Opinion

The Ginn Group, Inc. v. United States

Court
United States Court of Federal Claims
Filed
May 3, 2022
Status
Published
On the bench
David A. Tapp
Cited by
0 cases
Authority
More cited than 8.3%

“A plaintiff that cannot show that it will actually succeed on the merits of its claim cannot prevail on its motion for injunctive relief.”

How later courts described this case

  • “A plaintiff that cannot show that it will actually succeed on the merits of its claim cannot prevail on its motion for injunctive relief.”
  • “[I]f an offeror’s costs are not so high as to be unreasonable and unacceptable for contract award, the agency may conduct meaningful discussions without raising the issue of the offeror’s costs.”
  • finding that discussions are not coercive where the record demonstrates that an offeror retained the option to make any adjustment to its proposal
  • finding that evaluation of proposals must adhere to the rating system articulated in the RFP

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 22-18

Filed: April 14, 2022

Reissued: May 3, 2022†

THE GINN GROUP, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant,

and

GOVERNMENT CONTRACTING

RESOURCES, INC.,

Intervenor-Defendant.

Nathanael D. Hartland and Courtney E. Walsh, Nelson Mullins Riley & Scarborough LLP,

Baltimore, Maryland, for Plaintiff.

Elizabeth M.D. Pullin, Trial Attorney, Douglas K. Mickle, Assistant Director, Patricia M.

McCarthy, Director, Commercial Litigation Branch, Brian M. Boynton, Principal Deputy

Assistant Attorney General, Civil Division, U.S. Department of Justice, Washington, D.C., with

Robert Greg Palmer and Luke F. Killam, Associate Counsel for U.S. Navy, of counsel, for

Defendant.

Meghan F. Leemon, PilieroMazza PLLC, Washington, D.C., for Intervenor-Defendant.

MEMORANDUM OPINION AND ORDER

TAPP, Judge.

The United States Department of Navy (“the Agency” or “the Navy”) awarded

Government Contracting Resources, Inc. (“GCR”) a contract (over five other offerors) to provide

base operations support services at two U.S. Navy facilities in Florida. The disappointed offeror,

†

This Opinion was filed under seal on April 14, 2022. On April 29, 2022, the parties filed a joint

status report proposing redactions of protected information. (ECF No. 44). This public version

reflects those redactions.

the Ginn Group, proposed expanding one subset of the services requested: recycling services.

When the Agency did not assign a strength to Ginn Group’s proposal for that technical approach,

and more importantly, when it did not view this additional investment as worthy of the higher

price tag, Ginn Group challenged the award. The Court finds that the Agency’s determinations

fell squarely within the zone of reasonable decisions in reviewing and deciding awards in the

context of negotiated, best-value procurements. In this case, the Agency’s best-value

determination—particularly when reviewed in the context of the layers of deference owed to it—

did not lack a rational basis.

Accordingly, the Court DENIES Ginn Group’s Motion for Judgment on the

Administrative Record and GRANTS the United States’ and the Government Contracting

Resources, Inc.’s cross-motions for judgment on the Administrative Record.

I. Background1

The Navy sought to procure base operation support services at Naval Air Station in

Panama City, Florida, and the surrounding areas, including Naval Operations Support Center at

Tallahassee, Florida.2 The Navy conducted market research and selected service-disabled,

veteran-owned, small businesses (“SDVOSB”) set-aside as part of its acquisition strategy. (AR

9). Six offerors applied. (AR 6157).

The solicitation called for a single, indefinite delivery, indefinite-quantity contract.

(Def.’s xMJAR at 10, ECF No. 36). The request for proposal (“RFP”) anticipated that the

resulting contract would have a 12-month base period and seven 1-year option periods, and

another pair of 6-month option periods should an extension of services be necessary under FAR

52.217-8 (spanning from October of 2021 to March 2030). (AR 27–28). The contract

contemplates an eight-year ordering period and is valued at $54,929,956.73. (AR 8123, 8189).

The Navy evaluated six offerors on both price and non-price factors, among them Ginn Group

and GCR. (AR 6330).

The Navy evaluated offerors’ proposals for performing the following services: (1)

Facility Management; (2) Facility Investment; (3) Custodial; (4) Pest Control; (5) Integrated

Solid Waste Management (“ISWM”); (6) Other (Swimming Pools); (7) Grounds Maintenance

and Landscaping; (8) Pavement Clearance; and (9) Environmental.3 The solicitation described

1

The facts recited in this Memorandum Opinion and Order are taken from the Administrative

Record (“AR”) (ECF No. 24); Ginn Group’s memorandum in support of its Motion for Judgment

upon the Administrative Record (“Pl.’s MJAR”),(ECF No. 33); and the United States’ and

GCR’s respective Cross-Motions for Judgment upon the Administrative Record (“Def.’s

xMJAR” and “Def.-Int.’s xMJAR”),(ECF Nos. 36, 37).

2

RFP N6945021R0056 consolidated two previous contracts, Contract No N69450-16-D-2104

(awarded to Ginn Group in 2016) and Contract No 69450-17-D-1707 (awarded to GCR in 2017).

(AR 1–9, Market Research Report, and AR 10–16).

3

The Navy referred to these services as sub-annexes, in line with how they appeared in the PWS

all under one annex titled “Annex 15 Facilities Support.” (AR 188).

2

each of these services as sub-annexes. (AR 188). A Performance Work Statement (“PWS”)

accompanied the RFP which further outlined the performance objectives for each sub-annex.

(AR 188). For example, the PWS further broke down the ISWM sub-annex into various

subtasks, or “Spec Items,” that included collection, disposal, or recycling of different types of

waste. (AR 167–69).

The solicitation provided that the award would be made to the offeror whose proposal

presented the best value to the Government. (AR 27). The best-value determination involved

assessment of proposals against the criteria in the solicitation to determine which proposal would

be overall “most advantageous” to the Government. (AR 55). This best-value evaluation

involved considering price and four non-price factors: (1) corporate experience, (2) technical

approach, (3) safety, and (4) past performance. (AR 46–47). Under the best-value evaluation

criteria, corporate experience, technical approach, and safety were all of equal importance to

each other, and, when combined, were equal in importance to past performance. (Id.).

Furthermore, all of the above non-price factors, when combined, were weighted “approximately

equal” to price. (Id.)

The initial assessment of the proposals was divided into two areas—a Price Team and a

Technical Evaluation Team (“Technical Team”). Both teams met separately to evaluate the

proposals for those respective elements. (AR 6344–75, 8086–8102). The Source Selection

Evaluation Board (“SSEB”) convened to evaluate those findings and issue its own report. (AR

6344–75, 8086–8102).

