Nos. 18-1584 & 18-1587
In the Supreme Court of the United States
---------------------------------
UNITED STATES FOREST SERVICE, ET AL., PETITIONERS,
v.
COWPASTURE RIVER PRESERVATION ASSOCIATION, ET AL.
---------------------------------
ATLANTIC COAST PIPELINE, LLC, PETITIONER,
v.
COWPASTURE RIVER PRESERVATION ASSOCIATION, ET AL.
--------------------------------ON WRIT OF CERTIORARI TO
THE FOURTH CIRCUIT COURT OF APPEALS
--------------------------------BRIEF AMICUS CURIAE OF VIRGINIA
IN SUPPORT OF RESPONDENTS
--------------------------------MARK R. HERRING
Attorney General
TOBY J. HEYTENS
Solicitor General
Counsel of Record
DONALD D. ANDERSON
Deputy Attorney General MARTINE E. CICCONI
MICHELLE S. KALLEN
Deputy Solicitors General
JESSICA M. SAMUELS
Assistant Solicitor General
ZACHARY R. GLUBIAK
Attorney
OFFICE OF THE VIRGINIA
ATTORNEY GENERAL
202 North Ninth Street
Richmond, Virginia 23219
(804) 786-7240
solicitorgeneral@oag.state.va.us
COCKLE LEGAL BRIEFS (800) 225-6964
WWW.COCKLELEGALBRIEFS.COM
TABLE OF CONTENTS
Page
Table of Authorities .............................................
ii
Interest of the Amicus Curiae .............................
1
Summary of Argument ........................................
2
Argument .............................................................
4
I.
II.
III.
The Pipeline Threatens Virginia’s Natural
Resources Without Clear Corresponding
Benefits ......................................................
4
The Challenged Permitting Decision Violated Numerous Federal Statutes and
Regulations ................................................
9
The Writ of Certiorari Should Be Dismissed ........................................................ 15
Conclusion............................................................ 19
i
ii
TABLE OF AUTHORITIES
Page
Cases:
Black v. Cutter Laboratories,
351 U.S. 292 (1956) .................................................15
In re: Va. Elec. & Power Co.’s
Integrated Resource Plan filing,
No. PUR-2018-00065,
2018 WL 6524202 (Va. SCC 2018) ............................6
Sierra Club v. U.S. Dep’t of the Interior, et al.,
899 F.3d 260 (4th Cir. 2018) ....................................10
Constitutions, Statutes, Regulations, and Rules:
Va. Const., art. XI, § 1 ...................................................1
16 U.S.C. § 1246(a)(1) ...................................................9
16 U.S.C. § 1604(i) ................................................. 14, 16
36 C.F.R. §§ 219.8–219.11 ...........................................13
40 C.F.R. § 1500.2(b) ...................................................16
42 U.S.C. § 4332(C)(iii) ......................................... 14, 16
Planning Rule,
77 Fed. Reg. 21,162
(U.S. Dep’t of Agric. April 9, 2012) ..........................13
Mineral Leasing Act,
30 U.S.C. § 181 et seq..................................... 3, 15, 17
iii
TABLE OF AUTHORITIES—Continued
Page
Miscellaneous:
Atlantic Coast Pipeline,
Abbreviated Application for a Certificate of
Public Convenience and Necessity and
Blanket Certificates, Resource Report 1:
General Project Description (Sept. 18, 2015) ............4
Blue Ridge Parkway,
National Park Service ...............................................8
Dissent on Order Issuing Certificates and
Granting Abandonment Authority (Mountain
Valley Pipeline and Atlantic Coast Pipeline),
Commissioner Cheryl A. LaFleur
(Oct. 13, 2017) ...........................................................5
George Washington and Jefferson National Forests,
U.S. Forest Service ....................................................8
George Washington and Jefferson National Forests:
A Weeks Act Profile,
Nationalforest.org .....................................................8
George Washington and Jefferson National Forests,
Virginia.org ...............................................................7
Institute for Energy Economic
and Financial Analysis,
The Vanishing Need for the Atlantic Coast
Pipeline: Growing Risk That the Pipeline Will
Not Be Able to Recover Costs From Ratepayers
(Jan. 2019) ............................................................. 6, 7
iv
TABLE OF AUTHORITIES—Continued
Page
Robert Zullo,
Atlantic Coast Pipeline’s Projected
Price Tag Swells By Up To $1.5 Billion,
Richmond.com (Feb. 22, 2018) ..................................7
U.S. Energy Information Administration,
Annual Energy Outlook 2017 ...................................5
Virginia’s Appalachian Trail,
Virginia.org ...............................................................9
What We Believe,
U.S. Forest Service .............................................. 9, 18
INTEREST OF THE AMICUS CURIAE
This case impacts Virginia more than any other
State. 301 miles of the proposed Atlantic Coast Pipeline—50% of the pipeline’s total length—would be
located in Virginia and carve a path directly through
some of the Commonwealth’s most valuable natural resources. One of those resources is the Appalachian
Trail, which gently winds across Virginia for more
than 500 of its 2,000 miles—a greater percentage than
any other State.
