Amicus Curiae Brief — Dakota Access, LLC, Petitioner v. Standing Rock Sioux Tribe, et al.
Supreme Court briefNov 17, 2021
Ask Donna
What actually matters in this document.
Text
No. 21-560
In the
Supreme Court of the United States
DAKOTA ACCESS, LLC,
Petitioner,
v.
STANDING ROCK SIOUX TRIBE, et al.,
Respondents.
On Petition for a Writ of Certiorari to the U.S. Court
of A ppeals for the District of Columbia Circuit
BRIEF OF THE AMERICAN FUEL &
PETROCHEMICAL MANUFACTURERS, AMERICAN
PETROLEUM INSTITUTE, ASSOCIATION OF OIL
PIPE LINES AND NATIONAL ASSOCIATION OF
CONVENIENCE STORES AS AMICI CURIAE IN
SUPPORT OF PETITIONER DAKOTA ACCESS, LLC
David H. Coburn
Counsel of Record
Joshua H. Runyan
Cynthia L. Taub
Steptoe & Johnson LLP
1330 Connecticut Avenue, NW
Washington, DC 20036
(202) 429-3000
dcoburn@steptoe.com
Counsel for Amici Curiae
308701
i
TABLE OF CONTENTS
INTEREST OF AMICUS CURIAE ............................. 1
INTRODUCTION AND SUMMARY OF
ARGUMENT ..................................................... 4
ARGUMENT ............................................................... 6
I.
II.
THIS COURT SHOULD REVIEW THE D.C. CIRCUIT’S
HEIGHTENED NEPA STANDARD ......................... 6
A.
The D.C. Circuit’s Requirement that the
Corps Must “Convince the Court”
Conflicts with Precedent of this Court
and Other Circuits ................................. 7
B.
The D.C. Circuit Erred in Ordering the
Corps to Prepare an EIS Based on the
Court’s Finding of Controversy ........... 10
THE QUESTIONS PRESENTED IN THIS CASE ARE
EXCEPTIONALLY IMPORTANT FOR INDUSTRY .... 13
CONCLUSION .......................................................... 24
ii
TABLE OF AUTHORITIES
Page(s)
Cases
Coliseum Square Ass’n, Inc. v. Jackson,
465 F.3d 215 (5th Cir. 2006) ................................ 11
Dep’t of Transp. v. Public Citizen,
541 U.S. 752 (2004) .................................... 9, 10, 12
Hillsdale Envtl. Loss Prevention, Inc. v.
U.S. Army Corps of Eng’rs,
702 F.3d 1156 (10th Cir. 2012) .................. 9, 10, 13
Ind. Forest All., Inc. v. U.S. Forest Serv.,
325 F.3d 851 (7th Cir. 2003) ............................ 9, 11
Kleppe v. Sierra Club,
427 U.S. 390 (1976) ................................................ 8
Marsh v. Oregon Natural Resources
Council,
490 U.S. 360 (1989) .................................... 8, 10, 11
McGuinness v. U.S. Forest Serv.,
741 F. App’x 915 (4th Cir. 2018).......................... 10
Motor Vehicle Mfrs. Ass’n of U.S., Inc. v.
State Farm Mut. Auto. Ins. Co.,
463 U.S. 29 (1983) .................................................. 8
Nat’l Parks Conservation Ass’n v.
Semonite,
916 F.3d 1075 (D.C. Cir. 2019) ...................... 11, 12
iii
North Carolina v. FAA,
957 F.2d 1125 (4th Cir. 1992) ................................ 9
Save Our Cumberland Mountains v.
Kempthorne,
453 F.3d 334 (6th Cir. 2006) .................................. 9
Sierra Club v. Clinton,
746 F. Supp.2d 1025 (D. Minn. 2010) ................. 18
Sierra Club v. U.S. Forest Serv.,
828 F.3d 402 (6th Cir. 2016) ................................ 11
Soc’y Hill Towers Owners’ Ass’n v.
