Petition for Writ of Certiorari — BG Gulf Coast LNG, L.L.C., et al., Petitioners v. Sabine-Neches Navigation District of Jefferson County, Texas
Supreme Court briefFeb 22, 2023
Ask Donna
What actually matters in this document.
Text
APPENDIX
TABLE OF CONTENTS
Page
APPENDIX A—Fifth Circuit’s Opinion
(Sept. 14, 2022) .................................................... 1a
APPENDIX B—District Court’s Order
(Feb. 24, 2022) .................................................... 18a
APPENDIX C—Fifth Circuit’s Order
Denying Rehearing (Oct. 25, 2022) ................... 55a
APPENDIX D—Constitutional and
Statutory Provisions Involved ........................... 57a
APPENDIX E—Complaint Exhibit B –
User Fees Paid by BG Gulf Coast LNG,
LLC ..................................................................... 69a
i
1a
APPENDIX A
_________
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
_______
No. 22-40158
_______
BG GULF COAST LNG, L.L.C.; PHILLIPS 66 COMPANY,
Plaintiffs-Appellants,
v.
SABINE-NECHES NAVIGATION DISTRICT OF
JEFFERSON COUNTY, TEXAS,
Defendant-Appellee.
_______
Appeal from the United States District Court
for the Eastern District of Texas
USDC No. 1:21-CV-470
_______
Filed: September 14, 2022
_______
OPINION
_______
Before STEWART, ELROD, and GRAVES, Circuit Judges.
JENNIFER WALKER ELROD, Circuit Judge:
2a
The Sabine–Neches Waterway is located in the
southeastern-most parts of Texas and the
southwestern-most parts of Louisiana, providing
passage from the Gulf of Mexico to Port Arthur,
Beaumont, and Orange, Texas, and beyond. It is
vitally important to the local, state, and federal
economies. Despite its importance, sixty years have
gone by without much effort to maintain or otherwise
improve it. The Sabine–Neches Navigation District
set out to change that. The price tag on the proposed
improvements totaled roughly $1.1 billion. After some
bureaucratic wrangling, Congress covered most of the
cost with the District left to cover the rest. The
District planned to cover its share through port fees.
But the same federal law that led to congressional
funding also sets limits on how costs can be passed
onto consumers by local entities. Two energy
companies sued the District, claiming that the port
fees exceeded those limits. The district court
concluded that they failed to state plausible claims
and dismissed the case. We AFFIRM.
I.
As waterways here in America go, the Sabine–
Neches Waterway is one of our nation’s most critical.
Not only does it rank near the top in business and
busyness, it is home to the U.S. military’s largest
strategic commercial seaport. But as ships became
larger, the Sabine–Neches Waterway largely stayed
the same. Its lack of depth and width poses a problem
for many modern vessels.
To make the necessary improvements to the
Waterway, the District needed funds. Congress
opened up the federal purse for such projects through
the Water Resources Development Act of 1986, 33
3a
U.S.C. § 2201, et seq. In the years before the Act’s
passage, trying to improve waterways was a
bureaucratic nightmare. See New Orleans S.S. Ass’n
v. Plaquemines Port, Harbor & Terminal Dist., 874
F.2d 1018, 1024–25 (5th Cir. 1989) (digesting the
backstory of the Harbor Development and Navigation
Improvement Act, which was passed as part of the
Water Resources Development Act). It could take up
to twenty-six years from first study to project
completion, with as many as nineteen independent
reviews along the way. Id. When Congress passed and
President Reagan signed the Act, Congress had not
approved a project in nearly two decades. Id. Through
the Act, Congress streamlined the process and came
up with a new way to finance waterway-construction
and -improvement projects. Id. at 1025. Rather than
rely only on the federal fisc, the federal government
would shoulder some or most of the cost and would
share the rest with state and local entities. Id. Plus,
state and local entities had a greater practical interest
in the waterway development, so they were more
likely to get it done faster. Id.
The process begins with a feasibility study by the
U.S. Army Corps of Engineers. Once that is done, it is
published in the Federal Register and the Secretary of
the Army gives it to Congress. Congress then reviews
the study and the projected costs and puts it to a vote.
If it prevails and the President signs it, Congress gives
the local entities money to cover the first phase of the
project (called “new start” funds). The local entities
then enter into a cooperative agreement with the
Army Corps of Engineers covering the project, which
includes “provid[ing] to the Federal Government the
non-Federal share of all other costs of construction of
4a
[the] project.” 33 U.S.C. § 2211(e)(3). See also Air
Liquid Am. Corp. v. U.S. Corps of Engineers, 359 F.3d
358, 361 (5th Cir. 2004) (describing process).
The District prepared for years, but did not formally
begin the Sabine–Neches Waterway Channel
Improvement Project until 2011. The District worked
with the Army Corps of Engineers, and the Corps
completed its study in March of that year. The Corps
concluded that Congress should fund the Project:
deeper waterways means bigger ships which fit more
cargo, which means fewer ships, which means less
congestion. The Secretary of the Army transferred the
Project to Congress, Congress passed it, see Water
Resources Reform and Development Act of 2014, Pub.
L. No. 113–121, 128 Stat. 1193, 1364, § 7002 (2014)
(“WRDA-14”), 1 and President Obama signed it into
law.2 The Project’s price tag was just over $1.1 billion,
with the federal government covering around $748
million and the District just under $366 million. Id.
Congress then appropriated “new start” funds for the
Project to get the ball rolling in 2019. See Energy and
Water, Legislative Branch, and Military Construction
1
Because each new project that goes through this process
requires an act of Congress (literally), the parties refer to each
new act as “WRDA” followed by a two-digit year, e.g., “WRDA14.” They also refer to the 1986 Act (detailed above) as “WRDA86.” For ease of reference, we refer to the 1986 Act as “the Act”
and otherwise refer to any other project-approval act as “WRDA##.”
2
See David Hudson, President Obama Signs the Water
Resources Reform and Development Act, and Honors the
“Borinqueneers,” The White House (June 10, 2014),
https://obamawhitehouse.archives.gov/blog/2014/06/10/presiden
t-obama-signs-waterresources-reform-and-development-actand-honors-borinque.
5a
and Veterans Affairs Appropriations Act, 2019, Pub.
L. No. 115–244, 132 Stat. 2897, 2898–99 (2019). Those
new-start funds would ultimately be used to complete
the first part of the Project: the deepening of
Anchorage Basin No. 1 from twenty feet to forty feet.
The District and the Corps then entered into the
statutorily required agreement. See 33 U.S.C.
§ 2211(e)(3). The Agreement listed the projected cost
at over $1.2 billion (up a bit from WRDA-14), with a
$732 million/$488 million federal–District split
(roughly 60%–40%). That number, of course, was a
projection, and its fluidity becomes relevant later. The
Agreement otherwise detailed the specifics on the
deepening and widening of the Waterway and
outlined the environmental effects of the Project.3
3
“[D]eepening the Sabine Neches Waterway (SNWW) from 40
to 48 feet and the offshore channel from 42 to 50 feet in depth
from offshore to the Port of Beaumont Turning Basin; extending
the 50-foot deep offshore channel by approximately 13.2 miles to
deep water in the Gulf, increasing the total length of the channel
from approximately 64 to 77 miles; tapering and marking the
Sabine Bank Channel from 800 feet wide to 700 feet wide;
deepening and widening the Taylor Bayou channels and turning
basins; easing selected bends on the Sabine-Neches Canal and
Neches
River
Channel;
constructing
new
and
enlarging/deepening existing turning and anchorage basins on
the Neches River Channel; beneficial use of dredged material
features consisting of the restoration of 2,853 acres of emergent
marsh, improvement of 871 acres of shallow water habitat, and
nourishment of 1,234 acres of existing marsh in Texas;
mitigation measures consisting of the restoration of 2,783 acres
of emergent marsh, improvement of 957 acres of shallow water
habitat, and stabilization and nourishment of 4,355 acres of
existing marsh; and post-construction monitoring and adaptive
management of the beneficial use features and mitigation
areas[.]”
6a
So the District needed $488 million. The first $20
million in “new start” funds went to deepening
Anchorage Basin No. 1—before it was twenty-feet
deep, now it is forty-feet deep. Once that was done, the
District proposed the User Fee. The User Fee would
apply only to ships with drafts greater than twenty
feet—in other words, ships that were too big to use the
Basin before the deepening. The Fee could change
based on certain (unrelated) conditions, but the basics
are as follows:
hydrocarbon
cargo
nonhydrocarbon
cargo
minimum
$0.00 per short
ton
$0.00 per short
ton
starting
rate
$0.20 per short
ton
$0.02 per short
ton
maximum
$0.35 per short
ton
$0.035 per short
ton
Every short ton loaded onto a ship or unloaded from
a ship is charged. 4 Key for our purposes, the
ordinance says that the District would collect the Fee
until the first of either (a) all construction costs are
repaid, or (b) January 1, 2049.
Per the Act, the District published the proposed
ordinance in the Federal Register and received public
4
A “ton” in America and Canada is 2,000 lbs., while a “ton” in
the United Kingdom is 2,240 lbs. To avoid confusion, “short ton”
is used for something that is 2,000 lbs. and “long ton” for 2,240
lbs.
7a
comment. 86 Fed. Reg. 7369-05 (Jan. 28, 2021).5 After
a hearing, the Commissioners of the District passed
the Ordinance, and the District began levying the fee
against the bigger ships on May 1, 2021.
BG Gulf Coast LNG and Phillips 66 Company are
energy companies. BG Gulf Coast has already paid
well into the six figures because of the Ordinance. As
of the filing of the Complaint, Phillips 66 had not yet
sent any of its cargo on bigger ships. But it planned
to. They both sued, alleging that the Ordinance
violated several provisions of the Act. The District
moved to dismiss under Rule 12(b)(6). The district
court granted the motion on each claim, concluding
that the District satisfied all of the requirements of
the Act, including the requirement that any fees must
be imposed “on a fair and equitable basis.” 6 The
district court then dismissed the case with prejudice.
The energy companies (hereinafter “BG Gulf Coast”)
5
The District actually went through notice and comment twice.
The first proposed ordinance set a flat $0.35/short ton for
hydrocarbon cargo and no fee at all for the nonhydrocarbon
cargo. 85 Fed. Reg. 37,634, 37,635 (June 23, 2020). After a
hearing and talking with the Corps, the District revised the
ordinance to what it is today. Id.
6
Dictionaries at the time the Act was passed defined “fair” as
“[h]aving the qualities of impartiality and honesty; free from
prejudice, favoritism, and self-interest,” Fair, Black’s Law
Dictionary 534 (5th ed. 1979), and “equitable” as “[j]ust;
conformable to the principles of justice and right,” Equitable,
Black’s Law Dictionary 482 (5th ed. 1979). See also Webster’s
Third New International Dictionary 815 (1971) (“equitable”
means “characterized by equity”). The most recent edition of
Black’s Law Dictionary includes this example for the term “fair”:
“everyone thought Judge Reavley to be fair.” Fair, Black’s Law
Dictionary 715 (11th ed. 2019).
8a
appealed. We subsequently granted the District’s
motion to expedite the appeal.
II.
We review de novo the grant of a motion to dismiss
under Rule 12(b)(6). Residents of Gordon Plaza, Inc. v.
Cantrell, 25 F.4th 288, 295 (5th Cir. 2022). “To survive
a motion to dismiss, a complaint must contain
sufficient factual matter, accepted as true, to ‘state a
claim to relief that is plausible on its face.’” Ashcroft
v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl.
Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “A claim
has facial plausibility when the plaintiff pleads
factual content that allows the court to draw the
reasonable inference that the defendant is liable for
the misconduct alleged.” Id. We accept all wellpleaded facts as true and draw all reasonable
inferences in favor of the plaintiff. Id. But we do not
presume that a complaint’s legal conclusions are true,
no matter how well they are pleaded. Id.
A.
Section 2236 of the Act sets limits on (among other
things) how and when a non-federal interest can pass
costs onto consumers vis-à-vis “[p]ort or harbor dues.”
One such condition is in § 2236(a)(1): “Port or harbor
dues may be levied only in conjunction with a harbor
navigation project whose construction is complete
(including a usable increment of the project)[.]”
