Opinion

Mobil Pipe Line Co. v. Federal Energy Regulatory Commission

  • 676 F.3d 1098
  • 400 U.S. App. D.C. 161
  • 180 Oil & Gas Rep. 343
  • 2012 U.S. App. LEXIS 7625
  • 2012 WL 1292564
Court
Court of Appeals for the D.C. Circuit
Filed
Apr 17, 2012
Status
Published
Author
Kavanaugh
On the bench
Sentelle, Griffith, Kavanaugh
Cited by
3 cases
Authority
More cited than 51.4%

relying on "the economic and legal analysis of FERC's expert staff," even though it was not formally binding on the Commission, because the Court found it "so persuasive"

How later courts described this case

  • relying on "the economic and legal analysis of FERC's expert staff," even though it was not formally binding on the Commission, because the Court found it "so persuasive"

Written by the judges who cited it.

The opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 17, 2011 Decided April 17, 2012

No. 11-1021

MOBIL PIPE LINE COMPANY,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION AND UNITED

STATES OF AMERICA,

RESPONDENTS

CANADIAN NATURAL RESOURCES LIMITED, ET AL.,

INTERVENORS

On Petition for Review of an Order of the

Federal Energy Regulatory Commission

Joseph Guerra argued the cause for petitioner. On the

briefs were James F. Bendernagel, Jr., Lorrie M. Marcil,

Christopher M. Lyons, and Eric D. McArthur.

Lona T. Perry, Senior Attorney, Federal Energy

Regulatory Commission, argued the cause for respondents.

With her on the brief were Robert H. Solomon, Solicitor, and

Judith A. Albert, Senior Attorney. Robert J. Wiggers and

John J. Powers, III, Attorneys, U.S. Department of Justice,

entered appearances.

2

Marcus W. Sisk, Jr., Frederick G. Jauss IV, and James H.

Holt were on the brief for intervenors Canadian Natural

Resources Limited, et al. in support of respondents.

Before: SENTELLE, Chief Judge, and GRIFFITH and

KAVANAUGH, Circuit Judges.

Opinion for the Court filed by Circuit Judge

KAVANAUGH.

KAVANAUGH, Circuit Judge: Congress has directed the

Federal Energy Regulatory Commission to ensure that oil

pipeline rates are “just and reasonable.” When the market in

which a pipeline operates is not competitive, the Commission

caps the pipeline’s rates. When the market in which a

pipeline operates is competitive, however, the Commission

generally allows the pipeline to charge market-based rates.

Mobil owns and operates the Pegasus crude oil pipeline,

which runs from Illinois to Texas. The pipeline transports

mostly Western Canadian crude oil. Out of the 2.2 million

barrels of Western Canadian crude oil produced each day,

Pegasus transports only about three percent – about 66,000

barrels each day.

In light of the competitiveness of the Western Canadian

crude oil market and Pegasus’s minor role in it, Mobil applied

to FERC for permission to charge market-based rates on

Pegasus. FERC’s expert staff examined the market and

deemed this case a “slam dunk” for allowing Mobil to charge

market-based rates. But the Commission itself came out the

other way and denied Mobil’s application on the ground that

Pegasus possessed market power.

3

We conclude that the Commission’s decision was

unreasonable in light of the record evidence. The record

shows that producers and shippers of Western Canadian crude

oil have numerous competitive alternatives to Pegasus for

transporting and selling their crude oil. Pegasus does not

possess market power. We grant Mobil’s petition for review,

vacate FERC’s order, and remand to the Commission for

further proceedings consistent with this opinion.

I

A

Congress has directed FERC to ensure that oil pipelines

charge “just and reasonable” rates. 49 U.S.C. app. § 1(5)

(1988); see Frontier Pipeline Co. v. FERC, 452 F.3d 774, 776

(D.C. Cir. 2006).

To implement that command, the Commission regulates

rates via an indexing system. See Revisions to Oil Pipeline

Regulations Pursuant to the Energy Policy Act of 1992 (Order

No. 561), 58 Fed. Reg. 58,753, 58,754 (Nov. 4, 1993). Under

FERC’s indexing system, an oil pipeline must establish an

initial baseline rate with the Commission. 18 C.F.R.

