Throughout this entire time period
McCauley consistently failed to list its
reasons for disapprovals, a step which
could perhaps have been used to resolve
the growing impasse. This pattern of
action demonstrates a consistent failure
to make decisions in a way that could
enable construction to continue. Only
McCauley had the authority to make
these decisions, and it failed to fulfill
that responsibility. The resulting dam-
ages Ernst seeks here represent compen-
sation not for McCauley’s finally select-
ing a different generator system but
if it did, we think the cases that Justice Shores
relied upon in Berry make it clear that the rule
would not bar Ernst's recovery in tort here
See Old S. Life Ins. Co. v. Woodall, 295 Ala.
235, 326 So.2d 726 (1976); C & C Prods., Inc.
v. Premier Indus. Corp., 290 Ala. 179, 275
So. 2d 124 (1972). We understand these cases
to say that the breach of contract, without
more, cannot justify recovery in tort. See
note 14, supra. They do not deny the right to
a tort recovery here.
20. Manhattan Exh. 36.
19a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 3056
rather for this failure to decide. We
cannot extend the arbitral immunity to
such conduct.
We next examine McCauley’s claim of
immunity with respect to its rejection of
Palco bedlight fixtures." Here, the dis-
trict court found a pattern of action sim-
ilar to, though less drawn out than, its
response to the generator submittals.”
In characterizing McCauley’s activities,
we take care in distinguishing Provi-
dence’s decisions from MeCauley's re-
sponsibilities as arbitrator. Providence
made a decision in advance of bid sub-
missions that only Centron-5 fixtures
would do. This decision (a wrong one
for which Providence has been charged)
was different from the architect’s deci-
sion on subsequent submittals. With re-
spect to this responsibility, McCauley
never acted. “McCauley refused even to
look at a sample of the Palco fixture
delivered to its offices.” 387 F.Supp. at
1017. Later, each of the Palco sulmit-
tals was marked “disapproved for rea-
sons noted”; yet McCauley gave no such
reasons. Id While this failure to arbi-
trate is admittedly tied closely to Provi-
dence’s earlier affirmative decision to ac-
cept only Centron-5 fixtures, McCauley
had decisional! responsibilities subsequent
to this and independent of its status as
advisor to the owner. It failed to exer-
cise these responsibilities, and so here,
too, it cannot obtain immunity in dam-
ages. As noted above, we leave for the
district court the question whether this
“deficiency” constituted negligence.
21. The parties have not briefed the question of
the effect here of federal regulations requiring
competitive bidding. We decline to enter this
thicket on our own.
22. See 387 F.Supp. at 1017-18 (findings 47-
49).
23. We do not hold that architects-as-arbitra-
tors must issue satisfactory statements of rea-
Ernst’s claim that defects in MeCau-
ley’s generator plans and specifications
also contributed to its delays challenges
mistakes not even arguably made in the
capacity of arbitrator. We read Broyles
v. Brown Engineering Co., 275 Ala. 35,
151 So.2d 767 (1963), as imposing upon
architects drawing up plans and specifi-
cations not “a contract of guaranty or
insurance of favorable results,” id. at
771, but “a guaranty of reasonable re-
sults,” id. at 772. See Centraal Stikstof
Verkoopkanter, N.V. v. Walsh Stevedor-
ing Co., 380 F.2d 523, 529-31 (CA5 1967)
(interpreting Broyles). We interpret
this implied warranty under contract to
be equally applicable under negligence
claims. The facts of Broyles confirm
this view. The plaintiffs in that case
had failed to allege negligence, and the
court's opinion sought to protect them hy
finding a similar duty implied under the
contract:
Certainly a contracting party has a
right to expect the survey to be done
with reasonable accuracy chargeable
to the profession, and should not be
dependent in his effort to recover
damages on an allegation of negli-
gence or unskillful and imprudent
work.
151 So.2d at 772 (emphasis supplied).™
Again, if the district court finds on re-
mand that the “deficiencies” in the plans
and the specifications constituted negli-
gence, then Ernst is entitled to recover
for its delay damages attributable to this
particular act.
sons for their decisions in order to maintain
their immunity from suit. We point to this
action by McCauley only as evidence of its
failure to rule on the Palco submittals at all.
24. For a list of similar cases supporting liabili-
ty of architects to third parties for defects in
plans and specifications, see Annot., 65 A.L
R.3d 249 (1975).
3057 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
D. Ernst s claims for damages
from Fairbanks
Is] The court awarded Ernst $61,-
626.12 actual damages against Fairbanks
(in addition to a pass-through of liqui-
dated damages to Providence). This fig-
ure represents the difference between
Ernst's price to Manhattan for obtaining
and installing the Fairbanks generator
system and Manhattans replacement
cost in purchasing and installing the sub-
stitute Caterpillar- driven system. As
such, it is simply an indemnity to Ernst
for its payment of this same amount to
Manhattan.
Despite objections by both parties to
this figure, we uphold its propriety.
Ernst claims, in effect, that Fairbanks
should pay its installation fee. But
Ernst never installed anything Fair-
banks claims that $12,764.59 of the $61,-
626.12 figure is a windfall to Ernst. The
theory here is that Ernst should bear the
loss represented by Manhattan's installa-
tion expenses, since Fairbanks never con-
tracted to install a generator but only to
supply one. This seems a simple case of
requiring the breaching party in a con-
tract for the sale of goods to pay conse-
quential damages. Ala Code tit. 7A,
§ 2-71K2\a) (1966 Recomp.).
{9} Ernst claims in addition that
Fairbanks should pay its share of any
damages for the delay sustained by
Ernst as a result of the defective gener-
ator. We agree that Ernst has a con-
tractual claim against Fairbanks for this
consequence of the latter's breach. The
district court should determine the ex-
25. Manhattan also appeals from an identical
punitive damage award to « from Fairbanks.
adopting the arguments made by Ernst. Our
holding applies to both appeals.
tent of these delay damages actually
caused by Fairbanks.
{10,11} The district court also
charged Fairbanks with punitive dam-
ages for its fraud with respect to the
generator matter Ernst * appeals from
this award to it of $20,000 in punitive
damages on ground that the court fo-
cused too sharply on the cost of the gen-
erators rather than on Fairbanks’ net
worth. The factfinder is not required to
consider the wealth of the defendant as
paramount. His decision to award puni-
tive damages should be based on “the
enormity of the wrong and the necessity
of preventing similar wrongs.” Loch
Ridge Construction Co. v. Barra, 291 Ala.
312, 280 So.2d 745, 751 (1973). The dis-
trict court here recognized this principle
in observing generally that “the greater
the wrong the greater the damage.” 387
F.Supp. at 1031. The amount of puni-
tive damages was within the discretion
of the trier of the facts.
E. Problems of proof on remand
On remand the court will face the
question of whether Ernst has satisfacto-
rily proven that the extended time de-
voted by its personnel to this project has
resulted in financial loss“ We intimate
no view on this question. Ernst must
also prove to what extent the actionable
failings of Fairbanks and McCauley were
responsible for these alleged losses. Its
proof of the fact of loss should be meas-
ured against the “reasonably certain”
standard adopted in United Bonding In-
surance Co. v. W. S. Newell, Inc., 285
Ala. 371, 232 So.2d 616, 624 (1969). And
its proof of amount of loss, as well as
26. Because of its liquidated damage clause.
Providence did not confront this issue Ernst,
unhke Providence. has no time-based measure
of damages by which may automatically as-
sess and apporuon us damages.
21a
E. C. ERNST, INC. . MANHATTAN CONST. CO. OF TEXAS 3058
attribution to the above two causes,
should be governed by the “fair and rea-
sonable estimate” language cited in Ne-
well. The appellees argue for the appli-
cation of a nonapportionment rule, based
upon Kershaw Mining Co. v. Lankford,
213 Ala. 630, 105 So. 896 (1925). We see
the Kershaw rule as simply a refinement
of the general proposition in Alabama
that damage must be proven with rea-
sonabie certainty. See Mobile & O. R.
Co. v. Red Feather Coal Co., 218 Ala.
582, 119 So. 606, 609 (1928) (dictum) (cit-
ing Kershaw). Where the plaintiff does
present evidence of attribution to vari-
ous causes, he may recover under the
reasonable certainty standard. See Tan-
ner v. Case, 277 Ala. 641, 173 So.2d 803,
808 (1965).
Unlike the plaintiff in Kershaw, Ernst
faces four defendants all of whom to-
gether were in fact responsible for the
great majority of its damages. Each
seems to point its finger at the others.
Fairbanks, for example, claims that its
fraud caused no delays in the generator
installation because other pre-existing
delays were concurrent with its fraud.
In this context, the district court can, as
it did regarding Providence's claims, as-
certain Erust's total damages and then,
where there exists a legal duty to Ernst
as discussed above. allocate respective re-
sponsibilities for those damages based
upon reasonable certainty.
F. Ernst s claim for attorney's fees
The district court refused to award
Ernst attorney's fees on the basis of
Fairbanks’ agreement in its contract
with Ernst to “indemnify [Buyer]
against all liabilities for damages or in-
juries incurred by the Buyer, for Buyer's
27. Our holding ma, require some re-evaluation
by the district court of its $20,000 punitive
cost, resulting from Seller's failure to
make timely delivery of the materials
specified herein.” (Emphasis supplied).
In Alabama attorney's feces are not ru.
coverable unless provided for in the con-
State v. Alabama
did not examine whether the above in-
demnity provision constituted such à con-
tractual provision for fees but skirted
this issue by ruling:
attorney fees and expenses.
387 F Supp. at 1034. We do not know
how to interpret this conclusion. If thc
court was in fact including within its
$20,000 punitive damage award some in-
resulting from Fairbanks’ delay provide
a basis for Ernst to recover its attorney's
fees? We hold that it does, to some
extent.”
damages award to Ernst. if the court was
requiring the payment of attorney's as
3059 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
{12] The Alabama courts have not
squarely addressed the issue of whether
or when indemnity agreements contem-
plate the payment of attorney's fees.