To BG Gulf Coast, this means that the District can
only impose a fee for either (a) its share of the entire
$1.1 billion project once it is completed, or (b) its share
of a “usable increment” of the Project, provided that
the fee is imposed for use of that usable increment.
Put another way, the District cannot impose the User
9a
Fee on vessels and cargo because of Anchorage Basin
No. 1 to pay for any other part of the project, let alone
(as the Ordinance says) the District’s entire share of
the project. According to BG Gulf Coast, this follows
textually from the words “in conjunction with” in
subsection (a)(1). As well as by contextual inference
from other parts of § 2236 in which Congress only
allows fees for incurred costs, not speculative future
costs. BG Gulf Coast finds some further support in
certain language from Plaquemines, language which,
it says, makes this an open-and-shut issue. See 874
F.3d at 1025.
The District says that BG Gulf Coast’s reading of the
statute stops too soon; the full condition reads: “in
conjunction with a harbor navigation project whose
construction is complete (including a usable
increment of the project) and for the following
purposes and in amounts not to exceed those
necessary to carry out those purposes: (A)(i) to finance
the non-Federal share of construction and operation
and maintenance costs of a navigation project for a
harbor under the requirements of [33 U.S.C. § 2211].”
§ 2236(a)(1). According to the District, this means that
once a usable increment of the project is done, it may
then “finance” its “share of construction and operation
and maintenance costs of” the Project. In contrast to
BG Gulf Coast’s reading—which requires the nonfederal interest to build first and pay later—this
allows for the process under the Act to work like this:
(1) Congress funds the first phase of the project; (2)
the non-federal interest, after going through notice
and comment, imposes a fee to build revenue to cover
its share; (3) the fee raises funds to pay for the next
10a
increment of the project; and (4) so on until the project
is complete.
The district court agreed with the District. It
concluded that BG Gulf Coast’s approach was
atextual, as it required reading that parenthetical
“(including a usable increment of the project)” out of
the statute. BG Gulf Coast’s way around the
parenthetical was to say that “harbor navigation
project” in (a)(1) must mean the same thing as
“navigation project for a harbor” under (a)(1)(A)(i),
and thus a fee for “a usable increment of the project”
in (a)(1) meant that a fee could only finance the same
“usable increment.” The district court concluded that,
no, “a usable increment of the project” defines what it
means for a project to be “complete,” not what it
means to be a harbor navigation project. As for
Plaquemines, the district court concluded that it did
not apply as it was purely about subsection (a)(2) and
emergency-service fees.
We agree with the district court. BG Gulf Coast’s
interpretation of “in conjunction with” is far too
cramped. To be sure, “conjunction” was defined at the
time as a “simultaneous occurrence in space or time.”
Conjunction, American Heritage Dictionary 311 (2d
College ed. 1982). BG Gulf Coast says that the User
Fee is being levied “in conjunction with” the District’s
“plan to construct the Project’s remaining increments
at some future date.” But that argument fails because
subsection (a)(1) allows fees for projects “whose
construction is complete (including a usable
increment of the project).” It also says that other
subsections, like (a)(3)(B), contemplate using fees for
“project features constructed under this subchapter,”
which shows that fees are only for “incurred costs.”
11a
But subsection (a)(1) refers to “usable increment[s],”
not “project features,” and it has no similar past-tense
“constructed” language. See Christiana Tr. v. Riddle,
911 F.3d 799, 805 (5th Cir. 2018) (“When Congress
includes particular language in one section of a
statute but omits it in another, we presume[] that
Congress intended a difference in meaning.”
(quotation omitted)). So if anything, that cuts against
its argument because Congress presumptively treated
“usable increments” of projects differently than
“project features,” and thus fees are allowed under
different circumstances and require consideration of
completely different factors.
BG Gulf Coast again tries to tie fees to the specific
“usable increment of the project,” so that fees may
only be used after-the-fact to pay for that increment.
But to do so, it has to argue that “(including a usable
increment of the project)” modifies “a harbor
navigation project,” so that later when subsection
(a)(1)(A)(i) says “a navigation project for a harbor,” it
means “a usable increment of the project.” But it
makes far more sense that this language means that
once a usable increment of the project is complete, a
fee may be levied, not that a fee may only be levied to
finance a usable increment of the project. Cf. Antonin
Scalia & Bryan A. Garner, Reading Law: The
Interpretation of Legal Texts 152–53 (2012) (the
Nearest-Reasonable-Referent canon: “When the
syntax involves something other than a parallel series
of nouns or verbs, a prepositive or postpositive
modifier normally applies only to the nearest
reasonable referent.”).
At first blush, some language in Plaquemines
supports BG Gulf Coast, but that case concerned an
12a
entirely different provision of the Act. Knight v. Kirby
Offshore Marine Pac., L.L.C., 983 F.3d 172, 177 (5th
Cir. 2020) (“A statement is dictum if it could have been
deleted without seriously impairing the analytical
foundations of the holding and[,] being peripheral,
may not have received the full and careful
consideration of the court that uttered it.” (quoting
United States v. Segura, 747 F.3d 323, 328–29 (5th
Cir. 2014))). Plaquemines described § 2236(a)(1) as
“forbid[ing] fees to finance harbor improvements until
after the project is complete,” but that case was
actually about subsection (a)(2), and how the Act does
not otherwise constrain a port’s ability to assess a fee
until a port “has undertaken a harbor improvement
project.” 874 F.2d at 1026, 1024–25. So Plaquemines
is only relevant to the extent it holds that the Act
applies once a project begins, not when it ends, and
the fact that subsection (a)(1) was in no way raised or
relevant to the bottom-line conclusion is dispositive.
See Knight, 983 F.3d at 178 (dicta is “peripheral” and
“may not have received [our] careful consideration”).
BG Gulf Coast’s theory of subsection (a)(1) fails at
every turn. The statute, properly construed, allows
the District to finance its share of the project once a
usable increment of the project is completed. Because
Anchorage Basin No. 1 has been completed,
subsection (a)(1) permitted the District to pass the
Ordinance containing the User Fee.
B.
As discussed, upon completion of a usable increment
of the project, § 2236(a)(1)(A)(i) allows a non-federal
interest to levy a harbor fee “in amounts not to exceed
those necessary to carry out” the following purpose:
“to finance the non-Federal share of construction and
13a
operation and maintenance costs of a navigation
project for a harbor under the requirements of [33
U.S.C. § 2211].” Section 2211(a)(1)(B) says that the
non-federal interest “shall pay, during the period of
construction of the project,” 25% “of the cost of
construction of the portion of the project which has a
depth in excess of 20 feet but not in excess of 50 feet[.]”
BG Gulf Coast reads these provisions together to
argue that “amounts not to exceed those necessary”
means that the District may only use the fee to finance
25% of the Project, as (according to BG Gulf Coast) the
District “voluntarily agreed to pay more than 25% of
the Project’s total cost[.]” The District agreed to cover
around 40% of the project, but if the Project comes in
under budget, BG Gulf Coast alleges that the District
still plans to pay the amount it agreed to—in other
words, it may end up covering 60%–80% of the Project.
Because it voluntarily agreed to pay that much, “the
additional amount above 25% is not a ‘requirement’ of
[33 U.S.C. § 2211],” so the District has to cover
anything above 25% with funds that do not come from
the User Fee. Summing that up, BG Gulf Coast argues
that § 2211(a)(1)(B) places a 25% cap on financing a
non-federal interest’s share of an improvement project
because anything not “require[d]” by § 2211(a)(1)(B) is
not “necessary.”
The District responds with a different provision of §
2211. Subsection (e) says that before any construction
begins on harbors, the Secretary of the Army and the
non-federal interests “shall enter into a cooperative
agreement” and that the non-federal interests “shall
agree to” “provide to the Federal Government the nonFederal share of all other costs of construction” of the
project. 33 U.S.C. § 2211(e)(4). So when § 2236(a)(1)
14a
says “amounts not to exceed those necessary to carry
out” the financing of the Project, the District says that
the cooperative agreement was necessary to carry out
the Project, and so the User Fee can be used to cover
its contractual obligation.
The district court did not squarely address that
argument because it held that the 25% “requirement”
is a floor, not a ceiling or a set amount. As everyone
agrees, the District may voluntarily assume more
than 25% of the cost of the project, which necessarily
means that 25% is not both a floor and a ceiling. Shall
does not mean shall only, and the statute contains no
“up to” or “at least” language either. BG Gulf Coast
then must turn to § 2236(a)(1) which limits fees to the
“amount not to exceed those necessary” under § 2211.
The district court said that it “cannot be that Section
2211 imposes a cap for the fee-based non-Federal
share but not the alternatively funded non-federal
share because that reading would require an express
statutory provision. Section 2236(a)(1)’s language—
‘amount not to exceed those necessary’—is not
enough.”
The question is what § 2236(a)(1)(A)(i) means when
it says that fees must be “in amounts not to exceed
those necessary to carry out” the purpose of
“financ[ing]” the Project “under the requirements of”
§ 2211. BG Gulf Coast says that the “necessary”
amount under § 2211 is the 25% requirement in
subsection (a). The District says that the “necessary”
amount under § 2211 is the amount that the District
agreed to cover in the cooperative agreement with the
federal government in subsection (e). Sadly, Congress
did not say what subsection it was thinking of when it
said “under the requirements of” § 2211, and the most
15a
natural reading
requirements.
is
that
it
meant
all
of
its
The word “necessary” has been hard to pin down
since McCulloch v. Maryland, 17 U.S. (4 Wheat.) 316,
414 (1819). Black’s Law Dictionary, before even
getting to what the definition is, opens with this
warning: “This word must be considered in the
connection in which it is used, as it is a word
susceptible of various meanings. It may import
absolute physical necessity or inevitability, or it may
import that which is only convenient, useful,
appropriate, suitable, or conducive to the end sought.”
Necessary, Black’s Law Dictionary 928 (5th ed. 1979).
And between the two, at least in the legal context,
courts “rarely use ‘necessary’ in the latter sense.”
Payne v. United States, 289 F.3d 377, 389 (5th Cir.
2002) (Garza, J., dissenting in part). The term
“necessary” here “does not exist in a vacuum,” and its
meaning “must be determined in the context in which
[it] appear[s].” Texas v. E.P.A., 983 F.3d 826, 837, 837
n.2 (5th Cir. 2020).
Section 2236(a)(1) is concerned with fees being
levied “for the following purposes and in amounts not
to exceed those necessary to carry out those purposes.”
The purpose relevant here is “to finance.” And what
can it finance? The District’s share of the
“construction and operation and maintenance costs” of
the Project “under the requirements of” § 2211.
Section 2211 has many requirements about costs
under different specific circumstances, but if the
purpose is “to finance” the District’s share of the
Project, the focus should be on what it had to do to
secure financing. So it is true that paying 25% of the
costs was necessary to secure financing vis-à-vis the
16a
fees, but the District also had to secure an agreement
with the federal government under § 2211(e).
As BG Gulf Coast concedes, the Act gives the
District discretion to go beyond that 25% amount for
costs; it only sets a maximum on what percentage the
federal government can spend. See 33 U.S.C. § 2280.
With that discretion, because the amount of fees must
be necessary to secure financing, and because the
District had discretion to vary upward on the
percentage of costs it covers, the term “necessary”
more likely accords with the more permissive
definition of the term. Texas, 983 F.3d at 837. What
follows is that “necessary” means something more like
“convenient, useful, appropriate, suitable, or
conducive to the end sought.” Black’s, supra at 928
(emphasis added). Cf. 33 U.S.C. § 2236(a)(1)
(“necessary to carry out those purposes” (emphasis
added)). In this light, while it may not be strictly
necessary to cover 40% of the costs under § 2236(a)(1)
and § 2211(a), it was convenient and conducive to
financing the Project. Thus, the District did not
violate the Act by pledging to cover the costs above
25% with the proceeds of the User Fee.
BG Gulf Coast’s argument hinges on a strict reading
of “necessary.” But context is needed to determine
whether “necessary” means “absolute physical
necessity” or merely “conducive to the end sought.”
Under these circumstances, it is the latter. Thus, the
District can cover more than 25% of the cost with the
User Fee proceeds.
