Petition for Writ of Certiorari — Mayfair Construction Co. v. United States
Supreme Court brief1988
Ask Donna
What actually matters in this document.
Text
YVO"-4 2g
oO ~ @ Supreme Court, U.S.
FILED
NO. 88- ail Jie
JOSEPH F. SPANIOL, JR.
| CLERK
| IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1988
MAYFAIR CONSTRUCTION COMPANY,
Petitioner,
V.
THE UNITED STATES,
Respondent.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
PETITION FOR A WRIT OF CERTIORARI
Richard C. Walters
Alan H. Kent
1111 19th Street, N.W.
Suite 1000
Washington, D.C. 20036
(202) 463-2976/2960
Attorneys for Petitioner
SCHNADER, HARRISON, SEGAL
& LEWIS
1111 19th Street, N.W.
Washington, D.C. 20036
Of Counsel
QUESTIONS PRESENTED FOR REVIEW
1.. Whether an interim federal procurement
regulation and government contract
clause, in effect when a government con-
tract is issued, are still enforceable
after they have been repudiated and
retracted by the regulating agency as
contravening the statute they were to
implement (i.e., the Contract Disputes
AGG -0& i976, as amended, 41 U.S.C.
§§ 601-613 (1982) (the "CDA")).
= Whether the CDA requires that a govern-
ment contract claim be "in dispute" in
order to qualify as a "claim," under
that Act.
LIST OF PARTIES
Mayfair Construction Company and the
United States were the only parties to this
case in the United States Court of Appeals for
the Federal Circuit, and before the Armed Ser-
vices Board of Contract Appeals.
a a Na
TABLE OF CONTENTS
Page
QUESTIONS PRESENTED FOR REVIEW........... i
LIST OF PARTIRCGs « ¢castccunehs ee eee eae i
TABLE OF AUTHORS Aes ces Chee eee sewers ii
TABLE OF CONTENTS OF APPENDIX............ iii
PETITION FOR A WRIT OF CERTIORARI........ 1
OPINICNS BELA... 204 cb ok eer esa ae 2
JURISDICTION. «..< 6s 5.5 eee eee ee 3
FEDERAL STATUTE AND REGULATIONS INVOLVED. “
STATEMENT OF THE CARE. ci. cn aeveueeaneyb cus 5
REASON FOR ALLOWING THE WRIT............. 8
The Court of Appeals Decided A
Federal Question In A Way Which
Conflicts With Applicable Decisions
Of This Court: The Decision Below
Suggests That Substantive Rights
Under A Government Procurement
Statute May Be Undermined By
Executive Agency Regulations And
Boilerplate Contract Clauses
Repudiated By The Agency As
Contravening THO Statute... .essecseccs 8
CONCLUSION... . «06 «4:5 nents a baa ye 12
TABLE OF AUTHORITIES
Cases
R.G. Beer, Eng BCA No. 4885, 85-2 B.C.A.
(CCH) 9 18, 1626 :<sveus ee ee eens Cee ress G,; aa
Cases (continued)
Esprit Corp. v. United States, 6 Cl.Ct.
546 (1984), aff'd, No. 85-996, Slip
Ops Geen. Gab. GELY BU, 29BS). ccc ccces 7
Federal Election Commission v.
Democratic Senatorial Campaign
oS eS SD ey ee} eee ae
Tera Advanced Services, 85-2 B.C.A.
EE a a aa 6
Statutes and Regulations
OS ES rier 3
Se Vetoes © Meetae CLDBS Pace ccccas throughout
OFPP Interim Regulations, 44 Fed. Reg.
RUUD o Gs 6o6 es We ed cece ce eeesas 4,10
OFPP Policy Letter 80-3, Final
Regulations, 44 Fed. Reg. 31035-31037
I i ee aia cI a bnn 0b 6 6 6 0.6m 6 ee «80 8 6 >
ee eb eweseceses 3
Seen be oe) eb eo 6 oO wlele sere 3
rr eee ol ale od eee eee eee ee 1
TABLE OF CONTENTS OF APPENDIX
Notice to Counsel issued by United
States Court of Appeals for the
SE a App. 1
Cover Sheet of United States Court
of Appeals for the Federal Circuit
in Mayfair Construction Company v.
ec ree. MR. MOS ISO L. ccs ceaces App. 2
433.
TABLE OF CONTENTS OF APPENDIX (continued)
Majority Opinion of United States
Court of Appeals for the Federal
Circuit in Mayfair Construction
Company v. United States, No.
Ly rr oO ree ST eke App.
Dissenting Opinion of Bennett, J.
in Mayfair Construction Company v.
United States, No. 87-1251.......... App.
Order of United States Court of
Appeals for the Federal Circuit
Denying Petition for Rehearing...... App.
Order of United States Court of
Appeals for the Federal Circuit
Denying Suggesting for Rehearing
oe eee tee) ae ee ee App.
Majority Opinion of Armed Services
Board of Contract Appeals in
Mayfair Construction Company,
BE TD. Dd a6 ch RRS oes ibe App.
Dissenting Opinion of Duvall, A.J. in
Mayfair Construction Company, ASBCA
SOD, Se aS ne Oe dite e ee ee i a ee en App.
Relevant Portions of OFPP Interim
Regulations, 44 Fed. Reg. 12519-
pio Be py ) re ra ee ere ae App.
Relevant Portions of OFPP Policy
Letter 80-3, Final Regulations, 45
Fed. Reg. 31035-31037 (1980)........ App.
iv.
NO. 88-
IN THE
SUPREME COURT OF THE UNITED STATES
OCTOBER TERM, 1988
MAYFAIR CONSTRUCTION COMPANY,
Petitioner,
We
THE UNITED STATES,
Respondent.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
PETITION FOR A WRIT OF CERTIORARI
Petitioner, Mayfair Construction Company
("Mayfair"),* prays that a writ of certiorari
issue to review the judgment of the United
States Court of Appeals for the Federal Cir-
cuit, entered on March 9, 1988, ina cause
Rule 28.1 listing of all parent compan-
ies, subsidiaries and affiliates: None.
~~
there entitled Mayfair Construction Company,
Appellant v. The United States, Appellee, No.
87-1251 in that court, which affirmed a deci-
sion of the Armed Services Board of Contract
Appeals ("ASBCA") in Appeal of Mayfair Con-
struction Company, ASBCA No. 30800, 87-1
B.C.A. (CCH) 419,542, denying Mayfair's
appeal on a claim under Section 12 of the
CDA. Mayfair's Petition for Rehearing With
Suggestion for Rehearing In Banc was denied
by the United States Court of Appeals for the
Federal Circuit on June 9, 1988.
OPINIONS BELOW
The United States Court of Appeals for
the Federal Circuit, by 2 to 1 majority deci-
sion of a three-judge panel, reported at 841
F.2d 1576, affirmed an earlier decision of
the Armed Services Board of Contract Appeals
("ASBCA"), reported at 87-1 B.C.A. (CCH)
q 19,542, which likewise was a split decision,
of a 3 to 2 majority. Copies of the majority
and dissenting opinions in both the Court of
Appeals and the ASBCA are set forth in the
o2e
eee
Appendix hereto. (See Appendix ("App.") 3,
12, 41 and 66).
JURISDICTION
The decision of the Armed Services Board
of Contract Appeals was dated December 23,
1986. (App. 41) An appeal from that decision
was taken to the United States Court of
Appeals for the Federal Circuit. The judgment
of the Court of Appeals was dated March 9,
1988 and was entered on that day. (A copy of
the Notice to Counsel regarding such judgment
issued by that court is set forth in the
Appendix. See App. 1.) Subsequently, May-
fair filed a Petition for Rehearing With Sug-
gestion for Rehearing In Banc, which Petition
and Suggestion were both denied by the United
States Court of Appeals for the Federal Cir-
cuit on June 9, 1988. (Copies of the orders
containing those denials are set forth in the
Appendix. See App. 37 and 39.) The jurisdic-
tion of this Court is invoked under 28 U.S.C.
§ 1254(1) (1982), and Rules 20.2 and 20.4 of
the Revised Rules of this Court, effective
from June 30, 1980, as amended to May 1, 1987.
FEDERAL STATUTE AND REGULATIONS INVOLVED
Involved in this case are the following
federal statutes and regulations:
Be The Contract Disputes Act of 1978,
Pub. L. No. 95-563, 92 Stat. 2383-2391 (1978)
(amended 1982), 41 U.S.C. §§ 601-613 (1982)
("CDA") which provides, in pertinent part, as
follows:
Sec. 12. Interest on amounts found
due contractors on claims shall be
paid to the contractor from the
date the contracting officer
receives the claim pursuant’ to
Section 6(a) from the contractor
until payment thereof.
41 U.S.C. § 611 (1982).
Be Interim Regulations promulgated by
the Office of Federal Procurement Policy
(OFPP), 44 Fed. Reg. 12519-12524 (1979). A
copy of the relevant portions of those
Interim Regulations is appended hereto. See
App. 84.
PP Final OFPP Regulations under OFPP
Policy Letter 80-3, 45 Fed. Reg. 31035-31037
(1980). A copy of the relevant portions of
those Final Regulations is appended hereto.
See App. 90.
STATEMENT OF THE CASE
This Petition seeks review of a reported
decision of the United States Court of Appeals
for the Federal Circuit regarding remedies
afforded to Government contractors under a
basic federal procurement statute, the Con-
tract Disputes Act of 1978, as amended, 41
U.S.C. §§ 601-613 (1982) (the "CDA"). The
case originated as an appeal by petitioner,
Mayfair, to the Armed Services Board of Con-
tract Appeals ("ASBCA") from a decision of a
Department of Defense Contracting Officer.
That decision denied Mayfair's claim for in-
terest on costs claimed under a federal
Government contract which had been terminated
for the Government's convenience. The ASBCA,
by a 3 to 2 majority, denied Mayfair's appeal.
The United States Court of Appeals for the
oS<
Federal Circuit, by a 2 to 1 majority panel
decision, affirmed the ASBCA ruling. Dis-
senting opinions were filed in both the ASBCA
and the Court of Appeals.
The ASBCA majority opinion (App. 41) held
that Mayfair's termination settlement proposal
did not constitute a "claim" under the CDA
(i.e., a claim to which remedies under the CDA
would apply, including interest under Section
12 of that statute, 41 U.S.C. § 611 (1982)),
because it was not "in dispute." The ASBCA
majority took the position that the CDA itself
requires claims to be "in dispute" before they
can be considered "claims" under that Act --
a position which was admittedly contrary to
that previously espoused by two other major
federal boards of contract appeals.?
In contrast, the Court of Appeals
majority opinion (App. 3) held Mayfair's
a. See R.G. Beer, Eng BCA No. 4885, 85-2
B.C.A. (CCH) 18,162; Tera Advanced
Services, GSBCA No. 7109, 85-2 B.C.A.
(COn) ¥ 17,941.
iin ia et Sait. ts SAMIR. OE
termination proposal not to be a CDA "claim"
solely on the basis of a regulatory clause
promulgated by the Office of Federal Procure-
ment Policy ("OFPP") on an interim basis and
incorporated by reference into Mayfair's con-
tract, a clause which defined the term "claim"
for CDA purposes to be one "which is in dis-
pute." The Court of Appeals majority chose
not to rule on whether the Act itself required
"claims" to be "in dispute."* Senior Circuit
Judge Bennett, in a dissenting opinion (App.
12), posited that coverage of the CDA was not
intended to be restricted to claims which
develop into "disputes."
Petitioner filed with the Court of
Appeals a Petition for Rehearing with Sugges-
tion For Rehearing In Banc, arguing that the
Court's majority opinion violated precedent
x The Court of Appeals likewise avoided
dealing with that issue directly in an
earlier case. See Esprit Corp. v. United
States, 6 Cl.Ct. 546 (1984), aff'd, No.
85-996, Slip op. (Fed. Cir. July 30,
1985).
before this Court which requires rejection of
regulations and clauses found to be incon-
sistent with the purposes underlying the
statutes they are to implement. The Petition
and Suggestion were both denied. Two Circuit
Judges took exception to these denials. (See
App. 37 and 39).