Rendell,
210 F.3d 168 (3d Cir. 2000) ................................. 10
Standing Rock Sioux Tribe v. U.S. Army
Corps of Eng’rs,
255 F. Supp. 3d 101 (D.D.C. 2017) ...................... 18
Standing Rock Sioux Tribe v. U.S. Army
Corps of Eng’rs,
282 F. Supp. 3d 91 (D.D.C. 2017) ........................ 12
Town of Marshfield v. FAA,
552 F.3d 1 (1st Cir. 2008) .................................... 10
Wetlands Action Network v. U.S. Army
Corps of Engineers,
222 F.3d 1105 (9th Cir. 2000) .............................. 11
Wild Wilderness v. Allen,
871 F.3d 719, 729 (9th Cir. 2017) ........................ 13
iv
WildEarth Guardians v. Conner,
920 F.3d 1245 (10th Cir. 2019) .............................. 9
Statutes
33 U.S.C. §§ 1321(j)(5)(D)(iii)-(iv) ............................. 17
49 U.S.C. § 60102(a)(1) ............................................. 17
49 U.S.C. § 60121(a) .................................................. 19
Council on Environmental Quality, The
Fourth Report on Cooperating
Agencies in Implementing the
Procedural Requirements of the
National Environmental Policy Act,
Attachment A (Oct. 4, 2016),
https://ceq.doe.gov/docs/ceqreports/Attachment-A-FourthCooperating-AgencyReport_Oct2016.pdf ............................................. 15
Pipeline Safety Act, 49 U.S.C. §§ 60101,
et seq. ...................................................................... 5
Other Authorities
40 C.F.R. § 1508.27 ..................................................... 6
40 C.F.R. §§ 1508.27(b)(1)–(10)................................. 10
40 C.F.R. § 1508.27(b)(4) ....................................... 6, 13
49 C.F.R. Parts 194-195 ............................................ 17
49 C.F.R. § 194.105 ................................................... 17
v
49 C.F.R. § 195.452 ................................................... 17
49 C.F.R. § 195.452(i)(3)............................................ 17
51 Fed. Reg. 15,618 (Apr. 25, 1986) .......................... 13
85 Fed. Reg. 43,304 (July 16, 202 ....................... 14, 15
Council on Environmental Quality,
Environmental Impact Statement
Timelines (2010-2018) (June 12,
2020), https://ceq.doe.gov/docs/nepapractice/CEQ_EIS_Timeline_Report_
2020-6-12.pdf ........................................................ 15
Exec. Order No. 13,990, 86 Fed. Reg.
7,037 (Jan. 25, 2021) ............................................ 16
INTEREST OF AMICUS CURIAE1
Amici are trade associations whose members have
a significant interest in the reliable and consistent
application of the National Environmental Policy Act
(“NEPA”) to assess impacts resulting from pipeline
and other infrastructure projects advanced by Amici’s
members. Collectively, Amici represent entities that
account for, among other things, the vast majority of
petroleum
products
that
are
transported,
manufactured, and sold in the United States,
including crude oil and other hydrocarbons that are
transported by pipelines and other modes in
interstate and foreign commerce.
The
American
Fuel
&
Petrochemical
Manufacturers (“AFPM”) is a national trade
association representing most U.S. refining and
petrochemical manufacturing capacity.
AFPM’s
member refineries and petrochemical facilities receive
crude oil and other liquids products via the midstream
sector, which includes pipelines, rail roads, barges,
tankers, and trucks. AFPM’s member companies
have an interest in ensuring that they consistently
and reliably receive the North American crude oil
1 Amici provided timely notice of their intention to file this
brief to the parties, each of which consented. No counsel for
either party authored this brief in whole or in part, nor did any
party or other person or entity other than amicus curiae, its
members, and its counsel make a monetary contribution
intended to fund its preparation or submission. Petitioner
Dakota Access, LLC’s parent company, Energy Transfer, is a
member of AOPL and API, but apart from the dues it pays as a
member, did not contribute money intended to fund preparation
or submission of this brief.
2
volumes that are necessary to meet U.S. energy
consumption demand.
The American Petroleum Institute (“API”) is a
national trade association that represents all aspects
of America’s oil and natural gas industry. API’s
approximately 600 corporate members, from the
largest major oil companies to the smallest of
independents, come from all segments of the industry.
They are producers, refiners, suppliers, marketers,
pipeline operators, and marine transporters, as well
as service and supply companies that support the
industry.
The Association of Oil Pipe Lines (“AOPL”) is a
nonprofit national trade association that represents
the interests of oil pipeline owners and operators
before the United States Congress, regulatory
agencies, and the judiciary. AOPL’s members operate
pipelines that carry approximately 97% of the crude
oil and petroleum products moved by pipeline in the
United States, extending over 225,000 miles in total
length.
These pipelines safely, efficiently, and
reliably deliver more than 22 billion barrels of crude
oil and petroleum product each year, consistent with
safety regulations implemented by the Pipeline and
Hazardous
Materials
Safety
Administration
(“PHMSA”).
Founded in 1961, the National Association of
Convenience Stores (“NACS”) is a non-profit trade
association representing more than 1,900 retail and
1,800 supplier company members in the United States
and abroad. NACS is the pre-eminent representative
of the interests of convenience store operators. In
2019, the convenience and fuel retailing industry
3
employed approximately 2.46 million workers and
generated $647.8 billion in total sales, representing
approximately 3 percent of U.S. Gross Domestic
Product. Of those sales, approximately $395.9 billion
came from fuel sales alone.
The issues addressed in the Petition reach well
beyond this particular case. The decision here affects
the ability of Amici’s members, from a timing,
business, and cost perspective, to reliably construct
and operate new and replacement pipeline (or other)
energy-related projects. The unpredictable “convince
the court” standard applied by the D.C. Circuit could
thwart companies’ potential to secure necessary
project approvals and funding. It may also subject
them to untenable costs and risks, harming not only
Amici’s members, but also third-parties and
consumers that rely on the petroleum and other
energy products that are transported by pipelines
throughout the United States.
