Opinion

United Aeronautical Corp. v. Usaf

  • 80 F.4th 1017
Court
Court of Appeals for the Ninth Circuit
Filed
Sep 7, 2023
Status
Published
Cited by
28 cases
Authority
More cited than 73.7%

noting that “easily-spotted breach-of-contract claims” in Tucker Act-adjacent APA 13 actions include rights “flowing from” the “performing of contracts” (alterations omitted)

How later courts described this case

  • noting that “easily-spotted breach-of-contract claims” in Tucker Act-adjacent APA 13 actions include rights “flowing from” the “performing of contracts” (alterations omitted)
  • noting that “an injunction directing the Army to execute the [contract]” is “a 1 thinly veiled request for specific performance,” a “traditional” breach-of-contract remedy
  • “Thus, where the government’s waiver includes a 10 limitation about ‘what courts’ may hear a claim against it, we cannot defer to the plaintiff’s 11 choice of court; instead, we must ‘strictly’ construe the waiver to effectuate Congress’s 12 limitation on it.”
  • adopting the two-part test from Megapulse, Inc. v. Lewis, 672 F.2d 959, 968 (D.C. Cir. 1982)

Written by the judges who cited it.

The opinion

FOR PUBLICATION

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

UNITED AERONAUTICAL No. 21-56377

CORPORATION; BLUE

AEROSPACE, LLC, D.C. No.

2:20-cv-01985-

Plaintiffs-Appellants, ODW-JDE

v.

UNITED STATES AIR FORCE; OPINION

UNITED STATES AIR NATIONAL

GUARD,

Defendants-Appellees,

Appeal from the United States District Court

for the Central District of California

Otis D. Wright II, District Judge, Presiding

Argued and Submitted December 9, 2022

Pasadena, California

Filed September 7, 2023

Before: MILAN D. SMITH, JR., DANIEL P. COLLINS,

and KENNETH K. LEE, Circuit Judges.

Opinion by Judge Milan D. Smith, Jr.;

Dissent by Judge Collins

2 UNITED AERONAUTICAL CORP. V. USAF

SUMMARY *

Contract Disputes Act / Jurisdiction

The panel affirmed the district court’s dismissal for lack

of subject-matter jurisdiction of an Administrative

Procedure Act (APA) action brought by United Aeronautical

Corporation and Blue Aerospace, LLC (collectively, Aero)

against the U.S. Air Force and U.S. Air National Guard

(collectively, USAF) alleging that USAF improperly used

Aero’s intellectual property—data relating to the Mobile

Airborne Firefighting System (MAFFS)—in violation of

federal procurement regulations and the Trade Secrets Act.

Aero delivered a hard drive containing MAFFS-related

data to the United States Forest Service and executed a Data

Rights Agreement (DRA) granting the Forest Service

“unlimited rights to view and use” the data. The Forest

Service delivered that hard drive to USAF, and Aero sued

USAF for its receipt and use of the MAFFS data.

The APA waives sovereign immunity for actions in

federal district court by persons suffering legal wrong

because of agency action; however, when a statute vests

exclusive jurisdiction over a category of claims in a

specialized court, it “impliedly forbids” an APA action in

district court.

The panel agreed with the district court that the Contract

Disputes Act “impliedly forbids” jurisdiction over Aero’s

claims by vesting exclusive jurisdiction over federal-

*

This summary constitutes no part of the opinion of the court. It has

been prepared by court staff for the convenience of the reader.

UNITED AERONAUTICAL CORP. V. USAF 3

contractor disputes in the Court of Federal Claims. A claim

falls within the scope of the CDA’s exclusive grant of

jurisdiction if (1) the plaintiff’s action relates to (2) a

procurement contract (3) to which the plaintiff was a

party. Here, Aero’s claims that USAF improperly received

and used MAFFS data (1) relate to the DRA, (2) the DRA is

a procurement contract, and (3) Aero is a contractor for

purposes of the DRA.

The panel held that the test set forth in Megapulse, Inc.

v. Lewis, 672 F.2d 959 (D.C. Cir. 1982), is limited to

determining whether the Tucker Act—which grants

exclusive jurisdiction to the Court of Federal Claims over

breach-of contract actions for money damages—“impliedly

forbids” an ADA action because Megapulse addressed

implied preclusion only pursuant to the Tucker Act, not

pursuant to the CDA.

Dissenting, Judge Collins would reverse the district

court’s dismissal for lack of subject-matter jurisdiction, and

hold that the CDA does not “impliedly forbid” Aero from

bringing an APA action because Aero’s claims are not based

on a government contract, but instead on Aero’s independent

statutory rights under the Trade Secrets Act.

4 UNITED AERONAUTICAL CORP. V. USAF

COUNSEL

David M. Almaraz (argued), Grant Shenon APLC, Sherman

Oaks, California; Jonathan R. Hickman, Esquire Corporate

Services LC, Encino, California; for Plaintiffs-Appellants.

Paul B. Green (argued) and Joanne S. Osinoff, Assistant

United States Attorneys; David M. Harris, Assistant United

States Attorney, Civil Division Chief; Tracy L. Wilkison,

United States Attorney; United States Attorney’s Office, Los

Angeles, California, for Defendants-Appellees.

OPINION

M. SMITH, Circuit Judge:

United Aeronautical Corporation and Blue Aerospace,

LLC (collectively, Aero) filed suit against the United States

Air Force and Air National Guard (collectively, USAF) in

the U.S. District Court for the Central District of California.

Aero alleges that USAF has for some time violated federal

procurement regulations and the Trade Secrets Act, 18

U.S.C. § 1905, by improperly using Aero’s intellectual

property. The district court dismissed for lack of subject-

matter jurisdiction, concluding that the Contract Disputes

Act (CDA), 28 U.S.C. § 1491(a)(2), precludes jurisdiction

over Aero’s action by vesting exclusive jurisdiction over

federal-contractor disputes in the Court of Federal Claims.

We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

This litigation relates to the Mobile Airborne

Firefighting System (MAFFS): an anti-retardant tank system

UNITED AERONAUTICAL CORP. V. USAF 5

that converts cargo planes so that they can combat fires. 1

From about 1980 to 2000, Aero Union—a different company

than the plaintiffs in this case—developed the original

MAFFS. In 2000, Aero Union contracted with the U.S.

Forest Service to develop an updated MAFFS prototype

(MAFFS II), which incorporated significant amounts of

Aero Union’s intellectual property that was developed from

1980 to 2000.

In 2012, Aero—the plaintiffs in this case—purchased

Aero Union’s intellectual property in a foreclosure sale. In

2014, to support the Forest Service’s continued use of

MAFFS II, Aero delivered a hard drive containing MAFFS-

related data to the Forest Service and executed a Data Rights

Agreement (DRA) providing:

“[A]s set forth in [2000 Contract between

Aero Union and the Forest Service], the

technical data produced or specifically used

or related to [MAFFS II] developed pursuant

to such contract shall remain the property of

[Aero] (as the purchaser of assets of Aero

[Union] . . . ) and [the Forest Service] shall

have unlimited rights to view and use the

data required for the continued operation

1

For purposes of this appeal, we accept Aero’s allegations as true

because USAF’s motion to dismiss for lack of subject-matter jurisdiction

raised a facial, not factual, challenge. See Wolfe v. Strankman, 392 F.3d

358, 362 (9th Cir. 2004).

6 UNITED AERONAUTICAL CORP. V. USAF

and maintenance of [MAFFS II]”

(emphasis added).

Thereafter, the Forest Service delivered that hard drive to

USAF, which developed an upgraded system (iMAFFS) and

marketed that system internationally.

Aero sued USAF, not the Forest Service, for its receipt

and use of the MAFFS data. Specifically, Aero brought a

claim pursuant to the Administrative Procedure Act (APA),

5 U.S.C. §§ 701–06, alleging that USAF had violated and

continues to violate federal procurement regulations and the

Trade Secrets Act. USAF moved to dismiss, arguing that the

CDA vests exclusive jurisdiction over federal-contractor

disputes in the Court of Federal Claims. The district court

granted the motion with leave to amend. Aero filed an

amended complaint; USAF again moved to dismiss; and the

district court granted the motion, this time without leave to

amend. Aero timely appealed.

JURISDICTION AND STANDARD OF REVIEW

We have jurisdiction pursuant to 28 U.S.C. § 1291. We

review a district court’s dismissal for lack of subject-matter

jurisdiction de novo. Dogan v. Barak, 932 F.3d 888, 892

(9th Cir. 2019).

ANALYSIS

The district court correctly held that it lacked subject-

matter jurisdiction over Aero’s action. A private party may

sue the United States only if the United States has waived

sovereign immunity. Esquivel v. United States, 21 F.4th

565, 572 (9th Cir. 2021). If the United States has not waived

sovereign immunity, then the court where the suit is filed

UNITED AERONAUTICAL CORP. V. USAF 7

must dismiss the case for lack of subject-matter jurisdiction.