REASON FOR ALLOWING THE WRIT
This case merits this Court's review for
the following special and important reason:
The Court Of Appeals Decided A Federal
Question In A Way Which Conflicts With
Applicable Decisions Of This Court: The
Decision Below Suggests That Substantive
Rights Afforded Under A Government Procurement
Statute May Be Undermined By Executive Agency
Regulations And Boilerplate Contract Clauses
Repudiated By The Agency As Contravening
The Statute
The Court of Appeals majority here has
given effect to an interim regulation and
contract clause which the regulatory agency
itself (the OFPP) repudiated and retracted
because they were inconsistent with the
purposes of the Act which they were intended
to implement, the Contract Disputes Act of
1978, as amended, 41 U.S.C. §§ 601-613 (1982)
eQ<-
(the "CDA"). See App. 19-20, Dissenting Op.
of Bennett, J. This Court has long recognized
that “administrative constructions" of sta-
tutes must be rejected whenever they are "in-
consistent with the statutory mandate" or
"frustrate the policy that Congress sought to
implement." Federal Election Commission v.
Democratic Senatorial Campaign Committee, 454
U.S. 27, 32 (1981) (and cases cited therein).
In essence, the Court of Appeals
majority here indicates that it does not
matter whether’ the statute itself was
intended to limit CDA "claims" to those "in
' so long as the parties "agreed" to
dispute,'
so limit CDA coverage by way of a contract
provision defining the term "claim" in that
manner.* For the reasons cogently presented
4. The Court of Appeals majority opinion
states in this regard:
If we were to decide that the CDA
does not require a dispute, this
would not mean that the CDA pro-
hibits the parties from agreeing to
[Footnote continued on next page]
-
in the dissenting opinion of Senior Circuit
Judge Bennett (see App. 12), the OFPP Interim
Regulations, 44 Fed. Reg. 12519-12524 (1979)
and "Disputes" clause set forth therein (here-
inafter the "interim 'Disputes' Clause"), when
defining the term "claim" for CDA purposes as
only a claim "which is in dispute," were
clearly inconsistent with the CDA, because
Congress never intended to limit coverage of
that Act and the remedies afforded thereunder
to claims that the Government chooses to dis-
pute. Indeed, the plain language of the Act
clearly indicates that it was intended to
cover all Government contract claims, App.
70-71, ASBCA No. 30800, dissenting op. of
Duvall, A.J. Any regulation which imposes as
a pre-condition to contracting with the
[Footnote continued from previous page]
such a requirement, and there is
nothing in the language of the CDA
to suggest such a prohibition.
App. 9-10, Majority Op. (underscoring in
the original.
o iii
a x cecil
Government the inclusion of a mandatory con-
tract clause which would restrict that cover-
age to "disputed" claims would most certainly
frustrate and undermine the statutory mandate
and policies which Congress sought to imple-
ment when enacting the CDA. Such a regulation
and clause must therefore be rejected. See
Federal Election Commission, 454 U.S. at 32.
Thus, the Court of Appeals was plainly and
palpably wrong in enforcing and giving effect
to the interim regulations and "Disputes"
clause, which the OFPP itself deemed improper
"administrative constructions" of the CDA.
There are broader implications of the
Court of Appeals majority decision here. It
suggests that any substantive rights offered
to a class of persons by a Government pro-
curement statute may be undermined by an
executive agency regulation imposing on con-
tractors boilerplate Government contract
clauses which contravene the statutory
intent. The import of the Court of Appeals
majority opinion is that an executive agency
-l1l-
may obtain through such clauses a contractor's
"agreement" to limit or waive rights and reme-
dies expressly granted by Congress under a
statute, unless the statute itself expressly
"prohibits" such an "agreement." Unless this
Court reviews and rejects such reasoning, pro-
curement regulations and clauses promulgated
by an executive agency at the time of a
federal contract solicitation will be given
effect regardless of whether such regulations
or clauses are subsequently repudiated by the
agency as frustrating the purposes of the
statute they were intended to implement.
Without this Court's intercession, the Court
of Appeals decision here would confer upon
executive agencies the power to circumvent
the will of Congress at any time, by the mere
insertion of boilerplate contract clauses
which contractors are powerless to change.
See App. 23, Dissenting Op. of Bennett, J.;
citing R.G. Beer, Eng BCA No. 4885, 85-2
B.C.A. (CCH) | 18,162 at 91, 199.
«ttm
ee Pe eee ee ee ee a a ee ee |
CONCLUSION
For the foregoing reasons, this petition
for writ of certiorari should be granted.
Respectfully submitted
Richard C. Walters
lla be —
Alan H. Kent
1111 19th Street, N.W.
Suite 1000
Washington, D.C. 20036
(202) 463-2976/2960
Attorneys for Petitioner
SCHNADER, HARRISON, SEGAL
& LEWIS
1111 19th Street, N.W.
Washington, D.C. 20036
Of Counsel
«i3<
APPENDIX
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
717 Madison Place, N.W.
Washington, D.C. 20439
Francis X. Gindhart Telephone: 633-6550
Clerk Area Code 202
NOTICE TO COUNSEL
The Court today announced its decision
in the attached appeal or appeals.
A copy of the Court's opinion or opinions
is enclosed, and judgment thereon has been en-
tered today as required by Rule 36, Federal
Rules of Appellate Procedure.
Costs may be recovered (by Petitioner or
Respondent) as provided by Rule 39, Federal
Rules of Appellate Procedure.
If sanctions have been imposed, please
make check payable to the U.S. Treasury and
forward same to the opposing attorney of
record.
Very truly yours,
Francis X. Gindhart, Clerk
By Spencer C. Greene
Deputy Clerk
App. 1
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1251
MAYFAIR CONSTRUCTION COMPANY,
Appellant,
Vv.
THE UNITED STATES,
Appellee.
Richard C. Walters, Schnader, Harrison,
Segal & Lewis, of Washington, D.C., argued
for appellant. With him on the brief was
Alan H. Kent.
Carolyn E. Galbreath, Commercial
Litigation Branch, Department of Justice, of
Washington, D.C., argued for appellee. With
her on the brief were Richard K. Willard,
Assistant Attorney General, David M. Cohen,
Director and Thomas W. Petersen, Assistant
Director. Also on the brief were Larry W.
Mohl and Michael S. Moran, Defense Logistics
Agency, of St. Louis, Missouri, of counsel.
Appealed from: Armed Services Board of
Contract Appeals
App. 2
;
e
-
?
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1251
MAYFAIR CONSTRUCTION COMPANY,
Appeliant,
Vv.
THE UNITED STATES,
Appellee.
DECIDED: March 9, 1988
Before MARKEY, Chief Judge, BENNETT, Senior
Circuit Judge, and BISSELL, Circuit Judge.
BISSELL, Circuit Judge.
Mayfair Construction Company (Mayfair)
appeals from a decision of the Armed Services
Board of Contract Appeals (ASBCA), Mayfair
Construction Co., ASBCA NO. 30800, 87-1 BCA
49 19,542, denying Mayfair's appeal. We
affirm.
BACKGROUND
On September 5, 1980, the Department of
the Air Force awarded a contract to Mayfair
for the "Pacer Down" facilities restoration
App. 3
project at McConnell Air Force Base, Kansas,
in the amount of $4,176,296. This contract
incorporated by reference the March 1979 ver-
sion of the Defense Acquisition Regulation
Disputes clause.
On January 28, 1982, the contracting
officer terminated the contract for the con-
venience of the government. Mayfair sub-
mitted a termination settlement proposal to
the contracting officer on June 17, 1982, in
the amount of $990,937.29. By letter of
August 2, 1982, Mayfair's counsel denominated
the June 17, 1982 proposal as a claim under
the Contract Disputes Act of 1978 (CDA), 41
U.S.C. § 601 et. seq. (1982), and enclosed
certification of the proposal as a claim.
On December 11, 1984, Mayfair forwarded
an updated termination settlement proposal to
the contracting officer in the amount of
$610,172, and certified this proposal as a
claim under the CDA. The proposal included a
request for interest from August 2, 1982, to
App. 4
December 10, 1984, in the amount of
$146,612.12.
On February 14, 1985, the parties entered
into a termination supplemental agreement
under which they agreed that the government
would pay Mayfair $438,346 for its termination
costs. This agreement, however, expressly
reserved Mayfair's claim for interest. On
the same date, the contracting officer issued
a final decision denying Mayfair's claim for
interest. Thereafter, Mayfair appealed to the
ASBCA, which held that the Disputes clause of
the contract defined "claim" to require the
existence of a dispute; no dispute existed
between the parties, therefore no claim
existed; and consequently, no interest would
be allowable under the CDA where there was no
claim.
ISSUES
ix Whether Mayfair's termination
settlement proposal constitutes a claim.
ro Whether Mayfair may recover
interest on its termination settlement
proposal.
OPINION
ee
The contract at issue specifically
incorporated by reference the March 1979
version of the Disputes clause. That clause
defined claim as follows:
(b) "Claim" means:
(1) a written request submitted to the
Contracting Officer;
(2) for payment of money, adjustment of
contract terms, or other relief;
(3) which is in dispute.
44 Fed. Reg. 12,524 (1979) (emphasis added).
It is beyond cavil that under this clause, no
claim exists unless it involves a dispute.
As a matter of fact, the ASBCA found here
that no dispute existed between the parties.
It looked to Mayfair's substantial concurrence
with an August 1982 government audit report,
and the large reductions Mayfair made there-
App. 6
after in its proposed settlement. It noted
that excluding the $146,612.12 interest ele-
ment of Mayfair's December 1984 settlement
proposal, the final settlement agreement for
$438,346 gave Mayfair only $25,213.88 less
than the $463,559.88 it had requested in
December 1984. As a result, the ASBCA charac-
terized Mayfair and the government during this
period as being in "a pre-dispute, negotiation
posture."
Mayfair, 87-1 BCA at 98,744.
We must treat the ASBCA's’~ factual
findings as final unless "fraudulent, or arbi-
trary, or capricious, or so grossly erroneous
as to necessarily imply bad faith," or unless
those findings are "not supported by substan-
tial evidence." 41 U.S.C. § 609(b) (1982).
There is nothing here to suggest these find-
ings are fraudulent, arbitrary, capricious,
Or grossly erroneous. With respect to the
Pit lense shes owns B ae A at.
; substantial evidence standard, this "means
such relevant evidence as a reasonable mind
might accept as adequate to support a con-
al eal DOE fie,
clusion." Universal Camera Corp. v. National
App. 7
labor Relations Bd., 340 U.S. 474, 477 (1951)
(quoting Consolidated Edison Co. v. National
Labor Relations Bd., 305 U.S. 197, 229
(1938)). In our view, a reasonable fact-
finder could have found as the ASBCA did.
Therefore, we hold that the ASBCA's conclusion
that no dispute existed between Mayfair and
the government is supported by substantial
evidence. Under the terms of the controlling
contractual provision, consequently,
Mayfair's termination settlement proposal did
not constitute a claim.
Mayfair attempts to resist this result
with two arguments. First, Mayfair states
that a revised Disputes clause that did not
require a claim to be disputed superseded the
March 1979 Disputes clause in Mayfair's con-
tract. Mayfair notes that the new clause was
issued on April 30, 1980, well before the
award of the subject contract, on September 5,
1980. This argument, however, does not wash.
The new clause applied only to contracts re-
sulting from solicitations issued on or after
App. 8
June 1, 1980. 45 Fed. Reg. 31,035, 31,037
(1980). Because the solicitation for the
subject contract was dated February 17, 1980,
Mayfair, 87-1 BCA at 98,741, the new clause
is inapplicable.
Mayfair also contends that the CDA does
not require a claim to be disputed, and as
such, the terms of the Disputes clause
requiring a dispute are in violation of the
statute. In order to dispose of this case,
we need not, and do not, decide whether the
CDA requires a claim to be disputed.* If we
were to decide that the CDA requires a dis-
pute, the March 1979 Disputes clause would
certainly be valid. If we were to decide
that the CDA does not require a dispute, this
would not mean that the CDA prohibits the
parties from agreeing to such a requirement,
* The dissent focuses on construing the
CDA, and determines that the CDA does not re-
quire a claim to be disputed. The dissent's
analysis, however, virtually ignores the con-
tract clause requiring the existence of a dis-
pute. In contrast to the dissent, we consider
the terms of that clause to be dispositive.