To be evaluated for their technical approach, offerors submitted proposed labor hours and

provided a rationale for the basis of their estimated proposed labor hours by completing a labor

hours worksheet. (AR 142). Offerors were asked to provide a “narrative” justification explaining

the foundation of their estimates and demonstrate how the proposed approach would translate

into achieving performance objectives. (Id.). The RFP stated that omitting the total efforts of

either category or providing labor hours without a logical explanation of how they would achieve

that staffing level would lead to the proposal being evaluated as “less favorable” or

“unacceptable.” (AR 142). To properly assess the total labor hours offered by each offeror, the

Technical Team referenced two estimates—one based on a mixture of the mean labor hours

proposed by all offerors for each sub-annex of work and one a formal Independent Government

Estimate (“IGE”). (AR 5841). The Technical Team used the following methodology for rating

technical approaches: if proposed labor hours (for any sub-annex or Spec Item) fell short of the

labor hours anticipated by the Government by more than 25%, the offeror received a deficiency

mark for that section. However, if the sub-annex in question was “non-critical” or the difference

was “nominal,” the Technical Team would only give “[c]onsideration” for assigning “weakness,

significant weakness, or deficiency.” (AR 8031).

In evaluating each proposal’s technical approach, the Technical Team assigned adjectival

ratings (Outstanding, Good, Acceptable, Marginal, or Unacceptable), where each adjective

corresponded with a descriptive statement that captured both the adequacy of the proposed

technique and its associated risks. (AR 25–67). For example, an “Outstanding” rating was

defined as one that “indicates an exceptional approach and understanding of the requirements

and contains multiple strengths” and where the “risk of unsuccessful performance is low.” (AR

43). These ratings referenced terms such as weaknesses, significant weaknesses, and

3

deficiencies, and the RFP in turn defined those terms. (Id.). For example, strength was defined as

“[a]n aspect of an offeror’s proposal that has merit or exceeds specified performance or

capability requirements in a way that will be advantageous to the Government during contract

performance.” (Id.).

The Price Team also conducted a price analysis of all offers by comparing the proposed

prices to both the IGE and the median established by the proposals. (AR 6159). The Price Team

rated Ginn Group as third in price position and GCR as first.4

After the Technical Team and the Price Team’s first evaluations, the SSEB reviewed

each team’s findings independently and discussed its findings in a separate report. (AR 6344–

6375, 8086–8102). The SSEB concluded that all offerors were un-awardable for at least one

reason and recommended discussions with all six offerors to address shortcomings. (AR 6375).

Both Ginn Group and GCR had received an overall rating of “Unacceptable” and both received

an “Unacceptable” rating for their Technical Approaches. (AR 6348). Both offerors’ proposals

were also marked as significantly weak or deficient due to understaffing in certain sub-annexes.

(AR 5842, 5861–68, 5878–84). With each of these, the SSEB asked the offerors to “review and

confirm, or revise” their labor hours and to modify their narrative explanations to demonstrate to

the Agency that the labor hours proposed were adequate. (AR 6415–16, 6392–6393).

After this the Agency received Final Proposal Revisions (“FRPs”) from all six offerors,

the Technical Team re-evaluated the final proposals and revised all offerors’ ratings. (AR 8030).

In particular, the Technical Team found Ginn Group’s answers to the questions raised during the

first stage to be satisfactory and eliminated Ginn Group’s deficiency and significant weakness

rating for its technical approach. (AR 8068–69). After the final review, the Ginn Group’s overall

evaluation on the Technical Approach was “Good” with one strength, no weaknesses, significant

weaknesses, or deficiencies. (AR 8069). In at least one subset of the technical approach, the

reliability center maintenance program, Ginn Group received a strength rating. (Id.). The Agency

eliminated the deficiency and significant weakness marks from the first evaluation of GCR’s

proposal after reviewing GCR’s responses to the discussion questions. (AR 8053–54). GCR’s

overall evaluation on technical approach was “Acceptable” with no strengths, weaknesses,

significant weaknesses, or deficiencies. (Id.).

The Technical Team found that one category of the revised labor hours proposed by Ginn

Group (labor hours for Management and Administration services or Spec Items 1&2) fell short

of the Government’s estimate by approximately %. (AR 8068). The Agency noted that

because the proposed hours were only approximately full time equivalent (“FTE”) less than

the Government estimate, the proposed hours were not “significantly lower” than the estimate.

(Id.).5 The Technical Team also noted that GCR’s revised labor hours for two sub-annexes,

4

GCR’s price was % below the IGE and % below the median of all offerors, whereas

Ginn Group’s price was % below the IGE and % below the median of all offerors. (AR

6348).

5

The Government’s estimated hours, , subtracted by the Ginn Group reported hours,

, was which is slightly less than the standard FTE of 2,080. (AR 8068).

4

Facility Management and Custodial, were lower than the Government’s estimate; however,

because the proposed hours “were less than FTE lower” than expected, and only

approximately % “over the range” acceptable by the Government, this difference was viewed as

“nominal.” (AR 8053).

Both Ginn Group’s and GCR’s revised offers were evaluated again for price. (AR 8140).

The Price Team found Ginn Group’s proposed price to be the third lowest-priced among other

offerors and GCR’s proposed price to be the lowest-priced offer. (AR 8160–62, 8149–51). Ginn

Group’s overall proposed price was % lower than the IGE and % lower when

compared to the median price of all offerors. (AR 8160). GCR’s overall proposed price was

% lower than the IGE and % lower than the median proposed price. (AR 8149).

The SSEB reconvened and re-evaluated all offers based on price and non-price factors

again. (AR 8090). The SSEB found that the Technical Team and the Price Team had followed

the criteria in the RFP and found that the assigned ratings were supported by the evaluation and

findings. (Id.; Def.’s xMJAR at 30). After providing a comparative analysis of all final ratings

and accounted for the relative importance of each four factors, the SSEB recommended that

GCR’s proposal represented the best-value and was the most advantageous to the Government.

(AR 8099–8102). The SSEB noted that Ginn Group’s proposal was rated “Good” overall on non-

price factors, with an “Acceptable” or “Satisfactory” Confidence rating for Past Performance,

whereas GCR’s proposal was rated as “Acceptable” on non-price factors with an “Acceptable”

or “Satisfactory” Confidence rating for Past Performance. (AR 8099–8100). However, after

noting that Ginn Group only offered the third lowest price, the SSEB stated that the “factor-by-

factor review” of all proposals indicated that there was “no benefit to trade-off to the higher

priced offeror, as [they] did not present non-price advantages to the Government that would

merit the additional cost of selecting” those proposals. (AR 8102).

At the final stage, the Source Selection Authority (“SSA”) considered the lengthy SSEB

report which included comparative analysis of all offerors’ final proposals. (AR 8121). The SSA,

acting independently, determined that GCR’s offer represented the best value to the Government.

(Id.). The SSA distinctly addressed the comparison with Ginn Group, stating that although Ginn

Group received a better technical rating than GCR, GCR maintained a comparative advantage in

Corporate Experience and Past Performance (AR 8122–23). The SSA therefore also

independently found that the non-price advantages in Ginn Group’s proposal did not outweigh

GCR’s “non-price advantages in the remaining factors or merit the $2,263,020.19 price

premium.” (Id.).

In response, Ginn Group protested the contract award with the Government

Accountability Office (“GAO”). The foundation of Ginn Group’s protest before the GAO was

substantially similar to its arguments before the Court: that the Agency conducted discussions

that were not meaningful, that the Agency misevaluated the strengths and weaknesses of Ginn

Group and GCR’s proposals, and that as a result, the Navy’s ultimate best-value decision was

unreasonable. (AR 8397). The GAO found no support for the arguments and found the Navy’s

determination to be reasonable. (Id.).

