Opinion

Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC

Court
Commonwealth Court of Pennsylvania
Filed
May 5, 2022
Status
Unpublished
On the bench
Cohn Jubelirer, President Judge
Cited by
0 cases
Authority
More cited than 8.3%

The opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Transource Pennsylvania, LLC, and :

PPL Electric Utilities Corporation, :

Petitioners :

:

v. : No. 689 C.D. 2021

: Argued: March 7, 2022

Pennsylvania Public Utility :

Commission, :

Respondent :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge

HONORABLE ELLEN CEISLER, Judge

HONORABLE LORI A. DUMAS, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY

PRESIDENT JUDGE COHN JUBELIRER FILED: May 5, 2022

Transource Pennsylvania, LLC (Transource) and PPL Electric Utilities

Corporation (PPL) (together, Petitioners) petition for review of the May 24, 2021

Opinion and Order of the Pennsylvania Public Utility Commission (Commission)

that, in relevant part, denied an application and an amended application for the siting

and construction of two high-voltage (HV) transmission lines related to the

Independence Energy Connection (IEC) Project in Franklin and York Counties,

Pennsylvania (Siting Applications), and rescinded the provisional certificate of

public convenience (CPC) that the Commission had previously granted Transource

for the IEC Project. The Commission concluded that there was no error or abuse of

discretion in the Administrative Law Judge’s (ALJ) determination that Transource

failed to establish the requisite need for the IEC Project under Section 57.76(a)(1)

of the Commission’s Regulations (Regulations), 52 Pa. Code § 57.76(a)(1), or met

the requirements of Section 1501 of the Public Utility Code (Code), 66 Pa.C.S.

§ 1501. The Commission held that the ALJ’s findings of fact were supported by

substantial evidence, in the form of the credited evidence submitted by opposing or

objecting parties. The Commission further concluded that the ALJ’s determinations,

including that the Commission could evaluate the need for the IEC Project for

purposes of Pennsylvania law independently of the evaluation of need for the IEC

Project that had been performed by PJM Interconnection LLC (PJM), were

consistent with the Code, the Regulations, and Pennsylvania law.1

On appeal, Petitioners argue that the Commission erred in interpreting Section

1501 of the Code and Section 57.76(a)(1) of the Regulations and used an incorrect

standard in denying the Siting Applications. Petitioners assert that the findings of

fact necessary to support the conclusion of a lack of need or necessity for the IEC

Project were not supported by substantial evidence. As part of its evidentiary

challenge, Petitioners assert that the Commission erred in rejecting PJM’s findings

as evidence of need for the IEC Project under Pennsylvania law and in focusing only

on the negative impacts on local rates. Finally, Petitioners maintain that the

Commission erred in rescinding the provisional CPC and not resolving the merits of

Petitioners’ other Exceptions based on its decision on the Siting Applications, and,

therefore, this matter must be remanded.

1

The ALJ also recommended denying the Siting Applications because Transource did not

establish that it met the requirements of the other subparts of Section 57.76(a) of the Regulations

and denying applications related to the construction of structures related to the IEC Project in

Franklin and York Counties and to exercise the power of eminent domain over properties in

Franklin County. (Recommended Decision (R.D.) at 103-24, Order.) Petitioners filed Exceptions

to these determinations, but because the Commission affirmed the denial of the Siting Applications

on the lack of need, it did not specifically address these Exceptions beyond finding that they were

moot. (Commission Opinion and Order (Op. and Order) at 64-65, 67-73.)

2

The Commission and Intervenors, the Office of Consumer Advocate (OCA),

the County of Franklin (Franklin County), and Stop Transource Franklin County

(STFC), respond that the Commission’s interpretations of the Code and the

Regulations were not clearly erroneous and, therefore, are entitled to deference.

They further argue that the Commission applied the correct standard in determining

that Transource did not meet its burden of proof on the Siting Applications and

rescinding the provisional CPC. The Commission and Franklin County also assert

that Petitioners have waived certain of these issues as they had not been raised before

the Commission. Intervenors and the Commission further argue that the findings of

fact are supported by substantial evidence and that Petitioners’ arguments to the

contrary improperly seek to have this Court reweigh the evidence or to preclude the

Commission from performing its own evidentiary review and consideration of the

IEC Project. Finally, the Commission asserts there was no error in it not considering

Petitioners’ other Exceptions based on its determination on the Siting Applications.

I. BACKGROUND

A. Relevant Statutory Provisions

This matter involves the denial of the Siting Applications and the rescission

of Transource’s provisional CPC pursuant to Section 57.76(a) of the Regulations

and Section 1501 of the Code. Section 1501 of the Code addresses, generally, the

character of services and facilities of a public utility and provides, in pertinent part:

Every public utility shall furnish and maintain adequate, efficient, safe,

and reasonable service and facilities, and shall make all such repairs,

changes, alterations, substitutions, extensions, and improvements in or

to such service and facilities as shall be necessary or proper for the

accommodation, convenience, and safety of its patrons, employees, and

the public. . . . Such service and facilities shall be in conformity with

the regulations and orders of the [C]ommission.

3

66 Pa.C.S. § 1501. Section 57.76(a) of the Regulations relates to the siting and

construction of HV lines and states:

(a) The Commission will issue its order, with its opinion, if any, either

granting or denying the application, in whole or in part, as filed or

upon the terms, conditions or modifications, of the location,

construction, operation or maintenance of the line as the

Commission may deem appropriate. The Commission will not grant

the application, either as proposed or as modified, unless it finds and

determines as to the proposed HV line:

(1) That there is a need for it.

52 Pa. Code § 57.76(a)(1). Pursuant to Section 57.75(e)(1) of the Regulations, in

reviewing a siting application, the Commission must accept evidence of, among

other things, the “present and future necessity of the proposed HV line in furnishing

service to the public.” 52 Pa. Code § 57.75(e)(1).

In addition, this matter implicates Pennsylvania’s participation in regional

interstate power pools with other states, which is addressed in Section 2805(a) of the

Code. Section 2805(a) provides:

The [C]ommission shall take all necessary and appropriate steps to

encourage interstate power pools to enhance competition and to

complement industry restructuring on a regional basis. The

Commonwealth, the [C]ommission and Pennsylvania electric utilities

shall work with the Federal Government, other states in the region and

interstate power pools to accomplish the goals of restructuring and to

establish independent system operators or their functional equivalents

to operate the transmission system and interstate power pools. The

[C]ommission, Pennsylvania electric utilities and all electricity

suppliers shall work with the Federal Government, other states in the

region, the North American Electric Reliability Council [(NERC)] and

its regional coordinating councils or their successors, interstate power

pools, and with the independent system operator or its functional

equivalent to ensure the continued provision of adequate, safe and

reliable electric service to the citizens and businesses of this

Commonwealth.

4

66 Pa.C.S. § 2805(a).2

B. The IEC Project and Transource

In 2014, PJM, the Regional Transmission Organization charged with

managing electric utilities transmission systems in 13 states (PJM Region), that

includes most of Pennsylvania, Maryland, Virginia, and West Virginia, performed

an annual Regional Transmission Extension Plan (RTEP) of the PJM Region.

(Commission Opinion and Order (Op. and Order) at 3.)3 As part of the RTEP, PJM

conducted a market efficiency analysis to determine if there were areas where market

congestion4 existed, which was found on the AP South Reactive Interface (APSRI).

(Id.) “[O]n October 30, 2014, PJM opened a long-term RTEP proposal window”

and sought “market efficiency proposals in order to alleviate congestion on the

AP[SRI].” (Id.) During this process, it was projected that the “[c]ongestion on the

AP[SRI] totaled approximately $800 million from 2012 to 2016.” (Id.)

PJM received 41 proposals, and, on August 2, 2016, approved the market

efficiency project, known as Project 9A, submitted by Transource Energy,

Transource’s parent, to alleviate the APSRI congestion. (Id. at 2-3.) Project 9A is

a set of 4,500 kV transmission lines originating in West Virginia and terminating in

Maryland. (Id. at 3.) The IEC Project is the Pennsylvania portion of Project 9A,

and consists of IEC West, located in Franklin County, and IEC East, located in York

2

Section 2805(a) is located in Chapter 28 of the Code, which deregulated Pennsylvania’s

electric utility industry. See Section 2802 of the Code, 66 Pa.C.S. § 2802 (announcing the

declaration of policy to, among other things, deregulate the electric utility industry to encourage

greater competition in the wholesale electric market).

3

The Commission’s Opinion and Order is located at volume 7 pages 6427a through 6506a

of the Reproduced Record.

4

“Congestion occurs when the least costly resources that are available to serve load in a

given region cannot be dispatched because transmission facility limits constrain power flow on the

system.” (Recommended Decision, Finding of Fact ¶ 35.)

5

County, and involves HV transmission lines from new substations in those counties

to the Pennsylvania/Maryland border. (Id. at 3, 5-6.) Transource was “formed solely

to carry out . . . Project 9A.” (Id. at 2-3.)

Transource filed an “Application for All of the Necessary Authority,

Approvals, and Certificates of Public Convenience” relating to the IEC Project on

February 8, 2017. (Id. at 4.) The Commission recognized that Transource was “a

new type of entity in” Pennsylvania and was formed only to “carry out a particular

market efficiency project.” (Id. at 5 (internal quotations omitted).) On January 23,

2018, the Commission issued the provisional CPC, and its provisional approval

referenced, specifically, Project 9A, including the IEC Project, as a means to resolve

congestion on the APSRI.5 (Id. at 4 (citing Application of Transource, Pennsylvania,

LLC, Docket Nos. A-2017-2587821 & G-2017-2587822 (PUC Jan. 23, 2018)).)