The fundamental question here is whether the
extensive environmental analyses set forth in an
agency’s Environmental Assessment (“EA”) should be
deemed insufficient, and an Environmental Impact
Statement (“EIS”) ordered, because a so-called
“controversy” has not been fully resolved to the
satisfaction of a reviewing court. Such “controversy”
may have no bearing on reasonably-foreseeable
environmental impacts, and may be manufactured by
commenters with the sole intent of stopping a pipeline
or other infrastructure project through delay or
otherwise. Pipelines are critical to our nation’s energy
security and provide products vital to the public and
consumers.
The safety of pipelines, including
4
measures to prevent spills, are extensively and
exhaustively regulated by PHMSA. Yet, the D.C.
Circuit’s decision can be wielded as a weapon to stop
pipeline and any major energy or other infrastructure
projects in their tracks. Because the consequences are
so far reaching through the industry and this nation,
this Court should grant the Petition to review the
judgment below.
INTRODUCTION AND
SUMMARY OF ARGUMENT
Amici Curiae the AFPM, API, AOPL, and NACS
(together, the “Amici”), representing the interests of
pipelines, petroleum product manufacturers/refiners,
retailers, and other companies participating in all
sectors of the economy, submit this Amicus Brief in
support of Petitioner, Dakota Access, LLC (“Dakota
Access”).
Amici agree that this Court should grant the
Petition to address important questions of NEPA law
that the D.C. Circuit erroneously decided, to resolve a
conflict of law among the lower courts, and to
harmonize a body of NEPA law that lower courts have
struggled to consistently apply. The decision below is
manifestly wrong on a legal issue of substantial public
importance. The U.S. Army Corps of Engineers
(“Corps”), the expert agency charged by Congress to
evaluate the environmental impacts resulting from
the construction and operation of the Dakota Access
Pipeline (“DAPL”), reasonably concluded, based on a
full assessment of impacts in its initial and
supplemental EAs, that DAPL’s construction and
operation will not result in significant environmental
impacts sufficient to warrant the preparation of an
5
EIS. Yet, instead of deferring to the agency’s factfinding, the DC Circuit broke with at least six other
Circuit Courts by imposing a heightened standard,
requiring that the Corps resolve so-called
“controversy” to the court’s satisfaction.
This
“convince the court” standard contradicts this Court’s
precedents under which courts apply an “arbitrary
and capricious” standard to determine whether an
agency took a “hard look” at potential impacts,
deferring to the informed discretion of the agency
regarding whether impacts may be significant.
Further, in failing here to accord appropriate
deference to the Corps, the D.C. Circuit erroneously
elevated to dispositive status one of the ten intensity
factors used to determine whether an EIS is necessary
when it found that the presence of controversy alone
is sufficient to warrant an EIS.
The issues here are also important to the industry.
The decision will cause considerable uncertainty with
respect to the ability of Amici’s members to pursue,
finance, and timely and successfully complete new
and replacement pipeline (or other) projects. The
holding below invites uncertainty over when a NEPA
review may be deemed to be complete and whether a
project that is fully-constructed and has already been
subjected to years of environmental review can
lawfully continue to operate. Importantly, for all
pipeline environmental reviews, the so-called
“controversy” regarding spill risk is un-controversially
answered and governed by the Pipeline Safety Act, 49
U.S.C. §§ 60101, et seq., and the regulations
implementing that statute administered by PHMSA,
the expert federal agency on pipeline safety. A more
searching environmental review will not change the
6
regulatory framework in which pipelines safely
operate on a daily basis to prevent spills; it will only
add pointless delay.
This Court should grant certiorari.
ARGUMENT
I.
THIS COURT SHOULD REVIEW THE D.C.
CIRCUIT’S HEIGHTENED NEPA STANDARD
In determining whether a federal action will
“significantly affec[t]” the “human environment”—
thereby potentially triggering an EIS under NEPA, 42
U.S.C. § 4332(C)—agencies must consider ten
“intensity” factors.” 40 C.F.R. § 1508.27. In this case,
the D.C. Circuit Court of Appeals required an EIS
based on just one of those intensity factors—whether
the action’s environmental effects “are likely to be
highly controversial,” id. § 1508.27(b)(4)—because the
court was not “convinced” that the Corps successfully
resolved the project opponents’ critiques.
The D.C. Circuit’s approach conflicts with
established precedent of this Court and multiple
circuits on two fundamental points:
•
First, the D.C. Circuit judged the
Corps’ conclusions not under the
“arbitrary and capricious” standard,
but instead by whether the Corps had
succeeded in “convincing” the court
that the agency had resolved the
points of controversy.