Cf. Miller & Co. v. Louisville & Nashville
R_R., 328 F.2d 73, 78 (CA5), cert. denied,
377 U.S. 966, 84 S.Ct. 1648, 12 L.Ed.2d
737 (1964) (Alabama law), holding that
judgment against the indemnitee in a
third party's suit would entitle it to “the
costs of defending the claim as well as
the amount of liability. Miller at least
suggests that Alabama would follow the
generally held view that indemnification
agreements contemplate payment for at-
torney'’s fees incurred in litigation with
third parties concerning the matter in-
demnified against, regardiess of whether
they say so. See, e g., Bagby v. Merrill
Lynch, Pierce, Fenner & Smith, Inc, 491
F.2d 192, 198 n 9 (CA8 1974); Insurance
Co. of North America v. King, 340 So.2d
1175 (Pla.D.Ct.App.1976); cf. 5 A. Cor-
bin, Contracts § 1037, at 225 26 (1964 &
Supp.1971). Inclusion of attorney's fees
is presumed to have been the intent of
the drafter unless the agreement explic-
itly says otherwise This rule simply
gives effect to the very nature of indem-
part of the $20,000, Fairbanks should not now
have to pay again for these fees under an
indemnity theory. While our own scrutiny of
nity, which is to make the party whole.
“(T}rue indemnification would contem-
plate the inclusion of these items
”" Seaboard Coast Line Rail-
road v. Tennessee Corp., 421 F.2d 970,
975 (CA5), cert. denied, 398 U.S. 928, 90
S.Ct. 1819, 26 L.Ed 2d 91 (1970) (dictum).
The reference to “cost” in the Ernst-
Fairbanks agreement was not an explicit
denial of the right to attorney's fees.
We do not even interpret it to be an
implied denial,” although in view of the
rule above we need not go this far. As
a result, we hold that the agreement
contemplates recovery of relevant attor-
ney s fees.
{13} The cases cited above limit the
recovery of attorney's ſbes to the subject
matter of the indemnity agreement and
exclude fees expended in suing the in-
demnitor in order to recover under the
agreement. Accordingly, Ernst may re-
cover from Fairbanks only those fees
that it can show were related to its liti-
gation of the generator matter“ This
leaves the question whether Ernst can
recover fees expended in pursuit of delay
damages against Fairbanks itself. This
is not precisely what the rule contem-
(CAS), cert. demed. 357 US 881. 78 SC.
1372. 2 LEd 2d 1371 (1958) ( ‘Any expense’
includes, of course, attorney's fees”). The pro-
vision for cost here is more probably used
as synonymous with “expense it says noth-
ing about the costs being rendered with a
“judgment.” which reference might imply the
more technical concept of court costs (
Fazpatrick v Buzer, 427 US. 445, 459-460, 96
S.Ct. 2666, 2673. 49 L Edd 614, 624 (1976)
(Stevens, J. concurring)
38. These would include the origina! deciarato-
ry judgment action Ernst brought agaist
Manhattan insisting that the Fairbanks genera.
tor conformed to the specifications Applica-
tion of the general rule does not depend upon
who was the plaintiff in the third-party litiga
ton
23a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 3060)
plates when it denies a right of recovery
for fees expended in pursuit of indemni-
ty itself. However, we still find recov-
ery for this portion of the fees inappro-
priate. The terms of the agreement
speak of indemnity for “liabilities.” To
us, this seems to refer to the ciassic in-
demnity situation whereby one party
the reasonable certainty standard articu-
lated above.
II. Ernst’s challenge to Providence’s
liquidated damage recovery
At an early stage of this proceeding,
the district court ordered Providence to
pay over an added portion of the con-
court then proceed to the difficult task
of ascertaining which parties were re-
sponsible for which parts of the delays.
It ordered McCauley to pay its share and
ordered the three other parti (through
Manhattan) te pay their shares, deduct-
ing these from the balance of the con-
tract price which Providence ha! yet to
pay.
[14] Liquidated damage provisions in
contracts are enforceable under Alabama
law as long as the contractual stipulation
is reasonable and the measure of dam-
ages at the time of the contract was
conjectural and uncertain. This rule has
been applied to provisions against delay
in performance on construction con-
tracts. Otinger v. Water Works & Sani-
tary Sewer Board, 278 Ala. 213, 177
So.2d 320 (1965). None of the parties
disputes the conjectural nature of delay
damage in a case like this one or the
lack of disproportion in the $250 per day
damage formula.
1161 However, Ernst seeks to avoid
an assessment of liquidated damages
the so-called rule against
apportionment." This rule states that
under a liquidated damage provision
against delay, where the owner has con-
tributed to delays on the project he may
not apportion the fault but forfeits all
right to recover under the provision.
The rule has been adopted by some juris-
dictions but rejected by others™ The
Alabama courts have never been
presented with the decision of whether
to adopt it or allow apportionment. (/
Kershaw Mining Co., supra (concerning
apportionment for actual damages).
32. See Annot. i152 ALR 1349, 1359 78
(1944).
24a
3061 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
Like the Alabama district judge, we
—
do not remain in full force. One of the
dominant reasons underlying it is early
judicial hostility to the use of privately
agreed upon contract damage remedies.
See, > fea an = v. Maiden
Lane Safe Deposit Co., 199 N.Y. 479, 98
N.E. 81 (1910):
While such an agreement has not the
harshness of a penalty, it is, neverthe-
less, in its nature, such that its en-
forcement, where the party claiming
the right to enforce has, in part, been
the cause of delay, would be unjust.
Today, given the increasing complexity
of contractual relationships, liquidated
damage provisions have obtained firm
judicial and legislative support. See, e.
g. Otinger, supra; Ala. Code tit. 7A, § 2-
718 (1966 Recomp.). As long as the own-
ers own delay is not incurred in bad
faith, it is not unjust to allow propor-
tional fault to govern recovery. Gener-
ally, owners do not benefit from delays
that they incur. Another reason cited in
support of the rule is that proving ap-
portionment is simply too difficult. We
do not disagree with the difficulty of the
task,™ but recovery should not be barred
in every case by a rule of law that pre-
33. There are two different levels of “appor-
uonment that the district court had to reach
cludes examination of the evidence.™
The district court did not err in allowing
apportioned liquidated damages to Provi-
dence.
III. Ernstes appeal on the
electrical receptacles
Ernst concedes that its workmen in-
stalled the receptacles improperly but
claims that this caused no delay (i. c., no
damage). The district court's findings of
delay, 387 F.Supp. at 1014 15, are not
clearly erroneous.
IV. Manhattans claims for
delay damages
Like Ernst, Manhattan claims actual
damages for delays resulting from other
parties’ mistakes. Much of what we
have said about Ernst’s claims applies
with equal force to Manhattan's, but we
examine each party’s potential liability
to Manhattan separately.
A. Claims against Providence
{16) Manhattan’s claim bere is
stronger than that of Ernst, since Man-
hattan and Providence stood in privity of
contract. Providence contends, however,
that by failing to pursue the arbitration
provisions of the genera! conditions in
their contract,™ Manhattan cannot assert
The second step, necessary only for the gen-
E. C. ERNST, INC. . MANHATTAN CONST. CO. OF TEXAS
its claim in federal court. Manhattan's
response is that the activities of Provi-
dence constituted a waiver of the right
to demand arbitration. The district
court agreed, and we do also.
This question is one of federal law,
given the enactment of the United
States Arbitration Act of 1925, 9 U.S.C.
§§ 1 et seg.“ even though this is a di-
versity case. Prima Paint Corp. Flood
& Conklin Mfg. Co., 388 U.S. 395, 404
05, 87 S.Ct. 1801, 18 L.Ed.2d 1270, 1278
(1967); accord, Stokes v. Merrill Lynch,
Pierce, Fenner & Smith, Inc., 523 F.2d
433, 437 (CA6 1975). Section 3 of the
Act reads:
If any suit or proceeding be brought
in any of the courts of the United
States upon any issue referable to ar-
bitration under an agreement in writ-
ing for such arbitration, the court in
which such suit is pending, upon being
satisfied that the issue involved in
such suit or proceeding is referable to
Architect's decisions or interpretations of
Nea
i
14
: g
i!
|
i
12
1111
+
i
rE
arbitration under such an agreement,
shall on application of one of the par-
ties stay the trial of the action until
such arbitration has been had in ac-
cordance with the terms of the agree-
ment, providing the applicant for the
stay is not in default in proceeding
with such arbitration. [Emphasis sup-
plied).
The first indication of the parties’ atti-
tude about arbitration is an April 7,
1970, telephone conversation to Manhat-
tan from Providence's attorney, in which
the attorney
pointed out that the Architect turned
down the [Djorman engine in Septem-
ber of 1969. He further contends that
by not requesting arbitration within
the following six months period, the
contractor waived his right for arbi-
tration. He proposed that if they, at
this point, requested arbitration, Provi-
dence L.ospital will file a suit in feder-
al court asking that arbitration be dis-
ther mutually agreed that the decision of the
arbitrators shall be 2 prior condition to any
right of legal action which either party to
the contract may have against the other
(e) Demand for arbitration in connection
with any dispute shall he filed in writing
with the Architect and with the other party
to the contract. Any demand for arbitration
shall be made within thirty days after the
after the date of final payment except
in the case of a dispute arising in connection
with any guarantee provisions of the Con.
tract Documents."
36. Though no explicit finding was nad, the
Providence-Manhattan contract obviously is a
transaction involving commerce, so the Aci
applies. Insofar as Gavisk Constr. Co. v. H. F
Campbell Co. 526 F.2d 777. 784 (CA3 1975),
suggesis the need for explicit findings in a
case imvolving this clear a dependence upon
interstate commerce, we decline to follow
3063 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
allowed and that the contractor be re-
quired to furnish an engine meeting
specifications.”
