USCA Case #24-1119
1.
Document #2058570
Filed: 06/07/2024
Page 3 of 15
My name is Julie Fedorchak, and my business address is 600 E. Boulevard Ave. Dept 408,
Bismarck, ND 58505. I am over the age of 18, have personal knowledge of the subject
matter, and am competent to testify concerning the matters in this declaration.
2.
I have served as one of three commissioners on the North Dakota Public Service
Commission (NDPSC) since 2013. I am currently President of the National Association of
Regulatory Utility Commissioners (NARUC), the state's liaison to the Midcontinent
Independent System Operator (MISO), and on the advisory board of the Electric Power
Research Institute. I have previously served in numerous leadership roles including
President of the Organization of MISO States (OMS), vice-chair of the NARUC Gas
Committee, and vice president of the Gas Technology Institute's advisory board.
3.
The NDPSC is a state agency created under the Constitution of North Dakota and is vested
with, among other things, jurisdiction for the economic regulation of electric and gas public
utilities, telecommunications, the siting of energy plants and electric and natural gas
transmission facilities, reclamation of active and abandoned mine lands, and railroad
safety. The Commission also actively participates in the governance of MISO through
OMS and Southwest Power Pool (SPP) through the Regional State Committee (RSC).
4.
The NDPSC is responsible for ensuring safe, affordable, and reliable electric and gas
services for North Dakota ratepayers. It oversees the orderly development of capitalintensive infrastructure of investor-owned utilities within the state, including generation
resource planning. Furthermore, the NDPSC serves as the siting authority for energy
generation, gas processing, and pipeline and electric transmission within the state.
5.
I am submitting this declaration in support of Petitioners' Motion to Stay the Final Rule,
published by the U.S. Environmental Protection Agency (EPA) on May 7, 2024, entitled
(Page 54 of Total)
2
161a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 4 of 15
"National Emission Standards for Hazardous Air Pollutants: Coal- and Oil-Fired Electric
Utility Steam Generating Units Review of the Residual Risk and Technology Review," 89
Fed. Reg. 38508 (Final Rule).
6.
The NDPSC has consistently highlighted risks associated with the transition from
traditional thermal generation and has serious concerns that the Final Rule will further
undermine the reliability of the power grids in North Dakota and around the country. I
recently highlighted our concerns to Congress and FERC, expressing the critical need to
extend the lives of existing thermal resources to allow time for new technology to "bridge
the gap" between "reliability attributes of wind and solar megawatts versus thermal
megawatts."1 Since then, trends and forecasts have called for considerable load growth,
making it abundantly clear that this is not an energy transition at all. We are in a period of
energy expansion heightening the risks to which I testified to.
7.
The NDPSC has already expended significant amounts of staff time and resources trying
to determine and mitigate the impacts that the Final Rule will have on the ability of the
people of North Dakota to have access to reliable, affordable electricity. Absent a stay of
the Final Rule while litigation challenging it is pending, NDPSC anticipates further
dedicating thousands of hours of staff time and hundreds of thousands of dollars attempting
to understand and mitigate the adverse effects the Final Rule will have on the power grids
providing electricity to North Dakota's citizens. Those costs will not be recoverable if the
Final Rule is ultimately held unlawful. Staff time and resources that NDPSC must dedicate
' See Pathways to Lowering Energy Prices: Hearing Before S. Comm. on Energy & Nat. Res., 117th Cong. (July 13,
2022) (testimony of Comm'r J. Fedorchak, Chair, N.D. Pub. Serv. Comm'n). AD23-9 Annual Reliability Technical
Conference, Tr. at 239: 1 (Nov. 9, 2023) (Comm'r Fedorchak).
<https://www.energy.senate.gov/services/files/E565FF3C-3B1B-42CD-A4C0-68ED082CC280>. See also AD23-9
Annual Reliability Technical Conference, Tr. at 239: 1 (Nov. 9, 2023) (Comm'r Fedorchak).
(Page 55 of Total)
3
162a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 5 of 15
to understanding and trying to mitigate the effects of this Final Rule detract from the
NDPSC's ability to fulfill its obligations to the people of the State.
8.
The NDPSC has very serious concerns that the Final Rule will undermine the reliability of
the power grids that provide electricity for the people of North Dakota. An unreliable
power grid would cause the State to experience blackouts and would result in significantly
higher prices for electricity in North Dakota. The seriousness of these concerns cannot be
overstated.
9.
