"The Congressional intent of the avoided cost pricing scheme is to make the utilities' ratepayers economically indifferent between utility power plant additions and utility purchases of [qualifying facility] power."
How later courts described this case
- "The Congressional intent of the avoided cost pricing scheme is to make the utilities' ratepayers economically indifferent between utility power plant additions and utility purchases of [qualifying facility] power."
Written by the judges who cited it.
The opinion
ORDER
PER CURIAM.
Prior Report: 135 Pa.Commonwealth Ct. 15, 579 A.2d 1337 .
Order affirmed.
NIX, C.J., and CAPPY and MONTEMURO, JJ., affirm.
*110 FLAHERTY, ZAPPALA and PAPADAKOS, JJ., affirm in part and would reverse in part.
PAPADAKOS, J., files a concurring and dissenting opinion in which FLAHERTY and ZAPPALA, JJ., join.