“The party invoking federal jurisdiction bears the burden of establishing [the] elements [of standing].”
How later courts described this case
- “The party invoking federal jurisdiction bears the burden of establishing [the] elements [of standing].”
- noting that “the basic doctrine of equity jurisprudence [is] that courts of equity should not act . . . when the moving party has an adequate remedy at law and will not suffer irreparable injury if denied equitable relief”
- “The Court of Federal Claims has repeatedly held that a protester suffers irreparable harm if it is deprived of the opportunity to compete fairly for a contract.”
- “Without a price realism analysis in the record, the Court has nothing to review and no way of determining whether [the protestor] was prejudiced. This conclusion alone is sufficient to warrant remand to conduct a proper price realism analysis.”
Written by the judges who cited it.
The opinion
In the United States Court of Federal Claims
No. 22-1521 C
Filed Under Seal: March 31, 2023
Reissued: April 19, 2023 *
* * * * * * * * * * * * * * * * * * **
*
DIGIFLIGHT, INC., *
*
Plaintiff, *
*
v. *
*
THE UNITED STATES, *
*
Defendant, *
*
and *
*
THE TOLLIVER GROUP, INC., *
*
Defendant-Intervenor. *
*
* * * * * * * * * * * * * * * * * ***
Roderic G. Steakley, Dentons Sirote, PC, with whom were Benjamin R. Little, Dentons
Sirote, PC, of Huntsville, AL, and Jerome S. Gabig, Gabig Law Firm, of Guntersville, AL, for
Plaintiff.
Christopher L. Harlow, Trial Attorney, Commercial Litigation Branch, Civil Division,
Department of Justice, with whom were Douglas K. Mickle, Assistant Director, Patricia M.
McCarthy, Director, and Brian M. Boynton, Principal Deputy Assistant Attorney General, all of
Washington, D.C., for Defendant, and Major Brittney N. Montgomery, Trial Attorney, Legal
Service Agency, United States Army, of Fort Belvoir, VA, of counsel.
W. Brad English, Maynard, Cooper & Gale, PC, with whom were Jon D. Levin, Emily J.
Chancey, and Nicholas P. Greer, Maynard, Cooper & Gale, PC, all of Huntsville, AL, for
Defendant-Intervenor.
*
Pursuant to the protective order entered in this case, this opinion was filed initially under seal.
The parties provided proposed redactions of confidential or proprietary information, which are redacted in
this version of the opinion. In addition, the Court made minor typographical and stylistic corrections.
OPINION AND ORDER
SOMERS, Judge.
On October 14, 2022, Plaintiff, DigiFlight, Inc., filed a complaint in this Court protesting
the award of a task order to Defendant-Intervenor, The Tolliver Group, Inc., pursuant to Task
Order Request for Quotations 2020P-03 (“RFQ”), for programmatic support for the United
States Army Aviation and Missile Command (“AMCOM”). For the reasons that follow, the
Court has determined that the Army, in evaluating quotations, committed prejudicial errors in
conducting the price realism analysis it obligated itself to perform by the terms of the RFQ and
in evaluating quotations under the technical expertise factor. Accordingly, for those counts of
Plaintiff’s complaint for which it has standing, Plaintiff is entitled to judgment on the
administrative record, and Plaintiff’s request for a permanent injunction is granted.
BACKGROUND
A. The Solicitation
On December 1, 2021, the Army issued the RFQ seeking programmatic support services
for AMCOM, including: “resource management; cost estimating/analysis and budget
preparation; program management, plans, and integration; schedule development and
assessment; systems analysis; strategic planning; risk analysis; and risk mitigation to the various
offices and staffs within AMCOM.” AR 112. The RFQ was conducted as a total small business
set-aside, and exclusive to vendors who already had EXPRESS Blanket Purchase Agreements
(“BPAs”) with the General Services Administration (“GSA”). AR 113. Furthermore, the
solicitation explicitly stated that it was a FAR subpart 8.4 procurement and “not a FAR Part 15
negotiated competition.” AR 115.
According to the RFQ, the award would be made to the offeror “whose quotation
provide[d] the best value to the Government . . . .” AR 123. It stated three evaluation criteria:
Technical Expertise, Risk Mitigation and Management, and Price. AR 123–26. In addition, it
detailed how the three factors would be weighed in relation to each other:
The first two criteria, Technical Expertise, and Risk Mitigation and Management,
are of equal importance, and each of them is of greater importance than Price. Price
is not expected to be the controlling criterion in the selection, but its importance
will increase as the differences between the evaluation results for the other criteria
decrease.
AR 123.
In addition, the RFQ described how each criterion would be evaluated, respectively. As
to both Technical Expertise and Risk Mitigation and Management, the RFQ stated that ratings
would be “based on how well the quotation demonstrates a clear understanding of the
requirements and deliverables, and on the Offeror’s expressed ability to successfully perform.”
2
AR 124. The RFQ specified four possible ratings, and included charts describing the standard
associated with each rating level as summarized below:
Technical Expertise/Risk Mitigation and Management Ratings
Rating Description
Outstanding Quotation meets requirements and indicates an exceptional level of
expertise and an understanding of the requirements. Strengths far
outweigh any weaknesses. Risk of unsuccessful performance is very low.
Good Quotation meets requirements and indicates a thorough level of expertise
and an understanding of the requirements. Strengths outweigh any
weaknesses. Risk of unsuccessful performance is low.
Acceptable Quotation meets requirements and indicates an adequate level of expertise
and an understanding of the requirements. Strengths and Weaknesses are
offsetting or will have little or no impact on contract performance. Risk of
unsuccessful performance is moderate.
Unacceptable Quotation does not meet requirements and contains one or more
deficiencies. If this criterion is rated as Unacceptable, additional factors
will not be evaluated and the quotation is not eligible for award.
See AR 124–26.
Specifically with regard to the Technical Expertise, the RFQ stated that a quotation “will
be evaluated based on the degree to which it thoroughly demonstrates the Offeror understands
the services to be delivered in order to meet the requirements of the [Performance Work
Statement (“PWS”)] and the Offeror’s ability to perform those services.” AR 124. Moreover,
“[w]hile award of this task order will require the Offeror to perform all of the PWS requirements,
the Government considers the requirements in the following PWS paragraphs 3.1.3, 3.1.10,
3.1.11, 3.1.14, 3.1.15, 3.1.16, 3.1.17, 3.2.2, and 3.2.3 to be critical to evaluation of the Offeror’s
technical expertise.” Id. (emphasis omitted). Accordingly, the RFQ insisted that these
requirements “be specifically addressed in the quotation.” Id.
Finally, as to Price, the RFQ provided that “[t]he Government will use price analysis to
determine the overall price reasonableness,” AR 126, and that
[t]he government will assess the price quotation to ensure the proposed pricing is
realistic for the work to be performed, reflects a clear understanding of the
requirements, and is consistent with the various elements of the other parts of the
quotation. Unrealistic pricing will not be adjusted by the Government in its
evaluations, but it reserves the right to reject a quotation upon a determination that
a price is unrealistically low. All direct labor hours, skill mix, and labor categories
3
in the Price Quotation must be consistent with the technical expertise and Risk
Mitigation & Management portion of the quotation.
AR 127.
B. Award Decision
On January 31, 2022, three BPA holders submitted quotations in response to the RFQ:
Plaintiff, Tolliver, and . AR 476. On September
29, 2022, the Army informed the offerors that it had awarded the task order to Tolliver. AR 562.
In its evaluation, the Army purported to assess each quotation for Technical Expertise, Risk
Mitigation and Management, and Price, and summarized the results using the following charts:
DigiFlight EVALUATION RESULTS:
FACTORS DigiFlight
Technical Expertise Acceptable
Risk Mitigation and Management Good
Price
AR 562;
[Tolliver] EVALUATION RESULTS:
FACTORS TTGI
Technical Expertise Acceptable
Risk Mitigation and Management Acceptable
Price $43,794,113.06
AR 567;
EVALUATION RESULTS:
FACTORS
Technical Expertise Acceptable
Risk Mitigation and Management Acceptable
Price
AR 573.
With regard to Technical Expertise, none of the three offerors received a single strength,
weakness, or deficiency. See AR 562, 567, 573. As to Risk Mitigation and Management,
Plaintiff received a single strength for “[b]ringing together the right team to perform the PWS
requirements,” and no weaknesses or deficiencies. AR 563. Both Tolliver and received no
strengths, weaknesses, or deficiencies for this factor. AR 569, 574.
4
As to Price, the evaluators “reviewed the pricing received in response to th[e] solicitation
to determine price reasonableness.” AR 488. To do so, the evaluators compared the
Independent Government Cost Estimate (“IGCE”) rates to the prices proposed by the offerors.
AR 486. The IGCE rates are “based on historical labor rates,” and “represent the maximum
rates, which incorporate national prices and industry wide concern.” AR 488. The rates
submitted by the offerors were discounted, which was allowable under the terms of the RFQ.
Id. 1 The evaluators summarized their findings as follows:
[i]n conducting the price evaluation, the government assessed the price quotation
to ensure the proposed pricing is realistic for the work to be performed, reflects a
clear understanding of the requirements, and is consistent with the various elements
of the other parts of the quotation. The Contracting Officer reviewed the Offerors’
labor categories, skill mix, and hours and found that all three Offerors proposed the
appropriate education/experience levels in accordance with EXPRESS Labor
Categories: Minimum Requirements Listing. DigiFlight, and [Tolliver] all
proposed labor hours that are consistent with the TORFQ. The Offerors’ Task
Order/Rate Table rates were evaluated to ensure that they were equal to or less than
the established [GSA] rates. Since the TORFQ allowed Offerors to propose
discounts, all Offerors provided discounts from their negotiated GSA schedule.