Virginia thus has a strong interest in the Court’s
consideration and resolution of this matter. Conserving natural resources and historical sites is critically
important to Virginians and is enshrined in the state
Constitution. See Va. Const. art. XI, § 1. But for Virginia’s natural resources to be adequately protected,
federal agencies charged with administering federal
lands within its borders must fulfill their statutory
obligations. The Forest Service did not do so here, to
the detriment of Virginians and others who enjoy the
natural treasures in the pipeline’s path. The Commonwealth likewise has an interest in ensuring the
Court is presented with an accurate picture of need
for the pipeline, its (purported) benefits, and the burdens it would impose on Virginians and others.
1
2
SUMMARY OF ARGUMENT
The Atlantic Coast Pipeline is a proposed 600mile-long natural gas pipeline that would begin in
West Virginia and terminate in two different locations
in North Carolina and Virginia. The pipeline would bisect Virginia from its northwestern corner to its
southern border before splitting in two and turning
northeast towards the Atlantic Ocean. Along its proposed route, the pipeline would run directly through
several of Virginia’s most cherished places—the
George Washington National Forest, the Blue Ridge
Parkway, and the Appalachian Trail.
The pipeline company (Atlantic) claims the project
is necessary to address an unmet and growing demand
for natural gas in Virginia and North Carolina. But
that claim does not withstand scrutiny. Indeed, recent
analyses indicate that the demand for natural gas will
remain flat or decrease for the foreseeable future and
can be met with existing infrastructure.
Beyond offering dubious benefits, the pipeline unquestionably threatens some of Virginia’s most valued
natural sites. The George Washington National Forest,
the Blue Ridge Parkway, and the Appalachian Trail are
woven into the fabric of Virginia’s history, offering solitude and recreation to Virginians and visitors for generations, bringing tourism and its corresponding
benefits to the neighboring communities.
Despite the undisputed (and indisputable) value
of the natural resources in the pipeline’s path, the
United States Forest Service failed to conduct the meticulous review of Atlantic’s permit application called
3
for by the Service’s governing statutes and regulations.
Instead, the permitting process was rushed and slipshod and driven by Atlantic’s arbitrary deadlines.
Given the chaotic nature of the agency proceedings, it
is unsurprising that the Fourth Circuit invalidated the
permit on three separate grounds that are entirely independent of the question whether the Forest Service
has authority to grant Atlantic permission to cross the
Appalachian Trail.
Atlantic and the Forest Service challenge none of
those alternative holdings. As a result, the challenged
permit will be invalid regardless of how the Court resolves the question on which it granted review. What
is more, the Fourth Circuit’s decision specifically requires the Service to consider alternative routes that
do not cross National Forest land. For that reason, it is
highly unclear if the issue before this Court—whether
the Mineral Leasing Act would authorize the Forest
Service to issue a pipeline right-of-way across the Appalachian Trail—will re-emerge. The Forest Service’s
arguments to the contrary betray its intent to repeat
the shoddy review conducted the first time around, ignoring its statutory and regulatory mandate to give
due consideration to alternative routes for the pipeline.
This Court should not indulge the agency’s abdication
of its critical responsibilities.
Virginia agrees with the arguments made by respondents and their other State amici and urges this
Court to affirm if it reaches the question presented. In
the alternative, Virginia asks the Court to dismiss the
writ of certiorari given the Fourth Circuit’s (entirely
4
correct) conclusion that the challenged permit fails for
numerous other reasons. Because respondents and
their other State amici aptly present the arguments for
affirming on the specific question on which this Court
granted review, this brief focuses on the Fourth Circuit’s alternative grounds for invalidating the challenged permit.
