Opinion

California State Water Resourc v. Ferc

  • 43 F.4th 920
Court
Court of Appeals for the Ninth Circuit
Filed
Aug 4, 2022
Status
Published
Nature of suit
Agency
Cited by
10 cases
Authority
More cited than 69.8%

explaining the prevalence of this withdrawal-and-submission practice among multiple states “over the last several decades”

How later courts described this case

  • explaining the prevalence of this withdrawal-and-submission practice among multiple states “over the last several decades”
  • explaining one state’s process for conducting its review of an applicant’s certification request
  • describing the withdrawal-and-resubmission practice

Written by the judges who cited it.

The opinion

FOR PUBLICATION

UNITED STATES COURT OF APPEALS

FOR THE NINTH CIRCUIT

CALIFORNIA STATE WATER No. 20-72432

RESOURCES CONTROL BOARD,

Petitioner,

v.

FEDERAL ENERGY REGULATORY

COMMISSION,

Respondent,

NEVADA IRRIGATION DISTRICT,

Intervenor.

SOUTH YUBA RIVER CITIZENS No. 20-72452

LEAGUE; CALIFORNIA SPORTFISHING

PROTECTION ALLIANCE; FRIENDS OF FERC Nos.

THE RIVER; MOTHER LODE CHAPTER 2266-102

OF THE SIERRA CLUB, 2266-118

Petitioners,

v.

FEDERAL ENERGY REGULATORY

COMMISSION,

Respondent,

NEVADA IRRIGATION DISTRICT,

Intervenor.

2 CAL. STATE WATER RES. CONTROL BD. V. FERC

CALIFORNIA STATE WATER No. 20-72782

RESOURCES CONTROL BOARD,

Petitioner,

v.

FEDERAL ENERGY REGULATORY

COMMISSION,

Respondent,

YUBA COUNTY WATER AGENCY,

Respondent-Intervenor.

SOUTH YUBA RIVER CITIZENS No. 20-72800

LEAGUE; CALIFORNIA SPORTFISHING

PROTECTION ALLIANCE; FRIENDS OF FERC No.

THE RIVER; MOTHER LODE CHAPTER 2246-086

OF THE SIERRA CLUB,

Petitioners,

v.

FEDERAL ENERGY REGULATORY

COMMISSION,

Respondent,

YUBA COUNTY WATER AGENCY,

Respondent-Intervenor.

CAL. STATE WATER RES. CONTROL BD. V. FERC 3

CALIFORNIA STATE WATER No. 20-72958

RESOURCES CONTROL BOARD,

Petitioner, FERC Nos.

2179-043

v. 2467-020

2179-048

FEDERAL ENERGY REGULATORY 2467-022

COMMISSION,

Respondent,

MERCED IRRIGATION DISTRICT,

Respondent-Intervenor.

CALIFORNIA SPORTFISHING No. 20-72973

PROTECTION ALLIANCE; FRIENDS OF

THE RIVER; SIERRA CLUB AND ITS FERC No.

TEHIPITE CHAPTER, 2179-043

Petitioners,

v. OPINION

FEDERAL ENERGY REGULATORY

COMMISSION,

Respondent,

MERCED IRRIGATION DISTRICT,

Respondent-Intervenor.

On Petition for Review of an Order of the

Federal Energy Regulatory Commission

Argued and Submitted May 12, 2022

Pasadena, California

4 CAL. STATE WATER RES. CONTROL BD. V. FERC

Filed August 4, 2022

Before: Paul J. Watford and Michelle T. Friedland, Circuit

Judges, and Carol Bagley Amon, * District Judge.

Opinion by Judge Friedland

SUMMARY **

Federal Energy Regulatory Commission

The panel granted petitions for review, and vacated

orders issued by the Federal Energy Regulatory Commission

(“FERC”) in which FERC held that the California Water

Resources Control Board (the “State Board”) had waived its

authority to ensure that certain hydroelectric projects

complied with state water quality standards.

Section 401 of the Clean Water Act requires states to

provide a water quality certification before a federal license

or permit can be issued for activities that may result in any

discharge into intrastate navigable waters. Under Section

401, states may impose conditions on federal licenses for

hydroelectric projects to ensure that those projects comply

with state water quality standards. States must act on a

request for water quality certification within one year of

*

The Honorable Carol Bagley Amon, United States District Judge

for the Eastern District of New York, sitting by designation.

**

This summary constitutes no part of the opinion of the court. It

has been prepared by court staff for the convenience of the reader.

CAL. STATE WATER RES. CONTROL BD. V. FERC 5

receiving it to avoid waiving their Section 401 certification

authority.

In three FERC orders, FERC found that the State Board

had engaged in coordinated schemes with the Nevada

Irrigation District, the Yuba County Water Agency, and the

Merced Irrigation District (“Project Applicants”) to delay

certification and to avoid making a decision on their

certification requests. According to FERC, the State Board

had coordinated with the Project Applicants to ensure that

they withdrew and resubmitted their certification requests

before the State’s deadline for action under Section 401 in

order to reset the State’s one-year period to review the

certification requests. FERC held that, because of that

coordination, the State Board had “fail[ed] or refuse[d] to

act” on requests and therefore had waived its certification

authority under Section 401 of the Clean Water Act. See

33 U.S.C. § 1341(a)(1).

The panel held that FERC’s findings of coordination

were unsupported by substantial evidence. Instead, the

evidence showed only that the State Board acquiesced in the

Project Applicants’ own unilateral decisions to withdraw

and resubmit their applications rather than have them denied.

The panel held that, even assuming that FERC’s

“coordination” standard was consistent with the statute, the

State Board’s mere acquiescence in the Project Applicants’

withdrawals-and-resubmissions could not demonstrate that

the State Board was engaged in a coordinated scheme to

delay certification. Accordingly, FERC’s orders could not

stand. The panel remanded for further proceedings.

6 CAL. STATE WATER RES. CONTROL BD. V. FERC

COUNSEL

Jennifer Kalnins Temple (argued), Adam L. Levitan, Kristin

K. McCarthy and Julia K. Forgie, Deputy Attorneys

General; Eric M. Katz, Supervising Deputy Attorney

General; Robert W. Byrne, Senior Assistant Attorney

General; Rob Bonta, Attorney General; Office of the

Attorney General, Los Angeles, California; for Petitioner

California State Water Resources Control Board.

Julie Gantenbein (argued), Water and Power Law Group PC,

Berkeley, California; Andrew M. Hawley, Western

Environmental Law Center, Seattle, Washington; for

Petitioners South Yuba River Citizens League, California

Sportfishing Protection Alliance, Friends of the River, and

Sierra Club and its Mother Lode and Tehipite Chapters.

Jared B. Fish (argued), Attorney; Robert H. Solomon,

Solicitor; Matthew R. Christiansen, General Counsel;

Federal Energy Regulatory Commission, Washington D.C.;

for Respondent Federal Energy Regulatory Commission.