Although the provisional CPC was granted, “all parties reserved the right to

challenge the need for the [IEC] Project when Transource file[d] a siting application

with the Commission or to challenge any other project proposed by Transource.”

(Id. at 5.) Transource subsequently filed additional applications relating to the

construction of buildings or shelters and the exercise of eminent domain over various

properties in Franklin and York Counties. (Id. at 8.) PPL, an intervenor in the

Commission proceedings, became involved in the IEC East portion when it and

Transource entered into an agreement allowing Transource to utilize PPL’s existing

transmission infrastructure and rights-of-way for the IEC East portion of the IEC

Project.6 (Id. at 14-16.) As the design of the IEC Project was altered, Transource

5

The approval of the provisional CPC was part of a settlement agreement.

6

As a result of this agreement, there was no need for Transource to use eminent domain in

York County.

6

amended its various applications, including by adding PPL to the applications

relevant to the IEC East portion.

C. Proceedings Before the ALJ and the Recommended Decision

Transource’s applications were assigned to an ALJ7 for disposition. OCA,

STFC, and Franklin County, among others, intervened before the ALJ, with other

landowners, citizens, and entities filing protests.8 Between January 8, 2018, and

September 25, 2020, the ALJ held prehearing conferences, public input sessions, site

visits, and evidentiary hearings, and the parties served and submitted their respective

written submissions.

1. Evidence

Transource filed written direct, rebuttal, and rejoinder statements setting forth

its experts’ testimonies, as well as reports and studies, in support of its applications.

Several of its witnesses were cross-examined at evidentiary hearings before the ALJ.

Through this evidence, Transource sought to establish that the IEC Project satisfied

the need requirements of the Code and the Regulations through PJM’s cost-benefit

analysis, which was approved by the Federal Energy Regulatory Commission

(FERC), and is based on a 15-year projection of costs of a proposed project and

annual benefits for the first 15 years of the Project’s life. (Recommended Decision

(R.D.), Findings of Fact (FOF) ¶¶ 39, 41, 66.)9 Multiple re-evaluations continued to

show that the IEC Project met PJM’s cost-benefit analysis, thereby reflecting that it

7

Initially, the matter was assigned to two ALJs, but the second ALJ no longer participated

after March 1, 2020.

8

The Office of Small Business Advocate (OSBA) and various affected landowners and

entities were also granted intervenor status. (Op. and Order at 7-8.)

9

The Recommended Decision is located at volume 5 pages 4768a through 4901a of the

Reproduced Record.

7

continued to meet that standard. (R.D. at 66-67.) Transource offered former

Commission Chairman James Cawley’s testimony that no group is entitled to the

artificially lowered costs that result from market congestion and that considering the

benefits of congestion would be unreasonable because it would perpetrate

discriminatory rates. (Id. at 71-72.) Transource’s witnesses further asserted that the

IEC Project resolved congestion within the APSRI but was not intended to just

address congestion there but also elsewhere in the region, including the AP South

Area and “related constraints.” (Id. at 72-73.)

Transource offered the testimony of PJM’s vice president, Steven Herling,

who stated that congestion and reliability issues are often related. (Id. at 67, 74.) It

further presented evidence that, in November 2018, which was after OCA presented

direct testimony on the Siting Applications, PJM ran a single generation

deliverability study without the IEC Project. (FOF ¶¶ 83, 85.) That study revealed

five potential NERC reliability violations that could occur in 2023, which were

resolved by the IEC Project. (Id. ¶ 83, R.D. at 68.) Mr. Herling further testified that

if the IEC Project is not constructed, PJM would have to find an alternative solution,

and there was not enough time to address those reliability violations. (R.D. at 68-

69.) Transource further argued that the IEC Project provided benefits to

Pennsylvania beyond resolving market congestion and reliability issues, including

providing Pennsylvania generators with better access to markets and participating in

regional planning through PJM, as testified to by Mr. Cawley. (Id. at 71.)

Intervenors filed written statements, surrebuttal and supplemental surrebuttal

statements with their experts’ testimonies in opposition to the IEC Project. This

evidence raised questions regarding the ongoing need for the IEC Project where

Transource continued to rely on outdated data and the congestion in the APSRI did

8

not occur as predicted and, therefore, the identified purpose for the IEC Project was

no longer valid. (R.D. at 75-76.) For example, while congestion costs in the APSRI

in 2014 were approximately $468.8 million, in 2016 and 2017, those costs,

respectively, were $16.8 million and $21.6 million, and, by 2019, congestion costs

were $14.5 million. (FOF ¶¶ 51-52, 55.) Further, evidence showed that demand for

the PJM Region in general has decreased and that congestion event hours on the

APSRI has dropped considerably since 2015. (Id. ¶¶ 57-58.) OCA submitted

evidence reflecting that there have been recommendations to reevaluate PJM’s

market efficiency process and that PJM’s cost-benefit analysis did not consider any

increased costs or negative consequences to ratepayers elsewhere in the PJM Region

that are caused by constructing a market efficiency project. (Id. ¶¶ 45-46, 61-62,

117.) When such consequences were considered, the savings derived from the IEC

Project, which was estimated to cost $500 million, would decrease wholesale power

prices in some areas by approximately $845 million but would increase those prices

in other areas by $812 million, resulting in a net benefit of only around $32 million

over 15 years. (Id. ¶¶ 65, 110.)

OCA offered other evidence reflecting that the projected savings resulting

from the IEC Project would not be born out when other factors, including changes

in energy generation, were considered or under the additional simulations performed

by PJM. (Id. ¶¶ 73-81, 89, 97-104.) Further, areas that once benefited from the IEC

Project, both in Pennsylvania and elsewhere in the PJM Region, no longer benefited

in PJM’s most recent simulations. (Id. ¶¶ 102, 104, 107-08.) In Pennsylvania, the

IEC Project would lower wholesale power prices in certain areas of Pennsylvania by

about $60 million over the first 15 years of the IEC Project but would increase power

9

prices elsewhere in Pennsylvania by $429 million in the same period. (Id. ¶¶ 122,

124.)10

2. The Recommended Decision

On December 22, 2020, the ALJ issued the Recommended Decision, which

recommended denying the Siting Applications, as well as Transource’s other

ancillary applications. The ALJ held that the threshold issue was whether

Transource had demonstrated, by substantial evidence, that the IEC Project was

needed. According to the ALJ, Transource had to establish “that the IEC Project is

necessary to maintain adequate, efficient, safe, and reasonable service and facilities,”

pursuant to Section 1501 of the Code, and that there was a need for the HV

transmission lines under Section 57.76(a) of the Regulations. (R.D. at 53.) Noting

that the Commission’s grant of the provisional CPC did not contain a

predetermination of need and was narrowly tailored to the IEC Project, the ALJ

explained that “Transource may not construct the IEC [P]roject unless it can show

that the [P]roject is necessary or proper, and in conformity with the [R]egulations .

. . , which govern transmission line siting” because an “unnecessary change

constitutes inadequate service to the public.” (Id. at 53-54, 60.)

The ALJ concluded that Transource had not shown need for the IEC Project

as required by Section 57.76(a) of the Regulations and Section 1501 of the Code,

and that PJM’s determination of need for the IEC Project in 2014-2015 to remove

congestion on the APSRI did not definitively establish “need” for purposes of

Pennsylvania law. The ALJ noted the question of whether resolving “congestion,”

10

Additional evidence was taken, and findings of fact made, related to the other factors

under Section 57.76(a) of the Regulations, such as environmental impacts and reasonable

alternatives.

10

alone, is sufficient to meet the need requirement under the Code and the Regulations

had not yet been answered and that this Court in Energy Conservation Council of

Pennsylvania v. Public Utility Commission, 995 A.2d 465 (Pa. Cmwlth. 2010), did

not resolve the issue, determining that reliability issues within the PJM Region

supported the finding of need without consideration of “congestion.” (Id. at 82-83.)

In reviewing the evidence and arguments, the ALJ was persuaded by

Intervenors’ evidence that, even if there had been congestion on the APSRI in 2014-

2015, it was no longer congested, and, therefore, did not support a need for the IEC

Project. The ALJ accepted as persuasive evidence that Transource continued to rely

on outdated data and on inaccurate projections to support an ongoing claim of need.

(Id. at 83.) The ALJ determined that Transource had, throughout the majority of the

proceedings, cited relieving congestion on the APSRI as the purpose of the IEC

Project and only later raised the resolution of congestion in the AP South Area and

potential NERC reliability violations as reasons for the IEC Project. (Id. at 83, 87-

88.) Citing, among other things, the lateness of the assertion of these reasons, the

lack of a full investigation into the reliability violations, the lack of details regarding

the alleged new congestion, and the failure to include alternative bases to resolve the

claimed projection in the calculation, the ALJ found the evidence was insufficient

to support need. (Id. at 83-84, 86-93.) The ALJ determined that the benefits of the

IEC Project had to be weighed against all the detrimental impacts, both economic

and environmental, accepting the criticisms of PJM’s cost-benefit analysis used,

including by PJM’s Independent Market Monitor. (Id. at 94-95, 97-101.) The ALJ

concluded that, based on the credible evidence offered by Intervenors, the IEC

Project would “not provide sufficient benefits to Pennsylvania or the PJM [R]egion

as [a] whole,” because there would only be a net benefit of $32.5 million to the PJM

11

Region over a 15-year period, particularly where it was designed to “address a

congestion constraint that has diminished to very low levels since the [IEC] Project

was selected.” (Id. at 97-98, 101-02.)