C.
BG Gulf Coast briefed several other arguments
regarding the legality of the District’s imposition of
the User Fee. In its thorough and well-reasoned
17a
opinion, the district court explained why those claims
must be dismissed. We agree with the conclusions
reached by the district court and thus we do not
disturb its holdings on appeal.
***
Because the district court properly dismissed each
of BG Gulf Coast’s claims, we AFFIRM.
18a
APPENDIX B
_________
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF TEXAS
BEAUMONT DIVISION
_______
BG GULF COAST LNG, LLC, PHILLIPS 66 COMPANY,
Plaintiffs,
v.
SABINE-NECHES NAVIGATION DISTRICT OF JEFFERSON
COUNTY, TEXAS,
Defendant.
_______
Civil Action No. 1:21-cv-00470
_______
Signed 02/24/2022
_______
ORDER GRANTING DEFENDANT’S MOTION
TO DISMISS AND DENYING AS MOOT
PARTIES’ JOINT MOTION FOR PROTECTIVE
ORDERS
_______
MICHAEL J. TRUNCALE, United States District
Judge
Plaintiffs BG Gulf Coast LNG (‘‘BG’’) and Phillips 66
Company (‘‘Phillips’’), two major energy companies,
bring suit against Defendant Sabine Neches
19a
Navigation District (‘‘SSND’’), a political subdivision
of the State of Texas responsible for the construction
and maintenance of ports and harbors in southeast
Texas. Defendant began levying a fee against users of
the Sabine-Neches Waterway (‘‘Waterway’’) to fund
construction improvements made to the Waterway.
Plaintiffs contest this fee. Before the Court are
Defendant’s Motion to Dismiss, [Dkt. 5], and the
Parties’ Joint Motion for Protective Orders. [Dkt. 34].
For the following reasons, Defendant’s Motion to
Dismiss is GRANTED. Parties’ Joint Motion for
Protective Orders is DENIED AS MOOT.
I. BACKGROUND
Before the Court rests not only a matter of first
impression but also a matter of utmost importance to
this region, this nation, and the global economy.
Defendant SSND, a political subdivision of the State
of Texas responsible for southeast Texas’ ports and
harbors, is spearheading a $1.2 billion infrastructure
project (‘‘Project’’) to modernize the Waterway. The
Waterway feeds the Ports of Beaumont, Port Arthur,
and Orange, Texas. It is the country’s third largest
waterway by total shipping tonnage and critical to
national security.
Like much of the nation’s water infrastructure, the
Waterway has not been improved since the 1960s.
Ships have become larger, and technology has
advanced, but growth of the Waterway has lagged. At
only forty feet in depth, it is unable to accommodate
many modern, larger vessels.
To remedy this, Defendant partnered with the
United States Army Corps of Engineers (‘‘USACE’’) to
improve the Waterway through a process proscribed
20a
by the Water Resources Development Act of 1986, 33
U.S.C. § 2201 et seq. (‘‘WRDA-86’’).1 Congress passed
the WRDA-86 in the mid-1980s to revamp the arduous
process of updating the nation’s ports and harbors.
Prior to the WRDA-86, ‘‘[e]very project underwent
nineteen independent reviews, with an average of
twenty-six years passing between the first study of a
project and the project’s completion.’’ New Orleans
S.S. Ass’n v. Plaquemines Port, Harbor & Terminal
Dist., 874 F.2d 1018, 1024–25 (5th Cir.), opinion
amended on denial of reh’g, 891 F.2d 1153 (5th Cir.
1989). Furthermore, given the serious financial
burden these projects imposed, Congress did not have
enough funding for the projects that needed it most.
132 Cong. Rec. S3402 (1986). The length of time for
approving and the difficulty in financing these
projects hampered their implementation. In fact, ‘‘[n]o
new project was authorized between 1970 until
shortly before passage of the [WRDA-86]. Federal
spending on harbor construction declined 78% after
the 1960’s [sic]; mounting pressures on the federal
budget made increased appropriations for projects
unlikely.’’ Id.
In response, the WRDA-86 overhauled the system
for financing both new construction and improvement
projects for America’s ports and harbors. Instead of
relying solely on federal funding, the WRDA-86 split
the costs of construction with state and local entities
(‘‘non-Federal interests’’). By involving non-Federal
1
Although the process is proscribed in WRDA-86, Congress
approves new projects and provides cost projections for those
projects in subsequent WRDA enactments. See, e.g., Water
Resources Reform and Development Act of 2014, Pub. L. No. 113121, 128 Stat. 1193, 1364 (2014).
21a
interests, Congress intended to boost local investment
and hasten project completion.
The process prescribed by the WRDA-86 begins with
a feasibility study performed by the USACE. 33
U.S.C. §§ 2215, 2282. This study is published in the
Federal Register, then transferred to Congress by the
Secretary of the Army. Id.; see also Air Liquide Am.
Corp. v. U.S. Army Corps of Eng’rs, 359 F.3d 358, 365
(5th Cir. 2004) (describing the process for harborrestoration projects under the WRDA-86 and
subsequent legislation authorizing new projects
under the Water Resources Development Act of 1996,
Pub. L. No. 104–303, 110 Stat. 3658 (1996)). Upon
congressional approval, which includes projected
costs, Congress allocates funding (‘‘New Start
funding’’) to initiate the first phase of the project. See
Air Liquide, 359 F.3d at 365. The USACE and the
non-Federal interest then enter into a partnership
agreement covering the project. 33 U.S.C. § 2211(e).
This agreement must provide the federal government
with the non-Federal share of costs.
The Project has complied with these requirements.
The USACE produced its feasibility study in March
2011. The study recommended that Congress allocate
funding for the Project because it benefits the
hydrocarbon industry and the United States Military.
[Dkt. 5-3 at 3, 7, 12–14]. Namely, the Project would
ease congestion and allow the Waterway to
accommodate larger ships. The Secretary of the Army
then transferred the study to Congress, which
approved the Project in 2014. Water Resources
Reform and Development Act of 2014, Pub. L. No. 113121, 128 Stat. 1193, 1364 (2014) (‘‘WRDA-14’’). The
WRDA-14 listed the projected costs as $1.1 billion,
22a
with the federal government funding $748 million and
Defendant footing the remaining $365 million. Id. In
2019, Congress allocated New Start funding for the
Project. Energy and Water, Legislative Branch, and
Military Construction and Veterans Affairs
Appropriations Act, 2019, Pub. L. No. 115-244, 132
Stat. 2897, 2898–99 (2019). This New Start funding,
approximately $20 million, funded the first portion of
the Project, Anchorage Basin No. 1. [Dkt. 1 at ¶¶ 31,
50]. In July 2019, the USACE and Defendant entered
into a Partnership Agreement (‘‘Partnership
Agreement’’), which lists a projected $1.2 billion
construction cost, 2 with $732 million coming from
federal coffers and the remaining $488 million coming
from Defendant. Defendant’s projected share of costs
amounts to forty percent of the total cost of
construction.
Pursuant to the Partnership Agreement, the Project
will update many features of the Waterway,
including:
[D]eepening the Sabine Neches Waterway
(SNWW) from 40 to 48 feet and the offshore
channel from 42 to 50 feet in depth from
offshore to the Port of Beaumont Turning
Basin; extending the 50-foot deep offshore
channel by approximately 13.2 miles to deep
water in the Gulf, increasing the total length of
the channel from approximately 64 to 77 miles;
tapering and marking the Sabine Bank
Channel from 800 feet wide to 700 feet wide;
deepening and widening the Taylor Bayou
2
This is a projected cost. Plaintiffs have proffered evidence
that the actual cost of this Project will be significantly lower.
23a
channels and turning basins; easing selected
bends on the Sabine-Neches Canal and Neches
River Channel; constructing new and
enlarging/deepening existing turning and
anchorage basins on the Neches River Channel;
beneficial use of dredged material features
consisting of the restoration of 2,853 acres of
emergent marsh, improvement of 871 acres of
shallow water habitat, and nourishment of
1,234 acres of existing marsh in Texas;
mitigation measures consisting of the
restoration of 2,783 acres of emergent marsh,
improvement of 957 acres of shallow water
habitat, and stabilization and nourishment of
4,355 acres of existing marsh; and
postconstruction monitoring and adaptive
management of the beneficial use features and
mitigation areas[.]
[Dkt. 5-7 at 1–2]. Construction on the first portion of
the Project, Anchorage Basin No. 1, has been
completed. This portion of the Project deepened
Anchorage Basin No. 1 from twenty feet to forty feet.
To fund its share of Project costs, SSND passed a
User Fee Ordinance (‘‘Ordinance’’) in April 2021,
which charges a User Fee (‘‘Fee’’) on ships with drafts
in excess of twenty feet. [Dkt. 1-1]. Prior to enacting
the Ordinance, SSND published it in the Federal
Register in January 2021 and received public
comment. SNND User Fee Notice, 86 Fed. Reg. 736905 (Jan. 28, 2021). The Fee collects between $0.02–
$0.035 per short ton of non-hydrocarbon cargo and
$0.20–$0.35 per short ton of hydrocarbon cargo. The
Fee may be adjusted to as low as $0.00 for all types of
cargo. [Dkt. 1 at ¶ 38(g)]. SSND will collect the Fee
24a
until either all construction costs are repaid or
January 1, 2049, whichever comes first. Id. SSND
began levying the Fee upon completion of Anchorage
Basin No. 1 on May 1, 2021. Id. at ¶ 37.
Plaintiffs’ ships make extensive use of the
Waterway.3 Attached to the Complaint is a list of BG
ships that have been subject to the Fee, each with a
fully laden forward and aft sailing draft between
thirty-six and thirty-nine feet. [Dkt. 1-2]. At the time
of filing, BG incurred $326,983.70 in Fees. Although
Phillips has not yet paid the Fee, it has executed
contracts which will subject it to the Fee in the
immediate future. [Dkt. 1 at ¶ 43].
II. LEGAL STANDARD
Federal Rule of Civil Procedure 12(b)(6) authorizes
dismissal of a complaint for ‘‘failure to state a claim
upon which relief can be granted.’’ Fed. R. Civ. P.
12(b)(6). In reviewing a Rule 12(b)(6) motion, the
Court ‘‘accepts all well-pleaded facts as true, viewing
them in the light most favorable to the plaintiff.’’
Sonnier v. State Farm Mut. Auto. Ins. Co., 509 F.3d
673, 675 (5th Cir. 2007). However, ‘‘the tenet that a
court must accept as true all of the allegations
contained in a complaint is inapplicable to legal
conclusions [and] . . . Rule 8 does not unlock the doors
of discovery for a plaintiff armed with nothing more
than conclusions.’’ Ashcroft v. Iqbal, 556 U.S. 662,
678–79, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009).
To defeat a Rule 12(b)(6) motion to dismiss, a
plaintiff must ‘‘nudge their claims across the line from
conceivable to plausible’’ by pleading ‘‘enough facts to
3
The ships themselves are not owned by Plaintiffs, rather it is
their cargo that frequently traverses the Waterway.
25a
state a claim to relief that is plausible on its face.’’ Bell
Atl. Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct.
1955, 167 L.Ed.2d 929 (2007). In other words, a
plaintiff must establish ‘‘more than a sheer possibility
that a defendant has acted unlawfully.’’ Ashcroft, 556
U.S. at 678, 129 S.Ct. 1937. Determining whether a
complaint states a plausible claim for relief is ‘‘a
context-specific task that requires the reviewing court
to draw on its judicial experience and common sense.’’
Id. at 679, 129 S.Ct. 1937.
In evaluating a motion to dismiss, courts may need
to engage in statutory interpretation. In analyzing the
text, this Court undertakes ‘‘the traditional means of
statutory interpretation, which include the text itself,
its history, and its purpose.’’ Bellum v. PCE
Constructors, Inc., 407 F.3d 734, 739 (5th Cir. 2005).
The Supreme Court and Fifth Circuit prefer the
statute’s plain meaning unless doing so leads to an
absurd result. Hartford Underwriters Ins. Co. v.
Union Planters Bank, N. A., 530 U.S. 1, 6, 120 S.Ct.
1942, 147 L.Ed.2d 1 (2000); Bellum, 407 F.3d at 739.