App. 9
and there is nothing in the language of the
CDA to suggest such a prohibition. Thus,
Mayfair's argument that the March 1979
Disputes clause is in violation of the CDA is
without merit.
II
Mayfair's request for interest on its
termination settlement proposals is governed
by the Court of Claims decision in Nab-Lord
Associates v. United States, 682 F.2d 940
(Ct. Cl. 1982). There the Court of Claims
held that the CDA does not authorize an in-
terest award unless a contractor demands
interest on a claim cognizable under the CDA.
Id. at 943-44. For the reasons aliready given,
Mayfair's termination settlement proposals
were not cognizable claims. Therefore, any
demand for interest that relies on these
proposals as the underlying basis for an
interest demand must fail.
In its December ll, 1984 settlement
proposal, Mayfair demanded interest on its
August 2, 1982 proposal on the theory that
App. 10
:
5)
;
=
§
*
:
taiety
pale eat a age ae
i he a REDS Shatin 7» Reise shah dS DA EU IT eat A:AS OEPR ESATA AS Rng sie WR Nt Gia SO INASP EMESIS SEE OR LED he CENTS,
the earlier proposal had been properly certi-
fied as a CDA claim. However, because the
earlier settlement proposal was not a claim,
the demand for interest was unallowable.
Because Mayfair also certified its
December 11, 1984 proposal as a CDA claim, it
alleges that interest should run on the in-
terest component of that "claim." We may dis-
pose of this argument without reaching the
broader issue of whether the CDA permits in-
terest to run on an interest claim. Having
held that the interest component of the
December 1984 proposal was unallowable, no
corpus remains on which interest can run.
Therefore, no basis exists on which Mayfair
may recover interest.
AFFIRMED
App. 11
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1251
MAYFAIR CONSTRUCTION COMPANY,
Appellant,
Vv.
THE UNITED STATES,
Appellee.
BENNETT, Senior Circuit Judge, Dissenting.
I respectfully dissent. The majority
concludes that substantial evidence supports
the board's conclusion that no "dispute"
existed between the parties since the govern-
ment's final settlement payment was "only"
$25,213.88 less than Mayfair's second ter-
mination settlement proposal, which had been
certified as a claim pursuant to the require-
ments of the Contracts Disputes Act (CDA), 41
U.S.C. § 605(c)(1) (1982). That alone pro-
vides ample reason to dissent since, in my
view, a disagreement over $25,213.88 is a
App. 12
>
f
=
quite substantial and sufficient dispute,
even assuming that a dispute was indeed
needed for the existence of a CDA claim under
the terms of the subject contract. However,
the issue over the existence of a dispute is
not even that close, as the evidence of
dispute was far greater than a disagreement
over $25,213.88.
Following the government's termination
for convenience of the Mayfair contract on
January 28, 1982, Mayfair submitted a termina-
tion settlement proposal in the amount of
$990,937.29. On August 2, 1982, Mayfair
identified and certified the settlement pro-
posal as a claim under the CDA. Over 2 years
later, in December 1984, Mayfair submitted a
second certified settlement "proposal" in the
amount of $463,559.88 (not including an amount
claimed as interest on that figure). It was
not until May 28, 1985, that the government
paid Mayfair $438,346, which represented the
second proposal amount minus the disputed
App. 13
$25,213.88, in settlement of its termination
for convenience claim.
Thus, Mayfair did not receive the
government's final payment until 40 months
after the government terminated the contract
and the final payment received was
$552,591.29 less than Mayfair's initial
settlement proposal, which had been certified
as a CDA claim almost 3 years before. In
light of the time taken to resolve the amount
due following the government's termination
and the difference of over a half a million
dollars between Mayfair's initial claim and
the government's final payment, I do not
hesitate in concluding that substantial
evidence does not support the majority's (and
the board's) conclusion that the initial
termination settlement proposal submitted by
Mayfair was merely part of the usual and
ordinary process of a convenience
termination, and therefore could not consti-
tute a claim since the parties were in “a
pre-dispute, negotiation posture." See
App. 14
Hectares iiiiiaainiasaiaaiiial
Se a E
a eee ee ee ————_ «
ii
se
Mayfair Construction Co., ASBCA No. 30800,
87-1 BCA 47 19,542.
My disagreement with the majority,
however, is much more fundamental than a
difference of opinion over the length of time
or the amount of money needed to constitute a
"dispute." In my view, a contractor's certi-
fied settlement proposal following the ter-
mination of a contract for the convenience of
the government is as much a claim against the
government related to a contract, see 41
U.S.C. § 605(a), as more “traditional” claims
stemming from such events as constructive
changes, delay, or defective specifications
which unquestionably are treated as claims
under the CDA. Yet here the majority unjusti-
fiably allows contractor claims arising from
convenience terminations to be segregated from
all other types of claims arising from con-
tracts with the government, despite no such
App. 15
distinction being made in the cpa.2/ Not only
is the majority's position without support in
the clear legislative history surrounding the
enactment of the CDA, but it will serve as a
strong disincentive to accurate submission
and good faith negotiation of termination
settlement proposals by contractors and to
timely and orderly consideration of termina-
tion claims by the government. At a minimum,
the majority view must be seen as heralding,
at least with respect to termination claims,
a return of the pre-CDA days of inflated
settlement proposals as precursors to bar-
1/ See Walber Construction Co., HUD BCA No.
80-445-C2, 83-2 BCA 47 16,885 (concluding that
the Federal Acquisition Regulations not al-
lowing interest on amounts due under a settle-
ment agreement arising out of a termination
for convenience were supersedeed by the CDA).
In fact, the board in Walber specifically
noted that although a termination settlement
agreement claim is intended to be negotiated
rather than unilaterally decided by the con-
tracting officer and was not therefore subject
to the pressure of a right to interest for
less-than-immediate payment, the CDA made no
such distinction between types of claims.
Id. at 84,031.
App. 16
gaining and of litigation as the primary
means of claim resolution.
Congress chose not to provide an express
definition of "claim" in the CDA statute.
But, as the dissenting board opinion in this
case ably points out, there is no evidence
that Congress intended "claim" to have a
special meaning apart from its plain,
ordinary meaning. 87-1 BCA at 98,746
(ordinary meaning of "claim" is "'a demand
for something rightfully or allegedly due;
assertion of one's right to something'"
(citation omitted) ); see also Contract
Cleaning Maintenance, Inc. v. United States,
811 F.2d 586, 592 (Fed. Cir. 1987); Paragon
Energy Corp. v. United States, 645 F.2d 966,
971-76 (Ct. Cl. 1981); cf. In re Remington
Rand Corp., No. 87-5063 (3d Cir. Jan. 6,
1988) (Congress used "claim" in the CDA in
the *sraditional sense--as a legal cause of
action). In the absence of contrary legis-
lative history, the plain meaning of a statute
should be followed. Consumer Product Safety
App. 17
Commission v. GTE Sylvania, Inc., 447 U.S.
102, 108 (1980); Horner v. Jeffrey, 823 F.2d
1521, 1525 (Fed. Cir. 1987). I am able to
discern no congressional intent to exclude
contractor claims resulting from government
terminations for convenience from the pro-
visions of the CDA. See Essex Electro
Engineers v. United States, 702 F.2d 998,
1003 (Fed. Cir. 1983).2/
Nor is there any evidence that Congress
intended "claim" to incorporate, for the
purposes of the CDA, the additional
requirement of a dispute. As the board
dissent also correctly points out, "claim"
and "dispute" were not used synonymously by
2/ In Essex, this court allowed interest on
a termination for convenience claim from the
date that the claim was certified to the con-
tracting officer. The court made no sugges-
tion that claims stemming from the termination
of a contract for the convenience of the
government fell outside the terms of the CDA.
In fact, the court in Essex also noted that
the interest provision of the CDA superseded
the interest clauses in the contracts liti-
gated under the Act. 702 F.2d at 1003 &n.9.
Congress in the text of the CDA. See 87-1
BCA at 98,747. Furthermore, the erroneous
requirement of a dispute contained in the
interim 1979 regulations defining "claim,"
referenced in the contract at issue, was
deleted from the final regulations adopted in
1980. 3/ Deference to an interpretation of an
agency charged with administration of a
statute is not required where that interpreta-
tion conflicts with the statutory mandate or
would conflict with the policy that Congress
sought to implement. E.g., Jeffrey, 823 F.2d
at 1531. This would appear to be especially
true where the interpretation in question has
af The final regulations provided the fol-
lowing definition:
(i) As used herein ‘'claim' means a
written demand or assertion by one of
the parties seeking, as a legal right,
the payment of money, adjustment or
interpretation of contract terms, or
other relief, arising under or relating
to this contract.
87-1 BCA at 98,743 (quoting 45 Fed. Reg.
31035 (May 9, 1980)). See also Paragon, 645
F.2d at 976.
.
+
3
Fs
|
App. 19
been repudiated by the agency which origi-
nally proposed it. See generally R.G. Beer
Corp., ENG BCA No. 4885, 85-2 BCA 4 18,162.
In short, the unmistakable legislative intent
of Congress was to provide interest on all
contractor claims arising from contracts with
the government, regardless of whether the
claims were litigated or settled after nego-
tiation. See 41 U.S.C. § 611; R.G. Beer,
85-2 BCA at 91,199.
In determining that no valid claim under
the CDA existed in the present case, the
board majority rejected the analysis of R.G.
Beer and instead relied on Racquette River
Construction Co., ASBCA No. 26486, 82-1 BCA
7 15,769. The board in Racquette River
relied on a lack of a dispute and a lack of
delay in settlement beyond a reasonable time
to conclude that the contractor's settlement
proposal following a termination for the
government's convenience was not a claim.
But examination of the facts indicates that
the contractor submitted a claim for $91,454
App. 20
Bt iret 0,
and the government questioned at least
$32,138 of it. Thus, the board's conclusion
in Racquette River that no dispute existed
appears contrived since much of the board's
opinion delineates the contractor position
and the corresponding government proposal,
and then decides between the disputed posi-
tions. Even more curiously, the board in
Racquette River had also disallowed reimburse-
ment of attorney fees incurred in preparation
of the claim against the government since
"even prior to the incurrence of these fees,
the conflict between the parties was disputa-
tious and did reach the level of becoming a
claim against the Government." 82-1 BCA at
78,052. In my view, Racquette River cannot
be used as support for the result in this
case since it contains a fundamental incon-
sistency in denying attorney fees due to the
"disputatious" nature of the claim, yet also
denying interest on the same claim because
App. 21
there was "no dispute" at the time of the
4/
claim's submission.-—
The majority here attempts to avoid
addressing the issue of whether the require-
ment of a dispute as a prerequisite for a
claim under the CDA contravenes the statute
by concluding that the CDA does not prohibit
the parties from agreeing to additional re-
quirements not expressly contemplated or
provided by Congress in the statute. How-
4/ In the present case, the government
points to inconsistent assertions in Mayfair's
letter containing its August 2, 1982 certifi-
cation. In that letter, Mayfair attempted to
draw a distinction between certification of a
"claim" under the CDA sufficient to start the
time for interest and a "prosecuted claim"
for which recovery of legal fees associated
with negotiation of a settlement proposal
would not be reimbursed by the government.
The government argues that Mayfair's attempted
distinction between "CDA claim" and "prose-
cuted claim" shows that Mayfair's settlement
proposal was not a claim, despite the certifi-
cation. Rejection of Mayfair's attempted dis-
tinction may indicate that by electing to
certify its claim under the CDA, Mayfair
correspondingly ended any possible entitlement
to reimbursement for subsequent attorney fees
associated with settlement negotiations con-
cerning the claim, but it is not determinative
as to whether its initial proposal should be
considered a CDA claim once certified.
App. 22
ever, the clear intent of Congress should not
be permitted by this Court to be sidestepped
so easily by the parties. It is quite doubt-
ful that Congress intended, as the majority
allows here, for the parties to create a dif-
ferent definition of claim in every contract
involving the government, especially since
the government is the party which provides
that definition through its regulations
governing its procurement process. As was
observed by the board inR.G. Beer,
‘{i]t would indeed be ironic if, by
simply publishing a new and self-
serving definition of the familiar
term "claim," one of the contracting
parties could regain its superior
bargaining power and turn the event
selected by Congress to "provide a
specific date from which interest
will be paid" into a variable date,
and the benefit intended to "serve
as an incentive" for early submis-
Sion of claims into a disincentive
to early claim submittal or settle-
ment.