•
Second, the D.C. Circuit held that an
EIS was required because the court
found that the effects of the action
7
were “highly controversial,” even
though the degree of controversy is
only one of ten factors to make a
finding
of
significance.
By
transforming this factor from one of
many the agency considers into a
dispositive factor that the court
decides, the court usurped the
responsibility assigned to the Corps
under NEPA.
As noted in the Petition, the D.C. Circuit’s
heightened standard and its application of the highly
controversial factor has created a split with at least
six other circuits. Petition at 25-27. The D.C.
Circuit’s decision imposes a heightened standard that
will be challenging for agencies to meet as they assess
vital infrastructure projects like pipelines. This
standard will make the D.C. Circuit the “go to” court
for project opponents who will use the Circuit’s less
deferential standard to force agencies into preparing
time-consuming EISs based only on opponents’ ability
to articulate continued “controversy” around the
project at issue.
A.
The D.C. Circuit’s Requirement that the
Corps Must “Convince the Court”
Conflicts with Precedent of this Court
and Other Circuits
1. The D.C. Circuit held that the operative
standard in this case was whether the Corps had
“convinced the court” that the agency had “resolved”
the objections to its NEPA analysis. App. 15a-16a.
Requiring an agency to “convinc[e] the court” conflicts
with the deferential review this Court requires.
8
Under Marsh and its progeny, “as long as the Corps’
decision [whether to prepare an EIS] was not
‘arbitrary and capricious,’ it should not be set aside.”
Marsh v. Oregon Natural Resources Council, 490 U.S.
360, 375-78 (1989). It is well-established that under
the arbitrary and capricious standard, a court is
barred from “substitut[ing] its judgment for that of
the agency.” Motor Vehicle Mfrs. Ass’n of U.S., Inc. v.
State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983).
Yet that is exactly what occurred in this case – the
D.C. Circuit “delve[d] into the details” of the technical
pipeline safety issues raised by the opponents to
decide for itself whether those issues “presented an
unresolved controversy” and required an EIS. App.
16a. By failing to apply the “arbitrary and capricious”
standard, the D.C. Circuit “substituted its judgment”
for that of the Corps, violating basic tenets of
administrative law and creating a split with other
circuits.
The court’s limited role under NEPA “is to insure
that the agency has taken a ‘hard look’ at
environmental consequences.” Kleppe v. Sierra Club,
427 U.S. 390, 410 n.21 (1976). Under the APA’s
“arbitrary and capricious” standard, when “specialists
express conflicting views, an agency must have
discretion to rely on the reasonable opinions of its own
qualified experts even if, as an original matter, a court
might find contrary views more persuasive.” Marsh,
490 U.S. at 378. Yet now the D.C. Circuit has set that
limited role aside, instead requiring the Corps to
“convince[] the court” it has not only addressed, but
also has “resolved,” all material objections. App. 15a16a.
9
2. There is no requirement to “convince” the court
under this Court’s precedent or that of other circuits.
Indeed, as set forth in the Petition, the D.C. Circuit’s
requirement creates a serious split with other circuits.
See, e.g., Ind. Forest All., Inc. v. U.S. Forest Serv., 325
F.3d 851, 857, 860-61 (7th Cir. 2003) (recognizing that
the “highly controversial” intensity factor calls for the
limited “hard look” review); Hillsdale Envtl. Loss
Prevention, Inc. v. U.S. Army Corps of Eng’rs, 702 F.3d
1156, 1182 (10th Cir. 2012) (“all NEPA requires” is a
“hard look”); North Carolina v. FAA, 957 F.2d 1125,
1134 (4th Cir. 1992) (similar); WildEarth Guardians
v. Conner, 920 F.3d 1245, 1257, 1263 (10th Cir. 2019)
(similar); Save Our Cumberland Mountains v.
Kempthorne, 453 F.3d 334, 339 (6th Cir. 2006)
(Sutton, J.) (courts will not “‘substitute [their]
judgment . . . for the judgment of the agency.”). The
D.C. Circuit’s requirement that the Corps “convince
the court” it has resolved all Plaintiffs’ critiques
conflicts with these decisions, as well as this Court’s
direction that the deferential arbitrary and capricious
standard applies. See Dep’t of Transp. v. Public
Citizen, 541 U.S. 752, 763 (2004).
The problem with the D.C. Circuit’s heightened
standard is clear from the opinion below, as the nondeferential standard led the court “to delve into the
details” of the technical pipeline safety issues raised
by Plaintiffs and decide for itself whether those issues
“presented an unresolved controversy” and required
an EIS. App. 16a.
10
B.
The D.C. Circuit Erred in Ordering the
Corps to Prepare an EIS Based on the
Court’s Finding of Controversy
1. This Court has held that agencies, rather than
courts, must determine whether to prepare an EIS.
