Opinion

American Medical Equipment, Inc. v. United States

Court
United States Court of Federal Claims
Filed
Jun 30, 2022
Status
Published
On the bench
Armando O. Bonilla
Cited by
0 cases
Authority
More cited than 11.4%

“If fire is always an excuse, a contractor is free to use inflammable materials in a tinder-box factory and escape any damages for delay due to a resulting fire.”

How later courts described this case

  • “If fire is always an excuse, a contractor is free to use inflammable materials in a tinder-box factory and escape any damages for delay due to a resulting fire.”
  • “[A] termination for default that is unrelated to contract performance is arbitrary and capricious, and thus an abuse of the contracting officer’s discretion.”
  • implied duty of good faith cannot “alter[] the contract’s discernible allocation of risks and benefits” or “conflict[] with a contract provision.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

FOR PUBLICATION

No. 21-1553C

(Filed: June 30, 2022)

)

AMERICAN MEDICAL EQUIPMENT, INC. )

) Breach of Supply Contract:

Plaintiff, ) Termination for Default;

) Excusable Delay;

v.

) Implied Duty of Good Faith

UNITED STATES, ) & Fair Dealing

)

Defendant. )

Eric S. Montalvo, Federal Practice Group, Washington, DC, for plaintiff. With him

on the briefs was Carol A. Thompson, Federal Practice Group, Washington, DC.

Alison S. Vicks, Trial Attorney, Commercial Litigation Branch, Civil Division,

U.S. Department of Justice, Washington, DC, for defendant. With her on the briefs

were Brian M. Boynton, Principal Deputy Assistant Attorney General, Patricia M.

McCarthy, Director, Commercial Litigation Branch, U.S. Department of Justice,

Washington, DC. Tracy Downing, U.S. Department of Veterans Affairs, District

Contract Law National Practice Group, Of Counsel.

OPINION AND ORDER

BONILLA, Judge.

By January 2021, despite having “just 4% of the world’s population,” the

United States had incurred “25% of the world’s COVID-19 cases and 20% of all

COVID-19 deaths.” 1 The nationwide emergency measures that started in 2020

continued into a second year to mitigate the impact of the pandemic amid the

emergence of new virus variants and elevated records of hospitalizations. This

breach of contract action arose from the United States Department of Veteran

1See National Strategy for the COVID-19 Response and Pandemic Preparedness at 5 (Jan. 21, 2021),

available at https://www.whitehouse.gov/wp-content/uploads/2021/01/National-Strategy-for-the-

COVID-19-Response-and-Pandemic-Preparedness.pdf (last viewed June 27, 2022).

Affairs’ (VA) efforts in early 2021 to acquire and stockpile personal protective

equipment (PPE), i.e., nitrile examination gloves, to enable prompt delivery to

medical personnel at VA healthcare facilities located throughout the country.

Plaintiff, American Medical Equipment, Inc. (AME), bid for and was awarded

a contract to supply the VA with 10 million nitrile examination gloves. When

AME failed to meet the 45-day delivery schedule specified in the contract, the

VA terminated the contract for default. AME brings this action challenging the

contracting officer’s decision and seeking to convert the termination for default

into a termination for convenience and recover consequent monetary damages.

Pending before the Court are the parties’ cross-motions for summary judgment.

For the reasons stated below, defendant’s motion for summary judgment is

GRANTED and plaintiff’s cross-motion for summary judgment is DENIED.

BACKGROUND

I. Pre-Award Events and Contract Requirements

In late 2020, “[b]ecause of increased demand caused by COVID 19 [sic] and

a national shortage in the inventory and supply of nitrile examination gloves, the

[VA] determined it would implement a plan to maintain a 180-day stock of nitrile

examination gloves to ensure the availability of gloves for the Agency’s healthcare

providers.” ECF 15-1 at 50. To cover the agency’s 1,244 healthcare facilities located

throughout the United States, the VA determined that “hundreds of millions of

nitrile examination gloves [were] required.” Id.

Between October 2020 and February 2021, the VA issued three solicitations

for nitrile examination gloves. Id. at 50–54. “In order to ensure that the gloves

would be provided quickly by the distributors, the solicitations . . . requested

that the gloves be on-hand (or already in existence) so that delivery could be

accomplished within 30-45 calendar days of contract award.” Id. at 50. After

reviewing the quotes received, between December 2020 and June 2021, the VA

awarded a total of fifteen (15) contracts for the procurement of nitrile examination

gloves, requiring quantities ranging from 2.5–50 million. Id. at 50–54. Awarding

multiple contracts for smaller quantities of “on-hand” PPE was purposely done to

ensure delivery would be accomplished within 30–45 calendar days of contract

award. Id. at 50, 53.

A. VA Solicitation

On February 9, 2021, VA Contracting Officer Charles W. Worsham issued

Solicitation No. 36C24921Q0115 for an unspecified quantity of nitrile examination

gloves. Id. at 57–116. Under “Schedule of Supplies/Services,” the first page of the

solicitation states: “Delivery shall be 45 calendar days or sooner, after receipt of

order.” Id. at 57. Section B.2 of the solicitation, titled “Statement of Work,”

2

stressed to potential bidders that the supply contract was intended for on-hand

gloves subject to a non-negotiable delivery schedule:

This is not a request for manufacturing but a request for quantity

on hand to be delivered within 45 calendar days from order.

...

Contracts that are awarded based on submitted quotes will have

45 calendar days from receipt of order (award date) to deliver the

awarded quantities, or the contract will be terminated for cause

and negative performance will be reflected within the Contractor

Performance Assessment Reporting System (CPARS) and the Federal

Awardee Performance and Integrity Information System (FAPIIS).

Id. at 60 (emphases added); see also id. at 115 at Question No. 14 (PPE Source

Questionnaire: “Quantity on hand (in-stock and available for immediate delivery)”).

Under “Delivery Schedule” (Section B.4), the solicitation restates that the PPE

must be delivered “45 calendar days after receipt of order” and further specifies

the delivery location and instructions. Id. at 63.

Section C.1 of the solicitation, titled “Contract Clauses . . . Contract Terms

and Conditions—Commercial Items,” incorporates pertinent provisions of the

Federal Acquisition Regulation (FAR) governing commercial item acquisition. Id.

at 64–81. Relevant here, among the FAR provisions quoted in the VA solicitation

is FAR 52.212-4(f), which provides:

Excusable delays. The Contractor shall be liable for default unless

nonperformance is caused by an occurrence beyond the reasonable

control of the Contractor and without its fault or negligence such as,

acts of God or the public enemy, acts of the Government in either its

sovereign or contractual capacity, fires, floods, epidemics, quarantine

restrictions, strikes, unusually severe weather, and delays of common

carriers. The Contractor shall notify the Contracting Officer in writing

as soon as it is reasonably possible after the commencement of any

excusable delay, setting forth the full particulars in connection

therewith, shall remedy such occurrence with all reasonable dispatch,

and shall promptly give written notice to the Contracting Officer of the

cessation of such occurrence.