The only other evidence of any pre-suit
reference to arbitration is a September
17, 1970, letter to Manhattan from its
own attorney. This letter asked Man-
hattan to date, sign, and complete an
enclosed AIA Demand for Arbitration
and file it with the AAA Regional Of-
fice, sending copies to Providence and
McCauley.™
Ernst's complaint initiated this suit on
October 28, 1970. Providence’s initial
pleading, filed December 16, 1970, was
captioned as a “motion to dismiss” Man-
hattan’s claim and alternatively “to stay
the action.” The requested “stay” was
not for purposes of resort to arbitration
but to require Manhattan to finish con-
struction first. Attached to the motion
was a copy of the 20-page general condi-
tions of the contract, paragraphs 6 and 7
of which concerned arbitration. Provi-
dence filed a supplemental brief which
referred to arbitration but only as 4
ground for dismissing Manhattan’s suit.
For the next two and a half years Provi-
dence litigated—it engaged in discovery,
presented cross-claims (trying to appeal
to this court from dismissal of some of
them), and filed various motions.” It
never brought up arbitration except to
ever executed.
deny Manhattan's assertion that it (Man-
hattan) had earlier sought arbitration
pursuant to the contract. In May (or
possibly April) 1973, Providence for the
first time asserted that Manhattan's sole
remedy was arbitration. In view of this
pattern of pre- and post-suit behavior,
Providence waived arbitration. Burton-
Dixie Corp. v. Timothy McCarthy Con-
struction Co., 436 F.2d 405, 408 09 (CA5
1971); Cornell & Co. v. Barber & Ross
Co., 123 U.S.App.D.C. 378, 360 F.2d 512
(1966).
On remand the district court should
find Manhattan's actual delay damages
arising from Providence’s mistakes on
the sewage ejection and bedlight fixture
problems.
B. Claims against McCauley
[17] Manhattan's claims in this re-
gard are similar to Ernst’s. Manhattan's
closer relationship to the architect makes
an even more persuusive case for its in-
clusion within the scope of the risk cre-
ated by the latter’s actions. Manhattan
may recover on remand for actual delay
damages arising from McCauley’s defec-
tive plans and specifications regarding
the generator system (if such be found
to constitute negligence) as well as the
architect’s procrastinations in ruling on
Fairbanks’ submittals for that system.
4@. Manhattan is not barred by failing to obtain
a “certificate of completion” pursuant to the
general conditions. Its appeal is concerned
not with obtaining final payment but rather
with securing delay damages in addition to
final payment. We note that McCauley did
give Manhattan a “certificate of acceptance,”
dated June 21, 1972, accepting the building as
complete in accordance with plans, specifica-
tions, and contract documents.
41. See part |, section E. supra.
27a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 3064
C. Claims against Ernst
{18} The district court was not clear-
ly erroneous in finding that although it
was “an extremely close question,” 387
F.Supp. at 1028, Manhattan did not
make out a case of fraud by Ernst re-
garding the generator submittals.
The court also found that Ernst know-
ingly installed the explosion-proof recep-
tacles in an improper and hazardous
manner and then concealed this danger
by using longer screws. But the court
did not rule on the question whether this
action constituted fraud under Alabama
law. Manhattan raised this issue
throughout the trial,“ and the district
court should make appropriate findings
and conclusions on remand.
Manhattan’s claims for damages
against Ernst on this receptacle matter
are complicated by a subcontract provi-
sion ® which the district court appears to
have referred to in passing“ but which
we cannot find in the record. On re-
mand the district court should make
findings on the existence of, and conclu-
sions on the interpretation of, this provi-
sion in the subcontract.
*
D. Claims against Fairbanks
{19} The district court found Fair-
banks guilty by clear and convincing evi-
dence of fraud in its representations con-
cerning the generator's ability to comply
with the specifications. It awarded
42. Record on Appeal 128!. Our reading of the
record does not reveal with certainty whether
the district court ever ruled on this claim with
finality. The court granted Ernst’s motion to
dismiss the claim on May 9, 1973, without
opinion. Id at 1366. But it would seem to be
included within the scope of the pretrial order
setting issues for trial, and it later became
subject to various motions by Manhattan. Id.
at 1625, 2064.
Manhattan $20,000 in punitive damages
for this fraud but did not grant compen-
satory damages, even though it found
that [tjhe other parties did rely upon
the misrepresentations with the result
that the project was delayed and sub-
stantial losses were incurred.” 387
F.Supp. at 1031. Alabama law allows
recovery of compensatory damages in
cases of statutory fraud. Ala.Code tit. 7,
$§ 107 et seg. (1960 Recomp.); Ringer v.
First National Bank, 291 Ala. 364, 281
So.2d 261 (1973). On remand, Manhat-
tan is entitled to recover actual damages
from Fairbanks if it can prove them.
E. Claim for prejudgment interest
120] Manhattan claims prejudgment
interest on any damage award that it
may receive. Alabama law governs any
award of interest, regardless of the ex-
istence of 28 U.S.C. § 1961. Degelos
Bros. Grain Corp. v. Fireman's Fund In-
surance Co., 498 F.2d 1238 (CA5 1974).
In Alabama only liquidated claims gener-
ally justify prejudgment interest. Grand
Bay Land Co. v. Simpson, 207 Ala. 303,
92 So. 789 (1922). The claims of Man-
hattan here are too uncertain in amount
to qualify under any of the recognized
exceptions to this rule. Roc v. Baggett
Transportation Co., 326 F. 20 298 (CA5
1963) (Alabama law); accord, Belcher !
Birmingham Trust National Bunk, 488
F.2d 474 (CA5 1973).
43. According to Ernst, this provision read
Limit of liability for delay in «ompletion on
part of E C Ernst, inc. shall be no greater
than the penalty as set up in the Owner's
contract.
Reply Brief for Ernst 40 n
44. See 387 F.Supp. at 1004 05 (finding 3).
1009, 1033 (finding 128).
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS 300
3065 E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEXAS
V. Manhattan liability for
liquidated damages
121] Manhattan claims that the dis-
trict court was clearly erroneous in find-
ing that it failed to coordinate work,
leading to liquidated damages for delay
to Providence. The only claim worthy of
discussion here is that a general “flat-
tening out” of work occurred after the
generator delays had set in. The district
court recognized this problem, 387
F.Supp. at 1027, but apparently found it
to be no excuse to a party whose respon-
sibility as general contractor included
eliminating the effect of such occurrenc-
es, and we agree.
VI. Providence’s claims
{22} We agree with the district court
that Providence’s claim for damages
from Fairbanks’ proven fraud could not
withstand a motion to dismiss. Provi-
dence has proven no damages other than
delay, and for this it already has been
compensated by Fairbanks (through
Manhattan). Providence now has a Cat-
erpillar- driven generator in place of the
Dorman-powered one that never materi-
alized. In addition, as noted above, the
district court’s refusal to find Ernst
guilty of fraud in connection with the
generator matter was not clearly errone-
ous.
VII. Summary
1. Ernst may not recover from Man-
hattan, because of the “no damage”
clause in their subcontract.
2. Ernst may not recover from Provi-
dence, since the Providence-Manhattan
contract evidences an intention not to
vest Ernst with third-party beneficiary
rights.
3. The liquidated damages assessed
against Fairbanks by the district court
did not include delays caused by defec-
tive specifications for the emergency
generator's engine housing. McCauley
was properly assessed responsibility for
this mistake.
4. Ernst may recover under a negli-
gence theory for McCauley’s procrastina-
tions in rejecting the Fairbanks emer-
gency generator units.
5. Ernst may recover under a negli-
gence theory for McCauley’s erroneous
rejection of Palco bedlight fixtures and
its defective plans and specifications if,
on remand, the district court finds that
these defects constitute negligence.
6. The district court's calculation of
$61,626.12 as the indemnity due Ernst
from Fairbanks for Ernst's upstream lia-
bility on the generator is correct.
7. Ernst may recover damages for
delays caused by Fairbanks’ breach of
contract.
8. The district court’s $20,000 award
of punitive damages from Fairbanks to
Manhattan was not an abuse of its dis-
cretion.
9. The district court's $20,000 award
of punitive damages from Fairbanks to
Ernst was not an abuse of its discretion.
However, the court should reduce this
figure on remand if it included some
amount compensating Ernst for its at-
torney's fees.
10. Ernst may recover attorney's fees
from Fairbanks based on their indemnity
agreement. However, this recovery
should be limited to amounts expended
on the generator litigation, excluding
suit against Fairbanks itself.
11. The district court did not err in
allowing apportioned liquidated damages
to Providence.
12. The district court did not err in
finding that Ernst was responsible for
delay arising from its installation of the
explosion-proof receptacles.
13. Manhattan may recover for its
actual delay damages arising from Provi-
dence’s mistakes on the sewage system
and Paleo bedlight fixture matters.
14. Like Ernst, Manhattan may re-
cover under a negligence theory for
McCauley’s procrastination in rejecting
the Fairbanks emergency generator
units.
15. Like Ernst, Manhattan may re-
cover under a negligence theory for
MeCauley's erroneous rejection of Palco
bedlight fixtures and its defective plans
and specifications if, on remand, the dis-
trict court finds that these defects con-
stitute negligence.
16. The district court did not err in
rejecting Manhattan’s and Providence's
claims of fraud by Ernst in counseling
Fairbanks on its generator submittals.
17. Manhattan's claim for actual de-
lay damages from Ernst on the explo-
sion-proof receptacles matter is remand-
ed for further consideration concerning
4 true copy
Tests E NN
Clerk, Ve 5 1
eo Se LN. “yt
dev Orleans, Louisiana
the existence and effect of a provision in
their subcontract. The district court
should also make an explicit finding re-
garding the existence of fraud on
Ernst's part in connection with the in-
stallation of the receptacles.