85-2 BCA at 91,199.
~The CDA was designed to end the prior
practice rampant in the government contracting
area where a contractor would submit grossly
App. 23
inflated claims that had little relation to
the facts, were improper as a basis for
settlement, and were intended only as a start-
ing point for bargaining. See Fidelity Con-
struction Co. v. United States, 700 F.2d 1379,
1382-83 (Fed. Cir.) (citing legislative his-
tory of the CDA), cert. denied, 464 U.S. 826
(1983). To treat termination for convenience
settlement proposals differently from other
claims related to contracts and to ignore or
prevent their certification as CDA claims
encourages a return to submission of inflated
proposals as a precursor to bargaining and
contradicts the entire purpose of the CDA.
This is not the type of negotiation posture
intended by Congress or that should be
encouraged by this court.
The legislative purpose behind 41 U.S.C.
§ 611, the interest provision in the CDA,
adds further support for this conclusion. As
discussed in Fidelity, 700 F.2d at 1384, Con-
gress was concerned with fully compensating
contractors for additional costs incurred in
App. 24
continuing performance under a contract. See
also 87-1 BCA at 98,747. In the case of
termination for convenience, the contractor's
work may have been terminated prior to his
receiving adequate compensation for’ the
performance already completed. No interest
is allowed for the time during which the
contractor prepares the termination claim
prior to its submission and certification.
Allowing interest to accrue from the time
that a contractor claim related to a contract
is certified comports with congressional
intent in providing adequate compensation to
the contractor on its claims which are
upheld. Furthermore, treating termination
settlement claims no differently from other
claims requires, through contractor
compliance with the CDA certification
provisions, the submission of good faith
claims with accurate and complete supporting
data, which facilitates the orderly
resolution of any quantum due as a result of
the termination. See 41 U.S.C. § 605(c)(1);
App. 25
see also United States v. Turner Construction
Co., 827 F.2d 1554, 1561 (Fed. Cir. 1987).
The CDA interest provision also serves
to provide "an additional inducement for the
settlement of claims short of litigation."
Brookfield Construction Co. v. United States,
661 F.2d 159, 164 (Ct. Cl. 1981). It makes
little sense to say that termination settle-
ment claims should not be treated as claims
under the CDA because they are merely in the
predispute posture of negotiation, since a
purpose of the CDA is to facilitate the set-
tlement of claims short of litigation. Main-
tenance of a predispute posture should be
encouraged, not penalized. Requiring a dis-
pute before interest can accrue pushes the
parties that much closer to litigation and
only serves to encourage "creation" of a
dispute in order to permit the payment of
interest. If all other claims arising from
contracts with the government’ currently
handled under the CDA can be settled short of
litigation, and that is the clear intent and
App. 26
%
3
purpose of the statute, it does not follow
that treating settlement proposals in the
same manner would somehow lead to a different
result.
Allowing interest to contractors on
their claims under the CDA was intended by
Congress to make the bargaining process more
equal so that the government could not un-
reasonably delay the claim analysis to the
contractor's detriment. Since other types of
CDA claims (not involving fraud) can be nego-
tiated and settled, the fact that termination
Claims have historically been negotiated
rather than merely granted or denied by the
contracting officer is no reason to treat
termination settlement claims differently from
other claims under the CDA. Thus, I would
conclude that a contractor should be able to
elect to certify its settlement proposal as a
CDA claim following a termination for the con-
venience of the government. Since Mayfair did
exactly that, and there has been no suggestion
that its initial certification was otherwise
App. 27
defective, I would conclude that Mayfair's
termination settlement proposal was a valid
CDA claim from August 2, 1982, the date on
which the claim was validly certified in
accordance with the CDA.
This court has held that a contractor
can recover CDA interest even where the under-
lying quantum claim has been settled as long
as the quantum claim was subject to the act
and the settlement agreement did not extin-
guish the interest claim. ReCon Paving, Inc.
v. United Statees, 745 F.2d 34 (Fed. Cir.
1984). Since, unlike the majority, I would
conclude that appellant's certified termina-
tion settlement proposal was a cognizable
claim under the CDA and since the parties
specifically excluded Mayfair's claim for in-
terest from their settlement agreement, I
would conclude that Mayfair is entitled to
interest in accordance with the terms of 41
U.S.C. § 611:
Interest on amounts found due
contractors on claims shall be paid
to the contractor from the date the
App. 28
contracting officer receives the
claim pursuant to section 605(a) of
this title from the contractor until
payment thereof. The interest pro-
vided for in this section shall be
paid at the rate established by the
Secretary of the Treasury .
According to the parties’ stipulations, the
total interest due on the $438,346 payment by
the government for the period from the date
of the initial certification of the claim,
August 2, 1982, to the date of payment,
May 28, 1985, would be $171,229.09. In my
view, Mayfair is entitled to recover that
amount.
The “Interest on Interest" Claim
In addition to the above amount, Mayfair
also asserts that the interest element of its
certified claim of December ll, 1984, is it-
self a claim under the CDA which entitles it
to interest on the amount found due on that
disputed claim element. In accordance with
that theory, Mayfair alleges that since the
CDA interest owed on the $438,346 ultimately
paid amounted to $146,052 as of December 11,
1984, it is entitled to CDA interest on that
App. 29
amount for the period from December 14, 1984,
the date that the contracting officer received
the certified interest claim, through the
future date when the $146,052 is ultimately
paid by the government. Although the majority
does not reach the so-called “interest on
interest" issue in light of its holding that
no interest is to be awarded at all, I will
indulge in a brief comment thereon for the
sake of completeness.
As evidenced by the use of the term
"shall" in section 611, the terms of the sec-
tion are mandatory. When a proper CDA claim
(including certification) has been filed by
the contractor and an amount stemming from
the claim found to be due to the contractor,
the ccentractor is entitled to receive
interest on that amount from the date that
the claim was certified. E.g., Fidelity, 700
F.2d at 1385. In fact, although it is
uniformly done, it does not appear that the
contractor need specifically mention that it
seeks interest on the underlying claims in
App. 30
order to recover the interest under the
statute since payment of such interest is
mandatory. So, absent a dispute over whether
the underlying claim is indeed a claim,
payment of interest on the amount paid on the
claim should necessarily follow in accordance
with the statute, and the issue of additional
interest on that interest does not arise.
Here, however, since there was a dispute
over whether Mayfair's termination settlement
proposal could be certified as a CDA claim,
the issue did arise. The board in this case
unanimously agreed that no interest could be
paid to Mayfair on the unpaid interest
because only simple interest can be awarded
against the Government. See Brookfield, 661
F.2d at 170; United States v. Mescalero Apache
Tribe, 518 F.2d 1309, 1331-32 (Ct. Cl. 1975),
cert. denied, 425 U.S. 911 (1976); Central
Mechanical, Inc., ASBCA No. 29193, 85-2 BCA
§ 18,005. However, the asserted “compound
interest" in this case appears to stem from
the fact that Mayfair seeks interest on an
App. 31
unpaid amount which itself happens to be
interest. Thus, it appears that the interest
sought here is indeed simple interest rather
than compound interest, albeit simple interest
based on an amount which happens to be in-
terest itself, and therefore the claim for
such should not necessarly be denied on that
basis.
Nevertheless, I would also hold that
interest could not be recovered on the unpaid
interest of $171, 222.092/ because the under-
lying claim to the "interest on interest"
claim, the claim for interest on the termina-
of Assuming such interest recoverable, any
claim for interest on unpaid interest would
not actually accrue until the principal (the
unpaid interest) is paid and the interest
thereon is not. In this case, the alleged
claim for interest on the unpaid interest
accrued on May 28, 1985, so Mayfair's claim
(and attempted certification thereof) for
"interest on interest" made on December 10,
1984, was premature. Thus, contrary to
Mayfair's alleged computation method, any
additional recoverable interest should be
based on the entire amount of interest owed
on the settled claim ($171,222.09) from the
date that the settled claim was paid but the
interest was not.
App. 32
LLL
dnltites it ert,
tion claim, is not itself a claim under the
CDA. Section 605(a) of the CDA provides that
"[ajll claims by a contractor against the
government relating to a contract shall be in
writing and shall be submitted to the con-
tracting officer for a decision." (Emphasis
supplied.) In my view, the termination claim
at issue here is a claim by a contractor
against the government relating to a contract;
however, the "claim" for CDA interest on that
claim relates not to the contract, but to the
CDA itself. Since section 611 only provides
for the payment of interest on claims received
pursuant to section 605(a), the limited waiver
of sovereign immunity contained in the CDA
does not appear to extend to the payment of
interest on unpaid CDA interest. See, e.g.,
Soriano v. United States, 352 U.S. 270, 276
(1957) (the "limitations and conditions upon
which the Government consents to be sued must
be strictly observed and exceptions thereto
are not to be implied"); Fidelity, 700 F.2d
at 1383 (no interest shall be awarded absent
App. 33
an express contractual provision or an Act of
Congress specifically providing for payment).
The conclusion that a claim for interest
on unpaid CDA interest is not itself a cog-
nizable CDA claim is buttressed by the deci-
sion of the Court of Claims in Brookfield.’
In an extensive analysis of the CDA interest
provision, the court in Brookfield made no
mention of allowing additional interest on
the CDA interest ultimately determined to be
due. Furthermore, in reaching its conclusion,
the court also held that certification of the
claim for CDA interest was not necessary.
6/ In Brookfield, the court held that a
contractor was entitled to recover interest
on claims pending before the contracting
officer on March l, 1979, the effective date
of the CDA, despite the absence of an
interest provision in the contract, and
awarded simple interest on the amounts of the
underlying claims from March 1, 1979 through
the date of payment of those claims. 661
F.2d at 168-170.
+ ate Pal anal ect she
As for the post-Act interest
claim itself (distinguished from the
underlying claims), no certification
is necessary even though we assume
arguendo that the claim was present-
ed after March 1, 1979. Once the
amounts for the underlying claims
are set, the determination of the
amount of post-Act interest is ob-
jective, legal, and mathematical,
not lending itself to certification
nor serving any of certification's
fraud-preventive goals. It would
be needless, redundant, and overly-
technical to require certification
of that interest claim.
661 F.2d at 166-67.
The holding in Brookfield that claims
for CDA interest do not need to be certified
is a strong indication that such interest
claims, while arising from the CDA, do not
arise under a contract so as to qualify as
CDA claims. Thus, claims for CDA eendee
would not themselves be entitled to CDA
interest. See Nab-Lord Associates v. United
States, 682 F.2d 940, 944 (Ct. Cl. 1982) (in
order for a contractor to receive interest
under the CDA there must be an underlying
claim for quantum which is governed by the
act). Accordingly, for the reasons given, I
App. 35
would affirm that part of the board's decision
holding that no additional interest could be
recovered under the CDA on the $171,222.09
interest on the termination claim.
App. 36
Sen a ee ay
NOTE: This Order has not been prepared for
publication in a printed volume because it
does not add significantly to the body of law
and is not of widespread legal interest. It
is a public record. It is not citable as
precedent.
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1251
MAYFAIR CONSTRUCTION COMPANY,
Appellant,
Ws
THE UNITED STATES,
Appellee.
ORDER
A suggestion for rehearing having been
filed in this case,
UPON CONSIDERATION THEREOF, itis
ORDERED that the petition for rehearing
be, and the same hereby is, denied.
Judges Smith and Newman would grant the
suggestion.
FOR THE COURT:
Francis X. Gindhart
Francis X. Gindhart, Clerk
App. 37
6/9/88
Date
cc: Mr. Richard C. Walters
Ms. Carolyn Galbreath, DOJ
App. 38
NOTE: This Order has not been prepared for
publication in a printed volume because it
does not add significantly to the body of law
and is not of widespread legal interest. It
is a public record. It is not citable as
precedent.
