Opinion

United States of America for the use and benefit of EWS Texas, Inc. v. The Robins & Morton Group

Court
District Court, M.D. Alabama
Filed
Sep 28, 2023
Cited by
0 cases
Authority
More cited than 16.5%

stating the Supreme Court has “repeatedly held that ambiguities about the scope of an arbitration agreement must be resolved in favor of arbitration.” (citations omitted)

How later courts described this case

  • stating the Supreme Court has “repeatedly held that ambiguities about the scope of an arbitration agreement must be resolved in favor of arbitration.” (citations omitted)

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE MIDDLE DISTRICT OF ALABAMA

SOUTHERN DIVISION

UNITED STATES OF AMERICA, )

for the use and benefit of EWS TEXAS, )

INC., )

)

Plaintiffs, )

)

v. ) Case No. 1:23-cv-00288-RAH-KFP

) [WO]

THE ROBINS & MORTON GROUP, )

et. al., )

)

Defendants. )

MEMORANDUM OPINION AND ORDER

I. INTRODUCTION

The United States of America, for the use and benefit of EWS Texas, Inc.

(EWS), sues Defendants The Robins & Morton Group (RMG) and Zurich American

Insurance Company (Zurich) under the Miller Act, 40 U.S.C. § 3131, et seq., and

the Alabama Prompt Payment Act, Ala. Code § 8-29-3, after the Defendants

allegedly failed to pay EWS for work performed on a construction project at the Fort

Rucker Training Support Facility. RMG has moved to compel arbitration of all

claims against it and to stay this action. Zurich consents to RMG’s requested relief

but does not seek arbitration of the claims against it. EWS opposes RMG’s motion.

The motion being fully briefed and ripe for review, the Court concludes that it is due

to be granted.

II. JURISDICTION AND VENUE

The Court has jurisdiction over this action pursuant to 28 U.S.C. § 1331. The

Court finds adequate allegations to support both jurisdiction and venue.

III. BACKGROUND

According to the Complaint, RMG entered into a construction contract with

the United States Army Corps of Engineers to construct the Fort Rucker Training

Support Facility. (Doc. 1 at 3.) RMG obtained a payment bond for which Zurich

was the surety. (Id.) On June 14, 2021, RMG entered into a Subcontract with EWS

for work on the project, including roof and siding installation. (Id.) RMG failed to

pay EWS amounts due and owing under the Subcontract after EWS completed its

work and demanded payment. (Id.)

On May 1, 2023, EWS sued RMG and Zurich, asserting four causes of action:

(1) suit on the payment bond, brought jointly against RMG and Zurich; (2) breach

of contract, brought against RMG; (3) quantum meruit, brought against RMG; and

(4) violation of the Alabama Prompt Payment Act, brought against RMG. (Doc. 1

at 4–9.)

IV. LEGAL STANDARD

There is an “emphatic federal policy in favor of arbitral dispute resolution.”

Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473 U.S. 614, 631 (1985).

The Federal Arbitration Act (FAA) requires courts to “rigorously enforce

agreements to arbitrate.” Davis v. Prudential Sec., Inc., 59 F. 3d 1186, 1192 (11th

Cir. 1995) (quoting Shearson/Am. Express, Inc. v. McMahon, 482 U.S. 220, 226

(1987)). “[T]he party seeking to compel arbitration bears the burden of proving . . .

the existence of a binding arbitration agreement, its applicability to the claim at issue,

and a sufficient connection to interstate commerce[.]” Hammonds v. Montgomery

Children’s Specialty Center, LLC, No. 2:21-cv-448-MHT, 2023 WL 4474095, at *2

(M.D. Ala. July 11, 2023) (citation omitted). “If the moving party makes the

requisite showing, the burden shifts to the nonmoving party to present evidence that

the arbitration agreement is invalid or inapplicable to the dispute in

question. Finally, if the court finds that there is a binding and enforceable arbitration

clause pursuant to the FAA, it is required to order the parties to submit to arbitration.

Additionally, if one of the parties to the agreement requests a stay of litigation

pending said arbitration, the court is statutorily bound to grant the stay.” Id.

(citations omitted).

V. DISCUSSION

RMG asserts that EWS must pursue its claims against RMG in arbitration in

accordance with the arbitration clause contained in the Subcontract between RMG

and EWS. EWS opposes the motion, arguing that Miller Act claims cannot be

arbitrated and because the scope of the arbitration clause does not require arbitration

of EWS’s claims. Neither argument is persuasive.

A. The Miller Act

Asserting the parties did not contractually waive the right to bring a civil

action in federal court under the Miller Act, 40 U.S.C. § 3131, et seq., EWS

maintains the arbitration of disputes solely between RMG and EWS is statutorily

prohibited. EWS relies on § 3133(c) of the Miller Act which provides that a waiver

of the right to bring a civil action on a payment bond is void unless the waiver is in

writing, signed by the person whose right is waived, and is executed after the person

whose right is waived has furnished labor or material for use in the performance of

the contract. 40 U.S.C. § 3133(c). According to EWS, the waiver provision applies

because the Subcontract’s arbitration clause is a “quintessential waiver of the right

to bring a civil action” and, by analogy, courts have refused to enforce forum

selection clauses that require Miller Act suits to be brought in state court rather than

federal court. (Doc. 23 at 3.) EWS cites to no case decisions that support its

argument while RMG cites to numerous other court decisions that support its

position.

The Court sees little reason to discuss this issue further, especially in the

absence of any authority from EWS. In short, courts have overwhelmingly

concluded that Section 3133(c) of the Miller Act does not prohibit enforcement of

an arbitration agreement executed before the subcontractor has furnished labor or

material for use in the performance of the contract. See, e.g., United States v.