With that, the Court turns to the merits of Plaintiffs’
claims.
III. DISCUSSION
Plaintiffs contend that the Fee enacted by the
Ordinance violates the WRDA-86 in the following
ways:
a. WRDA permits a non-Federal sponsor to
levy fees only in conjunction with a harbor
navigation project ‘‘whose construction is
complete (including a usable increment of
the project).’’ 33 U.S.C. § 2236(a). The
Ordinance violates WRDA because it
permits SNND to prospectively collect User
26a
Fees for incomplete, unusable increments of
the Project.
b. WRDA contemplates that a project may
include multiple navigational features—
such as channel deepening features or
anchorage basin features—and requires
that fees be levied on a feature-by-feature
basis. Moreover, some vessels are exempt
from paying fees for certain navigational
features. For deepening features, WRDA
prohibits assessing a fee against any vessel
that, based on its design draft, could have
used the waterway before construction of
the project. 33 U.S.C. § 2236(a)(3). And as to
certain other specific project features
enumerated in the statute, ‘‘only vessels at
least comparable in size to those used to
justify these features may be charged’’ the
fee. Id. The Project at issue here includes
multiple navigational features. But, the
Ordinance fails to levy the User Fee on a
feature-by-feature basis and improperly
levies fees against exempt vessels.
c. WRDA caps the total amount of fees the
non-Federal sponsor may levy in two
respects. First, the fee must be limited to the
non-Federal share of construction costs (as
opposed to total construction costs). Second,
the fee must be limited to 25% of total
construction costs. The Ordinance fails to
impose these statutorily-required limits
because: (i) the Ordinance contemplates
collecting User Fees for ‘‘all’’ construction
costs ‘‘associated with the Project’’ and not
27a
merely the non-Federal share; and (ii) even
if such a limit existed, the Ordinance further
fails to limit the amount of User Fees to 25%
or less of the total construction costs.
d. WRDA requires non-Federal sponsors to
levy fees on a ‘‘fair and equitable’’ basis. The
Ordinance, however, improperly levies User
Fees on vessels carrying hydrocarbon cargo
at a rate at least 1000% greater than the
rate for vessels carrying non-hydrocarbon
cargo.
[Dkt. 1 at ¶ 8]. Plaintiffs request monetary damages
in the amount of the Fee already paid by BG as well
as injunctive and declaratory relief. The Court
evaluates each of these contentions in turn and
concludes that Plaintiffs do not state a claim for which
relief can be granted.
i.
Count I
The Court dismisses Count I of the Complaint
because it rests on a fundamental misunderstanding
of the WRDA-86. Plaintiffs contend that Defendant’s
Fee is unlawful because it funds incomplete portions
of the Project in violation of 33 U.S.C. § 2236. This
statute permits the non-Federal interest, Defendant,
to levy harbor fees to finance construction:
Port or harbor dues may be levied only in
conjunction with a harbor navigation project
whose construction is complete (including a
usable increment of the project) and for the
following purposes and in amounts not to
exceed those necessary to carry out those
purposes:
28a
(A)(i) to finance the non-Federal share of
construction
and
operation
and
maintenance costs of a navigation project for
a harbor under the requirements of section
2211 of this title.
§ 2236(a)(1). Defendant contends that this language
permits it to charge the Fee for the entire Project upon
completion of a usable increment. Plaintiffs assert
that Defendant may only charge the Fee for ‘‘(a) a
project whose construction is complete; or (b) for a
usable increment of a project whose construction is
complete.’’ [Dkt. 1 at ¶ 47 (internal quotations
omitted)].
Plaintiffs’ reading requires the Court to add
language to the statute and is therefore incorrect.
Section 2236(a) treats the completion of a usable
increment in the same manner as the completion of
the entire project; therefore, the non-Federal interest
may charge fees for the whole project upon completion
of one usable increment. The term ‘‘usable increment
of the project’’ defines when a project is considered
complete, which in turn triggers the ability to charge
a fee. Critically, a usable increment is not
synonymous with a harbor navigation project, but a
completed harbor navigation project. In this regard,
the placement of the parenthetical involving usable
increments is instructive. If Congress intended to
define ‘‘harbor navigation project’’ as a ‘‘usable
increment of the project,’’ then it would have placed
the parenthetical next to ‘‘harbor navigation project’’
rather than ‘‘complete.’’ Furthermore, the lack of the
term ‘‘usable increment’’ in Subsection (A)(i)
demonstrates the futility of Plaintiffs’ approach.
Congress did not add a similar parenthetical in
29a
Subsection (A)(i) and, therefore, made clear that
harbor fees may finance the ‘‘navigation project’’ as a
whole and not merely ‘‘a usable increment.’’ Even if
‘‘usable increment’’ and ‘‘harbor navigation project’’
were synonymous in Subsection (a)(1), this does not
transform the meaning of ‘‘navigation project for a
harbor’’ in Subsection (a)(1)(A)(i). Thus, upon
completion of a usable increment, Defendant may
charge the Fee to fund the entire Project. In addition,
other portions of Section 2236 discuss levying fees
based on the characteristics of individual project
features. See § 2236(a)(3); see also infra Part II.ii. The
Court concludes that the distinction between ‘‘project
feature’’ and ‘‘usable increment’’ was intentional, in
part, because Congress chose to discuss project
features in more depth in a different part of the same
section.
Plaintiffs also rely on New Orleans Steamship
Association v. Plaquemines Port, Harbor and
Terminal District for the propositions that Defendant
may only charge the Fee on a feature-by-feature basis
and for features that have already been completed.
874 F.2d 1018 (5th Cir. 1989). In Plaquemines, a
group of ship owners sued a local harbor district for
charging emergency-service fees because they
believed the fees violated, among other provisions, the
WRDA. The Fifth Circuit found that Section 2236
‘‘applies when a port has undertaken a harbor
improvement project and not otherwise.’’ Id. at 1024.
However, nothing in the statute prohibited port and
harbor authorities from charging an emergencyservice fee for regular use of the harbor. Id. at 1027.
Therefore, that fee did not violate the WRDA.
30a
Although Plaquemines dealt primarily with Section
2236(a)(2), part of the opinion discusses Section
2236(a)(1). This is the opinion’s strongest language in
support of Plaintiffs’ argument:
Section 2236(a)(1) forbids fees to finance harbor
improvements until after the project is
complete. Obviously, this prevents nonfederal
ports from fraudulently charging for projects
that are mere speculation or that suffer from
undue delays while under construction. More to
the point, it ensures that the fees will be paid
by ships that benefit directly from
improvements[.]
Id. at 1025.4
This—and other language regarding Section
2236(a)(1)—is dicta. ‘‘A statement is dictum if it could
have been deleted without seriously impairing the
analytical foundations of the holding and being
peripheral, may not have received the full and careful
consideration of the court that uttered it.’’ Int’l Truck
& Engine Corp. v. Bray, 372 F.3d 717, 721 (5th Cir.
2004). But ‘‘if the statement is ‘necessary to the result
or constitutes an explication of the governing rules of
law,’ it is not dictum.’’ U.S. Bank Nat’l Ass’n v. Verizon
Commc’ns., Inc., 761 F.3d 409, 427–28 (5th Cir. 2014)
(quoting Int’l Truck & Engine Corp., 372 F.3d at 721).
Plaquemines’s discussion of Section 2236(a)(1) is not
critical to its holding. First, the Fifth Circuit found
that Section 2236 did not apply because the
emergency-service fees were not assessed with a
harbor improvement project. Plaquemines, 874 F.2d
4
Plaintiffs cite to other language, but this is the strongest.
Regardless, all Plaintiffs’ references to Plaquemines are dicta.
31a
at 1024. Whether the non-Federal interest could
charge fees after the project’s completion is irrelevant
to the holding.
Even if the Fifth Circuit’s discussion of Section
2236(a)(1) were precedential, it would not necessarily
favor Plaintiff. Although the opinion states that fees
are only permissible after construction is complete,
the court does not specify whether it is completion of
the entire project or simply a usable increment. The
statement that ‘‘fees will be paid by ships that benefit
directly from improvements,’’ Id. at 1026, is similarly
unclear. While Plaintiffs contend that the direct
beneficiary language requires Defendant to charge on
a feature-by-feature basis, 5 the Fifth Circuit’s
language is vague as to whether ships must benefit
from the specific feature of the project or from the
project as a whole. Thus, the Plaquemines dicta does
not provide Plaintiffs’ claims with enough support to
withstand Defendant’s Motion to Dismiss.
ii.
Count II
In Count II, Plaintiffs assert that the Project should
assess the Fee on a feature-by-feature basis. 6
Plaintiffs principally rely on 33 U.S.C. § 2236(a)(3):
a. Port or harbor dues may not be levied under
this section in conjunction with a deepening
feature of a navigation improvement project
on any vessel if that vessel, based on its
design draft, could have utilized the project
5
Charging on a feature-by-feature basis would only permit
Fees for those features that Plaintiffs actually use, rather than a
single Fee for using any portion of the Project.
6
While there may be situation in which certain vessels are
exempt from Harbor Fees, this is not one of them.
32a
at mean low water before construction. In
the case of project features which solely—
i. widen channels or harbors,
ii. create or enlarge bend easings, turning
basins or anchorage areas, or provide
protected areas, or
iii. remove obstructions to navigation,
only vessels at least comparable in size to those
used to justify these features may be charged
under this section.
The Court distills this provision into two limitations:
(1) the Design Draft Limitation; and (2) the Size
Limitation.
(A) The Design Draft Limitation
First, Section 2236(a)(3) limits the fees that may be
assessed for a ‘‘deepening feature of a navigation
project’’:
Port or harbor dues may not be levied under
this section in conjunction with a deepening
feature of a navigation improvement project on
any vessel if that vessel, based on its design
draft, could have utilized the project at mean
low water before construction.
§ 2236(a)(3)(A). Plaintiffs assert that Defendant may
only charge ships for features that they would not be
able to use but for the Project’s improvements.
Accordingly, Plaintiffs believe that Defendant’s Fee
violates the statute because it charges all vessels with
a design draft in excess of twenty feet for all Project
features.
This reading ignores the statute’s plain meaning: a
vessel must be able to utilize the entire project before
33a
construction to avoid post-construction fees. Courts
assume that the legislature intended different
meanings when ‘‘the legislature uses certain language
in one part of the statute and different language in
another[.]’’ Sosa v. Alvarez-Machain, 542 U.S. 692,
711 n.9, 124 S.Ct. 2739, 159 L.Ed.2d 718 (2004)
(internal quotation marks omitted). Here, the statute
requires that the vessel be able to use the ‘‘project’’
prior to construction. § 2236(a)(3)(A). The Court
interprets this language to mean that a ship must be
able to use every feature of the project prior to
construction to avoid paying the fees associated with
project improvements. It is immaterial that a vessel
can use certain features before the project but not
others—‘‘features’’ is specific to a project’s subparts,
while ‘‘project’’ refers to the entire project. If Congress
intended to charge harbor fees on a feature-by-feature
basis, it could have used the term ‘‘deepening feature’’
in lieu of ‘‘project.’’ Indeed, Congress used the term
‘‘project features’’ in the next sentence of the statute
(‘‘In the case of project features . . . .’’). Id. Because
Congress used the term ‘‘project features’’ in a
different part of the same statute, the Court infers
that this distinction was intentional. At least one
other court has similarly found that the exemption
only applies to ‘‘any vessel that could have utilized the
harbor without the improvement.’’ Maher Terminals,
LLC v. Port Auth. of N.Y. and N.J., No. 2:12-6090,
2014 WL 3590142, at *11 (D.N.J. July 21, 2014), aff’d,
805 F.3d 98 (3d. Cir. 2015) (emphasis added).
Here, Plaintiffs’ ships could not have utilized the
whole Waterway prior to construction. For example,
before the Project, Anchorage Basin No. 1 had a draft
above twenty feet, meaning that it was fewer than
34a
twenty feet deep. [Dkt. 5 at 2]. Plaintiffs’ ships subject
to the Fee have design drafts in excess of twenty feet.