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
Corrected copy)
87-1251
MAYFAIR CONSTRUCTION COMPANY,
Appellant,
Vv.
THE UNITED STATES,
Appellee.
ORDER
A suggestion for rehearing in banc having
been filed in this case,
UPON CONSIDERATION THEREOF, itis
ORDERED that the suggestion for
rehearing in banc is declined.
Judges Smith and Newman would grant the
suggestion.
FOR THE COURT:
Francis X. Gindhart
Francis X. Gindhart, Clerk
App. 39
6/9/88
Date
cc: Mr. Richard C. Walters
Ms. Carolyn Galbreath, DOJ
App. 40
ne ee ee eee eRe ae See ee
DECISION OF THE ARMED SERVICES BOARD -
OF CONTRACT APPEALS IN
MAYFAIR CONSTRUCTION COMPANY
ASBCA No. 30800, December 23, 1986
Contract No. F14614-80-C-0018
Reported at 87-1 B.C.A. (C.C.H.) 4 19,542:
For the appellant: Schnader, Harrison,
Segal & Lewis, Washington, D.C., by Harold F.
Blasky and Richard C. Walters. For the
government: Richard F. Pier, Trial Attorney,
Defense Contract Administration Services
Region, St. Louis (DLA).
Opinion by Administration Judge Ruberry
with Administrative Judges Watkins and Arons
concurring; Administrative Judge Duvall dis-
senting; Administrative Judge Harper concurred
with the dissent.
[Text of Opinion]
The question presented by this appeal is
whether appellant can recover interest sania
the Contract Disputes Act of 1978 (CDA) (41
U.S.C. § 601 et. seq.) on the amount agreed
to as settlement for termination of the
contract for convenience of the Government.
App. 41
Appellant maintains that it is due interest
on the settled amount from the time it certi-
fied the settlement proposal and labeled the
proposal a claim under the CDA. The Govern-
ment contends that interest is not payable
for three reasons; first, because the termina-
tion settlement proposal was not a claim under
the CDA since the amount was not disputed;
second, because termination settlement pro-
posals traditionally have not been considered
to be claims and; third, because the termina-
tion settlement proposal was not properly cer-
tified as a claim under the CDA. The Govern-
ment does not question the sufficiency of the
text of the certification, but argues that
the certification was ineffective because it
was signed by an individual not properly
authorized to certify a claim under the CDA
and implementing regulations. Also at issue
is appellant's contention that the claim for
interest was itself a claim cognizable under
the CDA, entitling it to recover interest on
the interest allegedly accrued on the amount
App. 42
_ eee eV
oe see eee Le
of the settlement. There are no facts in
dispute. The appeal is before the Board on
the record, supplemented by a joint stipula-
tion of facts, pursuant to Board Rule ll.
Findings of Fact
The following is a summary of the
essential facts, most of which have been
stipulated by the parties.
Appellant's bid on the solicitation
dated 17 February 1980 for the "Pacer Down"
facilities, restoration project at McConnell
AFB, Kansas was signed by Mr. Phillip W.
Akwa, Contract Administrator, on behalf of
appellant (Stip 2).
By letter dated April 15, 1980, Mr. Paul
Cocose, appellant's president, notified Air
Force contracting personnel at McConnell AFB
that Mr. Akwa was authorized to execute the
construction contract and to negotiate and
execute any modifications and time changes to
that contract (Stip. 3).
On or about 5 September 1980 the contract
was awarded to appellant in the amount of
App. 43
$4,176,296. The contract was executed by Mr.
Akwa on behalf of appellant (Stip. 4).
Mr. Akwa likewise ener ted many
bilateral modifications to the contract on
behalf of Mayfair. However, bilateral
modifications Nos. 2 and 3 were executed by
Mr. A. Karwat, Project Manager and Mr.
Charles Whalen, Assistant Contracting
Administrator, signed Mod 4 (Stip. 5).
During the course of contract per-
formance, Mr. Akwa was Mayfair's chief repre-
sentative at most meetings with Government
officials concerning any matters relating to
the contract (Stip. 6).
The contract was terminated for conven-
ience of the Government on or about 28 January
1982 (Stip. 7). Subsequently, by letter
dated March 17, 1982, Mr. Cocose confirmed to
Government contracting officials that Mr. Akwa
was continuing in his capacity as contract ad-
ministrator for the project, and, as such, had
full authority to bind appellant (Stip. 8).
App. 44
A AO, MS ON te i we
The delegation of authority to Mr. Akwa
was acknowledged by Mr. R.D. Fischer, the
Government's Termination Contracting Officer
("TCO") by letter dated June 16, 1982 to Mr.
Cocose. In that letter, the TCO insisted
that all correspondence be signed by the
contract administrator (Stip. 9).
By letter dated June 17, 1982 from Mr.
Akwa to the TCO, Mayfair submitted a Termina-
tion Settlement Proposal in the amount of
$990,937.29. By letter dated August 2, 1982,
to the 2cO, Mayfair's counsel forwarded
Mayfair's certification of that proposal
specifically identified as a "claim" under
the CDA. That CDA certification was executed
by Mr. Akwa on behalf of appellant (Stip. 10).
On January 21, 1983, the TCO was orally
notified that Mr. Akwa no longer represented
Mayfair and that Mr. Cocose was personally
assuming Mr. Akwa'’s duties as contracts admin-
istrator. This notification was confirmed in
writing by Mr. Cocose's letter to the TCO
dated March 1, 1983. All subsequent CDA
App. 45
certifications with respect to Termination
Settlement Proposal updates were executed by
Mr. Cocose, including settlement proposals
submitted in June ($567,545) and August
($578,394) 1984. Stip. 11; R4, tab 5)
The reasons for the substantial
reduction in the $990,937.29 initially
proposed by appellant are not entirely
clear, but the record indicates that "The
contractor basically concurred" with the
findings of a Government audit report issued
in August 1982 (R4, tab 6).
The Termination Settlement Proposal,
updated December 11, 1984, certified by Mr.
Cocose as a claim under the CDA in the amount
of $610,172, included as an element of Settle-
ment Expenses in Schedule E of DD Form 541,
Settlement Proposal (Total Cost Basis), a
claim for CDA interest in the total amount of
$146,612.12. The computation of that amount
was set forth on a separate sheet attached to
the Settlement Proposal form and refiected the
accrual of interest (at rates promulgated
App. 46
aE
semi-annually by the United States Secretary
of the Treasury for purposes of the CDA) from
August 1, 1982, the date when appellant's
initial CDA certification was transmitted to
the TCO, until December 10, 1984 (Stip. 12;
R4, tab 8).
By Termination Supplemental Agreement
No. AOOOO1l dated February 14, 1985, the
parties agreed to a settlement with respect
to appellant's Settlement Proposal.
Expressly reserved from the Termination
Supplemental Agreement was appellant's claim
for interest. It was agreed that that
portion of appellant's Settlement Proposal
would be the subject of a unilateral
determination to be issued by the TCO (Stip.
re be
By letter also dated February 14, 1985,
the TCO issued a Final Decision denying
Mayfair's claim for interest on that Termina-
tion Settlement Proposal. A timely appeal
from that Final Decision was made by appel-
lant's counsel by letter dated February 20,
App. 47
1985 (Stip. 14). The contracting officer's
denial was based on the contention that a
settlement proposal is not a claim as
defined in Federal Acquisition Regulations
(FAR 33.001) but is a routine request for
payment pursuant to the Termination Clause,
and therefore interest is not payable.
The undisputed amount agreed upon under
Termination Supplemental Agreement No.
AOOOO1, $438,346, was paid by the Government
on May 20, 1985 and received by appellant on
May 28, 1985 (Stip. 15).
The parties have agreed that the correct
amount of interest, if found to be allowable,
from August 2, 1982 until December 10, 1984,
was $146,052 (Stips. 16 and 17).
The parties further have agreed that in
the event the Board should find the contractor
entitled to CDA interest on the termination
settlement amount eventually determined due,
that additional CDA interest would be due for
the period December 11, 1984 uv to and in-
cluding the date of payment under Termination
App. 48
at renee. castles Mestitehnaa! expats
Supplemental Agreement No. AQOOO1, May 20,
1985. Such additional interest was agreed to
be $25,170.09 (Stip. 18).
The contractor is also claiming interest
on the interest amount of $146,052 represent-
ing the interest accruing on that amount from
December 14, 1984 until payment-.is made by the
Government of the $146,052 (Stip. 19).
The record includes an affidavit from
appellant's president stating that as part of
his duties he appointed Mr. Akwa as
appellant's contracts administrator for the
project, that Mr. Akwa was in complete control
of all aspects of contract administration,
including submission and negotiation of all
claims on appellant's behalf and was appel-
lant's senior official in charge of the work
site until January, 1983, and that modifica-
tions 2 and 3 (Stip. 5, supra) were minor
modifications signed by subordinates of Mr.
Akwa under a delegation of authority from
him.
Applicable Statutory, Regulatory
and Contract Provisions
Under the CDA, all claims by a contractor
against the Government relating to a contract
shall be in writing and shall be submitted to
the contracting officer for a decision (41
U.S.C. § 605(a)). The CDA requires the con-
tractor to make a prescribed certification of
all claims over $50,000. The CDA does not
define a claim. Early in 1979, shortly after
enactment of the CDA, the Office of Federal
Procurement Policy (OFPP) issued interim
regulations defining a "claim" as a matter in
dispute and in March 1979 a Disputes Clause
was promulgated utilizing that definition, 44
Fed. Reg. 12524. That clause (DAR 7-602.6),
which was included in appellant's contract,
stated, in pertinent part:
Disputes. (a) This contract is subject
to the Contract Disputes Act of 1978 (41
U.S.C. 601, «et seqg.). If a dispute
arises relating to the contract, the
contractor may submit a claim to the
App. 50
Contracting Officer who shall issue a
written decision on the dispute in the
manner specified in DAR 1-314 (FPR
1-1.318).
(b) "Claim" means:
(1) a written request submitted to
the Contracting Officer;
(2) for payment of money, adjustment
of contract terms, or other relief;
(3) which is in dispute or remains
unresolved after a reasonable time for
its review and disposition by the
Government; and
(4) for which a Contracting
Officer's decision is demanded.
(c) In the case of disputes requests
or amendments to such requests for pay-
ment exceeding $50,000, or with any
amendment causing the total request in
dispute to exceed $50,000, the Contractor
shall certify, at the time of submission
as a claim, as follows:
I certify that the claim is made in good
faith, that the supporting data are
accurate and complete to the best of my
knowledge and belief; and that the amount
requested accurately reflects the con-
tract adjustment for which the contractor
believes the Government is liable.
(Contractor's
Name )
(Title)
(d) The Sevanduead shall pay the
contractor interest:
(1) on the amount found due on claims
submitted under this clause;
(2) at the rates fixed by the Secretary
of the Treasury, under the Renegotiation
Act, Public Law 92-41;
(3) from the date the Contracting Officer
receives the claim until the Government
makes payment.
The definition in the final OFPP regula-
tions issued the following year, was as
follows:
App. 52
ee oer,
ee ee Ee ee
(b) Definition of Claim:
(i) As used herein ‘claim’ means a
written demand or assertion by one of
the parties seeking, as a legal right,
the payment of money, adjustment or
interpretation of contract terms, or
other relief, arising under or relating
to this contract.
(ii) A voucher, invoice, or request for
payment that is not in dispute when
submitted is not a claim for the
purposes of the Act. However, where
such oubmi ssion is subsequently not
acted upon in a reasonable time, or
disputed either as to liability or
amount, it may be converted to a claim
under Section 6(a) of the Act...
(45 Fed.Reg. 31035 dtd May 9, 1980)
The OFPP prescribed a new Disputes
clause utilizing this language, and the new
clause was made a part of the Defense
Acquisition Regulations by the DAR council on
June 25, 1980 as paragraph (c) of the clause.
App. 53
Paragraph (b) of the new clause read as
follows:
{b) Except as provided in the Act, all
disputes arising under or relating to
this contract shall be resolved in
accordance with this clause.
