Opinion

WSP USA Solutions Inc.

Court
Armed Services Board of Contract Appeals
Filed
Oct 13, 2022
Status
Published
On the bench
Woodrow
Cited by
0 cases
Authority
More cited than 9.5%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

WSP USA Solutions Inc. ) ASBCA No. 62674

)

Under Contract No. W911WN-15-D-0001 )

APPEARANCES FOR THE APPELLANT: David M. Nadler, Esq.

Scott Arnold, Esq.

Carolyn R. Cody-Jones, Esq.

Blank Rome LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Richard J. Sprunk, Esq.

Olivia J. Estay, Esq.

Thomas X. McHugh, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Pittsburgh

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal involves a contract for WSP USA Solutions Inc. (WSP) to provide

the U.S. Army Corps of Engineers (USACE) with temporary emergency power services

required for declared federal disasters. Specifically, the appeal arises from work

performed under three task orders (TOs) issued in response to Hurricanes Irma and

Maria to provide emergency power services in Puerto Rico and the U.S. Virgin Islands

(USVI). WSP argues that work performed pursuant to these TOs during the contract’s

third option year should have been priced at the contract’s higher rates for that option

year, and not at the rates for the second option year, during which all three TOs were

issued. WSP alleges that USACE’s failure to pay it at Option Year 3 rates for this work

constituted breaches of both the contract and the implied covenant of good faith and fair

dealing. USACE asserts that WSP was appropriately paid for its services pursuant to

the agreed upon Option Year 2 rates. The Board has jurisdiction over this appeal

pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. Both parties

elected to submit this appeal on the record pursuant to Board Rule 11 and requested that

the Board decide both entitlement and quantum.

We hold that the contract unambiguously provides that the pricing for each TO is

set when the order is placed and remains in place for duration of the work under the

TO, even if the period of performance extends beyond the original term of the

underlying contract or option period. Therefore, we deny the appeal.

FINDINGS OF FACT

1. On October 22, 2014, USACE awarded Contract No. W911WN-15-D-0001

(the contract) to WSP to provide temporary emergency power services required for

declared federal disasters (R4, tab 2 at 12-13, 27). ∗

2. The contract was an indefinite quantity indefinite delivery contract with a

base period of one year and four option years (R4, tab 2 at 13-22). The contract’s

initial total contract price was $94,985,000.00 (id. at 13).

3. Section B of the contract included two firm-fixed price contract line item

numbers (CLINs) for the base year and for each option year: (i) ACI Emergency

Power, and (ii) Readiness and Preparedness (R4, tab 2 at 13-22). The ACI Emergency

Power CLINs covered:

ALL LABOR, TRANSPORTATION, EQUIPMENT,

MATERIALS SUPERVISION, AND REQUIRED

INTERNAL LOGISTIC SUPPORT TO PERFORM

GENERATOR SET ACTIVITIES . . . .

(Id. at 13, 15, 17, 19, 21)

4. The base year and the four option years were scheduled as follows:

Base Year: October 22, 2014 – October 21, 2015

Option Year 1: October 22, 2015 – October 21, 2016

Option Year 2: October 22, 2016 – October 21, 2017

Option Year 3: October 22, 2017 – October 21, 2018

Option Year 4: October 22, 2018 – October 21, 2019

(R4, tab 2 at 62-63)

5. Generally, the contract required WPS to mobilize its employees and

government-supplied generators in response to federal disaster declarations. The

contract called for three distinct phases of work: Mission Readiness, Mission

Mobilization, and Mission Execution. (R4, tab 2 at 27)

∗

The parties numbered pages in their Rule 4 submissions with a prefix of letters and/or

leading zeros. We have dropped the prefix and leading zeros and just cite the

numeric page number.

2

6. The contract provided for pricing schedules in the base and option years that

identified the line items being ordered and the rate to be paid for those items. The rate

schedule for each option year (Attachment 1) had corresponding rate increases over

the life of the contract. (R4, tab 2 at 91-95) The contract stated:

THE CONTRACTOR SHALL PROVIDE PRICING IN

ACCORDANCE WITH THE NARRATIVE IN SECTION

B AND THE CORRESPONDING RATE SCHEDULE

INCLUDED AS ATTACHMENT 1, WHICH WILL BE

INCLUDED IN THE CONTRACT.

(Id. at 13)

7. Attachment 1 included an approximately three percent increase in the rates

for each successive option year for each line item of labor, equipment, and parts for

servicing generators (R4, tab 2 at 91-95).