The NDPSC is not alone in its reliability concerns. FERC, NERC, and other entities
charged with overseeing the reliability of our power grids all around the country have in
recent years been shouting warnings about the long-term reliability of our nation's power
grids for anyone willing to listen. NERC recently stated that the bulk power system has
reached an "inflection point" in which the risk profile to customers is steadily deteriorating
due to the retirement of valuable generation resources outpacing the addition of new
dispatchable generation.2
10.
In its 2023 Long Term Reliability Assessment, NERC identified that the SPP region will be
at an "elevated risk" of shortfall in extreme conditions, such as the recent winter storms.
This risk is more prevalent when high demand coincides with low wind or above normal
generator outages.3 As recent as this past January, North Dakota experienced recordbreaking cold temperatures during which SPP declared extended cold weather and
conservation operation advisories. Concurrently, the weather prevented many generators
from running. The combination resulted in multiple severe reliability emergencies.
2 The Reliability and Resiliency of Electric Service in the United States in Light of Recent Reliability Assessments
and Alerts: Hearing Before the Committee on Energy and Natural Resources (June 1, 2023) (Statement of James B.
Robb, North American Electric Reliability Corporation).
3 Id. at 8.
(Page 56 of Total)
4
163a
USCA Case #24-1119
11.
Document #2058570
Filed: 06/07/2024
Page 6 of 15
NERC has identified even more risk in MISO, a regional transmission organization (RTO)
serving parts of North Dakota, projecting a "high risk" level indicating insufficient resource
adequacy for areas.4 This indicates that the electricity supply for these areas is more likely
to be insufficient in the forecast period and more firm resources are needed. While MISO
has trended up in installed capacity, accredited capacity that can be relied upon to meet
peak system needs is moving in the opposite direction. MISO's recent accreditation
reforms have shown that this trend is likely to worsen.5
12.
MISO released the following statement regarding long term grid reliability:
There are urgent and complex challenges to electric system
reliability in the MISO region and elsewhere. This is not just
MISO's view; it is a well-documented conclusion throughout the
electric industry. ...
Many dispatchable resources that provide critical reliability
attributes are retiring prematurely due to environmental regulations
and clean-energy policies. ...
The new weather-dependent resources that are being built, such as
wind and solar, do not provide the same critical reliability attributes
as the conventional dispatchable coal and natural gas resources that
are being retired. While emerging technologies such as long
duration battery storage, small modular reactors and hydrogen
systems may someday offer solutions to this issue, they are not yet
viable at grid scale.6
13.
Warnings of this nature are not typical from RTOs like MISO, which are generally policy
and politics neutral. However, they have a responsibility to ensure our country's power
grid remains reliable. This warning from MISO should be taken seriously.
4 Id.
Midcontinent Independent System Operator (MISO), Managing Reliability Risk in the MISO Footprint (June 16,
2022), available at https://cdn.misoenergy.org/20220616%20Board%20O)/020Directors%20Item%2008a%20
Reliability%20lmperative625168.pdf.
6 Midcontinent Independent System Operator, "MISO's Response to the Reliability Imperative," at 2 (Feb. 2024),
available at https://cdn.misoenergy.org/2024%20Reliability%20Imperative%20report%20Feb.%2021%20
Final504018.pdf?v=20240221104216.
(Page 57 of Total)
5
164a
USCA Case #24-1119
14.
Document #2058570
Filed: 06/07/2024
Page 7 of 15
To underscore our concerns, the loss of a single thermal plant could be the difference
between a stable grid and load shedding or brownouts in North Dakota and the surrounding
regions. During Winter Storms Uri and Elliott, Coal Creek Station, a unit capable of
dispatching 1,150 MW of power into the MISO market, operated at maximum capacity
during both winter storms. This resulted in a higher capacity rating due to Coal Creek's
value in maintaining reliability. Any negative impact to this one generator's capacity for
generating electricity for the grid has the potential for an immediate and significant impact
on the MISO North Region and North Dakota customers.
Impact of the Final Rule on North Dakota's Power Plants and Power Grids
15.
The Final Rule will require lignite-fired electric generation units (EGUs) in North Dakota
to determine whether to spend an extraordinary amount of money to come into compliance
with the Final Rule, or to close their units either because compliance with the new standards
is not technologically feasible or compliance with the standards would render their
operations no longer economically viable. The NDPSC's review of the State's EGUs has
provided merit to our concerns that the economics and technical infeasibility created by the
Final Rule makes power plant closures a likely reality. This will have a profound impact
on the citizens of North Dakota. There will also be regional impacts across the MISO and
SPP systems at times when people and communities are most vulnerable to life threatening
weather events.
16.
