Respondents Brief — Constitution Pipeline Company, LLC, Petitioner v. New York State Department of Environmental Conservation, et al.
Supreme Court briefMar 14, 2018
Ask Donna
What actually matters in this document.
Text
No. 17-1009
IN THE
Supreme Court of the United States
CONSTITUTION PIPELINE COMPANY, LLC,
Petitioners,
v.
NEW YORK STATE DEPARTMENT OF
ENVIRONMENTAL CONSERVATION, et al.,
Respondents.
ON PETITION FOR WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT
BRIEF IN OPPOSITION FOR
NEW YORK STATE RESPONDENTS
ERIC T. SCHNEIDERMAN
Attorney General
State of New York
BARBARA D. UNDERWOOD*
Solicitor General
ANDREW D. BING
Deputy Solicitor General
FREDERICK A. BRODIE
Assistant Solicitor General
BRIAN LUSIGNAN
Assistant Attorney General
Environmental Protection
Bureau
120 Broadway
New York, NY 10271
(212) 416-8020
barbara.underwood@ag.ny.gov
*Counsel of Record
i
QUESTION PRESENTED
Whether the State of New York acted arbitrarily
and capriciously when it denied a water-quality
certification for a natural gas pipeline under Clean
Water Act § 401, 33 U.S.C. § 1341, because the
applicant failed to provide material information about
the project’s anticipated impacts on state water
quality, despite the state agency’s repeated requests
for such information.
ii
TABLE OF CONTENTS
Page
STATEMENT OF THE CASE ....................................1
A. Introduction ......................................................1
B. The Pipeline and FERC Proceedings ...............2
C. The State’s Comprehensive Administrative
Review ...............................................................4
D. The State’s Denial.............................................7
E. Proceedings Below ............................................8
REASONS FOR DENYING THE PETITION ..........10
I.
This Case Does Not Present the Question
of Whether A Water Quality Certification Can
Be Denied for Failure to Consider Alternative
Routes. .............................................................10
II. The Second Circuit’s Decision Does Not
Conflict with the Governing Statutes, Any
Decision of This Court, or the Decisions
of Other Circuit Courts. ..................................13
III. This Case Does Not Implicate the National
Security and Federalism Concerns Cited
by Petitioner. ...................................................15
CONCLUSION ..........................................................17
iii
TABLE OF AUTHORITIES
Cases
Page(s)
Islander East Pipeline Co., LLC v. McCarthy,
525 F.3d 141 (2d Cir. 2008).................................. 12
National Fuel Gas Supply Corp. v. Public
Service Commission, 894 F.2d 571 (2d Cir.
1990) ..................................................................... 14
PUD No. 1 of Jefferson Cty. v. Washington
Dept. of Ecology, 511 U.S. 700 (1994) .................... 2
S.D. Warren Co. v. Maine Bd. of Environmental
Protection, 547 U.S. 370 (2006) ........................ 2,14
Schneidewind v. ANR Pipeline Co., 485 U.S.
293 (1988) ............................................................. 14
Weaver’s Cove Energy, LLC v. Rhode Island
Coastal Resources Management Council,
589 F.3d 458 (1st Cir. 2009)................................. 15
Laws
15 U.S.C.
§ 717b ................................................................. 2,14
§ 717f....................................................................... 2
33 U.S.C. § 1341 .................................................. 1,2,14
N.Y.C.R.R. tit. 6,
§ 621.7 ..................................................................... 5
§ 621.14 ................................................................... 5
STATEMENT OF THE CASE
A. Introduction
Following a comprehensive administrative process,
the State of New York concluded that petitioner
Constitution Pipeline Company, LLC failed to establish that its proposed construction of 100 miles of new
natural gas pipeline across undeveloped lands in
central New York, which would have crossed 220
streams and impacted more than 80 acres of wetlands,
would comply with water-quality standards. (Pet.