8. Section F of the contract included a chart entitled “Delivery Information”

that listed each CLIN next to a range of delivery dates. These delivery dates

corresponded with the contract’s base and option year periods. (R4, tab 2 at 62-63)

9. The contract incorporated by reference Federal Acquisition Regulation

(FAR) 52.243-1 Alt I, CHANGES – FIXED PRICE (AUG 1987) – Alternate I

(Changes Clause) (R4, tab 2 at 68). The Changes Clause provided:

(a) The Contracting Officer may at any time, by written

order, and without notice to the sureties, if any, make

changes within the general scope of this contract in any

one or more of the following:

(1) Drawings, designs, or specifications when the supplies

to be furnished are to be specially manufactured for the

Government in accordance with the drawings, designs, or

specifications.

(2) Method of shipment or packing.

(3) Place of delivery.

(b) If any such change causes an increase or decrease in the

cost of, or the time required for, performance of any part of

the work under this contract, whether or not changed by

the order, the Contracting Officer shall make an equitable

adjustment in the contract price, the delivery schedule, or

both, and shall modify the contract.

3

(c) The Contractor must assert its right to an adjustment

under this clause within 30 days from the date of receipt of

the written order. However, if the Contracting Officer

decides that the facts justify it, the Contracting Officer may

receive and act upon a proposal submitted before final

payment of the contract.

(d) If the Contractor's proposal includes the cost of

property made obsolete or excess by the change, the

Contracting Officer shall have the right to prescribe the

manner of the disposition of the property.

(e) Failure to agree to any adjustment shall be a dispute

under the Disputes clause. However, nothing in this clause

shall excuse the Contractor from proceeding with the

contract as changed.

FAR 52.243-1 Alt I.

10. The contract included FAR 52.216-18, ORDERING (OCT 1995) (Ordering

Clause). This clause provided:

(a) Any supplies and services to be furnished under this

contract shall be ordered by issuance of delivery orders or

task orders by the individuals or activities designated in the

Schedule. Such orders may be issued from date of contract

award through expiration date of the base contract year

unless extended in accordance with FAR Clause 52.217-9

“Option to Extend the Term of the Contract”.

(b) All delivery orders or task orders are subject to the

terms and conditions of this contract. In the event of

conflict between a delivery order or task order and this

contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered

"issued" when the Government deposits the order in the

mail. Orders may be issued orally, by facsimile, or by

electronic commerce methods only if authorized in the

Schedule.

(R4, tab 2 at 69)

11. The contract included FAR 52.216-21, REQUIREMENTS (OCT 1995)

(Requirements Clause). This clause provided:

4

(a) This is a requirements contract for the supplies or

services specified, and effective for the period stated, in the

Schedule. The quantities of supplies or services specified

in the Schedule are estimates only and are not purchased

by this contract. Except as this contract may otherwise

provide, if the Government's requirements do not result in

orders in the quantities described as "estimated'' or

"maximum" in the Schedule, that fact shall not constitute

the basis for an equitable price adjustment.

(b) Delivery or performance shall be made only as

authorized by orders issued in accordance with the

Ordering clause. Subject to any limitations in the Order

Limitations clause or elsewhere in this contract, the

Contractor shall furnish to the Government all supplies or

services specified in the Schedule and called for by orders

issued in accordance with the Ordering clause. The

Government may issue orders requiring delivery to

multiple destinations or performance at multiple locations.

(c) Except as this contract otherwise provides, the

Government shall order from the Contractor all the

supplies or services specified in the Schedule that are

required to be purchased by the Government activity or

activities specified in the Schedule.

(d) The Government is not required to purchase from the

Contractor requirements in excess of any limit on total

orders under this contract.

(e) If the Government urgently requires delivery of any

quantity of an item before the earliest date that delivery

may be specified under this contract, and if the Contractor

will not accept an order providing for the accelerated

delivery, the Government may acquire the urgently

required goods or services from another source.

(f) Any order issued during the effective period of this

contract and not completed within that period shall be

completed by the Contractor within the time specified in

the order. The contract shall govern the Contractor's and

Government's rights and obligations with respect to that

order to the same extent as if the order were completed

during the contract's effective period; provided, that the

Contractor shall not be required to make any deliveries

under this contract after the last established final delivery

date of any task order.