§ 342.1(a). That rate is usually determined by a pipeline’s

cost of providing service, including a reasonable return on

investment. 18 C.F.R. § 342.2; see also 58 Fed. Reg. at

58,758. After FERC accepts a pipeline’s initial baseline rate,

the pipeline may increase that rate up to a ceiling set by the

Commission’s indexing formula. 18 C.F.R. § 342.3. FERC’s

indexing system allows oil pipelines to adjust their rates to

account for inflation, while protecting shippers from large rate

increases. 58 Fed. Reg. at 58,758.

4

But rates set by indexing “do not function well to signal

individuals how to efficiently respond to changes in market

conditions.” Market-Based Ratemaking for Oil Pipelines

(Order No. 572), 59 Fed. Reg. 59,148, 59,150 (Nov. 16,

1994). To address that shortcoming, FERC may authorize

pipelines to charge rates established by market competition

instead of indexing. See 18 C.F.R. §§ 342.4(b), 348.1, 348.2.

Market-based rates “can result in pricing that is both efficient

and just and reasonable.” 59 Fed. Reg. at 59,150.

A pipeline does not have a unilateral right to charge

market-based rates. Rather, in order to charge market-based

rates, a pipeline must obtain approval from the Commission.

See 18 C.F.R. §§ 342.4(b), 348.1, 348.2.

FERC Order No. 572 guides the Commission’s

consideration of applications for market-based rate authority.

59 Fed. Reg. at 59,149. Under Order No. 572, FERC’s

inquiry centers on whether a pipeline possesses market power.

Id. at 59,150. To qualify for market-based rate authority, a

pipeline must demonstrate that it lacks market power in its

product and geographic markets. 18 C.F.R. §§ 342.4(b),

348.1(c)(1), (2). FERC has said that market power is “the

ability profitably to maintain prices above competitive levels

for a significant period of time.” See Department of Justice &

Federal Trade Commission, Horizontal Merger Guidelines

§ 0.1 (rev. ed. 1997); see also Mobil Pipe Line Co., 133

FERC ¶ 61,192, at 61,950-51 (2010); Explorer Pipeline Co.,

87 FERC ¶ 61,374, at 62,392 (1999); SFPP, L.P., 84 FERC

¶ 61,338, at 62,497 (1998). As that standard formulation

suggests, FERC has decided to adhere to well-settled

economic and competition principles in determining whether

an oil pipeline possesses market power.

5

B

Pegasus is an 858-mile, 20-inch-diameter crude oil

pipeline owned and operated by Mobil. Until April 2006,

Pegasus transported about 66,000 barrels of crude oil per day

from Nederland, Texas, to Patoka, Illinois. Rapid

development of the Western Canadian oil sands, however,

made transportation of Western Canadian crude oil to new

markets an attractive proposition. To take advantage of that

opportunity, in April 2006, Mobil reversed the direction of the

flow of crude oil on Pegasus so that it could transport Western

Canadian crude oil southward.

Pegasus now transports almost entirely Western

Canadian crude oil from Illinois to Texas. The crude oil

comes to the Pegasus pipeline in Illinois by pipelines from

Western Canada. Importantly, Pegasus transports only about

66,000 barrels of Western Canadian crude oil each day –

which is only about three percent of the 2.2 million barrels of

Western Canadian crude oil produced each day.

Mobil filed an application with FERC to charge market-

based rates on Pegasus. The Commission scheduled an initial

hearing before an administrative law judge to determine

whether Pegasus possessed market power. At the hearing,

FERC’s expert staff strongly supported Mobil’s application

for market-based rate authority, concluding that Pegasus’s

origin and destination markets were plainly competitive.

The contested issue here concerns Pegasus’s origin

market. 1 FERC’s expert staff defined that market as

1

FERC recognized that Pegasus’s Gulf Coast destination

market is extremely competitive. Refineries and other entities in

the Gulf Coast that want to obtain crude oil obviously have

6

consisting of the competitive alternatives available for

producers and shippers of Western Canadian crude oil to

transport and sell their crude oil. Those alternatives include

local refineries in Western Canada and refineries throughout

Canada and the United States that can be reached by

pipelines.