ECF 15-1 at 64 (italics in original). FAR 52.212-4(m), also incorporated and quoted

in the VA solicitation, states:

3

Termination for cause. The Government may terminate this contract,

or any part hereof, for cause in the event of any default by the

Contractor, or if the Contractor fails to comply with any contract terms

and conditions, or fails to provide the Government, upon request,

with adequate assurances of future performance. In the event of

termination for cause, the Government shall not be liable to the

Contractor for any amount for supplies or services not accepted,

and the Contractor shall be liable to the Government for any and

all rights and remedies provided by law. If it is determined that

the Government improperly terminated this contract for default,

such termination shall be deemed a termination for convenience.

ECF 15-1 at 68 (italics in original). Under other FAR provisions similarly

incorporated in the solicitation, the VA highlighted the importance of the strict

delivery schedule. See id. at 87–88 (FAR Part 13 Simplified Acquisition Procedures:

Section F—Delivery Schedule: “The contractor shall submit a proposed delivery that

is not to exceed 45 calendar days.”); ECF 15-1 at 94–95 (Subsection E.9 Evaluation

— Commercial Items (Tailored): “Delivery Schedule: To be eligible for award,

Offerors must be able to deliver within 45 calendar days from the award date.”).

B. AME Offer

On February 16, 2021, in response to the VA solicitation, AME submitted an

offer to provide 10 million nitrile examination gloves for $1.469 million. ECF 11-1

at 107–226. More specifically, AME committed to procure the 10 million nitrile

examination gloves from Chinese original equipment manufacturer (OEM) Hebei

Titans Hongsen Medical Technology Co. Ltd. (Titans Hongsen) and deliver them to

the specified United States Defense Logistics Agency (DLA) warehouse/distribution

center within 45 days after receipt of order. Id. at 109, 112–13, 203, 226. AME

holds itself out as a minority/woman-owned business, incorporated in 2006 and

located in Memphis, Tennessee; AME represents itself as an authorized reseller/

distributor of nitrile examination gloves manufactured by Titans Hongsen. Id. at

203, 225. Among the references AME listed in support of its bid was: Dennis J.

Stewart Sr., Bureau Director Logistics, Mississippi Emergency Management Agency

(MEMA). Id. at 225.

In response to the PPE Source Questionnaire, AME responded, in part:

Question Contractor Response

... ...

2. Has your company done business with the Federal NO

government previously? If yes, please provide contract

number for reference

... ...

6. Any unique terms and conditions being proposed NO

4

... ...

12. If already produced, where is product located now? CHINA

... ...

14. Quantity on hand (in-stock and available for Due to high demand

immediate delivery) ,nothing [sic] in

hand.

... ...

16. Provide summary of logistics chain (i.e. they are Buying direct from

buying from the manufacture or are they buying from OEM to expedite

another wholesaler/importer and reselling again (how delivery

many hand exchanges before delivery)[)]

Id. at 204–06. In the Delivery Schedule (Section B.4), for the two types of nitrile

examination gloves AME offered, AME President Masooma Tiwana handwrote:

“5.5 million” with a “Delivery Date” of “45 Days ARO [After Receipt of Order]”;

and “4.5 million” with a “Delivery Date” of “45 Days ARO.” Id. at 226.

C. Pre-Award Investigation and SBA Intervention

On February 25, 2021, VA Contract Specialist Scott Dickey notified

AME President Tiwana of certain VA concerns about AME’s ability to successfully

perform under the contract, citing a DNBi report assigning AME a Supplier

Evaluation Risk Rating of “High Risk (9),” 2 and the fact that AME had “no

procurement history with the federal government.” ECF 11-1 at 227. AME

responded the next day, explaining that the DNBi report was “based on outdated

data” and highlighting AME’s recent PPE supply contract with MEMA. Id. at 246.

Addressing delivery logistics for its pending bid, AME represented: “We have

already teamed up with Fedex [sic] to secure logistics supply chain for this contract

,if [sic] awarded. They have already worked with us in our previous contract with

MEMA.” Id.

In response to a February 25, 2021 reference check with MEMA, Mr. Stewart

immediately offered:

Sir it was not satisfactory. Delays in shipment, billing issues. They

drove down from Memphis and tried to take some of the gowns for

samples. After I told them no, they went to the warehouse and tried

to buy some gowns from our warehouse staff. Bottom line I will not

2 DNBi is an interactive web application that allows users possessing login credentials to access

financial information, analytics, and credit worthiness about over 120 million companies in the

Dun & Bradstreet Corporation database. See https://sso.dnbi.com/cas/login?null&cnt=4 (last viewed

June 28, 2022).

5

purchase from them again. I have been buying all the [COVID-19]

PPE for the state and I will not use them again.

Id. at 252–53. After reviewing AME’s submission, and taking into account the

negative reference check, Contracting Officer Worsham determined AME to

be “non-responsible,” explaining:

After the contracting team reviewed AME’s original submission and

conducted reference checks, I determined AME to be non-responsible

for the award because it did not have a satisfactory or better

performance rating for supplying personal protective equipment (PPE)

in a timely manner, as required by the solicitation. AME did not

have any experience in Federal contracting and the reference check

it provided indicated that AME had not been able to deliver

contracted-for PPE on the required performance schedule.

ECF 11-2 at 66 (Worsham Decl. ¶4). Due to AME’s small business status, in

accordance with the FAR, Contracting Officer Worsham requested a Certification

of Competency (COC) from the United States Small Business Administration (SBA).

Id. at 67 (Worsham Decl. ¶¶ 5–6); see ECF 11-1 at 258. On April 6, 2021, the SBA

issued the requested COC, certifying that AME “is responsible to perform the

proposed procurement covered by the referenced Solicitation No. 36C249-21-Q-

0115.” ECF 11-1 at 262–65 (emphasis omitted).

In an email dated April 8, 2021, Contracting Officer Worsham notified AME

that the VA received the COC from the SBA and that all new PPE supply contract

awards were on hold pending further direction from VA leadership. Id. at 266.

Nevertheless, the Contracting Officer continued: “We are not accepting glove

substitutions but if your pricing or qty available to be delivered within 45 calendar

days changes, please let us know.” Id. AME immediately confirmed continued

interest “for the price and quantity already quoted.” Id.