App. 25a-65a.) Accordingly, the State denied Constitution’s application for a water-quality certification
under Clean Water Act § 401, 33 U.S.C. § 1341.
Without a water-quality certification, the project could
not go forward as originally planned. In a thorough
decision, the Second Circuit upheld the State’s denial
of the § 401 certification, prompting Constitution to
seek review here.
This Court should deny the petition for certiorari,
which rests entirely on Constitution’s misreading of
the Second Circuit’s decision. Contrary to Constitution’s argument, the Second Circuit did not hold that
the State, rather than the Federal Energy Regulatory
Commission (FERC), had authority over the siting of
natural gas facilities. Rather, among other things,
that court held that New York’s denial of the § 401
certification was reasonable because Constitution had
“persistently refused” to provide information relating
to the methods it would use to minimize adverse
water-quality impacts where the proposed pipeline
crossed streams and wetlands. (Pet. App. 33a.)
All the conflicts that Constitution posits between
the Second Circuit’s decision and the Natural Gas Act,
2
this Court’s precedent, other circuit court decisions,
and federal energy policy, rest on its mistaken reading
of the Second Circuit’s decision and therefore are
illusory. This Court’s review is not warranted.
B. The Pipeline and FERC Proceedings
Under § 401 of the Clean Water Act, an applicant
for a federal license or permit that may result in
discharges into navigable waters must obtain a certification from the State that the project would comply
with applicable water-quality standards. 33 U.S.C.
§ 1341(a)(1). The State’s review covers both state and
federal water-quality standards. S.D. Warren Co. v.
Maine Bd. of Envtl. Prot., 547 U.S. 370, 374 (2006).
State water-quality certifications are required for
natural gas pipelines, just as they are for other
projects: the Natural Gas Act specifically does not
“affect[ ] the rights of States” under the Clean Water
Act. 15 U.S.C. § 717b(d)(3). A project cannot be licensed
without a State water-quality certification. See S.D.
Warren, 547 U.S. at 374; PUD No. 1 of Jefferson Cty.
v. Washington Dep’t of Ecology, 511 U.S. 700, 707-08
(1994).
In 2013, Constitution applied to FERC for a
certificate of public convenience and necessity under
Natural Gas Act § 7, 15 U.S.C. § 717f, for construction
of 124 miles of 30-inch-diameter natural gas pipeline,
temporary and permanent access roads, and various
related facilities. The proposed pipeline would stretch
from Susquehanna County, Pennsylvania to Schoharie
County, New York. (CA2 J.A. 132-133, 294.) The
pipeline would traverse roughly 100 miles in New
York State, almost all previously undisturbed and
undeveloped land. (CA2 J.A. 296, 1060, 1067.) It would
disrupt more than 80 acres of wetlands and cross 220
3
waterbodies in New York, while an additional 30
waterbodies would fall within the construction rightof-way. (CA2 J.A. 1218, 1235.)
FERC issued a certificate of public convenience
and necessity for the pipeline, but the certificate was
expressly “conditioned on” Constitution’s compliance
with environmental conditions recommended by FERC
staff in the environmental impact statement. (CA2
J.A. 1712, 1714.) Among those conditions was the
requirement that Constitution obtain “all applicable
authorizations required under federal law”—
including a Clean Water Act § 401 certification—
before beginning construction. (CA2 J.A. 1717.) FERC
reiterated the environmental impact statement’s
conclusion that “[c]onstruction and operation-related
impacts on waterbodies and wetlands will be further
mitigated by Constitution’s compliance with conditions
of the . . . Section 401 permit[ ] required under the
[Clean Water Act],” which FERC expected Constitution
to apply for and obtain. (CA2 J.A. 1691.)
On rehearing of the certificate, FERC noted that
until the State issued a § 401 certification,
“Constitution may not begin an activity, i.e., pipeline
construction, which may result in a discharge into
jurisdictional waterbodies.” (CA2 J.A. 2745-2746.)