Id. at 572–73.

The APA waives sovereign immunity for actions in

federal district court by “person[s] suffering legal wrong

because of agency action.” 5 U.S.C. § 702. That waiver,

however, is subject to three limitations: (1) the plaintiff must

“seek[] relief other than money damages”; (2) the plaintiff

must have “no other adequate remedy”; and (3) the

plaintiff’s action must not be “expressly or impliedly

forbid[den]” by “any other statute.” See id. §§ 702, 704;

Tucson Airport Auth. v. Gen. Dynamics Corp., 136 F.3d 641,

645 (9th Cir. 1998). Where a statute vests exclusive

jurisdiction over a category of claims in a specialized court

(e.g., the Court of Federal Claims), it “impliedly forbids” an

APA action brought in federal district court. See Tuscon

Airport, 136 F.3d at 646; N. Star Alaska v. United States, 9

F.3d 1430, 1432 (9th Cir. 1993) (en banc) (per curiam).

This appeal concerns only the third limitation: The

parties dispute whether the CDA forbids Aero from

maintaining its APA claim in district court because it falls

within the category of claims that the CDA requires to be

litigated in the Court of Federal Claims. 2 We hold that it

2

Aero also brought a claim pursuant to the Declaratory Judgment Act

(DJA), 28 U.S.C. § 2201. The DJA “does not ‘extend’ the ‘jurisdiction’

of the federal courts.” Medtronic, Inc. v. Mirowski Fam. Ventures, LLC,

571 U.S. 191, 197 (2014) (citing Skelly Oil Co. v. Phillips Petroleum

Co., 339 U.S. 667, 671 (1950)). A DJA claim, therefore, “may not be

used as an end run around” the limits of the APA’s sovereign-immunity

waiver. See Alaska Dep’t of Nat. Res. v. United States, 816 F.3d 580,

586 (9th Cir. 2016) (citing McMaster v. United States, 731 F.3d 881, 900

(9th Cir. 2013)). Because the availability of Aero’s DJA claim depends

on the availability of its APA claim, we need only analyze the latter.

8 UNITED AERONAUTICAL CORP. V. USAF

does and affirm the district court’s dismissal for lack of

subject-matter jurisdiction.

I. The CDA “impliedly forbids” jurisdiction over

Aero’s claims

The CDA serves two related functions. First, it

establishes an administrative system for disputes relating to

federal procurement contracts: Federal contractors can

submit written claims to agency contracting officers, receive

written decisions regarding their claims within a specified

timeframe, and administratively appeal adverse decisions.

See 41 U.S.C. §§ 7101–7109. Second, it waives sovereign

immunity over actions “arising under” that administrative

system and vests exclusive jurisdiction over such claims in

only two venues: (1) the Court of Federal Claims, 28 U.S.C.

§ 1491(a)(2); 41 U.S.C. § 7104(b)(1), and (2) agency boards

of contract appeals, 41 U.S.C. §§ 7104(a), 7105. A litigant

can appeal the decision of either the Court of Federal Claims

or an agency board to the U.S. Court of Appeals for the

Federal Circuit. U.S.C. § 1295(a)(3), (b); 41 U.S.C.

§ 7107(a)(1).

Through § 1491(a)(2)’s “arising under” language, the

scope of the CDA’s sovereign-immunity waiver and

jurisdictional grant is expressly tied to the scope of the

administrative system that it creates. This grant broadly

extends to “dispute[s] concerning termination of a contract,

rights in tangible or intangible property, compliance with

cost accounting standards, and other nonmonetary disputes

on which a decision of [a government] contracting officer

has been issued.” 28 U.S.C. § 1491(a)(2).

Because the scope of the CDA’s administrative system

dictates the scope of the CDA’s “arising under”

jurisdictional grant, we look to the contours of the

UNITED AERONAUTICAL CORP. V. USAF 9

administrative system to determine whether a particular

claim is covered by the CDA and thus must be litigated in

the Court of Federal Claims. First, the CDA applies to

“claim[s] . . . relating to a contract.” 41 U.S.C. § 7103(a)(1)

(emphasis added). Second, the CDA applies only to claims

involving a “contractor,” which is “a party to a Federal

Government contract other than the Federal Government.”

Id. §§ 7101(7), 7103(a)(1); see also 28 U.S.C. § 1491(a)(2)

(limiting jurisdiction to “any claim by or against, or dispute

with a contractor”). Third, as relevant here, the CDA applies

to contracts for “the procurement of property, other than real

property in being.” 41 U.S.C. § 7102(a)(1).

So, to summarize: a claim falls within the scope of the

CDA’s exclusive grant of jurisdiction if (1) the plaintiff’s

action “relat[es] to” (2) a procurement contract (3) to which

the plaintiff was a party. Aero’s action meets each

requirement, and thus the CDA “impliedly forbids” it.

A. Aero’s APA action “relat[es] to” the DRA

First, we must examine whether Aero’s claim “relat[es]

to” a contract. 41 U.S.C. § 7103(a)(1). We have not

previously construed the CDA’s “relating to” requirement.

USAF urges us to follow a Federal Circuit decision on a

related question and hold that a claim “relat[es] to” a

contract, and thus falls within the scope of the CDA, if it

“ha[s] some relationship to the terms or performance” of the

contract. Todd Constr., L.P. v. United States, 656 F.3d 1306,

1312 (Fed. Cir. 2011) (quoting Applied Cos. v. United States,

144 F.3d 1470, 1478 (Fed. Cir. 1998)).

We find the Federal Circuit’s reasoning to be persuasive

and adopt it here. In Todd, the Federal Circuit reasoned that

Congress’s “overall purpose to confer comprehensive

jurisdiction under the CDA” in the Court of Federal Claims

10 UNITED AERONAUTICAL CORP. V. USAF

counsels in favor of broadly interpreting “relating to.” Id. at

1311–12; see also United States v. Suntip Co., 82 F.3d 1468,

1474 (9th Cir. 1996) (“The intent behind [the CDA] is to

confine these government contract disputes to expert

tribunals created expressly for that purpose. That intent is

defeated if a contracting party may . . . compel the

government to litigate the merits of its contracting officers’

decisions in district court.”). It then turned to dictionary

definitions, finding that they treat “relating to” as a “term of

substantial breadth.” Todd, 656 F.3d at 1312. Finally, it

looked to Supreme Court precedent broadly interpreting

“related to” in other statutes, including in a similar

jurisdiction-conferring provision. Id. The Todd court

soundly applied traditional tools of statutory interpretation,

and we see no reason to depart from the result it reached.

Indeed, Aero concedes that Todd Construction “properly

analyzed” this “relating to” language.

To be sure, Todd presented a slightly different question.

Here, we are tasked with interpreting the statutory phrase

“claim . . . relating to a contract.” 41 U.S.C. § 7103(a)(1)

(emphasis added). Todd, on the other hand, construed

regulatory language that interpreted “claim,” as used in the

above phrase and throughout the CDA. 656 F.3d at 1311.

That regulation defined a “claim” as “a written demand . . .

seeking, as a matter of right, the payment of money in a sum

certain, the adjustment or interpretation of contract terms, or

other relief arising under or relating to the contract.” 48

C.F.R. § 2.101 (emphasis added). The “relating to” phrase

in the statute and regulation is the same, but the phrase

modifies different words in the two settings. In the CDA,

“relating to” modifies “claim.” In the regulation, it modifies

“relief.”

UNITED AERONAUTICAL CORP. V. USAF 11

The dissent argues that we should make the relief sought

the focal point of our “relating to” analysis—instead of

asking whether a plaintiff’s cause of action more generally

“relat[es] to” a contract. We need not decide in this case

which is the proper focal point: the cause of action generally

or the relief sought specifically. Here, our analysis under

both leads to the same result.

Starting with Aero’s cause of action generally, it has

“some relationship to the terms or performance” of the DRA.

Todd, 656 F.3d at 1312 (quoting Applied Cos., 144 F.3d at

1478). Aero brings an APA claim that USAF acted contrary

to law by violating the Trade Secrets Act. That Act, in turn,

simply prohibits government employees from disclosing

trade secrets “in any manner or to any extent not authorized

by law.” 18 U.S.C. § 1905. Therefore, the merits of this

case will, among other things, require a court to interpret the

DRA and determine whether the Forest Service was

authorized by that agreement’s “unlimited rights to view and

use” clause to disclose the MAFFS data to USAF.

