Petition for Writ of Certiorari — HSU Contracting, LLC, Petitioner v. Holton-Arms School, Inc.

Supreme Court briefMar 19, 2024

Ask Donna

What actually matters in this document.

Text

No. 23In the

Supreme Court of the United States

HSU CONTRACTING, LLC,

Petitioner,

v.

HOLTON-ARMS SCHOOL, INC.,

Respondent.

On Petition for a Writ of Certiorari

to the M aryland Supreme Court

PETITION FOR A WRIT OF CERTIORARI

A mber Wong Hsu

Counsel of Record

HSU Contracting, LLC

6100 Executive Blvd., Suite 450

N. Bethesda, MD 20852

(301) 437-1000

amber@hsubuilders.com

Counsel for Petitioner

328270

i

QUESTIONS PRESENTED

In 2018, the Petitioner and Respondent entered into an

AIA (American Institute of Architects) contract, a widely

utilized construction industry standardized contract,

for construction services. The plain language of the

agreement would have barred damages where no remedial

costs had actually been incurred by Respondent. Instead,

the Maryland courts discarded the unambiguous plain

language of the contract and allowed “any other rights

or remedies” to support a multi-million-dollar judgment

against Petitioner, in Respondent’s favor.

In doing so, did the Maryland court:

1.

Violate the Commerce Clause of the U.S.

Constitution in its interpretation of the AIA

contract, which serves to establish a common

framework for construction project participants,

using consistent terminology and legal principles,

by directly contradicting interpretation of the

same AIA contract by other states and federal

courts?

2.

Violate the Equal Protection Clause of the U.S.

Constitution in its interpretation of the AIA

contract, which serves to “level the playing field,”

by disproportionately impacting disadvantaged

small businesses w ith limited access and

opportunity to discern the universe of available

rights and remedies outside the standard contract

language?

ii

THE PARTIES

Petitioner is HSU Contracting, LLC, a construction

general contractor founded in 2009. It is located at

6100 Executive Blvd., Suite 450, North Bethesda, MD

20852. Respondent is the Holton-Arms School, Inc., an

independent school for girls grades 3-12 located at 7303

River Road, Bethesda, MD 20817.

iii

CORPORATE DISCLOSURE STATEMENT

Petitioner is a privately owned Maryland Limited

Liability Company. It is 50% owned by Direct Management,

Inc., a Maryland corporation owned by Amber Wong Hsu,

and 50% owned by Amber Wong Hsu, individually.

iv

RELATED PROCEEDINGS

HSU Contracting, LLC v. Holton-Arms School, et al.,

Case No. 472329-V, Montgomery County Circuit Court,

Maryland. Judgment entered October 12, 2022.

HSU Contracting, LLC v. Holton-Arms School, et

al., Case No. CSA-REG-1707-2022, Appellate Court of

Maryland. Judgment entered September 28, 2023.

HSU Contracting, LLC v. Holton-Arms School et

al., Case No. SCM-PET-0421, Maryland Supreme Court.

Cert. Denied December 20, 2023.

v

TABLE OF CONTENTS

Page

QUESTIONS PRESENTED . . . . . . . . . . . . . . . . . . . . . . . i

THE PARTIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii

CORPORATE DISCLOSURE STATEMENT . . . . . . iii

RELATED PROCEEDINGS . . . . . . . . . . . . . . . . . . . . . iv

TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . v

TABLE OF APPENDICES . . . . . . . . . . . . . . . . . . . . . . vii

TABLE OF CITED AUTHORITIES . . . . . . . . . . . . . viii

INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

OPINIONS BELOW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

JURISDICTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

CONSTITUTIONAL PROVISIONS

AND STATUTES INVOLVED . . . . . . . . . . . . . . . . . 4

STATEMENT OF THE CASE . . . . . . . . . . . . . . . . . . . . 5

BACKGROUND OF THE AIA CONTRACTS . . . . . . 11

REASONS FOR GRANTING THE PETITION . . . . 14

I.

Undue Burden on Interstate Commerce . . . . . . 14

vi

Table of Contents

Page

II. Denial of Equal Treatment . . . . . . . . . . . . . . . . . 19

CONCLUSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

vii

TABLE OF APPENDICES

Page

APPENDIX A — ORDER OF THE SUPREME

COU RT OF M A RY L A N D, FILED

DECEMBER 20, 2023 . . . . . . . . . . . . . . . . . . . . . . . . 1a

A P P E N DI X B — O P I N ION O F T H E

APPELLATE COURT OF MARYLAND,

FILED SEPTEMBER 28, 2023 . . . . . . . . . . . . . . . . 3a

APPENDIX C — TRIAL COURT OPINION

OF T HE CIRCU I T COU RT FOR

MONTGOMERY COUNTY, MARYLAND

FILED OCTOBER 12, 2022 . . . . . . . . . . . . . . . . . . 51a

viii

TABLE OF CITED AUTHORITIES

Page

Cases:

Adarand Constructors v. Pena,

515 U.S. 200 (1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Armco Inc. v. Hardesty,

467 U. S. 638 (1984) . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Beaver Construction Co. v. Lakehouse, LLC,

742 So. 2d 159 (Ala. 1999) . . . . . . . . . . . . . . . . . . . . . . 16

Boston Stock Exchange v. State Tax Comm’n,

429 U.S. 318 (1977) . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

C&L Enters., Inc. v. Citizen Band Potawatomi

Indian Tribe of Oklahoma,

532 U.S. 411 (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Comptroller of Treasury of Md. v. Wynne,

575 U.S. 542 (2015) . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

M&R Contractors & Builders, Inc. v. Michael,

215 Md. 340 (1958) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Mercantile Trust Co. v. Hensey,

205 U.S. 298 (1907) . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Metro. Life Ins. Co. v. Ward,

470 U.S. 869 (1985) . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

ix

Cited Authorities

Page

Moses H. Cone Memorial Hospital v.

Mercury Constr.,

460 U.S. 1 (1983) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Northwestern States Portland Cement Co. v.

Minnesota,

358 U. S. 450 (1959) . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Portuguese-American Bank v. Welles,

242 U.S. 7 (1916) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Ray v. William G. Eurice & Brothers,

201 Md. 115 (1952) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

Stiglich Construction, Inc. v. Larson,

621 N.W. 2d. 801, 803 (Minn. Ct. Appl.

2001), review denied, 2001 Minn. LEXIS

192 (Minn. Mar. 27, 2001) . . . . . . . . . . . . . . . . . . . . . . 16

Stonehill-PRM WC LLP v.

Chasco Constructors, Ltd., LLP,

2009 Tex. Appl. LEXIS 1019

(Tex. App. Feb. 11, 2009) . . . . . . . . . . . . . . . . . . . 17, 18

United States v.

Utah Construction & Mining Co.,

384 U.S. 394 (1966) . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Volt Information Sciences, Inc. v.

Board of Trustees,

489 U.S. 468 (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

x

Cited Authorities

Page

Wartzman v. Hightower Prods., Ltd.,

53 Md. App. 656 (1983) . . . . . . . . . . . . . . . . . . . . . . . . . 2

Constitutional Provisions and Statutes:

Commerce Clause: U.S. Constitution, Article I,

Section 8, Clause 3 . . . . . . . . . . . . . . . . . . . . . . . . . 4, 14

Equal Protection Clause: U.S. Constitution,

Article XIV, Section 1 . . . . . . . . . . . . . . . . . . . . . . . . . . 4

Small Business Act: 15 U.S.C. 631(a) . . . . . . . . . . . . . . . . 4

Miscellaneous:

15 U.S.C. 631(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

28 U.S.C. 1257(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

Stein, Steven G.M., Stein Ray, LLP, Editori n - C h i e f , T h e Am e r i c a n In s ti t u t e of

Ar chi t ec t s Le ga l Ci t a t o r, L e x i sNe x i s

Matthew Bender & Company, Inc., 2023 . . . . . . . . . 13

T h e A m e r i c a n I n s t it ut e of A r c h it e c t s ,

Official Guide to the 2007 AIA Contract

Documents, John Wiley & Sons, Inc., 2009 . . . . 11, 12,

13, 19, 20

1

INTRODUCTION

This contractual dispute arises out of an interpretation

of the American Institute of Architects (AIA) standard

form agreements that were executed for the performance

on a construction project in the State of Maryland. In

the normal course of business, Respondent Holton-Arms

School, Inc. presented Petitioner HSU Contracting LLC,

a woman-owned, minority-owned small business, with an

AIA 101-2007 (Standard Form of Agreement Between

Owner and Contractor) and AIA 201-2007 (General

Conditions of the Contract for Construction).1 AIA form

agreements, which were used between Petitioner and

Respondent on a previous project in 2012, 2 reflect industry

best practices and are commonly used by parties to

construction transactions in all fifty states.

The $6.6M contract was executed on June 5, 2018. 3

Less than one year later, Respondent terminated its

contract with Petitioner “for cause,” pursuant to AIA

201-2007 §14.2, claiming breach of performance.4 While

there are innumerable disagreements regarding the

Work performed, the following facts are undisputed:

1) Respondent resumed school operations in its fully

renovated 40,000 square foot Lower School Building on

September 6, 2018, 5 two days after the first day of school,

1. Appendix C, Page 63a.

2. Appendix C, Page 58a.

3. Appendix C, Page 62a

4. Appendix C, Pages 96a, 97a, 105a.

5. Appendix B, Page 30a.

2

and only ninety-three days after contract execution; and

2) Respondent undertook no further work, by the time of

trial in 2022, thereby incurring no actual costs,6 to remedy

its so-claimed damages that were the basis of the alleged

breach.7

The plain language of the form contract AIA 2012007 §14.2 provided an express remedy for the calculation

of damages in the event of a “Termination for Cause,”

permitting Owner [Respondent] to “complete and

correct the Work in an expedient manner and then claim

6. Respondent claimed a singular untimely expense of

$36,299 incurred on March 29, 2021 for the installation of a thermal

barrier paint, however, it played no part in the Respondent’s

termination of Petitioner in 2019. (Defendant’s Trial Ex. #1222,

E355)

7. Appendix B, Page 49a. In acknowledging that Respondent

expended no amounts to remedy the alleged breach (and declining

the obligation to mitigate), the Appellate Court offered the following:

‘Holton, being a non-profit, had limited funding. “The party who is

in default may not mitigate his damages by showing that the other

party could have reduced those damages by expending large amounts

of money or incurring substantial obligations. Since such risks arose

because of the breach, they are to be borne by the defaulting party.”

Wartzman v. Hightower Prods., Ltd., 53 Md. App. 656, 667, 456 A.2d

82 (1983) (citation omitted). In light of HSU’s estimate that the cost to

complete the work in 2019 would have been over $800,000, it would be

unreasonable to require Holton to immediately expend such a large

amount of money to mitigate its damages, especially once it became

clear that funds would be needed for litigation.’ (Emphasis added.)

The Appellate Court failed to acknowledge that Respondent Holton

had withheld approximately $1.5M (amounts earned and retained

from Petitioner HSU, as well as the remaining contract balance),

yielding a net judgment of $2.6M from the $4.1M award, and had

sufficient funds to perform the remedial work.

3

any such amounts from the Contractor [Petitioner]. 8

Despite not having performed any such remedial Work,

Respondent was awarded a judgment of $4.1M based on

the presentation of its 250-page expert witness report.9

On appeal, the Appellate Court affirmed the award, and

in its “Limitation of Damages” analysis, found authority

in a separate “reservation of rights” provision, §13.4.1,

and “cumulative rights” provision §2.6, to affirm the lower

court’s damages award based on Maryland case law.10

The Maryland court held that the presence of these two

provisions permitted Respondent to opt out of the plain

and unambiguous contractual obligations and pursue any

other remedies outside of the contract. Petitioner filed a

Petition for Writ of Certiorari to the Maryland Supreme

Court, which was denied.

OPINIONS BELOW

The Order of the Maryland Supreme Court Denying

Certiorari (Appendix A, Pages 1a-2a) is reported at 486

Md. 245. The Opinion of the Appellate Court of Maryland

(Appendix B, Pages 3a-50a) is reported at 23 WL 6304935.

The Memorandum and Order of the Circuit Court for

Montgomery County, Maryland (Appendix C, Pages

51a-141a) is unreported.

8. Appendix B, Page 40a.

9. Appendix C, Page 125a.

10. Appendix B, Page 40a.

4

JURISDICTION

The Order of the Maryland Supreme Court denying

Petitioner’s Petition for Writ of Certiorari was entered

on December 20, 2023. The jurisdiction of this Court is

invoked under 28 U.S.C. 1257(a).

CONSTITUTIONAL PROVISIONS AND

STATUTES INVOLVED

Commerce Clause: U.S. Constitution, Article I,

Section 8, Clause 3

[The Congress shall have the Power…] To

regulate commerce with foreign nations, and

among the several states …

Equal Protection Clause: U.S. Constitution, Article

XIV, Section 1

“No State shall make or enforce any law which

shall abridge the privileges or immunities of

citizens of the United States; nor shall any

State deprive any person of life, liberty or

property, without due process of law; nor deny

to any person within its jurisdiction the equal

protection of the laws.”

Small Business Act: 15 U.S.C. 631(a): “Declaration of

Policy” - Aid, counsel, assistance, etc. to small business

concerns:

“The essence of the American economic system

of private enterprise is free competition.

5

Only through full and free competition can

free markets, free entry into business, and

opportunities for the expression and growth

of personal initiative and individual judgment

be assured. The preservation and expansion

of such competition is basic not only to the

economic well-being but to the security of this

Nation. Such security and well-being cannot

be realized unless the actual and potential

capacity of small business is encouraged and

developed. ….”

STATEMENT OF THE CASE

Petitioner and Respondent executed the standardized

AIA contract (AIA 101-2007 and AIA 201-2007) for a twophased construction project: to renovate the Respondent’s

Lower School Building and to simultaneously upgrade

its central plant HVAC system.11 Once the project was

underway, multiple design changes were initiated and

the cost for the construction rose from $6.6M to more

than $8M.12 Petitioner completed the first phase in only

93 days, renovating the entirety of the 40,000 square foot

Lower School building so that Respondent could resume

its operations by September 6, 2018.13 The balance of the

contract was carried out progressively during the school

year and final completion was slated for the summer of

2019.14

11. Appendix C, Page 55a.

12. Appendix C, Page 125a.

13. Appendix B, Page 6a.

14. Appendix B, Page 93a, 96a, 138a.

6

On May 24, 2019, prior to completing the final 10%

of the work, Respondent terminated Petitioner “for

cause,” pursuant to AIA 201-2007 §14.2, claiming breach

of performance on the contract.15 Petitioner’s tenth and

final invoice was unpaid. According to the formal and

contemporaneous certifications by Respondent’s own

architect, 89% of the total contract had already been

completed in accordance with the contract documents by

early spring.16

Petitioner contested the characterization that it

had breached performance on the contract, and filed

a mechanics lien action on September 11, 2019 for

$2,046,902, the amount of the unpaid final invoice, against

Respondent. 17 Respondent initially counterclaimed

unspecified damages “in an amount to be determined

at trial.”18 Then, over the course of the next two years,

Respondent developed a 250-page expert witness report

utilizing contractor estimates as the basis to claim gross

damages in excess of $4M.19 Respondent’s Director of

Facilities testified at trial that it had not undertaken

any effort to remedy the so-claimed defective work.

Respondent has fully and continuously operated its

activities without interruption since 2018. 20

15. Appendix C, Page 105a.

16. Appendix C, Page 121a.

17. Appendix B, Page 6a.

18. “Holton-Arms’ Counterclaims Against HSU Contracting,”

Case No. 472329-V, p. 15, filed November 27, 2019, Record Extract

E109.

19. Appendix C, Page 127a.

20. Deferred Record Extract, Page E811, Lines 23-25. Trial

7

Six months after the conclusion of a fifteen-day

trial, Montgomery County Circuit Court Judge Steven

Salant issued a Memorandum Opinion on October 12,

2022 adopting Respondent’s factual and legal claims in

toto. 21 Despite having had full use of its school facilities22

without paying the tenth and final invoice, Respondent was

awarded a $4.1M judgment, netting the amounts unpaid to

Petitioner, yielding a judgment of approximately $2.6M. 23

The damages awarded to Respondent were primarily: 1)

costs to complete and correct the work in breach, and 2)

liquidated damages. 24 Respondent then garnished and

Transcript, Testimony of Michael Joyce, March 14, 2022.

21. On January 22, 2024, Petitioner filed a Motion to Vacate

the October 12, 2022 judgment based on newly-discovered evidence

that Trial Court Judge Steven Salant, and his wife Sandra GordonSalant, had a personal kinship or affinity with the Respondent as

donors and “Grandparents, Relatives or Friends.” The relationship,

spanning more than ten years, was revealed on pages 35, 39 and

42 of Respondent’s fundraising brochure coincidentally published

online (https://issuu.com/peapoddesign/docs/holton-arms_school_

annual_report), which has now been removed from public access.

At no time during the trial court proceedings was this relationship

ever disclosed to Petitioner. The Motion to Vacate, based on the

irregularity of process in failing to disclose this information or

otherwise conduct a disqualification hearing pursuant to Md. Rule.

18-102.11(c), was summarily denied without hearing on March 5,

2024 and is subject to appeal. While this issue was brought before

the Maryland Supreme Court, it is not addressed here and has no

bearing on the instant Petition for Writ of Certiorari.

22. Deferred Record Extract, Page E808, Lines 21-25. Trial

Transcript, Testimony of Michael Joyce, March 14, 2022.

23. Appendix C, Page 127a.

24. While Petitioner disagrees with the Appellate Court’s

8

seized the entire balance of Petitioner’s remaining assets,

a commercial checking account, rendering the Petitioner

unable to conduct any business except the continued

litigation, including defense of the judgment collection 25

by Respondent and unpaid subcontractors.