5

II. Analysis

Ginn Group challenges the Navy’s contract award on four grounds. First, Ginn Group

contends that the Agency’s evaluation of GCR’s proposal lacked rational basis because the

Agency did not downgrade or find GCR’s proposal unacceptable for its low staffing level and for

a technical approach to recycling services that Ginn Group views as inadequate. (Pl.’s MJAR at

4–10, ECF No. 33). Second, Ginn Group argues that the Navy’s evaluation of Ginn Group’s

offer lacked a rational basis because the Navy did not assign Ginn Group a strength for its

technical approach to recycling services. (Id.). Third, that the Agency failed to conduct

meaningful discussions with Ginn Group that would have helped Ginn Group modify its

technical approach in the ISWM performance area. (Id.). And fourth, that because of the

conglomeration of these errors the Agency’s ultimate best-value decision in this case lacked a

rational basis, as it did not follow a fair and reasonable assessment of each proposal’s strengths

and weaknesses. (Id.)

The Court reviews an agency’s action to determine if it was “arbitrary, capricious, an

abuse of discretion,”—in other words, lacked a rational basis—or if the agency’s action was not

“in accordance with law”—in other words, it involved a violation of regulation or procedure. 28

U.S.C. § 1491(b)(4); Tinton Falls Lodging Realty, LLC v. United States, 800 F.3d 1353, 1358

(Fed. Cir. 2015). In reviewing whether the Agency’s decision lacked a rational basis, the Court

seeks to find if “the contracting agency provided a coherent and reasonable explanation of its

exercise of discretion.” Impresa Construzioni Geom. Domenico Garufi v. United States, 238 F.

3d 1324, 1333 (Fed. Cir. 2001) (quoting Latecoere Int’l, Inc. v. Dep’t of Navy, 19 F.3d 1342,

1356 (11th Cir. 1994)); PAI Corp. v. United States, 614 F.3d 1347, 1352 (Fed. Cir. 2010) (“To

demonstrate that [the agency’s procurement decision was] arbitrary or capricious, a protester

must identify ‘hard facts’; a mere inference or suspicion of an actual or apparent [violation] is

not enough.” (quoting C.A.C.I., Inc.-Fed. v. United States, 719 F.2d 1567, 1581 (Fed. Cir.

1983)). This standard is highly deferential. Advanced Data Concepts, Inc., v. United States, 216

F.3d 1054, 1058 (Fed. Cir. 2000).

Even under this highly deferential standard, the Court will set aside an agency action

when the agency “‘entirely fail[ed] to consider an important aspect of the problem, offer[ed] an

explanation for its decision that runs counter to the evidence before the agency,” or when the

decision “is so implausible that it cannot not be ascribed to a difference in view or the product of

agency expertise.’” Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43,

(1983)). However, this highly deferential standard means that “a court is not to substitute its

judgment for that of the agency.” Id. Therefore, if the agency’s actions show rational reasoning

and consideration of relevant factors, the Court is required to sustain the decision. Advanced

Data Concepts, 216 F.3d at 1058 (citing Bowman Transp., Inc. v. Ark. Best Freight Sys., Inc.,

419 U.S. 281, 285 (1974)). “Greater yet,” is the deference to the procurement official’s

discretion in awarding a contract “on the basis of a best-value determination,” which often

involves balancing price and non-price factors. Linc Gov’t Serv.s, LLC v. United States, 96 Fed.

Cl. 672, 706 (2010). This deferential standard is even further heightened in the context of

negotiated procurements, where the agency officials must engage in an “inherently[] judgmental

process,” Burroughs Corp. v. United States, 223 Ct. Cl. 53 (1980), and are therefore entrusted

with “especially great discretion, extending even to [their] application of procurement

regulations,” Am. Tel. & Tel. Co. v. United States, 307 F.3d 1374, 1379 (Fed. Cir. 2002).

6

More relevant to the exact procurement in this case, reviewing the agency’s technical

evaluations is subject to another separate level of deference, as it falls within a special category

of “discretionary determinations” that the Court “will not second guess.” E.W. Bliss Co. v.

United States, 77 F.3d 445, 449 (Fed. Cir. 1996). Therefore, for the protester to prevail, it must

show that “the agency unreasonably downgraded its proposal for deficiencies that were

‘substantively indistinguishable’ or nearly identical from” those in the other proposals. Office

Design Grp. v. United States, 951 F.3d 1366, 1372 (Fed. Cir. 2020) (citing Enhanced Veterans

Solutions, Inc. v. United States, 131 Fed. Cl. 565, 588 (2017)). Hence, protesters challenging the

agency’s technical evaluation in the context of negotiated, best-value procurements must

overcome a “triple whammy of deference.” Gulf Group, Inc. v. United States, 61 Fed. Cl. 338,

351 (2004).

Should the Court find that the Agency’s conduct failed under this standard of review, it

must then decide if the “bid protester was prejudiced by that conduct.” Bannum, Inc. v. United

States, 404 F.3d 1346, 1351 (Fed. Cir. 2005). The protester can establish prejudice by showing

“that there was a ‘substantial chance’ it would have received the contract award but for the

[agency’s] errors.” Id. at 1353.

A. The Agency’s evaluation of Ginn Group’s and GCR’s recycling proposals did not

lack a rational basis.

Ginn Group argues that the Agency’s evaluation of its and GCR’s recycling proposals

lacked a rational basis. (Pl.’s MJAR at 10–13). Ginn Group specifically argues that GCR’s

technical approach to recycling services should have resulted in either a downgrade or an

“Unacceptable” rating. (Id.). Ginn Group also argues that the Agency should have assigned a

strength to Ginn Group’s technical approach to recycling. (Id. at 17). Neither the plain meaning

of the terms of the solicitation nor the context or structure of the RFP support Ginn Group’s

arguments.

Ginn Group highlights what it sees as the significant difference between the two technical

approaches to recycling: Ginn Group proposed to “establish recycling services at NSA Panama

City for white paper and aluminum cans” whereas GCR’s proposal did not provide the Agency

with that option. (Id. at 11). Ginn Group argues that the Agency’s final evaluation of GCR’s

proposal did not reflect this shortcoming in comparison to Ginn Group’s offer.

The Agency is required to evaluate all offers according to the terms and conditions of the

RFP. See FAR § 15.305(a) (“An agency shall evaluate competitive proposals and then assess

their relative qualities solely on the factors and subfactors specified in the solicitation.”); see also

Dubinsky v. United States, 43 Fed. Cl. 243, 267 n.56 (1999) (finding that evaluation of proposals

must adhere to the rating system articulated in the RFP). Therefore, the question of what

consideration should have been given to the absence of white paper and aluminum can recycling

in GCR’s proposal must be answered by referencing the exact terms of the RFP.