Public Citizen, 541 U.S. at 767. Courts, in turn, must
“defer to ‘the informed discretion of the responsible
federal agencies’” on whether to prepare an EIS, so
long as the agencies “‘consider[ed] . . . the relevant
factors’” and did not commit “‘a clear error of
judgment.’” Marsh, 490 U.S. at 377-78. The degree of
controversy is one of ten factors that agencies weigh,
in context, to determine whether the effects of their
actions are “significant.” 40 C.F.R. §§ 1508.27(b)(1)–
(10). The D.C. Circuit replaced this established
framework with a new standard: under the D.C.
Circuit’s rendering, a court’s finding on a single
intensity factor can require an EIS.
The D.C. Circuit’s approach conflicts with that of
other circuits, which instead have held that the
controversy factor by itself is not determinative. As
noted in the Petition, the D.C. Circuit’s application of
the highly controversial factor has created a split with
at least six other circuits. Petition at 25-27. See Town
of Marshfield v. FAA, 552 F.3d 1, 5 (1st Cir. 2008)
(“[C]ontroversy is not decisive but is merely to be
weighed in deciding what documents to prepare.”);
Soc’y Hill Towers Owners’ Ass’n v. Rendell, 210 F.3d
168, 184 (3d Cir. 2000) (similar); McGuinness v. U.S.
Forest Serv., 741 F. App’x 915, 927 (4th Cir. 2018)
(similar); Hillsdale Envtl. Loss Prevention, Inc., 702
F.3d at 1181 (even when “a project is controversial,”
that “does not mean the Corps must prepare an
11
EIS”);Coliseum Square Ass’n, Inc. v. Jackson, 465
F.3d 215, 233-34 (5th Cir. 2006) (intensity factors are
not “categorical rules that determine by themselves
whether an impact is significant”);see also Sierra Club
v. U.S. Forest Serv., 828 F.3d 402, 411 (6th Cir. 2016)
(“[T]he [agency] was not required independently to
evaluate these factors.”).
Even assuming the record contains evidence
“supporting a different scientific opinion[, that] does
not render the agency’s decision arbitrary and
capricious.” Wetlands Action Network v. U.S. Army
Corps of Engineers, 222 F.3d 1105, 1120-21 (9th Cir.
2000). Instead, if there is “a substantial dispute
concerning the specific environmental effects of the
action,” the agency must “come forward with a ‘wellreasoned explanation’ demonstrating why” the effects
of its action are not “highly controversial.” Ind. Forest
All., Inc., 325 F.3d at 857-858. This is especially true
where, as here, the issues raised by Plaintiffs “require
a high level of technical expertise.” Marsh, 490 U.S.
at 374, 377-78.
2. The D.C. Circuit failed to apply this standard.
By requiring the Corps not only to respond to
Plaintiffs’ objections, but also to “convince the court”
the Corps has “successfully resolved” them, the court
imposed on the agency a more burdensome standard
of its own creation. The court crafted this standard
largely based on Nat’l Parks Conservation Ass’n v.
Semonite, 916 F.3d 1075 (D.C. Cir. 2019), in which the
court opined that the “question is not whether the
Corps attempted to resolve the controversy, but
whether it succeeded.” Id. at 1085-86. But what the
Corps had to do to “succeed” in “resolving the
12
controversy” was to assess the issues and explain
whether they raised a level of controversy that
triggered an EIS. Unlike in Semonite, the Corps in
this case fully considered the issues raised by
Plaintiffs and explained why the effects of its action
were not “highly controversial.” In addition, the low
probability of an oil spill or release was a critical factor
here that was not present in Semonite, where the
aesthetic impacts of the project were undisputed. The
D.C. Circuit’s decision thus undermines the statutory
standard by requiring an EIS even though the Corps
found that the effects purportedly generating
controversy are too unlikely to be “significant.”
This is a critical point. Anyone can spin disaster
scenarios to drum up “controversy” regarding a project
or agency action. But such scenarios do not trigger
additional NEPA analysis if they are highly
improbable. This is a core tenet of NEPA’s “rule of
reason.” Public Citizen, 541 U.S. at 763. Otherwise,
every NEPA review would devolve into extensive
modeling of unlikely scenarios that yield little
practical information to aid the agency decisionmaking process. In this case the Corps’ expert
analysis on the highly technical issues of pipeline
safety found the spill risks raised by Plaintiffs were
too unlikely to trigger an EIS. See, e.g., Standing Rock
Sioux Tribe v. U.S. Army Corps of Eng’rs, 282 F. Supp.
3d 91, 101, 105 (D.D.C. 2017) (referencing “low”
likelihood and “minimal risk” of oil spill under Lake
Oahe). The court erred, and created a conflict with
other circuits, by dismissing the Corps’ analysis and
making its own finding of significance.