On October 24, 2022, Petitioner then filed a Motion to

Alter and Amend the Judgment, pursuant to Md. Rule.

2-534, on the basis that the plain language of the executed

AIA contracts did not support an award where no remedial

or completion work had ever been undertaken. 26 Because

Respondent had terminated Petitioner’s contract “for

cause,” pursuant to AIA 201-2007 §14.2, Respondent was

permitted to: “Finish the Work by whatever reasonable

method the Owner may deem expedient,” AIA 201-2007

§14.2.2.3, which it did not. 27

The AIA contract offered further detailed instruction

that, upon Contractor’s [Petitioner’s] request, Owner

[Respondent] was to provide a “detailed accounting of the

costs incurred by the Owner in finishing the Work.” In the

event that such costs incurred by the Owner [Respondent]

interpretation of the liquidated damages provision, review of that

decision does not per se implicate the Constitutional provisions at

issue.

25. Upon Respondent’s seizure of Petitioner’s remaining

assets, Petitioner’s owner, a 1994 graduate of Georgetown

University Law Center and former tax practitioner, has, where

possible, represented the Petitioner without the assistance of

outside legal representation.

26. Appendix B, Page 9a.

27. Appendix B, Page 40a.

9

exceed the unpaid balance, the Contractor [Petitioner]

would have been responsible for paying the difference to

Respondent. AIA 201-2007 §14.2.4. 28

Petitioner’s Motion to Alter and Amend the Judgment

was denied and the appeal ensued. 29 This Petition seeks

only a limited review of the Appellate Court’s opinion with

regard to “Limitation of Damages,”30, affirming the lower

court’s damage award. The Appellate Court held that the

existence of AIA 201-2007 §13.4.1, a “reservation of rights”

provision, and AIA 201-2007 §2.6, a “cumulative rights”

provision, rendered the plain language of A201 §14.2.2.3

a non-exclusive remedy that could simply be discarded.

(Emphasis added.)

AIA 201-2007 §13.4.1:

“Except as expressly provided in the Contract

Documents, duties and obligations imposed

by the Contract Documents and rights and

remedies available thereunder shall be in

addition to and not a limitation of duties,

obligations, rights and remedies otherwise

imposed or available by law.” 31

28. Appendix B, Page 40a.

29. Appendix B, Page 9a.

30. Appendix B, Pages 40a-42a.

31. Appendix B, Page 41a.

10

AIA 201-2007 §2.6:

“The rights stated in this Article and elsewhere

in the Contract Documents are cumulative and

not in limitation of any rights of the Owner (1)

granted in the Contract Documents, (2) at law,

or (3) in equity.” 32

The Appellate Court specifically held that the above

provisions allowed for multiple remedies, not only those

expressly stated in the plain language of the contract, but

allowed common law remedies33 that, in this case, were

not made known to the parties at the time of contract

execution.

Petitioner filed its Petition for Writ of Certiorari to

the Maryland Supreme Court, requesting review that

the court’s interpretation, based on the background of

the AIA documents, would lead to inconsistency across

jurisdictions in the interpretation of industry and legal

standards, terminology and practices. The petition for

writ of certiorari was denied on December 20, 2023. 34

32. Appendix B, Page 41a.

33. Appendix B, Page 41a-42a.

34. Appendix B, Page 1a-2a.

11

BACKGROUND OF THE AIA CONTRACTS35

Since 1888, the American Institute of Architects (AIA)

standard Contract Documents have been used to unify,

shape and regulate the construction industry. AIA forms

are revised nearly every decade to create uniformity in the

law of construction contracts and address the diversity and

disparity of size, economic power, and legal sophistication

of the parties to a construction project. They are “carefully

drafted to avoid inconsistencies that create ambiguities

or call their meaning into question.” 36

“If anything can be considered a unifying

force in the construction industry, it is the

standard contract forms and documents issued

by the American Institute of A rchitects.

They establish a common framework of roles

and responsibilities for many of the project

participants, using consistent terminology and

legal principles. They tend to level the playing

field between the large and the small, the rich

and the poor, those who can afford lawyers to

scrutinize every transaction and those who

cannot. By reducing transaction costs, they

promote transactional economy. They also save

time, permitting projects to move forward much

more quickly than they would otherwise could

35. The background of the AIA Contracts was presented to

the Maryland Supreme Court in the Petition for Writ of Certiorari,

which was denied.

36. The A mer ican Institute of A rchitects, Of ficial

Guide to the 2007 AIA Contract Documents, 2009, Chapter 1.

Standardization of Construction Contracts, p. 7.

12

if each participant had to come to agreement

on new, unfamiliar terms with every project.

The AIA documents make it possible for

construction industry participants to engage

in private law-making as a practical reality. 37

These form documents reflect industry standards and

best practices:

‘The influence of the AIA documents extends

well beyond the particular contracts in which

they are used. While the documents reflect

standard industry practices, they also embody

“best practices” of the industry, and through

their use, help to bring those practices into

the mainstream. Because of the widespread

acceptance of the AIA documents, their terms

soon come to represent the standards of the

industry. When a contract is silent on an issue

that is before a court, the court will often look

at normal trade practices.’38

… Moreover, they “set legal standards that are

reflected in thousands of cases.” 39

“The widespread use of the AIA documents

has resulted in a large body of law construing

almost every one of their provisions.”40

37. Id. at 3-4.

38. Id. at 9-10.

39. Id. at 10.

40. Id. at 11.

13

“In order to assist the legal community in

construction law cases, the AIA developed The

American Institute of Architects Legal Citator,

which has cataloged and digested thousands of

legal decisions construing all of the principal

AIA contract forms since it was introduced

in the mid-1960s. (Since the mid-1980s, The

American Institute of Architects Legal Citator

has been published by Matthew Bender &

Company, a member of the Lexis-Nexis Group,

as part of its multi-volume Construction Law

treatise.)41

According to the AIA’s website,42 the AIA documents are

routinely used in all aspects of construction nationwide.

When the first AIA contract document was

created in 1888, there were only 38 states.

Today, AIA users create more than 960 AIA

documents per hour, and, at any point during

the workday, an average of 500 contractors,

architects, engineers and owners are using the

AIA platform. AIA payment applications have

been used in $1 trillion worth in construction

projects. Notable projects constructed with the

AIA contract include: Dallas Cowboys Stadium,

New Orleans Louis Armstrong Airport, Los

Angeles Dodger Stadium, and Seattle’s Space

Needle. Today, there are more than 100,000

AIA users in all fifty states.

41. Id. See also, footnote 4.

42. See, https://learn.aiacontracts.com/company-facts/

14

The sig nif icant and w idespread use of these

standardized documents has contributed to the growth

and development of the construction industry nationwide.

REASONS FOR GRANTING THE PETITION

I.

Undue Burden on Interstate Commerce

T he M a r yl a nd St at e cou r t ’s f l awed a d hoc

interpretation of the industry standard contract places

an undue burden on interstate commerce. For more than

130 years, the AIA contracts, by establishing a common

framework for construction project participants, using

consistent terminology and legal principles, and reducing

transaction costs, have promoted transactional economy

in the construction industry.

The Commerce Clause grants Congress the power to

“regulate Commerce . . . among the several States.” Art.

I, § 8, Cl. 3. This authority gives rise to the “Dormant

Commerce Clause,” a further negative command

that prohibits discriminatory state action based on

transactions or incidents that cross state lines and

results in an advantage or burden based on commerce.

Under the Dormant Commerce Clause, states may not

discriminate “between transactions on the basis of some

interstate element.” Boston Stock Exchange v. State

Tax Comm’n, 429 U.S. 318, n. 12 (1977). A state “may

not tax a transaction or incident more heavily when it

crosses state lines than when it occurs entirely within

the State.” Armco Inc. v. Hardesty, 467 U. S. 638, 642

(1984). “Nor may a State impose a tax which discriminates

against interstate commerce either by providing a direct

commercial advantage to local business, or by subjecting

15

interstate commerce to the burden of ‘multiple taxation.’ ”

Northwestern States Portland Cement Co. v. Minnesota,

358 U. S. 450, 458 (1959) (citations omitted). See also,

Comptroller of Treasury of Md. v. Wynne, 575 U.S. 542

(2015).

Under the Maryland court’s interpretation of the

AIA Contract, the parties may simply discard or opt out

of the unambiguous plain language of the AIA contract

that they have agreed upon and look to any and all rights

and remedies that may exist. This interpretation imposes

an undue and impermissible burden disadvantageous

to parties to construction projects within the state

of Maryland.43 They may not simply rely on the plain

language of their AIA contract, but must now anticipate

any and all other rights and remedies available at law.

The AIA 101 and 201 Standard Contracts have been

the subject of thousands of cases and have been litigated

in state and federal courts in all fifty states. According to

the Legal Citator, they have made their way to the U.S.

Supreme Court on nine separate occasions, Mercantile

Trust Co. v. Hensey, 205 U.S. 298 (1907), PortugueseAmerican Bank v. Welles, 242 U.S. 7 (1916), United States

v. Utah Construction & Mining Co., 384 U.S. 394 (1966),

Moses H. Cone Memorial Hospital v. Mercury Constr.,

460 U.S. 1 (1983), Volt Information Sciences, Inc. v. Board

of Trustees, 489 U.S. 468 (1989) recognizing that the AIA

Contract is interstate commerce), C&L Enters., Inc. v.

Citizen Band Potawatomi Indian Tribe of Oklahoma,

532 U.S. 411 (2001).

43. Jurisdiction and choice of law is usually determined by

the site of the project, or otherwise agreed upon by the parties,

as offered in AIA 201-2007 §15.4.

16

The Maryland court’s interpretation of the “reservation

of rights provision,” §13.4.1, is contrary to courts of other

jurisdictions. The Maryland court is the only jurisdiction

that allows unstated rights and remedies to supplant the

plain language of the AIA contract if a party chooses to

pursue an alternative remedy.

The Minnesota Court of Appeals held that AIA 2012007 §13.4.1 permitted a separate claim for attorneys fees,

even though it was not specifically indicated in the contract,

after the parties resolved a mechanics lien through

arbitration. The Court reviewed both the arbitration

provision and the reservation of rights provision and

concluded that the law required it to construe the contract

as a whole, to harmonize all provisions, if possible, and

avoid a construction that would render one or more

provisions meaningless. Stiglich Construction, Inc. v.

Larson, 621 N.W. 2d. 801, 803 (Minn. Ct. Appl. 2001),

review denied, 2001 Minn. LEXIS 192 (Minn. Mar. 27,

2001). The court opined that it was improper to construe

the contract in a way that would render one or more

provisions meaningless.

In Beaver Construction Co. v. Lakehouse, LLC,

742 So. 2d 159 (Ala. 1999), the Owner’s claim that

§13.4.1 permitted non-exclusive remedies, i.e., in lieu of

contractual remedies, was flatly rejected. The Owner

had argued that the arbitration clause contract was not

intended to be the exclusive means of redress because

§13.4.1 provided that “duties and obligations imposed by

the Contract Documents and rights and remedies available

thereunder shall be in addition to and not a limitation of

duties, obligations rights and remedies otherwise imposed

or available by law.” The Owner contended that this

17

“reservation of rights” provision allowed the Owner to

pursue a jury trial through litigation. The Court held that

if this were the case, the provision relating to arbitration

setting in detail specific procedures to be followed in

arbitration would have been negated by § 13.4.1. Because

a construction contract cannot be construed in a manner

such that one clause would nullify another, the Owner’s

claim was rejected.

Lastly, in Stonehill-PRM WC LLP v. Chasco

Constructors, Ltd., LLP, 2009 Tex. Appl. LEXIS 1019

(Tex. App. Feb. 11, 2009), the court reviewed the “limitation

of damages” clause in conjunction with the “reservation of

rights” clause, with an outcome contrary to that offered by

the Maryland Appellate Court. The limitation on damages

clause, § 14.2.4 offered the following:

“To the extent the costs of completing Work,

including, without limitation, compensation for

additional professional services and expenses,

exceed those costs which would have been

payable to Contractor to complete the Work

except for Contractor’s default, Contractor shall

pay the difference to Owner, and this obligation

for payment shall survive termination of the

Contract. Such costs incurred by Owner will

be determined by the Owner and confirmed by

the Architect.”

The reservation of rights provision, §13.4.1, provided that:

“Duties and obligations imposed by the

Contract Documents and rights and remedies

available thereunder shall be in addition to and

18

not a limitation of duties, obligations, rights

and remedies otherwise imposed or available

by law or in equity or by any other agreement,

and any such rights and remedies shall survive

the acceptance of the Work and/or termination

of the Contract Documents.” §13.4.1.

The Owner Stonehill argued on appeal that the

above limitation on damages clause applied only if it had

chosen to complete the project, i.e., that there would be

another remedy available for the calculation of damages

if it chose not to complete the project. The court held that

this interpretation contradicted the plain language of the

provision. Similar to the case at hand, the contractual

provision entitled, “Termination by the Owner for Cause,”

was deemed to be the sole remedy in addressing the

owner’s claim for damages in a termination for cause. The

Texas court further held that the owner’s position was

inconsistent with the presence of a waiver of consequential

damages in another paragraph. “Binding the parties to

the contractually agreed measure of damages in the event

the contractor was terminated for cause was consistent

with its waiver of the types of damages expressed in

the consequential damages clause.” Id. The waiver of

consequential damages further supported its finding

that 14.2.4 was the “sole remedy” that had been agreed

upon in claiming damages in a termination for cause. The

decision in Stonehill is entirely at odds with the Maryland

Appellate Court’s interpretation.44

44. Also concerning was the Maryland court’s decision to

disregard the existence of waiver of consequential damages as

support for the limitation on remedies in a termination for cause

claiming that its argument was insufficiently preserved for review,

See, Appendix B, P. 41a, Footnote 10.

19

The Maryland court’s decision places an undue

burden on interstate commerce by offering inconsistent

interpretations of identical provisions of the AIA

Contracts. Although unreported, there is no reported

Maryland precedent interpreting the effect of §13.4.1,

and the decision may therefore be cited for its “persuasive

value,” see Appendix B, P. 3a. By its reading that AIA

§13.4.1 renders the plain and unambiguous of the contract

as “non-exclusive,” it is the only jurisdiction to interpret

the contract this way. Parties transacting business with

the AIA contract within the state of Maryland will now be

held to a completely different standard than those outside

of Maryland. The result is a reverse effect on transactional

economy in the construction industry and, instead of

being able to rely on the plain language of the contract

that reflects industry standards and the normal course of

business, parties to an AIA contract may not ever be able

to fully comprehend the magnitude of its transaction. The

possibilities are endless and unduly burdensome.

II. Denial of Equal Treatment

The AIA standardized agreements not only establish

a common framework of consistency and legal principles

for its participants, but they also operate to:

“level the playing field between the large and

the small, the rich and the poor, those who can

afford lawyers to scrutinize every transaction

and those who cannot.”45

45. The American Institute of Architects, Official Guide to the

2007 AIA Contract Documents, 2009, Chapter 1. Standardization

of Construction Contracts, p. 3-4.

20

The AIA standardized forms are intended to promote

freedom of contract. They recognize that “not everyone

involved in the construction industry has the same ability

to promote or protect his or her legal interests.”46 In

doing so, they address “the diversity and disparity of size,

economic power, and legal sophistication of the parties to

a construction project.”47

The Maryland court’s interpretation, however,

obliterates this concept of leveling the playing field. It

makes optional the unambiguous plain language of the

AIA contract agreed upon by the parties, and places a

distinct disadvantage on the small, the poor and those

who cannot afford lawyers to scrutinize every transaction.

By its interpretation of this standardized contract, the

Maryland court’s decision imposes a barrier that denies

equal treatment provided by the Equal Protection Clause

of the Fourteenth Amendment of the U.S. Constitution.

“All persons born or naturalized in the United

States, and subject to the jurisdiction thereof,

after citizens of the United States and the

State wherein they side. No state shall make

or enforce any law which shall abridge the

privileges or immunities of citizens of the

United States; nor shall any State deprive any

person of life, life or property, without due

process of law; nor deny to any person within

its jurisdiction the equal protection of the laws.”

46. Id. at 3

47. Id.

21

The courts have interpreted this Constitutional

provision to apply to corporations. Metro. Life Ins. Co. v.

Ward, 470 U.S. 869, 881 n.9 (1985). Petitioner, a womanowned and minority-owned small business, is entitled to

the same protections under the Nonetheless, the Maryland

court’s opinion disproportionately discriminates against

all small businesses. It favors the party that has the

greater capacity to engage the more capable legal team

to scrutinize every aspect of a transaction to avoid its

agreed upon obligations or pursue its claims wherever it

may find support. The Maryland court’s reading that AIA

§13.4.1 renders the plain and unambiguous of the contract

as “non-exclusive,” and the party with greater resources

may create whatever narrative it desires to suit any action

at law that its team of legal experts is able to craft outside

of the contract language.48

It is plainly evident in the case at hand, where the

Respondent took occupancy of its renovated school

facilities on September 6, 2018, then terminated Petitioner

“for cause” several months later to avoid making

payment on its tenth and final invoice. When Petitioner

brought a mechanics lien action in 2019, Respondent’s

initial counterclaim offered unspecified damages “to be

determined at trial.”49 By convincing the court to ignore

48. According to its own Internal Revenue Service records

(IRS Form 990), Respondent reported expenditures of $1,927,489

(in 2021) and $881,140 (in 2020) for legal fees paid to Arent Fox, as

well as an additional $200,021 paid to HKA Global, its expert witness

firm in this litigation. See, https://apps.irs.gov/pub/epostcard/cor/53

0196507_202206_990_2023061221438830.pdf

49. Holton-Arms’ Counterclaims Against HSU Contracting,”

Case No. 472329-V, p. 15, filed November 27, 2019, Record Extract

E109.