International Fidelity Ins. Co., 232 F. Supp. 3d 1193, 1195–98 (S.D. Ala. 2017);

United States ex rel. Milestone Tarant, LLC v. Fed. Ins. Co., 672 F. Supp. 2d 92,

104 (D.D.C. 2009) (collecting cases). The Court agrees with the logic in those

decisions. See also United States ex rel. Harbor Const. Co., Inc. v. T.H.R. Enters.,

Inc., 311 F. Supp. 3d 797, 802 (E.D. Va. 2018). Accordingly, EWS’s Miller Act

waiver argument is unavailing and due to be rejected.

B. Scope of the Arbitration Agreement

Citing Article 30 (Claims and Disputes; Arbitration as a Remedy) of the

Subcontract, EWS argues “only those claims which are the result of the Owner’s

errors and omissions are subject to arbitration” and since “EWS’ claims are not

against the Owner nor does EWS allege that the Owner is at fault” and that its

“damages are the result of Robins & Morton’s errors and omissions, not the

Owner’s,” then EWS’s claims against RMG cannot be forced into arbitration. RMG

responds, arguing that EWS misinterprets the language in Article 30 and in fact has

it backwards.1

The Subcontract (see Doc. 16-2 at 6–49) provides that “any disputes between

[RMG] and [EWS] not resolved under Paragraphs 30.2 and 30.3 shall be finally

1 Neither party argues that this is an issue of arbitrability that must be submitted to the arbitrator

for resolution due to the existence of a delegation clause. Compare Betkowski v. Kelley Foods of

Ala, Inc., 697 F. Supp. 2d 1296, 1300–01 (M.D. Ala. 2010), with Neal v. GMRI, Inc., No. 1:19-

cv-647-RAH, 2020 WL 698270, at *4–5 (M.D. Ala. Feb. 11, 2020). Accordingly, the Court

does not consider this issue.

determined by binding arbitration in accordance with the Construction Industry

Rules of the American Arbitration Association as those Rules existed on January 1,

1994 (notwithstanding any later amendments, except as to fees) by one or more

arbitrators selected in accordance with said Rules.” (Doc. 16-2 at 16.) Paragraph

30.2 provides, “In case of any dispute between [RMG] and [EWS], in any way

relating to or arising from any act or omission of the [Army Corps] or involving the

Contract Documents, [EWS] agrees to be bound to [RMG] to the same extent that

[RMG] is bound to the [Army Corps], by the terms of the Contract Documents, and

by any and all preliminary and final decisions or determinations made thereunder by

the party, board or court so authorized in the Contract Documents or by law, whether

or not [EWS] is a party to such proceedings.” (Id.) And paragraph 30.3 provides,

“If an appeal or legal proceeding is specifically permitted by the Contract

Documents and if requested in writing by [EWS], [RMG] will, in its name and on

[EWS’s] behalf, appeal any decision of [the Army Corps] or Architect or institute a

legal proceeding against [the Army Corps] based on any just claim by [EWS]

involving the Work.” (Id.)

The Court disagrees with EWS’s interpretation of the scope of Article 30 and,

alternatively, EWS’s assertion of ambiguity concerning Paragraphs 30.2, 30.3 and

30.4. Article 30 generally contemplates two types of claims: (1) claims brought by

EWS that arise out of conduct by the Army Corps, and (2) claims brought by EWS

that arise out of conduct by RMG that is unrelated to the acts of the Army Corps.

The former type of claims arguably cannot be arbitrated, as they contemplate an

action whereby EWS is bound by whatever resolution and outcome that RMG

obtains from and against the Army Corps. The latter type of claims however must

be arbitrated.

In its brief, EWS concedes that its claims are against RMG, that EWS’s claims

are not against the Army Corps, that the Army Corps bears no fault for EWS’s

damages, and that EWS’s damages flow from RMG’s own errors and omissions.

Under the plain language of Paragraphs 30.2, 30.3 and 30.4 of Article 30, these are

the type of claims that must be determined by binding arbitration in accordance with

the Construction Industry Rules of the American Arbitration Association. That was

the agreement of the parties. Contrary to EWS’s assertion, there is no ambiguity,

but to the extent there is ambiguity, considering the favorability that must be shown

toward enforcement of arbitration agreements under the FAA, such ambiguity must

be construed in favor of enforcing the arbitration agreement. Lamps Plus, Inc. v.

Varela, 587 U.S. __, 139 S.Ct. 1407, 1418 (2019) (stating the Supreme Court has

“repeatedly held that ambiguities about the scope of an arbitration agreement must

be resolved in favor of arbitration.” (citations omitted)).

VI. CONCLUSION

Accordingly, it is ORDERED that,

(1) Defendant The Robins & Morton Group’s Motion to Compel

Arbitration and to Stay This Action Pending Arbitration (Doc. 16) is GRANTED;

(2) Plaintiff United States of America, for the use and benefit of EWS

Texas, Inc., shall immediately pursue its claims against Defendant The Robins &

Morton Group by binding arbitration in accordance with the Construction Industry

Rules of the American Arbitration Association;

(3) This action is STAYED, including the claims brought against Zurich

American Insurance Company, pending resolution of the arbitration proceeding;

(4) Onor before November 10, 2023, and on or before the tenth day of

every second month thereafter, the Defendants are ORDERED to jointly file and

serve a report detailing the status of the arbitration proceeding;

(5) Plaintiff shall notify the Court of the conclusion of the arbitration

proceeding within fourteen days of the same.

DONE on this the 28th day of September 2023.

Cbd.

Bhife

UNITED STATES DISTRICT JUDGE

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.