As for Transource’s arguments that PJM’s determination of need would be

binding due to this matter involving issues of interstate regional transmission subject

to FERC oversight, the ALJ held that the Commission was obligated to make an

independent determination based on Pennsylvania law. (Id. at 82, 86, 99-102.) The

ALJ further observed that while FERC has exclusive jurisdiction over the interstate

transmission of electric energy and wholesale electric process, that jurisdiction was

limited to matters that are not subject to state regulation. (Id. at 85 (citing Section

824(a) of the Federal Power Act, 16 U.S.C. § 824(a)).) According to the ALJ, FERC

recognized this limitation by stating that there is “longstanding state authority over

certain matters that are relevant to transmission planning and expansion, such as

matters relevant to siting, permitting, and construction” and that the FERC was in

no way invoking “an exercise of authority over those specific substantive matters

traditionally reserved to the states . . . .” (Id. (quoting Transmission Planning and

Cost Allocation by Transmission Owning & Operating Pub. Utils., 76 Fed. Reg.

¶¶ 49,842, 49,861 (Aug. 11, 2011) (FERC Order No. 1000)).) This means,

according to the ALJ, that FERC Order No. 1000 was “not intended to dictate

substantive outcomes” or to allow FERC to “determine what needs to be built, where

it needs to be built, and who needs to build it.” (Id. at 85 n.13 (quoting S.C. Pub.

Serv. Auth. v. Fed. Energy Reg. Comm’n, 762 F.3d 41, 57-58 (D.C. Cir. 2014)

(internal quotation marks and citation omitted)).)

For these reasons, the ALJ issued the Recommended Decision recommending

that the Commission deny the Siting Applications and all ancillary matters based on

12

Transource having failed to meet its burden of proving need for the IEC Project

under the Code and the Regulations. The ALJ additionally recommended that a Rule

to Show Cause be issued on why Transource’s provisional CPC should not be

rescinded.

D. Appeal to the Commission

Petitioners filed eight Exceptions to the Recommended Decision, to which

Intervenors filed Reply Exceptions. Relevant to the issues before us, Petitioners

argued, in Exception 1, that the ALJ erred in concluding that Transource did not

carry its burden of persuasion to establish the need for the Siting Applications

pursuant to Section 1501 of the Code and Section 57.76(a) of the Regulations. This

Exception asserted three general challenges to the ALJ’s decision: (1) the

Commission lacked authority to make an independent determination of need

pursuant to the Code and the Regulations separate from PJM’s determination of need

based on PJM’s authority as a federal regional transmission planning authority; (2)

the ALJ improperly weighed the evidence; and (3) the ALJ’s analysis

misapprehended the state and federal roles in the nature of and need for regional

transmission planning. (Reproduced Record (R.R.) Volume (Vol.) 5 at 4935a-59a.)

The Commission rejected each of these challenges and adopted and incorporated the

ALJ’s findings of fact and conclusions of law, unless expressly rejected or modified.

On the first challenge, the Commission rejected the notions that federal

jurisdiction controlled and that it was bound to accept PJM’s determinations on the

question of need for state approval of the PJM-approved regional transmission

project. It held that whether the Pennsylvania standards were satisfied fell under the

Commission’s jurisdiction and discretion under the Code, the Regulations, and

precedent. (Op. and Order at 54-55.) According to the Commission, the standard

13

used for determining need by PJM does not necessarily meet the requirements

established and weighed under Section 1501 of the Code, the Regulations, and

precedent. (Id. at 54.) The Commission concluded that the ALJ considered FERC

Order No. 1000 and “PJM’s regional planning responsibilities, and weighed those

considerations as part of, but not dispositive of, the weight of the evidence regarding

‘need’ under” Section 57.76(a) of the Regulations. (Id. at 55.) Citing the same

language in FERC Order No. 1000 and South Carolina Public Service Authority, the

Commission held that the PJM approval did “not guarantee approval for siting and

construction of transmission lines within the borders of . . . Pennsylvania.” (Id. at

56-58.)

The Commission explained that the determination of whether need is

established is broad and includes considering numerous factors, including the facts

before it and the potential impact of the project, and a weighing of all the evidence

presented. (Id. at 56.) Part of this determination, the Commission held, was its

discretion to consider all the economic and environmental impacts of a PJM-

approved project, even if PJM did not consider those impacts as part of its analysis.

(Id. at 58.) This included the negative impacts on ratepayers, both in Pennsylvania

and elsewhere in the PJM Region, that resulted from resolving congestion due to the

IEC Project. (Id. at 59.) Because the ALJ considered the regional planning impacts,

as well as the impacts on Pennsylvania customers, the Commission rejected

Petitioners’ argument that the ALJ improperly took a Pennsylvania-only approach.

(Id.) Noting the main purpose of the IEC Project was to resolve regional economic

congestion that was predicted to substantially increase utility rates elsewhere, the

Commission held its review of the project needed to examine the underlying data

14

and congestion trends to determine if the current data of those needs was more

persuasive than the detrimental impact. (Id. at 60.)

Applying these conclusions, the Commission agreed with the weight the ALJ

gave to the evidence. The Commission agreed that Intervenors’ arguments that the

data congestion relied upon by PJM to approve the IEC Project, which was tied to

the APSRI, was not reliable enough to meet Pennsylvania’s standard for need where

that data reflected substantial fluctuation and, ultimately, decline in congestion in

that area. (Id.) The Commission further cited Transource’s shifting bases for the

need of the IEC Project, from originally relieving congestion in the APSRI, then to

the potential reliability violations, and finally the resolution of other congestion on

“related constraints” in the AP South Area, which the Commission did not dismiss

outright as “new reasons,” but found reflected the nature and the scope of the IEC

Project. (Id. at 61.) Nonetheless, the Commission “agree[d] with the ALJ[] that the

relative weight of the evidence of the later-asserted bas[e]s for need for the project

diminishe[d] as it [became] more tangential to the unambiguous original driver of”

the IEC Project, which was the “alleviation of economic congestion on the

AP[SRI].” (Id. at 62.) Finally, the Commission explained it was not persuaded by

Petitioners’ challenges to the ALJ’s acceptance of Intervenors’ evidence criticizing

Transource’s evidence and PJM’s analysis as credible and persuasive. (Id.)

For these reasons, the Commission concluded:

Therefore, based upon the broad powers conferred upon [it], we find

that the ALJ properly construed the state versus federal roles regarding

transmission planning in the analysis and application of the relevant

statutory authority, applicable regulations and case law to the present

case. Accordingly, we shall reject [Petitioners’] arguments to the

contrary.

15

Based upon our review of the record in this proceeding, the relative

weight of the evidence presented, and the arguments of the [p]arties,

we conclude that in the present circumstances Transource fail[ed] to

carry the burden of persuasion by a preponderance of the evidence to

establish need for the proposed [S]iting Applications, pursuant to our

authority under Section 1501 of the Code and [Section 57.76(a)(1) of

the] . . . Regulations, 52 Pa. Code [§] 57.76(a)(1). Because we have

concluded that the evidence is insufficient to establish the required

element of “need” under [Section 57.76(a)(1) of the Regulations,] the

arguments related to the other required elements under [Section

57.76(a)(2)-(4)] are rendered moot and shall not be addressed.

(Op. and Order at 63-64.)

In addition, the Commission denied Petitioners’ Exception No. 5, which

challenged the ALJ’s recommendation relating to the rescission of Transource’s

provisional CPC. The Commission concluded that the grant of the provisional CPC

was related specifically to the IEC Project and specifically deferred the statutory

determination of need to a future proceeding. (Id. at 70.) Having found that

Transource had not established need, a statutory requirement for retaining the

provisional CPC, and the denial of the Siting Applications, the Commission held

that “the provisional need for which Transource’s CPC was issued will cease to

exist.” (Id. at 71.) Acting within its statutory authority and discretion, the

Commission concluded that “the failure to establish necessity of the service for

which the provisional CPC was issued . . . constitutes ‘cause’ to rescind the

provisional CPC.” (Id.) The Commission further denied Petitioners’ Exception that

asserted that the ALJ issued “faulty findings,” reasoning that the Exception was

insufficiently specific, the “[f]actual [f]indings and [c]onclusions of [l]aw were

based upon a careful review of the extensive and complex evidence presented in this

proceeding,” and the Exception was simply a general disagreement with those

16

findings and conclusions. (Id. at 73-74.) The Commission denied all of the

remaining Exceptions except one as moot.11 (Id. at 64-66, 72.)

Petitioners now petition for review of the Commission’s Opinion and Order.12

11

The Commission granted Petitioners’ Exception No. 4, concluding that the challenged

finding of fact appeared to improperly treat lay witness testimony as expert witness testimony and

striking that finding of fact. (Op. and Order at 65-66.)

12

In addition to filing a Petition for Review in this Court, Transource filed a suit against

the Commission in the United States District Court for the Middle District of Pennsylvania

(District Court), Transource Pennsylvania, LLC v. Dutrieuille, Docket No. 21-cv-1101, asserting

that the Commission violated the Supremacy and Dormant Commerce Clauses of the United States

Constitution. Petitioners included, in their Petition for Review, a reservation of the right to pursue

those federal claims in federal court pursuant to England v. Louisiana State Board of Medical

Examiners, 375 U.S. 411 (1964) (England Reservation). This reservation was reiterated in

Petitioners’ main brief and reply brief, and Petitioners have not provided any direct argument

regarding the federal constitutional claims. Rather, they assert that the issue before this Court is

whether the Commission “erred in applying state law when denying the [IEC] Project,” which is

distinct from its federal claims that the Commission lacked the legal authority to reject PJM’s

determinations under federal law. (Petitioners’ Reply Brief (Br.) at 29.) The Commission and

Franklin County argue that Petitioners have impliedly placed the federal issues before this Court

in this appeal by arguing that the Commission had to accept PJM’s determinations, and, as such,

we should address them.