ARGUMENT
I.
The Pipeline Threatens Virginia’s Natural
Resources Without Clear Corresponding
Benefits
1. In their effort to garner public and political
support for the pipeline project, Atlantic and its allies
have insisted that it will address a growing and unmet
demand for natural gas from customers in Virginia and
North Carolina. See, e.g., West Virginia Amicus Br. 23
(invoking the interests of “[r]esidents of North Carolina and Virginia”). But there is reason to doubt those
claims.
In its application for a certificate of public convenience and necessity from the Federal Energy Regulatory Commission (FERC), Atlantic cited studies
forecasting that “demand for natural gas for power
generation in Virginia and North Carolina [will]
grow 6.3 percent annually between 2014 and 2035.”1
1
Atlantic Coast Pipeline, Abbreviated Application for a
Certificate of Public Convenience and Necessity and Blanket Certificates, Resource Report 1: General Project Description, Federal
Energy Regulatory Commission Case No. CP15-554, September
18, 2015, p. 1–6.
5
Its pipeline, Atlantic argues, is needed to meet the
growing energy demands of these customers. See Atlantic Br. 1 (referencing “consumers in Virginia and
North Carolina”).2
Atlantic’s argument, however, rests on a faulty
premise. In 2017, for example, a federal agency
charged with collecting information to promote sound
energy policymaking projected that demand for natural gas for electricity would actually decrease between
2015 and 2020—and not return to 2015 levels until
2034.3
The numbers for Atlantic have not improved since
then. In its most recent long-term Integrated Resource
Plan (IRP), the electric utility affiliate of Dominion Energy—the majority stakeholder in the pipeline joint
venture—modeled five scenarios for meeting electricity demand through 2033. All but one of the models
2
As Atlantic’s filing indicates, FERC has responsibility for
determining whether there is a market need for the pipeline. Although FERC answered that question affirmatively, it focused
narrowly on Atlantic’s gas-transportation contracts with affiliated utilities without addressing the likelihood that demand for
natural gas would remain flat or decrease in coming years. Cf.
Dissent on Order Issuing Certificates and Granting Abandonment Authority (Mountain Valley Pipeline and Atlantic Coast
Pipeline), Commissioner Cheryl A. LaFleur (Oct. 13, 2017) (“I believe that evidence of the specific end use of the delivered gas
within the context of regional needs is relevant evidence that
should be considered as part of our overall needs determination.”).
3
See U.S. Energy Information Administration, Annual Energy
Outlook 2017, at 70, available at, https://www.eia.gov/outlooks/
aeo/pdf/0383(2017).pdf. This estimate assumes that the Clean
Power Plan, which the Trump administration has rescinded, is
not implemented.
6
showed no significant increase in natural gas consumption, and the only model that included annual
consumption numbers actually showed a decrease at
the end of that time frame.4
Even these estimates may be overstated. In 2018,
Virginia’s State Corporation Commission rejected Dominion’s annual IRP, expressing “considerable doubt
regarding the accuracy and reasonableness of the
Company’s load forecast.”5 For one thing, the Commission pointed out that Dominion’s forecasted load
growth exceeded the forecast of the regional transmission organization by more than 50%. Id. The Commission also criticized Dominion for consistently failing to
meet expectations, observing that “[t]he record . . . reflects that the load forecasts contained in the Company’s past IRPs have been consistently overstated,
particularly in years since 2012, with high growth expectations despite generally flat actual results each
year.” Id.
Complicating matters further, natural gas is increasingly at a competitive disadvantage due to technical advances and cost reductions in renewable
4
See Institute for Energy Economic and Financial Analysis
(IEEFA), The Vanishing Need for the Atlantic Coast Pipeline:
Growing Risk That the Pipeline Will Not Be Able to Recover Costs
From Ratepayers, at 5 (Jan. 2019) (IEEFA Analysis), available at,
https://ieefa.org/wp-content/uploads/2019/01/Atlantic-Coast-Pipeline_
January-2019.pdf (estimating consumption for four models based
on information provided in IRP).
5
In re: Va. Elec. & Power Co.’s Integrated Resource Plan filing, No. PUR-2018-00065, 2018 WL 6524202, at *5 (Va. SCC Dec.
7, 2018).