The Government took no exceptions or issues to the Offerors’ proposed pricing and
found all three to be realistic for the work to be performed. Additionally, all three
Offerors reflect a clear understanding of the requirements.
AR 489.
In addition, the evaluators had the following to say regarding their price realism analysis:
[i]n further evaluating for price realism, the Government compared the two lowest
composite rates offered by and [Tolliver]. While both companies offered
composite rates well below the IGCE composite rates, the Government found that
multiple companies offering low composite rates suggested there was no evidence
of an attempt to offer unrealistically low prices as a strategy to receive the award.
Since DigiFlight offered a composite rate far higher than the two lowest Offerors,
it was determined that DigiFlight did not offer an unrealistically low price for the
purpose of receiving award either. Further, the Government used the GSA Contract
Awarded Labor Categories (CALC) tool to substantiate a random sample of labor
category prices offered by all three Offerors. All offered labor category prices were
well within the acceptable range. Based upon this analysis, the Government
determined that all Offerors’ prices are realistic.
Id.
The evaluators also assessed the labor mix for all three bidders, using exactly the same
language to summarize each respective evaluation:
1
Despite the RFQ clearly requiring a price realism analysis, the evaluators still stated that “the
TORFQ does not limit the amount of discount an offeror may propose.” AR 488.
5
A review of the basis of estimate was done and the level of effort and mix of labor
proposed to perform the tasks outlined in the PWS reflects understanding of the
requirements, is consistent with the various elements of the other parts of the
quotation and is considered realistic to support the proposed approach at an
acceptable level of risk to the Government. Overall, [ DigiFlight/Tolliver]’s
[Basis of Estimate] appears appropriate and reasonable to perform the tasks
outlined in the PWS.
AR 489–90.
The Army then conducted a trade-off analysis by balancing the Technical Expertise
ratings, the Risk Mitigation and Management factor ratings, and Price. Because the Technical
Expertise ratings were all the same and Plaintiff—despite its one strength in the Risk Mitigation
and Management factor—was more costly than Tolliver, “the Contracting Officer determined
that [Tolliver] provide[d] the best-value to the Government.” See AR 495–96.
DISCUSSION
A. Jurisdiction and Standing
The Tucker Act, as amended by the Administrative Dispute Resolution Act, provides the
Court with “jurisdiction to render judgment on an action by an interested party objecting to a
solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed
award or the award of a contract or any alleged violation of statute or regulation in connection
with a procurement or a proposed procurement.” 28 U.S.C. § 1491(b)(1). In order to come
within this jurisdictional grant, a protestor must demonstrate that it has standing. Castle v.
United States, 301 F.3d 1328, 1337 (Fed. Cir. 2002) (“Standing is a threshold jurisdictional
issue, which . . . may be decided without addressing the merits of a determination.”); see also
Lujan v. Defs. of Wildlife, 504 U.S. 555, 561 (1992) (“The party invoking federal jurisdiction
bears the burden of establishing [the] elements [of standing].”). To establish standing in a bid
protest case, the protestor must show that it is an “interested party” under 28 U.S.C.
§ 1491(b)(1), “which . . . imposes more stringent standing requirements than Article III.” Weeks
Marine, Inc. v. United States, 575 F.3d 1352, 1359 (Fed. Cir. 2009). Under § 1491(b)(1), a party
must show that it “(1) is an actual or prospective bidder and (2) possesses the requisite direct
economic interest.” Rex Serv. Corp. v. United States, 448 F.3d 1305, 1307 (Fed. Cir. 2006). In a
post-award bid protest, an offeror has a “direct economic interest” if it can demonstrate that
“there was a ‘substantial chance’ it would have received the contract award but for the alleged
error in the procurement process.” Info. Tech. & Applications Corp. v. United States, 316 F.3d
1312, 1319 (Fed. Cir. 2003).
In addition, while neither the government nor the Defendant-Intervenor have directly
challenged Plaintiffs’ standing to bring the instant protest, the Court has an independent duty to
ensure that it has jurisdiction over the matter. Hertz Corp. v. Friend, 559 U.S. 77, 94 (2010)
(“Courts have an independent obligation to determine whether subject-matter jurisdiction exists,
even when no party challenges it.”) (citing cases); see also Rule 12(h)(3) of the Rules of the
6
United States Court of Federal Claims. Plaintiff is clearly an actual bidder in this procurement.
However, whether Plaintiff has established a “direct economic interest” in the resolution of each
error it alleges shall be assessed with respect to each individual claim. 2
B. Legal Standard
If a protestor establishes that it has standing, this Court has authority to review the
agency’s decision under the standards set forth in the Administrative Procedure Act (“APA”).
28 U.S.C. § 1491(b)(4); see also 5 U.S.C. § 706. The Federal Circuit has defined a two-part test
to determine the merits of a bid protest under the APA standard. Bannum, Inc. v. United States,
404 F.3d 1346, 1351 (Fed. Cir. 2005). First, the protestor is required to show that the agency
action in question is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance
with law.” 5 U.S.C. § 706(2)(A). Accordingly, this prong of the test is satisfied if either “the
procurement official’s decision lacked a rational basis” or “the procurement procedure involved
a violation of regulation or procedure.” WellPoint Mil. Care Corp. v. United States, 953 F.3d
1373, 1377 (Fed. Cir. 2020) (quoting Impresa Construzioni Geom. Domenico Garufi v. United
States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)). Second, “[t]o prevail in a bid protest, a protestor
must show a significant, prejudicial error in the procurement process.” Id. (quoting Alfa Laval
Separation, Inc. v. United States, 175 F.3d 1365, 1367 (Fed. Cir. 1999)). To establish that it has
suffered a prejudicial error in a post-award protest, a plaintiff is “required to show that there was
a ‘substantial chance’ it would have received the contract award but for the [agency’s] errors in
the bid process.” Bannum, 404 F.3d at 1358 (citations omitted).
Moreover, in reviewing an agency’s procurement decisions, the Court’s task is not to
“substitute its judgment for that of the agency.” Citizens to Preserve Overton Park v. Volpe, 401
U.S. 402, 416 (1971); see also Weeks Marine, Inc., 575 F.3d at 1368–69 (stating that under
“‘highly deferential’ rational basis review,” courts will “sustain an agency action ‘evincing
rational reasoning and consideration of relevant factors’” (quoting Advanced Data Concepts, Inc.
v. United States, 216 F.3d 1054, 1058 (Fed. Cir. 2000))). Rather, the protestor “bears a heavy
burden,” and the agency is “entitled to exercise discretion upon a broad range of issues . . . .”
Impresa, 238 F.3d at 1332–33 (citations omitted). Nonetheless, the APA requires the Court to
intervene in cases in which agency action is unreasonable. “Not only must an agency’s decreed
result be within the scope of its lawful authority, but the process by which it reaches that result
must be logical and rational.” Allentown Mack Sales & Serv., Inc. v. NLRB, 522 U.S. 359, 374
(1998) (citation omitted). “This standard requires that the agency not only have reached a sound
decision, but have articulated the reasons for that decision.” In re Sang Su Lee, 277 F.3d 1338,
1342 (Fed. Cir. 2002). Thus, the Court must use the evidence in the record to determine
“whether the decision was based on the relevant factors and whether there has been a clear error
of judgment.” Citizens to Pres. Overton Park, 401 U.S. at 416.
Finally, bid protests are generally decided on cross-motions for judgment on the
administrative record, pursuant to Rule 52.1 of the Rules of the United States Court of Federal
Claims, which requires the Court to “make factual findings from the record evidence as if it were
2
The Court has determined that Plaintiff has failed to meet its burden to demonstrate it has
standing to protest two of the five counts in its complaint. The Court will specifically address the lack of
standing for these two counts below.
7
conducting a trial on the record.” Bannum, 404 F.3d at 1354. “Unlike a motion for summary
judgment, a genuine dispute of material fact does not preclude a judgment on the administrative
record.” Id. at 1355–56. Therefore, in reviewing cross-motions for judgment on the
administrative record, “the court asks whether, given all the disputed and undisputed facts, a
party has met its burden of proof based on the evidence in the record.” Jordan Pond Co., LLC v.
United States, 115 Fed. Cl. 623, 630 (2014).
C. Analysis
1. The Agency’s Price Realism Analysis was Irrational
In general, a price realism analysis examines whether an offeror’s prices are
unrealistically low for the work to be performed. Thus, a price realism analysis is performed to
ensure that an offeror’s proposed prices are not so low that contract performance is put at risk or
that they evidence a lack of understanding of the solicitation’s requirements. Although the FAR
does not require an agency to conduct a price realism analysis in procurements for fixed-price
contracts, an agency may nonetheless obligate itself to perform one by the terms of its
solicitation. See ViON Corp. v. United States, 122 Fed. Cl. 559, 573 (2015) (holding that a
solicitation stating that “[t]he Government may reject any proposal that is . . . unreasonably high
or low in price when compared to Government estimates” was enough to “commit[] the agency
to conducting a price realism analysis”); Rotech Healthcare, Inc. v. United States, 121 Fed. Cl.