Under the England doctrine, a litigant is required to advise state courts of its federal claims

“so that the state statute may be construed ‘in light of’ those claims,” England, 375 U.S. at 419-

21, and involves “a federal court abstain[ing] from deciding a federal constitutional issue to enable

the state courts to address an antecedent state-law issue,” San Remo Hotel, L.P. v. City & County

of San Francisco, 545 U.S. 323, 339 (2005). On August 26, 2021, the District Court denied a

challenge to its subject matter jurisdiction based on an allegation that Transource lacked standing

and, over Transource’s objection, abstained from considering the remainder of the motion to

dismiss. Transource Pa., LLC, (M.D. Pa. Aug. 26, 2021), 2021 WL 3784284, at *3-4, 10-12. In

doing so, the District Court noted, in part: resolution of the federal claims would not resolve the

state[]law claims at issue in the Commonwealth Court; while Transource had asserted an England

Reservation and maintained the federal claims would not be before the Commonwealth Court, it

also represented that it may “protectively brief” the federal claims in that matter; and the issues in

both matters, while distinctly worded, were substantially similar. Based on Transource’s

representation that it may protectively brief the federal claims in this Court, the District Court

reasoned that abstention was appropriate as there was “a distinct possibility that both courts may

essentially be asked to resolve the same issues,” and, therefore, “the same issues have at least been

presented before both courts.” Id. at *10-11 (emphasis in original).

(Footnote continued on next page…)

17

II. DISCUSSION

A. Relevant Legal Principles

Our review of the Commission’s Opinion and Order is guided by the

following legal principles. “Appellate review of a [Commission] order is limited to

determining whether a constitutional violation, an error of law, or a violation of

[Commission] procedure has occurred and whether necessary findings of fact are

supported by substantial evidence.” Popowsky v. Pa. Pub. Util. Comm’n, 910 A.2d

38, 48 (Pa. 2006) (Popowsky II). Where an agency action involves the exercise of

discretion, we will not find an abuse of that discretion in the absence of bad faith,

fraud, capricious actions, or an abuse of power. Slawek v. State Bd. of Med. Educ.

& Licensure, 586 A.2d 362, 365 (Pa. 1991). Pursuant to Section 332(a) of the Code,

66 Pa.C.S. § 332(a), the proponent of the order in a proceeding before the

Commission bears the burden of proof and must prove its case by a preponderance

of the evidence, which is evidence more convincing than that offered by the other

parties. Se-Ling Hosiery, Inc. v. Marguilies, 70 A.2d 854, 855-56 (Pa. 1950);

Samuel J. Lansberry, Inc. v. Pa. Pub. Util. Comm’n, 578 A.2d 600, 602 (Pa. Cmwlth.

1990). The burden of proof contains two distinct burdens, the burden of production

and the burden of persuasion. Riedel v. Cnty. of Allegheny, 633 A.2d 1325, 1328

n.11 (Pa. Cmwlth. 1993). “[T]he burden of persuasion never leaves the party on

Reviewing the issues presented and argued by Petitioners, which do not include any

“protective[] briefing” of the federal claims, id., the issues before this Court relate to whether the

Commission’s decision is consistent with Pennsylvania law and is supported by substantial

evidence, also a matter of Pennsylvania law. We read Petitioners’ arguments regarding the

Commission’s consideration of the PJM determinations as relating to substantial evidence, rather

than relating to federal preemption. Accordingly, we will not address the federal claims that

Transource has reserved for consideration in the District Court and focus instead on whether the

Commission’s decision is correct under Pennsylvania law.

18

whom it is originally cast, but the burden of production may shift during the course

of the proceedings.” Id.

Here, Petitioners argue that Transource met its burden of proof on the IEC

Project and that the Commission erred in interpreting Section 1501 of the Code and

Section 57.76(a) of the Regulations to conclude otherwise. They further argue that

the Commission’s findings necessary to support its conclusion that the IEC Project

does not meet the standard for approval under Pennsylvania law are not supported

by substantial evidence. Finally, Petitioners argue that the Commission erred in

rescinding the provisional CPC and not addressing the merits of the remaining

Exceptions.13 We address these arguments in turn.

B. Section 1501 of the Code and Section 57.76(a) of the Regulations

1. Parties’ Arguments

Petitioners argue that the Commission erred as a matter of law in interpreting

Section 1501 of the Code as requiring the IEC Project to be both necessary and

proper when that provision requires a proposed facility to be necessary or proper for

the service of the public. The Commission further erred in interpreting Section

57.76(a) of the Regulations as requiring Transource to prove that the IEC Project

was “reasonable and necessary and in the public interest,” which is inconsistent with

Section 1501’s recognition that a service may be approved if it is proper.

(Petitioners’ Brief (Br.) at 18 (quoting Op. and Order at 56).) Petitioners argue that

“proper” means something that is “appropriate to the purpose or circumstance; fit;

suitable.” (Id. at 19-20 (citing PPL Elec. Utils. Corp. v. Pub. Util. Comm’n (Pa.

Cmwlth., No. 624 C.D. 2019, filed Oct. 27, 2020), slip op. at 24) (quotation

13

Although Petitioners set forth eight separate arguments in their brief, those arguments

have been consolidated into these three main arguments.

19

omitted).)14 Petitioners assert that the IEC Project is a proper means of resolving

market congestion and the potential NERC violations, the latter of which relate to

the provision of safe and reasonable service. According to Petitioners, had the

Commission applied the correct standard, that is, considered whether the IEC Project

was “proper for the accommodation, convenience, and safety of . . . the public,” the

Siting Applications would have been granted. (Id. at 19-20.)

Petitioners further argue that the Commission erred in focusing solely on the

potential impact to Pennsylvania rates, rather than considering the mitigation of

regional market congestion, in concluding that there was no need for the IEC Project.

That prices may increase for Pennsylvania ratepayers due to the resolution of

congestion and market inefficiencies is not, per Mr. Cawley, a “cost” that should be

considered in ascertaining whether a project is proper or needed under, respectively,

Section 1501 of the Code and Section 57.76(a) of the Regulations. (Petitioners’ Br.

at 41-42.) Citing Section 2805(a) of the Code, Petitioners assert the Commission is

required to consider regional concerns and to work with PJM to support and enhance

regional transmission planning, from which Pennsylvania benefits. In focusing on

local rates in a matter involving a project related to resolving wholesale impacts to

the PJM Region, Petitioners maintain that the Commission did not comply with its

obligation to support regional transmission planning as required by Section 2805(a).

The Commission responds that it properly interpreted and applied Section

1501 of the Code and Section 57.76(a) of the Regulations in reviewing whether the

IEC Project met the standards for approval under Pennsylvania law. It considered

14

PPL Electric Utilities is an unreported opinion which, while not binding, may be cited

for its persuasiveness pursuant to Pennsylvania Rule of Appellate Procedure 126(b), Pa.R.A.P.

126(b), and Section 414(a) of this Court’s Internal Operating Procedures, 210 Pa. Code

§ 69.414(a).

20

whether the IEC Project was necessary or proper and if it was needed and, based on

its evidentiary weight determinations, found that the IEC Project was not. To the

extent that Petitioners maintain all that was required to be proven was that the IEC

Project was proper under Section 1501 of the Code, Transource did not make this

argument before it or the ALJ and, therefore, any such claim has been waived. Even

if not waived, the Commission contends that the propriety of a project is not so broad

as Petitioners assert, as a project should be “suitable” and “fitting,” and substantial

evidence supports that the IEC Project is not suitable or fitting for its purported

purpose. (Commission’s Br. at 42 (quoting Merriam-Webster Thesaurus, available

at https://www.merriam-webster.com/thesaurus/proper (last visited May 4, 2022)).)

The Commission also argues that necessity for proposed transmission lines

may be found when such lines provide lower prices or improved reliability, Hess v.

Pennsylvania Public Utility Commission, 107 A.3d 246, 260 (Pa. Cmwlth. 2014),

and, here, the Commission was not persuaded by the evidence offered to establish

that the IEC Project was necessary or proper. That PJM determined that there was

a need for the IEC Project under its standards, while relevant, is not determinative

of the approval of siting applications under the Code and the Regulations, which is

an independent decision that belongs to the Commission. The Commission disputes

that it relied only on the impacts to Pennsylvania rates in determining the lack of

need for the IEC Project, pointing to findings relating to the overall regional costs

and benefits, which likewise support its decision that the IEC Project was not

needed, necessary, or proper.

OCA argues the Commission applied the correct legal standard in determining

whether Transource met its burden of proof under Section 1501 of the Code and

Section 57.76(a) of the Regulations. OCA maintains that despite Petitioners’

21

argument that “proper” is distinct from “need,” Petitioners still connect the two by

arguing that if a project is proper, it must be needed. (OCA’s Br. at 11 (citing

Petitioners’ Br. at 17).) Accepting Petitioners’ broad interpretation of “proper”

would allow any utility plan that is functional to be approved irrespective of the

consequences to the environment, consumers, or the market. Even applying a

proper-only standard, OCA asserts, Petitioners did not meet that standard because

the identified need for the IEC Project, resolving congestion in the APSRI, is no

longer present. As for Petitioners’ argument that the standard under Section

57.76(a), as interpreted by the Commission, conflicts with Section 1501, they made

no such arguments to the Commission in the Exceptions and, even if raised, the two

provisions have distinct purposes – one standard applies distinctly to HV

transmission lines and the other to public utilities in general. OCA contends that the

Commission did not ignore the importance of regional transmission needs, it

considered those needs, as required by Section 2805(a) of the Code, but correctly

concluded the evidence relating to the various reasons proffered by Transource did

not establish the need for the IEC Project under Pennsylvania law, which is a

determination independent of PJM’s determination of need. The Commission’s

review was not limited to the impacts in Pennsylvania, OCA argues; rather, it

examined the impacts throughout the PJM Region, much of which would see

increases in their energy prices as a result of the IEC Project.