13
3. Finally, even if the D.C. Circuit were correct
and the effects of the Corps’ action are “highly
controversial,” that does not necessarily mean an EIS
is required. Controversy is only one of ten factors that
agencies must consider when deciding whether to
prepare an EIS. 40 C.F.R. § 1508.27(b)(4). “The
presence of one factor does not necessarily [trigger an
EIS].” Wild Wilderness v. Allen, 871 F.3d 719, 729
(9th Cir. 2017). Thus, “if a project is controversial,
this does not mean the Corps must prepare an EIS,
although it would weigh in favor of an EIS.” Hillsdale,
702 F.3d at 1181; see also 51 Fed. Reg. 15,618, 15,622
(Apr. 25, 1986) (“controversy does not, alone, require
preparation of an EIS; rather, it is one of many factors
which the responsible official must bear in mind”).
The NEPA regulations assign the consideration of
these factors to the agency. Once the D.C. Circuit
found that the Corps had failed to adequately explain
why this factor did not trigger an EIS, the D.C. Circuit
should have remanded the case to the Corps to allow
the agency to make a new finding in light of the court’s
decision. The D.C. Circuit erred in short-circuiting
that process and ordering the Corps to prepare an
EIS.
II.
THE QUESTIONS PRESENTED IN THIS CASE ARE
EXCEPTIONALLY IMPORTANT FOR INDUSTRY
Certiorari is further warranted because this case
has significant and long-term ramifications for Amici
and their members.
1. The D.C. Circuit’s decision harms the ability of
Amici’s members to pursue new or replacement
pipeline (or other energy) projects and threatens the
operation of approved, fully-constructed projects. A
14
primary impediment to advancing projects is the
delay, uncertainty, and increased costs resulting from
the time necessary to obtain permits for project
construction.
This uncertainty and risk is
compounded by the D.C. Circuit’s holding that the
federal approval for a fully-constructed and
operational project can be vacated, at a much later
date, if additional environmental review is ordered by
a court.
2. In an attempt to provide some certainty under
NEPA for project proponents, “Presidents have issued
directives, and Congress has enacted legislation to
reduce delays and expedite the implementation of
NEPA and the CEQ regulations, including for
transportation, water, and other types of
infrastructure projects.” 85 Fed. Reg. 43,304, 43,305
(July 16, 2020). Yet, “[d]espite these efforts, the
NEPA process continues to slow or prevent the
development of important infrastructure and other
projects that require Federal permits or approvals, as
well as rulemakings and other proposed actions.” Id.
The holding below exacerbates this problem. Namely,
should the “convince the court” standard remain,
requiring an EIS will become the failsafe option,
resulting
in
significant,
and
perhaps
unsurmountable, project delay.
3. NEPA provides that a federal agency may
prepare an EA to document the environmental
impacts resulting from a proposed project. If, in that
EA, the agency reasonably concludes “that the action’s
effects would not be significant, the agency documents
its reasoning in a FONSI, which completes the NEPA
process.” 85 Fed. Reg. at 43,323. In satisfaction of
15
their
NEPA
obligations,
the
Council
on
Environmental Quality (“CEQ”) estimates that, in
2015, federal agencies prepared 11,353 EAs, as
compared to only 261 EISs.2
The D.C. Circuit’s decision (ordering an EIS based
on a “convince the court” standard) will result in
agencies having to prepare more EISs than have
historically been required, substantially extending
the environmental review period. CEQ estimates that
“across all Federal agencies, the average (i.e., mean)
EIS completion time (from NOI to ROD) was 4.5
years.”3
CEQ calculates that the average EIS
completion time for the Corps is even longer, taking
on average 6.04 years to complete. Id. If an agency
must prepare an EA, and despite that EA being
acceptable to the federal agency, a reviewing court
then orders the agency to prepare an EIS to resolve
“controversy” to its satisfaction, this could lead to
years of delay.
Over
that
time
period,
Presidential
administrations and agency heads could change with
dissonant views towards pipelines and fossil fuels,
2 Council on Environmental Quality, The Fourth Report
on Cooperating Agencies in Implementing the Procedural
Requirements of the National Environmental Policy Act,
Attachment A (Oct. 4, 2016), https://ceq.doe.gov/docs/ceqreports/Attachment-A-Fourth-Cooperating-AgencyReport_Oct2016.pdf at 1.
3 See Council on Environmental Quality, Environmental
Impact Statement Timelines (2010-2018) (June 12, 2020),
https://ceq.doe.gov/docs/nepapractice/CEQ_EIS_Timeline_Report_2020-6-12.pdf.
16
further compounding uncertainty relative to the
successful completion of a pipeline project. This
increased political risk is real and harms Amici’s
members, as illustrated by President Biden’s aboutface to revoke the Presidential Permit for the
Keystone XL Pipeline that was previously granted by
President Trump.4
4. To ensure the ability to fund, construct, and
operate a pipeline project with any degree of certainty,
there must be a reasonable finishing line under
NEPA; fully resolving “controversy” to the satisfaction
of the reviewing court is not it. The standard imposed
by the D.C. Circuit gives traction to any so-called
“controversy,” irrespective of whether it materially or
accurately calls into question the significance of
impacts resulting from a proposed activity.