387, 404 (2015) (“[T]he only reason any consideration of realism is necessary is the language in
the RFP stating that unrealistically low offers may be eliminated.” (emphasis added)); FCN, Inc.
v. United States, 115 Fed. Cl. 335, 376 (2014) (“Because a price realism analysis was
contemplated by the Solicitation, one had to be conducted, as the Solicitation stated that
unrealistically low offers ‘may be considered unacceptable and rejected on that basis.’” (internal
citation omitted)). In conducting a realism analysis, including a price realism analysis, “agencies
enjoy wide latitude.” Agile Def., Inc. v. United States, 959 F.3d 1379, 1385–86 (Fed. Cir. 2020);
see also A-T Sols., Inc. v. United States, 122 Fed. Cl. 170, 180 (2015) (“As cost realism
determinations are within an agency’s sound discretion and expertise, the Court will not overturn
a cost realism determination unless the plaintiff demonstrates the absence of a rational basis for
the agency’s decision.” (internal quotation omitted)). 3 In other words, the methodology
employed in a price realism analysis is largely left to the discretion of the agency in instances in
which it does not commit itself to a particular methodology in the solicitation. Afghan Am. Army
Servs. Corp. v. United States, 90 Fed. Cl. 341, 358 (2009). However, whatever methodology the
agency chooses to employ must be reasonable. Westech Int’l, Inc. v. United States, 79 Fed. Cl.
272, 286 (2007) (“While an agency’s cost realism analysis need not have been performed with
‘impeccable rigor’ to be rational, the analysis must reflect that the agency considered the
information available and did not make ‘irrational assumptions or critical miscalculations.’”
(quoting OMV Med., Inc. v. United States, 219 F.3d 1337, 1344 (Fed. Cir. 2000)).
Here, the evaluation criteria in the RFQ clearly committed the agency to conduct a price
realism analysis: “[t]he government will assess the price quotation to ensure the proposed pricing
is realistic for the work to be performed, reflects a clear understanding of the requirements, and
3
Agile Defense and A-T Solutions both addressed cost realism, but the wide agency latitude
discussed in those cases is equally applicable in the price realism context.
8
is consistent with the various elements of the other parts of the quotation.” AR 127. The agency
did not further commit itself to a specific methodology for conducting the analysis; therefore, it
enjoyed discretion in conducting a price realism analysis so long as it reasonably considered
whether the offerors’ proposed pricing: 1) was “realistic for the work to be performed”; 2)
“reflect[ed] a clear understanding of the requirements”; and 3) was “consistent with the various
elements of the other parts of the quotation.” Id. While the agency appears to have conducted a
rational price reasonableness analysis, as is explained below, its price realism analysis was not
conducted in a rational manner.
The agency’s price realism analysis, at least as documented in the administrative record,
essentially consisted of a set of conclusory and repetitive statements with very little explanation
or documentation of what, if anything, was actually done to complete this requirement. For
instance, the price evaluation section of the source selection decision, which intermixes both the
reasonableness and realism components, states that “[i]n conducting the price evaluation, the
government assessed the price quotation to ensure the proposed pricing is realistic for the work
to be performed, reflects a clear understanding of the requirements, and is consistent with the
various elements of the other parts of the quotation.” AR 489. Fair enough, but this statement
simply restates the requirements of the price realism analysis the agency committed itself to
conduct and then, in conclusory fashion, states the agency did in fact conduct such an analysis.
The analysis then reiterates this same conclusion, that “[t]he Government took no exceptions or
issues to the Offerors’ proposed pricing and found all three to be realistic for the work to be
performed. Additionally, all three Offerors reflect a clear understanding of the requirements.”
Id. The Court is left to wonder where the actual analysis is.
Reading on, the Court finally comes across some level of explanation as to why the
agency concluded that the offerors’ proposed prices were realistic. It appears that the realism
determination was based on three factors. First, “the Government compared the two lowest
composite rates offered by and [Tolliver],” and “found that multiple companies offering
low composite rates suggested there was no evidence of an attempt to offer unrealistically low
prices as a strategy to receive the award.” Id. Second, “the Government used the GSA Contract
Awarded Labor Categories (CALC) tool to substantiate a random sample of labor category
prices offered by all three Offerors,” and found that “[a]ll offered labor category prices were well
within the acceptable range.” Id. “Based upon this analysis, the Government determined that all
Offerors’ prices [we]re realistic.” Id. Finally, after concluding that “all Offerors’ prices [we]re
realistic[,]” the agency, explains (using identical language for all three offerors) that it also
examined the level of effort and mix of labor for all three offerors and concluded that the effort
and labor mix “proposed to perform the tasks outlined in the PWS reflects understanding of the
requirements, is consistent with the various elements of the other parts of the quotation and is
considered realistic to support the proposed approach at an acceptable level of risk to the
Government.” AR 489–91 (repeating the language verbatim for each offeror). As explained
below, the Court finds all three of these conclusions, at least to the extent they are documented in
the administrative record, to be unreasonable.
9
a. The agency’s conclusion that two offerors would not propose unrealistically low
prices is irrational
In its MJAR, Plaintiff asks the Court to examine the reasonableness of the Army’s
conclusion that while both and Tolliver “offered composite rates well below the IGCE
composite rates, the Government found that multiple companies offering low composite rates
suggested there was no evidence of an attempt to offer unrealistically low prices as a strategy to
receive the award.” ECF No. 29 (“Pl.’s MJAR”) at 12 (citing AR 489). Plaintiff argues that this
conclusion from the Army’s source selection decision is “predicated on false logic.” Id. at 13.
Specifically, Plaintiff takes issue with the conclusion that it would be “inconceivable” that two
offerors would “offer unrealistically low prices as a strategy to receive the award.” Id.
According to Plaintiff, this line of reasoning “entirely failed to consider an important aspect of
the problem,” which is the possibility that “both Tolliver and proposed unrealistic prices.”
Id.
Although the Court is not in a position to determine whether the prices quoted by Tolliver
and were, in fact, unrealistically low, there is no doubt that the agency’s conclusion that
they were realistic was predicated on an irrational assumption. The conclusion that it would be
“inconceivable” that both Tolliver and would underbid a contract lacks any rational basis.
Surely, it is conceivable that two companies—competing for award—would have similar
motivations for lowering the price of their quotations, even to the point of offering unrealistically
low prices. Why is it that one company would bid an unrealistically low price (hence the whole
reason for a price realism analysis), but two offerors would not? Is it not possible that two
offerors could have underestimated the work required, not understood the requirements, or for
some reason saw some value in this contract that made it worth underbidding? There may be
some explanation for the agency’s conclusion that no two offerors would underbid a contract—
the Court cannot conceive of one—but to any extent there is, such an explanation is not found in
the administrative record. And, without any explanation in the administrative record as to why
this seemingly irrational conclusion is, in fact, rational in this case, the Court cannot find that this
conclusion is reasonable. This conclusion, therefore, does not support a finding that the agency
conducted a rational price realism analysis as was required by the RFQ.
Moreover, the Court must mention that the government entirely failed to respond to
Plaintiff’s argument on this point in its cross-motion, which constitutes waiver. See, e.g., Sarro
& Assocs., Inc. v. United States, 152 Fed. Cl. 44, 58 (2021) (“A party’s failure to raise an
argument in an opening or responsive brief constitutes waiver.”). When questioned about this by
the Court at oral argument, the government could only cite a case mentioned solely in its Reply
brief. Oral Argument at 6:30–14:20; see also ECF No. 38 (“Gov.’s Reply”) at 7 (citing Afghan
Am. Army Servs. Corp., 90 Fed. Cl. at 358). That case—Afghan American Army Services Corp.
v. United States—is of little, if any, help to the government on this point 4 and, even if it were
4
In Afghan American Army Services, Judge George Miller found that a price realism analysis can
be accomplished by “comparison of the prices received with each other” in a case in which the price
comparisons involved evaluating the prices of twenty-one offerors and the independent government
estimate. 90 Fed. Cl. at 358 (internal quotation omitted). Judge Miller nonetheless found the price
realism analysis was irrational because it was based on a flawed independent government estimate. Thus,
10
helpful, waiting to respond to an argument for the first time in a reply brief is not sufficient to
preserve a response. See Novosteel SA v. U.S., Bethlehem Steel Corp., 284 F.3d 1261, 1274
(Fed. Cir. 2002) (“Raising the issue for the first time in a reply brief does not suffice; reply briefs
reply to arguments made in the response brief—they do not provide the moving party with a new
opportunity to present yet another issue for the court’s consideration.”).
Despite the government’s failure to respond to Plaintiff’s argument, Defendant-
Intervenor was able to preserve a response to Plaintiff’s argument on this point; however, the
government’s good fortune is short-lived because Defendant-Intervenor’s argument is
unconvincing. Defendant-Intervenor cites Mil-Mar Century Corp. v. United States, 111 Fed. Cl.