22

the unambiguous plain language of the contract, it then,

after two years, crafted a $4.1M damages claim in 2021,

which was presented by its expert witness at trial, and

only nominally supported only by 1950s case law. M&R

Contractors & Builders, Inc. v. Michael, 215 Md. 340

(1958) and Ray v. William G. Eurice & Brothers, 201 Md.

115 (1952). 50 This was not the plain language remedy that

was agreed upon by the parties, or even known to the

parties, at the time of contracting, but a remedy artfully

developed by the legal team of the party with the deeper

pockets over the course of several years. Parties to the

AIA Contract, or any contract, should be able to rely on

the plain language of the contract, as executed, and not

have to litigate or “determine at trial” the extent of their

obligations.

While this Court has acknowledged, in the realm

of government contracting, a right to compete on equal

footing, Adarand Constructors v. Pena, 515 U.S. 200

(1995), Congress has also expressly mandated the need

to protect small businesses through the Small Business

Act, 15 U.S. C 631(a), which sets forth:

“The essence of the American economic system

of private enterprise is free competition.

Only through full and free competition can

free markets, free entry into business, and

opportunities for the express and growth of

personal initiative and individual judgment

be assured. The preservation and expansion

of such competition is basic not only to the

50. These cases, when read in their entirety, offer no support

for Holton’s damages claim.

23

economic well-being but to the security of this

Nation. Such security and well-being cannot be

realized unless the actual and potential capacity

of small business is encouraged and developed.

It is the declared policy of the Congress

that the Government should aid, counsel,

assist, and protect, insofar as is possible, the

interests of small business concerns in order to

preserve free competitive enterprise, to insure

that a fair proportion of the total purchases

and contracts or subcontractors for property

and services for the Government (including

but not limited to contracts or subcontractors

for maintenance, repair, and construction) to

be placed with small-business enterprises…”

(Emphasis added.)

The federal government has recognized the importance

of promoting small business participation in the American

economic system of private enterprise, and mandated

their assistance and protection, while the Maryland

court’s interpretation serves as the antithesis. It denies

Maryland small businesses equal protection of the laws

by favoring those with greater resources and access, such

as the Respondent.

24

CONCLUSION

Review should be granted because of the strong

federal interest in promoting interstate commerce served

by the standardized AIA agreements in that they create

a reliable, common, and consistent framework that serves

to level the playing field for small businesses. If left to

stand, the Maryland court’s decision will unreasonably

burden interstate commerce by depriving contracting

parties and others in the interstate construction industry,

who have historically relied upon these forms as industry

standard, of the confidence and certainty they require

in their interstate business arrangements. Review is

appropriate because the Maryland court departed from

well-recognized principles of regularity and construction

of the industry standard plain language, instead relying on

Maryland common law to fashion a freewheeling post-hoc

remedy resulting in a disproportionate impact on small,

disadvantaged businesses that cannot afford the legal

costs associated with negotiating or defending the plain

language of the terms that were agreed upon.

Respectfully submitted,

A mber Wong Hsu

Counsel of Record

HSU Contracting, LLC

6100 Executive Blvd., Suite 450

N. Bethesda, MD 20852

(301) 437-1000

amber@hsubuilders.com

Counsel for Petitioner

APPENDIX

i

TABLE OF APPENDICES

Page

APPENDIX A — ORDER OF THE SUPREME

COU RT OF M A RY L A N D, FILED

DECEMBER 20, 2023 . . . . . . . . . . . . . . . . . . . . . . . . 1a

A P P E N DI X B — O P I N ION O F T H E

APPELLATE COURT OF MARYLAND,

FILED SEPTEMBER 28, 2023 . . . . . . . . . . . . . . . . 3a

APPENDIX C — TRIAL COURT OPINION

OF T HE CIRCU I T COU RT FOR

MONTGOMERY COUNTY, MARYLAND

FILED OCTOBER 12, 2022 . . . . . . . . . . . . . . . . . . 51a

1a

AppendixOF

A THE SUPREME

APPENDIX A — ORDER

COURT OF MARYLAND, FILED

DECEMBER 20, 2023

IN THE SUPREME COURT OF MARYLAND

HSU CONTRACTING LLC,

V.

HOLTON-ARMS SCHOOL, INC.

Petition No. 241

September Term, 2023

(No. 1707, Sept. Term, 2022

Appellate Court of Maryland)

(Cir. Ct. No. 472329V)

ORDER

Upon consideration of the petition for a writ of

certiorari to the Appellate Court of Maryland, the briefs

of amicus curiae Associated General Contractors of

Metropolitan Washington, DC and Associated General

Contractors of Maryland, respondent’s answer to the

petition, petitioner’s motion for leave to reply to the

respondent’s answer, and petitioner’s reply to the answer,

it is this 20th day of December 2023, by the Supreme

Court of Maryland,

2a

Appendix A

ORDERED that petitioner’s motion for leave to file

a reply to the answer to the petition is granted; and it is

further

ORDERED that the petition for writ of certiorari

is denied as there has been no showing that review by

certiorari is desirable and in the public interest.

/s/ Matthew J. Fader

Chief Justice

3a

Appendix

B

APPENDIX B

— OPINION

OF THE

APPELLATE COURT OF MARYLAND,

FILED SEPTEMBER 28, 2023

UNREPORTED*

IN THE APPELLATE COURT OF MARYLAND

No. 1707

September Term, 2022

Filed September 28, 2023

HSU CONTRACTING, LLC

v.

HOLTON-ARMS SCHOOL, INC., et al.

Berger,

Beachley,

Moylan, Charles E., Jr.

(Senior Judge, Specially Assigned), JJ.

Opinion by Beachley, J.

HSU Contracting, LLC (“HSU”) filed a complaint in

the Circuit Court for Montgomery County against the

Holton-Arms School, Inc. (“Holton”) alleging breach of

contract, conversion, and other related claims. Holton

* This is an unreported opinion. This opinion may not be cited

as precedent within the rule of stare decisis. It may be cited for its

persuasive value only if the citation conforms to Rule 1-104(a)(2)(B).

4a

Appendix B

filed a counter-complaint, also alleging breach of contract.

After a fifteen-day bench trial, the circuit court awarded

$2,579,366 to Holton on its breach of contract claim and

$9,550 to HSU on its conversion claim.

HSU noted this timely appeal and presents the

following questions for our review, which we have slightly

rephrased and renumbered to set forth the questions as

we shall address them:

I.

Did the circuit court err in permitting the

testimony of Holton’s experts, whose reports

were disclosed after the close of discovery?

II. Did the testimony of expert Lawrence

Smith satisfy the requirements of Daubert

v. Merrell Dow Pharm., Inc.?

III. Did the circuit court err in awarding liquidated

damages in addition to actual damages and

despite the contract provision that barred

liquidated damages once the project had

reached “Substantial Completion”?

IV. Did the circuit court err in awarding Holton’s

damages based on estimates of costs despite

a contractual provision limiting damages to

costs incurred?

V.

Did the circuit court err in failing to require

Holton to mitigate its damages?

5a

Appendix B

As to the third question, we agree that a portion of the

damages must be remitted. We answer the remaining four

questions in the negative. Accordingly, we shall modify

the damages award and affirm the judgment as modified.

FACTUAL AND PROCEDURAL BACKGROUND

On June 5, 2018, the parties entered into a contract for

HSU to renovate one of Holton’s classroom buildings (the

“Lower School”) and to upgrade Holton’s HVAC system

in all of its buildings. The contract required that HSU

substantially complete the Lower School renovation by

August 24, 2018, and substantially complete the HVAC

work by January 18, 2019.1 If substantial completion was

not timely achieved, the contract provided for liquidated

damages of $500 per day for the Lower School renovation,

and a lump sum of $5,000 for the HVAC work.

Holton alleged that HSU did not substantially

complete either the Lower School renovation or the

HVAC work on time. Classes for the 2018/2019 school year

began on September 4, 2018. Because the Lower School

renovation was not completed by that time, Holton had

to temporarily hold classes in “the library, the theater,

a dance studio, and a couple of other classrooms and

common spaces.” On September 5, 2018, HSU notified

Holton that it could begin holding classes in the Lower

School. Holton hired movers to set up the classrooms for

1. The substantial completion deadline for the HVAC work was

originally August 25, 2018, but the parties later agreed to change

the deadline to January 18, 2019.

6a

Appendix B

immediate use and began holding classes in the Lower

School on September 6, 2018.

In September of 2018, Holton noticed warping and

buckling in the newly installed bamboo flooring in the

Lower School. Neither HSU nor its subcontractor, Capital

City Flooring, attempted to repair the bamboo flooring

during the winter or spring break, when the Lower School

was not being used.

On May 31, 2019, Holton sent HSU a letter notifying

HSU that Holton was terminating the contract for cause.

The letter noted several material breaches of the contract,

including failure to achieve substantial completion, failure

to submit certain schedules as required by the contract,

and defects in the work performed.

HSU filed a complaint on September 11, 2019, against

Holton and Capital Projects Management, a company

hired by Holton to act as its project manager. 2 HSU

alleged, inter alia, that Holton breached the contract

by failing to pay HSU for work it had performed, and

alleged that Holton converted certain materials and

tools belonging to HSU by not allowing HSU to enter the

school grounds to retrieve the items after terminating the

contract. Holton filed a counter-complaint alleging breach

of contract against HSU for failing to complete the project

and providing defective work.

2. The trial court entered judgment in favor of Capital Projects

Management at the close of HSU’s case-in-chief. HSU has not

appealed that ruling.

7a

Appendix B

The circuit court originally set the discovery deadline

for May 21, 2020. After several agreements between the

parties to extend the scheduling order, the final discovery

deadline was set for February 28, 2021. However, the

parties continued to conduct discovery after this date,

including the taking of several depositions.

In April 2020, Holton requested that HSU produce

the Daily Reports that were generated by HSU while the

construction project was ongoing. HSU failed to provide

the Daily Reports, despite its employees’ deposition

testimony that the Daily Reports existed. After further

requests for the Daily Reports were unsuccessful, Holton

filed a motion to compel HSU to produce the Daily

Reports, or to explain why they could not be produced. In

its motion, Holton alleged that HSU’s failure to produce

the reports “made it impossible for Holton’s experts to

complete their work.” As a result of the circuit court’s

March 22, 2021 order granting the motion to compel,

HSU produced “several hundred pages of Daily Reports.”

Holton provided HSU with expert reports on May 5, 2021,

slightly more than a month before trial was scheduled to

begin on June 14, 2021.

On May 25, 2021, HSU filed a motion seeking to

continue the trial. Trial was originally scheduled for five

days, but it had become apparent to both parties that it

would require at least ten days to try the case. In addition

to representing that trial “will require ten (10) days, if

not more,” HSU also sought a continuance based on the

late disclosure of Holton’s expert reports. HSU stated:

“Because of [Holton’s] production of expert reports

8a

Appendix B

only weeks before the trial date, [HSU] has not had an

opportunity to depose [Holton’s] expert[s] regarding

the substance of their reports, nor the opportunity to

adequately review the report[s] and consult with [HSU’s]

expert.” HSU further noted that “a postponement of the

trial date in this matter will prevent further prejudice to

[HSU] as a result of [Holton’s] belated production of expert

reports.” The court granted the continuance, rescheduling

the trial for ten days beginning December 6, 2021. After

the continuance was granted, HSU never attempted to

depose Holton’s expert witnesses.

On October 13, 2021, Holton served deposition notices

for two of HSU’s witnesses. In an email exchange, HSU

explained that it would not produce any witnesses for

deposition, reasoning: “As the discovery deadline has long

since passed and no party has moved for leave to reopen

discovery, no further depositions are permitted.” Holton

filed an Emergency Motion to Compel HSU’s Cooperation

in Scheduling Depositions, which noted that Holton “also

offered to produce their own experts for deposition.” HSU

filed an opposition to Holton’s motion, in which it stated

that Holton “had the option of requesting the scheduling

of depositions at any time from late-May 2021 through the

entire summer of 2021, or alternatively moving to reopen

discovery during that period, but [Holton] elected not to

do so.” HSU additionally requested the court to “issue a

protective order stating that no further discovery be had

prior to the commencement of trial.” On November 9,

2021, the court denied Holton’s motion and granted HSU’s

motion, barring any further discovery.

9a

Appendix B

A fter a second postponement, the trial began

on February 28, 2022, and lasted fifteen days. HSU

produced nine witnesses, including one expert witness

and HSU’s Director of Operations for this project, Steven

Smith. Holton produced seven witnesses, including its

two experts, the lead architect, and Holton’s Director

of Facilities. We shall recount relevant portions of the

testimony of these witnesses as necessary to our analysis.

After closing arguments, the court requested that the

parties file post-trial memoranda. On October 12, 2022, the

court issued a written opinion, finding that HSU breached

the contract, and awarding $2,579,366 in damages to

Holton. The court also found that Holton converted certain

property belonging to HSU and awarded $9,550 to HSU.

Holton has not appealed the court’s conversion award.

On October 24, 2022, HSU filed a motion to alter or

amend, presenting many of the same arguments that it

raises on appeal. The court denied the motion.

We shall provide additional facts as necessary to

resolve the issues raised on appeal.

DISCUSSION

The issues HSU raises in this appeal can be grouped

into two categories: 1) those concerning Holton’s expert

witnesses; and 2) those concerning the trial court’s

calculation of damages. Because the court relied heavily

on expert testimony for its damages calculation, we shall

first consider HSU’s arguments concerning the expert

witnesses.

10a

Appendix B

Issues Related To Expert Witnesses

HSU raises two challenges related to Holton’s expert

witnesses. First, HSU argues that the trial court erred

by denying its motion to preclude the testimony of both

experts due to Holton’s late disclosure of the expert

reports. Second, HSU argues that the court erred by

admitting the testimony of Lawrence Smith, 3 Holton’s

damages expert, because his methodology did not meet

the Daubert/Rochkind standard. See Daubert v. Merrell

Dow Pharm., Inc., 509 U.S. 579, 113 S. Ct. 2786, 125 L.

Ed. 2d 469 (1993); Rochkind v. Stevenson, 471 Md. 1, 236

A.3d 630 (2020). We shall discuss each argument in turn.

I.

The Alleged Discovery Violation

Holton disclosed its two experts, Wayne Deflaminis

and Expert Smith, on February 6, 2020, more than a

year before the close of discovery on February 28, 2021.

However, it did not provide HSU with copies of the

experts’ reports until May 5, 2021, after the discovery

deadline. HSU argues that this late disclosure of the

reports made it impossible for HSU to depose the experts,

causing it prejudice that required preclusion of the

experts’ testimony.

Holton responds, first, that the reason for the late

disclosure of the reports was HSU’s own late disclosure

of the Daily Reports needed by the experts to develop

3. To avoid confusion between witnesses Lawrence Smith and

Steven Smith, we shall refer to Lawrence Smith as “Expert Smith.”

11a

Appendix B

their opinions. Second, Holton asserts that HSU was not

prejudiced by the late disclosure because the experts’

reports were disclosed nearly ten months before trial

began, and HSU never attempted to depose the experts

in that time. We agree with Holton that the court did not

abuse its discretion in admitting the expert testimony

because HSU was not prejudiced by the late disclosure

of the expert reports.

The trial was originally scheduled for five days,

starting on June 14, 2021. On May 25, 2021, HSU moved

to continue the June 14 trial. In its motion, HSU stated

that “[b]ecause of [Holton’s] production of expert reports

only weeks before the trial date, [HSU] has not had an

opportunity to depose [Holton’s] expert[.]” HSU further

asserted that the parties needed at least ten days for

trial. The court granted the motion and set the trial for

December 2021. After a second postponement, the case

was tried over fifteen days in late-February and earlyMarch 2022.

A fair reading of HSU’s motion for continuance reveals

that HSU sought a postponement, in part, because it

intended to depose Holton’s experts. Nevertheless, at

no point did HSU attempt to depose Holton’s expert

witnesses. HSU argues that it was unable to depose the

experts because the discovery deadline had passed. HSU’s

argument is disingenuous for several reasons. First,

HSU deposed several other witnesses after the discovery

deadline without any resistance from Holton. Thus, there

is nothing in the record to suggest that Holton would

have objected to HSU deposing their experts even in the

12a

Appendix B

absence of a formal extension of the discovery deadline.

Second, to the extent that HSU believed the formal

discovery deadline presented an impediment, HSU never

requested the court to extend the discovery deadline.

Third, in October 2021 Holton proposed deposition dates

for several witnesses, but HSU refused to agree to the

witness depositions, asserting that Holton “had the option

of requesting the scheduling of depositions at any time

from late-May 2021 through the entire summer of 2021,”

but elected not to do so. Indeed, HSU sought and was

granted an order barring further discovery. Aside from

the continuance, which was granted, the only cure HSU

requested for Holton’s discovery violation was preclusion

of the expert testimony.

A trial court’s decision on discovery sanctions is

reviewed for abuse of discretion. In deciding whether to

impose sanctions, the court should consider the Taliaferro

factors: “(1) whether the disclosure violation was technical

or substantial; (2) the timing of the ultimate disclosure;

(3) the reason, if any, for the violation; (4) the degree of

prejudice to the parties respectively offering and opposing

the evidence; (5) whether any resulting prejudice might

be cured by a postponement; (6) and, if so, the overall

desirability of a continuance.” Watson v. Timberlake, 251

Md. App. 420, 434, 253 A.3d 1094 (2021) (citing Taliaferro

v. State, 295 Md. 376, 390-91, 456 A.2d 29 (1983)). Courts

may also consider “any other relevant circumstances.”

Thomas v. State, 397 Md. 557, 571, 919 A.2d 49 (2007).