[Dkt. 1-2]. A ship cannot make port or sail in water
that is shallower than its design draft. Therefore,
Plaintiffs’ vessels could not have used the entire
Waterway prior to construction. Plaintiffs’ ships are
subject to the Fee.7
As they do in Count I, Plaintiffs rely on Plaquemines
for the proposition that only those ships that actually
benefit from the improvements may be charged for
those improvements. Plaquemines, 874 F.2d at 1026
(‘‘[the statute] ensures that the fees will be paid by
ships that benefit directly from improvements’’). As
explained, this is dicta. And, even if precedential, this
proposition does not provide Plaintiffs with the level
of support they believe it does. The Fifth Circuit did
not claim that the ships subject to the fee needed to
benefit from every single element of the improvement
project. Rather, the Fifth Circuit required that the
ships obtain some direct benefit from the project. This
Project is multifaceted. It is immaterial that
Plaintiffs’ ships do not benefit from every feature.
(B) The Size Limitation
Section 2236(a)(3) imposes fee limitations for certain
features of harbor improvement projects. However,
7
It is possible that a ship may not have been able to use the
usable increment, such as Anchorage Basin No. 1, either before
or after the improvement. But to avoid the fee, the statute only
requires that the ship be able to use the entire project before
construction. The Court takes no opinion on an improvement
that only improves portions of a harbor that a ship could not use
both before and after construction.
35a
these limitations are inapplicable to Plaintiffs. The
statute provides that:
In the case of project features which solely—
i. widen channels or harbors,
ii. create or enlarge bend easings, turning
basins or anchorage areas, or provide
protected areas, or
iii. remove obstructions to navigation,
only vessels at least comparable in size to those
used to justify these features may be charged
under this section.
§ 2236(a)(3). Plaintiffs complain that numerous
features of the Project incorporate the above
limitations:
The Project involves several navigational
features, including: (i) deepening the Waterway
from 40 to 48 feet; (ii) deepening the offshore
channel portion of the Waterway (up to the Port
of Beaumont Turning Basin) from 42 to 50 feet,
(iii) extending the 50-foot deep offshore channel
by approximately 13.2 miles to deep water in
the Gulf, increasing the total length of channel
from approximately 64 to 77 miles, (iv) tapering
and marking the Sabine Bank Channel from
800 feet wide to 700 feet wide, (v) deepening
and widening the Taylor Bayou channels and
turning basins, (vi) easing selected bends on the
Sabine-Neches Canal and Neches River
Channel, and (vii) constructing new and
enlarging/deepening existing turning and
36a
anchorage
Channel.8
basins
on
the
Neches
River
[Dkt. 1 at ¶ 26]. Only one of these features ‘‘solely’’
conforms to the limitations of Section 2236(a)(3):
feature (vi). However, Plaintiffs assert that many
features meet Section 2236(a)(3)(A)’s criteria. This is
because Plaintiffs improperly define ‘‘solely.’’
Plaintiffs argue that it is inappropriate to group
improvements to the same portion of the Project
together. Instead, Plaintiffs contend that each
improvement to each portion of the Project should be
assessed individually. 9 This ignores the plain
meaning of the statute, which requires the Court to
evaluate each feature and all the improvements made
to that feature. Therefore, only those project features
that solely ‘‘widen,’’ ‘‘create or enlarge,’’ or ‘‘remove
obstructions’’ can be considered. See § 2236(a)(3).
Plaintiffs’ reading would render the word ‘‘solely’’
meaningless, which violates the cannon against
surplusage—‘‘the presumption that each word
Congress uses is there for a reason.’’ Advoc. Health
Care Network v. Stapleton, ––– U.S. ––––, 137 S. Ct.
1652, 1659, 198 L.Ed.2d 96 (2017); see also Williams
v. Taylor, 529 U.S. 362, 404, 120 S.Ct. 1495, 146
L.Ed.2d 389 (2000) (‘‘we must give effect, if possible,
to every clause and word of a statute.’’) (internal
8
This language is derived from the Project Partnership
Agreement. [Dkt. 5-7 at 1–2].
9
For example, instead of evaluating feature (v) as both
‘‘deepening and widening the Taylor Bayou channels and turning
basins’’ Plaintiffs’ reading would have the Court separate (v) into
deepening the Taylor Bayou channels and turning basins, and
also widening the same. When taken separately, Plaintiffs claim
the feature solely engages in widening a channel or harbor.
37a
citations omitted). The word ‘‘solely’’ indicates that
Congress intended for each project feature to be
evaluated in light of all the improvements performed
on that feature. Therefore, the Court must evaluate
every feature to determine whether the feature solely
engaged in any of the activities enumerated in Section
2236(a)(3)(A). Features (i)–(iii) only engage in
deepening. Feature (iv) narrows, rather than widens,
the channel. Feature (v) deepens and widens certain
channels and basins. Feature (vii) deepens turning
basins and anchorage areas, in addition to creating
and enlarging them.10
This leads the Court to feature (vi), which solely
engages in creating or enlarging bend easing and
turning basins. Because this feature meets the first
prong of the Size Limitation, the Court must
determine whether Plaintiffs’ ships are ‘‘at least
comparable in size to those used to justify these
features[.]’’ § 2236(a)(3). Courts have broad discretion
when comparing boats’ sizes, which is evidenced by
the statute’s plain meaning. The statute only requires
that the boats subject to the fee be ‘‘at least
comparable in size.’’ § 2236(a)(3)(A) (emphasis added).
By using the term ‘‘at least,’’ Congress clarified that
this is not an exacting inquiry. The boats subject to
the fee need not be the same size or even within a few
10
To deepen is not to enlarge. However, the statute uses
‘‘deepening’’ in the Draft Limitation. By using ‘‘deepening’’ in one
part of the statute and ‘‘enlarge’’ in another, Congress
intentionally distinguished the meaning of these words. See
Sosa, 542 U.S. at 711 n.9, 124 S.Ct. 2739 (‘‘when the legislature
uses certain language in one part of the statute and different
language in another, the court assumes the different meanings
were intended.’’).
38a
feet of the ship used to ‘‘justify’’ the project features
(the ‘‘design ship’’). Rather, they need only be at least
comparable in size to be subject to the fee for that
feature. Furthermore, courts may consider numerous
additional factors under Section 2236(a)(3)(B), such
as: elapsed time of passage; safety of passage; vessel
economy of scale; under-keel clearance; vessel draft;
vessel squat; vessel speed; sinkage; and trim.
§ 2236(a)(3)(B). Congress further expanded the
district courts’ discretion by allowing them to evaluate
these additional factors beyond a ship’s basic
dimensions.
In its Motion to Dismiss, [Dkt. 5], Defendant asserts
that the design ship is a 158,000 DWT Suez Supermax
Tanker, which is the ship that the USACE used in its
feasibility study. [Dkt. 5-10 at 12].11 This is not so. The
design ship is the ship that the project was meant to
benefit: any ship with a design draft in excess of
twenty feet. Fees may only be levied on ‘‘vessels at
least comparable in size to those used to justify these
features[.]’’ § 2236(a)(3)(A) (emphasis added). The
Court’s reading of this provision turns on the word
‘‘justify,’’ which Merriam-Webster dictionary defines
as ‘‘to provide or be a good reason for (something).’’
Justify, Merriam Webster Dictionary, https://
www.merriam-webster.com/dictionary/ justify (last
visited February 23, 2022). This definition necessarily
looks to the benefits created by someone or something.
In the context of the Size Limitation, this Court must
look to the benefits the features create and to whom
11
The Court takes judicial notice of the feasibility study
prepared by the USACE. See Fed. R. Evid. 201(b); see also Funk
v. Stryker Corp., 631 F.3d 777, 783 (5th Cir. 2011) (permitting
judicial notice of documents produced by a federal agency).
39a
those benefits were designed to inure. This is because
the beneficiaries of a harbor improvement project
should bear the brunt of its costs.
The Project was designed to benefit ships with
design drafts in excess of twenty feet. Although the
USACE design ship may be helpful in determining
certain characteristics for the Project, the Project
itself was not meant to exclusively benefit Suez
Supermax Tankers. As the Ordinance asserts: ‘‘a User
Fee as set out below reflects the benefits provided by
the Project to vessels whose design draft exceeds 20
feet.’’ [Dkt. 1-1 at 3]. Therefore, any ship with a design
draft in excess of 20 feet may be considered ‘‘at least
comparable in size to those used to justify these
features’’ and therefore ‘‘may be charged under this
section.’’ See § 2236(a)(3).12
The Court already possesses sufficient legal and
evidentiary support that the Fee complies with the
Size Limitation. Even so, the Court finds it significant
that Defendant, as the non-Federal interest,
determined that ships with design drafts in excess of
twenty feet justified the Project features. [See Dkt. 11 at 3]. The statute delegates authority to non-Federal
interests in determining which ships are ‘‘at least
comparable in size to those used to justify these
features.’’ § 2236(a)(3). Section 2236(a)(3)(B) reads:
‘‘In developing port or harbor dues that may be
charged under this section on vessels for project
features constructed under this subchapter, the non12
Even if the design ship were a 158,000 DWT Suezmax
Tanker (‘‘Suezmax Design Ship’’), the Court’s decision would not
change. Plaintiffs’ ships that have thus far been subject to the fee
are comparable in size to the Suezmax Design Ship. See [Dkt. 510 at 12].
40a
Federal interest may consider such criteria as . . . .’’
§ 2236(a)(3)(B) (emphasis added). By delegating
authority to the non-Federal interest in crafting the
fee, Congress intended to give broad discretion in
determining the size of the ship used to justify project
features and which vessels are ‘‘at least’’ comparable
in size.
The statutory scheme of the WRDA is a prime
example of the cooperative federalism that permeates
the administrative state. Enlarging federal programs
requires investment and execution by state and local
actors. However, this increased cooperation leaves
courts grappling with whether to afford deference to
state agency interpretations of federal law. With
scarce precedent, the Court finds Voigt v. Coyote Creek
Mining Co., LLC influential. 999 F.3d 555 (8th Cir.
2021). In Voigt, the Eighth Circuit grappled with
whether to afford deference to a state agency given
permitting authority under the Clean Air Act, 42
U.S.C. § 7401, et seq. On its first appeal, the court
determined that the state agency’s permitting
decision should be afforded deference. Voigt v. Coyote
Creek Mining Co., LLC, 980 F.3d 1191 (8th Cir. 2020),
aff’d on reh’g on other grounds, 999 F.3d 555 (8th Cir.
2021). However, on rehearing, the court sidestepped
the issue, finding for the defendant on alternate
grounds. Voigt, 999 F.3d at 562. While the court did
not explicitly rule on whether deference was
appropriate, it found that the state agency’s
‘‘permitting decision [was] a useful guide in reaching
41a
[its] decision regarding the most
interpretation of the regulations[.]’’13 Id.
reasonable
Public policy supports applying the Eighth Circuit’s
logic here: granting the non-Federal interest some
leeway will provide future vessel and cargo owners
with a manageable standard for determining whether
their vessels will be subject to the fee, so they will not
need to petition the Court for guidance. Such
frequent, individualized determinations would be
unworkable and kill any harbor construction project.
Accordingly, the Court treats Defendant’s decision to
charge vessels with design drafts in excess of twenty
feet as a significant but non-dispositive factor when
deciding whether Plaintiffs’ ships are comparable in
size. To clarify, non-Federal interests do not have
carte blanche to levy harbor fees. The Court merely
finds significance in SSND’s, the non-Federal
interest’s, determination that a certain size ship was
used to justify the Project, and SSND has broad
discretion in determining which ships ‘‘are at least
comparable in size[.]’’ § 2236(a)(3)(A).
iii. Count III
Count III rests on a misinterpretation of the
Ordinance and is not ripe for adjudication. It contends
that the Ordinance enacting the Fee is unlawful
because it allows Defendant to use the Fee to fund
construction costs for the entire Project, rather than
13
Although the Eighth Circuit did not give deference to the
state agency’s decision, it did not rule out the possibility of
affording such deference. The court appeared to apply prior
Supreme Court rulings, and the factors therein, regarding
deference to federal agency decisions to the decisions of the state
agency. Regardless, it is not within the providence of this Court
to create doctrine.
