Petition for Writ of Certiorari — Unisys Corp. v. United States
Supreme Court brief1988
Ask Donna
What actually matters in this document.
Text
C
R & ~4 1 #) Supreme Court, U.S.
. FiLED
SEP 7 1988
<n pienaamamaes | YOSEPH F. SPANIOL, JR.
IN THE
Supreme Court of the United States
OCTOBER TERM, 1988
UNISYS CORPORATION,
Petitioner,
UNITED STATES OF AMERICA,
Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BERNARD FRIED CLARENCE T. KIPPS, JR.*
NORMAN A. STEIGER JOHN LLOYD RICE
UNISYS CORPORATION MILLER & CHEVALIER, Chartered
655 Fifteenth Street, N.W.
Washington, D.C. 20005
(202) 626-5840
* Counsel of Record
PR ENA SS RN IRR ORTBIT OREO TAMAR CS ROE ER
WILSON - EPES PRINTING Co., INC. - 789-0096 - WASHINGTON, D.C. 20001
QUESTIONS PRESENTED
1. Whether the United States Court of Appeals for
the Federal Circuit (“Federal Circuit”) may properly
avoid enforcing the Order of Precedence clause, which is
a widely used disputes prevention clause, by saying that
patently inconsistent clauses can be harmonized, when
Government procurement is about $200 billion a year and
Government contract disputes already total billions of
dollars?
2. Whether the Federal Circuit, contrary to estab-
lished doctrine, may properly construe an ambiguous op-
tion provision in favor of rather than against the drafter
and loosely rather than strictly?
(i)
TABLE OF CONTENTS
IIE asic cnt ccncitnivapinnnmnceesiieseniasanhinditnesies
TT osc ccnatnanoettabtaionghpnedpesensienenincinnmbicehitanatioe
I TE CI ncinscccnivtatnestensmiqntnnenaennsnneseshindinese
REASONS FOR GRANTING THE WRIT ....................
I.
Il.
III.
IV.
The magnitude of Government procurement and
the importance of the disputes prevention and
resolution procedures require the Federal Cir-
cuit to enforce the disputes prevention clauses
and provide doctrinal stability —..........000000200000000....
The Federal Circuit may not properly avoid en-
forcing the Order of Precedence clause by saying
that patently inconsistent clauses can be har-
ONC rT
The Federal Circuit may not properly disregard
the Federal rule of construction against the con-
EE EET EES SORTS TORT
The Federal Circuit may not properly disregard
the strict construction of option principle ..........
I ii dicidinsiel nbenilenaesasensbatilhvcestitanncvsesnimesinsnee
APPENDIX
Appendix A CAFC Opinion.......................0.000....
Appendix B Claims Court Opinion ..........0..000000000...
Appendix C Board Opinion ..........00....00000000000.00...-..
Appendix D Claims Court Judgment ............002.......
Appendix E CAFC Order Denying Panel Rehear-
| EERE ATE TRE a ane nee
Appendix F CAFC Judgment ...........0.0...00000000000....
Appendix G CAFC Order Denying In Banc Hear-
Oe cusaoman
Appendix H Contracting Officer’s Memorandum..
(iii)
Page
la
15a
40a
77a
78a
79a
80a
8la
iv
TABLE OF AUTHORITIES
Cases: Page
Consolidated Diesel Elec. Co. v. United States, 533
a Ee LGR, Gs Be werenicnintstnttisnsitbiiasatintnieincs 14
Cummings v. Bullock, 367 F.2d 182 (9th Cir.
| ON ene EAM SUM rr BR 3 TS SL 15
General Dynamics Corp., ASBCA No. 20882, 77-1 |
GS Senate NERS Me are Cw vt eh CO lees 15 )
Gorn Corp. v. United States, 424 F.2d 588 (Ct. Cl.
I ciateinscaiecrstticeate tiinitaiilliedctigsiicalisineepeiniiadaliniteaais tits 14 )
H & M Moving, Inc. v. United States, 499 F.2d 660 |
SEE A ID suiendinetiaicsipidemeghaclaiiibadinbibaibids 13
J.E.TS., Inc., ASBCA No. 26135, 82-2 BCA |
ON ee ee 15
Lear Siegler, Inc., ASBCA No. 12164, 69-1 BCA )
, RDB ene nie tee a chine 15
Peter Kiewit Sons’ Co. v. United States, 109 Ct. Cl. |
BP MINED sisiceicrcocernsiontaeisceinip ithiioncnsusiacaitanaaananiadbaniies 14
Space Age Eng’g, Inc., ASBCA No. 22901, 78-2
Re Se esirvtntbcctae eee 15
Sturm v. United States, 421 F.2d 723 (Ct. Cl.
I idecesiatenitiateacnisbb icing cbiiainaiig ici: tanldidbideaapaliibiia 13
Sun Shipbuilding & Dry Dock Co. v. United States,
Be ¢ £ + fh Seay 13
Trio-Tech, Inc., VACAB No. 598, 68-1 BCA {] 6828.. 17
United Pac. Ins. Co. v. United States, 497 F.2d
TR | RRR UE See Sedna nan: Mr x RO 14
United States v. Seckinger, 397 U.S. 203 (1970)... 4,13
United States v. Turner Constr. Co., 819 F.2d 282
CR er EN 14
'
Statutes :
I i 2
Regulations:
ASPR §§ 1-1502 to 1-1504 (1974) 20002. 15
PE EE TR IC CEI 17
DAR §§ 1-1501 to 1-1503 (1983) 00. 15
Vv
TABLE OF AUTHORITIES—Continued
Legislative Materials: Page
H.R. Rep. No. 1300, 96th Cong., 2d Sess. (1980) .... 7
Miscellaneous:
4 Williston on Contracts § 620 (3d ed. 1961) ........... 15
IN THE
Supreme Court of the United States
OCTOBER TERM, 1988
No.
SPERRY CORPORATION,
Petitioner,
Vv.
UNITED STATES OF AMERICA,
Respondent.
PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
Petitioner, Sperry Corporation,’ respectfully prays that
a writ of certiorari issue to review the judgment and
opinion of the United States Court of Appeals for the
Federal Circuit entered in this proceeding on April 21,
1988.
OPINIONS BELOW
The opinion of the United States Court of Appeals
for the Federal Circuit (App. at la-l4a)* is reported
at 845 F.2d 965. The opinion of the United States Claims
‘Sperry Corporation was merged into Burroughs Corporation
as of November 12, 1986. Burroughs Corporation changed its
name to Unisys as of November 13, 1986. Unisys has no parent
company, subsidiaries or affiliates.
2 “App.” refers to the Appendix to this Petition.
2
Court (App. at 15a-39a) is reported at 9 Cl. Cts. 488.
The opinion of the Armed Services Board of Contract
Appeals (App. at 40a-76a) is reported at 83-2 BCA
7 16,841.
JURISDICTION
The judgment of the Court of Appeals (App. at 77a)
was entered on April 21, 1988. A timely petition for
panel rehearing was denied on June 9, 1988. (App. at
78a). This petition for certiorari was filed within 90
days after that date. This Court’s jurisdiction is invoked
under 28 U.S.C. § 1254(1).
STATEMENT OF CASE
By failing to apply the plainly applicable Order of
Precedence clause, the Federal rule of construction
against the drafter and the settled rule of strictly con-
struing options, the Federal Circuit transformed a rela-
tively routine case into an enormously important Govern-
ment contract case justifying this Court’s review. The
result of the Federal Circuit’s decision is to create chaos
rather than doctrinal stability and increase disputes and
litigation, which already involve billions of dollars. This
decision undermines the very reason for the Federal Cir-
cuit’s existence.
The Government spends about $200 billion a year for
the purchase of a wide variety of products and services,
including sophisticated weapons systems, construction of
dams, roads, and buildings, and research and develop-
ment to advance the state-of-the-art. Contract clauses
and the Contract Disputes Act of 1978 provide carefully
developed and coordinated contractual, administrative
and judicial procedures to prevent and resolve Govern-
ment contract disputes.
Most Government contracts contain special provisions
tailored to fit the particular acquisition, general provi-
sions included in all Government contracts, and a multi-
tude of other documentary data such as statements of
a
es es SS
3
work, drawings and specifications. Because inconsisten-
cies inevitably exist among these provisions, the contracts
contain an Order of Precedence clause. The Government
developed the clause to serve the imrortant function of
specifying which provision in the contract the Govern-
ment wants to be given priority, thereby resolving the
inconsistency in accordance with the Government’s inten-
tion and preventing a dispute and litigation.
The contract at issue was awarded to Petitioner to
design, fabricate, test and deliver a LORAN navigation
system (Item 0001). Special provisions, including a spe-
cial acceptance provision tailored to meet the needs of
this procurement, were included in “Part II The Sched-
ule” and the Order of Precedence clause made the Sched-
ule provisions controlling over other parts of the contract
in the event of inconsistency. (App. at 45a).
The Schedule granted the Government option rights
but limited the time within which the rights could be ex-
ercised to “the period specified in the Schedule.” The
period specified in the Schedule is “no later than 120
days after final acceptance by the Government of
Item 0001,” which was the first system. (App. at
27a). The Schedule specifies that final acceptance of
Item 0001 occurs “upon successful completion of DT&E
Field Test at destination” (App. at 27a), which was
February 3, 1978. There are two other acceptance pro-
visions in the contract, each providing for a time for ac-
ceptance different from each other and different from
the acceptance clause in the Schedule. The dispute before
the Federal Circuit was whether the Government timely
exercised options to purchase additional navigation sys-
tems.
As the Claims Court pointed out, the various clauses
for acceptance in the contract are inconsistent and one
or more must fall. (App. at 32a). The acceptance event
specified in the Schedule, which the Order of Precedence
4
clause makes controlling, occurred on February 3, 1978.
(App. at 23a). The times of acceptance under the other
two acceptance clauses could be as late as March 20,
1979. The time of acceptance found by the Federal Cir-
cuit was March 20, 1978, which is not the same as the
time specified under any of the acceptance clauses or any
place in the contract. It is sophistry for the Federal Cir-
cuit to conclude that these different times (February 3,
1978, March 20, 1978 and March 20, 1979) could be
“harmonized” which was the Court’s reason for not en-
forcing the Order of Precedence clause. Such a decision
effectively nullifies the clause in the eyes of lawyers and
the Government agencies and contractors who read and
are guided by the Claims Court and Federal Circuit
decisions.
Failure to give effect to the Order of Precedence clause,
when plainly applicable, defeats the Government’s in-
tention in creating the clause and makes every incon-
sistency in a Government contract a potential dispute to
be resolved through litigation. Because the “boilerplate”
in Government contracts is so voluminous, these incon-
sistencies inevitably are found in large numbers. The
disputes resolution process will not be able to handle the
mountains of litigation that a de facto invalidation of the
Order of Procedence clause will cause.
The acceptance clause in the Schedule should have been
applied in accordance with its terms as required by the
Order of Precedence clause, or if ambiguous, the Federal
Circuit should have applied the well-established Federal
rule of construction against the drafter. That Federal
rule of contract construction is an extremely important
Government contract principle. The failure of the Fed-
eral Circuit tc apply that principle to the instant case is
contrary to this Court’s decision in United States v.
Seckinger, 397 U.S. 203, 210 (1970), and numerous Court
of Claims and Federal Circuit decisions. In addition, the
Court’s failure to apply the well-settled strict construc-
5
tion of options rule now casts doubt upon its future via-
bility in Government procurement.
Petitioner delivered the additional systems to the Gov-
ernment at the direction of the Contracting Officer and
filed its claim for an equitable adjustment in the con-
tract price on the basis that the option exercise was un-
timely.* The Contracting Officer and the Armed Services
Board of Contract Appeals (“Board’’) denied Petitioner’s
claim (with a dissenting opinion at the Board). The
Claims Court reversed the Board and entered judgment
for Petitioner in the amount of $6,121,590. The Court
of Appeals for the Federal Circuit sitting in a three judge
panel reversed the Claims Court, with a concurring
opinion stating that the basis for the majority decision
was wrong. The Court denied a timely motion for panel
rehearing and the suggestion for rehearing in banc.
The contract is a performance contract which required
Petitioner to design and build a highly sophisticated
LORAN navigational system. It was necessary for Peti-
tioner to advance the state of the art to meet the per-
formance requirements set by the Government. (App. at
41a). The Government needed additional systems, but
before ordering them, wanted to know that the first sys-
tem (Item 0001) met the performance requirements.
Successful completion of the DT&E Field Test provided
that crucial information. The Board found that “. . .
these tests demonstrated the ability of the LORAN chain
to function in accordance with the contract requirements
. .’ (App. at 54a). Therefore, successful completion
of the DT&E Field Test was an appropriate event to
8 Petitioner encountered substantial problems in advancing the
state of the art that caused a two-year delay in contract per-
formance. As a result, costs incurred for the basic chain and for
each fixed price option substantially exceeded the respective con-
tract prices. (Board Finding 49, App. at 58a). Petitioner’s claim
is for unrecovered costs for the delivered option chains. (Board
Finding 48, App. at 57a).
Te
6
mark acceptance of Item 0001 and to start the 120-day
period for exercise of the option.
Before the dispute arose, the Contracting Officer’s in-
terpretation was the same as Petitioner’s; he informed
the Administrative Contracting Officer that final accept-
ance would take place “at the completion of DT&E (field)
Testing.” (App. at 8la, emphasis added).
It is undisputed that the DT&E Field Test was suc-
cessfully completed on February 3, 1978 and that the
Government did not exercise its option within 120 days
after that date. (App. at 54a). Therefore, the pur-
ported option exercise was untimely and the decision of
the Claims Court should have been affirmed.
Here, there were two other acceptance clauses in the
contract calling for different acceptance dates. The term
“upon” was used in inconsistent ways in the contract.
The normal time for acceptance was the date of
execution of a DD250 in the absence of an acceptance
provision specifying a different time. These circumstances
justified calling into play and enforcing the Order of
Precedence clause, and the construction against the
drafter and strict construction of options principles. The
Federal Circuit adopted a time for acceptance not speci-
fied in the Schedule or in any of the three acceptance
clauses or in any piace in the contract; resolved the am-
biguity in favor of, instead of against, the drafter of the
contract; and construed the options liberally.
In reality, the Federal Circuit rendered an ad hoc
decision that is patently incorrect and contradicts its
reason for existence—doctrinal stability. The Court
reached a result that throws contract administration of
inconsistent provisions into chaos and encourages litiga-
tion. The Federal Circuit is a great institution with a
rich heritage and an important role in our judicial sys-
tem. Ad hoe decisions like the instant one, however, fall
short of the quality required of the Federal Circuit which
7
has the exclusive appellate jurisdiction of Government
contract claims.
REASONS FOR GRANTING THE WRIT
I. The magnitude of Government procurement and the
importance of the disputes prevention and resolution
procedures require the Federal Circuit to enforce the
disputes prevention clauses and provide doctrinal
stability.
One of the primary reasons for the creation of the
United States Court of Appeals for the Federal Circuit
was to provide doctrinal stability in certain areas of law
such as patents and Government contract claims. Accord-
ingly, the Circuit was given exclusive appellate jurisdic-
tion in these special areas.
In creating the Circuit Congress stated:
Since the jurisdiction of the Court of Appeals for
the Federal Circuit consists of an unusual num-
ber of complex cases in which current law lacks
uniformity or is inconsistently applied, and since the
new court’s decisions are intended to have nation-
wide precedential effect, the legislation authorizes the
judges of the Federal Circuit to determine the size
of the panels in which the court will sit.... This
permits the Federal Circuit to sit in panels of more
than three judges, but as less than a full en banc
court, for cases in which authoritativeness of deci-
sion and doctrinal stability could be enhanced by use
of larger panels.
H.R. Rep. No. 1300, 96th Cong., 2d Sess. 18 (1980).
The Government spends about $200 billion annually for
procurement. Contract disputes run into billions of dol-
lars. It is, therefore, imperative that the Federal Circuit
render quality decisions that enforce the disputes preven-
tion clauses and provide reliable guidance to the Govern-
ment and its contractors in resolving disputes.
8
Doctrinal stability is essential for parties to Govern-
ment contracts to understand their rights and responsi-
bilities. It enables both parties to better evaluate the
probable outcome of litigation and therey settle or
not initiate claims. The Federal Circuit’s decision in
the instant case, however, tells the Government contract-
ing community that the probable outcome of a case in the
Circuit defies evaluation. The contract terms and three
well established and widely relied upon Government con-
tract principles were plainly applicable but not applied.
In their place the Court substituted ad hoc views that
are wrong and contradict the objectives of eliminating
disputes through use of contract clauses and providing
doctrinal stability.
Unless the Supreme Court insists upon the continued
application of the Order of Precedence clause and the
well-settled rules of construction, it will have permitted
the Federal Circuit to open the “floodgates” to endless
litagation arising from disagreements about inconsistent
contract provisions and ambiguous contract language.
II. The Federal Circuit may not properly avoid enforc-
ing the Order of Precedence clause by saying that pat-
ently inconsistent clauses can be harmonized.
The Schedule grants the Government option rights and
provides in Section 6:
The Contracting Officer may exercise these options
at any time within the period specified in the Sched-
ule by giving written notice to the Contractor.
(b) The time for exercise of the options is set forth
in Section E hereof.
Section E of the Schedule provides:
(T)he Government may exercise this option at any
time during contract performance, but not later than
120 days after final acceptance by the Government
of Item 0001.
(App. at 3a).
9
The Inspection and Acceptance clause in the Schedule
(Section I) provides for final acceptance of Item 0001
to occur as follows:
Final inspection and acceptance upon successful com-
pletion of DT&E Field Test at destination.