The forced, premature retirement of dispatchable fossil fuel generation in North Dakota
will increase reliance on intermittent sources of power (e.g., wind and solar). An increased
reliance on intermittent resources will result in a markedly lower accredited capacity value
(Page 58 of Total)
6
165a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 8 of 15
for those resources in the future, signaling that such resources will increasingly have
difficulty serving load during all hours.
17.
Regional Transmission Organizations, Public Service Commissions, and similar entities
across the country have been warning that projected increases in intermittent generation
resources will be unable to resolve the reliability issues that result from the forced
retirement of dispatchable generation resources.
18.
MISO recently reiterated that warning in its "MISO Region Reliability Imperative" report:
Wind resources can experience "fuel" availability challenges in the
form of highly variable wind speeds. Consequently, the energy
output of wind can fluctuate significantly on a day-to-day and even
an hour-by-hour basis — including multi-day periods when output
drops far below average.
For example, over 60 consecutive days in January-February 2020,
hourly wind output in MISO averaged more than 8,000 MW.
However, ... for 40 consecutive hours in the middle of that 60-day
block, average hourly wind output dropped to less than 47 MW, and
only once exceeded 200 MW in any single hour.
An even longer and broader "wind drought" occurred during Winter
Storm Uri in 2021 when the MISO, Southwest Power Pool, Electric
Reliability Council of Texas and PJM regions all experienced 12
consecutive days of low wind output.7
19.
The forced retirement of reliable, dispatchable power generation sources has already
significantly threatened the reliability and resilience of the power grids even in states like
North Dakota where we invest heavily in dispatchable resources — especially during
severe weather events. High load growth magnifies this problem. Implementation of the
Final Rule will foreseeably make an already precarious situation even worse.
7 Midcontinent Independent System Operator, "MISO's Response to the Reliability Imperative," at 11 (Feb. 2024),
available at https://cdn.misoenergy.org/2024%20Reliability%20Imperative%20report%20Feb.%2021%20
Final504018.pdf?v=20240221104216.
(Page 59 of Total)
7
166a
USCA Case #24-1119
20.
Document #2058570
Filed: 06/07/2024
Page 9 of 15
The NDPSC has also determined that in North Dakota, intermittent generation resources
like wind and solar, while providing value as energy and capacity resources, are energy
limited and cannot replace attributes from coal-fired EGUs that will be affected by the
Final Rule, including on-demand dispatchability. Coal-fired plants provide essential
reliability services such as frequency support and spinning reserves, along with voltage
regulation. The grid operators use these services to operate reliably under an array of
system conditions, generally without the concern of having too few of these services
available. Merely having capacity does not equate to having necessary reliability services
or ramping capability to balance generation and load.
21.
Furthermore, MISO has flagged that voltage instability challenges within the next five
years are strongly correlated with today's aggressive pursuit of weather-dependent
resources by many states.8 MISO's Renewable Integration Impact Assessment study
determined that stability-related challenges are projected to reach a tipping point when a
30% renewable threshold is reached, which is projected to occur around 2027. The grid
stability-related challenges from increased renewable integration will also drive mitigation
capital cost.
22.
A lack of voltage stability could result in loss of load in an area or protective system
tripping of transmission lines or system components, leading to cascading outages.
Voltage collapse, one potential result from voltage instability, has been identified as a
contributing factor in large scale blackouts across the globe, including Scandinavia (2003),
Northeastern U.S. (2003), Athens, Greece (2004), and Brazil (2009).
During the
Northeastern U.S. event in 2003, voltage stability resulted from multiple line tripping
8 Pg 36 of https://cdn.misoenergy.org/2023%20Attributes%20Roadmap631174.pdf.
(Page 60 of Total)
8
167a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 10 of 15
contingencies, causing voltage fluctuations, reactive power deficiencies, and the tripping
or malfunctioning of generators and transformers.
23.
The State's lignite coal plants have the capability to respond to frequency and voltage
changes and actively provide these services to the market.9
North Dakota's lignite
resources also have fuel supply reserves in near proximity to the plant, and in many cases
are mine-mouth, protecting them from supply chain disruption.
24.
In short, the forced retirement of reliable, dispatchable power generation resources has
already significantly threatened the reliability of the power grids that provide electricity to
the people of North Dakota, especially during extreme weather events. Implementation of
the Final Rule will foreseeably make an already precarious situation even worse.
Impact of the Final Rule on North Dakota's Electricity Pricing
25.
EPA's claims that the Final Rule will not affect the price of electricity in the nation are not
true for North Dakota.
If a stay is not granted, North Dakota lignite EGUs will
immediately incur significant investment cost to become compliant or be forced to begin
winding down operations. The economic or technical infeasibility of complying with the
Final Rule will inherently subject ratepayers to stranded costs pancaked with replacement
generation and transmission infrastructure investment.