42a
for only the non-Federal share. Plaintiffs read the
Ordinance improperly. But, even if their reading of
the Ordinance was correct, their claim is not yet ripe.
The Ordinance reads: ‘‘User Fee authorized by this
ordinance will expire on January 1, 2049, or upon final
payment of all construction and construction
financing costs associated with the Project, whichever
comes first.’’ [Dkt. 1 at ¶ 65; Dkt. 1-1 at 6 (emphasis
added)]. By setting the expiration of the Fee after ‘‘all’’
construction costs are paid, Plaintiffs assert that the
Ordinance permits levying the Fee for costs related to
both the federal and non-Federal shares of the Project,
in violation Section 2236(a)(1)(A)(i). The statute
permits fees only ‘‘to finance the non-Federal share of
construction and operation and maintenance costs of
a navigation project for a harbor under the
requirements of section 2211 of this title[.]’’
§ 2236(a)(1)(A)(i). The complained-of portion of the
Ordinance imposes a temporal limitation on
Defendant’s ability to charge the Fee. It does not, and
indeed cannot, mandate that ships subject to the Fee
finance the federal portion of Project costs.
Plaintiffs have also not overcome the presumption of
regularity that attaches to government actions.
Courts presume that government actors act lawfully
and do not violate their own regulations. Sealed
Appellee 1 v. Sealed Appellant 1, 767 F.3d 418, 423
(5th Cir. 2013). While this presumption may be
overcome, Plaintiffs’ ‘‘assertion amounts to nothing
more than speculation that the Government may
intend to violate its own regulations, which we
normally do not assume.’’ Id.
Additionally, Plaintiffs’ claims regarding Count III
are speculative and therefore not ripe. ‘‘Ripeness is a
43a
justiciability doctrine ‘drawn from both Article III
limitations on judicial power and from prudential
reasons for refusing to exercise jurisdiction.’ ’’ Watkins
v. City of Arlington, No. 4:14-CV-381-O, 2015 WL
12733395, at *3 (N.D. Tex. Jan. 8, 2015) (citing Reno
v. Catholic Soc. Servs., Inc., 509 U.S. 43, 57 n.18, 113
S.Ct. 2485, 125 L.Ed.2d 38 (1993)). It ‘‘separates those
matters that are premature because the injury is
speculative and may never occur from those that are
appropriate for judicial review,’’ United Transp.
Union v. Foster, 205 F.3d 851, 857 (5th Cir. 2000), and
stops courts ‘‘from entangling themselves in abstract
disagreements over administrative policies . . . .’’
Abbott Labs. v. Gardner, 387 U.S. 136, 148–49, 87
S.Ct. 1507, 18 L.Ed.2d 681 (1967), abrogated on other
grounds by Califano v. Sanders, 430 U.S. 99, 97 S.Ct.
980, 51 L.Ed.2d 192 (1977). ‘‘A court should dismiss a
case for lack of ‘ripeness’ when the case is abstract or
hypothetical.’’ Monk v. Huston, 340 F.3d 279, 282 (5th
Cir. 2003).
When assessing ripeness, courts examine: ‘‘(1) the
fitness of the issues for judicial resolution, and (2) the
potential hardship to the parties caused by declining
court consideration.’’ Lopez v. City of Hous., 617 F.3d
336, 341 (5th Cir. 2010) (citing Texas v. United States,
497 F.3d 491, 498 (5th Cir. 2007), cert. denied, 555
U.S. 811, 129 S.Ct. 32, 172 L.Ed.2d 18 (2008)). When
declaratory judgment is sought, courts also
determine, (3) whether the case ‘‘presents sufficient
adversity and concreteness by examining whether an
‘actual controversy’ exists between the parties.’’ Bear
Creek Bible Church v. EEOC, No. 4:18-cv-00824-O,
571 F.Supp.3d 571, 597 (N.D. Tex. 2021) (citing Orix
44a
Credit Alliance, Inc. v. Wolfe, 212 F.3d 891, 896 (5th
Cir. 2000)).
First, ‘‘[a] case is generally ripe’’ and fit for review
‘‘if any remaining questions are purely legal ones.’’
New Orleans Pub. Serv., Inc. v. Council of City of New
Orleans, 833 F.2d 583, 587 (5th Cir. 1987). However,
a case may still be unfit for adjudication even if the
legal issues are clear:
[T]he question of fitness does not pivot solely on
whether a court is capable of resolving a claim
intelligently, but also involves an assessment of
whether it is appropriate for the court to
undertake the task. Federal courts cannot—
and should not—spend their scarce resources
on what amounts to shadow boxing. Thus, if a
plaintiff’s claim, though predominantly legal in
character, depends on future events that may
never come to pass, or that may not occur in the
form forecasted, then the claim is unripe.
Ernst & Young v. Depositors Econ. Prot. Corp., 45 F.3d
530, 537 (1st Cir. 1995). This is the case here.
Plaintiffs have not alleged that Defendant is using the
Fee to fund the federal portion of construction costs,
just that they might do so in the future. This is
speculation, and Plaintiffs require further factual
development to successfully lodge this claim.
Furthermore, Plaintiffs have not demonstrated that
they meet the ‘‘hardship’’ prong of the analysis. For
example, Plaintiffs have not pled that Defendant has
turned over the Fees to the federal government.
Dismissal is warranted.
45a
iv. Count IV
Count IV of Plaintiffs’ Complaint must be dismissed
because Section 2211 does not impose a cap on the
non-Federal interest’s spending. This Count alleges
that Defendant is using the Fee to fund a larger
portion of project costs than the statute permits.
Section 2236(a)(1) permits non-Federal interests to
levy fees in ‘‘amounts not to exceed those necessary . . .
to finance the non-Federal share of construction and
operation and maintenance costs of a navigation
project for a harbor under the requirements of section
2211[.]’’ 33 U.S.C. § 2236(a)(1)(A)(i) (emphasis added).
Pursuant to Section 2211:
The non-Federal interests for a navigation
project for a harbor . . . shall pay, during the
period of construction of the project, the
following costs associated with general
navigation features: . . . (B) 25 percent of the
cost of construction of the portion of the project
which has a depth in excess of 20 feet but not in
excess of 50 feet[.]
33 U.S.C. § 2211(a)(1)(B) (emphasis added). By
limiting the use of fees to ‘‘amounts not to exceed those
necessary’’ to finance a harbor improvement project,
Plaintiffs claim that Section 2211 imposes a cap on fee
collection for non-Federal interests. Plaintiffs concede
that non-Federal interests may contribute more than
twenty-five percent of the cost of construction. [Dkt.
23 at 24–25]. However, they claim Defendant may not
use port fees to fund any voluntary additional cost
sharing.
Plaintiffs’ reading is incorrect. The language of
limitation in Section 2236 does not transform the
percentages of Section 2211 into a cap on non-Federal
46a
funding. Rather, it limits what the fee may fund to
construction, operation, and maintenance costs.
Plaintiffs are not exempt from paying their share of
costs through a user fee merely because the nonFederal interest assumes a larger percentage of
project costs. And Plaintiffs’ concession that
Defendant may voluntarily assume a greater portion
of the Project’s costs undermines their argument. It
cannot be that Section 2211 imposes a cap for the feebased non- Federal share but not for the alternatively
funded non-Federal share because that reading would
require an express statutory provision. Section
2236(a)(1)’s language—‘‘amount not to exceed those
necessary’’—is not enough.
Even without Plaintiffs’ concession, the law itself
expressly permits non-Federal interests to assume a
higher share of project costs. Under 33 U.S.C. § 2280,
the projected costs listed in WRDA-14 form the
maximum federal share of project costs. § 2280(a).14
However, Section 2280(b) expressly permits ‘‘the
Secretary [to] accept funds from a non-Federal
interest for any authorized water resources
development project that has exceeded its maximum
cost under subsection (a), and use such funds to carry
14
Although the statute was originally enacted in 1986, it
expressly encompasses projected costs listed in any subsequent
WRDA enactment: ‘‘In order to insure against cost overruns,
each total cost set forth with respect to a project for water
resources development and conservation and related purposes
authorized to be carried out by the Secretary in this Act or in a
law enacted after the date of the enactment of this Act, including
the Water Resources Development Act of 1988, or in an
amendment made by this Act or any later law with respect to such
a project shall be the maximum cost of that project[.]’’ 33 U.S.C.
§ 2280(a) (emphasis added).
47a
out such project, if the use of such funds does not
increase the Federal share of the cost of such project.’’
§ 2280(b). This clear mandate permits non- Federal
interests to contribute additional funds within their
discretion.
Even without Section 2280(b)’s command, Plaintiffs’
reading requires that the Court view the percentages
listed in Section 2211 as a cap on the non-Federal
share. However, nothing in the statute’s text or
legislative history suggests this. The term ‘‘shall pay’’
indicates that Section 2211 imposes either a spending
floor or discretionary guidelines for cost sharing
between federal and non-Federal interests. The
Supreme Court has found that ‘shall’ can be
mandatory or precatory. See Maine Cmty. Health
Options v. United States, ––– U.S. ––––, 140 S. Ct.
1308, 1320, 206 L.Ed.2d 764 (2020) (holding that
‘shall’ indicates a mandatory requirement); see also
Cairo & F.R. Co. v. Hecht, 95 U.S. 168, 170, 24 L.Ed.
423 (1877) (noting ‘shall’ means ‘may’ in certain
contexts); Gutierrez de Martinez v. Lamagno, 515 U.S.
417, 429–30, 115 S.Ct. 2227, 132 L.Ed.2d 375 (1995);
Castle Rock v. Gonzales, 545 U.S. 748, 760–62, 125
S.Ct. 2796, 162 L.Ed.2d 658 (2005) (concluding that
the word ‘‘shall’’ should not be read as requiring the
police to take action); West Wis., Ry. Co., v. Foley, 94
U.S. 100, 103, 24 L.Ed. 71 (1877).
The Court need not rule on whether the percentages
in Section 2211 are mandatory or precatory because
the result would be the same. Should Section 2211 be
read as precatory, then non-Federal interests would
be able to assume a larger or smaller portion of project
costs. This variable cost structure would afford
48a
discretion in determining the breakdown of project
costs.
However, if the statute is read as mandatory, such
percentages form a minimum contribution from nonFederal interests. It is clear from the statute’s
legislative history that Congress intended to increase
the involvement of non-Federal interests in
constructing and improving America’s ports. Prior to
the WRDA-86, Congress appropriated funds for only
three to four projects every year. 132 Cong. Rec. S3402
(1986). Because of the fierce competition to secure
funding, influence within the people’s chamber
became more important than need. Id. By requiring
local investment, Congress incentivized only those
non-Federal interests that actually needed harbor
improvements to apply for the funding. Id. Given this
motivation to involve non-Federal interests in
‘‘bidding’’ for congressional funding, it would be
absurd to think that Section 2211 forms a ceiling
because it would deprive local interests of the ability
to demonstrate the need for congressional funds. A
principal cosponsor of the statute, Representative
Glenn Anderson, noted that ‘‘[n]ew cost-sharing rules
have been implemented, which are nearly identical to
those proposed by the administration, that require
non-Federal interests to pay a much greater share of
project costs.’’ 132 Cong. Rec. 11561 (1986). It is
unlikely that Congress desired the inclusion of nonFederal funds but imposed a cap on such funding.
Rather, the twenty-five percent minimum assured
that the non-Federal interest had a concrete stake in
a project’s success.
Furthermore, subsequent congressional enactments
on cost sharing for harbor improvement projects
49a
demonstrate that Section 2211 imposed minimum
contribution levels. Where two statutes ‘‘deal with
precisely the same subject matter,’’ they may be read
in pari materia. United States v. Stewart, 311 U.S. 60,
64, 61 S.Ct. 102, 85 L.Ed. 40 (1940). All statutes ‘‘in
pari materia are to be taken together, as if they were
one law.’’ Id.; see also Cope v. Cope, 137 U.S. 682, 687–
88, 11 S.Ct. 222, 34 L.Ed. 832 (1891); United States v.