(App. at 18a).
Finally, the Schedule contained an Order of Precedence
Clause (Section J—Special Provisions, paragraph 5),
which stated:
In the event of an inconsistency in this contract,
unless otherwise provided herein, the inconsistency
shall be resolved by giving precedence in the follow-
ing descending order: 1) Schedule (excluding State-
ment of Work, the Specifications, and Contract Data
Requirements List); 2) General Provisions; 3) the
other provisions .. .; 4) Statement of Work... .
(App. at 20a).
The function of the phrase “upon successful comple-
tion of DT&E Field Test” in the context of Section I
is to specify within the Schedule the time for accept-
ance of Item 0001. This provides within the Schedule
the determinable starting time for the 120-day option
period. If the term “upon” does not mean “at the
time of,’ then the special acceptance clause has no
meaning whatsoever; there is no time specified within the
Schedule for acceptance of Item 0001; and there is no
period specified within the Schedule for exercise of the
option. The plain meaning of the term “upon” in this
context is ‘at the time of.” This was the understanding
of the Contracting Officer and of the Government in-
spector before the dispute arose. (App. at 8la). There-
fore, the period specified in the Schedule for exercise of
the option is not later than 120 days after successful
completion of the DT&E Field Test.
The majority’s view that the inconsistent acceptance
provisions and times (February 3, 1978, March 20, 1978
10
and March 20, 1979) can be harmonized is unquestion-
ably wrong. As pointed out by the Claims Court:
The acceptance terms of this contract are inconsist-
ent and one or more must fall.
(App. at 32a). The acceptance clause in the Schedule
provides for acceptance “upon successful completion of
DT&E Field Test at destination” and that was indisput-
ably February 3, 1978. (App. at 18a). The Statement
of Work {| 5.2.4 acceptance clause provides “Acceptance
will take place following successful completion of DT&E
and correction of design deficiencies.” (App. at 21a,
emphasis added.) Under the Correction of Deficiencies
clause Petitioner was required to correct all deficiencies
discovered within twelve months after acceptance, which
under the Federal Circuit’s holding was one year after
March 20, 1978. (App. at 30a). One clause that pro-
vides for acceptance to occur prior to and another clause
providing for acceptance to occur after correction of de-
sign deficiencies cannot be harmonized. Paragraph 6 of
Task I has the same inconsistency and provides for ac-
ceptance after acceptance. (App. at 21a). It is obvious
that these different acceptance times and clauses cannot
be “harmonized”. None of these times or clauses can be
harmonized with the March 20, 1978, date of signing the
DD 250 which the Federal Circuit found was the accept-
ance date. The acceptance times are different and there-
fore inconsistent. The Order of Precedence clause had to
be applied to choose the correct date of acceptance.
The majority opinion of the Federal Circuit inter-
preted “upon” to mean “shortly afterward” which de-
prived the special acceptance clause in the Schedule
of any meaning whatsoever when the Order of Prece-
dence clause made it controlling. That interpretation
says that the starting date for the 120-day option period
is “shortly after” the event specified as the starting date
in the contract. That interpretation also is contrary to the
a >"
11
terms of the Schedule because it provides no determin-
able starting date within the Schedule.
Judge Bissell’s concurring opinion points out that the
majority’s interpretation of “upon” to mean “shortly
afterward” is wrong:
The majority decision turns on the proposition that
“upon” means “shortly afterward,” and that we
must so interpret it throughout the contract. Exam-
ining the Title and Risk of Loss clause belies this
position. That clause states that title to supplies
“shall pass to the Government upon formal accept-
ance” (emphasis added). In this clause, it is obvious
that “upon” means “at the time of acceptance,” and
not “shortly afterward.”
(App. at 18a).
The term “upon” does not mean the same thing
throughout the contract and its meaning is determinable
only by examining its function and context. The only
function of the term “upon successful completion of
DT&E Field Test” in the context used in the special
acceptance clause in the Schedule is to designate in the
Schedule the time when acceptance of Item 0001 will
occur, which starts the 120-day option period as provided
in Section E of the Schedule.
The Federal Circuit majority decision recognized that
the purpose of Section I, the acceptance clause in the
Schedule, was to specify the time and place for accept-
ance, but inexplicably held that acceptance did not take
place at either the time or place specified in Section I.
The majority states that this clause:
. . . Specifies the time when and the place where the
government affirmatively finally will inspect and ac-
cept the LORAN 1 chain.
(App. at 5a).
Although not a model of draftsmanship, the “In-
spection at Origin” clause does two things: it specifies
the time at which (“upon successful completion of
12
DT&E field tests”) and the place where (“at des-
tination”) final inspection and acceptance shall take
place.
(App. at 7a).
These statements are correct. The time for acceptance
was “upon successful completion of DT&E Field Test at
destination” which was February 3, 1978. The place for
acceptance was at the Government sites at which the
equipment had been installed. Successful completion of
DT&E Field Test took place at Eglin AFB, Florida,
where the Monitor Synchronizer Group of the chain was
located. The Government representative witnessed and
affirmatively signed the inspection document marking the
successful completion of the final DT&E Field Test. He
did so at one of the places designated in the contract.
The majority substituted “shortly afterward” for
“upon” and mistakenly thought that the DD250 was
signed at destination. The DD250 was signed at Hans-
com AFB, Massachusetts, which was not the destination
of the chain. Thus, the majority’s holding that the Gov-
ernment accepted the LORAN chain upon signing the
DD250 is contrary to both the terms of the acceptance
clause and the majority’s own interpretation of the clause.
In the eyes of the Government contracting community,
the Federal Circuit’s decision cripples the Order of Prece-
dence clause and makes every contract inconsistency a
potential dispute to be resolved through litigation.
III. The Federal Circuit may not properly disregard the
Federal rule of construction against the contract
drafter.
There was a split decision at the Board. The Board’s
decision was reversed by the Claims Court and the con-
curring opinion states that the basis of the majority opin-
ion is wrong. There are three possible acceptance clauses
with each being inconsistent with the other and with
13
each specifying acceptance times different from the other.
The term “upon” is used in inconsistent ways in the con-
tract. The majority decision recognized that the contract
was “not a model of draftsmanship,” “upon” is susceptible
to different meanings, and that the acceptance clause in
the Statement of Work is inconsistent with Petitioner’s
reading of the acceptance clause in the Schedule. (App.
at 7a). The majority nevertheless disregarded the widely
used construction against the drafter principle relied
upon by the Claims Court. Instead, the majority pro-
ceeded to interpret “upon” as meaning “shortly after-
ward” which gives the final acceptance clause in the
Schedule absolutely no meaning when the contract ex-
pressly provides that it is controlling.
In United States v. Seckinger, 397 U.S. at 210, this
Court, citing Court of Claims precedents, established the
construction against the drafter principle as a federal
rule of contract interpretation. This Court stated:
in fashioning a federal rule we are, of course, guided
by the general principles such as that involved here.
Among these principles is the general maxim that a
contract should be construed most strongly against
the drafter, which in this case was the United States.
Where “a contract that has been written by the gov-
ernment . . . is ambiguous, the ambiguity will be re-
solved against the drafter of the document (the govern-
ment) ...” Sun Shipbuilding & Dry Dock Co. v. United
States, 393 F.2d 807, 816 (Ct. Cl. 1968) cited with ap-
proval in Seckinger. As Judge Davis pointed out in
Sturm v. United States, 421 F.2d 723, 727 (Ct. Cl. 1970):
“This oft-repeated and much-applied rule (contra profer-
entem) ... puts the risk of ambiguity, lack of clarity,
and absence of proper warning on the drafting party
which could have forestalled the controversy; it pushes
the drafters toward improving contractual forms; and it
saves contractors from hidden traps not of their own
making.” See also Gorn Corp. v. United States, 424 F.2d
14
588, 592 (Ct. Cl. 1970) ; Consolidated Diesel Elec. Co. v.
United States, 533 F.2d 556, 574 (Ct. Cl. 1976); H & M
Moving, Inc. v. United States, 499 F.2d 660, 671 (Ct. Cl.
1974) ; Peter Kiewit Sons’ Co. v. United States, 109 Ct.
Cl. 390, 418 (1947).
The Federal Circuit heretofore has applied the rule.
For example, in United States v. Turner Constr. Co.,
819 F.2d 283, 286 (Fed. Cir. 1987), the Court held “hav-
ing concluded that Turner’s interpretation of the con-
tract was reasonable, we apply the rule of contra pro-
ferentum, which requires that a contract be construed
against the party who drafted the document.”
A contractor’s reasonable interpretation of a contract
drafted by the government “. . . will prevail . . . even
though the Government’s interpretation may be a more
reasonable one since the Government drafted the con-
tract.” United Pac. Ins. Co. v. United States, 497 F.2d
1402, 1407 (Ct. Cl. 1974). Petitioner’s interpretation
was reasonable and was precisely the interpretation of
the Contracting Officer and the Government's principal
inspector before the dispute arose. The Contracting Of-
ficer’s March 12, 1976 letter to the Administrative Con-
tracting Officer stated:
Subject contract provides that final acceptance of the
entire Ground Chain shall take place at the comple-
tion of DT&E (field) Testing.
(App. at 8la, emphasis added). The failure of the Fed-
eral Circuit to apply the construction against the drafter
federal rule requires reversal.
IV. The Federal Circuit may not properly disregard the
strict construction of option principle.
As the Claims Court appropriately recognized:
Inasmuch as the purpose of determining the ac-
ceptance date of Chain 1 is to discover the beginning
date of the 120-day option period the court is bound
15
to construe the terms of the contract strictly. Indeed,
the general attitude of the courts and the ASBCA
is to strictly construe contractual option provisions
because the options subject contractors to potentially
major risks which should not be extended beyond the
limits the contractor had agreed to accept.
(App. at 31a).
It was well-settled that option contracts “are strictly
interpreted in favor of the party bound and against the
party that is not bound.” 4 Williston on Contracts § 620
at 753 (3d ed. 1961) ; see, e.g., Cummings v. Bullock, 367
F.2d 182, 186 (9th Cir. 1966), where the court, in a
lease option to purchase agreement, applied both the strict
construction of options and construction against the
drafter rules.
The Federal Procurement Regulations reflect the pol-
icy in favor of strictly limiting the period in which an
option may be exercised. See ASPR §§ 1-1502-1 to 1-1504
(1974); DAR §§ 1-1501 to 1-1503 (1983). As pointed
out by the Board in Lear Siegler, Inc., ASBCA No. 12164,
69-1 BCA { 7563 at 35,020:
ASPR 1, Part 15, “Options,” provides clear Depart-
mental policy guidance to the effect that an option
contract shall fix the period within which the option
may be exercised, and that the fixed period shall in
all cases be kept to a minimum, for the stated reason
that options require offerors to guarantee prices for
definite periods of time with no assurance that orders
will be placed.
In General Dynamics Corp., ASBCA No. 20882, 77-1
BCA { 12,504, the Board held that a purportedly timely
option exercise which varied the delivery schedule was
invalid and a subsequent purported option exercise which
corrected the schedule was invalid because it was one
day late. See also J.E.T.S., Inc., ASBCA No. 26135, 82-2
BCA § 15,986 at 79,274 (“Exercise of an option must be
strictly construed.”), and Space Age Eng’g, Inc., ASBCA
seen
16
No. 22901, 78-2 BCA { 13,543 (option terms strictly con-
strued and that the Government’s attempted option exer-
cise was a day late and invalid).
The federal law was well settled that options are to
be strictly, not expansively, construed. Although relied
upon by the Claims Court, the Federal Circuit majority
opinion does not even mention this principle. The con-
curring opinion attempts to distinguish this principle on
the ground that the trigger to the 120-day option period
is not a part of the option agreement.
The failure of the Federal Circuit to apply the strict
construction of options and construction against the
drafter rules and the Order of Precedence clause appears
to have been based on the notion that acceptance could
not “automatically” take place upon the happening of
an event. Such a notion is contrary to the terms of
the contract, the understanding of the Contracting Officer
and the Government's inspector before the dispute arose,
the regulations, as well as the cases. The concurring
opinion recognized that the parties could agree on the
happening of an event as the time of acceptance.
The contract terms plainly specify an event and do
not require a DD250 for acceptance. (All of the accept-
ances provisions in the contract provide for acceptance to
occur upon the happening of an event.) In performance
contracts, tests are the primary means of inspection. The
successful completion of the DT&E Field Test on Febru-
ary 3, 1978 represented the successful completion of 150
performance requirements tests and provided the critical
information needed for option exercise. The Board found
that: “The successful completion of these tests demon-
strated the ability of the LORAN chain to function in
accordance with the contract requirements.” (App. at
54a). It therefore made sense to start the 120-day op-
tion period at the time the Government’s inspector signed
the final test (inspection) marking the successful com-
pletion of all the performance requirements. Acceptance
ee Oe
17
of Item 0001 triggered the 120-day option period, but
did not excuse Petitioner from complying with any un-
performed terms of the contract.
Petitioner’s interpretation of the time of acceptance of
Item 0001 was made known to the Contracting Officer
prior and subsequent to February 3, 1978. Before the
dispute arose, the Contracting Officer and the Govern-
ment inspector understood that “upon” in the applicable
acceptance clause meant at successful completion of the
DT&E Field Test. (App. at 8la).*
The regulations relied upon by the majority expressly
recognize that the time of acceptance depends on the
contract provisions. ASPR § 14-306 (1974) provides:
Acceptance of Supplies or Services. . . . (b) De-
pending upon the provisions of the contract, accept-
ance may be effected prior to, at the time of, or
after delivery.
{Emphasis added).
Here, the provisions of the contract covering Item
0001 expressly called for acceptance earlier than delivery
and acceptance at a time different from the date of sign-
ing the DD250. There is no basis in the regulations to
disregard a contract provision specifying a time for ac-
ceptance different from the date of signing the DD250.
The cases establish that final Government acceptance
can take place upon the successful completion of inspec-
tions without the execution of a DD250. See Trio-Tech,
Inc., VACAB No. 598, 68-1 BCA { 6828 at 31,557 n.3
(acceptance was effected by final inspection and pay-
ment, even though there was no “evidence of a formal
written acceptance,” because the contract provided that
*The majority decision’s reference to the parties’ interpretation
during performance of the contract is to statements made after
the dispute arose and are in the context of complying with the
Government's demands in order to receive payment on Item 0001.
(App. at 37a.)
®
18
“Taleceptance will be the date the Veterans Administra-
tion receives satisfactory inspection or test report.’”’) and
cases cited by Claims Court.
Instead of providing doctrinal stability, the Federal
Cireuit’s decision in the instant case created turmoil in
areas that had been well-settled.
CONCLUSION
WHEREFORE, for the foregoing reasons, Petitioner
respectfully requests that this Court issue a writ of cer-
tiorari to the United States Court of Appeals for the
Federal Circuit.
Respectfully submitted,
BERNARD FRIED CLARENCE T. KIPppPs, JR.*
NORMAN A. STEIGER JOHN LLOYD RICE
UNISYS CORPORATION MILLER & CHEVALIER, Chartered
655 Fifteenth Street, N.W.
Washington, D.C. 20005
(202) 626-5840
* Counsel of Record
Retic
ae
see
ee
te
oe
ih
APPENDICES
CCC
la
APPENDIX A
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1475
SPERRY CORPORATION,
Plaintiff-A ppellee,
Vi
THE UNITED STATES,
Defendant-Appellant.
Appealed from U.S. Ciaims Court
Judge Tidwell
Decided April 21, 1988
Clarence T. Kipps, Miller and Chevalier, of Washing-
ton, D.C., argued for plaintiff-appellee. With him on the
brief were John Lloyd Rice and John J. O’Connor, III.
Also on the brief were Bernard Fried and Norman A.
Steiger, Unisys Corporation, of counsel.
E. Kathleen Shahan, Commercial Litigation Branch,
Department of Justice, of Washington, D.C., argued for
defendant-appellant. With her on the brief were Richard
K. Willard, Assistant Attorney General and David M.
Cohen, Director. Also on the brief was Lt. Col. William
M. Henabray, Department of the Air Force, of counsel.
2a
Before FRIEDMAN, NEWMAN, and BISSELL, Circuit
Judges.
FRIEDMAN, Circuit Judge.
The sole question in this case, here on the government’s
appeal from the United States Claims Court, is whether
the government’s exercise of an option to purchase addi-
tional items under a procurement contract was timely.
The contract required the government to exercise the
option within 120 days of the government’s acceptance
of the product that was the subject of the contract, and
the issue is the date of acceptance. The Claims Court,
reversing the decision of the Armed Services Board of
Contract Appeals, held that the government’s exercise of
the option was untimely. Sperry Corp. v. United States,
9 Cl. Ct. 488 (1986). We reverse, concluding that the
exercise was timely.
I
A. In January 1974, the government executed a con-
tract with the appellee, Sperry Corporation, that required
Sperry to design, fabricate, test and deliver one LORAN-
D ground chain (Item 0001). This item was an advanced
transportable, computer controlled, solid state long-range
navigation (LORAN) system. The equipment transmits
signals that can be received aboard aircraft, ships, or
manpacks. The receiver determines locations by inter-
preting the time differences between precisely controlled
pulses from the transmitters.
The contract called for a significant amount of testing
by Sperry, lasting throughout the contract period. The
tests were designed by Sperry and approved by the gov- ©
ernment, which participated in, or observed most, if not
all, of the tests. Participation in the tests by Air Force
personnel was intended to enable them to learn to operate
the system and to verify that the equipment met the
contractual requirements.