Franklin County argues Petitioners waived the issue that Transource only had

to establish that the IEC Project was proper because it was not raised before the ALJ

or the Commission. Since the grant of the provisional CPC, the issue to be addressed

was whether there was a need for the IEC Project under Pennsylvania law, which

Transource attempted to prove during the ALJ proceedings without arguing that it

22

only had to prove that the IEC Project was proper. Even if not waived, Franklin

County asserts, the Commission applied the correct standards, reviewing the IEC

Project under the specific standards of Section 57.76(a)(1) of the Regulations, which

must take into consideration the environmental and safety concerns of HV

transmission lines pursuant to article I, section 27 of the Pennsylvania Constitution

(Environmental Rights Amendment),15 and the general standards of Section 1501 of

the Code. Franklin County argues the Commission did not err in considering PJM’s

determination of need but not finding such need sufficient for purposes of

Pennsylvania law. Contrary to Petitioners’ argument, the Commission did not rely

on Pennsylvania impacts, but examined the needs and congestion of the PJM Region,

which is consistent with the Commission’s obligations under Section 2805(a) of the

Code. Based on the evidence presented and credited, Franklin County maintains the

Commission properly concluded that the IEC Project was not necessary “to ensure

the continued provision of adequate, safe and reliable service to the citizens and

businesses in” Pennsylvania, or in the entire PJM Region. (Franklin County’s Br. at

24 (quoting 66 Pa.C.S. § 2805(a)) (emphasis omitted) (internal quotations omitted).)

STFC argues the Commission committed no error of law or abuse of

discretion in interpreting Section 1501 of the Code and applied the “necessary or

proper” standard in exercising its independent authority to analyze the Siting

15

Article I, section 27 of the Pennsylvania Constitution states:

The people have a right to clean air, pure water and to the preservation of the

natural, scenic, historic and esthetic values of the environment. Pennsylvania’s

public natural resources are the common property of all the people, including

generations yet to come. As trustee of these resources, the Commonwealth shall

conserve and maintain them for the benefit of all the people.

PA. CONST. art. I, § 27.

23

Applications. As to the argument that Transource only had to prove that the IEC

Project was proper, STFC asserts that this standard, in the context of transmission

line siting, is not an alternative, lesser standard that would allow construction of any

transmission line proposed – such line still must be appropriate to the purpose or

circumstance, which the IEC Project is not. According to STFC, Section 57.76(a)

of the Regulations, which requires denial of siting applications unless need for the

proposed HV transmission lines is shown, is not unreasonable or beyond the Code’s

grant of authority, particularly where the Commission has recognized that such lines

“cannot be constructed without some adverse effect upon the environment,” and

implicates the Commission’s obligations under the Environmental Rights

Amendment. (STFC’s Br. at 22 (citing In Re Proposed Elec. Reg., 49 Pa. P.U.C.

709, 712, 1976 Pa. PUC LEXIS 114 (1976)).) That a regulation is burdensome does

not make its application or interpretation an abuse of discretion, but rather to be

invalid, “what has been ordered must appear to be so entirely at odds with

fundamental principles . . . as to be the expression of a whim rather than an exercise

of judgment.” (Id. at 18 (citing Pa. Hum. Rels. Comm’n v. Uniontown Area Sch.

Dist., 313 A.2d 156, 169 (Pa. 1973)).)

In their reply brief, Petitioners assert that necessary and proper are distinct

standards, as recognized by this Court in PPL Electric Utilities, and that this Court

has recognized that “necessity” is present “whenever the project result[s] in a benefit

to the public, such as an improvement to the reliability of service or lower prices,”

which Transource established would happen through the construction of the IEC

Project. (Petitioners’ Reply Br. at 8 (quoting Hess, 107 A.3d at 260).) According

to Petitioners, they did not waive the right to argue that the IEC Project is proper and

that applying Section 57.76(a) as requiring need beyond the necessary or proper

24

standard conflicts with Section 1501 of the Code because such arguments are

encompassed in their original argument that the IEC Project should be approved

because it meets the Section 1501 standards. Petitioners point to their brief to the

Commission that the IEC Project “is clearly needed and is necessary or proper for

the accommodation, convenience and safety of its patrons, employees and the

public,” as encompassing its current arguments before the Court. (Petitioners’ Reply

Br. at 10 (quoting R.R. Vol. 5 at 4045a).) Further, they assert they could not know

that the Commission would misinterpret Section 57.76(a) before it issued the

Opinion and Order and, therefore, its current arguments could not have been raised

earlier.

2. Analysis

Section 1501 of the Code addresses, generally, the character of services and

facilities of a public utility and provides, in relevant part:

Every public utility shall furnish and maintain adequate, efficient,

safe, and reasonable service and facilities, and shall make all such

repairs, changes, alterations, substitutions, extensions, and

improvements in or to such service and facilities as shall be necessary

or proper for the accommodation, convenience, and safety of its

patrons, employees, and the public. . . . Such service and facilities

shall be in conformity with the regulations and orders of the

[C]ommission.

66 Pa.C.S. § 1501 (emphasis added). Our Supreme Court has recognized that the

word “or” in “necessary or proper” “must be given its ordinarily disjunctive meaning

unless such a construction would lead to an absurd result.” Elite Indus., Inc. v. Pa.

Pub. Util. Comm’n, 832 A.2d 428, 431 (Pa. 2003). While Elite Industries involved

Section 1103(a) of the Code, which relates to the grant of a CPC, both that section

25

and Section 1501 use the phrase “necessary or proper.” Compare 66 Pa.C.S.

§ 1103(a), with 66 Pa.C.S. § 1501.

Section 57.76(a)(1) of the Regulations relates specifically to the siting and

construction of HV lines and states:

(b) The Commission will issue its order, with its opinion, if any, either

granting or denying the application, in whole or in part, as filed or

upon the terms, conditions or modifications, of the location,

construction, operation or maintenance of the line as the

Commission may deem appropriate. The Commission will not

grant the application, either as proposed or as modified, unless it

finds and determines as to the proposed HV line:

(1) That there is a need for it.

52 Pa. Code § 57.76(a)(1). Pursuant to Section 57.75(e)(1) of the Regulations, in

reviewing siting applications, the Commission must accept evidence of, among other

things, the “present and future necessity of the proposed HV line in furnishing

service to the public.” 52 Pa. Code § 57.75(e)(1) (emphasis added). When the

Commission promulgated these regulations, it recognized that HV transmission lines

could not “be constructed without some adverse effect upon the environment,” and,

therefore, its review must incorporate the requirements of the Environmental Rights

Amendment. In Re Proposed Elec. Reg., 49 Pa. P.U.C. at 712.

Finally, Section 2805(a) of the Code provides that

[t]he [C]ommission shall take all necessary and appropriate steps to

encourage interstate power pools to enhance competition and to

complement industry restructuring on a regional basis. The

Commonwealth, the [C]ommission and Pennsylvania electric utilities

shall work with the Federal Government, other states in the region and

interstate power pools to accomplish the goals of restructuring and to

establish independent system operators or their functional equivalents

to operate the transmission system and interstate power pools. The

[C]ommission, Pennsylvania electric utilities and all electricity

26

suppliers shall work with the Federal Government, other states in the

region, the . . . [NERC] and its regional coordinating councils or their

successors, interstate power pools, and with the independent system

operator or its functional equivalent to ensure the continued provision

of adequate, safe and reliable electric service to the citizens and

businesses of this Commonwealth.

66 Pa.C.S. § 2805(a).

This matter involves the interpretation of these provisions, and the

Commission’s “interpretations of the Code, the statute for which it has enforcement

responsibility, and its own regulations are entitled to great deference and should not

be reversed unless clearly erroneous.” Lehigh Valley Transp. Servs. v. Pa. Pub. Util.

Comm’n, 56 A.3d 49, 56 (Pa. Cmwlth. 2012) (quoting Energy Conservation

Council, 995 A.2d at 478). “The statutory and regulatory scheme regarding the

approval of the siting and construction of transmission lines is technically complex,

and a reviewing court should put aside its discretion in favor of the Commission’s

expertise.” Hess, 107 A.3d at 259. Thus, a Commission determination that facilities

are “necessary or proper for the service, accommodation, convenience or safety of

the public” is entitled to “strong deference” and “given controlling weight unless it

is clearly erroneous.” Riverwalk Casino, L.P. v. Pa. Gaming Control Bd., 926 A.2d

926, 940 (Pa. 2007).

Reviewing the Commission’s Opinion and Order with these principles in

mind, we discern no clear error in the determination that Transource did not meet its

burden of proof under Section 1501 of the Code and Section 57.76(a) of the

Regulations on the Siting Applications. First, we agree with the Commission that

the determination of whether a utility meets the requisite burden of proof under

Pennsylvania law is an independent one. The Commission’s role is to regulate

utilities for the purposes of Pennsylvania law and to determine if the proposed

27

services and facilities comport with Pennsylvania law. That is what it did here; it

examined the Siting Applications, the evidence offered in support of and opposition

to those applications, and made a determination as to whether Transource met its

burden of proof on those Siting Applications under Pennsylvania law. The need for

the Commission’s independent review is particularly true where Pennsylvania law

sets forth different requirements and considerations for approving HV transmission

lines than may be addressed in PJM’s proceedings.