A week later, on April 15, 2021, Contracting Officer Worsham reached out to

AME President Tiwana, inquiring:

We have received the go ahead with additional awards for this

solicitation. Please confirm pricing and the qty of gloves that you can

deliver within 45 calendar days. Is it still 10M gloves at $0.1469 per

glove (total $1.469M) or has it changed?

Please note that this is not a notice for award.

Id. at 269. AME immediately responded:

6

Pricing and quantity is re-confirmed i.e [sic] 10M gloves at $0.1469 per

glove (total $1.469M) to be delivered in 45 days ARO. Furthermore

,should [sic] you require additional quantity over [sic] and above

10 million gloves at the same price ,please [sic] let us know. We will

be able to supply the same.

Id. at 268.

II. Contract Award

On April 16, 2021, the day after their most recent email exchange,

Contracting Officer Worsham formally extended AME a notice of award stressing,

among other things, the firm 45-day delivery deadline and the need for constant

communication:

Prior to signing the [award] document, there are some items that

need to be re-addressed and/or re-confirmed. Due [to] recent past

experiences, I want to overcommunicate these points.

...

2. The delivery date is set for 07 June 2021 for 100% qty of gloves

being awarded. No extensions will be granted. This includes

but is not limited to delays associated with the manufacturer,

the supplier, shipping delays, customs, lack of financing and

the pandemic.

...

5. Ensure to communicate with both the contracting office and

the DLA warehouse personnel; including weekly updates to the

contracting office. Ensure communication with DLA is done well

ahead of time for each and every shipment/delivery.

...

Id. at 271–72 (emphases added). The remaining four points of emphasis included

matching the gloves, pricing, and packaging AME included in its offer, and

completing the necessary government accounting forms. Id. at 271. AME President

Tiwana responded that she “comprehend[ed] and reconfirm[ed] the 6 points flagged

in [the] communication,” and submitted the signed award document several days

later. Id. at 271; ECF 11-2 at 1–24.

In the April 20, 2021 email returning the signed award document to AME,

Contracting Officer Worsham again stressed:

7

Please note that the period of performance start date in the price/cost

schedule reflects today. The delivery date remains at June 7th since

it is still the next business day after 45 calendar days. Please send

regular updates to both [Contract Specialist Dickey] and myself and

please ensure to contact the warehouse personnel well in advance to

schedule delivery(ies).

ECF 11-2 at 25. That evening, AME President Tiwana “acknowledge[d] the period

of performance as communicated” and promised to provide “regular[] update[s]” as

requested. Id.

The fully executed PPE supply contract award includes the same “Statement

of Work” (Section B.2), delivery schedule, and incorporated FAR provisions as those

in the initial VA solicitation (Feb. 9, 2021) and AME’s offer (Feb. 16, 2021) and is

consistent with the pre-award communications between the VA Contracting Office

and AME. Compare ECF 11-2 at 1–24 (contract award) with ECF 15-1 at 57–116

(solicitation) and ECF 11-1 at 107–226 (AME offer). Above AME’s signature on the

first page of the award document, the “Schedule of Supplies/Services” section states:

This is an acquisition for surge supply of Nitrile Gloves for hospital

staff in response to the increased usage caused by COVID-19.

The contractor agrees to deliver the amount of supplies ordered

in 45 calendar days from the execution of this contract.

The No Later Than Delivery Date for entirety of order is 06/07/2021.

ECF 15-1 at 125. Under “Statement of Work,” the contract restates the on-hand

requirement and the firm 45-day deadline:

This is not a request for manufacturing but a request for quantity

on hand to be delivered within 45 calendar [d]ays from order.

...

Contracts that are awarded based on submitted quotes will have

45 calendar days from receipt of order (award date) to deliver the

awarded quantities, or the contract will be terminated for cause and

negative performance will be reflected within the [CPARS] and the

[FAPIIS].

Id. at 128. Under “Delivery Requirements,” the contract repeats that delivery is

due “45 calendar days after receipt of order” to the DLA Distribution warehouse

located in Chambersburg, Pennsylvania. Id. at 129–30.

8

III. Contract Performance

AME provided updates to the VA for the first two weeks after the award.

See, e.g., ECF 11-2 at 33–34 (April 21, 2021 email from AME to VA: “Just a quick

update[.] I have placed the order with OEM and remitted funds to it.”); id. at 33

(April 27, 2021 email from AME to VA: “Our production run had [sic] commenced

and is likely to complete by April 29.”). Despite the somewhat ambiguous

representation in its offer, AME’s April 27, 2021 report makes clear that it ordered

the manufacture of the 10 million nitrile examination gloves post-award rather

than simply purchasing existing quantity for more immediate delivery. Compare

ECF 11-1 at 206 (AME responded “CHINA” to the solicitation PPE Source

Questionnaire Question No. 12: “If already produced, where is product located

now?”) 3 (emphasis added) and id. (AME responded “Due to high demand ,nothing

[sic] in hand.” to Question No. 14: “Quantity on hand (in-stock and available

for immediate delivery)”) (emphasis added) and id. (AME responded “Buying direct

from OEM to expedite delivery” to the Question No. 16: “Provide summary of

logistics chain . . . .) with ECF 11-2 at 33–34 (quoted above) (AME statement of

April 21, 2021 that it “ha[s] placed the order with OEM and remitted funds” and

report of April 27, 2021 that “production” commenced).

Thereafter, on May 3-4, 2021, AME informed the VA that the PPE equipment

was being delivered from China by container ships, in several batches, rather than

by air or via FedEx. Compare ECF 15-1 at 37 (May 3, 2021 email from AME to VA:

“This is to update you on our Contract. 75% of the Contract shipment has been

despatched [sic] from factory to port of origin in China .Remaining [sic] 25% goods

will be despatched [sic] by tomorrow to the port.. [sic]”) and id. at 36 (May 3, 2021

email from VA to AME: “Are these being shipped via air or container ships?”) and

id. at 35 (May 4, 2021 email from AME to VA: “All 10 million gloves packed in 4

containers are ready and are being shipped on container ship.”) with ECF 11-1 at

246 (February 26, 2021 email from AME to VA: “We have already teamed up with

Fedex [sic] to secure logistics supply chain for this contract ,if [sic] awarded.”).

Nevertheless, AME’s May 4, 2021 correspondence closed with the following

assurance to the VA: “All is on track to have the gloves delivered by June 7th.”

ECF 15-1 at 35.