Importantly, recycling services was not a distinct sub-annex in the solicitation. (AR 27

(listing the sub-annexes of services requested)). The terms of the solicitation categorized the

Base Operation Services sought under the contract within the following sub-annexes: Facility

Management, Facility Investment, Custodial, Pest Control, Other (Swimming Pools), Grounds

7

Maintenance and Landscaping, Pavement Clearance, Environmental, and Integrated Solid Waste

Management (ISWM). (Id.). Recycling services only constituted a subtask under one out of the

six sub-annexes previously mentioned. (AR 301).

The PWS provided a more detailed explanation of the subset of services required under

each sub-annex mentioned in the RFP. (AR 188–301). The PWS section pertaining to the ISWM

sub-annex established that the overall requirement for the contractor under this sub-annex was to

“provide refuse collection, disposal and recycling services to ensure refuse and recyclables are

properly collected and disposed.” (AR 301). Indeed, many of the performance objectives or

subtasks listed in the PWS for this sub-annex did not relate to recycling. Under Spec Item 3.2.1.,

for example, the contractor was required to “dispose of non-recyclable solid waste,” and, under

Spec Item 3.3, the contractor was required to “maintain vehicles and equipment in a manner to

ensure a clean appearance, minimal foul odors, and normal working conditions.” (AR 303). One

subtask in the PWS under the ISWM sub-annex involved Solid Waste Collection. (AR 301). For

Solid Waste Collection, the PWS required that contractor “provide collection of residential,

commercial, and industrial solid wastes to ensure refuse and recyclables are properly collected.”

(AR 301). The RFP language that influenced Ginn Group to include white paper and cans

recycling in its proposal appears in part of the subsection titled “Related Information” for this

subtask in the PWS: “The Contractor shall use Materials Recovery Facility (MRF) or a Single

Stream Recycling Facility to the fullest extent possible.” (AR 301). Ginn Group argues that this

language “gave bidders strong reason to think” that expanding recycling services would be

counted as a strength and or any shortcomings counted as a deficiency. (Pl.’s MJAR at 13).

Despite Ginn Group’s reliance on one excerpt of the PWS, the RFP must be considered

as a whole. See Banknote Corp. of Am. v. United States, 365 F.3d 1345, 1353 (Fed. Cir. 2004)

(“[W]e must consider the solicitation as a whole, interpreting it in a manner that harmonizes and

gives reasonable meaning to all of its provisions.” (citing Coast Fed. Bank, FSB v. United States,

323 F.3d 1035, 1038 (Fed. Cir. 2003))). There is no clear instruction in the RFP that any

additional recycling service, in isolation, merited a strength rating or that its absence should

render a proposal “Unacceptable,” as Ginn Group claims. (Pl.’s MJAR at 7). Instead, clear

instructions in the RFP provided that every aspect of any technical approach would be analyzed

within the context of its impact across “all other technical specification simultaneously,” and

with the view on how that specific technical approach would be “advantageous to the

Government.” (AR 50–51; see also AR 43 (defining strength as technical approach that

“exceed[]” specified performance or capability requirements “in a way that will be advantageous

to the Government during contract performance.”)).

Furthermore, because the RFP should be interpreted “as a whole,” the relative weight of

the excerpt Ginn Group relies on cannot be assessed without reference to the context of the

whole solicitation. Linc Gov’t Servs., LLC, 96 Fed. at 672; see also Metric Constructors, Inc. v.

NASA, 169 F.3d 747, 752 (Fed. Cir. 1999). The United States correctly asserts that recycling

service was not a separate factor in the RFP but appeared only as one segment of one sub-annex

in the RFP. (Def.’s xMJAR 36). Given this structure, the Agency’s decision to evaluate Ginn

Group’s technical approach to a subset of the proposal in the context of its overall advantage to

the Government, rather than in isolation, was in line with the evaluation criteria in the RFP. See

e.g., Rotech Healthcare, Inc. v. United States, 121 Fed. Cl. 387, 397 (2015) (finding that a

bidder’s “transition plan” was less important than the many other substantive aspects of the

8

bidders’ proposals’ when that factor constituted “only one of five subfactors in the Technical

factor, which in turn [was] only one of the three factors that the RFP required the agency to

consider and evaluate”); Quanterion Sols., Inc. v. United States, 152 Fed. Cl. 434, 441–43 (2021)

(finding that an “isolated sentence” in the RFP cannot render performance of Information

Analysis Center services a requirement, when “the majority of the verbiage in the RFP” focused

on other factors.). Given the context and the broader structure of the RFP, the Court’s second-

guessing of the Agency’s evaluation of only a part of an offeror’s approach to a subpart of a

subpart of the proposal would be akin to delving into the “minutiae of the procurement process,”

a practice that the Court has long avoided. E.W. Bliss Co., 77 F.3d at 449 (finding that bid

protest challenges “deal[ing] with the minutiae of the procurement process in such matters as

technical ratings . . . involve discretionary determinations of procurement officials that a court

will not second guess”); Commc’n Constr. Servs., Inc. v. United States, 116 Fed. Cl. 233, 266

(2014) (“As the Federal Circuit has recognized, challenges to the technical scoring involve the

minutiae of the procurement process, discretionary determinations that a court will not second

guess.”) (internal citations and quotation marks omitted). The Court’s assessment of the overall

structure of the RFP indicates that the Agency’s evaluation of GCR’s and Ginn Group’s

technical approaches to recycling was reasonable.

For its part, Ginn Group claims that its decision to include white paper and aluminum

can recycling in its proposal was influenced by the particular terms of the RFP. (Pl.’s MJAR at

6). Specifically, Ginn Group points the Court to language in the RFP that stated: “The Contractor

shall use Materials Recovery Facility (MRF) or a Single Stream Recycling Facility to the fullest

extent possible.” (AR 1838 (emphasis added)). Ginn Group claims that it took this “statement[]

about recycling to heart and proposed a substantial expansion of recycling activities.” (Compl. at

2). Ginn Group claims that through its own research of available recycling services at the Navy

facility in Panama City, Ginn Group discovered that recycling for white paper and cans was

available and therefore included that in its proposal. (Pl.’s MJAR at 11). The United States

disagrees that this language meant that the Navy sought recycling services to the maximum

extent possible. (Def.’s xMJAR at 38).

The dispute between the parties based upon their disparate interpretations of the

solicitation poses a question of law that the Court reviews de novo. CBY Design Builders v.

United States, 105 Fed. Cl. 303, 327 (2012) (citing NVT Techs., Inc. v. United States, 370 F.3d

1153, 1159 (Fed. Cir. 2004)). Well-established principles of contract interpretation apply to the

interpretation of government solicitations. Linc Gov’t Servs., LLC, 96 Fed. Cl. at 708. This

requires that the Court begin its analysis with an independent review of the plain language of an

agency’s solicitation. Id. Ginn Group asserts that the Solicitation terms advising offerors to “use

Materials Recovery Facility (MRF) or a Single Stream Recycling Facility to the fullest extent

possible,” imposed an effective requirement on all offerors to provide those services to the

maximum. (Pl.’s MJAR at 6). Although this is a plausible reading of the text, it is by no means

the only one. It is a cardinal principle of construction of contracts to interpret phrases in a way

that every word is given its effect. AMP, Inc. v. United States, 182 Ct. Cl. 86 (1968). In line with

that principle, it is difficult to imagine why the terms of the Solicitation would qualify the phrase

“to the fullest extent” with the phrase “possible” if the Agency’s goal, as Ginn Group claims,

was simply to request the absolute maximum of those services without any conditions. In other

words, a command to the offerors to “use Materials Recovery Facility (MRF) or a Single Stream

9

Recycling Facility to the fullest extent,” would have simply carried that message with

unmistakable clarity and without the need for the qualifier “possible.”