Next, examining the Opinion and Order in its entirety, the Commission did

not deviate from the “necessary or proper” standard set forth in Section 1501 of the

Code or interpret Section 57.76(a) of the Regulations in a way that is inconsistent

with that standard. While there may be places where the Opinion used “necessary

and proper,” rather than “necessary or proper,” the Commission recognized the

statutory standard and applied it, as well as the regulatory standard of “need” as set

forth in Section 57.76(a), to the evidence presented. After doing so, the Commission

concluded that Transource had not met its burden of proving those standards based

on the evidence it presented, which was found to be less persuasive than the evidence

in opposition to the IEC Project.

Necessity and need are corollaries, and this Court has explained that, for

purposes of HV transmission lines, necessity can be established by showing an

improvement in the reliability of services or lower prices. Hess, 107 A.3d at 260.

As for any lower prices that could result from the IEC Project, the Commission

considered all the costs and benefits of the IEC Project, not just those considered by

PJM, and, because there were considerable increases in prices to ratepayers in both

Pennsylvania and elsewhere in the PJM Region, found that this did not support the

grant of the Siting Applications. As for the potential NERC reliability violations,

28

the Commission, as factfinder, found that the relative weight to this later-asserted

basis for the IEC Project had diminished because, among other reasons, “it bec[a]me

more tangential to the unambiguous original driver of the” IEC Project. (Op. and

Order at 62.) As for the resolution of congestion in the APSRI, it does not appear

that we have ever held that congestion, which is an economic consideration, is

sufficient on its own to support need or necessity under Pennsylvania law. In Energy

Conservation Council, we observed that while there was a challenge to the

Commission’s reliance on congestion to find need, we did not address that challenge,

stating that “even if the [Commission] erred in considering congestion issues,” the

finding of public need in that case was supported on reliability grounds. 995 A.2d

at 487. Similar to that case, we need not decide this issue here because the

congestion in the APSRI decreased significantly over the years and, therefore, was

rejected as being a valid basis for the IEC Project. To the extent that Transource

later asserted that the IEC Project would resolve congestion in the AP South Area

and related constraints, like the potential NERC reliability violations, that reason

was not given much weight for a variety of reasons. Thus, based on the evidentiary

findings of the Commission, we discern no clear error in the Commission’s

determination that Petitioners did not satisfy the standards under Section 1501 of the

Code and Section 57.76(a) of the Regulations.

Alternatively, Petitioners argue that the Siting Applications should have been

granted because the IEC Project was proper, that is, “being adapted or appropriate

to the purpose or circumstances; fit; suitable,” for its purpose. PPL Elec. Utils., slip

op. at 24 (quotation and citation omitted). The Commission argues that, if the issue

is not waived, it addressed the propriety of the IEC Project, finding that the costs

outweighed the limited benefits, and, moreover, that the proper standard is not as

29

broad as Petitioners claim, which requires that a project be “suitable,” or

“acceptable.” (Commission’s Br. at 42.) We agree that Petitioners’ broad

interpretation of “proper” goes beyond what is intended by Section 1501 of the Code.

The application of the “proper” standard is dependent on the circumstances of

each case. For example, the Supreme Court determined in Elite Industries that

“necessary or proper” must be given its disjunctive meaning and that using a less

stringent standard to obtain a CPC was appropriate in that case. This reasoning was

based, at least in part, on the facts that the applicant sought to offer a private

limousine service, the applicant “would be hard pressed to show a ‘public need’ for

convenience,” and approval of the CPC would allow for growth and competition

within the industry. 832 A.2d at 432. The Supreme Court explained that, in

requiring a showing of public need, this Court had infringed upon the Commission’s

broad discretion within which the General Assembly left the determinations

regarding the propriety of granting a CPC. Id. Similarly, in PPL Electric Utilities,

slip op. at 22-24, which involved a utility’s internal corporate restructuring, this

Court recognized that “it would be very difficult, if not impossible, for [a u]tility to

establish an affirmative and substantial benefit to the public,” and that this was a

case in which “the Commission c[ould] conduct a disjunctive analysis,” and then

remanded the matter to the Commission to determine if the restructuring was

proper. (Emphasis added.) Thus, in these cases, the disjunctive “proper” standard

was used primarily because it was unlikely that the public need, i.e., necessity,

standard could ever be met based on the type of service or action that was being

proposed and was to be determined to apply based on the circumstances involved.

From these cases, we discern that while the Commission is to determine whether a

service or facility is “necessary or proper,” 66 Pa.C.S. § 1501 (emphasis added), that

30

determination should consider the circumstances, such as the type of service or

action being proposed, and that this determination falls within the Commission’s

sound discretion.

Unlike the situations in Elite Industries and PPL Electric Utilities, it cannot

reasonably be said that it is unlikely or nearly impossible to establish a public need

for an HV transmission line – the Commission and this Court have addressed

numerous such applications and findings of public need have been made which

support approving those lines. See Hess, 107 A.3d at 250, 257-58, 260-61; Energy

Conservation Council, 995 A.2d at 486-87; In Re: Application of Trans-Allegheny

Interstate Line Co. (TrAILCo), 103 Pa. P.U.C. 554, 2008 WL 5786507 (Pa. PUC

Dec. 12, 2008), slip op. 10-12, 16-18; Application of PP&L Elec. Utils. Corp., 2010

WL 637064 (Pa. PUC Feb. 12, 2010) (Susquehanna-Roseland), slip op. at 9, 14, 30.

Thus, the broad application of the “proper” standard asserted by Petitioners is not as

warranted here as it had been in Elite Industries and PPL Electric Utilities. Further,

we must remain cognizant that the standards for siting HV transmission lines must

be read in the context of the Environmental Rights Amendment, with which the

Commission’s Regulations were promulgated to be consistent. Here, the

Commission reviewed the evidence presented and concluded that the proffered

reasons for the IEC Project, including the later-asserted alleged resolution of

congestion outside the APSRI and the possible NERC reliability violations, when

weighed against the detriments of the IEC Project, did not meet the standard under

Section 1501, which necessarily includes whether such facility was “proper.” As

this determination is within the Commission’s expertise and discretion, and because

that determination is not clearly erroneous, we will not infringe on that discretion.

31

Finally, the Commission did not violate its obligations under Section 2805(a)

of the Code to work with regional transmission planning groups and the Federal

Government when it denied the Siting Applications and rescinded Transource’s

provisional CPC under Pennsylvania law. The Commission recognized the asserted

regional planning goals of the IEC Project but found, after weighing the evidence,

that the evidence offered to support that the IEC Project satisfied the Pennsylvania

standards for approval was not persuasive for a variety of reasons. Further, and

contrary to Petitioners’ arguments, the Commission did not engage in a

Pennsylvania-only review of the costs and benefits of the IEC Project. While

evidence of the detrimental impact to Pennsylvania ratepayers was cited and

considered as part of the conclusion that Transource did not meet its burden of proof,

the Commission also examined the detrimental impacts to ratepayers in other parts

of the PJM Region in reaching that conclusion. Accordingly, this is not a reason to

find that the Commission’s determination was clearly erroneous.

C. Evidentiary Claims

1. Parties’ Arguments

Petitioners argue the Commission made several errors in reviewing and

rejecting Transource’s evidence in this matter. First, Petitioners argue the

Commission erred in rejecting PJM’s determination of the need for the IEC Project,

which was presented as evidence to establish need under the Code and the

Regulations, despite PJM’s expertise in the area of transmission planning, including

the management and mitigation of chronic congestion within the PJM Region.

Petitioners maintain that the Commission should have relied on that evidence

because PJM’s process was approved by FERC, was supported by numerous studies,

32

and had been accepted by the Commission and this Court in the past, including in

Energy Conservation Council, 995 A.2d 465, to support granting siting applications.

Second, Petitioners assert the Commission’s finding that the IEC Project is

not necessary to resolve congestion or the potential NERC violations is not

supported by substantial evidence because the evidence relied upon, that of the

opposing parties, constituted “a vast oversimplification of the complex electrical

engineering analysis required to evaluate congestion on the interstate transmission

system.” (Petitioners’ Br. at 29.) Petitioners contend that only Transource presented

evidence of actual studies or modeling showing that the IEC Project was needed to

resolve congestion in the AP South Area and to resolve the NERC reliability issues,

which the Commission abused its discretion in disregarding. According to

Petitioners, the opposing parties’ witnesses had less experience than Transource’s

experts and their evidence regarding the IEC Project no longer being needed due to

reduced congestion on the APSRI was speculative, particularly where the IEC

Project was not limited to resolving congestion on that particular interface.

Petitioners further assert that no opposing party offered substantive or empirical data

regarding the pending NERC reliability violations. Petitioners maintain that the

Commission improperly relied on speculation that other upgrades may resolve those

violations and the lack of additional testing to reject PJM’s findings in this regard

despite there being no reason for PJM to run additional testing because the IEC

Project, a baseline upgrade, would resolve the potential reliability violations in a

timely fashion.

The Commission responds that its findings that the IEC Project did not meet

the standard for approval under Pennsylvania law are supported by substantial

evidence. According to the Commission, its rejection of PJM’s need determination

33

was based on credible evidence reflecting that PJM’s cost-benefit analysis was

flawed and did not consider costs to other parts of the PJM Region, that the

congestion in the APSRI had decreased since the initial study that supported PJM’s

need determination, and that there was insufficient proof of the potential NERC

reliability violations. It maintains that there was substantial evidence to support each

of these determinations, including that the net benefit would only be $32.5 million

over a 15-year period, that the data relied upon to continue supporting the need for

the IEC Project became outdated, and that the congestion cited as the purpose for

the IEP Project was no longer an issue. As for the alleged potential NERC reliability

violations, the Commission asserts the reasons offered for giving less weight to that

evidence were supported by the record and reasonable. The Commission contends

that Petitioners’ arguments to the contrary are simply a request for this Court to

reweigh the evidence, which is beyond this Court’s appellate role.