“[I]n fashioning a sanction, the court should impose the

least severe sanction that is consistent with the purpose

of the discovery rules.” Id. “[T]he more draconian

13a

Appendix B

sanctions, of dismissing a claim or precluding the evidence

necessary to support a claim, are normally reserved for

persistent and deliberate violations that actually cause

some prejudice[.]” Admiral Mortg., Inc. v. Cooper, 357

Md. 533, 545, 745 A.2d 1026 (2000).

Applying these factors to the present case, nearly

every factor weighs heavily in Holton’s favor. Although

the disclosure was made only slightly more than a month

before trial was originally scheduled to begin, the delay

in disclosure was at least partially caused by HSU’s

refusal to provide the Daily Reports needed by Holton’s

experts. Any prejudice that may have existed when the

reports were first produced was cured when the June

2021 trial was ultimately postponed to late February

2022, giving HSU ample time to conduct depositions.

Indeed, in its motion to continue, HSU stated that “a

postponement of the trial date in this matter will prevent

further prejudice to [HSU] as a result of [Holton’s]

belated production of expert reports.” (emphasis added).

“Other relevant circumstances” include HSU’s strong

resistance to discovery after the trial was rescheduled,

contrary to HSU’s suggestion in its motion to continue

that a continuance would afford HSU the opportunity to

depose Holton’s experts.

In two cases, Giant Food Inc. v. Satterfield, 90 Md.

App. 660, 669-71, 603 A.2d 877 (1992), and Thomas, 397

Md. at 572-75, parties disclosed witnesses one week before

trial and the opposing parties sought exclusion of those

witnesses. In both cases, the opposing parties did not

seek either to depose the witnesses or to continue the

14a

Appendix B

trial. This Court and the Supreme Court of Maryland

held that the trial courts did not abuse their discretion by

allowing the witnesses to testify. In Thomas, the Supreme

Court of Maryland noted that opposing counsel had “an

opportunity to interview the witness and to prepare for

crossexamination. Significantly, petitioner requested

only that the trial court exclude the evidence. He was not

interested in a continuance nor an opportunity to talk to”

the witness. Thomas, 397 Md. at 572. Instead, he sought

only the “windfall” of excluding the witness. Id. at 573,

75. The same is true in the present case.

It is apparent that in the nearly ten months between

the May 2021 disclosure of the expert reports and the

start of trial, HSU never showed an interest in deposing

Holton’s experts. Although the discovery deadline had

passed, it is not true, as HSU seems to claim, that the

deadline made deposition of the experts impossible. HSU

acknowledged that expert depositions could be taken when

it requested a postponement of the trial based in part on

its need to depose the experts. Indeed, HSU deposed other

witnesses after the discovery deadline. HSU’s recognition

that Holton “had the option” to take depositions between

“late-May 2021 through the entire summer for 2021”

applied equally to HSU. HSU simply chose not to depose

Holton’s experts. Moreover, Holton provided no resistance

to any potential deposition, instead attempting to work

with HSU to complete the outstanding depositions.

We reject HSU’s argument that the court should

have precluded Holton’s experts where HSU was at least

partially responsible for the delay and the record amply

demonstrates that the experts could have been deposed

15a

Appendix B

had HSU made a reasonable effort to do so. Under these

circumstances, the trial court did not abuse its discretion

in allowing Holton’s experts to testify.

II. Challenges To Expert Smith’s Testimony

HSU makes three discrete arguments concerning

Expert Smith’s testimony: 1) “Experts Cannot Merely

Parrot the Statements of Others”; 2) “Experts Cannot

Ambush Parties with New Opinions at Trial”; and 3)

“Experts Cannot Provide ‘Expert’ Testimony on Subjects

They Know Nothing About.” We shall address each

argument in turn.

A.

“Parroting” opinions of others

Expert Smith was accepted by the court as an expert

in “construction, construction bidding, construction cost

management and construction cost estimating.” HSU did

not challenge Expert Smith’s qualifications or the court’s

acceptance of him as an expert in the designated fields.

Although we shall discuss Expert Smith’s opinions in more

detail below, he stated that he substantially formed his

opinion concerning the “base damages” resulting from

HSU’s breach of contract by relying on 1) the architect’s

assessment of the scope of work necessary to complete

the project, and 2) competitive bids Holton received from

two contractors to complete the project in accordance

with the architect’s “scope of work” assessment. Expert

Smith confirmed that the documents he relied on were

“definitely” the type of data that an expert in his field

would rely on to form an opinion as to construction costs.

16a

Appendix B

HSU claims that Expert Smith’s testimony should

have been excluded because he merely “parroted”

statements of others. On the fifth day of trial HSU argued

for the first time that Expert Smith’s opinion should be

excluded because it did not satisfy the Daubert/Rochkind

standard for the admissibility of expert testimony.

Specifically, HSU argued that Expert Smith’s opinion was

“not reasonably limited to the remaining scope of work

on the project,” and “merely adopted the calculations and

bids of the third-parties without any meaningful analysis.”

HSU next raised this issue on the thirteenth day of trial,

shortly before Expert Smith’s testimony began. HSU did

not move to exclude Expert Smith’s testimony at that time,

but expressed its belief that “all we’re basically having this

expert do is parrot whatever it is that was contained” in

bids Holton received to complete the work. HSU raised

the issue again on the last day of trial, just before closing

arguments. The entirety of HSU’s argument at that time

was that “the predicate for the opinion [was] based on work

that was done apparently by somebody else.”

On appeal, HSU reiterates that Expert Smith

improperly “parroted” the opinions of others by

unquestioningly relying on the architect’s assessment of

the work that needed to be done to complete the project

and the two responsive competitive bids. In HSU’s view,

the trial court improperly admitted Expert Smith’s

testimony because his testimony did not satisfy the

Daubert/Rochkind standard for admissibility.

In Rochkind, the Supreme Court of Maryland adopted

the Daubert analysis for determining admissibility

17a

Appendix B

of expert testimony, and added several factors from

other cases. 471 Md. 1, 35-36, 236 A.3d 630 (2020). The

factors for determining reliability of an expert witness’s

methodology are:

(1)

whether a theory or technique can be (and

has been) tested;

(2)

whether a theory or technique has been

subjected to peer review and publication;

(3)

whether a particular scientific technique has

a known or potential rate of error;

(4)

the existence and maintenance of standards

and controls; . . .

(5)

whether a theory or technique is generally

accepted[;]

[. . .]

(6)

whether experts are proposing to testify

about matters grow ing naturally and

directly out of research they have conducted

independent of the litigation, or whether

they have developed their opinions expressly

for purposes of testifying;

(7)

whether the expert has unjustif iably

extrapolated from an accepted premise to

an unfounded conclusion;

18a

Appendix B

(8)

whether the expert has adequately accounted

for obvious alternative explanations;

(9)

whether the expert is being as careful as

he [or she] would be in his [or her] regular

professional work outside his [or her] paid

litigation consulting; and

(10) whether the field of expertise claimed by the

expert is known to reach reliable results for

the type of opinion the expert would give.

Katz, Abosch, Windesheim, Gershman & Freedman, P.A.

v. Parkway Neuroscience & Spine Inst., LLC, 485 Md. 335,

301 A.3d 42, 2023 Md. LEXIS 382, *36-*37, No. 30, Sept.

Term 2022 (filed August 30, 2023) [hereinafter Parkway

Neuroscience] (alterations in original) (quoting State

v. Matthews, 479 Md. 278, 310-11, 277 A.3d 991 (2022)).

“[T]he admissibility of expert testimony is a matter

largely within the discretion of the trial court, and its

action in admitting or excluding such testimony will

seldom constitute ground for reversal.” Rochkind, 471 Md.

at 10 (alteration in original) (quoting Roy v. Dackman, 445

Md. 23, 38-39, 124 A.3d 169 (2015)).

In denying HSU’s request to preclude Expert Smith’s

testimony, the court noted that “we didn’t hear anything

about” many of the Daubert/Rochkind factors, and that

if the motion had been raised prior to trial, there would

have been a full hearing on the issue.4 As to the factors

4. Although we have not found any decisional law that mandates

a pre-trial Daubert hearing, we agree with the trial court’s

observation that raising a Daubert issue “for the first time during

19a

Appendix B

concerning testing of the methodology, peer review, and

rate of error, the court noted that “neither side really

question[ed] that witness about these matters.” Instead,

the only factor that HSU focused on was “whether

there’s an unjustifiable extrapolation,” also known as an

“analytical gap.” The court concluded:

In this case, we do have [Expert] Smith,

who told us exactly what he did. He told us what

he thought was reliable. He told us about the

two bids that he reviewed, that two competitive

bids, in his view, were a better standard of

market value for costs than him just going out

and doing it.

Now [HSU], as they are able to and can,

can attack some of the data that he received.

In fact, that is a very viable challenge to an

expert’s opinion is to claim the data that you’re

relying on is faulty; but that does not mean

that the analysis is the gap there; that means

that you might have been operating from a bad

premise initially.

So, in this particular case, that goes more

to the weight than whether it goes to the

admissibility of the expert’s opinion. So, for that

reason, I am going to deny the motion of counsel

to exclude the testimony of [Expert] Smith.

trial” is “generally not . . . the best practice.” That HSU first raised

Daubert/Rochkind on the fifth day of trial and substantively argued

only one of the ten relevant factors evinces its feeble (and ultimately

unpersuasive) attempt to preclude Expert Smith’s testimony.

20a

Appendix B

We begin our analysis with State v. Matthews, 479

Md. 278, 277 A.3d 991 (2022), our Supreme Court’s first

post-Rochkind decision applying the new standard. In

Matthews, the State requested the FBI’s assistance to

determine the height of a suspect captured in a video

carrying a shotgun. Id. at 288. An FBI scientist, using

“reverse projection photogrammetry,” determined that

the suspect in the video was approximately 5’8” tall,

plus or minus two-thirds of an inch. Id. That opinion was

significant because Matthews was approximately 5’9”

tall. Id. at 300. However, the forensic scientist’s report

noted that several variables could cause “the degree of

uncertainty in this measurement” to be “significantly

greater.” Id. at 288-89. At a pre-trial hearing, the FBI

scientist “acknowledged that she could not quantify the

overall margin of error based on the variables that were

not calculable.” Id. at 295. The trial court admitted the

scientist’s testimony, and the jury convicted Matthews of

murder. Id. at 297, 303-04.

This Court reversed Matthews’s conviction, concluding

that there was an “analytical gap” between the underlying

data and the expert scientist’s conclusion. Id. at 304. On

certiorari, the Supreme Court reinstated Matthews’s

conviction, holding that the expert’s methodology was

reliable and that no analytical gap existed in the expert’s

opinion. Id. at 313. The Court concluded: “The unknown

degree of uncertainty concerning the accuracy of [the

FBI scientist’s] height estimate went to the weight

the jury should give to the expert testimony, not to its

admissibility.” Id. The Court held that the trial court

acted within its discretion in determining that the expert

21a

Appendix B

testimony would be helpful to the trier of fact under Rule

5-702. The Court reasoned:

First, [the FBI scientist] explained in detail

how she conducted her analysis, which allowed

the trial court to assess the rigor and care with

which [she] approached her work. . . .

Second, [the FBI scientist] explained

. . . why, despite the unknown degree of

uncertainty attributable to certain variables,

she nevertheless was comfortable with her

height estimate of 5’8” plus or minus two-thirds

of an inch. . . .

Third, given [the FBI scientist’s] known

height of between 5’9” and a half and 5’10”, and

the fact that she ensured that she stood in the

same spot and position as the subject in the

questioned image, [the FBI scientist] was able

to opine that the subject appeared to be slightly

shorter than [the FBI scientist] herself.

Id. at 319-320. These factors allowed the trial court to

reasonably conclude that the expert’s opinion would assist

the jury despite the expert’s acknowledged uncertainty.

Id. at 320.

The Supreme Court reaffirmed these principles

recently in Parkway Neuroscience, Md. , 2023 Md.

LEXIS 382, No. 30, Sept. Term 2022. That case involved

an expert accountant’s opinion as to a medical practice’s

22a

Appendix B

lost profits. In light of the trial court’s specific, articulated

concerns about the expert’s “speculative, insufficiently

substantiated judgment calls that were central” to the

expert’s methodology, the Court held that “it was within

the trial court’s discretion to admit or exclude” the expert’s

testimony. 5 2023 Md. LEXIS 382 at *63. The Court made

clear that the admissibility of expert testimony in the

vast majority of cases will be left to the discretion of the

trial court, stating that “[d]etermining whether a dispute

concerning expert testimony implicates the soundness of

data or soundness of methodology is precisely the type

of matter that calls for the exercise of a trial court’s

discretion.” 2023 Md. LEXIS 382 at *55.

Applying these principles to the case at bar, we

conclude that the trial court here likewise did not abuse

its discretion in admitting Expert Smith’s testimony.

Although Expert Smith’s report was not entered into

evidence, his testimony and an accompanying PowerPoint

presentation indicated the methodology Expert Smith

used to develop his opinion. Expert Smith testified that

he reviewed all of the relevant contract documents and

change orders, visited the site, and viewed photographs

of the work. In addition, he reviewed two responsive bids

Holton received in 2020 to complete the work, and a report

from the architect as to the scope of the remaining work.

As previously noted, he testified that these documents

were “definitely” the type of data relied on by experts in

his field to form an opinion.

5. The Court did send the case back to the circuit court for a

limited remand involving a matter not relevant to the instant case.

23a

Appendix B

Expert Smith testified that his calculations began

with the 2020 competitive bids to complete the work. He

focused almost exclusively on the lower of the two bids.

He then “did a reconciliation” of the bid by comparing

it to the higher bid and to the remaining scope of the

work. He determined the scope of the remaining work

by reviewing reports from the architect and Holton’s

Director of Facilities, as well as doing his own analysis.

This reconciliation was done “for the comparison purpose

of coming up with what [he] thought would be the best

reasonable cost for the owner that would be a true

reflection of the market cost at the time the proposal was

tendered.” Because his report was done a year after the

bid was submitted, he adjusted the bid upward by 5% to

account for inflation. He concluded that the fair market

value of the portion of the work HSU failed to complete

that was covered by the 2020 bid was $3,121,446.

Next, Expert Smith added the cost to complete the

smaller tasks that were not included in the 2020 bids.

These costs were based on quotes Holton received for

the work. He then increased the cost by 5% to account

for inflation. He also added to his damages calculation

liquidated damages and money that Holton had already

expended for services HSU should have rendered under

the contract. The total cost to correct and complete the

work, by Expert Smith’s calculation, was $4,103,509. He

then subtracted from these “gross damages” the amount

HSU was owed for work it had completed, $1,524,142, to

reach a “net damages” conclusion of $2,579,366.

In its cross-examination of Expert Smith, HSU tried

to elicit testimony that Expert Smith’s opinion merely

24a

Appendix B

amounted to him accepting the costs reflected in the 2020

bid and adding 5% for inflation, but his testimony belies

that assertion. Expert Smith testified:

I took the two proposals, looked at the scope

that they were quoted on, that they gave a

guaranteed quote for, looked at the adjustments

that needed to be made in order for them to

conform to my interpretation of what remained

to be done to correct and complete the work

that was left by HSU, and I selected the low

number of the two responsive bidders that have

essentially at that time committed to entering

into a contract to perform that work.

HSU’s counsel questioned Expert Smith about why he

did not calculate damages by assigning his own estimate of

the fair market value of completing each item of remaining

work. Expert Smith responded that HSU’s suggested

method could be valid, but countered, “I don’t consider

that to be the best way.” Concerning his use of the lower

of the two 2020 bids, Expert Smith testified, “[W]hen two

contractors, two reputable contractors tender a proposal

. . . and guarantee to stand behind that proposal to enter

into a contract to perform the work, I consider that to be

a true and clear indication of what the present market

value is for that scope of work.” He opined that using the

2020 bids, with adjustments, would be “the most accurate

way of determining a fair market value to estimate the

damages.” He explained,

if I sit down and come up with the cost, unless

I’m going to do the work, it really has no value

25a

Appendix B

to compare with someone who has given a

proposal to do the work and will stand behind

the proposal and do it. That is . . . how you

determine fair market value.

In Rochkind, the Supreme Court of Maryland noted

that “[t]rained experts commonly extrapolate from

existing data.” 471 Md. at 36 (alteration in original)

(quoting Gen. Elec. Co. v. Joiner, 522 U.S. 136, 146, 118

S. Ct. 512, 139 L. Ed. 2d 508 (1997)). Moreover, the law

is clear that experts “may give an opinion based on facts

contained in reports, studies or statements from third

parties if the underlying material is shown to be of a type

reasonably relied upon by experts in the field.” Milton

Co. v. Council of Unit Owners of Bentley Place Condo.,

121 Md. App. 100, 120, 708 A.2d 1047 (1998) (quoting

U.S. Gypsum v. Baltimore, 336 Md. 145, 176, 647 A.2d

405 (1994)), aff’d, 354 Md. 264, 729 A.2d 981 (1999). Here,

Expert Smith prepared his own report and described the

methodology he used to determine the fair market value

of the remaining work. In admitting the testimony, the

circuit court noted that Expert Smith “told us exactly

what he did” and “what he thought was reliable.” The court

recognized that there was an alternative methodology,

but credited Expert Smith’s testimony that using “two

competitive bids, in [Expert Smith’s] view, were a better

standard of market value for costs than him just going

out and doing it.” The trial court obviously found Expert

Smith’s opinion persuasive and helpful in its role as the

trier of fact, and we discern no abuse of discretion in

admitting the testimony.