5

(R4, tab 2 at 69-70)

12. The contract included FAR 52.216-19, ORDER LIMITATIONS (OCT 1995)

(Order Limitations Clause). This clause provided:

(a) Minimum order. When the Government requires

supplies or services covered by this contract in an amount

of less than $1,000.00, the Government is not obligated to

purchase, nor is the Contractor obligated to furnish, those

supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to

honor:

(1) Any order for a single item in excess of

$15,000,000.00 for ACI Emergency Power and

$15,000.00 for Readiness and Preparedness;

(2) Any order for a combination of items in excess of

$95,000,000.00 for ACI Emergency Power and

$15,000.00 for Readiness and Preparedness;

(3) A series of orders from the same ordering office within

30 days that together call for quantities exceeding the

limitation in subparagraph (1) or (2) above.

(c) If this is a requirements contract (i.e., includes the

Requirements clause at subsection 52.216-21 of the

Federal Acquisition Regulation (FAR)), the Government is

not required to order a part of any one requirement from

the Contractor if that requirement exceeds the maximum-

order limitations in paragraph (b) above.

(d) Notwithstanding paragraphs (b) and (c) above, the

Contractor shall honor any order exceeding the maximum

order limitations in paragraph (b), unless that order

(or orders) is returned to the ordering office within one day

after issuance, with written notice stating the

Contractor's intent not to ship the item (or items) called for

and the reasons. Upon receiving this notice, the

Government may acquire the supplies or services from

another source.

(R4, tab 2 at 69)

13. USACE exercised the contract’s first option year on August 28, 2015. This

option was effective from October 22, 2015 through October 21, 2016. (R4, tab 4

at 300)

6

14. USACE exercised the contract’s second option year on September 14,

2016. This option was effective from October 22, 2016 through October 21, 2017.

(R4, tab 6 at 314, 326-27)

15. USACE exercised the contract’s third option year on August 16, 2017.

This option was effective from October 22, 2017 through October 21, 2018. (R4, tab 8

at 328, 333-34)

16. On or about September 6, 2017, Hurricane Irma caused widespread damage

in USVI and Puerto Rico (gov’t br. ¶ 20). On or about September 20, 2017, Hurricane

Maria made landfall in USVI as a Category 5 storm and in Puerto Rico as a

Category 4 storm (id. ¶ 21; R4, tab G-18 at 16516). Hurricane Irma caused extensive

damage to USVI and Puerto Rico’s electrical grids, and then Hurricane Maria

completely destroyed both grids, causing a total power loss. (R4, tab G-18 at 16516)

17. In response to these disasters, on September 20, 2017, USACE issued

TO W911WN17F3031 (3031) at a price of $444,854.24 to provide emergency power

services in Puerto Rico (R4, tab 18 at 376-77). This TO was modified 23 times

between September 22, 2017 and September 18, 2018 to increase funding and/or to

extend the mission (R4, tabs 19-41).

18. On September 25, 2017, USACE issued TO W911WN17F3033 (3033) at a

price of $5,244,301.09 to provide temporary emergency power services in USVI until

October 9, 2017 (R4, tab 44 at 454-55). This TO was modified nine times between

October 6, 2017 and February 15, 2018 to increase funding and/or extend the mission

(R4, tabs 45-53).

19. On October 6, 2017, USACE issued TO W911WN18F3001 (3001) at a

price of $300,000.00 to provide emergency power services in Puerto Rico until

October 14, 2017 (R4, tab 55). TO 3001’s initial funding was erroneously obligated to

CLIN 3001 but was moved to CLIN 2001 via Unilateral Modification No. P00001 on

October 10, 2017 (R4, tab 56). TO 3001 was modified nine times between

October 11, 2017 and March 19, 2018 to increase funding and/or to extend the mission

(R4, tabs 57-65).

20. In mid-October 2017, USACE realized that substantial additional funding

would be necessary to complete the missions in USVI and Puerto Rico under the

contract due to the extensive hurricane damage. (R4, tab G-24 (Kaufmann dep.)

at 16605-06). USACE accordingly contacted the chain of command to seek a

justification to increase the contract’s capacity. (Id. at 16606)

21. On November 15, 2017, USACE executed a Justification Review for Other

than Full and Open Competition (J&A) (R4, tab G-19; app. supp. R4, tab A-8).

7

22. On November 17, 2017, in connection with the J&A, USACE issued a

Determination and Findings Award of a Single-Source Task Order Contract in Excess

of $112 Million for Advanced Contract Initiative Temporary Emergency Power (D&F)

to facilitate approval of the funding increase (R4, tab G-18).