Turning specifically to the relief that Aero sought, that

too has “some relationship to the terms or performance” of

the DRA. Todd, 656 F.3d at 1312 (quoting Applied Cos.,

144 F.3d at 1478). Aero, among other things, seeks a

declaration that the United States government generally “has

no ownership rights” in the MAFFS data and that USAF

does “not have the right to use” the MAFFS data “to develop

the iMAFFS system for . . . procurement to the international

market.” It blinks reality to argue that this requested relief

lacks “some relationship” to the DRA’s “unlimited rights to

view and use” clause. Such a declaration, which defines the

scope of the government’s MAFFS-data use rights,

12 UNITED AERONAUTICAL CORP. V. USAF

necessarily relates to the DRA, which grants the Forest

Service “unlimited rights to view and use” MAFFS data. 3

B. The DRA is a procurement contract

Second, we must examine whether the contract at issue

is one for “the procurement of property, other than real

property in being.” 41 U.S.C. § 7102(a)(1). USAF contends

that, through the DRA, it procured a property right in the

form of “unlimited rights to view and use” Aero’s purported

trade secrets. Aero’s argument comports with the statutory

text of the CDA, which extends the Court of Federal Claims’

jurisdiction to “dispute[s] concerning rights in . . . intangible

property.” 28 U.S.C. § 1491(a)(2) (emphasis added).

Moreover, it finds support in the Supreme Court’s decision

in Ruckelshaus v. Monsanto Co. 467 U.S. 986, 1000–04

(1984), where the Court held that trade secrets constitute

“property” for purposes of the Takings Clause. 4

Aero responds to USAF’s argument by analogizing the

DRA to a bailment contract, which one Court of Federal

Claims decision suggests does not constitute a procurement

contract covered by the CDA. See Telenor Satellite Servs.,

Inc. v. United States, 71 Fed. Cl. 114, 119 (2006) (“The

3

The district court stopped its analysis here. By declining to consider

whether Aero is a contractor and whether the DRA is a procurement

contract, the district court erred. However, that error was harmless: As

explained below, Aero’s action also fits the CDA’s second and third

jurisdictional requirements.

4

We recognize that an interest can sometimes constitute property for

constitutional purposes but not statutory ones. See, e.g., Shulman v.

Kaplan, 58 F.4th 404, 408, 410–12 (9th Cir. 2023) (holding that plaintiff

sufficiently pleaded a cannabis-related injury to property for Article III

standing but not for RICO statutory standing). But here, there is no

“statutory purpose or congressional intent,” id. at 410, behind the CDA

that warrants a departure from Ruckelshaus’s treatment of trade secrets.

UNITED AERONAUTICAL CORP. V. USAF 13

parties agree that this case is not governed by the Contract

Disputes Act because it does not involve a contract for the

procurement of goods or services. Rather, it involves an

alleged bailment contract for the possession and use of

certain electronic transmission equipment.”). We are not

persuaded by this analogy. To begin, Aero does not discuss

whether bailment (the granting of possession of personal

property to another for a temporary amount of time) applies

to intellectual property. But more critically, Aero does not

allege that it only temporarily granted intellectual property

rights to the Forest Service—an essential element of

bailment under the case law it cites. See Telenor, 71 Fed. Cl.

at 119 (bailment relationship “includes a return of the goods

to the owner” (quotation omitted)).

C. Aero is a contractor for purposes of the DRA

Third, we must examine whether Aero is a “contractor,”

which the CDA defines as “a party to a Federal Government

contract other than the Federal Government.” 41 U.S.C.

§ 7107(7). As the only party to the DRA other than the

Forest Service, Aero is clearly a contractor.

***

Because Aero’s action satisfies each of the prerequisites

of the CDA’s exclusive-jurisdiction provision and

sovereign-immunity waiver, we hold that the CDA

“impliedly forbids” Aero from invoking the otherwise-

applicable waiver of sovereign immunity contained in the

APA.

II. The Megapulse test for implied preclusion pursuant

to the Tucker Act does not apply to the CDA

Aero resists dismissal by arguing that Megapulse, Inc. v.

Lewis, 672 F.2d 959 (D.C. Cir. 1982), requires that its claim

14 UNITED AERONAUTICAL CORP. V. USAF

may be brought in district court. The Megapulse test,

however, is limited to determining only whether the Tucker

Act, not the CDA, “impliedly forbids” an APA action. The

CDA was not yet in effect when the parties in Megapulse

contracted with each other. And while the Tucker Act and

CDA share a common core, each statute confers a distinct

grant of exclusive jurisdiction to the Court of Federal

Claims. See Winter v. FloorPro, Inc., 570 F.3d 1367, 1372–

73 (Fed. Cir. 2009). Courts, therefore, must separately

analyze whether each statute “impliedly forbids” an APA

action. We use the Megapulse test to determine implied

preclusion pursuant to the Tucker Act, but we use the

analysis conducted above to determine implied preclusion

pursuant to the CDA. Here, we need not decide whether

Aero satisfies the Tucker Act’s Megapulse test because,

even if it does, the CDA still “impliedly forbids” bringing

this action in federal district court.

The Tucker Act dates back to the late nineteenth century,

see Tucker Act, ch. 359, § 1, 24 Stat. 505, 505 (1887), and

in its current form provides: “The United States Court of

Federal Claims shall have jurisdiction to render judgment

upon any claim against the United States founded either

upon the Constitution, or any Act of Congress or any

regulation of an executive department, or upon any express

or implied contract with the United States.” 28 U.S.C.

§ 1491(a)(1) (emphasis added). “Generally speaking, the

Tucker Act does not permit the [Court of Federal Claims] to

grant equitable or declaratory relief.” N. Star, 9 F.3d at

1432; see 28 U.S.C. § 1491(a)(2) (listing limited forms of

non-monetary relief the Court of Federal Claims may award

“as an incident of and collateral to” damages). Due to this

limited remedial authority, a contract-based action falls

within the scope of the Tucker Act only if the plaintiff seeks

UNITED AERONAUTICAL CORP. V. USAF 15

money damages for the breach of a government contract.

See, e.g., Boaz Hous. Auth. v. United States, 994 F.3d 1359,

1364–65 (Fed. Cir. 2021).

Therefore, we interpret the Tucker Act to “impliedly

forbid” an APA action seeking injunctive and declaratory

relief only if that action is a “disguised” breach-of-contract

claim. Megapulse, 672 F.2d at 968. To determine whether

that is the case, we use a two-part test derived from the D.C.

Circuit’s Megapulse decision, which looks to (1) “the source

of the rights upon which the plaintiff bases its claims” and

(2) “the type of relief sought (or appropriate).” Doe v. Tenet,

329 F.3d 1135, 1141 (9th Cir. 2003) (quoting Megapulse,

672 F.2d at 968); N. Star Alaska v. United States, 14 F.3d

36, 37 (9th Cir. 1994) (same). If rights and remedies are

statutorily or constitutionally based, then districts courts

have jurisdiction; if rights and remedies are contractually

based then only the Court of Federal Claims does, even if the

plaintiff formally seeks injunctive relief. This test imposes

something akin to a well-pleaded complaint rule for Tucker

Act-adjacent APA actions. The Tucker Act does not bar an

APA action if the plaintiff’s rights and remedies, as alleged,

are noncontractual—even if it is inevitable that the

government will raise a contract provision as a defense. Cf.

City of Oakland v. BP PLC, 969 F.3d 895, 903 (9th Cir.

2020) (explaining that federal-question jurisdiction’s well-

pleaded complaint rule “depends solely on the plaintiff’s

claims for relief and not on anticipated defenses to those

claims” (quotation omitted)).

Megapulse involved facts similar to this case. The

plaintiff brought an APA action alleging that the Coast

Guard violated its intellectual-property rights and sought

injunctive relief preventing further disclosure. 672 F.2d at

961–63. The merits inevitably turned on an intellectual-

16 UNITED AERONAUTICAL CORP. V. USAF

property licensing clause in a contract between the plaintiff

and the Coast Guard. See id. at 961. Nonetheless, the court

held that the plaintiff’s rights were derived not from the

contract but from the Trade Secrets Act and that the relief

sought (an injunction preventing disclosure) was not akin to

the traditional remedies available for breach of contract

(damages or specific performance). Id. at 968–970. As

such, the Tucker Act did not “impliedly forbid” the

plaintiff’s APA action brought in district court.

Aero relies on Megapulse to argue that the district court

has jurisdiction here because (1) its rights come but from

federal procurement regulations and the Trade Secrets Act,

not the contract; and (2) it seeks injunctive relief preventing

further use of its intellectual property and a declaration that

the USAF lacks any rights to the MAFFS data, not the

breach-of-contract remedies of money damages or specific

performance. USAF contends that this case is

distinguishable from Megapulse because the plaintiff in that

case developed its proprietary data before entering into any

government contract and requested quite limited injunctive

relief (return of only six documents). See Megapulse, 672

F.2d at 966.

We need not decide whether these differences warrant a

different jurisdictional decision pursuant to the Tucker Act’s

Megapulse test. That decision addressed implied preclusion

only pursuant the Tucker Act; it did not consider implied

preclusion pursuant to the CDA. Indeed, the contracts at

issue in Megapulse were not subject to the CDA. The last

contract in that case was formed in 1975, id. at 399–400, but

the CDA applies only to contracts formed after 1978, and a

key amendment to the CDA did not take effect until 1992,

see 28 U.S.C. § 1491 notes (effective dates of 1978 and 1992

amendments).