The record does not reflect further shipping or delivery updates from AME

until May 25, 2021. In response to Contract Specialist Dickey’s May 24, 2021

3 In response to the following question “Are you able to provide a letter from the manufacturer

stating they will allocate a quantity to you as a distributor? If so, provide letter with quote[,]”

AME stated “Auth letter indication [sic] quantity attached.” ECF 11-1 at 206 (emphasis in original).

Rather than an allocated quantity available for AME’s distribution, the attached letter from Titans

Hongsen stated “[AME is] authorized to quote a quantity of 10 Million . . . for this project.” Id. at 203

(emphasis added).

9

request for an update, AME represented that the “entire production of 10 million

nitrile gloves was completed on April 28” and

The marine containers are expected to be in New York port [sic]

on June1.After [sic] necessary clearance these will be shipped to [the]

delivery site within 3-4 days .We [sic] intend to coordinate with [the]

delivery site as soon as shipments arrive at the port .i.e [sic] a week

prior to delivery.

Id. at 18. When the VA asked for another update on June 2, 2021—the day after

the touted June 1, 2021 port arrival—AME reported that none of the containers

arrived:

The original ETA for all 4 containers was 06/01. As per attached

Arrival Notice received from shipping company ,ETA [sic] at New York

Port is now 06/09.These [sic] will be 3 containers having 75% of the

supply. A 4th container which was loaded on the ship called

“M.Y.Witness” [sic] on 04/29 and was expected along with these

containers was off loaded [sic] at the last minute due to operational

reasons cited by [the] shipping company and re-loaded on another ship

on 05/22 as per [the] attached notice from the shipper [and] is now

expected to arrive on 06/22.

Id. at 23. Attached to AME’s June 2, 2021 correspondence were several shipping

documents. Id. at 38–42. These include: (1) three “Arrival Notice / Freight Invoice”

forms from BNX Shipping Inc. documenting three containers were estimated to

depart from Yantian, China (port of loading) “05/06/2021” and estimated to arrive at

New York port (port of discharge) “06/09/2021”; and (2) a vessel notification email

between two shipping companies (i.e., Ocean Network Express and Hecny

Transportation (Shanghai)) showing a fourth container originally estimated to

arrive at New York port “08 JUN 2021,” but re-nominated to depart from Yantian

port on “22 MAY 2021” to arrive at New York port “22 JUN 2021.” Id.

As of the June 7, 2021 contracted delivery date, AME delivered no gloves to

the DLA warehouse/distribution center and, further, had not coordinated with the

warehouse regarding any expected deliveries. See ECF 11-2 at 61 (June 7, 2021

VA delivery tracking table listing AME status: “No advance delivery information

received”); id. at 54–61 (June 7-8, 2021 internal VA emails confirming no AME

deliveries received under the contract).

IV. Termination for Default

After reviewing the June 7, 2021 receipts, the delivery warehouse again

confirmed that “nothing was delivered by [AME].” Id. at 55. On June 8, 2021,

Contracting Officer Worsham terminated AME’s contract, contract number

10

36C24921P0320, for cause for failing to meet the June 7, 2021 delivery deadline,

and formally notified AME’s President of the VA’s decision. Id. at 63–65. The

Termination for Cause notice explained:

The contract was awarded on April 20th, thereby requiring

50M[ 4] nitrile gloves to be delivered by 07 June 2021, and

[AME] delivered zero.

The April 20th award stated:

Contracts that are awarded based on submitted quotes will have

45 calendar days (i.e. 07 June) to deliver the awarded quantities,

or the contract will be terminated for cause and negative

performance will be reflected within the [CPARS] and the

[FAPIIS].

See ECF 11-2 at 65.

V. AME’s Challenge to the Termination for Default

On July 7, 2021, AME commenced this action, alleging that the termination

for default was arbitrary and capricious, and that the government breached its

implied duty of good faith. See ECF 1 at 2, 5–9. In support of its claims, AME

contends that the Contracting Officer should have exercised his discretion to extend

the delivery deadline. See ECF 15 at 23–25. AME further argues that the shipping

delays were due to a May 2021 COVID-19 outbreak in China restricting Yantian

port operations and, thus, were excusable. See ECF 1 at 6–7. AME also avers that

the default termination was not in the best interest of the government in that the

consequent re-procurement further delayed the VA’s receipt of the PPE. Id. at 4.

Defendant counters that the VA properly terminated the supply contract

for cause because AME failed to perform. See ECF 11 at 1. The termination was

further justified, defendant maintains, in light of AME’s advance notice that it

would not meet the June 7, 2021 deadline. Id. at 8. Defendant avers that AME’s

nonperformance was not excusable because AME’s failure to meet the strict delivery

schedule was caused by its choices to: contract for the manufacture of the nitrile

examination gloves rather than locate and purchase existing PPE for prompt

delivery; have the gloves manufactured in China rather than the United States; and

import the gloves on container ships after representing to the VA that the company

had made arrangements with FedEx. Id. at 27–28. Defendant further contends

4The reference to 50 million nitrile examination gloves is clearly a typographical error as the AME

PPE supply contract involved the procurement and delivery of 10 million gloves. Id. at 66; ECF 11-1

at 6.

11

that the terms of the supply contract, which required delivery within 45 days or else

risk default termination, were clear and repeatedly confirmed with AME. Id. at 1.

DISCUSSION

I. Legal Standards

A. Cross-Motions for Summary Judgment

Summary judgment is appropriate “if the movant shows that there is no

genuine dispute as to any material fact and the movant is entitled to judgment

as a matter of law.” RCFC 56(a). A “genuine dispute” exists where a reasonable

factfinder “could return a verdict for the nonmoving party.” Anderson v. Liberty

Lobby, Inc., 477 U.S. 242, 248 (1986). “Material facts,” in turn, are those “that

might affect the outcome of the suit.” Id. In deciding motions for summary

judgment, particularly where, as here, the parties filed cross-motions for summary

judgment, the Court must draw all inferences in the light most favorable to the

nonmoving party, evaluating each motion on its own merits. Matsushita Elec.

Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587–88 (1986) (quoting United

States v. Diebold, Inc., 369 U.S. 654, 655 (1962)); Mingus Constructors, Inc. v.

United States, 812 F.2d 1387, 1391 (Fed. Cir. 1987).

The moving party bears the initial burden to demonstrate the absence of

any genuine issue of material fact. See Celotex Corp. v. Catrett, 477 U.S. 317, 323

(1986). That burden can be met by showing “there is an absence of evidence to

support the nonmoving party’s case.” Dairyland Power Co-op. v. United States,

16 F.3d 1197, 1202 (Fed. Cir. 1994) (citing Celotex, 477 U.S. at 325). “Once the

moving party has satisfied its initial burden, the opposing party must establish a

genuine issue of material fact and cannot rest on mere allegations, but must present

actual evidence.” Crown Operations Int’l, Ltd. v. Solutia Inc., 289 F.3d 1367, 1375

(Fed. Cir. 2002) (citing Anderson, 477 U.S. at 248). Summary judgment is

warranted when “the record taken as a whole could not lead a rational trier of fact

to find for the non-moving party.” Matsushita, 475 U.S. at 587.