26.
Using just one North Dakota coal-fired power plant as an example, if Coyote Station can
successfully implement necessary technology for compliance with the Final Rule, that
plant alone is anticipated to pass through over 2 million dollars of additional annual
revenue requirements onto consumers, resulting in at least a 0.5 percent increase in rates
to North Dakota customers. That is just the compliance costs associated with one plant.
9 NERC 2022 Long-Term Reliability Assessment, pg 19 in document. December 2022. https://www.nerc.com/
pa/RAPA/ra/Reliability%20Assessments%20DUNERC_LTRA_2022.pdf.
(Page 61 of Total)
9
168a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 11 of 15
Similar rate impacts are anticipated for Northern States Power customers for the state's
jurisdictional allocation of costs for upgrades to their existing coal facilities. It is also
worth noting that implementation of the necessary technology to meet compliance for
Coyote Station is far from a sure thing. In the event that compliance cannot be met for that
plant, NDPSC estimates that the cost for replacement generation will increase rates by 510 percent for many North Dakota ratepayers.
27.
Replacement generation will likely require billions of dollars of investment in gas
generation and transmission infrastructure.1° Firm service contracts will also be necessary.
The increased reliance and demand for natural gas will put upward pressure on the
commodity, increasing the price of the fuel supply for both electricity and natural gas utility
service for ratepayers, and increase price volatility during times of extreme weather.11
28.
For example, during the 2021 Storm Uri, excess demand in our region created extreme
competition that caused high spot pricing resulting in a total of 45.9 million dollars of under
collection and notable rate impacts to North Dakota gas customers over amortization
periods of 16 to 24 months.12 During this period, the NDPSC received an abundance of
calls from struggling residential customers and industrial customers having difficulty
maintaining operations. And this was a far cry from the natural gas turmoil experienced in
states like Oklahoma, where the Corporation Commission required securitization to
I° Basin Electric recently announced construction of a 1,400 MW gas-fired generation facility in North Dakota that
will require billions of dollars of investment and would use about 7% of the natural gas currently produced in North
Dakota. See https://northdakotamonitor.com/2024/05/15/utility-plans-another-gas-fired-power-plant-for-northdakota/.
" See Great Plains Natural Gas Co., Cost of Gas 2021, Application for Variance, Case No. PU-21-10, available at
https://www.psc.nd.gov/database/documents/21-0010/028-020.pdf; Montana-Dakota Utilities Co., Cost of Gas
2021, Application for Variance, Case No. PU-21-8, available at https://www.psc.nd.gov/database/documents/210008/029-020.pdf; and Northern States Power Company, Cost of Gas 2021, Application for Variance, Case No. PU21-9, available at https://www.psc.nd.gov/database/documents/21-0009/055-020.pdf.
12 Montana-Dakota 12.8 million; Great Plains Natural Gas 593k, and Northern States Power Company 32.5 million.
(Page 62 of Total)
10
169a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 12 of 15
amortize $675 million in fuel costs over 20 years to reduce what would have been an
estimated $476 residential charge per month per customer to a more manageable rate.13
29.
Furthermore, closure of the thermal generation and the replacement with intermittent
renewable resources will drive down accredited capacity values of current renewable
generation units owned by our regulated utilities — driving down the value of existing
renewable generation and requiring additional investment in resources with capacity value
to meet reserve margin requirements. The foreseeable cascading cost impacts and grid
reliability risks associated with the Final Rule are unacceptable if ensuring access to
reliable and affordable power is one of the most important imperatives of government.
30.
The closure of thermal generation units in North Dakota would also foreseeably have
immediate and negative impacts on the price of energy to electricity customers in the
region. The existing transmission system was designed and built to ensure delivery of
power from all North Dakota generation units primarily to customers within the state, with
approximately 35% of energy generated within the state currently exported outside of our
borders.
31.
Our neighboring states have relied upon the energy generated in North Dakota for many
decades, and do not currently have available resources to serve both their own needs and
North Dakota's needs if North Dakota's coal-fired plants are forced into early retirement
by the Final Rule. This scenario would result in significant congestion across the
transmission system of both MISO and SPP, which would significantly drive up energy
prices for customers in both RTOs.
13 See https://oklahoma.gov/occ/news/news-feed/2022/commission-approves-order-on-pso-february-2021-stormcosts.html. Final Financing Order, Order No. 723434, https://imaging.occ.ok.gov/AP/Orders/occ30453173.pdf.
(Page 63 of Total)
11
170a
USCA Case #24-1119
32.