7
energy. IEEFA Analysis at 10. Unfortunately for Virginians, regardless of the need for the pipeline (and
whether it is ultimately completed), the ever-rising
costs of building it will be passed on to consumers by
the companies that have contracted with Atlantic to
carry gas through the pipeline—all of which are affiliates of the pipeline’s sponsors, Dominion, Duke Energy,
and Southern Company. See Robert Zullo, Atlantic
Coast Pipeline’s Projected Price Tag Swells By Up To
$1.5 Billion, Richmond.com (Feb. 22, 2018).6
2. Although demand for the pipeline may be
questioned, there is no debate about the value of the
natural resources it will invariably impact. In Virginia
alone, the proposed route crosses three celebrated natural features: the George Washington National Forest,
the Blue Ridge Parkway, and the Appalachian Trail.
a. The George Washington National Forest. Combined with the adjacent Jefferson National Forest, the
George Washington National Forest spans more than
1.6 million acres, extending along the Appalachians
and following Virginia’s northwest border with Kentucky and West Virginia.7 Together, the two forests “afford virtually every type of outdoor recreation activity
. . . imagin[able],” including “[h]iking, mountain biking,
6
Available at, https://www.richmond.com/business/atlanticcoast-pipeline-s-projected-price-tag-swells-by-up/article_bd8f073df563-511e-8988-b93cb1874a05.html; see also IEEFA at 2 (explaining that “all of the[ ] transportation contracts are with regulated
utility companies affiliated with the three ACP-LLC partners”).
7
George Washington and Jefferson National Forests, Virginia.org,
available at, https://www.virginia.org/gwjnf.
8
camping, . . . fishing . . . bird watching, horseback riding, photography, orienteering, and cross-country skiing.”8 Given their natural beauty and varied offerings,
it is not surprising the forests attract three million visitors per year.9
b. The Blue Ridge Parkway. The Blue Ridge
Parkway runs for nearly 500 miles through Virginia
and North Carolina, following the Blue Ridge Mountains and linking the Shenandoah National Park to the
Great Smoky Mountains National Park. It was the
product of numerous public works projects undertaken
in the 1930s, which helped the Appalachian region
climb out of the Great Depression. Labeled “America’s
[f ]avorite [d]rive,” the Parkway boasts “stunning longrange vistas and close-up views of the rugged mountains and pastoral landscapes of the Appalachian
Highlands.”10 According to the National Park Service,
the Parkway “protect[s] a diversity of plants and animals, and provid[es] opportunities for enjoying all that
makes this region of the country so special.” Id.
c. The Appalachian Trail. The Appalachian Trail
stretches from Maine to Georgia, with more than a
8
George Washington and Jefferson National Forests, U.S. Forest
Service, available at, https://www.fs.usda.gov/recmain/gwj/recreation.
9
George Washington and Jefferson National Forests: A
Weeks Act Profile, Nationalforest.org, available at, https://www.
nationalforests.org/blog/a-weeks-act-profile.
10
Blue Ridge Parkway, National Park Service, available at,
https://www.nps.gov/blri/index.htm.
9
quarter of its 2,000 miles traversing Virginia.11 The
trail has a rich history, both in its creation nearly 100
years ago and in the public-private partnerships that
have stewarded its preservation through the years. See
16 U.S.C. § 1246(a)(1) (entrusting private landowners
with the responsibility to manage the portions of the
Trail on their lands); see also Appalachian Trail Conservancy Amicus Br. 27–29 (describing role of local governments and conservancy groups in managing the
Trail). Virginia is home to several of the Trail’s most
visited sites, including Grayson Highlands and Mount
Rogers. These and other highlights draw countless visitors each year to enjoy the solitude and natural
beauty of the Trail—the same attributes that led Congress to designate the Trail as one of the first two scenic trails under the National Trails System Act more
than fifty years ago.
II.
The Challenged Permitting Decision Violated
Numerous Federal Statutes and Regulations
Because it planned to cross National Forest land,
Atlantic needed a permit from the United States Forest Service—an agency that describes its own mission
as “Caring for the Land and Serving People.”12
11
Virginia’s Appalachian Trail, Virginia.org, available at,
https://www.virginia.org/appalachiantrail/.
12
What We Believe, U.S. Forest Service, available at,
https://www.fs.usda.gov/about-agency/what-we-believe.