26a

Appendix B

B. “Ambushing” HSU with new opinion

HSU next argues that Expert Smith improperly

“ambushed” HSU with a new opinion by adding $141,688

to his damages calculation. Expert Smith testified that

he altered his calculations during the course of the trial

by adding a $141,688 expense that he had mistakenly

omitted from his report. Because HSU never objected

to the admission of this evidence, it has waived this

argument. See Patriot Constr., LLC v. VK Elec. Servs.,

LLC, 257 Md. App. 245, 268, 290 A.3d 1108 (2023) (“The

failure to object as soon as the . . . evidence was admitted,

and on each and every occasion at which the evidence was

elicited, constitutes a waiver of the grounds for objection.”

(alteration in original) (quoting Berry v. State, 155 Md.

App. 144, 172, 843 A.2d 93 (2004))).

C.

Providing expert testimony on unfamiliar

subject

Third, HSU argues that Expert Smith improperly

provided expert testimony on a subject with which he

was unfamiliar. Specifically, HSU argues that Expert

Smith was unable to explain a $37,420 line item in his

damages calculation for “Engenium expenses for HSU

Failures.” During cross examination, HSU asked Expert

Smith “what components went into” that expense, and

Expert Smith responded that he could not provide

further information about that expense “without looking

back further at backup documentation.” We do not

interpret Expert Smith’s response as meaning that he

was “unfamiliar” with that component of damages. In

27a

Appendix B

any event, we note that HSU did not pursue this issue

further during this lengthy trial. See Concerned Citizens

of Cloverly v. Montgomery Cnty. Plan. Bd., 254 Md. App.

575, 603, 274 A.3d 1144 (2022) (“[A] passing reference to

an issue, without making clear the substance of the claim,

is insufficient to preserve an issue for appeal, particularly

in a case with a voluminous record.”).

Issues Related To Damages

III. Liquidated Damages

HSU makes two separate arguments concerning

the liquidated damages award. First, HSU argues that

the court “failed to apply the contractual limitation on

liquidated damages, which bars liquidated damages after

the project reaches ‘Substantial Completion.’” Second,

HSU argues that “the court impermissibly awarded

Holton redundant liquidated and actual damages” for the

same loss. We shall address each argument in turn.

A.

The contract provided for liquidated damages of

“Five Hundred Dollars ($500.00) for each calendar day

that expires after the time specified for Substantial

Completion until the Work is substantially complete

for the Lower School Renovation Project.” The “time

specified for Substantial Completion” of the Lower School

project was August 24, 2018. The court found that HSU

never substantially completed the work, and calculated

liquidated damages from August 24, 2018, to May 31, 2019,

28a

Appendix B

the date Holton terminated the contract.6 This 280-day

delay resulted in a liquidated damages award of $140,000.

HSU argues that it achieved substantial completion of

the Lower School project on September 6, 2018, thereby

limiting a liquidated damages award to 13 days, totaling

$6,500.

There are several contract provisions relating to

substantial completion:

• § 8.1.3: “The date of Substantial Completion

is the date certified by the Architect in

accordance with Section 9.8.”

• § 9.8.1: “Substantial Completion is the

stage in the progress of the Work when

the Work or designated portion thereof

is sufficiently complete in accordance

with the Contract Documents so that the

Owner can occupy or utilize the Work for

its intended use. As a condition precedent

to Substantial Completion, the Owner shall

receive all unconditional permits, approvals,

licenses, and other documents from any

governmental authority having jurisdiction

over the Project. Under no circumstances

shall the Work or any portion thereof be

6. The contract also provided for a lump sum of $5,000 in

liquidated damages for delayed substantial completion of the HVAC

project. HSU does not challenge the court’s decision to award this

amount to Holton.

29a

Appendix B

deemed to be Substantially Complete

unless and until unconditional certificates

of occupancy and completion governing that

portion of the Project have been issued by

all appropriate governmental authorities

having jurisdiction over the Project thereby

allowing the intended use of the portion of

the Work.”

• § 9.8.1.1: “The Work will not be considered

suitable for Substantial Completion review

until all Project systems included in area

of the Work are operational as designed

and scheduled, all designated or required

governmental inspections and certifications,

including certificates of occupancy, have been

made and posted, designated instruction of

the Owner’s personnel and the operation

of systems and equipment completed,

and all final finishes within the Contract

Documents are in place. In general, the only

remaining Work shall be minor in nature, so

that the Owner can occupy the portion of the

building on that date for its intended use and

the completion of the Work the Contractor

would not materially affect, or hamper the

normal business operations or intended use

of Owner.”

• § 9.8.4: “When the Work or designated

portion thereof is substantially complete,

the Architect will prepare a Certificate

30a

Appendix B

of Substantial Completion that shall

establish the date of Substantial Completion

. . . . Warranties required by the Contract

Documents shall commence on the date of

Substantial Completion . . . .”

HSU avers that the only section of the contract

relevant to a determination of whether substantial

completion has been achieved is § 9.8.1. According to HSU,

substantial completion is achieved under the contract

when Holton is able to “occupy or utilize the Work for its

intended use,” with a singular precondition that Holton

receive the necessary documents for occupancy from

governmental authorities. Because Holton received a

certificate of occupancy and began holding classes in the

Lower School on September 6, 2018, HSU argues that

it achieved substantial completion of the project on that

date. HSU argues that the court improperly focused on the

lack of an architect’s certificate of substantial completion

and failed to consider “the contract’s actual definition of

Substantial Completion,” i.e. the first sentence of § 9.8.1.

The trial court found that HSU had not achieved

substantial completion, stating in its written opinion:

The Contract stated that the work would

not be considered suitable for Substantial

Completion review until “all Project systems

included in area of the Work are operational

as designed and scheduled.” [§ 9.8.1.1]. The

lighting control system is still not operational

as designed. Further, [Holton’s] personnel

were not instructed on operating the system

31a

Appendix B

and the final finishes specified in the Contract

documents were not in place. There is a

substantial amount of work on the Project still

outstanding.

[HSU] completely ignored the Substantial

Completion provisions of the Contract. The

evidence established [HSU’s] failure to achieve

Substantial Completion. [HSU] never submitted

a request to the architect for certification of

Substantial Completion. It is a reasonable

inference therefrom that [HSU] was aware

that it had not achieved Substantial Completion.

The court made detailed findings of fact concerning HSU’s

defective performance and concluded that HSU “made

little or no effort to cure the defects, complete the work

or respond to the demands in the Second Cure Notice”

dated May 1, 2019.

In support of its argument that the architect’s

certificate does not determine the date of substantial

completion, HSU cites an Illinois case applying New Jersey

law, In re Liquidation of Lumbermens Mutual Cas. Co.,

2018 IL App (1st) 171613, 431 Ill. Dec. 186, 127 N.E.3d

719 (Ill. App. Ct. 2018). Lumbermens Mutual involved

three contracts between D&D Associates, Inc. and the

North Plainfield Board of Education (the “Board”) for the

renovation of five schools.7 Id. at 724. These projects were

7. Notably, the parties in Lumbermens Mutual used form

contracts developed by the American Institute of Architects

similar to the contracts in the present case. See id. at 730. In both

32a

Appendix B

separated into three contracts: Contract 1A, Contract

1B, and Contract 1C. Id. The substantial completion

issue only involved Contracts 1A and 1B. The architect

issued a certificate of substantial completion for Contract

1A on December 8, 2004, and a certificate of substantial

completion for Contract 1B on November 17, 2004. Id. at

730. The Board argued that these dates should be used

to calculate liquidated damages for delayed completion of

the project. Id. at 727. However, in April 2003, the Board

applied for a state grant related to Contract 1A from the

New Jersey Economic Development Authority (“EDA”),

and submitted architect’s certifications as part of that

application that stated:

A. The essential requirements of the Contracts

have been fully performed so that the

purpose of the Contracts is accomplished.

B. The Punchlist has been created.

C. There a re no impor tant or mater ial

omissions or technical defects or deficiencies

regarding the School Facilities Project.

D. The temporary certificate of occupancy,

continued use or completion has been issued.

E. The School Facilities Project is ready for

occupancy in accordance with its intended

purpose.

cases, § 9.8.1 is substantively identical. See id. However, there is no

indication in Lumbermens Mutual that the contracts at issue there

contained a provision similar to § 9.8.1.1.

33a

Appendix B

Id. at 730-31. The Appellate Court of Illinois noted

that “[t]he language of the EDA certification tracks

the language of substantial completion in the contracts.

Thus, the architect . . . at one point declared Contract

1A substantially complete well before the dates” in the

2004 certificates of substantial completion. Id. at 731.

The court further held that “the architect’s arbitrary

conduct as to Contract 1A undermines the integrity of

the architect’s date of substantial completion for Contract

1B.” Id. The Appellate Court of Illinois therefore agreed

with the trial court’s finding that the 2004 certificates of

substantial completion were not a reliable measure of the

date of substantial completion. Id. The trial court referred

to the certificates of occupancy issued in September

2002 to determine the substantial completion date as

defined in the contract, which the Appellate Court of

Illinois noted “can be an appropriate benchmark for

substantial completion.” Id. “Because the Board could

use the buildings for teaching children, it was not an

abuse of discretion for the court to find that the buildings

were substantially complete in September 2002.” Id. The

Board argued that use of the buildings in September 2002

“should be classified as ‘partial occupancy,’ which per the

General Conditions ‘may commence whether or not the

portion [is] substantially complete.’” Id. The Appellate

Court of Illinois rejected this argument:

[T]he circuit court’s written order indicates

that the court considered the evidence of

allegedly incomplete work that the Board points

to on appeal. We see no error in the court’s

thorough analysis and its finding that there was

no delay. The circuit court’s conclusion was not

34a

Appendix B

unreasonable, and so the court did not abuse its

discretion in denying liquidated damages for

contracts 1A and 1B.

Id. at 731-32.

HSU’s reliance on Lumbermens Mutual is unavailing.

The trial court in Lumbermens Mutual, faced with a

situation where there was no reliable architect’s certificate

to determine the date of substantial completion, instead

looked to other relevant evidence to determine substantial

completion. The Appellate Court of Illinois held that the

trial court did not abuse its discretion in doing so and

affirmed the trial court’s “thorough analysis.”

We likewise see no clear error in the trial court’s

detailed findings of fact in this case. Contrary to the

argument HSU advances, the court did not focus solely

on the lack of a certificate of substantial completion from

the architect. The court noted that HSU “never submitted

a request to the architect for a certificate of Substantial

Completion,” but also considered other contract language

to conclude that HSU never achieved substantial

completion. The court properly applied the restriction

in § 9.8.1.1, which provides that “The Work will not be

considered suitable for Substantial Completion review

until all Project systems included in area of the Work are

operational as designed and scheduled, . . . designated

instruction of the Owner’s personnel and the operation of

systems and equipment completed, and all final finishes

within the Contract Documents are in place.” (Emphasis

added). Relevant to this provision, the court found that

35a

Appendix B

HSU did not ensure that the lighting control system was

operational, did not instruct Holton’s personnel on how to

operate the system, and did not complete final finishes.

The court also found that HSU “made little or no effort to

cure the defects” or “complete the work,” and “completely

ignored the Substantial Completion provisions of the

Contract.” HSU does not challenge these findings of fact,

and our independent review of the record confirms that

the court’s findings were not clearly erroneous. Thus,

pursuant to § 9.8.1.1, HSU did not attain “substantial

completion” of the Lower School, regardless of Holton’s

use of the building. 8

We hold that the trial court did not err in its

determination that HSU never achieved substantial

completion. Accordingly, except for the $23,812.15

duplication of damages that we discuss in the next

section, we conclude that the court did not err in assessing

liquidated damages from August 24, 2018, to May 31, 2019.

8. HSU attempts to bolster its position by noting that § 9.8.4

provides that “[w]arranties required by the Contract Documents

shall commence on the date of Substantial Completion.” HSU points

to several letters from subcontractors to Holton representing that

warranties on their work began on September 6, 2018. Although

HSU attached these letters to its motion to alter or amend, none of

the letters were entered into evidence at trial. The only evidence

produced at trial concerning when the warranties began was

testimony from Steven Smith that the warranty from Capital City

Flooring began on September 6, 2018. The circuit court found that

Steven Smith “was not a credible witness.” Even if further evidence

about the warranties had been admitted at trial, the existence

of warranties beginning on September 6, 2018, does not render

meaningless the requirements of § 9.8.1.1.

36a

Appendix B

B.

The liquidated damages clause of the contract

provides: “Contractor and Owner recognize that time is

of the essence and that Owner will suffer financial loss

if the Work is not completed within the times specified

for completion of the Work.” The contract states that the

liquidated damages are “for delay.”

HSU argues that the court improperly awarded

both liquidated damages for delay and also actual

damages incurred because of delay. Specifically, HSU

argues that the liquidated damages provision acted as

an “impermissible penalty” because it overlapped with

actual damages. HSU provides two examples of actual

damages that the court improperly awarded because

they are duplicative of liquidated damages for delayed

performance: $63,687 listed in “Bulletin 26,” and $168,473

in “escalation fees.”

Generally speaking, “if a plaintiff receives liquidated

damages, then a claim may not be made for actual

damages.” Gonsalves v. Bingel, 194 Md. App. 695,

714, 5 A.3d 768 (2010) (quoting Ecology Servs., Inc. v.

GranTurk Equip. Inc., 443 F. Supp. 2d 756, 773 (D. Md.

2006)). “Where the parties to a contract have included a

reasonable sum that stipulates damages in the event of

breach, that sum replaces any determination of actual

loss.” Barrie Sch. v. Patch, 401 Md. 497, 513, 933 A.2d 382

(2007). Because Holton’s school year begins in September,

the parties ostensibly included the liquidated damages

provision to cover all costs the school might incur due to

a delay in reopening the school.

37a

Appendix B

First, we reject HSU’s argument as to the escalation

costs because these are not expenses related to Holton’s

inability to use the school as a result of HSU’s failure to

accomplish substantial completion on time. Rather, the

escalation costs were adjustments made by Expert Smith

to account for inflation in determining the fair market cost

of the work necessary to complete the project as a result

of HSU’s breach.

This leaves us with HSU’s argument concerning

Bulletin 26, a document created by the architect that

modified the contract by reducing the amount paid to

HSU because of additional expenses incurred by Holton.

The trial court included the entire amount reflected in

Bulletin 26 in its damages calculation, in addition to

awarding liquidated damages. Bulletin 26 lists $63,687.54

in expenses Holton incurred either because of HSU’s delay

in completing the project, or to prevent further delay. A

large portion, $23,812.15, of Bulletin 26 is for “Moving

Services,” which is described:

Moving services were to be provided

by Owner and were arranged based on the

contractor schedule for August 25, 28, and 29.

Due to work not being completed additional

moving time was required as work could not

be completed in all areas. Owner contracted

to have work done directly as base contract

was with owner. i. Initial plan was for teachers

to perform unpacking, but due to schedule

teachers were teaching and could not perform

unpacking concurrently, requiring additional

assistance. . . .

38a

Appendix B

Michael Joyce, the Director of Facilities at Holton,

testified that the “Moving Services” charge came about

“because we were late moving into the lower school and

really didn’t have a lot of time” to set up the classrooms.

“[W]e expected to have time that the teachers could put

things back where they wanted to . . . in their classrooms.

And that didn’t happen.”

Julianna von Zumbusch, the principal architect for

the project, testified about Bulletin 26: “So some of these

had to do with costs that were not directly related to the

repair of defective work, but due to schedule delays from

the work. So the moving services would be one of those,

where movers had to deploy for multiple days and the

school wasn’t able to get a refund due to short notice for

their original scheduled move date.”

The “Moving Services” described in Bulletin 26

are clearly expenses resulting directly from the delay.

Ms. von Zumbusch’s testimony conceded as much. The

court’s award should not have included the $23,812.15

for the moving services because that sum represents

actual damages contemplated by the liquidated damages

provision of the contract. We shall therefore reduce the

court’s award by that amount.

The remaining expenses listed in Bulletin 26 were not

expenses that arose solely because of the delay. Rather,

they primarily represent the cost for Holton to hire

another company to expeditiously complete work that

39a

Appendix B

HSU was obligated to perform.9 Additionally, prior to its

motion to alter or amend, HSU did not argue before the

trial court that the remaining expenses listed in Bulletin

26 were duplicative of the liquidated damages; HSU’s

only argument concerned duplication of the moving

services expense. HSU accordingly waived any argument

concerning the expenses listed in Bulletin 26 other than

for moving services. See Morton v. Schlotzhauer, 449 Md.

217, 232 n.10, 144 A.3d 592 (2016) (“A circuit court does

not abuse its discretion when it declines to entertain a

legal argument made for the first time in a motion for

reconsideration that could have, and should have, been

made earlier, and consequently was waived.”).

While we other w ise affirm the circuit court’s

judgment, we shall modify the judgment to remove the

$23,812.15 cost of moving services, thereby reducing the

award from $2,579,366.00 to $2,555,553.85.

9. For example, the second-largest expense in Bulletin 26

is “Johnson Controls costs” totaling $11,626.38. This expense is

described as: “HSU agreed for the Owner to have work performed

directly due to the Electricians inability to perform work and in

effort to maintain schedule and campus-wide fire alarm functioning.”

Unlike the moving services, an expense Holton would not have had if

HSU had performed in a timely manner, the electrical work described

as “Johnson Controls costs” is work that HSU was contractually

obligated to perform and therefore had no relationship to the

liquidated damages clause related to the delay in having the school

ready for occupancy.

40a

Appendix B

IV. Limitation of Damages

HSU next argues that the contract limited Holton’s

damages to costs Holton actually incurred to complete

the work. HSU bases its argument on the following

contractual provisions:

• §14.2.2, providing that, if there is cause to

terminate the contract, Holton “may without

prejudice to any other rights or remedies of

the Owner . . . terminate employment of the

Contractor and may, subject to any prior

rights of the surety: . . . Finish the Work

by whatever reasonable method the Owner

may deem expedient. Upon written request

of the Contractor, the Owner shall furnish

to the Contractor a detailed accounting of

the costs incurred by the Owner in finishing

the Work.”