Moreover, FERC recognized that “[i]f and when [the
State] issues” a § 401 certification, Constitution would
be “required to comply” with its conditions. (CA2 J.A.
2748-2749.) FERC also observed that the State had
the authority to require Constitution “to materially
modify its project to satisfy any conditions imposed.”
(Id.)
4
C. The State’s Comprehensive
Administrative Review
In August 2013, while FERC’s administrative
review was still pending, Constitution applied for a
Clean Water Act § 401 certification from the State.
(CA2 J.A. 208.) The Second Circuit’s opinion and the
State’s ruling both detail the extensive correspondence between Constitution and the State regarding
the application. (See Pet. App. 11a-22a, 44a-62a.)1
Following an initial, partial review, the State
notified Constitution that the application was
incomplete, and listed a number of additional
materials that would be required. (CA2 J.A. 214.)
Among other things, the State asked Constitution to
submit “all details for proposed stream crossings”.
(CA2 J.A. 216.) The State also repeatedly indicated its
preference for “trenchless” waterbody crossing methods,
which minimize impacts to water quality by drilling
under—rather than digging through—streams and
wetlands. (CA2 J.A. 77, 89, 166.)
Constitution submitted supplemental permit
application materials in November 2013, but refused
to provide some of the materials the State requested.
(CA2 J.A. 301, 379-382.) In particular, Constitution
1 Constitution’s suggestion that the State agreed to “rely” on
FERC’s environmental review (Pet. 12), does not accurately reflect
the record. The State told Constitution that, “[a]long with the
permit applications, the [State] also intends to rely on the federal
environmental review prepared pursuant to [NEPA] to determine if the Project will comply with applicable New York State
standards.” (CA2 J.A. 75-76 [emphasis added]; accord CA2 J.A.
164). The State thus intended to conduct its own review of
Constitution’s “permit application[ ] ” to assess the project’s
impacts to state water quality.
5
refused to evaluate the feasibility of trenchless
crossings at any streams less than 30 feet in width,
effectively eliminating most of the crossings from
consideration for use of the more protective technology. (CA2 J.A. 307, 319.)
On May 9, 2014, Constitution voluntarily withdrew
and re-submitted the application so the parties could
continue to develop it without risking expiration of the
one-year deadline for state action set by § 401 of the
Clean Water Act. (CA2 J.A. 851.)
In July 2014, the State requested additional
information to be included in a revised application.
(CA2 J.A. 891-95.) Constitution supplemented its
application in August 2014, but the supplement
included only “a portion” of the items the State had
requested. (CA2 J.A. 898.) Constitution submitted
further information in November 2014 (CA2 J.A.
1665); however, much of the information the State
sought was not provided.
In December 2014, the State published a Notice of
Complete Application, which opened a public comment
period on the application. (CA2 J.A. 1725.) The State’s
determination to treat the application as complete did
not preclude the agency from requesting further
information. See N.Y. Comp. Codes, Rules & Regs. tit.
6, § 621.14(b) (“6 N.Y.C.R.R.”). Rather, the State’s
regulations required a Notice of Complete Application
before public comment could be solicited. 6 N.Y.C.R.R.
§ 621.7(a). The State received more than 15,000 public
comments on the application. (CA2 J.A. 2853.) Active
review of the application continued throughout the
comment period and the following months. (CA2 J.A.
1853-1855.)
6
Constitution again supplemented its application
in February and March 2015. The new material still
did not include all the information relating to
waterbody impacts that the State had requested
almost a year earlier. (CA2 J.A. 2061.) In particular,
Constitution still refused to evaluate the use of
trenchless crossing technologies for any stream less
than 30 feet in width. (CA2 J.A. 1895.) At the small
number of crossings Constitution did evaluate,
Constitution did not complete full geotechnical
evaluations as requested by the State, and refused to
provide the State with the evaluations it had
completed. (CA2 J.A. 307, 353-59, 2055-2057, 20952097.) Constitution ultimately submitted geotechnical
evaluations for only two stream crossings. (CA2 J.A.