508, 542 (2013), for the proposition that comparing prices between offerors is “one of the
allowable methods to test [price] realism.” ECF No. 32 (“Def-Int.’s MJAR”) at 9. What
Defendant-Intervenor fails to grasp is that Plaintiff’s argument does not rely on an assertion that
comparing prices is a per se unacceptable method of evaluating price realism. Rather, what
Plaintiff challenges is the irrational application of that methodology in this case. Thus, a simple
assertion that comparing offerors’ prices is an acceptable method for conducting a price realism
analysis is largely non-responsive to Plaintiff’s argument and does nothing to bolster the
agency’s irrational conclusion. Again, a method itself not only needs to be rational, but the
application of that method must be rational as well. One needs to look no further than the
opinion in Mil-Mar Century Corp. to understand the unreasonableness of the agency’s
conclusion in this case. In Mil-Mar Century Corp., the agency did far more than just look at two
sets of pricing proposals and conclude that multiple companies offering low composite rates
suggested there was no evidence of an attempt to offer unrealistically low prices as a strategy to
receive the award. Instead, in Mil-Mar Century Corp., “the Agency compared [the awardee’s]
estimated material costs to those of the other offerors and the IGCE, evaluated [the awardee’s]
estimated prices of the engine, tank and frame, and compared [the awardee’s] proposed labor
hours to those of the other offerors.” 111 Fed. Cl. at 542 (internal citations omitted). Simply
put, the apparently thorough price realism analysis in Mil-Mar Century Corp. does not compare
to the conclusory one conducted here, especially considering the irrationality of the conclusion
drawn by the agency.
b. There is insufficient documentation in the record for the Court to review the
reasonableness of the agency’s use of the CALC tool
Plaintiff further alleges that the agency’s use of the GSA Contract Awarded Labor
Categories (“CALC”) tool was not properly documented to be considered a sufficient method of
evaluating price realism. Pl.’s MJAR at 14. In its source selection decision, the agency stated
citation to a case in which the comparison involved the prices of twenty-one offerors is of little value to
this case in which the contracting officer compared the prices of two offerors and ignored the fact that
both the third offeror’s price and the government estimate were much higher. But more importantly, as
will be discussed below in addressing Defendant-Intervenor’s argument regarding Mil-Mar Century
Corp., Plaintiff is not questioning the general proposition that price comparison may be an acceptable
method of conducting a price realism analysis; rather, Plaintiff is questioning the rationality of the
conclusion that “multiple companies offering low composite rates suggested there was no evidence of an
attempt to offer unrealistically low prices as a strategy to receive the award.” Pl.’s MJAR 12–13 (citing
AR 489).
11
that the CALC tool was employed “to substantiate a random sample of labor category prices
offered by all three Offerors,” and it determined that “[a]ll offered labor category prices were
well within the acceptable range.” AR 489. However, Plaintiff points out that “there is no
documentation in the record as to the supposed use of a CA[LC] tool.” Pl.’s MJAR at 14.
“Absent such documentation there is no basis to determine if the use of the CALC tool rationally
supports a price realism analysis.” Id.
Yet again, the government failed to provide any response to Plaintiff’s contention—and,
this time, neither did Defendant-Intervenor. Instead, the government chose to rely on the
assertion that this was a FAR subpart 8.4 procurement, and, therefore, “[t]he amount of
documentation required . . . is far less than that required by FAR [Part] 15.” ECF No. 31
(“Gov.’s Cross MJAR”) at 6 (citing G4S Secure Sols. (USA), Inc. v. United States, 146 Fed. Cl.
265, 270 (2019), aff’d, 829 F. App’x 518 (Fed. Cir. 2020)). However, it is well established that
although FAR subpart 8.4 does require minimal documentation, “[a]n agency [still] must
articulate a satisfactory explanation for an action to permit effective judicial review.” Lab’y
Corp. of Am. Holdings v. United States, 116 Fed. Cl. 643, 652 (2014) (citing Timken U.S. Corp.
v. United States, 421 F.3d 1350, 1355 (Fed. Cir. 2005)).
Initially, it should be noted that the Court takes no issue with the agency’s utilization of
the CALC tool as a method of evaluating price realism. The government devotes large segments
of its brief defending the integrity and usefulness of the CALC tool. See Gov.’s Cross MJAR 7–
9. As the government explains, the CALC tool is a “publicly-available pricing tool,” which
“allows vendors and Government officials to review position-specific hourly rates for contracts
awarded under GSA Multiple Award Schedule (MAS) contracts, such as the EXPRESS Program
BPA.” Id. at 7. “Based on GSA Special Item Numbers (SIN), the CALC tool generates, a
comprehensive list and a corresponding graph of awarded rates for the requested position, and
calculates the average awarded rate, along with the ‘statistical market range.’” Id. The
government defines the “statistical market range” as including “roughly 70%” of the prices
awarded or “plus or minus 1 standard deviation from the mean.” Id.
However, while this Court is inclined to agree that use of the CALC tool could be an
effective method of evaluating price realism, the issue here is that without documentation in the
administrative record, there is no way to know whether the CALC tool was utilized reasonably.
First, the Court cannot discern whether the agency employed a statistically significant random
sample of offerors’ proposed prices. How large was the sample? Which price categories were
run through the CALC tool? Second, the contracting officer does not specify the threshold that
was used to evaluate the sampling for price realism. The decision simply states that “prices were
well within the acceptable range,” AR 489, but nowhere in the administrative record is there an
explanation or definition of what constitutes the “acceptable range.” Without this minimal
amount of documentation, the Court is unable to effectively review whether the contracting
officer’s use of the CALC tool was a reasonable method for evaluating price realism.
What is more, in an attempt to demonstrate to the Court how the CALC tool can be
utilized to effectively evaluate price realism, the government included in its cross-motion tables
showing the results of running three of the required labor categories through the CALC tool.
Gov.’s MJAR at 8. The government does not represent that these three labor categories were the
12
same ones that the agency used in its “random sample of labor category prices”; however,
unfortunately for the government, in one of the three labor categories for which it chose to
supply demonstrative CALC tool graphs—program manager—the results show that one of the
supposedly realistic proposed prices is actually unrealistic according to the government’s own
argument. Gov.’s MJAR at 8. According to the government’s briefing, “acceptable range”
means one standard deviation from the historical awarded rate. See Gov.’s MJAR at 7–8. For
program manager, the low on this range is $111. Id. at 8. Based on the government’s
delineation of the “acceptable range” in its briefing, a proposed labor rate that is at or above $111
is realistic and one that falls below $111 would be unrealistic. The problem for the government
is that the program manager price proposed by is $110.63. AR 391. The agency
determined that prices were realistic, yet the government’s own argument here shows that,
at least for the program manager position, the price proposed was unrealistic. This is not to say
that prices were or were not realistic; rather, the Court simply points out the
unreasonableness of the agency’s use of a “random sample of labor category prices” with
absolutely no explanation or documentation.
c. The agency’s conclusion that “all three Offerors reflect a clear understanding
of the requirements” is unsupported by the administrative record
The agency’s price realism analysis language required it to determine, inter alia, that the
proposed prices “reflect[ed] a clear understanding of the requirements.” AR 127 (emphasis
added). The agency did determine that “all three Offerors reflect a clear understanding of the
requirements.” AR 489. This finding, however, appears to be by ipse dixit. Nowhere else in the
evaluation are the offerors’ clear understandings reflected. In fact, in the technical expertise
evaluation, the evaluators determined that all three offerors had an “adequate” or “acceptable”
level of understanding of the requirements. For all three offerors, the evaluators concluded that
The Offeror’s quotation indicates an adequate understanding of the PWS
requirements and deliverables for a rating of “ACCEPTABLE”. . . . The overall
knowledge and experience communicated by the Offeror demonstrates they have
adequate knowledge necessary to successfully perform the requirements in the
critical PWS paragraphs. . . . In summary, the Offeror’s quotation indicates an
overall acceptable level of understanding of the PWS requirements. Based on the
Offeror’s technical methodology as presented, they have adequate knowledge to
provide the services stated in the PWS and exhibit “ACCEPTABLE” technical
capabilities with moderate risk of unsuccessful performance to the Government.
AR 443, 451, 457 (emphasis added). In addition, all three offerors were rated “acceptable” on
their technical expertise. AR 492. The rating of “acceptable” meant that an offeror had “an
adequate level of expertise and an understanding of the requirements.” AR 124. In other words,
the acceptable rating only documents that an offeror had “an understanding” versus “a clear
understanding” of the requirements.
However, without explanation, in the price evaluation section of the source selection
decision, the offerors are all found to have a “clear understanding of the requirements.” AR 489.
This may be the case, but it is not documented in the administrative record. Instead, it appears
13
airdropped in when needed to satisfy the requirements of the price realism analysis the agency
committed itself to conducting. The agency was not permitted to reach this conclusion without
some rationale as to why the offerors all had a clear understanding of the requirements,
especially considering the only documentation of the offerors’ understanding of the requirements
is that their understanding was adequate or acceptable, not clear.
d. The agency’s conclusory analysis regarding level of effort and mix of labor
appears to be untethered to price
Finally, after concluding that “all Offerors’ prices [we]re realistic[,]” the agency explains
(using identical language for all three offerors) that it also examined the level of effort and mix
of labor for all three offerors and concluded that the effort and labor mix “proposed to perform
the tasks outlined in the PWS reflects understanding of the requirements, is consistent with the
various elements of the other parts of the quotation and is considered realistic to support the
proposed approach at an acceptable level of risk to the Government.” AR 489–91 (repeating the
language verbatim for each offeror). It may be that the level of effort and labor mix, in and of
themselves, were reasonable for the requirements of the RFQ, but to conclude—divorced from
price—that this means the prices proposed were realistic, is an irrational conclusion. Essentially
the agency conducted step one in a two-step analysis. Yes, it is important that, for instance, the
number of hours proposed to conduct a task meets the agency’s estimates for the required
number of hours. But the number of hours proposed tells one little about the realism of the
proposed price if the hourly rate is not considered as part of that analysis. If, for example, the
going rate for a program manager is $150 per hour, and it is reasonably estimated that the
program manager will work 1,000 hours a year (thus $150,000 in total yearly compensation), the
fact that an offeror estimates that the program manager will work 1,000 hours means little in
terms of price realism if the offeror proposes a $75 per hour rate for the program manager
position.