Michael A. Swiger (argued), Michael F. McBride, and Ani

Esenyan, Van Ness Feldman, LLP, Washington, D.C.; for

Respondent-Intervenors Nevada Irrigation District and Yuba

County Water Agency.

Thomas M. Berliner and Jolie-Anne S. Ansley, Duane

Morris LLP, San Francisco, California; Phillip R.

McMurray, General Counsel, Merced Irrigation District,

Merced, California; for Respondent-Intervenor Merced

Irrigation District.

Jonathan D. Brightbill and Lauren Gailey, Winston &

Strawn LLP, Washington, D.C.; Andrew R. Varcoe and

CAL. STATE WATER RES. CONTROL BD. V. FERC 7

Stephanie A. Maloney, United States Chamber Litigation

Center, Washington, D.C.; for Amicus Curiae Chamber of

Commerce of the United States of America.

Andrea W. Wortzel, Troutman Pepper Hamilton Sanders

LLP, Richmond, Virginia; Charles R. Sensiba and Morgan

M. Gerard, Troutman Pepper Hamilton Sanders LLP,

Washington, D.C.; for Amici Curiae National Hydropower

Association and Northwest Hydroelectric Association.

Gabrielle Gurian and Kelly Thomas Wood, Assistant

Attorneys General; Robert W. Ferguson, Attorney General;

Office of the Attorney General, Olympia, Washington; Jill

Lacedonia, Assistant Attorney General; William Tong,

Attorney General; Office of the Attorney General, Hartford,

Connecticut; Scott W. Boak; Aaron M. Frey, Attorney

General; Office of the Attorney General, Augusta, Maine;

Gillian Wener; Dana Nessel, Attorney General; Office of the

Attorney General, ENRA Division, Lansing, Michigan;

Peter N. Surdo, Special Assistant Attorney General; Keith

Ellison, Attorney General; Office of the Attorney General,

Saint Paul, Minnesota; Kristina Miles, Deputy Attorney

General; Andrew J. Bruck, Acting Attorney General; Office

of the Attorney General, Environmental Permitting and

Counseling, Trenton, New Jersey; William Grantham,

Assistant Attorney General; Hector Balderas, Attorney

General; Office of the Attorney General, Consumer and

Environmental Protection Division, Albuquerque, New

Mexico; Taylor H. Crabtree and Asher P. Spiller, Assistant

Attorneys General; Daniel S. Hirschman, Senior Deputy

Attorney General; Joshua S. Stein, Attorney General;

Department of Justice, Raleigh, North Carolina; Paul

Garrahan, Attorney-in-Charge; Ellen F. Rosenblum,

Attorney General; Natural Resources Section, Department

of Justice, Salem, Oregon; Laura B. Murphy; Thomas J.

8 CAL. STATE WATER RES. CONTROL BD. V. FERC

Donovan, Jr., Attorney General; Office of the Attorney

General, Montpelier, Vermont; Brian R. Caldwell; Karl A.

Racine, Attorney General; Public Advocacy Division,

Washington, D.C.; Turner H. Smith, Deputy Chief; Matthew

Ireland, Assistant Attorney General; Maura Healey,

Attorney General; Office of the Attorney General,

Environmental Protection Division, Boston, Massachusetts;

Donald D. Anderson, Deputy Attorney General; David C.

Grandis, Chief, Environmental Section; Mark R. Herring,

Attorney General; Office of the Attorney General,

Richmond, Virginia; for Amici Curiae States of Washington,

Connecticut, Maine, Michigan, Minnesota, New Jersey,

New Mexico, North Carolina, Oregon, Vermont, the District

of Columbia, and the Commonwealths of Massachusetts and

Virginia.

CAL. STATE WATER RES. CONTROL BD. V. FERC 9

OPINION

FRIEDLAND, Circuit Judge:

Section 401 of the Clean Water Act gives states the

authority to impose conditions on federal licenses for

hydroelectric projects to ensure that those projects comply

with state water quality standards. In these consolidated

cases, we consider several petitions for review of decisions

by the Federal Energy Regulatory Commission (“FERC”)

holding that the California Water Resources Control Board

(the “State Board” or “State Water Board”) waived that

authority for certain hydroelectric projects in federal

relicensing proceedings. FERC found that the State Board

had engaged in coordinated schemes with the Nevada

Irrigation District, the Yuba County Water Agency, and the

Merced Irrigation District (collectively, the “Project

Applicants”) to delay certification and to avoid making a

decision on their certification requests. FERC held that,

because of that coordination, the State Board had “fail[ed] or

refuse[d] to act” on the requests and had therefore waived its

certification authority. See 33 U.S.C. § 1341(a)(1). We hold

that FERC’s findings of coordination are unsupported by

substantial evidence. We therefore grant the petitions for

review and vacate FERC’s orders.

I.

A.

The Clean Water Act provides that “[i]t is the policy of

the Congress to recognize, preserve, and protect the primary

responsibilities and rights of States” to “prevent, reduce, and

eliminate pollution” and to “plan the development and use

(including restoration, preservation, and enhancement) of

land and water resources.” 33 U.S.C. § 1251(b). To achieve

10 CAL. STATE WATER RES. CONTROL BD. V. FERC

those goals, Congress has enacted a scheme of cooperative

federalism that gives states an important role in regulating

water quality. “The states remain, under the Clean Water

Act, the ‘prime bulwark in the effort to abate water

pollution.’” Keating v. FERC, 927 F.2d 616, 622 (D.C. Cir.

1991) (quoting United States v. Puerto Rico, 721 F.2d 832,

838 (1st Cir. 1983)).

As relevant here, Section 401 of the Clean Water Act

“requires States to provide a water quality certification

before a federal license or permit can be issued for activities

that may result in any discharge into intrastate navigable

waters.” PUD No. 1 of Jefferson Cnty. v. Wash. Dep’t of

Ecology, 511 U.S. 700, 707 (1994) (citing 33 U.S.C.

§ 1341). States may adopt water quality standards that are

more stringent than federal law requires, and any limitation

included in the state certification becomes a condition on any

federal license. Id. at 705, 708. That certification process is

“essential in the scheme to preserve state authority to address

the broad range of pollution” that might affect water quality.

S.D. Warren Co. v. Me. Bd. of Env’t Prot., 547 U.S. 370, 386

(2006).

To prevent a state from “indefinitely delaying a federal

licensing proceeding by failing to issue a timely water

quality certification,” Section 401 includes a deadline by

which the state must act to avoid waiving its certification

authority. Alcoa Power Generating Inc. v. FERC, 643 F.3d

963, 972 (D.C. Cir. 2011). The relevant statutory language

reads:

If the State . . . fails or refuses to act on a

request for certification, within a reasonable

period of time (which shall not exceed one

year) after receipt of such request, the

certification requirements of this subsection

CAL. STATE WATER RES. CONTROL BD. V. FERC 11

shall be waived with respect to such Federal

application. No license or permit shall be

granted until the certification required by this

section has been obtained or has been waived

as provided in the preceding sentence. No

license or permit shall be granted if

certification has been denied by the State.