Freeman, 3 How. 556, 564, 11 L.Ed. 724 (1845). The
WRDA-86 and the WRDA-14 are to be read in pari
materia. Both statutes deal with harbor expansion
projects and provide a cost breakdown for the federal
and non-Federal share. For this Project, Congress
provided a projected split of $748,070,00 in federal
funding and $365,970,000 in non-Federal funding for
the Project. These amounts, which exceed the
percentages listed in Section 2211, reflect
congressional intent to depart from the percentages in
Section 2211.
v.
Count V
Section 2236(a)(4) of WRDA-86 provides that ‘‘dues
may be levied only on a vessel entering or departing
from a harbor and its cargo on a fair and equitable
basis.’’ 33 U.S.C. § 2236(a)(4). Plaintiffs contend that
the Fees are unlawful because SNND imposes a
higher Fee on hydrocarbon cargo than nonhydrocarbon cargo with no ‘‘legitimate justification.’’
[Dkt. 1 at ¶ 82]. The Court disagrees and finds that
this discrepancy is reasonable.
The Fee for hydrocarbon cargo is $0.20 per short ton
with a maximum of $0.35 per short ton, and the Fee
for non-hydrocarbon cargo is $0.02 per short ton with
a maximum of $0.035 per short ton. [Dkt. 1-1 at 7].
This discrepancy is reasonable based on the Section
50a
2236(a)(4) factors for the non-Federal interest to
consider when formulating fees:
a. the direct and indirect cost of construction,
operations, and maintenance, and providing
the facilities and services under [33 U.S.C.
§ 2236(a)(1)];
b. the value of those facilities and services to
the vessel and cargo;
c. the public policy or interest served; and
d. any other pertinent factors.
§ 2236(a)(4).
SNND reasonably decided to impose disparate Fees
depending on the type of cargo so that: (1) the vessels
and cargo benefitting the most from the
improvements would fund the majority of the costs; (2)
the Fee remains approximately equal when measured
as a percentage of the cargo’s value; and (3) the Fee
furthers public policy by ‘‘funding improvements
intended to secure the Waterway’s position as
America’s
leading
import/export
harbor
for
hydrocarbons.’’ [Dkt. 5 at 31].
When calculating harbor fees, a non-Federal
interest must consider ‘‘the value of’’ the facilities ‘‘to
the vessel and cargo’’ pursuant to Section
2236(a)(4)(B). The Project itself was designed to
benefit the hydrocarbon industry, and hydrocarbons
make up a substantial percentage of the tonnage for
both Beaumont and Port Arthur. [Dkt. 5-10 at 4, 8].15
15
Plaintiffs argue that the Court may not take judicial notice
of Exhibit 9, [Dkt. 5-10], because it is from 2011; therefore, it
cannot be used to determine the Waterway’s hydrocarbon traffic
in 2021 when the Ordinance was passed. But Defendant does not
ask the Court to forward-model 2021 statistics from the
51a
SNND determined it was proper to charge
hydrocarbon carriers more because the improvements
were largely geared to their benefit. [Dkt. 5 at 32].
Whether hydrocarbon carriers are the only vessels
that would benefit from deeper channels is not
dispositive. The same is true for whether all
hydrocarbon cargoes are more valuable than all nonhydrocarbon cargoes. The only material question is
whether SNND appropriately considered this factor
when crystallizing the Project’s plan. The Court finds
that SNND did so. 16 Imposing higher fees on
hydrocarbon carriers also comports with the statute
because it better reflects the value that the facilities
add to the vessel and cargo. This is because the value
of hydrocarbon cargo per ton is generally much higher
than the value of non-hydrocarbon cargo. 17
feasibility study, nor does the Court need to engage in this
exercise. The feasibility study is cited and noted for the purpose
of showing those factors that SNND considered when
formulating the Project and its Fees. Furthermore, the Court
may take judicial notice of ‘‘publicly-available documents and
transcripts produced by [government agencies], which were
matters of public record directly relevant to the issue at hand.’’
Funk v. Stryker Corp., 631 F.3d 777, 783 (5th Cir. 2011). Thus,
the Court takes judicial notice of the Feasibility Report.
16
SNND need not ‘‘draw the perfect line’’—just a ‘‘rational
line.’’ See Armour v. City of Indianapolis, 566 U.S. 673, 685, 132
S.Ct. 2073, 182 L.Ed.2d 998 (2012).
17
As Defendant explains in its Motion to Dismiss:
By way of illustration, in April 2021—the month when
the Ordinance was passed—statistics published by the
U.S. Energy Information Administration indicated that
the price of American LNG for export was about $5.92
per thousand cubic feet, or about $318 per short ton
(given that 1 short ton is 53,682.56 cubic feet). Natural
Gas, U.S. Energy Info. Admin. (Sept. 30, 2021),
52a
Additionally, SSND and USACE created the Project,
in part, to benefit the hydrocarbon industry. [Dkt. 5-3
at 3, 7, 12–14]. Thus, the Fee is equitable when
considering the ‘‘value of those facilities and services
to the vessel and cargo.’’ § 2236(a)(4)(B).
Furthermore, a non-Federal interest must also
consider public policy. § 2236(a)(4)(C). The Project
itself is intended to benefit the hydrocarbon industry.
[Dkt. 5-3 at 3, 7, 12–14]. The Ordinance itself
expressly states that the Navigation District’s Board
of Commissioners considered the statutory factors like
‘‘the cost of construction, operations, [and] the value
of the services to the vessel and cargo.’’ [Dkt. 1-1 at 3].
Therefore, this Court concludes that SNND
reasonably imposed a higher Fee for hydrocarbon
carriers because it considered and applied the
relevant statutory factors.
https://bit.ly/3l8RAag. A 20-cent harbor due on cargo
worth $318 per ton equates to dues of about 0.063% based
on the value of the cargo. The average price for of
nonhydrocarbon cargo tends to be much lower, often
around $30 per ton (e.g., $28 per ton for iron and steel
slag, $29 per ton for peat, $33 per ton for pumice rock,
and between $35 and $50 per ton for sand and gravel).
See U.S. Dep’t of Interior, U.S. Geological Survey,
Mineral Commodity Summaries 2020, at 86, 118, 128,
142 (Jan. 2020), https://on.doi.gov/3D3Bh4S. A 2-cent
harbor due on cargo worth $30 per ton equates to dues of
0.066% based on the value of the cargo—almost exactly
the same as the dues for hydrocarbons.
[Dkt. 5 at 25 n.12]. The Court may take judicial notice of these
government statistics because their accuracy and source cannot
be questioned. Fed. R. Evid. 201(b); Funk, 631 F.3d at 783;
Victoria Cruises, Inc. v. Changjiang Cruise Overseas Travel Co.,
630 F. Supp. 2d 255, 263 n.3 (E.D.N.Y. 2008).
53a
vi. Counts VI & VII
Count VI seeks a declaratory judgment that
Defendant’s Fee violates the WRDA-86 and is
therefore unenforceable. Count VII seeks an
injunction barring SNND from implementing the Fee.
Both are pendant upon Plaintiffs’ previous
allegations, Counts I through V. Because Counts I
through V are dismissed, the Court also dismisses
Counts VI and VII. See Adams v. Nissan N. Am., Inc.,
395 F. Supp. 3d 838, 856 (S.D. Tex. 2018) (‘‘Defendant
correctly contends that Plaintiffs’ claims for
declaratory and injunctive relief are derivative of
their other claims, and if the other claims are
dismissed, so too must the claims for declaratory and
injunctive relief be dismissed.’’).
vii. Leave to Amend
A district court may deny leave to amend when ‘‘the
proposed amendment would be futile because it could
not survive a motion to dismiss.’’ Rio Grande Royalty
Co. v. Energy Transfer Partners, L.P., 620 F.3d 465,
468 (5th Cir. 2010); see also Foman v. Davis, 371 U.S.
178, 182, 83 S.Ct. 227, 9 L.Ed.2d 222 (1962) (holding
that denying leave to amend is within the trial court’s
discretion so long as there is an appropriate reason
given, including futility). An amended complaint is
futile when the plaintiff has pled his or her best case,
and there are no ‘‘additional facts that could be alleged
in a second amended complaint that could not have
been alleged in the [original complaint].’’ Heck v.
Orion Grp. Holdings, Inc., 468 F. Supp. 3d 828, 863
(S.D. Tex. 2020).
Here, there are no additional facts that Plaintiffs
may plead that would change the outcome of this
54a
Court’s decision. This case rests on issues of law, and
there is no reasonable possibility that a change in
facts would lead to a change in outcome—any
attempts at amendment are futile. Therefore, this
case is dismissed with prejudice and leave to amend is
not given.
IV. CONCLUSION
After a careful review of all pleadings, facts, and
applicable law, this Court reaches a decision on
Defendant’s Motion to Dismiss.
It is therefore ORDERED that Defendant’s Motion
to Dismiss, [Dkt. 5], is hereby GRANTED.
It is further ORDERED that Counts IVII of
Plaintiffs’ Complaint, [Dkt. 1], are hereby
DISMISSED WITH PREJUDICE.
It is further ORDERED that Parties’ Joint Motion
for Protective Orders [Dkt. 34] is hereby DENIED AS
MOOT.
55a
APPENDIX C
_________
UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
_______
No. 22-40158
_______
BG GULF COAST LNG, L.L.C.; PHILLIPS 66 COMPANY,
Plaintiffs-Appellants,
v.
SABINE-NECHES NAVIGATION DISTRICT OF
JEFFERSON COUNTY, TEXAS,
Defendant-Appellee.
_______
Appeal from the United States District Court
for the Eastern District of Texas
USDC No. 1:21-CV-470
_______
Filed: October 25, 2022
_______
ON PETITION FOR REHEARING AND
REHEARING EN BANC
_______
56a
Before STEWART, ELROD, and GRAVES, Circuit Judges.
PER CURIAM:
The petition for panel rehearing is DENIED. Because
no member of the panel or judge in regular active
service requested that the court be polled on rehearing
en banc (Fed. R. App. P. 35 and 5th Cir. R. 35), the
petition for rehearing en banc is DENIED.
*
*
Judge Carolyn Dineen King, Jacques L. Wiener, Jr., James L.
Dennis, did not participate in the consideration of the rehearing
en banc.
57a
APPENDIX D
_________
CONSTITUTIONAL AND STATUTORY
PROVISIONS INVOLVED
_________
1.
U.S. Const. art. 1, § 8, cls. 1, 3 provide in
pertinent part:
[1] The Congress shall have Power * * *
***
[3] To regulate Commerce with foreign Nations, and
among the several States, and with the Indian Tribes;
*
2.
*
*
*
*
U.S. Const. art. 1, § 10, cls. 2-3 provide:
[2] No State shall, without the Consent of the
Congress, lay any Imposts or Duties on Imports or
Exports, except what may be absolutely necessary for
executing it’s inspection Laws: and the net Produce of
all Duties and Imposts, laid by any State on Imports
or Exports, shall be for the Use of the Treasury of the
United States; and all such Laws shall be subject to
the Revision and Controul of the Congress.
[3] No State shall, without the Consent of Congress,
lay any Duty of Tonnage, keep Troops, or Ships of War
in time of Peace, enter into any Agreement or
Compact with another State, or with a foreign Power,
or engage in War, unless actually invaded, or in such
imminent Danger as will not admit of delay.
*
*
*
*
*
58a
3.
33 U.S.C. § 2211 provides in pertinent part:
Harbors
(a) Construction
(1) Payments during construction
The non-Federal interests for a navigation
project for a harbor or inland harbor, or any
separable element thereof, on which a contract
for physical construction has not been awarded
before June 10, 2014, shall pay, during the period
of construction of the project, the following costs
associated with general navigation features:
(A) 10 percent of the cost of construction of the
portion of the project which has a depth not in
excess of 20 feet; plus
(B) 25 percent of the cost of construction of the
portion of the project which has a depth in
excess of 20 feet but not in excess of 50 feet; plus
(C) 50 percent of the cost of construction of the
portion of the project which has a depth in
excess of 50 feet.