Simply put, it was unreasonable for the agency to conclude, based on level of effort and
labor mix alone (without considering price), that that all three offerors’ proposed prices were
realistic, i.e., that they are “realistic for the work to be performed, reflect[] a clear understanding
of the requirements, and [are] consistent with the various elements of the other parts of the
quotation.” AR 489.
e. Plaintiff was prejudiced by the failure to conduct a rational price realism
analysis
First, it has been repeatedly held that an agency’s failure to conduct a required price
analysis is a prejudicial error in and of itself, constituting a “significant . . . error in the
procurement process.” Al Ghanim Combined Grp. Co. Gen. Trad. & Cont. W.L.L. v. United
States, 56 Fed. Cl. 502, 516 (2003) (quoting Alfa Laval Separation, Inc., 175 F.3d at 1367);
Active Network, LLC v. United States, 130 Fed. Cl. 421, 429 (2017) (“Without a price realism
analysis in the record, the Court has nothing to review and no way of determining whether [the
protestor] was prejudiced. This conclusion alone is sufficient to warrant remand to conduct a
proper price realism analysis.”); IAP World Servs., Inc. v. United States, 152 Fed. Cl. 384, 409
(2021) (“Therefore, this Court agrees with the Al Ghanim and Green Tech. line of cases and
14
concludes that Plaintiff has adequately shown prejudice from the Navy’s failure to perform an
unbalanced pricing analysis.”). In this case, as was explained above, the agency was required to
perform a price realism analysis under the terms of the RFQ and failed to do so in a manner that
was rational (at least as can be observed by the documentation in the administrative record).
Thus, under the above line of cases, this failure alone would be sufficient to show prejudice.
But even leaving this line of cases aside, the prejudice here is obvious. The award
decision in this case came down to price:
Beyond the mere adjectival ratings, the Contracting Officer found there was no
functional differences between the approaches offered by [Tolliver and ].
Therefore, in accordance with the evaluation criteria, the importance of price
increased when performing the trade-off analysis. With price increased in
importance, the Contracting Officer found that [Tolliver] offered a better value
because its price is nearly $1 million dollars lower than /RTC’s price and there
was no identifiable advantage to justify paying this price premium. Therefore,
between these two offerors, the Contracting Officer determined that [Tolliver]
offered the better value for the Government. . . .
Both [Tolliver and Digiflight] received identical adjectival ratings in the Technical
Factor. Beyond the mere adjectival ratings, the Contracting Officer found no
functional differences between the technical approaches of both companies.
However, in the Risk Mitigation and Management factor, DigiFlight offered a slight
advantage over [Tolliver] due to the strength assigned to DigiFlight. The
Contracting Officer then compared the prices offered by both companies and
determined that [Tolliver] offered a much lower price than DigiFlight. . . . The only
advantage offered by DigiFlight concerns the particular subcontractors DigiFlight
plans to employ for this task. . . . [T]he strength assigned only applies to one of
those concerns and does not justify paying a roughly $16 million price premium.
Therefore, the Contracting Officer determined that [Tolliver] provides the best-
value to the Government.
AR 495–96. In short, price was the deciding factor.
Given that price was the deciding factor and that Plaintiff’s allegation is that the prices of
the other offerors were unrealistically low compared to the prices it proposed (which were
determined to be both reasonable and realistic), if Plaintiff is correct that the other offerors’
prices were unrealistic (an analysis that the agency did not rationally undertake), Plaintiff would
have a not insubstantial chance of award once those offerors are either eliminated from
competition for proposing unrealistic prices or have their prices adjusted upwards to realistic
levels. Accordingly, although the Court does not know what the outcome of a rational price
realism analysis would be, certainly it is possible that the price differential that resulted in
Tolliver being awarded the contract over Plaintiff could change if a proper price realism analysis
is conducted. Therefore, Plaintiff was prejudiced by the error.
15
2. Plaintiff Lacks Standing to Challenge Whether the Agency Complied with
FAR § 52.222-46
Plaintiff next alleges that the Army failed to comply with FAR § 52.222-46. That
regulation—if applicable 5—would require each offeror to submit a “total compensation plan”
along with its proposal, “setting forth salaries and fringe benefits proposed for the professional
employees who will work under the contract.” 48 C.F.R. § 52.222-46(a). It would also require
the contracting agency to “evaluate the plan[s] to assure that [they] reflect[] a sound management
approach and understanding of the contract requirements.” Id. Plaintiff alleges that the agency
never performed such an assessment.
As a threshold matter, Plaintiff lacks standing to bring such a challenge. First, Plaintiff
failed to plead in its complaint how the Army’s alleged failure to comply with the regulation
prejudiced it in any way. 6 For example, a well-pled complaint would likely contain an allegation
that Plaintiff proposed higher prices in its price proposal to account for the professional
compensation levels it believed a proposal would need to meet in order to survive analysis under
FAR § 52.222-46; however, such an allegation, or something similar, appears nowhere in
Plaintiff’s complaint. 7 Second, Plaintiff fails to allege in its complaint that the RFQ even
required the “meaningful numbers of professional employees necessary” for FAR § 52.222-46 to
apply in the first place. See 48 C.F.R. § 22.1103. FAR § 52.222-46 only applies to contracts that
meet the standards of FAR § 22.1103, which requires that 1) the contract amount be “expected to
exceed $750,000” and 2) the “services are to be provided which will require meaningful numbers
of professional employees.” Id. While it is clear from the complaint that the contract amount
was certainly expected to well-exceed $750,000, an allegation that the RFQ met the meaningful
number of professional employees’ requirement is nowhere to be found. These two pleading
insufficiencies require the Court to dispense of this argument before even considering its merit.
Castle, 301 F.3d at 1337 (“Standing is a threshold jurisdictional issue, which . . . may be decided
without addressing the merits of a determination.”).
Moreover, even if Plaintiff’s theory were sufficiently pleaded and meritorious, Plaintiff
waived its right to bring such a claim here by failing to object to the non-inclusion of FAR
§ 52.222-46 as part of the evaluation criteria prior to the conclusion of the bidding process.
According to Federal Circuit precedent, “a party who has the opportunity to object to the terms
of a government solicitation containing a patent error and fails to do so prior to the close of the
5
FAR § 22.1103 requires the inclusion of FAR § 52.222-46 “in solicitations for negotiated
contracts when the contract amount is expected to exceed $750,000 and services are to be provided which
will require meaningful numbers of professional employees.” 48 C.F.R. § 22.1103.
6
At oral argument, Plaintiff even conceded that it did not plead in the complaint that the alleged
violation impacted its bid. Oral Argument at 1:14:08.
7
Plaintiff does make a statement that would have likely been sufficient for standing purposes in
its MJAR had that statement been made in its complaint: “DigiFlight relied upon FAR § 52.222-46(c) that
the ‘Government is concerned with the quality and stability of the work force to be employed on this
contract.’ In so doing, DigiFlight did not radically cut professional wage rates in order to be more
competitive for award.” Pl.’s MJAR at 22. Unfortunately for Plaintiff, an allegation like this needed to
be in its complaint in order to meet its standing burden. Even had Plaintiff met its standing burden,
however, this bare allegation in its MJAR would not have been sufficient on the merits to meet its burden
of proof of demonstrating merits prejudice.
16
bidding process waives its ability to raise the same objection subsequently in a bid protest action
in the Court of Federal Claims.” Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313
(Fed. Cir. 2007). If Plaintiff were correct that FAR § 52.222-46 applied to this RFQ, the
agency’s failure to include FAR § 52.222-46 in the RFQ would have been obvious, because the
agency never asked Plaintiff to submit, nor did Plaintiff’s offer contain, a total compensation
plan—as would be required by FAR § 52.222-46 if it applied. See generally AR 191–270. This
is not some minor undertaking that could have been missed and thus would not have been
obvious to Plaintiff. To comply with FAR § 52.222-46, Plaintiff would have needed to provide:
“a total compensation plan setting forth salaries and fringe benefits proposed for the professional
employees who will work under the contract . . . [and] [s]upporting information [] includ[ing]
data, such as recognized national and regional compensation surveys and studies of professional,
public and private organizations, used in establishing the total compensation structure.” 48
C.F.R. § 52.222-46; see also 48 C.F.R. § 22.1103 (same). Plaintiff had to be aware that it was
not providing this information and that, accordingly, the agency did not consider FAR § 52.222-
46 to be applicable. Therefore, even if Plaintiff had standing to raise this claim, under Blue &
Gold, Plaintiff waived any objection to a FAR § 52.222-46 violation by failing to raise the issue
prior to the close of bidding.