Ginn Group argues that the “ordinary” meaning of “to the fullest extent possible,”

suggests that the Navy would have been willing to “pay a little more” for additional services and

that failure to provide all the services available would have been “viewed negatively.” (Pl.’s

MJAR at 6). Ginn Group is correct that the phrase “to the fullest” certainly connotes emphasis

and not limitation. Yet the language used by the Navy cannot be read to require recycling

services to the exact absolute outer boundaries because the language is qualified by the word

“possible.” The Oxford dictionary defines “possible” as that which “is capable of being; that may

or can exist, be done, or happen (in general, or in given or assumed conditions or

circumstances).” See Oxford English Dictionary Online, https://www.oed.com/

view/Entry/148376?redirectedFrom=possible#eid (last visited Apr. 13, 2022)). The dictionary

definitions of the word possible therefore evade absolutes and instead connote conditions. See

also Johnson v. State, 366 S.W.3d 11 (Mo. Banc. 2012) (finding that the word possible is most

commonly used to evoke deviations from what would otherwise be “the absolute degree” and

specially to signal a need for “consideration of other recognized factors”); Rhoades v. State, 848

N.W.2d 22, 26–28 (Iowa 2014) (collecting cases finding the word possible to mean contingent

on circumstances). Therefore, the phrase “to the fullest extent possible,” cannot be read to

command compliance to the utmost degree and with no exceptions; instead, it means that minor

and reasonable deviations from the requirement were anticipated. The Court then has to look at

the context of the RFP to assess what those anticipated conditions are.

It is evident from the terms and the structure of the RFP that price was one limiting

condition. The clear terms of the RFP notified all offerors that when combined, all non-price

factors (including technical approach) were “approximately equal” in importance to price. (AR

46–47). Therefore, although the Agency’s edict that offerors “shall use Materials Recovery

Facility (MRF) or a Single Stream Recycling Facility to the fullest extent possible,” meant that

offerors should have given those sub-services comprehensive and objective treatment, it did not

mean that the Agency required absolute perfection in that area at any cost. Therefore, the Court

finds that the most reasonable reading of the phrase “to the fullest extent possible,” is to require

recycling services subject to and consistent with other essential considerations of the proposal,

namely cost and price.

As the United States contends, Ginn Group failed to articulate how its proposed recycling

approach fits within the balance of other equally important elements of the RFP including “cost

savings.” (AR 8335). Although Ginn Group claims that it “was not required to articulate a reason

why the Agency wanted recycling to the fullest extent possible,” this statement reflects a

misunderstanding of the RFP’s requirements. (Pl.’s MJAR at 6). The terms of the RFP required

that the offerors describe in detail how their technical approach would benefit the Government.

Ginn Group did not. For this procurement, the Agency’s evaluation standard involved reviewing

each offeror’s technical approach for adequate staffing overall and for each sub-annex. (AR

142). The offerors were instructed to provide a narrative that explained not only “how the

proposed approach and labor hours will effectively achieve each performance objective,” and

“each technical specification,” but importantly, how that approach would translate “across all

technical specification simultaneously.” (AR 51). In line with that goal, the RFP evaluation

criteria did not simply assign strengths to any aspect of the proposal that might exceed the

10

Government’s expectations; instead, evaluators were instructed to assign strength to an aspect

“of an offeror’s proposal that has merit or exceeds specified performance or capability

requirement in a way that will be advantageous to the Government during contract

performance.” (AR 4632 (emphasis added)). Although Ginn Group claims that the Agency

should have given Ginn Group a strength for “going above and beyond” in its proposed staffing

for recycling services, there is no evidence that Ginn Group ever informed the Agency how this

approach would work across all other technical specification to make the proposal more

advantageous to the Agency. (AR 55). Therefore, the Agency’s decision to not assign Ginn

Group a strength merely for proposing additional recycling services was a reasonable decision

supported by the record. See L-3 Commc’ns EOTech, Inc. v. United States, 83 Fed. Cl. 643, 650

(2008) (“The deference afforded to an agency’s decision must be even greater when a trial court

is asked to review a technical evaluation.”).

B. The Agency’s evaluation of GCR’s and Ginn Group’s proposed staffing levels did not

lack a rational basis.

Ginn Group argues that the Agency’s evaluation of GCR’s and Ginn Group’s staffing

levels lacked a rational basis because the Agency’s award does not account for the fact that GCR

proposed “the most thinly staffed workforce of all bidders.” (Pl.’s MJAR at 8). Ginn Group’s

staffing argument focuses on GCR’s staffing levels in two performance areas: Facility

Management and Custodial. Particularly, the Agency’s final evaluation found GCR’s proposed

staffing to be % less than the Government anticipated labor hours in the Facility

Management sub-annex and % less in the Custodial sub-annex. (AR 8053). The Agency

claims that its final determination that both proposed hours were adequate is supported by the

methodology outlined in the Technical Team Report and the terms of the RFP. (Def.’s xMJAR at

41–45).

The Navy’s method for evaluating the adequacy of labor hours, as applied by the

Technical Team, distinguished between understaffing in critical and non-critical sub-annexes.

Unlike other sub-annexes, Facility Management was not defined as a critical sub-annex under

Factor 1 (Corporate Experience). (AR 140–141, 626–627). The Technical Team’s approach was

to only give “[c]onsideration for weaknesses, significant weaknesses or deficiencies . . . if an

offeror’s proposed labor hours for a [non-critical Sub-Annex] were less than minus 25% of the

labor hours anticipated by the Government [] or if the difference in labor hours was nominal.”

(AR 5841 (emphasis added)).

This approach meant that for some proposed labor hours that would have otherwise

resulted in a downgraded assessment (those in non-critical sub-annexes or those found to be

nominal), the Agency was going to review the labor hours on a more comprehensive level. (See

e.g., AR 8036 (finding the difference of approximately FTE to be nominal in light of the

“potential efficiencies” of the offerors’ “proven Predictive Maintenance Program.”)). The RFP

stated as much in other parts as well: “[t]he Government will evaluate how well the offeror’s

approach demonstrates adequate labor hours on an overall level, as well as for each technical

specification (and each specification item) supported by a reasonable [Basis of Estimate], and

demonstrates a reasonable understanding of the requirements and labor quantities and skills

needed to successfully perform.” (AR 628 (emphasis added)). Given this language and a

technical evaluation methodology that gave the Agency the discretion to forgo downgrading for

11

certain labor differences that the Agency viewed as “nominal,” the Agency made the reasonable

decision to assess certain proposed labor hours in a broader context.