1855, 2079; Pet. App. 20a, 33a.)
On April 27, 2015, Constitution voluntarily
withdrew and resubmitted its application a second
time (CA2 J.A. 2072), thus giving the State additional
time to consider the recent supplemental submission
and the thousands of public comments it had received.
During the ensuing year, the State’s review of the
application and public comments continued, as did
active discussions with Constitution regarding
geotechnical investigations, third-party environmental
monitoring, and other topics relevant to the waterquality impacts on the many streams and other
waterbodies that would be affected.2 (CA2 J.A. 2248,
2 Contrary to Constitution’s claim that the State “shut down
substantive communications . . . during the eight month period”
before the denial (Pet. 14), the record includes at least 188 entries
for that period reflecting ongoing communications between the
State and Constitution on a range of issues related to water
quality.
7
2529-2533, 2594, 2602, 2607, 2612-2614, 2621, 2624,
2805.)
D. The State’s Denial
On April 22, 2016, the State denied Constitution’s
request for a § 401 certification. (Pet. App. 35a-65a.)
The State concluded that Constitution had “fail[ed] in
a meaningful way to address the significant water
resource impacts that could occur from this Project”
and “failed to provide sufficient information to demonstrate compliance with New York State water quality
standards.” (Pet. App. 36a.) The State outlined the
project’s large impact to numerous streams and
wetlands, including many classified as sensitive or
unique. (Pet. App. 38a-43a.)
The State determined that Constitution had failed
to provide sufficient information on the feasibility of
trenchless crossing methods at stream crossings. (Pet.
App. 51a-52a.) The State described its numerous
requests, dating back to June 2012, for technical information on the feasibility of trenchless crossings, and
Constitution’s continued failure to provide adequate
and complete information on that issue. (Pet. App.
53a-57a.) Instead, the State found, Constitution
provided a patchwork of insufficient information based
on limited analysis to support its conclusion that only
11 of the more than 250 streams could be crossed using
trenchless methods. (Pet. App. 59a.) In particular, the
State noted Constitution’s continued unwillingness to
evaluate the feasibility of trenchless crossing technologies at streams less than 30 feet wide or to provide
site-specific analyses, including geotechnical evaluations, for the handful of crossings it did evaluate. (Pet.
App. 58a-59a.) Based on Constitution’s failure to
provide adequate information on trenchless crossings
8
and other water-quality protection measures, the
State concluded that Constitution had failed to
demonstrate that the project would comply with New
York’s water-quality standards. (Pet. App. 60a.)
The State identified several additional bases for
denying the § 401 certification. First, the State
observed that Constitution had provided limited
analysis of pipe-burial depth covering only 21 of the
more than 251 streams, making it impossible for the
State to determine whether the proposed depth would
be sufficient to protect water-quality standards. (Pet.
App. 62a-63a.) Further, Constitution had failed to
provide site-specific information on whether and when
blasting would be required in waterbodies and
wetlands. (Pet. App. 63a.) Finally, Constitution had
failed to provide sufficient information on wetlands
crossings. (Pet. App. 64a.)
In describing the project’s background, the State
noted that it had asked Constitution to evaluate alternative routes that would minimize environmental
impacts by co-locating the pipeline with existing highway or power-line rights-of-way. (Pet. App. 38a-39a.)
E. Proceedings Below
Constitution petitioned for review of the denial in
the Second Circuit pursuant to Natural Gas Act § 19(d),
15 U.S.C. § 717r(d). The Second Circuit unanimously
rejected all of Constitution’s arguments. The Court
observed that the denial was not an improper collateral
attack on FERC’s permitting process, because “the
relevant federal statutes entitled [the State] to
conduct its own review of the Constitution Project’s
likely effects on New York waterbodies and whether
9
those effects would comply with the State’s water
quality standards.” (Pet. App. 28a.)