3a
Development, Test and Evaluation (DT&E) is a process
by which each item, including the whole system assembled
from previously proven items, is tested to assure that
the items and the system meet the requirements of the
contract. The Physical Configuration Audit is designed
to compare the equipment tests with the prescribed tech-
nical data and to correct any deficiencies. The Formal
Qualification Review (Qualification Review) is intended
to gather data from the different tests and review them
as a whole. The Functional Configuration Audit exam-
ines the test results to determine whether the testing
was conducted properly.
The final delivery date under the contract (as modi-
fied) was May 15, 1978. DT&E field tests were com-
pleted February 3, 1978. The field portion of the Physi-
cal Configuration Audit was completed February 9, 1978.
The Functional Configuration Audit was completed Feb-
ruary 28, 1978, and the Formal Qualification Review
was completed by March 1, 1978. Between February 3
and March 18, 1978, Sperry refurbished the site on which
the tests were completed and the equipment. The govern-
ment made its final inspection from February 27 to
March 18, 1978, and on March 20, 1978, it executed a
DD Form 250 accepting the chain.
B. The contract “granted to the government the option
to purchase up to three additional LORAN-D Ground
Chains (Chains 2, 3, and 4) at prices specified in the
contract. The option had to be exercised ‘within 120 days
after final acceptance by the Government of Item 0001
[chain one] ....’” Sperry Rand Corp., 83-2 B.C.A.
(CCH) {16,841 at 83,787 (ASBCA Sept. 27, 1983).
Contending that it had finally accepted the LORAN-D
on March 20, 1978, when it executed the DD Form 250,
the government exercised the option for two additional
chains on July 6, 1978, within 120 days of the date of
that acceptance.
|
4a
Sperry responded that the government finally had ac-
cepted the LORAN-D upon completion of the DT&E field
tests on February 3, 1978, so that the government had
failed to exercise the option within 120 days. Sperry
interpreted the government’s exercise of the option as a
constructive change in the contract entitling it to an
equitable adjustment in the contract price. Sperry sup-
plied chains 2 and 3 under protest. :
Sperry filed a claim with the contracting officer for an
equitable adjustment. The contracting officer denied the
claim. In a lengthy opinion the Armed Services Board
of Contract Appeals (Board) (with one of the five mem-
bers dissenting) denied the appeal.
Sperry sought review in the Claims Court pursuant to
the Wunderlich Act, 41 U.S.C. § 321 (1982). The Claims
Court reversed the decision of the Board and remanded
for a determination of damages. The Claims Court sub-
sequently entered final judgment against the United
States in the amount stipulated by the parties.
Because the numerous contractual provisions involved
are complicated and best understood in the context of the
facts of the case, we describe those provisions in connec-
tion with our discussion of the legal issues in part II.
a NEE A Stare ots Bett anh Wine bal
II
The linchpin of the Claims Court decision that the
government did not timely exercise its option and Sperry’s
defense of that ruling is the following provision con-
tained in a section of the contract called the Schedule:
0001 Inspection at origin. Final inspection and
acceptance upon successful completion of
DT&E Field Test at destination.
Sperry contends that under this provision “[f]inal
. acceptance” of the contract by the government oc-
curred automatically upen the successful completion of
eee
5a
the DT&E field testing in February 3, and that this date
was the beginning of the government’s 120-day period for
exercising the option. Sperry then refers to Special Pro-
vision 5 of Section J of the contract, ORDER OF PREC-
EDENCE, which states:
In the even of an inconsistency in this contract,
unless otherwise provided herein, the inconsistency
shall be resolved by giving precedence in the follow-
ing descending order: 1) Schedule (excluding State-
ment of Work, the Specifications, and Contract Data
Requirements List); 2) General Provisions; 3) the
other provisions of the contract whether incorporated
by reference or otherwise; 4) Statement of Work;
5) Contract Data Requirements List; 6) the Speci-
fications . . .; 7) The Contractor’s Technical Pro-
posal as described in Section F.
According to Sperry, the “Order of Precedence” clause
makes the “Inspection at Origin” clause, as Sperry inter-
prets that clause, controlling in resolving any inconsist-
encies between the “Inspection at Origin” clause and the
other provisions of the contract upon which the Board
relied in its decisioii.
We conclude, however, that the “Inspection at Origin”
clause does not have the effect that Sperry ascribes to it.
Instead, it merely specifies the time when and the place
where the government affirmatively finally will inspect
and accept the LORAN 1 chain. Moreover, under our
view of that clause, there is no “inconsistency in this
contract” that requires resort to the “Order of Prece-
dence” clause. The Board correctly concluded that
it is possible to harmonize all contract provisions re-
lating to inspection, testing, delivery and acceptance
without creating conflicts between them or rendering
some of the provisions meaningless. In the absence
of conflict, the “Order of Precedence” clause need
not be called upon to establish the alleged primacy
6a
of the schedule “Inspection and Acceptance” provi-
sion [Section I] over general provisions and speci-
fications as suggested by appellant [Sperry] and in
the dissenting opinion.
Sperry Rand Corp., 83-2 B.C.A. (CCH) {16,841 at
83,799 (ASBCA Sept. 27, 1983) (citations omitted).
Various clauses in the contract, read in combination,
show that the government finally accepted the LORAN 1
chain on March 20, 1978, when it signed the DD Form
250. This conclusion accords with the parties’ interpre-
tation of those provisions during the performance of the
contract. The result of our holding that the government
finally accepted the LORAN 1 chain on March 20, 1978,
is that the government’s exercise of the options was
timely because it took place within 120 days of that
acceptance.
A. The contract incorporated the Armed Services Pro-
curement Regulations (ASPR) (which have been suc-
ceeded by the current Federal Acquisition Regulations),
including ASPR 14-1001.6 and ASPR 14-306, which
stated:
14-1001.6
Acceptance means the act of an authorized repre-
sentative of the Government by which the Govern-
ment assumes for itself, or as agent of another, own-
ership of existing and identified supplies tendered
or approves specific services rendered, as partial or
complete performance of the contract on the part of
the contractor.
14-306
(b) Depending upon the provisions of the contract,
acceptance may be effected prior to, at the time of,
or after delivery. Acceptance shall ordinarily be
evidenced by execution of an acceptance certificate
Ta
on the applicable inspection and receiving report form
(DD Form 250, DD Form 115, or Standard Form
44) sis
Read in the light of this and other provisions of the
contract, the “Inspection at Origin” clause does not pro-
vide that completion of DT&E testing itself constituted
final acceptance by the government. Nor does that clause
indicate that the parties intended in this contract to de-
part from the usual procedure that government accept-
ance would “be evidenced by execution of an acceptance
certificate on the applicable inspection and receiving re-
port form [here DD Form 250].”
Although not a model of draftsmanship, the “Inspec-
tion at Origin” clause does two things: it specifies the
time at which (“upon successfvl completion of DT&E
field tests”) and the place where (“at destination”) final
inspection and acceptance shall take place. The clause,
like some contract clauses, contains no verb, but inherent
in the provision are the words “shall take place” follow-
ing “final inspection and acceptance.” The word “upon”
generally is susceptible to different interpretations but
in this context we think it means “shortly afterward.”
The identical language is used in section F of the con-
tract, which states in pertinent part:
Upon successful completion of the DT&E field test,
the contractor shall restore the sites to the con-
dition they were in prior to the test.
Since this provision requires Sperry to take affirmative
action to restore the test site to its former condition, the
word “upon” necessarily means “shortly afterward.” The
identical word in the identical language of the ‘“Inspec-
tion at Origin” clause should be given the same meaning
unless there were clear indication that the parties in-
tended it to have a different meaning. See Peerless Cas-
ualty Co. v. Mountain States Mutual Casualty Co., 283
8a
F.2d 268, 276-77 (9th Cir. 1960). There is no indica-
tion that the parties so intended. Indeed, if the “Inspec-
tion at Origin” clause had been intended to have the
meaning that Sperry and the Claims Court would give it,
one would have thought it would have stated: “The suc-
cessful completion of DT&E Field Tests shall constitute
final inspection and acceptance.”
Other provisions of the contract indicate that final in-
spection by the government required some affirmative ac-
tion and did not occur automatically upon successful com-
pletion of the DT&E field test. Subparagraph (a) of the
General Provisions of the contract under the category
“INSPECTION” states: “All supplies (which term
throughout this clause includes without limitation . . .
end products) shall be subject to inspection and test by
the Government, to the extent practicable at all times
and places including the period of manufacture, and in
any event prior to acceptance.”
Subparagraph (a) in the General Provisions under
the category “TITLE AND RISK OF LOSS” states:
“Unless this contract specifically provides for earlier pas-
sage of title, title to supplies covered by this contract
shall pass to the Government upon formal acceptance,
regardless of when or where the Government takes physi-
cal possession.”
These two paragraphs require that there will be “in-
spection and test by the Government . . . prior to accept-
ance” and that there will be a “formal acceptance” by the
government.
Finally, in the “Statement of Work” category, para-
graph 5.2.4 provides:
Acceptance will take place following successful com-
pletion of DT&E and correction of design deficiencies.
This latter provision, which specifically deals with the
subject of “acceptance,” shows that the parties contem-
9a
plated and intended that acceptance would take place
“following” successful DT&E testing. This provision
necessarily rested on the assumption that the govern-
ment would take affirmative action to accept. it is in-
consistent with Sperry’s view that acceptance took place
immediately and automatically upon successful comple-
tion of the DT&E field tests. As the Board stated:
These acceptance tests were the conduct constituting
“final inspection” within the meaning of Section I
of the contract schedule. As such, inspection was
completed only when the acceptance tests had been
performed. The SPD confirmed delivery and accept-
ance at the destination by his signature on the DD250
(Finding 39)....
However, it is important to note that acceptance
not only follows delivery, but also is not contem-
plated to occur until all required inspection) includ-
ing testing) has been completed. This is not only
mandated by the “Inspection” clause, but also by
Section I of the contract schedule that requires
“(flinal inspection and acceptance upon successful
completion of DT&E Field Test at destination.”
Id. at 83,797 (emphasis in original).
In sum, we agree with the Board that the government’s
“final acceptance” did not occur until the government
executed the DD Form 250 on March 20, 1978. As the
Board stated, “[t]his was the ‘conclusive and decisive
action by the Government upon which it determines
through its authorized agents that, on the basis of all the
facts within its knowledge, the contractor has satisfac-
torily performed his obligations under the contract.’” 83-
2 B.C.A. (CCH) 716,841 or 83,799 (citation omitted).
The Board determined that “the contract established a
well-defined procedure from inspection to acceptance and
10a
we can find no indication that the parties intended to
discard these contractual steps.” Jd. at 83,796-97.
B. Alternatively, Sperry argues, as the Claims Court
held, that the government’s acceptance took place on
March 1, 1978, which still would make the government’s
exercise of the option untimely. According to the Claims
Court and Sperry, all of the testing was completed by
that date and the government’s acceptance took place at
that time. The Claims Court held, and Sperry argues,
that refurbishment of the chain was not necessary to ac-
ceptance, and the government “received from plaintiff
exactly what the contract called for, i.e., refurbishment
of the chain after sucessful completion of the DT & E
Field Test.” Sperry Corp. v. United States, 9 Cl. 488,
498 (1986). As the Claims Court viewed the situation,
“Chain 1 was accepted on March 1, 1978 even though
plaintiff [Sperry] was obligated by the terms of the con-
tract to continue unfinished tasks.” /d. at 498 (footnote
omitted ).
We agree with the Board’s reasoning in rejecting that
contention:
There is nothing to indicate that the parties con-
templated acceptance of the entire system when
equipment was only partially refurbished or refur-
bishment had been completed at some of the sites.
... The fact that the parties recognized that re-
furbishment of the equipment at all sites would have
to be accomplished before acceptance is shown by the
requirement to have the equipment in “deliverable
condition” as a result of refurbishment. Delivery
of the system had to occur before acceptance, and
thus refurbishment also had to be completed at that
point.
Sperry Rand Corp., 83-2 B.C.A. 16,841 at 83,798.
Moreover, this contention is subject to the same fatal
infirmity as the argument that the government’s accept-
lla
ance occurred on February 3, 1978, namely, that under
the “Inspection at Origin” clause, the government’s ac-
ceptance occurred automaticaily when the DT&E field
tests successfully were completed and did not require any
further affirmative action by the government. The same
reasoning that led us to reject the contention that the gov-
ernment accepted on February 3, 1978, also requires re-
jection of the claim that in any event acceptance took
place on March 1, 1978.
C. Finally, our interpretation of the contract accords
with the views expressed by the parties during perform-
ance of the contract that acceptance would require some
affirmative action by the government and would take
place only when the government executed a DD Form
250. That fact is a relevant consideration in interpret-
ing the contract. General Warehouse Two, Inc. v. United
States, 389 F.2d 1016, 1020 (Ct. Cl. 1967) and cases
cited.
In Sperry’s Production Progress Report of November
1977, Sperry stated that “the balance of program tasks
including . . . system acceptance and delivery is scheduled
to be completed by 15 May 1978.” In the January 1978
Production Progress Report, Sperry stated that “{rJe-
liability demonstration tests have been completed. The
balance of program tasks including antenna teardown,
design reviews, refurbishment, system acceptance and
delivery is scheduled to be completed by 10 March 1978.”
In a meeting with the government on February 2, 1978,
Sperry’s program manager requested the government to
execute a DD Form 250 upon completion of the “on-site”
portion of the physical configuration audit, which was
scheduled to occur on February 15, 1978. The govern-
ment declined to do so.
An inter-office memorandum prepared by Sperry per-
sonnel on February 24, 1978, stated that acceptance had
not yet occurred. A letter from the contracting officer to
12a
Sperry on February 27, 1978, discussed acceptance as a
future event. An Engineering Development report issued
by Sperry for the period February 1-28, 1978, contained
a note stating: “The only remaining program tasks are
completion of refurbishment and acceptance of transmit-
ter sites and completion of CDRL data items.” The gov-
ernment Production Progress Report for February 1978
stated: “Loran Chain—aAll program tasks have been com-
pleted except for refurbishment and acceptance of trans-
mitter sites which is scheduled to be completed by mid-
March.” A Program Progress Report prepared by Sperry
March 18, 1978, stated substantially the same thing.
Finally, in a letter to the government dated April 20,
1978, Sperry stated that “the Loran C/D Ground Chain
was formally accepted by the Air Force on March 20,
1978”—-the date the DD Form 250 was signed. Although
conduct after the dispute arises is not necessarily indica-
tive of the intent of the parties, (Dynamics Corp. v.
United States, 389 F.2d 424 (Ct. Cl. 1968)), this par-
ticular statement is consistent with and confirms Sperry’s
earlier recognition that affirmative action by the govern-
ment would be necessary for acceptance.
CONCLUSION
The judgment of the United States Claims Court award-
ing Sperry damages against the United States is
REVERSED.
13a
UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
87-1475
SPERRY CORPORATION,
Plaintiff-A ppellee,
Vv.
THE UNITED STATES,
Defendant-A ppellant.
BISSELL, Circuit Judge, concurring in result.
The majority decision turns on the proposition that
“upon” means “shortly afterward,” and that we must so
interpret it throughout the contract. Examining the Title
and Risk of Loss clause belies this position. That clause
states that title to supplies “shall pass to the Government
upon formal acceptance” (emphasis added). In _ this
clause, it is obvious that “upon” means “at the time of
acceptance,” and not “shortly afterward.”
In my view, a better basis for decision begins with the
recognition that the government is widely known to ac-
cept contract performance through the execution of the
DD250. As the majority acknowledges, ASPR 14-306 (b)
states that “|a]eceptance shall ordinarily be evidenced
by execution” of a DD250. The Title and Risk of Loss
clause just noted reveals why such a bright line event
is particularly important: the government owns the goods
and bears the risk of loss for them once it has accepted
them. In light of the normal practice of government ac-
ceptance through execution of the DD250, and the policy
reasons underlying such a bright line event, I would hold
l4a
that acceptance occurs only through the execution of the
DD250, or similar document, unless the contract clearly
states otherwise. Although the parties may agree to ac-
ceptance by some other means, the subject contract is
too loosely worded to hold that Sperry and the govern-
ment did so here.
I must add that this conclusion does not reflect in-
sensitivity to Sperry’s right, as optionor, to protect it-
self against attempts by the government to enlarge a
fixed option period. This case, however, is not about
strictly construing the terms of an option agreement.
It is about the separate question of how to interpret what
this contract means by the term “final acceptance.”
ld5a
APPENDIX B
IN THE UNITED STATES CLAIMS COURT
(FILED: February 5, 1986)
No. 116-84C
SPERRY CORPORATION,
Plaintiff,
We
THE UNITED STATES,
Defendant.
Contract; Wunderlich Act Review; Option Period/Strict
Int >rpretation; Order of Precedence Clause; Disparate
Contract Terms; Acceptance of Item; DD250
Standard Form.
[Filed Feb. 5, 1986]
Clarence T. Kipps, Jr., Washington, D.C., for plaintiff.
John L. Rice, John J. O’Connor, III, and Norman A.
Steiger, of counsel.
Kathleen A. Fiynn, Washington, D.C., with whom was
Acting Assistant Attorney General Richard K. Willard,
for defendant. Major Gerald J. Brentnall, of counsel.
l6a
OPINION
TIDWELL, Judge:
This action is before the court on cross-motions for
summary judgment. At issue is a decision by the Armed
Services Board of Contract Appeals (ASBCA or the
Board) brought under the Wunderlich Act, 41 U.S.C.