This is illustrated by the “controversy” that the
court below found to be unresolved so as to warrant
preparation of an EIS. For example, the spill risk here
was undisputedly “extremely low” given “the
engineering
design,
proposed
installation
methodology, quality of material selected, operations
measures and response plans.” Petition at 7. Yet, the
court below found that the Corps failed to fully resolve
controversy with respect to environmental impacts
and response preparedness resulting from this highlyremote possibility of release.
Further, the significance (or lack thereof) of
impacts resulting from any pipeline release is
4 See Exec. Order No. 13,990, 86 Fed. Reg. 7,037 (Jan. 25,
2021).
17
necessarily constrained by the highly-regulated
setting in which pipelines like DAPL are constructed
and operate. Specifically, the Pipeline Safety Act, 49
U.S.C. §§ 60101, et seq., and Clean Water Act, along
with regulations implementing these statutes at 49
C.F.R. Parts 194-195, govern every aspect of the leak
detection/spill issues that the court found to be
unresolved.
See, e.g., 49 C.F.R. § 195.452
(establishing comprehensive integrity management
requirements, including that “[a]n operator must have
a means to detect leaks on its pipeline system.”); 49
C.F.R. § 195.452(i)(3) (requiring an operator to have a
leak detection system and provides that “[a]n
operator’s evaluation [of the capability of its leak
detection system] must, at least, consider . . . leak
history,” among other factors); 33 U.S.C. §§
1321(j)(5)(D)(iii)-(iv) (requiring operators to have an
approved emergency response plan in place to ensure
the removal, to the maximum extent practicable, of
the largest foreseeable discharge in adverse weather
conditions, and to mitigate or prevent a substantial
threat of the largest foreseeable discharge in adverse
weather conditions.); 49 C.F.R. § 194.105
(establishing the precise methodology for calculating
the worst-case discharge for a pipeline, which is based
on the largest volume that could be released between
valve-to-valve segments). Such safety standards are
precisely designed to provide “adequate protection
against risks to life and property posed by pipeline
transportation.” 49 U.S.C. § 60102(a)(1).
The Corps reasonably relied on PHMSA’s
regulations in its EA to conclude that operational
impacts from DAPL would not be significant. Yet,
18
notwithstanding
PHMSA’s
extensive
safety
regulations and well-established framework under
which all interstate liquid pipeline operators assess,
prevent and respond to releases from their pipelines,
the court below ordered an EIS to further study spill
risk impacts for the DAPL pipeline. This is despite
the fact that the District Court below expressly
acknowledged that “[o]ther courts, including this
Circuit, have favorably viewed similar agency reliance
on applicable regulatory standards when assessing
impacts as part of a NEPA-required analysis.”
Standing Rock Sioux Tribe v. U.S. Army Corps of
Eng’rs, 255 F. Supp. 3d 101, 126 (D.D.C. 2017) (citing
EarthReports, Inc. v. FERC, 828 F.3d 949, 957 (D.C.
Cir. 2016)) (holding agency fulfilled its NEPA
obligations to evaluate ballast-water impacts by, inter
alia, noting requirements of applicable regulatory
agencies)); Sierra Club v. Clinton, 746 F. Supp.2d
1025, 1047 (D. Minn. 2010) (holding agency properly
considered impacts of pipeline abandonment by
referencing PHMSA regulations).
5. Beyond the implications for the DAPL project,
the D.C. Circuit’s decision creates a clear roadmap for
future pipeline opponents to generate “controversy” in
an effort to prevent or delay a new or replacement
pipeline or other energy infrastructure or disrupt
their operation post-construction. Opponents need
only identify an alternative way, regardless of how
reasonable, accurate, or nuanced, to perform a
calculation to ensure that a reviewing court will find
their so-called “controversy” to not be fully resolved.
Where an agency implements NEPA as extensively as
the Corps did here, a reviewing court should not be
revisiting each and every calculation, methodology, or
19
piece of data raised in comments by a pipeline
opponent. This is particularly true here, where
PHMSA regulations provide a reasonable basis on
which to conclude spill-related impacts from a
pipeline will not be significant. In fact, DAPL will in
all cases be subject to extensive regulations designed
to reduce spill risk.
Leak detection and leak
sensitivity are highly-technical issues within the
purview of PHMSA. Prolonging the NEPA process in
this setting based on comments from entities that
possess no technical knowledge of pipeline leak
detection or prevention will not yield a safer pipeline.
It will only yield pointless delay.
If those commenters have concerns about the
safety of a pipeline, including spill risk, there are
established processes under PHMSA regulations for
prompting an investigation or initiating a private
action to force an operator to come into compliance
with applicable PHMSA requirements.5 Also, if
PHMSA believes that there is any risk of release, the
Agency would be required to take action pursuant to
its extensive injunctive authority under the Pipeline
Safety Act. Demanding an EIS to study these risks
will not change the bottom line that PHMSA
regulation effectively reduces spill risks to a level far
below that of significant impacts that might justify an
EIS.