The Second Circuit noted that “[a] state’s
consideration of a possible alternative route that would
result in less substantial impact on its waterbodies is
plainly within the state’s authority.” (Pet. App. 29a.)
It then observed that it was unnecessary to address
Constitution’s numerous arguments that the State
was exceeding its authority in this consideration,
because “where an agency decision is sufficiently
supported by even as little as a single cognizable
rationale, that rationale, ‘by itself, warrants our denial
of [a] petition’ for review under the arbitrary-andcapricious standard of review.” (Pet. App. 29a [citation
omitted].)
The Second Circuit went on to explain that, apart
from Constitution’s failure to provide information on
alternative routes, the State had ample basis for
denying the certification—namely, Constitution’s
failure to provide multiple categories of requested
information. The court outlined the areas of information that the State had requested but not received, and
observed that Constitution did not even “claim to have
provided” that information. (Pet. App. 31a-32a.)
Accordingly, the Court concluded that “the record
amply shows, inter alia, that Constitution persistently
refused to provide information as to possible alternative routes for its proposed pipeline or site-by-site
information as to the feasibility of trenchless crossing
methods for streams less than 30 feet wide.” (Pet. App.
33a [emphasis added].)
The Second Circuit unanimously denied
Constitution’s motion for panel rehearing or rehearing
en banc. (Pet. App. 67a.)
10
REASONS FOR DENYING THE PETITION
The petition should be denied for three reasons.
First, it does not squarely present the issue on which
Constitution seeks review—both the State and the
Second Circuit rested their decisions on grounds
separate from and independent of the failure to
consider alternative routes. Second, the decision below
does not conflict with any decision of this Court or any
other court. Third, the case does not present the issues
of national security and federalism that petitioner
seeks to raise.
I.
This Case Does Not Present the Question of
Whether A Water Quality Certification Can
Be Denied for Failure to Consider Alternative
Routes.
The petition should be denied because this case
does not squarely present the issue that Constitution
seeks to have reviewed, namely, whether a State may
deny a certification under § 401 of the Clean Water Act
“on the basis of purportedly receiving insufficient
information regarding alternative routes for [an]
interstate natural gas pipeline” (see Pet. ii). The State
based its denial on Constitution’s failure to support its
application in multiple areas. Thus, even if Constitution’s failure to provide information regarding
“alternative routes” were one of the areas on which the
Second Circuit relied—and, as shown below, it was
not—the State denied Constitution’s application for a
water-quality certification based on numerous
independent grounds.
Contrary to Constitution’s argument, the Second
Circuit did not hold that the “single cognizable
rationale” for the denial was “the issue of alternative
11
routes” (Pet. 16). Rather, the Second Circuit observed
that the State was authorized to request information
regarding alternative routes. (Pet. App. 29a.) The
court added, however, that it “need not address”
Constitution’s contention that the State relied on
improper factors because the State’s decision was
independently sustainable on other grounds and,
“where an agency decision is sufficiently supported by
even as little as a single cognizable rationale, that
rationale, ‘by itself, warrants our denial of [a] petition’
for review under the arbitrary-and-capricious standard
of review.” (Pet. App. 29a [record citation omitted].)
The Second Circuit observed that the State had
“requested but had not received sufficient information
with regard to” multiple issues, including not only
“alternative routes,” but also “construction methods
and site-specific project plans for stream crossings”;
“pipeline burial depth in stream beds”; “procedures
and safety measures Constitution would follow in the
event that blasting is required”; “plans to avoid,
minimize, or mitigate discharges to navigable waters
and wetlands”; and “cumulative impacts” from the
project. (Pet. App. 31a; see also Pet. App. 15a-22a, 33a
[Second Circuit]; 50a-52a, 58a-64a [administrative
denial].) The court recognized that “[n]owhere does
Constitution claim to have provided the above categories of information.” (Pet. App. 32a.) Constitution’s
failure to provide information as to any one of those
other matters—all of which fall within New York’s
authority under § 401—suffices to uphold the denial.