UNITED AERONAUTICAL CORP. V. USAF 17

Congress passed the CDA in 1978, adding subsection

1491(a)(2)’s second sentence that originally read: “The

Court of Claims shall have jurisdiction to render judgment

upon any claim by or against, or dispute with, a contractor

arising under the Contract Disputes Act of 1978.” Pub. L.

No. 95-563, § 14(i), 92 Stat. 2383, 2391; Todd Constr. L.P.

v. United States, 85 Fed. Cl. 34, 38–39 (2008). Following

the addition of this language, there was confusion about the

availability of declaratory relief pursuant to the CDA. See

Todd, 85 Fed. Cl. at 39–40. A little over a decade later,

Congress resolved this ambiguity when it passed the Federal

Courts Administration Act of 1992, which further amended

subsection 1491(a)(2) to clarify that CDA jurisdiction

encompasses “nonmonetary disputes.” Pub. L. No. 102-572,

§ 907(b)(1), 106 Stat 4506, 4519 (emphasis added).

Given these legislative amendments, the court in

Megapulse simply did not have the question before it that we

do: whether the CDA’s jurisdictional grant, separate from

that of the Tucker Act, “impliedly forbids” application of the

APA’s sovereign-immunity waiver. Nor do we see any

reason to adopt Megapulse as the test for determining

whether the CDA precludes district court jurisdiction over

an APA claim. The Tucker Act and CDA confer exclusive

jurisdiction over different sets of claims, so they necessarily

preclude different sets of APA claims—even if an implied-

preclusion analysis pursuant to each will often lead to the

same result.

The Tucker Act grants exclusive jurisdiction to the Court

of Federal Claims over breach-of-contract actions for money

damages. Therefore, the Megapulse test asks whether an

APA action is simply a disguised breach-of-contract action.

18 UNITED AERONAUTICAL CORP. V. USAF

The CDA, by contrast, grants exclusive jurisdiction to

the Court of Federal Claims over actions “relating to” a

procurement contract—some of which will look a lot like

Tucker Act claims. But unlike the Tucker Act, the CDA also

empowers the Court of Federal Claims to hear “nonmonetary

dispute[s]” and issue declaratory relief therein. Therefore,

to determine whether there is implied preclusion pursuant to

the CDA, we must ask whether an APA action is a disguised

CDA action. To do so, we employ the analysis conducted in

the previous section that determines whether an APA litigant

could bring a similar action pursuant to the CDA and obtain

similar relief.

For the reasons explained in the previous section, Aero’s

action satisfies each of the criteria necessary to fall within

the CDA’s exclusive-jurisdiction provision and waiver of

sovereign immunity. Indeed, had Aero exhausted its

administrative remedies, it could have maintained a

remarkably similar action in the Court of Federal Claims—

substituting the Forest Service as a defendant. 5 Aero asks

the district court to interpret its agreement with the Forest

Service, evaluate whether the Forest Service’s provision of

the MAFFS data to USAF exceeded the use rights granted

by the DRA, and grant injunctive and declaratory relief. The

CDA authorizes federal contractors to submit claims

“relating to” a government contract, 41 U.S.C. § 7103(a)(1)–

(2); authorizes judicial review of agency decisions, id.

5

USAF argues that dismissal for lack of subject-matter jurisdiction is

alternatively appropriate because Aero failed to exhaust its

administrative remedies pursuant to the CDA. Aero does not assert that

it ever submitted a claim to a Forest Service contracting officer, as

required by the CDA. In light of this concession and our holding that the

CDA applies to Aero’s action, dismissal was also proper on exhaustion

grounds.

UNITED AERONAUTICAL CORP. V. USAF 19

§ 7104(b)(1); incorporates standards of review similar to

those of the APA, id. § 7107(b); and, as explained more fully

below, empowers the Court of Federal Claims to issue

declaratory relief, 28 U.S.C. § 1491(a)(2) (jurisdiction

extends to “nonmonetary disputes”). The availability of

such an action in the Court of Federal Claims “impliedly

forbids” Aero from bringing its action in district court.

III. The Dissent’s Remaining Arguments Do Not Alter

This Conclusion

The dissent offers several other arguments for why the

CDA does not deprive the district court of jurisdiction over

Aero’s APA action, even though Aero could have brought a

remarkably similar action in the Court of Federal Claims.

None displaces the conclusion that we reached in this

decision.

A. The Well-Pleaded Complaint Rule Has No

Bearing On Whether the United States Has

Waived Its Sovereign Immunity

First, the dissent argues that our reading of the CDA

“erase[s] the distinction between a claim and a defense,” and

thus cannot be squared with the well-pleaded complaint rule,

which allows a plaintiff to avoid bringing a matter within the

jurisdiction of a particular forum by limiting the types of

claims it asserts. However, the well-pleaded complaint rule

is an interpretation applicable to a single statute: 28 U.S.C.

§ 1331. We have long interpreted that provision to require

that, for a court to be able to exercise its statutorily conferred

federal-question jurisdiction, “a federal question [must]

appear[] on the face of the complaint.” City of Oakland v.

BP PLC, 969 F.3d 895, 903 (9th Cir. 2020). Here, in

assessing whether Aero’s claims are of the type that fall

within § 1331, we complied with the well-pleaded complaint

20 UNITED AERONAUTICAL CORP. V. USAF

rule. By alleging violations of federal statutes and

regulations pursuant to the APA’s cause of action, Aero’s

complaint asserts a federal question and satisfies § 1331.

As the dissent acknowledges, § 702 of the APA does not

provide “an independent basis for subject matter

jurisdiction”—whether the federal courts are empowered to

hear the type of claims that the plaintiff asserts. Tucson

Airport, 136 F.3d at 645. Instead, that section provides a

limited waiver of sovereign immunity—whether, and

pursuant to what conditions, has the United States consented

to be sued for a claim that is otherwise within a federal

court’s jurisdiction. Though the dissent recognizes this

distinction, it fails to offer a good reason for exporting the

well-pleaded complaint rule from the former context

(federal-question jurisdiction) to the latter (waiver of

sovereign immunity).

Indeed, the two inquires have very different background

presumptions that counsel against the reflexive use of the

well-pleaded complaint rule in sovereign-immunity

analyses. Section 1331 analyses begin with a dual-

sovereignty presumption: “Under [our] system of dual

sovereignty, we have consistently held that state courts have

inherent authority, and are thus presumptively competent, to

adjudicate claims arising under the laws of the United

States.” Tafflin v. Levitt, 493 U.S. 455, 458 (1990). Because

state courts and federal courts are, as a general matter,

equally competent to adjudicate federal issues, we—when

applying § 1331—defer to the plaintiff as “the master of the

complaint” and allow him or her “to have [a] cause heard in

state court” by “eschewing claims based on federal law.”

See Holmes Grp., Inc. v. Vornado Air Circulation Sys., Inc.,

535 U.S. 826, 831 (2002) (citation omitted). In other words,

our § 1331 analysis lets litigants choose where to bring a

UNITED AERONAUTICAL CORP. V. USAF 21

claim (state or federal court) because each is competent to

hear it.

Sovereign immunity analysis, on the other hand, begins

with a presumption of government immunity: “An action can

be brought by a party against the United States only to the

extent that the Federal Government waives its sovereign

immunity.” Esquivel, 21 F.4th at 572 (citation omitted).

“[I]t rests with Congress to determine not only whether the

United States may be sued, but in what courts the suit may

be brought.” McGuire v. United States, 550 F.3d 903, 913

(9th Cir. 2008) (emphasis added) (quoting Minnesota v.

United States, 305 U.S. 382, 388 (1939)). Waivers of

sovereign immunity are, in turn, “construed strictly in favor

of the sovereign.” McGuire v. United States, 550 F.3d 903,

912 (9th Cir. 2008). Thus, where the government’s waiver

includes a limitation about “what courts” may hear a claim

against it, we cannot defer to the plaintiff’s choice of court;

instead, we must “strictly” construe the waiver to effectuate

Congress’s limitation on it.

Our analysis of the APA’s waiver followed the latter

sovereign-immunity-specific approach—not the section-

1331-specific approach that the dissent urges. The APA

waives sovereign immunity over certain claims in district

court unless “any other statute . . . impliedly forbids the relief

which is sought.” 5 U.S.C § 702. We held that the CDA

“impliedly forbids” certain contract-related actions by

requiring they be brought in the Court of Federal Claims or

before an agency contracting board (with appellate review

then before the Federal Circuit). A plaintiff cannot sidestep

the “impliedly forbids” limitation on the APA’s waiver of

sovereign immunity through clever pleading.