In arguing that Mobil should be allowed to charge

market-based rates on the Pegasus pipeline, FERC’s expert

staff did not think this a close case. To get a flavor of the

expert staff’s views, we here quote some of their

observations:

• “Staff’s competitive story is that of a competitive

origin market with a small pipeline – the Pegasus

straw – through which producers or shippers can

access refiners in a competitive destination market.”

J.A. 787.

• “[T]here is little difference between the destination

market for Pegasus and the origin market. . . . What

we have are two competitive markets . . . .” J.A. 788-

89.

• “[I]f one excludes Pegasus from the analysis and

finds the origin market competitive, then logic

suggests that adding a small player such as Pegasus to

the competitive market will not render the market less

competitive.” J.A. 618.

• “[H]ow can a small pipeline exert market power over

a large origin market?” J.A. 617.

• “Pegasus clearly cannot be a monopolist for the

transportation” of “Western Canadian crude . . . as the

numerous alternatives to Pegasus-transported crude oil. The

competitiveness of Pegasus’s destination market is not disputed in

this litigation.

7

supply of such products . . . vastly exceeds Pegasus’s

capacity.” J.A. 825.

• “[I]t is clear that Pegasus is not a monopolist, nor

does it possess significant market power. It makes no

economic sense for Pegasus to be considered a

monopolist . . . in an expansive geographic market

. . . . Nor does it make economic sense to claim that a

new entrant to a market is a monopolist . . . .” J.A.

714.

• “There are no allegations or evidence that the market

associated with the Alberta producing area was not

competitive prior to 2006. The reversal of the

Pegasus line (in 2006) effectively created a new

supplier of crude oil transportation service out of

[that] origin market . . . .” J.A. 628.

• “As Staff developed its analysis, it seemed illogical

that when we looked at the competitive alternatives

that Western Canadian producers had to dispose of

their crude oil, they faced a very unconcentrated set

of destinations until Pegasus reversed its flow. How

can these same producers (or producer-shippers) be

said to face a less competitive set of alternatives when

they have an additional outlet, albeit small, for their

crude oil? Logic would dictate the opposite

conclusion.” J.A. 791.

• “[T]hese very alternatives were available to the

Western Canadian . . . shippers prior to the 2006

reversal of the Pegasus line, and are still being used.

It is difficult to believe that these alternatives, given

current usage, are no longer viable or competitive

. . . .” J.A. 728.

• “[I]t is literally impossible for a recent entrant to be a

monopolist if it is entering an already established

market.” J.A. 640.

8

Despite the force of the conclusions reached by FERC’s

expert staff, the Commission denied Mobil’s application for

market-based rate authority. FERC reasoned that Pegasus

possessed market power in its origin market. Indeed, FERC

actually concluded that Pegasus had a 100 percent market

share in that market.

Mobil timely petitioned for review in this Court. We

assess FERC’s order under the Administrative Procedure

Act’s arbitrary and capricious standard. That standard

requires that FERC’s decision be reasonable and reasonably

explained.

II

FERC denied Mobil’s application for market-based rate

authority on the ground that Pegasus possessed market power

in its origin market. Indeed, FERC reached the rather

extraordinary conclusion that Pegasus possessed a 100

percent market share in that market. We find FERC’s

decision unsustainable.

The Pegasus pipeline transports almost exclusively

Western Canadian crude oil. The proper question, therefore,

is whether producers and shippers of Western Canadian crude

oil must rely so heavily on Pegasus for transportation of their

crude oil that Pegasus can be said to possess market power –

that is, whether Mobil could profitably raise rates on Pegasus

above competitive levels for a significant period of time

because of a lack of competition. The answer is an emphatic

no: Pegasus transports only about 66,000 of the 2.2 million

barrels – about three percent – of Western Canadian crude oil

produced each day.