18. Manhattan may recover compen-
satory damages for Fairbanks’ fraud.
19. Manhattan may not recover pre-
judgment interest on any damage award
that it may receive.
20. The district court did not err in
assessing liquidated damages for delay
against Manhattan for its failure to co-
ordinate the work on the job site.
21. Providence has proven no dam-
ages for which it has not already been
compensated with respect to Fairbanks’
fraud.
22. On remand, Ernst and Manhat-
tan’s recoveries will be predicated on
their ability to show fact, amount, and
apportionment of damage with reasona-
ble certainty.
The district court's judgment is AF-
FIRMED in part, VACATED, in part,
and REMANDED for further proceed-
ings not inconsistent with this opinion.
+ geen 7
x:
Sp. ay
OCT 3 1977
Adm. Office, U.S. Courts—West Publishing Company, Saint Paul, Minn.
30a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
E. C. ERNST, INC., Plaintiff-Appellant
Appellee,
V.
MANHATTAN CONSTRUCTION COM-
PANY OF TEXAS, Providence Hospi-
tal, Fairbanks-Morse, Inc., Charles H.
McCauley Associates, Inc., Defend-
ants-Appellees Appellants.
No. 75-1794.
United States Court of Appeals,
Fifth Circuit.
Sept. 14, 1977.
In a complex diversity case, concern-
ing difficulties encountered during con-
struction and renovation of a hospital,
the parties appealed from a judgment
entered in the United States District
Court for the Southern District of Ala-
bama, at Mobile, Daniel H. Thomas, J.,
387 F.Supp. 1001. The Court of Appeals
affirmed in part, vacated in part and
remanded for further proceedings, 551
F.2d 1026. On petition for rehearing
and petition for rehearing en banc, the
Court of Appeals held that (1) a subcon-
tractor was entitled to profit that it
would have earned for installing a gen-
erator pursuant to contract, not the full
amount it would have charged the con-
tractor had there been no breach by sup-
plier, but profit on the installation job,
though only if amount of profit could be
shown with reasonable certainty; (2) ex-
tensive postsuit actions in all phases of
complex litigation served as a waiver of
the hospital's right to demand arbitra-
tion of grievances, and (3) where the
hospital was given opportunity to have
its fraud claim reinstated and considered
5796
during trial but elected not to avail itself
of the offer, the hospital was in no posi-
tion to complain of want of opportunity
to prove fraud damages.
Granted in part and denied in part;
petition for rehearing en bane denied.
I. Damages 117
Damages «warded for breach of con-
tract should return party to position he
would have occupied had contract not
been violated.
2. Damages 12403)
Subcontractor was entitled to profit
that it would have earned for installing
generator pursuant to contract, not full
amount it would have charged contractor
had there been no breach by supplier,
but profit on installation job, though
only if amount of profit could be shown
with reasonable certainty.
3. Arbitration 23.4
Extensive postsuit .actions in all
phases of complex litigation served as
waiver of party's right to demand arbi-
tration of grievances.
4. Federal Courts 714
Where landowner was given oppor-
tunity to have its fraud claim reinstated
and considered during trial but elected
not to avail itself of offer, landowner
was in no position to complain of want
of opportunity to prove fraud damages
Appeals from the United States Dis
trict Court for the Southern District o:
Alabama.
31
5797
ON PETITION FOR REHEARING
AND PETITION FOR REHEAR-
ING EN BANC
(Opinion May 9, 5 Cir., 1977, 551
F.2d 1026.)
Before GODBOLD, MeCREE and
TJOFLAT, Circuit Judges.
PER CURIAM:
Ernst, McCauley and Providence have
petitioned for a rehearing of numerous
aspects of our original opinion in this
case, 551 F.2d 1026 (CA5, 1977). We
modify that opinion in the following re-
gards.
1. Ernst challenges our agreement
with the district court's calculation of
damages due from Fairbanks for fraud
in connection with its generator contract,
551 F.2d at 1035, asserting that it was
shortchanged by 85.541, the amount that
it would have charged Manhattan for in-
stallation had Fairbanks actually sup-
plied the generator.
{1,2) By requiring Fairbanks to com-
pensate Ernst only for the amount Ernst
paid to Manhattan to make Manhattan
whole, we essentially returned Ernst to
its position prior to the contract (except
for its alleged delay damages, to be de-
termined on remand). This was wrong.
Damages awarded for breach of contract
should return the party to the position
he would have occupied had the contract
not been violated. Jewell v. Jackson &
Whitsitt Cotton Co., 331 So.2d 623, 625
26 (Ala.1976). Ernst should therefore be
entitled to the profit that it would have
earned for installing the generator, not
the full $5,541 that it would have
charged Manhattan but the profit on the
installation job. Of course, this recovery
will be predicated on ability to show the
Hon Wade H. McCree, Jr., of the Sixth Circuit,
now Solicitor General of the United States,
E. C. ERNST, INC. ». MANHATTAN CONST. CO. OF TEX.
amount with reasonable certainty. Paris
v. Buckner Feed Mill, Inc., 279 Ala. 148,
182 So.2d 880 (1966).
2. For the first time in this court,
McCauley raises the statute of limita-
tions as a bar to possible recovery by
Ernst and Manhattan for its negligence
in failing to rule on the acceptability of
the generator and for its alleged negli-
gence in drawing plans and in rejecting
Palco bedlight fixtures. McCauley as-
serts that it pleaded this affirmative de-
fense in the trial court. It cites no
pleading to substantiate this assertion,
and our search of the record reveals
none. Rather than engage in any fur-
ther search, we think it appropriate to
include the entire statute of limitations
question in the issues to be determined
upon remand of Ernst's and Manhattan's
negligence claims. Remand will also
give these parties an opportunity to re-
spond to the views first propounded here
by McCauley concerning the dates of ac-
crual and tolling of their various causes
of action.
{3} 3. Providence correctly points
out that the April 7, 1970, telephone call
by Providence’s attorney, threatening to
sue Manhattan if it attempted to arbi-
trate the generator matter, was made to
Alabama state officials and not, as we
said at 551 F.2d 1040, to Manhattan it-
self. However, this does not affect our
holding that Providence’s extensive post-
suit actions in all phases of this complex
litigation served as a waiver of its right
to demand that Manhattan arbitrate its
grievances concerning the sewage
ejection and bedlight fixture matters.
When one party reveals a disinclination
to resort to arbitration on any phase of
suit involving all parties, those partics
participated in the oral argument of this case
but did not participate in this decision.
32a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX. 5798
are prejudiced by being forced to bear
the expenses of a trial, which in this case
was quite lengthy. Arbitration is de-
signed to avoid this very expense. Sub-
stantially invoking the litigation machin-
ery qualifies as the kind of prejudice to
Manhattan that is the essence of waiver.
Burton-Dixie Corp. v. Timothy McCarthy
Construction Co., 436 F.2d 405, 408-09
(CA5, 1971); Cornell & Co. v. Barber &
Ross Co., 123 U.S.App.D.C. 378, 360 F.2d
512 (1966). See also Carolina Throwing
Co. „ S & E Novelty Corp., 442 F.2d 329
(CA4, 1971); Carcich v. Rederi A/B Nor-
die, 389 F.2d 692 (CA2, 1968).
[4] 4. Providence takes issue with
our statement that it “has proven no
damages other than delay” for Fair-
banks’ fraud in connection with the gen-
A “rane copy
erator matter, 551 F.2d at 1042. The
district court dismissed Providence's
fraud claim prior to trial, and Providence
points out it had no opportunity to prove
fraud damages. But Providence was
given an opportunity to have its fraud
claim reinstated and considered during
trial but elected not to avail itself of the
offer.
In all other respects, the petitions are
to be denied.
The petitions for rehearing are
GRANTED in part and DENIED ir
part. No member of this panel nor
judge in regular active service on the
court having requested that the court b.
polled on the petition for rehearing er
banc of Providence Hospital, the petitior
for rehearing en banc is DENIED.
cast: FDWARD N. 74° T7OSTH
; -ifth Circuit
cc l.a, L. 8. Cowyst D ;
a ee
Lever 3 1977
Sew Orleans, Louisiena
33a
E. C. ERNST, INC., Plaintiff,
V.
MANHATTAN CONSTRUCTION
COMPANY OF TEXAS
et al., Defendants,
v.
MANHATTAN CONSTRUCTION COM.
PANY OF TEXAS, Plaintiff
by Counterclaim,
v.
E. C. ERNST, INC., et al., Defendants
by Counterclaim.
Civ. A. No. 6340-70-T.
United States District Court,
S. D. Alabama, S. D.
Dec. 11, 1974.
An electrical subcontractor on a
hospital building project brought an ac-
tion against the hospital owner, archi-
tect, prime contractor and others seek-
ing a declaratory judgment and order
preventing the purchase and installation
of any substitute equipment in place of
an emergency generator which the sub-
contractor had proposed to install under
its contract with the prime contractor.
After final completion of the project,
and after parties to the action had filed
numerous cross claims and counter-
claims, the suit developed into one for ap-
portionment of responsibility for a con-
struction overrun of 453 duys. The Dis-
trict Court, Daniel Holcombe Thomas, J.,
34a
1002
entered numerous findings of fact and
conclusions of law concerning responsi-
bility for the overrun and damages pay-
able as a result thereof.
Order accordingly.
1. Federal Civil Proced ure 1938
Even though hospital made no for-
mal claim in its pleadings to recover liq-
uidated damages from prime contractor
and others involved in hospital construc-
tion contract, such damages were re-
coverable where issue of liquidated dam-
ages was framed by district court in its
pretrial order. Fed.Rules Civ.Proc. rule
15(b), 28 U.S.C.A.