Indeed, the Second Circuit made clear that the
State had “focused principally on Constitution’s failure
to provide information with respect to stream crossings.” (Pet. App. 16a [record citation omitted].) Apart
from the refusal to provide information as to possible
12
alternative routes, the Second Circuit ultimately
concluded that the denial could be upheld because
Constitution “persistently refused” to submit “site-bysite information as to the feasibility of trenchless
crossing methods for streams less than 30 feet wide—
i.e., the vast majority of the 251 New York waterbodies
to be crossed by its pipeline.” (Pet. App. 33a.)
Accordingly, reading the decision below in context,
the Second Circuit held that the failure to provide
information regarding waterbody-crossing technologies
constituted at least one valid reason supporting the
State’s denial. That reason would support the denial
independently, even if the State’s request for information regarding possible alternative routes had been
improper. (See Pet. App. 29a-33a.) Thus, contrary to
the suggestion of amici (Br. for National Ass’n of Mfrs.
et al. at 21), the State did not act “based on its disagreement with FERC over a matter within FERC’s
exclusive authority.” Rather, the State denied the
certification because Constitution had not provided
information on stream-crossing methods and other
issues directly within the State’s authority under
Clean Water Act § 401.
Further, the State did not require that the proposed
pipeline be rerouted. The State simply expressed its
dissatisfaction with Constitution’s failure to explore
fully an alternative route that would co-locate the
pipeline with an existing right-of-way instead of
clearing 100 miles of new right-of-way. (Pet. App. 38a39a, 60a.) Such analysis reasonably fell within the
State’s overarching mission under § 401(a) to enforce
state water-quality standards. Examining impacts on
water quality necessarily requires the State to
examine a project’s location. See, e.g., Islander E.
13
Pipeline Co., LLC v. McCarthy, 525 F.3d 141, 151-52
(2d Cir.), cert. denied, 555 U.S. 1046 (2008).
In sum, even if the State’s observations regarding
possible alternative routes exceeded its authority
under Clean Water Act § 401 (and they did not), the
Second Circuit upheld the denial based on other valid
grounds. As shown above, the Second Circuit confirmed
the State’s denial of a water-quality certification based
on Constitution’s failure to provide information on
many issues, most notably the means by which
Constitution would minimize impacts on the many
streams the pipeline would cross. Therefore, this case
does not squarely present the question of whether
failure to provide information on alternative routes
can justify denying a water-quality certification, and
this Court’s resolution of the issue proposed by
Constitution would be an academic exercise.
Accordingly, the petition should be denied.
II. The Second Circuit’s Decision Does Not
Conflict with the Governing Statutes, Any
Decision of This Court, or the Decisions of
Other Circuit Courts.
The Court should deny certiorari for the additional
reason that the Second Circuit’s decision does not
conflict with any decision of this Court or any other
court of appeals.
First, the Second Circuit’s decision is a straightforward application, on the specific administrative
record in this case, of the Clean Water Act’s carve-out
for state water-quality regulation, which the Natural
Gas Act expressly preserves. As the Second Circuit
recognized (Pet. App. 28a-29a), Clean Water Act § 401
authorizes States to deny certification to a federally
14
approved project when the applicant fails to establish
that the project will comply with state water-quality
standards. See 33 U.S.C. § 1341(a)(1), (d). If a State
denies a § 401 certification, “[n]o license or permit
shall be granted” for the project by the federal
permitting agency. Id. § 1341(a)(1). The Natural Gas
Act broadly preserves the States’ authority over
water-quality issues by providing that “nothing in [the
Natural Gas Act] affects the rights of States under”
the Clean Water Act. 15 U.S.C. § 717b(d)(3).