33 U.S.C. § 1341(a)(1). FERC, through regulations

governing hydropower licensing proceedings and through

agency adjudication, has interpreted the “reasonable period

of time” for action under Section 401 to be the statutory

maximum of one year from the receipt of the request.

18 C.F.R. §§ 4.34(b)(5)(iii), 5.23(b)(2); Const. Pipeline Co.,

162 FERC ¶ 61,014, at P 16 (Jan. 11, 2018).

The consequences of a waiver are potentially significant.

Federal licenses for hydroelectric projects can last up to fifty

years, and the default term is forty years. 1 16 U.S.C. § 799;

Policy Statement on Establishing License Terms for

Hydroelectric Projects, 82 Fed. Reg. 49501, 49503 (Oct. 26,

2017). Accordingly, if a state waives its authority to impose

conditions on a hydroelectric project’s federal license

through Section 401’s certification procedure, that project

may be noncompliant with prevailing state water quality

standards for decades.

California’s criteria for issuing water quality

certifications often make it impracticable for a certification

to issue within one year of a project applicant’s submitting

1

If a project’s initial license expires while the relicensing process is

ongoing, FERC may issue annual, interim licenses under the same terms

and conditions as the initial license. 16 U.S.C. § 808(a)(1); 18 C.F.R.

§ 16.18.

12 CAL. STATE WATER RES. CONTROL BD. V. FERC

its request. The main cause of delay appears to be

California’s requirement, pursuant to the California

Environmental Quality Act (“CEQA”), that the State Board

receive and consider an analysis of a project’s environmental

impact before granting a certification request. 2 See Cal. Pub.

Res. Code § 21100(a) (requiring completion of “an

environmental impact report on any project . . . that may

have a significant effect on the environment”); Cal. Code

Regs. tit. 23, § 3856(f) (“[T]he [Section 401] certifying

agency shall be provided with and have ample time to

properly review a final copy of valid CEQA documentation

before taking a certification action.”). California law assigns

a “lead agency” (here, the Project Applicants) to prepare the

CEQA evaluation and designates a “responsible agency”

(here, the State Board) that must “consider[] the [evaluation]

prepared by the lead agency” and decide “whether and how

to approve the project involved.” 3 Cal. Code Regs. tit. 14,

§ 15096(a). For complex projects like the ones at issue here,

2

After FERC issued the waiver orders challenged here, the

California legislature authorized the State Board to issue certifications

before completion of CEQA review where failure to issue the

certification “poses a substantial risk of waiver of the state board’s

certification authority” under Section 401. Cal. Water Code

§ 13160(b)(2); see also 2020 Cal. Stat. 1379. The new provision directs

the State Board, “[t]o the extent authorized by federal law,” to “reserve

authority to reopen and . . . revise the certificate” as necessary after

CEQA review is eventually completed. Cal. Water Code § 13160(b)(2).

Because that amendment took effect after the events at issue here, it has

no bearing on our analysis.

3

In cases like ours, where the project applicant is a public agency,

the project applicant is the “lead agency” that must complete the CEQA

evaluation. By contrast, in cases where the project applicant is a private

entity, the State Board is both the “lead agency” and the “responsible

agency” and, accordingly, must complete the CEQA process itself. See

Cal. Code Regs. tit. 14, § 15051.

CAL. STATE WATER RES. CONTROL BD. V. FERC 13

the CEQA process itself can often take more than a year to

complete. If the materials required for CEQA are not

submitted until late in the State Board’s Section 401 review

period, the State Board is unlikely to be ready to issue a

certification within the one-year deadline. 4 If the project

applicants do not give the State Board a sufficient

opportunity to “receive and properly review the necessary

environmental documentation” under CEQA by the end of

the review period, California regulations require the State

Board to “deny without prejudice certification . . . unless the

applicant in writing withdraws the request for certification.”

Id. tit. 23, § 3836(c).

Because it is often not feasible for a Section 401

certification to issue within one year of its submission, a

practice has developed over the last several decades—in

California and in other states—whereby project applicants

withdraw their requests for certification before the end of the

one-year review period and resubmit them as new requests,

rather than have their original requests denied. The theory

behind this practice is that a withdrawn-and-resubmitted

request starts a new one-year review period, affording the

project applicant more time to comply with procedural and

substantive prerequisites to certification and the state more

time to decide whether and under what conditions it will

grant the certification request. Although FERC expressed

misgivings in some orders that withdrawal-and-

resubmission could lead to delays in federal licensing, FERC

4

FERC used to “deem the one-year waiver period to commence

when the certifying agency found the request acceptable for processing,”

but it has since departed from that interpretation. See California ex rel.

State Water Res. Control Bd. v. FERC, 966 F.2d 1541, 1552 (9th Cir.

1992). Apparently as a result, submitting a Section 401 certification

request in California does not require the project applicant to provide all

the materials that the State Board will eventually need for final approval.

14 CAL. STATE WATER RES. CONTROL BD. V. FERC

accepted the withdrawal-and-resubmission practice for

many years. See, e.g., Barrish & Sorenson Hydroelectric

Co., 68 FERC ¶ 62,161, 64,258 (Aug. 12, 1994) (noting that

the applicant “withdrew and refiled” its Section 401 request

the day before the one-year review deadline); Bradwood

Landing LLC, 126 FERC ¶ 61,035, at P 24 n.26 (Jan. 15,

2009) (observing that the project applicant’s withdrawal-

and-resubmission of its request for certification from the

state of Oregon “restarted the statutory one-year period” for

the state certifying agency); Const. Pipeline Co., 162 FERC

¶ 61,014, at P 23 (Jan. 11, 2018) (“We reiterate that once an

application is withdrawn, no matter how formulaic or

perfunctory the process of withdrawal and resubmission is,

the refiling of an application restarts the one-year waiver

period under section 401(a)(1).”), reh’g denied, 164 FERC

¶ 61,029, at P 17 (July 19, 2018) (reaffirming that

conclusion).

In 2019, however, the D.C. Circuit held that California

and Oregon had waived their certification authority by

entering a formal contract with a project applicant to delay

federal licensing proceedings through the continual

withdrawal-and-resubmission of the applicant’s certification

requests. Hoopa Valley Tribe v. FERC, 913 F.3d 1099

(D.C. Cir. 2019). The court held that the states’ engagement

in a “coordinated withdrawal-and-resubmission scheme”

constituted a “failure” or “refusal” to act under the meaning

of Section 401. Id. at 1104–05. In response to Hoopa

Valley, FERC changed its position. In a series of orders,

including those at issue here, FERC concluded that states

had waived their Section 401 certification authority by

coordinating with project applicants on the withdrawal-and-

resubmission of Section 401 certification requests, even in

the absence of an explicit contractual agreement to do so.