The Federal Acquisition Regulation (FAR
33.201) uses essentially the same definition
except that the FAR states that "a voucher,
invoice, or other routine request for payment
that is not in dispute when submitted is not
a claim." (Emphasis added)
Section 12 of the CDA, 41 U.S.C. § 611,
provides for interest on contractor claims as
follows:
Interest on amounts found due contractors
on claims shall be paid to the contractor
from the date the contracting officer
receives the claim pursuant to Section
6({a) from the contractor until payment
thereof....
Appellant points out that the contract
Termination for Convenience of the Government
App. 54
dt A st teal hen
clause refers to the contractor's submission
as a “claim", particularly in paragraph (c)
thereof, to wit:
(c) After receipt of a Notice of
Termination, the Contractor shall submit
to the Contracting Officer his termina-
tion claim, in the form and'with certi-
fication prescribed by the Contracting
Officer.
The Government counters that the
regulation in effect at the time of the
termination here (DAR 8-213.2 (c)) expressly
prohibited interest on termination for con-
venience settlement amounts, as follows:
(c) Interest. No interest shall be
paid by the Government on the amount due
under a settlement agreement or a settle-
ment by determination. Interest may,
however, be allowed on successful con-
tractor appeals to the contracting
officer's determination in accordance
with the Payment of Interest on
Contractors' Claims clause in 7-104. 82.
App. 55
The FAR contains a substantially
identical prohibition (FAR 49.112-2(d)):
(d) Interest. The Government shall
not pay interest on the amount due under
a settlement agreement or a settlement
by determination. The Government may,
however, pay interest on a successful
contractor appeal from ae contracting
officer's determination under the
Disputes clause at 52.233-1.
The CDA does not specify who must
certify a claim on a contrractor's behalf
when it requires "the contractor" to certify
the claim. However, both the Federal
Acquisition Regulation (FAR) and its
predecessor, the Defense Acquisition
Regulation (DAR), furnish specific guidance
in this regard.
FAR 33.207(c) provides, in pertinent
part:
(c)(2) If the contractor is not an
individual, the certification shall be
executed by-
App. 56
(i) A senior company official in
charge at the contractor's plant or
location involved; or
(ii) An officer or general partner
of the contractor having overall respon-
sibility for the conduct of the con-
tractor's affairs.
Language identical to that in subsection
(c)(2) (i) and (ii) above was previously
applied in defense contracts through DAR
1-314(L)(2) and in other federal agency
procurements through Paragraph 1.7 of OFPP
Policy Letter No. 80-3 (45 Fed. Reg. 31,035
May 9, 1980).
DECISION
The Government's contention that the
August, 1982 cértification of appellant's
settlement proposal\ was ineffective because
Mr. Akwa, the individual who signed it, was
not authorized to do so is not supported by
the facts. Mr. Akwa executed the original
contract on appellant's behalf, negotiated
and executed modifications to the contract,
App. 57
and administered the contract with full
authority. He was the senior company
official in charge of the work site until
January, 1983. Consequently, under governing
regulations he was authorized to execute the
certification. See Transamerica Insurance
Co. v. United States [32 CCF @% 73,012], 6 Cl.
Ct. 367 (1984). There is no legal basis for
the Government's contention that Mr. Akwa
required a specific grant of authority from
the company's Board of Directors to execute
the certification and other documents for
appellant.
With respect to the question of whether
CD interest on the settled amount is due
appellant, we addressed the issue of whether
a settlement proposal is a claim for CDA
interest purposes in Racquette River Construc-
tion, Inc., ASBCA NO. 26486, 82-1 BCA
91 15,769. Faced with the identical Disputes
clause we have in this contract, we said:
In the instant case appellant
submitted its settlement proposal in the
App. 58
A= oe OO ele a amaliallagall
amount of $91,454 on 17 November 1980.
At that point its proposal was, to use
the terminology of the Disputes clause,
"a written request ... for payment of
money." However, it was neither for an
amount in dispute or unresolved beyond a
reasonable time, nor did appellant, at
that point, demand a decision by the
contracting officer. Appellant's
17 November 1980 settlement proposal was
therefore no a "claim" See, R.G.
Robbins Co., Ime. ASBCA NO. 26521,
7 January 1982, slip. op. at 7.
The DCAA audit report was issued on
16 January 1981. In that report, the
auditor questioned costs totalling
$32,138, and recommended approval of the
remaining $59,316 proposed by appellant.
Following a series of unsuccessful
settlement negotiations, held pursuant
to the provisions of the termination for
convenience clause, appellant, on
16 March 1981, requested that a contract-
App. 59
ing officer's final decision be issued.
On that date, having a written request
for payment of money, an amount in dis-
pute, and a demand for the issuance of a
contracting officer's final decision, we
conclude that appellant's proposal
ripened into a claim.
Appellant is therefore entitled to
be paid interest on the amount held
allowable in this decision from 16 March
1981 until payment thereof or any portion
thereof.
Cf. HSQ Technology, ASBCA No. 32272,
86-3 BCA 97 19,221 (prior history of disagree-
ments over amounts due under contract showed
that settlement proposal-upon being certified-
was actually ta disputed claim); also _ see
A Machine Company, ie.» ASBCA No.
29739, 86-1 BCA 7 18,684. No history (such
as we fourd in HSOQ Technology) is present in
this case. The settlement proposal was sub-
mitted as the first step in the usual and
5 entalt
ordinary process following a termination for
convenience.
The absence of such a transforming
history also means that the prohibition of
DAR 8-213.2(c) applies here. Cf. HSQ
Technology, supra. Any notion that the DAR
provision was merely a pre-CDA relic which
the DAR Council had neglected to retire has
been: dispelled by the almost identical
prohibition in FAR, supra, adopted long after
the CDA was enacted. The regulation supports
our conclusion that - at least when the
Disputes clause in this contract is present -
a termination for convenience settlement pro-
posal is not ordinarily a CDA claim when
submitted (whether certified or not).
Subssquent actions are usually necessary for
the matter to ripen into a claim. Racquette
River Construction, Inc., supra.
No such effective actions occurred in
this case. The belated labeling of the
settlement proposal as a CDA claim by appel-
lant's counsel and submission of a certifica-
App. 61
tion in August 1982 contrast sharply with
appellant's substantial concurrence with the
auditor's findings made that same month and
the large reduction in appellant's proposed
settlement which followed. Except for the
interest sought ($146,612.12), the settlement
amount ultimately agreed upon ($438,346) was
only $25,213.88 less than appellant's updated
proposal in December 1984 ($610,172). Thus,
aside from the interest issue introduced by
appellant's counsel, the termination for
convenience settlement proceeded to agreement
without apparent dispute.
Appellant argues that the Disputes
clause in this contract and the regulations
upon which it was based are contrary to the
clear mandates of the CDA that interest be
paid on all claims. It points to the revised
definition of claim in OFPP's 9 May 1980
policy letter (supra) as supporting its
position that the settlement proposal, when
certified, became a CDA claim.
Unlike FAR 49.112-2(d), supra, which
expressly prohibits payment of interest on
termination for convenience settlements, the
revised regulation does not refer to settle-
ment proposals expressly. Furthermore, the
change to the definition of claim, inter
alia, was described as a merely "technical
change". (45 F.R. 31035)
Neither the legislative history of the
CDA nor the administrative history of the
implementing regulations speak clearly on
whether CDA interest applies to a proposed
settlement following a termination for
convenience. Nor do we agree that the CDA
itself is so clear that the Disputes clause
in this contract and the regulations on which
it was based are invalid. There is a time-
honored presumption in favor of the validity
of an administrative determination made
pursuant to statute. Coleman v. Paccar,
iee., €24 U.S. 1301, 47 L. Ed. 2d 67 (1976);
Trans Akaska Pipeline Rate cases, 436 U.S.
631, 56 L. Ed. 591 (1978). In promulgating
App. 63
——————————EEeeVv'Vrlue
its interim regulation, the OFPP was acting
pursuant to statute (41 U.S.C. 405a). And
specifically applicable to whether interest
is allowable is the long established principle
that interest is not allowed against the
Government unless Congress or a contract
plainly authorizes it. This "entrenched
immunity" is a part of sovereign immunity.
Brookfield Construction Co. v. United States
[29 CCE 4 81;076),: 28 Cet. Ci.’ Sa, 662 B26
159 (1981).
Neither this Board nor the United States
Claims Court has been able to find that the
CDA or the Disputes clause plainly authorizes
payment of interest while the Government and
contractor are in a pre-dispute, negotiation
posture. Esprit Corp., Inc. v. United States
[32 cor ¢ 73,0601, 6 CL. Ce. - See <2008),
affirmed without discussion of this issue,
Appeal No. 85-996 (unpublished) (Fed. Cir.,
July 30, 1985) 4 F.P.D. 7 36; Hoffman
Construction Co. v. United States [32 CCF
q 73,279},. 7 Cl. €&. 928 42980); Racguecce
App. 64
River Construction, Ine. ,; supra; Fortec
Constructors, _ASBCA~ No. 27601, 983-1 BCA
q 16,402; Cf. J.M.T. Machine Company, Inc.,
ASBCA No. 29739, 86-1 BCA ff 18,684, motion
for recon. den. 86-2 BCA J 18,917.
However, we need not and do not decide
whether, under the "new" (1980) Disputes
clause, a dispute is a pre-condition to
entitlement to CDA interest.
Moreover, as we have discussed
previously, with regard to termination of
convenience settlements specifically the DAR
(and now FAR) prohibit such interest. Such
regulations have the force and effect of law,
and their mandates must be accorded the same
respect as a congressional enactment. Paul
v. United States [9 CCF { 71,972], 371 U.S.
245, 9L. Bd. 292 (1963).
We must respectfully disagree with the
contrary view of the Engineer Board (R.G.
Beer Corporation, ENG BCA No. 4885, 85-2 BCA
71 18,162; Barter Engineering Corporation, ENG
BCA Nos. 4754, 4791, 85-3 BCA f 18,342).
App. 65
Other cases cited by appellant are either
dictum (e.g., Tera Advanced Services Corp.,
GSBCA No. 7109, 85-2 BCA q 17,941) or clearly
involved disputed claims (e.g., Walber Con-
struction Company, Inc., HUD BCA No. 80-445-
C2, 83-2 BCA 1 16,885).
We conclude that appellant cannot
recover interest under the CDA on the agreed
settlement.
Our rejection of the claim for interest
on the settlement amount also effectively
disposes of appellant's claim for interest on
unpaid interest. Even if we had sustained
the basic interest claim, appellant would not
be entitled to recover interest on interest.
Central Mechanical, Inc., ASBCA No. 29193,
85-2 BCA 4 18,005; Sierracin/Sylmar, ASBCA
No. 31179, 86-1 BCA § 18,688, 3 January 1986.
The appeal is denied.
Dissenting Opinion of Administrative
Judge Duvall
I dissent from the holding of the
majority that the appelllant cannot recover
App. 66
a
interest on the agreed settlement because of
the requirement in the interim Disputes
clause utilized in the contract that the
claimed amount must be disputed, and because
a Defense Acquisition Regulation prohibited
interest on termination for convenience
settlement amounts. Section 12 of the CDA
requires payment of interest on contractor
claims. The Government cannot contravene the
plain meaning of a statute by enforcing a
contrary regulation or utilizing a Disputes
clause that denies payment of interest by
stretching the meaning of the word claim
beyond the commonly accepted definition
without the clear support of ilegislative
history. Appellant is due interest on the
settled amount from the date of contracting
officer receipt of the letter identifying
appellant's termination for convenience
proposal as a claim under the CDA and trans-
mitting a certification of the claim.
As the Beard noted in J.M.T. Machine,
ASBCA No. 29739, 86-1 BCA § 18,684, disagree-
App. 67
ment exists between and within the tribunals
regarding the requirement for the existence
of an antecedent dispute in order to have a
"claim" under the _ CDA. Racquette River
Construction, Inc., ASBCA No. 26846, 82-1 BCA
"1 15,769; Esprit Corp., Inc. v. United States
[32 CCF 9 73,069}, 6 Cl. Ct. 546 (1984),
aff'd by unpublished decision, Apeal No.
85-996 (Fed. Cir. July 30, 1985); Hoffman
Construction Co. v. United States [32 CCF
S 73,279}, 7 ©. €t. S26 4306037" Serecec
Constructors, ASBCA No. 27601, 83-1 BCA
1 16,402; R.G. Beer Corporation, ENG BCA No.