22 UNITED AERONAUTICAL CORP. V. USAF

B. Our Opinion Follows Circuit Precedent

Second, the dissent argues that our holding “ignores our

prior caselaw.” However, our opinion is wholly consistent

with the decisions that the dissent contends are contrary to

our interpretation of the CDA as it currently stands. The

dissent quotes Concrete Tie of San Diego Inc. v. Liberty

Constr., Inc., 9 F.3d 800 (9th Cir. 1993) for the proposition

that we have “‘narrowly’ construed” the “CDA’s preclusive

effect.” But that case concerned the pre-1992-amendment

CDA’s impact on jurisdiction conferred by the Small

Business Act’s sue-and-be-sued clause. See id. at 801–02.

That case said nothing about how the availability of

declaratory relief pursuant to the post-1992-amendment

CDA affects whether an APA action is “impliedly

forbid[den].” See 5 U.S.C. § 702. The other decision the

dissent cites is to a similar effect—even stating that it was

construing a “virtually identical” clause as Liberty

Construction had. Wright v. U.S. Postal Serv., 29 F.3d 1426,

1430 (9th Cir. 1994). In Wright, we once again considered

the interaction of a sue-and-be-sued clause with the CDA.

See id. Neither case, as this one did, discussed how the APA

interacts with the CDA—a unique context given the former’s

implied-preclusion limit on its waiver. These cases,

therefore, are fully consistent with our decision.

C. Our Opinion Considers a Different Kind of Claim

Than Sister-Circuit Precedent Has

Third, the dissent argues that our decision “creates a

circuit split with at least four circuits that expressly apply

Megapulse in assessing whether the CDA impliedly forbids

reliance on the APA.” But the sister-circuit decisions that

the dissent cites are, after further inspection, distinguishable.

UNITED AERONAUTICAL CORP. V. USAF 23

If depicted as a Venn diagram, the Tucker Act and

CDA’s two circles would have a large common area. A

classic Tucker Act action is a breach-of-contract claim for

money damages. E.g., Boaz Hous. Auth., 994 F.3d at 1364–

65. Similarly, CDA claims often involve the “seeking, as a

matter of right, the payment of money in a sum certain” for

the breach of a contract. 48 C.F.R. § 2.101. Thus, actions

seeking damages for the breach of a contract would form a

large common area in the Tucker Act–CDA Venn diagram.

But each statute also covers ground that the other does not.

On one side as the Federal Circuit explained in FloorPro,

third-party beneficiary contractors can sue pursuant to the

Tucker Act, while they cannot do so pursuant to the CDA.

570 F.3d at 1371–72. On the other side, as we explained

here, the CDA generally allows declaratory relief in

“nonmonetary disputes,” while the Tucker Act authorizes

declaratory relief only in limited circumstances. See 28

U.S.C. § 1491(a)(2).

Each of the sister-circuit decisions that the dissent cites

falls within the large overlapping area of the Tucker Act–

CDA Venn diagram and all involved claims that were easily-

spotted breach-of-contract claims. The D.C. Circuit

considered claims that the plaintiff framed as “flow[ing]

from their performing [of] contracts,” and even expressly

sought damages—notwithstanding that damages are

unavailable pursuant to the APA. A & S Council Oil Co. v.

Lader, 56 F.3d 234, 240 (D.C. Cir. 1995). The Second

Circuit decision was similar; the plaintiff expressly sought

“an injunction directing the Army to execute the facility

lease”—a thinly veiled request for specific performance. Up

State Fed. Credit Union v. Walker, 198 F.3d 372, 374, 376–

77 (2d Cir. 1999). Similarly, in the Third Circuit decision,

the government brought suit “seeking rescission of the

24 UNITED AERONAUTICAL CORP. V. USAF

contract”—yet another breach-of-contract remedy. United

States v. J & E Salvage Co., 55 F.3d 985, 987–89 (4th Cir.

1995). And in the Sixth Circuit decision, the plaintiffs

asserted rights and regulatory violations that were wholly

“depend[ent] upon whether contracts with [the Postal

Service] afford[ed] such a right.” B & B Trucking, Inc. v.

U.S. Postal Serv., 406 F.3d 766, 769–70 (6th Cir. 2005) (en

banc). Each of these decisions followed the Tucker Act’s

Megapulse test with little to no discussion of the CDA’s

statutory text. Though doing so was imprecise, it was

ultimately immaterial in those cases because each involved

a claim that fell squarely within the two statute’s common

overlap: breach-of-contract actions. In each case, whether

the implied-preclusion analysis was rooted in the Tucker Act

or the CDA, the result was the same: dismissal of the

plaintiffs’ claims.

Here by contrast, this case implicates an area that the

CDA covers but the Tucker Act does not; in other words, it

falls outside of the Venn diagram’s middle-ground overlap.

We do not understand our sister circuits’ decisions to require

blind adherence to the Megapulse test in such a situation.

Indeed, doing so would directly contradict the CDA’s text.

The CDA, unlike the Tucker Act, extends to “nonmonetary

disputes,” including requests for declaratory relief regarding

“rights in intangible property.” 28 U.S.C. § 1491(a)(2)

(emphasis added). The Megapulse test, if applied in cases

like this one, would risk rendering that aspect of the CDA a

dead letter. Given materially similar facts to Megapulse, a

plaintiff could always side-step the CDA because the

plaintiff’s asserted rights would be extracontractual (derived

from patent, trademark, copyright, or trade secret law) and

its remedies would be extracontractual (an injunction

preventing misuse). Presented with a case in which the

UNITED AERONAUTICAL CORP. V. USAF 25

Megapulse test would run roughshod over the CDA’s text,

we chose to follow the text. None of the decisions the dissent

cites stands for the proposition that, if presented with a case

like this, our sister circuits would do otherwise.

D. Aero Can Seek Declaratory Relief in the Court of

Federal Claims

Fourth, the dissent argues that our decision “could

seriously impede the ability of plaintiffs to obtain injunctive

relief.” That may be correct as a factual matter—depending

on how the Federal Circuit resolves the question it reserved

in Todd, 656 F.3d at 1311 n.3 (reserving the question of

whether the Court of Federal Claims may issue injunctive

relief in addition to declaratory relief in CDA cases). But we

are unsure what legal significance that observation has, since

the government is free to waive its immunity only for certain

forms of relief.

In any event, Aero could seek declaratory relief in a

CDA action that would not be materially different from the

injunctive relief it would be able to seek in an APA action.

Indeed, “there is little practical difference between

injunctive and declaratory relief.” California v. Grace

Brethren Church, 457 U.S. 393, 394 (1982). The primary

difference is that declaratory relief “is a much milder form”

of relief because it is not backed by the power of contempt.

Steffel v. Thompson, 415 U.S. 452, 471 (1974) (quoting

Perez v. Ledesma, 401 U.S. 82, 125–26 (1971) (Brennan, J.,

concurring in part)). But in suits against government

officials and departments, we generally assume that they will

comply with declaratory judgments. See Poe v. Gerstein,

417 U.S. 281, 281 (1974) (per curiam) (“[T]here was ‘no

allegation here and no proof that respondents would not, nor

26 UNITED AERONAUTICAL CORP. V. USAF

can we assume that they will not, acquiesce in the

[declaratory judgment] decision . . . .’” (citation omitted)).

E. We Lack Jurisdiction to Consider the

Government’s Signature-Based Argument

Finally, the dissent expressed concern that “the

Government—while vigorously arguing for CDA

preclusion—also argues that the DRA is invalid and

unenforceable on the grounds that it was not signed by a

‘contracting’ officer.” We share the dissent’s concern that

the government appears to have taken a heads-I-win, tails-

you-lose approach to arguing this appeal. We also note that

in the two pages the government dedicates to its signature-

based argument, it cites no CDA-specific precedent for its

novel argument that technical non-compliance with a

contracting regulation would vitiate a CDA cause of action

even if an agreement is otherwise an “express or implied

contract.” 41 U.S.C. § 7102(a). That said, we do not

ultimately resolve USAF’s signature-based argument

because we lack jurisdiction over it. USAF raised it as a

Rule 12(b)(6) failure-to-state-a-claim argument, not a Rule

12(b)(1) lack-of-subject-matter-jurisdiction argument.

Because we affirmed the district court’s dismissal for a lack

of subject-matter jurisdiction, we cannot proceed to reach

this merits argument. 6

6

Our determination we lack jurisdiction to decide whether the DRA is a

valid contract is fully compatible with our finding that the DRA qualifies

as the requisite procurement contract needed to give rise to CDA

jurisdiction. Contrary to the dissent’s argument, the threshold

jurisdictional question of whether a procurement contract is at issue in

the dispute for the purpose of establishing CDA jurisdiction has no

bearing on the merits-based question of whether that procurement

UNITED AERONAUTICAL CORP. V. USAF 27

CONCLUSION

For the foregoing reasons, the district court’s dismissal

for lack of subject-matter jurisdiction is AFFIRMED.