CAL. STATE WATER RES. CONTROL BD. V. FERC 15

B.

These petitions for review challenge three orders issued

by FERC holding that California waived its authority to

issue water quality certifications for the Yuba-Bear Project

(operated by the Nevada Irrigation District 5), the Yuba River

Project (operated by the Yuba County Water Agency), and

the Merced River and Merced Falls Projects (together, the

“Merced Projects”) (operated by the Merced Irrigation

District). We now summarize the relevant facts underlying

each of those three orders.

1.

In 1963, FERC issued the Nevada Irrigation District

(“NID”) a fifty-year license to operate the Yuba-Bear

Hydroelectric Project on the Middle Yuba, South Yuba, and

Bear Rivers, in Sierra, Placer, and Nevada Counties,

California. In 2011, two years before the license expired,

NID applied for a renewal of the license, as required by

statute. The relicensing application is still pending, 6 and

since the original license expired in 2013, NID has operated

the Yuba-Bear Project on interim, annual licenses under the

original license terms. 7 Because FERC licensed the Yuba-

Bear Project before the enactment of Section 401, those

5

The word “Nevada” in Nevada Irrigation District refers to Nevada

County, California.

6

Licensing, Federal Energy Regulatory Commission,

http://www.ferc.gov/licensing (follow hyperlink entitled “Pending

License, Relicense, and Exemption Applications” (updated July 15,

2022)).

7

See supra note 1.

16 CAL. STATE WATER RES. CONTROL BD. V. FERC

interim licenses are not subject to state-imposed conditions

under a Section 401 water quality certification.

On March 15, 2012, NID submitted a request for water

quality certification to the State Board. The request stated

that “NID intends to be the Lead Agency for the purpose of

compliance with the requirements of [CEQA], and will

coordinate with the [State] Board and other responsible

agencies.” The State Board acknowledged receipt of the

request, confirmed that the request met the state’s filing

requirements, and notified NID that the request was pending

before the State Board. The State Board reminded NID that,

“[a]lthough a final CEQA document is not required for [a]

complete application for certification, CEQA requirements

must be satisfied before the State Water Board can issue

certification.”

NID apparently never prepared the CEQA evaluation

required by California regulations. According to a status

report sent by the State Board to FERC, the State Board was

still “[a]waiting commencement of [the] CEQA process by

[NID]” as of December 2019, more than seven years after

NID submitted its initial certification request.

On March 1, 2013—two weeks before the State Board’s

deadline to act on the certification request—NID filed a

letter with the State Board withdrawing and resubmitting its

application for water quality certification. NID reiterated its

intent to act as the lead agency for CEQA purposes. The

State Board acknowledged receipt of the withdrawal-and-

resubmission and stated: “The new deadline for certification

action is February 28, 2014.”

Soon after, FERC issued a draft of its own environmental

impact statement, as required by federal law. The draft noted

NID’s withdrawal-and-resubmission and the State Board’s

CAL. STATE WATER RES. CONTROL BD. V. FERC 17

new February 2014 deadline to act on the certification

request. The State Board submitted comments on the draft,

including both substantive comments on various water

quality concerns and comments attempting to clarify the

expected timeline for a Section 401 certification. The latter

set of comments stated:

The CEQA process has not started, and will

not be finished by the spring of 2014. The

most likely action will be that the Licensees

will withdraw and resubmit their respective

applications for water quality certification

before the one year deadline if the State

Water Board is not ready to issue its water

quality certifications. Otherwise, the State

Board will deny certification without

prejudice.

As noted above, NID never prepared a CEQA evaluation.

Instead, it continued to withdraw and resubmit its

certification request each year, for the five years between

2014 and 2018. In response to each withdrawal-and-

resubmission, the State Board acknowledged receipt and

conveyed the new deadline for certification action.

In 2019, on the day the D.C. Circuit decided Hoopa

Valley, the State Board denied without prejudice NID’s last

request for Section 401 certification. In the letter notifying

NID of the denial, the State Board explained that “[w]ithout

completion of the CEQA process, the State Water Board

cannot issue a certification.” NID then sought a declaratory

order from FERC that the State Board had waived its Section

401 certification authority.

FERC granted NID’s request, holding that the State

Board had waived its certification authority for the Yuba-

18 CAL. STATE WATER RES. CONTROL BD. V. FERC

Bear Project. FERC reasoned that, although Hoopa Valley

had involved a formal contract between the parties to defer

certification and delay federal licensing proceedings, “an

explicit agreement to withdraw and refile is not necessary”

to a finding of waiver. Rather, evidence of a “functional

agreement” or evidence of “the state’s coordination with the

licensee” would suffice to show that the state had “fail[ed]

or refuse[d] to act” under Section 401. Turning to the

evidence in the instant case, FERC first noted that the State

Board had consented to NID’s decision to continually

withdraw and resubmit its certification requests rather than

issue a denial. As evidence of the State Board’s coordination

in a withdrawal-and-resubmission scheme, FERC pointed to

the State Board’s comments on FERC’s draft environmental

impact statement, quoted above, describing the State

Board’s expectation that NID would withdraw and resubmit

its request. FERC also asserted that California regulations

“codify” the withdrawal-and-resubmission practice. Finally,

FERC found it “[t]elling[]” that the State Board had “failed

to dispute NID’s repeated statements” in its withdrawal-and-

resubmission letters that “the Board had all of the

information it needed to act.”

2.

The administrative record underlying FERC’s Yuba

River Project order is similar to the record from the Yuba-

Bear Project. In 1963, FERC issued the Yuba County Water

Agency (“YCWA”) a fifty-year license to operate the Yuba

River Development Project on the Yuba, North Yuba, and

Middle Yuba Rivers in Sierra, Yuba, and Nevada Counties.

YCWA filed an application for a new license in June 2017.

As with the Yuba-Bear Project, the Yuba River Project has

been operating under interim, annual licenses while its

CAL. STATE WATER RES. CONTROL BD. V. FERC 19

relicensing application is pending, and those interim licenses

are not subject to state-imposed Section 401 conditions. 8

On August 24, 2017, YCWA submitted a request for

water quality certification to the State Board and affirmed its

role as the lead agency for CEQA compliance. The State

Board acknowledged receipt of the request and stated that

the deadline for certification action was one year later.

On July 25, 2018, a month before the end of the one-year

review period, a member of the State Board’s staff emailed

YCWA to remind it of the upcoming deadline. The email

stated:

YCWA’s water quality certification action

date for the Yuba River Development Project

(FERC No. 2246) is August 24, 2018. A final

CEQA document for the Project has not been

filed; therefore, the State Water Board cannot

complete the environmental analysis of the

Project that is required for certification.