For example, although GCR’s proposed staffing was % less than the Government

anticipated labor hours for the Facility Management sub-annex, the Agency found this difference

to be nominal. (AR 8053). Instead, the Agency decided to view this staffing level in the context

of GCR’s past experience operating at that level and found the risk associated with the proposed

hours to be low. (Id.).

The Agency applied this flexible approach consistently to other offerors’ proposals as

well. (See e.g., AR 8076, finding labor hours that were % and % below the

Government’s estimates to present nominal differences in the context of the offeror’s staffing

levels in other areas and the low risk to the Government). In fact, even Ginn Group’s own

proposal received this comprehensive analysis from the Technical Team. (See AR 8068 (finding

Ginn Group’s low labor estimates for overall Spec Items 1 and 2 as “nominal” because of the

low risk it represents.)). The Agency’s exercise of its judgment to treat certain low levels of

understaffing as nominal was also in line with the terms of the RFP which stated that labor hours

“may be evaluated less favorably or considered unacceptable,” if they were not accompanied by

a logical explanation. (AR 628 (emphasis added)). This language allowed the Agency to also

exercise its own independent judgment in evaluating certain staffing levels.

Ginn Group also challenges the Agency’s decision to revise its internal estimate for

staffing in these two areas and labels the Agency’s failure to explain that decision as “inherently

suspicious and irrational.” (Pl.’s MJAR at 15).6 Ginn Group does not support that statement with

any caselaw establishing a requirement that agencies provide an explanation of every change in

the Government estimate. In particular, Ginn’s contention is impossible to reconcile with past

cases which have found that agencies may at times even rely on fully undisclosed Government

estimates. SP Sys. v. United States, 86 Fed. Cl. 1 (2009); SDS Int’l v. United States, 48 Fed. Cl.

742, 758 (2001). The test for the Court instead has been to ensure that the agency does not

mechanically rely on an estimate that it has found to be inadequate; and that the agency’s

reliance on its estimate does not prejudice any offerors whose offers significantly differ from the

estimate relied on. SP Sys., 86 Fed. Cl. at 18. Although Ginn Group emphasizes the fact that the

Agency revised its internal staffing estimates downward, reducing the size of GCR’s deviation

from the estimate from close to % to only %, this adjustment also clearly benefited Ginn

Group and other offerors. Although Ginn Group’s proposed hours under Facility Management

were originally % lower than anticipated by the Government, Ginn Group’s final proposed

hours for that sub-annex were only % less than the Government revised anticipated total.

(AR 8068).

6

GCR originally underbid the staffing for Facility Management sub-annex by about

(offering labor hours against the Agency’s expected labor hours). (AR 5863).

Subsequent to the Agency’s revision of its internal estimate, GCR was understaffed by

approximately % (having offered labor hours against the Agency’s

expected labor hours). (AR 8094).

12

Ginn Group’s claim that “the Agency did not assign even a single weakness to GCR’s

proposal relating to this staffing shortage,” is a conclusory statement unsupported by the

provisions of the RFP. The terms of the RFP indicated that staffing levels would be reviewed

with an eye towards assessing whether each offeror had “a reasonable understanding of the

requirements and labor quantities and skills needed to successfully perform.” (AR 51). To this

end, the Agency used the methodology outlined in the Technical Team’s report in conjunction

with the information available regarding offerors’ past experience. (AR 8102). URS Federal

Services Inc. v. United States, 142 Fed. Cl. 392 (2019) (finding that when the Solicitation does

not prescribe a particular method for analyzing the offerors’ understanding of the technical

requirements the greatest deference possible should be given to special expertise of procurement

officials); Telos Corp. v. United States, 129 Fed. Cl. 573, 578 (2016) (finding that the FAR does

not require a documented explanation of “why the staffing [proposed by an offeror] was found

adequate for each task to be performed under the contract.”). GCR informed the Agency that,

despite its lower proposed labor hours in certain areas, it had implemented the same management

system in other similar projects. (AR 7198). The Agency found that GCR’s experience with

similar projects justified certain degree of deviation from the estimate in labor hours. (AR 7198).

As the Court has previously found, agencies are the best judge of relevance of past performance,

and the Agency decision here adequately documented the reasoning. (Id. (“GCR also

benchmarked its custodial labor hours against several current NAVFAC SE contracts including

custodial requirements (NCBC Gulfport, MS; NSB Kings Bay, GA, and MCSF Blount Island,

FL)”)); see Glenn Defense Marine (ASIA), PTE Ltd. v. United States, 720 F.3d 901, 911 (Fed.

Cir. 2013); Appsential, LLC v. United States, 153 Fed. Cl. 610 (2021).

Ginn Group asserts that the Agency failed to substantiate the relevance of GCR’s

experience or establish that it was done without “a detrimental effect on those other customers,”

(Pl.’s Reply at 9, ECF No. 38), but that is not the standard governing Agency evaluation of labor

hours. GCR had informed the Agency that it intended to “implement the same management

systems and processes that have historically proven successful” for GCR at NSA Panama City,

and under its current contract that involved custodial services. (AR 11337). GCR provided the

Agency with the details of its past performance, (AR 11318; see also 11408–25 (GCR’s

contractor performance assessment report)), and the Agency emphasized the importance of

GCR’s past experience in a number of instances. (See e.g., AR 8122). Therefore, the record

includes sufficient documentation supporting the Agency’s determination that GCR’s Custodial

staffing hours were adequate. See Telos Corp., 129 Fed. Cl. at 578 (the FAR does not require a

documented explanation of “why the staffing [proposed by an offeror] was found adequate for

each task to be performed under the contract.”); Synaptek, Inc. v. United States, 141 Fed. Cl. 443,

453 (2018) (awardee made representations in its proposal on which the agency was entitled to

rely); see also Survival Sys., USA, Inc. v. United States, 102 Fed. Cl. 255, 264 (2011). In sum,

the Agency’s evaluation of GCR’s Custodial labor hours is not “so implausible that it could not

be ascribed to a difference in view or the product of agency expertise,” and therefore, does not

lack rational basis. Motor Vehicle Mfrs. Ass’n of U.S., 463 U.S. at 43.

Finally, Ginn Group points to what it describes as the Agency’s reoccurring mathematical

error in discussing GCRs staffing levels. Ginn Group points the Court to two instances in which

the Agency claimed that GCR’s staffing levels for Facility Management were “less than FTE

lower, than anticipated by the Government,” where the correct phrasing would instead have been

“more than” FTE. (Pl.’s MJAR at 15). Ginn Group frames these errors as the Agency’s

13

attempt to “cover” for GCR’s staffing levels and carried out in an “effort to award to GCR.”

(Pl.’s MJAR at 9). Ginn Group fails to substantiate how the Agency’s incorrect statements would

have undermined the rationality of the award decision. Quanterion Solutions, Inc., 152 Fed. Cl.

at 22 (a minor mathematical error in the IGE by itself does not impair the rationality of an award

decision). Regardless of whether the approximately hours difference amounts to less than

or above FTE, the Agency found the raw difference between GCR’s labor hours and

its estimate to be nominal because of the context of GCR’s relevant experience with conducting

similar projects at the same staffing level. (AR 8123). The Agency’s underlying reasoning for

viewing this staffing difference as nominal is satisfactory.