Finally, even if Plaintiff had demonstrated that it has standing and that Blue & Gold was
inapplicable, Plaintiff would still be unable to demonstrate merits prejudice here because it
benefited from the same alleged error as the awardee did. As pointed out above with regard to
its obligations under Blue & Gold, Plaintiff itself did not submit a total compensation plan as
would be required by FAR § 52.222-46 if that provision applied to this procurement. “There has
been no prejudice when a bid protestor benefited from the same potentially unlawful discretion
from which the awardee benefited.” G4S Secure Integration LLC v. United States, No. 21-
1817C, 2022 WL 211023, at *8 (Fed. Cl. Jan. 24, 2022), appeal dismissed, No. 2022-1513, 2023
WL 316142 (Fed. Cir. Jan. 19, 2023).
3. The Agency Erred by Essentially Converting a Best Value Procurement into a
Lowest Price Technically Acceptable Procurement
In its complaint, Plaintiff alleges that “by not evaluating the proposals for strengths, the
evaluators converted a best value procurement to a technically acceptable low-price
procurement.” ECF Nos. 1, 28 (“Compl.”) ¶ 1. 8 The evaluation criteria stated that the award
“will be made to the Offeror whose quotation provides the best value to the Government based
upon evaluation of all submitted quotations using the criteria below and a tradeoff process.” AR
123. As stated above, the three criteria were to be weighed as follows: “Technical Expertise, and
Risk Mitigation and Management, are of equal importance, and each of them is of greater
importance than Price.” Id. Furthermore, the evaluation criteria provided that while “[p]rice is
not expected to be the controlling criterion in the selection,” “its importance will increase as the
differences between the evaluation results for the other criteria decrease.” Id. In addition,
regarding how the proposals were to be evaluated for Technical Expertise, the RFQ explicitly
8
Plaintiff filed its complaint on October 14, 2022, ECF No. 1, and filed an amended complaint on
November 30, 2022, ECF No. 28. That amended complaint, however, merely added an additional count
(Count V) to the original complaint. It did not restate paragraphs 1–52 of the original complaint or the
prayer for relief. Accordingly, the citations to the complaint throughout will only refer to one complaint.
17
noted that “the Government considers the requirements in the following PWS paragraphs 3.1.3,
3.1.10, 3.1.11, 3.1.14, 3.1.15, 3.1.16, 3.1.17, 3.2.2, and 3.2.3 to be critical.” AR 124 (emphasis
omitted).
Plaintiff challenges the agency’s evaluation of Technical Expertise, claiming that “the
evaluators only assessed if the proposals were technically acceptable without seeking to
differentiate among the proposals.” Pl.’s MJAR at 24. Specifically, Plaintiff points to the source
selection decision, in which “for the evaluation criteria of Technical Expertise, all three
proposals were identically evaluated,” and all were awarded zero strengths, zero weaknesses, and
zero deficiencies. Id. Moreover, Plaintiff asserts that “there is no separate analysis of
differences among the proposals as to PWS paragraphs 3.1.3, 3.1.10, 3.1.11, 3.1.14, 3.1.15,
3.1.16, 3.1.17, 3.2.2, and 3.2.3.” Id. Although Plaintiff admits that “it is possible that the
proposals for technical expertise of the three offerors did not contain a single strength or
weakness,” Plaintiff still contends that such a “remote possibility cannot withstand scrutiny when
examined against the facts.” Id. at 25.
Rather, according to Plaintiff, this case is factually similar to the Government
Accountability Office’s (“GAO”) decision in Systems Research and Applications Corporation;
Booz Allen Hamilton, Inc., B-299818, 2007 WL 4867939 (Comp. Gen. Sept. 6, 2007). In that
case, GAO sustained a protest because “the record evidence[d] that the agency did not evaluate
the proposals . . . in a way that reasonably distinguished their relative merits in accordance with
the RFP’s evaluation scheme.” Id. at *20. According to GAO,
[w]here, as here, the RFP states a best value evaluation plan—as opposed to
selection of the lowest priced, technically acceptable offer—evaluation of
proposals is not limited to determining whether a proposal is merely technically
acceptable; rather, proposals should be further differentiated to distinguish their
relative quality under each stated evaluation factor by considering the degree to
which technically acceptable proposals exceed the stated minimum requirements
or will better satisfy the agency’s needs.
Id. at *19.
In response (to the extent it can be characterized as such), the government largely ignores
Plaintiff’s arguments and essentially asserts two things: 1) that Plaintiff did not prove it was
prejudiced by the alleged failure to properly evaluate the proposals for their technical merit; and
2) that lack of documentation in the record that Plaintiff is complaining about is simply a result
of this being a FAR subpart 8.4 procurement with streamlined documentation requirements.
Defendant-Intervenor largely mirrors the government’s arguments on these points.
Taking the government’s second argument first (as it goes to whether there was error,
versus whether any error was prejudicial), the government puts slightly more meat on the bones
of this argument in its reply brief asserting that “[a]s this Court has explained, FAR Subpart 8.4
requires minimal ‘documentation of any tradeoffs’ when the source selection authority chooses
between proposals with similar overall ratings.” ECF No. 38 (“Gov. Reply”) at 2 (citing Matt
18
Martin Real Estate Mgmt., LLC v. United States, 96 Fed. Cl. 106, 116 n.11 (2010)). In other
words, the government’s argument is that any failure to document the results of the technical
expertise evaluation is not an error because this is a FAR subpart 8.4 procurement and FAR
subpart 8.4 procurements require less documentation. 9
Although the government is correct that FAR subpart 8.4 procurements permit more
streamlined documentation than, for instance, FAR part 15 procurements, this streamlined
documentation requirement does not get the agency off the hook for the almost complete lack of
documentation of its rationale regarding its technical expertise evaluation for at least two
reasons. First, the streamlined or “minimum” documentation required by FAR subpart 8.4 does
not mean that the agency can provide almost no rationale for the decisions made on the technical
evaluation. FAR subpart 8.4 is clear on this point. Second, even if the FAR permitted the level
of streamlined documentation the government argues for, effective judicial review under the
Tucker Act, applying the APA standard, requires more documentation of the reasoned basis for
the agency’s decision than was provided here.
The Army’s technical expertise evaluations for all three offerors are identical, with one
small immaterial difference: 10
The Offeror’s quotation indicates an adequate understanding of the PWS
requirements and deliverables for a rating of “ACCEPTABLE.” The Evaluation
Team reviewed and evaluated all of the Offeror’s presented PWS paragraphs.
There were zero strengths, zero weaknesses, zero deficiencies, and [no/no/two]
comments identified in the Offeror’s quotation. The overall knowledge and
experience communicated by the Offeror demonstrates they have adequate
knowledge necessary to successfully perform the requirements in the critical PWS
paragraphs.
All PWS sections were reviewed, and if not addressed above, they were determined,
at a minimum, to have been adequately covered in the Offeror’s quotation. In
summary, the Offeror’s quotation indicates an overall acceptable level of
understanding of the PWS requirements. Based on the Offeror’s technical
9
Apparently, the government also believes that protests involving FAR subpart 8.4 procurements
require less briefing. As the Court has already observed, and will observe later in this opinion, the
government failed to address important aspects of Plaintiff’s arguments, as well as two of the four
injunctive relief factors. With regard to this particular FAR subpart 8.4 argument—that FAR subpart 8.4
requires less documentation—the government cited to, or quoted from, FAR subpart 8.4 exactly zero
times. See, e.g., Gov.’s MJAR at 15–16 (neither quoting nor citing anything in FAR subpart 8.4 in
support of its argument). The government’s table of authorities indicates that it cited to FAR subpart 8.4
five or more times in its opening brief by identifying the location of its citations as “passim” or
throughout. Although FAR subpart 8.4 is mentioned throughout the government’s brief, not a single
section within the entire subpart is cited or quoted even once, leaving the Court to wonder exactly what
the government is referring to in FAR subpart 8.4 (a subpart that contains thirteen sections and seven
subsections) that supports the government’s argument. As is discussed in the body of this opinion, FAR
subpart 8.4 has clear documentation requirements that the Army did not comply with here.
10
The Army did make two comments on Tolliver’s proposal regarding what were apparently two
minor concerns. See AR 480. These concerns did not affect Tolliver’s overall technical expertise rating.
19
methodology as presented, they have adequate knowledge to provide the services
stated in the PWS and exhibit “ACCEPTABLE” technical capabilities with
moderate risk of unsuccessful performance to the Government.
AR 478–480.
This incredibly repetitive and completely conclusory five-sentence long summary of the
results of the technical expertise evaluation comports with neither FAR subpart 8.4, nor the
APA. First, FAR subpart 8.4 requires, for a BPA like this procurement, that the “contracting
officer shall include in the BPA file documentation” of, inter alia: 1) “[e]vidence of compliance
with paragraph (b) of this section,” which requires that the “contracting officer shall ensure all
quotes received are fairly considered and award is made in accordance with the basis for
selection in the RFQ”; and 2) the “[b]asis for the award decision[, which] . . . should include the
evaluation methodology used in selecting the contractor, the rationale for any tradeoffs in
making the selection, and a price reasonableness determination for services requiring a statement
of work.” 48 C.F.R. § 8.405-3(a)(7). There is, however, no evidence in the administrative
record demonstrating compliance with paragraph (b) or providing any real rationale for any
tradeoffs in making the selection. With regard to compliance with paragraph (b), the Court
simply cannot tell from this administrative record whether all proposals were fairly considered or
whether the award was made in accordance with the basis for selection in the RFQ. In other
words, the repetitive and conclusory explanation of the results of the technical evaluation quoted
above gives the Court no indication that the quotes were either fairly evaluated or evaluated in
accordance with the RFQ, which, for instance, set forth nine paragraphs in the PWS that were
deemed by the agency “to be critical.” AR 124. Moreover, with regard to the basis for the
award decision, the Court can neither tell what the evaluation methodology actually was for
selecting the awardee nor discern the rationale for the tradeoff analysis, which simply adopted
the evaluation team’s technical expertise ratings. Indeed, the technical expertise ratings
themselves offer little, to no, rationale for the ratings given, or why no strengths, weaknesses, or
deficiencies were awarded. In short, although FAR subpart 8.4 may create a low bar for
documentation, the Army has fallen woefully short of that bar here.
