Opinion

Severin v. United States

  • 99 Ct. Cl. 435
  • 1943 U.S. Ct. Cl. LEXIS 65
  • 1943 WL 4198
Court
United States Court of Claims
Filed
May 3, 1943
Status
Published
Author
Whaley
On the bench
Jones, Littleton, Madden, Took, Whaley, Whitaker
Cited by
135 cases
Authority
More cited than 12.6%

holding that, if contractor is liable to sub, “that liability, though not yet satisfied by payment, might well constitute actual damages to [the contractor], and sustain their suit” under rule that contractor may only sue to recover its own damages

How later courts described this case

  • holding that, if contractor is liable to sub, “that liability, though not yet satisfied by payment, might well constitute actual damages to [the contractor], and sustain their suit” under rule that contractor may only sue to recover its own damages
  • holding that, if contractor is hable to sub, ‘that liability, though not yet satisfied by payment, might well constitute actual damages to [the contractor], and sustain their suit’ under rule that contractor may only sue to recover its own damages
  • holding that in a breach of contract claim against the federal government, a prime contractor may recover damages on behalf of its subcontractor only if the prime contractor suffered actual damages
  • holding that a prime contractor cannot recover on behalf of subcontractor to whom prime contractor is not independently liable

Written by the judges who cited it.

The opinion

Whaley, Chief Justice,

dissenting:

I cannot agree with the majority opinion.

There is no legal or equitable assignment involved. This is an action by a contractor to recover damages suffered by himself and his subcontractor, occasioned by the delay of the defendant. It is admitted that defendant’s delay caused damages to both the contractor and the subcontractor. The plaintiff failed to prove the amount of his own damages but the damages suffered by the subcontractor were established by clear proof. The majority opinion admits that the subcontractor was damaged in the amount of $737.10 by allowing overhead on this amount to plaintiff.

For fifty years it has been the settled doctrine of this court that a contractor could bring suit for himself and his subcontractor for losses occasioned by delay by the defendant before payment was made to the subcontractor. In innumerable cases from Stout, Hall & Bangs v. United States, 27 C. Cls. 385 , to Consolidated Engineering Company, No. 43159, decided February 1, 1943 ( 98 C. Cls. 256 ), this doctrine has been uniformly followed and never been questioned.

We must bear in mind that general contractors usually sublet specialized work like plumbing and electrical installations to subcontractors. The effect of the majority opinion would be to compel such subcontractors, and they are legion in numbers, to sue in their own names, which they could not do for lack of privity with the United States. This anomalous situation has never been recognized by this court in all *445 its history. And the majority opinion cites no case in the Supreme Court in which subcontractors have been held to be assignors of claims against the United States, merely because they were unfortunate enough to be subcontractors.

The subcontractor of plaintiff agreed in his contract not to hold the contractor for “loss, damage, detention or delay caused by the owner.”

The contractor is the plaintiff in this action. The subcontractor is not suing the contractor or the defendant. Plaintiff is suing for himself and his subcontractor for an admitted loss. The. defendant was not a party to the subcontract. No consideration has been paid by the defendant for the protection given the contractor in the subcontract and without it the defendant cannot avail itself of this defense.

In my judgment it is a travesty of justice to allow plaintiff overhead on the losses suffered by his subcontractor and to deny recovery to plaintiff for his subcontractor of the amount admittedly due him from the defendant, which any court of equity would require the contractor to pay over to his subcontractor after payment to him by the defendant.

I think plaintiff is entitled to recover $810.81.

Jones, Judge, took no part in the decision of this case.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.