4885, 85-2 BCA § 18,162; Barter Engineering
Corporation, ENG BCA Nos. 4754 and 4791, 85-3
BCA 7 18,342; Vepco, Inc., ASBCA No. 26993,
on motion to dismiss, 82-2 BCA 7 15,824; R.G.
Robbins Co. Inc., ASBCA No. 26521, on motion
to dismiss, 82-1 BCA 4% 15,643; Tera Advanced
Services Corp., GSBCA No. 7109, 85-2 BCA
1 17,941.
The contradictory opinions expressed in
Racquette River, followed by the majority,
App. 68
and R.G. Beer illustrate the conflict over
application of the interim clause and the
meaning of the word claim in the CDA. The
ASBCA held in Racquette River that no CDA
claim exists where the contractor fails to
meet the requirments of the clause, including
the existence of a dispute. In R.G. Beer,
the Corps of Engineers Board took a contrary
position. It held that the definition in the
interim Disputes clause is inoperative because
it conflicts with the final OFPP deectubions
and accompanying clause which omitted the
requirement for the existence of a dispute to
have a claim, except in the case of invoices,
vouchers, and other regular payments under
the contract. The Corps Board concluded that
the interim clause was contrary to the intent
of Congress which was to provide interest on
monies found due on contractor's claims
whether settled or litigated, and to provide
an incentive for early submission of claims.
The majority opinion ignores the
fundamental precept that the starting point
for interpreting a statute is the language
itself. If the statutory language is clear,
it is ordinarily conclusive. See Consumer
Project Safety Comm. v. GTE Sylvania, Inc.
,
447 U.S. 102, 108 (1980). The word "claim"
as commonly used has a plain meaning. It is
defined as "a demand for something rightfully
or allegedly due; assertion of one's right to
something." Webster's New World Dictionary
(1968 edit.). I have found no other recog-
nized authority on either common or legal
usage applying the requirement of a dispute
to the meaning of the word claim. Under case
law, the conception of a claim against the
Government normally connotes "a demand for
money or for some transfer of public property"
United States v. McNinch, 356 U.S. 595, 599
(1958). However, the word has been given
special meaning in the context of particular
statutes. Cf., John C. Grimberg Co., Inc. v.
United States {30 CCF @% 70,884], 1 FPD 8
Ww
App. “70
(CAFC 1983) (Claims Court jurisdiction over
bid protests under the Federal Courts Improve-
ment Act of 1982). In order to amend the
common definition, e.g., require the existence
of an antecedent dispute, the Board would
have to find in the legislative history an
intent on the part of Congress to ive the
term a special meaning in the context of
Government contracting.
The history of Section 12, calling for
payment of interest, offers no clear insight
into the definition of the word "claim" as
used in the CDA. As stated in the Senate
Report, Section 12 executes recommendation 11
of the Commission on Government Procurement,
established by Congress in 1969 to examine
the existing procurement system. That recom-
mendation was to "Pay interest on claims
awarded by administrative and judicial
forums." In making this recommendation, the
successful party, and that these goals are
frustrated if final payment of a judgment
ignored long delays and losses resulting from
a lengthy mandatory review procedure. The
commission determined that without interest,
the contractor would bear additional financial
burdens as a result of such extended delays.
The commission also stated that it believed
payment of interest would serve as additional
inducement to settle claims short of litiga-
tion, noting that:
The prospect of agencies being
required to pay interest on claims
delayed by litigation encourages’ the
agencies to avoid these payments by
settling claims at an early stage and
gives the contractor added bargaining
power with the assurance of full payment
if the claim is eventually paid.
While the report may be read as implying
that the commission intended that interest be
paid on disputed claims, any such intent, if
it existed, was not carried out in the Senate
App. 72
bill which, in final form, was adopted by
both houses. The bill reported out of
committees of the Senate (S3178) stated in
Section 12 that "Interest on amounts found
due contractors on claims shall be paid to
the contractor from the date the claim under
Section 5 [now 6] accrues until payment Pi
the Senate joint committee report on the
legislation noted that the contractor's cost
ef financing required additional changed work
uncompensated by progress payments was a
legitimate business expense and stated that
the interest section of the bill:
provides interest to the contractor
upon a favorable decision on his claim
from the point in time the cause of
action raises [arises] or the additional
costs are incurred, whichever is later,
to the date of payment following either
a final decision of the agency board or
a court of competent jurisdiction, or a
settlement between the contractor and
the Government prior to a decision by
the agency boards or the courts.
(S. Rep. No. 1118, 95th Cong., 2d Sess. 32
(1978)).
When the bill was presented on the
fioor, st was amended to provide for
beginning interest when a claim was filed
with the contracting officer. Sen. Robert
Byrd explained that the change was deemed
necessary to fix the actual starting date of
interest, expressing concern that contractors
might delay submission of claims, preventing
early review and possible disposal of the
claim. The amendment, according to the
Senator, would "serve as an incentive for
contractors to submit claims as soon as they
are identified." (124 Cong. Rec. 36267
(1978)).
This history of the development of the
interest requirement provides no basis for
concluding that Congress intended to equate a
claim with a dispute in the context of payment
of interest. In fact, the evolution of the
App. 74
actual language of Section 12 indicated a
contrary intent. A claim could "accrue",
i.e., the cause of action could arise or
additional costs could be incurred with the
contractor bearing the cost of financing the
additional work, well before a disagreement
between the parties existed. The Senate
report indicates that Congress intended to
compensate contractors for such financing
costs. The last minute change in language to
begin interest from the claim filing date
does not affect this observation.
I also note that the Act itself (Pub. L.
No. 95-563), while not defining the word
claim, does not equate a claim with a dispute
and suggests that they are not synonymcus
terms. Its preamble identified it as an Act
"to provide for the resolution of claims and
disputes relating to Government contracts
awarded by executive agencies." (Emphasis
added) In two paragraphs, Sec 6(a) and
14(i), the CDA uses the word "claim" and
"dispute" separated by the disjunctive "or".
App. 75
oe VT
However, some support can be found in
the legislative history for the proposition
that a dispute must exist in order to have a
claim. The Senate Report, in outlining the
purpose of the Act, stated:
The Contract Disputes Act of 1978
provides a fair, balanced, and compre-
hensive statutory system of legal and
administrative remedies in resolving
Government contract claims. The Act's
provisions help to induce resolution of
more contract disputes by negotiation
prior to litigation; equalize the bar-
gaining power of the parties when a
dispute exists; provide alternate forums
Suitable to handle the different types
of disputes; and insure fair and equit-
able treatment to contractors and Govern-
ment agencies.
(S. Rep. at 1)
The Claims Court considered this
language, and the Procurement Commission's
intent to use interest as an incentive to the
App. 76
Government to timely settle claims to avoid
litigation, together with the established
doctrine that waivers of sovereign immunity
should be strictly construed, in concluding
that a claim must be disputed and that
Congress wanted interest to run against the
Government only when the Government delayed
in resolving disputes. Esprit Corp., supra.**
It is apparent that in conflicting
opinions, Boards and the Claims Court have
erred in attempting to divine a clear con-
gressional mandate with respect to either the
requirement or lack thereof for an antecedent
disagreement in order to have a written re-
**The facts in Esprit distinguish that
case from this appeal. There the contractor
claimed interest from the time of submission
of requests for contract modifications that
were not demands for specified sums of money
and were not addressed to the contracting
officer for decision under the Act. In
affirming the Claims Court decision, the
United States Court of Appeals for the
Federal Circuit in an unpublished opinion
determined that the "dispositive factor" was
that the contractor failed to submit the
types of claims called for in Sec. 6(a) of
the Act. My opinion does not conflict with
this determination.
App. 77
quest for payment constitute a claim, although
in my opinion the previously mentioned con-
gressional intent to compensate contractors
for financing costs and final language of the
bill both weigh in favor of an intent to
award interest on claims irrespective of the
existence of a dispute. Absent a clear
expression of intent in the legislative his-
tory to give the word claim a special meaning
in the context of Government contract law, it
should be given its plain meaning. There is
no reason to create an ambiguity where none
exists concerning the definition of the word
claim as used in the Disputes Act. In the
absence of ambiguity the doctrine of strict
construction of waiver of sovereign immunity
is not applicable here. The Act expressly
provides for payment of interest on claims.
Since the common definition of the word claim
does not contain a requirement for an existing
dispute, the requirement in the temporary
Disputes clause used in this contract that
the request for payment be in dispute in
App. 78
order to constitute a CDA claim contravenes
the plain meaning of the statute.
This defect in the definition of a claim
was removed in the 1980 final OFPP regulation.
I find it incongruous for the majority to
rely on "a time honored presumption in favor
of the validity of an administrative deter-
mination made pursuant to statute" in
applying the temporary Disputes Clause claim
definition to deny interest since that
definition was changed to eliminate the
element of a dispute from the definition in
the final Disputes clause adopted after
solicitation but prior to award of this
contract. I note, as the Engineer Board did
in R.G. Beer, that in 1982 the DAR Council
proposed revisions to the Disputes clause
which are set off in brackets in the language
quoted below:
(c)(1) As used herein, "claim"
means a written demand or assertion by
one of the parties seeking, as a matter
of right, the payment of money, adjust-
App. 79
ment, or interpretation of contract
terms, or other relief, arising under or
relating to this contract [and disputed
by the other party.] However, a written
demand by the Contractor seeking the
payment of money in excess of $50,000 is
not a claim until certified in
accordance with (d) below).
(2) A voucher, invoice, other rou-
tine request for payment [or other con-
tract administration matter such as a
change or settlement proposal] that is
not in dispute when submitted is not a
claim for the purpose of the Act. How-
ever, where such [contractor] submission
is subsequently disputed [by the Con-
tracting Officer] either as to liability
Or amount [or is] not acted upon in a
reasonable time, [the contractor] may
convert [it] to a claim pursuant to the
Act by complying with the submission and
certification requirements of this
clause.
App. 80
38 Federal Contracts Report 695 (Oct. 25,
1982)
The revisions were not adopted. In a
letter to the DAR Council commenting on the
proposals dated 28 January 1983, the OFPP
objected to the changes, stating that they
did not properly implement the Act, and that
"The Act does not require that a claim be
"disputed by the other party’, nor does it
require that a claim be submitted under the
Disputes clause." Government Contracts Re-
ports, CCF, % 92,682. I also find that the
labelling of appellant's proposal as a claim
under the CDA is an implicit demand for a
contracting officer's decision. Luedtke
Engineering Company, ENG BCA No. 4556, 82-2
BCA 9 15,851. The Board erred in applying
the interim Disputes clause in Racquette
River, and that decision should be overruled
to the extent it addressed the issue of
whether the settlement proposal was a claim
for CDA interest purposes under the clause.
App. 81
Since interest is due on this claim
under the Contract Disputes Act, the regula-
tion which prohibits interest on termination
for convenience settlements contravenes the
statute and does not apply. HSQ Technology,
ASBCA 32272, 86-3 BCA @ 19,221; Walber Con-
struction Company, Inc., HUD BCA No. 84-445-
C2, 83-2 BCA 7 16,885.
Further, I conclude that appellant's
termination for convenience proposal did not
fall within the request for payment exception
to the definition of a claim under either the
FAR, as the contracting officer held in his
final decision, or para (b)(ii) of the OFPP's
final regulation. The exceptions to the
definition of a claim are meant to apply to
routine payment requests under the contract
payments clause, such as progress payments,
and not to requests for extraordinary pay-
ments, including termination for convenience
settlement proposals. This view is buttressed
by the above mentioned failure to adopt the
clause changes proposed by the DAR Council in
App. 82
1982. I note in this connection that the
Termination for Convenience clause as well as
standard equitable adjustment clauses call
such requests for payment "claims".
I agree with the majority that appellant
is not entitled to interest on unpaid in-
terest. Such an award would be contrary to
the Board's decision in Central Mechanical,
Inc., ASBCA No. 29193, 85-2 BCA 7 18.005. In
denying such a claim the Board there noted
the general rule that where a statute requires
the payment of interest, only simple interest
can be awarded against the Government. The
Board cited Brookfield Construction Co. v.