Moreover, rather than directing the Court to any section, subsection, paragraph, or clause
in FAR subpart 8.4 that supports its streamlined documentation argument, the government
directed the Court to decisions of other judges of this Court in FAR subpart 8.4 bid protests,
principally Matt Martin Real Estate Management LLC v. United States, 96 Fed. Cl. 106 (2010).
Notably, however, the facts of Matt Martin actually support the Plaintiff’s position. Although it
is true that Matt Martin holds that “[t]he amount of documentation necessary in FAR Subpart 8.4
procurements does not rise to the level required by FAR Part 15,” it does not hold that the almost
non-existent documentation that is present in this protest complies with FAR subpart 8.4. 96
Fed. Cl. at 116. Thus, rather than help the government, Matt Martin provides an example of the
type of evaluation and documentation thereof that should be present in a FAR subpart 8.4
procurement:
The TET members rated each proposal independently. AR Tab 10, at 316. Once
individual TET members completed their individual evaluations, the TET convened
to review and compare individual evaluation ratings. Id. at 317. The TET members
20
discussed the strengths, weaknesses, significant weaknesses[,] and deficiencies of
each offeror and determined appropriate ratings. Id. The TET then completed an
Initial Evaluation devoting twenty-two pages to its analysis of Matt Martin's
proposal. AR Tab 44, at 2248–70. In the Initial Evaluation, the TET identified
Matt Martin’s strengths and weaknesses and included a narrative explaining its
basis for each determination. Id. The TET then requested revised proposals. AR
Tab 21. In the Revised Evaluation, the TET devoted eight pages to its analysis of
Matt Martin's proposal. AR Tab 43, at 1860–67.
Following the Initial and Revised Evaluations, the TET prepared its Source
Selection Memorandum with ratings of each proposal based on the Solicitation
factors and the Initial and Revised Evaluations. AR Tab 42, at 1702. The TET
submitted the Source Selection Memorandum, its Initial Evaluations and its
Revised Evaluations to the SSO. Id.
96 Fed. Cl. at 115–16. Simply put, the documentation in the government’s principal case in
support of its streamlined documentation argument far exceeded the mere five-sentence long,
conclusory explanation present in this protest.
Beyond violating the even minimal documentation requirements of FAR subpart 8.4, the
Army insufficiently documented its technical expertise evaluation for purposes of the APA
standard of review this Court applies in a bid protest. It is axiomatic “that an agency must
explain its action with sufficient clarity to permit ‘effective judicial review.’ Failure to provide
the necessary clarity for judicial review requires the agency action be vacated.” Timken U.S.
Corp., 421 F.3d at 1355 (quoting Camp v. Pitts, 411 U.S. 138, 142–43 (1973)). “Specifically,
the agency must articulate the reasons for its procurement decision including a rational
connection between the facts found and the choice made.” Lab’y Corp. of Am. Holdings, 116
Fed. Cl. at 652 (citing Distributed Sols., Inc. v. United States, 104 Fed. Cl. 368, 377 (2012)); see
also Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43
(1983) (“[T]he agency must examine the relevant data and articulate a satisfactory explanation
for its action including a rational connection between the facts found and the choice made.”
(internal quotations and citation omitted)). Here, the administrative record does not provide a
satisfactory explanation for the Army’s technical evaluation of the offerors’ proposals. In other
words, the Army—to harken back to grade school math—forgot to show its work. But the
Court’s task is to determine whether the Army “considered the relevant factors and articulated a
rational connection between the facts found and the choice made.” Balt. Gas & Elec. Co. v.
NRDC, 462 U.S. 87, 105 (1983) (citation omitted). The record before the Court does not allow it
to make that determination.
The government additionally argues that Plaintiff has not demonstrated that it was
prejudiced by this complete failure of the Army to demonstrate that it conducted a rational
technical expertise evaluation. The government’s argument is without merit. According to the
government, in order to demonstrate prejudice, Plaintiff was supposed to prove not only that the
government’s failure to conduct a technical evaluation and thus trade-off analysis (thereby
converting this best value procurement into a lowest price, technically acceptable procurement)
was in error, but also that there were strengths Plaintiff was supposed to be awarded that it did
21
not receive. The government’s argument misses the mark. First, Plaintiff alleged in its
complaint that it would have received eleven strengths, see Compl. Ex. 4, and reasserted that
argument, albeit without great detail, in its MJAR, Pl.’s MJAR at 25. But what Plaintiff is really
arguing here is not that it should have received additional strengths—it is arguing that the Army
completely failed to document its technical evaluation and its rationale for not awarding any
strengths, weaknesses, or deficiencies. By so doing, according to Plaintiff, the Army
impermissibly turned a best value procurement into a lowest price, technically acceptable
procurement. See 48 C.F.R. § 8.405-3(b)(2)(viii) (“The ordering activity contracting officer
shall establish the BPA with the schedule contractor(s) that represents the best value.”).
The prejudice to Plaintiff of converting this procurement from best value to lowest price,
technically acceptable is obvious. For instance, the pricing for the level of effort and expertise
that satisfies technical acceptability is likely substantially lower than the pricing of the level of
effort and expertise needed to compete for a best value award. If Plaintiff were aware of the
playing field it was playing on, it likely would have submitted a substantially different pricing
proposal potentially making its proposed prices more in line with those of the other two offerors.
Conversely, if the agency had actually evaluated the technical expertise presented in the
proposals, which it did not according to the record information before the Court, it is likely that
Plaintiff may have received strengths or that the other offerors may have received weaknesses
that would have affected the best value analysis. Instead, the agency erred by essentially
ignoring its obligation to conduct a technical expertise evaluation and thereby significantly
elevating the relative importance of price in its best-value tradeoff analysis. This error
prejudiced Plaintiff.
4. Plaintiff Failed to Demonstrate Standing to Protest the Evaluation of the Risk
Management and Mitigation factor
Finally, Plaintiff argues that the agency’s evaluation of Risk Mitigation and Management
was unreasonable because “the Army entirely failed to consider an important aspect of the
problem – Tolliver’s ability to obtain and retain qualified personnel.” Compl. ¶ 58. However,
the Court need not reach the merits because Plaintiff has failed to sufficiently plead that it has
standing to challenge this aspect of the evaluation. Nowhere in Plaintiff’s complaint did it allege
how it was prejudiced by the agency’s alleged error in evaluating Tolliver’s proposal under the
Risk Mitigation and Management factor. Rather, Plaintiff simply states that it “was prejudiced
by the arbitrary evaluation of Risk Mitigation and Management.” Id. ¶ 59. That may be, but
proper pleading of prejudice for standing purposes requires more than just this conclusion. The
next paragraph of the amended complaint may offer a little more of a clue as to what Plaintiff’s
prejudice might be: “because the evaluators failed to consider Tolliver’s ability to obtain and
retain qualified personnel in light of Tolliver proposing wages that were drastically lower than
historically paid, Count V should be sustained, and the relief granted as requested.” Id. ¶ 60.
While this sentence is slightly more illuminating as to prejudice—as in, maybe what Plaintiff is
alleging is that Tolliver’s proposed prices were artificially low and if they were higher Plaintiff
would have had a substantial chance of award—it still does not, if fact, allege how Plaintiff was
prejudiced. For instance, did Plaintiff increase its prices in anticipation of the evaluation of Risk
Mitigation and Management factor? The Court does not know whether that is the alleged
prejudice because Plaintiff did not plead it.
22
Moreover, it is not clear from Plaintiff’s complaint or its MJAR that this is what it is
actually asserting caused it prejudice. Rather, it appears from those documents that it seems to
be arguing that Tolliver should have received a weakness under the Risk Mitigation and
Management factor because it was questionable, according to Plaintiff, whether Tolliver had the
“ability to obtain and retain qualified personnel.” Pl.’s MJAR at 31. The “ability to obtain and
retain qualified personnel” sounds more like an argument regarding weaknesses or deficiencies
than price. But Plaintiff makes no allegation as to how Tolliver receiving a weakness would
have affected Plaintiff. This discussion is an example of why the Court, in all but the most
obvious cases, cannot, on behalf of a protestor, surmise the prejudice the protestor allegedly
suffered as a result of a procurement error. It was Plaintiff’s obligation to plead some sort of
allegation as to how exactly a failure to properly evaluate Tolliver under this factor affected
Plaintiff.