Second, the decision below is consistent with this
Court’s decisions. This Court has recognized that § 401
“was meant to ‘continu[e] the authority of the
State . . . to act to deny a permit and thereby prevent
a Federal license or permit from issuing to a discharge
source within such State.’” S.D. Warren, 547 U.S. at
380 (quoting S. Rep. No. 92-414, at 69 [1971]). No
similar express preservation of state rights was at
issue in Schneidewind v. ANR Pipeline Co., relied on
by Constitution, which held that the Natural Gas Act
occupied the field with respect to the issuance of
securities of natural gas companies, preempting a
state law attempting to regulate in that arena. 485
U.S. 293, 309-11 (1988).
Third, the two circuit cases cited by Constitution
to show a conflict (Pet. 16-17) miss the mark. The
Second Circuit’s decision in National Fuel Gas Supply
Corp. v. Public Service Commission did not involve the
State’s federally granted authority under the Clean
Water Act. Instead, it concerned regulations under the
State’s Public Service Law, which were not federally
sanctioned. See 894 F.2d 571, 574-75 (2d Cir.), cert.
denied, 497 U.S. 1004 (1990). Moreover, even if
National Fuel Gas conflicted with the decision below
(and it does not), an intra-circuit conflict does not
15
merit this Court’s review. Notably, the Second Circuit
denied Constitution’s petition for panel rehearing or
rehearing en banc. (Pet. App. 67a.)
As for Weaver’s Cove Energy, LLC v. Rhode Island
Coastal Resources Management Council, that case
concerned a Rhode Island state licensing program for
coastal dredging. 589 F.3d 458, 472 (1st Cir. 2009). As
relevant here, the First Circuit held that the state
dredging regulation could not block the construction of
a liquefied natural gas terminal when FERC had
exercised its federal authority to permit the dredging.
Id. at 473-74. Again, the State’s separate, federally
preserved right to review water-quality impacts under
§ 401 of the Clean Water Act was not implicated.
III. This Case Does Not Implicate the National
Security and Federalism Concerns Cited by
Petitioner.
This case does not raise the national security and
federalism concerns that Constitution seeks to invoke.
Nothing in FERC’s conditional certificate or
rehearing order indicated that the agency considered
Constitution’s proposed pipeline to be necessary as a
matter of national security. (See CA2 J.A. 1668-1686,
1711-1713, 2723-2798.) Rather, the Certificate reflected
FERC’s judgment that the benefits of the project
would outweigh the costs only if Constitution complied
with certain environmental conditions, including satisfying the State that the project would comply with
state water-quality standards. (CA2 J.A. 1668, 17111712, 1717.) Thus, there is no basis for petitioner’s
claim that national security concerns warrant this
Court’s review.
16
Nor does the decision implicate federalism
concerns. Constitution’s argument that the Second
Circuit’s decision would violate the Supremacy and
Commerce Clauses of the U.S. Constitution (Pet. 2125) is premised on the incorrect proposition that the
State exceeded its authority in denying the application
for a Clean Water Act § 401 certification. To the
contrary, as demonstrated above (at 13-14), the Second
Circuit’s decision is consistent with the cooperative
federalism framework established by § 401 of the Clean
Water Act and § 717b(d)(3) of the Natural Gas Act.
Therefore, federalism concerns do not support a grant
of certiorari.
Finally, the State’s denial of the § 401 certification
was effectively without prejudice: Constitution remains
free to re-apply for a § 401 certification and provide
the information the State determined to be deficient.
(Pet. App. 65a.)
17
CONCLUSION
The petition for a writ of certiorari should be
denied.
Respectfully submitted,
ERIC T. SCHNEIDERMAN
Attorney General
State of New York
BARBARA D. UNDERWOOD*
Solicitor General
ANDREW D. BING
Deputy Solicitor General
FREDERICK A. BRODIE
Assistant Solicitor General
BRIAN LUSIGNAN
Assistant Attorney General
Environmental Protection
Bureau
barbara.underwood@ag.ny.gov
March 2018
*Counsel of Record
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.