23. On November 22, 2017, in connection with the J&A and the D&F, USACE

issued a modification increasing the contract’s ceiling from $95 million to

$955 million. The modification stated that “[a]ll other terms and conditions remain

unchanged.” (R4, tab 13 at 363)

24. On September 28, 2018, WSP submitted a request for equitable adjustment

(REA) to USACE in the amount of $13,489,630.00 (R4, tab 149 at 15126). This REA

sought an adjustment to prices for performance under TOs 3031, 3033, and 3001 that

took place during Option Year 3 of the contract. (Id.) The amount reflected what

WSP claimed to be the difference between the applicable Option Year 3 rates and the

Option 2 rates it had previously invoiced. (Id.)

25. On February 20, 2019, WSP updated its REA to account for additional

work performed between August 29, 2018 and the end of the mission on November

20, ¶ 2018 (R4, tab 150 at 15130). This amended REA requested a total payment of

$14,220,817.00. (Id.)

26. On May 17, 2019, USACE’s contracting officer (CO) denied WSP’s REA

in its entirety (R4, tab 153 at 15140-41). In denying the REA, the USACE’s CO

asserted that the Option Year 2 rates applied to all work WSP performed under the

relevant TOs—regardless of when the work was performed—because the TOs were

executed during Option Year 2 (id. at 15140).

27. On March 16, 2020, WSP submitted a certified claim to the CO in the

amount of $14,069,044.60 (R4, tab 154 at 15144). This amount reflected the

difference between Option Year 2 rates invoiced during contract performance and

Option Year 3 rates. WSP alleged it was owed for services rendered during Option

Year 3 to the end of the mission (id. at 15144-45).

28. On July 1, 2020, the CO issued a final decision denying WSP’s claim in

its entirety (R4, tab 1).

29. On September 24, 2020, WSP filed this appeal with the Board.

8

DECISION

The Parties’ Contentions

WSP argues that the contract’s language provided that Option Year 3 rates

applied to work performed during Option Year 3, and thus it should have been paid

Option Year 3 rates for work performed during Option Year 3 under the relevant TOs

(app. br. at 2). WSP alleges that USACE’s failure to pay at Option Year 3 rates for

this work constituted breaches of both the contract and the implied covenant of good

faith and fair dealing. (Id.). USACE asserts that Option Year 2 prices applied to all

work performed under these TOs because the TOs were issued during Option Year

2 (gov’t br. at 28-31) and that WSP failed to timely assert its right to an adjustment

under the Changes Clause (id. at 31-36).

Standard of Review

Board Rule 11 allows the parties to waive a hearing and instead have the Board

issue a decision based on the record. ASBCA Rule 11(a). “Unlike a motion for

summary judgment, which must be adjudicated on the basis of a set of undisputed

facts, pursuant to Board Rule 11, the Board ‘may make findings of fact on disputed

facts.’” U.S. Coating Specialties & Supplies, LLC, ASBCA No. 58245, 20-1 BCA

¶ 37,702 at 183,031 (citing Grumman Aerospace Corp., ASBCA No. 35185, 92-3

BCA ¶ 25,059 at 124,886 n.13). As the proponent of the claim, WSP bears the burden

of proving liability and damages in this appeal. Stobil Enter., ASBCA Nos. 61688,

61689, 19-1 BCA ¶ 37,400 at 181,809 (citing Wilner v. United States, 24 F.3d 1397,

1401-02 (Fed. Cir. 1994)).

The Contract Supports USACE’s Interpretation

WSP argues that the contract unambiguously required USACE to pay it

at Option Year 3 rates for work performed during Option Year 3 and that

USACE’s failure to do so constituted a breach of the contract (app. br. at 20-27; app.

reply at 2-7). USACE contends that the contract’s terms do not support

WSP’s interpretation and that it properly compensated WSP at Option Year 2 rates

(gov’t br. at 28-31).

Contract terms must be interpreted and read as a whole, giving reasonable

meaning to all of their parts, and without leaving “a portion of the contract useless,

inexplicable, void, or superfluous.” NVT Techs., Inc. v. United States, 370 F.3d 1153,

1159 (Fed. Cir. 2004). The Board must look to the contract’s plain language to

determine whether an ambiguity exists. Am. Int’l Contractors, Inc., ASBCA

No. 60948, 18-1 BCA ¶ 37,061 at 180,411. A contract is ambiguous if it is reasonably

susceptible to more than one interpretation. Edward R. Marden Corp. v. United States,

9

803 F.2d 701, 705 (Fed. Cir. 1986). It is not enough that the parties differ in their

respective interpretations of the contract’s terms for an ambiguity to exist. Metric

Constructors, Inc. v. Nat’l Aeronautics and Space Admin., 169 F.3d 747, 751 (Fed.