• § 14.2.4, providing: “If such costs and

damages incurred by the Owner exceed the

unpaid balance, the Contractor shall pay the

difference to the Owner. This obligation for

payment shall survive termination of the

Contract.”

HSU first raised this “limitation of damages”

argument in its Motion to Alter or Amend. “A circuit court

does not abuse its discretion when it declines to entertain

a legal argument made for the first time in a motion for

reconsideration that could have, and should have, been

made earlier, and consequently was waived.” Morton, 449

41a

Appendix B

Md. at 232 n.10. This well-established principle forecloses

HSU’s limitation of damages argument on appeal.10

Even if this argument were preserved, we fail to see

how §§ 14.2.2 and 14.2.4 operate to limit Holton’s damages.

Another section of the contract, § 13.4.1, provides that,

“[e]xcept as expressly provided in the Contract Documents,

duties and obligations imposed by the Contract Documents

and rights and remedies available thereunder shall be in

addition to and not a limitation of duties, obligations,

rights and remedies otherwise imposed or available

by law.” (Emphasis added). Furthermore, § 2.6 states,

“[t]he rights stated in this Article and elsewhere in the

Contract Documents are cumulative and not in limitation

of any rights of the Owner (1) granted in the Contract

Documents, (2) at law, or (3) in equity.” We see nothing

in §§ 14.2.2 and 14.2.4 that creates an express limitation

on the remedies available to Holton. Indeed, consistent

with §§ 2.6 and 13.4.1, § 14.2.2 gives Holton the right

to terminate the contract and finish the work “without

prejudice to any other rights or remedies.” “[A] contract

will not be construed as taking away a common-law

remedy unless that result is imperatively required.”

O’Brien & Gere Eng’rs, Inc. v. City of Salisbury, 447

Md. 394, 408, 135 A.3d 473 (2016) (quoting Mass. Indem.

& Life Ins. Co. v. Dresser, 269 Md. 364, 369-70, 306 A.2d

213 (1973)). The O’Brien & Gere Court further stated:

“Reviewing our case law, we discern that the parties must

10. HSU also briefly argues that the court improperly awarded

consequential damages, despite a provision in the contract expressly

waiving consequential damages. Because HSU never made this

argument before the circuit court, it has not been preserved for our

review.

42a

Appendix B

at least use clear language to show their agreement to

limit available remedies.” Id. at 407. Here, the express

contractual provisions create a remedy that is “in addition

to” the remedies available by law for breach of contract.

Under the common law, a party prevailing on a breach

of contract claim “may recover the amount of damages

‘which will place the injured party in the monetary

position he would have occupied if the contract had been

properly performed.’” Yaffe v. Scarlett Place Residential

Condo., Inc., 205 Md. App. 429, 445 n. 5, 45 A.3d 844 (2012)

(quoting Hall v. Lovell Regency Homes Ltd. P’ship, 121

Md. App. 1, 12, 708 A.2d 344 (1998)). In this case, damages

would include not only the amount that Holton has already

spent as a result of HSU’s breach, but also any additional

funds reasonably necessary to complete the work required

by the contract. See Andrulis v. Levin Constr. Corp.,

331 Md. 354, 371, 628 A.2d 197 (1993) (In cases involving

breach of a construction contract, the proper measure of

damages is the “reasonable cost of reconstruction and

completion in accordance with the contract[.]” (quoting

A. Corbin, Corbin on Contracts § 1089, at 485-87 (1964))).

In conclusion, we reject HSU’s argument that Holton’s

contractual damages were limited to amounts Holton had

“actually incurred.”

V. Mitigation of Damages

Finally, HSU argues that Holton “failed to present

any evidence of properly mitigated damages.” Holton

initially responds that this argument was not raised below

and is therefore waived. However, HSU briefly raised its

43a

Appendix B

mitigation argument in the following two sentences in

HSU’s 45-page post-trial memorandum:

One purpose of a liquidated damages provision

is to obviate the need for the nonbreaching

party to prove actual damages but was required

[sic] to mitigate any damages resulting from

the breach and minimize its losses prior to

seeking any monetary relief in contract. Holton

advanced no proof that it sought to mitigate

its alleged damages, and because it failed to

accept any of the proposals or perform any

alleged remedial work since HSU’s termination,

it is limited at best to the liquidated damages

provision.

(Citation omitted). Because HSU has minimally preserved

this argument for our review, we shall address it.11

11. We note that the court did not explicitly discuss the

mitigation issue in its written opinion. However, during closing

arguments, the court questioned Holton’s counsel about its obligation

to mitigate. We can unequivocally state that mitigation was not at

the forefront of HSU’s defense—it never mentioned it at trial and

raised the issue only in its post-trial memorandum. As mentioned

above, HSU’s entire mitigation argument consisted of two sentences

in its 45-page memorandum. In light of (1) the minimal attention

HSU gave to its mitigation argument, (2) the court’s questioning

during closing arguments concerning mitigation, and (3) the principle

that judges are presumed “to know the law and apply it, even in the

absence of a verbal indication of having considered it[,]” Sinclair v.

State, 214 Md. App. 309, 325, 76 A.3d 442 (2013) (quoting Wagner

v. Wagner, 109 Md. App. 1, 50, 674 A.2d 1 (1996)), we infer that the

court was convinced that HSU fell far short of meeting its burden

of proof on this issue.

44a

Appendix B

To the extent that the mitigation of damages doctrine

applies in this case, we note that HSU had the burden

of proof on this issue. “When it is determined that the

[mitigation of damages] doctrine applies, the burden is

necessarily on the defendant to prove that the plaintiff

failed to use ‘all reasonable efforts to minimize the loss he

or she sustained.’” Cave v. Elliott, 190 Md. App. 65, 96, 988

A.2d 1 (2010) (quoting Schlossberg v. Epstein, 73 Md. App.

415, 422, 534 A.2d 1003 (1988)). The burden is on the party

alleging failure to mitigate “[b]ecause it is aimed primarily

at benefitting” that party, and the damages were caused by

that party’s breach of contract. Id. (quoting Schlossberg, 73

Md. App. at 422). “Thus, it is clear that the doctrine does

not place any duty on a plaintiff or create an affirmative

right in anyone.” Id. (quoting Schlossberg, 73 Md. App. at

422). HSU’s argument that “Holton failed to present any

evidence” on this issue is therefore misplaced, as Holton

had no burden to produce such evidence.

On appeal, HSU specifically argues that Holton failed

to mitigate its damages by either (1) making use of the

warranties of the subcontractors, or (2) completing the

work earlier, before the cost of construction significantly

increased due to the Covid-19 pandemic. We shall discuss

each of these arguments in turn.

A.

Warranties

HSU argues that “nearly all the allegedly defective

work was under warranty and could have been repaired

or replaced at no expense to Holton.” By failing to use the

warranties, HSU argues that Holton “artificially inflat[ed]

45a

Appendix B

the damage assessment.” HSU first specifically discusses

the warranty on the bamboo flooring, which it argues

would have allowed Holton to have the flooring repaired

at no cost. HSU then states: “The same is true of most

of the remainder of Holton’s alleged damages for ‘cost to

correct’ work, all of which was covered by warranty[.]”

The only evidence produced at trial concerning

subcontractor warranties was testimony from three

witnesses about Capital City Flooring’s one-year warranty

on the bamboo flooring. Steven Smith, HSU’s Director of

Operations, who the circuit court found was not a credible

witness, testified that the flooring warranty began on

September 6, 2018. Ms. von Zumbusch testified that she

could not recall any agreement that the warped flooring

would be covered by the warranty. Holton’s Director

of Facilities testified that the subcontractor had taken

the position that the warping of the flooring was not a

warranty issue and would not be covered by the warranty,

although he admitted that Holton never made a warranty

claim for the flooring. On this record, we have no hesitation

in concluding that HSU failed to demonstrate that the

flooring warranty would have fully (or even partially)

covered the damaged bamboo floors.

There was no evidence produced at trial concerning

the other warranties that HSU mentions in passing in its

brief. The letters that HSU references were not admitted

into evidence, but were attached as exhibits to HSU’s

motion to alter or amend. The trial court did not abuse

its discretion by refusing to consider these letters. See

Steinhoff v. Sommerfelt, 144 Md. App. 463, 484, 798 A.2d

46a

Appendix B

1195 (2002) (“With respect to the denial of a Motion to

Alter or Amend, . . . the discretion of the trial judge is more

than broad; it is virtually without limit. What is, in effect,

a post-trial motion to reconsider is not a time machine in

which to travel back to a recently concluded trial in order

to try the case better with hindsight. The trial judge has

boundless discretion not to indulge this all-too-natural

desire to raise issues after the fact that could have been

raised earlier but were not or to make objections after the

fact that could have been earlier but were not.”).

Furthermore, there was affirmative evidence that

Holton attempted to mitigate its damages. The court

found that Holton attempted to take an assignment of one

of the subcontracts, a mechanism that should have been

available under the contract, but that HSU’s subcontractor

agreement provided for assignment to Holton only upon

termination for convenience. The contract between Holton

and HSU provides that, when the Owner terminates for

cause, the Owner has the option to “[a]ccept assignment

of subcontracts.” However, HSU’s subcontract agreement

with Kent Island Mechanical—the only subcontractor

discussed at trial with relation to assignment—provides:

“The Constructor’s [sic] contingent assignment of this

Agreement to the Owner, as provided in the Prime

Contract, is effective when the Owner has terminated

the Prime Contract for its convenience.” Three witnesses

testified that Holton sought an assignment of the Kent

Island Mechanical contract after termination of its

contract with HSU. Steven Smith, HSU’s Director of

Operations for the Holton project, testified that HSU’s

subcontract agreement with Kent Island Mechanical

47a

Appendix B

did not match the assignment requirement in its prime

contract with Holton. He further testified that Holton

attempted to obtain an assignment of the Kent Island

Mechanical subcontract. Kent Island Mechanical’s

president confirmed that Holton discussed the possibility

of an assignment of the subcontract. Additionally,

William Koch, a senior project manager for Kent Island

Mechanical, testified that he received a letter from Holton

attempting to accept assignment of the subcontract.

The evidence supports the trial court’s finding that

HSU’s actions prevented Holton from exercising its right

to assignment of the subcontracts, which may have allowed

it to mitigate its damages. In short, the record is clear

that HSU failed to satisfy its burden of proof on this issue.

B. Completing the Work in 2019

HSU argues that Holton should have mitigated its

damages by having the remaining work completed before

the Covid-19 pandemic caused construction prices to

significantly increase.

Part of this argument involves issues related to HSU’s

“limitation of damages” argument, discussed above. HSU

avers that “[u]nder Maryland law, ‘contract damages are

measured at the time of breach.’” (Quoting CR-RSC Tower

I, LLC v. RSC Tower I, LLC, 429 Md. 387, 405, 56 A.3d

170 (2012)). This statement is not accurate in this context,

as the Supreme Court of Maryland made clear in the very

case HSU cites:

48a

Appendix B

Tenants would have us apply this “time of

breach” rule across the board, to every kind of

damages claim. Yet as Corbin explains, there

cannot be one rule for every kind of breach,

because different kinds of damages require

different kinds of calculations. See [11 Corbin

on Contracts] § 55.11 [(Rev. ed. 2005)] (“There

are many rules of damages for particular kinds

of contracts, such as contracts for the sale of

goods, construction contracts, employment

contracts, etc.” (footnotes omitted)); see also

Great Atlantic & Pacific Tea Co. v. Atchison,

T. & S. F. R. Co., 333 F.2d 705, 708 (7th Cir.

1964) (“Since the market value rule is merely

a method, it is not applied in cases where it is

demonstrated that another rule will better

compute actual damages.”).

CR-RSC Tower I, LLC, 429 Md. at 410. HSU has not cited

a case for the proposition that damages are measured

at the time of breach for construction contracts. In

Andrulis v. Levin Constr. Corp., the Supreme Court of

Maryland stated that the proper measure of damages

for breach of a construction contract is the “reasonable

cost of reconstruction and completion in accordance

with the contract, if this is possible and does not involve

unreasonable economic waste.” 331 Md. 354, 371, 628 A.2d

197 (1993).12

Concerning HSU’s argument that Holton should have

hired a new contractor to complete the work in 2019 before

prices substantially increased, there was testimony that

12. HSU has not made an economic waste argument.

49a

Appendix B

Holton, being a non-profit, had limited funding. “The party

who is in default may not mitigate his damages by showing

that the other party could have reduced those damages

by expending large amounts of money or incurring

substantial obligations. Since such risks arose because

of the breach, they are to be borne by the defaulting

party.” Wartzman v. Hightower Prods., Ltd., 53 Md. App.

656, 667, 456 A.2d 82 (1983) (citation omitted). In light of

HSU’s estimate that the cost to complete the work in 2019

would have been over $800,000, it would be unreasonable

to require Holton to immediately expend such a large

amount of money to mitigate its damages, especially once

it became clear that funds would be needed for litigation.

Additionally, HSU did not present evidence indicating

that Holton could have predicted the steep rise in the cost

of construction a year before the Covid-19 pandemic. In

Blumenthal Kahn Elec. Ltd. P’ship. v. Bethlehem Steel

Corp. , this Court stated:

It is axiomatic that, before the doctrine of

mitigation of damages or avoidable consequences

will operate to impose a duty upon a plaintiff to

minimize a loss that he has incurred by virtue of

the defendant’s breach of contract, the plaintiff

must be aware that he has sustained a loss; to

require a plaintiff to mitigate damages that he

does not know he has suffered would be patently

unreasonable.

120 Md. App. 630, 644, 708 A.2d 1 (1998). We see nothing

in the record to support any argument that Holton could

have reasonably predicted that deferring corrective

50a

Appendix B

work until the following summer would have resulted in

a substantial increase in costs. Holton’s delay in hiring

another contractor to complete the work does not amount

to a failure to mitigate.

CONCLUSION

For the reasons stated, we shall modify the judgment

in favor of Holton by removing the cost of the moving

services, thereby reducing the award to $2,555,553.85,

and affirm the judgment as modified.

JUDGMENT OF THE CIRCUIT COURT FOR

MONTGOMERY COUNTY MODIFIED IN

ACCORDANCE WITH THIS OPINION AND

AFFIRMED AS MODIFIED. CLERK OF

THE CIRCUIT COURT FOR MONTGOMERY

COU N T Y TO EN TER A REVISED

JUDGMENT IN FAVOR OF APPELLEE

IN THE AMOUNT OF $2,555,553.85. IN

LIGHT OF THE RELATIVELY MINIMAL

REDUCTION IN THE DAMAGES AWARD,

COSTS ARE TO BE PAID BY APPELLANT.

51a

Appendix

C OPINION OF THE

APPENDIX C — TRIAL

COURT

CIRCUIT COURT FOR MONTGOMERY COUNTY,

MARYLAND FILED OCTOBER 12, 2022

CIRCUIT COURT FOR

MONTGOMERY COUNTY, MARYLAND

50 Maryland Avenue

Rockville, Maryland 20850

Main: 240-777-9400

Case Number: 472329V

HSU CONTRACTING LLC VS. HOLTON-ARMS

SCHOOL INC, ET AL.

MEMORANDUM AND ORDER

This construction contract matter was tried between

February 28, 2022 and March 18, 2022 before the

undersigned member of the bench. At the conclusion

of Plaintiff’s case, and upon the Defendants’ motions,

the Court entered judgment against Plaintiff on its

claims for fraud, intentional misrepresentation, tortious

interference with contract, tortious interference with

prospective advantage, negligent misrepresentation,

and unjust enrichment, which also discharged Capital

Projects Management Firm, LLC as a defendant. At

the conclusion of trial, three counts remained in dispute:

(1) Plaintiff’s claim for breach of contract; (2) Plaintiff’s

conversion claim; and (3) the Defendant Holton-Arms

School’s claim for breach of contract. At the conclusion

of trial, the Court requested that counsel for each party

52a

Appendix C

submit “Proposed Findings of Fact and Conclusions of

Law” based upon the evidence presented. After review

of the extensive testimony, admitted exhibits, credibility

of the witnesses, arguments of counsel, and post-trial

submissions, the court has chosen to adopt, in full or in

part, with additions as necessary, many of the proposals

submitted by counsel.

INTRODUCTION

A major construction project is a difficult and

complex task that requires large amounts of manpower,

equipment, supervision, coordination, and communication.

To successfully complete the project in a timely manner,

a general contractor is necessar y to coordinate,

supervise, evaluate, adapt to changes, and ensure quality

performance. A good relationship between the owners of

the property upon which the project is to be completed

and the general contractor is crucial. That relationship

is governed by a contract. The standard contract 1

incorporates many provisions used by the construction

industry and familiar to experienced construction firms.

The parties may negotiate or modify those terms as

they reach the agreement that is ultimately executed by

the parties. The contract may incorporate many other

documents including but not limited to accepted bid

proposals, specifications, and drawings to be used and

relied upon by both parties. Recognizing the need for

flexibility and modification, construction contracts provide

1. American Institute of Architects A101-2007 (Standard Form

of Agreement Between Owner and Contractor).

53a

Appendix C

a process by which the parties can communicate, consult,

make changes to the scope of work and product selections,

and deal with unforeseen circumstances. Communication

under a contract or agreed protocol may occur through

requests for information (RFI), submittals for equipment,

submitted change orders, or bulletins issued by the

architect, engineers or other agents engaged by the

owners. Construction contracts may include “time is of

the essence” provisions, set strict timelines for tasks to be

completed and specify penalties for non-timely completion.