B. Termination for Default

When a contractor challenges a termination for default, the government

bears the initial burden to show the contractor was in default at the time of

termination. See Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 763–65

(Fed. Cir. 1987). For contracts concerning delivery of goods, “[a] contractor’s failure

to make timely delivery of agreed-upon goods establishes a prima facie [sic] case of

default.” Gen. Injectables & Vaccines, Inc. v. Gates, 519 F.3d 1360, 1363 (Fed. Cir.),

opinion supplemented on denial of reh'g, 527 F.3d 1375 (Fed. Cir. 2008). Once

default is established, “[t]he burden then shifts to the contractor to show that the

failure to deliver the contract goods was excusable.” Id. (citing DCX, Inc. v. Perry,

12

79 F.3d 132, 134 (Fed. Cir. 1996)). Under FAR 52.212-4(f), incorporated in AME’s

contract, the contractor’s failure to timely deliver is excusable if it “is caused by an

occurrence beyond the reasonable control of the Contractor and without its fault or

negligence.”

The Court reviews an agency’s termination for default de novo. 41 U.S.C.

§ 7104(b)(4); see also McDonnell Douglas Corp. (McDonnell Douglas II) v. United

States, 323 F.3d 1006, 1018 n.3 (Fed. Cir. 2003). “In determining whether a default

termination was justified, a court must review the evidence and circumstances

surrounding the termination, and that assessment involves a consideration of

factual and evidentiary issues.” McDonnell Douglas II, 323 F.3d at 1014 (citing

cases). As a general matter, government contracting officers have “broad discretion

to determine whether to terminate a contract for default,” and those decisions must

be sustained unless they are “arbitrary, capricious, or an abuse of discretion.”

Allen Eng’g Contractor Inc. v. United States, 611 F. App’x 701, 705 (Fed. Cir. 2015)

(quoting Lanterman v. United States, 75 Fed. Cl. 731, 733–34 (2007)). Nevertheless,

in reaching a default termination, a contracting officer must “make sure that

termination is in the best interests of the Government.” Nuclear Rsch. Corp. v.

United States, 814 F.2d 647, 649 (Fed. Cir. 1987); FAR § 12.403(b). Further, there

must be a nexus between the default termination and the contractor’s performance.

See McDonnell Douglas Corp. (McDonnell Douglas I) v. United States, 182 F.3d

1319, 1326 (Fed. Cir. 1999) (“[A] termination for default that is unrelated to

contract performance is arbitrary and capricious, and thus an abuse of the

contracting officer’s discretion.”) (citing United States Fidelity & Guaranty Co. v.

United States, 676 F.2d 622, 630 (1982)). 5

II. Contract Performance: Default and Repudiation

AME bid for and was awarded a contract with the VA to deliver 10 million

nitrile examination gloves to a designated warehouse/distribution center in

Pennsylvania by June 7, 2021, or else risk default termination. Contrary to the

clearly stated (and repeated) strict 45-day delivery schedule, AME delivered zero

gloves to the VA on or before June 7, 2021. In fact, as of the June 7, 2021 deadline,

none of the four containers AME commissioned to import the PPE had even reached

the United States, let alone cleared U.S. Customs and completed their drayage to

the designated Pennsylvania warehouse/distribution center. See e.g., ECF 1 ¶ 11

(AME complaint conceding none of the containers would arrive at the New York

port by June 7, 2021). Accordingly, a prima facie case of default has been

5 Citing McDonnell Douglas I, AME argues that the termination was an abuse of discretion because

“there was no performance-based reason for default termination” and it was “pretextual.” ECF 15 at

24–25, 25 n.12. AME’s reliance upon this case is misplaced. As discussed infra, contrary to AME’s

assertion, the Court finds that the Contracting Officer’s decision to terminate for cause was directly

related to contract performance: AME’s failure to meet the clearly stated and agreed to strict

delivery deadline.

13

established due to AME’s “failure to make timely delivery of agreed-upon goods.”

Gen. Injectables & Vaccines, 519 F.3d at 1363; see, e.g., Fin. & Realty Servs., LLC v.

United States, 128 Fed. Cl. 770, 777 (2016) (“As a general rule, ‘the government is

entitled to strict compliance with contract specifications.’”) (quoting TEG–Paradigm

Envtl., Inc. v. United States, 465 F.3d 1329, 1342 (Fed. Cir. 2006)). Consistent

with repeated pre-award confirmation with AME, and as provided in the initial

solicitation and restated in the contract award itself, “the contract [was] terminated

for cause” when AME failed to deliver any PPE by the contracted non-extendable

deadline. See, e.g., ECF 15-1 at 128.

The immediacy of the termination is supported by AME’s anticipatory

repudiation. According to the only shipping status documentation AME shared

with the VA, three (of four) containers were estimated to arrive at the New York

port on June 9, 2021, two days after the PPE was contractually required to be

delivered to the Pennsylvania warehouse/distribution center; the fourth container

was estimated to arrive at the New York port on June 22, 2021, fifteen days after

the contracted delivery date. See ECF 15-1 at 38–42. By notifying the Contracting

Officer five days before the contractual deadline that it could not deliver any of the

10 million nitrile examination gloves by June 7, 2021, AME effectively renunciated

its “contractual duty before the time fixed in the contract for performance” which

constituted a repudiation. Franconia Assocs. v. United States, 536 U.S. 129, 130

(2002) (emphasis in original); Restatement (Second) of Contracts (“Restatement”)

§ 250 (1981) (“[L]anguage that under a fair reading ‘amounts to a statement of

intention not to perform except on conditions which go beyond the contract’

constitutes a repudiation.”). AME’s anticipatory repudiation, accompanied by

non-performance, “give[s] rise to a claim for total breach.” Restatement § 243(b).