Please submit a withdraw/resubmit of the

certification application as soon as possible.

Let me know if you have any questions.

YCWA responded that it planned to submit the withdrawal-

and-resubmission letter on August 20. The State Board staff

member replied: “My management usually gets a little antsy

when our action date gets below 3 weeks because a ‘deny

without prejudice’ letter takes time to route to our Executive

8

See supra notes 1 & 6.

20 CAL. STATE WATER RES. CONTROL BD. V. FERC

Director. If possible, please submit the letter by next

Friday.”

On August 3, 2018, YCWA filed a withdrawal-and-

resubmission letter with the State Board, reiterating its intent

to act as the lead agency for CEQA purposes. The State

Board acknowledged receipt of the withdrawal-and-

resubmission letter and stated: “The new deadline for

certification action is August 3, 2019.”

Like NID, YCWA apparently never prepared a CEQA

evaluation. A State Board status report to FERC indicated

that it was still “[a]waiting commencement of [the] CEQA

process by YCWA” in December 2019. After the D.C.

Circuit decided Hoopa Valley, the State Board denied

without prejudice YCWA’s resubmitted request for

certification, relying on YCWA’s failure to begin the CEQA

process. YCWA then sought a declaratory order from FERC

that the State Board had waived its Section 401 certification

authority.

FERC concluded that the State Board had waived its

certification authority for the Yuba River Project, employing

essentially the same reasoning as in its Yuba-Bear Project

order. This time, FERC found evidence of coordination in

the email exchange between the State Board’s staff member

and YCWA, reasoning that YCWA’s “withdrawal and

refiling of its application was in response to the [State]

Board’s request that it do so.” FERC asserted that “[t]he

coordination” demonstrated by that exchange “alone [was]

sufficient evidence that the [State] Board sought the

withdrawal and resubmittal of the Yuba River application to

circumvent the one-year statutory deadline for the state

agency to act.” As in the Yuba-Bear Project order, FERC

also pointed to California’s “codification” of the

withdrawal-and-resubmission practice in its regulations and

CAL. STATE WATER RES. CONTROL BD. V. FERC 21

to the State Board’s failure to “dispute Yuba County’s

statements that . . . the [State] Board had all of the

information it needed to act.”

3.

The administrative record underlying FERC’s Merced

Projects order resembles the administrative records from the

Yuba-Bear and Yuba River Projects. In 1963 and 1969,

respectively, FERC issued licenses to the Merced Irrigation

District (“MID”) to operate the Merced River Hydroelectric

Project for a fifty-year term and to its predecessor licensee,

Pacific Gas and Electric Company (“PG&E”), to operate the

Merced Falls Hydroelectric Project for a forty-five-year

term. The Merced Projects are located on the Merced River

in Merced and Mariposa Counties. As with the Yuba-Bear

and Yuba River Projects, the Merced Projects are currently

operating under interim, annual licenses while relicensing is

pending. 9

On May 20 and May 21, 2014, MID and PG&E10

submitted to the State Board requests for water quality

certifications for the Merced Projects. The State Board

acknowledged receipt of the requests, conveyed the one-year

deadline for action, and warned that, “[i]f the information

necessary for compliance with CEQA is not provided to the

9

See supra notes 1 & 6.

10

PG&E transferred its license for the Merced Falls Project to MID

in 2017, making MID the applicant in the relicensing proceeding before

FERC. For the Merced Falls Project, between the initial certification

request in 2014 and the license transfer in 2017, it was the State Board—

not PG&E—that was the lead agency for the purpose of CEQA

compliance.

22 CAL. STATE WATER RES. CONTROL BD. V. FERC

State Water Board, staff may recommend denial of

certification without prejudice.”

In April 2015, one month before the original one-year

deadline, a State Board member emailed MID to remind it

of the upcoming deadline. The email stated:

Merced Irrigation District’s application for

water quality certification for the Merced

River Hydroelectric Project, FERC Project

No. 2179[,] expires on May 21, 2015. Please

withdraw the [sic] and simultaneously

resubmit an application for water quality

certification prior to May 13, 2015. If you

have any questions regarding this request or

this process, please feel free to contact me.

Please respond by email verifying receipt of

this correspondence.

MID apparently never prepared the CEQA evaluation

required by California regulations—the State Board said in

a status report to FERC that it was still “[a]waiting

commencement of [the CEQA] process” for both Merced

Projects in December 2019. Instead, each year between

2015 and 2018, MID and PG&E withdrew and resubmitted

their water quality certification requests before the

expiration of the State Board’s one-year period of review. In

response, the State Board acknowledged receipt of the

withdrawal-and-resubmission letters, conveyed the new

deadlines for certification action, and warned that failure to

comply with CEQA could result in denial of certification

without prejudice.

After the D.C. Circuit decided Hoopa Valley, the State

Board denied without prejudice MID’s resubmitted requests

for certification, relying on MID’s failure to comply with

CAL. STATE WATER RES. CONTROL BD. V. FERC 23

CEQA. MID then sought a declaratory order from FERC

that the State Board had waived its Section 401 certification

authority.

FERC concluded that the State Board had waived its

certification authority for the Merced Projects, again using

nearly identical reasoning as in its Yuba-Bear Project and

Yuba River Project orders. In particular, FERC pointed to

“the four years of the applicants[’] withdrawing and

resubmitting their applications” and to the April 2015 email

from the State Board staff member to MID as evidence that

the State Board had engaged in a coordinated scheme to

continually reset its one-year deadline and avoid taking

action on the certification request. As in the other orders,

FERC noted that California’s regulations “codify” the

withdrawal-and-resubmission practice and highlighted the

State Board’s failure to “request additional information

regarding the [Section 401 requests.]”

***

In sum, in all three challenged orders, FERC held that

the Project Applicants’ withdrawals-and-resubmissions of

their Section 401 certification requests did not restart the

State Board’s one-year review clock because the State Board

“coordinated” with the Project Applicants in a scheme to

avoid deciding the request within the statutory deadline.

The State Board and various environmental

organizations timely petitioned our court for review of all

three orders.

II.

“We review FERC decisions to determine whether they

are ‘arbitrary, capricious, an abuse of discretion,

24 CAL. STATE WATER RES. CONTROL BD. V. FERC

unsupported by substantial evidence, or not in accordance

with the law.’” California ex rel. Harris v. FERC, 784 F.3d

1267, 1272 (9th Cir. 2015) (quoting Cal. Dep’t of Water Res.

v. FERC, 341 F.3d 906, 910 (9th Cir. 2003)). “[S]ubstantial

evidence constitutes more than a mere scintilla. It means

such relevant evidence as a reasonable mind might accept as

adequate to support a conclusion. If the evidence is

susceptible of more than one rational interpretation, we must

uphold [FERC’s] findings.” Fall River Rural Elec. Coop. v.