United States [29 CCF 7 81,878], 661 F.2d 159,
170 (Ct. Cl. 1981), where the Court of Claims
expressed the view that there is no support
for the award of compound interest rather than
simple interest under the CDA. Appellant has
given us no sound reason for overturning our
decision in Central Mechanical.
App. 83
Relevant Portions of OFPP Interim
Regulations, 44 Fed. Reg. 12519-12524 (1979):
OFFICE OF MANAGEMENT AND BUDGET
Office of Federal Procurement Policy
UNIFORM RULES OF PROCEDURE FOR BOARDS OF
CONTRACT APPEALS AND RELATED REGULATIONS
Interim Final Rules
February 26, 1979
AGENCY: Office of Federal Procurement Policy
(OFPP), Office of Management and Budget.
ACTION: Notice of Interim Final Uniform
Rules of Procedure for Boards of Contract
Appeals and related regulations.
SUMMARY: This document sets out the text of
interim rules which boards of contract
appeals must adopt as well as rules which the
Department of Defense, the General Services
Administration, and the National Aeronautics
and Space Administration must incorporate in
their procurement regulations.
On November 1, 1978, the President
signed into law Pub. L. 95-563, the "Contract
Disputes Act of 1978." That Act, among other
things requires changes to the Rules of
App. 84
Procedure currently in use by the Boards of
Contract Appeals of the procuring agencies,
as well as certain other changes in contract
clauses and procurement regulations by
March 1, 1979. Proposed Rules of Procedure
and related regulations were published for
comment in the January 25, 1979, FEDERAL
REGISTER. The Interim final Rules and
regulations set forth below incorporate the
changes required by Pub. L. 95-563, and
reflect many of the comments received on the
proposed Rules and regulations. Some of the
changes to the Rules and regulations made as
a result of comments received are significant.
These Rules and regulations are therefore
issued as implementation of Pub. L. 95-563,
effective on March 1, 1979, on an interim
basis, and will automatically become final on
June 1, 1979 unless changed before that time.
This will enable the Office of Federal Pro-
curement Policy to evaluate additional com-
ments on the Interim Rules and regulations.
App. 85
The Rules of Procedure are to be adopted
uniformly by all Boards of Contract Appeals.
x *© & &
s. Payment of Interest on Contractor's
Claims. The Government shall pay interest on
contractor's claims as prescribed in paragraph
(d) of the Disputes Clause.
II. Disputes Clause.
1. Sections 7-103.12 and 7-602-6 of
the Defense Acquisition Regulation and
Sections 1-7.102-12 and 1-7.602-6 of the
Federal Procurement Regulations are amended
to provide as follows:
The Contracting Officer shall insert the
following clause in all contracts unless
exempted by the head of the agency under 41
U.S.C. 603(c).
Disputes. (a) This contract is subject
to the Contract Disputes Act of 1978 (41
U.S.C. 601, et seg.). If a dispute arises
relating to the contract, the contractor may
submit a claim to the Contracting Officer who
shall issue a written decision on the dispute
App. 86
in the manner specified in DAR 1-314 (FPR
1-1.318).
(b) "Claim" means:
(1) a written request submitted to the
Contracting Officer;
(2) for payment of money, adjustment of
contract terms, or other relief;
(3) which is in dispute or remains
unresolved after a reasonable time for its
review and disposition by the Government; and
(4) for which a Contracting Officer's
decision is demanded.
(c) In the case of disputed requests or
amendments to such requests for payment
exceeding $50,000, or with any amendment
causing the total request in dispute to
exceed $50,000, the Contractor shall certify,
at the time of submission as a claim, as
follows:
I certify that the claim is made in good
faith, that the supporting data are accurate
ond complete to the best of my knowledge and
belief; and that the amount requested
App. 87
EE CY
TT
accurately reflects the contract adjustment
for which the contractor believes the Govern-
ment is liable.
(Contractor's Name)
(Title)
(d) The Government shall pay the
contractor interest:
(1) on the amount found due on claims
submitted under this clause;
(2) at the rates fixed by the Secretary
of the Treasury, under the Renegotiation Act,
Public Law 92-41;
(3) from the date the Contracting Officer
receives the claim, until the Government makes
payment.
(e) The decision of the Contracting
Officer shall be final and conclusive and not
subject to review by any forum, tribunal, or
Government agency unless an appeal or action
is timely commenced within the times specified
by the Contract Disputes Act of 1978.
(f) The Contractor shall proceed dili-
gently with performance of this contract,
pending final resolution of any request for
relief, claim, appeal or action related to
the contract, and comply with any decision of
the Contracting Officer
(End of Clause)
* * * *
Relevant Portions of OFPP Policy Letter
80-3, Final Regulations, 45 Fed. Reg.
31035-31037 (1980):
Final Contract Disputes Regulatory Coverage
and Contract Disputes Clause
AGENCY: Office of Federal Procurement Policy,
Office of Management and Budget.
ACTION: Policy Directive.
SUMMARY: This policy directive sets forth
amendments to be made to the Federal Procure-
ment Regulations (FPR), the Defense Acquisi-
tion Regulations (DAR), and the National
Aeronautics Procurement Regulations (NASAPR)
relating to contract disputes regulatory
coverage and the contract dispute clause.
The final Disputes clause and regulations
also provide technical changes from the in-
terim clause and regulations with regard to
payment of interest, procedures for certifica-
tion of a claim exceeding $50,000, and other
areas. These changes are made to better
reflect the intent of the Contract Disputes
Act.
OFPP Policy Letter 80-3
To the Heads of Executive Departments and
Establishments
Subject: Regulatory Guidance on Pub. L.
95-563, the Contract Disputes Act of 1978
There is a need in Government for
uniformity and consistency in the application
of procurement policy. This directive
provides the uniform policy applicable to the
Contract Disputes Act of 1978. The clauses
and regulatory coverage that follow articulate
this uniform policy. The Defense Acquisition
Regulation (DAR), the Federal Procurement
Regulations (FPR), and the National Aero-
nautics and Space Administration Procurement
Regulations (NASA PR) shall be amended to
conform to this policy. This guidance
supersedes in its entirety the guidelines
previously published in the Federal Register,
Mod
'O
Ke)
Ke)
ae
i i
on March 7, 1979 (44 FR 12519), and June 14,
1979 (44 FR 24228).
I. Regulatory Coverage-Resolution of Claims
ha Contract Disputes Act of 1978:
(a) General. The Contract Disputes Act
of 1978 (Pub. L. 95-563, 41 U.S.C. 601-613)
establishes procedures and requirements for
asserting and resolving claims by or against
contractors relating to a contract subject to
the Act. In addition, the Act provides for
the payment of interest on contractor claims,
for the certification of contract claims in
excess of $50,000, and a civil penalty for
contractor claims that are fraudulent or
based on a misrepresentation of fact.
(b) Definition of Claim:
(i) As used herein "claim" means a
written demand by one of the contracting
parties seeking, as a legal right, the
payment of money, adjustment or interpretation
of contract terms, or other relief, arising
under or related to the contract.
App. 92
(ii) A voucher, invoice, or request for
payment that is not in dispute when submitted
is not a claim for the purposes of the Act.
However, where such submission is subsequently
not acted upon in a reasonable time, or
disputed either as to liability or amount, it
may be converted to a claim under Section
6(a) of the Act as provided in Section 3,
below.
(c) Government Policy on Settlement by
Mutual Agreement. It is the Government's
policy, consistent with the Act, to try to
resolve all claims by mutual agreement at the
contracting officer's level, without liti-
gation. Implementation of this policy
depends on an open mind with regard to the
matter in dispute and the adequacy of the
information provided in support of the claim
by both the contractor and the Government.
In appropriate circumstances, before issuance
of a contracting officer's decision on a
claim, informal discussions between the par-
ties, to the extent feasible, by individuals
App. 93
who have not participated substantially in
the matter in dispute, can aid in the
resolution of differences by mutual agreement
and should be considered.
ee
aie Initiation of a Claim-Except as
provided in the Act, (a) contractor claims
shall be made in writing and submitted to the
contracting officer for a decision, and (b)
claims by the Government against a contractor
shall be the subject of a contracting officer
decision.
4. Contracting Officer's Decision:
(a) When a claim by or against a
contractor cannot ke satisfied or settled by
agreement and a decision on the claim is
necessary, the Contracting Officer shall:
(i) Review the facts pertinent to the
claim;
(ii) Secure assistance from legal and
other advisors; and
(iii) Coordinate with the contract
administration office or Contracting Office
when appropriate.
eS. & & 2
S. Payment of Interest on Contractor's
Claims-The Government shall pay interest on a
contractor claim on the amount found due and
unpaid, from the date the Contracting Officer
receives the claim until the date payment is
made, at the rates fixed by the Secretary of
the Treasury pursuant to the Renegotiation
Act, Pub. L. 92-41.
6. Disputes Clause:
(a) The Act applies to all disputes with
respect to contracting officer decisions on
matters arising out of or relating to a
contract. Agency Boards of Contract Appeals
(BCA) created under the Act have the same
jurisdiction as the Court of Claims with
respect to a claim that is subject to the
Act. Thus, the statutory agency BCAs
continue to have all of the authority they
possessed before the Act with respect to
App. 95
disputes arising under a contract, as well as
authority to decide disputes relating to a
contract. The Disputes clause set forth in
Part II recognizes the all disputes authority
established by the Act, and states certain
requirements and limitations of the Act for
the guidance of contractors and contracting
agencies. It is not intended to affect the
rights and obligations of the parties as
provided by the Act, nor to constrain the
authority of the statutory agency BCAs in the
handling and deciding of contractor appeals
pursuant to the Act.
xz ©£& 2 @
II. Contract Disputes Clause
The following clause shall be included
in all contracts subject to the contract
Disputes Act unless (1) exempted by the head
of the Agency under 41 U.S.C. 603(c), or (2)
modified in accordance with DAR 1-314 or FPR
1-1.318:
Disputes Clause:
(a) This Contract is subject to the
Contract Disputes Act of 1978 (Pub. L.
85-563).
(b) Except as provided in the Act, all
disputes arising under or relating to this
contract shall be resolved in accordance with
this clause.
(c)(i) As used herein, “claim" means a
written demand or assertion by one of the
parties seeking, as a legal right, the
payment of money, adjustment or interpretation
of contract terms, or other relief, arising
under or relating to this contract.
(ii) A voucher, invoice, or request for
payment that is not in dispute when submitted
is not a claim for the purposes of the Act.
However, where such submission is subsequently
not acted upon in a reasonable time, or
disputed either as to liability or amount, it
may be converted to a claim pursuant to the
Act.
App. 97
(iii) A claim by the contractor shall be
made in writing and submitted to the contract-
ing officer for decision. A claim by the
Government against the contractor shall be
subject to a decision by the Contracting
Officer.
(d) For contractor claims of more than
$50,000, the contractor shall submit with the
claim a certification that the claim is made
in good faith; the supporting data are
accurate and complete to the best of the
contractor's knowledge and belief; and the
amount requested accurately reflects the
contract adjustment for which the contractor
believes the Government is liable. The
certification shall be executed by the
contractor if an individual. When the
contractor is not an individual, the
certification shall be executed by a senior
company official in charge at the
contractor's plant or location involved, or
by an officer or general partner of the
App. 98
contractor having overall responsibility for
the conduct of the contractor's affairs.
(e) For contractor claims of $50,000 or
less, the Contracting Officer must render a
decision within 60 days. For contractor
claims in excess of $50,000, the Contracting
Officer must decide the claim within 60 days
or notify the contractor of the date when the
decision will be made.
(f) The Contracting Officer's decision
shall be final unless the contractor appeals
or files a suit as provided in the Act.
(g) The authority of the Contracting
Officer under the Act does not extend to
claims or disputes which by statute or
regulation other agencies are expressly
authorized to decide.
(h) Interest on the amount found due on
a contractor claim shall be paid from the
date the claim is received by the Contracting
Officer until the date of payment.
(i) Except as the parties may otherwise
agree, pending final resolution of a claim by
App. 99
ooo
the contractor arising under the contract,
the contractor shall proceed diligently with
the performance of the contract in accordance
with the contracting officer's decision.
* * * *
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.