9

Market-power analysis focuses on whether there are

alternatives to a firm’s services that constrain its ability to

profitably charge prices above competitive levels for a

significant period of time. The inquiry examines the

alternatives reasonably available to consumers and the cross-

elasticity of demand – that is, the extent to which consumers

will respond to an increase in the price of one good by

substituting or switching to another. See, e.g., Eastman

Kodak Co. v. Image Technical Services, Inc., 504 U.S. 451,

469 (1992); United States v. Microsoft Corp., 253 F.3d 34,

51-52 (D.C. Cir. 2001) (en banc) (per curiam); FTC v. H.J.

Heinz Co., 246 F.3d 708, 718 (D.C. Cir. 2001); 2B PHILLIP E.

AREEDA, HERBERT HOVENKAMP & JOHN L. SOLOW,

ANTITRUST LAW ¶ 506a (3d ed. 2007); Department of Justice

& Federal Trade Commission, Horizontal Merger Guidelines

§ 1.11 (rev. ed. 1997).

In the crude oil context, because “crude oil in an area

may either be exported out of the area or consumed, i.e.,

refined, in the area,” a pipeline “transporting crude oil out of

an area therefore competes with local crude refineries as well

as with other crude transportation facilities.” DEPARTMENT

OF JUSTICE, OIL PIPELINE DEREGULATION 16 (1986) (footnote

omitted). The competitive alternatives in crude oil pipeline

origin markets thus include: (1) pipelines that transport crude

oil out of the area and (2) local refineries. Id.

Here, in considering the relevant market, FERC’s expert

staff identified many local refineries that process Western

Canadian crude oil, as well as several pipelines that move

Western Canadian crude oil to other refineries in Canada and

the United States. As the staff noted, the critical statistic is

that about 97 percent of Western Canadian crude oil gets to

refineries by means other than Pegasus.

10

Given that eye-opening 97 percent figure, Mobil rightly

asks: How can Pegasus be said to possess market power over

producers and shippers of Western Canadian crude oil when

Pegasus transports only about three percent of Western

Canadian crude oil? FERC has no good answer to that simple

question. And the absence of a good answer is why FERC’s

expert staff concluded that this case was a “slam dunk” for

market-based rates. Tr. of Administrative Hearing at 2216. 2

The hole in the Commission’s analysis is highlighted by

the fact that Pegasus is a new entrant into a previously

competitive market. Before Pegasus started transporting

Western Canadian crude oil in 2006, producers and shippers

of Western Canadian crude oil had numerous competitive

alternatives for transporting and selling their crude oil. When

Pegasus came onto the scene, it simply provided an additional

alternative for Western Canadian crude oil producers and

shippers. Basic economic logic dictates that the introduction

of a new alternative into a highly competitive market further

increases competition; it does not suddenly render a

previously competitive market uncompetitive. 3

2

The Commission, of course, is by no means obliged to heed

the advice of its expert staff. It is “our well-established view that

an agency is not bound by the actions of its staff if the agency has

not endorsed those actions.” Comcast Corp. v. FCC, 526 F.3d 763,

769 (D.C. Cir. 2008) (quoting Vernal Enterprises, Inc. v. FCC, 355

F.3d 650, 660 (D.C. Cir. 2004)); see also Community Care

Foundation v. Thompson, 318 F.3d 219, 227 (D.C. Cir. 2003);

MacLeod v. ICC, 54 F.3d 888, 891 (D.C. Cir. 1995). In this case,

we cite the economic and legal analysis of FERC’s expert staff only

because we find it so persuasive.

3

To be sure, the effect on competition can depend on the new

entrant’s size. But that is not an issue here, as shown by the

statistics on Pegasus’s market share.

11

Put simply, we fail to understand how the entry of

Pegasus, which transports only about 66,000 barrels per day,

into a previously competitive 2.2 million barrel per day

market makes that market suddenly uncompetitive. As

FERC’s expert staff explained, “If you evaluate the market

with no Pegasus, and it’s clearly competitive, adding one

more option can’t possibly make the market less

competitive.” Tr. of Administrative Hearing at 2216. The

Commission’s contrary conclusion is analogous to saying that

a new shoe store in a city has monopoly power even though

there are already numerous shoe stores in the same city. That

doesn’t make much sense.