2. Contracts ©300(1)
Where prime contractor under hos-
pital construction and renovation con-
tract experienced delay in obtaining ac-
cess to old operating room area of hospi-
tal because hospital was required to keep
area in operation until it could occupy
new operating area, hospital was re-
quired to extend construction deadline
accordingly and prime contractor was
not responsible for overrun resulting
from lack of access.
3. Contracts 300(3)
Where hospital and its architect
caused delay of 131 days in installation
of sewage system under hospital con-
struction contract because of failure to
decide promptly whether to use electric
sewage ejection pump or gravity system,
but some of such delay could have been
absorbed by prime contractor during re-
mainder of job, one-half of resulting
contract overrun would be charged
against hospital and subtracted from pe-
riod for which it would be paid liquidat-
ed damages under construction contract.
4. Damages 85
Where employees of electrical sub-
contractor under hospital construction
contract knowingly installed explosion-
proof receptacles in operating room of
hospital in unacceptable manner and
concealed their wrongdoing, subcontrac-
tor was liable to pay liquidated damages
387 FEDERAL SUPPLEMENT
for 108-day project overrun caused by
such actions.
5. Contracts 301, 312(1)
Hospital and its architect breached
hospital construction contract by failing
in timely manner to accept bed light fix-
tures which were admittedly equivalent
to those described in contract specifica-
tions, and each would therefore be held
responsible for one-half of 59-day project
overrun caused by resulting delay. Pub-
lic Health Service Act, § 600 et seq., 42
U.S.C.A. § 291 et seq.
6. Contracts 23
Where electrical subcontractor un-
der hospital construction contract failed
to provide emergency generator system
which complied with contract specifica-
tions and such system was instead pro-
vided by prime contractor at its own
cost, prime contractor was entitled to re-
duce amount due to subcontractor by en-
tire amount which it cost to obtain and
install emergency generator sytem.
7. Sales 418(7)
Where company which was to sup-
ply emergency generator system through
electrical subcontractor under hospital
construction contract failed to supply
system which met specifications of con-
tract, and system was instead procured
by prime contractor, subcontractor could
recover from supplier difference be-
tween purchase price of system as in-
curred by prime contractor and refunded
to it by subcontractor and price of sup-
plier’s proposed system, plus additional
installation costs incurred by prime con-
tractor and subcontractor.
8. Contracts 301
Where architect under hospital con-
struction contract prepared deficient
plans and specifications for emergency
generator to be installed in hospital and
failed to act properly and promptly on
proposal submitted for furnishing of
that equipment, and where proposed
supplier of generator unit concealed fact
that unit did not meet specifications of
contract, architect and supplier were |
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
Cite ax XT F.Supp. 1001 (1974)
each responsible for one-half of 161-day
project overrun occasioned by resulting
delay.
9. Fraud ©58(1)
Although proposed supplier of emer-
gency hospital generator unit under hos-
pital construction project engaged in
fraudulent conduct in misrepresenting
unit as complying with specifications of
contract, evidence faile’ ‘> establish
that electrical subcontractor, which was
responsible for obtaining unit, partici-
pated in such fraud.
10. Fraud ©=13(1), 61
Proposed supplier of emergency hos-
pital generator system under hospital
construction contract was guilty of
fraud in seeking to obtain approval of
proposed units by means of flagrant and
false representations, including repre-
sentations that units met specifications
of contract and false statements as to
quality and performance capabilities of
equipment, and supplier was therefore
liable to pay punitive damages both to
electrical subcontractor and prime con-
tractor.
11. Contracts $301
Prime contractor under hospital
construction proj was guilty of lack
of proper management of project in sev-
eral respects, including failure to pro-
vide additional manpower when request-
ed to do so by architect and required by
general conditions of construction con-
tract, and failure to schedule work prop-
erly, and 60 days of a 453-day overrun
on project would therefore be attributa-
ble to prime contractor’s failure to prop-
erly supervise and coordinate work.
12. Principal and Agent 159(1)
Architect is agent for owner in con-
struction project, and owner is responsi-
ble for any damages caused by archi-
tect’s deficiencies insofar as other par-
ties are affected thereby.
13. Damages 85
Where, although no _ contractual
agreement existed between architect and
owner concerning liquidated damages
which might arise from delay of comple-
tion of hospital construction project at-
tributable to fault of architect, architect
itself hed been instrumental in inclusion
vision in construction contract, such rate
of liquidated damages would be utilized
in awarding damages to owner for de-
lays in completion of project caused by
architect.
14. Contracts 290
Where hospital at no time sought to
begin arbitration of disputes arising un-
der hospital construction contract and in
fact threatened to prevent arbitration by
filing lawsuit, hospital’s actions consti-
tuted waiver of arbitration provisions of
contract, and litigation arising under
contract would therefore not be dis-
missed for failure to arbitrate.
15. Federal Civil Procedure 2737.5
Where all parties involved in dis-
pute over responsibility for overrun in
hospital construction contract were to
some extent at fault, all parties had op-
portunity to settle action but chose to
litigate, and each party defended only
its own interests and asserted only its
own claims and defenses, each party-liti-
gant would bear its own attorneys fees
and expenses.
16. Damages ©80(2)
Provision in hospital construction
contract for payment by prime contrac
tor to hospital of sum of $250 per day
for each day that completion of project
was delayed beyond date specified in
contract was reasonable and binding
upon hospital and prime contractor.
17. Damages 88
Where hospital, either itself or
through its architect, was chargeable
with 163 days of 453-day overrun on
project, it could not recover liquidated
damages from prime contractor for such
portion of overrun.
18. Contracts C290
Litigant cannot fail to invoke per-
missive arbitration provisions of con-
tract and then attempt to advance such
failure as defense to claims aaserted
against it.
19. Limitation of Actions © 100(1)
Where more flagrant facets of
fraud of proposed supplier of emergency
generating equipment for hospital con-
struction project were revealed in dis-
covery within only months prior to com-
mencement of hearing on litigation con-
cerning parties’ responsibility for delay
in project, claims for punitive damages
against supplier on grounds of such
fraud were not barred by one-year stat-
ute of limitations.
20. Fraud 81
When misrepresentation and fraud
have been established by clear, cogent
and convincing evidence, it is appropriate
and proper for court to award not only
actual damage caused thereby, but also
punitive damages in appropriate
amount.
ee
Willis C. Darby, Jr., Mobile, Ala., for
Providence Hospital.
Glower W. Jones, Smith, Currie &
Hancock, Atlanta, Ga., Edward S. Sledge,
III. Gallalee, Denniston 4 Edington,
Mobile, Ala, Arthur Friedman, Tanner
& Friedman, New York City, for E. C.
Ernst, Inc.
David M. Thornton, Thornton &
Stamper, Tulsa, Okl., for Manhattan
Const. Co. of Texas.
Maurice Bishop, Bishop & Carlton,
Clarence L. McDorman, Jr., London,
Yancey, Clark & Allen, Birmingham,
Ala., for Charles H. McCauley Asso-
ciates, Inc.
Louis E. Braswell, Hand,
Bedsole, Greaves & Johnston,
Ala., for Fairbanks-Morse, Inc.
Arendall,
Mobile,
FINDINGS OF FACT AND CONCLU-
SIONS OF LAW
DANIEL HOLCOMBE THOMAS,
District Judge.
HISTORY OF CASE
1. This proceeding should serve for
years to come as a classic example of the
|. Ernst had also submitted bids to several of
the geveral contractors bidding on the job,
economic futility of litigation of this na-
ture and the need for settlement of such
controversies.
2. In 1967, Providence Hospital of
Mobile ( Providence), a Catholic hospital
operated by the Sisters of Charity, de-
cided to substantially expand its facili-
ties and to renovate and remode! its ex-
isting buildings. Providence obtained a
Hill-Burton Federal Grant in the
amount of $1,000,000.00. On October
27, 1967, Providence entered into a
standard form architectural contract
with Charles H. McCauley Associates,
inc. (McCauley), a large architectural
firm in Alabama with wide experience
in hospital construction. Pursuant to
this contract, McCauley prepared plans,
specifications and contract documents.
On April 12, 1968, McCauley advertised
the job for bids to be received until July
18, 1968. Seven contractors submitted
bids. On July 29, 1968, the contract was
let by Providence to Manhattan Con-
struction Company of Texas ( Manhat-
tan) for a total contract price of
$6,117,500.00. Manhattan entered into a
subcontract with E. C. Ernst, Inc.
(Ernst) under which Ernst agreed to
furnish the materials and equipment and
perform all of the electrical work for a
cost of $982,215.00.' Under this subcon-
tract, Ernst was required to provide
emergency generators which it later con-
tracted to purchase from Fairbanks-
Morse, Inc. (Fairbanks-Morse), a fifth
party to this litigation.
3. The contract between Manhattan
and Providence incorporated the plans
and specifications prepared by McCauley
and provided that Manhattan was re-
quired to complete the project within
730 days. If the project was not com-
pleted within this specified period and
any granted extensions of time, Manhat-
tan agreed to pay liquidated damages of
$250.00 per day until completion. The
subcontract between Manhattan and
Ernst provided the same time schedule
and liquidated damages plus an indemni-
but submitted its lowest proposal to Manhat-
tan.
37a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
1005
Cite as M F Supp. 1001 (1974)
fication agreement from Ernst to Man-
hattan.
4. The order to proceed was issued
August 19, 1968. Therefore, the origi-
nal completion date was August 18,
1970. During the period of construc-
tion, the time was extended by appropri-
ate change orders for 185 days. Accord-
ingly, the revised completion date was
February 19, 1971. The job was accept-
ed on May 17, 1972, making an overrun
of 453 days.