FERC, 543 F.3d 519, 525 (9th Cir. 2008) (second alteration

in original) (quoting Bear Lake Watch, Inc. v. FERC, 324

F.3d 1071, 1076 (9th Cir. 2003)). Although we must accept

reasonable inferences drawn by an agency, “[s]ubstantial

evidence cannot be based upon an inference drawn from

facts which are uncertain or speculative and which raise only

a conjecture or a possibility.” Woods v. United States, 724

F.2d 1444, 1451 (9th Cir. 1984).

III.

As noted above, FERC changed its position on

withdrawal-and-resubmission following the D.C. Circuit’s

decision in Hoopa Valley. Hoopa Valley concerned a series

of dams along the Klamath River in California and Oregon

that were operated by PacifiCorp pursuant to a federal

license. 913 F.3d 1099, 1101 (D.C. Cir. 2019). As

PacifiCorp’s license was due to expire, PacifiCorp asked

FERC to relicense the upper dams and decommission the

lower dams. Id. PacifiCorp requested Section 401

certifications from California and Oregon. Id. While those

requests were pending, a consortium of parties—including

PacifiCorp, the two states, and various other interested

groups—entered negotiations to address certain risks

associated with decommissioning the lower dams. Id.

Those negotiations culminated in a formal agreement, in

CAL. STATE WATER RES. CONTROL BD. V. FERC 25

which the states promised that they would not take any

action on the certification requests and PacifiCorp promised

to withdraw and resubmit them annually as necessary to

preserve the states’ certification authority. Id. at 1101–02.

The goal of that arrangement was to pause federal licensing

proceedings until PacifiCorp had satisfied various

preconditions for decommissioning specified in the

agreement, including adopting interim environmental

measures and securing federal funds for the project. Id.

Pursuant to the agreement, PacifiCorp’s water quality

certification requests remained undecided by California and

Oregon even though they “ha[d] been complete and ready

for review for more than a decade.” Id. at 1105.

The Hoopa Valley Tribe, which was not a party to the

contractual agreement and whose reservation is downstream

of the dams, petitioned FERC for a declaratory order that

California and Oregon had waived their Section 401

certification authority. Id. at 1102. FERC declined to find a

waiver, id., in keeping with its long-held position that the

withdrawal-and-resubmission procedure restarted a state’s

one-year review period. The D.C. Circuit disagreed,

concluding that California and Oregon had demonstrated

“deliberate and contractual idleness” by “shelving water

quality certifications” pursuant to the “coordinated

withdrawal-and-resubmission scheme” required by the

parties’ contractual agreement. Id. at 1104–05.

Accordingly, the court held that the states had failed or

refused to act on the certification requests within one year

and had therefore waived their certification authority under

Section 401. Id.

Following Hoopa Valley, FERC began finding waiver in

many cases where project applicants had withdrawn and

resubmitted certification requests. FERC has applied Hoopa

26 CAL. STATE WATER RES. CONTROL BD. V. FERC

Valley not only to cases involving express agreements to

delay certification through withdrawal-and-resubmission,

like the agreement at issue in Hoopa Valley itself, but also to

cases involving what FERC has deemed more informal,

coordinated schemes. E.g., McMahan Hydroelectric, LLC,

168 FERC ¶ 61,185, at P 37 (Sept. 20, 2019), vacated by

N.C. Dep’t of Env’t Quality v. FERC (NCDEQ), 3 F.4th 655

(4th Cir. 2021); Placer Cnty. Water Agency, 167 FERC

¶ 61,056, at P 12 (Apr. 18, 2019).

In defining its standard for waiver, FERC draws a line

between a “coordinated” scheme and a “unilateral”

withdrawal-and-resubmission by the project applicant. In its

brief to our court, FERC takes the position that “an

applicant’s unilateral withdrawal and resubmittal is not

imputed to the State” and therefore does not trigger a waiver.

Ordinarily, FERC acknowledges, “[o]nce an applicant

withdraws a request, it is not clear that the State retains

power to act on it”; the withdrawal of the request removes it

from the state’s consideration, and the resubmission of the

certification request begins a new one-year review period.

Accordingly, where the evidence shows that the state has

merely acquiesced in a project applicant’s own decision to

withdraw and refile—and, especially, where the state would

have no discernible motive for attempting to procure a

withdrawal-and-resubmission—FERC’s position is that the

state has not waived its certification authority. See, e.g.,

Village of Morrisville, 174 FERC ¶ 61,141, at P 22 (Feb. 24,

2021) (“[The Vermont certifying agency’s] mere acceptance

of Morrisville’s requests to withdraw and refile is not

evidence of a functional agreement between the parties with

the motivation to restart the one-year clock.”), modifying on

reh’g 173 FERC ¶ 61,156 (Nov. 19, 2020).

CAL. STATE WATER RES. CONTROL BD. V. FERC 27

By contrast, FERC contends that “where the State

coordinates in an applicant’s withdrawal of its request, the

State has affirmatively ‘fail[ed] or refus[ed] to act’ on it

within one year,” and thus waived its Section 401

certification authority. FERC emphasizes that “it is a State’s

efforts to avoid the one-year deadline by way of withdrawal

and resubmittal that reflect the ‘State’s dalliance or

unreasonable delay.’” (quoting Hoopa Valley, 913 F.3d at

1104). In other words, according to FERC, “the dispositive

factor” is whether the state coordinates with the project

applicant “to afford itself more time to decide a certification

request.” Under that standard, where the state has sought a

withdrawal-and-resubmission for its own purposes—

perhaps, for example, because it lacks an adequate basis to

deny certification but needs more time to craft certification

conditions—the state has engaged in a coordinated scheme

to avoid the one-year deadline for action.

We need not decide whether the coordination standard

FERC advances is consistent with the text of Section 401

because we agree with the State Board and the

environmental organizations that FERC’s findings of

coordination are not supported by substantial evidence in the

record. 11 Instead, the evidence shows only that the State

11

Because the Environmental Protection Agency (“EPA”) is

charged with administering the Clean Water Act, including Section 401,

EPA’s interpretations of the Act, rather than FERC’s, are entitled to

deference under Chevron U.S.A., Inc. v. Nat. Res. Def. Council, Inc., 467

U.S. 837 (1984). Alcoa Power Generating Inc. v. FERC, 643 F.3d 963,

972 (D.C. Cir. 2011). In 2020, after the events at issue here, EPA

promulgated a final rule interpreting the waiver provision in Section 401

for the first time, and EPA has since proposed a new rule that would

revise and replace the 2020 rule. See 40 C.F.R. pt. 121 (codifying Clean

Water Act Section 401 Certification Rule, 85 Fed. Reg. 42210 (July 13,

2020)); Clean Water Act Section 401 Water Quality Certification

28 CAL. STATE WATER RES. CONTROL BD. V. FERC

Board acquiesced in the Project Applicants’ own decisions

to withdraw and resubmit their applications rather than have

them denied. 12

In the Yuba-Bear Project order, FERC relied almost

entirely on comments that the State Board submitted in

response to FERC’s draft environmental impact statement.