10
Unfortunately, the Service’s evaluation of the permit
fell far short of that promise.13
1. a. Initially, the Forest Service appeared skeptical of the pipeline project and prepared to conduct the
type of rigorous review envisioned by its governing
statutes and regulations.
In October 2016, the Service expressed concern
about Atlantic’s plan to construct the pipeline on the
steep slopes of the George Washington and Monongahela National Forests. Because the project would need
to be consistent with “Forest Plan standards that
limit activities in areas that are at high risk for slope
and soil instability,” the Service explained that it
needed further evidence before it could continue processing Atlantic’s permit application. Pet. App. 4a.
Specifically, the Forest Service requested plans for ten
sites that could demonstrate that Atlantic’s technology
would meet stabilization requirements. Id. Those
plans would be “merely representative,” the Service
cautioned: “Should the ACP project be permitted, multiple additional high hazard areas [would] need to be
addressed on a site-specific basis.” Id. at 5a. Months
later, in February 2017, the Forest Service confirmed
that all ten site-specific stabilization designs would
be required, informing Atlantic that it was “not
13
The Forest Service was not alone in failing to meet its statutory and regulatory obligations when it reviewed the pipeline
project. The permit review the U.S. Park Service conducted before
allowing Atlantic to cross the Blue Ridge Parkway was similarly
flawed. See Sierra Club v. U.S. Dep’t of the Interior, et al., 899
F.3d 260, 290–94 (4th Cir. 2018).
11
comfortable” with proceeding with the permit without
seeing the plans. Id. at 7a.
In December 2016, Atlantic circulated a timeline
for FERC and the Forest Service’s review, looking to
complete the administrative process by October 2017.
Consistent with that timeline, FERC completed its
draft Environmental Impact Statement (EIS) in late
2016. In April 2017, the Forest Service commented on
the draft, noting repeatedly that FERC lacked adequate information to draw the conclusions it reached,
particularly about sensitive soils and steep slopes.
Pet. App. 9a. Most significantly, the Forest Service
commented that “[n]o analysis of a National Forest
Avoidance Alternative has been conducted, and environmental impacts of this alternative have not been
considered or compared to the proposed action.” Id. at
38a. The Service explained that it “[could not] support
the recommendation that the National Forest Avoidance Alternative be dropped from consideration” and
“reiterate[d]” its request for evaluation of such an alternative. Id. at 39a.
Around the same time, the Forest Service provided
critical comments on Atlantic’s draft biological evaluation. In particular, the Service cautioned that Atlantic’s
plans would “likely . . . create long-term negative impacts to the ecosystem,” including detrimental impacts
on “potentially sensitive species.” Pet. App. 9a–10a.
b. Just a month later, however, the Forest Service
abruptly changed course. Without acknowledging its
change of position, the Service now told Atlantic that
the eight additional site-specific exemplars it had
12
requested would not be required and the two previously provided designs would be adequate to proceed
with the permit review. Pet. App. 11a.
In line with Atlantic’s timeline, the Forest Service
released its draft Record of Decision, which proposed
granting the permit and exempting the pipeline from
a number of forest plan standards. Directly contradicting its prior position, the Forest Service agreed to drop
its request for an analysis of alternatives that did not
cross National Forest land, stating that such alternatives—never analyzed—“[would] not offer a significant
environmental advantage when compared to the proposed route or would not be economically practical.”
Pet. App. 11a–12a. In response to comments, the Service stated that FERC had “adequate[ly] consider[ed]”
alternatives and “concluded these alternatives would
not provide a significant environmental advantage
over a shorter route that passes through National Forests.” Id. at 12a. In a similar about-face, the Service responded to Atlantic’s updated biological evaluation by
amending its previous conclusion to find that the pipeline would not result in a loss of sensitive species. Id.
at 13a.