6. If the D.C. Circuit’s decision were to stand,
Amici’s members will suffer harm in the form of
increased costs and project-completion risks. Such
costs and risks become heightened where the
5 See, e.g., 49 U.S.C. § 60121(a).
20
“convince the court” standard will frequently result in
the need for a lengthy and uncertain EIS process.
Pipeline projects take years of planning and cost
hundreds of millions to billions of dollars to complete.
Pipeline companies must typically finance project
costs through one or more credit facilities or loans that
are secured through private banks; or by issuing
bonds sold to investors. Such credit facilities, loans,
and bonds are critical to provide pipeline companies
with sufficient liquidity to fund the project during
project design, construction, and operation. From
underwriting to lending, a new pipeline project would
not happen without the support of the private sector.
But, in order for a bank to provide funding, banks
must first have a reasonable assurance that a
proposed pipeline project will be completed in a
predictable timeframe, and once completed, the
pipeline will be allowed to continue its operation even
if further environmental review is required.
The holding below has caused and will continue to
cause doubt to ripple throughout the banking and
investment community about the viability of new
pipeline projects. Financing simply does not exist – or
at least does not exist on commercially reasonable
terms – for a pipeline project that may never be
started due to never-ending environmental review.
Importantly, this impacts not only Amici members’
ability to fund new projects like DAPL, but also
replacements of, or upgrades to, existing critical
pipeline infrastructure, the continued need for which
has been firmly demonstrated. Even assuming that
funding can be secured for a project, the holding below
will also subject project proponents to heightened risk
21
and potentially uncapped costs if – as a result of the
“convince the court” standard – an agency’s permit
can be vacated and the pipeline’s operations delayed
pending lengthy additional reviews. These uncertain
and added costs come at the expense of Amici’s
members without any meaningful benefit in terms of
environmental review.
7. This uncertainty is not only detrimental to
Amici and their members, but also third-parties,
consumers, and the nation as a whole. As PHMSA has
stated:
The arteries of the Nation’s energy
infrastructure, as well as one of the safest
and least costly ways to transport energy
products, our oil and gas pipelines provide
the resources needed for national defense,
heat and cool our homes, generate power for
business and fuel an unparalleled
transportation system. . . . The nation's more
than 2.6 million miles of pipelines safely
deliver trillions of cubic feet of natural gas
and hundreds of billions of ton/miles of
liquid petroleum products each year. They
are essential: the volumes of energy products
they move are well beyond the capacity of
other forms of transportation. . . . Pipeline
systems are the safest means to move these
products.6
Vacatur of an agency’s approval(s) and ordering an
operating pipeline to cease on the basis of a “convince
6 https://www.phmsa.dot.gov/faqs/general-pipeline-faqs.
22
the court standard” would have serious adverse
economic consequences.
Pipelines like DAPL
typically transport a significant percentage of regional
petroleum supplies to specific refiners. Abruptly
cutting off the supply of petroleum products
transported by pipelines once their operations have
begun
causes
immediate,
and
sometimes
irreplaceable, shortages. Refineries may be required
to reduce production, lay-off employees, and/or close if
volumes cannot be secured through alternative means
of transportation.
Alternatives to an operating
pipeline, however, may not be available, or may not be
available
without
significant
infrastructure
development and investment, which may take years.
If a pipeline is shut down, the economic principle
of supply and demand points to increased costs up and
down the supply chain. Also, if a pipeline is not
operating, producers may be required to shut in wells
if there is a lack of available transportation. As a
result, a shutdown of a pipeline and shutting in
production could lead to lost tax revenue for the
states, counties, and local communities, with such tax
revenue typically being significant, amounting to tens
or hundreds of millions of dollars (inclusive of taxes
on production).
These consequences lead to economic disruption
throughout the supply chain, potentially amounting
to business closures and higher unemployment, while
eroding our nation’s energy security and
independence. All because, under the “convince the
court” standard, a reviewing court has determined
that an EIS is needed to resolve “controversy”
generated by commenters regarding the highly
23
remote possibility of a release from a newlyconstructed pipeline.
8. For the foregoing reasons, Amici agree with
the Petition that this Court should intervene to
eliminate this uncertainty created by the D.C.
Circuit’s departure from this Court’s standard of
review.
24
CONCLUSION
For the foregoing reasons, this Court should grant
the Petition.
Respectfully submitted,
DAVID H. COBURN
Counsel of Record
JOSHUA H. RUNYAN
CYNTHIA L. TAUB
STEPTOE & JOHNSON LLP
1330 Connecticut Ave., N.W.
Washington, D.C. 20036
(202) 429-3000
dcoburn@steptoe.com
Counsel for Amicus Curiae
November 17, 2021
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.