COLLINS, Circuit Judge, dissenting:

Plaintiffs filed this suit under § 702 of the Administrative

Procedure Act (“APA”), 5 U.S.C. § 702, seeking injunctive

and declaratory relief against Defendants United States Air

Force and United States Air National Guard based on

Defendants’ alleged misuse of Plaintiffs’ intellectual

property. The majority affirms the district court’s dismissal

of this action for lack of subject matter jurisdiction, holding

that the Contract Disputes Act (“CDA”) “impliedly forbids”

Plaintiffs from bringing an APA action in federal district

court. But the CDA does not impliedly forbid reliance on

the APA where, as here, Plaintiffs’ claims and relief are

based, not on a Government contract, but rather on

Plaintiffs’ independent statutory rights under the Trade

Secrets Act. The majority’s contrary decision misconstrues

the CDA, contravenes Ninth Circuit precedent, creates a split

with four other circuits, and undermines the ability of

contractors to obtain injunctive relief in federal court against

Government violation of their statutory rights. Accordingly,

I respectfully dissent.

I

The intellectual property at issue in this case relates to

the Mobile Airborne Firefighting System (“MAFFS”),

contract is valid and enforceable. The dissent’s criticism unfortunately

collapses the crucial distinction between jurisdiction and merits.

28 UNITED AERONAUTICAL CORP. V. USAF

which is fire-retardant tank system used to convert cargo

planes into fire-fighting aircraft. From about 1980 to 2000,

Aero Union, a separate company from Plaintiffs, developed

the original MAFFS through its own privately funded

research and development. In 2000, Aero Union contracted

with the U.S. Forest Service (“USFS”) to develop an updated

MAFFS prototype, called “MAFFS II.” MAFFS II relied

significantly on Aero Union’s independently developed

intellectual property, which Plaintiffs refer to as the “Pre-

MAFFS II Proprietary Data.” Under the terms of the 2000

contract, Aero Union retained ownership of the Pre-MAFFS

II Proprietary Data, subject to the USFS’s limited use rights.

The contract terminated in 2012.

Following the termination of the 2000 contract, Plaintiffs

purchased Aero Union’s intellectual property, including the

Pre-MAFFS II Proprietary Data, in a foreclosure sale. To

support the USFS’s ongoing use of MAFFS II, Plaintiffs

executed a Data Rights Agreement (“DRA”) in 2014, which

provided that the USFS “shall have unlimited rights to view

and use the data required for the continued operation and

maintenance of the [MAFFS II] product.” The DRA also

reaffirmed, however, that the “Pre-MAFFS II Proprietary

Data, and the technical data produced or specifically used or

related to the [MAFFS II system] developed pursuant to [the

2000] contract shall remain the property of [Plaintiffs] (as

the purchaser of assets of Aero [Union] . . . ).” Pursuant to

the DRA, Plaintiffs provided the USFS with a hard drive

containing Pre-MAFFS II Proprietary Data. The USFS

subsequently delivered that hard drive to Defendants, which

developed a competing system to market internationally

without Plaintiffs’ consent.

Plaintiffs then sued Defendants (but not the USFS) under

the APA, challenging Defendants’ unlawful use of the

UNITED AERONAUTICAL CORP. V. USAF 29

MAFFS data. The district court dismissed Plaintiffs’ claims

for lack of subject matter jurisdiction, holding that any such

claims had to be brought before the Court of Federal Claims

(“CFC”). Plaintiffs timely appealed.

II

As a general matter, no suit may be brought against the

United States unless it has waived its sovereign immunity.

See Esquivel v. United States, 21 F.4th 565, 572 (9th Cir.

2021). The APA provides a limited waiver of sovereign

immunity that allows plaintiffs who have “suffer[ed] legal

wrong because of agency action” to file suit against the

United States in federal district court. 5 U.S.C. § 702. 1 To

maintain such a suit, plaintiffs generally must satisfy three

conditions: (1) they must “seek[] relief other than money

damages,” id.; (2) they must have “no other adequate

remedy,” id. § 704; and (3) the relief sought must not be

“expressly or impliedly forbid[den]” by “any other statute

that grants consent to suit,” id. § 702. See Tucson Airport

Auth. v. Gen. Dynamics Corp., 136 F.3d 641, 645–46 (9th

Cir. 1998). The majority holds that the third requirement is

not met here, because, in its view, exclusive jurisdiction over

Plaintiffs’ assertedly contract-related claim rests in the CFC.

I disagree. There are two grants of jurisdiction to the CFC

that are potentially relevant here, but neither impliedly

forbids this suit.

1

As we have recognized, the APA supplies the cause of action and the

waiver of sovereign immunity, but the APA is not itself “an independent

basis for subject matter jurisdiction in the district courts.” See Tucson

Airport Auth. v. Gen. Dynamics Corp., 136 F.3d 641, 645 (9th Cir. 1998)

(citing California v. Sanders, 430 U.S. 99, 105 (1977)). Rather,

jurisdiction in APA cases rests on 28 U.S.C. § 1331. See Allen v. Milas,

896 F.3d 1094, 1099 (9th Cir. 2018).

30 UNITED AERONAUTICAL CORP. V. USAF

A

First, the Tucker Act grants the CFC jurisdiction over,

inter alia, “any claim against the United States founded . . .

upon any express or implied contract with the United

States.” 28 U.S.C. § 1491(a)(1). Applying long-settled law,

I conclude that the Tucker Act does not impliedly forbid this

suit.

Because the Tucker Act authorizes the CFC to grant

“equitable relief” only “in limited circumstances,” the

general rule is that “the Tucker Act does not permit the

[CFC] to grant equitable or declaratory relief in a contract

dispute case.” North Star Alaska v. United States, 9 F.3d

1430, 1432 (9th Cir. 1993) (en banc) (North Star I). 2 We

have held that, because “the Tucker Act ‘impliedly forbids’

declaratory and injunctive relief” in suits founded on

Government contracts, it “precludes” invocation of the

waiver of sovereign immunity in § 702 of the APA, which

applies only to equitable relief. North Side Lumber, 753

F.2d at 1485; see also North Star I, 9 F.3d at 1432.

However, because the Tucker Act’s relevant grant of

jurisdiction is limited to claims “founded . . . upon any

express or implied contract,” it does not bar invocation of the

2

Subject to certain exceptions, the federal district courts also exercise

concurrent jurisdiction with the CFC over such contract-based actions

against the United States, but only if the amount claimed does not exceed

$10,000. See 28 U.S.C. § 1346(a)(2) (sometimes called the “Little

Tucker Act”). The district courts’ limited concurrent jurisdiction over

contract-based claims under $10,000 has been similarly construed as

generally precluding nonmonetary relief on such claims. See North

Star I, 9 F.3d at 1432; North Side Lumber Co. v. Block¸ 753 F.2d 1482,

1485 (9th Cir. 1985).

UNITED AERONAUTICAL CORP. V. USAF 31

APA’s waiver of sovereign immunity if the claim is not

“founded upon” a contract.

In determining whether a claim is “founded upon” a

contract within the meaning of the Tucker Act—and thus

impliedly forbidden to be asserted under the APA—we have

long applied the test set forth by the D.C. Circuit in

Megapulse, Inc. v. Lewis, 672 F.2d 959 (D.C. Cir. 1982). As

we have explained, that test requires us to determine whether

the suit is “‘at its essence’ a contract action” by considering

both “the source of the rights upon which the plaintiff bases

its claims” and “the type of relief sought (or appropriate).”

North Star Alaska v. United States, 14 F.3d 36, 37 (9th Cir.

1994) (North Star II) (quoting Megapulse, 672 F.2d at 968).

Here, consideration of these factors confirms that Plaintiffs’

claim is not “founded upon” a contract with the Government.

In considering how the Megapulse test applies here, I

begin by reviewing the D.C. Circuit’s decision in that case,

which involved somewhat similar facts. In Megapulse, the

plaintiff contractor filed suit in the district court to enjoin the

Government from disclosing data that the plaintiff had

independently developed prior to executing its first contract

with the Government and prior to its delivery of the data to

the Government under that contract. Megapulse, 672 F.2d

at 961–62. The plaintiff alleged that disclosure of the data

by the Government to other entities would violate the Trade

Secrets Act, see 18 U.S.C. § 1905, but the Government

argued that its contemplated disclosures were authorized by

its contract with the plaintiff. Megapulse, 672 F.2d at 962,

966. The D.C. Circuit held that the plaintiff’s claims for

relief were not impliedly forbidden by the Tucker Act and

that suit was therefore properly brought under the APA in

federal district court. In reaching this conclusion, the D.C.

Circuit considered both the source of the plaintiff’s rights

32 UNITED AERONAUTICAL CORP. V. USAF

and the relief sought, and it ultimately held that the

plaintiffs’ suit did not involve “‘disguised’ contract claims.”

Id. at 969.