5. This extended litigation was com-
menced on August 28, 1970, by Ernst fil-
ing a complaint against all other parties
seeking a declaratory judgment and or-
der “preventing the purchase and instal-
lation of any substitute equipment” in
place of the Fairbanks-Morse emergency
generator, with engines, which Ernst
had proposed to install under its con-
tract with Manhattan. The Court set
the matter for hearing on January 27,
1971, on the sole issue of the sufficiency
of the Fairbanks-Morse emergency gen-
erator system. Hearing on this issue
was concluded on February 4, 1971, when
this Court issued an order specifically
finding that:
“The emergency generator system
(proposed to be furnished) does not
meet the requirements of the specifi-
cations”,
and that:
“The Dorman engines proposed by
Fairbanks-Morse to power the emer-
gency generator system do not fulfill
the horsepower requirements of the
specifications.
“The Court finds from the evidence
that the material submitted to Mc-
Cauley by Fairbanks-Morse, Ernst
and Manhattan, or any one or more of
them, failed to establish that the
emergency generator system proposed
to be supplied by Fairbanks-Morse,
met the requirements of the
specifications.” *
2. The Court's Findings of Fact and Conciu-
sions of Law on this generator feature are
6. This suit triggered a long plead-
ing war with a series of amendments,
cross-claims, counterclaims, and motions,
bearing little resemblance to the original
complaint and resulting in many issues
between and among the parties.
7. On April 11, 1973, this matter was
set down for pretrial, and the attorneys
were instructed to have present at the
pretrial, a representative of each litigant
who had authority to negotiate settle-
ment of this matter. Besides all attor-
neys being present, the litigants were
represented as follows: Ernst, by a Vice
President; Fairbanks-Morse, by e direc-
tor; McCauley, by its liability carrier;
Manhattan, by a Vice President; Provi-
dence, by its Administrator. At the
commencement of the pretrial, the Court
made the following statement:
“Gentlemen, this is a case which should
be settled between the parties. In
present day thinking, it seems to be the
idea that any problem can be cured in a
Federal District Court. This, I assure
you, is an erroneous approach. There is
not a lawyer in this courtroom capable
of operating the Providence Hospital.
There is not a lawyer in this courtroom
capable of running Manhattan Construc-
tion Company; there is not a lawyer in
this room capable of running McCauley
Associates; nor a lawyer in this room
capable of running Fairbanks-Morse;
nor a lawyer capable of running Ernst,
and I assure you there is not a Judge in
this courtroom capable of doing so. All
of you litigants are successful operators
or you would not be participating in a
six million dollar contract. Lawyers in
their zeal to represent their clients many
times fail to see but one side of the liti-
gation and that is the side of his client.
This litigation is not a one-sided bit of
litigation, it is a five-sided bit of litiga-
tion.
I stated at the outset that this was a
case that should be settled between the
hereto attached and made a pert hereof as
Exhibit 1.
1006
patios. I said that because this is a
classic example where the cost of proper
preparation of the case for trial is com-
pletely disproportionate to the benefits
any of the parties could hope to derive.
You’all are represented by capable attor-
neys. None of the attorneys want to go
to trial in this case unless and until they
have properly and thoroughly prepared
their case for trial. This entails much
pretrial discovery and pretrial discovery
entails much lawyer time, much travel,
much hotel expense. The point is, it is
extremely expensive.
Not only does this continued litigation
require discovery expenses, it entails ex-
penses in the appellate court. This case
is already no stranger to the Fifth Cir-
cuit nor the U. S. Supreme Court. Yes,
litigation is expensive, but remember the
courts do not create litigation, it is cre-
ated by the litigants. I have asked that
you representatives of the litigants be
here today. Although I know you have
been kept abreast of this litigation by
your attorneys, I wanted you to hear di-
rectly from the trial judge his thoughts
on this matter. You litigants are in a
fairly closely related field. Being
trained in this field, you are in a far bet-
ter position to adjust your differences
than those untrained in these related
fields. As an illustration, I, who have
had no training whatsoever in engineer-
ing, had to determine whether or not the
emergency generator system proposed to
be furnished by Fairbanks-Morse, met
the specifications, when experts couldn't
agree. That is a strange bit of logic.
If this case is not settled quickly, it is
going to trial quickly, properly prepared
or otherwise. To try this case will prob-
ably take not only days, but weeks, and I
wish to state to all of you litigants and
all attorneys here and now, if this case
is not settled, it will be tried during the
month of August, 1973, and it will take
the precedence over vacations or any
other business conflict.
The object of litigation is to do sub-
stantial justice between the parties liti-
gant, but the parties litigant should re-
387 FEDERAL SUPPLEMENT
alize that, in most situations, they are
by their particular training better able
to accomplish this among themselves.
This is your court, it is the peoples’
court. It is properly staffed and ready,
willing and able to try this case and will
do so in August.
Regardless of the outcome, an appeal
is almost certain. This will entail more
expense and more delay.
Having thusly expressed myself, we
will now proceed with the pretrial of
this case. I will ask you representatives
of the litigants to remain throughout
this pretrial as your presente will most
likely be helpful.”
8. The case was not settled, and the
trial was commenced on August 6, 1973.
It entailed 40 days of court time, 41 wit-
nesses (34 live and 7 by deposition) and
1056 exhibits. Presentation of the evi-
dence was finally concluded on Novem-
ber 27, 1973. Thereafter, the litigants
were given until the 28th day of Janu-
ary, 1974, within which to file Findings
of Fact and Conclusions of Law. This
time was extended to February 11, 1974.
The Court after studying these Findings
and Conclusions set the matter for final
argument on May 22, 1974, each litigant
being given one hour’s time. The pre-
trial order entered in this case on the
26th day of April 1973, and amended on
the 6th day of July 1973, is attached
hereto and made a part of this Finding
hereof as Exhibit 2. As stated above,
portions of this case have already been
before the Fifth Circuit and the Su-
preme Court. Docket numbers 72-3073
and 73-1287, Fifth Circuit and A-129,
Supreme Court. Each contains a part
of the history of this litigation.
9. PARTIES—The following parties
are litigants in this action: Plaintiff, E.
C. Ernst, Inc. (Ernst), is a corporation
incorporated under the laws of the Dis-
trict of Columbia and has its principal
place of business in the District of Col-
umbia. Defendant Manhattan Construc-
tion Company of Texas (Manhattan) is
a corporation incorporated under the
laws of the State of Texas and has its |
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
1007
Cite as 387 F Supp. 1001 (1974)
principal place of business in the State
of Texas. Defendant Fairbanks-Morse,
Inc. (Fairbanks-Morse) is a corporation
incorporated under the laws of the State
of Delaware and has its principal place of
business in the State of Wisconsin. De-
fendant Providence Hospital (Provi-
dence) is a corporation incorporated un-
der the laws of the State of Alabama.
Defendant Charles H. McCauley Asso-
ciates, Inc. (McCauley) is a corporation
incorporated under the laws of the State
of Alabama and has its principal place
of business in the State of Alabama.
10. DESIGNATION OF BUILD-
INGS—In the plans and specifications
and in the testimony of witnesses, vari-
ous portions of the construction project
are referred to by separate building des-
ignations, although all of the work was
inter-related and not separable into inde-
pendent units. The project upon com-
pletion was a single integrated struc-
ture. The structure as it existed prior
to commencement of the new construc-
tion or remodeling was referred to as the
“existing building”. The newly con-
structed six floor addition was referred
to as “Building A” and consisted princi-
pally of patient rooms, operating suites,
x-ray facilities and treatment rooms. A
new single story addition with basement
was added to the front of the existing
building and was referred to as “Build-
ing B“. It contained principally admin-
istrative spaces, entrance lobby, and rec-
ords library (Tr. 2119). The kitchen
and cafeteria of the existing building
were expanded by another one story ad-
dition referred to as “Building C“. (PX
14A)
11. CLAIMS—The matter in contro-
versy exceeds, exclusive of interests and
costs, the sum of Ten Thousand Dollars
($10,000.00). The following claims are
asserted by the different parties:
A. ERNST AGAINST MANHAT-
TAN—Ernst seeks damages against
Manhattan for delays and disruptions
3. The following abbreviations are used
throughout this opinion: Tr., Transcript of
Trial; EX, Ernst Exhibit; PX, Providence
caused by Manhattan's breach of its ob-
ligations to do the following: To pro-
vide accurate plans, drawings and speci-
fications for the project; to complete all
preliminary work necessary in order to
allow Ernst to perform its work; to co-
ordinate the work of and among the var-
ious subcontractors; to make or obtain
prompt decisions on all questions requir-
ing an answer from the owner, architect
or general contractor; to supply
promptly information required from the
owner, architect or general contractor;
to act promptly and dispositively, or to
procure others to so act, upon all re-
quests for approval of material and
equipment; to make available to Ernst
in timely fashion the specific areas nec-
essary for the performance of each part
of Ernst’s work; to coordinate the work
performed by Manhattan and other sub-
contractors so as to prevent any inter-
ference with the timely performance
of Ernst's work; to promptiy make, is-
sue or procure understandable and feasi-
ble clarifications of specifications, draw-
ings or plans, and to issue promptly any
directions necessitated thereby; and to
do all things necessary to be done in or-
der to complete, or to permit the comple-
tion of, the project within the time
frame specified therefor. In addition to
the above, Ernst claims a balance of 36.
252.60 due from Manhattan under the
contract. Finally, Ernst asserts that a
novation was agreed to among Manhat-
tan and Tube-O-Matic, Inc., one of Man-
hattan’s subcontractors, whereby Man-
hattan was directed in writing to pay
Ernst a sum of money on account of
work done by Ernst in fulfillment of
Tube-O-Matic's obligations on the proj-
ect.
B. ERNST AGAINST FAIR-
BANKS-MORSE—Enrnst claims damages
against Fairbanks-Morse for breach of
its obligations under their contract for
the procurement of an acceptable emer-
gency generator system. Manhattan has
Exhibit; Mex. McCauley Exhibit; MX.
Manhattan Exhibit and FX, Feirbanks-
Morse Exhibit.