OCA likewise argues that there was no error or abuse of discretion by the

Commission in not relying on PJM’s determination and that PJM’s process is

inherently unfair in ascertaining whether the benefits of a market efficiency project

outweigh its costs. OCA maintains that the Commission considered and weighed all

of the evidence in its role as factfinder, that Petitioners’ arguments are impermissible

attacks on the evidentiary determinations, and that the fact that Transource presented

evidence that supports other findings of fact is of no moment because the findings

made are supported by substantial evidence. According to OCA, while the

Commission has relied on PJM determinations in the past, it did so merely as

evidence to be considered and not as the sole reason for granting relief.

Franklin County argues that the Commission’s findings regarding the lack of

need for the IEC Project are supported by substantial evidence, including by

34

Transource’s own data, and that the evidence related to Transource’s later-asserted

reasons for the IEC Project was properly rejected as being insufficient after being

weighed by the Commission. There was no impropriety, according to Franklin

County, for the Commission to make its own determination as to the reliability of

PJM’s projections based on the evidence presented or to accept evidence opposing

the IEC Project as more persuasive. To the extent that the Commission has cited

PJM data and witnesses in the past, it was as part of the Commission’s own analysis

and not merely accepting PJM’s determination as establishing need.

STFC argues that the findings of fact are supported by substantial evidence,

Petitioners seek to have this Court reweigh the evidence by claiming only

Transource presented substantial evidence, and the Commission is not bound by

PJM’s determination of need for the IEC Project for purposes of Pennsylvania law.

STFC maintains that the Commission has not historically relied solely on PJM’s

determinations to establish need under Pennsylvania law but considered such

determinations as evidence. STFC further argues that the Commission has not held

that PJM-identified congestion and economic issues were sufficient, in themselves,

to support a finding of need under Pennsylvania law.

Petitioners respond, reemphasizing their arguments that the Commission’s

findings as to the lack of need, congestion, and reliability violations are not

supported by substantial evidence, pointing to Transource’s own evidence in

support. Petitioners reassert that the Commission has accepted PJM determinations

of need as being sufficient to meet the standard for granting siting applications under

Pennsylvania law and it should have done so here. PJM’s determinations that the

IEC Project is needed to relieve congestion and resolve the potential NERC

reliability violations constitute substantial evidence to support that the project is both

35

necessary and proper and were improperly rejected by the Commission. Petitioners

claim that they are not asking this Court to reweigh the evidence but to reverse the

finding that the IEC Project did not meet the standard for approval under

Pennsylvania law because it is not supported by substantial evidence, as the

opposing parties’ evidence was fully rebutted by Transource’s evidence.

(Petitioners’ Reply Br. at 26.)

2. Analysis

It is well settled that the Commission “is the ultimate factfinder[] and makes

all decisions as to the weight and credibility of evidence.” Borough of Duncannon

v. Pa. Pub. Util. Comm’n, 713 A.2d 737, 739 (Pa. Cmwlth. 1998). For a

Commission finding to be supported by substantial evidence, which is “the amount

of relevant evidence which a reasonable person would accept as adequate to support

a determination,” Popowsky v. Pennsylvania Public Utility Commission, 937 A.2d

1040, 1054 (Pa. 2007) (Popowsky III), there must be “more than a mere trace of

evidence or suspicion of the existence of a fact sought to be established,” HIKO

Energy, LLC v. Pennsylvania Public Utility Commission, 163 A.3d 1079, 1094 (Pa.

Cmwlth. 2017) (quoting Lyft, Inc. v. Pennsylvania Public Utility Commission, 145

A.3d 1235, 1240 (Pa. Cmwlth. 2016)), aff’d, 209 A.3d 246 (Pa. 2019). Additionally,

the record evidence, as well as the inferences that can be logically drawn from that

evidence, must be “viewed in a light most favorable to” “[t]he party who [sic]

prevailed before the” Commission. United Transp. Union v. Pa. Pub. Util. Comm’n,

68 A.3d 1026, 1032 (Pa. Cmwlth. 2013). It is irrelevant if “the record may contain

evidence that supports a different result than that reached by the [Commission] . . .

so long as the record contains substantial evidence supporting the [Commission’s]

36

decision.” Lyft, Inc., 145 A.3d at 1240. This Court should not “‘substitute its

judgment for that of the [Commission] when substantial evidence supports the

[Commission]’s decision on a matter within the [C]ommission’s expertise,’ nor

should it indulge in the process of weighing evidence and resolving conflicting

testimony.” Energy Conservation Council, 995 A.2d at 478 (citing Popowsky v. Pa.

Pub. Util. Comm’n, 706 A.2d 1197, 1201 (Pa. 1997) (Popowsky I)).

Petitioners’ evidentiary challenges focus, essentially, on the Commission’s

acceptance of the opposing parties’ evidence over that offered by Transource. Their

arguments challenge the Commission’s decision to: not accept PJM’s

determinations as sufficient evidence under Pennsylvania law, despite having done

so in other proceedings; reject evidence that the IEC Project would resolve, and was

designed to resolve, congestion beyond the APSRI; and reject evidence that the IEC

Project would resolve five potential NERC reliability violations. A review of the

record under the applicable appellate standard reveals that the Commission’s

findings are supported by substantial evidence and support the Commission’s

conclusion that Transource did not meet its burden of proof, which includes both the

burden of production and the burden of persuasion, on the Siting Applications.

First, Petitioners’ assertion that the Commission erred in not accepting

Transource’s evidence related to PJM’s determination of need and the testimony of

PJM employees because the Commission has done so in the past is not persuasive.

Petitioners cite various Commission decisions and this Court’s opinion in Energy

Conservation Council for support because the PJM-based evidence presented in

those cases was found sufficient to establish need under Pennsylvania law.

However, a close reading of those Commission decisions and Energy Conservation

Council reveals that PJM’s determinations of need and related testimony and reports

37

were simply evidence offered by the applicant, which were found credible and

persuasive by the Commission based on those factual records. This is apparent in

this Court’s decision in Energy Conservation Council, which references the PJM

submissions as evidence that had been offered by the applicant, and accepted as

persuasive by the Commission, to support a determination that the transmission lines

at issue met the standards of Pennsylvania law. 995 A.2d at 470-73, 480-86. The

Commission’s decisions cited by Petitioners, which include the decision reviewed

in Energy Conservation Council, likewise refer to the PJM submissions as evidence,

which the Commission considered and “was persuaded by.” TrAILCo, 2008 WL

5786507, slip op. 10-12, 16-18. See also Susquehanna-Roseland, 2010 WL 637064,

slip op. at 9, 14, 30 (explaining that the applicant “presented extensive testimony

and exhibits in order to support its [a]pplication” and describing the evidence

introduced regarding PJM’s process as supporting the application and meeting the

applicant’s burden of proof on need); Joint Application for Approval of Merger of

GPU, Inc. with FirstEnergy Corp., 2001 Pa. PUC LEXIS 604 (Pa. PUC May 24,

2001), slip op. at 9-10, 22-23 (accepting PJM evidence as sufficient to support the

need for a merger of two electric utilities, but with a concurring opinion questioning

whether such evidence was affirmative evidence that supported the relief requested).

Indeed, in the TrAILCo case, the Commission rejected the argument of one of the

opposing parties that it was “required to accept PJM’s RTEP findings or that [it]

must in some fashion defer to PJM on transmission siting issues,” but it did “find

that PJM’s RTEP and the testimony surrounding the need for [proposed transmission

line facilities] compelling.” Id., slip op. at 18 n.3 (emphasis omitted). That the

Commission found evidence persuasive in some proceedings does not require it to

accept it as such in all. As PJM’s determinations, reports, and witnesses were offered

38

in the current proceedings as evidence for the Commission’s consideration, that

evidence is subject to challenge by opposing parties and witnesses and to weighing

by the Commission. Accordingly, this is not a basis to reverse the Commission’s

factual findings.

Second, Petitioners argue that the Commission’s findings of fact regarding

PJM’s cost-benefit analysis are flawed and not supported by substantial evidence.