Cir. 1999). Rather, each party’s interpretation must fall within a “zone of

reasonableness.” Id.; see also WPC Enters., Inc. v. United States, 323 F.2d 874,

876 (Ct. Cl. 1963). If the contract’s terms are clear and unambiguous, they must be

given their plain and ordinary meaning. Alaska Lumber & Pulp Co. v. Madigan,

2 F.3d 389, 392 (Fed. Cir. 1993). The Board may not use extrinsic evidence to

“introduce an ambiguity where none exists.” Interwest Constr. v. Brown, 29 F.3d 611,

615 (Fed. Cir. 1994); see also Am. Int’l Contractors Inc., 18-1 BCA ¶ 37,061

at 180,411.

WSP argues that the contract unambiguously tied the rates that USACE was

obligated to pay it to the periods of performance during which the work under the

contract was performed (app. br. at 23). Regarding the rates for each period of

performance, the contract states:

THE CONTRACTOR SHALL PROVIDE PRICING IN

ACCORDANCE WITH THE NARRATIVE IN SECTION B

AND THE CORRESPONDING RATE SCHEDULE

INCLUDED AS ATTACHMENT 1, WHICH WILL BE

INCLUDED IN THE CONTRACT.

(Finding 6) (emphasis added) According to WSP, because Attachment 1 set forth

firm-fixed labor rates for each period of performance, the rates were tied to the period

of performance during which the work was completed, and not when the relevant TO

was issued. Additionally, WPS asserts that the delivery dates in the “Delivery

Information” chart in Section F of the contract listed each CLIN next to a delivery

date, unambiguously tie each CLIN to a specific period of performance (app. br.

at 22). Furthermore, because none of the TOs relevant to this appeal modified

Attachment 1 nor amended the contractual rates applicable to work performed during

the base year and each option year, when USACE exercised Option Year 3, WSP

contends that USACE became obligated to pay WSP at Option Year 3 rates for work

performed during that option year (id. at 24).

In contrast, USACE contends that the contract’s periods of performance defined

the ordering periods during which it could place orders and the pricing that

corresponded to these orders (gov’t br. at 29). In other words, USACE asserts that

WSP’s obligations and right to payment were set when it issued the TOs and continued

to be governed by Option Year 2’s terms regardless of the fact that performance of

TOs 3031, 3033, and 3001 carried over into Option Year 3’s calendar period (id.

at 30).

10

According to the USACE’s interpretation of the contract, at the time it issued

the TOs in question, the only CLIN available was 2001, and therefore Option

Year 2 pricing was properly applied to these TOs and all subsequent modifications to

the TOs (id. at 29). In support of its interpretation, USACE cites the Ordering Clause,

which states that a TO “may be issued from the execution of the contract through the

expiration of the base contract year unless extended . . . .” (finding 10). USACE

contends that, because the contract was extended, it follows that it could have placed a

TO up to and including the final day of Option Year 2 (gov’t br. at 29). Furthermore,

USACE argues that the performance period for TOs issued during Option Year 2 was

governed by the Requirements clause (id.), which stated in part:

(f) Any order issued during the effective period of this

contract and not completed within that period shall be

completed by the Contractor within the time specified in

the order. The contract shall govern the Contractor’s and

Government’s rights and obligations with respect to that

order to the same extent as if the order were completed

during the contract’s effective period . . . .

(Finding 11) (emphasis added) Because the relevant TOs were not completed within

Option Year 2’s effective period, USACE reasons, they were intended to be completed

within the timeframe specified within each TO (gov’t br. at 30).

We agree. The FAR 52.216-21 Requirements clause states that the rights and

obligations of the parties (e.g., pricing) are established at the time the task order is

placed and that those obligations remained fixed for the duration of the work required

under that order. This is true even if the work under the task order continues beyond

the effective date of the underlying contract.

Additional support for the government’s position can be found in FAR

¶ 16.505(a)(2) (Ordering), which provides:

(2) Individual orders shall clearly describe all services to

be performed or supplies to be delivered so the full cost or

price for the performance of the work can be established

when the order is placed. Orders shall be within the scope,

issued within the period of performance, and be within the

maximum value of the contract.