As described above, those comments stated: “The CEQA

process has not started . . . . The most likely action will be

that [NID] will withdraw and resubmit . . . . Otherwise, the

State Water Board will deny certification without prejudice.”

From those comments, FERC concluded that NID had not

“acted voluntarily and unilaterally” in withdrawing and

resubmitting its certification request because the State Board

“expected NID to withdraw and refile its application.”

Far from showing that the State Board coordinated a

scheme to delay a decision on certification, the State Board’s

comments (which were not even conveyed directly to NID)

show merely that the State Board predicted that NID would

decide to withdraw and resubmit. The State Board observed

that NID had not started the CEQA process and that, as a

result, “[t]he most likely action” was that NID would

withdraw and resubmit its request. The statement describes

the State Board’s prediction but gives no indication that the

Improvement Rule, 87 Fed. Reg. 35318 (proposed June 9, 2022) (to be

codified at 40 C.F.R. pts. 121, 122, & 124). We need not consider EPA’s

interpretations of Section 401 because they apply only prospectively and

because, in any event, we do not reach the statutory-interpretation issue.

12

Because we vacate FERC’s orders on substantial-evidence

grounds, we also do not reach the State Board’s arguments that FERC’s

“coordination” standard cannot be applied retroactively either under

Chevron Oil Co. v. Huson, 404 U.S. 97 (1971), or under Montgomery

Ward & Co. v. FTC, 691 F.2d 1322 (9th Cir. 1982).

CAL. STATE WATER RES. CONTROL BD. V. FERC 29

State Board was working to engineer that outcome. Indeed,

the State Board went on to say that it was fully prepared to

“deny certification without prejudice” if NID took a different

course. The comments do not suggest that the State Board

was motivated to delay certification by way of withdrawal-

and-resubmission. 13

FERC’s order ignored the import of other evidence in the

record that furnishes crucial context: It was NID that had

failed to comply with CEQA, and thus it was NID—not the

State Board—that apparently had a motive for delay. If,

conversely, NID had complied with its legal obligations

under state law, then statements like those quoted above

might suggest that the State Board was seeking to extend its

own decision-making window by instructing NID to

withdraw and resubmit the application. Here, though, the

comments indicate only that the State Board predicted that

NID would withdraw its application because of NID’s own

failure to comply with CEQA—and that the State Board

would deny the certification request without prejudice if

13

FERC speculates in its brief that the State Board might have

preferred withdrawal-and-resubmission because, unlike a denial without

prejudice, the withdrawal-and-resubmission might not be subject to

judicial review in state court. There is no evidence in the record that the

State Board was motivated to avoid judicial review. And, in any event,

the parties have given us no reason to believe that a state-court challenge

to such a denial would have succeeded, given that the Project Applicants

had not submitted the materials required by CEQA. See Cal. Code Regs.

tit. 23, § 3836(c) (providing that, in the absence of required CEQA

documentation, “the certifying agency shall deny without prejudice

certification for any discharge resulting from the proposed activity”);

Turlock Irrigation Dist., 174 FERC ¶ 61,042, at PP 31-33 (Jan. 19, 2021)

(noting that state law governs the validity of the State Board’s action to

deny certification pursuant to state water quality standards), petition for

review denied by Turlock Irrigation Dist. v. FERC, 36 F.4th 1179 (D.C.

Cir. 2022).

30 CAL. STATE WATER RES. CONTROL BD. V. FERC

NID chose not to withdraw it, as state law would have

required, see Cal. Code Regs. tit. 23, § 3836(c). In short, the

State Board’s comments show only that it consented to

NID’s own decision to withdraw and resubmit its

certification requests.

The evidence supporting FERC’s waiver finding in the

Yuba River Project order is similarly inadequate. FERC

relied almost exclusively on an email exchange between a

member of the State Board’s staff and YCWA, in which the

staff member reminded YCWA that the “final CEQA

document for the Project has not been filed” and asked

YCWA to “[p]lease submit a withdraw/resubmit of the

certification application as soon as possible.” The staff

member noted in a follow-up email that the reason for the

urgency was that “a ‘deny without prejudice’ letter takes

time to route to our Executive Director.”

Considered in context, those emails do not support

FERC’s finding of coordination. Because YCWA had not

complied with CEQA, the State Board could not grant a

Section 401 certification. Cal. Code Regs. tit. 23, § 3836(c).

The staff member’s request that YCWA send a withdrawal-

and-resubmission letter merely reflected his prediction that

YCWA would choose the withdrawal-and-resubmission

path rather than have its certification denied by the Board.

After all, the withdrawal-and-resubmission mechanism had

become a standard practice employed by project applicants

who had not yet complied with CEQA—a practice that both

the State Board and FERC had long accepted. The follow-

up email confirms that understanding. The State Board was

prepared to deny certification but wanted to prepare such a

denial before the deadline if YCWA chose not to withdraw;

from the State Board’s perspective, withdrawal-and-

resubmission and denial without prejudice were functional

CAL. STATE WATER RES. CONTROL BD. V. FERC 31

substitutes that would have had the same practical effect.

Like the State Board’s comments on the Yuba-Bear Project,

the State Board’s communication here shows only that the

State Board acquiesced in YCWA’s own decision to

withdraw its requests.

Finally, in the Merced River Project order, FERC again

relied primarily on a single email from the State Board,

which, for similar reasons, cannot support FERC’s waiver

finding. The email asked that MID “[p]lease withdraw the

[sic] and simultaneously resubmit an application for water

quality certification prior to” the deadline. 14 Once again,

context is critical to understanding the message: MID had

not complied with its obligation to furnish the CEQA

documents required by state law. For that reason, the State

Board anticipated that MID would withdraw and resubmit

its certification request, as was the common practice, and

accepted MID’s decision to do so. Nothing in the record

suggests that the State Board was unprepared to deny the

requests in accordance with state regulations if MID chose

not to withdraw and resubmit, see Cal. Code Regs. tit. 23,

§ 3836(c), or that the State Board had any motive to delay a

certification decision by coordinating a withdrawal-and-

resubmission.

14

As noted above, see supra note 10, the State Board was the lead

CEQA agency for the Merced Falls Project before PG&E transferred its

license to MID. FERC has not offered a similar email or any other

evidence that might support a waiver determination for the Merced Falls

Project; nor has FERC argued that the State Board’s initial role provides

a basis for treating the Merced Falls Project differently from the Merced

River Project. See United States v. Dreyer, 804 F.3d 1266, 1277 (9th

Cir. 2015) (en banc) (“Generally, an appellee waives any argument it

fails to raise in its answering brief.”).

32 CAL. STATE WATER RES. CONTROL BD. V. FERC

Indeed, for all three projects, it seems that the State

Board, unlike the Project Applicants, would have had an

interest in moving along the environmental-review process.