In determining the source of the plaintiff’s rights,

Megapulse emphasized that the plaintiff there had carefully

limited its claim to a discrete set of documents reflecting

“proprietary technology developed prior” to its contracts

with the Government and that the plaintiff relied solely on

the theory that the Government was violating its property

rights and the Trade Secrets Act. Megapulse, 672 F.2d at

969 (simplified). As the court explained, it was “actually the

Government, and not Megapulse, which is relying on the

contract” by claiming in defense that its actions were

authorized under the contract. Id. The court specifically

rejected the Government’s argument that “the mere

existence of such contract-related issues must convert this

action to one based on the contract.” Id. As to the relief

sought, the court noted that Megapulse did not seek

“monetary damages,” nor could its claim be “properly

characterized as one for specific performance” of any

contract. Id. On the latter score, the court expressly rejected

the Government’s argument that the existence of parallel

contractual duties that matched the Government’s statutory

obligations should be sufficient to convert Megapulse’s

claim into one for specific performance of a contract. Id. at

971.

Under Megapulse, this is an easy case. Here, as in

Megapulse, Plaintiffs have carefully limited the factual

predicate of their claims to proprietary data that preceded

Aero Union’s first contract with the Government in 2000.

Here, as in Megapulse, Plaintiffs are relying upon their rights

under trade secret law, including the Trade Secrets Act, and

it is the Government that is raising contractual issues as a

UNITED AERONAUTICAL CORP. V. USAF 33

defense. Thus, as a factual and legal matter, “the source of

the rights upon which the plaintiff bases its claims” are

independent of any contract with the Government. North

Star II, 14 F.3d at 37. Moreover, as in Megapulse, Plaintiffs

are not seeking money damages, nor are they seeking any

contract-based remedies. Cf. id. at 37–38 (holding that

plaintiff seeking reformation was asserting a contract-based

claim under the Megapulse test). Instead, they seek an

“injunction[] against activities violative of a statutory duty.”

Megapulse, 672 F.2d at 971; see also Crowley Govt. Servs.

v. Gen. Servs. Admin., 38 F.4th 1099, 1108–10 (D.C. Cir.

2022) (holding that district court had jurisdiction under

Megapulse where the plaintiff “‘does not claim a breach of

contract, it has limited its request for relief’ in district court

to the enforcement of the [agency’s] statutory obligations, ‘it

seeks no monetary damages against the United States, and

its claim is not properly characterized as one for specific

performance.’” (quoting Megapulse, 672 F.2d at 969)).

Because, under the Megapulse test, Plaintiffs’ claims are

not “founded . . . upon any express or implied contract,” 28

U.S.C. § 1491(a)(1), the Tucker Act does not impliedly

forbid invocation of the APA.

B

The second potentially relevant grant of jurisdiction to

the CFC is the CDA. In my view, the CDA does not

impliedly forbid Plaintiff’s claims here.

1

The CDA, enacted in 1978, has since been codified as

Chapter 71 of title 41 of the United States Code. See 41

U.S.C. §§ 7101–7109. By its terms, the CDA applies only

to “any express or implied contract . . . made by an executive

34 UNITED AERONAUTICAL CORP. V. USAF

agency for” (1) the “procurement of property, other than real

property in being”; (2) the “procurement of services”; (3) the

“procurement of construction, alteration, repair, or

maintenance of real property”; or (4) the “disposal of

personal property.” Id. § 7102(a)(1)–(4). The CDA

establishes an administrative process under which any

“claim by a contractor against the Federal Government

relating to a contract shall be submitted to the contracting

officer for a decision.” Id. § 7103(a)(1). The contracting

officer must then issue a written decision, see id.

§ 7103(a)(3), (d), and if it is adverse to the contractor, then

the contractor can either appeal to the appropriate agency

board of contract appeals, see id. § 7104(a), or “bring an

action directly on the claim” in the CFC, id. § 7104(b)(1).

An adverse decision in either forum may be reviewed by the

Federal Circuit. See id. § 7107(a)(1); 28 U.S.C.

§ 1295(a)(3).

The corresponding provision of the judicial code that

confers jurisdiction on the CFC to adjudicate an action filed

by a contractor under § 7104(b)(1) states:

The Court of Federal Claims shall have

jurisdiction to render judgment upon any

claim by or against, or dispute with, a

contractor arising under section 7104(b)(1) of

title 41, including a dispute concerning

termination of a contract, rights in tangible or

intangible property, compliance with cost

accounting standards, and other nonmonetary

disputes on which a decision of the

UNITED AERONAUTICAL CORP. V. USAF 35

contracting officer has been issued under

section 6 of that Act [41 U.S.C. § 7103].

28 U.S.C. § 1491(a)(2). The majority describes this

provision as conferring “exclusive” jurisdiction in the CFC,

see Opin. at 17, but that is not exactly correct. As noted

earlier, there are two possible routes for review of a

contracting officer’s determination of a claim under the

CDA, and the other option (review by an agency board of

contract appeals, followed by review in the Federal Circuit)

bypasses the CFC altogether. To the extent that the CDA

impliedly forbids invocation of the APA here, that is

attributable, not so much to any “exclusive” jurisdiction of

the CFC, but rather to the CDA’s “mandatory administrative

process for resolving contract disputes.” Menominee Indian

Tribe v. United States, 577 U.S. 250, 252 (2016). If the CDA

applies here, then Plaintiffs were required to present their

claim to the relevant contracting officer before invoking one

of the CDA’s two paths to judicial review. That would, in

my view, impliedly forbid them from invoking the APA as

an end-run around the CDA’s administrative process and the

specific methods of judicial review applicable to that

process.

The question, then, is whether Plaintiffs were required to

submit their claim in this case to a contracting officer in

accordance with the CDA. As noted earlier, the CDA

requires that any “claim by a contractor against the Federal

Government relating to a contract” governed by the CDA

“shall be submitted to the contracting officer for a decision.”

41 U.S.C. § 7103(a)(1) (emphasis added). And, generally

speaking, the only contracts that are governed by the CDA

are “procurement” contracts. Id. § 7102(a)(1)–(3). On that

basis, I agree that, if Plaintiffs’ “claim” here is one “relating”

36 UNITED AERONAUTICAL CORP. V. USAF

to a procurement contract, then they were required to invoke

the CDA’s processes, and any resort to the APA as a

substitute is impliedly forbidden. 5 U.S.C. § 702.

2

Whether this case may proceed in the district court thus

turns on whether Plaintiffs’ claim is one “relating to” a

procurement contract within the meaning of § 7103(a)(1) of

the CDA. The majority concludes that the Megapulse test

that is used for distinguishing between claims “founded

upon” a contract in the Tucker Act context does not apply to

the similar inquiry, in the CDA context, as to whether a

claim “relat[es] to a contract.” See Opin., § II. According

to the majority, any cause of action that, broadly speaking,

has “some relationship to the terms or performance” of a

procurement contract is a claim “relating to a contract” for

purposes of the CDA and therefore may not be the subject of

a suit under § 702 of the APA. See Opin. at 9 (quoting Todd

Constr., L.P. v. United States, 656 F.3d 1306, 1312 (Fed. Cir.

2011)). And that remains true, according to the majority,

even if the only “relationship” between the plaintiff’s claims

and the procurement contract is that the Government has

invoked contract-based defenses to the plaintiff’s non-

contract-based claims. See Opin. at 11–12, 16–20. For

multiple reasons, the majority is wrong in holding that the

Megapulse test is limited to the Tucker Act context and does

not apply to the CDA.

First, the majority overlooks the meaning, in context, of

the entire relevant phrase in the CDA, and in doing so the

majority misreads the Todd case on which it primarily relies.

In describing what must be submitted to a contracting

officer, § 7103(a)(1) refers to a “claim by a contractor

against the Federal Government relating to a contract.” 41

UNITED AERONAUTICAL CORP. V. USAF 37

U.S.C. § 7103(a)(1) (emphasis added). As the Federal

Circuit noted in Todd, the CDA does not define the crucial

word “claim.” 656 F.3d at 1311. Todd held, however, that

under the Federal Circuit’s prior decision in H.L. Smith, Inc.

v. Dalton, 49 F.3d 1563 (Fed. Cir. 1995), “the definition of

the term ‘claim’ in the FAR [Federal Acquisition

Regulations] governs.” 656 F.3d at 1311. As Todd

explained, “[t]he FAR defines ‘claim’ as ‘a written demand

or written assertion by one of the contracting parties seeking,

as a matter of right, the payment of money in a sum certain,

the adjustment or interpretation of contract terms, or other

relief arising under or relating to the contract.’” Id.

(emphasis omitted) (quoting 48 C.F.R. § 2.101). The types

of “claims” governed by the CDA are thus limited to those

seeking “relief arising under or relating to the contract.” Id.

(emphasis added). This focus on contract-based rights and

contract-related relief is not materially different from the

Megapulse test, which requires consideration of the same

factors. See Megapulse, 672 F.2d at 968. Moreover, the

“claim” at issue in Todd—which challenged the “quality of

the contractor’s performance under the terms of the

contract,” Todd, 656 F.3d at 1313 (emphasis added)—

readily qualifies as “at its essence a contract claim” under

Megapulse, 672 F.2d at 967.