§§ 321 and 522 (1982), which denied the contractor’s
claim, plaintiff here, for equitable adjustment for alleged
constructive changes in the government’s application of
certain test procedures and decisions having to do with
the purchase of two additional option items. This court
will cite facts as necessary to support its conclusions but
not all of the facts as found by the Board which are art-
fully set out in its decision, Sperry Rand Corp., 83-2
BCA { 16,841. On the basis of the administrative record,
the parties’ briefing and oral argument, the court con-
cludes that as a matter of law the Board’s decision is
erroneous.
FACTS
This case involves negotiated fixed-price incentive con-
tract No. F19628-74-C-0098 executed on January 25,
1974 by plaintiff Sperry and defendant the United States,
acting through the United States Air Force which re-
quired plaintiff to design, fabricate, test and deliver one
LORAN-D Ground Chain (Chain 1), an advanced state-
of-the-art aid to navigation systems.' The contract called
for a significant amount of testing by plaintiff, lasting
throughout the course of the contract, plus a significant
amount of paperwork analysis and review, with “hands-
on” effort by Air Force personnel to verify that the equip-
ment offered met the contractual requirements and to
1 Chain 1 is actually item 0001 of the contract. Sperry was obli-
gated to build, test and refurbish Chain 1. Chains 2, 3 and 4 were
respectively items 0002, 0003 and 0004 of the same contract.
17a
learn to operate the equipment.? The tests were designed
by plaintiff and approved by defendant who participated
in or observed most, if not all, of the tests.
The contract also contained option provisions permit-
ting defendant to purchase up to three additional ground
chains, at set prices if purchased within a time frame
set out in the contract. Defendant gave notice on July
14, 1978, that it wished to exercise its option for chains
2 and 3. Plaintiff responded by stating that by the terms
of the contract defendant had 120 days from the date of
acceptance of Chain 1 within which to exercise its option
and that in plaintiff’s opinion the 120-day option period
had passed.* Because of defendant’s need for the chains
plaintiff agreed to supply chains 2 and 3 under protest
and seek an equitable adjustment at a later date to cover
their increased costs and time of performance. Plaintiff
subsequently delivered chains 2 and 3 to defendant as
well as a claim for equitable adjustment. Defendant
does not agree with plaintiff that the 120-day option
period had expired prior to its ordering of Chains 2 and
3 because, according to defendant, Chain 1 was not ac-
cepted until March 20, 1978, within the 120-day option
period. The contracting officer denied plaintiff’s claim
on that basis and the ASBCA upheld the decision of the
contracting officer. Plaintiff thereupon filed an appeal
with this court pursuant to the Wunderlich Act, supra.
The Board found that the contract gave defendant the
authority to exercise the options at the pre-arranged
price, for Chains 2 and 3 at any time during perform-
2 Practically every item, configuration, etc., was covered within
the contract by tests. The tests were called for as Contract Sub-
Line Item No. AO006AA, Category I Test Plan/Procedures, Sub-
system Test. There were approximately 150 tests.
3 Plaintiff alleged that Chain 1 was accepted on February 3, 1978.
There are 161 days between February 3 and July 14, 1978. For
reasons that will soon become obvious, there were 135 days between
March 1 and July 14, 1978.
18a
ance of the contract but no later than 120 days after
final acceptance of Chain 1 and that Chain 1 was ac-
cepted on March 20, 1978. The option was exercised on
July 14, 1978, within the 120-day option period. From
this issue confusion abounds. The following contractual
terms and conditions bear upon the issue and are very
possibly the chief cause of the mischief:
From the Schedule
SECTION E—SUPPLIES/SERVICES & PRICES
1. The Contractor shall design, fabricate, test and
deliver the equipment, data, and services below in
accordance with the documents set forth in Section F:
0001 LORAN Ground Chain, Tactical, Transport-
able, 1 each (Basic with Technical Alternate
2 Configuration)
* * * *
SECTION I—INSPECTION AND ACCEPTANCE *
Items
0001 Inspeciion at origin. Final inspection and
acceptance upon successful completion of
DT&E Field Test at destination.
SECTION F—DESCRIPTION/SPECIFICATIONS
Through Section F of the Schedule the following lan-
guage was added to Task 1 of the SOW (Statement of
Work).
Location of DT&E. Field testing of the first chain
is to be accomplished in S.E.U.S. (Southeastern
United States) such that the location of the monitor
and primary service area would be the Eglin AFB,
FL area. The three transmitter sites would have to
be located in S.E. U.S. such that they provide 400
‘ As amended-by POGG0T; July 8, 1975.
NNN Tf
19a
mile base legs, with the open side of the TRIAD
facing the Gulf of Mexico. Test sites to be selected
for the DT&E testing in S.E. section of the U.S.
shall be on Government-owned property.
Refurbishment and Restoration After DT&E. Upon
successful completion of the DT&E field test (sic),
the contractor shall restore the sites to the condition
they were in prior to the test. Also, the contractor
shall refurbish and restore, including replacement if
necessary, all elements of the chain to a deliverable
condition including any material and fixtures and
other aspects which may have been damaged in dis-
assembling the chain.
Design Deficiencies. During or subsequent to DT&E
the contractor shall correct any design deficiencies.
From the General Provisions
TITLE AND RISK OF LOSS (1968 JUN)
(a) Unless this contract specifically provides for
earlier passage of title, title to supplies covered by
this contract shall pass to the Government upon
formal acceptance, regardless of when or where the
Government takes physical possession.
* ~ 2 *
MATERIAL INSPECTION AND RECEIVING RE-
PORT (1969 DEC)®
At the time of each delivery of supplies or services
under this contract, the Contractor shall prepare and
furnish to the Government a Material Inspection
and Receiving Report in the Manner and to the ex-
5 The Armed Services Procurement Regulation Appendix cited in
this clause requires plaintiff to proffer a document (Standard
Form DD250) of which more will be said, to defendant for ac-
ceptance or rejection of any item, or for the chain in its entirety.
20a
tent required by ASPR Appendix I, “Material In-
spection and Receiving Report.”
From the Special (or Other) Provisions
5. ORDER OF PRECEDENCE.
In the event of an inconsistency in this contract,
unless otherwise provided herein, the inconsistency
shall be resolved by giving precedence in the foilow-
ing descending order: 1) Schedule (excluding State-
ment of Work, the Specifications, and Contract Data
Requirements List) ; 2) General Provisions; 3) the
other provisions of the contract whether incorporated
by reference or otherwise; 4) Statement of Work;
5) Contract Data Requirements List; 6) the Speci-
fications . . .; 7) The Contractor’s Technical Pro-
posal as described in Section F.
From the Statement of Work
5.0 Delivery
5.1 Deliver dates and quantities for Development
Items shall be as specified in the schedule of the
contract of which this SOW is a part. Acceptance
by the Government of the LORAN D Ground Chain
Equipment shall be accomplished at the Configura-
tion Item level.
5.2 Configuration Items will not be accepted until
the following conditions are met.
5.2.1 The Contracting Officer has acknowledged
completion of Preliminary Design Review, Critical
Design Review, Functional Configuration Audits,
Physical Configuration Audit, Formal Qualification
Review.
5.2.2 One or more of each Configuration Item has
been qualified and tested in accordance with Govern-
ment approved test plan, procedures and meet the
specification requirements.
OW Sas Sh NL AI ob OE
2la
5.2.3 The Configuration Items have satisfactorily
passed acceptance test in accordance with Acceptance
Test Plans, Procedures, and Specifications which
have been previously approved by the Contracting
Officer.
5.2.4 Acceptance will take place following successful
completion of DT&E and correction of design de-
ficiencies.
7.0 Contractor Tasks
+ * > *
7.2 Development Test and Evaluation The con-
tractor shall perform development tests and evalua-
tions as specified in Task 1 of SOW and [the] devel-
opment specifications.
7.3.2.2 Configuration Management The contractor
shall accomplish this effort in accordance with Task
17 of this SOW.
TASK I
TEST
6. Acceptance Final acceptance of all contractor
provided equipment services, and materials shall be
accomplished upon both the successful completion of
System Tests and the clearing of all test and design
discrepancies from all test phases.
7. Configuration Audits Functional Configuration
Audits and Functional Qualification Reviews shall
be conducted in accordance with Task 17 of this
statement of work.
* * * *
TASK 17
CONFIGURATION MANAGEMENT
* * * *
22a
4. Configuration Audits:
a. Functional Configuration Audit. The contractor
and the procuring activity shall conduct a Functional
Configuration Audit on the first unit of each configu-
ration item. . . . The contractor is responsible for
the conduct of the audits. . . .
b. Physical Configuration Audit. The contractor
and the procuring activity shall conduct an incre-
mental Physical Configuration Audit on the first
production unit of each configuration item. .. .
Physical Configuration Audit on all Configuration
Items shall be completed not later than “end of
DT&E.” ... The contractor is responsible for the
conduct of the audit... .
c. Formal Qualification Review. The contractor
and the procuring activity shall conduct a Formal
Qualification Review on a unit of each configuration
item after successful completion of System Testing.
. . . The contractor is responsible for the conduct
of the audit. .. .
This concludes the court’s listing of pertinert contract
terms.
“DT&E,” mentioned above, stands for Development,
Test and Evaluation. It is a process by which each item,
including the whole system assembled from previously
proven items is tested to assure the items and the
meet the requirements of the contract. The DT&E plans
were prepared by plaintiff and approved by defendant.
Plaintiff was primarily responsible for the testing, but
defendant’s representatives were present throughout the
process. The Board found that the Physical Configura-
tion Audit (PCA), Functional Configuration Audit
(FCA) and Formal Qualification Review (FQR) were
* As amended by P00021, June 2, 1976.
23a
included within DT&E. PCA is designed to compare the
equipment tests with the technical data described in
Chain 1 and to correct any deficiencies." FQR is intended
to gather data from the different tests and review them
as a whole. FCA supports FQR by examining the same
test results, but is designed specifically to see whether
the testing was conducted properly. Amendment P00021
changed the Statement of Work by requiring PCA on
the first production unit of each component prior to
completion of DT&E. The Board found that “every com-
ponent” in Chain 1 was a configuration item.
The Board found that the DT&E Field Tests were
successfully completed on February 3, 1978 and from
that date until March 18, 1978 plaintiff performed re-
furbishment work on the equipment at the sites in
preparation for the government’s Initial Operating Test
and Evaluation (IOT&E).* The Board also found that
the field portion of the PCA was completed on February
9, 1978 but that PCA was not formally completed until
sometime in April, 1978. FCA was completed on Febru-
ary 28, 1978 and FQR on March 1, 1978. Defendant's
inspection was completed March 18, 1978 and on March
20, 1978 the parties executed a DD250 in accordance
7 After finding that PCA was a part of DT&E, the Board, and the
parties as well, proceeded to ignore its place in the acceptance
process. For example, the Board found that FCA and FQR were
completed prior to March 1, 1978, without noting the PCA comple-
tion date. The Board also found that plaintiff's witnesses, “advanced
the position that acceptance occurred simultaneously with the con-
clusion of the last DT&E test. The Government's witnesses con-
tended that the option could not begin to run until all tests and
all data procedures (FCA and FQR) had been completed.” (Tran-
script citations omitted.)
* It was intended by defendant under IOT&E to have it’s per-
sonnel operate Chain 1, with support from plaintiff's personnel. The
IOT&E started on March 21, 1978 and lasted for 61 days, until
May 21, 1978. It is interesting to note that there were 81 days
between March 1 and May 21, 1978, and 102 days between February
3 and May 21, 1978. Both within the 120-day option period.
24a
with the “Material Inspection and Receiving Report”
clause for Chain 1. The Board thereafter concluded that
the option period began to run on March 20, 1978, the
date of the DD250 and that since the option was ac-
cepted on July 14, 1978, 116 days later, the option was
valid and plaintiff was required to provide Chains 2
and 3 at the contract price.
In the opinion of the court the only issues in this
case of any merit are legal in nature and can be deter-
mined by an analysis and interpretation of several of
the specifications of the contract which might to be in
conflict with each other. The principle issue is: Did
defendant exercise its option rights for Chains 2 and 3
within the 120-day time period? *
DISCUSSION
The terms of the contract, and the Wunderlich Act *
do not prohibit the ASBCA from making conclusiens of
* The Board listed three issues described thusly:
1. What was the impact of the implementation of the new
billing schedule contained in the DD250 executed on 29 March
1977?
2. What impact did completion of the last DT&E filed test,
(sic) on 3 February 1978, have on commencement of the period
within which the Government could exercise its option to pur-
chase additional LORAN chains?
3. If the option period did not begin on 3 February 1978,
on what date did it commence and what event marked that
milestone?
% The Wunderlich Act, 41 U.S.C. §§ 321 and 322 (1982) provide:
§ 321. Limitation on pleading contract-provisions relating to
finality; standards of review
No provision of any contract entered into by the United
States, relating to the finality or conclusiveness of any decision
of the head of any department or agency or his duty authorized
representative or board in a dispute involving a question aris-
ing under such contract, shall be pleaded in any suit now filed or
25a
fact and law in order to render its decisions. In truth,
the Wunderlich Act gives the decision of a Board finality
unless the decision is fraudulent, capricious, arbitrary, so
grossly erroneous as to necessarily imply bad faith, or
is not supported by evidence. 41 U.S.C. § 321 (1965).
This court in reviewing the factual findings of the Board
must accept the findings as final and conciusive even
if the court would not have reached the same findings or
conclusions. United States v. Utah Construction & Min-
ing Co., 384 U.S. 394 (1966); Tagg Brothers & Moor-
head v. United States, 280 U.S. 420 (1930); Marley v.
United States, 191 Ct. Cl. 205, 423 F.2d 324 (1970);
Southwest Welding & Manufacturing Co. v. United
States, 188 Ct. Cl. 925, 413 F.2d 1167 (1969). This is
a very difficult standard to meet; however it would be
incorrect to conclude that the court is powerless to re-
dress a wrong or that an appeal to the court is a useless
act. The interpretations of law made by the Board and
applied to the facts are not accorded tiie finality by the
Wunderlich Act that the Board’s factual determinations
receive. BCM Corp. v. United States, 2 Cl. Ct. 602
(1983); Dynamics Corp. of America v. United States,
182 Ct. Cl. 62, 389 F.2d 424 (1968). In Donald M.
Drake Co. v. United States, 194 Ct. Cl. 549, 439 F.2d
169 (1971), the court stated that board decisions on
“questions of law are open to independent judicial con-
sideration.” Jd. at 552, 439 F.2d at 171. Because the
to be filed as limiting judicial review of any such decision to
cases where fraud by such official or his said representative or
board is alleged: Provided, however, That any such decision
shall be final and conclusive unless the same is fraudulent or
capricious or arbitrary or so grossly erroneous as necessarily
to imply bad faith, or is not supported by substantial evidence.
§ 322. Contract-provisions making decisions final on questions
of law
No Government contract shall contain a provision making
final on a question of law the decision of any administrative
official, representative, or board.
26a
interpretation of specifications is a legal matter finality
thereupon is reserved to the courts. The court may agree
with the legal interpretations made by a Board of Con-
tract Appeals because such interpretations are a neces-
sary adjunct to the Board’s ability to reach its decision.
C.J. Langenfelder & Sons, Inc. v. United States, 169 Ct.
Cl. 465, 341 F.2d 600 (1965). The Board’s legal inter-
pretations, including the interpretation given specifica-
tions, must be examined, but with respect and dignity,
given the overall degree of expertise of the ASBCA in
this area of the law. George Hyman Construction Co. v.
United States, 215 Ct. Cl. 70, 564 F.2d 939 (1977).
Oftentimes the expertise of a Board in such matters can
be helpful to the court. Icono v. United States, 6 Cl. Ct.
149 (1984), aff'd, 770 F.2d 179 (Fed. Cir. 1985). See
also, Hegeman-Harris & Co. v. United States, 194 Ct.
Cl. 574, 440 F.2d 1009 (1971). Copco Steel & Engineer-
ing Co. v. United States, 169 Ct. Cl. 601, 341 F.2d 590
(1965), which is factually similar to the case at bar,
held that the search for the acceptance date of items
under a government contract must of necessity begin
with a search for the date from which the clock began
to run on the option item(s); a question of law for
decision by the court. Dynamics Corp. of America v.
United States, 182 Ct. Cl. 62, 72, 389 F.2d 424, 429-30
(1968), stated that questions of when an option period
commenced and how options were to be exercised were
legal issues of contract interpretation—and not factual
issues. The court said:
The Board cannot convert these clearly legal issues
of contract interpretation into factual issues simply
by resolving them in terms of the intent of the
parties. ...
. . . If the Board could make binding decisions
on matters of contract interpretation merely by
speaking in terms of the intent of the parties, the
Wunderlich Act would be robbed of much of its
Py
i
|
3
2
3
:
27a
purpose. Accordingly, this court is not bound by the
Board’s decision, but is free to decide this case in
accordance with its own view of the law.
Id. at 72, 389 F.2d at 429-30.
Both parties, the Board and the court all agree that
the contract clearly provided that the defendant could
exercise its option for Chains 2 and 3 at any time during
performance of the contract and for a period of time
not exceeding 120 days after final acceptance of Chain 1.
The difficulty with this seemingly simple issue is in estab-
lishing the date of final acceptance of Chain 1. Plaintiff
claims that the following term in the contract Schedule,
as amended, is of great probative value in making this
determination :
Inspection at origin. Final inspection and acceptance
upon successful completion of DT&E Field Test at
destination.
Plaintiff advocates that this means just what it says;
final acceptance occurs when the DT&E Field Test is
successfully completed. Defendant is just as adamant
that an interpretation of the entire contract shows that
final acceptance did not occur until the DD250 was signed
by defendant’s Program Director.
Plaintiff has asked the court to ascertain the intent
of the parties in order to properly interpret the contract.
This, the court will not do for the reasons set out in
Dynamics Corp. of America v. United States, 182 Ct.