AME questions whether the Contracting Officer’s decision to terminate the

contract was in the best interest of the government, arguing that re-procurement

would take longer than awaiting AME’s late delivery. As an initial matter, in a

related bid protest, the Government Accountability Office (GAO) rejected AME’s

argument that the VA’s award of certain other PPE supply contracts under the

same solicitation were unlawful re-procurements, finding that they “were made

under the existing solicitation and were not re-procurements.” The Noble Att’y,

LLC; Am. Med. Equip., Inc., B-419884 et al., 2021 CPD ¶ 276, 2021 WL 3602132,

at *4 (Comp. Gen. Aug. 2, 2021). 6 Indeed, as detailed supra, rather than award

one contract for the delivery of “hundreds of millions” of nitrile examination gloves,

the VA purposely awarded a series of “smaller quantity” PPE delivery contracts

under the same solicitation. See ECF 15-1 at 50–54; id. at 94 (initial solicitation

stating: “The Government intends to award one or more firm fixed price contracts

resulting from this solicitation”); see also ECF 15-3 (Dickey Depo. Tr.) at 23

6AME acknowledges that “all contracts were issued under the same solicitations,” thereby effectively

conceding the additional contracts were not re-procurements. See ECF 15 at 35 n.18.

14

(VA awarded nine contracts under the solicitation); id. at 28 (“We were in a multiple

award scenario situation. . . . [E]ach offer was put through the same system and it

was independent of the other offers.”). Such contracting effort increased the

likelihood that any contractor’s failure to perform would not impair the needs of

VA medical staff. Id. at 54 (commenting that “the VA [personnel] do have the

gloves to support what they need” at the time of AME’s contract was terminated).

Further, the VA’s termination decision was based on AME’s failure to deliver

any PPE by the strict non-extendable deadline, which the VA repeatedly and

unequivocally stressed to AME. AME repeatedly and unequivocally agreed to these

terms, likely because AME was expecting $366,000 in profit from the contract;

properly characterized as a 33% return on investments in 45 days. 7 The revelation

that AME commissioned manufacture of the gloves post-award and shipped them by

sea, in view of its ambiguous offer representation and contradictory pre-award

assurance of partnership with FedEx, likely raised concern about AME’s ability to

produce from the onset of its performance. Its repeated assurances—pre- and post-

award—regarding its ability to comply with the June 7, 2021 delivery deadline went

unrealized. Despite agreeing to provide regular updates, AME only informed the

VA of the purported May 2021 shipping delays five days before the contracted

delivery date and only after the VA requested an additional update. 8

AME’s conduct during its performance up to the time of termination instilled

in the VA Contracting Office little confidence that its claimed new delivery dates

would materialize, and AME provided no assurance that they would. See ECF 15-2

(Worsham Depo. Tr.) at 42 (“[T]he information [regarding the delay] came right

before the delivery date, in my opinion. So I do not believe they were open and

honest from the get-go when it came to that issue.”); ECF 15-3 (Dickey Depo. Tr.) at

71–72 (“I believe that there was discussions [sic] between the contracting officer and

the vendor whether or not they could guarantee the delivery within two days and

that was not able to be accomplished. So, therefore, there was no two-day extension

guarantee that the gloves would arrive on the vendor side, nor the contracting

side.”); id. at 77 (“[AME could] never guarantee the delivery date, the new delivery

date”), id. at 79 (“If you look [at] the way [AME’s email is] written, it says ‘it’s now

expected to arrive.’ There’s no will, shall, or must arrive. . . . I believe there was

other [sic] discussions other than this that they could not guarantee the 6-22 date.”).

The VA’s concerns about the materialization of the claimed new delivery dates were

validated when, as it turned out, none of the four containers arrived on the dates

7 Quoting the VA $1.469 million for the supply contract, AME claims it paid a total of $1,103,500

“for the gloves and shipment of the gloves.” ECF 1 ¶ 11.

8Given the firm 45-day deadline and AME’s commitment to provide weekly updates, at a minimum,

AME should have monitored and confirmed, in early May 2021 (i.e., the time of purported delay)

whether and when its commissioned ships left the Chinese port.

15

AME represented in its June 2, 2021 email to the VA or its argument to the Court. 9

“Well-established precedent holds that the government is entitled to strict

compliance when it contracts for goods.” Hannon Elec. Co. v. United States,

31 Fed. Cl. 135, 147 (1994), aff’d, 52 F.3d 343 (Fed. Cir. 1995). Allowing a

contractor to unilaterally modify an essential and repeatedly confirmed contract

term after-the-fact with little assurance for future delivery, however desirable it

may be to the contractor, does not the serve the best interests of the government.

Based on AME’s record of conduct and ultimate failure to deliver any PPE by the

established delivery date, the Contracting Officer consulted the procurement team

and legal counsel and “determined terminating AME’s contract was in the best

interest of the Government.” ECF 11-2 at 67–68 (Worsham Decl. at ¶¶ 8–15);

see ECF 15-2 (Worsham Depo. Tr.) at 41; accord ECF 15-3 (Dickey Depo. Tr.) at 54

(“[I]t is in the government’s interest, when there’s an agreement made between a

contractor and the government, that the government gets what is intended from the

contract.”). The circumstances surrounding AME’s (non)performance, discussed

supra, supports the Contracting Officer’s determination. See Nuclear Rsch. Corp.,

814 F.2d at 650–651 (finding default termination proper where the factual

circumstances support contracting officer’s informed decision that termination

would be in best interest of the government).

III. Claims of Excusable Delay

AME asserts that its nonperformance was excusable because the primary

cause was “global and industry-wide shipping delays” due to a sudden COVID-19

outbreak restricting operations at the loading port in China. AME further claims

that the contract did not forbid sourcing the PPE abroad and that the VA cannot

reasonably rely upon a strict definition of “on hand” under the contract. In opting to

procure post-award manufacture of the 10 million nitrile examination gloves from a

Chinese OEM and then import them by container ship, however, AME alone bore

the risk of both additional delays and failing to meet the strict delivery deadline.

A. “On Hand” Gloves and 45-Day Delivery

Against the backdrop of the rampant spread of COVID-19 and increasing

PPE demand in VA healthcare facilities nationwide, the VA issued the solicitation

at issue for “on-hand (or already in existence)” nitrile examination gloves available

for delivery within 45 days. See ECF 15-1 at 50; ECF 15-3 (Dickey Depo. Tr.) at 34

(“we were very specific in [the] solicitation” that it was “a request for on-hand

gloves, not manufactured gloves); Orsa Techs., LLC v. DVA, CBCA 7141, 22-1 BCA

9 According to the container tracking information, available on https://ct.shipmentlink.com/servlet/

TDB1_CargoTracking.do and https://ecomm.one-line.com/one-ecom/manage-shipment/cargo-

tracking?trakNoParam (searchable by B/L or Booking number), AME’s commissioned containers

arrived at the New York port respectively on June 12, 13, 14, and 25, 2021.