To the extent that the Agency may have erred in describing the approximate size of this

relatively small deviation, such errors have typically been categorized as de minimis errors.7 See

Andersen Consulting v. United States, 959 F.2d 929, 935 (Fed. Cir. 1992) (“De minimis errors

are those that are so insignificant when considered against the solicitation as a whole that they

can safely be ignored and the main purposes of the contemplated contract will not be affected if

they are.”). The Court has persistently held that overturning awards based on de minimis errors is

unadvisable. See e.g., Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 1000 (Fed. Cir. 1996).

As the Court has previously noted, even “violations of law,” let alone innocuous mistakes,

should not result in setting aside awards unless those mistakes have some significance, for “[a]ny

good lawyer can pick lint off any Government procurement.” Andersen Consulting, 959 F.2d at

932.8

C. The Agency did not fail in conducting meaningful discussions with Ginn Group.

Ginn Group also argues that the Agency failed to conduct meaningful discussions as

required by FAR 15.306. Ginn Group claims that the SSA was obligated to address what Ginn

Group characterizes “as a vast difference between” the two staffing levels and/or to inform Ginn

Group that the Agency did not seek recycling to the fullest extent possible.

When the agencies conduct discussions, those discussions must be “meaningful” and not

misleading. CRAssociates, Inc. v. United States, 102 Fed. Cl. 698, 715 (2011). During

discussions, the Agency is required to identify “deficiencies, significant weaknesses, and adverse

past performance information to which the offeror has not yet had an opportunity to respond.”

FAR § 15.306(d)(3). The Court has recognized that “practical considerations” limit the agency’s

power to discuss every aspect of every offeror’s proposal and that discussions often therefore

7

Unlike motions for summary judgment, existence of genuine issues of material fact does not

preclude judgment on the administrative record. See Fort Carson Supp. Servs. v. United States,

71 Fed. Cl. 571, 585 (2006). When the administrative record forms the Court’s “focal point for

judicial review,” Camp v. Pitts, 411 U.S. 138, 142 (1973), the Court will review both disputed

and undisputed facts in that record to decide if the Agency complied with the legal standards

governing the decision under review. See Greene v. United States, 65 Fed. Cl. 375, 382 (2005).

8

To the extent that the Agency may have made a mistake in reciting the results of its

mathematical calculations, Ginn Group has conceded its claim does not constitute a bad faith

challenge. (Pl.’s Resp. at 9, ECF No. 38).

14

focus on parts of the “proposals requiring amplification or correction.” Advanced Data Concepts,

Inc., at 422. To that end, “[t]he scope and extent of discussions are a matter of [a] contracting

officer[’s] judgment.” FAR § 15.306(d)(3). A discussion is misleading when the agency

“misdirect[s] the protestor as it revises its proposal.” DMS All-Star Joint Venture v. United

States, 90 Fed. Cl. 653, 670 (2010) (collecting cases).

“The contracting officer is not required to discuss every area where the proposal could be

improved.” FAR § 15.306(d)(3). There is no evidence in the record that the Agency found Ginn

Group’s technical approach to recycling or its related staffing levels to be so unreasonable to

make it unacceptable for contract award. DMS All-Star Joint Venture, 90 Fed. Cl. at 669 (“[I]f an

offeror’s costs are not so high as to be unreasonable and unacceptable for contract award, the

agency may conduct meaningful discussions without raising the issue of the offeror’s costs.”);

(see AR 8339 (“Both the Ginn Group and GCR provided an acceptable organizational chart,

BOE, and approach to recycling.”)). As Ginn Group avers, neither its proposed staffing levels

nor its technical approach to recycling were burdened by any inherent deficiencies or

unacceptable weaknesses; the fact that the same aspects of the proposal may be viewed as

relative weaknesses only when compared against other equally acceptable offers does not create

an obligation for the Agency to discuss them with the offeror. CRAssociates, 102 Fed. Cl. at 715

(finding that the agencies need not “discuss every aspect of [a] proposal that receives less than

the maximum score,” neither do they need to “identify relative weaknesses in a proposal that

[are] technically acceptable but present[] a less desirable approach than others.”); (see also AR

8122 (finding “[a]ll offerors proposed adequate staffing and no weaknesses, significant

weaknesses or deficiencies were identified in any of the four offeror’s FPRs for Factor 2.”)).

In this case, both offerors were given adequate information to ensure that they bid even-

handedly. They were both given the option to either “review and confirm, or revise,” their

approach in areas that the Agency found lacking. (AR 6307, 6408). The agency did not take any

concrete actions during the discussions to put Ginn Group under the impression that it should not

revise its staffing level or change its recycling proposal and its mere inaction with regards to

those areas cannot constitute misleading discussion. DMS All-Star Joint Venture, 90 Fed. Cl. at

671 (holding that the agency did not mislead the offeror when it identified one price concern

related to the offeror’s proposal, but not other concerns regarding labor salaries and non-labor

costs, because the agency did nothing to suggest that the offeror “should not consider lowering

certain cost elements”); CSC Gov’t Sols. LLC v. United States, 129 Fed. Cl. 416, 439–40 (2016)

(finding that discussions are not coercive where the record demonstrates that an offeror retained

the option to make any adjustment to its proposal).

When two or more offerors’ proposals differ in meaningful ways that reflect each

offeror’s distinct approach to the project, so long as both approaches are adequate, the Agency

has every right to preserve its options and make the best-value determination with the

comparative advantages of each proposal before it. Ginn Group’s insistence that the Agency

needed to homogenize the two offers before reaching its final determination misconstrues the

Agency’s obligations in conducting meaningful discussions, especially in the context of best-

value procurement. The Navy’s discussions with the offerors were not arbitrary, capricious, an

abuse of discretion, or otherwise contrary to applicable law or regulation.

15

D. The Agency’s best-value determination did not lack a rational basis.

Finally, Ginn Group asserts that the Agency’s best-value determination lacked rational

basis as it did not “fairly and reasonably reflect proposal strengths and weaknesses with respect

to recycling and staffing.” (Pl.’s MJAR at 10). As discussed previously, the Court finds that Ginn

Group has not met its burden to prove that the Agency’s assessment of the offerors’ recycling

proposals or staffing levels lacked a rational basis. For that reason, those assertions do not

support Ginn Group’s argument that the best-value determination lacked a rational basis.

To challenge a best-value determination the protester must offer more than mere

disagreements with the Agency’s overall assessment of the adequacy of different proposals.

Banknote Corp. of Am., Inc. v. United States, 56 Fed. Cl. 377, 384 (2003). Ginn Group has not

shown that the agency entirely failed “to consider an important aspect” of the best-value tradeoff,

nor has it shown that the explanation provided by the Agency ran “counter to the evidence”

before it. Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir.