Cl. 67, 72, 389 F.2d 424, 429-30 (1968). What the court
will do is review the decision of the ASBCA which will
include an analysis of the intent of the parties, as well
as other factors. The Board properly concluded that in
order to resolve the dispute the contract must be inter-
preted to give effect to all parts of the agreement if
possible and bring seemingly disparate provisions to read
as one. SCM Corp. v. United States, 230 Ct. Cl. 199,
675 F.2d 280 (1982); Merando, Inc. v. United States,
201 Ct. Cl. 28, 475 F.2d 603 (1973). The general rule
is that contracts are to be read as a whole so as not to
28a
leave one or more terms meaningless or useless. Astro-
Space Laboratories, Inc. v. United States, 200 Ct. Cl.
282, 470 F.2d 1008 (1972); Jamsar, Inc. v. United
States, 194 Ct. Cl. 819, 442 F.2d 930 (1971). “[TJhis
court must be guided by the well-accepted and basic
principle that a contract should be interpreted to give
effect to all parts of an agreement. An interpretation
which gives reasonable meaning to all provisions is pre-
ferred to one which renders a provision useless or mean-
ingless.” SCM Corp. v. United States, 230 Ct. Cl. 199,
203-04, 675 F.2d 280, 283 (1982). The court in Thanet
Corp. v. United States, 219 Ct. Cl. 75, 591 F.2d 629
(1979), perhaps said it best:
Provisions of a contract must be construed so as to
effectuate the spirit and purpose of the contract. The
agreement must be considered as a whole, and inter-
preted so as to harmonize and give meaning to all
its provisions.
Id. at 82, 591 F.2d at 633.
At times, however, the terms of a contract are so dis-
parate that they cannot be read together and interpre-
tive procedures must be used to find the proper interpre-
tation. One interpretive procedure which could be used in
the absence of any guidance from within the contract
itself is the rule of contra proferentem which seeks to re-
solve the ambiguity by construing offending terms in a
contract against the drafter of the language which is
usually, but not always, the government. Department of
Natural Resources & Conservation v. United States, 1
Cl Ct. 727, 737 (1983); WPC Enterprises v. United
States, 163 Ct. Cl. 1, 323 F.2d 874 (1963). When the
government drafts the contract and uses language that is
susceptible to more than one meaning and the intention
of both parties is not discernible, the meaning given it
by the contractor will prevail. The rule of contra pro-
ferentem, “puts the risk of ambiguity, lack of clarity,
and absence of proper warning on the drafting party
.... Sturm v. United States, 190 Ct. Cl. 691, 421 F.2d
29a
723 (1970); see also Peter Kiewit Sons’ Co v. United
States, 109 Ct. Cl. 390, 418 (1947).
Another interpretive procedure is when the parties by
mutual consent, prior to the execution of a contract,
agree upon a scheme for interpreting the contract should
it be discovered at a later date that one or more terms
must be rendered useless and meaningless because it or
they are so disparate they cannot be read together. One
popular format for this is a separate contract clause
stating which terms have precedence over other terms.
As plaintiff accurately points out, the parties in this
case agreed in the Order of Precedence clause contained
in the Special (or Other) Provisions of the contract that
certain terms of the contract would have precedence over
other items in the event of any inconsistency. Its pur-
pose is such that if there are inconsistencies within the
terms of the contract subordinate clause(s) must bow to
and be disregarded when there is an inconsistent higher
priority clause in the contract. As noted in John A. Volpe
Construction Co., 68-1 BCA { 6857, an Order of Prece-
dence clause “has been consistently recognized as a le-
gally valid and fully effective agreement by the parties
as to how their contract is to be interpreted.” Jd. The
Board, in the instant case, found it possible to “harmo-
nize all contract provisions relating to inspection, test-
ing, delivery and acceptance without creating conflicts
between them or rendering some of the provisions mean-
ingless.” The court is not as sanguine.
The contract Schedule stated that final inspection and
acceptance of Chain 1 would occur upon successful com-
pletion of the DT&E Field Test. Depending upon what
was included in the DT&E Field Test that test was com-
pleted either on February 3 or March 1, 1978. Sub-
ordinate terms, as per the Order of Precedence Clause
contained in inconsistent acceptance terms, such as terms
which forbade acceptance until (1) the contracting of-
ficer had acknowledged completion of the Preliminary
30a
Design Review, Critical Design Review, Functional Con-
figuration Audits, Physical Configuration Audit and the
Formal Qualification review; (2) each item had been
tested successfully; (3) DT&E had been successfully com-
pleted; and (4) design deficiencies corrected; and (5) a
properly filled out DD250 was executed.
The court need go no further to show inconsistent
terms of the contract that cannot be harmonized. Con-
sider: one term of the contract specifies acceptance upon
successful completion of the DT&E Field Tests. Another
forbids acceptance until all tests and audits are final,
DT&E is completed, all design deficiencies corrected, and
a DD250 executed. The court notes that the former term
referred to the DT&E Field Test and the latter to DT&E
without the modifier ‘Field Test” which, we assume, pre-
supposed some higher level or final test, as opposed to a
field or intermediate test even though there was no higher
level DT&E referenced in the contract. Common sense
tells us that a DT&E Field Test is not the same as an
unmodified DT&E, which would read “Final DT&E,” or
something akin to that. Even the Board was concerned
with what constituted “finalization of DT&E.” Either
Chain 1 was accepted at the time of completion of DT&E
Field Tests, or following formal completion of several
other items, including the completion of design deficien-
cies even though under a separate provision plaintiff was
required to correct design deficiencies as a part of its
warranty. The “Order of Precedence” clause was de-
signed expressly to address this kind of inconsistency. As
we have said, an interpretation which would give a
reasonable effect to all parts of the contract is clearly
preferred to one which leaves a part of the contract
useless, but this result is sometimes impossible to reach.
Government contracts are long and complex and the
draftsmanship oftentimes displays a deplorable lack of
care by the drafters, as appears here. When terms of a
contract are inconsistent, and each could be dispositive,
3la
an order of precedence must be established.'' Hence, the
“Order of Precedence” clause. See Restatement (Second)
& Contracts § 299(a) (Tent. Draft, 1973).
Inasmuch as the purpose of determining the acceptance
date of Chain 1 is to discover the beginning date of the
120-day option period the court is bound to construe the
terms of the contract strictly. Indeed, the general at-
titude of the courts and the ASBCA is to strictly con-
strue contractual option provisions because the options
subject contractors to potentially major risks which should
not be extended beyond the limits the contractor had
agreed to accept. In one instance, the ASBCA refused
to uphold the agency’s exercise of an option because the
exercise was one day late. Space-Age Engineering, Inc.,
78-2 BCA { 13,548.
In the instant case, the ASBCA determined that it was
not required to interpret the contract option provisions
but, rather, the term “final acceptance,” as used in the
Inspection and Acceptance clause and that, therefore,
“the strict interpretation rules, whatever they may mean
in this context, are not applicable.” The court disagrees.
The final acceptance language of the Inspection and Ac-
ceptance clause of the contract was an integral part of
the option provision inasmuch as the trigger date for the
120-day option period was the date Chain 1 was finally
accepted. Because this is a question of contract inter-
pretation the court is not bound by the Board’s inter-
pretation, but is free to decide this case in accordance
with its own view of the law. International Telephone
& Telegraph v. United States, 197 Ct. Cl. 11, 548 F.2d
11 “Tnconsistent” is defined as “[m]utually repugnant or contra-
dictory; contrary, the one to the other, so that both cannot stand,
but the acceptance or establishment of the one implies the abroga-
tion or abandonment of the other; as, in speaking of “inconsistent
defenses,’ or the repeal by statute of ‘ali laws inconsistent here-
with.’” Blacks Law Dictionary, 689 (rev. 5th ed. 1979).
32a
1283 (1972). Dynamics Corp. of America v. United
States, 182 Ct. Cl. 62, 389 F.2d 424 (1968).
The court finds that the various terms affecting and
defining acceptance of Chain 1 cannot be interpreted so
as to give them all effect. The terms cannot merely be
read as appearing to be conflicting and then tinkered
with, such as by reading them out of context, ignoring
their plain meaning, etc. The acceptance terms of this
contract are inconsistent and one or more must fall.
The court agrees with the Board’s conclusion that FCA,
FQR and PCA were part of DT&E. The Board found
that FCA and FQR were both completed prior to March
1, 1978. PCA was conditionally approved in early Feb-
ruary 1978. The reason it was not unconditionally ap-
proved was because there were some discrepancies be-
tween the drawings and the equipment, but not so great
as to cause rejection. The Board found that PCA was
formally completed sometime in April 1978, but notwith-
standing the lack of formal completion, defendant con-
ducted IOT&E based upon the PCA conditional approval.
The record below shows that conditional approval of PCA
was made on February 9, 1978 and that defendant went
forward with IOT&E prior to formal PCA acceptance
because the discrepancies were so minor that IOT&E
could be conducted safely while plaintiff continued to
check the drawings against the actual equipment. The
significance of this issue goes to the Board’s finding that
the contract was accepted on March 20, 1978, when a
DD250 was executed for Chain 1. The court agrees with
the Board that final acceptance occurred prior to formal
completion of PCA in April, 1978.
The Board ignored a stipulation reached by the parties
at the administrative level ostensibly because it was not
necessary to support the decision reached by the Board.
Under the court’s view the stipulation is important. The
stipulation read that if FCA and FQR were found by the
Board not to be part of DT&E tests then DT&E testing
33a
was completed on February 3, 1978, if they were found
to be part of DT&E tests then DT&E testing was com-
pleted on March 1, 1978. The significance of the Feb-
ruary 3, 1978 date is that on that day plaintiff completed
all of the tests identified as tests in the Statement of
Work, Task No. 1, Test. The Board found that FCA and
FQR were completed subsequent to February 3, 1978 but
on or prior to March 1, 1978. PCA was not referred to
again.” The court must hold that all tests, including
especially, DT&E Field Tests were completed by March
1, 1978. The stipulation of the parties was improperly
ignored by the Board and, at the least, should have been
addressed. In Gresham & Co. v. United States, 200 Ct.
Cl. 97, 470 F.2d 542 (1972), our predecessor court held
that a stipulation of the parties is dispositive of the issue
of whether government inspectors agreed with the con-
tractor’s interpretation of the specifications because a
“stipulation is a judicial admission binding on the par-
ties... .” Id. at 112, 470 F.2d at 551. It is binding
on the Board and it is binding on this court in the ab-
sence of any factors to the contrary such as coercion,
fraud, impossibility, ete.
The court is well aware that its conclusions, so far
fly in the face of the Board’s legal conclusion that Chain
1 could only be accepted by the proper execution of a
DD250 following some undesignated period of time for
defendant to contemplate the effects of the test results.
The court disagrees with both conclusions. It may well
be that execution of a DD250 is the generally recognized
method for acceptance of an item in government con-
tracting but this ignores the fact that the parties may,
as they did here, mutually agree to another form of ac-
ceptance, i.e., the event of completion of the DT&E Field
Tests. The court also sees no reason why the parties
12 It is readily apparent to the court that PCA is a component part
of FQR and since FQR was completed prior to March 1, 1978 the
conditionally accepted status of PCA must have been sufficient to
the parties, and the Board, and, it should be added, the court.
34a
could not agree to acceptance automatically predicated
upon the same or some other event. Legal precedent
establishes that there is no requirement that government
acceptance be accomplished only by the joint execution
of a formal DD250. Acceptance may be effected upon
the happening of a stated event. See Raymond-Kaiser-
Macco-Puget Sound, 66-1 BCA { 5,498, where acceptance
occurred upon the final inspection at a contractor’s plant
as provided in the contract because the final inspection
disclosed no defects and regardless of the fact that the
DD250’s executed by the government stated that the in-
spection did not constitute government acceptance. T'ro-
Tech Inc. 68-1 BCA { 6,828, held that where there was
no formal written acceptance by the government, the
Board nevertheless properly found that government ac-
ceptance was effected by inspection and payment where
a contract provision baldly stated, “[a]eceptance will be
the date the Veterans Administration receives satisfac-
tory inspection or test report” (sic). There is no merit
to the argument that to permit the parties to agree to
their own manner of acceptance is improper because it
would read out of the contract the “Material Inspection
and Receiving Report” clause. The right of the parties to
agree to ignore the clause is a valid right under the
other terms of the contract and procurement law. The
contract, as amended, made practically every item, sub-
assembly audit, configuration, and so forth, subject to a
separate test both individually and as assembled.’* That
being the case and following the Board’s views a DD250
would have to be executed for most of those bits of the
whole, which would have conceivably amounted to hun-
dreds if not thousands of proffers and acceptances under
the “Material Inspection and Receiving Report” with a
corresponding DD250 for each. There is no evidence that
such activity ever occurred.
13 “Assembled” in this sense does not mean just the entire Chain
1; it also includes subassemblies of many units less than the whole.
35a
Moreover, the Board distilled from the contract that
defendant did not intend for acceptance to be automatic
upon the occurrence of successful completion of the DT&E
Field Test, but that a completed DD250 at some uniden-
tified later point in time was necessary to denote formal
acceptance. We have dealt sufficiently with the latter is-
sue. The Board looked at the word “upon” in the phrase
“upon successful completion of DT&E Field Test,” '* and
found that the word could be defined several different
ways, such as, “at this moment” to “in the very near
future.” The Board did find that it could not support an
interpretation of “upon” as synonymous with the occur-
rence of a particular event and not bureaucratically re-
corded by the proper officer on a correctly completed
DD250. We disagree. Acceptance of Chain 1 occurred
on March 1, 1978 and whether a DD250 was issued that
day is irrelevant. The court finds that “upon” can mean
many things and must be interpreted in light of its
usage. In the context in which it is used in this case,
the court finds that “upon,” contrary to the Board’s con-
clusion, means “now,” concurrent with the successful ecn-
clusion of the DT&E Field Test. The court can easily
understand why defendant wanted a completed DD250
to record the March 1, 1978 acceptance because the vo-
luminous amount of information contained in it would
clearly be to defendant’s benefit. See ASPR § 30.8 Ap-
pendix I (1968).% The Board also concluded that the
contract mandated that inspection must precede accept-
ance, citing the title and order of language in the In-
spection and Acceptance clause of the General Provisions
and the operative language of the contract schedule term
14 From the Schedulue, Section I—INSPECTION & ACCEPT-
ANCE, “Inspection at origin. Final inspection and acceptance upon
successful completion of DT&E Field Test, at destination.” (Em-
phasis added.)
15 The court sees no reason why a properly completed DD250
could not be executed at a later date to memorialize the earlier
acceptance and to acquire the information required in a DD250.
36a
controlling in this instance, that requires “[f]inal inspec-
tion and acceptance upon successful completion of DT&E
Field Test at destination.” This is not correct. At times,
in government contracts acceptance may precede final in-
spection, but more importantly, the argument is moot.
It has nothing to do with the ultimate decision; Chain 1
was accepted on March 1, 1978 even though plaintiff was
obligated by the terms of the contract to continue un-
finished tasks."*
One task which continued was refurbishment of land
and Chain 1. “Section F—Description/Specifications” of
the contract Schedule required plaintiff to restore and
refurbish the land and Chain 1, “[u]pon successful com-
pletion of the DT&E field test [sic].” The clause con-
tinued, that plaintiff was to “refurbish and restore, in-
cluding replacement (sic) if necessary all elements of the
chain to a deliverable condition including (anything) .. .
which may have been damaged in disassembling the
chain 1... .” Again, the Board has made the same er-
ror. It concluded that defendant’s position was correct;
that Chain 1 could not be accepted before refurbishment
was completed and that refurbishment was a part of
DT&E. The court again understands why defendant
would probably have liked Chain 1 completely refur-
bished before acceptance, but that is not what it con-
tracted for. Defendant received from plaintiff exactly
what the contract called for, i.e., refurbishment of the
chain after successful completion of the DT&E Field
16 Plaintiff also alleges that the argument of whether inspection
had to precede acceptance was raised by defendant as a “straw
man” because inspection took place at its plant prior to delivery, and
as required by the contract. The court will not consider this argu-
ment because it need not do so to resolve the appeal. The Board's
address to this issue would lead you back to section 5.2 of the
Statement of Work which forbids acceptance before inspection.
The reader will remember that the court found section 5.2 of the
Statement of Work to be subservient to and, in this instance,
nullified by the Schedule.
37a
Test. Defendant has been in the business of writing con-
tracts for over 200 years and is capable of drafting con-
tract language to describe accurately what it wants. To
state otherwise is disingenuous. It is also not lost on
the court that defendant did reserve to itself 120 days
after acceptance of Chain 1 to evaluate the Chain, train
military personnel to operate it (IOT&E), complete more
testing and documentation, permit refurbishment, replace
damaged parts (though this item was covered under the
warranty provisions of the contract) and myriad other
items of unfinished work. It is not that defendant did
not have other options for accomplishing these goals.
For example, defendant could have keyed acceptance to a
later event than DT&E, or it could have allowed itself
more time for the completion of any possible unfinished
work by the contractor or itself, and as a corollary
thereto, more time within which to make the decision
of whether to exercise the option.
The final finding of the Board was that plaintiff main-
tained site security at the site(s) until March 18 or
20, 1978 thereby manifesting that acceptance by defend-
ant had not occurred prior thereto. When plaintiff gave
notice that it planned to withdraw its guard force on or
about February 3 and March 1, 1978 because Chain 1
had been accepted, defendant refused to accept the re-
sponsibility for security, and so told plaintiff. The court
believes as a result, plaintiff was forced by economic
considerations to continue providing site security as it
was required to do under the contract. Plaintiff had not
been totally paid for its work on the contract and expen-
sive equipment of its own and defendant’s was on the
site(s). Plaintiff's actions were completely reasonable
in these circumstances. Defendant, operating under the
false premise that it had not accepted Chain 1 until
March 20, 1978, naturally refused responsibility for site
security because, had it done so, that action would have
presaged defendant’s control over the real and personal
property and have been inconsistent with defendant’s
38a
litigation position, that during the first few weeks of
March 1978 it had not accepted Chain 1.