Furthermore, to any extent that the prejudice caused by this alleged error is obvious, the
Court believes that this potential prejudicial effect is already covered by the price realism
analysis that the agency will be required to rationally conduct if it chooses to go forward with
this procurement. In other words, although the prejudice for pricing-error allegations in
procurements in which price is the deciding factor may generally be obvious, because the Court
has already determined the price realism evaluation was in error, Plaintiff needed to allege more
here for this seemingly cumulative argument (if in fact this was Plaintiff’s argument) in order to
demonstrate prejudice. Because Plaintiff failed to allege how it was prejudiced by the agency’s
alleged error with regard to its evaluation of the Risk Mitigation and Management factor,
Plaintiff lacks standing to challenge this aspect of the agency’s evaluation.
D. Injunctive Relief
As the Court has determined that the Army’s award of the contract to Tolliver was
unreasonable and that Plaintiff was prejudiced by the agency’s error, the Court now turns to the
question of whether Plaintiff is entitled to injunctive relief. The Federal Circuit has articulated a
four-part test for the issuance of a permanent injunction as follows:
To determine if a permanent injunction is warranted, the court must consider
whether (1) the plaintiff has succeeded on the merits of the case; (2) the plaintiff
will suffer irreparable harm if the court withholds injunctive relief; (3) the balance
of hardships to the respective parties favors the grant of injunctive relief; and (4)
the public interest is served by a grant of injunctive relief.
Centech Group, Inc. v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009) (citing PGBA, LLC
v. United States, 389 F.3d 1219, 1228–29 (Fed. Cir. 2004)). Because Plaintiff has succeeded on
the merits of its protest, the Court turns to the three remaining injunctive relief factors.
1. Irreparable Harm
With respect to irreparable harm, the pertinent question is “whether plaintiff has an
adequate remedy in the absence of an injunction.” Magellan Corp. v. United States, 27 Fed. Cl.
23
446, 447 (1993); see also Younger v. Harris, 401 U.S. 37, 43–44 (1971) (noting that “the basic
doctrine of equity jurisprudence [is] that courts of equity should not act . . . when the moving
party has an adequate remedy at law and will not suffer irreparable injury if denied equitable
relief”). Plaintiff asserts that it will be harmed absent the issuance of an injunction because the
only other available relief—recoupment of bid preparation costs—would not remedy its lost
opportunity to fairly compete for the contract.
In response, the government once again skips over Plaintiff’s argument and argues
instead that Plaintiff has not suffered irreparable harm because Plaintiff has not demonstrated
that it was prejudiced by any alleged errors. Gov.’s Cross MJAR at 18. However, as explained
above regarding the merits of the two errors upon which Plaintiff prevailed, Plaintiff was
prejudiced by the Army’s errors. Moreover, “[t]his court has recognized that a lost opportunity
to compete for a contract—and the attendant inability to obtain the profits expected from the
contract—can constitute irreparable injury.” Bluewater Mgmt. Grp., LLC v. United States, 150
Fed. Cl. 588, 619 (2020) (citing Akal Sec., Inc. v. United States, 87 Fed. Cl. 311, 319 (2009));
Hosp. Klean of Tex., Inc. v. United States, 65 Fed. Cl. 618, 624 (2005)); see also CW Gov’t
Travel, Inc. v. United States, 110 Fed. Cl. 462, 494 (2013) (“The Court of Federal Claims has
repeatedly held that a protester suffers irreparable harm if it is deprived of the opportunity to
compete fairly for a contract.”); Serco Inc. v. United States, 81 Fed. Cl. 463, 501–02 (2008)
(noting that because “the only other available relief—the potential for recovery of bid
preparation costs—would not compensate [the protestors] for the loss of valuable business on the
[contract]. This type of loss, deriving from a lost opportunity to compete on a level playing field
for a contract, has been found sufficient to prove irreparable harm”). Accordingly, Plaintiff has
adequately demonstrated that it will suffer irreparable harm if injunctive relief is not provided.
2. Balance of Hardships
In addition to considering whether a protestor would suffer an irreparable injury absent
injunctive relief, the Court must determine whether the balance of hardships to the government
and Defendant-Intervenor in issuing an injunction outweigh the harms to Plaintiff. PGBA, LLC,
389 F.3d at 1229. Here, Plaintiff has established irreparable harm, as explained above.
Furthermore, Plaintiff argues that the government would not be harmed beyond the “the garden-
variety costs and delays that may result from this Court’s issuance of a preliminary injunction.”
ECF No. 4 at 21 (citing Univ. Rsch. Co., LLC v. United States, 65 Fed. Cl. 500, 514 (Fed. Cl.
2005) (finding that the costs and inconvenience associated with the delay in transition caused by
the issuance of a preliminary injunction were typical of the costs and inconveniences that face
almost every new contractor seeking to unseat an incumbent contractor and did not outweigh the
imminent harm to plaintiff)).
Astonishingly, the government provided no actual response to Plaintiff’s argument. 11
The Court is bewildered by the lack of response to this injunctive relief criteria. 12 It is difficult
11
Defendant-Intervenor also did not point to any hardships it would suffer due to this Court’s
issuance of an injunction in this case. See ECF No. 32 at 28–29.
12
The sum total of the government’s response on the hardship and public interest factors was as
follows: “[l]ikewise, as acknowledged in DigiFlight’s motion, the hardship and public interest factors
24
for the Court to discern whether the government’s failure to respond is because the government
believes that it will not suffer any harm if an injunction is issued or if it is the result of
overconfidence regarding the strength of its positions on the merits. 13 Coincidently, it is
similarly difficult for the Court to “balance” hardships when the government could not be
bothered to assert what, if any, hardships it will suffer if an injunction is issued. Thus, the Court
will presume that Plaintiff was correct in asserting that the government would not be harmed
beyond the costs and delays that typically result from the issuance of an injunction. 14
3. Public Interest
Turning to the final factor, the Court finds that issuing a permanent injunction will serve
the public interest. The Supreme Court has instructed that before a court “employ[s] the
extraordinary remedy of injunction,” it “should pay particular regard for the public
consequences” of so doing. Weinberger v. Romero-Barcelo, 456 U.S. 305, 312 (1982). It is
beyond dispute that “[t]here is an overriding public interest in preserving the integrity of the
procurement process by requiring the government to follow its procurement regulations.”
Turner Constr. Co. v. United States, 94 Fed. Cl. 561, 586 (2010) (citation and internal quotation
marks omitted), aff’d, 645 F.3d 1377 (Fed. Cir. 2011). Moreover, “the public interest in honest,
open, and fair competition in the procurement process is compromised whenever an agency
abuses its discretion in evaluating a contractor’s bid.” PGBA, LLC, 57 Fed. Cl. at 663. It is
paramount that a procuring agency abide by the terms of its solicitation and the FAR in order to
maintain public confidence in the procurement process. This was not done here and, to any
extent that this general rule or some other reasons weigh against Plaintiff on this factor, the
government, as with the hardship factor, could not be bothered with addressing Plaintiff’s
argument. Accordingly, this factor likewise weighs in Plaintiff’s favor.
4. Weighing of the Factors
In addition to prevailing on the merits of its protest, Plaintiff has established that it will
suffer irreparable harm if the Court does not provide injunctive relief, that the balance of harms
turns in its favor, and that awarding injunctive relief is clearly in the public interest.
Accordingly, the issuance of a permanent injunction is warranted.
often coalesce around the merits in bid protests. Pl.’s Mot. at 38 (citations omitted). As such, these
factors also weigh against injunctive relief.” Gov.’s Cross MJAR at 17–18. First, the Court does not see
anything that resembles Plaintiff “acknowledg[ing] . . . the hardship and public interest factors often
coalesce[ing] around the merits” on page 38 of Plaintiff’s motion such that the government is somehow
responding to what Plaintiff argues regarding these two factors. Second, and more importantly, these two
sentences (falsely bolstered by a phantom citation to a non-existent argument in Plaintiff’s motion) are
conclusory. Simply put, “these factors also weigh against injunctive relief” is not a responsive argument.
13
If it is the latter, this would be an even odder position to take considering the government failed
to even respond to Plaintiff’s main argument regarding price realism.
14
And even if this presumption is incorrect, the factor nonetheless weighs in Plaintiff’s favor as a
matter of waiver. See, e.g., SmithKline Beecham Corp. v. Apotex Corp., 439 F.3d 1312, 1319 (Fed. Cir.
2006) (“Our law is well established that arguments not raised in the opening brief are waived.”).
25
CONCLUSION
For the reasons set forth above, counts II and V of Plaintiff’s complaint are DISMISSED
for lack of subject matter jurisdiction; the Court GRANTS Plaintiff’s motion for judgment on
the administrative record as to the remaining counts in its complaint; and DENIES the
government’s and Defendant-Intervenor’s cross-motions. Additionally, the Court orders that:
1. The United States, including the Department of the Army, its officers, agents, and
employees, is hereby PERMANENTLY RESTRAINED AND ENJOINED from
obtaining, or continuing to obtain, performance from Tolliver on the task order awarded
to Tolliver pursuant to the RFQ at issue in this protest;
2. Furthermore, the United States, including the Department of the Army, its officers,
agents, and employees, is hereby PERMANENTLY RESTRAINED AND ENJOINED
from awarding a task order under the RFQ at issue in this protest or allowing any
contractor to perform under any task order under the RFQ at issue in this protest until a
price realism analysis, technical expertise evaluation, and best value trade-off analysis
are performed in a manner that is not inconsistent with this opinion; and
3. The Clerk shall ENTER final judgement accordingly.
IT IS SO ORDERED.
s/ Zachary N. Somers
ZACHARY N. SOMERS
Judge
26