16

¶ 38,025, 2022 WL 179215 (Jan. 18, 2022) (“The Government issued a solicitation

designed to obtain that safety equipment as quickly as possible, attempting to

guarantee fast delivery by limiting competition to contractors with those materials

‘on hand’ and ‘in-stock,’ with delivery of that ‘on hand’ safety equipment to be made

within forty-five days after contract award.”). Stressing the importance of meeting

the 45-day delivery deadline, the VA solicitation forewarned all potential

contractors, including AME, that the strict deadline would serve as an eligibility

requirement and that failure to meet the specified delivery deadline would result

in termination for default. ECF 15-1 at 95 (“Delivery Schedule: To be eligible for

award, Offerors must be able to deliver within 45 calendar days from the award

date.”); id. at 60 (“Contracts that are awarded based on submitted quotes will

have 45 calendar days from receipt of order (award date) to deliver the awarded

quantities, or the contract will be terminated for cause . . . .”) (emphasis added).

Reiterating these unequivocal contract terms, the Statement of Work

memorialized in AME’s contract award restates: “This is not a request for

manufacturing but a request for quantity on hand to be delivered within

45 calendar days from order.” See id. (solicitation); id. at 128 (award); ECF 15-3

(Dickey Depo. Tr.) at 62–63 (“that language was put into the solicitation and the

contract . . . for the vendor’s benefit to know the ramifications of not meeting the

contract.”). Moreover, throughout the solicitation and contract award process and

during the contract performance period, the VA reminded AME of the strict delivery

deadline. See, e.g., ECF 11-1 at 271 (“The delivery date is set for 07 June 2021 for

100% qty of gloves being awarded. No extensions will be granted. This includes

but is not limited to delays associated with the manufacturer, the supplier, shipping

delays, customs, lack of financing and the pandemic.”); see also id. at 266, 268–69;

ECF 11-2 at 25; ECF 15-1 at 36. Fully aware from the outset of the firm 45-day

delivery deadline and the risk of default termination, AME submitted an offer and,

thereafter, repeatedly assured the VA that the strict deadline would be met.

See, e.g., ECF 11-1 at 226, 266, 268, 271; ECF 11-2 at 25; ECF 15-1 at 25–26, 35.

At bottom, in awarding AME the PPE supply contract, the VA made clear

that the government was seeking delivery of 10 million nitrile examination gloves

to its warehouse/distribution center within 45 days of award; the government was

not soliciting a manufacturing contract (or subcontract) or entertaining a contractor

unwilling or unable to comply with the strict deadline and banking on obtaining

an extension. AME accepted the contract award under these terms: deliver the

required PPE within 45 days or face termination for default. That the contract did

not expressly prohibit AME from procuring the PPE from an overseas manufacturer

and awaiting award of the government contract before ordering production of the

gloves does not excuse AME’s failure to meet the 45-day delivery deadline or justify

its demand for extension. To find otherwise would empower AME to unilaterally

modify a critical contract term after-the-fact despite the VA’s unwavering position

on the issue from the outset. It would also force the government to bear the burden

17

of the calculated risks AME accepted in opting not to locate a manufacturer or

supplier with existing inventory or, at a minimum, a domestic manufacturer or

supplier.

B. Shipping Delays

Citing the “excusable delays” clause of the contract, ECF 15-1 at 132, AME

asserts that the container shipping delays amid the global pandemic merited an

extension of contract performance. By its terms, however, FAR 52.212-4(f) is not

triggered where the contractor or its subcontractor bears responsibility for the

delay. 10 Gen. Injectables & Vaccines, 519 F.3d at 1365. Here, as explained supra,

AME elected to take the calculated risk of procuring the PPE from an overseas

manufacturer and awaiting award of the government contract before ordering

production of the gloves. Consequently, AME alone bears the fault for burning

the initial two-week period (out of 45 days) attributed to manufacturing before

placing the PPE in shipment (i.e., April 20 to May 4, 2021). Compare ECF 11-2 at

25 (April 20, 2021 supply contract award) with id. at 33 (AME representation that

production of the 10 million gloves was to be completed by April 29, 2021) and ECF

15-1 at 17 (May 3, 2021 AME representation that 75% of the required PPE supply

was sent to the port of origin in China, with the remaining PPE scheduled to be

sent to the port on May 4, 2021).

Further, to bolster its pre-award assertion that the PPE delivery would be

timely, on February 26, 2021, AME represented to the VA that it had arranged to

transport the gloves with FedEx. ECF 11-1 at 246. On May 4, 2021, two weeks

into contract performance, AME revealed that the PPE would be transported via

container ship and not FedEx. ECF 11-2 at 37. No explanation was provided for

the change in carrier or mode of transport, and nothing in the record supports the

counterintuitive notion that importation to the United States from China is faster

by sea than by air. 11 Regardless, as with AME’s decision to manufacture post-

award, AME alone bears the calculated risks—and the negative consequences of

10The parties dispute whether or not BNX, the shipping company AME commissioned, qualifies as

a “common carrier” under FAR 52.212-4(f) or is AME’s subcontractor. Compare ECF 11 at 39 n.7

with ECF 15 at 18–19, 19 n.10. While the record does not include sufficient information to enable a

conclusive determination, the Court notes the “common carrier” designation is not dispositive and

does not affect the inexcusability analysis and conclusion herein.

11 Even if AME had intended to use FedEx’s ocean cargo services, the initial impression made on the

VA appears to be FedEx shipment via air. See ECF 11-1 at 246 (February 26, 2021 email from AME

to VA: “We have already teamed up with Fedex [sic] to secure logistics supply chain for this contract

,if [sic] awarded.”); ECF 11-2 at 37–38 (May 3, 2021 email from VA to AME: “Are these being shipped

via air or container ships?”). AME claims, in a footnote, that “AME utilized container ships because

it was faster than the timeline presented by Fedex [sic].” ECF 24 at 14 n.3. AME cites no support

for its assertion and the Court finds no corroborative evidence in the record.

18

any resulting delays—attributable to its decision to import the PPE by container

ship rather than FedEx.

AME maintains that all four shipping containers were originally scheduled

to arrive at the destination port in New York on June 1, 2021, but were delayed

because of unspecified COVID-19 related restrictions at the loading port in China.