We have answered two of the three issues posed by
the Board. Issue two asked, “[w]hat impact did com-
pletion of the last DT&E field test [sic], on 3 February
1978, have on commencement of the period within which
the Government could exercise its option to purchase
LORAN chains?” The answer is none, because the
DT&E Field Test was not completed until March 1, 1978.
The 120-day option period on Chains 2 and 3 began run-
ning concurrently with the March 1, 1978 automatic
acceptance by defendant of Chain 1. Issue three was,
“li]f the option period did not begin on 3 February
1978, on what date did it commence and what event
marked that milestone?” The option period began on
March 1, 1978 as determined by the parties in the per-
tinent stipulation of facts and the Inspection and Ac-
ceptance Clause of the contract, as amended, which
established the acceptance date of Chain 1 and the begin-
ning of the option period as the day DT&E was success-
fully completed at destination.
The Board also asked “[w]hat was the impact of the
implementation of the new billing schedule contained in
the DD250 executed on 29 March 1977?” We agree with
the Board on this issue. Briefly, plaintiff apparently
encountered money-flow problems and requested, on
March 29, 1977, that defendant revise the billing sched-
ule. This was done through the submission of a DD250
(which exemplifies the confusion surrounding the use of
DD250’s). Defendant then issued amendment P00023
which divided line item 0001 (Chain 1) into three epa-
rate parts. This particular DD250 was addressed to line
item 1.1 “Design, Develop, Fabricate and in Plant Test
one each [LORAN CHAIN].” Plaintiff argued to de-
fendant and the Board that the signature of defendant’s
Systems Program Director on that particular DD250
started the 120-day option period. The Board and this
39a
court disagree with plaintiff. The execution of the Sys-
tem Program Director only operated to acknowledge the
new billing schedule set out in the DD250. Plaintiff’s
argument carries no weight.
CONCLUSION
This case has been complex, complicated all the fur-
ther, by a poorly drafted contract and an extremely
well-crafted Board opinion that this court was required
to disagree with, as a matter of law, on several issues
including the primarily dispositive one; the date of ac-
ceptance of Chain 1 by defendant which started the run-
ning of the option period for Chains 2 and 3. That date
was March 1, 1978 meaning, therefore, that the option
was executed 135 days after acceptance of Chain 1.
Accordingly, for the reasons given in this decision, plain-
tiff’s Motion for Summary Judgment is granted; defend-
ant’s Cross-Motion for Summary Judgment is denied;
the decision of the Armed Services Board of Contract
Appeals is reversed and plaintiff is entitled to recover.
The case is remanded to the ASBCA for further proceed-
ings in accordance with RUSCC 60.1 and the holdings of
this court and, as relevant to the determination of quan-
tum. The proceedings in this court shall be stayed for
a period of six months, or such other time as the court
may allow upon motion of either party as the needs cf
this case may require. Counsel for plaintiff shall provide
the court with a status report beginning 90 days from
the issuance of this decision and every 30 days thereafter.
IT IS SO ORDERED.
/s/ Moody R. Tidwell
Moopy R. TIDWELL
Judge
40a
Skit nee een
APPENDIX C
ARMED SERVICES BOARD OF CONTRACT APPEALS
ASBCA No. 23448
Appeal of —
SPERRY RAND CORPORATION, SPERRY DIVISION
Under Contract No. F19628-74-C-0092
Appearances for the Appellant:
John Lloyd Rice, Esq.
John J. O’Conner, Esq.
Miller & Chevalier, Chartered
Washington, D.C.
Appearances for the Government:
Colonel William P. Rudland, USAF
Chief Trial Attorney
Major Gerald J. Brentnall, USAF
Patrick D. Quinn, Esq.
Trial Attorneys
OPINION BY
ADMINISTRATIVE JUDGE RIISMANDEL
This timely appeal presents a question as to whether
the Government’s exercise of an option provision in the
contract was timely. At issue is the act marking com-
mencement of the option period. A hearing was held and
both parties have submitted briefs. Only entitlement is
presented for the Board’s consideration. This appeal is
not subject to the Contract Disputes Act of 1978, 41
U.S.C. §§ 601 et seq.
4ia
The record in this appeal consists of the Rule 4 sub-
mittals, supplemental Rule 4 documents presented by
appellant, stipulations of fact and the transcript of the
hearing.
FINDINGS OF FACT
The Contract
1. Contract F19628-74-C-0098 was entered into be-
tween Sperry Rand Corporation, Sperry Division (here-
inafter appellant) and the Government with an effective
date of 25 January 1974. The contract was a fixed price
incentive fee (firm target) contract, requiring the de-
sign, fabrication, testing and delivery of a LORAN-D
Ground Chain as contract line item 0001 at a target
price of $13,430,000. Delivery of the basic chain was
to occur two years after contract award date. (R4, tab
25, part II, section H)
2. LORAN-D is a precision navigation system used to
provide navigational information and precision fixes
within a tactical service area. This system represents an
advanced generation of transportable, computer-controlled,
solid waste long range navigation (LORAN) systems.
The equipment transmits signals which can be received
aboard aircraft or ships. The receiver determines loca-
tion by interpreting the time differences between pre-
cisely controlled pulses from transmitters. The LORAN-
D ground chain system consists of a transmitting chain
(composed of from 3 to 5 high power pulse transmitters)
and a ground monitor (to receive, process and score criti-
cal information related to transmissions of the system).
The development of this equipment represented an ad-
vancement in the state of the art. Appellant experienced
delays in connection with this program and was given ex-
tensions of time. (App. supp. R4, tab A-38 at 2; stip. 2;
tr. 1/34-35, 73)
3. The contract granted to the Government the option
to purchase up to three additional LORAN-D Ground
42a
Chains (Chains 2, 3 and 4) at prices specified in the
contract (app. supp. R4, tab A-22; stip. 1). The option
had to be exercised “within 120 days after final accept-
ance by the Government of Item 0001 or by 76APR15
whichever is later” (contract schedule at 2).
4. In addition to the “Changes (1958 JAN)” and
“Disputes (1958 JAN)” clauses, the contract contained
the following provisions which pertain to this appeal:
INSPECTION (1958 MAY)
(a) All supplies (which term throughout this
clause includes without limitation raw materials,
components, intermediate assemblies, and end prod-
ucts) shall be subject to inspection and test by the
Government, to the extent practicable at all times
and places including the period of manufacture, and
in any event prior to acceptance.
* * * *
TITLE AND RISK OF LOSS (1968 JUN)
(a) Unless this contract specifically provides for
earlier passage of title, title to supplies covered by
this contract shall pass to the Government upon for-
mal acceptance, regardless of when or where the
Government takes physical possession.
(b) (1) Unless this contract specifically provides
otherwise, risk of loss of or damage to supplies cov-
ered by this contract shall remain with the Contrac-
tor until, and shall pass to the Government upon:
(i) delivery of the supplies to a carrier, if
transportation is f.o.b. origin;
(ii) acceptance by the Government or delivery
of possession of the supplies to the Government
at the destination specified in this contract,
whichever is later, if transportation is f.o.b.
destination.
43a
(2) Notwithstanding (1) above, the risk of loss
or damage to supplies which so fail to conform to the
contract as to give a right of rejection shall remain
with the Contractor until cure or acceptance, at
which time (1) above shall apply.
(c) Notwithstanding (b) above, the Contractor
shall not be liable for loss of or damage to supplies
caused by the negligence of officers, agents, or em-
ployees of the Government acting within the scope
of their employment.
* * * *
MATERIAL INSPECTION AND
RECEIVING REPORT (1969 DEC)
At the time of each delivery of supplies or services
under this contract, the Contractor shall prepare and
furnish to the Government a Material Inspection and
Receiving Report in the manner and to the extent re-
quired by ASPR Appendix I, “Material Inspection
and Receiving Report.”
+ * * *
PART II—THE SCHEDULE
SECTION E—SUPPLIES/SERVICES & PRICES
i. The Contractor shall design, fabricate, test and
deliver the equipment, data, and services below in
accordance with the documents set forth in Section
F:
0001 LORAN Ground Chain, Tactical, Transporta-
ble, 1 each (Basic with Technical Alternate 2
Configuration )
* * * *
44a
SECTION F—DESCRIPTION/SPECIFICATIONS
Item Basic Chain Description
0001 SOW para 7.1 & Spee Nos. SS-DCL-450A-S1;
SS-DCL-450A-Ti; SS-DCL-450A-M1 (Refer-
ence WBS Attach, Transmitting Set (level 2,
Task 30) and Monitor Set (level 2, Task 30)
and to include Dev. Test and Eval and Sys
Proj Mgt SOW para 1, 7.1, 7.3 and tasks 1,
2, and 4-28.)
Amendment #2 dated 75 JUL 08, Task 31,
Transmitter Antenna Fence” attached hereto
and hereby made a part hereof.
IAW Annex “A” to SOW & Spec No. SS-
DCL-450A-T1, Para 3.2.1..2 and Section 4.
* * * *
The following is added to Task 1 of the
SOW:
Location of DT&E. Field testing of the
first chain is to be accomplished in S.E. U.S.
such that the location of the monitor and
primary service area would be the Eglin,
AFB, FL area. The three transmitter sites
would have to be located in 8.E. U.S. such
that they provide 400 mile base legs, with
open side of the TRIAD facing the Gulf of
Mexico. Test sites to be selected for the
DT&E testing in S.E. section of the U.S.
shall be on Government-owned property.
Refurbishment and Restoration After
DT&E. Upon successful completion of the
DT&E field test, the contractor shall restore
the sites to the condition they were in prior
to the test. Also, the contractor shall refur-
bish and restore, including replacement if
SSS ae eee
Be re eh yea sgn he a inet Lichen roi aaiial scene Eile a)
45a
necessary, all elements of the chain to a de-
liverable condition including any material
and fixtures and other aspects which may
have been damaged in disassembling the
chain.
* * % x
Design Deficiencies. During or subsequent
to DT&E the contractor shall correct any
design deficiencies.
SECTION H—DELIVERIES OR PERFORMANCE
1. Delivery is required in accordance with the fol-
lowing schedule:
ITEM QTY F.0.B. POINT ON OR BEFORE
0001 1 ea. DT&E POINT 2 years after
(destination) contract award
date
* * * *
SECTION I—INSPECTION AND ACCEPTANCE
Items
0001 Inspection at origin. Final inspection and
acceptance upon successful completion of
DT&E Field Test (at Eglin ABF, FL)
* * * *
SECTION J—SPECIAL PROVISIONS
* * * *
5. ORDER OF PRECEDENCE.
In the event of an inconsistency in this contract,
unless otherwise provided herein, the inconsistency
Shall be resolved by giving precedence in the follow-
ing descending order: 1) Schedule (excluding State-
46a
ment of Work, the Specifications, and Contract Data
Requirements List); 2) General Provisions; 3) the
other provisions of the contract whether incorporated
by reference or otherwise; 4) Statement of Work;
5) Contract Data Requirements List; 6) the Specifi-
eations (a. SS-DCL-450A-S1; b. SS-DCL-450A-T1;
ce. SS-DCL-450A-M1) ; 7) The Contractor’s Technical
Proposal as described in Section F.
* * & *
STATEMENT OF WORK
5.0 Delivery
5.1 Delivery dates and quantities for Development
Items shall be as specified in the schedule of the con-
tract of which this SOW is a part. Acceptance by
the Government of the LORAN D Ground Chain
Equipment shall be accomplished at the Configura-
tion Item level.
5.2 Configuration Items will not be accepted until
the following conditions are met.
5.2.1 The Contracting Officer has acknowledged
completion of Preliminary Design Review, Critical
Design Review, Functional Configuration Audits,
Physical Configuration Audit, Formal Qualification
Review.
5.2.2 One or more of each Configuration Item has
been qualified and tested in accordance with Govern-
ment approved test plan, procedures and meet the
specification requirements.
5.2.3 The Configuration Items have satisfactorily
passed acceptance test in accordance with Acceptance
Test Plans, Procedures, and Specifications which
have been previously approved by the Contracting
Officer.
47a
5.2.4 Acceptance will take place following success-
ful completion of DT&E and correction of design
deficiencies.
7.2 Development Test and Evaluation The con-
tractor shall perform development tests and evalua-
tions as specified in Task 1 of SOW and Specifica-
tions SS-DCL-450A-S-1, SS-DCL-450A-T-1, SS-DCL-
450A-M-1 and development specifications.
TASK 1
TEST
6. Acceptance Final acceptance of all contractor
provided equipments, services, and materials shal! be
accomplished upon both the successful completion of
System Tests and the clearing of all test and design
discrepancies from all test phases.
* * * *
5. “DT&E” is an acronym for Development, Test and
Evaluation. This is a process through which a mecha-
nism is subjected to a series of tests in order to establish
that the equipment meets the performance levels set forth
in the specifications. (Tr. 1/40, 75, 3/110) DT&E test-
ing, which is common to contracts with technical require-
ments, is developed from a test plan prepared by the con-
tractor and approved by the Government (tr. 1/42-43,
75, 81, 2/15). In this contract, the DT&E test plan was
quite extensive, requiring over 150 tests for all phases of
the system’s performance (tr. 1/47, 74). By the terms
of the contract, appellant was required to perform DT&E
testing (R4, tab 25 at 5; tr. 1/39).
6. In addition, the systems had to pass a Physical Con-
figuration Audit (PCA), Functional Configuration Audit
(FCA) and Formal Qualification Review (FQR) (tr.
2/52, 3/124).
48a
7. The purpose of PCA is to compare the actual equip-
ment test results with the technical data describing the
equipment in order to identify any discrepancies needing
correction (tr. 2/106, 3/103, 121).
8. The purpose of FQR is to accumulate all data from
the different tests and to review them as a package. By
reviewing these test results and the result of the FCA, it
can be determined whether the equipment conforms to
the specifications and is suitable for the intended use.
(Tr. 1/54, 2/12, 105)
9. The purpose of FCA, an underpinning to FQR, is
to examine results of tests and compare them with spe-
cification requirements to ascertain if the tests were con-
ducted properly in accordance with accepted test proce-
dures and that the test results demonstrated that the par-
ticular component conformed to the tests (tr. 2/12, 64,
104-05).
10. Data underlying the testing phase was covered
under separate Line Item 0006 and is not involved in the
consideration of when acceptance of Line Item 0001
occurred (R4, tab 25 at 2).
Contract Performance
11. During the course of contract performance, the
parties entered into numerous modifications (R4, tabs 26-
51). None of these modifications changed the contract
option prices (tr. 1/118).
12. A negotiation memorandum prepared by appellant
on 4 June 1975 contained the following information vis-
a-vis “Option Dates”:
Proposed 120 days after delivery of Chain 1 hard-
ware as period within which they can purchase op-
tions for Chains 2, 3 and 4 at target prices currently
stipulated by contract. Accepted.
(App. supp. R4, tab A-1)
:
49a
13. During negotiations between the parties on 23
June 1975, the Government’s contract negotiator advised
appellant that any supplemental agreement would include
language to the effect that the Government could order
the option quantities at any time, but no later than 120
days after delivery of Item 0001 (R4, tab 71).
14. Modification P00007 to the contract, negotiated
pursuant to 10 U.S.C. § 2304(a) (10), was executed on
28 July 1975. This modification extended the time for
delivery of the basic claim by eight months and provided,
inter alia, that with regard to both Chain 1 and Chain 2,
the “Government may exercise this option at any time
during contract performance, but not later than 120 days
after final acceptance by the Government of Item 0001.”
(Emphasis supplied) Item 0001 of Section I, “Inspection
and Acceptance” was modified to read as follows:
0001 Inspection at origin. Final inspection and
acceptance upon successful completion of DT&E
Field Test at destination.
(R4, tab 32)
15. A, “Program Schedule” (AFSC Form 103) was
incorporated into Modification P00007, reflecting that the
completion of DT&E, Functional Qualification Review
and “AF accept chain” all would occur on 25 September
1976 (R4, tab 32 at 8, tabs 68, 70; tr. 1/93-94, 123-124).
16. Contract management reviews were conducted by
appellant during the term of the contract. Representa-
tives of appellant and the Government were present at
these meetings. In a contractor management review con-
ducted in July 1975, “Critical Field Test Milestones”
were depicted as follows:
FIELD TEST MILESTONES
COMPLETE FIELD DT&E 9/25/76
COMPLETE FQR 9/25/76
AF ACCEPT CHAIN 9/25/76
DELIVER DT&E REPORTS 10/25/76
50a
(Exh. A-8 at A-8). The same timetable was set forth
in contractor management reports prepared in October
and December 1975 (exh. A-9 at A-8, A-10 at A-8; tr.
1/107).
17. Modification P00021 was executed on 2 June 1976,
with the express purpose of providing “confidence testing
at the Wildwood, N. J. High Power Test Site.” (R4,
tab 46) A program schedule was attached to this bi-
lateral Modification and provided:
Completion
Date
FIELD TEST MILESTONES
COMPLETE FIELD DT&E 26 Oct 76
FUNCTIONAL QUALIFICATION
REVIEW 26 Oct 76
AF ACCEPT CHAIN 1 Nov 76
DELIVER DT&E REPORTS 26 Nov 76
(R4, tab 46). At the request of appellant, this timetable
provided one week for refurbishment after the comple-
tion of testing and before acceptance, for it was antici-
pated that the equipment on the site would have “taken
a beating.” This week also was available in order to
correct any problems discovered during testing. Tr.