This means that the pricing for each TO is set when the order is placed. When read in

conjunction with the requirements clause at FAR 52.216-21, this clarifies that the

pricing for a TO is set when the order is placed and remains in place for duration of the

work under the TO, even if the period of performance extends beyond the original

11

term of the underlying contract or option period. Thus, even if the government

exercises the subsequent option period after placing a TO, it does not affect the pricing

of the work being performed pursuant to the TO. In our view, this provision is

intended to eliminate the very confusion raised by appellant’s arguments in this

appeal.

Additional support for our interpretation is found in Securityhunter, Inc.,

ASBCA No. 60896, 18-1 BCA ¶ 36,981 at 180,135. In Securityhunter, the contractor

sought to be released from performance on the grounds that its obligation to complete

performance of work under a task order ended when the order and base contract

periods of performance expired. The Board found otherwise, holding that the

obligation to perform did not automatically disappear upon expiration of the

contract’s period of performance. The Board reasoned that “[r]elieving Securityhunter

of its contractual obligations to complete that work merely because it failed to perform

on time would render the contract illusory and void.” Id. at 180,137. As the Board

noted, this is true even when the government may have been responsible for delaying

performance – in that situation, the contractor generally is obligated to perform after

the impairment is removed. Id. (Citing Consolidated Molded Prods. Corp. v. United

States, 600 F.2d 793 (Ct. Cl. 1979)).

In this appeal, USACE exercised Option Year 3 on August 16, 2017, prior to

issuing the TOs at issue (finding 15). USACE subsequently issued the TOs shortly

before the end of Option Year 2 (finding 17-19). However, even if USACE had not

exercised the third option year, WPS would still have been obligated to continue

performance of the task orders until complete. Moreover, because USACE issued the

TOs during Option Year 2, the pricing for the TOs was based upon the Option Year

2 price schedule. Indeed, had USACE not exercised Option Year 3, there would have

been no reason to consider whether to apply the Option Year 3 pricing schedule. In

sum, the obligation to perform, and the pricing associated with that performance, is

established upon the date the task order is placed.

USACE Did Not Breach The Implied Warranty of Good Faith and Fair Dealing

Additionally, WSP argues that USACE breached the implied warranty of good

faith and fair dealing by failing to pay it at Option Year 3 rates for work performed

during Option Year 3 (app. br. at 27-30; app. reply at 12-13). “The covenant of good

faith and fair dealing is an implied duty that each party to a contract owes to

its contracting partner.” Centex Corp. v. United States, 395 F.3d 1283, 1304 (Fed. Cir.

2005). The covenant imposes obligations on both contracting parties that include the

“duty not to interfere with the other party’s performance and not to act so as to destroy

the reasonable expectations of the other party regarding the fruits of the contract.” Id.

This duty applies to the government just as it does to private parties. Id. Failure to

12

fulfil the implied covenant of good faith and fair dealing constitutes a breach of the

contract. Metcalf Constr. Co., Inc. v. United States, 742 F.3d 984, 990 (Fed. Cir. 2014).

Because we have found that the contract did not obligate USACE to pay WSP

at Option Year 3 rates, we need not reach whether the failure to do so breached the

implied warranty of good faith and fair dealing. A party to a contract cannot use an

implied duty of good faith and fair dealing to “expand another party’s contractual

duties beyond those in the express contract or create duties inconsistent with the

contract’s provisions.” Agility Pub. Warehousing Co. v. Mattis, 852 F.3d 1370,

1384 (Fed. Cir. 2017) (quoting Metcalf Constr. Co v. United States, 742 F.3d 984,

991 (Fed. Cir. 2014)). Therefore, because USACE’s actions were consistent with the

contract’s terms, they cannot have breached the implied duty of good faith and fair

dealing.

WSP’s Claim is not Waived

USACE argues that even if WSP interpreted the contract correctly, its claim is

invalid because it failed to timely preserve its rights under the Changes Clause (gov’t

br. at 31-32). Because we uphold USACE’s interpretation of the contract, we need not

address its affirmative defense of waiver.

CONCLUSION

Because the contract unambiguously tied the rates at which USACE was to pay

WSP to the dates the relevant TOs were placed, we hold that USACE did not breach

the contract by failing to pay WSP at Option Year 3 rates for work performed during

Option Year 3 of the contract. Accordingly, we deny the appeal.

Dated: October 13, 2022

KENNETH D. WOODROW

Administrative Judge

Armed Services Board

of Contract Appeals

(Signatures continued)

13

I concur I concur

RICHARD SHACKLEFORD J. REID PROUTY

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 62674, Appeal of WSP

USA Solutions Inc., rendered in conformance with the Board’s Charter.

Dated: October 13, 2022

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

14

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.