2. Given the Forest Service’s whiplash-inducing
approach to Atlantic’s permit, it is hardly surprising
that the Fourth Circuit invalidated its decision on a
number of separate grounds.
a. Observing that the National Environmental
Policy Act (NEPA) requires “particular care” when a
proposed project would cross a National Forest, the
court of appeals found that the Service had failed to
13
offer a “detailed discussion” of steps Atlantic could take
to mitigate landslide risks, erosion impacts, and waterquality degradation. Pet. App. 43a. The court recognized that the Forest Service had expressed numerous
concerns in its comments on FERC’s draft EIS and
had insisted that the permit should not be issued unless Atlantic provided ten site-specific designs to
demonstrate that its technology would be effective at
mitigating the risks posed by steep slopes. Id. Given
statements made in the final EIS—including that
“slope instability/landslide risk reduction measures
have not been completed or have not been adopted”—
the court determined that the final EIS could not have
addressed the Service’s concerns. Pet. App. 44a. In
other words, “[t]o support its decision to approve the
project and grant the [permit], the Forest Service relied on the very mitigation measures it previously
found unreliable.” Id. In the Fourth Circuit’s view, that
was “insufficient to satisfy NEPA, and did not constitute the necessary hard look at the environmental consequences of the ACP project.” Id. at 45a.
b. The Fourth Circuit also found that the Service
had not complied with its Planning Rule when it applied project-specific amendments to 13 standards, including nine amendments related to the plan for the
George Washington National Forest. Pet. App. 18a;
see also Planning Rule, 77 Fed. Reg. 21,162 (U.S. Dep’t
of Agric. April 9, 2012); 36 C.F.R. §§ 219.8–219.11.
Those amendments relaxed forest plan standards for
soil, water, riparian, threatened and endangered species, and recreational and visual resources. Despite
14
acknowledging that the purpose of the amendments
was to allow Atlantic to meet the requirements of the
National Forest Management Act (NFMA) and accompanying regulations (because it could not meet those
standards without amendments), the Service “fail[ed]
to analyze whether the substantive requirements of
the 2012 Planning Rule [were] directly related to the
purpose of the amendments.” Pet. App. 19a. As the
Fourth Circuit explained: “The lengths to which the
Forest Service apparently went to avoid applying the
substantive protections of the 2012 Planning Rule—its
own regulation intended to protect national forests—
in order to accommodate the ACP project through national forest land on Atlantic’s timeline are striking,
and inexplicable.” Pet. App. 27a.
c. Finally, the court of appeals found that the
Forest Service had violated NEPA and other governing
laws by failing to consider alternatives that did not
cross National Forest land. See 42 U.S.C. § 4332(C)(iii)
(requiring consideration of alternatives); see also
16 U.S.C. § 1604(i) (requiring compliance with forest
plans, which require non-National Forest alternatives). In the court’s view, it was improper for the Service to rely on FERC’s final EIS for several reasons:
First, the standard FERC applied to determine
whether an alternative route should be used was different from the standard imposed on the Forest Service. Pet. App. 31a. Second, despite expressing
concerns about the lack of study of off-forest alternatives in the draft EIS, the final EIS the Service adopted
included a discussion of “National Forest Avoidance
15
Route Alternatives” that was identical to the draft. Pet
App. 39a. The court “simply [could not] conclude that
the Forest Service undertook an independent review
and determined that its comments and concerns were
satisfied when it seemingly dropped its demand that
off-forest alternative routes be studied before the ACP
was authorized without any further analysis.” Id. at
41a (internal quotation marks omitted). The court thus
determined that the Service had acted “arbitrarily and
capriciously.” Id. at 41a–42a.
III. The Writ of Certiorari Should Be Dismissed
It is undisputed that this Court’s decision will not
change the outcome of this case. See Gov’t Cert. Reply
8; Atlantic Cert. Reply 9. As just described, the Fourth
Circuit determined that the Forest Service violated its
statutory and regulatory obligations in three different
ways that are separate and apart from its authority
under the Mineral Leasing Act to issue a pipeline
right-of-way crossing the Appalachian Trail. Atlantic
and the Service challenge none of those holdings and
each is independently sufficient to invalidate the permit. Because “[t]his Court . . . reviews . . . judgments,
not statements in opinions,” Black v. Cutter Laboratories, 351 U.S. 292, 297 (1956), that fact alone provides
a sufficient basis to dismiss the writ of certiorari.
The reasons Atlantic and the Forest Service offer
for deciding the question presented now are both unpersuasive and betray a fundamentally misguided
(and troubling) understanding of the Service’s task on
remand. Focusing on the Fourth Circuit’s holding that
16
the Service was required to consider non-forest alternatives, the government doubles down on the very
reasoning the court rejected—that FERC’s final EIS
properly analyzed all non-forest alternatives and there
is nothing left for the Forest Service to do. See Gov’t
Cert. Reply 10–11. But as the Fourth Circuit explained, that argument fails on multiple levels, including that the Service was required to undertake an
independent review to determine whether FERC had
addressed its concern that “[n]o analysis of a National
Forest Avoidance Alternative ha[d] been conducted,
and environmental impacts of [that] alternative ha[d]
not been considered or compared to the proposed action.” Pet. App. 41a. By promising to repeat its blind
adherence to FERC’s analysis on remand, the government endorses nothing less than an abdication of the
Forest Service’s responsibilities.