This evidence was rejected because, inter alia, it did not consider the negative

impacts of the IEC Project on other ratepayers or that the data used to support the

ongoing need for the IEC Project was outdated, ultimately, and inaccurate, and it did

not include other means of resolving the alleged congestion, such as future potential

generation sources. As to the first reason, OCA’s evidence revealed that prior to

2014, PJM considered the negative impacts in its benefit calculation but removed

this from the cost-benefit analysis in order to “increase[] the number of projects that

could qualify as a market efficiency project.” (OCA Cross Exhibit (Ex.) 4 at 4, 8,

R.R. Vol. 7 at 6384a, 6388a.) It was not just OCA’s witness who criticized PJM’s

cost-benefit analysis, but PJM’s own Independent Market Monitor who suggested

that its market efficiency process, which includes the cost-benefit analysis, be

reevaluated and that the actual costs and benefits of a project should be considered

and not ignored in determining whether a market efficiency project is needed. (OCA

Cross Ex. 12 at 7-8, R.R. Vol. 7 at 6421a-22a; Hearing Transcript (Hr’g Tr.) at 2619-

22, R.R. Vol. 3 at 2894a-97a.) Because a finding of necessity may be found under

Pennsylvania law if a project results in a decrease in prices, Hess, 107 A.3d at 260,

we do not view it an abuse of discretion for the Commission to consider evidence of

increased consumer prices and weigh the competing cost impacts of the IEC Project

to determine the necessity of that project. Further, the finding that the cost-benefit

39

analysis was based on outdated data and inaccurate predictions was supported by the

credited testimony of Edward McGavran, who testified that data from 2014 was still

being used to support the need for the IEC Project, despite the resolution of the

congestion on the APSRI, and the reports demonstrating the significant decrease in

congestion in the APSRI that was contrary to the initial predictions. (Hr’g Tr. at 8-

10, R.R. Vol. 4 at 3447a-49a; OCA Statement (St.) 2 at 17 Table 3, R.R. Vol. 2 at

1079a.) Finally, the cost-benefit analysis used to support the IEC Project did not

consider other ways of ameliorating congestion, such as new generation, and, in fact,

was modified in 2018 to exclude from the simulation potential future generation

projects that had executed a Facilities Study Agreement, which is an agreement that

identifies facility additions and upgrades. (FOF ¶¶ 73-74, 76; R.D. at 89, 93-94;

Transource St. AA3, Ex. TJH-AA1 at 19, R.R. Vol. 4 at 3377a; OCA Hr’g Ex. 3,

R.R. Vol. 6 at 5634a-78a; Transource Response to OCA XLIII-12, R.R. Vol. 6 at

5648a; Hr’g Tr. at 2266-68, R.R. Vol. 3 at 2541a-43a; Hr’g Tr. at 2930-33, R.R.

Vol. 4 at 3858a-61a.) Prior to this change, the cost-benefit ratio of the IEC Project

in 2018 was 1.40, and after the change, the cost-benefit ratio in 2019 was 2.17. (FOF

¶¶ 77-78.) Ultimately, the cost-benefit analysis was evidence offered to support

Petitioners’ claim that the IEC Project met the standard for approval under the Code

and the Regulations and, as such, it was subject to challenge by the opposing parties

and weighing by the Commission. In this instance, the Commission examined the

evidence presented by all the parties, weighed it, and found the opposing parties’

evidence more persuasive. As this Court may not reweigh the evidence, this is not

a basis for reversing.

Third, Petitioners assert that the Commission’s findings rejecting congestion

as a basis for the need for the IEC Project are not supported by substantial evidence.

40

The findings reflect that the IEC Project was designed to resolve congestion on the

APSRI, and that congestion on the APRSI has decreased significantly since 2014,

such that it no longer supports the need for the IEC Project. These findings are

supported by substantial evidence, including Petitioners’ own evidence.

(Transource St. 2 at 7, 11, R.R. Vol. 1 at 864a; Transource St. 3 at 24-25, R.R. Vol.

1 at 905a-06a; Transource St. 8-R, Ex. TH-5R at 2, 4-5, R.R. Vol. 2 at 1738a, 1740a-

41a; Transource St. No. 3-AA-RJ at 8, R.R. Vol. 4 at 3662a; Hr’g Tr. at 2132-33,

2381, 2387-88, R.R. Vol. 3 at 2662a-63a; Hr’g Tr. at 2921-23, R.R. Vol. 4 at 3849a-

51a.) While Petitioners claim that the IEC Project was also intended to resolve

congestion in the AP South Area, this evidence was not found to be persuasive

because it was not asserted as a basis for the project from the beginning, was raised

after the APSRI congestion had substantially resolved, little detail was provided

regarding the related constraints in the AP South Area, and the evidence did not

show that the congestion at the later-identified facilities was within PJM’s top 25

most congested facilities. (R.D. at 83-84, 88; OCA Hr’g Ex. 6 at 559, R.R. Vol. 7

at 6263a; Transource St. AA3, Ex. TJH-AA1 at 19, R.R. Vol. 4 at 3377a; OCA Cross

Ex. 7 at 2, R.R. Vol. 7 at 6505a; OCA Cross Ex. 8 at 1-2, R.R. Vol. 7 at 6408a-09a.)

This reasoning does not reflect an abuse of discretion but is based on a review and a

weighing of the evidence presented. Accordingly, this is not a basis for reversing.

Fourth, Petitioners maintain the Commission’s findings rejecting the five

potential NERC reliability violations are not supported by substantial evidence. The

evidence of these potential reliability violations was found not to be persuasive

because reliability violations were not the driver for the IEC Project, the potential

reliability issues were not identified until 2018 – after OCA presented evidence in

opposition to the congestion-based reasons, PJM did not perform its standard set of

41

reliability tests to confirm the need in this matter, and PJM did not rerun the

reliability tests after other projects were approved to determine if those projects

would resolve the potential reliability concerns. (R.D. at 83-84; Op. and Order at

61-62.) Again, these findings are supported by substantial evidence. (Transource

St. 7-R at 21, R.R. Vol. 2 at 1358; Transource St. 7-RJ-SUPP at 3-4, R.R. Vol. 4 at

3108a-09a; Transource St. AA-2, Ex. SRH-AA2 at 13, R.R. Vol. 4 at 3350a; OCA

St. 1-SSR at 16-17, R.R. Vol. 4 at 3077a-78a; OCA Hr’g Ex. 3, R.R. Vol. 6 at 5634a-

78a; Transource Response to OCA-XLIII-10, R.R. Vol. 6 at 5647a; Hr’g Tr. at 2926-

27, R.R. Vol. 4 at 3854a-55a.) While Petitioners argue that there was no need for

PJM to run its standard set of reliability tests or to examine whether subsequently

approved projects would resolve the potential issues once it determined that the IEC

Project would do so, these arguments go to the weight to be given the evidence.

Reviewing the conflicting evidence, the Commission reasonably held that “the

relative weight of the evidence of . . . later-asserted bas[es] for need for the [IEC

P]roject diminishe[d] as it bec[a]me[] more tangential to the unambiguous original

driver[, which was the] alleviation of economic congestion on the AP[SRI].” (Op.

and Order at 62.)

To summarize, Petitioners discount all the evidence presented by the opposing

parties that supports the Commission’s findings and attack this evidence as being

overly simplistic and speculative. However, because these arguments go to the

weight of the evidence presented, which is an issue for the factfinder and not this

Court, and the findings of fact are supported by substantial evidence, those findings

of fact are binding and cannot be set aside. Energy Conservation Council, 995 A.2d

at 478.

42

D. The Rescission of the Provisional CPC and Petitioners’ Other Exceptions

Petitioners assert that the Commission erred in rescinding Transource’s

provisional CPC because the Commission erred in concluding the IEC Project was

not needed, necessary, or proper. Petitioners further argue that the Commission

erred and abused its discretion in not addressing the Exceptions related to the ALJ’s

determination that Transource did not establish that the IEC Project met the other

requirements for approval of the Siting Applications under Section 57.76(a) of the

Regulations. They similarly argue that the Commission erred and abused its

discretion in not addressing Transource’s eminent domain applications and zoning

petitions. Petitioners maintain that the Commission misinterpreted the requirements

of Section 1511(a) and (c) of the Business Corporation Law of 1988 (BCL), 15

Pa.C.S. § 1511(a), (c), by omitting the “proper” from “necessary or proper” language

of that section in the Opinion and Order. (Petitioners’ Br. at 56-57 (quoting 15

Pa.C.S. § 1511(a), (c)).) They request that, upon this Court finding that the IEC

Project meets the requirements of Section 1501 of the Code and Section 1511 of the

BCL, we remand for the Commission to resolve these Exceptions.

The Commission and Intervenors respond there was no error or abuse in the

Commission’s rescinding Transource’s provisional CPC because the CPC was

granted only for the IEC Project. They further argue that the Commission did not

err or abuse its discretion in not considering Transource’s other Exceptions. The

Commission and Intervenors contend that because the Commission’s determination

that the IEC Project did not meet the necessary or proper and need standards was not

in error and was supported by substantial evidence, the other issues raised in the

other Exceptions were moot.

In January 2018, the Commission granted Transource a provisional CPC that

related only to the IEC Project and the parties to those proceedings expressly

43

reserved the issue of the determination of need for the IEC Project for future

proceedings on the siting of the HV transmission lines at issue. Having concluded

that the Commission did not err or abuse its discretion in determining that

Transource did not meet its burden of proving that the IEC Project met the standards

for approval of transmission lines under Section 1501 of the Code and Section

57.76(a)(1) of the Regulations, we discern no error or abuse of discretion in the

Commission’s decision to then rescind Transource’s related provisional CPC.

Similarly, the Commission’s decision to deny the Siting Applications pursuant to

Section 1501 of the Code and Section 57.76(a) of the Regulations rendered the

Exceptions that addressed other alleged errors moot, and the Commission did not err

or abuse its discretion in not addressing those arguments on that basis.

III. CONCLUSION

Because we conclude that the Commission’s decision denying the Siting

Applications and rescinding Transource’s provisional CPC was in accordance with

Pennsylvania law, including Sections 1501 and 2805(a) of the Code, and Section

57.76(a) of the Regulations, and is supported by substantial, credited evidence of

record, we affirm.

__________________________________________

RENÉE COHN JUBELIRER, President Judge

Judge Fizzano Cannon did not participate in the consideration of this matter.

44

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Transource Pennsylvania, LLC, and :

PPL Electric Utilities Corporation, :

Petitioners :

:

v. : No. 689 C.D. 2021

:

Pennsylvania Public Utility :

Commission, :

Respondent :

ORDER

NOW, May 5, 2022, the Order of the Pennsylvania Public Utility

Commission, entered in the above-captioned matter, is AFFIRMED.

__________________________________________

RENÉE COHN JUBELIRER, President Judge