Document #2058570
Filed: 06/07/2024
Page 13 of 15
One very recent example of how dramatic the cost of congestion can be is a very localized
transmission constraint in northwest North Dakota. Due to a relatively small (200MW)
load addition in the area, the congestion pricing in the region over the course of six months
totaled up to $18 million to customers of Montana-Dakota Utilities Co. alone.14 Comparing
the impact of that event to the Final Rule potentially removing nearly four thousand
megawatts of thermal generation, the pricing impacts on North Dakota electricity
consumers can foreseeably be anticipated to be severe.
33.
In short, the Final Rule will have a clear and dramatic impact on rates and risks to North
Dakota ratepayers, even if all North Dakota power plants are able to comply with the Rule
and remain economically viable in the long-term, which is far from a certainty. As with
all rate impacts, the most significant impact will be on low-income North Dakotans, as
high energy prices operate like a regressive tax. But the impact will be felt by all North
Dakotans, who will have no choice but to retain service at higher rates. For people and
businesses, electricity and natural gas heating is a requirement, it is not a luxury that can
be set aside if the Federal Rule causes energy prices to increase dramatically.
34.
The Final Rule also recklessly interjects the EPA into areas traditionally reserved for
States, FERC, and RTOs. State utility commissions have traditionally had a reserved
authority to establish their own energy and environmental policies, including the authority
to determine their own preferred generation mixes, as long as they do not interfere with
wholesale markets.15 This rule mutes the NDPSC's careful consideration of rates, utility
14 See Montana-Dakota Utilities Co. v. Midcontinent Independent System Operator, Inc. and Southwest Power Pool,
Docket No. EL-24-61-000 (Jan. 23, 2024).
15 See, e.g., Hughes v. Talen Energy Mktg., LLC, 570 U.S. 150, 154 (2016) ("The States' reserved authority includes
control over in-state `facilities used for the generation of electric energy.'" (quoting 16 U.S.C. § 824(b)(1)) (citing
Pac. Gas & Elec. Co. v. State Energy Res. Conserv. & Dev. Comm'n, 461 U.S. 190, 205 (1983) ("Need for new
power facilities, their economic feasibility, and rates and services, are areas that have been characteristically
governed by the States.")); id. at 166 ("Nothing in this opinion should be read to foreclose Maryland and other
(Page 64 of Total)
12
171a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 14 of 15
investments, and its vested role in ensuring the orderly development of generation and
transmission infrastructure within North Dakota.16
35.
Indeed, to the extent that the Final Rule creates disruptions in electricity reliability—
brownouts or blackouts—the Final Rule will have far reaching direct, indirect, and tertiary
impacts throughout the State.
36.
Any changes to the electricity generation portfolio caused by implementation of the Final
Rule will be immediate, irreversible, and will likely impact North Dakotans for decades,
even if the Final Rule is overturned in litigation.
37.
In summary, NDPSC has significant concerns with implementation of the Final Rule that
cannot be overstated. The Final Rule will likely have lasting and severe impacts with no
discernable benefit. If the Final Rule is not stayed while the legal challenges against it
proceed, there will foreseeably be serious and irreparable harm to the State and people of
North Dakota. North Dakota power plants will likely be forced to retire, North Dakota
ratepayers will pay more for electricity, and the reliability of the grids servicing North
Dakota will be significantly threatened.
38.
NDPSC strongly encourages the Court to stay implementation of the Final Rule.
States from encouraging production of new or clean generation through measures "untethered to a generator's
wholesale market participation." ... So long as a State does not condition payment of funds on capacity clearing the
auction, the State's program would not suffer from the fatal defect that renders Maryland's program unacceptable.").
16 See, e.g., Hughes, 578 U.S. at 166; accord, e.g., PPL EnergyPlus, LLC v. Solomon, 766 F.3d 241, 255 (3d Cir.
2014) ("The states may select the type of generation to be built—wind or solar, gas or coal—and where to build the
facility[,] [o]r states may elect to build no electric generation facilities at all."); PPL EnergyPlus, LLC v. Nazarian,
753 F.3d 467, 478-80 (2014); N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 97 (3d Cir. 2014)
(Page 65 of Total)
13
172a
USCA Case #24-1119
Document #2058570
Filed: 06/07/2024
Page 15 of 15
Executed in Bismarck, North Dakota, on May 28, 2024.
J i 1 FedorchakV
missioner
orth Dakota Public Service Commission
(Page 66 of Total)
14
173a
174a
175a
176a
177a
178a
179a
180a
181a
182a
183a
184a
185a
186a
187a
188a
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.