Atlantic’s arguments are even more dismissive of
the Forest Service’s important statutory and regulatory mandate. Atlantic insists that “even if it were
somehow possible to divert the pipeline to permissibly
cross the Trail on State or private land, that diversion
would involve additional unnecessary cost, cause
needless delay, and make no sense.” Atlantic Cert. Reply 10. But diverting the pipeline away from National
Forest land where appropriate is precisely what the
statutes and regulations were intended to accomplish,
and what they require of the Forest Service. See, e.g.,
16 U.S.C. § 1604(i); 42 U.S.C. § 4332(C)(iii); 40 C.F.R.
§ 1500.2(b). Atlantic’s suggestion that doing what existing law demands would impose costs and “make no
17
sense” is an argument for changing the law, not ignoring it as the Service did here.14
Even more striking, Atlantic characterizes respondents’ effort to defer review of the question presented
until after remand (if necessary) as “particularly disingenuous given the Fourth Circuit’s apparent discomfort with pipelines.” Atlantic Cert. Reply 12. According
to Atlantic, this Court should ignore a United States
court of appeals’ unanimous analysis and the multiple
independent reasons it found for remand because a
private petitioner asserts that court cannot fairly decide an entire category of cases. Instead, Atlantic asks
this Court to join it and the federal government in
their all-out push to see that a particular pipeline is
constructed when, where, and how the pipeline company wants it to be. But as the Fourth Circuit appropriately recognized, the Service’s statutory and
14
Respondents and their other State amici demonstrate why
this Court should reject the government and Atlantic’s alternative argument that immediate resolution is needed because the
Fourth Circuit’s decision has sweeping implications. See e.g.,
Resp. Br. 46–48; Vermont Amicus Br. 17–25 (explaining that few
trails would be covered by the Fourth Circuit’s decision on the
Mineral Leasing Act and the decision would not affect existing
pipeline crossings and utility easements). It is telling that, in response to respondents’ argument that no federal agency had
granted a right-of-way under the Mineral Leasing Act until 2017,
the government could muster only a single permit authorized in
2013, where the Forest Service knew that the Appalachian Trail
was scheduled to be re-routed away from the proposed construction. Gov’t Cert. Reply 7. That single example hardly suggests an
urgent need to conclusively resolve whether the Fourth Circuit
was correct about a single (non-outcome determinative) threshold
holding.
18
regulatory obligations are not optional, nor are they
speed bumps to be hurried over and driven around if
necessary.
*
*
*
The requirements the Forest Service ignored
when it granted Atlantic’s permit were crafted by Congress with an eye towards protecting the National Forests for generations to come. Virginians rightly should
be able to count on the Forest Service to fulfil its congressionally mandated obligations—not to mention its
self-professed mission of “Caring for the Land and
Serving People.”15 This Court should not endorse the
dismissive attitude the Service and Atlantic demonstrate towards the Forest Service’s critical responsibilities by prematurely deciding a question whose
resolution will not impact the outcome of this case.
15
What We Believe, U.S. Forest Service, available at,
https://www.fs.usda.gov/about-agency/what-we-believe.
19
CONCLUSION
The judgment of the Fourth Circuit should be affirmed. In the alternative, the writ of certiorari should
be dismissed.
Respectfully submitted.
MARK R. HERRING
Attorney General
TOBY J. HEYTENS
Solicitor General
Counsel of Record
DONALD D. ANDERSON
Deputy Attorney General MARTINE E. CICCONI
MICHELLE S. KALLEN
Deputy Solicitors General
JESSICA M. SAMUELS
Assistant Solicitor General
ZACHARY R. GLUBIAK
Attorney
OFFICE OF THE VIRGINIA
ATTORNEY GENERAL
202 North Ninth Street
Richmond, Virginia 23219
(804) 786-7240
solicitorgeneral@oag.state.va.us
JANUARY 2020
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.