See ECF 15-1 at 18, 23. Aside from AME’s May 25, and June 2, 2021 unsupported

representations to the VA, nothing in the record corroborates these assertions. On

the contrary, the “Arrival Notice[s] / Freight Invoice[s]” and other shipping

notification AME shared with the VA suggest otherwise. For three of the four

shipping containers, the documentation lists May 6, 2021, as the estimated time of

departure (ETD) from Yantian, China, and June 9, 2021, as the estimated time of

arrival (ETA) in New York, New York. Id. at 38–40. As for the fourth shipping

container—clearly delayed—the Change of Vessel Notification lists May 6, 2021, as

the original ETD from Yantian and June 8, 2021, as the ETA in New York; the re-

nominated dates listed are May 22, 2021 (ETD Yantian) and June 22, 2021 (ETA

New York). Id. at 41–42. These dates align with AME’s May 3, 2021 report of the

four containers being sent to the loading port by May 4, 2021; and no evidence in

the record indicates an earlier ETA. Based upon the record presented, the

Court finds that AME’s contracted supply of 10 million nitrile examination gloves

were never scheduled to arrive at the designated DLA warehouse/distribution

center in Pennsylvania on or before the June 7, 2021 delivery deadline. 12

Despite having agreed to provide “weekly updates” to the VA Contracting

Office, see ECF 11-1 at 271, AME did not reveal the alleged early May 2021

shipping delays until June 2, 2021, after the VA requested an update from them;

the update revealing the containers would not arrive in time came one day after the

date AME represented to the VA that the four containers were scheduled to arrive

in New York. See ECF 15-1 at 23. AME’s failure to secure and share more timely

delivery updates during the period of contract performance does not support a

finding that AME was “without . . . fault or negligence.” Gen. Injectables &

Vaccines, 519 F.3d at 1363 (citing FAR 52.212-4(f)). A contractor’s mere reference

12 The specific shipping documentation included in the record, cited above, trumps AME’s current

citation to general reports and media coverage regarding the overall impact of the pandemic on

the global shipping industry and Chinese ports throughout 2020 and into 2021. By the time the

April 20, 2021 PPE supply contract was awarded—over a year into the pandemic—AME should have

considered the possibility of COVID-19-related and transatlantic shipping delays before committing

to manufacture 10 million nitrile examination gloves in China, then transport them by sea, then

get them through U.S. Customs, and then drayage to a designated warehouse/distribution center in

the United States within 45 days; especially considering AME was warned in an April 16, 2021 email

from Contracting Officer Worsham that no extensions would be granted due to delays associated

with the pandemic. See ECF 11-1 at 271; Orsa Techs., LLC, CBCA 7141, 22-1 BCA ¶ 38,025

(“Because [the contractor] was well aware of the pandemic when it executed the contract at issue

and was supposed to have had the gloves ‘on hand’ when it entered the contract, it cannot use the

pandemic as a cause of excusable delay.”).

19

to a listed event under FAR 52.212-4(f) (e.g., delays of common carriers, quarantine

restrictions) does not automatically excuse noncompliance particularly where,

as here, the contractor accepted calculated risks of delayed delivery and opted to

arrange supply of the PPE the way it did. See United States v. Brooks-Callaway

Co., 318 U.S. 120, 124 (1943) (“If fire is always an excuse, a contractor is free to use

inflammable materials in a tinder-box factory and escape any damages for delay

due to a resulting fire.”). Based on the facts presented, excusing AME’s untimely

performance would “mak[e] the time fixed for completion practically meaningless

and depriv[e] the Government of all recompense for the delay.” Id.

For these reasons, the Court finds that AME has not met its shifted burden

of demonstrating that its failure to timely perform under the PPE supply contract

was excusable.

IV. Implied Duty of Good Faith & Fair Dealing

Finally, AME argues that, by not extending the contract deadline to allow

AME’s late delivery, the government violated its implied duty of good faith and

fair dealing. “The duty of good faith and fair dealing is inherent in every contract.

In essence, this duty requires a party to not interfere with another party’s rights

under the contract.” Precision Pine & Timber, Inc. v. United States, 596 F.3d 817,

828 (Fed. Cir. 2010) (citing Restatement § 205). As explained by the Federal

Circuit:

Cases in which the government has been found to violate the implied

duty of good faith and fair dealing typically involve some variation on

the old bait-and-switch. First, the government enters into a contract

that awards a significant benefit in exchange for consideration. Then,

the government eliminates or rescinds that contractual provision or

benefit through a subsequent action directed at the existing contract.

The government may be liable for damages when the subsequent

government action is specifically designed to reappropriate the benefits

the other party expected to obtain from the transaction, thereby

abrogating the government’s obligations under the contract.

Id. at 829 (internal citations omitted). What the precise duty of good faith and fair

dealing entails in a particular case “depends in part on what that contract promises

(or disclaims).” Id. at 830.

In this case, as discussed supra, the express language of the PPE supply

contract, fully supported by the parties’ pre- and post-award communications,

makes clear that the 45-day delivery deadline was firm, that no extensions would be

granted, and that AME’s failure to meet the contractual deadline would result in a

termination for cause. Accordingly, as in Precision Pine & Timber, Inc., “[t]here are

no . . . indicia of a governmental bait-and-switch or double crossing at work here.”

20

Id. at 829. In terminating AME’s contract, the VA Contracting Office did not

“specifically target” AME, nor did it “reappropriate any ‘benefit’ guaranteed by the

contract[].” Id. The contract did not guarantee that extensions of time would be

granted (and in fact stressed the opposite) and did not insulate AME from the

consequences of the calculated risks it took in performing under the contract.

Put simply, the “implied duty of good faith and fair dealing cannot expand

a party’s contractual duties beyond those in the express contract or create duties

inconsistent with the contract’s provisions.” Metcalf Const. Co. v. United States,

742 F.3d 984, 991 (Fed. Cir. 2014) (quoting Precision Pine & Timber, Inc., 596 F.3d

at 831). AME accepted the unequivocal terms to deliver 10 million nitrile

examination gloves to the designated DLA warehouse/distribution center within the

strict 45-day deadline in exchange for an expected $366,000 profit, or else risk

default termination. The implied duty of good faith and fair dealing, “limited by

the original bargain,” does not justify modifying the terms as AME now wishes,

allowing AME to reap the benefit of the bargain while insulating it from the

consequences of the calculated risks the company undertook in executing contract

performance. Id. (implied duty of good faith cannot “alter[] the contract’s

discernible allocation of risks and benefits” or “conflict[] with a contract

provision.”). 13 The Court finds that the government did not breach its implied duty

of good faith and fair dealing.

CONCLUSION

For the reasons stated above, defendant’s motion for summary judgment

(ECF 11) is GRANTED and plaintiff’s cross-motion for summary judgment (ECF

15) is DENIED. The Clerk is directed to ENTER judgment accordingly.

IT IS SO ORDERED.

___________________

Armando O. Bonilla

Judge

13In further support of this argument, AME reiterates its contention that termination was not in the

best interest of the government. ECF 15 at 34 n.17. For the reasons stated supra, the Court finds

that argument unpersuasive.

21