However, as the result of communications between the

parties or other circumstances during the construction

process, there may be a delay that compromises the

contractor’s ability to meet the time requirements of

the project. In that event, a contract may provide for

the contractor to submit a “change order” as to the time

requirements. Then a dialogue may ensue between the

parties for the owner to approve or deny the requested

change. Without such an opportunity for resolution

initiated by an aggrieved party, frustrations fester and

the relationship critical to success in a construction

project sours. Once there is a loss of faith in either party’s

performance, conflict arises that may end the contractual

relationship.

FINDINGS OF FACT

Project Background and Key People

1.

The Holton-Arms School (Defendant) is an

independent college-preparatory school which

educates girls and young women in grades 3

54a

Appendix C

through 12. It is located at 7303 River Road in

Bethesda, Maryland.

2.

Susanna Jones (“Jones”) serves as the Head of

School, Tracey Fudge (“Fudge”) as the Director

of Finance and Operations, Michael Joyce

(“Joyce”) as the Director of Facilities, Steve

Bilyeu (“Bilyeu”) as the Facilities Manager of

Engineering, and Carlee Dietterick (“Dietterick”)

as the Assistant Director of Facilities.

3.

In 2017, Defendant identified the need for capital

improvements to its existing school buildings

(the “Project”). The single Project had several

components, including the “Lower School

Renovation” and the “Middle and Upper School,

Central Plant & HVAC Replacement.”

4.

Defendant engaged Capital Project Management

Firm (“CPMF”) as its project manager/owner’s

representative. CPMF was led by Robert “Bob”

Waechter (“Waechter”). Cox Graae + Spack

(“CGS”) was engaged as the Architect (with

the team of William Spack, Tom Wheeler, and

Julianna von Zumbusch – “von Zumbusch”),

and Engenium Group LLC as the mechanical,

electrical, and plumbing (“MEP”) Engineer

(Architect and MEP, collectively, the “Design

Team”).

55a

Appendix C

5.

A general contracting company, HSU Contracting,

LLC (“Plaintiff’)2, subsequently received a formal

“Invitation to Bid” dated December 22, 2017, on

Defendant’s Request for Proposal “RFP”. The

RFP was for two (2) standalone projects: 1) a

Lower School renovation; and 2) a modernization

of the H VAC system and replacement of

mechanical equipment. According to the RFP,

Defendant was to obtain the construction building

permit from Montgomery County Department

of Permitting Services after a 70-day review

process and would have the permit issued on or

before March 30, 2018. The RFP construction

documents/drawings dated December 12, 2017,

and the Invitation to Bid (collectively the “RFP

documentation”), called for two separate projects

to be performed as “design-bid-build” during the

summer of 2018. However, further discussion

led to the understanding that it would be more

efficient to have the two standalone projects

be treated and worked as one project. Plaintiff

was not to do any design work on either of these

projects.

Pre-Contract Conduct of the Parties

6.

In late 2017 and early 2018, the Defendant issued

an RFP and obtained proposals from general

contractors. Defendant sent the RFP to Plaintiff

2. HSU Development, HSU Contracting, LLC and DMI all

exist under the umbrella of “HSU Builders”.

56a

Appendix C

based upon its extensive history with Plaintiff’s

principals. Also, members of Plaintiff’s staff had

children who attended Holton, were donors and

legacies of Holton, and Plaintiff’s principals had

been instrumental on various Holton boards and

committees. In 2012, Plaintiff had completed

a similar summer work project for Defendant

exceeding $4,000,000.

7.

This RFP included bid documents such as

detailed drawings and specifications prepared by

the Design Team. Design development drawings

were also provided to Plaintiff and other potential

bidders in November of 2017. The RFP also

included a preliminary milestone schedule.

8.

Prior to submitting a proposal, Plaintiff requested,

and was granted, access to the Lower and

Middle/Upper School buildings to survey existing

conditions and gather information to factor into

its bid, and to evaluate the dates proposed in

the RFP for Substantial Completion. Plaintiff

and its Project Manager, Terry Edmondson

(“Edmondson”), began inspecting the school in

late 2017 and early 2018. This included inspecting

concealed work and providing feedback to the

Defendant for use in preparing drawings and

specifications. The Design Team also responded

to requests for information (“RFIs”) from

Plaintiff to address outstanding questions about

the Project.

57a

Appendix C

9.

Plaintiff submitted a proposal dated January

22, 2018, signed by Sean Frazier (“Frazier”),

Plaintiff ’s SV P of Commercial Inter iors.

Plaintiff’s proposal included an organizational

chart identifying Walter Hsu as the President of

HSU Builders. The proposal also indicated that

Plaintiff’s executive team for the Project would

include Frazier and Edmondson, and that the

project team would include Scott Clegg (Senior

Project Manager), Connor Sullivan (“Sullivan”)

(Assistant Project Manager), and Mark Johnson

(Senior Superintendent). 3

10. Plaintiff’s proposal stated that it “provides the

project and subcontractors with CPM scheduling

(which becomes part of their contract)” and that

Plaintiff would use both updated CPM schedules

and 3-week lookahead schedules to manage

the project. The proposal included a proposed

construction schedule developed by Edmondson.

11. CPM refers to critical path method scheduling,

which involves a mathematical representation of

a construction project. The tasks in the schedule

are linked together with logic and calculate the

latest dates or time that an activity can finish

based on all the subsequent activities. Expert

testimony established that only construction

work on the critical path has an impact upon the

3. Frazier and Edmondson both left HSU at the end of 2018,

and neither Scott Clegg nor Mark Johnson worked on the Project.

58a

Appendix C

time in which the project is completed. If work

on the critical path is delayed, then the eventual

completion date of the project is delayed. Delay

involving work not on the critical path generally

has no impact on the eventual completion date of

the project.

12. CPM scheduling is in fact “critical” because

it is the best way to determine the effects of

delayed tasks upon the whole project. The

process of determining such effects is “critical” to

calculating damage to the project, both temporal

and monetary. The CPM Schedule is “critical”

in that it provides a clear view of the level of

coordination required by the general contractor

for all trades and sub-contractors to get the tasks

completed timely.

13. Plaintiff represented in its bid proposal that

because of its previous experience with Holton,

Plaintiff was familiar with restrictions on when

construction could be performed at the school due

to the school schedule or students and teachers

in the buildings.

14. Plaintiff represented that it would use Procore,

“a cloud-based construction project management

software” and provide its field teams with tablets

“to access information when needed in real time.”

Much of the work for submittals, RFI (Requests

for Information) and other communication during

the Letter of Intent (“LOI”) period (infra.) was

59a

Appendix C

accomplished utilizing Plaintiff’s subscription

to Procore Project Management Software

(“Procore”), with access provided to Plaintiff’s

subcontracting team, CPM (Defendant’s agent),

Defendant’s employees, Defendant’s AE Team,

and Defendant’s commissioning agent. This

software provides real time project status and

allows for facilitation of communication and

access to information.

15. While negotiating the Contract, the parties

executed a LOI on February 27, 2018, authorizing

the release of up to $2 million to ensure that

Plaintiff could start work on the project. The LOI

authorized Plaintiff to proceed with the buyout

of subcontractors, processing of submittals,

preparing the contract schedule and establishing

project logistical planning, and purchasing long

lead equipment. Plaintiff agreed in the LOI that

the work on the Lower School Renovation would

be completed by August 24, 2018, before the start

of the 2018-2019 school year.

16. On Febr uar y 2 8, 2018, Plaintiff issued a

Notice to Proceed (“NTP”) to Kent Island

Mechanical (“KIM”), its mechanical and plumbing

subcontractor on the Project. The President

of KIM is Mark Bowen (“Bowen”). Will Koch

(“Koch”) was assigned as KIM’s project manager.

The NTP provided for a limited release amount of

$1. 1 million so that KIM could begin to furnish

submittals and procure equipment. Shortly

60a

Appendix C

thereafter, KIM began working onsite to survey

the mechanical scope. KIM had unfettered access

to the school over spring break, starting March

12, 2018, when students were not on campus.

Despite the February NTP, KIM did not sign a

contract with Plaintiff ($4,223,000) until August

2, 2018, almost two months after the parties’

contract was signed.

17. In the spring of 2018, Plaintiff issued additional

RFIs seek ing cla r i f ication or additiona l

information from the Design Team. The Design

Team also issued pre-contract bulletins with

revisions to the drawings based on comments

from the County during the permitting process.

These bulletins were incorporated into the

Contract that was later signed.

18. Plaintiff hired Russell Fitzgerald (“Fitzgerald”)

to start May 1, 2018, as superintendent for

the Project. Fitzgerald was not named in the

organizational chart provided by Plaintiff in its

bid proposal. Defendant was not consulted about

this change in personnel and expressed concerns

about having a superintendent without prior HSU

experience.

19. In May 2018, Sullivan received a call from the

project engineer informing him “that the first

four submittals [from NOVA, Plaintiff’s electrical

contractor] he had reviewed were all rejected,

one of which had already been rejected once

61a

Appendix C

prior” and that the project engineer wanted

to have a call with NOVA, to discuss submittal

expectations.

20. The building permit for the Project was issued on

June 4, 2018, prior to the Contract being signed.

Defendant was supposed to have obtained the

building permit by March 30, 2018. However,

Montgomery County “denied” approval of

the permit on 10 separate occasions. Denial

of a permit is not unusual as many times the

multiple levels of review request modifications

to the original application. Therefore, the permit

application is returned/denied for there to be

modifications made to the application. Contrary

to Plaintiff’s argument that the delay by the

Defendant in obtaining the building permit

caused a significant delay in Plaintiff’s going

forward, Stephen Smith, Plaintiff’s Director

of Operations, admitted that the failure by the

owner obtaining a building permit until June

5, 2018 did not delay their performance. Even

though some trade permits were not obtained per

the Plaintiff’s schedule by June 8, 2018, Smith

noted that trades can commence work without

trade permits, even on HVAC.

21. Beginning in March 2018, after bid submission

and prior to execution of the Contract, there were

30 RFIs submitted by Plaintiff and CGS issued

11 bulletins. These communications and the

responses had some impact on scheduling, work

62a

Appendix C

sequencing, and costs. According to Plaintiff,

Defendant’s bulletins and responses to RFIs

resulted in major redesigns and represented

significant construction changes. According to

Plaintiff, Defendant’s bulletins and responses

to RFIs impacted project cost, permitting, and

construction schedules to an extent that was

beyond the ordinary course of a construction

project and that indicates a deficiently designed

and under-developed project. However, Plaintiff

executed the Contract with full knowledge of

Defendant’s bulletins and responses to RFIs.

Plaintiff, with the full ability to negotiate the

yet unexecuted contract, did not seek to extend

deadlines or Substantial Completion dates or alter

the previously submitted schedules. Even after

executing the Contract, which provides a formal

procedure for requesting schedule adjustments,

Plaintiff did not utilize that procedure to seek

extensions of time from the Defendant.

Negotiation and Execution of the Contract4

22. Following months of negotiations and almost

immediately after the building permit issued,

the parties executed the Contract on June

5, 2018. The Contract defined the singular

Project as the “Central Plant Equipment &

4. This opinion references 4 documents containing relevant

provisions of the parties’ agreement: Project Specifications

(Appendix A), Modified A101-2007 (Appendix B), Modified A201-2007

(Appendix C), and Additional Provisions (Appendix C).

63a

Appendix C

HVAC Systems Replacement and Renovation

of the Lower School,” with interim Substantial

Completion Dates of August 24, 2018 for the

Lower School Renovation and August 25, 2018

for the Middle and Upper School Central Plant

& HVAC Replacement. The Overall Substantial

Completion date for the Project was March 1,

2019.

23. The Contract was executed by the parties for

the total stipulated sum of $6,522,722 (“Contract

Sum”) subject to adjustments for Alternates. With

those approved adjustments, the Contract Sum

increased to $6,928,309 subject to subsequent

increases for approved change orders.

24. The Contract is a heavily modified form of

American Institute of Architects A101-2007

(Standard Form of Agreement Between Owner

and Contractor), together with a heavily modified

form of A201-2007 (General Conditions). The

Contract incorporated Plaintiff’s RFP Revised

Response dated January 30, 2018, Conditions

of the Contract (General, Supplementary, and

other Conditions), Drawings, Specifications,

Addenda issued prior to execution of the

Contract, and detailed schedules setting forth

dates for Substantial Completion as defined by

the Contract.

25. The Contract required Plaintiff, as the Contractor,

to “furnish only skilled and properly trained

64a

Appendix C

staff,” and identified key personnel for the

Project, which could not be changed without the

written agreement of the Defendant. Appendix

B §2.2. These personnel included Frazier (SVP/

Project Executive), Edmondson (SVP/Sr. Project

Manager), Sullivan (Assistant Project Manager),

Fitzgerald (Senior Superintendent), and a to-bedetermined assistant project manager and area

superintendent.

26. Fudge, Holton’s Director of Finance and

Operations, was designated as the Defendant’s

representative for purposes of legally binding

the Defendant (Appendix B § 8.3) and CPMF was

designated as the Defendant’s representative for

administering the Contract. Id. § 8.3.1.

27. Plaintiff was afforded early access to the school

in connection with the RFP process and the

LOI. Plaintiff signed the Contract with the

representation that “Execution of the Contract

by the Contractor is a representation that the

Contractor has visited the site, become generally

familiar with local conditions under which the

Work is to be performed and correlated personal

observations with requirements of the Contract

Documents.” APPENDIX C § 3.2.1.

28. Plaintiff, through Frazier, acknowledged it was

already three months behind when it signed the

Contract on June 5, 2018, because it had not been

able to mobilize on site in March based on the

preliminary schedule. Frazier testified that he

65a

Appendix C

was aware that the contract schedule referenced

in the LOI might vary from the preliminary

schedule, and that he agreed to the Substantial

Completion deadlines when he signed the

Contract on June 5, 2018. Also, Frazier agreed

that the Contract time from June to August 24,

2018 was reasonable.

Contract Provisions Relevant to Dispute5

Substantial Completion and Time of the Essence

Schedule

29. The date of commencement was June 8, 2018 for

the Lower School Renovation and August 4, 2018,

for the Middle and Upper School, Central Plant

& HVAC Replacement. APPENDIX B § 3. 1.

Consistent with the LOI, Plaintiff agreed in the

Contract that (1) the Lower School Renovation

would need to reach Substantial Completion

by August 24, 2018, (2) the Middle and Upper

School, Central Plant & HVAC Replacement

would need to reach Substantial Completion

by August 25, 2018, (3) the overall Project

would need to reach Substantial Completion by

March 1, 2019, and (4) time was of the essence in

meeting these dates.6 By executing the Contract,

5. Complete language of the provisions appears in the

Appendices attached hereto.

6. Because there were limited times during which work could

be performed so as to not interfere with the operations of the school,

the parties included a liquidated damages provision for failure to

achieve Substantial Completion by the stated dates.

66a

Appendix C

Plaintiff also confirmed that the Contract Time

was “a reasonable period for performing the

Work,” (APPENDIX C § 8.2.1) and that it would

“proceed expeditiously with adequate forces and

shall achieve Substantial Completion within the

Contract Time.” APPENDIX C §8.2.3. Plaintiff

warranted that it was “able to furnish the plant,

tools, materials, supplies, equipment and labor

required to complete the Work and perform

its obligations hereunder and has sufficient

experience and competence to do so.”

30. “The Work w[ould] not be considered suitable

for Substantial Completion review until all

Project systems included in area of the Work

are operational as designed and scheduled,

all designated or required gover nmental

inspections and cer tifications, including

certificates of occupancy, have been made and

posted, designated instruction of the [School’s]

personnel and the operation of systems and

equipment completed, and all final finishes

within the Contract Documents are in place.

In general, the only remaining Work shall be

minor in nature, so that the [School] can occupy

the portion of the building on that date for its

intended use and the completion of the Work

would not materially affect, or hamper the

normal business operations or intended use of

[the School].” APPENDIX C § 9.8.1.1.

67a

Appendix C

31. The date of Substantial Completion would be the

date certified by the Architect in accordance with

Section 9.8. APPENDIX C § 8.1.3.

32. At the time of Substantial Completion, Plaintiff

was to assign all manufacturer’s warranties

related to materials and labor. APPENDIX C

§ 3.5.2.

33. Plaintiff was obligated to prepare and submit a

construction schedule for the work to “be revised

at appropriate intervals as required by the

conditions of the Work and Project.” APPENDIX

C § 3.10.1.

34. Plaintiff was obligated to use a detailed CPM

schedule showing the requisite interdependence

of activities and sequence of work, with any “float”

accruing to Defendant’s benefit.7 APPENDIX A

Section 013216 - 4.04. Plaintiff was also obligated

to submit an updated CPM schedule with each

application for payment. APPENDIX D § B.2.10.

35. Plaintiff was required to prepare a submittal

schedule 8 promptly after being awarded the

7. “Float” is the amount of days an activity may be delayed

before the overall project is delayed. Usually activities on the critical

path have zero float. Put another way, any delay to a critical activity

will cause a delay to the project’s end date.

8. A submittal schedule contains dates on which the submittals

for the project will be issued and allows the architect to effectively

68a

Appendix C

Contract and submit the schedule for the

Architect’s approval. “If [HSU] fails to submit a

submittal schedule, [HSU] shall not be entitled

to any increase in Contract Sum or extension of

Contract Time based on the time required for

review of submittals.” APPENDIX C § 3.10.2.

36. Plaintiff’s sole and exclusive remedy for any delay

was an extension of time in which to complete

the work. Direct out-of-pocket costs associated

with the delay were only permissible when the

delay was caused solely by Defendant, with no

other “remedy or compensation or recovery of

any damages” permitted. APPENDIX C § 8.3.3.

Claims relating to time were to be made in

accordance with Article 15, with any extension of

the contract time memorialized by change order.

APPENDIX C § 8.3.2.

Change Orders and Claims Provisions Expressly Bar

Alleged Course of Conduct Arguments

37. A change order required agreement among the

Defendant, Plaintiff and the Architect. “[A]

change in the Contract Sum or Contract Time

shall only be accomplished by Change Order.