2/185, 3/7-8, 28-29; R4, tab 81)
18. Modification P00021 also amended the statement
of work as follows:
Task 17—Configuration Management
1, Delete paragraph 4.b and substitute the follow-
ing: Physical Configuration Audit. The contractor
and the procuring activity shall conduct an incre-
mental Physical Configuration Audit on the first
production: unit of each configuration item, in ac-
cordance with MIL-STD-483 (USAF), and appendix
XII thereto. Physical Configuration Audit on all
Configuration Items shall be completed not later
than “end of DT&E.” The contractor is responsible
for the conduct of the audit, MIL-R-83313 (USAF)
5la
will be used as a guide. (Note DIDs DI-A-3029/
S-105 and DI-E-3118/C-131-1).
(R4, tab 46, att. 1 at 2)
Thus, PCA had to be performed on the first production
unit of each Configuration Item prior to the completion
of DT&E. Every component in each LORAN chain was
a configuration item. (Tr. 3/98)
19. In 1975 and 1976, appellant requested that the
Government grant it financial relief by means of con-
verting progress payments to revenue through use of a
provisional billing system or an economic price adjust-
ment clause (R4, tabs 1, 4, 5, 6, 7, 8, 10, 11).
20. After lengthy negotiations, Modification P00023
to the contract was executed on 29 March 1977. This bi-
lateral modification extended the contract delivery sched-
ule to 30 June 1977 and provided for a revised billing
schedule. (R4, tab 48) By means of the revised billing
schedule, appellant was able te convert progress payments
into earnings for its accounting purposes (tr. 1/128-30,
2/60). Upon appellant’s suggestion, Line Item 0001 was
divided into three subparts solely for billing purposes,
in order to accomplish this new billing and payment
method. Modification P00023 did not alter the terms of
Section E or Section H of the contract schedule. (Tr.
2/178, 183, 3/10-12; stip. 8.
21. The billing schedule added by Modification P00023
subitemized Line Item 0001 as follows:
SECTION J—Add the following clauses:
27. BILLING SCHEDULE:
The parties hereby agree to the Contract Billing
Schedule as set forth below which sub-itemizes CLIN
0001 as follows:
Billing Price
1.1 Design, Develop, Fabricate
and In Plant Test one each
LORAN GROUND CHAIN $12,500,000
52a
1.2 Field System Test to include
Environmental, Maintainability,
Segment, and System Testing (less
High Power Test) plus residual
tasks from 1.1 and Data (less
A052 and A093) 692,956
1.3 Data A052 and 093 450,000
Notwithstanding the provisions of the ‘Payment’ and ‘Incentive
Price Revision (Firm)’ clauses of this contract, the above
billing price break out shall not entitle the contractor to
voucher for or receive payments in excess of the amounts it
would be entitled to receive under the ‘Progress Payments’
clause if CLIN 0001 had not been sub-itemized.
(R4, tab 48 at 10)
22. On 29 March 1977, a “Material Inspection and
Receiving Report” DD Form 250, (hereinafter “DD250”)
was signed on behalf of the Government accepting con-
‘tract line item 1.1, except for certain residual tasks set
forth in accompanying documents (app. supp. R4, tab
A-6). The System Program Director (SPD) for the Air
Force signed the DD250, but did not check the box indi-
cating that his signature amounted to acceptance of the
chain in the block provided in the document. As of 29
March 1977, appellant successfully had completed design
development and in-plant tests of the basic LORAN chain
and had accomplished transportability, environmental,
functional and acceptance tests successfully, except for
the residual items designated in the DD250. The Reli-
ability Demonstration which was a part of the Field Sys-
tem Test had not been performed. (Stip. 10) There is
no evidence that the Government accepted anything other
than work already performed pursuant to the revised
billing schedule of Modification P00023 when the 29
March 1977 DD250 was signed (tr. 1/139, 2/66, 179,
3/15). Indeed, Block 16 of the document described the
item accepted in the terms of Item 1.1 as the “billing
schedule” only (app. supp. R4, tab A-6).
23. Reliability testing of the LORAN system was per-
formed in the field (tr. 2/110). Because the operability
See ae ee
a Pe AS
53a
of the system in terms of the specification requirements
could be determined only through field testing, four sites
were used. Eglin AFB served as the monitor site and
the three triangulation legs of the system were located
in Raiford, Florida, Kisatchie, Louisiana, and Anniston,
Alabama. (Tr. 2/109-10, 3/44)
24. In a Production Progress Report for November
1977, appellant stated, inter alia, that “the balance of
program tasks including all test effort, design review,
refurbishment, system acceptance and delivery is sched-
uled to be completed by 15 May 1978” (R4, tab 185).
This prediction was repeated in the Production Progress
Report for December 1977 (R4, tab 186).
25. The Production Progress Report for January 1978
estimated a completion date of 10 March 1978, and
stated:
Reliability demonstration tests have been completed.
The balance of program tasks including antenna
teardown, design reviews, refurbishment, system ac-
ceptance and delivery is scheduled to be completed
by March 1978.
(R4, tab 187)
26. On 23 January 1978, an inter-office memorandum
prepared by appellant revealed that a number of com-
ponents were missing from the LORAN assembly at
Eglin AFB. Correction of these deficiencies was required
on or before 30 January 1978. (R4, tab 92)
27. In a meeting between the parties on 25 January
1978, Mr. Jack Regan, a Sperry representative, indicated
a desire to get a DD250 signed for Item 1.2, since this
action would “start the clock” in so far as the option
period was concerned. At that meeting, appellant also
indicated that it considered the DD250 executed on 29
March 1977 to represent final acceptance of Item 1.1.
(R4, tab 94)
54a
28. On 26 January 1978, appellant forwarded a
DD250 for Item 1.2 to the Government, requesting that
it be executed upon completion of PCA at the Anniston
site (R4, tab 107).
29. In a meeting held on 2 February 1978, Mr. Ralph
D’Avino, appellant’s program manager, requested that
the Government execute a DD250 upon completion of the
“on-site” portion of PCA, which was scheduled to occur
on 15 February 1978 (R4, tab 99). The Government
did not accede to Mr. D’Avino’s wishes.
30. Testing had occurred in the field throughout 1977,
and on 3 February 1978, the last scheduled test, antenna
teardown demonstration was _ performed successfully
(tr. 1/74-75, 79, 98, 2/47, 51; app. supp. R4, tab A-32).
The successful completion of these tests demonstrated the
ability of the LORAN chain to function in accordance
with the contract requirements (tr. 1/50 77).
31. Minor problems existed with respect to the equip-
ment upon the conclusion of the last test of DT&E. These
problems were confined to missing components and worn
insulation, and were remedied during appellant’s refur-
bishing efforts. (Tr. 2/7, 119-20; R4, tab 18 at attach-
ment 1)
32. Beginning on 3 February 1978 and continuing
until 18 March 1978, appellant performed refurbishment
work on the equipment at the sites, in order to make it
ready for the Government’s testing in the Initial Oper-
ating Test and Evaluation (IOT&E) program once the
equipment was accepted (tr. 2/25, 114, 3/56, 62).
33. The field portion of the PCA, whereby the hard-
ware was examined in light of the drawings, was com-
pleted on 9 February 1978 (tr. 3/87). The PCA per-
formed at Anniston, Alabama required two weeks and
found discrepancies (tr. 2/130). However, the PCA was
not formally completed until April 1978 (tr. 3/87).
34. An inter-offee memorandum prepared by Sperry
personnel on 24 February 1978 stated that acceptance
55a
had not yet occurred (R4, tab 110). A letter from the
contracting office to appellant on 27 February 1978 dis-
cussed acceptance as a future event (R4, tab 111).
35. FCA was completed on 28 February 1978 and
FQR was completed on 1 March 1978 (tr. 1/60, 87,
2/37, 3/30-31).
36. An “Engineering Development” report issued by
appellant for the period 1-28 February 1978 contained
the note that:
The only remaining program tasks are completion
of refurbishment and acceptance of transmitter sites
and completion of CDPL data items.
(R4, tab 189 at 2). This corresponds to a Government
“Production Progress Report” (DD Form 375C) for the
period of February 1278, which related that:
Loran Chain—All program tasks have been com-
pleted except for refurbishment and acceptance of
transmitter sites which is scheduled to be completed
by mid March.
(R4, tab 190)
37. A Program Progress Report prepared by appel-
lant dated 13 March 1978 contained the same information
(R4, tab 188, 190).
38. From 27 February 1978 until 18 March 1978, the
Government’s Quality Assurance Representative (QAR)
had been conductihg acceptance tests at the four sites, in
accordance with paragraph 5.2.3 of the Statement of
Work, to assure that the system operated functionally
(tr. 2/45-53; R4, tab 197). The last acceptance test was
accomplished on 18 March 1978 but the inspector’s certi-
fication letter was dated 17 March (R4, tab 197; tr.
3/53). This completed the inspection process on the en-
tire LORAN chain (tr. 3/61).
39. Appellant performed refurbishment and _ restora-
tion work at each site prior to inspection. These efforts
concluded on 18 March 1978. (Stip. 13)
56a
40. On 20 March 1978, the Government QAR and the
System Program Director (SPD) signed the DD250 pre-
pared and submitted by appellant in accordance with the
“Material Inspection and Receiving Report” clause for
Line Item 0001, “LORAN Ground Chain, Tactical, Trans-
portable (Basic with Mechanical Alternative 2 Configura-
tion)” (stip. 13; R4, tab 21; tr. 3/53). This document
reflected that the chain was “shipped” on 17 March 1978
(R4, tab 197). The SPD checked the “acceptance” box
in block 21B of the DD250. The Government’s signature
on the DD250 represented that all tests had been evalu-
ated and the DT&E had been completed successfully (tr.
2/18).
41. Execution of the DD250 is the recognized method
for acceptance in Government contracts (tr. 2/17, 61,
155).
42. On 21 March 1973, after the signing of the DD250,
the Government embarked on an Initial Operating Test
and Evaluation program (IOTE), the purpose of which
was to permit Government personnel to assure that they
could operate the systems as successfully as appellant’s
employees (tr. 2/19, 123, 133). The contractor’s par-
ticipation in this program was limited to furnishing a
number of engineers as support personnel for a period
of three months. Their services were “to begin after
acceptance” of the system by the Government. (Item
0010 in Section F of the contract schedule, at R4, tab
25 and in Modification P00002 at R4, tab 27) IOTE
is a crucial factor in the decision to exercise an option,
and an option can be exercised only upon the successful
eompletion of IOTE. A piece of equipment must be in
a restored condition to order to be subjected to IOTE.
As a result, the LORAN chain in this case had to be
refurbished prior to the performance of IOTE. (Tr.
2/20, 144, 158) IOTE cannot be performed until DT&E
is complete (tr. 2/132-33).
Me
TEM Minas Anan Bw vated idee MOR Rant Saas A Ws
io
CAE ic: we ery.
57a
43. Performance of IOTE consumed 60 days. Upon its
successful completion, the Government reviewed the test
data and concluded that Government personnel could
operate the equipment and that it met the specified per-
fomance levels set forth in the contract. (Tr. 2/19-20)
44. In correspondence to the Government dated 20
April 1978, appellant acknowledged that the system had
been formally accepted on 20 March 1978 (R4, tab 199).
45. There is no evidence of any comment by appellant
on 3 June 1978 (the 120th day following 3 February
1978) when the Government had not exercised its option
for chains 2 and 3.
46. Through unilateral Modification P00026 dated 6
July 1978 and received by appellant on 14 July 1978,
the Government advised appellant that, inter alia:
Options for CLIN 0002 (Chain 2), CLIN 0003
(Chain 3), and related Data CLIN 0012 are hereby
exercised and a contract modification to that effect
was mailed to Sperry Gyroscope Division on 7 Jul 78.
(R4, tab 51; stip. 14)
47. 14 July 1978 marked the 161st day following 3
February 1978 and the 116th day subsequent to 20 March
1978.
48. Appellant advised the Government in a letter dated
14 July 1978 that:
Sperry acknowledges receipt on July 14, 1978 of
your TWX and Contract Modification P00026 dated
July 6, 1978 purporting to exercise options for
CLINS 0002 and 0003 of Contract F19628-74-C-
0098. You are hereby advised that for the reasons
set forth below Sperry believes these options to be
invalid and no longer exerciseable by the Depart-
ment of the Air Force, and that the attempted exer-
cise of these options at this date constitutes a con-
58a
structive change to Contract F19628-74-C-0098 for
which Sperry is entitled to an equitable adjustment
in contract price and contract schedule.
In recognition of the Air Force’s acknowledged
need for the equipment and services covered by the
option, Sperry will proceed with CLINS 0002 and
0003 as a change to the contract, and will prepare
and submit a claim for an equitable adjustment in
the contract price and delivery schedule. Our claim
will be filed within thirty (30) days and will be in
an amount estimated to be between $4,000,000 and
$5,000,000 at the target cost line. Sperry estimates
that the time within which the Air Force must re-
spond to this notice to minimize costs, delay or dis-
ruption of performance is seven (7) days.
(R4, tab 22)
49. Essentially, appellant’s problems stemmed from the
inflationary period of the mid-1970’s which adversely
affected its projected costs for LORAN chains to be built
after Chain 0001 (R4, tabs 86, 101).
50. Appellant made deliveries under protest and sub-
mitted a claim for equitable adjustment to the contract
price in a letter dated 10 August 1978 (stip. 14).
51. Appellant’s claim was denied in the contracting
officer’s final decision dated 31 October 1978 (R4, tab
24). Appellant took a timely appeal from the final de-
cision.
Events Determining Acceptance
Completion of DT&E
52. At the hearing, appellant’s witnesses advanced the
position that acceptance simultaneously with the con-
clusion of the last DT&E test (tr. 1/106, 109, 2/42).
The Government’s witnesses contended that the option
could not be triggéred until all tests and all data pro-
cedures (FCA and FQR) had been completed (tr. 2/47).
———
59a
58. DT&E under this contract was a comprehensive
process whereby the new design was fabricated, imple-
mented and tested, with the test results being analyzed
to verify performance (tr. 3/124). DT&E testing was
divided into two categories: category I, “Test Plan/
Procedures, Subsystem Test” was to demonstrate that
individual subsystems performed within the qualifica-
tion requirements, while category II, “Test Plan/Proce-
dures, System Test,” would demonstrate how the system
interacted to form a chain. Essentially, category I fo-
cused on individual component function, while category
, II concentrated on the operation of the chain as a whole.
(Tr. 1/44-45; app. supp. R4, tab A-33) The DT&E field
| tests were category II tests.
54. The third leg of the DT&E triad, “evaluation,” oc-
curred throughout the DT&E program, but final results
could be evaluated only after the testing process had
ended (tr. 2/54, 104-06, 3/96).
55. Because of its unique evaluation position, FQR
should be performed as late as possible in the DT&E
process to ensure that as much data as possible is avail-
able for analysis. FQR fully falls within the ambit of
“Evaluation” for purposes of DT&E. As such, we find
that FQR is a component of DT&E and that DT&E is
not complete until FQR has been performed. (Tr. 2/12,
63, 106)
56. While PCA does not evaluate the actual perform-
ance of a component, it functions as a part of DT&E,
since it facilitates the discovery and correction of dis-
crepancies (tr. 2/107, 3/86). Because of the interrela-
tionship between DT&E and PCA/FQR, we find that
DT&E was not complete until those two tests had been
completed (tr. 3/135; R4, tab 25, Statement of Work
at 57). FCA is a quality control function and an un-
derpinning to FQR (tr. 2/12, 52, 64).
| ee as ?
60a
Refurbishment
57. By the language of Modification P00021, time was
set aside after the completion of field testing so that the
equipment could be refurbished. While the parties had
anticipated that refurbishment after field tests would
be necessary, Modification P00021 marked the first time
that a specific time period was allowed for refurbish-
ment. (Tr. 3/20; R4, tab 25 at 5) Refurbishment was
required as part of DT&E, to restore the equipment to a
safe, operable condition (tr. 2/64, 113). The parties
originally thought that refurbishment would be a minor
task (tr. 3/25).
58. Controversy existed over whether refurbishment
was to commence upon the conclusion of DT&E testing
as part of the scheduled work. Appellant’s witnesses con-
tended that it did not, while the Government’s witnesses
asserted that refurbishment was the last work to be
performed on Chain 1 before acceptance. (Tr. 1/108,
2/45, 54, 3/106).
59. By the time DT&E field tests were complete, the
equipment had been on site for over 114 years and needed
active refurbishment (tr. 1/51, 74, 77, 2/88).
60. The Government’s witnesses contended that IOTE
could not begin until the chain had been accepted, and the
Government could accept only a refurbished chain (tr.
2/17-18, 70, 133, 151, 174, 3/79, 84-86; finding 32).
Thus, until refurbishing was complete, the Government
contended that it had not been tendered a product which
could be accepted for purposes of the option.
Security
61. Under Modification P00023, appellant was re-
quired to provide site security until the chain was de-
livered to the Government (R4, tab 48). The parties
defined “delivery” and “acceptance” to be synonymous
(tr. 1/116, 2/15, 65, 154, 186, 3/15).
6la
62. Initially, appellant indicated that it would cease
providing site security at the end of January 1978 (tr.
2/155). However, in response to a letter dated Jan-
uary 1978 from the Government stating that appellant
was required to provide security through delivery, ap-
pellant continued providing site security beyond 31 Jan-
uary 1978 (R4, tab 93).