The Commission may have been led astray by its

assessment that Mobil, if granted market-based rate authority,

could raise rates on Pegasus by 15 percent or more. But the

Commission calculated that figure by using Pegasus’s

regulated rate as the baseline. As FERC’s expert staff

explained, the 15 percent figure demonstrates only that

Pegasus’s regulated rate is below the competitive rate. The

regulated rate does not reflect Pegasus’s full value to Western

Canadian crude oil producers and shippers. Therefore, the

possibility that the market rate might be higher than the

regulated rate does not show that Pegasus possesses market

power.

FERC also seemed concerned that producers and shippers

of Western Canadian crude oil could obtain higher prices on

the Gulf Coast, thereby giving Pegasus undue leverage over

producers and shippers of Western Canadian crude oil who

sought that particular outlet. It is true that Pegasus is the

primary avenue for producers and shippers of Western

Canadian crude oil to get their crude oil to Gulf Coast

refineries. But from the perspective of producers and shippers

of Western Canadian crude oil, there is nothing unique about

12

Gulf Coast refineries, as distinct from other refineries

available to them in Canada and the United States. See

Williams Pipe Line Co., 71 FERC ¶ 61,291, at 62,131 (1995)

(“the real economic concern of shippers is the delivered

product and its price rather than whether the product travels

between specific locations via pipeline”). The overall picture

here, as FERC’s expert staff emphasized, is one of robust

competition for Western Canadian crude oil: Producers and

shippers of Western Canadian crude oil have numerous

competitive alternatives to get their crude oil to refineries. If

Pegasus raised its rates above competitive levels, then

producers and shippers of Western Canadian crude oil would

choose one of the many alternative outlets available to them.

Those other outlets thereby constrain the rates that Pegasus

can charge. There is thus no plausible way, as we see it and

as FERC’s expert staff saw it, to say that Pegasus holds a

hammer over Western Canadian crude oil producers and

shippers.

Moreover, contrary to FERC’s suggestion, short-term

price variations – which may temporarily make Gulf Coast

refineries (and thus Pegasus) an attractive outlet for Western

Canadian crude oil producers and shippers – are consistent

with competition. See Blumenthal v. FERC, 552 F.3d 875,

883 (D.C. Cir. 2009); Edison Mission Energy, Inc. v. FERC,

394 F.3d 964, 969 (D.C. Cir. 2005); Interstate Natural Gas

Ass’n of America v. FERC, 285 F.3d 18, 32 (D.C. Cir. 2002);

see also Explorer Pipeline Co., 87 FERC ¶ 61,374, at 62,392,

62,394 (1999); Longhorn Partners Pipeline, L.P., 83 FERC

¶ 61,345, at 62,380 (1998); Williams Pipe Line Co., 71 FERC

at 62,145; Williams Pipe Line Co., 68 FERC ¶ 61,136, at

61,658 (1994). As FERC has previously explained, short-

term price variations that result in regional price differentials

do not establish market power. See Explorer Pipeline Co., 87

FERC at 62,394 (“Differential pricing, when constrained by

13

effective competition, can materially improve the efficiency

of transportation markets by allocating capacity to those

shippers who value it the most, particularly in markets

involving different degrees of geographic or seasonal

variation.”); Longhorn Partners Pipeline, L.P., 83 FERC at

62,380 (“[A]ny price differential between the origin and

destination markets does not confer monopolistic power upon

[the pipeline], but rather it promotes competition.”).

In sum, when an agency is statutorily required to adhere

to basic economic and competition principles – or when it has

exercised its discretion and chosen basic economic and

competition principles as the guide for agency

decisionmaking in a particular area, as FERC did in Order No.

572 – the agency must adhere to those principles when

deciding individual cases. Here, the Commission jumped the

rails by treating the Pegasus pipeline as the rough equivalent

of a bottleneck or essential facility for transportation of

Western Canadian crude oil. As we have explained, the

record thoroughly undermines FERC’s conclusion. The

Commission’s decision thus cannot stand.

***

We conclude that the Commission’s denial of Mobil’s

application for market-based rate authority was unreasonable

on the facts and evidence before it. We grant Mobil’s petition

for review, vacate FERC’s order, and remand for further

proceedings consistent with this opinion.

So ordered.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.