2009) (quoting Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43). The Agency adequately documented

its analysis throughout the solicitation period, highlighted the exact differences between Ginn

Group and GCR’s proposals as well as the price/technical tradeoffs they presented, and included

a narrative rationale for the business judgments and the tradeoff adopted in reaching the final

decision. See Blackwater Lodge & Training Center, Inc. v. United States, 86 Fed. Cl. 488, 514

(2009) (finding that the best-value determination was not arbitrary and capricious when the

agency’s “business judgment” as to why certain strengths did not warrant a price premium were

documented and recorded). The fact that Ginn Group has not informed the Court of any

significant differences between its proposal and GCR’s that are not already apparent from the

Agency’s own documentation of its comparative decision attests to the fact that the Agency did

not overlook any significant factors. (AR 8338–40); see, e.g., FirstLine Transportation Security,

Inc. v. United States, 100 Fed. Cl. 359, 368 (2011) (finding that the agency’s best-value

determination lacked rational basis when the agency failed to provide a coherent account of why

it awarded the contract to an inferior lower-priced offeror that had one technical strength and one

weakness, while the protestor had 33 strengths and no weaknesses). Even when the best-value

procurement criteria elevates importance of technical factors above price, which it does not in

this case, an agency’s determination to select a technically-lower-rated but lower-priced proposal

remains within the bounds of rational decision making so long as it is supported by the record.

See Mil-Mar Century Corp. v. United States, 111 Fed. Cl. 508, 553 (2013). Here, the evaluation

criteria already elevated price above technical factors and the Agency ultimately determined that

the lower-priced proposal was more advantageous to the Government. (See AR 8121–22; 46–47;

8338 (stating that all technical factors and past performance rating, when combined were

approximately equal to price)). The SSA’s determination reflects an independent analysis of the

record before the Agency and contains an adequate comparison of the proposals against the

evaluation criteria and other proposals.

Although Ginn Group claims that the Agency “failed to consider Ginn Group’s plan to

expand recycling in its evaluation of the Ginn Group proposal or its best-value tradeoff

decision,” the Agency was not required to provide an in-depth critical analysis of a technical

approach that it found adequate just because it was different than the awardee’s approach. (See

AR 8339 (“Both the Ginn Group and GCR provided an acceptable organizational chart, BOE,

and approach to recycling.”)). As the Court has stated, “when an agency is not finding fault with

16

a particular approach to a task, or noting its superior quality, the Court cannot see how the

agency should be required to explain its finding—that the approach is merely adequate—in any

detail.” InSpace 21 LLC. v. United States, 128 Fed. Cl. 69, 89 (2016). No statutory or regulatory

authority requires in-depth documentation and discussion of every technical approach that the

agency finds adequate, and the Court has been wary of imposing on the agencies the high

transactions costs associated with including such lengthy discussions in the best-value

determination. Id. Instead, the Court has reiterated that protesters cannot unilaterally impose

upon an agency the duty to explain why any feature in their proposal “was not found to be a

strength, merely by disputing this determination.” Telos Corp., 129 Fed. Cl. at 577. Ginn

Group’s argument that the Agency needed to discuss the “vast difference” in staffing levels as a

part of its best-value determination is unavailing for the same reason. The Source Selection

Decision noted that “[a]ll offerors proposed adequate staffing and no weaknesses, significant

weaknesses or deficiencies were identified in any of the four offeror’s FPRs for Factor 2.” (AR

8122). The notion that when an agency finds aspects of a protester’s proposal to be adequate, and

thus not material to the best-value determination, each adequacy determination must nevertheless

be explained for the award decision to be rational, “has no basis in law or reason.” Telos Corp.,

at 577.

Reviewing the administrative record establishes that, by all indications, both GCR and

Ginn Group provided the Agency with acceptable proposals which presented their own costs and

benefits. The best in the best-value determination naturally connotes the existence of perhaps

many good, maybe some better, but only one best proposal. The agency that has the power to

pick the best value is incentivized at every stage to improve all offers so that it is ideally faced

with a plethora of diverse but equally good approaches to implementing the project. Therefore, at

the final stage of a best-value procurement, it is the agency’s challenging task, and not the

Court’s, to decide which offer is more desirable to the Government among the many potentially

good options. Tiber Creek Consulting, Inc. v. United States, 129 Fed. Cl. 409, 415–16 (2016)

(“[A] best-value determination requires a series of judgment calls,” and “is very difficult to

overturn, particularly when the [deciding official] gives supporting rationale for their

decision[.]”).

Disappointed offerors understandably lament the marginal differences that shape the

agencies’ final determinations. However, the Court cannot substitute its own judgment for that of

an agency without disincentivizing the agency from optimizing its portfolio of options and from

establishing a record that highlights other offerors’ strengths. The Court’s persistent reference to

best-value determinations as ones “necessarily” entailing “a subjective process” reflects this

understanding. One Largo Metro, LLC v. United States, 109 Fed. Cl. 39, 96 (2013).

Ginn Group made the reasonable business judgment to offer the Agency the option to

expand one subpart of the services required under the contract, recycling services, at an

additional price. The agency found this offer overall acceptable and assessed its strengths and

weaknesses against an offer from another offeror that had more relevant past experience and

offered a lower price. The Agency found the latter option more desirable and advantageous for

the particular needs of the Government. The Court’s highly deferential standard towards

agencies’ assessment of technical differentials, making best-value determinations, and

conducting negotiated procurements, only requires that the Agency documents a rational

connection between the facts before it and the choice it made. Motor Vehicle Mfrs. Ass’n., 463

17

U.S. at 43 (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168 (1962)). The

Agency has adequately met that burden in this case.

Ginn Group also seeks as relief a permanent injunction barring the Agency from

proceeding with an award to GCR. (Pl.’s MJAR at 20–23). For the Court to grant injunctive

relief, the plaintiff must succeed on the merits of the case. PGBA, LLC v. United States, 389 F.3d

1219, 1228–29 (Fed. Cir. 2004) (discussing the four-part test for injunctive relief, including a

determination of whether “the plaintiff has succeeded on the merits of the case”). Ginn Group

has not succeeded on the merits, so the Court is unable to award injunctive relief and need not

address the remaining factors for injunctive relief. Int’l Res. Recovery, Inc. v. United States, 64

Fed. Cl. 150, 164 (2005) (“A plaintiff that cannot show that it will actually succeed on the merits

of its claim cannot prevail on its motion for injunctive relief.”); Argencord Mach. & Equip., Inc.

v. United States, 68 Fed. Cl. 167, 176 (2005).

III. Conclusion

Accordingly, the Court DENIES Ginn Group’s Motion for Judgment on the

Administrative Record, (ECF No. 33), and GRANTS the United States’ and the Government

Contracting Resources, Inc.’s Cross-Motions for Judgment on the Administrative Record. (ECF

Nos. 36, 37).

The parties shall meet and confer and file a joint status report proposing redactions to the

memorandum opinion by April 29, 2022, to allow the Court to file a public version of the

opinion.

The Clerk is DIRECTED to enter judgment for the defendants.

IT IS SO ORDERED.

s/ David A. Tapp

DAVID A. TAPP, Judge

18