***
(e) Agreement
Before initiation of construction of a project to which
this section applies, the Secretary and the nonFederal interests shall enter into a cooperative
agreement according to the provisions of section
1962d–5b of title 42. The non-Federal interests shall
agree to—
(1) provide to the Federal Government lands,
easements, and rights-of-way, including those
necessary for dredged material disposal facilities,
and perform the necessary relocations required for
59a
construction, operation, and maintenance of such
project;
(2) hold and save the United States free from
damages due to the construction or operation and
maintenance of the project, except for damages due
to the fault or negligence of the United States or
its contractors;
(3) provide to the Federal Government the nonFederal share of all other costs of construction of
such project; and
(4) in the case of a deep-draft harbor, be
responsible for the non-Federal share of operation
and maintenance required by subsection (b) of this
section.
*
4.
*
*
*
*
33 U.S.C. § 2232 provides in pertinent part:
Construction of water resources development
projects by non-Federal interests
***
(d) Credit or reimbursement
(1) General rule
Subject to paragraph (3), a project or separable
element of a project carried out by a non-Federal
interest under this section shall be eligible for
credit or reimbursement for the Federal share of
work carried out on a project or separable
element of a project if—
(A) before initiation of construction of the
project or separable element—
(i) the Secretary approves the plans for
construction of the project or separable
60a
element of the project by the non-Federal
interest;
(ii) the Secretary determines, before
approval of the plans, that the project or
separable element of the project is feasible;
and
(iii) the non-Federal interest enters into a
written agreement with the Secretary under
section 1962d–5b of title 42, including an
agreement to pay the non-Federal share, if
any, of the cost of operation and maintenance
of the project; and
(B) the Secretary determines that all Federal
laws and regulations applicable to the
construction of a water resources development
project, and any conditions identified under
subsection (b)(1)(B), were complied with by the
non-Federal interest during construction of the
project or separable element of the project.
(2) Application of credit
The Secretary may apply credit toward—
(A) the non-Federal share of authorized
separable elements of the same project; or
(B) subject to the requirements of this section
and section 2223 of this title, at the request of
the non-Federal interest, the non-Federal
share of a different water resources
development project.
(3) Requirements
The Secretary may only apply credit or provide
reimbursement under paragraph (1) if—
61a
(A) Congress has authorized construction of
the project or separable element of the project;
(B) the Secretary certifies that the project has
been constructed in accordance with—
(i) all applicable permits or approvals; and
(ii) this section; and
(C) in the case of reimbursement,
appropriations are provided by Congress for
such purpose.
(4) Monitoring
The Secretary shall regularly monitor and
audit any water resources development project,
or separable element of a water resources
development project, constructed by a nonFederal interest under this section to ensure
that—
(A) the construction is carried out in
compliance with the requirements of this
section; and
(B) the costs
reasonable.
of
the
construction
are
(5) Discrete segments
(A) In general
The Secretary may authorize credit or
reimbursement under this subsection for
carrying out a discrete segment of a federally
authorized water resources development
project, or separable element thereof, before
final completion of the project or separable
element if—
62a
(i) except as provided in clause (ii), the
Secretary determines that the discrete
segment satisfies the requirements of
paragraphs (1) through (4) in the same
manner as the project or separable element;
and
(ii) notwithstanding paragraph (1)(A)(ii),
the Secretary determines, before the approval
of the plans under paragraph (1)(A)(i), that
the discrete segment is technically feasible
and environmentally acceptable.
(B) Determination
Credit or reimbursement may not be made
available to a non-Federal interest pursuant to
this paragraph until the Secretary determines
that—
(i) the construction of the discrete segment
for which credit or reimbursement is
requested is complete; and
(ii) the construction is consistent with the
authorization of the applicable water
resources development project, or separable
element thereof, and the plans approved
under paragraph (1)(A)(i).
(C) Written agreement
(i) In general
As part of the written agreement required
under paragraph (1)(A)(iii), a non-Federal
interest to be eligible for credit or
reimbursement under this paragraph shall—
(I) identify any discrete segment that the
non-Federal interest may carry out; and
63a
(II) agree to the completion of the water
resources development project, or separable
element thereof, with respect to which the
discrete segment is a part and establish a
timeframe for such completion.
(ii) Remittance
If a non-Federal interest fails to complete a
water resources development project, or
separable element thereof, that it agreed to
complete under clause (i)(II), the non-Federal
interest shall remit any reimbursements
received under this paragraph for a discrete
segment of such project or separable element.
(D) Discrete segment defined
In this paragraph, the term ‘‘discrete
segment’’ means a physical portion of a water
resources development project to be carried out,
or separable element thereof—
(i) described by a non-Federal interest in a
written agreement required under paragraph
(1)(A)(iii); and
(ii) that the non-Federal interest can
operate and maintain, independently and
without creating a hazard, in advance of final
completion
of
the
water
resources
development project, or separable element
thereof.
*
*
*
*
*
64a
5.
33 U.S.C. § 2236 provides in pertinent part:
Port or harbor dues
(a) Consent of Congress
Subject to the following conditions, a non-Federal
interest may levy port or harbor dues (in the form of
tonnage duties or fees) on a vessel engaged in trade
entering or departing from a harbor and on cargo
loaded on or unloaded from that vessel under clauses
2 and 3 of section 10, and under clause 3 of section 8,
of Article 1 of the Constitution:
(1) Purposes
Port or harbor dues may be levied only in
conjunction with a harbor navigation project
whose construction is complete (including a usable
increment of the project) and for the following
purposes and in amounts not to exceed those
necessary to carry out those purposes:
(A)(i) to finance the non-Federal share of
construction and operation and maintenance
costs of a navigation project for a harbor under
the requirements of section 2211 of this title; or
(ii) to finance the cost of construction and
operation and maintenance of a navigation
project for a harbor under section 2232 or 2233
of this title; and
(B) provide emergency response services in
the harbor, including contingency planning,
necessary personnel training, and the
procurement of equipment and facilities.
65a
(2) Limitation on port or harbor dues for
emergency service
Port or harbor dues may not be levied for the
purposes described in paragraph (1)(B) of this
subsection after the dues cease to be levied for the
purposes described in paragraph (1)(A) of this
subsection.
(3) General limitations
(A) Port or harbor dues may not be levied
under this section in conjunction with a
deepening feature of a navigation improvement
project on any vessel if that vessel, based on its
design draft, could have utilized the project at
mean low water before construction. In the case
of project features which solely—
(i) widen channels or harbors,
(ii) create or enlarge bend easings, turning
basins or anchorage areas, or provide
protected areas, or
(iii) remove obstructions to navigation,
only vessels at least comparable in size to those
used to justify these features may be charged
under this section.
(B) In developing port or harbor dues that
may be charged under this section on vessels
for project features constructed under this
subchapter, the non-Federal interest may
consider such criteria as: elapsed time of
passage, safety of passage, vessel economy of
scale, under keel clearance, vessel draft, vessel
squat, vessel speed, sinkage, and trim.
66a
(C) Port or harbor dues authorized by this
section shall not be imposed on—
(i) vessels owned and operated by the
United States Government, a foreign country,
a State, or a political subdivision of a country
or State, unless engaged in commercial
services;
(ii) towing vessels, vessels engaged in
dredging activities, or vessels engaged in
intraport movements; or
(iii) vessels with design drafts of 20 feet or
less when utilizing general cargo and deepdraft navigation projects.
(4) Formulation of port or harbor dues
Port or harbor dues may be levied only on a
vessel entering or departing from a harbor and its
cargo on a fair and equitable basis. In formulating
port and harbor dues, the non-Federal interest
shall consider—
(A) the direct and indirect cost of construction,
operations, and maintenance, and providing
the facilities and services under paragraph (1)
of this subsection;
(B) the value of those facilities and services to
the vessel and cargo;
(C) the public policy or interest served; and
(D) any other pertinent factors.
(5) Notice and hearing
(A) Before the initial levy of or subsequent
modification to port or harbor dues under this
section, a non-Federal interest shall transmit
to the Secretary—
67a
(i) the text of the proposed law, regulation,
or ordinance that would establish the port or
harbor dues, including provisions for their
administration, collection, and enforcement;
(ii) the name, address, and telephone
number of an official to whom comments on
and requests for further information on the
proposal are to be directed;
(iii) the date by which comments on the
proposal are due and a date for a public
hearing on the proposal at which any
interested party may present a statement;
however, the non-Federal interest may not set
a hearing date earlier than 45 days after the
date of publication of the notice in the Federal
Register required by subparagraph (B) of this
paragraph or set a deadline for receipt of
comments earlier than 60 days after the date
of publication; and
(iv) a written statement signed by an
appropriate official that the non-Federal
interest agrees to be governed by the
provisions of this section.
(B) On receiving from a non-Federal interest
the information required by subparagraph (A)
of this paragraph, the Secretary shall transmit
the material required by clauses (i) through (iii)
of subparagraph (A) of this paragraph to the
Federal Register for publication.
(C) Port or harbor dues may be imposed by a
non-Federal interest only after meeting the
conditions of this paragraph.
68a
(6) Requirements on non-Federal interest
A non-Federal interest shall—
(A) file a schedule of any port or harbor dues
levied under this subsection with the Secretary
and the Federal Maritime Commission, which
the Commission shall make available for public
inspection;
(B) provide to the Comptroller General of the
United States on request of the Comptroller
General any records or other evidence that the
Comptroller General considers to be necessary
and appropriate to enable the Comptroller
General to carry out the audit required under
subsection (b) 1 of this section;
(C) designate an officer or authorized
representative, including the Secretary of the
Treasury acting on a cost-reimbursable basis,
to receive tonnage certificates and cargo
manifests from vessels which may be subject to
the levy of port or harbor dues, export
declarations from shippers, consignors, and
terminal operators, and such other documents
as the non-Federal interest may by law,
regulation, or ordinance require for the
imposition, computation, and collection of port
or harbor dues; and (D) consent expressly to the
exclusive exercise of Federal jurisdiction under
subsection (c) of this section.
69a
APPENDIX E
_________
[COMPLAINT EXHIBIT B]
_______
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF TEXAS
BEAUMONT DIVISION
_______
BG GULF COAST LNG, LLC AND PHILLIPS 66
COMPANY,
Plaintiffs,
v.
SABINE-NECHES NAVIGATION DISTRICT OF JEFFERSON
COUNTY, TEXAS,
Defendant.
_______
Civil Action No. 1:21-cv-00470
_______
User Fees Paid by BG Gulf Coast LNG, LLC
Load
Date
User Fee
Charged
Fully Laden
Sailing Draft
1-MayMagdala
21
$15,887.00
Fwd 37.40 / Aft
37.23
13-MayGaslog Gibraltar
21
$15,981.02
Fwd 37.76 / Aft
37.76
Ship Name
70a
20-MayPan Europe
21
$15,918.72
Fwd 37.56 / Aft
37.76
21-MaySCF Barents
21
$15,913.92
Fwd 37.95 / Aft
38.05
26-May- Castillo de
21
Santisteban
$15,462.21
Fwd 36.05 / Aft
37.76
31-MayGaslog Genoa
21
$16,357.03
Fwd 38.35 / Aft
38.38
4-JunMaran Gas Roxana
21
$15,888.87
Fwd 37.76 / Aft
37.76
3-Jun- FLEX
21
COURAGEOUS
$15,531.92
Fwd 37.40 / Aft
37.43
11-JunMaran Gas Spetses
21
$15,843.64
Fwd 36.08 / Aft
36.25
19-Jun- Rias Baixas
21
Knutsen
$16,251.29
Fwd 37.76 / Aft
37.76
24-JunMaran Gas Ulysses
21
$15,489.64
Fwd 38.35 / Aft
38.38
28-Jun- Maran Gas
21
Olympias
$15,883.49
Fwd 36.41 / Aft
36.41
5-Jul-21 Minerva Psara
$16,138.92
Fwd 37.69 / Aft
37.76
14-JulLNGships Athena
21
$15,553.00
Fwd 36.08 / Aft
36.97
23-JulMaran Gas Achilles
21
$16,072.34
Fwd 37.40 / Aft
37.43
28-JulSCF MITRE
21
$15,808.09
Fwd 37.76 / Aft
37.82
3-AugGlobal Star
21
$15,574.72
Fwd 37.76 / Aft
37.56
71a
11-AugMinerva Psara
21
$15,873.01
Fwd 37.56 / Aft
37.53
17-AugSevilla Knutsen
21
$15,946.96
Fwd 37.59 / Aft
37.76
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.