Second, even setting aside Todd’s particular definition of

a “claim,” the majority’s analysis still fails. According to

the majority, a contractor’s “claim” “relat[es] to” a contract

if the Government’s defenses to that claim relate to the

contract. See Opin. at 11–12. The majority cites no

authority that supports this rewriting of the statute, which

focuses on the “claim” asserted and not the defenses raised

against it. The majority notes that Plaintiffs cannot prevail

on their claim without defeating those defenses and that

38 UNITED AERONAUTICAL CORP. V. USAF

Plaintiffs’ complaint itself anticipates those defenses. See

Opin. at 11–12. But that does not erase the distinction

between a claim and a defense, cf. Caterpillar Inc. v.

Williams, 482 U.S. 386, 393 (1987) (holding that the rule

that a federal defense does not suffice to show that a claim

arises under federal law applies “even if the defense is

anticipated in the plaintiff’s complaint, and even if both

parties concede that the federal defense is the only question

truly at issue”), and the CDA requires that the claim—not an

anticipated defense—relate to the contract. 41 U.S.C. §

7103(a)(1). The Megapulse test honors that distinction

between claims and defenses, because Megapulse

specifically held that the Government’s decision to raise a

contract-based defense does not make a plaintiff’s claim a

contract claim. 672 F.2d at 969. 3

Third, the majority’s expansive reading of the CDA

ignores our prior caselaw holding that the CDA’s preclusive

effect on the availability of other jurisdictional statutes

should be “narrowly” construed. Concrete Tie, Inc. v.

Liberty Constr., Inc. (In re Liberty Constr.), 9 F.3d 800, 801

(9th Cir. 1993). In Liberty Construction, we invoked that

narrow-construction rule in rejecting the Government’s

argument that our construction of the statute “vest[ing]

jurisdiction in the district court over claims against the SBA

3

The majority insists that this distinction between claims and defenses

is an artifact of the jurisprudence governing 28 U.S.C. § 1331 and does

not apply outside that context. See Opin. at 19–20. But the provision of

the CDA that the majority says impliedly forbids invocation of the APA

applies, by its terms, only if the “claim” is one “arising under section

7104(b)(1) of title 41,” 28 U.S.C. § 1491(a)(2), and § 7104(b)(1) in turn

authorizes an “action directly on the claim” raised by the contractor. The

statute’s focus here is on the claim asserted by the contractor and not the

defenses asserted by the Government.

UNITED AERONAUTICAL CORP. V. USAF 39

[Small Business Administration]” had been “implicitly

overruled” by the CDA. Id.; see also Wright v. U.S. Postal

Serv., 29 F.3d 1426, 1429 (9th Cir. 1994) (expressly

rejecting the view that “the CDA ‘pre-empt[s] the entire field

of government contract remedies’”). 4

Fourth, the majority creates a circuit split with at least

four circuits that expressly apply Megapulse in assessing

whether the CDA impliedly forbids reliance on the APA.

See B & B Trucking, Inc. v. U.S. Postal Serv., 406 F.3d 766,

768 (6th Cir. 2005) (en banc) (“The CDA bars district court

jurisdiction if the court determines that a plaintiff’s claims

against a government agency are ‘essentially contractual’ in

nature. ‘The classification of a particular action as one

which is or is not [essentially contractual] depends both on

the source of the rights upon which the plaintiff bases its

claim, and upon the type of relief sought (or appropriate).’”

(quoting Megapulse, 672 F.2d at 968) (other internal

citations omitted)); A&S Council Oil Co. v. Lader, 56 F.3d

234, 239–40 (D.C. Cir. 1995) (applying Megapulse test in

determining whether a claim is one “relating to a contract”

within the meaning of the CDA); Up State Fed. Credit Union

v. Walker, 198 F.3d 372, 374–76 (2d Cir. 1999) (applying

Megapulse in determining whether claims were contract

4

Indeed, we have gone so far as to hold that the CDA does not bar

invoking other bases of jurisdiction even in the context of claims that

would qualify as contract-based under the Megapulse test. See, e.g.,

Wright, 29 F.3d at 1429; Liberty Construction, 9 F.3d at 801–02; North

Side Lumber, 753 F.2d at 1485–86. That further rule has provoked a

split with the Second Circuit. See Cohen v. Postal Holdings, LLC, 873

F.3d 394, 401–02 (2d Cir. 2017) (holding that the claim at issue was a

contract claim under Megapulse and that the CDA was the exclusive

vehicle for relief, expressly rejecting contrary Ninth Circuit authority).

Because this case does not involve a contract claim within the meaning

of Megapulse, this case does not implicate that distinct split of authority.

40 UNITED AERONAUTICAL CORP. V. USAF

claims subject to the CDA); United States v. J & E Salvage

Co., 55 F.3d 985, 987–88 (4th Cir. 1995) (same). Although

the majority tries to distinguish these cases on their specific

facts, see Opin. at 23–24, it cannot deny that these other

circuit decisions explicitly apply to the CDA the Megapulse

test that the majority rejects.

Fifth, the majority’s holding could seriously impede the

ability of plaintiffs to obtain injunctive relief against

Government misconduct, even for statutory violations such

as those at issue here, if the plaintiffs’ claims can be said, in

some broad sense, to “relate” to a contract the plaintiff

assertedly has with the Government. The majority dismisses

this concern, even while acknowledging that the Federal

Circuit itself expressly declined to decide in Todd whether

the CFC had authority to issue injunctive relief in that case.

See Opin. at 25 (citing 656 F.3d at 1311 n.3). The majority

hopes that declaratory relief—which the majority concedes

could not be enforced by contempt authority—would be

sufficient. Id. But if not, well, then too bad, according to

the majority, because “the government is free to waive its

immunity only for certain forms of relief.” Id. The

majority’s overbroad rule threatens to seriously thwart the

critical role served by APA § 702’s waiver of sovereign

immunity in cases seeking injunctive relief against the

Government. See Transohio Sav. Bank v. Director, Off. of

Thrift Supervision, 967 F.2d 598, 611–12 (D.C. Cir. 1992)

(“[W]e are mindful of the warning that federal courts not

subvert the congressional objectives underlying the

enactment of § 702 of the APA by allowing the government

to give an overly expansive scope to the notion of claims

‘founded upon’ a contract” (simplified)).

For all of these reasons, the majority seriously errs in

rejecting the Megapulse test in assessing whether the CDA

UNITED AERONAUTICAL CORP. V. USAF 41

impliedly forbids a claim for injunctive relief under § 702 of

the APA. Because I would apply Megapulse in assessing the

limits of the CDA, I necessarily conclude that Plaintiffs’

claims are not impliedly forbidden by the CDA.

III

Finally, I cannot let pass without comment an additional

troubling feature of this case that the majority brushes aside.

In finding that the CDA impliedly forbids invocation of the

APA here, the majority holds that the DRA qualifies as a

procurement contract within the meaning of the CDA. See

Opin. § II(b). But the majority nonetheless declines to

address the fact that the Government—while vigorously

arguing for CDA preclusion—also argues that the DRA is

invalid and unenforceable on the grounds that it was not

signed by a “contracting” officer. The extraordinary result

of the majority’s decision is that Plaintiffs’ loss of their

ability to file a district court action seeking injunctive relief

to enforce their statutory rights against the Government is

attributable to the Government’s assertion of a contract-

based defense under a contract that the Government

simultaneously contends is invalid. This cannot be right.

See Crewzers Fire Crew Trans., Inc. v. United States, 741

F.3d 1380, 1382 & n.3 (Fed. Cir. 2014) (holding that the

plaintiff’s contract with the Government was unenforceable

and therefore could not “be used to invoke” the jurisdiction

of the CFC under the Tucker Act or the CDA); Ridge Runner

Forestry v. Veneman, 287 F.3d 1058, 1060–61 (Fed. Cir.

2002) (holding that, because the “Tender Agreement” upon

which CDA jurisdiction was predicated was not a valid

42 UNITED AERONAUTICAL CORP. V. USAF

contract, the CFC properly concluded that it lacked

jurisdiction under the CDA). 5

IV

For the reasons I have explained, neither the Tucker Act

nor the CDA impliedly forbid invocation of the APA here.

Accordingly, the district court erred in dismissing this action

for lack of jurisdiction, and its judgment should be reversed.

I respectfully dissent.

5

The majority protests that, in addressing whether there is jurisdiction

under the CDA, we lack jurisdiction to decide whether the DRA is a valid

contract. See Opin. at 26. That contention is contrary to the Federal

Circuit’s decisions in Crewzers and Ridge Runner, and it also contradicts

the majority’s assertion that the DRA qualifies as the requisite

procurement contract needed to give rise to CDA jurisdiction. It is

apparently the majority’s view that the Government may invoke the

CDA—and deprive a plaintiff of its ability to assert an APA injunctive

claim—merely by showing that the plaintiff is asserting a claim as to

which the Government has a defense that is related to a putative

agreement that the Government contends is not actually a valid contract.

Once again, that cannot be right.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.