40a
1008
withheld from Ernst funds due it total-
ling $143,293.65 on account of claimed
costs to Manhattan in furnishing, in lieu
of the Fairbanks-Morse system, an
emergency generator system which com-
plied with the plans and specifications.
Ernst therefore claims damages in an
amount, plus interest, equal to all or any
portion of such back charges which are
sustained as proper by this court and
which are in excess of $83,740.00, such
latter sum being the contract price to
Ernst for the Fairbanks-Morse system.
If all back charges are sustained, then
the damages sought by Ernst hereunder
would be $59,553.65 plus interest. Ernst
also seeks general damages for any loss-
es it has sustained which are attributa-
ble to delays or disruptions caused by
Fairbanks-Morse’s attempt to supply
and have accepted its non-complying
emergency generator system. In addi-
tion, Ernst claims that Fairbanks-Morse
is obligated pursuant to their contract to
indemnify Ernst against any losses for
which Ernst is held liable and which re-
sulted from Fairbanks-Morse's failure to
furnish timely a complying emergency
generator, said indemnification to in-
clude all of Ernst’s legal fees and expens-
es in this action. Finally, Ernst claims
punitive and compensatory damages
against Fairbanks-Morse for wilfully
and knowingly making fraudulent mis-
representations to Ernst relating to its
generator’s compliance with all specifi-
cations of the Contract Document and
Ernst’s own purchase order, Ernst hav-
ing relied upon such misrepresentationr:
Ernst asserts that such misrepresenia-
tions regarded, among other matters,
horsepower ratings and merchantability,
the latter despite the used, failed, re-
built and cannibalized condition of the
generators supplied by Fairbanks-Morse.
C. ERNST AGAINST PROVI-
DENCE—As a third-party beneficiary of
the contract between Providence and
Manhattan, Ernst claims damages
against Providence for delays and costs
of court caused by Providence’s breach
of its contract to do the following: to
supply plans, drawings and specifica-
387 FEDERAL SUPPLEMENT
tions for the project which correctly and
completely depicted the work to be per-
formed and which were feasible for the
accomplishment of the work; to prompt-
ly supply such information as was re-
quired from it in the course of the per-
formance of the work; te promptly is-
sue such clarifications as were required
from it in the course of the performance
of the work; to act promptly upon nec-
essary approvals of material or equip-
ment to be used in the course of per-
formance of the work; and to promptly
do all things required in order to enable
all persons, including Ernst, timely and
in an orderly manner to perform their
obligations under their contracts and
subcontracts within the time frame spec-
ified therein.
D. ERNST AGAINST McCAULEY
As a contractee with McCauley in con-
nection with the procurement of the
plans and specifications, Ernst claims
damages against McCauley for breach of
its warranty that the plans and specifi-
cations were in all respects accurate,
complete and sufficient so as to allow
proper evaluation of work to be done un-
der the contract. Ernst asserts that
McCauley’s breach of its warranty
caused delays and disruptions in the
supply of equipment and materials and
ultimately in the completion of the proj-
ect. As third-party beneficiary of the
contract between Providence and Mc-
Cauley, Ernst claims damages against
McCauley for failure to provide plans
and specifications suitable for determin-
ing the scope and cost of work to be per-
formed and for feasible construction;
for failure to timely effect necessary
clarifications, corrections and changes in
the plans and specifications; and for
failure to promptly act upon submittals
of data, samples and the like which were
required to be submitted to the archi-
tect.
E. MANHATTAN AGAINST
PROVIDENCE—Manhattan initially
claimed that a balance of $334,473.79
was due it under its contract with Prov-
idence. On July 27, 1973, the Court or-
dered Providence to make a payment of
4la
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
1009
Cite ax 387 F.Supp. 1001 (1974)
$211,475.00, thus reducing the balance
due to $123,000.00. In addition, Man-
hattan claims damages against Provi-
dence for intentional interference with
Manhattan’s timely performance of the
contract by failing to deliver portions of
the “existing building” for renovation
and by employing incompetent agents
and representatives. Manhattan claims
further damages for improper process-
ing of submittals, improper handling of
the patient bed light fixtures selection
and installation, and improper handling
of the emergency generator selection
and installation.
F. MANHATTAN AGAINST Me—
CAULEY—Manhattan seeks damages
against McCauley for failure to perform
general contractual duties, for failure
to properly process submittals, jor fail-
ure to handle properly the bed light fix-
tures selection and installation and for
failure to handle properly the emergency
generator selection and installation.
G. MANHATTAN AGAINST
ERNST—Manhattan seeks indemnifica-
tion from Ernst as to any liquidated
damages for which Manhattan is deemed
liable to Providence and for recoveries
against Manhattan by any cross-claim-
ant or plaintiff. Manhattan also seeks
damages based on contract and fraud
theories relating to the furnishing of
the patient bed light fixtures, the explo-
sion-proof receptacles, the wiring and
the emergency generator. Manhattan
alleges that Ernst and Fairbanks-Morse,
jointly and independently beginning in
October 1968, represented to Manhattan
that the Fairbanks-Morse generator sys-
tem met the required specifications, that
said representations were made knowing
them to be false and that Manhattan re-
lied on the misrepresentations to its det-
riment. Manhattan alleges a conspiracy
to defraud it by Ernst and Fairbanks-
Morse and seeks punitive damages
against Ernst for its fraud.
H. MANHATTAN AGAINST
FAIRBANKS-MORSE — Manhattan
seeks damages against Fairbanks-Morse
based on contract and fraud theories re-
387 F
lating to the furnishing of the emergen-
cy generator. Manhattan also seeks pu-
nitive damages against Fairbanks-
Morse.
II] I. CLAIMS BY PROVIDENCE
—Providence has no formal claim for
liquidated damages. However, this issue
was framed by the Court in its pretrial
order. Rule 150b) provides that,
(hen issues not raised by the plead-
ings are tried by the express or implied
consent of the parties, they shall be
treated in all respects as if they had
been raised in the pleadings.“ Provi-
dence has also pleaded over against
McCauley for indemnification as to any
liability Providence might have on the
various claims asserted by Manhattan
against Providence.
12. McCauley and Fairbanks-Morse
make no claims against any of the other
litigants. Their sole position being de-
fensive.
13. The pleadings as framed are
more the product of fertile legal minds
that they are definitive of the real is-
sues involved in the law suit. Every
conceivable issue was raised even though
many would have no effect on the out-
come of the case. The real issues are:
a. What was the actual number of
days of overrun for which liquidated
damages are to be assessed, and who
was responsible therefor?
b. Did the question of whether or
not to use a sewage ejector pump or a
gravity system cause any delay in the
completion of the entire contract?
e. Did the installation of the explo-
sive proof receptacles in the new operat-
ing rooms cause any delay in the ulti-
mate completion of the job?
d. Did the decision as to what pa-
tient room light fixtures would be used
cause any delay in the ultimate comple-
tion of the job?
e. Did the problems in selection and
installation of the emergency generator
system cause any delay in ultimate com-
pletion of the job?
42a
387 FEDERAL SUPPLEMENT
1010
t. Did Ernst's activities during the
selection and installation of the emer-
gency generator constitute fraud?
g. Was Fairbanks-Morse guilty of
fraud in regards to the emergency gen-
erator system?
h. Did the method in which the hos-
pital released space in the old building
to Manhattan cause any delay in the ul-
timate completion of the job?
i. Did Manhattan fail in its duty to
supervise and coordinate the work, and,
if so, did it delay the ultimate comple-
tion of the job? |
j. Is Providence entitled to a judg-
ment over against McCauley?
FINDINGS OF FACT
The Issue of Liquidated Damages
14. The claim of Providence, raised
sua sponte by the Court, for liquidated
damages under its construction contract
creates several factual issues, primary
of which is the period of time for which
these damages should be applied. This
question is resolved by determining the
number of days for which extensions
were granted or should have been grant-
ed beyond the scheduled completion date
of August 18, 1970. The number of
days for which extensions were ap-
proved, or should have been approved,
should be subtracted from the 638 days
between August 18, 1970, and May 17,
1972, when the project was conditionally
accepted. Another question relates to
the extent, if any. that Providence may
have been responsible for delays which
caused the project to extend beyond its
scheduled completion date.
{2} 15. There was a dispute with
respect to a request by Manhattan for
an extension of time for 39 days. Man-
hattan contended that it experienced
that much delay in obtaining access to
the old operating room area, which had
necessarily been kept in operation until
occupancy of the new operating area.
(EX-492. 493) By letter of April 27,
1972, McCauley had recommended ap-
proval of the request to Providence.
(EX-493) On April 28, 1973, Providence
first denied the request (EX-494), but
then, by letter of May 10, 1972, it ad-
vised that it would grant the extension
of 39 calendar days. (EX-495) On
May 18, 1972, Providence changed its
position and directed McCauley to disre-
gard its approval letter of May 10, 1972,
and to deny the requested extension
(EX-494) The Court finds that the ex-
tension requested should have been, and
was, approved by Providence and there-
fore allows it in the computation herein.
16. Additional extensions of time
were requested and denied. These re-
quests were properly denied and will be
considered in connection with the discus-
sion of the portion of the work to which
they were related. The extensions prop-
erly granted and due to be deducted
from the 638 total days overrun com-
prise 185 days which total includes the
disputed 39 days discussed above and ex-
tensions granted in connection with
Change Orders i-12, inclusive. There
should also be deducted 65 days for
which Providence was responsible in re-
gard to the sewage ejector pump and
2914 days in regard to the bed light
fixtures, as are hereinafter discussed.
In addition, for the purpose of comput-
ing liquidated damages, there must be
deducted from the total overrun the de-
lays caused by McCauley, it being Provi-
dence’s agent, which were 2942 days in
regard to the bed light fixtures and 80!
days in regard to the emergency gen-
erator, also hereinafter discussed. Ac-
cordingly, the overrun for which liqui-
dated damages are due is 2482 days
for a total of $62,125.00 in damages, the
contract providing for liquidated dam-
ages of $250.00 per day.