63. In a meeting held on 2 February 1978, appellant
suggested transferring the security obligation to the
Government on 3 February 1978 (tr. 2/53). Appellant
then revised its schedule to terminate site security on 15
February 1978 and agreed to provide site security serv-
ice until 1 March 1978, in response to a telegram dated
14 February 1978 stating that “Sperry is required to
provide site security services until acceptance of [Line
Item] 001” (R4, tab 102; tr. 2/34). In fact, appellant
provided guards at the site until 20 March 1978, the
date the Government executed the DD250 (tr. 2/31, 115,
131, 156). While appellant claims that it continued to
provide security at the sites solely because of the value
of its equipment located there, we have no evidence of
any claim by appellant for the costs of these services.
(Tr. 2/98, 8/119) The most revealing indication of who
exercised control over the equipment after 3 February
1978 came from Mr. Ralph D’Avino, appeliant’s Program
Manager, who stated that appellant performed site se-
curity after 3 February 1978 because “we had approxi-
mately $15 million worth of equipment sitting |there].
(emphasis supplied). (Tr. 3/1119)
DECISION
This appeal raises three questions which can be framed
as follows:
1. What was the impact of the implementation of
the new billing schedule contained in the DD250 ex-
ecuted on 29 March 1977?
a ee
62a
2. What impact did completion of the last DT&E
field test, on 3 February 1978, have on commence-
ment of the period within which the Government
could exercise its option to purchase additional
LORAN chains?
3. If the option period did not begin on 3 February
1978, on what date did it commence and what event
marked that milestone?
The DD250 of 29 March 1977
Appellant urges upon us that execution of the DD250
for the revised billing schedule on 29 March 1977 con-
stituted an acceptance under the contract and started
the Government’s 120 day option period for Chains 2
and 3. (Br. at 31) We disagree.
Adoption of the revised billing schedule through Modi-
fications P00023 was undertaken to afford financial re-
lief to appellant. It divided Line Item 0001 into three
separate sub-categories, and the DD250 operated only
with respect to Line Item 1.1, “Design, Develop, Fabri-
cate and In Plant Test one each |LORAN Chain].”
While the SPD (System Program Director) signed the
DD250, he did not indicate that he was accepting the
LORAN chain; he acknowledged only the revised billing
schedule in the document.
In its brief, appellant relies upon two of this Board’s
eases, Lear Siegler, Inc., ASBCA No. 12164, 69-1 BCA
{ 7563, and Keco Industries, Inc., ASBC No. 16645, 73-2
BCA § 10,056.
Appellant cites Lear Siegler, supra, for the proposition
that the “conditional” acceptance of the billing schedule
operated to trigger the option period. (Br. at 34) The
facts in Lear Siegler are distinguishable from the facts
in the case at hand. In that case, the Government’s op-
tion arose because of the conditional approval of a first
item, subject to correction of deficiencies. Here, the sig-
63a
nature of the SPD on the DD250 did not indicate accept-
ance of the LORAN chain; it only signified the implemen-
tation of a revised billing schedule.
Appellant also relies on Keco Industries, Inc., supra,
to support its contention that the Government’s option
period commenced on 29 March 1977. Appellant’s re-
liance on our holding in that case is misplaced. The
Board held there that Government-caused deiays in the
delivery time for a product did not operate to extend the
pertinent option period. (At 47,175) Here, the delays
were not attributable to any Government action, but
merely were the result of problems attendant to the de-
velopment of a technologically novel apparatus. (Finding
2)
Appellant’s contentions in its brief are not consistent
with its conduct during performance. For example, in a
meeting conducted on 25 January 1978, appellant ad-
mitted that the DD250 referred only to Item 1.1 (the
billing schedule), and not the entire Line Item 0001.
(Finding 26) It is well recognized that the conduct of the
parties before the dispute arose is of great weight in
interpreting the contract. General Warehouse Tow, Inc.
v. United States, 181 Ct. Cl. 180, 389 F.2d 1016 (1967) ;
Chromalloy American Corporation, ASBCA Nos. 22119,
22120, 80-2 BCA {] 14,566.
Therfore, we conclude that the DD250 executed on 29
March 1977 served only to enable payment in accord-
ance with the new billing scheduled, did not constitute
acceptance of the LORAN systems and did not “start
the clock” on the Government’s option period.
Completion of DT&E Field Tests and Acceptance
The parties agree that the term “final acceptance” in
the option provision in Section E of the contract schedule
had the same meaning as in Section I, Inspection and
Acceptance, which provided for “|F Jina! inspection and
64a
acceptance upon successful completion of DT&E Field
Test.” This does not mean, however, that this term could
be given different meanings for the purpose of exercis-
ing the option and for the operation of other provisions
of the contract.
Since we are not interpreting the option provisions, but
the term “final acceptance” as it appears in the “Inspec-
tion and Acceptance” provision, the strict interpretation
rules, whatever they may mean in this context, are not
applicable, despite the approach taken by the dissenting
opinion.
Appellant contends that this language is unambiguous;
acceptance for the purpose of exercising the option oc-
curred simultaneously with or at the time of completion
of the last DT&E field test on 3 February 1978 and be-
fore a DD250 was executed. (Br. at 27-28) In the al-
ternative, appellant contends that DT&E was completed
no later than 1 March 1978 when both FCA and FQR
had been completed. (Br. at 22-23) In either case, the
Government’s option period would have expired on 6
July 1978, thus rendering the option exercise on 14 July
1978 untimely. (Br. at 23)
In opposition, the Government takes the position that
the acceptance of the LORAN chain that started the 120-
day option period did not occur until the DD250 was
signed on 20 March 1978 and, consequently, exercise of
the option for two additional systems on 14 July 1978
was timely.
In resolving contract disputes arising from the differ-
ent readings the parties have attributed to contract lan-
guage, the Board’s function is to discern the parties’ in-
tent as this is expressed in the contract. Dynamics Cor-
poration of America v. United States, 182 Ct. Cl. 62, 72,
389 F.2d 424, 429 (1968); SCM Corporation v. United
States, Ct. Cl. ——, 675 F.2d 280, 283 (1982). We
accomplish this by ascertaining the meaning to be given
—————
65a
to the words and manifestations in the contract in a proc-
ess commonly referred to as interpretation. Restatement
(Second) of Contracts § 226 (1973 Tent. Draft); 4 Wil-
liston on Contracts, §§ 600, 602 (3d ed. 1961); 3 Corbin
on Contracts § 534 (1960).
The rules that govern the interpretation have been
stated as follows:
In attempting to give effect to the contracting par-
ties’ intent, the court is guided by the principles that
“(tjhe parties’ intent must be gathered from the in-
strument as a whole.” Kenneth Reed Constr. Corp.
v. United States, 201 Ct. Cl. 282, 288, 475 F.2d 583,
586 (1973), preferably giving a reasonable meaning
to all parts of the instrument rather than leaving a
portion of it useless, Martin Lane Company, Inc. v.
United States, 193 Ct. Cl. 203, 215, 432 F.2d 1013,
1019 (1970), from the perspective of a “reasonably
intelligent person acquainted with the contemporary
circumstances.” Firestone Tire & Rubber Co. v.
United States, 195 Ct. Cl. 21, 30, 444 F.2d 547, 551
(1971), and ascribing to the contract language “its
ordinary and commonly accepted meaning”, Hol-Gar
Manufacturing Corp. v. United States, 169 Ct. Cl.
384, 390, 351 F.2d 972, 976 (1965), without twisted
or strained out of context analysis, Aero Mayflower
Transit Co. v. United States, 162 Ct .Cl. 233 (1963),
or regarded to the subjective unexpressed intent of
one of the parties. Dana Corp. v. United States, 200
Ct. Cl. 200, 214, 470 F.2d 1032, 1041 (1972); John
C. Kohler Co. v. United States, 204 Ct. Cl. 777, 787,
498 F.2d 1360, 1365 (1974).
ITT Arctic Services, Inc. v. United States, 207 Ct. Cl.
743, 751, 524 F.2d 680 (1975).
For these rules to be considered, the language need not
be ambiguous or the provisions conflicting, as appellant
and the dissenting opinion insist, in our opinion errone-
66a
ously. Even in the absence of ambiguity, contract lan-
guage must be given a meaning which can be derived
from a reading of the document by a reasonable person
familiar with the surrounding circumstanees. W.G. Cor-
nell Co. v. United States, 179 Ct. Ch. 651, 670, 376 F.2d
299, 311 (1967). An authoritative commentator has
stated:
All contract language is potentially ambiguous and
all contract language is potentially capable of being
made unambiguous. Instead of starting with the
question, “Is the contract ambiguous?”, the proper
approach to cuntract interpretation is to go directly
to the question, “What does the contract mean with
respect to this fact situation?”
Shedd, Jr., “Resolving Ambiguities in Interpretation of
Government Contracts,” 36 Geo. Wash. L. Rev. 1, 21
(1967); see also 3 Corbin on Contracts, supra, at § 535.
The problem with appellant’s position is that it focuses
on one isolated provision of the contract to the exclusion
of all other pertinent provisions. See Restatement (Sec-
ond) of Contracts § 228, comment d (1973 Tent. Draft).
This narrow reading of the contract is exaggerated fur-
ther by appellant’s defining “upon” in the context to
mean “at the time DT&E Field Test at destination is
successfully completed” (reply br. at 1-2) (emphasis
supplied), thus choosing one of the several possible mean-
ings for this word. “Upon” is defined variously by
Webster’s Third New International Dictionary (1971) at
2517-18 as “immediately following upon,” “very soon af-
ter,” “on the occasion of” and “at the time of.” See also
Black’s Law Dictionary, 981 (rev. 5th ed. 1979).
We disagree with appellant’s propositions that the par-
ties intended acceptance of the LORAN chain to occur
upon occurrence of an event (i.e., the successful comple-
tion of the DT&E field tests) and that a completed DD250
was not required to denote acceptance.
i es ee, ee as en
67a
The record does not support these propositions. A fair
reading of the contractual provisions does not permit
such a conclusion. On the contrary, the contract estab-
lished a well-defined procedure from inspection to ac-
eeptance and we can find no indication that the parties
intended to discard these contractual steps.
Although the parties regarded “delivery” and “ac-
ceptance” to be synonymous terms in the performance of
this contract, the two terms represent two distinct ac-
tions within the entire contractual framework.
Section H of the contract schedule required delivery
of the LORAN chain at the DT&E field site (destina-
tion). This was understood to mean that the equipment
was to be tendered to Government personnel at the var-
ious field sites. Thus, as specified in the contract, delivery
was used with reference to the time and place when and
where transfer of possession was to occur. It was sig-
nified by the completion and submisison of a DD250 pur-
suant to the “Material Inspection and Receiving Report”
clause, which provides, in pertinent part:
At the time of each delivery of supplies or services
under this contract, the Contractor shall prepare and
furnish to the Government a Material Inspection and
Receiving Report...
(emphasis supplied)
This act of delivery occurred at each site when the
Government’s Quality Assurance Representative (QAR)
conducted his final inspection in the form of acceptance
tests at each of the four sites. These acceptance tests
were the conduct constituting “final inspection” within
the meaning of Section I of the contract schedule. As
such, inspection was completed only when the acceptance
tests had been performed. The SPD confirmed delivery
and acceptance at the destination by his signature on the
DD250. (Finding 39) This procedure is consistent with
the requirements of the Armed Services Procurement
68a
Regulations (ASPR) when acceptance is to occur at des-
tination. See ASPR App. I-301 (31 JAN. 1977).
Acceptance is defined as follows in ASPR § 14-001.6:
Acceptance means the act of an authorized repre-
sentative of the Government by which the Govern-
ment assumes for itself, or as agent of another,
ownership of existing and identified supplies tendered
or approves specific services rendered, as partial or
complete performance of the contract on the part
of the contractor.
The “Inspection” clause further provides that accept-
ance “shall be made as promptly as practicable after
delivery except as otherwise provided in this contract”’
and that acceptance shall be conclusive (with exceptions
not pertinent here).
However, it is important to note that acceptance not
only follows delivery, but also is not contemplated to
occur until all required inspection (including testing)
has been completed. This is not only mandated by the
“Tnspection” clause, but also by Section I of the contract
schedule that requires “[f]inal inspection and acceptance
upon successful completion of DT&E Field Test at desti-
nation.”
(emphasis supplied)
Appellant seems to ignore this point when it argues
that acceptance of the LORAN chain occurred upon com-
pletion of the DT&E field tests. If this were the case,
final inspection would be eliminated or reduced to a
formality. Appellant has not shown how a final inspec-
tion could have been or was accomplished prior to the
alleged acceptance of the system on 3 February 1978.
Moreover, our comparison of the standard “Inspection”
and “Material Inspection and Receiving Report” clauses
with pertinent provisions of the contract schedule does
not show any conflict or inconsistency between them. It
also should be considered that such standard clauses
69a
“cannot lightly be read out of it [the contract], or de-
prived of most [their] normal substance.” Thompson
Ramo Woodridge Inc. v. United States, 175 Ct. Cl. 527,
536, 361 F.2d 222, 229 (1966).
The specifics of the testing and inspection to be com-
pleted before acceptance of the LORAN system could
occur were set forth in the Statement of Work and the
description of various tasks. These provisions provided
that after successful completion of the field tests, and
before acceptance of the system, the contractor was re-
quired to correct all design deficiencies and the contract-
ing officer must have acknowledged completion of pre-
liminary design review, critical audits, physical con-
figuration audit and formal qualification review. These
tasks constituted the third leg of the DT&E triad, “eval-
uation.” While evaluation occurred throughout the
DT&E process, final results of the program could be
evaluated only after the testing phase had ended. The
language of paragraph 5.2 of the Statement of Work
mandated that acceptance could occur only upon the
completion of PCA, FCA and FQR. Since these pro-
cedures had not been completed by 3 February 1978, the
LORAN chain could not be accepted by the Government
on that date. Inasmuch as final inspection had to be
completed before acceptance, we find no inconsistency
between the contract schedule and the Statement of Work
as appellant suggests.
Refurbishing of the Equipment After Testing
The PCA, FCA and FQR had been completed by 1
March 1978, and the only task appellant performed after
that date was refurbishing of the equipment. This lasted
until 18 March 1978. During the same period, the Gov-
ernment’s QAR conducted his final inspection of the
four sites by performing acceptance tests on the refur-
bished equipment.
There is no disagreement between the parties that
when the DT&E field tests were completed, the LORAN
70a
chain was in a deteriorated condition, owing to the fact
that it had been exposed to the elements for over a year
and needed active refurbishment.
Appellant argues, in the alternative, that the LORAN
chain should have been accepted on 1 March 1978 since
all contract requirements for DT&E had been satisfied.
In appellant’s opinion, refurbishing was not part of
DT&E and was not required to be completed prior to
acceptance.
The Government claims that the system could not have
been accepted before refurbishment was completed, and
this is what actually happened. We agree with the Gov-
ernment on this point.
The only contractual provision the parties have iden-
tified as requiring refurbishment of the equipment is
found in Section F of the contract schedule as an addi-
tion to Task 1 of the Statement of Work. This requires
the contractor to “refurbish and restore, including re-
placement if necessary, all elements of the chain to a
deliverable condition . . .” after DT&E tests were com-
pleted. (emphasis supplied) During performance, the
parties had recognized this requirement by scheduling
a period of time after completion of the field portion
of DT&E for refurbishment.
There is nothing to indicate that the parties contem-
plated acceptance of the entire system when the equip-
ment was only partially refurbished or refurbishment
had been completed at some of the sites. Quite to the
contrary, appellant’s own engineering development re-
port for the period 1-28 February 1978 revealed that
“the only remaining program tasks are completion of
refurbishment. . . .” (emphasis supplied) (Finding 35)
The fact that the parties recognized that refurbishment
of the equipment at all sites would have to be accom-
plished before acceptance is shown by the requirement to
have the equipment in “deliverable condition” as a result
la Pele Abb « a erin OMEN abated IS yas
Tla
of refurbishment. Delivery of the system had to occur
before acceptance, and this refurbishment also had to
be completed at that point.
This conclusion likewise is consistent with the imme-
diate availability of the system after acceptance for the
Government’s performance of Initial Operating Test and
Evaluation (IOTE). For these tests to be conducted, the
equipment had to be in fully operable condition and it
could not be in such a condition without having been
refurbished. IOTE could start, and in fact did commence,
immediately after acceptance of the system. Thus, re-
furbishment had to be completed by that time. Any
refurbishment action or activity by the contractor after
acceptance also would have been inconsistent with the
possession and custody of the equipment transferring to
the Government upon acceptance.
Providing Security at the Sites
Under the terms of the contract, appellant was re-
quired to provide site security until delivery. (Finding
60) Despite the disagreement which arose whenever
appellant suggested that it would cease providing secu-
rity, appellant provided security at the sites until 20
March 1978. (Findings 60-62)
In John C. Kohler Co. v. United States, 204 Ct. Cl.
777, 498 F.2d 1360 (1974), the Court held that when the
Government takes control over an item and operates it,
although some preconditions to acceptance have not oc-
curred, the Government will be deemed to have accepted
the item constructively (at 1367). While Kohler ad-
dresses the problem in terms of risk of loss, we believe
it is instructive in this appeal.
Prior to 20 March 1978, the Government exerted no
dominion and control over the LORAN chain equipment
at any of the sites; it did not provide for their security.
Indeed, had the Government provided security for the
72a
equipment prior to 20 March 1978, it would have assumed
a degree of control and financial responsibility incon-
sistent with its claim that it had not yet accepted the
equipment. Thus, appellant’s provision of security at the
LORAN sites constituted an exercise of dominio