The Project Applicants were operating under interim, annual

licenses that were not subject to state-imposed water quality

conditions. See supra notes 1 & 6. Completing the Section

401 certification process would have allowed the State

Board to impose conditions on any eventual new license.

The evidence shows that, for all three projects, the State

Board was at least actively engaged in relicensing

proceedings by, for example, participating in the pre-

application process to design the necessary environmental

studies, submitting comments on FERC’s draft

environmental analyses, and providing regular status

updates to FERC on pending certification requests. The

Project Applicants, by contrast, stood to benefit from any

delays because a Section 401 certification likely would have

imposed additional environmental-protection measures. See

Turlock Irrigation Dist. v. FERC, 36 F.4th 1179, 1183 n.6

(D.C. Cir. 2022) (noting that applicants operating under

interim, annual licenses have “an incentive to delay” because

their expired, decades-old licenses “presumably include[] far

fewer environmental conditions” than current law requires).

FERC’s remaining evidence is no more persuasive. In

all three orders under review, FERC pointed to the serial

withdrawals-and-resubmissions themselves. But, as

FERC’s own position recognizes, “an applicant’s unilateral

withdrawal and resubmittal is not imputed to the State.”

Even under FERC’s interpretation of the statute, the mere

fact that withdrawals-and-resubmissions occurred cannot

demonstrate that the State Board was engaged in a

coordinated scheme to delay certification.

CAL. STATE WATER RES. CONTROL BD. V. FERC 33

FERC also observed in all three waiver orders that

California’s regulations “codify [the] practice” of

withdrawal-and-resubmission—and, in its brief to our court,

FERC offers those regulations as additional evidence that the

State Board directed the Project Applicants to withdraw their

certification requests. FERC is wrong to describe

California’s regulations as “prescribing withdrawal as a

response to the impending risk of federal waiver.” Those

regulations instead state that, where a project applicant has

failed to comply with CEQA, “the certifying agency shall

deny without prejudice certification for any discharge

resulting from the proposed activity unless the applicant in

writing withdraws the request for certification.” Cal. Code

Regs. tit. 23, § 3836(c) (emphasis added). 15 The most that

can be said about the regulations is that they acknowledge

applicants’ longstanding practice—accepted by FERC for

decades—of withdrawing and resubmitting Section 401

certification requests to avoid having them denied for failure

to comply with state environmental-review requirements.

Finally, all three orders also relied on the State Board’s

alleged failure to dispute statements by the Project

Applicants “that the Board had all of the information it

needed” or to request additional information. FERC’s orders

mischaracterize the record. The State Board never disputed

that the Project Applicants had met the minimum filing

requirements to submit a Section 401 certification request.

But the State Board continually reminded NID, YCWA, and

MID that it did not have the information it would need to

15

As mentioned above, see supra note 2, the California legislature

recently amended state law to permit the State Board to issue a Section

401 certification without a final CEQA evaluation under certain

circumstances. We express no view on how that amendment might

affect the operation of this regulation going forward.

34 CAL. STATE WATER RES. CONTROL BD. V. FERC

grant a request—namely, the CEQA evaluation that

California law required, Cal. Code Regs. tit. 23, § 3856(f).

In short, the records in all three orders under review

demonstrate that the Project Applicants chose to withdraw

and resubmit their certification requests because they had not

complied with California’s CEQA regulations. Without a

complete CEQA evaluation, the State Board was legally

obligated to deny the requests without prejudice, and the

record suggests that the State Board was prepared to do so.

To avoid such a denial, the Project Applicants employed the

common and long-accepted withdrawal-and-resubmission

maneuver, with the State Board’s acquiescence. 16 We note

that, if the Project Applicants had preferred not to undertake

withdrawal-and-resubmission, they could have declined to

do so, forced the State Board to deny their certification

requests, and, if they believed the denials were unwarranted,

challenged them in state court. The Project Applicants chose

16

Although it appears that, from the State Board’s perspective,

withdrawal-and-resubmission and denial without prejudice were

functionally equivalent, the Project Applicants apparently had reasons to

prefer withdrawal-and-resubmission. At oral argument, FERC

suggested that “there are risks that come with a denial” for the applicant,

suggesting that a denial might “affect[] their investor decisions” and

could also “imperil their federal license.” Oral Argument at 33:01-

33:16. The latter concern apparently stems from the fact that a denial

without prejudice might signal to FERC that the project applicant is not

diligently pursuing Section 401 certification—which could constitute

grounds for dismissal of the federal licensing application, see Turlock

Irrigation Dist., 174 FERC ¶ 61,042, at PP 37-38 (Jan. 19, 2021). The

Project Applicants confirmed at oral argument that they preferred to

avoid denials without prejudice: “You say denial without prejudice, but

denial is denial no matter what label you put on it. Then the applicants

would have been in the position of deciding whether they had to appeal

or not, if they didn’t appeal, whether they might be estopped from

appealing in the future.” Oral Argument at 52:50-53:12.

CAL. STATE WATER RES. CONTROL BD. V. FERC 35

not to take that path—and nothing in the record shows that

the State Board encouraged that choice. Under FERC’s own

coordination standard, a state’s mere acceptance of a

withdrawal-and-resubmission is not enough to show that the

state engaged in a coordinated scheme to avoid its statutory

deadline for action. Accordingly, FERC’s orders cannot

stand.

The Fourth Circuit recently reached the same conclusion

in a case with similar facts. See NCDEQ, 3 F.4th 655. In

that case, FERC had also found waiver based on email

correspondence from the certifying agency reminding the

project applicant of the deadline for withdrawal-and-

resubmission. Id. at 662–64. The Fourth Circuit vacated

FERC’s order, concluding that, even “[a]ssuming without

deciding that a State may waive its certification authority

under [Section] 401 by coordinating with an applicant in a

scheme to defeat the statutory review period through a

process of withdrawing and resubmitting the certification

application,” the correspondence between the certifying

agency and the project applicant was not substantial

evidence of coordination. Id. at 676.

We agree with the Fourth Circuit’s observation in

NCDEQ that “it must take more than routine informational

emails to show coordination” because the states’ “rights and

responsibilities to ensure compliance with their own water-

quality standards are too important to be so easily stripped

away.” Id. at 675. Because the default term of a federal

license is forty years, a state’s waiver could result in a

hydroelectric project’s being noncompliant with a state’s

standards for decades. Considering those dramatic

consequences, FERC’s coordination findings cannot rest on

such thin evidence as a simple courtesy email reminding an

applicant of an impending deadline.

36 CAL. STATE WATER RES. CONTROL BD. V. FERC

IV.

For the foregoing reasons, we conclude that FERC’s

orders are not supported by substantial evidence. We

therefore VACATE those orders and REMAND for further

proceedings consistent with this opinion.