Accordingly, no course of conduct or dealings

between the parties, nor express or implied

acceptance of alterations or additions to the

manage its work so it can handle and address the submittals and

return those in accordance with the contractor’s submittal schedule.

69a

Appendix C

Work, and no claim that the [School] has been

unjustly enriched by any alteration or addition

to the Work, whether or not there is, in fact,

any unjust enrichment, shall be the basis of any

claim to an increase in any amounts due under

the Contract Documents or a change in any time

period provided for in the Contract Documents.”

APPENDIX C § 7.1.2.

38. The Change Order amounts were to be “inclusive

of any and all General Conditions costs.”

APPENDIX C § 7.2.3.

39. A claim for additional money or an extension of

time had to be made in writing within 21 days

of the occurrence of the event giving rise to the

claim. APPENDIX C § 15.1.2.

40. A claim for an increase in the contract sum

required written notice before proceeding with

the Work. APPENDIX C § 15.1.4.

Waiver Arguments Barred Under the Contract

41. The Contract contained multiple provisions

addressing waiver, including the no waiver

provision discussed above with regard to change

orders. APPENDIX C § 7.1.2.

42. The Contract also stated that “[t]he failure

of the either party to insist upon the strict

performance of any provision of this Agreement,

70a

Appendix C

or the failure of either party to exercise any

right, option or remedy hereby reserved, shall

not be construed as a waiver in the future of

any such provision, right, option or remedy or

as a waiver of a subsequent breach thereof. The

consent or approval by the Owner of any act by

the Contractor requiring the Owner’s consent or

approval shall not be construed to waive or render

unnecessary the requirement for the Owner’s

consent or approval of any subsequent similar act

by the Contractor. The payment by the Owner of

any amount due hereunder with the knowledge

of a breach of any provision of this Agreement

shall not be deemed a waiver of such breach. No

provision of this Agreement shall be deemed to

have been waived unless such waiver is in writing

signed by the party to be charged.” APPENDIX

B § 8.6.1.0.

43. “No action or failure to act by the Owner,

Architect or Contractor shall constitute a waiver

of a right or duty afforded them under the

Contract, nor shall such action or failure to act

constitute approval of or acquiescence in a breach

there under, except as may be specifically agreed

in writing.” APPENDIX C § 13.4.2.

Plaintiff’s Sole Responsibility for Means and Methods

and Coordination

44. Plaintiff had sole responsibility for “construction

means, methods, techniques, sequences and

71a

Appendix C

procedures and for coordinating all portions

of the Work under the Contract” and was

responsible for supervising and directing the

Work. APPENDIX C §§ 2.5, 3.3.1, 4.2.2.

45. Plaintiff was required “to provide professional

ser v ices t hat const it ut e t he pra c t ice of

architecture or engineering” if “such services are

specifically required by the Contract Documents

for a portion of the Work or unless [HSU] needs

to provide such services in order to carry out

[HSU’s] responsibilities for construction means,

methods, techniques, sequences and procedures.”

APPENDIX C § 3.12.10.

46. Pla i nt i f f wa s responsible for p repar in g

coordination drawings prior to the preparation of

shop drawings.9 The failure to submit coordination

drawings waived “claims for additional costs

associated with relocation of fixtures, equipment,

and appurtenances.” APPENDIX A Section

013100 - 1.02.B.1.

47. “By submitting Shop Draw ings, Product

Data, Samples and similar submittals, [HSU]

represent[ed] to the [School] and Architect that

[HSU] ha[d] (1) reviewed and approved them,

(2) determined and verified materials, field

9. Koch testified that coordination drawings are used to

uncover “potential conflicts between trades of installation and it’s

an effort to avoid conflicts.”

72a

Appendix C

measurements and field construction criteria

related thereto, or will do so and (3) checked

and coordinated the information contained

within such submittals with the requirements

of the Work and of the Contract Documents.”

APPENDIX C § 3.12.6.

Plaintiff Substitutions

48. In making a request for a substitution, Plaintiff

represented that it had investigated the proposed

product and that it was equal or superior to that

which was specified. APPENDIX C § 3.4.2.

49. A request for a substitution also constituted a

representation that Plaintiff would “coordinate

installation of the substitute” and “mak[e] such

changes as may be needed for Work to be complete

in all respects.” It included a waiver of “claims

for additional costs which subsequently become

apparent.” APPENDIX A Section 016300.

Quality of Work

50. Plaintiff was required to perform the work

in accordance with the contract documents.

APPENDIX C § 3.1.2.

51. Plaintiff warranted that the materials and

equipment would be of good quality and that the

work would conform to the contract documents

and be free from defects. APPENDIX C § 3.5.

73a

Appendix C

52. Plaintiff was responsible for all cutting, fitting,

and patching and was obligated to restore all

areas to the condition existing prior to the

cutting, fitting, and patching. APPENDIX C

§ 3.14.1.

Site Maintenance

53. Plaintiff was obligated to keep the site in an

orderly and clean state (APPENDIX C § 3.15.1,

APPENDIX D §§ B.2.21, B.3.15) and protect the

work and adjacent structures from damage until

acceptance by Defendant. APPENDIX D § B.2.8.

54. All personnel working on site were required to

undergo a background check. Extensions would

not be granted for Plaintiff’s failure to obtain

background checks for any worker, which were

estimated to take two weeks. APPENDIX D

§ B.3.2.

55. Plaintiff was required to maintain daily reports

at the site that included specific information on

manpower, weather, and work performed each

day. APPENDIX D § B.3.7.

Payment Applications and Retainage

56. The issuance of a certificate for payment did not

constitute “a representation that the Architect

ha[d] ... made exhaustive or continuous on-site

inspections to check the quality or quantity of

74a

Appendix C

the Work.” APPENDIX C § 9.4.2. A certificate

for payment or partial or entire use or occupancy

of the Project also did “not constitute acceptance

of Work not in accordance with the Contract

Documents.” APPENDIX C § 9.6.6.

57. The payment applications contained language

indicating that payment was made without

prejudice to any rights of Defendant under the

Contract.

58. Defendant had the right to withhold retainage

of “ten percent (10%) of the Contract Sum as is

necessary to protect [the School] against claims

or if the Work is unsatisfactory or not progressing

properly.” APPENDIX B § 5.1.8.

Termination for Cause

59. Defendant could terminate the Contract for

cause if Plaintiff (1) repeatedly refused or failed

to supply enough properly skilled workers or

proper materials; (2) failed to make payment

to Subcontractors for materials or labor in

accordance with the respective agreements

between Plaintiff and the Subcontractors; (3)

repeatedly disregarded applicable laws, statutes,

ordinances, codes, rules and regulations, or lawful

orders of a public authority; or (4) otherwise was

guilty of substantial breach of a provision of the

contract documents. APPENDIX C § 14.2.1.

75a

Appendix C

60. After receiving certification from the Architect

that sufficient cause existed to justify termination,

Defendant could, upon seven days’ written notice,

terminate Plaintiff’s employment and (1) exclude

Plaintiff from the site and take possession of all

materials, equipment, tools, and construction

equipment and machinery thereon owned by

Plaintiff; (2) accept assignment of subcontracts

pursuant to Section 5.4 (APPENDIX C); and (3)

finish the Work by whatever reasonable method

the school may deem expedient. APPENDIX C

§ 14.2.2.

61. Upon a termination for cause, Plaintiff was not

entitled to receive further payment until the work

was finished. APPENDIX C § 14.2.3. If the costs

and damages incurred by Defendant exceed the

unpaid balance, Plaintiff must pay the difference

to Defendant. APPENDIX C § 14.2.4.

Plaintiff’s Performance During Summer 2018

62. From the start of demolition in June 2018, just

days after the parties signed the Contract,

Defendant encountered problems with Plaintiff’s

performance. At this time, Frazier was also

overseeing multiple other projects for Plaintiff.

63. During this time, the issue of inadequate

manpower to complete tasks was identified.

Pla i nt i f f ’s Sen ior Vice P resident (S V P),

Edmondson, wrote to subcontractor Tammal

76a

Appendix C

“Your trades need more manpower so we can

try to stay on schedule.” The SVP wrote to

subcontractor Nova “As you know we failed the

electrical ceiling inspection today because of

lights not being tied up and open junction boxes.

I asked Will about additional manpower after

looking at our sign-in sheet and noticed 2 men less

today....... We need more manpower. I was over

at Holy Child and saw 6 of your men on that site

working for Boland. Can you please get us a few

men as Will [KIM] is saying unless he has more

manpower, he won’t be ready by this weekend.”

64. Plaintiff’s proposal represented that all of the

workers on the project would be fingerprinted

and have been background checked. Joyce

testified that on the first day of demolition, many

of the people who showed up to work had not

gone through background checks or had to be

turned away because their background checks

were not approved. As a result, Plaintiff had less

manpower than needed to meet the schedule,

leading to delays which were a persistent issue

throughout the summer.

65. Koch testified that Plaintiff did not submit

coordination drawings for the DOAS10 units, and

that he did not know what Plaintiff did with the

10. DOAS stands for “dedicated outdoor air system.” It is a

type of heating, ventilation and air-conditioning system that consists

of two parallel systems: a dedicated system for delivering outdoor

air ventilation and a parallel system to provide heating and cooling.

77a

Appendix C

shop drawings KIM prepared. He acknowledged

that coordination drawings were required by

the Contract, and that it was “concerning” that

Plaintiff, as the general contractor, was not

following the Contract procedures.

66. Plaintiff failed to coordinate installation of the

fan coil units (FCUs), leading to conditions where

“right-handed” units were connected on the left

side (wrong side) and vice versa, requiring extra

piping along the exterior wall. As with DOAS

units 6 and 7, Plaintiff and KIM substituted

Trane for the Daikin basis of design. No one

informed Defendant that the units were smaller.

These coordination issues were not isolated and

continued throughout construction.

67. Both Joyce and Fudge testified about a significant

lack of protection on the Project, which resulted

in damage to the existing facilities. At one point,

for example, a worker had placed a fan coil panel

against the drinking fountain, causing water to

run and flood into the library, where it caused

mold in the carpet and wood panels. Furniture

and books in the library were not adequately

protected from dust and debris of construction

as required by the Contract.

68. On July 3, 2018, Edmondson told Defendant that,

in response to Defendant’s concerns, they had

“since put a full court press on protection and

understand the importance of this activity as

78a

Appendix C

well as staying on schedule.” However, one month

later, on August 7, 2018, Plaintiff’s employee,

Erich Millar (Millar), acknowledging manpower

issues wrote: “I agree protection is needed

but who, what army can we get to lay all this

protection?????”

69. Plaintiff had significant performance problems

over the summer of 2018 with its electrical

subcontractor, NOVA, related to “Nova’s inability

to provide approved electrical submittals and

failure to order the lighting package per the

contract which will delay the schedule.” As

a result, Plaintiff sent a “Notice to Cure” to

NOVA. The work performed by NOVA was

non-conforming to the contract, defective and

incomplete such that Plaintiff subsequently

terminated its sub-contract with NOVA for cause.

70. These coordination issues impacted Plaintiff’s

ability to maintain the schedule. SVP Edmondson

told KIM “We have zero chance of making this

happen [re: the equipment pads needed to place

the boilers and domestic hot water heaters]”

because of late notice by Plaintiff. Koch told

Plaintiff in an email that KIM could not complete

its scope of work because Plaintiff had not yet

completed necessary predecessor activities.

71. During this time, Waechter told Plaintiff to “do

what they needed to do” to get the girls in school

on time as required by the Contract schedule.

79a

Appendix C

72. As the result of Plaintiff being three months

behind at the execution of the Contract, Plaintiff

stated there was a need to “compress time

schedules and accelerate” the construction work

to meet the August 24, 2018, Opening Day for

Holton. However, compression and acceleration

does not mean toleration or acceptance of poor

workmanship and failure to meet contract

specifications. Plaintiff did not maintain daily

logs and manpower reports, nor did it maintain

consistent records of the subcontractors on site.

73. KIM, Plaintiff’s main sub-contractor, provided

Defendant with a list documenting the deficiencies

in Plaintiff’s performance. Those deficiencies,

which include lack of coordination, supervision,

support staff, and protection for the job site,

delayed KIM’s work 3 weeks during the summer.

74. The “time crunch” to get the scheduled work

done by Opening Day resulted in a suspension

of the formal change order process, which was

replaced by a temporary agreement between

the parties. They agreed that if change requests

were approved, then issues of “Extended General

Conditions” (profit margin per contract allowed

to Plaintiff) or credits would be worked out by the

parties later. The 21-day deadline for submitting

change orders/claims per the Contract was not

enforced by Defendant until a series of disputes

occurred in late 2018 into 2019.

80a

Appendix C

75. Plaintiff contends that one of several long lead

items (for example, door and door frames) caused

delay during the summer due to Defendant’s

changing the doors from metal to wood as late as

June 11, 2018. It could take as long as 15 weeks

to fabricate the doors for use in the project.

Defendant’s architect admitted that a drawing

error showed the doors as metal instead of wood.

However, Plaintiff’s submittals for such long lead

items were supposed to be provided at least two

months prior to the time Plaintiff submitted the

item for approval in May 2018. Plaintiff paid

to expedite the fabrication of the doors and

Defendant accepted those costs.

76. To save time during this period, Plaintiff

suggested using spray foam insulation in the attic

area instead of batten insulation that required

more time and manpower. Defendant approved

the change. However, the submission included

that a fire-retardant sealant be applied to the

foam as a safety measure. Plaintiff never applied

the sealant.

Opening of Holton-Arms School

77. Plaintiff failed to achieve Substantial Completion

of the Lower School Renovation by August 24,

2018 and tum that portion of the school over to

Defendant in time for the students’ return from

the 2018 summer recess. This forced Defendant

to temporarily place the students in “the library,

81a

Appendix C

the theater, a dance studio, and a couple of other

classrooms and common spaces to house classes

for the first three days” until Plaintiff made the

Lower School provisionally accessible to students

and faculty. Even in areas made provisionally

accessible, Plaintiff’s work remained defective

and far from Substantially Complete as defined

by the Contract.

78. In September 2018, a Certificate of Occupancy

was issued to Defendant. The issuance of the

Certif icate of Occupancy to Holton-A rms

School does not establish and is not a substitute

for Substantial Completion as defined in the

Contract.

79. On September 4, 2018 (the date classes began),

Waechter contacted Edmondson and Fitzgerald

to express concerns about the cleanliness of the

Project site, the fact that classrooms were not

ready for move-in, and a list of defective and

incomplete work. He stated that “it is imperative

that HSU to [sic] provide the coordination,

management and sufficient manpower to complete

the work in accordance with the schedule.”

80. On September 5, 2018, Waechter contacted Walter

Hsu telling him that “We need to talk as soon as

possible, you have two cleaners, one electrician

and seven mechanical contractors on site today.

This is completely unacceptable. The classrooms

have construction materials and dirt in them, the

82a

Appendix C

school still cannot move in fully and the areas

that were supposed to be turned over for move

in today have not changed since Saturday. We

need HSU to step up or step aside, the school

can no longer continue with a consistent lack of

performance.” Walter forwarded this message to

Edmondson, Frazier, and Smith.

81. Later that day, Waechter sent to Walter Hsu and

the Plaintiff’s team another email listing numerous

issues related to the status of construction,

including the incomplete storefront, the fact that

construction materials and tools had been left in

the courtyard, the wires hanging from the ceiling

in the maintenance area, the incomplete offices.

There were also electrical issues throughout the

school. The incomplete storefront presented a

“critical safety and security issue” because the

front doors to the Lower School did not close

properly, could not be locked, and could not be

chained shut due to fire code.

82. Fudge testified about her concerns with the

volume of work remaining by the end of summer.

Her concerns included 1) the volume of work that

was still to be completed and 2) the conditions of

the project over the summer. She believed that

a punch list would deal with minor issues but

that there were major tasks that Plaintiff had

to accomplish. The FCUs all had to be raised in

the hallways to allow them to sit on the flooring

per design. The lighting system didn’t work. The

83a

Appendix C

floor was cupping. There were other defects that

needed to be addressed. Electrical breakers were

tripping through the whole month of September,

and Defendant had to replace breakers multiple

times in September and October.

83. Plaintiff’s lack of diligence and supervision over

the project was called to Plaintiff’s attention from

its own employees. On September 13, 2018, Sarah

Moore Herbst (Plaintiff’s comptroller- “Moore

Herbst”) emailed Plaintiff’s team with concerns.

She stated that the “[o]riginal substantial

completion date was 8/20” and that “[n]o updates

have been made to schedule.” She also stated that

[m]anpower is also not being fully completed”

and that Punch Plus had been “on site working

for quite some time” but weren’t listed in the

manpower log “one time.” She further indicated

that American Cleaning “[n]ever returned a

signed contract for $13,700 and have now billed

over $30,000” and that Alonzo Ours had been

on site working with “[n]o signed contract, no

COI (Certificate of Insurance). This must stop

happening.”11

11. At trial, Moore Herbst was questioned about this email in

which she indicated that Punch Plus had been on site according to

invoices but did not appear on the manpower log once. She was then

shown multiple manpower entries for August and early September

2018 made by Smith reflecting up to ten workers on site for Punch

Plus and acknowledged that these entries would have been made

after September 13, 2018.

84a

Appendix C

84. Based upon Defendant’s numerous concerns

with the quality and timeliness of Plaintiff’s

work, Defendant began looking into potential

replacement contractors because Defendant

“needed to have a back-up if HSU wasn’t able to

get things together to address the deficient work,

to complete the work that had been left undone,

to fix things that weren’t going well, and in case

we decided we had to terminate.” Defendant did

not hide its concerns. Defenda

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.