17. The more difficult age 4 —
confronting this Court is how the blame
for this overrun should be assessed
among the parties and what effect this
will have on the right of Providence to
recover the liquidated damages sought.
From the foundation to the finish work
there were multiple difficulties, many of
which should have been anticipated in a
job of this magnitude involving new con-
43a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
1011
Cite as 387 F.Supp. 1001 (1974)
struction and the remodeling of hospital
facilities where sick patients had to be
treated, operations performed, and hos-
pital functions continued without inter-
ruption.
18. In summary form, to be further
detailed in connection with the more
specific issues to follow, the progress
was substantially as follows: In 1968
and early 1969, foundations for the addi-
tions to the existing hospital (Buildings
A and B) were being laid. Inclement
weather and the necessity for some un-
expected work on the pilings on which
the foundation would rest (for which all
extensions requested were granted) put
the project behind schedule. Manhattan
prepared a bar chart showing anticipat-
ed commencement and completion dates
for cataloged portions of the job, but ad-
mittedly abandoned the chart during the
early parts of the project. There is tes-
timony that there was a period of prog-
ress during the time that Building A
was being raised to its full six stories,
but there were difficulties regarding
certain materials and equipment to be
installed, specifically the emergency gen-
erator system, bed light fixtures, and
deficiencies discovered in the explosion-
proof receptacles. Delays involving
these items will be discussed in more de-
tail. In 1970 work continued on the new
building. Building B was completed in
November 1970, and the renovation work
begun in the non-patient areas of the ex-
isting building. By Janury 1971, Build-
ing A had reached a point in its con-
struction where it could have promptly
been made ready for patient occupancy
if the emergency generators had been
available. Apparently, Manhattan and
its subcontractors did not push to com-
plete the building during the winter of
1970-1971. After the emergency gener-
ator arrived and was installed, Building
A was occupied by patients from the ex-
isting building, and portions of the ex-
isting building were turned over from
time to time, by Providence to Manhat-
tan for renovation.
19. On May 3, 1971, it was discov-
ered that the explosion-proof receptacles
(FX-115, p. 328) which were required
in the new operating rooms in Building
A had been defectively and dangerously
installed, thereby delaying occupancy un-
til the defects could be corrected. This
meant that Providence had to continue
to use the operating rooms in the exist-
ing building which to some extent dis-
rupted Manhattan’s renovation of the
existing building. There were further
problems with the emergency generator,
but the work continued through May
1972, in connection with renovations in
the existing building.
20. The various witnesses at the trial
attempted to allocate periods of delay
which prolonged the ultimate completion
of the project. However, the Court
finds it impossible to affix periods of
delay with any degree of accuracy, ex-
cept with respect to the emergency gen-
erator, the explosion-proof receptacles
and the bedlight fixtures. There is
some evidence that Providence delayed
completion of the project through a lack
of coordination in turning over parts of
the existing building to Manhattan.
There is other evidence that Providence
was conscientious in providing access to
the existing building but necessarily was
at times delayed in view of the recog-
nized commitment to keep the hospital
operational. It is apparent that Manhat-
tan and Ernst underestimated the diffi-
culties inherent in this renovation under
the contract conditions.
21. Representatives of the various
parties attempted to assess the responsi-
bility for delay on others than them-
selves. Every witness testified that
there was some overlap with respect to
the delays experienced and the cause
therefor. They further testified that
the delays were due to various causes, as
to a portion of which some defendants
admittedly could not be held responsible.
Sewage Ejection Pump
{3] 22. The plans and specifica-
tions for the project provided for the
sewage outflow line serving the hospit '
to be placed underground beneath the
44a
1012
floor of the Building B addition. An
electric sewage ejection pump was to be
installed for the purpose of lifting or
pumping the sewage up to the level at
which it could be discharged into the
municipal sewer lines. By November
1968, Manhattan had completed the ex-
cavation for the basement of Building B
(an area approximately two hundred
feet by fifty feet by ten feet deep) and
the reinforcing steel for the pilings and
had in place the pile caps, the walls and
the underground piping. Manhattan
was now ready to pour the basement
floor. At this time, McCauley directed
that the pouring be held up. The build-
ing engineer for Providence had belated-
ly realized that, by running the sewage
line through the basement rather than
under the floor, the sewage could be
made to flow out of the hospital by
gravity and that the need for the ejec-
tion pump could be eliminated along
with its resulting cost and operating and
maintenance expense. (PX 3, Tr.
2116-2123)
23. On November 14, 1968, Manhat-
tan was requested by McCauley to pro-
pose a change in the contract price for
eliminating the pump and changing the
sewage line to a gravity flow system.
Had the gravity flow arrangement been
originally designed by McCauley, it
would have been less expensive than the
underground pipe and pump system.
However, the work had progressed so
far at the time the change was proposed
that it would then have cost more to
change the design to a gravity-flow line
than it would have cost to proceed with
installation of the pump. Manhattan
and its plumbing subcontractor submit-
ted to McCauley a proposal for the
change on December 11, 1968. That
proposal was disapproved for the reason
that it did not coincide with an estimate
made by one of McCauley’s consulting
engineers. The proposal was resubmit-
ted on February 21, 1969. Manhattan
was notified on March 25, 1969, that the
proposal was rejected. Manhattan was
then permitted to resume its work and
387 FEDERAL SUPPLEMENT
to install the pump as originally de-
signed. (MX 244, Tr. 2116-2123)
24. Installation of the sewage ejec-
tion pump system was stopped on No-
vember 14, 1968, and resumed again on
March 25, 1969. Thus, there was a de-
lay of some 131 days in the installation
of the sewage system. Manhattan re-
quested an extension on its contract of
131 days because of this delay, but its
request was denied by the architect. At
trial, Manhattan insisted that it was en-
titled to this extension. Fairbanks-
Morse joined Manhattan in this position.
Ernst also insisted at trial that it was
entitled to an extension of 131 days with
the delay being attributed to Providence
and McCauley. Both McCauley and
Providence argued that the extension
was properly denied.
25. It is true that there was a delay
of 131 days in the installation of the
sewage system and that this particular
delay resulted from the failure of Provi-
dence and McCauley to decide promptly
which sewage system would be used.
However, the Court does not find that
this delay caused a corresponding delay
of 131 days in the completion of the
project as a whole. According to his
testimony (EX 244), Manhattan’s own
Vice President, Mr. Roberts, originally
had felt that this 131 days could have
been absorbed within the contract’s time
limit for the job. Although Mr. Roberts
later changed his mind, the Court shares
his original thoughts to the extent that
with proper supervision and coordination
by Manhattan and McCauley, this entire
time could have been absorbed. How-
ever, the fact is that it was not ab-
sorbed. Providence is the one who orig-
inally came up with the idea of the
gravity system, and this caused the stop-
page of this phase of the work. While
it is impossible to determine to a cer-
tainty the number of days delay which
this problem caused in the ultimate com-
pletion of the job, suffice it to say that
such delay, as there was, was caused by
Providence. The Court feels therefore
that one-half of this 131 days is as accu-
45a
E. C. ERNST, INC. v. MANHATTAN CONST. CO. OF TEX.
1013
Cite ax 387 F.Supp. 1001 (1974)
rate an estimate as can be made of the
actual resulting delay, that 65 days of
delay should be charged against Provi-
dence and that Providence should not be
paid liquidated damages for that period.
Explosion-Proof Receptacles
{[4] 26. The specifications provided,
in part:
“Receptacles:
“Explosion-proof receptacles in oper-
ating rooms and hazardous area shall
be flush mounted, 125 volt, 20 amps, 3
pole (grounding) with armored cord
grip plug for each receptacle, polished
chrome finish, Hubbell No. 24309 and
No. 24312 cap.” (PX 3, pg. 18-26;
Tr. 499)
“Type of Installation:
(e) All work installed in Operating,
Delivery and Emergency Rooms and
areas containing combustible anesthet-
ics shall be in accordance with re-
quirements of the National Electric
Code for Class I Group C installation
of all equipment within five feet of
the floor. Other equipment in areas
shall comply with N.F.D.A. No. 56.”
(PX 3, p. 18-6; Tr. 499)
“Standards of Materials and Work-
manship:
“All materials shall be new and shall
be listed as approved by the Under-
writers’ Laboratories, Inc., in every
case where a standard has been estab-
lished for the particular type of mate-
rial in question. All work shall be ex-
ecuted in a workmanlike manner and
shall present a neat and mechanical
appearance when completed.” (PX 3,
pg. 18-3)
27. An explosive-proof receptacle, of
the type involved in this litigation, is a
device consisting of three principal
parts. The largest part is a heavy cast-
steel, cube-shaped box fitted with screw-
out plugs for attachment to electrical
conduits at various points. The box is
hollow, and one side has a threaded
opening three inches in diameter. Into
this threaded opening is screwed a cast-
steel collar, the threaded portion of
which is approximately 1½ inches long.
On the outer end of the collar is a
flange plate 4', inches in diameter and
1, inch thick. The outer face is ma-
chined perfectly flat, and it has four
threaded holes for the attachment of the
third part. The third part of the device
has a heavy cast-steel face plate, the out-
er face of which is chrome plated and
the inner face is machined so as to seal
against the face of the flange on the col-
lar. On the inner side of the ace plate
is a sealed can-type unit containing the
electrical contact portion of the recepta-
cle. When assembled, four screws pass
through holes in the face plate and into
the holes in the collar flange, making an
airtight sea! between the machined faces
of each. The face plate contains the fe-
male portion of the receptacle, into which
a specially-designed male plug may be
inserted. (EX 706; EX 511)
28. The codes referred to in the spec-
ifications quoted above require the use
of explosion-proof receptacles for all in-
stallations in operating rooms and simi-
lar areas below the level of five feet
above the floor in order to eliminate the
risks of explosion and fire